Council Paper No. IDC 03/2019

Progress Report of Major Projects in Islands District

Civil Engineering and Development Department Sustainable Lantau Office February 2019 Progress Report of Major Projects in Islands District (as at 31 Dec 2018)

Contents Page

(1) Objectives 2 (2) Community Facilities Works 3 (3) Port and Reclamation Works 9 (4) Roads Works 13 (5) Drainage Works 20 (6) Water Works 29 (7) Others 31 (8) Appendix – Location Plan of some major works in Islands District

(1) Objectives

(i) This report contains project information provided by relevant government departments up to 31 Dec 2018.

(ii) Projects include

 Items completed from 1 Jan 2018 to end 2018;

 Items in progress; and

 Items expected to commence in /after 2019.

ArchSD: Architectural Services Department SDEV: Secretary for Development CEDD: Civil Engineering and Development Department SEN: Secretary for Environment DSD: Drainage Services Department STH: Secretary for Transport and Housing EDB: Education Bureau WSD: Water Supplies Department HyD: Highways Department Page 2

(2) Community Facilities Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

464RO Improvement 72.30 SDEV 07/2016 02/2019 This project was part-upgraded from 414RO in works at – June 2016 for construction of the proposed A CEDD Phase 2 Stage 1 Improvement works at Mui Wo, Phase 2 Stage 1 which include the following – (a) realignment of a section of Mui Wo Ferry Pier Road and extension of existing car parking area and; (b) ancillary works including geotechnical, landscaping, drainage and utility works.

. Works commenced in July 2016 The proposed

extension of car park and Mui Wo Ferry Pier Road would be completed in February 2019.

Page 3

(2) Community Facilities Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

414RO Improvement under SDEV under review under review This project comprises the works at Mui Wo – review remaining works of the proposed B CEDD Remaining Phases Improvement works at Mui Wo, Phase 2 Stage 2 and Phase 3 works including reprovisioning of cooked food market, beautification of the south waterfront promenades and entrance plaza; and improvement of existing cycle tracks.

Based on the views collected from

the public engagement activity held in March 2017, the review of the layout for the improvement works is nearly completed. The next round of

public engagement exercise for consultation of the revised layout would be conducted after the

consultation with Mui Wo Rural Committee and local Islands DC members later. The implementation programme is under review.

Page 4

(2) Community Facilities Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing Cat. ($M) Dept/ (M/Yr) (M/Yr) Organization The project aims at implementing the remaining phases of Improvement Works at , which comprise Phase 2 Stage 1, Phase 2 Stage 2 and remaining works.

469RO Improvement works 124.00 SDEV 9/2016 12/2019 Improvement Works at Tai O, Phase 2 Stage A at Tai O (Phase 2 CEDD 1 comprises the construction of a public open space, a public transport terminus, a Stage 1) public car park, a loading and unloading area, a cycle parking area and ancillary

works. It aims to enhance traffic and pedestrian circulation and provide additional parking spaces at Tai O. Construction of Phase 2 Stage 1 works commenced in September 2016 for completion in end 2019.

Improvement works at Tai O, Phase 2 Stage Improvement Works at Tai O, Phase 2 Stage 1 417RO Improvement works Under SDEV Under Under 2 mainly cover two proposed footbridges for B at Tai O (Phase 2 Review CEDD Review Review improving local connectivity. Consultants Stage 2 and has been employed for the detailed design remaining works) and the design of Phase 2 Stage 2 works is in progress. Improvement Works at Tai O, remaining works mainly cover works for improving facilities to help preserve the heritage and facilitate visitors’ appreciation

of natural attributes of Tai O and the scope

of works is under review.

Improvement Works at Tai O, Phase 2 Stage 2

Page 5

(2) Community Facilities Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

5101CX Greening Master 18.10 SDEV 2012 2015 The scope of works includes formulation of Plan (GMP)s of the (formulation) (formulation) the GMPs of SWNT (including Islands, Tsuen 5G66CG (including CEDD South West New Wan and Kwai Tsing) and the detailed design the cost on D Territories (SWNT) – and necessary site investigation for the Islands, 2015 2017 Consultancy Study & greening measures. Tsuen Wan Site Investigation (detailed (detailed and Kwai design) The relevant GMP proposal was submitted to design) Tsing) the Islands Tourism, Agriculture, Fisheries and Environmental Hygiene Committee on 30 September 2013 for consultation, and support was received from the Committee on the implementation of the GMP works.

The Consultants’ detailed design has completed and the funding process has commenced. Upon funding available, GMP Focal Area established procedures would be followed for tendering and works implementation.

Cheung Chau GMP Focal Area

Page 6

(2) Community Facilities Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

Peng Chau and GMP Focal Areas

5101CX Landscape 17.8M SDEV 1/2018 9/2018 The scope of works includes planting of around 400 numbers of cherry trees and spring- 5J71CG Improvement Works [ cost CEDD flowering trees in and associated included construction works. in Ngong Ping tree planting, Tree planting works were completed in the 3rd establishme quarter of 2018. We are now carrying out tree nt works establishment works. and associated civil works]

Page 7

(2) Community Facilities Works Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing Cat. ($M) Dept/ (M/Yr) (M/Yr) Organization

111ET A Special School for 334.7 EDB/ArchSD 6/2017 9/2019 The scope of works includes the construction of students with mild, a Special School for students with mild, A moderate and severe moderate and severe intellectual disabilities in intellectual Area 108, Tung Chung with 18 classrooms, a disabilities in Area 60-place boarding section and ancillary 108, Tung Chung facilities.

