SPECIFICATIONS AND SPECIMEN CONTRACT DOCUMENTS FOR:

2012 PAVEMENT PRESERVATION AND REPAIRS

TOWN OF WESTPORT PROJECT #2012-03

BID NO. 13-690T

DEPARTMENT OF PUBLIC WORKS GORDON JOSELOFF FIRST SELECTMAN STEPHEN J. EDWARDS DIRECTOR OF PUBLIC WORKS

PETER A. RATKIEWICH TOWN ENGINEER

DATE ISSUED

CONTRACTOR

June 2012

Engineering Division THIS DOCUMENT IS TO REMAIN 110 Myrtle , Room #210 INTACT NO ADDITIONS OR DELETIONS Tel: (203)-341-1120 ARE TO BE MADE.

IRS ID #06-6002128 TOWN OF WESTPORT

TOWN OF WESTPORT, CONNECTICUT DEPARTMENT OF PUBLIC WORKS 2012 PAVEMENT PRESERVATION AND REPAIRS WESTPORT PROJECT #2012-03

TABLE OF CONTENTS

SECTION 1 - TOWN OF WESTPORT BIDDING AND CONTRACT REQUIREMENTS 00100 - INVITATION TO BID 00200 - INFORMATION FOR BIDDERS 00300 - PROPOSAL 00401 - BID BOND 00402 - QUALIFICATIONS OF BIDDER 00403 - NON-COLLUSIVE BID STATEMENT 00404 - AGREEMENT 00405 - PAYMENT BOND 00406 - PERFORMANCE BOND 00500 - GENERAL CONDITIONS 00700 - SPECIAL CONDITIONS 01010 - INTRODUCTION TO TECHNICAL SPECIFICATIONS 01530 – DUST CONTROL 01600 - RESTORATION 01800 – PAVEMENT PRESERVATION LIST

SECTION 2 – ConnDOT-BASED NOTICES, SPECIFICATIONS, AND SPECIAL PROVISIONS A1-NOTICE TO CONTRACTOR - UTILITY CONTACT LIST A2-NOTICE TO CONTRACTOR - MIX DESIGNATION EQUIVALENCY A3-NOTICE TO CONTRACTOR - SUPERPAVE DESIGN LEVEL INFORMATION A4-NOTICE TO CONTRACTOR - NCHRP 350 REQ. FOR WORK ZONE CONTROL DEVICES B1-SECTION 1.08T - PROSECUTION AND PROGRESS C1-SECTION 9.75T – MOBILIZATION D1-ITEM #0980001A-T – CONSTRUCTION STAKING E1-SECTION 9.71T – MAINTENANCE AND PROTECTION OF TRAFFIC E2-ITEM #971001A-T – MAINTENANCE AND PROTECTION OF TRAFFIC-SUPPLEMENTAL E3-ITEM #971001A – PLAN 13-ALTERNATING ONE-WAY TRAFFIC OPERATION-TRAFFICPERSON E4-ITEM #971001A – NOTES FOR TRAFFIC CONTROL PLANS E5-ITEM #971001A – PAVEMENT MARKINGS DURING CONSTRUCTION-SECONDARY ROADWAYS F1-SECTION 9.77 – F2-CONSTRUCTION BARRICADE TYPE III F3-ITEM #1220011A – CONSTRUCTION SIGNS – TYPE III REFLECTIVE SHEETING F4-ITEM #0970006A,7A-T – TRAFFICPERSON G1-ITEM #0406267A ..9A - MILLING OF HOT MIX ASPHALT (HMA) G2-SECTION 4.03T – COLD RECLAIMED ASPHALT PAVEMENT G3-SECTION M.05T-PROCESSED AGGREGATE G4-SECTION M.04T – BITUMINOUS – (HMA MATERIALS-REV. 1/13/09) G5-SECTION 4.06T – BITUMINOUS CONCRETE – (HMA EXECUTION-REV. 1/13/09) G6-ITEM #0406999A-T – ASPHALT ADJUSTMENT COST

SECTION 3 – PREVAILING WAGE RATES AND REQUIRED DOCUMENTS

00100 TOWN OF WESTPORT - INVITATION TO BID

Bids for:

BID #13-690T 2012 PAVEMENT PRESERVATION AND REPAIRS PROJECT # 2012-03 will be received by the Controller of the Town of Westport, Connecticut in the Town Hall, 110 Myrtle Avenue, Westport, Connecticut until 11:00 AM, Friday, August 3, 2012, at which time said bids shall be opened publicly and read aloud. No proposals will be accepted after said hour. Each proposal must be submitted on the official form which is furnished by the Town. All blank spaces in the proposal form must be filled in as noted, and no change shall be made in the language of the proposal or in the items mentioned therein.

Information for Bidders, Proposal Forms, Specimen Agreement, Plans and Specifications and copies or specimens of all pertinent documents may be examined at the Department of Public Works - Room 210 Town Hall, 110 Myrtle Avenue, Westport, Connecticut, between the hours of 8:30 A.M., and 4:00 P.M. daily, except Saturdays, Sundays and holidays.

A bid bond or certified check in the amount of 15% must be submitted by the bidder with his bid as a guarantee that, in case the contract is awarded to him, he will, within ten days after appropriation of funds and approval by the Board of Selectmen, execute such contract and furnish a satisfactory Performance Bond and Payment Bond.

The Town of Westport reserves the right to reject any or all bids. Bids which are irregular in form, incomplete, conditioned, or qualified may be disregarded and rejected as improper except that the Town may waive any defects or irregularities. All bids are subject to appropriation by the Town of Westport.

PUBLIC WORKS DEPARTMENT

______Stephen J. Edwards Director of Public Works

______Peter A. Ratkiewich P.E. Town Engineer

1 00200 INFORMATION FOR BIDDERS

Bids will be received by The Town of Westport (herein called the "Owner"), at the Office of the Controller, Room 313 Town Hall - 110 Myrtle Avenue, Westport, Connecticut, 06880 until 11:00 AM, Friday, August 3, 2012 at which time said bids shall be opened publicly and read aloud. No bids will be received after said hour. The bid opening will take place in room #201 immediately thereafter.

Each Bid must be submitted in a sealed envelope, addressed to THE TOWN OF WESTPORT, OFFICE OF THE CONTROLLER, ROOM 313 AT 110 MYRTLE AVENUE, WESTPORT, CONNECTICUT. Each sealed envelope containing a Bid must be plainly marked on the outside as:

BID #13-690T 2012 PAVEMENT PRESERVATION AND REPAIRS, PROJECT # 2012-03

The bid envelope should also bear on the outside the name of the Bidder, his address, and his license number if applicable. If forwarded by mail, the sealed envelope containing the Bid must be enclosed in another envelope addressed to the Owner at the OFFICE OF THE CONTROLLER, ROOM 313, TOWN HALL, 110 MYRTLE AVENUE, WESTPORT, CONNECTICUT, 06880.

All Bids must be made on the required Bid form. All blank spaces for Bid prices must be filled in, in ink or typewritten, and the Bid form must be fully completed and executed when submitted. Only one copy of the Bid form is required.

The Owner may waive any informalities or minor defects or reject any and/or all Bids. Any Bid may be withdrawn prior to the above scheduled time for the opening of Bids or authorized postponement thereof. Any Bid received after the time and date specified shall not be considered. No Bidder may withdraw a Bid within 90 days after the actual date of the opening thereof. Should there be reasons why the contract cannot be awarded within the specified period, the time may be extended by mutual agreement between the Owner and the Bidder.

Bidders must satisfy themselves of the accuracy of estimated quantities in the Bid Schedule by examination of the site and a review of the Contract Drawings and Specifications including Addenda. After Bids have been submitted, the Bidder shall not assert that there was a misunderstanding concerning the quantities of Work or of the nature of the Work to be done.

Purchases made by the Town of Westport are exempt from payment of Federal Taxes and Connecticut Sales and Use Taxes, and such tax must not be included in the bid price of any items or materials permanently incorporated into the work or furnished to the Town under the contract.

The Contract Documents contain the provisions required for the construction of the Project. Information obtained from an officer, agent, or employee of the Owner or any other person shall not affect the risks or obligations assumed by the Contractor or relieve him from fulfilling any of the conditions of the contract.

Each Bidder must include completed Qualifications of Bidder and Non-Collusive Bid Statement forms with his Bid. The low Bidder is required to submit completed Qualifications of Subcontractors, and non- collusion Affidavit of Subcontractor forms within ten (10) days of the Bid.

Each Bid must be accompanied by a Bid Bond payable to the Owner for fifteen (15) percent of the total amount of the Bid, including both the base bid amount and all alternates. As soon as the Bid prices have been compared, the Owner will return the bonds of all except the three lowest responsible Bidders. When the Agreement is executed the bonds of the two remaining unsuccessful Bidders will be returned. The Bid Bond of the successful Bidder will be retained until the payment bond and performance bond have been

1 00200 INFORMATION FOR BIDDERS executed and approved, after which it will be returned. The surety on the bid bond must be a corporate surety licensed to sign surety bonds in the State of Connecticut and also listed by the United States Treasury Department in its latest list as a qualified surety acceptable to the United States Government. No bid bond will be accepted if the amount is less than 15% of the total estimated bid, including both the base bid and all alternates, or if the amount exceeds the limit for which the United States Treasury Department has qualified the surety for any one bond. A certified check may be used in lieu of a Bid Bond.

A performance bond and a payment bond, each in the amount of 100 percent of the Contract Price, with a corporate surety approved by the owner, will be required for the faithful performance of the contract. The surety on the bond must meet the requirements stated under Bid Security except that the amount of the bond may exceed the limit for which the United States Treasury Department has qualified the surety if the excess is reinsured with surety companies that are qualified on the United States Treasury Department list for an amount equal to the amount of the reinsurance. Written evidence of how any excess suretyship has been placed by the surety signing the bond must accompany the bond.

Attorneys-in-fact who sign the Bid bonds or payment bonds and performance bonds must file with each bond a certified and effective dated copy of their power of attorney.

The party to whom the contract is awarded will be required to execute the Agreement and obtain the performance bond and payment bond within ten calendar days from the date when Notice of Award is delivered to the bidder. The Notice of Award shall be accompanied by the necessary Agreement and bond forms. In case of failure of the Bidder to execute the Agreement, the Owner may at his option consider the Bidder in default, in which case the Bid Bond accompanying the proposal shall become the property of the Owner.

The Owner upon receipt of acceptable performance bond, payment bond and Agreement signed by the Contractor shall sign the Agreement and return to the Contractor an executed duplicate of the Agreement within a 10 day period. The returned executed Agreement by the Owner to the Contractor shall be accompanied with a Notice to Proceed.

The completion time for all work under this contract is 45 consecutive calendar days AFTER ISSUANCE OF THE NOTICE TO PROCEED based on a work schedule agreed upon by both parties unless otherwise approved in writing by the Director of Public Works, (reference Article 16, "Time for Completion and Liquidated Damages" in the General Conditions).

The Owner may make such investigation as he deems necessary to determine the ability of the Bidder to perform the Work, and the Bidder shall furnish to the Owner all such information and data for this purpose as the Owner may request. The Owner reserves the right to reject any Bid if the evidence submitted by, or investigation of, such Bidder fails to satisfy the Owner that such Bidder is properly qualified to carry out the obligations of the Agreement and to complete the Work contemplated therein.

A conditional or qualified Bid will not be accepted.

The Owner reserves the right to reject the use of the Bidders subcontractor if the evidence submitted by, or investigation of, such subcontractor fails to satisfy the Owner that such subcontractor is properly qualified to complete the work contemplated herein. Rejection of the Bidders subcontractor shall not relieve the Bidder of any requirements of the Bid or this Contract nor provide grounds for the Bidder to request compensation for his use of an alternate qualified subcontractor.

2 00200 INFORMATION FOR BIDDERS

All applicable laws, ordinances, and the rules and regulations of all authorities having jurisdiction over construction of the project shall apply to the contract throughout.

Each Bidder is responsible for inspecting the site and for reading and being thoroughly familiar with the Contract Documents. The failure or omission of any Bidder to do any of the foregoing shall in no way relieve any Bidder from any obligation in respect to his Bid.

The low Bidder must supply the name and addresses of major material suppliers and subcontractors when requested to do so by the Owner.

Procedure for determining the lowest responsible, qualified bidder:

The Town shall determine the “Lowest Responsible Qualified Bidder” on the basis of the bidder submitting the lowest “Total Bid”; responsiveness of his proposal; and demonstrating a history of the ability and integrity necessary to perform the required work; and certifying he can perform the required work in accordance with the contract documents.

In the event of any discrepancies between this Information To Bidders and other sections of the contract documents, this Information to Bidders shall govern.

- End of Section -

3 00300 PROPOSAL

The Board of Selectman Town Hall Westport, Connecticut

PROJECT: 2012 PAVEMENT PRESERVATION AND REPAIRS PROJECT # 2012-03

The undersigned declares he/she has carefully examined the Information for Bidders, Form of Proposal, Plans, Specifications and any other contract documents and site of work for above project and hereby proposes to furnish all plant, labor, materials and equipment and perform all work necessary to complete the project in strict accordance with the requirements of the contract documents. The Proposal is based on the herein attached schedule of estimated quantities and is as follows:

TOTAL BID------$______

Accompanying this proposal is security for 15% of the contract bid upon, in the form of a bid bond in the amount of:

$______

The names and addresses of all partners, officers or parties interested in the foregoing bid are as follows:

NAME ADDRESS

______

______

______

The undersigned hereby designates ______at his office to which all notices and letters may be delivered or mailed. SIGNATURE OF BIDDER ______

(Corporation, Firm or Individual)______

- THIS PROPOSAL IS NOT TO BE SEPARATED FROM THIS DOCUMENT -

p. 1 00300 PROPOSAL

NOTE: All prices must be written in ink, in words and figures, for the entire Proposal ______

Item Estimated Brief description and price bid, in Price bid in Total in figures No. Quantity words figures ______(* = Indeterminate quantity assumed for comparison of bids)

1. 8370 TON ConnDOT Item #0406441A Bituminous Concrete, Mix Type HMA S0.375, level 2, Complete in place, per ton, the sum of,

dollars

and cents $ $

2. 38356 SY ConnDOT Item #0406267A Roadway Milling, 0" - 4" depth, Complete in place, per square yard, the sum of, dollars

and cents $ $

3. 15177 SY ConnDOT Item #0403869 Cold Reclaimed Asphalt Pavement, Complete in place, the sum of,

dollars

and cents $ $

4. *30 EA ConnDOT Item #0977001 Traffic Cone 28”, per each, the sum of,

dollars

and cents $ $

- THIS PROPOSAL IS NOT TO BE SEPARATED FROM THIS DOCUMENT -

p. 2 00300 PROPOSAL

NOTE: All prices must be written in ink, in words and figures, for the entire Proposal ______

Item Estimated Brief description and price bid, in Price bid in Total in figures No. Quantity words figures ______(* = Indeterminate quantity assumed for comparison of bids)

5. *20 EA ConnDOT Item #0977001 Traffic Cone 42”, per each, the sum of,

dollars

and cents $ $

6. *100 SF ConnDOT Item #1220011A Construction Signs, per Square foot, the sum of,

dollars

and cents $ $

7. *10 TON Westport Item #01530 Calcium Chloride for Dust Control, per ton, the sum of,

dollars

and cents $ $

8. *50 TON ConnDOT Item #0305000 Processed Aggregate, per Ton, the sum of,

dollars

and cents $ $

- THIS PROPOSAL IS NOT TO BE SEPARATED FROM THIS DOCUMENT -

p. 3 00300 PROPOSAL

NOTE: All prices must be written in ink, in words and figures, for the entire Proposal ______

Item Estimated Brief description and price bid, in Price bid in Total in figures No. Quantity words figures ______(* = Indeterminate quantity assumed for comparison of bids)

9. *EST ConnDOT Item #0406999A Asphalt Adjustment Cost, the ESTIMATED sum of,

One Hundred dollars

And zero cents $_100.00__ $___100.00 TOTAL OF COMPETITIVE BID ITEM NUMBERS 1 THROUGH 9 OF THIS PROPOSAL, AS COMPUTED BY THE BIDDER USING THE ESTIMATED QUANTITIES INDICATED ABOVE:

$ Price in words Price in figures

But it is understood that the various unit prices bid will control in any contract which may be awarded arising from this Proposal; that the estimated quantities above are approximate only and used only for the comparison of bids; and that the products obtained by multiplication of the above unit prices by estimated quantities, and the total thereof, have been inserted only for the convenience of the Bidder and to facilitate consideration of this and other Proposal

- THIS PROPOSAL IS NOT TO BE SEPARATED FROM THIS DOCUMENT -

p. 4 00401 BID BOND

TOWN OF WESTPORT WESTPORT, CONNECTICUT

KNOW ALL MEN BY THESE PRESENTS

THAT WE, of the Town of , County of , and State of Connecticut, as PRINCIPAL, and , a corporation organized and existing under the laws of the State of , and duly authorized to transact a surety business in the State of Connecticut (hereinafter called the "Surety"), as Surety, are held and firmly bound unto the Town of Westport, as Obligee, in the sum of:

($ ) lawful money of the United States of America, for the payment of which, well and truly to be made to the Obligee, we bind ourselves, our heirs, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH THAT, whereas the Principal has submitted herewith to the Town of Westport, a Proposal dated attached, which is

2012 PAVEMENT PRESERVATION AND REPAIRS PROJECT # 2012-03

NOW THEREFORE,

(a) if such Proposal is rejected; or in the alternative,

(b) if such Proposal is accepted and the contract is awarded to the Principal, and the Principal enters into a written agreement when required by the Obligee, with such surety bonds as shall be acceptable to the agreement and for the payment of all labor and material used in the performance of the work, then this obligation shall be null and void; otherwise the same shall remain in full force and effect, and the Principal and Surety hereto agree to pay to the Obligee all damages sustained by

1 00401 BID BOND the agreement, including, but without limiting the generality of the foregoing, the difference between the amount of the Principal's Proposal submitted herewith and the amount for which the

Obligee may contract with another party to perform the work covered by such Proposal if the latter amount be in excess of the former, subject, however, to the following conditions:

1. The liability of the Principal to pay to the Obligee the damages sustained by the Obligee as a

consequence of the principal's failure to enter into the agreement is not limited to the

amount of this bond, and

2. The obligation of the surety hereunder shall be the full amount of the Principal's liability,

reduced by any amount paid by the Principal on account of such liability, but not more than

the amount of this bond in any event.

3. The surety, for value received, hereby stipulates and agrees that the obligation of said Surety

and its bond shall in no way be impaired or affected by any extension of the time within

which the Town of Westport may accept such bid; and such Surety does hereby waive

notice of any such extension.

2 00401 BID BOND

IN WITNESS WHEREOF, WE HAVE SET our hands and seals this

day of A.D. 20 .

(L.S.)

WITNESS PRINCIPAL

By: (L.S.)

WITNESS

(If the Principal is a Corporation or Partnership, so indicate, as well as title of officer signing this bond on its behalf.)

(L.S.)

WITNESS SURETY

By: (L.S.)

WITNESS

Note: If an individual signs as agent for a Surety Company, he must also submit a Power of Attorney enabling him to act on behalf of the Surety Company, as well as a statement of its financial condition, and a copy of the corporate resolution authorizing the issuance of bonds.

3 00401 BID BOND

ACKNOWLEDGEMENT OF PRINCIPAL

STATE OF

COUNTY OF SS , 20

PERSONALLY APPEARED FOR signer (s) and sealer (s) of the foregoing instrument and acknowledged the same to be free act and deed, before me.

Commissioner of the Superior Court Notary Public My Commission Expires

ACKNOWLEDGEMENT OF SURETY

STATE OF

COUNTY OF SS , 20

PERSONALLY APPEARED FOR signer(s) and sealer(s) of the foregoing instrument, being thereunto duly authorized, and acknowledged the same to be free act and deed, and the free act and deed of said corporation, before me.

Commissioner of the Superior Court Notary Public My Commission Expires

4 00402 QUALIFICATIONS OF BIDDER

2012 PAVEMENT PRESERVATION AND REPAIRS PROJECT # 2012-03

The Bidder is required to submit on the following pages the information required in regard to qualifications for the Work.

(USE BACK OF THIS SHEET IF NECESSARY)

A. The location, character, cost, date and names of engineers or officials of similar work previously constructed by the undersigned are as follows:

B. The equipment which will be available for performing the work under this contract is as follows:

Own Equipment:

Rented Equipment:

C. The undersigned has failed to complete satisfactorily the following contracts, including also those in which the surety has participated. (If there have been no contracts which the bidder has failed to complete satisfactorily, including also those in which the surety has participated, the bidder shall definitely so state.)

Name of Bidder ______Address ______

1 00403 NON-COLLUSIVE BID STATEMENT

2012 PAVEMENT PRESERVATION AND REPAIRS PROJECT # 2012-03

All bidders are required to sign a Non-Collusive Bid Statement with all public bids as follows:

1. The bid has been arrived at by the bidder independently and has been submitted without

collusion with, and without any agreement, understanding, or planned common course of

action with any other vendor or materials, supplies, equipment, or services described in the

Advertisement for Bids, designed to limit independent billing or competition, and

2. The contents of the bid have not been communicated by the bidder or its employees or

agents to any person not an employee or agent of the bidder or its surety on any bond

furnished with the bid, and will not be communicated to any such person prior to the

official opening of the bid.

Name of Bidder

Address

Signature

Title

1 00404 AGREEMENT

THIS AGREEMENT, made this______day of______, 20_____, by and between THE TOWN OF WESTPORT, a municipal corporation in the COUNTY OF FAIRFIELD and the State of Connecticut (hereinafter called the "Owner") and

______

______, doing business as a (an individual), or (a partnership), or (a Corporation) (hereinafter called the

"Contractor") organized and existing under the laws of the State of Connecticut.

WITNESSETH: That for and in consideration of payments and agreements hereinafter mentioned:

1. The Contractor will commence and complete the construction of:

2012 PAVEMENT PRESERVATION AND REPAIRS,

PROJECT # 2012-03

within 45 consecutive calendar days of receipt of the Notice to Proceed.

2. The Contractor will furnish all of the material, supplies, tools, equipment, labor and

other services necessary for the construction and completion of the project described

herein.

3. The Contractor agrees to perform all of the Work described in the Contract

Documents for the sum arrived at by multiplying the Unit Prices of the respective

1 00404 AGREEMENT

items in the Bid Schedule by the total quantities of the items completed and

accepted, subject to additions and deductions as provided in the General Conditions.

4. The term "Contract Documents" means and includes the following:

Advertisement for Bids

Information for Bidders

Proposal

Agreement

General Conditions

Special Provisions

Specifications

Contract Drawings

Addenda as herein enumerated:

No. , dated , 20

No. , dated , 20

No. , dated , 20

2 00404 AGREEMENT

5. The Owner will pay to the Contractor in the manner and at such times as set forth in

the General Conditions such amounts as required by the Contract Documents.

6. This Agreement shall be binding upon all parties hereto and their respective heirs,

executors, administrators, successors, and assigns.

3 00404 AGREEMENT

IN WITNESS WHEREOF, the parties hereto have executed, or caused to be executed by their duly authorized officials, 4 copies of this Agreement, each of which shall be deemed an original on the date first above written.

(SEAL)

ATTEST:

CONTRACTOR

BY (L.S.)

NAME

TITLE

(SEAL)

ATTEST:

TOWN OF WESTPORT

BY (L.S.)

NAME

GORDON JOSELOFF, FIRST SELECTMAN

Approved as to form:

Asst. Town Attorney

I certify that the foregoing Contract has been examined and found to conform to the requirements of Chapter 11 of the Town Charter.

Controller

4 00405 PAYMENT BOND

TOWN OF WESTPORT

WESTPORT, CONNECTICUT

KNOW ALL MEN BY THESE PRESENTS

THAT WE,______of the Town of______,

County of______, and state of Connecticut; as PRINCIPAL, and______, as SURETY, are held and firmly bound unto the TOWN OF WESTPORT, hereinafter called OWNER in the sum of:

______($______) in Lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH THAT, whereas the Principal has entered into a certain written contract with the Owner, dated the______day of______, A.D.,

20_____, a copy of which is hereto attached and made a part hereof for the construction of:

2012 PAVEMENT PRESERVATION AND REPAIRS PROJECT # 2012-03

NOW THEREFORE, if the Principal and each of its Subcontractors shall promptly make payment to persons, firms, subcontractors, and corporations furnishing materials for or performing labor in the prosecution of the work provided for in such contract, and any authorized extension or modification thereof, including all amounts due for materials, lubricants, oil, gasoline, repairs on

1 00405 PAYMENT BOND machinery, equipment and tools, consumed or used in connection with the construction of such work, and all insurance premiums on said work, and for all labor, performed in such work whether by subcontractor or otherwise, then this obligation shall be void; otherwise to remain in full force and effect.

PROVIDED, FURTHER, that the said Surety, for value received hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the contract or to the work to be performed thereunder or the specifications accompanying the same shall in any way affect its obligation on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the contract or to the work or to the specifications.

PROVIDED, FURTHER, that no final settlement between the Owner and the Contractor shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied.

Every person furnishing material or performing labor in the performance of the contract, either as an individual, as a subcontractor, or otherwise, shall have the right to sue on this bond.

2 00405 PAYMENT BOND

IN WITNESS WHEREOF, WE HAVE SET our hands and seals this______day of______A.D., 20______.

______(L.S.)

Witness Principal

______(L.S.)

Witness Surety

______By:______(L.S.)

NOTE: Date of Bond must not be prior to date of Contract. If Contractor is Partnership, all partners should execute bond.

IMPORTANT: Surety companies executing bonds must appear on the Treasury Department's most current list (Circular 570 as amended) and be authorized to transact business in the State of

Connecticut.

3 00406 PERFORMANCE BOND

TOWN OF WESTPORT

WESTPORT, CONNECTICUT

KNOW ALL MEN BY THESE PRESENTS

THAT WE,______of the Town of______,

County of______, and state of Connecticut; as PRINCIPAL, and______, as SURETY, are held and firmly bound unto the TOWN OF WESTPORT, hereinafter called OWNER in the sum of:

______($______) in Lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH THAT, whereas the Principal has entered into a certain written contract with the Owner, dated the______day of______, A.D.,

20_____, a copy of which is hereto attached and made a part hereof for the construction of:

2012 PAVEMENT PRESERVATION AND REPAIRS PROJECT # 2012-03

NOW THEREFORE, if the Principal shall well and truly keep, and perform its duties, all the undertakings, covenants, terms, conditions and agreements of said Contract during the original term thereof, and any extensions thereof which may be granted by the Owner, with or without notice to the Surety and during the one year guaranty period, and if he shall satisfy all claims and demands

1 00406 PERFORMANCE BOND incurred under such Contract, and shall fully indemnify and save harmless the Owner from all costs and damages which it may suffer by reason of failure to do so, and shall reimburse and repay the

Owner all outlay and expense which the Owner may incur in making good any default, then this obligation shall be void; otherwise to remain in full force and effect.

PROVIDED, FURTHER, that the said Surety, for value received hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the contract or to the work to be performed thereunder or the specifications accompanying the same shall in any way affect its obligation on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the contract or to the work or to the specifications.

PROVIDED, FURTHER, that no final settlement between the Owner and the Contractor shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied.

2 00406 PERFORMANCE BOND

IN WITNESS WHEREOF, WE HAVE SET our hands and seals this______day of______A.D., 20______.

______(L.S.)

Witness Principal

______(L.S.)

Witness Surety

______By:______(L.S.)

NOTE: Date of Bond must not be prior to date of Contract. If Contractor is Partnership, all partners should execute bond.

IMPORTANT: Surety companies executing bonds must appear on the Treasury Department's most current list (Circular 570 as amended) and be authorized to transact business in the State of

Connecticut.

3 00500 GENERAL CONDITIONS

TABLE OF CONTENTS

ARTICLE TITLE PAGE

1. Definitions GC-1

2. Contract and Contract Documents GC-1

3. Shop Drawings and Submittals GC-1

4. Work Area, Materials Storage, Temporary Services and Facilities GC-2

5. Inspection, Testing and Certificates of Conformance GC-2

6. Substitutions GC-2

7. Surveys, Layout of Work GC-2

8. Permits, Ordinances, and Regulations GC-3

9. Supervision by Contractor GC-3

10. Protection of Work, Property, Persons GC-3

11. Night and Sunday Work GC-3

12. Blasting and Explosives GC-3

13. Job Meetings GC-3

14. Changes in the Work GC-3

15. Changed Conditions GC-4

16. Changes in Contract Price GC-4

17. Time for Completion and Liquidated Damages GC-4

18. Suspension of Work, Termination and Delay GC-4

19. Measurement and Payments to Contractors GC-5

20. Partial Use of Site Improvements GC-6

21. Acceptance of Final Payment as Release GC-6

22. Insurance GC-6

1 00500 GENERAL CONDITIONS

23. Contract Security GC-7

24. Assignments GC-7

25. Indemnification GC-7

26. Separate Contracts GC-8

27. Private Utility Lines GC-8

28. Work by Others GC-8

29. Subcontracting GC-8

30. Engineer's Authority GC-8

31. Land and Rights of Way GC-8

32. Guaranty GC-8

33. Taxes GC-8

34. Provisions Required by Law Deemed Inserted GC-9

35. Safety Provisions GC-9

36. Wage Rates GC-9

2 00500 GENERAL CONDITIONS

1. DEFINITIONS WORK - All labor necessary to produce the construction required by the Contract Documents, and all materials and equipment ADDENDA - Written or graphic instruments issued prior to the incorporated or to be incorporated in the Project. execution of the Agreement which modify or interpret the Contract Documents, Contract Drawings and Specifications, by additions, WRITTEN NOTICE - Any notice to any party of the Agreement deletions, clarifications or corrections. relative to any part of this Agreement in writing and considered delivered and the service thereof completed, when posted by AGREEMENT - The written Agreement between the Owner and certified or registered mail to the said party at his last given the Contractor for covering the Work to be performed. address, or delivered in person to said party or his authorized representative on the Work. CHANGE ORDER - A written order to the Contractor authorizing an addition, deletion or revision in the Work within the general 2. CONTRACT AND CONTRACT DOCUMENTS scope of the Contract Documents, or authorizing adjustment in the Contract Price or Contract Time. The Contract Drawings, contract specifications, and all addenda shall form this Contract, and provisions thereof shall be as binding CONTRACT PRICE - The total monies payable to the Contractor upon the parties hereto as if they were herein fully set forth. under the terms and conditions of the Contract Documents. The Owner will furnish the Contractor, without charge, five copies CONTRACT TIME - The number of calendar days stated in the of the Contract Documents, including Specifications and Contract Documents for the completion of the Work. Drawings. Additional copies will be furnished at nominal cost to the Contractor, upon request. CONTRACTOR - The person, firm or corporation with whom the Owner has executed the Agreement. In case of conflict between the Contract Drawings and Specifications, the Specifications shall govern. Figure dimensions ENGINEER - The Westport Town Engineer. on drawings shall govern over scale dimensions, and detailed Drawings shall govern over general drawings. Any discrepancies FIELD ORDER - A written order effecting a change in the Work found between the drawings and Specifications and site conditions, not involving an adjustment in the Contract Price or an extension or any inconsistencies or ambiguities in the drawings or of the Contract Time, issued by the Engineer to the Contractor Specifications, shall be immediately reported to the Engineer, in during construction. writing, who shall promptly correct such inconsistencies or ambiguities in writing. Work done by the Contractor after his NOTICE OF AWARD - The written notice of the acceptance of discovery of such discrepancies, inconsistencies or ambiguities the Bid from the Owner to the successful Bidder. shall be done at the Contractor's risk.

NOTICE TO PROCEED - Written communication issued by the The Contractor may be furnished additional instructions and detail Owner to the Contractor authorizing him to proceed with the Work drawings by the Engineer as necessary to carry out the Work and establishing the date of commencement of the Work. required by the Contract Documents. The additional drawings and instructions thus supplied will become a part of the Contract OWNER - The Town of Westport Documents.

PROJECT - The undertaking to be performed as provided in the 3. SHOP DRAWINGS AND SUBMITTALS Contract Documents. The Contractor shall provide three (3) copies of all shop drawings RESIDENT PROJECT REPRESENTATIVE - The authorized and submittals as required by the contract specifications. The representative of the Owner who is assigned to the Project site or Engineer will retain two (2) copies of all approved Shop Drawings any part thereof. and submittals, and return one to the Contractor. Shop drawings and submittals are to be submitted as detailed in the Special SPECIAL PROVISIONS - Modifications, additions and Provisions, and/or sufficiently in advance of requirements, to clarifications to the Contract Documents. provide the Engineer time for review and correction if necessary. The Engineer's review of shop drawings and submittals shall not SPECIFICATIONS - A part of the Contract Documents consisting release the Contractor from responsibility for deviations from the of written descriptions of a technical nature of materials, Contract documents. Certificates of conformance must be equipment, construction systems, standards and workmanship. submitted on all material and/or equipment that will become the property of the Owner. Portions of the Work requiring shop drawings or submittals shall not begin until after review by the

GC-1 00500 GENERAL CONDITIONS

Engineer. Any submittals not following this procedure will be any Work is covered contrary to the written request of the rejected. Engineer, it must, if requested by the Engineer, be uncovered for his observation and replaced at the Contractor's expense. 4. WORK AREA, MATERIALS STORAGE, TEMPORARY SERVICES AND FACILITIES If the Engineer considers it necessary or advisable that covered Work be re-exposed, due to suspicion of defective work, the The Contractor shall provide and pay for all materials, labor, tools, Contractor will uncover, expose or otherwise make available for equipment, water, light, power, transportation, supervision, observation, inspection or testing as the Engineer may require, that temporary construction of any nature, and all other services and portion of the Work in question, furnishing all necessary labor, facilities of any nature whatsoever necessary to execute, complete, materials, tools, and equipment. If it is found that such Work is and deliver the Work within the specified time. defective, the Contractor will bear all the expenses of such uncovering, exposure, observation, inspection and testing and of The Contractor shall confine his work/storage area to the limits as satisfactory reconstruction. If, however, such Work is not found to designated or approved and shall be responsible for the security of be defective, the Contractor will be allowed an increase in the the work/storage area. Storage of materials or establishing Contract Price or an extension of the Contract Time, or both, temporary facilities on private property shall be solely up to the directly attributable to such uncovering, exposure, observation, Contractor and he shall assume all responsibility and liability for inspection, testing and reconstruction and an appropriate Change same. Upon completion of the Contract, the Contractor shall Order shall be issued. remove all equipment and materials except as otherwise specified and restore the site to its original condition. 6. SUBSTITUTIONS

5.INSPECTION, TESTING AND CERTIFICATES OF References to brand names or catalogue numbers in the Contract CONFORMANCE documents are for the purpose of defining the performance or other salient requirements of materials and equipment. The Contractor The Owner reserves the right to require testing of any and all may request to substitute materials or equipment of equal materials, equipment or samples delivered to the job site. Such substance and function. If in the opinion of the Engineer, such testing shall be done by an independent testing laboratory at the material or piece of equipment is of equal substance and function expense of the Contractor. Any material so sampled and found not to that specified, the Engineer may approve its substitution and use to meet the requirements of these specifications shall be rejected by the Contractor. Any cost differential shall be deductible from and the entire shipment removed from the site at the Contractor's the Contract price and the Contract documents shall be expense. Furthermore, the Owner reserves the right to then require appropriately modified by Change Order. The Contractor warrants each material to be manufactured and tested in accordance with the that if substitutes are approved, no major changes in the function or standard specifications, (e.g. AWWA, ANSI, etc.), cited hereafter. general design of the Project will result. Incidental changes or extra component parts required to accommodate the substitute will In addition to other requirements specified, the Contractor shall be made by the Contractor without a change in the Contract Price furnish to the Engineer, in the manner as directed, notarized or Contract Time. certificates of conformance for all materials to be furnished under this Contract, The notarized certificates of conformance shall state 7. SURVEYS, LAYOUT OF WORK that the material to be furnished under this Contract meets the specification requirements. When directed, each shipment of The Engineer shall furnish initial land surveys and establish all material shall be accompanied by the manufacturer's notarized base lines for locating the principal component parts of the Work certificates of conformance, certifying that the materials meet the together with a suitable number of bench marks adjacent to the requirements of the specifications. Work as shown on the Contract Drawings.

All materials and equipment used in the construction of the Project The Contractor shall perform all layout work necessary for the shall be subject to adequate inspection in accordance with satisfactory execution of the construction as shown on the Contract generally accepted standards. Neither observations by the Drawings and all costs in connection therewith shall be included in Engineer nor inspections, tests or approvals by persons other than the Contract Price(s). the Contractor shall relieve the Contractor from his obligations to perform the Work in accordance with the requirements of the The Contractor shall be held responsible for protecting and Contract Documents. safeguarding all control points and bench marks set by the Engineer and his own forces. Any replacement or re-establishment The Engineer, the Owner and their representatives will at all times of control points and bench marks set by the Engineer, shall be at have access to the Work. The Contractor will provide proper the expense of the Contractor. facilities for access, inspection, and observation of the Work. If

GC-2 00500 GENERAL CONDITIONS

8. PERMITS, ORDINANCES, AND REGULATIONS 11. NIGHT AND SUNDAY WORK

Permits and licenses of a temporary nature necessary for the Unless otherwise especially permitted by the Owner, no work shall prosecution of the Work shall be secured and paid for by the be done between the hours of 6:00 p.m. and 7:00 a.m., nor on Contractor. The Contractor will be required to obtain a Sunday, except as necessary for the proper care and protection of Opening permit from the Town of Westport. All fees will be the work already performed. The Engineer shall be informed a waived. reasonable time in advance of the beginning of performance of such work. Only such work will be permitted at night as can be Permits, licenses and easements for permanent structures or done satisfactorily and in a first class manner and without permanent changes in existing facilities shall be secured and paid disturbance to adjoining property owners. Good lighting and all for by the Owner, unless otherwise specified. The Contractor shall other facilities for carrying out and inspecting the work shall be give all notices and comply with all laws, ordinances, rules and provided and maintained at all points where such work is being regulations bearing on the conduct of the Work as drawn and done. The parties hereto recognize and agree that the work is specified. affected with a public interest, affecting the health, safety, and general welfare of the people of the Town of Westport. 9. SUPERVISION BY CONTRACTOR 12. BLASTING AND EXPLOSIVES The Contractor will supervise and direct the Work. He will be solely responsible for the means, methods, techniques, sequences Explosives shall not be brought onto or used on the site without and procedures of construction. Except where the Contractor is an prior written permission of the Owner. If approved, the use of individual and gives his personal superintendence to the Work he explosives and blasting methods will be in strict conformance with: will employ and maintain on the Work a qualified supervisor or superintendent who shall have been designated in writing by the Administrative Regulations, Connecticut State Police Contractor as the Contractor's representative at the site. The Department - Storage, Transportation, and Use of Explosive supervisor shall have full authority to act on behalf of the and Blasting Agents, (latest revision). Contractor and all communications given to the supervisor shall be as binding as if given to the Contractor. The supervisor shall be Copies of these regulations may be obtained at the State Fire present on the site at all times to provide adequate supervision and Marshall's Office, Meriden, Connecticut. coordination of the Work. Prior to any blasting, the Contractor must obtain a Blasting Permit 10. PROTECTION OF WORK, PROPERTY AND PERSONS from the Westport Fire Department. Proof of Insurance will be required. Police and Fire departments must be notified at least 24 The Contractor will be responsible for initiating, maintaining and hours prior to blasting. Any additional requirements of the Owner supervising all safety precautions and programs in connection with or the Westport Fire Department regarding the use of explosives the Work. He will take all necessary precautions for the safety of, shall be strictly complied with. and will provide the necessary protection to prevent damage, injury or loss to all employees on the Work and other persons who may 13. JOB MEETINGS be affected thereby, all the Work and all materials or equipment to be incorporated therein, whether in storage on or off the site, and Job meetings may be called by the Engineer on behalf of the other property at the site or adjacent thereto, including trees, Owner on the Project site, or at such place as is mutually agreed, at shrubs, lawns, walks, pavements, roadways, structures and utilities such times as is deemed necessary by the Owner which the not designated for removal, relocation or replacement in the course Contractor shall attend. The Contractor if required, shall be of construction. notified in writing of the job meetings and shall have his Subcontractors attend as is deemed necessary to accomplish the In emergencies affecting the safety of persons or the Work or purposes of said meeting. The Contractor and his Subcontractors property at the site or adjacent thereto, the Contractor, without shall be prepared to present complete and definite reports as to special instruction or authorization from the Engineer or Owner, status of Work, dates of delivery, conditions of manufacturing, shall act to prevent threatened damage, injury or loss. He will give labor, shipping data, time of accomplishment or completion, the Engineer prompt Written Notice of any significant changes in method of construction and such other information as may be the Work or deviations from the Contract Documents caused related to the execution of the Work. thereby, and a Change Order shall thereupon be issued covering the changes and deviations involved. 14. CHANGES IN THE WORK

The Director of Public Works shall have the power, without notice, or approval of Surety, to alter and change the line, grade, plan,

GC-3 00500 GENERAL CONDITIONS

form, position, dimension or material of or for the Work herein b. An agreed lump sum. contemplated, or any part thereof, in a manner not inconsistent with the general layout of the project. This may be done either c. The actual cost for labor, direct overhead, materials, supplies, before the signing of the Contract or after starting of the work, or equipment, and other services necessary to complete the work. the Director may order in writing any extra work which may be In addition there shall be added an amount to be agreed upon deemed necessary in connection with the work. The Director of but not to exceed fifteen (15) percent of the actual cost of the Public Works may increase or decrease the unit quantities in the Work to cover the cost of general overhead and profit. Proposal. 17. TIME FOR COMPLETION AND LIQUIDATED The Engineer, also, may at any time, by issuing a Field Order, DAMAGES make changes in the details of the Work. The Contractor shall proceed with the performance of such changes unless the The Contractor will proceed with the Work at such rate of progress Contractor believes that such Field Order entitles him to a change to insure full completion within the Contract Time. The Contractor in Contract Price or Time, or both, in which event he shall give the agrees that no construction work shall commence until a Pre- Engineer Written Notice of same within five (5) days after the construction video has been approved by the Director of Public receipt of the ordered change. The Contractor shall not execute Works. It is expressly understood and agreed, by and between the such changes until he receives an executed Change Order or Contractor and the Owner, that the Contract Time for the further instruction from the Engineer. completion of the Work described herein is a reasonable time, taking into consideration the average climatic and economic 15. CHANGED CONDITIONS conditions and other factors prevailing in the locality of the Work. If the Contractor shall fail to complete the Work within the The Contractor shall promptly, and before such conditions are Contract Time, or extension of time granted by the Owner, disturbed, except in the event of an emergency, notify the Owner then the Contractor will pay to the Owner, liquidated damages by Written Notice of latent physical conditions at the site differing in the amount of $200.00 for each calendar day that the materially from those indicated in the Contract Documents or of an Contractor shall be in default after the time stipulated in the unusual nature, differing materially from those ordinarily Contract Documents. encountered and generally recognized as inherent in Work of the character provided for in the Contract Documents. The Contractor shall not be charged with liquidated damages or any excess cost when the delay in completion of the Work is due to The Owner shall promptly investigate the conditions, and if he the following, and the Contractor has promptly given Written finds that such conditions do so materially differ and cause an Notice of such delay to the Owner or Engineer: increase in the cost of, or in the time required for, performance of the Work, an equitable adjustment shall be made and the Contract a. to any preference, priority or allocation order duly issued by the Documents shall be modified by a Change Order. Any claim of Owner; the Contractor for adjustment hereunder shall not be allowed unless he has given the required Written Notice. b. to unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to 16. CHANGES IN CONTRACT PRICE acts of God, or of the public enemy, acts of the Owner, acts of another Contractor in the performance of a Contract with the The Director of Public Works reserves the right to increase or Owner, fires, floods, epidemics, quarantine restrictions, strikes, decrease any item of the Proposal. If such change increases or freight embargoes, and abnormal and unforeseeable weather; decreases the total original contract price by more than 25%, then and the costs of the changed work will be subject to negotiation. c. to any delays of Subcontractors occasioned by any of the causes The Contract Price may be changed only by a Change Order. The specified above. value of any Work covered by a Change Order or of any claim for increase or decrease in the Contract Price shall be determined by 18. SUSPENSION OF WORK, TERMINATION AND DELAY one or more of the following methods in the order of precedence listed below: The Owner may, at any time and without cause, suspend the Work or any portion thereof for a period of not more than ninety days or a. Unit prices previously approved. such further time as agreed upon by the Contractor, by Written Notice to the Contractor which notice shall fix the date on which Work shall be resumed. The Contractor will be allowed an extension of the Contract Time directly attributable to any suspension.

GC-4 00500 GENERAL CONDITIONS

If the Contractor is adjudged bankrupt or insolvent, or if he makes has been paid all amounts then due, in which event and upon a general assignment for the benefit of his creditors, or if a trustee resumption of the Work, Change Orders shall be issued for or receiver is appointed for the Contractor or for any of his adjusting the Contract Price or extending the Contract Time or property, or if he files a petition to take advantage of any debtor's both to compensate for the costs and delays attributable to the act, or to recognize under the bankruptcy or applicable law or if he stoppage of the Work. repeatedly fails to supply sufficient skilled workmen or suitable materials or equipment, or if he repeatedly fails to make prompt payments to Subcontractors for labor, materials or equipment or if 19. MEASUREMENT AND PAYMENTS TO CONTRACTORS he disregards laws, ordinances, rules, regulations or orders of any public body having jurisdiction of the Work or if he disregards the The Work is divided into both unit quantity and lump sum pay authority of the Engineer, or if he otherwise violates any provision items. The unit quantity items will be measured as stipulated in the of the Contract Documents, then the Owner may without prejudice applicable specification section. Lump sum items will be paid in to any other right or remedy and after giving the Contractor and his proportion to the amount of work done. All work required under surety a minimum of ten (10) days from delivery of a Written this contract shall be performed in complete conformance with the Notice, terminate the services of the Contractor and take Contract Documents and will be paid for at the Bid Price, complete possession of the Project and of all materials, equipment, tools, and accepted. The Bid Price shall include the cost of all materials, construction equipment and machinery thereon owned by the tools, labor, equipment, testing, appurtenances and work incidental Contractor and finish the Work by whatever method he may deem to or necessary for the completion of the work. expedient. In such case the Contractor shall not be entitled to receive any further payment until the Work is finished. If the Where variances occur between the Contract Drawings and unpaid balance of the Contract Price exceeds the direct and Specifications or within either document itself, the item or indirect costs of completing the Project, including compensation arrangement of better Quality, greater quantity, or highest cost for additional professional services, such excess shall be paid to shall be included in the Contract Price. The Engineer will decide the Contractor. If such costs exceed such unpaid balance, the on the item and manner in which work shall be installed. Contractor will pay the difference to the Owner. Such costs incurred by the Owner will be determined by the Engineer and Monthly progress payments will be made on the basis of incorporated in a Change Order. completed, in-place unit quantities, and agreed-upon percentages of completion of individual lump sum items. The Contractor shall Where the Contractor's services have been so terminated by the submit to the Engineer, when each progress payment falls due (but Owner, said termination shall not affect any right of the Owner not more than once a month), four (4) certified copies of a partial against the Contractor then existing or which may thereafter payment estimate filled out and signed by the Contractor covering accrue. Any retention or payment of monies by the Owner due the the Work performed during the period covered by the partial Contractor will not release the Contractor from compliance with payment estimate. Payment should not be requested on the basis the Contract Documents. of materials and equipment not incorporated in the Work. The Engineer will after receipt of each partial payment estimate, review After ten (10) days from delivery of a Written Notice to the the estimate and if necessary return the partial payment estimate to Contractor, the Owner may, without cause and without prejudice to the Contractor indicating corrections required and the Contractor any other right or remedy, elect to abandon the Project and will make the necessary corrections and resubmit the partial terminate the Contract. In such case, the Contractor shall be paid payment estimate. The Owner will, within thirty (30) days, pay the for all Work executed and any expense sustained plus reasonable Contractor a progress payment on the basis of the partial payment profit. estimate. The Owner shall retain five (5%) percent of the amount of each payment, for the one (1) year maintenance period If, through no act of fault of the Contractor, the Work is suspended following final completion and acceptance of all work covered by for a period of more than ninety (90) days by the Owner or under the Contract Documents. an order of court or other public authority, or the Engineer fails to act on any request for payment within thirty (30) days after it is All work covered by partial payment made shall thereupon become submitted, or the Owner fails to pay the Contractor substantially the sole property of the Owner, but this provision shall not be the sum approved by the Engineer, then the Contractor may, after construed as relieving the Contractor of the sole responsibility for ten (10) days from delivery of a Written Notice to the Owner and care and protection of the Work upon which payments have been the Engineer, terminate the Contract and recover from the Owner made or the restoration of any damaged Work, or as a waiver of payment for all Work executed and all expenses sustained. In the right of the Owner to require the fulfillment of all terms of the addition and in lieu of terminating the Contract, if the Engineer has Contract Documents. failed to act on a request for payment or if the Owner has failed to make any payment as aforesaid, the Contractor may, upon ten (10) Upon completion and acceptance of the Work, the Contractor shall days notice to the Owner and the Engineer, stop the Work until he submit to the Engineer four (4) copies of a final payment estimate

GC-5 00500 GENERAL CONDITIONS

filled out and signed by the Contractor covering all the Work 21. ACCEPTANCE OF FINAL PAYMENT AS RELEASE performed and supported by such data as the Engineer may reasonably require. The entire balance found to be due the The acceptance by the Contractor of final payment shall be and Contractor, minus the five percent (5%) retainage and minus any shall operate as a release to the Owner of all claims and all liability such sums as may be lawfully retained by the Owner, shall be paid to the Contractor for all things done or furnished in connection to the Contractor within thirty (30) days. with this Work and for every act and neglect of the Owner and others relating to or arising out of this Work. Any payment, The Contractor will indemnify and save the Owner or the Owner's however, final or otherwise, shall not release the Contractor or his agents harmless from all claims growing out of the lawful demands sureties from any obligations under the Contract Documents or the of Subcontractors, laborers, workmen, mechanics, materialmen, Performance Bond and Payment Bonds. and furnishers of machinery and parts thereof, equipment, tools, and all supplies, incurred in the furtherance of the performance of 22. INSURANCE the Work. The Contractor shall, at the Owner's request, furnish satisfactory evidence that all obligations of the nature designated The Contractor shall carry or require that there be carried: above have been paid, discharged, or waived. If the Contractor fails to do so the Owner may, after having notified the Contractor, A. LIABILITY INSURANCE either pay unpaid bills or withhold from the Contractor's unpaid compensation a sum of money deemed reasonably sufficient to pay The Contractor shall at his own cost and expense, procure and any and all such lawful claims until satisfactory evidence is maintain Comprehensive General Liability insurance, furnished that all liabilities have been fully discharged whereupon Comprehensive Auto liability insurance, and Comprehensive payment to the Contractor shall be resumed, in accordance with the Catastrophe liability insurance, as well as Worker's Compensation terms of the Contract Documents, but in no event shall the insurance as required by the appropriate Worker's Compensation provisions of this sentence be construed to impose any obligations Law or Act. All insurance shall be carried with insurers authorized upon the Owner, to either the Contractor, his Surety, or any third to do business in the State of Connecticut and evidence of party. In paying any unpaid bills of the Contractor, any payment insurance, with adequate limits of liability, shall be furnished to the so made by the Owner shall be considered as a payment made Town of Westport. Such evidence shall be in the form of a formal under the Contract Documents by the Owner to the Contractor and certificate of insurance properly executed by a licensed the Owner shall not be liable to the Contractor for any such representative of the participating insurers and must contain a payments made in good faith. clause granting at least thirty (30) days prior written notice to the Town of Westport of intent to affect cancellation, non-renewal, or 20. PARTIAL USE OF SITE IMPROVEMENTS other material change which may have an adverse effect on the policies of insurance referred to in the certificate. The interests of The Owner, at its election, may give notice to the Contractor and the Town of Westport must be added to the aforementioned place in use those sections of the Work which have been liability policies of insurance as an additional insured. completed, inspected and can be accepted as complying with the Specifications, if in its opinion each such section is reasonably Minimum coverage and limits of liability required: safe, fit and convenient for the use or accommodation for which it was intended, provided: -For Comprehensive General and Auto liability insurance the combined single limit of liability as respects bodily injury, a. The use of such sections of the Work shall in no way impede the personal injury and property damage liability shall be as completion of the remainder of the Work by the Contractor. follows: b. The Contractor shall not be responsible for any damages or Comprehensive General Liability: maintenance costs due directly to the use of such sections. $1,000,000. per occurrence $2,000,000. aggregate c. The use of such sections shall in no way relieve the Contractor of his liability due to having used defective materials or to poor Comprehensive Automobile Liability: workmanship. $1,000,000. per occurrence d. The period of guarantee stipulated in the section GUARANTY Comprehensive Catastrophe Liability (UMBRELLA): shall not begin until the final acceptance of all Work which the $5,000,000. per occurrence/aggregate Contractor is required to construct under this Contract. The above limits of liability shall apply to all premises-operations, elevators, independent contractors, products-completed operations, contractual liability, broad form property damage, XCU coverage

GC-6 00500 GENERAL CONDITIONS

extension, employee as additional insureds, automobiles- owned a Payment Bond in penal sums equal to the amount of the Contract and non-owned, including hired automobiles, and other coverage Price. Bonds shall be conditioned upon the performance by the which may be required to satisfy the Town of Westport. In every Contractor of all undertaking covenants, terms, conditions and instance coverage must apply both on and away from the premises agreements of the Contract Documents and upon the prompt referred to in the contract, and apply to all operations related payment by the Contractor to all persons supplying labor and thereto. Additionally, the Comprehensive General Liability materials in the prosecution of the Work. The Surety shall be a coverage must contain a per job/per location aggregate corporate bonding company licensed to transact business in the endorsement. State of Connecticut and named on the current list of "Surety Companies Acceptable on Federal Bonds" as published in the B.WORKER'S COMPENSATION INSURANCE Treasury Department Circular Number 570. The expense of these Bonds shall be borne by the Contractor. If at any time a surety on The policy shall be written in accordance with the statutory any such Bond is declared bankrupt, or loses its right to do provisions of the state of Connecticut, and shall include a broad business in the state within which the Work is to be performed, or form "All States" endorsement in the event the operations require is removed from the list of Surety Companies accepted on Federal any interstate involvement as respects employers-employee Bonds, or for any other justifiable cause, the Contractor shall, relationship. Full compliance with United States Longshoremen's within ten (10) days after notice from the Owner to do so, and Harborworkers's act must be observed where applicable. substitute an acceptable Bond (or Bonds) in such form and sum and signed by such other surety or sureties as may be satisfactory C.ADDITIONAL REQUIREMENT to the Owner. The premiums on such Bond shall be paid by the Contractor. No further payments shall be deemed due nor shall be The Contractor must require that all sub-contractors, agents and made until the new surety or sureties shall have furnished an assigns procure and maintain insurance protection comparable to acceptable Bond to the Owner. that required of the contractor. The Contractor shall not commence work under the contract until all insurance required has 24. ASSIGNMENTS been procured and approved by the Town of Westport; nor shall the Contractor allow any of its subcontractors to commence work Neither the Contractor nor the Owner shall sell, transfer, assign or until comparable insurance has been procured and approved by the otherwise dispose of the Contract or any portion thereof, or of his Town of Westport. All insurance shall be carried with insurers right, title or interest herein, or his obligations thereunder, without authorized by the Connecticut Department of Insurance to transact written consent of the other party. business in the State of Connecticut, and evidence of insurance must be furnished to the Town of Westport. All insurance shall be 25. INDEMNIFICATION written by companies of recognized financial standing, best rating "A" or better. The Contractor will indemnify and hold harmless the Owner and the Engineer and their agents and employees from and against all D.PROPERTY INSURANCE claims, damages, losses and expenses including attorneys' fees, arising out of, or resulting from, the performance of the Work, The Contractor shall, at its own cost and expense, assume all provided that any such claims, damage, loss or expense is responsibility for equipment and other property to be installed until attributable to bodily injury, sickness, disease or death, or to injury such equipment or other property is approved and accepted by the to or destruction of tangible property, including the loss of use Town of Westport. resulting therefrom; and is caused in whole or in part by an negligent or willful act or omission of the Contractor, and/or The Contractor shall also assume full responsibility for his and his Subcontractor, anyone directly or indirectly employed by any of employees own tools and equipment as well as for those tools and them or anyone for whose acts any of them may be liable. equipment of his subcontractors and their employees. In any and all claims against the Owner or the Engineer, or any of E. SURETY BONDS their agents or employees, by any employee of the Contractor, any Subcontractor, anyone directly or indirectly employed by any of The Contractor shall furnish the Town of Westport, a performance them, or anyone for whose acts any of them may be liable, the bond and a separate labor and materials payment bond as indemnification obligation shall not be limited in any way by any described below under "Contract Security". limitation on the amount of type of damages, compensation or benefits payable by or for the Contractor or any Subcontractor 23. CONTRACT SECURITY under Workmen's compensation acts, disability acts or other employee benefits acts. The Contractor shall within ten (10) days after the receipt of the Notice of Award furnish the Owner with a Performance Bond and

GC-7 00500 GENERAL CONDITIONS

The obligation of the Contractor under this section shall not extend persons directly employed by him. Nothing contained in this to the liability of the Engineer, his agents or employees, arising out Contract shall create any contractual relation between any of the preparation or approval of maps, contract Drawings, Subcontractor and the Owner. opinions, reports, surveys, Change Orders, designs or Specifications. 30. ENGINEER'S AUTHORITY

26. SEPARATE CONTRACTS The Engineer shall be the Owner's representative during the construction period and will decide questions which may arise as The Owner reserves the right to let other contracts or perform to quality and acceptability of materials furnished and Work Work by himself in connection with this Project. The Contractor performed. The Engineer will have a representative on site to shall afford the Owner and other Contractors reasonable determine if the Work is proceeding in accordance with the opportunity for the introduction and storage of their materials and Contract Documents. The Contractor will be held strictly to the the execution of their Work, and shall properly connect and intent of the Contract Documents in regard to the quality of coordinate his Work with theirs. If the proper execution or results material, workmanship and execution of the Work. Inspections of any part of the Contractor's Work depends upon the Work of may be made at the factory or fabrication plant of the source of others, the Contractor shall inspect and promptly report to the material supply. The Engineer will not be responsible for the Engineer any defects in such Work that render it unsuitable for construction means, controls, techniques, sequences, procedures, such proper execution and results. or construction safety.

27. UTILITY LINES 31. LAND AND RIGHTS-OF-WAY

The Contractor's attention is called to the fact that he is obligated Prior to issuance of Notice to Proceed, the Owner shall obtain all to inform all utility companies of his starting date on any work land and rights-of-way necessary for carrying out and for the phase and that any delays caused due to conflicts with the utility completion of the Work that is to be performed pursuant to the lines shall not be considered as a basis for extending the time for Contract Documents. completion. The Contractor assumes all responsibilities for any damage to the various utility services and all liabilities arising 32. GUARANTY therefrom. Please see Specification section A1-“NTC-Utility Mailing List” for a current list of utilities with facilities in the The Contractor shall guarantee all materials and equipment Town of Westport. furnished and Work performed for a period of one (1) year from the date of Completion unless a longer period is specified The Contractor is required to call "Call Before You Dig" at 1- elsewhere in the Contract Documents. The Contractor further 800-922-4455 at least 48 hours prior to any excavations or guarantees that all materials and equipment are new unless pavement removal operations. otherwise specified. The Contractor shall promptly make such corrections as may be necessary, including the repairs of damage to 28. WORK BY OTHERS other parts of the system resulting from defects. The Owner will give notice of observed defects. In the event that the Contractor Private utilities, Contractors, Developers, or other parties may be should fail to make such repairs, adjustments, or other Work that expected to be working within the Project area during the Contract. may be made necessary by defects, the Owner may do so and These may be as specifically listed elsewhere or if not so listed, charge the Contractor the cost thereby incurred. The Performance shall be determined by the Contractor. The Contractor shall Bond shall remain in full force and effect through the guarantee coordinate his work under this Contract with the work being done period. by others in order that construction may proceed in an efficient and logical manner. The Contractor shall have no claim or claims 33. TAXES whatever against the Owner, Engineer or other parties due to delays or other reasons caused by the work by others or his failure The Owner is exempt from payment of sales and compensating use to coordinate such work. taxes of the State of Connecticut and of Federal excise taxes on all 29. SUBCONTRACTING materials to be permanently incorporated into the work. These taxes shall not be included in the Bid. The Contractor may utilize the services of specialty Subcontractors on those parts of the Work which, under normal contracting The Owner will furnish the required certificates of tax exemption practices, are performed by specialty Subcontractors. The to the Contractor for use in the purchase of supplies and materials Contractor shall be fully responsible to the Owner for the acts and to be incorporated in the work. omissions of his Subcontractors, and of persons either directly or indirectly employed by them, as he is for the acts and omissions of

GC-8 00500 GENERAL CONDITIONS

The Owner's exemption does not apply to construction tools, In accordance with Public Act No. 366, the Contractor and each machinery, equipment, or other property purchased by or leased by Subcontractor shall agree and warrant that in the performance of the Contractor or to supplies or materials not incorporated in the this Contract they will not discriminate or permit discrimination work. The Contractor shall be responsible for and shall pay any against any person or group of persons on the grounds of race, and all applicable taxes, including sales and compensating use color, religion, or national origin in any manner prohibited by the taxes, on such tools, machinery, equipment or other property, or laws of the United States of the State of Connecticut. such supplies and materials not incorporated in the work. Prevailing Wage Rates can be found in Section 3 of the The Contractor shall pay all other sales, consumer, use and other specification. similar taxes required to be paid by him in accordance with any law from which the Town is not exempt.

34. PROVISIONS REQUIRED BY LAW DEEMED INSERTED

Each and every provision of law and clause by law to be inserted in this Contract shall be read and enforced as though it were included therein and, if through mistake or otherwise any such provision is not inserted, or is not correctly inserted, upon the application of either party the Contract shall forthwith be physically amended to make such insertion or correction.

35. SAFETY PROVISIONS

"This project is subject to all of the Safety and Health Regulations (See 29 CFR 1926 and all subsequent agreements) as promulgated by the U.S. Department of Labor on June 24, 1974. Contractors are urged to make themselves familiar with the requirements of these regulations."

The safety provisions of applicable laws, building and construction codes and the safety codes approved by the State Labor Commission and the provisions of the Federal "Occupational Safety and Health Standards" and "Safety and Health Regulations for Construction" shall be observed.

The Contractor shall employ such safety precautions as are required to prevent the happening of any accident to health, limb or property. When required, lights shall be maintained between the hours of sunset and sunrise, and during periods of low visibility.

36. WAGE RATES

Pursuant to Section 31-53 of the General Statues, as currently amended, every Contractor and Subcontractor performing work on this project shall post the prevailing wage scale as determined by the Labor Commissioner in prominent and easily accessible locations at the site, protected from the elements, or at such place or places as are used to pay its employees their wages.

GC-9 00700 SPECIAL CONDITIONS

TABLE OF CONTENTS

ARTICLE DESCRIPTION PAGE

1. Project Location SP-2

2. Scope of Work SP-2

3. Contract Documents SP-2

4. Certificates of Conformance SP-2

5. Performance Affidavits SP-3

6. Measurement and Payment SP-3

7. Construction Videotape Records SP-3

8. Sequence of Operations SP-3

9. Utilities SP-4

10. Job Meetings SP-4

11. Temporary Facilities SP-4

12. Tests SP-4

13. Codes, Ordinances, and Permits SP-5

14. Salvaged Materials SP-5

15. Disposal of Surplus Material SP-5

SP-1 00700 SPECIAL CONDITIONS

The Contractor's attention is directed to the following Special Provisions of this Contract. These Special Provisions shall be strictly adhered to. ------1. PROJECT LOCATION

The work included under this contract shall be conducted at various locations within the Town of Westport, on local roadways. Special Provision Section 01800 describes the limits of roadways to be milled and/or overlaid or reclaimed and rebuilt. All work shall be coordinated or scheduled so as to keep the schedule of the work as continuous as possible. Any construction easements and rights-of way shall be acquired by the Town if required.

2. SCOPE OF WORK

The Contractor shall furnish all labor, tools, equipment, appliances, and materials as required, shown on the Contract Drawings, if applicable, and described in these specifications. The principal items of Work are as follows:

a. The maintenance of traffic through the work zone during all paving and reconstruction operations through the use of certified flagmen or policemen supplied by the Town as necessary. These men shall coordinate the safe flow of traffic at all times and shall not be a part of the paving operation. All barricades, cones, advanced warning signs, and symbols necessary shall be provided by the contractor.

b. Preparation of the roadway prior to overlay. This shall include full depth reclamation where indicated, profile milling, milling of keys, shimming or leveling course required in the technical specifications. All areas to be paved shall receive a tack coat in accordance with the specifications.

c. Placement of bituminous concrete pavement at 2" and 4” thickness’ where indicated respectively, on town inclusive of tack coat in accordance with the specifications.

The work items described above do not define the complete list of work items required to complete the overlay improvements. The Contractor shall be responsible to perform all other associated work necessary for the completion of the project. In addition, the Contractor will be required to obtain all necessary licenses and permits required to construct the facilities, and assist others in conducting inspections related to the work.

3. CONTRACT DOCUMENTS

The Owner will furnish the Contractor, without charge, three copies of the Contract Documents, including Specifications and/or Drawings. Additional copies requested by the Contractor will be furnished at cost to the Contractor.

4. CERTIFICATES OF CONFORMANCE

In addition to other requirements specified, the Contractor shall furnish to the Engineer, in the manner as directed, notarized certificates of conformance for all materials to be furnished under

SP-2 00700 SPECIAL CONDITIONS this Contract, The notarized certificates of conformance shall state that the material to be furnished under this Contract meets the specification requirements. When directed, each shipment of material shall be accompanied by the manufacturer's notarized certificates of conformance, certifying that the materials meet the requirements of the specifications.

5. PERFORMANCE AFFIDAVITS

Whenever the specifications set forth, or imply, performance levels required of any equipment, apparatus or process, the Contractor shall secure certificates from the manufacturer or supplier of the same, certifying to the Contractor and the Owner, jointly, that the equipment, apparatus or process will meet in every way the performance levels so required. Certificates must be turned over to the Owner by the Contractor before approval will be given to the furnishing and installing of any such equipment, apparatus or process.

6. MEASUREMENT AND PAYMENT

The work has been divided into numerous unit quantity pay items. The unit quantity items will require measurement as stipulated in their respective Specifications. Monthly progress payments will be made on the basis of completed, in-place unit quantities.

All work required under this contract shall be performed in complete conformance with the Contract Documents and will be paid for at the Bid Price, complete and accepted. The Bid Price shall include the cost of all materials, tools, labor, equipment, testing, appurtenances and work incidental to or necessary for the completion of the work.

Where variances occur between the Contract Drawings and Specifications or within either document itself, the item or arrangement of better Quality, greater quantity, or highest cost shall be included in the Contract Price. The Engineer will decide on the item and manner in which work shall be installed.

7. CONSTRUCTION VIDEOTAPE RECORDS

Pre-construction and post-construction videotape recordings of the construction site, if required, shall be taken by Public Works personnel. The contractor should not include any cost associated with said videos in the contract price.