Page 8

(3) Port and Reclamation Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization The proposed Tung Chung New Town 799CL Tung Chung New 729.5 SDEV 06/2016 03/2021 Extension (TCNTE) will cover areas on the Town Extension – A CEDD Detailed Design and eastern and western flanks of the existing Tung Chung New Town. It will provide about 49,600 Site Investigation residential flats for a population of about

814CL Tung Chung New 20,210.0 145,500. Town Extension – 12/2017 12/2023

A Reclamation and The reclamation and advance works Advance Works commenced in Dec 2017. The detailed design for site formation and infrastructure works are

786CL Tung Chung New under in progress. under review under review Town Extension – review Tung Chung East Extension Area B Site formation and Infrastructure Works

Tung Chung West Extension Area

Page 9

(3) Port and Reclamation Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

737CL Dredging, 344.15 SDEV 09/2012 12/2018 The project comprises formation of 2 sediment management and A CEDD disposal pits at the seabed to the south of The capping of Brothers for the disposal of about 4 million contaminated cubic metres sediment; on-site control of mud

sediment disposal disposal activities; and implementation of an facility to the south Environmental Monitoring and Audit (EM&A) Site programme. of The Brothers All the disposal and capping works at the 2 sediment disposal pits were completed in early and end 2016 respectively whereas the

EM&A continued until end 2018. (From March 2016 onward, the contaminated sediment generated from works projects was disposed of at the existing sediment disposal pits to the East of Sha Chau under Project No.729CL.)

Works were completed in Dec 2018.

Page 10

(3) Port and Reclamation Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing Cat. ($M) Dept/ (M/Yr) (M/Yr) Organization

5101CX Study for Pier 9.15 SDEV 11/2017 First Quarter of The scope of the Study comprises: Improvement at Yung 2019 (i) Assessment of the potential environmental D Shue Wan, Shek Tsai CEDD impact including ecological and fisheries Wan, Yi O and Ma impact, and carrying out preliminary Wan Chung - environmental study; Investigation (ii) Preliminary engineering studies including hydraulic study and geotechnical appraisal, and preparation of preliminary engineering layouts; (iii) Site investigation works and associated supervision; and (iv) Stakeholder consultation.

Current Status The Consultants are preparing the preliminary environmental study and the preliminary engineering layouts. The initial stakeholder consultation with relevant stakeholders is being conducted and Islands District Council will be consulted at appropriate time.

The project aims to reconstruct the Pak Kok Pier on 5051TF Reconstruction of Pak Under STH Second half of Second half of Lamma Island. Kok Pier on Lamma review 2019 2021 B CEDD Island Planning and design of the proposed works is in

progress.

The project was gazetted under the Foreshore and Sea-bed (Reclamations) Ordinance (Cap. 127) on 30 November 2018.

Page 11

(3) Port and Reclamation Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing Cat. ($M) Dept/ (M/Yr) (M/Yr) Organization

5768CL Studies Related to (The item SDEV (The item was (The item was We will focus on the studies for developing Artificial Islands in was withdrawn at the withdrawn at the artificial islands of about 1 000 hectares B CEDD the Central Waters withdrawn PWSC meeting the PWSC near . This scale is similar to that of the East Lantau Metropolis mentioned in at the on 26.11.2014. meeting on the respective public engagement documents

PWSC The 26.11.2014. The of the Task Force on Land Supply and Hong meeting on implementation implementation Kong 2030+. As for the remaining artificial 26.11.2014. programme of programme of islands of about 700 hectares near Hei Ling The this item is under this item is Chau and the waters south of , the studies will collect technical data for estimated review.) under review.) future reference in long-term planning, and

cost of this there is no concrete implementation timetable item is at the moment. The Government will take under into account the findings in the final report submitted by the Task Force on Land Supply review.) to the Government at the end of 2018 before firming up the details of the proposed studies.

Page 12

(4) Road Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing Cat. ($M) Dept/ (M/Yr) (M/Yr) Organization

781CL Infrastructural 284.80 STH 11/2017 12/2020 The project is to provide supporting Works for infrastructure works for housing A CEDD Development in development in Tung Chung Area 54. Area 54, Tung Amenity area, including footpath and cycle Chung track to the north of Ying Hei Road, would also be provided. The works commenced in November 2017 and were expected to be completed in 2 stages. At the 1st stage, the proposed improvement works for the junction of Ying Hei Road and Tung Chung Waterfront Road and construction of footpaths, a cycle track, a cycle parking area, amenity areas and bus lay-bys to the north of Ying Hei Road were anticipated to be completed in mid 2019. At the 2nd stage, the rest of the works including construction of the proposed roadworks and sewerage works were anticipated to be completed in end 2020.