8. SEQUENCE OF OPERATIONS

Prior to commencement of construction, and within 10 days after the award of the Contract, the Contractor will be required to submit a detailed Sequence of Operations to the Engineer. The Sequence shall include, but not be limited to, expected start and finish dates each work item, a plan for sedimentation and erosion control, a plan for dust control, a plan for maintaining traffic during construction, and a schedule of shop drawing submittals (if required). Submittals for each section of the Specifications must be complete. Piecemeal submittals, at the option of the Engineer, will not be reviewed.

SP-3 00700 SPECIAL CONDITIONS

9. UTILITIES

Please refer to the "Notice to Contractor - Utility Contact List" in the ConnDOT Special Provisions.

The Contractor is required to call "Call Before You Dig" at 1-800-922-4455 at least 48 hours prior to any excavations or pavement removal operations.

The contractor is required to coordinate with all utility companies for the adjustment of structures in the area of the work.

10. JOB MEETINGS

Job meetings may be called by the Engineer on behalf of the Owner on the Project site, or at such place as is mutually agreed, at such times as is deemed necessary by the Owner which the Contractor shall attend. The Contractor shall have his Subcontractors attend as is deemed necessary to accomplish the purposes of said meeting. The Contractor and his Subcontractors shall be prepared to present complete and definite reports as to status of Work, dates of delivery, conditions of manufacturing, labor, shipping data, time of accomplishment or completion, method of construction and such other information as may be related to the execution of the Work.

11. TEMPORARY FACILITIES

The Contractor shall make all arrangements for temporary utility services needed for execution of the Contract, including, but not limited to water, and electric power. In addition the Contractor shall provide all heat and ventilation as may be necessary for thawing out, heating and drying the ground or materials and for proper execution, protection, and drying out of the Work. The Contractor shall provide all air, water, or electricity as may be required for the cleaning, testing, or repairs, of any vehicles or equipment.

12. TESTS

The Owner reserves the right to require testing of any and all material or samples of material delivered to the job site. The majority of testing shall be done by an independent testing laboratory at the expense of the Owner. However, in the case of HMA materials placed in paving operations, the Contractor shall also hire an independent testing agency to test in- place density during construction. Any material sampled and found not to meet the requirements of these specifications shall be rejected and the entire shipment removed from the site at the Contractor's expense. Furthermore, the Owner reserves the right to then require each material to be manufactured and tested in accordance with the standard specifications, (e.g. AWWA, ANSI, etc.), cited hereafter. Also all sampling and testing will conform to the current minimum requirements applicable to federally funded projects in accordance with the Standard Specification form 816. Normally, however, certificates of manufacture as called for in Special Provision 4 shall suffice unless specified otherwise in these Specifications.

SP-4 00700 SPECIAL CONDITIONS

13. CODES, ORDINANCES, AND PERMITS

1. Work shall be in conformance with the requirements of the Connecticut Building Code and ordinances of authorities having jurisdiction, as specified in the General Conditions.

2. If Contract Documents conflict with codes and ordinances, the Contractor shall so notify the Engineer immediately. If requirements of Contract Documents exceed requirements of codes and ordinances, the Contractor shall comply with requirements of Contract Documents.

3. Each Subcontractor shall obtain and pay for his own permits and certificates required by all governing bodies having jurisdiction and shall post them at the job site. Copies of the permits shall be sent to the Owner.

14. SALVAGED MATERIAL

Existing material to be salvaged, as called for or specified elsewhere in the Specifications, or as ordered by the Engineer, shall be delivered to a storage facility within the Town of Westport designated by the Engineer. Any material not identified by the Engineer for salvage is to be removed from the site and disposed of at the Contractor's expense. Asphalt millings and any broken asphalt shall be disposed of at the contractors’ expense.

15. DISPOSAL OF SURPLUS MATERIAL

The Contractor shall not dispose of any materials on private or public property, other than its own, in the Town of Westport without written permission from the Director of Public Works.

SP-5 01010 INTRODUCTION TO SPECIFICATIONS

The following specifications shall apply to the Work under this Contract:

Within the Specifications of this Contract, the following definitions shall apply.

STANDARD SPECIFICATIONS shall mean the State of Connecticut, Department of Transportation, "Standard Specifications for Roads, Bridges and Incidental Construction, Form 816”, latest Supplement.

Within the referred to portions of the Standard Specifications wherein the following terms are used they shall mean respectively:

Owner Town of Westport

Engineer Town of Westport Town Engineer or other authorized representative

Laboratory Laboratory designated by the Engineer, or Owner

APPLICABLE SAFETY CODE: shall mean the latest edition including any and all amendments, revisions and additions thereto of the Federal Department of Labor, Occupational Safety and Health Administration's "Occupational Safety and Health Standards" and "Safety and Health Regulations for Construction," the State of Connecticut, Labor Department, "Construction Safety Code," or State of Connecticut "Building Code," whichever is the more stringent for the applicable requirement.

LIST OF ABBREVIATIONS

AASHTO - American Association of State and Traffic Officials

ASTM - American Society of Testing and Materials

ANSI - American National Standard Institute

AWWA - American Water Works Association

AISC - American Institute of Steel Construction

ACI - American Concrete Institute

ACPA - American Concrete Pipe Association

APWA - American Public Works Association

01530 DUST CONTROL

A. GENERAL

DESCRIPTION- The Contractor shall provide water and/or calcium chloride and all equipment, labor, materials and related work necessary for the prevention and control of dust resulting from his operations in the performance of the Work.

B. MATERIALS

Water used shall be non-polluted. Calcium chloride shall conform to the requirements of AASHTO M 144 (ASTM D-98) except that the pellet form and the flake form shall be equally acceptable.

C. CONSTRUCTION METHODS

The Contractor shall exercise every precaution and means to prevent and control dust arising out of all construction operations from becoming a nuisance to abutting property owners of surrounding neighborhoods. The Contractor shall have available and maintain in operable condition, equipment capable of efficiently sweeping up earth and/or other materials from paved surfaces, and for applying water and/or calcium chloride uniformly over the applicable surfaces. Water and/or calcium chloride shall be applied to surface areas within the area of full depth reclamation work, and areas of milling if necessary, to all stockpiled materials, and surfaces at such rates and at such times as may be directed by the Engineer to allay dust conditions.

D. MEASUREMENT AND PAYMENT

No measurements or separate payment will be made for sweeping activities, or the procurement and application of water, under this section; the cost of this work shall be included in the Prices bid for other items.

Measurement will be made for calcium chloride based on the weights of shipping containers actually used, (i.e. bags), or alternatively if approved by the Engineer, based on weights of bulk calcium chloride used, measured with scales furnished by and at the expense of the Contractor, in a manner acceptable to the Engineer.

Pay item

Calcium Chloride for Dust Control TON

- END OF SECTION -

1 01600 RESTORATION

A. GENERAL

DESCRIPTION- The Contractor shall replace and/or restore to the condition existing immediately prior to construction or better, all signs, mailboxes, topsoil, lawns, bushes, shrubs, trees, fences, fields, walls, walks, driveways, , incidental works, or any and all other property removed or harmed in any way by reason of work done under this Contract except any item excepted elsewhere in the Contract Documents.

Restoration is divided into two categories:

1. Non-maintained areas are defined as pastures, orchards, open-field, woodlands or other areas which are not regularly maintained by the property owner.

2. A maintained area is defined as a lawn, garden, shrub area, drive, walk or other surface or surface structures, all of which are maintained in a regular fashion.

C. CONSTRUCTION METHODS

1. In restoring Non-maintained and Maintained areas the Contractor shall:

a. Replace to an equivalent depth any topsoil that has been removed or disturbed.

b. Remove all trees, brush and other items that the Contractor has cut in order to perform his work and dispose of the materials in a fashion approved by the Engineer.

c. Remove upon completion of the Work or sooner as directed by the Engineer all excess materials of construction such as stone, pipe, concrete block, gravel, etc. that the Contractor may have stockpiled for use during the course of the work.

d. Leave the land in smooth, even condition. All ruts, holes or other undesirable grading conditions which resulted from work under this Contract shall be filled and the area so graded to eliminate ponding. All drainage courses shall be restored to their pre-existing condition or better.

e. Fertilize and seed those areas where the original ground cover was removed or disturbed by operations under this Contract.

f. Reset all public or private monuments, iron pipes or other types of property line and geodetic markers damaged or disturbed by operations under this Contract. This work will be done by a Licensed Land Surveyor, approved by the Engineer, at no additional cost to the Owner.

g. Repair, reset or replace as directed by the Engineer, all walks, driveways, curbs, pipes, walls, utilities, fences, railings, stone walls, etc., and ornamental or utilitarian domestic accessories, such as but not limited to arbors, fireplaces, sheds, or other surfaces, structures, or property which may have been damaged, either directly or indirectly by his operations under this Contract.

Walks and driveways shall be equivalent to that removed but in no case shall concrete or bituminous concrete walks and driveways be of less quality than that shown on the Contract Drawings. 1 01600 RESTORATION

2. In addition within Maintained Areas, the Contractor shall:

a. Transplant all trees and cultivated bushes and shrubs which must be removed for construction. The Contractor shall not be required to transplant trees of more than 3-inch caliper. Trees over this caliper shall be cut and removed. For any such trees cut and removed, the Contractor shall replace them with a tree of like or approved kind, of 2-1/2 to 3-inch caliper, planted in a location as directed by the property owner but not more than 100 feet from the original tree's position.

b. Notify each property owner of the cultivated trees and shrubs scheduled for transplanting and shall transplant them at his own expense as directed by and to the satisfaction of the Engineer. However, in no case shall trees be replanted within 10 feet measured horizontally at the edge of a new pavement or new underground pipe line. The Contractor will not be required to transplant any shrub or tree over 200 feet away from its original location. Responsibility for successful transplanting rests with the Contractor, and any trees or shrubs that do not survive transplanting shall be replaced to the satisfaction of the Owner by the Contractor at the Contractor's expense. However, no tree or shrub required for replacement shall be over 3 inch caliper.

3. Prior to construction, the Contractor will carefully identify for inspection, by flagging, all trees, cultivated bushes and shrubs which shall be scheduled for transplanting. No trees or shrubs shall be transplanted without prior inspection and approval by the Engineer or his representatives. No trees, shrubs or bushes shall be cut or removed without notification of the Owner unless specifically called for in the Contract Drawings.

All landscaping work, transplanting, planting, etc., within the limits of maintained areas; will be done by a Landscaping Contractor or Subcontractor.

All work under this section shall conform to applicable sections of these specifications and the Standard Specifications.

D. MEASUREMENT AND PAYMENT- Monthly payments will be made in proportion to the amount of work done. The lump sum price listed in the bid schedule under the item "Restoration" shall include all the Work as described above, and/or as indicated in other specification sections, which may be necessary to complete the project.

The lump sum price shall include the cost of furnishing all materials, labor, equipment, tools, and incidentals required for the completion of this Work.

If no item "Restoration" appears in the Bid Schedule, the cost of this Work shall be included in the Prices bid for other items.

-End of Section-

2 01800 PAVEMENT PRESERVATION LIST

Road Sect ID From To SF SY Tons Application

Berndale Dr BERN1 Joanne Cir Pumpkin Hill 23823.0 2647.0 152.20 1” HMA overlay Berndale Dr BERN2 Pumpkin Hill Leslie Ln 41130.6 4570.1 262.78 1” HMA overlay Joanne Circle JOANNE1 Roseville Roseville 49252.6 5472.5 314.67 1” HMA overlay

Fresenius Rd FRESNI1 Long Lots Rd CDS 17826 1980.7 227.78 2” HMA overlay

Catamount Rd CATMNT1 Rte 136 Sturges Hwy 30039.3 3337.7 383.84 2” HMA overlay

Cross Highway 7 CROSSH7 Bayberry Ln Sturges Hwy 64611.3 7179.0 825.59 2” Mill & 2” HMA overlay Charcoal Hill1 CHARRD1 North Ave Charcoal Hill Cmn 41492.2 4610.2 530.18 2” Mill & 2” HMA overlay Charcoal Hill2 CHARRD2 Charcoal Hill Cmn Greenbriar 24382.8 2709.2 311.56 2” Mill & 2” HMA overlay Greenbrier Rd GRNBRI1 Easton Rd Charcoal Hill Rd 53176 5908.4 679.47 2” Mill & 2” HMA overlay Whitney St WHITNE1 East Main St Peaceful 21265 2362.8 271.72 2” Mill & 2” HMA overlay East Main St. EASTMN1 Post Road East Compo Rd N 28966 3218.4 370.12 2” Mill & 2” HMA overlay Sylvan Rd. So SYLVNS1 Post Road West Riverside Ave 36106.3 4011.8 461.36 2” Mill & 2” HMA overlay Sylvan Lane SYLVNL1 Sylvan Road S Riverside Ave 12061.6 1340.2 154.12 2” Mill & 2” HMA overlay Park Lane PARK1 Compo Road S Spicer Road 63147.5 7016.4 806.88 2” Mill & 2” HMA overlay

Cardinal La CARD1 Tupelo Rd CDS 35076.5 3897.4 672.30 Full Depth Recl. & 3” HMA overlay Tupelo Rd TUPELO1 Sturges HWY CDS 32170.6 3574.5 616.60 Full Depth Recl. & 3” HMA overlay Woody Lane WOODY1 Cross Hwy CDS 69342 7704.7 1329.06 Full Depth Recl. & 3” HMA overlay

Total milling SY = 38356

Total Reclamation SY = 15177

Total tons HMA = 8370.23

SP-1

SECTION 2 –

ConnDOT-BASED NOTICES, SPECIFICATIONS, AND SPECIAL PROVISIONS A1-NOTICE TO CONTRACTOR - UTILITY CONTACT LIST, (4/4/11)

The following Utility Companies have facilities in the Town of Westport:

Aquarion Water Company of Connecticut Mr. Carlos Vizcarrondo, Relocations Coordinator 600 Lindley Bridgeport, CT 06606 PHONE: (203) 337-5950 EXT: FAX: (203) 337-5839 E-MAIL: [email protected]

AT&T Connecticut (The Southern New England Telephone Company) Mr. Eric Clark, Manager-OSP Engineering 1441 North Colony Road Meriden, CT 06450-4101 PHONE: (203) 238-7407 EXT: FAX: (203) 237-8902 E-MAIL: [email protected]

AT&T - Local Network Services Mr. Michael J. Byrne, Senior Project Manager 153 Market Street, 5th Floor Hartford, CT 06103 PHONE: (860) 509-9985 EXT: FAX: E-MAIL: [email protected]

AT&T Corp. (Long Lines) Mr. Mark P. Burkhart, Manager Technical Analysis Senior Cable Engineer 139 Bacon Pond Road Woodbury, CT 06798 PHONE: (203) 266-4372 EXT: FAX: (203) 266-4487 E-MAIL: [email protected]

Cablevision of Connecticut, LP Mr. George Rebentisch, Construction Manager 122 River Street Bridgeport, CT 06604 PHONE: (203) 696-4765 EXT: FAX: (203) 334-0250 E-MAIL: [email protected]

______Fiber Technologies Networks, LLC Mr. Mark Schnauber, Controller 300 Meridian Centre Rochester, New York 14624 PHONE: (585) 697-5107 EXT: FAX: (585) 442-9709 E-MAIL: [email protected]

Northeast Utilities Service Company

1

A1-NOTICE TO CONTRACTOR - UTILITY CONTACT LIST, (4/4/11)

Mr. Stephen J. Klubnik, Engineering Manager - System Projects 107 Selden Street Berlin, CT 06037 PHONE: (860) 665-2473 EXT: FAX: (860) 665-2002 E-MAIL: [email protected]

Northeast Utilities Service Company - Transmission Department Mr. Daniel J. Garstka, Senior Engineer - Transmission Projects 107 Selden Street Berlin, CT 06037 PHONE: (860) 665-3515 EXT: FAX: E-MAIL: [email protected]

The Southern Connecticut Gas Company Mr. Thomas Chizinski, Director of Engineering 60 Marsh Hill Road Orange, CT 06477 PHONE: (203) 795-7868 EXT: FAX: (203) 795-7784 E-MAIL: [email protected]

Tennessee Gas Pipeline Company Mr. James Sinclair, Division Manager 8 Anngina Drive Enfield, CT 06082 PHONE: (860) 763-6028 EXT: FAX: E-MAIL: [email protected]

For a complete listing of Statewide Utility Contacts please visit the Connecticut DOT - Utility Mailing list website at:

http://www.ct.gov/dot/lib/dot/documents/dutilities/utilitymailinglist.pdf

2

A2-NOTICE TO CONTRACTOR - SECTION 4.06 AND M.04 MIX DESIGNATION EQUIVALENCY

Sections 4.06 and M.04 have been replaced in their entirety with the Special Provisions included as part of this contract. These Special Provisions reflect changes in mix designations for various types of hot-mix asphalt (HMA). The following table is to be used to associate mix designations noted on the plans with that in the contract specifications and related documents. Mix designations on each row are equivalent and refer to a single mix, which shall be subject to the requirements of the Special Provisions replacing Sections 4.06 and M.04.

Mix Designation Equivalency Table

Official Mix Designation Equivalent Mix Equivalent Mix Designation (a) Designation (b) (c) Superpave 1.5 inch Superpave 37.5 mm HMA S1 Superpave 1.0 inch Superpave 25.0 mm HMA S0.5 Superpave 0.5 inch Superpave 12.5 mm HMA S0.375 Superpave 0.375 inch Superpave 9.5 mm HMA S0.25 Superpave 0.25 inch Superpave 6.25 mm (d) Superpave #4 Superpave #4 Bituminous Concrete Class 1 N/A* N/A* Bituminous Concrete Class 2 N/A* N/A* Bituminous Concrete Class 3 N/A* N/A* Bituminous Concrete Class 4 N/A* N/A* Bituminous Concrete Class 12 N/A* N/A*

(a) This mix designation is generally included with projects where the English measurement system is used. The mix designation may contain both the English measurement system designation and the SI (metric) measurement system designation, one of which would be in parenthesis.

(b) This mix designation is generally included with projects where the SI (metric) measurement system is used. The mix designation may contain both the English measurement system designation and the SI measurement system designation, one of which would be in parenthesis.

(c) This mix is no longer in use except by contract-specific Special Provision; if this mix is called for in the Plans but no such Special Provision is included for this contract a suitable substitute must be approved by the Engineer.

(d) This mix is no longer in use except by contract-specific Special Provision; if this mix is called for in the Plans but no such Special Provision is included for this contract a suitable substitute must be approved by the Engineer.

* N/A = Not applicable; mix designation has not changed.

1

A3-NOTICE TO CONTRACTOR - SUPERPAVE DESIGN LEVEL INFORMATION

Hot-Mix Asphalt (HMA) constructed according to the Superpave mix-design system is required to attain a Superpave Design Level and is required to use a Performance Graded (PG) binder. The Superpave Design Levels required for this project are listed in Table 1. The required PG binder is indicated for each mix with an “X” in the appropriate box in Table 1.

TABLE 1 – Superpave Design Level and Performance Graded (PG) Binder

Project No. 2011 - 04 will require the following Superpave Design Level(s):

Mix Route Route Route Designation ____ALL______PG Binder ______PG64-22 Design Level Design Level Design Level HMA S0.25 X 2 - - HMA S0.375 X 2 - - HMA S0.5 X 2 - - HMA S1 X 2 - -

1

A4-NOTICE TO CONTRACTOR - NCHRP 350 REQ. FOR WORK ZONE TRAFFIC CONTROL DEVICES

CATEGORY 1 DEVICES (traffic cones, traffic drums, tubular markers, flexible delineator posts)

Prior to using the Category 1 Devices on the project, the Contractor shall submit to the Engineer a copy of the manufacturer’s self-certification that the devices conform to NCHRP Report 350.

CATEGORY 2 DEVICES (construction barricades, construction signs and portable sign supports)

Prior to using Category 2 Devices on the project, the Contractor shall submit to the Engineer a copy of the Letter of Acceptance issued by the FHWA to the manufacturer documenting that the devices (both sign and portable support tested together) conform to NCHRP Report 350 (TL-3).

Specific requirements for these devices are included in the Special Provisions.

Information regarding NCHRP Report 350 devices may be found at the following web sites:

FHWA: http://safety.fhwa.dot.gov/roadway_dept/road_hardware/index.htm

ATSSA: http://www.atssa.com/resources/NCHRP350Crashtesting.asp

NOTE: The portable wooden sign supports that have been traditionally used by most contractors in the State of Connecticut do NOT meet NCHRP Report 350 criteria and shall not be utilized on any project advertised after October 01, 2000.

CATEGORY 3 DEVICES (Truck-Mounted Attenuators & Work Zone Crash Cushions)

Prior to using Category 3 Devices on the project, the Contractor shall submit to the Engineer a copy of the Letter of Acceptance issued by the FHWA to the manufacturer documenting that the devices conform to NCHRP Report 350.

1

B1-SECTION 1.08T - PROSECUTION AND PROGRESS

Article 1.08.04 - Limitation of Operations - Add the following:

TIME RESTRICTIONS

In order to provide for traffic operations as outlined in the Special Provision "Maintenance and Protection of Traffic," the Contractor will not be allowed to perform any work that will interfere with existing traffic operations on all project roadways as follows:

ROUTE 1 (Post Road) and Riverside Ave The Contractor will not be allowed to perform any work that will interfere with the existing number of of traffic, including turning lanes, on: Monday through Friday between 6:00 a.m. and 8:00 p.m. Saturday and Sunday between 10:00 a.m. and 9:00 p.m.

ALL OTHER ROADWAYS The Contractor will not be allowed to perform any work that will interfere with the existing number of lanes of traffic, including turning lanes, on Monday through Friday between 5:00AM and 7:00AM or between 5:00PM and 7:00PM, unless approved in advance by the Engineer.

BITUMINOUS CONCRETE MILLING

The Contractor will be allowed to mill up to one (1) mile of roadway at a time, unless otherwise approved in advance by the Engineer. The Contractor shall schedule the operations so that pavement milling and/or re-paving operations shall be full width across the roadway section at the end of a work day/work night.

The Contractor shall perform the milling of existing pavement, and the installation of the new bituminous concrete pavement in accordance with the Special Provisions as contained elsewhere in the contract documents.

LANE CLOSURE RESTRICTIONS

It is anticipated that work on adjacent projects may be ongoing simultaneously with this project. The Contractor shall be aware of those projects so that coordination is maintained for proper Traffic flow at all times on all project roadways and this coordination is acceptable to the Engineer.

The Contractor will not be allowed to close a lane if a contractor working on an adjacent project has the opposite lane closed unless there is at least a one mile clear area length where the entire roadway is open to traffic, measured from the end of the first work area to the beginning of the next work area.

OTHER LIMITATIONS

The field installation of a signing pattern shall constitute interference with existing traffic operations and shall not be allowed except during the allowable periods.

If there is more than one alternating one-way traffic operation at one time, then there shall be at least one mile between signing patterns.

1

B1-SECTION 1.08T - PROSECUTION AND PROGRESS

The Contractor shall schedule operations so that pavement removal and roadway resurfacing shall be completed full width across a roadway (bridge) section by the end of a workday (worknight). All transverse height differentials on all roadway surfaces shall be tapered to negate any "bump" to traffic as specified elsewhere in this contract or as approved by the Engineer. Material for this taper shall be as approved by the Engineer.

All protective systems and traffic control devices as called for by the contract or ordered by the Engineer must be on-hand and available in sufficient quantity for immediate installation prior to any stage change.

Road Closures will only be allowed upon approval of the Engineer, and must be proposed at least 7 days in advance to provide for the necessary notification of Town agencies.

CONTRACTOR’S USE OF TOWN PROPERTY FOR STAGING

If permission is granted to the Contractor to utilize Town property or Town Right of Way as a storage area for either construction equipment or materials, the Contractor shall conform to the following:

1. After hours and weekend parking of construction equipment will not be allowed in landscaped areas which will cause damage to said areas. Also, equipment shall not be parked in locations which will cause sight line restrictions for motorists entering or exiting adjacent properties.

2. The Contractor will not be allowed to stockpile any material other than that material which is permitted in an Agreement that is required between the Town of Westport and the Contractor. The storage of unacceptable material such as construction debris, hazardous material, old truck batteries, abandoned construction vehicles, etc. will not be allowed.

3. The Contractor shall restore those areas used in accordance with the provisions as contained in Town Specification 001600 - Restoration.

TRAFFIC SIGNALS

The contractor shall coordinate construction operations with the Town of Westport Department of Public Works so as to coordinate replacement of loop detectors as needed. The Town will contract for loop detector installation separate from this contract.

2

C1-SECTION 9.75T - MOBILIZATION

9.75.01—Description: This item shall consist of all work necessary for the movement of personnel and equipment to the project site, and for the establishment of all Contractor's field offices, buildings and other facilities necessary to the performance of the work.

9.75.04—Method of Measurement: There shall be no separate measurement for “Mobilization”.

9.75.05—Basis of Payment: There will be no separate direct payment for “Mobilization” but rather it shall be included in the cost of other items

1

D1-0980001A-T – CONSTRUCTION STAKING

9.80.01—Description: The work under this item shall consist of construction layout and reference staking necessary for the proper control and satisfactory completion of all work on the project, except property lines, highway lines, or non-access lines.

9.80.02—Materials: All stakes used for control staking shall be of the same quality as used by the Department for this purpose. For slope limits, pavement edges, gutter lines, etc., where so- called "green" or "working" stakes are commonly used, lesser quality stakes will be acceptable, provided the stakes are suitable for the intended purpose. 9.80.03—Construction Methods: The Department will furnish the Contractor such control points, bench marks, and other data as may be necessary for the construction staking and layout by qualified engineering or surveying personnel as noted elsewhere herein. The Contractor shall be responsible for the placement and preservation of adequate ties to all control points, necessary for the accurate re-establishment of all base lines, center lines, and all critical grades as shown on the plans. All stakes, references, and batter boards which may be required for construction operations, signing and traffic control shall be furnished, set and properly referenced by the Contractor. The Contractor shall be solely and completely responsible for the accuracy of the line and grade of all features of the work. Any errors or apparent discrepancies found in previous surveys, plans, specifications or special provisions shall be called to the Engineer's attention immediately for correction or interpretation prior to proceeding with the work. During roadway construction (or site work), the Contractor shall provide and maintain for the periods needed, as determined by the Engineer, reference stakes at 50 foot intervals immediately prior to and during the formation of subgrade and the construction of all subsequent pavement layers. These stakes shall be properly marked as to station, offset and shall be referenced to the proposed grade, even if laser or GPS machine controls are used. All staking shall be performed by qualified engineering or surveying personnel who are trained, experienced and skilled in construction layout and staking of the type required under the contract. Prior to start of work, the Contractor shall submit for review and comment the qualifications of personnel responsible for construction staking on the project. All field layout and staking required for the project shall be performed under the direct supervision of a person, or persons, of engineering background experienced in the direction of such work and acceptable to the Engineer. If the personnel responsible for construction staking change during the course of the project, the Department shall be notified. The Department may check the control of the work, as established by the Contractor, at any time as the work progresses. The Contractor will be informed of the results of these checks, but the Department by so doing in no way relieves the Contractor of responsibility for the accuracy of the layout work. The Contractor shall correct or replace, at the Contractor’s own expense, any deficient layout and construction work which may be the result of the inaccuracies in the Contractor’s staking operations or the failure to report such inaccuracies, or the Contractor’s failure to report inaccuracies found in work done by the Department or by others. If, as a result of these inaccuracies, the Department is required to make further studies, redesign, or both, all expenses incurred by the Department due to such inaccuracies will be deducted from any monies due the Contractor. The Contractor shall furnish all necessary personnel, engineering equipment and supplies, materials, transportation, and work incidental to the accurate and satisfactory completion of this work.

1 ITEM NO. 0980001A

D1-0980001A-T – CONSTRUCTION STAKING

For roadways where the existing pavement markings need to be reestablished: Prior to any resurfacing or obliteration of existing pavement markings, the Contractor and a representative of the Engineer must establish and document pavement marking control points from the existing markings. These control points shall be used to reestablish the positions of the lanes, the beginnings and endings of tapers, lines, lane use arrows, stop bars, and any lane transitions in the project area. The Contractor shall use these control points to provide appropriate premarking prior to the installation of the final markings. The Contractor shall provide and maintain reference stakes and/or markings at 100 foot intervals immediately off the edge of pavement to be used to reestablish the existing pavement markings. The Contractor shall also provide and maintain reference stakes and/or markings at any point where there is a change in pavement markings to reestablish the existing pavement markings.

9.80.04—Method of Measurement: There shall be no separate measurement for “Construction Staking” under this contract. 9.80.05—Basis of Payment: There shall be no separate direct payment for "Construction Staking" under this contract. Rather, the cost of the work described above shall be included in the cost of other items.

2 ITEM NO. 0980001A

E1-SECTION 9.71T-MAINTENANCE AND PROTECTION OF TRAFFIC

9.71.01—Description: Unless other provisions are made on the plans or in the special provisions of the contract, the Contractor shall keep the roadway under construction open to traffic for the full length of the project and shall provide a sufficient number of travel lanes and pedestrian passways to move that traffic ordinarily using the roadway. The travel lanes and pedestrian passways shall be drained and kept reasonably smooth and in suitable condition at all times in order to provide minimum interference to traffic consistent with the proper prosecution of the work.

Suitable ingress and egress shall be provided at all times where required, for all intersecting roads and for all abutting properties having legal access.

When a scheme for maintenance of traffic, which may include detours, is shown on the plans or described in the special provisions of the contract, this shall govern unless an alternate scheme acceptable to the Engineer is offered by the Contractor at no additional cost. If no scheme is shown on the plans or described in the special provisions of the contract, and the Contractor wishes to deviate from the provisions of maintaining traffic as described in this section, the Contractor may submit and the Engineer may approve a schedule showing a proposed sequence of operations and a compatible method of maintaining traffic.

9.71.03—Construction Method: The Contractor shall furnish and erect signs legally closing the highway to traffic, as shown on the plans or directed by the Engineer, prior to commencing any work on the Project.

The Contractor shall furnish a sufficient number of signs, barricades, drums, traffic cones and delineators to forewarn traffic of the construction as shown on the traffic control plans contained within or as directed by the Engineer.

The Contractor shall also provide such safety measures, pavement markings, warning devices and signs as deemed necessary to safeguard and guide the traveling public through detours ordered by the Engineer, included in the approved scheme for maintenance of traffic, or as shown on the plans. The Contractor shall erect, maintain, move, adjust, clean, relocate and store these signs, barricades, drums, traffic cones and delineators when, where and as directed by the Engineer, and in accordance with the ATSSA guidelines contained in "Quality Standards for Work Zone Traffic Control Devices."

The use of unauthorized or unapproved signs, barricades, drums, traffic cones or delineators will not be permitted.

All signs in any one signing pattern shall be mounted the same height above the traveled surface. The Contractor shall keep all signs in proper position, clean and legible at all times. Care shall be taken so that weeds, shrubbery, construction materials or equipment, and soil, are not allowed to obscure any sign, light, or barricade. Signs that do not apply to existing conditions shall be removed or adjusted so that the legend is not visible to approaching traffic.

1

E1-SECTION 9.71T-MAINTENANCE AND PROTECTION OF TRAFFIC

The Contractor, when ordered by the Engineer, shall remove snow and take care of icy conditions on temporary, new and existing on any part of the right-of-way within the limits of the project. Payment for the cost thereof, will be made as extra work.

Snow removal and correction of icy conditions, other than those resulting from the Contractor's operations, on uncompleted contracts under traffic, will remain an obligation of the Town, the State, or others.

Should the Contractor fail to perform any of the work required under this section, the Town may perform or arrange for others to perform such work. In such cases, the Town will deduct from money due or to become due the Contractor all expenses connected there with which are found to be greater than the cost to the Town of Westport had the Contractor performed the specified work.

9.71.05—Basis of Payment: There shall be no separate payment for the item “Maintenance and Protection of Traffic”. Rather the cost of the work herein shall be included in the cost of other items.

2

E2-971001A-T – MAINTENANCE AND PROTECTION OF TRAFFIC

Article 9.71.01 – Description is supplemented by the following:

The Contractor shall maintain and protect traffic as follows and as limited in the Special Provision "Prosecution and Progress":

ROUTE 1 (Post Road) and Riverside Ave. The Contractor shall at all times maintain and protect the existing number of lanes of traffic, including turning lanes, each lane on a paved travel path not less than 11 feet in width, when performing work at or near the intersections of East Main Street/Route 1, Sylvan Road South/Route 1, Sylvan Road South/Riverside Ave., or Sylvan Lane/ Riverside Ave..

ALL OTHER ROADWAYS

The Contractor shall maintain and protect the existing number of lanes of traffic, including turning lanes, each lane on a paved travel path not less than 11 feet in width.

Excepted therefrom will be those periods, during the allowable periods, when the Contractor is actively working, at which time the Contractor will be allowed to maintain and protect at least an alternating one-way traffic operation on a paved travelpath not less than 12 feet in width. The length of the alternating one-way traffic operation shall not exceed 1000 feet.

Excepted therefrom will be those periods, during the allowable periods, when the Contractor will be allowed to halt traffic for a period not to exceed ten minutes. The Contractor shall allow all stored vehicles to proceed through the work area before halting traffic for another ten-minute period.

At all times the work area shall be separated from the travel path by the use of Traffic Cones placed at intervals not to exceed 30 feet.

COMMERCIAL AND RESIDENTIAL DRIVEWAYS

The Contractor shall maintain access to and egress from all commercial and residential driveways throughout the project limits. The Contractor will be allowed to close said driveways to perform the required work during those periods when the businesses are closed unless permission is granted from the business owner to close the during business hours. If a temporary closure of a residential driveway is necessary, the Contractor shall coordinate with the owner to determine the time period of the closure.

SIGNALIZED INTERSECTIONS

At all signalized intersections the Contractor shall coordinate with the Town of Westport to utilize a Uniformed Policemen with a police vehicle to maintain traffic flow during the period of time that the Contractor is in the or within 100 feet of the intersection. No work within 100 feet of the intersection shall commence until and unless the Uniformed Policeman is on station and actively directing traffic.

1 ITEM #0971001A E2-971001A-T – MAINTENANCE AND PROTECTION OF TRAFFIC

Article 9.71.03 - Construction Method is supplemented as follows:

TEMPORARY CONTROLS

All Traffic Cones, construction Signs, Construction sign supports, construction barricades, etc used in this project are required to be NCHRP 350 approved.

SIGNING

The Contractor shall maintain all existing overhead and side-mounted signs throughout the project limits during the duration of the project. The Contractor shall temporarily relocate signs and sign supports as many times as deemed necessary and install temporary sign supports and foundations if necessary and as directed by the Engineer. The temporary relocation of signs and supports, and the furnishing, installation and removal of any temporary supports and foundations, shall not be paid for separately but shall be included in the cost of the work.

When the necessary construction is completed, the Contractor, the Contractor shall re-install the existing signs in their original locations or as directed by the Engineer.

SIGNING PATTERNS

The Contractor shall erect and maintain all signing patterns in accordance with the traffic control plans contained herein. Proper distances between advance warning signs and proper taper lengths are mandatory.

The Contractor shall follow and conform to the alternating one way traffic pattern shown in the Special Provisions as Plan 13.

2 ITEM #0971001A E3-0971001A-PLAN13-ALTERNATING ONE-WAY TRAFFIC OPERATION - TRAFFICPERSON

1 ITEM #971001A E3-0971001A-PLAN13-ALTERNATING ONE-WAY TRAFFIC OPERATION - TRAFFICPERSON

2 ITEM #971001A E4-0971001A-NOTES FOR TRAFFIC CONTROL PLANS

1 ITEM #971001A E5-0971001A-T-PAVEMENT MARKINGS DURING CONSTRUCTION-SECONDARY ROADWAYS

During construction, the Contractor shall maintain temporary pavement markings on paved surfaces on all roadways throughout the limits of the project.

Temporary Pavement Markings

The Contractor shall install Temporary Plastic Pavement Marking Tape in place of painted pavement markings by the end of the work day/night. These temporary pavement markings shall include centerlines, lane lines (broken lines) and stop bars; edge lines are not required. Centerlines shall consist of two 4 inch wide yellow markings, 2 feet in length, side by side, 4 to 6 inches apart, at 40-foot intervals. No passing zones should be posted with signs in those areas where the final centerlines have not been established on two-way roadways. Stop bars may consist of two 6 inch wide white markings or three 4 inch wide white markings placed side by side. The Contractor shall remove and dispose of the Temporary Plastic Pavement Marking Tape when another course of bituminous concrete pavement is installed. The cost of furnishing, installing and removing the Temporary Plastic Pavement Marking Tape shall be at the Contractor’s expense.

1 F1-SECTION 9.77-TRAFFIC CONE

9.77.01—Description: Under this item the Contractor shall furnish all reflectorized orange traffic cones required on the project to conform to the requirements as stated in the item "Maintenance and Protection of Traffic," as shown on the plans and as directed by the Engineer.

The Contractor shall have, available on the project, a sufficient number of traffic cones to fulfill all the requirements as specified in the contract and to replace those traffic cones which have become damaged.

9.77.02—Materials: Traffic cones shall be constructed of materials to a thickness to withstand impact without damage to cones or to vehicles. The traffic cones shall be of sufficient mass or have bases to which ballast may be added to assure that they will not be blown over or displaced by wind from passing vehicles. Traffic cones used at night shall be reflectorized by utilizing Type VI Retroreflective Sheeting, in accordance with Subarticle M.18.09.01.

9.77.04—Method of Measurement: This item will be measured for payment by the number of traffic cones used on the Project.

9.77.05—Basis of Payment: This item will be paid for at the contract unit price each for "Traffic Cone" used on the Project. Each cone will be paid for once, regardless of the number of times it is used on the Project.

Any traffic cones that are missing, damaged or defaced so that they are not effective, as determined by the Engineer in accordance with the ATSSA guidelines contained in "Quality Standards for Work Zone Traffic Control Devices," shall be replaced by the Contractor at no cost to the State.

When the traffic cones are no longer required on the Project they shall remain the property of the Contractor.

Pay Item Pay Unit

Traffic Cone 28” ea. Traffic Cone 42” ea.

1 F3-1220011A-T - CONSTRUCTION SIGNS – TYPE III REFLECTIVE SHEETING

Article 12.20.01 – Description: The Contractor shall furnish construction signs with Type III reflective sheeting and their required portable supports or metal sign posts that conform to the requirements of NCHRP Report 350 (TL-3) and to the signing requirements stated in Article 9.71 “Maintenance and Protection of Traffic,” as shown on the plans and/or as directed by the Engineer.

Article 12.20.02 – Materials: Prior to using the construction signs and their portable supports, the Contractor shall submit to the Engineer a copy of the Letter of Acceptance issued by the FHWA to the manufacturer documenting that the devices (both sign and portable support tested together) conform to NCHRP Report 350 (TL-3).

Portable sign supports shall be designed and fabricated so that the signs do not blow over or become displaced by the wind from passing vehicles. Portable sign supports shall be approved by the Engineer before they are used.

Mounting height of signs on portable sign supports shall be a minimum of 1 foot and a maximum of 2 feet, measured from the pavement to the bottom of the sign.

All sign faces shall be rigid and reflectorized. Reflective sheeting shall conform to the requirements of Article M.18.09.01 (Type III). Sheet aluminum sign blanks shall conform to the requirements of Article M.18.13. Metal sign posts shall conform to the requirements of Article M.18.14. Application of reflective sheeting, legends, symbols, and borders shall conform to the requirements specified by the reflective sheeting manufacturer. Attachments shall be provided so that the signs can be firmly attached to the portable sign supports or metal posts without causing damage to the signs.

The following types of construction signs shall not be used: mesh, non-rigid, roll-up.

The following portable sign support systems or equivalent systems that meet the above requirements may be used:

• Korman Model #SS548 flexible sign stand with composite aluminum sign substrate (APOLIC)

• Traffix “Little Buster” dual spring folding sign stand with corrugated polyethylene (0.4 in. thick) sign substrate (InteCel)

Article 12.20.03 – Construction Methods: Ineffective signs, as determined by the Engineer and in accordance with the ATSSA guidelines contained in “Quality Standards for Work Zone Traffic Control Devices”, shall be replaced by the Contractor at no cost to the Town of Westport.

Signs and their portable supports or metal posts that are no longer required shall be removed from the project and shall remain the property of the Contractor.

1

F3-1220011A-T - CONSTRUCTION SIGNS – TYPE III REFLECTIVE SHEETING

Article 12.20.04 – Method of Measurement: Construction Signs - Type III Reflective Sheeting will be measured for payment by the number of square feet of sign face. Sign supports will not be measured for payment.

Article 12.20.05 – Basis of Payment: “Construction Signs – Type III Reflective Sheeting” required and used on the project will be paid for at the Contract unit price per square foot. This price shall include the furnishing and maintenance of the signs, portable sign supports, metal sign posts and all hardware. Each sign and support or posts will be paid for once, regardless of the number of times it is used.

Pay Item Pay Unit Construction Signs – Type III Reflective Sheeting S.F.

2

F4-0970006A-T - TRAFFICPERSON (MUNICIPAL POLICE OFFICER) 0970007A-T - TRAFFICPERSON (UNIFORMED FLAGGER) 9.70.01—Description: Under this item the Contractor shall coordinate with the Town of Westport to assist the Town in providing the services of Trafficpersons of the type and number, and for such periods, as the Engineer approves for the control and direction of vehicular traffic and pedestrians. Traffic persons requested solely for the contractor’s operational needs will not be paid for by the Town.

9.70.03—Construction Method: Prior to the start of operations on the project requiring the use of Trafficpersons, a meeting will be held with the Contractor, Trafficperson agency or firm, Engineer, and Westport Police, if applicable, to review the Trafficperson operations, lines of responsibility, lines of communication, and operating guidelines which will be used on the project.

On a weekly basis, the Contractor shall inform the Engineer of their scheduled operations for the following week and the number of Trafficpersons requested. The Engineer shall review this schedule and approve the type and number of Trafficpersons required. In the event of an unplanned, emergency, or short term operation, the Engineer may approve the temporary use of properly clothed persons for traffic control until such time as an authorized Trafficperson may be obtained. In no case shall this temporary use exceed 8 hours for any particular operation.

If the Contractor changes or cancels any scheduled operations without prior notice of same as required by the agency providing the Trafficpersons, and such that Trafficperson services are no longer required, the Contractor will be responsible for payment at no cost to the Town, of any show-up cost for any Trafficperson not used because of the change. Exceptions, as approved by the Engineer, may be granted for adverse weather conditions and unforeseeable causes beyond the control and without the fault or negligence of the Contractor.

Trafficpersons assigned to a work site are to only take direction from the Engineer or his authorized representative.

Trafficpersons shall wear a high visibility safety garment that complies with OSHA, MUTCD, ASTM Standards. Worn/faded safety garments that are no longer highly visible shall not be used. The Engineer shall direct the replacement of any worn/faded garment at no cost to the Town.

A Trafficperson shall assist in implementing the traffic control specified in the Maintenance and Protection of Traffic contained elsewhere in these specifications or as directed by the Engineer. Any situation requiring a Trafficperson to operate in a manner contrary to the Maintenance and Protection of Traffic specification shall be authorized in writing by the Engineer.

Trafficpersons shall consist of the following types:

1. Uniformed Law Enforcement Personnel: Law enforcement personnel shall wear the high visibility safety garment provided by their law enforcement agency. If no high visibility safety garment is provided, the Contractor shall provide the law enforcement personnel with a garment meeting the requirements stated for the Uniformed Flaggers’ garment.

1 F4-0970006A-T - TRAFFICPERSON (MUNICIPAL POLICE OFFICER) 0970007A-T - TRAFFICPERSON (UNIFORMED FLAGGER) Law Enforcement Personnel may be also be used to conduct motor vehicle enforcement operations in and around work areas as directed and approved by the Engineer.

Municipal Police Officers: Uniformed Municipal Police Officers shall be sworn Municipal Police Officers or Uniformed Constables who perform criminal law enforcement duties from the Municipality in which the project is located. Their services will also include an official Municipal Police vehicle when requested by the Engineer. Uniformed Municipal Police Officers will be used on non-limited access highways. If Uniformed Municipal Police Officers are unavailable, other Trafficpersons may be used when authorized in writing by the Engineer. Uniformed Municipal Police Officers and requested Municipal Police vehicles will be used at such locations and for such periods as the Engineer deems necessary to control traffic operations and promote increased safety to motorists through the construction sites.

2. Uniformed Flagger: Uniformed Flaggers shall be persons who have successfully completed flagger training by the American Traffic Safety Services Association (ATTSA), National Safety Council (NSC) or other programs approved by the Engineer. A copy of the Flagger’s training certificate shall be provided to the Engineer before the Flagger performs any work on the project. Uniformed Flaggers shall conform to Chapter 6E, Flagger Control, in the Manual of Uniformed Traffic Control Devices (MUTCD) and shall wear high-visibility safety apparel. The safety garment shall have the words "Traffic Control" clearly visible on the front and rear panels (minimum letter size 2 inches. Uniformed Flaggers shall use a STOP/SLOW paddle that is at least 18 inches in width with letters at least 6 inches high. The paddle shall be mounted on a pole of sufficient length to be 6 feet above the ground as measured from the bottom of the sign.

9.70.04—Method of Measurement: Services of Trafficpersons will be measured for payment by the actual number of hours for each person rendering services approved by the Engineer. These services shall include, however, only such trafficpersons as are employed within the limits of construction, project right of way of the project or along detours authorized by the Engineer to assist the motoring public through the construction work zone. Services for continued use of a detour or bypass beyond the limitations approved by the Engineer, for movement of construction vehicles and equipment, or at locations where traffic is unnecessarily restricted by the Contractor’s method of operation, will not be measured for payment by the Town, and will be directed to be charged to the Contractor.

Trafficpersons shall not work more than twelve hours in any one 24 hour period. In case such services are required for more than twelve hours, additional Trafficpersons shall be furnished and measured for payment. In cases where the Trafficperson is an employee on the Contractor’s payroll, payment under the item “Trafficperson (Uniformed Flagger)” will be made only for those hours when the Contractor’s employee is performing Trafficperson services, and when specifically approved by the Engineer.

Travel time will not be measured for payment for services provided by Uniformed Municipal Police Officers or Uniformed Flaggers.

Mileage fees associated with Trafficperson services will not be measured for payment.

2 F4-0970006A-T - TRAFFICPERSON (MUNICIPAL POLICE OFFICER) 0970007A-T - TRAFFICPERSON (UNIFORMED FLAGGER) Safety garments and STOP/SLOW paddles will not be measured for payment.

9.70.05—Basis of Payment: Trafficpersons will be paid in accordance with the schedule described herein. There will be no direct payment for safety garments or STOP/SLOW paddles. All costs associated with furnishing safety garments and STOP/SLOW paddles shall be considered included in the general cost of the item.

Uniformed Law Enforcement Personnel: The Town of Westport will pay the actual costs for “Trafficperson (Municipal Police Officer)” directly to the Westport Police Department. Billing should be addressed to the Town of Westport, Department of Public Works.

The invoice must include a breakdown of each officer’s actual hours of work and actual rate applied. Mileage fees associated with Trafficperson services are not reimbursable expenses and are not to be included in the billing invoice. The use of a municipal police vehicle authorized by the Engineer will be paid at the actual rate charged by the municipality. The invoice will be reviewed and approved by the Engineer prior to any payments. The rate charged by the municipality for use of a uniformed municipal police officer and/or a municipal police vehicle shall not be greater than the rate it normally charges others for similar services.

2. Uniformed Flagger: The Town of Westport will pay the actual costs for “Trafficperson (Uniformed Flagger)”, which price shall include all compensation, insurance benefits and any other cost or liability incidental to the furnishing of the trafficpersons ordered. Billing should be addressed to the Town of Westport, Department of Public Works.

There shall be no contract unit price in the bid or payments made through the contractor for these services.

3 G1-0406267A-T - MILLING OF Hot Mix Asphalt (HMA) – (0- 4 inches)

Description: This work shall consist of the milling, removal, and disposal of existing HMA pavement.

Materials: The existing HMA surface millings shall be disposed of offsite by the Contractor unless otherwise stated in the contract documents, or directed by the Engineer.

Construction Methods: The Contractor shall remove the HMA material using means acceptable to the Engineer. The pavement surface shall be removed to the line, grade, and existing or typical cross-section shown on the plans or directed by the Engineer.

The equipment for milling the pavement surface shall be designed and built for milling flexible pavements. It shall be self propelled with sufficient power, traction, and stability to maintain depth and slope and shall be capable of removing the existing HMA pavement.

The milling machine shall be equipped with a built-in automatic grade averaging control system that can control the longitudinal profile and the transverse cross-slope to produce the specified results. The longitudinal controls shall be capable of operating from any longitudinal grade reference, including string line, contact ski (30 feet minimum), non-contact ski (20 feet minimum), or mobile string line (30 feet minimum). The transverse controls shall have an automatic system for controlling cross-slope at a given rate. The Engineer may waive the requirement for automatic grade or slope controls where the situation warrants such action.

5 The rotary drum of the machine shall utilize carbide tip tools spaced not more than /8 inches apart. The forward speed of the milling machine shall be limited to no more than 45 feet/minute. The tools on the revolving cutting drum must be continually maintained and shall be replaced as warranted to provide a uniform pavement texture. The Contractor may request to perform a test strip to demonstrate that the same surface tolerance can be attained at an increased forward speed. The test strip shall be a maximum length of 500 feet and shall have the same criteria for surface tolerance as noted in this specification. The final decision for implementing the increased forward speed will be at the discretion of the Engineer.

The machine shall be equipped with an integral pickup and conveying device to immediately remove material being milled from the surface of the roadway and discharge the millings into a truck, all in one operation. The machine shall also be equipped with a means of effectively limiting the amount of dust escaping from the milling and removal operation.

When milling smaller areas or areas where it is impractical to use the above described equipment, the use of a lesser equipped milling machine may be permitted when approved by the Engineer.

Protection shall be provided around existing catch basin inlets, manholes, utility valve boxes, and any similar structures. Any damage to such structures as a result of the milling operation is the Contractor’s responsibility and shall be repaired at the Contractor’s expense.

1

G1-0406267A-T - MILLING OF Hot Mix Asphalt (HMA) – (0- 4 inches)

To prevent the infiltration of milled material into the storm drainage system, the Contractor shall take special care to prevent the milled material from falling into the inlet openings or inlet grates. Any milled material that has fallen into inlet openings or inlet grates shall be removed at the Contractor’s expense.

Surface Tolerance: The milled surface shall provide a riding surface with a uniform textured appearance. The milled surface shall be free from gouges, longitudinal grooves and ridges, oil film, and other imperfections that are a result of defective equipment, improper use of equipment, or poor workmanship. The Contractor, under the direction of the inspector, shall perform random spot-checks with a Contractor supplied ten-foot straightedge to verify surface tolerances at a minimum of five locations per day. The variation of the top of two ridges from 3 the testing edge of the straightedge, between any two ridge contact points, shall not exceed /8 inch. The variation of the top of any ridge to the bottom of the groove adjacent to that ridge shall not exceed 3/8 inch. Any unsatisfactory surfaces produced are the responsibility of the Contractor and shall be corrected at the Contractor’s expense and to the satisfaction of the Engineer.

The depth of removal will be verified by taking a measurement every 250 feet per each pass of the milling machine, or as directed by the Engineer. These depth measurements shall be used to monitor the average depth of removal.

Where a surface delamination between HMA layers or a surface delamination of HMA on Portland cement concrete causes a non-uniform texture to occur, the depth of milling shall be adjusted +/- ½ inch or until delamination is eliminated.

When removing a HMA pavement entirely from an underlying Portland cement concrete pavement, all of the HMA pavement shall be removed leaving a uniform surface of Portland cement concrete, unless otherwise directed by the Engineer.

Any unsatisfactory surfaces produced by the milling operation are the Contractor’s responsibility and shall be corrected at the Contractor’s expense and to the satisfaction of the Engineer.

No vertical faces, transverse or longitudinal, shall be left exposed to traffic. If any vertical face is formed in an area exposed to traffic a temporary paved transition will be established according to the requirements shown on the plans. If the milling machine is used to form a temporary transition, the length of the temporary transition shall conform to, Section 4.06 – Bituminous Concrete, “Transitions for Roadway Surface”, the requirements shown on the plans, or as directed by the Engineer. At all permanent limits of removal, a clean vertical face shall be established by saw cutting prior to paving.

The milling operation shall proceed in accordance with the requirements of the “Maintenance and Protection of Traffic” and “Prosecution and Progress” specifications, or other contract requirements. The more stringent specification shall apply.

2

G1-0406267A-T - MILLING OF Hot Mix Asphalt (HMA) – (0- 4 inches)

Prior to opening an area which has been milled to traffic, the pavement shall be thoroughly swept with a sweeper. The sweeper shall be equipped with a water tank and be capable of removing the millings and loose debris from the surface. Other sweeping equipment may be provided in lieu of the sweeper where acceptable by the Engineer.

Method of Measurement: This work will be measured for payment by the number of square yards of area from which the milling of asphalt has been completed and the work accepted. No area deductions will be made for minor unmilled areas such as catch basin inlets, manholes, utility boxes and any similar structures.

The depth of removal will be calculated by taking a measurement at a minimum every 250 feet per each pass of the milling machine, or as directed by the Engineer. The average depth of each section will determine which payment item is applicable.

Basis of Payment: This work will be paid for at the contract unit price per square yard for “Milling of HMA, (0 to 4 inches) (4 to 8 inches) (greater than 8 inches)”. This price shall include all equipment, tools, labor, and materials incidental thereto.

No separate payments will be made for cleaning the pavement prior to paving; providing protection and doing handwork removal of bituminous concrete around catch basin inlets, manholes, utility valve boxes and any similar structures; repairing surface defects as a result of the Contractors negligence; providing protection to underground utilities from the vibration of the milling operation; removal of any temporary milled transition; removal and disposal of millings; furnishing a sweeper and sweeping after milling. The costs for these items shall be included in the contract unit price.

Pay Item Pay Unit Milling of HMA – Sq. Yd (0- 4 inches)

Milling of HMA – Sq. Yd (over 4 to 8 inches)

Milling of HMA – Sq. Yd (greater than 8 inches)

3

G2-SECTION 4.03T-COLD RECLAIMED ASPHALT PAVEMENT

4.03.01—Description: Work under this section shall consist of the in-place recycling of an existing pavement. The pavement will be pulverized to a specified particle size, mixed with a specified depth of existing base, with additional aggregates as required, water and/or a liquid asphalt, and placed in a specified grade and cross section. Where necessary, existing subgrades may be modified (raised, lowered or modified with additional aggregates) to meet required design specifications.

Work shall also include rough and fine re-grading to the lines and grades specified by the Engineer, removal and disposal of excess material, compaction, and dust control in accordance with Town specification section 01530.

4.03.02—Materials: Materials for reclaimed asphalt pavements shall consist of existing pavements and bases. When it is necessary to improve the base or raise the grade line, additional base material may be specified by the Engineer.

If it is necessary to raise or lower any utilities or underdrains, the trench backfill material will meet Section M.02.05 or have the approval of the Engineer. If a rejuvenator is used during the final mixing operation, the material used shall be approved by the Engineer.

Samples of material will be obtained by the Materials Testing Laboratory as often as deemed necessary by the Engineer.

4.03.03—Construction Methods: Prior to the start of the pavement rehabilitation, all utilities and drainage systems shall be relocated as necessary.

Methods, equipment, tools, and any machinery to be used during construction shall be approved by the Engineer prior to the start of the Project. Prior to the actual pulverization of the pavement, drop inlets or catch basins that might be affected shall be sufficiently barricaded so as to prevent silt or runoff from plugging the drainage system.

If a rejuvenator is used, an approved metering device shall be used to ensure the accuracy of the amount of rejuvenator used.

Compaction shall be achieved by the use of a vibratory roller having the capability of producing high amplitude and low frequency vibrations. The compaction shall be a minimum of 95% of the proctor wet density (AASHTO T-180D).

4.03.04—Method of Measurement: The cold reclaimed asphalt pavement work will be measured for payment in square yards. The thickness will be as indicated on the plans, or as ordered by the Engineer and within +2 inches and -1 inch.

Measurement to determine the thickness will be made by the Engineer at intervals of 500 feet or less. If deficient thicknesses are found, the Engineer will make such additional measurements as he considers necessary to determine the limits of the deficiency. Areas not within allowable tolerance shall be corrected, as ordered by the Engineer, without additional compensation to the Contractor.

1

G2-SECTION 4.03T-COLD RECLAIMED ASPHALT PAVEMENT

Additional aggregates, as required, shall be measured for payment by the number of tons of aggregate delivered and incorporated into the pavement structure.

4.03.05—Basis of Payment: This work will be paid for at the contract unit price per square yard for "Cold Reclaimed Asphalt Pavement," which price shall include all materials (except additional aggregate), equipment, tools, and labor incidental thereto.

Additional aggregate shall be paid at the contract unit price per ton (metric ton) delivered to the project site.

Pay Item Pay Unit Cold Reclaimed Asphalt Pavement s.y. Additional Aggregate ton

2

G3-SECTION M.05T-PROCESSED AGGREGATE

M.05.01—Processed Aggregate Base and Pavement: The materials for this work shall conform to the following requirements:

1. Gradation: Coarse and fine aggregates shall be combined and mixed by approved methods so that the resulting material shall conform to the following gradation requirements:

Square Mesh Sieves Percent Passing by Mass

Pass 2 1/2 inches (63 mm) 100

Pass 2 inches (50 mm) 95-100

Pass 3/4 inch (19 mm) 50-75

Pass 1/4 inch (6.3 mm) 25-45

Pass #40 (425 µm) 5-20

Pass #100 (150 µm) 2-12

2. Coarse Aggregate: Coarse aggregate shall be either gravel, broken stone or reclaimed miscellaneous aggregate containing no more than 2% by weight (mass) of asphalt cement, at the option of the Contractor. When tested by means of the Los Angeles Machine, using AASHTO Method T 96, the coarse aggregate shall not have a loss of more than 50%.

(a) If gravel is used for the coarse aggregate, it shall consist of sound, tough, durable particles of crushed or uncrushed gravel or a mixture thereof, free from soft, thin, elongated or laminated pieces, lumps of clay, loam and vegetable or other deleterious substances.

(b) If broken stone is used for the coarse aggregate, it shall consist of sound, tough, durable fragments of rock of uniform quality throughout. It shall be free from soft disintegrated pieces, mud, dirt, organic or other injurious material.

(c) If the reclaimed miscellaneous aggregate is used for the coarse aggregate, it shall consist of sound, tough, durable fragments of uniform quality throughout. It shall be free from soft disintegrated pieces, mud, dirt, glass, organic or other injurious material.

(d) Soundness for Gravel, Broken Stone and Reclaimed Miscellaneous Aggregate: When tested by magnesium sulfate solution for soundness using AASHTO Method T 104, the coarse aggregate shall show a loss of not more than 15% at the end of 5 cycles.

3. Fine Aggregate: The fine aggregate shall be natural sand, stone sand, screenings or any combination thereof. The fine aggregate shall be limited to material 95% of which passes a No. 4 (4.75-mm) sieve having square openings and not more than 8% of which passes a No. 200 (75- µm) sieve. The material shall be free from clay, loam and deleterious materials.

1

G3-SECTION M.05T-PROCESSED AGGREGATE

(a) Plasticity: When natural sand is used, the fine aggregate shall conform to the requirements of Article M.02.06-2.

(b) Plasticity: When screenings or any combination of screenings and natural sand or any combination of stone sand and natural sand are used, the following requirements shall apply:

(1) When the fraction of the dry sample passing the No. 100 (150-µm) mesh sieve is 6% or less by weight (mass), no plastic limit test will be made.

(2) When the fraction of the dry sample passing the No. 100 (150-µm) mesh sieve is greater than 6% and not greater than 10% by mass, that fraction shall not have sufficient plasticity to permit the performing of the plastic limit test, using AASHTO Method T 90.

(3) When the fraction of the dry sample passing the No. 100 (150-µm) mesh sieve is greater than 10% by weight (mass), the sample shall be washed; and additional material passing the No. 100 (150-µm) mesh sieve shall be determined by AASHTO Method T 146, except that the No. 100 (150-µm) mesh sieve shall be substituted for the No. 40 (425-µm) mesh sieve where the latter is specified in AASHTO Method T 146. The combined materials that have passed the No. 100 (150-µm) mesh sieve shall not have sufficient plasticity to permit the performing of the plastic limit test using AASHTO Method T 90.

Additional aggregates, as required, shall be measured for payment by the number of tons (metric tons) of aggregate delivered and incorporated into the pavement structure.

4.03.05—Basis of Payment:

Additional aggregate shall be paid at the contract unit price per ton (metric ton) delivered to the project site.

Pay Item Pay Unit Additional Aggregate ton

2

G4-SECTION M.04T - BITUMINOUS CONCRETE M.04.01—Bituminous Concrete Materials and Facilities M.04.02—Mix Design and Job Mix Formula (JMF) M.04.03—Production Quality Control (QC) Testing and Control of Mixture

M.04.01—Bituminous Concrete Materials and Facilities: Each source of material, and facility used to produce and test bituminous concrete (HMA) must be a source that has been qualified on an annual basis by the Connecticut Department of Transportation, (ConnDOT). The basis of approval for plant machinery, material processing & controls, and field laboratory requirements are available from ConnDOT. Test Procedures and Specifications referenced herein are in accordance with the latest AASHTO and ASTM Standard Test Procedures and Specifications. Such references when noted with an (M) have been modified by ConnDOT and are detailed in Table M.04.03-6.

The Contractor shall submit to the Engineer all sources of coarse aggregate, fine aggregate, mineral filler and PG binder. The Contractor shall submit a Material Safety Data Sheet (MSDS) for each grade of binder to be used on the Project. The Contractor shall not change material sources without prior approval of the Engineer.

An adequate quantity of each size aggregate, mineral filler and bitumen shall be maintained at the HMA plant site at all times while the plant is in operation to ensure that the plant can consistently produce bituminous concrete mixtures that meet the job mix formula (JMF) as specified in M.04.02. The quantity of such material shall be reviewed by the Engineer on an individual plant basis and is dependent upon the plant's daily production capacity, but shall never be less than one day’s production capacity. Less than one day’s production capacity may be cause for the job mix formula to be rejected.

1. Coarse Aggregate: a. Requirements: The coarse aggregate shall consist of clean, hard, tough, durable fragments of crushed stone or crushed gravel of uniform quality. Aggregates from multiple sources of supply must not be mixed or stored in the same stockpile.

b. Basis of Approval: The request for approval of the source of supply shall include a washed sieve analysis in accordance with AASHTO T 27. The Gsa, Gsb, and Pwa shall be determined in accordance with AASHTO T 85. The coarse aggregate must not contain more than 1% crusher dust, sand, soft disintegrated pieces, mud, dirt, organic and other injurious materials. When tested for abrasion using AASHTO T 96, the aggregate loss must not exceed 40%. When tested for soundness using AASHTO T 104 with a magnesium sulfate solution, the coarse aggregate must not have a loss exceeding 10% at the end of 5 cycles.

For HMA mixtures, materials shall also meet the coarse aggregate angularity criteria as specified in Tables M.04.02-2 thru M.04.02-4 for blended aggregates retained on the #4 sieve when tested according to ASTM D 5821. The amount of aggregate particles of the coarse aggregate blend retained on the #4 sieve that are flat or elongated shall be determined in accordance with ASTM D 4791 and shall not exceed 10% by weight when tested to a 3:1 ratio, as shown in Tables M.04.02-2 thru M.04.02-4.

1

G4-SECTION M.04T - BITUMINOUS CONCRETE

2. Fine Aggregate: Requirements: The fine aggregate from each source quarry/pit deposit shall consist of clean, hard, tough, rough-surfaced and angular grains of natural sand; manufactured sand prepared from washed stone screenings; stone screenings, slag or gravel; or combinations thereof, after mechanical screening or manufactured by a process approved by the Engineer. The Contractor is prohibited from mixing two or more sources of fine aggregate on the ground for the purpose of feeding into an HMA plant.

a. All fine aggregate shall meet the listed criteria shown in items #1 thru #7 of Table M.04.01-1. Table M.04.01-1 indicates the quality tests and criteria required for all fine aggregate sources. Individually approved sources of supply shall not be mixed or stored in the same stockpile. The fine aggregates must be free from injurious amounts of clay, loam, and other deleterious materials.

For Superpave mixtures, in addition to the above requirements, the fine aggregate angularity shall be determined by testing the materials passing the #8 sieve in accordance with AASHTO T 304, Method A. Qualification shall be based on the criteria listed in Tables M.04.02-2 thru M.04.02-4. The fine aggregate shall also be tested for clay content as a percentage contained in materials finer than the #8 sieve in accordance with AASHTO T 176.

Table M.04.01-1: Fine Aggregate Criteria by Pit/Quarry Source AASHTO Item Title Criteria Protocol 1 Grading T 27 and T 100% Passing the 3/8 inch 11 95% Passing the #4 minimum 2 Absorption T 84 3% maximum 3 Plasticity limits T 90 0 or not detectable 4 L.A. Wear T 96 50% maximum(fine aggregate particle size # 8 and above) 5 Soundness by T 104 20% maximum @ 5 cycles Magnesium Sulfate 6 Clay Lumps and T 112 3% maximum Friable Particles 7 Deleterious As Deleterious substances include: Organic or inorganic Criteria determined calcite, hematite, shale, clay or clay lumps, friable by the materials, coal-lignite, shells, loam, mica, clinkers, or Engineer organic matter (wood, etc). -Shall not contain more than 3% by mass of any individual listed constituent and not more than 5% by mass in total of all listed constituents.

If Fine aggregate is tested by the CTDOT twice and does not meet above criteria.

2

G4-SECTION M.04T - BITUMINOUS CONCRETE

• Required to be performed by the Contractor at no expense to the Department.

• Report assignable cause(s), corrective action taken to mitigate source and written request for resample.

• If fine aggregate fails upon retest, Contractor may Pit/source C 295 be permitted to request trial use on roadway for 8 Petrographic (ASTM) evaluation using the subject fine aggregate in Analysis HMA, to be monitored for no more than 48 months.

• Evaluation location(s); mix size & level; terms and costs related to this application; determination of performance, and approval will be established at the sole discretion of the Engineer.

b. Basis of Approval: A Quality Control Plan for Fine Aggregate (QCPFA) provided by the Contractor shall be submitted for review and approval for each new source documenting how conformance to Items 1 through 7 as shown in Table M.04.01-1 is monitored. The QCPFA must be resubmitted any time the process, location or manner of how the fine aggregate (FA) is manufactured changes, or as requested by the Engineer. The QCPFA must include the locations and manufacturing processing methods. The QCPFA for any source may be suspended by the Engineer due to the production of inconsistent mixtures.

The Contractor shall submit all test results to the Engineer for review. The Contractor shall also include a washed sieve analysis in accordance with AASHTO T 27/T 11. Any fine aggregate component or final combined product shall have 100% passing the 3/8 inch sieve and a minimum of 95% passing the # 4. The Gsa, Gsb, and Pwa shall be determined in accordance with AASHTO T 84.

The Contractor will be notified by the Engineer if any qualified source of supply fails any portion of Table M.04.01-1. One retest will be allowed for the Contractor to make corrections and/or changes to the process. If, upon retest, the material fails again, the use of the material will not be permitted without additional testing.