Page 13

(4) Road Works

Head of

Item No Estimated Bureau & Commenceme Completion & Title Cost responsible nt Date Date (M/Yr) Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) Organization

844TH – 25,047.20 STH 05/2012 Hong Kong- The project mainly involves the design Zhuhai – Macao Zhuhai-Macao and construction of the Hong Kong – A HyD Bridge Hong Kong Bridge Hong Kong Zhuhai – Macao Bridge Hong Kong Link Link Road was Road. Link Road opened to the public on 24 October Two Design and Build contracts 2018. commenced on 31 May 2012.

Page 14

(4) Road Works

Head of

Item No Estimated Bureau & Commenceme Completion & Title Cost responsible nt Date Date (M/Yr) Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) Organization Hong Kong-Zhuhai- The project mainly involves reclamation

845TH Hong Kong – 35,895.00 STH 11/2011 Macao Bridge Hong and construction of infrastructures for Zhuhai – Macao A HyD Kong Boundary Hong Kong – Zhuhai – Macao Bridge Bridge Hong Kong Crossing Facilities Hong Kong Boundary Crossing Facilities Boundary Crossing were opened to the (HKBCF). Facilities – public on 24 October 2018. reclamation and The HKBCF reclamation works commenced on 30 November 2011. For infrastructures the superstructure works, the traffic control and surveillance system contract, the passenger clearance building contract, the infrastructure works stage 1 (western portion) contract, the infrastructure works stage 2 (southern

portion) contract, the vehicle clearance plazas and ancillary buildings and facilities contract, and the automatic

vehicle clearance support system contract commenced in January 2014, April 2014, July 2014, March 2015, April 2015 and August 2015 respectively. The

gantry type X-ray vehicle inspection system contract and the remaining ancillary buildings and facilities contract

also commenced in December 2015.

Page 15

(4) Road Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

846TH Tuen Mun – Chek 1,909.60 STH 11/2011 Under Review The project mainly involves reclamation for Lap Kok Link – the southern landfall of the Tuen Mun – Chek A HyD detailed design, site Lap Kok Link (TM-CLKL) subsea tunnel (i.e. investigation and advance works) and engaging consultants to advance works undertake the detailed design and associated site investigation for the remaining works of TM-CLKL (i.e. the works excluding the advance works).

The advance works had been taken forward as the same works together with the reclamation of the artificial island of HKBCF and commenced on 30 November 2011. The associated site investigation was completed in November 2013.

Page 16

(4) Road Works

Head of

Item No Estimated Bureau & Commencement Completion Photo/Drawing & Title Cost responsible Date Date Scope of Works/ Notes Cat. ($M) Dept/ (M/Yr) (M/Yr) Organization The project mainly involves construction of Tuen Mun – 857TH Tuen Mun – Chek 44,798.40 STH 06/2013 First half of Link (TM-CLKL). TM-CLKL comprises Lap Kok Link – 2019 Southern Connection and Northern Connection, which is a A HyD construction works (Remaining dual 2-lane of approximately 9 km long carriageway. The works of the Southern Connection will connect North Lantau Highway Southern (NLH) at Tai Ho and Hong Kong – Zhuhai – Macao Bridge Connection) Hong Kong Port (HKP) while Northern Connection will link the HKP and Tuen Mun.

The viaducts of Southern Connection linking Hong Kong 2020 at the Port with the urban bound and Tung Chung bound of North earliest Lantau Highway was opened to the public on 24 October (Northern 2018 and 30 November 2018 respectively. The remaining Connection) works is anticipated to be completed by the first half of 2019. Based on the present situation, the Northern Connection is anticipated to be completed in 2020 at the earliest.

The Northern Connection comprises mainly the toll plaza, sub-sea tunnel section, tunnel building, associated E&M works, and traffic control and surveillance system (TCSS). With regard to the toll plaza in Tuen Mun Area 46, site formation, construction of land viaducts, footbridge spanning across the toll plaza and vehicular underpass are mostly completed while the roadworks and sewerage works at Lung Mun Road and Lung Fu Road and construction of retaining wall are in progress. The excavation works, from the reclamation just east of Tuen Mun Rivper Trade Terminal to the Hong Kong Port, by large tunnel boring machines (TBMs) for the sub-sea tunnel section of about 5 km long were completed. The installation of precast units within the tunnel and the construction of cross passages by small TBMs between the tunnel tubes are in progress. The construction of north ventilation building on the Northern Landfall at Tuen Mun is substantially completed. The construction of the cut- and-cover tunnel section at the Hong Kong Port artificial island also commenced. The last two construction contracts on tunnel buildings, E&M works and TCSS were both commenced in May 2018.

Page 17

(4) Road Works

Head of Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing Cat. ($M) Dept/ (M/Yr) (M/Yr) Organization

6850TH New Wang Tong Under STH 2020-Q1 2024-Q1 The Project mainly comprises the River Bridge review construction of a twin-bridge of B HyD (If Finance (If Finance Committee of Committee of approximately 35m long across Wang Legislative Legislative Tong River at Silver Mine Bay in Mui Council Council Wo, comprising a footpath and a cycle (LegCo) (LegCo) track with clear widths of 2.0m and 3.5m approves approves respectively to replace the existing funding in funding in 2018-19 2018-19 footbridge. LegCo LegCo The project is under detailed design stage. session) session) Gazette notice under Roads (Works, Use and Compensation) Ordinance (Cap. 370) was published on 23 November 2018 with the objection period ending on 22 January 2019.

Page 18

(4) Road Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawi Cat. ($M) Dept/ (M/Yr) (M/Yr) ng Organization

6101TX Provision of 118.00 STH 11/2015 06/2019 The project aims to provide lift facilities for the Universal Access following three public footbridges/subway in D CEDD Facilities at Public Islands district: Footbridges, i. Footbridge across Yu Tung Road and Chung Elevated Walkways Yan Road (Structure No. NF328); & Subways Package ii. Footbridge across Yu Tung Road near Tung 2 – Investigation, Chung Ha Ling Pei (Structure No. Design and NF332); and Construction iii. Pedestrian subway across Shun Tung Road near Lantau North Divisional Police Station (Structure No. NS230). The project commenced in November 2015 and the progress of works is as follows:- Structure No.of Completion Progress of No. Lifts Date Works NF328 3 2019 Lift 1:Lift car Second installation in progress. Quarter Lift 2:Opened for (Targeted) public use in November 2018. Lift 3:Lift shaft construction and underground utilities diversion in progress. NF332 2 August Lift 1:Opened for 2018 public use in August (Actual) 2018. Lift 2:Opened for public use in August 2018. NS230 2 2019 First Lift 1:Opened for Quarter public use in October (Targeted) 2018. Lift 2:Preparation for lift car installation and associated electrical and mechanical works in progress.

Page 19

(5) Drainage Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing Cat. ($M) Dept/ (M/Yr) (M/Yr) Organization

387DS Upgrading of Mui 967.20 SEN 07/2012 04/2018 The project mainly comprises upgrading of the Wo sewage treatment existing Mui Wo Sewage Treatment Works and A works and sewerage DSD about 2km of existing trunk sewers at town at Mui Wo town centre, and construction of sewers for two centre and Wang unsewered areas (Wang Tong and Yue Kwong Tong Chuen) in Mui Wo. The works were substantially completed in April 2018.

Page 20

(5) Drainage Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

397DS Outlying Islands 340.20 SEN 12/2013 09/2018 The project mainly comprises construction of sewerage stage 2 – about 9km long sewers in 13 unsewered areas A Lamma village DSD (Sha Po New Village, Sha Po Old Village, sewerage phase 2, Yung Shue Wan Back Street, Tai Shan West, package 1 Tai Shan East, Tai Shan Central, Ko Long (portion), Tai Yuen Village (portion), O Tsai, Po Wah Yuen, Yung Shue Long New Village, Yung Shue Long Old Village and Tai Peng) in Yung Shue Wan of Lamma Island.

The project was completed in September 2018.

381DS Construction of 1,362.60 SEN 08/2016 Phase 1 The project comprises the construction of additional sewage (new rising additional sewage rising mains, rehabilitation A DSD rising mains and main) of the existing sewage rising main and rehabilitation of the modification of related facilities between Tung 06/2023 existing sewage Chung and Siu Ho Wan. rising main between Phase 2 Phase 1 works commenced in August 2016. Tung Chung and Siu (rehabilitation The works are in progress and about 33% Ho Wan of existing completed. rising main)

12/2025

Page 21

(5) Drainage Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

163CD Drainage Under SDEV 2019Q4 2022Q1 The project comprises construction of about improvement works review 900m long drains and box culverts at the B at Ngong Ping DSD northern side of and Terminal in order to relieve the potential flood risk in Ngong Ping area. Detailed design of the project is in progress.

Page 22

(5) Drainage Works

Head of Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

422DS Outlying Islands 133.70 SEN 2018Q4 2022Q4 The project aims at providing a public sewage sewerage stage 2 – collection system for the unsewered areas in DSD in order to improve the water A Peng Chau village sewerage phase 2 quality of nearby watercourses and the hygiene package 1 condition of six unsewered areas (Nam Wan (formerly San Tsuen, Tai Yat San Tsuen (part), Wai Tsai Tseng San Tsuen, Central Peng Chau, Nam 343DS-1) Wan Shan Ting Tsuen, and Tung Wan Village (part). Construction works commenced in November 2018.

Page 23

(5) Drainage Works Head of Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing Cat. ($M) Dept/ (M/Yr) (M/Yr) Organization

343DS-2 Outlying Islands Under SEN 2020Q4 2023Q4 The project aims at providing a public sewage B sewerage stage 2 – review collection system for the unsewered areas in Peng Chau village DSD sewerage phase 2 Peng Chau in order to improve the water remaining works quality of nearby watercourses and the hygiene condition of five unsewered areas (Shan Ting Tsuen, Tai Lung Tsuen, Wai Tsai Tsuen, Tai Yat San Tsuen (remaining part) and Tung Wan Village (remaining part)).

Detailed design of the project is in progress.

353DS Outlying Islands Under SEN 2019Q4 2024Q2 The project mainly comprises the provision of sewerage stage 2 – review sewers at unsewered areas in Mui Wo. B extension of DSD Detailed design of the project is in progress. sewerage system to other unsewered villages in Mui Wo

Page 24

(5) Drainage Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing Cat. ($M) Dept/ (M/Yr) (M/Yr) Organization

354DS-1 Outlying Islands Under review SEN 2019Q4 2025Q1 The project mainly comprises upgrading the sewerage stage 2 – sewage treatment facilities at the existing B DSD upgrading of Cheung Cheung Chau sewage treatment works and the Pak She sewage pumping station. Chau sewage treatment and disposal facilities Detailed design of the project is in progress.