The Contractor may solicit additional testing by a third party acceptable to the Engineer to perform a Petrographic analysis (ASTM C 295), at its expense. The Contractor shall submit the results of the analysis with recommended changes to the manufacturing process to the Engineer. The Contractor shall submit fine aggregate samples for testing by the Engineer after the recommended changes have been made. Upon review of the Petrographic analysis report and identified items that were corrected, the source may be re-sampled and tested by the Engineer.

3

G4-SECTION M.04T - BITUMINOUS CONCRETE c. The Contractor may request that the use of such material not meeting the requirements be considered on select project(s) for certain applications. HMA pavement incorporating such material will be monitored and evaluated for a period not to exceed 48 months, at the direction of the Department and at the expense of the Contractor. Terms of any evaluation and suitable application will be predetermined by the Engineer.

If the Engineer determines, upon evaluation, that the fine aggregate performance is adequate and not harmful to the pavement’s serviceability, the Department may approve the material for use in HMA mixtures in similar applications.

3. Mineral Filler: a. Requirements: Mineral filler shall consist of finely divided mineral matter such as rock dust, including limestone dust, slag dust, hydrated lime, hydraulic cement, or other accepted mineral matter. At the time of use it shall be freely flowing and devoid of agglomerations. Mineral Filler shall be introduced and controlled at all times during production in a manner acceptable to the Engineer.

b. Basis of Approval: The request for approval of the source of supply shall include the location, manufacturing process, handling and storage methods for the material. Mineral filler shall conform to the requirements of AASHTO M-17

4. Liquid Bituminous Materials: a. Performance grade (PG) binder Requirements: i. Binders shall contain uniformly mixed and blended liquid bituminous materials that are free of contaminants such as fuel oils and other solvents. Such binders shall be properly heated and stored to prevent damage or separation. A PG binder shall be classified by the supplier as a “Neat” binder for each lot and be so labeled on each bill of lading. Neat PG binders shall be asphalts free from modification with: fillers, extenders, reinforcing agents, adhesion promoters, thermoplastic polymers, acid modification and other additives, and shall indicate such information on each bill of lading and certified test report.

ii. The blending at mixing plants of PG binder from different suppliers is strictly prohibited. Contractors who blend PG binders will be classified as a supplier and will be required to certify the binder in accordance with AASHTO R-26(M). The asphalt binder shall be Performance Grade 64-22 Neat asphalt. The binder shall meet the requirements of AASHTO M-320(M) and AASHTO R-29(M). The Contractor shall submit a Certified Test Report and bill of lading representing each delivery in accordance with AASHTO R-26(M). The Certified Test Report must also indicate the binder specific gravity at 77°F; rotational viscosity at 275°F and 329°F and the mixing and compaction viscosity-temperature chart for each shipment. iii. The Contractor shall submit the name(s) of personnel responsible for receipt, inspection, and record keeping of PG binder materials. Contractor plant personnel shall document specific storage tank(s) where binder will be transferred and stored until used, and provide binder samples to the Engineer upon request. The person(s) shall assure that each shipment (tanker truck) is accompanied by a statement certifying

4

G4-SECTION M.04T - BITUMINOUS CONCRETE that the transport vehicle was inspected before loading and was found acceptable for the material shipped and that the binder will be free of contamination from any residual material, along with two (2) copies of the bill of lading.

iv. Basis of Approval: The request for approval of the source of supply shall list the location where the material will be manufactured, and the handling and storage methods, along with necessary certification in accordance with AASHTO R-26(M). Only suppliers/refineries that have an approved “Quality Control Plan for Performance Graded Binders” formatted in accordance with AASHTO R-26(M) will be allowed to supply PG binders to Department projects.

b. Cut-backs (medium cure type) i. Requirements: The liquid petroleum materials shall be produced by fluxing an asphalt base with appropriate petroleum distillates to produce the grade specified.

ii. Basis of Approval: The request for approval of the source of supply shall be submitted at least seven days prior to its use listing the location where the materials will be produced, and manufacturing, processing, handling and storage methods. The Contractor shall submit a Certified Test Report in accordance with article 1.06 and a Material Safety Data Sheet (MSDS) for the grade to be used on the Project. The liquid asphalt shall be MC-250 conforming to AASHTO M-82.

c. Emulsions i. Requirements: The emulsified asphalt shall be homogeneous and not be used if exposed to freezing temperatures.

ii. Basis of Approval: The request for approval of the source of supply must include the location where the materials will be produced, and manufacturing, processing, handling and storage methods.

1. Emulsified asphalts shall conform to the requirements of AASHTO M-140. Materials used for tack coat shall not be diluted and meet grade RS-1. When ambient temperatures are 80˚F and rising, grade SS-1 or SS-lh may be substituted if accepted by the Engineer. Each shipment shall be accompanied with a Certified Test Report listing Saybolt viscosity, residue by evaporation, penetration of residue, and weight per gallon.

2. Cationic emulsified asphalt shall conform to the requirements of AASHTO M- 208(M). Materials used for tack coat shall not be diluted and meet grade CRS-1. The settlement and demulsibility test will not be performed unless deemed necessary by the Engineer. When ambient temperatures are 80˚F and rising, grade CSS-1 or CSS-lh may be substituted if accepted by the Engineer. Each shipment shall be accompanied with a Certified Test Report listing Saybolt viscosity, residue by evaporation, penetration of residue, and weight per gallon.

5. Reclaimed Asphalt Pavement (RAP):

5

G4-SECTION M.04T - BITUMINOUS CONCRETE a. Requirements: RAP shall consist of asphalt pavement constructed with asphalt and aggregate reclaimed by cold milling or other removal techniques approved by the Engineer. For bituminous mixtures containing RAP, the Contractor shall submit a JMF in accordance with M.04.02 to the Engineer for review.

b. Basis of Approval: The RAP material will be accepted on the basis of one of the following criteria:

i. When the source of all RAP material is from pavements previously constructed on Department projects, the Contractor shall provide a materials certificate listing the detailed locations and lengths of those pavements and that the RAP is only from those locations listed.

ii. When the RAP material source or quality is not known, the Contractor shall test the material and provide the following information along with a request for approval to the Engineer at least 30 calendar days prior to the start of the paving operation. The request shall include a material certificate stating that the RAP consists of aggregates that meet the specification requirements of M.04.01-1 through 3 and that the binder in the RAP is substantially free of solvents, tars and other contaminants. The Contractor is prohibited from using unapproved material on Department projects and shall take necessary action to prevent contamination of approved RAP stockpiles. Stockpiles of unapproved material shall remain separate from all other RAP materials at all times. The request for approval shall include the following:

1. A 50-pound sample of the RAP to be incorporated into the recycled mixture. 2. A 25-pound sample of the extracted aggregate from the RAP. 3. After recovery of binder from the RAP by AASHTO T 170(M), the viscosity test results shall be reported when tested at 140°F by AASHTO T 202 or T 316. 4. A statement that RAP material has been crushed to 100% passing the ½ inch sieve and remains free from contaminants such as joint compound, wood, plastic, and metals.

6. Crushed Recycled Container Glass (CRCG): a. Requirements: The Contractor may propose to use clean and environmentally-acceptable CRCG in an amount not greater than 5% by weight of total aggregate.

b. Basis of Approval: The Contractor shall submit to the Engineer a request to use CRCG. The request shall state that the CRCG contains no more than 1% by weight of contaminants such as paper, plastic and metal and conform to the following gradation:

CRCG Grading Requirements Sieve Size Percent Passing 3/8-inch 100 No. 4 35-100 No. 200 0.0-10.0

6

G4-SECTION M.04T - BITUMINOUS CONCRETE 7. Joint Seal Material: Requirements: Joint seal material shall be a hot-poured rubber compound intended for use in sealing joints and cracks in Pavements. Joint seal material must meet the requirements of AASHTO M-324 – Type 2.

8. Plant production requirements a. Storage Silos: i. The Contractor may use silos for short-term storage of Superpave mixtures with prior notification and approval of the Engineer. A silo must have heated cones and an unheated silo cylinder if it does not contain a separate internal heating system. Prior approval must be obtained for storage times greater than those indicated. When multiple silos are filled, the Contractor shall discharge one silo at a time. Simultaneous discharge of multiple silos is not permitted. Type of silo cylinder Maximum storage time for all classes (hr) Open Surge 4 Unheated – Non-insulated 8 Unheated – Insulated 18 Heated – No inert gas To be determined by the Engineer

ii. For all classes of mixture sampled from hauling vehicles at the plant after storage in silos (virgin or mixture containing RAP) except 5, 5A, and 5B, the binder properties of the recovered asphalt shall meet the PG binder grade specified when recovered by AASHTO T 170(M) and tested in accordance with AASHTO R-29 and M-320(M).

iii. If mixture coming out of a silo continuously does not meet the requirements of M.04.03, or the binder does not meet the PG requirements, the Engineer shall deem that silo unacceptable for use.

b. Aggregates: The Contractor shall ensure that aggregate stockpiles are managed to provide uniform gradation and particle shape, prevent segregation and cross contamination in a manner acceptable to the Engineer. For drum plants only, the Contractor shall determine the percent moisture content a minimum of twice daily, prior to production and half way through production. The Contractor shall perform cold feed gradation analysis (AASHTO T 27(M) & T 11) for each component aggregate to ensure values remain within the tolerances stated in Table M.04.02 when compared to the latest JMF for that class. c. Mixture: The dry and wet mix times shall be sufficient to provide proper coating (minimum 95% as determined by AASHTO T 195(M)) of all particles with bitumen and produce a uniform mixture. The Contractor shall make necessary adjustments to ensure bituminous concrete mixtures are free from moisture throughout. The Contractor shall make necessary adjustments to ensure all types of bituminous concrete mixtures contain no more than 0.5% moisture throughout when tested in accordance with AASHTO T 329.

d. RAP: The Contractor shall indicate the percent of RAP, the moisture content (as a minimum, determined twice daily – prior to production and halfway through production), and the net dry weight of RAP added to the mixture on each truck ticket. For each day of

7

G4-SECTION M.04T - BITUMINOUS CONCRETE production, the production shall conform to the job mix formula and RAP percentage and no change shall be made without the prior approval of the Engineer.

e. Documentation system: The mixing plant documentation system shall include equipment for accurately proportioning the components of the mixture by weight and in the proper order, controlling the cycle sequence and timing the mixing operations. Recording equipment shall monitor the batching sequence of each component of the mixture and produce a printed record of these operations on each truck ticket, as specified herein. Tolerance controls shall be automatically or manually adjustable to provide proportions within these tolerances for any batch size. The automatic proportioning system shall be capable of consistently delivering mixtures within these limits for the full range of batch sizes.

An asterisk (*) shall be automatically printed next to any individual batch weight(s) exceeding these tolerances. The entire batching and mixing interlock cut-off circuits shall interrupt and stop the automatic batching operations when an error exceeding the acceptable tolerance occurs in proportioning.

Each Aggregate Component: ±1.0 % total target batch weight Mineral Filler ±0.5 % of the total batch Bituminous Material ±0.1 % of the total batch Zero Return (Aggregate) ±0.5 % of the total batch Zero Return (Bituminous Material) ±0.1 % of the total batch

There must be provisions so that scales are not manually adjusted during the printing process. In addition, the system shall be interlocked to allow printing only when the scale has come to a complete rest. A unique printed character (m) shall automatically be printed on the truck and batch plant printout when the automatic batching sequence is interrupted or switched to auto-manual or full manual during proportioning. For each day's production, each project shall be provided a clear, legible copy of these recordings on each truck ticket.

f. Field Laboratory: The Contractor shall furnish the Engineer an acceptable field laboratory, to test bituminous mixtures during production and the Engineer shall have priority to use it for testing. The HMA plant production field laboratory shall have a minimum of 300 square feet, have a potable water source and drainage in accordance with the CT Department of Public Health Drinking Water Division, be equipped with all necessary testing equipment as well as with a PC, printer, dedicated phone, and separate dedicated data line. This equipment shall be maintained in clean and good working order at all times and be made available for use by the Engineer.

The laboratory shall be equipped with a suitable heating system capable of maintaining a minimum temperature of 65°F. It shall be clean and free of all materials and equipment not associated with the laboratory. Windows shall be installed to provide sufficient light and ventilation. During summer months, the laboratory temperature shall not exceed

8

G4-SECTION M.04T - BITUMINOUS CONCRETE ambient temperature. Light fixtures and outlets shall be installed at convenient locations, and a telephone shall be within audible range of the testing area. The laboratory shall be equipped with an adequate workbench that has a suitable length, width, and sampling tables, and be approved by the Engineer.

The field laboratory testing apparatus, supplies, and safety equipment shall be capable of performing all tests in their entirety that are referenced in AASHTO R 35(M), Standard Practice for Superpave Volumetric Design for Hot-Mix Asphalt (HMA) and AASHTO M 323, Standard Specification for Superpave Volumetric Mix Design. In addition, the quantity of all equipment and supplies necessary to perform the tests must be sufficient to initiate and complete the number of tests identified in Table M.04.03-2 for the quantity of mixture produced at the plant on a daily basis. The Contractor shall ensure that the Laboratory is adequately supplied at all times during the course of the project with all necessary testing materials and equipment.

g. Mixing Plant and Machinery: The mixing plant used in the preparation of the bituminous concrete shall comply with AASHTO M-156(M)/ASTM D 995 for a Batch Plant or a Drum Dryer Mixer Plant, and be approved by the Engineer.

M.04.02—Mix design and Job Mix Formula (JMF)

1. Superpave Design Method – S0.25, S0.375, S0.5, and S1

a. Requirements: The Contractor or its representative shall design and submit Superpave mix designs annually for approval. The design laboratory developing the mixes shall be approved by the Engineer. The mix design shall contain the nominal maximum aggregate size and include a JMF consisting of target values for gradation and bitumen content for each HMA mix type designated for the project, as specified in Tables M.04.02-2 thru Table M.04.02-5 and in accordance with the latest requirements of AASHTO M 323(M) and AASHTO R 35(M).

The contractor shall provide a certified test report with supporting documentation from an accredited AASHTO Materials Reference Laboratory (AMRL) with the use of NETTCP Certified Technicians for aggregate consensus properties for each type & level, as specified in Table M.04.02-3. In addition the Gsa, Gsb, Pwa shall also be provided for each component aggregate. New mixes shall be tested in accordance with AASHTO T 283(M) Standard Method of Test for Resistance of Compacted Hot Mix Asphalt (HMA) to Moisture-Induced Damage. The tensile strength ratio must be indicated on the certified test report. The mix design shall conform to all criteria applicable to the selected traffic level equivalent single-axle loads (ESAL) as specified in this contract. Each HMA mix type must meet the requirements shown in Tables M.04.02-2 thru Table M.04.02-5.

In addition, minimum binder content values apply to all types of HMA mixtures, as stated in Table M.04.02-5. For mixtures containing RAP, the virgin production and the

9

G4-SECTION M.04T - BITUMINOUS CONCRETE anticipated proportion of binder contributed by the RAP cannot be less than the total permitted binder content value for that type nor the JMF minimum binder content.

Superpave Mixture (virgin): For HMA mixtures that contain no recycled material, the limits prescribed in Tables M.04.02-2 thru Table M.04.02-5 apply. The Contractor shall submit a JMF, on a form provided by the Engineer, with the individual fractions of the aggregate expressed as percentages of the total weight of the mix and the source(s) of all materials to the Engineer for approval. The JMF shall indicate the corrected target binder content and applicable binder correction factor (ignition oven or extractor) for each mix type by total weight of mix. The mineral filler (dust) shall be defined as that portion of blended mix that passes the #200 sieve by weight when tested in accordance with AASHTO T 30(M). The dust-to-effective asphalt (D/Pbe) ratio shall be between 0.6 and 1.2 by weight. The dry/wet mix times and hot bin proportions (batch plants only) for each type shall be included in the JMF.

The percentage of aggregate passing each sieve shall be plotted on a 0.45 power gradation chart and shall be submitted for all HMA mixtures. This chart shall delineate the percentage of material passing each test sieve size as defined by the JMF. The percentage of aggregate passing each standard sieve shall fall within the specified control points, but outside the restricted zone limits as shown in Tables M.04.02-2 thru Table M.04.02-5. Mixes with documented performance history which pass through the restricted zone may be permitted for use as long as all other physical and volumetric criteria meets specifications as specified in Tables M.04.02-2 thru Table M.04.02-5 and with prior approval from the Engineer. A change in the JMF requires that a new chart be submitted.

Superpave Mixtures with RAP: In addition to sections M.04.02 – 3 a through c, for HMA that contains RAP, the Contractor shall submit a materials certificate to the Engineer stating that the RAP complies with requirements stated in section M.04.01. Upon approval of the Engineer, a maximum of 15% RAP may be used with no binder grade modification for batch plants and drum plants.

The RAP shall be crushed after milling or other removal method so that 100 % passes the 0.5 inch sieve. Also, under no circumstances shall the top-size aggregate in the RAP exceed the nominal maximum aggregate size allowed by the job mix formula for that mix. The Contractor shall assure that the RAP is free from contaminating substances such as joint seal compound. The aggregate type used, either gravel, trap rock or a blend of the two, shall be maintained and consistent throughout the entire roadway. The final Superpave mixture shall conform to specifications as amended herein. RAP material shall not be used with any other recycling option.

b. Basis of Approval: On an annual basis the Contractor shall submit to the Engineer a request for approval of the HMA mixture, the mix design, and JMF in accordance with one of the methods described herein. Prior to the start of any paving operations, the JMF must be approved by the Engineer, and the Contractor must demonstrate the ability to meet the accepted JMF and production percentage of bitumen for each type of mixture.

10

G4-SECTION M.04T - BITUMINOUS CONCRETE HMA mixture supplied to the project without an approved mix design, JMF and approved facility will be rejected. The JMF shall also indicate the target temperature of completed mixture as it is dumped from the mixer and tested in accordance with M.04.03. Additionally, the fraction of material retained between any two consecutive sieves shall not be less than 4%.

HMA Plant Trials: Upon submittal and approval of the mix design by the Engineer, the Contractor shall test and evaluate plant-produced mixture (PPT) in accordance with these specifications when required.

The JMF shall be accepted if the HMA Plant mixture and materials meet all criteria as specified in Tables M.04.02-2 thru Table M.04.02-5. If the mixture does not meet the requirements, the contractor shall adjust the JMF within the ranges shown in Tables M.04.02-2 thru Table M.04.02-5 until an acceptable mixture is produced. All equipment, tests, and computations shall conform to the latest AASHTO R-35(M) and AASHTO M- 323(M).

Any JMF, once approved, shall only be acceptable for use when it is produced by the designated HMA plant, it utilizes the same component aggregates and binder source, and it continues to meet all criteria as specified herein, and component aggregates are maintained within the tolerances shown in Table M.04.02-2.

The Contractor shall not change any component source of supply including consensus properties after a JMF has been accepted. Before a new source of materials is used, a revised JMF shall be submitted to the Engineer for approval. Any approved JMF applies only to the plant for which it was submitted. Only one mix with one JMF will be approved for production at any one time. Switching between approved JMF mixes with different component percentages or sources of supply is prohibited.

The following information must be included in the mix design submittal: a. Gradation, specific gravities and asphalt content of the RAP, b. Material Certificate stating that all RAP inventory conforms to all material specifications, c. Percentage of RAP to be used.

Superpave mixture with CRCG: In addition to M.04.02 – 3 a through c, for HMA mixtures that contain CRCG, the Contractor shall submit a materials certificate to the Engineer stating that the CRCG complies with requirements stated in M.04.01, as applicable. Additionally, 1% hydrated lime, or other accepted non-stripping agent, shall be added to all mixtures containing CRCG. CRCG material shall not be used with any other recycling option.

c. Mix Status: Each Plant will have each type of HMA mixture evaluated based on previous years production compliance, for the next construction paving season, as determined by the Engineer. Based on the rating a type receives it will determine

11

G4-SECTION M.04T - BITUMINOUS CONCRETE whether the mixture can be produced without the prior completion of a PPT. Ratings will be provided to each HMA producer annually at the beginning of the paving season.

1) Rating Procedure: Ratings for each type are as follows:

“A” – Approved: Rating assigned to a mixture type from a producer with a current rating of 70% or better based on specification compliance based on binder content (Pb), air voids (Va), maximum theoretical gravity (Gmm), and Voids in Mineral Aggregate (VMA).

“PPT” – Pre-Production Trial: Rating assigned to a type of mixture when there is no production history from the previous year, has a change in one or more aggregate components from the JMF on record, a change in RAP percentage, or is a new JMF not previously on record.

HMA mixtures rated with a “PPT” cannot be shipped or used on Department projects. A passing “PPT” test shall be performed with NETTCP certified personnel on that type of mixture by the HMA producer and meet all specifications (Table M.04.02-2 Table M.04.02-5) before production shipment may be resumed. At no time shall mixture rated “PPT” be shipped to Department projects.

Contractors that have mix types rated a “PPT” may use one of the following methods to change the rating to an “A.”

Option A: Schedule a day when a Department inspector can be at the HMA facility to witness a passing “PPT” test or,

Option B: When the Contractor or their representative performs a “PPT” test without being witnessed by an inspector, the Contractor shall submit the test results and a split sample including 2 gyratory molds, 5,000 grams of boxed HMA for binder and gradation determination, and 5,000 grams of cooled loose HMA for Gmm determination for verification testing and approval. Passing verifications will designate the HMA type to be on an “A” status. Failing verifications will require the contractor to submit additional trials.

Option C: When the Contractor or their representative performs a “PPT” test without being witnessed by a Department inspector, the Engineer may verify the mix in the Contractor’s laboratory. Passing verifications will designate the HMA type to be an “A” status. Failing verifications will require the Contractor to submit additional trials.

When Option (A) is used and the “PPT” test meets all specifications, the “PPT” test is considered a passing test and the rating for that mix is changed to “A”. When the “PPT” test is not witnessed, the “PPT” Option (B) procedure must be followed and the mixtures along with the test results delivered to the Materials

12

G4-SECTION M.04T - BITUMINOUS CONCRETE Testing Lab. The test results must meet the “B” tolerances established by the Engineer.

“U” – No Acceptable Mix Design on File:

Rating assigned to a type of mixture that does not have a JMF submitted, or the JMF submitted has not been approved, or is incomplete. A mix design or JMF must be submitted annually thirty (30) days prior in order to obtain an “A,” or “PPT” status for that mix. A “U” will be used only to designate the mix status until the mix design has been approved, and is accompanied with all supporting data as specified. HMA mixtures rated with a “U” cannot be used on Department projects.

13

G4-SECTION M.04T - BITUMINOUS CONCRETE TABLE M.04.02– 2: SUPERPAVE MASTER RANGE FOR MIXTURE DESIGN CRITERIA

Notes: (1) Minimum Pb as specified in Table M.04.02-5. (2) Voids in Mineral Aggregates shall be computed as specified herein. (3) Control point range is also defined as the master range for that mix. (4) Dust is considered to be the percent of materials passing the #200 sieve.

S0.25 S0.375 S0.5 S1 CONTROL RESTRICTED CONTROL RESTRICTED CONTROL RESTRICTED CONTROL RESTRICTED Sieve POINTS (3) ZONE POINTS(3) ZONE POINTS(3) ZONE POINTS(3) ZONE Min Max Max Min Min Max Min Max Min Max Min Max Min Max Min Max inches (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) (%) 2.0 ------1.5 ------100 - - - 1.0 ------90 100 - - 3/4 ------100 - - - - 90 - - 1/2 100 - - - 100 - - - 90 100 ------3/8 97 100 - - 90 100 - - - 90 ------#4 - 90 - - - 90 ------39.5 39.5 #8 32 67 47.2 47.2 32 67 47.2 47.2 28 58 39.1 39.1 19 45 26.8 30.8 #16 - - 31.6 37.6 - - 31.6 37.6 - - 25.6 31.6 - - 18.1 24.1 #30 - - 23.5 27.5 - - 23.5 27.5 - - 19.1 23.1 - - 13.6 17.6 #50 - - 18.7 18.7 - - 18.7 18.7 - - 15.5 15.5 - - 11.4 11.4 #100 ------#200 2.0 10.0 - - 2.0 10.0 - - 2.0 10.0 - - 1.0 7.0 - - Pb (1) ------VMA (2) (%) 16.0 ± 1 16.0 ± 1 15.0 ± 1 13.0 ± 1 VA (%) 4.0 ± 1 4.0 ± 1 4.0 ± 1 4.0 ± 1 Gse JMF value JMF value JMF value JMF value Gmm JMF ± 0.030 JMF ± 0.030 JMF ± 0.030 JMF ± 0.030 Dust/Pbe(4) 0.6 – 1.2 0.6 – 1.2 0.6 – 1.2 0.6 – 1.2 Agg. Temp 280 – 350F 280 – 350F 280 – 350F 280 – 350F

14

G4-SECTION M.04T - BITUMINOUS CONCRETE Mix Temp 265 – 325 F 265 – 325 F 265 – 325 F 265 – 325 F

TABLE M.04.02–3 SUPERPAVE MASTER RANGE FOR CONSENSUS PROPERTIES OF COMBINED AGGREGATE STRUCTURES Notes: (1) If less than 25 % of a given layer is within 4 inches of the anticipated top surface, the layer may be considered to be below 4 inches for mixture design purposes. Coarse Aggregate Fine Aggregate Flat or Elongated Sand Traffic Design ESALs Angularity (1) Angularity (7) Particles Equivalent Level (80 kN) ASTM D 5821 AASHTO T 304 ASTM D 4791 AASHTO T 176

- - - - - (million) > # 4 - - - - - 1* < 0.3 55/- - 40 10 40 2 0.3 to < 3.0 75/- - 40 10 40 3 ≥ 3.0 95/90 45 10 45 Design ESALs are the Criteria presented as minimum values. Criteria presented as minimum Cri t e r ia presented as Criteria presented anticipated project traffic 95/90 denotes that a minimum of percent air voids in loosely maximum Percent by mass as minimum values level expected on the design 95% of the coarse aggregate, by compacted fine aggregate of flat or elongated for fine aggregate lane, projected over a 20 mass, shall have one fractured face passing the #8 sieve. particles of materials passing the #8 year period, regardless of and that a minimum of 90% shall retained on the #4 sieve, sie v e . the actual expected design have two fractured faces. determined at 3:1 ratio. life of the roadway. * NOTE: Level 1 for use by Towns and Municipalities ONLY.

15

G4-SECTION M.04T - BITUMINOUS CONCRETE TABLE M.04.02– 4: SUPERPAVE MASTER RANGE FOR TRAFFIC LEVELS AND DESIGN VOLUMETRIC PROPERTIES. Number of Gyrations by Design Superpave Gyratory Percent Density of Gmm Voids Filled with Asphalt (VFA) Traffic ESALs Compactor from HMA specimen Based on Nominal mix size – inch Level (million) Nini Ndes Nmax Nini Ndes Nmax 0.25 0.375 0.5 1 1* < 0.3 6 50 75 ≤ 91.5 96.0 ≤ 98.0 70 - 80 70 - 80 70 - 80 67 - 80 2 0.3 to < 3.0 7 75 115 ≤ 90.5 96.0 ≤ 98.0 65 - 78 65 - 78 65 - 78 65 - 78 3 ≥ 3.0 8 100 160 ≤ 90.0 96.0 ≤ 98.0 73 – 76 73 - 76 65 - 75 65 - 75 * NOTE: Level 1 for use by Towns and Municipalities ONLY.

16

G4-SECTION M.04T - BITUMINOUS CONCRETE TABLE M.04.02– 5: SUPERPAVE MINIMUM BINDER CONTENT BY MIX TYPE & LEVEL. Mix Type Level Binder Content Minimum (1) S0.25 2* 5.5 S0.25 3 5.4 S0.375 2* 5.5 S0.375 3 5.4 S0.5 2* 4.9 S0.5 3 4.8 S1 2* 4.5 S1 3 4.4 * NOTE: Level 2 shall be the minimum level

M.04.03—Production Quality Control (QC) Testing, Approval and Control of Mixture: The Contractor shall submit a Quality Control plan for HMA production specifically for the plant producing the HMA mixture in accordance with Section 4.06.03-9 for review and approval of the Engineer. The plan must also include a list of sampling & testing methods and frequencies used during production, and the names of all Quality Control plant personnel and their duties. In addition;

i. All plant personnel involved with sampling and testing for Quality Control purposes must have a current certification as an NETTCP HMA Plant Technician or Interim HMA Plant Technician and be in good standing. Technicians found by the Engineer to be non-compliant with NETTCP and Department policies may be suspended by the Engineer from participating in the production of mixtures for Department projects until their actions can be reviewed by NETTCP.

ii. The Contractor shall maintain a list of laboratory equipment used in their quality control processes including but not limited to, balances, scales, manometer/vacuum gauge, thermometers, gyratory compactor, clearly showing calibration and/or inspection dates, in accordance with AASHTO R-18.

In addition, the following also applies:

1. Material Sampling & Testing Methods for Superpave Mix Design: a. Samples of mixtures will be obtained from the hauling vehicles at the plant during each day's production, as indicated in Table M.04.03– 1. The Contractor shall perform necessary moisture susceptibility testing annually or when material component sources change, and for all levels of HMA S0.5 plant produced mixtures, as specified in the latest version of AASHTO T 283(M). The T 283(M) test results shall be submitted by the Contractor for approval. The acceptable tensile strength ratio shall be 80 percent minimum, and show no evidence of stripping. This shall be completed within 30 days of

17

G4-SECTION M.04T - BITUMINOUS CONCRETE beginning of production. Superpave mixtures that require anti-strip additives (either liquid or mineral) shall continue to meet all requirements specified herein for binder and HMA. The Contractor shall submit the name, manufacturer, percent used, and MSDS sheet for the anti-strip additive (if applicable) to the Engineer. In addition;

i. The Contractor shall maintain all testing equipment within a field laboratory in good working order. ii. The Contractor shall not modify or use the equipment within the field laboratory without the consent of the Engineer. Any such action by the Contractor may be cause for the Engineer to re-inspect equipment, check calibrations, which could delay production at that facility until such checks are completed. iii. The Contractor shall take immediate action to replace, repair, and/or recalibrate any piece of equipment that is deemed by the Engineer to be out of calibration, malfunctioning, or not in operation. iv. Production without the use of required testing equipment will be permitted for only 1 hour. Additional production beyond the first hour may be considered by the Engineer. If permitted to continue production, box samples will be taken, tested, and incorporated as stated in Subarticle M.04.03 and Article 4.06.04-1b. No production shall be permitted beyond that day until the subject equipment is repaired or replaced to the satisfaction of the Engineer. v. Compaction of samples shall be accomplished utilizing an accepted Superpave Gyratory Compactor (SGC), supplied by the Contractor. The SGC shall be located at the HMA plant supplying mixture to the project. vi. The Engineer will perform all acceptance and verification testing for HMA production.

b. Additional QC plan Requirements for Plants producing Superpave Mix Design mixture:

i. The Contractor shall perform all listed component aggregates and Superpave mixture Quality Control testing in accordance with the test procedures and schedule listed in Table M.04.03-1, as a minimum, any day that Superpave mixtures are produced.

ii. The Contractor shall propose a QC test frequency for AASHTO T 27(M) on the cold feed material and AASHTO T 308 for RAP binder content.

iii. All process control (PC) test data shall be kept on file for the duration of the project for review by the Engineer.

c. Determination of Off-Test status: i. Off Test Status: Superpave mixes shall be considered “off test” when any Control Point Sieve, VA, VMA, and Gmm values are outside of the limits specified in Table M.04.03-3 and the computed binder content (Pb) established by AASHTO T308(M) or as documented on the vehicle delivery ticket is below the minimum binder content stated in M.04.03-5. Note that further testing of samples or portions of samples not initially tested for this purpose cannot be used to change the status.

18

G4-SECTION M.04T - BITUMINOUS CONCRETE

ii. Any time the HMA mixture is considered Off-test: 1. The Contractor shall notify the Engineer (and project staff) when the plant is "off test" for a type of mixture. When multiple plants and silos are located at one site, mixture supplied to one project is considered as coming from one source for the purpose of applying the “off test” determination.

2. The Contractor must take immediate actions to correct the deficiency, minimize “off test” production to the project, and obtain an additional Process Control (PC) test after any corrective action to verify production is in conformance to the specifications. A PC test will not be used for acceptance and is solely for the use of the Contractor in its quality control process.

d. Test Section: The test section, as specified in Article 4.06, shall be considered acceptable if payment for HMA mixture tested at the plant is no less than 100% and the field density meets the specified requirements.

19

G4-SECTION M.04T - BITUMINOUS CONCRETE

Table M.04.03– 1: Contractor Quality Control Testing Procedures & Minimum Frequency of Test Protocol Reference Description Frequency (min)

1 AASHTO T 27 Sieve Analysis of Fine and Coarse Determined by Aggregate Contractor 2 AASHTO T 329 Moisture content of RAP (before start and 2/day halfway thru production - when used) 3 AASHTO T 255(M) Moisture content of each cold feed 2/day aggregate (before start and halfway thru production - drum plants only) 4 AASHTO T 308(M) Binder content of RAP by Ignition Oven Determined by method (before start of production when Contractor used) 5 AASHTO T 168(M) Sampling of HMA See Note (3) 6 AASHTO T 308(M) Binder content by Ignition Oven method See Note (3) & Note (adjusted for aggregate correction factor) (4) 7 AASHTO T 30(M) Gradation of extracted aggregate for HMA See Note (3) mixture 8 AASHTO T 312(M) (1)Superpave Gyratory molds compacted to See Note (3) Ndes 9 AASHTO T 166(M) (2)Bulk specific gravity of HMA See Note (3) 10 AASHTO R 35(M) (2)Air voids, VMA See Note (3) 11 AASHTO T 209(M) Maximum specific gravity of HMA (average of See Note (3) two tests) 12 AASHTO T 329 Moisture content of Production HMA See Note (3)

Notes: (1) One set equals two six-inch molds. Molds to be compacted to Nmax for PPTs and Ndes for production testing (2) Average value of one set of six-inch molds. (3) Test frequency shall be based on HMA quantity produced per day. Table M.04.03-2 denotes the number of tests required for daily QC by the Contractor. (4) The aggregate correction factor will be determined by the Engineer.