354DS -2 Outlying Islands Under review SEN 2021Q1 2025Q4 The project mainly comprises the provision of sewerage stage 2 – public sewerage for the unsewered areas in B DSD upgrading of Tai O Cheung Chau and Tai O, and upgrading the sewage treatment facilities at the existing Tai sewage disposal and O sewage treatment works. treatment facilities

and sewage Detailed design of the project is in progress. collection facilities for Tai O and Cheung Chau

Page 25

(5) Drainage Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing Cat. ($M) Dept/ (M/Yr) (M/Yr) Organization

355DS Outlying Islands Under SEN 2020Q3 2025Q2 The project mainly comprises the provision of sewerage stage 2 – review public sewerage for seven unsewered areas (Tai B Lamma village DSD Yuen Village (portion), Ko Long (portion), sewerage phase 2, Wang Long, Tai Wan San Tsuen, Tai Wan Kau package 2 Tsuen, Long Tsai Tsuen and Hung Shing Ye) in Yung Shue Wan and construction of two sewage pumping stations. Detailed design of the project is in progress.

Page 26

(5) Drainage Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

331DS-1 Construction of San Under review SEN 2019Q4 2024Q4 The project aims at providing public sewerage B Shek Wan sewage at South Lantau. It mainly comprises the treatment works, DSD construction of a secondary sewage treatment associated submarine works at San Shek Wan with associated outfall and Pui O submarine outfall, trunk sewer from Pui O to sewerage works , village sewers at Lo Uk and a sewage pumping station at Pui O

Detailed design of the project is in progress.

331DS-2 Outlying Islands Under review SEN 2021Q2 2026Q3 The project aims at providing public sewerage Sewerage Stage 2 – at South Lantau. It mainly comprises the B South Lantau DSD construction of trunk and village sewers, Sewerage Works at Shui Hau, Tong Fuk, Cheung Sha, San (Remaining Works) Shek Wan, Pui O and Ham Tin. Detailed design is in progress.

Page 27

(5) Drainage Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

426DS Rehabilitation of 514.70 SEN 01/2019 2022Q4 The projects comprise 110 km of condition underground sewers survey and about 18 km of rehabilitation of the A stage 1 (7.00 for DSD underground sewers and stormwater drains Islands over the territory. Among these, the proposed and District) works in Islands District comprises condition 180CD Rehabilitation of survey of about 700 m and rehabilitation of A underground SDEV about 400 m of underground sewers and stormwater drains stormwater drains. stage 1 DSD Construction works will commence in January 2019

Page 28

(6) Water Works

Head of Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing Cat. ($M) Dept/ (M/Yr) (M/Yr) Organization

356WF Uprating of Tung 300.20 SDEV 12/2017 2020Q3 This project comprises construction of Tung Chung fresh water Chung No.2 Fresh Water Service Reservoir A WSD supply system with a capacity of approximate 40,000 m3 and connection of proposed Tung Chung No. 2 Fresh Water Service Reservoir to existing fresh water distribution network.

Advance works commenced in December 2017 whereas Contract No. 4/WSD/17 commenced in February 2018 and is anticipated to be completed in 2020.

Page 29

(6) Water Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

9100WX Uprating of Cheung Under SDEV 2019Q1 2020Q4 The project comprises uprating of Cheung Sha Sha Water Treatment review water treatment works from its nominal output D WSD Works of 6,000 cu.m. to 7,500 cu.m per day. The works will involve addition, modification and/or retrofitting of water treatment units, and associated civil, structural, geotechnical, mechanical and electrical works within the existing WSD’s Land Allocation for Cheung Sha Water Treatment Works. Besides, mainlaying of 1.6km length along South Lantau Road is included to meet fire-fighting flow

requirement.

365WF Siu Ho Wan Water Under SDEV 2021Q3 2025Q4 The project comprises expansion of the Siu Ho Treatment Works Wan Water Treatment Works to increase its review WSD B Extension water treatment capacity from 150,000 m3 per day to 300,000 m3 per day, and corresponding increase in the transfer capacity of the associated raw water supply systems.

The investigation study, design and associated site investigation works for the project commenced in August 2018.

Page 30

(7) Others

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

7100CX Planning & 29.90 SDEV 01/2012 2019 The study includes the formulation of various land 7D67CL Engineering Study use options for the ex-Lamma Quarry at Sok Kwu PlanD on Future Land Use Wan in Lamma Island, and the related planning and engineering study as well as environmental impact D at Ex-Lamma Quarry & assessment. Area – Feasibility CEDD Study For formulating the development mode, the Government is actively considering making use of private developers’ capacity in providing infrastructure and ancillary facilities for the development. The “Market Sounding Out and Invitation for Development Proposal Exercise for Development at Ex-Lamma Quarry Area at Sok Kwu Wan, Lamma Island” (the Exercise) was completed.

Taking into account the findings of the Exercise,

different land use initiatives, implementation

arrangement of infrastructure and land uses, cost effectiveness of the development as well as the views collected in previous two stage Community Engagement, the Government will consider the way

forward of the ex-Lamma Quarry development and the associated follow up actions.