20

G4-SECTION M.04T - BITUMINOUS CONCRETE Table M.04.03 – 2: Contractor Acceptance Testing Required Based on Daily Production per Type/Level/Plant(1) Daily quantity Minimum number of tests required(2) Acceptance produced in tons min. # of tests

0 to 150 No testing required (if mix already accepted) (3) 1 151 to 600 1 test 1 601 to 1,200 2 tests 2 1,201 to 1,800 3 tests 3 1,801 and greater (4) 4 tests 4 Notes: (1) For the purpose of the Contractor complying with the number of tests stated in Table M.04.03-2, tons of the same type/level per plant shall be combined from multiple state projects. (2) All testing shall be selected using stratified – random sampling of total estimated daily tons in accordance with ASTM D 3665, except that the first test shall be randomly taken from the first round of trucks, the first 151 ton sublot, or as otherwise ordered by the Engineer. QC samples shall be saved and stored at the HMA facility for 7 days for Engineer retrieval, after which they may be disposed of. (3) When directed by the Engineer, a minimum of 1 test is required for bridge and critical areas. (4) An additional random test shall be taken by the Contractor for each additional 600 tons.

e. Incentive/disincentive adjustment for Superpave mixtures: The quantity of Superpave mixtures shipped to the project that meets the incentive criteria for Air Voids (VA) will be adjusted in accordance with Article 4.06.04.

The quantity of Superpave mixtures shipped to the project that is “off-test” for binder content (Pb) and/or Air Voids (VA) will be adjusted in accordance with Article 4.06.04.

f. Cessation of Supply for Superpave mixtures with no disincentive adjustment: Production of HMA shall cease for the Project from any plant that consistently fails to produce mixture that meets the JMF and volumetric properties. The quantity of Superpave mixtures shipped to the project that is “off-test” will not be adjusted for deficient mixtures.

i. An HMA production plant will be required to cease supplying mixtures to the project when:

1. HMA mixture is “off test” on three (3) consecutive tests for VMA, regardless of date of production due to inconsistency (i.e., small production requires 1 test per day for multiple days).

2. HMA mixture is “off test” on two (2) consecutive tests for the Control Point sieves in one day’s production.

3. HMA mixture is “off test” on two (2) consecutive tests for the Gmm in one day’s production or on three (3) consecutive tests regardless of date of production.

21

G4-SECTION M.04T - BITUMINOUS CONCRETE 4. The Pb content from the ignition oven/centrifuge minus the mix moisture differs by more than 0.2 from the HMA plant production weigh ticket, the Contractor shall immediately investigate, determine an assignable cause and correct the issue. If issue is not corrected after three (3) consecutive tests, mixture from that HMA plant shall not be permitted until the issue is resolved to the satisfaction of the Engineer.

5. The Pb content is below the requirements of Table M.04.03 – 5 on the ignition oven test results or the HMA plant weigh ticket.

6. Following cessation, the Contractor shall immediately make necessary material or HMA plant corrections and run a Pre-Production Trial (PPT) for that type of mixture. Use of that type of mixture from that plant will be prohibited to the Project until the plant has demonstrated the ability to consistently produce acceptable mixture. When the Contractor has a passing test and has received approval from the Engineer, the use of that mixture to the Project shall resume.

3. JMF Changes for Superpave mixtures production: It is understood that a JMF change is effective from the time it was submitted forward and is not retroactive to the previous test or tests. JMF changes are permitted to allow for trends in aggregate and mix properties but every effort shall be employed by the Contractor to minimize this to ensure a uniform and dense pavement.

a. JMF changes to the Gmm or mix Absorption Correction Factor (Acf) are only permitted prior to or after a production shift for all HMA types of mixtures and only when they: i. Are requested in writing and pre-approved by the Engineer; ii. Are based on a minimum of a two test trend; iii. Are documented with a promptly submitted revised JMF on form provided by the Engineer.

22

G4-SECTION M.04T - BITUMINOUS CONCRETE TABLE M.04.03– 3: SUPERPAVE MASTER RANGE FOR HMA MIXTURE PRODUCTION

Notes: (1) 300oF minimum after October 15. (2) Minimum Pb as specified in Table M.04.03-5 (3) Control point range is also defined as the master range for that mix. (4) JMF tolerances shall be defined as the limits for production compliance. VA & Pb payment is subject to adjustments, as defined in sub-article 4.06.04 - 2. S0.25 S0.375 S0.5 S1 Tolerances CONTROL CONTROL CONTROL CONTROL JMF Sieve POINTS (4) POINTS (4) POINTS (4) POINTS (4) Limits (4) Min Max Min Max Min Max Min Max inches ±Tol (%) (%) (%) (%) (%) (%) (%) (%) 2.0 ------1.5 ------100 - 1.0 ------90 100 3/4 - - - - 100 - - 90 1/2 100 - 100 - 90 100 - - 3/8 97 100 90 100 - 90 - - #4 - 90 - 90 - - - - #8 32 67 32 67 28 58 19 45 #16 ------#200 2.0 10.0 2.0 10.0 2.0 10.0 1.0 7.0 Pb(2) ------note (2) VMA (%) 16.0 16.0 15.0 13.0 1.0 VA (%) 4.0 4.0 4.0 4.0 1.0 Gmm JMF value JMF value JMF value JMF value 0.030 Agg. Temp 280 – 350F 280 – 350F 280 – 350F 280 – 350F Mix Temp 265 – 325 F (1) 265 – 325 F (1) 265 – 325 F (1) 265 – 325 F (1)

23

G4-SECTION M.04T - BITUMINOUS CONCRETE TABLE M.04.03– 4: SUPERPAVE MASTER RANGE FOR TRAFFIC LEVELS AND DESIGN VOLUMETRIC PROPERTIES. Traffic Design ESALs Number of Gyrations by Superpave Gyratory Compactor Level (million) Nini Ndes 1* < 0.3 6 50 2 0.3 to < 3.0 7 75 3 ≥3.0 8 100 * NOTE: Level 1 for use by Towns and Municipalities ONLY.

TABLE M.04.03– 5: SUPERPAVE MINIMUM BINDER CONTENT BY MIX TYPE & LEVEL.

Mix Type Level Binder Content Minimum (1)

S0.25 1* 5.6 S0.25 2 5.5 S0.25 3 5.4 S0.375 1* 5.6 S0.375 2 5.5 S0.375 3 5.4 S0.5 1* 5.0 S0.5 2 4.9 S0.5 3 4.8 S1 1* 4.6 S1 2 4.5 S1 3 4.4 * NOTE: Level 1 for use by Towns and Municipalities ONLY.

24

G4-SECTION M.04T - BITUMINOUS CONCRETE Table M.04.03-6: Modifications to Standard AASHTO and ASTM Test Specifications and Procedures. AASHTO Standard Specification Reference Modification AASHTO 1. Mass change for PG 64-22 shall be a maximum loss of 0.5% when tested in M 320 accordance with AASHTO T 240. 2. The two bottles used for the mass change determination may be re-heated and used for further testing.

AASHTO Standard Methods of Test Reference Modification AASHTO Section 7.7.1 Samples are not washed T 27 AASHTO Section 6.2 thru 6.5 Samples are not routinely washed T 30 Section 8.7.3 Accuracy: Batch Plants AASHTO The automation proportioning system shall be capable of consistently delivering M-156 mixtures within the full range of batch sizes within the following tolerances: /ASTM D Total Batch Weight Of 995 Paving Mix. % Batch aggregate component ± 1.0%

Note: AASHTO T 40 is modified as follows: Section 9.1.1 Sampling valve is located on bottom third of storage tank. AASHTO Method A T 164 APPARATUS: Section 5 ConnDOT in addition to AASHTO apparatus includes infrared lamp and substitutes graduated cylinder with a 1000 ml flask.

Section 6. Reagent. Must be Conn D.O.T. approved ******* Article 8.2.1 all classes of HMA except Class 4 are scooped from the sample container.

Section 9.1 and 9.2 Moisture content is periodically determined on production samples as plant conditions require.

Section 11.1 See Section 9.0 AASHTO T 164

Section 11.3 and 11.5 Filter paper is dried and weighed in field using heat lamp or oven when an ash test is performed.

Section 11.6.2 Extract is collected if an ash test is to be performed Section 11.6.2 Performed on selected samples only Section 11.6.2 A three test running average is used to correct for total binder in HMA.

25

G4-SECTION M.04T - BITUMINOUS CONCRETE

AASHTO Samples are taken at one point in the pile. All types of bituminous concrete except T 168 Class 4 are scooped from the sample container instead of remixing and quartering. (Method verified by laboratory study). Samples from a hauling vehicle are taken from only one point instead of four as specified. Selection of Samples: Sampling is equally important as the testing, and the sampler shall use every precaution to obtain samples that are truly representative of the bituminous mixture. Box Samples: In order to enhance the rate of processing samples taken in the field by construction or maintenance personnel the samples will be tested in the order received and data processed to be determine conformance to material specifications and to prioritize inspections by laboratory personnel. AASHTO Recovery of Asphalt from Solution by Abson Method T 170 Delete the referenced section and replace with the language shown: 5.0 Apparatus Centrifuge batch unit capable of exerting a minimum centrifugal force of 770 times gravity or a continuous unit capable of exerting a minimum force of 300 times gravity.

5.1. Centrifuge tubes- a 250ml wide mouth bottles 5.2. Extraction Flasks- a 500ml three angle necks and joints flask with 24/40 side necks.

5.3.2. Glass Tubing- Heat resistant glass tubing, having 10mm inside diameter and a gooseneck shaped delivery tube, for connecting the flask to the condenser.

5.3.3. Inlet Aeration Tube- 180mm in length having a 6mm outside diameter with a 10-mm bulb carrying six staggered holes approximately 1.5 mm in diameter.

5.3.4. Electric Heating Mantle- Variable transformer to fit a 500 ml flask. 5.3.5 Water-jacketed Condenser, Alliham type, with 200 mm Minimum jacket length.

5.3.6. Thermometer- an ASTM low distillation thermometer having a range of –2 to 300_C (30 to 580_F), respectively, and conforming to the requirements in ASTM specification E 1

5.3.7. Gas Flow Meter- A type capable of indicating a gas flow of up to 1000 ml per minute.

5.3.8. Corks. NO. 20

5.3.9. Flexible Elastomeric Tubing-

5.3.10. Separatory Funnel 500 ml capacity or larger

26

G4-SECTION M.04T - BITUMINOUS CONCRETE

6.0. Reagents and Materials 6.1. Carbon Dioxide Gas- A pressurized tank, with pressure-reducing valve. The solvent for extracting the asphalt from the mixtures should be reagent grade trichloroethylene or methylene chloride. Other solvents may affect the bitumen to change its properties significantly from that as it exists in the mixture.

8. Sample 8.1. The sample shall consist of the solution from previous extraction of a sample of sufficient mass to result in approximately 105 to 110 g of recovered bitumen.

9. Procedure 9.1. The entire procedure, form the start of the extraction to the final recovery, must be completed within 8 hours.

9.2 Centrifuge the solution from the previous extraction for a minimum of 30 minutes at 770 times gravity (approx. 2700rpm) in 250 wide mouth bottles. Assemble the apparatus as shown in figure 1 with the separatory funnel in the thermometer hole in the cork. Lower the aeration tube so that the bulb is in contact with the bottom of the flask. Fill the separatory funnel with the centrifuged solution and open the stopcock to fill the flask approximately one-half full of solvent mixture. Apply low heat to the flask and start distillation. Introduce carbon dioxide gas at a low rate (approx. 100mL/minute) to provide agitation and prevent foaming. Adjust the funnel stopcock to introduce fresh solvent at a rate that will keep the flask approximately one half full during distillation, adding additional solvent mixture to the funnel into all solvent has been introduced into the distillation flask. When the temperature reaches 157 to 160_C (315 to 320_F), increase the carbon dioxide gas flow to approximately 900mL/minute. Maintain this gas flow rate for 20 minutes while also maintaining the temperature of the residue in the flask at 160 to 166_C (320 to 330_F).

AASHTO Section 3.3 only one truck load of mixture is sampled. Samples are taken from T 195 opposite sides of the load.

AASHTO Section 6.4 Bowl is suspended 2 minutes prior to reading rather than 10 minutes. T 209 This makes no significant difference in results. Section 7.2 The average of two bowls is used proportionally in order to satisfy minimum mass requirements. 8.3 Omit Pycnometer method. AASHTO Section 3.3.1 A molding temperature of 140 to 146 C is used T 245 Section 3.5.1 Seventy-five (75) blows per side are used on Classes 1 and 12, per ConnDOT design requirements

Section 3.1 for production testing: one specimen is molded for each extraction test

27

G4-SECTION M.04T - BITUMINOUS CONCRETE

(generally five molds per day) for production over 275 metric tons/day. Other mixtures: two specimens per extraction test.

AASHTO This protocol shall be performed at the HMA plant in accordance with section 7 on T 283 HMA S0.5 (all design levels) by the Contractor or their representative at a time designated by the DRM. TSR testing is required on all classes and design levels during the design phase and on all HMA S0.5 design levels during the production phase. AASHTO In addition to the standard testing procedure, the Department has adopted a T 308 procedure that addresses a correction factor that is calculated using the composite aggregate percentages (Composite Aggregate Correction Factor Method (CACF)).

The aggregate is burned in compliance with the standard ASSHTO procedure Method A exclusively. All modifications are listed for this method only. 5.5. Omit. Replace with: The individual aggregate samples are to be dried in an oven at a maximum temperature of 148 ± 5ºC (300 ± 9º F) to a constant weight. RAP samples are to be oven dried at a maximum temperature of 110 ± 5ºC (230 ± 9º F) to a constant weight. RAP samples will be burned for total binder content only and not to arrive at a correction factor for a mixture. 6.2. Omit Note 2 6.3. Omit. 6.6. Omit. Replace with: Perform a gradation analysis on the burned blank and compare it to the gradation performed prior to burning. 6.7. Omit. 6.8. Omit. The correction factors for each size aggregate are provided by the Engineer. The Composite Aggregate Correction Factor (CACF) for any mixture may be calculated by summing the result of the correction factor for each individual aggregate multiplied by the percentage of that aggregate in the overall mixture. (Note: All correction factors must be re-calculated every time the percentage of any aggregate changes within the mixture.)

AASHTO T 331 5.1 Cores are dried to a constant mass prior to testing using a core-dry machine.

AASHTO Standard Recommended Practices Reference Modification AASHTO Volumetric Calculations of VMA and Correction Factor R 35 VMAa - Voids in Mineral Aggregate from (Va + Vbe) the mix: A. VMA calculated from the mix shall be determined in accordance with Formula 5.16.1 (i). It can be correlated that the VMA calculated from AASHTO R-35(M) is equivalent to VMAa when the Pba is known and substituted for Acf, as shown in Formula 5.16.1(i). Test results from VMAa shall therefore be required to meet all contract specifications. Values of

28

G4-SECTION M.04T - BITUMINOUS CONCRETE

VMAa that are out of specifications during production may be cause for the contractor to determine assignable cause, take corrective action, and modify the Job Mix Formula (JMF), as needed. Continued VMAa data that is out of specifications may be cause for the Engineer to order cessation of supply.

i. Formula 5.16.1A. Determining the VMA of HMA by the mix or air voids & effective binder method:  −× APbGmb )((  += cftd 1. VVMA aa    Gb 

Where: VMAa = VMA calculated from plant production mix( Va + Vbe) Gmbd = Bulk specific gravity as determined by AASHTO T 166(M) Pbt = Binder Total content (corrected) by AASHTO T 308(M) Acf = Absorption correction factor provided by Contractor (refer to b. i thru iii) Gse = Effective Specific gravity determined by AASHTO M 323

Formula 5.16.1B. Determining the HMA mix binder correction factor for each class by use of Percent absorption of water by AASHTO T 84/85, AASHTO T 315 and Df method. This value shall be performed by the Contractor during the mix design only and submitted as a JMF value. Three methods for determining the Acf are shown, although method (i) will be the desired method to be used. All three methods are equivalent when the Gsa, Gsb and Pwa are recent and valid for the mix. Since method (iii) is an estimate based on trap rock based mixtures, some allowance and calibration may be needed for mixes that are composed with granite, gravel, or other aggregate materials but the change is estimated to be minimal (+ 0.1 or less). = × i. cf PwaDfA = ii. cf FromPbaA annual JMF submittal)____( = iii. cf xxA 6...1 Where: Df = as determined by Formula 5.16.1C. Pwa = as determined by AASHTO T 84/85 Pba = as determined by AASHTO M 323 (from annual JMF submittal)

MIX TRAP GRAVEL & GRANITE & TORRINGTON ROCK BROWN TRAP GRANITE S0.25 0.5 1.2 0.6 S0.375 0.5 1.2 0.6 S0.50 0.4 1.0 0.5 S1 0.4 1.0 0.5

Df (Density Factor): The Contractor shall calculate the HMA mix design Df (derived from formula X1.2 APPENDIX X1 of AASHTO R 35(M)) for each class

29

G4-SECTION M.04T - BITUMINOUS CONCRETE

of material, in accordance with Formula 5.16.1C. 2) Formula 5.16.1C. Determining the Density Factor (Df) of mix design HMA:  − GsbGse  i. D =   f  − GsbGsa  Where: Df = Density Factor or multiplier determined by AASHTO R-35(M) Gse = Effective Specific gravity determined by AASHTO M-323 at plant Gsa = Apparent Specific gravity determined by AASHTO T 84/85 of mix design Gsb = Bulk specific gravity determined by AASHTO T 84/85 of mix design

AASHTO Quality Control Plans must be formatted in accordance with AASHTO R 26, R 26 certifying suppliers of performance-graded asphalt binders, Section 9.0, Suppliers Quality Control Plan, and “NEAUPG Model PGAB QC Plan.”

1. The Department requires that all laboratory technician(s) responsible for testing PG-binders be certified or Interim Qualified by the New England Transportation Technician Certification Program (NETTCP) as a PG Asphalt Binder Lab Technician.

2. Sampling of asphalt binders should be done under the supervision of qualified technician. NECTP “Manual of Practice,” Chapter 2 Page 2-4 (Key Issues 1-8).

3. A copy of the Manual of Practice for testing asphalt binders in accordance with the Superpave PG Grading system shall be in the testing laboratory.

4. All laboratories testing binders for the Department are required to be accredited by the AASHTO Materials Reference Laboratory (AMRL).

5. Sources interested in being approved to supply PG-binders to the Department by use of an “in-line blending system,” must record properties of blended material, and additives used.

6. Each source of supply of PG-binder must indicate that the binders contain no additives used to modify or enhance their performance properties. Binders that are manufactured using additives, modifiers, extenders etc., shall disclose the type of additive, percentage and any handling specifications/limitations required.

Suppliers shall provide M-320 Table 2 testing at a minimum of once per month on one sample of material. Each supplier shall rotate the PG grade each month (including PMA), so that data can be collected for all the grades produced. Comment [r1]: Ownership of this special provision lies with Edgardo Block at 860-594-2495. No revisions are permitted without prior consent.

30

G5-SECTION 4.06T BITUMINOUS CONCRETE

4.06.01—Description: Where reference is made to bituminous concrete, it shall also refer to hot-mix asphalt (HMA) mixtures using the Marshall or Superpave mix-design method.

Work under this section shall consist of the production, delivery and placement of a non- segregated, smooth and dense bituminous concrete mixture brought to proper grade and cross section. This section shall also include the method and construction of longitudinal joints. The Contractor shall furnish Quality Control Plans for both plant production and placement of HMA mixtures.

The terms listed below as used in this specification are defined as:

Course: A lift or multiple lifts comprised of the same HMA mixture placed as part of the pavement structure.

Dispute Resolution: A procedure used to resolve conflicts resulting from discrepancies between the Engineer and the Contractor’s density results that may affect payment.

Hot Mix Asphalt (HMA): A bituminous concrete mixture.

Disintegration: Wearing away or fragmentation of the pavement. Disintegration will be evident in the following forms: Polishing, weathering-oxidizing, scaling, spalling, raveling, or loss of material.

Lift: A single HMA mixture placed at a defined thickness.

Marshall: A HMA mixture design designated as “Bituminous Concrete Class ( ).”

Superpave: A HMA mixture design designated as “HMA S*.” Where “S” indicates Superpave and * indicates the sieve related to the nominal maximum aggregate size of the mix. For example Superpave 0.50 inch is now designated as HMA S0.5.

Segregation: A non-uniform distribution of a HMA mixture in terms of volumetrics, gradation or temperature.

Quality Assurance (QA): All those planned and systematic actions necessary to provide confidence that a product or facility will perform as designed.

Quality Control (QC): The sum total of activities performed by the vendor (producer, manufacturer, and contractor) to ensure that a product meets contract specification requirements.

4.06.02—Materials: All materials shall conform to the requirements of Section M.04.

1. Materials Supply: The HMA mixture must be from one source of supply and originate from one HMA Plant unless authorized by the Engineer.

1 G5-SECTION 4.06T BITUMINOUS CONCRETE

2. Recycle Option: The Contractor has the option of recycling reclaimed asphalt pavement (RAP) or Crushed Recycled Container Glass (CRCG) in HMA mixtures in accordance with Section M.04. CRCG shall not be used in the final lift of the surface course.

4.06.03—Construction Methods:

1. Material Documentation: All vendors producing bituminous concrete must have their truck- weighing scales, storage scales, and mixing plant automated to provide a detailed ticket.

Delivery tickets must include the following information: a. State of Connecticut printed on ticket. b. Name of producer, identification of plant, and specific storage bin (silo) if used. c. Date and time of day. d. Mixture Designation (If RAP is used, the plant printouts shall include RAP dry weight, percentage and daily moisture content.) Class 3 mixtures for machine-placed curbing must state " mix only". e. Net weight of mixture loaded into truck (When RAP is used, RAP moisture shall be excluded from mixture net weight). f. Gross weight (Either equal to the net weight plus the tare weight or the loaded scale weight). g. Tare weight of truck – Daily scale weight. h. Project number, purchase order number, name of contractor (if contractor other than producer). i. Truck number for specific identification of truck. j. Individual aggregate, RAP, and virgin asphalt high/target/low weights shall be printed on batch plant tickets (For drum plants and silo loadings, the plant printouts shall be printed out at 5 minute intervals maintained by the vendor for a period of three years after the completion of the project).

The net weight of mixture loaded into the truck must be equal to the cumulative measured weight of its components.

The Contractor must notify the Engineer immediately if, during the production day, there is a malfunction of the weighing or recording system in the automated plant or truck-weighing scales. Manually written tickets containing all required information will be allowed for one hour, but for no longer, provided that each load is weighed on State-approved scales. At the Engineer’s sole discretion, trucks may be approved to leave the plant if a State inspector is present to monitor weighing. If such a malfunction is not fixed within forty-eight hours, mixture will not be approved to leave the plant until the system is fixed to the Engineer's satisfaction. No damages will be considered should the State be unable to provide an inspector at the plant.

The State reserves the right to have an inspector present to monitor batching and /or weighing operations.

2. Transportation of Mixture: Trucks with loads of bituminous concrete being delivered to State projects must not exceed the statutory or permitted load limits referred to as gross vehicle

2 G5-SECTION 4.06T BITUMINOUS CONCRETE

weight (GVW). The Contractor shall furnish a list of all vehicles and allowable weights transporting mixture.

The Town of Westport reserves the right to check the gross and tare weight of any delivery truck. A variation of 0.4 percent or less in the gross or tare weight shown on the delivery ticket and the certified scale weight shall be considered evidence that the weight shown on the delivery ticket is correct. If the gross or tare weight varies from that shown on the delivery ticket by more than 0.4 percent, the Engineer will recalculate the net weight. The Contractor shall take action to correct discrepancy to the satisfaction of the Engineer.

If a truck delivers mixture to the project and the ticket indicates that the truck is overweight, the load will not be rejected but a “Measured Weight Adjustment” will be taken in accordance with Sub-article 4.06.04.

The mixture shall be transported from the mixing plant in trucks that have previously been cleaned of all foreign material and that have no gaps through which mixture might inadvertently escape. The use of kerosene, gasoline, fuel oil, or similar products for the coating of the inside of truck bodies is prohibited.

Truck body coating and cleaning agents must not have a deleterious effect on the transported mixture. When acceptable coating or agents are applied, truck bodies shall be raised immediately prior to loading to remove any excess agent in an environmentally acceptable manner. The Contractor shall take care in loading trucks uniformly so that segregation is minimized.

Loaded trucks shall be tightly covered with waterproof covers acceptable to the Engineer. Mesh covers are prohibited. The front and rear of the cover must be fastened to minimize air infiltration. The Contractor shall assure that all trucks are in conformance with this specification. Trucks found not to be in conformance shall not be allowed to be loaded until re-inspected to the satisfaction of the Engineer.

3. Paving Equipment: The Contractor shall have the necessary paving and compaction equipment at the project site to perform the work. All equipment shall be in good working order and any equipment that is worn, defective or inadequate for performance of the work shall be repaired or replaced by the Contractor to the satisfaction of the Engineer. The use of solvents or fuel oil as a release agent on any paving equipment (i.e., rollers, pavers, transfer devices, etc.) is strictly prohibited.

Refueling of equipment is prohibited in any location on the paving project where fuel might come in contact with bituminous concrete mixtures already placed or to be placed. Solvents for use in cleaning mechanical equipment or hand tools shall be stored clear of areas paved or to be paved. Before any such equipment and tools are cleaned, they shall be moved off the paved or to be paved area; and they shall not be returned for use until after they have been allowed to dry.

Pavers: Each paver shall have a receiving hopper with sufficient capacity to provide for a uniform spreading operation and a distribution system that places the mix uniformly, without

3 G5-SECTION 4.06T BITUMINOUS CONCRETE

segregation. The paver shall be equipped with and use a vibratory screed system with heaters or burners. The screed system shall be capable of producing a finished surface of the required evenness and texture without tearing, shoving, or gouging the mixture. Pavers with extendible screed units as part of the system shall have auger extensions and tunnel extenders as necessary. Automatic screed controls for grade and slope shall be used at all times unless otherwise authorized by the Engineer. The controls shall automatically adjust the screed to compensate for irregularities in the preceding course or existing base. The controls shall maintain the proper transverse slope and be readily adjustable, and shall operate from a fixed or moving reference such as a grade wire or floating beam.

Rollers: All rollers shall be self-propelled and designed for compaction of bituminous concrete. Rollers types shall include steel-wheeled, pneumatic or a combination there of and may be capable of operating in a static or dynamic mode. Rollers that operate in a dynamic mode shall have drums that use a vibratory or oscillatory system or combination of. The vibratory system achieves compaction through vertical amplitude forces. Rollers with this system shall be equipped with indicators that provide the operator with amplitude, frequency and speed settings/readouts to measure the impacts per foot during the compaction process. The oscillatory system achieves compaction through horizontal shear forces. Rollers with this system shall be equipped with frequency indicators. Rollers can operate in the dynamic mode using the oscillatory system on concrete structures such as bridges and catch basins if at the lowest frequency setting.

Pneumatic tire rollers shall be self-propelled and equipped with wide-tread compaction tires capable of exerting an average contact pressure from 60 to 90 pounds per square inch uniformly over the surface, adjusting ballast and tire inflation pressure as required. The Contractor shall furnish evidence regarding tire size; pressure and loading to confirm that the proper contact pressure is being developed and that the loading and contact pressure are uniform for all wheels.

Lighting: There are no lighting requirements for this project

Material Transfer Vehicle (MTV): This project does not require the use of an MTV.

4. Seasonal Requirements: Paving shall be divided into two seasons, In-Season and Extended Season; In-Season shall be from May 1 – September 30, and Extended Season shall be from October 1- April 30. In no case shall the final lift of HMA be placed during the extended season unless otherwise authorized or directed by the Engineer. No HMA mixes shall be placed when the air or base temperature is below 32°F. HMA for temporary pavement will be subject to the seasonal requirements unless otherwise authorized or directed by the Engineer.

Additional Requirements for Extended Season:

- The minimum mixture temperature for all HMA mixtures in the delivery truck prior to discharge into the paver or transfer vehicle hopper shall be 290°F. The temperature will be taken from the initial discharge of mixture from the truck. If found to be below the minimum requirement, the truck will not be allowed to unload remaining mixture.

4 G5-SECTION 4.06T BITUMINOUS CONCRETE

- The Contractor shall use a minimum of 3 rollers with operators for paving lengths greater than 1000 feet. Two rollers must be capable of operating in the dynamic mode.

- The Contractor’s Quality Control Plan shall include a section on Extended Season Paving and address paver speed, roller patterns and balancing mixture delivery and placement operations to meet specification requirements.

- 5. Superpave Test Section: The Engineer may require the Contractor to place a test section whenever the requirements of this specification or M.04 are not met.

The Contractor shall submit the quantity of mixture to be placed and the location of the test section for review and acceptance by the Engineer. The equipment used in the construction of a passing test section shall be used throughout production.

If a test section fails to meet specifications, the Contractor shall stop production, make necessary adjustments to the job mix formula, plant operations, or procedures for placement and compaction. The Contractor shall construct test sections, as allowed by the Engineer, until all the required specifications are met. All test sections shall also be subject to removal as set forth in Section 1.06.04.

6. Transitions for Roadway Surface: Transitions shall be formed at any point on the roadway where the pavement surface deviates, vertically, from the uniform longitudinal profile as specified on the plans. Whether formed by milling or by bituminous concrete mixture, all transition lengths shall conform to the criteria below unless otherwise specified.

Permanent Transitions: A permanent transition is defined as any transition that remains as a permanent part of the work. All permanent transitions, leading and trailing ends shall meet the following length requirements:

a) Roadways greater than 35 MPH = 30 feet per inch of vertical change (thickness) b) Roadways 35 MPH or less = 15 feet per inch of vertical change (thickness). c) Bridge and underpass transition length will be 75 feet either (1) Before and after the bridge , or (2) Before or after the parapet face of the overpass.

In areas where it is impractical to use the above described permanent transition lengths the use of a shorter permanent transition length may be permitted when approved by the Engineer.

Temporary Transitions: A temporary transition is defined as a transition that does not remain a permanent part of the work. All temporary transitions shall meet the following length requirements:

a) Roadways greater than 35 MPH (1) Leading Transitions = 15 feet per inch of vertical change (thickness) (2) Trailing Transitions = 6 feet per inch of vertical change (thickness)

5 G5-SECTION 4.06T BITUMINOUS CONCRETE

b) Roadways 35 MPH or less (1) Leading and Trailing = 4 feet per inch of vertical change (thickness)

Note: Any temporary transition to be in-place over the winter shutdown period, holidays, or during extended periods of inactivity (more than 7 calendar days) shall conform to the “Permanent Transition” requirements shown above.

7. Spreading and Finishing of Mixture: Prior to the placement of the bituminous concrete, the underlying base course shall be brought to the plan grade and cross section within the allowable tolerance. Immediately before placing the mixture, the area to be surfaced shall be cleaned by sweeping or by other means acceptable to the Engineer. The HMA mixture shall not be placed whenever the surface is wet or frozen. The temperature of the mix at time of placement must be between 265°F and 325°F. The Engineer will verify the mix temperature by means of a probe or infrared type of thermometer. Rejection of mixture based on temperature will only be allowed if verified by means of a probe type thermometer.

Placement: The HMA mixture shall be placed and compacted to provide a smooth, dense surface with a uniform texture and no segregation at the designed thickness and dimensions indicated in the plans and specifications. The maximum paver speed during placement shall not exceed 40 ft/min unless authorized by the Engineer.

When unforeseen weather conditions prevent further placement of the mix, the Engineer is not obligated to accept or place the bituminous concrete mixture that is in transit from the plant.

In advance of paving, traffic control requirements shall be set up daily, maintained throughout placement, and shall not be removed until all associated work including density testing is completed.

The Contractor shall inspect the newly placed pavement for defects in the mixture or placement before rolling is started. Any deviation from standard crown or section shall be immediately remedied by placing additional mixture or removing surplus mixture. Such defects shall be corrected to the satisfaction of the Engineer.

Where it is impractical due to physical limitations to operate the paving equipment, the Engineer may permit the use of other methods or equipment. Where hand spreading is permitted, the mixture shall be placed by means of suitable shovels and other tools, and in a uniformly loose layer at a thickness that will result in a completed pavement meeting the designed grade and elevation.

Placement Tolerances: Each lift of HMA placed at a uniform design thickness shall meet the following requirements for thickness and area. Any pavement exceeding these limits shall be subject to an HMA adjustment or removal. Lift tolerances will not relieve the Contractor from meeting the final designed grade. Lifts of designed non-uniform thickness, i.e. wedge or shim course, shall not be subject to thickness and area adjustments.

6 G5-SECTION 4.06T BITUMINOUS CONCRETE

a) Thickness- Where the total thickness of the lift of mixture exceeds that shown on the plans beyond the tolerances shown in Table 2, the longitudinal limits of such variation including locations and intervals of the measurements will be documented by the Engineer for use in calculating a HMA adjustment in 4.06.04-2.

TABLE 2 - Thickness Tolerances Mixture Designation Lift Tolerance 3 Class 4 and HMA S1 +/- /8 inch Class 1, 2 and 12 and HMA S0.25, S0.375, S0.5 +/- ¼ inch

Where the thickness of the lift of mixture is less than that shown on the plans beyond the tolerances shown in Table 2, the Contractor, with the approval of the Engineer, shall take corrective action in accordance with this specification.

b) Area- Where the width of the lift exceeds that shown on the plans by more than the designed thickness of each lift, the longitudinal limits of such variation including locations and intervals of the measurements will be documented by the Engineer for use in calculating a HMA adjustment in 4.06.04-2.

c) Delivered Weight of Mixture - When the delivery ticket shows that the truck exceeds the allowable gross weight for the vehicle type the quantity of tons representing the over weight will be documented by the Engineer for use in calculating a HMA adjustment in 4.06.04-2.

Transverse Joints: All transverse joints shall be formed by saw-cutting a sufficient distance back from the previous run, existing bituminous concrete pavement or bituminous concrete driveways to expose the full thickness of the lift. A brush of tack coat shall be used on any cold joint immediately prior to additional bituminous concrete mixture being placed.

Tack Coat Application: A thin uniform coating of tack coat shall be applied to the pavement immediately before overlaying and be allowed sufficient time to break (set). All surfaces in contact with the HMA that have been in place longer than 3 calendar days shall have an application of tack coat. The tack coat shall be applied by a non-gravity pressurized spray system that results in uniform overlapping coverage at a target application rate of 0.07 + 0.02 gallons per square yard for a non-milled surface and a target application rate of 0.12 + 0.02 gallons per square yard for a milled surface. For areas where both milled and un-milled surfaces occur, the tack coat shall be a target application rate of 0.07 + 0.02 gallons per square yard. The Engineer must approve the equipment and the method of measurement prior to use. The material for tack coat shall not be heated in excess of 160°F and shall not be further diluted.

Compaction: The Contractor shall compact the mixture to meet the density requirements as stated in Section 4.06.03-11 and eliminate all roller marks without displacement, shoving, cracking, or aggregate breakage.

7 G5-SECTION 4.06T BITUMINOUS CONCRETE

The Contractor shall only operate rollers in the dynamic mode using the oscillatory system at the lowest frequency setting on concrete structures such as bridges and catch basins. The use of the vibratory system on concrete structures is prohibited.

Rollers operating in the dynamic mode shall be shut off when reversing directions.

If the Engineer determines that the use of compaction equipment in the dynamic vibratory mode may damage highway components, utilities, or adjacent property, the Contractor shall provide alternate compaction equipment. The Engineer may allow the Contractor to operate rollers in the dynamic mode using the oscillatory system at the lowest frequency setting.

These allowances will not relieve the Contractor from meeting pavement compaction requirements.

Surface Requirements: The pavement surface of any lift shall meet the following requirements for smoothness and uniformity. Any irregularity of the surface exceeding these requirements shall be corrected by the Contractor.

a) Smoothness- Each lift of the surface course shall not vary more than ¼ inch from a Contractor-supplied 10 foot straightedge. For all other lifts of HMA, the tolerance shall 3 be /8 inch. Such tolerance will apply to all paved areas.

b) Uniformity- The paved surface shall not exhibit segregation, rutting, cracking, disintegration, flushing or vary in composition as determined by the Engineer.

8. HMA Longitudinal Joint Construction Methods: the Contractor shall use Method II- Butt Joint, for all work on this project. During placement of multiple lifts of HMA, the longitudinal joint shall be constructed in such a manner that it is located at least 6 inches from the joint in the lift immediately below. The joint in the final lift shall be at the centerline or at lane lines.

Method I - Notched Wedge Joint:

Notched Wedge Joints shall not be used on this project

Method II - Butt Joint:

Lift Thickness Joint Less than 1 ½” Greater than 3” Hot side Cold Side

8 G5-SECTION 4.06T BITUMINOUS CONCRETE

When adjoining HMA passes are placed, the Contractor shall utilize equipment that creates a near vertical edge (refer to figure). The completing pass (hot side) shall have sufficient mixture so that the compacted thickness is not less than the previous pass (cold side). The end gate on the paver should be set so there is an overlap onto the cold side of the joint.

The Contractor shall not allow any butt joint to be incomplete at the end of a work shift unless otherwise allowed by the Engineer. When using this method, the Contractor is not allowed to leave a vertical edge exposed at the end of a work shift and must complete paving of the roadway full width “curb to curb.”

Method III- Butt Joint with Hot Poured Rubberized Asphalt Treatment: When required by the contract or allowed by the Engineer, Method III may be used.

Hot poured rubberized asphalt treatment

Hot side Cold Side

All of the requirements of Method II must be met with Method III. In addition, the longitudinal vertical edge must be treated with a hot poured rubberized asphalt material prior to placing a completing pass. The rubberized asphalt material shall be applied in accordance with the manufacturer’s recommendation so as to provide a uniform coverage and avoid excess onto the newly placed pavement.

9. Contractor Quality Control (QC) Requirements for HMA Placement: A Quality Control Plan (QCP) shall be required for any project that has a total of 2500 tons or more of HMA.

Quality Control is defined as all those planned and specified actions or operations necessary to produce bituminous concrete that will meet contract specification requirements. The Contractor shall be responsible for quality control throughout the production and placement operations. Therefore, the Contractor must ensure that the materials, mixture and work provided by Subcontractors, Suppliers and Producers also meet contract specification requirements.

Quality Control Plan: Prior to placement and production, the Contractor shall submit a QCP to the Engineer for approval. The QCP shall include separate sections for HMA Plant Production and for HMA Placement which shall describe the organization and procedures which the Contractor shall use to administer quality control. The QCP shall include the procedures used to control the HMA production and placement process, to determine when immediate changes to the processes are needed, and to implement the required changes. The QCP must address the actions, inspection, sampling and testing necessary to keep the production and placement

9 G5-SECTION 4.06T BITUMINOUS CONCRETE

operations in control, to determine when an operation has gone out of control and to respond to correct the situation and bring it back into control.

The QCP shall also include the name and qualifications of a Quality Control Manager. The Quality Control Manager shall be responsible for the administration of the QCP, including compliance with the plan and any plan modifications. The Quality Control Manager shall be directly responsible to the Contractor and shall have the authority to make decisions where the quality of the work or product is concerned. All sampling, inspection and test reports shall be reviewed and signed by the Quality Control Manager prior to submittal to the Engineer. Approval of the QCP will be based on the inclusion of all of the required information. Approval of the QCP does not imply any warranty by the Engineer that adherence to the plan will result in production of HMA that complies with these specifications. It shall remain the responsibility of the Contractor to demonstrate such compliance. The Contractor may propose in writing a supplement to the QCP as work progresses and must propose a supplement whenever there are changes in production or placement of HMA or to quality control procedures or personnel. HMA production and placement may be suspended by the Engineer until the revisions to the QCP have been put into effect.

The Quality Control Plan shall also include the name and qualifications of any outside testing laboratory performing any QC functions on behalf of the Contractor.

Quality Control Inspection, Sampling and Testing: The Contractor shall perform all quality control sampling and testing, provide inspection, and exercise management control to ensure that HMA production and placement conforms to the requirements as outlined in its QCP during all phases of the work.

a) Control Charts: The Contractor shall develop and maintain control charts and shall be distributed as directed by the Engineer. The control charts shall identify the project, test number, test parameter, applicable upper and lower specification limits, and test data. The control charts shall be used as part of the quality control system to document variability of the HMA production and placement process. The control charts shall be kept current. The control charts shall be updated each day of HMA production, and up-to-date copies shall be distributed prior to the beginning of the next day's production of HMA.

b) Records of Inspection and Testing: For each day of HMA production and placement, the Contractor shall document all test results and inspections on forms approved by the Engineer. The document shall be certified by the Quality Control Manager or his representative that the information in the document is accurate, and that all work complies with the requirements of the contract.

The Contractor shall submit sampling, testing and inspection documents, when directed by the Engineer, within 24 hours or by noon of the next day's HMA production. If the document is incomplete or in error, a copy of the document will be returned to the Contractor with the deficiencies noted by the Engineer. The Contractor shall correct the deficiencies and return the updated document to the Engineer by the start of the following working day. When errors

10 G5-SECTION 4.06T BITUMINOUS CONCRETE

or omissions in the sampling, inspection or testing documents repeatedly occur, the Contractor shall correct the procedures by which the documents are produced.

If control charts, sampling, testing and inspection documents are not distributed or provided as required within the time specified the Engineer may require work to be suspended until the missing documents have been provided.

Additional requirements for HMA plant production are defined in Section M.04.

10. Core Correlation Procedure for Density Testing of HMA: There will be no Core Correlation required on this project, unless required for Density Dispute Resolution, (see #12 below), or otherwise directed by the Engineer.

11. Acceptance Inspection, Sampling and Testing: Inspection, sampling, and testing to be used by the Engineer shall be performed at the minimum frequency specified in Section M.04 and stated herein.

Sampling for acceptance shall be established using a statistically based procedure of random sampling approved by the Engineer.

HMA Plant Material Acceptance: The Contractor shall provide the required acceptance sampling, testing and inspection during all phases of the work in accordance with Section M.04.

HMA Density Acceptance: All acceptance testing will be performed by the Engineer for the completed pavement course on roadways and bridges in accordance with ConnDOT’s density testing procedures. Each lift designed to a compacted lift of 1½ inches or more shall have the HMA pavement including the longitudinal joints compacted to 94.5 +/- 2.5 percent of the maximum theoretical gravity. Bituminous Concrete Class 4 and HMA S1 are excluded from the longitudinal joint density requirements.

12. Density Dispute Resolution Process: The Contractor and Engineer will work in partnership to avoid potential conflicts and to resolve any differences that may arise during quality control or acceptance testing for density. Both parties will review their sampling and testing procedures and results and share their findings. If the Contractor disputes the Engineer’s test results, the Contractor must submit in writing a request to initiate the Dispute Resolution Process within 10 calendar days of the placement of the mixture. No request for dispute resolution will be allowed unless the Contractor provides quality control results supporting its position. Should the dispute not be resolved through evaluation of existing testing data or procedures, the Engineer may authorize the Contractor to obtain representative core samples of the pavement. The core samples must be extracted no later than 30 calendar days from the date of Engineer’s authorization. Core samples shall be located using the stratified random sampling procedure in accordance with ASTM D 3665 as determined by the Engineer. Core samples shall be extracted and filled using the procedure outlined in the Core Correlation Procedure. The densities from the 5 representative cores will be averaged for determining the final HMA density acceptance including any payment adjustments, in accordance with Section 4.06.04-2, that may apply.

11 G5-SECTION 4.06T BITUMINOUS CONCRETE

13. Corrective Work Procedures: Any portion of the completed pavement that does not meet the requirements of the specification shall be corrected at the expense of the Contractor. Any corrective courses placed as the final wearing surface shall not be less than 1½ inches in thickness after compaction.

If pavement placed by the Contractor does not meet the specifications, and the Engineer requires its replacement or correction, the Contractor shall:

a) Propose a corrective procedure to the Engineer for review and approval prior to any corrective work commencing. The proposal shall include: - Limits of pavement to be replaced or corrected, indicating stationing or other landmarks that are readily distinguishable. - Proposed work schedule. - Construction method and sequence of operations. - Methods of maintenance and protection of traffic. - Material sources. - Names and telephone numbers of supervising personnel.

b) Perform all corrective work in accordance with the Contract and the approved corrective procedure.

14. Protection of the Work: The Contractor shall protect all sections of the newly finished pavement from damage that may occur as a result of the Contractor’s operations for the duration of the Project. Prior to the Engineer’s authorization to open the pavement to traffic, the Contractor is responsible to protect the pavement from damage. 15. Cut Bituminous Concrete Pavement: Work under this item shall consist of making a straight-line cut in the bituminous concrete pavement to the lines delineated on the plans or as directed by the Engineer. The cut shall provide a straight, clean, vertical face with no cracking, tearing or breakage along the cut edge.

4.06.04—Method of Measurement:

1. HMA S* : The quantity of bituminous concrete measured for payment will be determined by the documented net weight in tons accepted by the Engineer in accordance with this specification and Section M.04.

2. HMA Adjustments: There will be no HMA adjustments in this contract.

3. Transitions for Roadway Surface: The installation of permanent transitions shall be measured under the appropriate item used in the formation of the transition.

- The quantity used for the installation of temporary transitions shall be measured for payment under the appropriate HMA item used in the formation of the transition. The installation and removal of a bond breaker, and the removal and disposal of any temporary transition formed by milling or with bituminous concrete pavement is not measured for payment.

12 G5-SECTION 4.06T BITUMINOUS CONCRETE

4. Cut Bituminous Concrete Pavement: Cutting of bituminous concrete pavement will not be measured for payment, but rather shall be included in the cost of the HMA.

5. Material for Tack Coat: The quantity of tack coat will not be measured for payment but rather included in the cost of the HMA.

4.06.05—Basis of Payment:

1. HMA S*: The furnishing and placing of bituminous concrete will be paid for at the Contract unit price per ton for “HMA S ( ).” Such Price shall include items listed in 4.06.04 items 1-5 and shall include all costs associated with obtaining cores for dispute resolution should dispute resolution be required.

2. HMA Adjustment Cost: There will be no HMA Adjustments in this contract

Pay Item Pay Unit HMA S* ton

13 G6-ITEM # 0406999A-T – ASPHALT ADJUSTMENT COST

The Asphalt Price is available on the Department of Transportation web site at:

http://www.ct.gov/dot/asphaltadjustment

The asphalt adjustment cost will be based on the variance in price for the performance-graded binder component of hot mix asphalt (HMA) mixtures completed and accepted in the contract.

An asphalt adjustment cost will be applied only if all of the following conditions are met:

a) The HMA mixture in which the adjustment is being applied is listed as a contract item with a pay unit of tons or metric tons. b) The total quantity for all HMA mixtures in a contract or individual purchase order (Department of Administrative Service contract awards) exceeds 1000 tons or more. c) The difference between the posted Asphalt Base Price and Asphalt Period Price varies by more than $5.00.

The Connecticut Department of Transportation (ConnDOT) shall post on its website, the average per ton selling price (asphalt price) of the performance-graded binder. The average is based on the high and low selling price published in the most recent available issue of the Asphalt Weekly Monitor® furnished by Poten & Partners, Inc. under the “East Coast Market – New England, New Haven, Connecticut area”, F.O.B. manufacturer’s terminal.

The selling price furnished from the Asphalt Weekly Monitor ® is based on a standard ton (US$/ST). The metric ton price is determined by applying a factor of 1.1023 (US$/ST x 1.1023 = US$/mton). Example: $150.00/ton x 1.1023 = $165.34/mton

Formula: HMA X PG% x [(Period Price - Base Price] = $ ____ 100

- HMA: The quantity (tons or metric tons) of accepted HMA mixture measured and accepted for payment.

- Asphalt Base Price: The asphalt price that is posted on the ConnDOT website 28 days before the actual bid opening posted.

- Asphalt Period Price: The asphalt price that is posted on the ConnDOT website for the period in which the HMA mixture is placed.

- Performance-Graded Binder percentage (PG%) for HMA mixes:

PG% = 4.5 ° For Superpave 37.5mm (1.5 inch), Superpave 25.0mm (1.0 inch), HMA S1, and Class 4 ITEM #0406999A 1 G6-ITEM # 0406999A-T – ASPHALT ADJUSTMENT COST

PG % = 5.0 ° For Superpave 12.5mm (0.50 inch), HMA S0.5 and Class 1.

PG % = 6.0 ° For Superpave 0.375 inch (9.5mm), HMA S0.375, Superpave 6.25mm (0.25 inch), HMA S0.25, Superpave 4.75mm (#4) and Class 2.

The adjustment shall not be considered as a changed condition in the contract because of this provision and because the Contractors are being notified before submission of bids.

Basis of Payment: The "Asphalt Adjustment Cost" will be calculated using the formula indicated above. A payment will be made for an increase in costs. A deduction from monies due the Contractor will be made for a decrease in costs.

The sum of money shown on the estimate, and in the itemized proposal as "Estimated Cost", for this item will be considered the bid price although payment will be made as described above. The estimated cost figure is not to be altered in any manner by the bidder. If the bidder should alter the amount shown, the altered figure will be disregarded and the original cost figure will be used to determine the amount of the bid for the Contract.

ITEM #0406999A 2

SECTION 3 – STATE PREVAILING WAGE RATES CARPENTERS, MILLWRIGHTS. PILEDRIVERMEN. LATHERS. RESILEINT FLOOR LAYERS, DOCK BUILDERS, DIKERS, DIVER TENDERS

Constructs, erects, installs and repairs structures and fixtures of wood, plywood and wallboard. Installs, assembles, dismantles, moves industrial machinery. Drives piling into ground to provide foundations for structures such as buildings and bridges, retaining walls for earth embankments, such as cofferdams. Fastens wooden, metal or rockboard lath to walls, ceilings and partitions of buildings, acoustical tile layer, concrete form builder. Applies firestopping materials on fire resistive joint systems only. Installation of curtain/window walls only where attached to wood or metal studs. Installation of insulated material of all types whether blown, nailed or attached in other ways to walls, ceilings and floors of buildings. Assembly and installation of modular furniture/furniture systems. Free- standing furniture is not covered. This includes free standing: student chairs, study top desks, book box desks, computer furniture, dictionary stand, atlas stand, wood shelving, two-position information access station, file cabinets, storage cabinets, tables, etc.

CLEANING LABORER

The clean up of any construction debris and the general cleaning, including sweeping, wash down, mopping, wiping of the construction facility, washing, polishing, dusting, etc., prior to the issuance of a certificate of occupancy falls under the Labor classification.

DELIVERY PERSONNEL

If delivery of supplies/building materials is to one common point and stockpiled there, prevailing wages are not required. If the delivery personnel are involved in the distribution of the material to multiple locations within the construction site then they would have to be paid prevailing wages for the type of work performed: laborer, equipment operator, electrician, ironworker, plumber, etc.

An example of this would be where delivery of drywall is made to a building and the delivery personnel distribute the drywall from one "stockpile" location to further sub‐locations on each floor. Distribution of material around a construction site is the job of a laborer/tradesman and not a delivery personnel.

ELECTRICIANS

Install, erect, maintenance, alteration or repair of any wire, cable, conduit, etc., which generates, transforms, transmits or uses electrical energy for light, heat, power or other purposes, including the Installation or maintenance of telecommunication, LAN wiring or computer equipment, and low voltage wiring. *License required per Connecticut General Statutes: E-1,2 L-5,6 C-5,6 T-1,2 L- 1,2 V-1,2,7,8,9.

ELEVATOR CONSTRUCTORS

Install, erect, maintenance and repair of all types of elevators, escalators, dumb waiters and moving walks. *License required by Connecticut General Statutes: R-1,2,5,6.

FORK LIFT OPERATOR

Laborers Group 4) Mason Tenders - operates forklift solely to assist a mason to a maximum height of nine (9) feet only.

Power Equipment Operator Group 9 ‐ operates forklift to assist any trade, and to assist a mason to a height over nine (9) feet.

GLAZIERS

Glazing wood and metal sash, doors, partitions, and 2 story aluminum storefronts. Installs glass windows, skylights, store fronts and display cases or surfaces such as building fronts, interior walls, ceilings and table tops and metal store fronts. Installation of aluminum window walls and curtain walls is the "joint" work of glaziers and ironworkers which requires either a blended rate or equal composite workforce.

IRONWORKERS

Erection, installation and placement of structural steel, precast concrete, miscellaneous iron, ornamental iron, metal curtain wall, rigging and reinforcing steel. Handling, sorting, and installation of reinforcing steel (rebar). Metal bridge rail (traffic), metal bridge handrail, and decorative security fence installation. Installation of aluminum window walls and curtain walls is the "joint" work of glaziers and ironworkers which requires either a blended rate or equal composite workforce. Insulated metal and insulated composite panels are still installed by the Ironworker.

INSULATOR

Installing fire stopping systems/materials for "Penetration Firestop Systems": transit to cables, electrical conduits, insulated pipes, sprinkler pipe penetrations, ductwork behind radiation, electrical cable trays, fire rated pipe penetrations, natural polypropylene, HVAC ducts, plumbing bare metal, telephone and communication wires, and boiler room ceilings. Past practice using the applicable licensed trades, Plumber, Sheet Metal, Sprinkler Fitter, and Electrician, is not inconsistent with the Insulator classification and would be permitted.

LABORERS

Acetylene burners, asphalt rakers, chain saw operators, concrete and power buggy operator, concrete saw operator, fence and erector (except metal bridge rail (traffic), metal bridge handrail, and decorative security fence installation.), hand operated concrete vibrator operator, mason tenders, pipelayers (installation of storm drainage or sewage lines on the street only), pneumatic drill operator, pneumatic gas and electric drill operator, powermen and wagon drill operator, air track operator, block paver, curb setters, blasters, concrete spreaders.

PAINTERS

Maintenance, preparation, cleaning, blasting (water and sand, etc.), painting or application of any protective coatings of every description on all bridges and appurtenances of highways, roadways, and railroads. Painting, decorating, hardwood finishing, paper hanging, sign writing, scenic art work and drywall hhg for any and all types of building and residential work.

LEAD PAINT REMOVAL

Painter’s Rate 1. Removal of lead paint from bridges. 2. Removal of lead paint as preparation of any surface to be repainted. 3. Where removal is on a Demolition project prior to reconstruction.

Laborer’s Rate 1. Removal of lead paint from any surface NOT to be repainted. 2. Where removal is on a TOTAL Demolition project only.

PLUMBERS AND PIPEFITTERS

Installation, repair, replacement, alteration or maintenance of all plumbing, heating, cooling and piping. *License required per Connecticut General Statutes: P- 1,2,6,7,8,9 J-1,2,3,4 SP-1,2 S-1,2,3,4,5,6,7,8 B-1,2,3,4 D-1,2,3,4.

POWER EQUIPMENT OPERATORS

Operates several types of power construction equipment such as compressors, pumps, hoists, derricks, cranes, shovels, tractors, scrapers or motor graders, etc. Repairs and maintains equipment. *License required, crane operators only, per Connecticut General Statutes.

ROOFERS

Covers roofs with composition shingles or sheets, wood shingles, slate or asphalt and gravel to waterproof roofs, including preparation of surface. (tear-off and/or removal of any type of roofing and/or clean-up of any and all areas where a roof is to be relaid)

SHEETMETAL WORKERS

Fabricate, assembles, installs and repairs sheetmetal products and equipment in such areas as ventilation, air-conditioning, warm air heating, restaurant equipment, architectural sheet metal work, sheetmetal roofing, and aluminum gutters. Fabrication, handling, assembling, erecting, altering, repairing, etc. of coated metal material panels and composite metal material panels when used on building exteriors and interiors as soffits, facia, louvers, partitions, wall panel siding, canopies, cornice, column covers, awnings, beam covers, cladding, sun shades, lighting troughs, spires, ornamental roofing, metal ceilings, mansards, copings, ornamental and ventilation hoods, vertical and horizontal siding panels, trim, etc. The sheet metal classification also applies to the vast variety of coated metal material panels and composite metal material panels that have evolved over the years as an alternative to conventional ferrous and non-ferrous metals like steel, iron, tin, copper, brass, bronze, aluminum, etc. Insulated metal and insulated composite panels are still installed by the Iron Worker. Fabrication, handling, assembling, erecting, altering, repairing, etc. of architectural metal roof, standing seam roof, composite metal roof, metal and composite bathroom/toilet partitions, aluminum gutters, metal and composite lockers and shelving, kitchen equipment, and walk‐in coolers.

SPRINKLER FITTERS

Installation, alteration, maintenance and repair of fire protection sprinkler systems. *License required per Connecticut General Statutes: F-1,2,3,4.

TILE MARBLE AND TERRAZZO FINISHERS

Assists and tends the tile setter, marble mason and terrazzo worker in the performance of their duties.

TRUCK DRIVERS

Definitions:

1) “Site of the work” (29 Code of Federal Regulations (CFR) 5.2(l)(b) is the physical place or places where the building or work called for in the contract will remain and any other site where a significant portion of the building or work is constructed, provided that such site is established specifically for the performance of the contact or project;

(a) Except as provided in paragraph (l) (3) of this section, job headquarters, tool yards, batch plants, borrow pits, etc. are part of the “site of the work”; provided they are dedicated exclusively, or nearly so, to the performance of the contract or project, and provided they are adjacent to “the site of work” as defined in paragraph (e)(1) of this section;

(b) Not included in the “site of the work” are permanent home offices, branch plant establishments, fabrication plants, tool yards etc, of a contractor or subcontractor whose location and continuance in operation are determined wholly without regard to a particular State or political subdivision contract or uncertain and indefinite periods of time involved of a few seconds or minutes duration and where the failure to count such time is due to consideration justified by industrial realities (29 CFR 785.47)

2) “Engaged to wait” is waiting time that belongs to and is controlled by the employer which is an integral part of the job and is therefore compensable as hours worked. (29 CFR 785.15)

3) “Waiting to be engaged” is waiting time that an employee can use effectively for their own purpose and is not compensable as hours worked. (29 CFR 785.16)

4) “De Minimus” is a rule that recognizes that unsubstantial or insignificant periods of time which cannot as a practical administrative matter be precisely recorded for payroll purposes, may be disregarded. This rule applies only where there are uncertain and indefinite periods of time involved of a short duration and where the failure to count such time is due to consideration justified by worksite realities. For example, with respect to truck drivers on prevailing wage sites, this is typically less than 15 minutes at a time.

Coverage of Truck Drivers on State or Political subdivision Prevailing Wage Projects

Truck drivers are covered for payroll purposes under the following conditions:

Truck Drivers for time spent working on the site of the work.

Truck Drivers for time spent loading and/or unloading materials and supplies on the site of the work, if such time is not de minimus

Truck drivers transporting materials or supplies between a facility that is deemed part of the site of the work and the actual construction site.

Truck drivers transporting portions of the building or work between a site established specifically for the performance of the contract or project where a significant portion of such building or work is constructed and the physical places where the building or work outlined in the contract will remain.

For example: Truck drivers delivering asphalt are covered under prevailing wage while” engaged to wait” on the site and when directly involved in the paving operation, provided the total time is not “de minimus”

Truck Drivers are not covered in the following instances:

Material delivery truck drivers while off “the site of the work”

Truck Drivers traveling between a prevailing wage job and a commercial supply facility while they are off the “site of the work”

Truck drivers whose time spent on the “site of the work” is de minimus, such as under 15 minutes at a time, merely to drop off materials or supplies, including asphalt.

These guidelines are similar to U.S. Labor Department policies. The application of these guidelines may be subject to review based on factual considerations on a case by case basis.

For example:

Material men and deliverymen are not covered under prevailing wage as long as they are not directly involved in the construction process. If, they unload the material, they would then be covered by prevailing wage for the classification they are performing work in: laborer, equipment operator, etc. Hauling material off site is not covered provided they are not dumping it at a location outlined above. Driving a truck on site and moving equipment or materials on site would be considered covered work, as this is part of the construction process.

Any questions regarding the proper classification should be directed to: Public Contract Compliance Unit Wage and Workplace Standards Division Connecticut Department of Labor 200 Folly Brook Blvd, Wethersfield, CT 06109 (860) 263-6543 Ironworkers a. Paid Holiday: Labor Day provided employee has been on the payroll for the 5 consecutive work days prior to Labor Day.

Laborers (Tunnel Construction) a. Paid Holidays: New Year’s Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day. No employee shall be eligible for holiday pay when he fails, without cause, to work the regular work day preceding the holiday or the regular work day following the holiday.

Roofers a. Paid Holidays: July 4th, Labor Day, and Christmas Day provided the employee is employed 15 days prior to the holiday.

Sprinkler Fitters a. Paid Holidays: Memorial Day, July 4th, Labor Day, Thanksgiving Day and Christmas Day, provided the employee has been in the employment of a contractor 20 working days prior to any such paid holiday.

Truck Drivers (Heavy and Highway Construction & Building Construction)

a. Paid Holidays: New Year’s Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas day, and Good Friday, provided the employee has at least 31 calendar days of service and works the last scheduled day before and the first scheduled day after the holiday, unless excused.

Project: Pavement Preservation And Repairs On Various Roads

Minimum Rates and Classifications for Heavy/Highway Construction Connecticut Department of Labor ID#: H 16706 Wage and Workplace Standards Division

By virtue of the authority vested in the Labor Commissioner under provisions of Section 31-53 of the General Statutes of Connecticut, as amended, the following are declared to be the prevailing rates and welfare payments and will apply only where the contract is advertised for bid within 20 days of the date on which the rates are established. Any contractor or subcontractor not obligated by agreement to pay to the welfare and pension fund shall pay this amount to each employee as part of his/her hourly wages. Project Number: 2012 Project Town Westport FAP Number: State Number: Project: Pavement Preservation And Repairs On Various Roads

CLASSIFICATION Hourly Rate Benefits 01) Asbestos/Toxic Waste Removal Laborers: Asbestos removal and encapsulation (except its removal from mechanical systems which are not to be scrapped), toxic waste removers, blasters. **See Laborers Group 5 and 7**

1) Boilermaker 33.79 34% + 8.96

1a) Bricklayer, Cement Masons, Cement Finishers, Plasterers, Stone Masons 32.50 24.55

2) Carpenters, Piledrivermen 29.65 21.00

2a) Diver Tenders 29.65 21.00

As of: Tuesday, July 03, 2012 Project: Pavement Preservation And Repairs On Various Roads

3) Divers 38.11 21.00

4) Painters: (Bridge Construction) Brush, Roller, Blasting (Sand, Water, 42.75 16.90 etc.), Spray

4a) Painters: Brush and Roller 30.22 16.90

4b) Painters: Spray Only 33.22 16.90

4c) Painters: Steel Only 30.47 15.40

4d) Painters: Blast and Spray 33.22 16.90

4e) Painters: Tanks, Tower and Swing 32.22 16.90

5) Electrician (Trade License required: E-1,2 L-5,6 C-5,6 T-1,2 L-1,2 35.30 18.52 V-1,2,7,8,9)

As of: Tuesday, July 03, 2012 Project: Pavement Preservation And Repairs On Various Roads

6) Ironworkers: (Ornamental, Reinforcing, Structural, and Precast Concrete 33.50 27.98 + a Erection)

7) Plumbers (Trade License required: (P-1,2,6,7,8,9 J-1,2,3,4 SP-1,2) and 38.67 25.56 Pipefitters (Including HVAC Work) (Trade License required: S-1,2,3,4,5,6,7,8 B-1,2,3,4 D-1,2,3,4 G-1, G-2, G-8, G-9)

----LABORERS---- - Last updated 4/11/12

8) Group 1: Laborer (Unskilled), Common or General, acetylene burner, 25.80 16.45 concrete specialist

9) Group 2: Chain saw operators, fence and guard rail erectors, pneumatic 26.05 16.45 tool operators, powdermen, air tool operator

10) Group 3: Pipelayers (Installation of water, storm drainage or sewage lines 26.30 16.45 outside of the building line with P6, P7 license)

11) Group 4: Jackhammer/Pavement breaker (handheld); mason tenders 26.30 16.45 (cement/concrete), catch basin builders, asphalt rakers, air track operators, block pavers and curb setters

12) Group 5: Toxic waste removal (non-mechanical systems) 27.80 16.45

As of: Tuesday, July 03, 2012 Project: Pavement Preservation And Repairs On Various Roads

13) Group 6: Blasters 27.55 16.45

Group 7: Asbestos Removal, non-mechanical systems (does not include 26.80 16.45 leaded joint pipe)

Group 8: Traffic control signalmen 16.00 16.45

----LABORERS (TUNNEL CONSTRUCTION, FREE AIR). Shield Drive and Liner Plate Tunnels in Free Air.---- Last updated 4/11/12----

13a) Miners, Motormen, Mucking Machine Operators, Nozzle Men, Grout 31.28 16.45 + a Men, Shaft & Tunnel Steel & Rodmen, Shield & Erector, Arm Operator, Cable Tenders

13b) Brakemen, Trackmen 30.37 16.45 + a

----CLEANING, CONCRETE AND CAULKING TUNNEL----Last updated 4/11/12----

14) Concrete Workers, Form Movers, and Strippers 30.37 16.45 + a

As of: Tuesday, July 03, 2012 Project: Pavement Preservation And Repairs On Various Roads

15) Form Erectors 30.68 16.45 + a

----ROCK SHAFT LINING, CONCRETE, LINING OF SAME AND TUNNEL IN FREE AIR:----Last updated 4/11/12----

16) Brakemen, Trackmen, Tunnel Laborers, Shaft Laborers 30.37 16.45 + a

17) Laborers Topside, Cage Tenders, Bellman 30.26 16.45 + a

18) Miners 31.28 16.45 + a

----TUNNELS, CAISSON AND CYLINDER WORK IN COMPRESSED AIR: ----Last updated 4/11/12----

18a) Blaster 37.41 16.45 + a

19) Brakemen, Trackmen, Groutman, Laborers, Outside Lock Tender, Gauge 37.22 16.45 + a Tenders

As of: Tuesday, July 03, 2012 Project: Pavement Preservation And Repairs On Various Roads

20) Change House Attendants, Powder Watchmen, Top on Iron Bolts 35.35 16.45 + a

21) Mucking Machine Operator 37.97 16.45 + a

----TRUCK DRIVERS----(*see note below)

Two axle trucks 27.88 17.22 + a

Three axle trucks; two axle ready mix 27.98 17.22 + a

Three axle ready mix 28.03 17.22 + a

Four axle trucks, heavy duty trailer (up to 40 tons) 28.08 17.22 + a

Four axle ready-mix 28.13 17.22 + a

As of: Tuesday, July 03, 2012 Project: Pavement Preservation And Repairs On Various Roads

Heavy duty trailer (40 tons and over) 28.33 17.22 + a

Specialized earth moving equipment other than conventional type on-the road 28.13 17.22 + a trucks and semi-trailer (including Euclids)

----POWER EQUIPMENT OPERATORS----

Group 1: Crane handling or erecting structural steel or stone, hoisting 35.50 20.50 + a engineer (2 drums or over), front end loader (7 cubic yards or over), Work Boat 26 ft. & Over. (Trade License Required)

Group 2: Cranes (100 ton rate capacity and over); Backhoe/Excavator over 2 35.18 20.50 + a cubic yards; Piledriver ($3.00 premium when operator controls hammer). (Trade License Required)

Group 3: Excavator/Backhoe under 2 cubic yards; Cranes (under 100 ton 34.44 20.50 + a rated capacity), Gradall; Master Mechanic; Hoisting Engineer (all types of equipment where a drum and cable are used to hoist or drag material regardless of motive power of operation), Rubber Tire Excavator (Drott-1085 or similar);Grader Operator; Bulldozer Fine Grade (slopes, shaping, laser or GPS, etc.). (Trade License Required) Group 4: Trenching Machines; Lighter Derrick; Concrete Finishing Machine; 34.05 20.50 + a CMI Machine or Similar; Koehring Loader (Skooper)

Group 5: Specialty Railroad Equipment; Asphalt Paver; Asphalt Spreader; 33.46 20.50 + a Asphalt Reclaiming Machine; Line Grinder; Concrete Pumps; Drills with Self Contained Power Units; Boring Machine; Post Hole Digger; Auger; Pounder; Well Digger; Milling Machine (over 24" Mandrell)

As of: Tuesday, July 03, 2012 Project: Pavement Preservation And Repairs On Various Roads

Group 5 continued: Side Boom; Combination Hoe and Loader; Directional 33.46 20.50 + a Driller.