Page 31

(7) Others

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

770CL Planning, 63.40 SDEV 01/2015 Under review The project comprises a planning, engineering and engineering and architectural study for the proposed commercial PlanD architectural study development and the development of other economic activities at the Hong Kong boundary A for topside & crossing facilities (HKBCF) island of Hong Kong- development at Hong CEDD Zhuhai-Macao Bridge (HZMB) and the associated Kong boundary site investigation works. crossing facilities island of Hong Pursuant to the 2018 Policy Address, the

Kong-Zhuhai-Macao Government has invited the Airport Authority Bridge Hong Kong to submit a proposal for the topside development at the HKBCF Island.

Page 32

(7) Others

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

7E38RG Preliminary 18.00 SDEV 07/2015 01/2019 The project comprises engineering studies to assess Feasibility Study of the preliminary technical feasibility and financial 7E34RG viability of constructing a cable car system from Cable Car System Ngong Ping to Tai O, and spa and resort D CEDD from Ngong Ping To development at Cheung Sha and . Tai O, and Spa and

Resort Development at Cheung Sha and

Soko Islands - Feasibility Study Cable Car System from Ngong Ping To Tai O Study

Spa and Resort Development at Soko Islands Study

Spa and Resort Development at Cheung Sha Study

Page 33

(7) Others

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

5290RS Expansion of 41.63 SDEV 12/2016 06/2019 The project comprises construction of new Mountain Bike Trail mountain bike trails (MBTs) and training A CEDD Networks in Mui facilities in South Lantau, which includes: Wo and Chi Ma (i) a new training ground, with MBTs for Wan, South Lantau different skill level requirements and attractive technical features, to be located at a hill top near Lai Chi Yuen Tsuen;

(ii) new MBTs to connect the existing Chi Ma Wan trails to form a loop network; and

(iii) a gathering place at Mui Wo trail head near Mui Wo Ferry Pier Road with Expansion of Mountain Bike Trail Networks in Mui Wo and Chi supporting facilities, such as Ma Wan, South Lantau – Location Plan information/educational kiosks as well as new MBTs connecting the Mui Wo trail head and the new training ground

Part of the construction works commenced in end 2016. The main works contract also commenced in November 2017 for completion by mid 2019.

Proposed Training Ground at a Hilltop near Lai Chi Yuen Tsuen

Page 34

(7) Others Head of

Item No Estimated Bureau & Commencement Completio & Cat. Title Cost responsible Date (M/Yr) n Date Scope of Works/ Notes Photo/Drawing ($M) Dept/ (M/Yr) Organization

5001BX Landslip 1,035 SDEV 2010 On-going Landslip Prevention and Mitigation (LPMit) Prevention and (Estimated works for 130 man-made slopes and 16 natural Mitigation D Programme expenditur CEDD hillside study areas in Islands District were (LPMitP) e for completed. Financial Year The LPMit works for 15 man-made slopes and 8 2018/19) natural hillside study areas in Islands District are in progress.

The details of man-made slopes are:  4 Slopes Nos. 10SW-C/C318 , 10SW-C/C321 , 10SW-C/C322 and 10SW-C/CR320 at Tung Wan Tau Road, ;  1 Slope No. 9SE-C/C97 at Tei Tong Tsai, Lantau Island;  1 Slope No. 10SW-B/CR346 at Cheung Sha Lan Village, Lantau Island;  1 Slope No. 10SW-C/C269 at Wang Tong, Lantau Island;  1 Slope No. 13NE-A/R28 at Tong Fuk Village, Lantau Island;  1 Slope No. 13NE-B/R6 at Cheung Sha Sheung Tsuen, Lantau Island;  1 Slope No. 13NW-B/C329 at Keung Shan Road, Lantau Island;  1 Slope No. 14NW-C/CR93 at Yi Long Wan, Lantau Island;  1 Slope No. 14NE-B/R31 at Pak Kok Kau Tsuen, Lamma Island;  1 Slopes Nos. 14NE-B/R68 and at Sha Po New Village, Lamma Island;  1 Slope No. 14NW-D/R172 at Nam She Tong, Cheung Chau; and  1 Slope No. 14NW-D/R217 at Ko Shan Tsuen, Cheung Chau.

Page 35

(7) Others Head of

Item No Estimated Bureau & Commencement Completion & Cat. Title Cost responsible Date (M/Yr) Date Scope of Works/ Notes Photo/Drawing ($M) Dept/ (M/Yr) Organization

The details of natural hillside study areas are:  1 Study Area No. 13NW-B/SA6 near Keung Shan Road, Lantau Island;  3 Study Areas No. 10SW-A/SA1 , 10SW-A/SA2 and 10SW-C/SA1 near Wang Tong, Lantau Island;  1 Study Area No. 13NW-B/SA4 near , Lantau Island;  1 Study Area No. 9SW-D/SA7 near Luk Wu, Lantau Island;  1 Study Area No. 15NW-C/SA2 near Sok Kwu Wan, Lamma Island; and  1 Study Area No. 15NW-A/SA2 near Lo Tik Wan, Lamma Island.

CEDD plan to commence the LPMit works for another 29 man-made slopes and 4 natural hillside study areas in Islands District in the coming year. The works are scheduled to commence in the 1st Quarter of 2019 and they will be completed by end of 2020.

Page 36 SM U GG LE ( RS ' M a R ID Ts GE z SHA TIN K Sun Chui So Kwun en Siu Lam g SIU LANG ) HEIGHTS Estate Tan TAI LAM CHUNG Yau Kom Tau Tin Sam SHUI 5 D 1 A 5 P O ip TSUEN WAN R e R C l Kwai Chung Ting Kau in R PO e GOLDEN HILL Kak Tin 2 Estate I A SIU LAM SHAM TSENG T PEARL ISLAND R D 10 OA 10 R P 770CL - Planning, engineering and architectural study for topside developmenti at p e K l EA in PILLAR POINT P e Hin Keng TSING LUNG TAU 5 C 5 20 R ( Mong Hau Shek ) Wong Uk LE Kwai Shing Estate Estate C AST 10 C KWAI CHUNG Hong Kong boundary crossing facilities island of Hong Kong-Zhuhai-Macao Bridge NGA YING 5 AD M Ngau Kok Cheung CHAU RO A W Wan AMAH ROCK A Shue Tau 5 UN 10 N M 20 C TUEN Brothers Point H 5101CX - Study for Pier Improvement at Yung Shue Wan, Shek Tsai PAK CHAU A 30 N ( Tai Lam Kok ) N 10 E 5 5 L R A 846TH - Tuen Mun - Chek Lap Kok Link - detailed design, 737CL - Dredging, management and capping of contaminated PAK WAN M 30 Wan,B Yi O and Ma Wan ChungKowloon Reservoirs - Investigation L 20 E SHEK WAN R

10 BEACON HILL

Tin Liu 5 E BRIDG Cheung Hong MA LION ROCK site investigation and advance works sediment disposal facility to the south of The Brothers G IN TS Estate C R MA WAN H A N R 20 N E 30 L Shek Lei Tau 10 HA KWAI CHUNG EAGLE'S NEST Kwai Shek KAM CHUK ( Tsim Shan ) 30 KOK 2 0 3 Container 5 San Po Tsui Kau Wa K Terminal A SHA CHAU P R Keng 5 TAI WO PING 4 S H U Cemetery 20 I 4 781CLe - Infrastructural Works for Development in Area 54, Tung Chung n i 10 l M e p U i N 10 1 P TANG LUNG SO UK 2 Oil Depot 5 0 TSING YI WANG CHAU

857TH - Tuen Mun - Chek Lap Kok Link - construction works 3 20 TAU HOM 0

10 SIU MO TO 9 10 LAI CHI KOK SHEK KIP 3 0 5 5 6101TX - Provision of UniversalCHEUNG Access Facilities at Public Footbridges, Elevated CHEUNG SHA WAN MEI 5 Tso Wan 3 5 SOK 5 KOWLOON cau 30 Ma 3 THE BROTHERS 10 0 To 5 TONG 2 Walkways & Subways Package 2 - Investigation, Design0 and Construction 845TH - Hong Kong - Zhuhai - Macao Bridge Hong Kong TAI MO TO Container Terminal Pro p R os 2 Luk Keng Ngong 10 ed YAM O R SHAM SHUI PO KOWLOON 5 Tsuen a Shuen Au Fa Peng ilw WAN Power Station a CITY 10 y Boundary Crossing Facilities - reclamation and infrastructures 10 Oil Depot

5 3 0

Mong Tung TSZ KAN CHAU 20 Hang 5 381DS - Construction ( ofP additional sewage rising mains and rehabilitation of the E C N h N o Y Container Terminal k ' MA TAU S

K o B PA TAU KWU WAI YAM O A AY Y PUN SHAN HW W MA TAU KOK IG existing sewagea rising main between Tung Chung and Siu Ho Wan STONECUTTERS ISLAND H n SHEK TAI KOK Sham Shui Kok TAU LAN ) Power Station ( Ngong Shuen Chau ) MONG KOK 5101CX - Greening Master Plan (GMP)s of the South West New Territories (SWNT) TSUI TH NOR 10 KOWLOON 5G66CG - Consultancy Study & Site Investigation 2 ay 0 TO KWA Runw

TAI CHE 3 WAN 5 0 5 TUNG 5 HO MAN 5 5 365WF - Siu Ho Wan Water Treatment Works Extension 1 TIN Sam Pak 5101CX - Greening Master Plan (GMP)s of the 2 Sze Pak YAU MA 10 TEI KING'S 5101CX - Study for Pier Improvement at Yung Shue Wan, 5 PARK 5G66CG South West New Territories2 (SWNT)