Group 6: Front End Loader (3 up to 7 cubic yards); Bulldozer (rough grade 33.15 20.50 + a dozer).

Group 7: Asphalt Roller; Concrete Saws and Cutters (ride on types); Vermeer 32.81 20.50 + a Concrete Cutter; Stump Grinder; Scraper; Snooper; Skidder; Milling Machine (24" and Under Mandrel).

Group 8: Mechanic, Grease Truck Operator, Hydroblaster, Barrier Mover, 32.41 20.50 + a Power Stone Spreader; Welder; Work Boat under 26 ft.; Transfer Machine.

Group 9: Front End Loader (under 3 cubic yards), Skid Steer Loader 31.98 20.50 + a regardless of attachments (Bobcat or Similar); Fork Lift, Power Chipper; Landscape Equipment (including hydroseeder).

Group 10: Vibratory Hammer, Ice Machine, Diesel and Air Hammer, etc. 29.94 20.50 + a

Group 11: Conveyor, Earth Roller; Power Pavement Breaker (whiphammer), 29.94 20.50 + a Robot Demolition Equipment.

Group 12: Wellpoint Operator. 29.88 20.50 + a

As of: Tuesday, July 03, 2012 Project: Pavement Preservation And Repairs On Various Roads

Group 13: Compressor Battery Operator. 29.30 20.50 + a

Group 14: Elevator Operator; Tow Motor Operator (Solid Tire No Rough 28.16 20.50 + a Terrain).

Group 15: Generator Operator; Compressor Operator; Pump Operator; 27.75 20.50 + a Welding Machine Operator; Heater Operator.

Group 16: Maintenance Engineer/Oiler 27.10 20.50 + a

Group 17: Portable asphalt plant operator; portable crusher plant operator; 31.41 20.50 + a portable concrete plant operator.

Group 18: Power Safety Boat; Vacuum Truck; Zim Mixer; Sweeper; 28.99 20.50 + a (minimum for any job requiring CDL license).

**NOTE: SEE BELOW

----LINE CONSTRUCTION----(Railroad Construction and Maintenance)----Last updated 9/3/2010----

As of: Tuesday, July 03, 2012 Project: Pavement Preservation And Repairs On Various Roads

20) Lineman, Cable Splicer, Dynamite Man 44.36 3% + 13.70

21) Heavy Equipment Operator 39.92 3% + 13.70

22) Equipment Operator, Tractor Trailer Driver, Material Men 37.71 3% + 13.70

23) Driver Groundmen 33.27 3% + 13.70

----LINE CONSTRUCTION----Last updated 4/17/09----

24) Driver Groundmen 30.92 6.5% + 9.70

25) Groundmen 22.67 6.5% + 6.20

26) Heavy Equipment Operators 37.10 6.5% + 10.70

As of: Tuesday, July 03, 2012 Project: Pavement Preservation And Repairs On Various Roads

27) Linemen, Cable Splicers, Dynamite Men 41.22 6.5% + 12.20

28) Material Men, Tractor Trailer Drivers, Equipment Operators 35.04 6.5% + 10.45

As of: Tuesday, July 03, 2012 Project: Pavement Preservation And Repairs On Various Roads

Welders: Rate for craft to which welding is incidental. *Note: Hazardous waste removal work receives additional $1.25 per hour for truck drivers. **Note: Hazardous waste premium $3.00 per hour over classified rate Crane with 150 ft. boom (including jib) - $1.50 extra Crane with 200 ft. boom (including jib) - $2.50 extra Crane with 250 ft. boom (including jib) - $5.00 extra Crane with 300 ft. boom (including jib) - $7.00 extra Crane with 400 ft. boom (including jib) - $10.00 extra

All classifications that indicate a percentage of the fringe benefits must be calculated at the percentage rate times the "base hourly rate".

Apprentices duly registered under the Commissioner of Labor's regulations on "Work Training Standards for Apprenticeship and Training Programs" Section 31-51-d-1 to 12, are allowed to be paid the appropriate percentage of the prevailing journeymen hourly base and the full fringe benefit rate, providing the work site ratio shall not be less than one full-time journeyperson instructing and supervising the work of each apprentice in a specific trade.

~~Connecticut General Statute Section 31-55a: Annual Adjustments to wage rates by contractors doing state work ~~ The Prevailing wage rates applicable to this project are subject to annual adjustments each July 1st for the duration of the project. Each contractor shall pay the annual adjusted prevailing wage rate that is in effect each July 1st, as posted by the Department of Labor. It is the contractor's responsibility to obtain the annual adjusted prevailing wage rate increases directly from the Department of Labor's website. The annual adjustments will be posted on the Department of Labor's Web page: www.ct.gov/dol. The Department of Labor will continue to issue the initial prevailing wage rate schedule to the Contracting Agency for the project. All subsequent annual adjustments will be posted on our Web Site for contractor access.

As of: Tuesday, July 03, 2012 Project: Pavement Preservation And Repairs On Various Roads

Effective October 1, 2005 - Public Act 05-50: any person performing the work of any mechanic, laborer, or worker shall be paid prevailing wage

All Person who perform work ON SITE must be paid prevailing wage for the appropriate mechanic, laborer, or worker classification. All certified payrolls must list the hours worked and wages paid to All Persons who perform work ON SITE regardless of their ownership i.e.: (Owners, Corporate Officers, LLC Members, Independent Contractors, et. al) Reporting and payment of wages is required regardless of any contractual relationship alleged to exist between the contractor and such person. ~~Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clause (29 CFR 5.5 (a) (1) (ii)).

Please direct any questions which you may have pertaining to classification of work and payment of prevailing wages to the Wage and Workplace Standards Division, telephone (860)263-6790.

As of: Tuesday, July 03, 2012

Sec. 31-53b. Construction safety and health course. New miner training program. Proof of completion required for mechanics, laborers and workers on public works projects. Enforcement. Regulations. Exceptions. (a) Each contract for a public works project entered into on or after July 1, 2009, by the state or any of its agents, or by any political subdivision of the state or any of its agents, described in subsection (g) of section 31-53, shall contain a provision requiring that each contractor furnish proof with the weekly certified payroll form for the first week each employee begins work on such project that any person performing the work of a mechanic, laborer or worker pursuant to the classifications of labor under section 31-53 on such public works project, pursuant to such contract, has completed a course of at least ten hours in duration in construction safety and health approved by the federal Occupational Safety and Health Administration or, has completed a new miner training program approved by the Federal Mine Safety and Health Administration in accordance with 30 CFR 48 or, in the case of telecommunications employees, has completed at least ten hours of training in accordance with 29 CFR 1910.268.

(b) Any person required to complete a course or program under subsection (a) of this section who has not completed the course or program shall be subject to removal from the worksite if the person does not provide documentation of having completed such course or program by the fifteenth day after the date the person is found to be in noncompliance. The Labor Commissioner or said commissioner's designee shall enforce this section.

(c) Not later than January 1, 2009, the Labor Commissioner shall adopt regulations, in accordance with the provisions of chapter 54, to implement the provisions of subsections (a) and (b) of this section. Such regulations shall require that the ten-hour construction safety and health courses required under subsection (a) of this section be conducted in accordance with federal Occupational Safety and Health Administration Training Institute standards, or in accordance with Federal Mine Safety and Health Administration Standards or in accordance with 29 CFR 1910.268, as appropriate. The Labor Commissioner shall accept as sufficient proof of compliance with the provisions of subsection (a) or (b) of this section a student course completion card issued by the federal Occupational Safety and Health Administration Training Institute, or such other proof of compliance said commissioner deems appropriate, dated no earlier than five years before the commencement date of such public works project.

(d) This section shall not apply to employees of public service companies, as defined in section 16-1, or drivers of commercial motor vehicles driving the vehicle on the public works project and delivering or picking up cargo from public works projects provided they perform no labor relating to the project other than the loading and unloading of their cargo.

(P.A. 06-175, S. 1; P.A. 08-83, S. 1.)

History: P.A. 08-83 amended Subsec. (a) by making provisions applicable to public works project contracts entered into on or after July 1, 2009, replacing provision re total cost of work with reference to Sec. 31-53(g), requiring proof in certified payroll form that new mechanic, laborer or worker has completed a 10-hour or more construction safety course and adding provision re new miner training program, amended Subsec. (b) by substituting "person" for "employee" and adding "or program", amended Subsec. (c) by adding "or in accordance with Federal Mine Safety and Health Administration Standards" and setting new deadline of January 1, 2009, deleted former Subsec. (d) re "public building", added new Subsec. (d) re exemptions for public service company employees and delivery drivers who perform no labor other than delivery and made conforming and technical changes, effective January 1, 2009. Informational Bulletin

THE 10-HOUR OSHA CONSTRUCTION SAFETY AND HEALTH COURSE (applicable to public building contracts entered into on or after July 1, 2007, where the total cost of all work to be performed is at least $100,000)

(1) This requirement was created by Public Act No. 06-175, which is codified in Section 31-53b of the Connecticut General Statutes (pertaining to the prevailing wage statutes);

(2) The course is required for public building construction contracts (projects funded in whole or in part by the state or any political subdivision of the state) entered into on or after July 1, 2007;

(3) It is required of private employees (not state or municipal employees) and apprentices who perform manual labor for a general contractor or subcontractor on a public building project where the total cost of all work to be performed is at least $100,000;

(4) The ten-hour construction course pertains to the ten-hour Outreach Course conducted in accordance with federal OSHA Training Institute standards, and, for telecommunications workers, a ten-hour training course conducted in accordance with federal OSHA standard, 29 CFR 1910.268;

(5) The internet website for the federal OSHA Training Institute is http://www.osha.gov/fso/ote/training/edcenters/fact_sheet.html;

(6) The statutory language leaves it to the contractor and its employees to determine who pays for the cost of the ten-hour Outreach Course;

(7) Within 30 days of receiving a contract award, a general contractor must furnish proof to the Labor Commissioner that all employees and apprentices performing manual labor on the project will have completed such a course;

(8) Proof of completion may be demonstrated through either: (a) the presentation of a bona fide student course completion card issued by the federal OSHA Training Institute; or (2) the presentation of documentation provided to an employee by a trainer certified by the Institute pending the actual issuance of the completion card;

(9) Any card with an issuance date more than 5 years prior to the commencement date of the construction project shall not constitute proof of compliance;

(10) Each employer shall affix a copy of the construction safety course completion card to the certified payroll submitted to the contracting agency in accordance with Conn. Gen. Stat. § 31-53(f) on which such employee’s name first appears;

(11) Any employee found to be in non-compliance shall be subject to removal from the worksite if such employee does not provide satisfactory proof of course completion to the Labor Commissioner by the fifteenth day after the date the employee is determined to be in noncompliance;

(12) Any such employee who is determined to be in noncompliance may continue to work on a public building construction project for a maximum of fourteen consecutive calendar days while bringing his or her status into compliance;

(13) The Labor Commissioner may make complaint to the prosecuting authorities regarding any employer or agent of the employer, or officer or agent of the corporation who files a false certified payroll with respect to the status of an employee who is performing manual labor on a public building construction project;

(14) The statute provides the minimum standards required for the completion of a safety course by manual laborers on public construction contracts; any contractor can exceed these minimum requirements; and

(15) Regulations clarifying the statute are currently in the regulatory process, and shall be posted on the CTDOL website as soon as they are adopted in final form.

(16) Any questions regarding this statute may be directed to the Wage and Workplace Standards Division of the Connecticut Labor Department via the internet website of http://www.ctdol.state.ct.us/wgwkstnd/wgemenu.htm; or by telephone at (860)263-6790.

THE ABOVE INFORMATION IS PROVIDED EXCLUSIVELY AS AN EDUCATIONAL RESOURCE, AND IS NOT INTENDED AS A SUBSTITUTE FOR LEGAL INTERPRETATIONS WHICH MAY ULTMATELY ARISE CONCERNIG THE CONSTRUCTION OF THE STATUTE OR THE REGULATIONS. November 29, 2006 Notice To All Mason Contractors and Interested Parties Regarding Construction Pursuant to Section 31-53 of the Connecticut General Statutes (Prevailing Wage)

The Connecticut Labor Department Wage and Workplace Standards Division is empowered to enforce the prevailing wage rates on projects covered by the above referenced statute.

Over the past few years the Division has withheld enforcement of the rate in effect for workers who operate a forklift on a prevailing wage rate project due to a potential jurisdictional dispute.

The rate listed in the schedules and in our Occupational Bulletin (see enclosed) has been as follows:

Forklift Operator:

- Laborers (Group 4) Mason Tenders - operates forklift solely to assist a mason to a maximum height of nine feet only.

- Power Equipment Operator (Group 9) - operates forklift to assist any trade and to assist a mason to a height over nine feet.

The U.S. Labor Department conducted a survey of rates in Connecticut but it has not been published and the rate in effect remains as outlined in the above Occupational Bulletin.

Since this is a classification matter and not one of jurisdiction, effective January 1, 2007 the Connecticut Labor Department will enforce the rate on each schedule in accordance with our statutory authority.

Your cooperation in filing appropriate and accurate certified payrolls is appreciated. Sec. 31-55a Page 1 of 1

STATUTE 31-55a

- SPECIAL NOTICE -

To All State and Political Subdivisions,Their Agents, and Contractors

Connecticut General Statute 31-55a - Annual adjustments to wage rates by contractors doing state work.

Each contractor that is awarded a contract on or after October 1, 2002, for (1) the construction of a state highway or bridge that falls under the provisions of section 31-54 of the general statutes, or (2) the construction, remodeling, refinishing, refurbishing, rehabilitation, alteration or repair of any public works project that falls under the provisions of section 31-53 of the general statutes shall contact the Labor Commissioner on or before July first of each year, for the duration of such contract, to ascertain the prevailing rate of wages on an hourly basis and the amount of payment or contributions paid or payable on behalf of each mechanic, laborer or worker employed upon the work contracted to be done, and shall make any necessary adjustments to such prevailing rate of wages and such payment or contributions paid or payable on behalf of each such employee, effective each July first.

ò The prevailing wage rates applicable to any contract or subcontract awarded on or after October 1, 2002 are subject to annual adjustments each July 1st for the duration of any project which was originally advertised for bids on or after October 1, 2002. ò Each contractor affected by the above requirement shall pay the annual adjusted prevailing wage rate that is in effect each July 1st, as posted by the Department of Labor. ò It is the contractor’s responsibility to obtain the annual adjusted prevailing wage rate increases directly from the Department of Labor’s Web Site. The annual adjustments will be posted on the Department of Labor Web page: www.ctdol.state.ct.us. For those without internet access, please contact the division listed below. ò The Department of Labor will continue to issue the initial prevailing wage rate schedule to the Contracting Agency for the project. All subsequent annual adjustments will be posted on our Web Site for contractor access.

Any questions should be directed to the Contract Compliance Unit, Wage and Workplace Standards Division, Connecticut Department of Labor, 200 Folly Brook Blvd., Wethersfield, CT 06109 at (860)263-6790.

Workplace Laws

http://www.ctdol.state.ct.us/wgwkstnd/laws-regs/statute31-55a.htm 6/22/2012 ~NOTICE~

TO ALL CONTRACTING AGENCIES

Please be advised that Connecticut General Statutes Section 31-53, requires the contracting agency to certify to the Department of Labor, the total dollar amount of work to be done in connection with such public works project, regardless of whether such project consists of one or more contracts.

Please find the attached “Contracting Agency Certification Form” to be completed and returned to the Department of Labor, Wage and Workplace Standards Division, Public Contract Compliance Unit.

O Inquiries can be directed to (860)263-6543. CONNECTICUT DEPARTMENT OF LABOR WAGE AND WORKPLACE STANDARDS DIVISION CONTRACT COMPLIANCE UNIT

CONTRACTING AGENCY CERTIFICATION FORM

I, , acting in my official capacity as , authorized representative title

for , located at , contracting agency address

do hereby certify that the total dollar amount of work to be done in connection with

, located at , project name and number address

shall be $ , which includes all work, regardless of whether such project

consists of one or more contracts.

CONTRACTOR INFORMATION

Name:

Address: Authorized Representative: Approximate Starting Date:

Approximate Completion Date:

Signature Date

Return To: Connecticut Department of Labor Wage & Workplace Standards Division Contract Compliance Unit 200 Folly Brook Blvd. Wethersfield, CT 06109

Date Issued: ______CONNECTICUT DEPARTMENT OF LABOR WAGE AND WORKPLACE STANDARDS DIVISION

CONTRACTORS WAGE CERTIFICATION FORM

I, of Officer, Owner, Authorized Rep. Company Name

do hereby certify that the Company Name

Street

City and all of its subcontractors will pay all workers on the

Project Name and Number

Street and City the wages as listed in the schedule of prevailing rates required for such project (a copy of which is attached hereto).

Signed

Subscribed and sworn to before me this day of , 20 .

Notary Public Return to: Connecticut Department of Labor Wage & Workplace Standards Division 200 Folly Brook Blvd. Wethersfield, CT 06109

[New] In accordance with Section 31-53b(a) of the C.G.S. each contractor shall provide a copy of the OSHA 10 Hour Construction Safety and Health Card for each employee, to be attached to the first certified payroll on the project.

In accordance with Connecticut General Statutes, 31-53 PAYROLL CERTIFICATION FOR PUBLIC WORKS PROJECTS Connecticut Department of Labor Certified Payrolls with a statement of compliance Wage and Workplace Standards Division shall be submitted monthly to the contracting agency. WEEKLY PAYROLL 200 Folly Brook Blvd. Wethersfield, CT 06109 CONTRACTOR NAME AND ADDRESS: SUBCONTRACTOR NAME & ADDRESS WORKER'S COMPENSATION INSURANCE CARRIER

POLICY # PAYROLL NUMBER Week-Ending PROJECT NAME & ADDRESS Date EFFECTIVE DATE: EXPIRATION DATE:

PERSON/WORKER, APPR MALE/ WORK DAY AND DATE Total ST BASE HOURLY TYPE OF GROSS PAY TOTAL DEDUCTIONS GROSS PAY FOR ADDRESS and SECTION RATE FEMALE CLASSIFICATION S M T W TH F S Hours RATE FRINGE FOR ALL FEDERAL STATE THIS PREVAILING CHECK # AND % AND BENEFITS WORK RATE JOB NET PAY RACE* Trade License Type TOTAL FRINGE Per Hour PERFORMED LIST & Number - OSHA Total BENEFIT PLAN 1 through 6 THIS WEEK FICA WITH- WITH- OTHER 10 Certification Number HOURS WORKED EACH DAY O/T Hours CASH (see back) HOLDING HOLDING 1. $ $ 2. $ Base Rate 3. $ 4. $ $ 5. $ Cash Fringe 6. $ 1. $ $ 2. $ Base Rate 3. $ 4. $ $ 5. $ Cash Fringe 6. $ 1. $ $ 2. $ Base Rate 3. $ 4. $ $ 5. $ Cash Fringe 6. $ 1. $ $ 2. $ Base Rate 3. $ 4. $ $ 5. $ Cash Fringe 6. $ 7/13/2009 *IF REQUIRED WWS-CP1 *SEE REVERSE SIDE PAGE NUMBER OF

OSHA 10 ~ATTACH CARD TO 1ST CERTIFIED PAYROLL

*FRINGE BENEFITS EXPLANATION (P):

Bona fide benefits paid to approved plans, funds or programs, except those required by Federal or State Law (unemployment tax, worker’s compensation, income taxes, etc.).

Please specify the type of benefits provided: 1) Medical or hospital care 4) Disability 2) Pension or retirement 5) Vacation, holiday 3) Life Insurance 6) Other (please specify)

CERTIFIED STATEMENT OF COMPLIANCE

For the week ending date of ,

I, of , (hereafter known as

Employer) in my capacity as (title) do hereby certify and state:

Section A: 1. All persons employed on said project have been paid the full weekly wages earned by them during the week in accordance with Connecticut General Statutes, section 31-53, as amended. Further, I hereby certify and state the following: a) The records submitted are true and accurate;

b) The rate of wages paid to each mechanic, laborer or workman and the amount of payment or contributions paid or payable on behalf of each such employee to any employee welfare fund, as defined in Connecticut General Statutes, section 31-53 (h), are not less than the prevailing rate of wages and the amount of payment or contributions paid or payable on behalf of each such employee to any employee welfare fund, as determined by the Labor Commissioner pursuant to subsection Connecticut General Statutes, section 31-53 (d), and said wages and benefits are not less than those which may also be required by contract;

c) The Employer has complied with all of the provisions in Connecticut General Statutes, section 31-53 (and Section 31-54 if applicable for state highway construction);

d) Each such employee of the Employer is covered by a worker’s compensation insurance policy for the duration of his employment which proof of coverage has been provided to the contracting agency;

e) The Employer does not receive kickbacks, which means any money, fee, commission, credit, gift, gratuity, thing of value, or compensation of any kind which is provided directly or indirectly, to any prime contractor, prime contractor employee, subcontractor, or subcontractor employee for the purpose of improperly obtaining or rewarding favorable treatment in connection with a prime contract or in connection with a prime contractor in connection with a subcontractor relating to a prime contractor; and

f) The Employer is aware that filing a certified payroll which he knows to be false is a class D felony for which the employer may be fined up to five thousand dollars, imprisoned for up to five years or both.

2. OSHA~The employer shall affix a copy of the construction safety course, program or training completion document to the certified payroll required to be submitted to the contracting agency for this project on which such employee’s name first appears.

(Signature) (Title) Submitted on (Date)

Section B: Applies to CONNDOT Projects ONLY That pursuant to CONNDOT contract requirements for reporting purposes only, all employees listed under Section B who performed work on this project are not covered under the prevailing wage requirements defined in Connecticut General Statutes Section 31-53.

(Signature) (Title) Submitted on (Date)

Note: CTDOL will assume all hours worked were performed under Section A unless clearly delineated as Section B WWS-CP1 as such. Should an employee perform work under both Section A and Section B, the hours worked and wages paid must be segregated for reporting purposes. ***THIS IS A PUBLIC DOCUMENT*** ***DO NOT INCLUDE SOCIAL SECURITY NUMBERS*** Weekly Payroll Certification For PAYROLL CERTIFICATION FOR PUBLIC WORKS PROJECTS Week-Ending Date: Public Works Projects (Continued) Contractor or Subcontractor Business Name: WEEKLY PAYROLL

PERSON/WORKER, APPR MALE/ WORK DAY AND DATE Total ST BASE HOURLY TYPE OF GROSS PAY TOTAL DEDUCTIONS GROSS PAY FOR ADDRESS and SECTION RATE FEMALE CLASSIFICATION S M T W TH F S Hours RATE FRINGE FOR ALL WORK FEDERAL STATE THIS PREVAILING CHECK # AND % AND BENEFITS PERFORMED RATE JOB NET PAY RACE* Trade License Type TOTAL FRINGE Per Hour THIS WEEK & Number - OSHA Total BENEFIT PLAN 1 through 6 FICA WITH- WITH- OTHER 10 Certification Number HOURS WORKED EACH DAY O/T Hours CASH (see back) HOLDING HOLDING 1. $ $ 2. $ Base Rate 3. $ 4. $ $ 5. $ Cash Fringe 6. $ 1. $ $ 2. $ Base Rate 3. $ 4. $ $ 5. $ Cash Fringe 6. $ 1. $ $ 2. $ Base Rate 3. $ 4. $ $ 5. $ Cash Fringe 6. $ 1. $ $ 2. $ Base Rate 3. $ 4. $ $ 5. $ Cash Fringe 6. $ 1. $ $ 2. $ Base Rate 3. $ 4. $ $ 5. $ Cash Fringe 6. $ *IF REQUIRED 7/13/2009 WWS-CP2 NOTICE: THIS PAGE MUST BE ACCOMPANIED BY A COVER PAGE (FORM # WWS-CP1) PAGE NUMBER OF [New] In accordance with Section 31-53b(a) of the CG.S. each contractor shall provide a copy of the OSHA 10 Hour Construction Safety and Health Card for each employee, to be attached to the first certificd payroll on the project.

I.1.I. $$ 5.80 2 $ xxx.XX$40 xxx.xx Yantic, CT 06389 S-TIME Base Rate EFFECTIVE2. $ DATE:EXPIRATION 1/1/09 DATE: 12/31/09 ANDFEMALEMALE!MISBENEFIT$1,582.80ElectricalBASEProjectElectrical8M888WTIIFSHoursRATEFRINGEFORALLT26212223WITH-WITH-M-xx.x2425xx.xxxxx.xxOTHERSTATEHOLDINGCLASSIFICATIONTradeCASHPERFORMEDTHIS(seeGROSS$1,464.80$1,582.80FICA 1I0URL5.2.WORK ManagerPROJECT3.36.6xx.xx LicenseWORKTYPENET LinemanIPLAN$ back)PerCHECKS$WEEKTHIS$1,464.80 through202.01 HourPAYTOTALDEDUCTIONSGROSSPAY PAYYAPPRFEDERAL65% TypeOFRATE4.I. PREVAILING NAME# 6$#124 AND8'IF8 & REQUIREDADDRESSHOLDINGHOURSApprenticeE-18DAY 1234567Tolal FOR AND WORKEDLISTP-xxxxG-xxx ST Off DATE HouRATETravelersWORKER'S EACH JOB DAY Insurance COMPENSATION CompanyPAYROLL INSURANCEPAGETotalO-TIME NUMBER CARRIERCERTIFICATION#123#125 4. $ WEEKLY FORBENEFITS PUBLIC0- TIME PAYROLLSUBCONTRACTOR$'SEE WORKS REVERSE PROJECTS SIDE NAME & ADDRESS OSHA 234567 xx.xx In accordanceBase RateDOT$1,500.005.2. withTOTAL$ 105-296, Connecticut9/26/09Week-Ending FRINGE Route$ 19.99 General 82 Statutes, 31-53 POLICY # #BAC8888928 20040 Foil)' Brook 81vd. Connecticut DepartmentXYZ Corporation of Labor Wage and Workplace Standards Division WWS-CPI234 Washington Rd.212 Elm Street Willimantic,Ronald Jones CT 06226 Norwich,New london.M/CMIH CT 06360 CT O-TIME 8 OF ;:L OSHA 123456 $ $xxx.xx $ 30.75 81 Maple Street ADDRESS%RACE' and SECTIONCONTRACTORPA NAME YROLL AND NUMBER ADDRESS:&10Number Certification - OSHANumber 7/13/2009 Wethersfield,$ 8.82 CT 06109 I SECTION B Certifiedshall bePayrolls submitted1 with monthl}'Owner a statement to the of contracting compliance agency. 06320 Date 2 Main Street O-TIMES-TIME CashBase$$ 16.63 RateFringeFrinl.!e Robert Craft landon Corporation. 15 Connecticut Avenue,Franklin Northford, T. Smith CT 06472 PERSON/WORKER,

OSHA 10 -ATIACH CARD TO 1ST CERTIFIED PAYROLL *FRINGE BENEFITS EXPLANATION (P):

Bona fide benefits paid to approved plans, funds or programs, except those required by Federal or State Law (unemployment tax, worker's compensation, income taxes, etc.).

Please specify the type of benefits provided: 1) Medical or hospital care Blue Cross 4) Disability _ 2) Pension or retirement 5) Vacation, holiday _

3) Life Insurance Utopia 6) Other (please specify) _

CERTIFIED STATEMENT OF COMPLIANCE

For the week ending date of------' 9/26/09

I, Robert Craft of XYZ Corporation , (hereafter known as

Employer) in my capacity as Owner (title) do hereby certify and state:

Section A: I. All persons employed on said project have been paid the full weekly wages earned by them during the week in accordance with Connecticut General Statutes, section 31-53, as amended. Further, I hereby certify and state the following: a) The records submitted are true and accurate;

b) The rate of wages paid to each mechanic, laborer or workman and the amount of payment or contributions paid or payable on behalf of each such employee to any e'mployee welfare fund, as defined in Connecticut General Statutes, section 31-53 (h), are not less than the prevailing rate of wages and the amount of payment or contributions paid or payable on behalf of each such employee to any employee'welfare fund, as determined by the Labor Commissioner pursuant to subsection Connecticut General Statutes, section 31-53 (d), and said wages and benefits are not less than those which may also be required by contract;

c) The Employer has complied with all of the provisions in Connecticut General Statutes, section 31-53 (and Section 31-54 if applicable for state highway construction);

d) Each such employee of the Employer is covered by a worker's compensation insurance policy for the duration of his employment which proof of coverage has been provided to the contracting agency;

e) The Employer does not receive kickbacks, which means any money, fee, commission, credit, gift, gratuity, thing of value, or compensation of any kind which is provided directly or indirectly, to any prime contractor, prime contractor employee, subcontractor, or subcontractor employee for the purpose of improperly obtaining or rewarding favorable treatment in connection with a prime contract or in connection with a prime contractor in connection with a subcontractor relating to a prime contractor; and

f) The Employer is aware that filing a certified payroll which he knows to be false is a class D felony for which the employer may be fined up to five thousand dollars, imprisoned for up to five years or both.

2. OSHA-The employer shall affix a copy of the construction safety course, program or training completion document to the certified payroll required to be submitted to the contracting agency for this project on which such employee's name first appears.

ow~ /o/~-) t/ Cj ~~~(Signature) , (Title) Submitte6 on (.Date)

Section B: Applies to CONNDOT Projects ONLY That pursuant to CONNDOT contract requirements for reporting purposes only, all employees listed under Section B who performed work on this project are not covered under the prevailing wageRquirements defined in Connecticut General Statutes Section 31-53. o u/I.../e; "• (Title)

Note: CTDOL will assume all hours worked were performed under Section A unless clearly delineated as Section B WWS-CP I as such. Should an employee perform work under both Section A and Section B, the hours worked and wages paid must be segregated for reporting purposes. ***THIS IS A PUBLIC DOCUMENT*** ***DO NOT INCLUDE SOCIAL SECURITY NUMBERS*** Information Bulletin Occupational Classifications

The Connecticut Department of Labor has the responsibility to properly determine "job classification" on prevailing wage projects covered under C.G.S. Section 31-53.

Note: This information is intended to provide a sample of some occupational classifications for guidance purposes only. It is not an all-inclusive list of each occupation's duties. This list is being provided only to highlight some areas where a contractor may be unclear regarding the proper classification.

Below are additional clarifications of specific job duties performed for certain classifications:

ASBESTOS WORKERS

Applies all insulating materials, protective coverings, coatings and finishes to all types of mechanical systems.

ASBESTOS INSULATOR

Handle, install apply, fabricate, distribute, prepare, alter, repair, dismantle, heat and frost insulation, including penetration and fire stopping work on all penetration fire stop systems.

BOILERMAKERS

Erects hydro plants, incomplete vessels, steel stacks, storage tanks for water, fuel, etc. Builds incomplete boilers, repairs heat exchanges and steam generators.

BRICKLAYERS, CEMENT MASONS, CEMENT FINISHERS, MARBLE MASONS, PLASTERERS, STONE MASONS, PLASTERERS. STONE MASONS, TERRAZZO WORKERS, TILE SETTERS

Lays building materials such as , structural tile and concrete cinder, glass, gypsum, terra cotta block. Cuts, tools and sets marble, sets stone, finishes concrete, applies decorative steel, aluminum and plastic tile, applies cements, sand, pigment and marble chips to floors, stairways, etc.

Connecticut Department of Labor Wage and Workplace Standards Division FOOTNOTES

Please Note: If the “Benefits” listed on the schedule for the following occupations includes a letter(s) (+ a or + a+b for instance), refer to the information below.

Benefits to be paid at the appropriate prevailing wage rate for the listed occupation.

If the “Benefits” section for the occupation lists only a dollar amount, disregard the information below.

Bricklayers, Cement Masons, Cement Finishers, Concrete Finishers, Stone Masons (Building Construction) and (Residential- Hartford, Middlesex, New Haven, New London and Tolland Counties)

a. Paid Holiday: Employees shall receive 4 hours for Christmas Eve holiday provided the employee works the regularly scheduled day before and after the holiday. Employers may schedule work on Christmas Eve and employees shall receive pay for actual hours worked in addition to holiday pay.

Elevator Constructors: Mechanics

a. Paid Holidays: New Year’s Day, Memorial Day, Independence Day, Labor Day, Veterans’ Day, Thanksgiving Day, Christmas Day, plus the Friday after Thanksgiving.

b. Vacation: Employer contributes 8% of basic hourly rate for 5 years or more of service or 6% of basic hourly rate for 6 months to 5 years of service as vacation pay credit.

Glaziers a. Paid Holidays: Labor Day and Christmas Day.

Power Equipment Operators (Heavy and Highway Construction & Building Construction)

a. Paid Holidays: New Year’s Day, Good Friday, Memorial day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day, provided the employee works 3 days during the week in which the holiday falls, if scheduled, and if scheduled, the working day before and the working day after the holiday. Holidays falling on Saturday may be observed on Saturday, or if the employer so elects, on the preceding Friday.