YI PAK AU 10 Shek Tsai Wan, Yi O and Ma Wan Chung - Investigation 353DS - Outlying Islands sewerage stage 2 - extension of sewerage - Consultancy Study & Site Investigation 10 HUNG HOM ( Tai Pak Wan ) ay Runw system to other unsewered villages in Mui Wo 111ET - A special school for students with mild, 10 10 Discovery Bay TAI HO LO FU TAU TSIM SHA TSUI moderate and severe intellectual disabilities WAN 3 20 9 10 20 C

r o ng s 387DS - Upgrading of Mui Wo sewage treatment works and i s s 6850TH - New Wang Tong River Bridge s O Pak Mong o Cr H T 10 5 in Area 108, Tung Chung a r ur b C o o I rb u 5 a r H V N TAI HO IM 5 n T Nim Shue er u SH t n sewerage at Mui Wo town centre and Wang Tong n U s E e e Wan Village W DOUGLAS ROCK W l AN Ngau Kwu TAI LEI 10 10 SAI YING e 5 lin 5 pe Long Reservoir PUN Pi 844TH - Hong Kong - Zhuhai - Macao Bridge e 5 5 n 7 i SIU KAU l e p Cheung i P PENG CHAU 5 YI CHAU SHA LO WAN Yu Tung Sha Lan 5 10 d Tai Ho San 10 5 Fu Tung Court 5 Hong Kong Link Road San Tau Tsuen SAI WAN 10 20 TUNG CHUNG Estate GREEN ISLAND Golf Course KAU YI CHAU UR CENTRAL BAY Ma Wan LPH SU NEL AN DISTRICT Chung CH H.K. University def qb 422DS - Outlying Islands sewerage stage 202 - 10 POK TO YAN R San Shek Wan HUNG FA 5 Ma Wan CAUSEWAY BAY 7 NGAN R Peng Chau village sewerage phase10 2KENNEDY TOWN TUNG CHUNG Shan Ha TAI SHUI HANG WAN CHAI VICTORIA PEAK 1

MOUNT DAVIS 5 Ngau Au New Tung package 1 SHAM SHEK 5 5 Chung Hang R R TSUEN R 356WF - Uprating of Tung Chung R Race R Shek Lau R Course SO KON PO Tung Wan k Wang Tong Kau Shat a Nim Yuen R e y Po Cemetery R P a Tau w Pak Ngan Wan HIGH WEST m Lung Mei R ra 343DS-2 - Outlying Islands sewerage stage 2 - T fresh water supply system Wong Lung Heung 7E38RG - Preliminary Feasibility Study of Cable 786CL - Tung Chung New Town ExtensionTsuen MT. GOUGH Hang ­»´ Sai Tso Wan R Pipeline Sham Wat Man Kok R Shek 10 R SILVER MINE BAY Peng Chau village sewerage phase 2 Tai Tei Tong Chung Hau MAGAZINE Car System from Ngong Ping To Tai O Mun Kap 799CL HAPPY VALLEY 5 GAP POK LIN FA SHAN WAN CHAI GAP R Pipeline remaining works FU LAM C 814CL MUI WO 20 MT. KELLETT HONG KONG ISLAND Kau San Tei LANTAU ISLAND Luk Tei Tong Pok Fu Lam 10 10 Reservoir 3 R MT. CAMERON SUNSHINE ISLAND 0 e MT. NICHOLSON n i C 2 l 10 0 e p CHEUNG SHAN 414RO - Improvement works at Mui Wo - Remaining Phases i ( Chau Kung To ) P YI TUNG SHAN 5051TF - Reconstruction of Pak Kok Pier SUNSET PEAK R TEI TONG TSAI Aberdeen 469RO - Improvement works at NGONG PING 331DS-2 - Outlying Islands( Tai Tung Shan ) Sewerage Stage 2 - Reservoirs C NAM SHAN on Lamma Island Shek Tsai Po Tai O (Phase 2 Stage 1) Yim Tin South Lantau Sewerage Works R Statue of 5 WAH FU Hang Mei Luk Wu Buddha Mau Yuen ABERDEEN T C TAI O U Shui Tseng R 1 N Ngau Kwu Wan SHOUSON HILL G 5101CX - Greening Master Plan (GMP)s of the Cemetery Wan 464RO - Improvement works at Mui Wo ( Fung Wong Shan ) C 5 H ne U li WONG CHUK HANG 417RO - Improvement works at Tai O e KEUNG SHAN p 20 Pi Golf Course N 5G66CG South West 10New Territories R(SWNT) G SHEK PAI WAN R C R Wang Tong - Phase 2 Stage 1 5 Fan Kwai Tong Pui O Ocean Park (Phase 2 Stage 2 and 163CD Cheung- DrainageTing improvement R BRICK HILL 5 O ( Nam Long Shan ) Nga Ying Kok A - Consultancy Study & Site Investigation R D 20 CHI MA WAN MAGAZINE ISLAND C Pak Kok R KAU NGA LING Shap Long E DEEP WATER BAY works at NgongR Ping def A remaining works) C 20 Ham Tin Kau Tsuen S San Shek 5290RS - Expansion of Mountain Bike Trail Networks T R R Ngau Kwo Tin r Wan a R L R C Shap Long A A PUI O WAN M B le E b Chung Hau M R a 10 A D C AP LEI CHAU E E in Mui Wo and Chi Ma Wan, South Lantau N 5 10

30 C 20 H C R Pak Kok H Ocean Park A 5 A N N C San Tsuen N YI O N 10 E E 5101CX - 30Study for PierL Improvement at Shek 20 L AD CHEUNG SHA 5101CX - Landscape ImprovementShek Pik RO Cheung Sha Wan Kok Tsui 10 KEUNG SHAN L Reservoir U E MIDDLE ISLAND TA 331DS-1 - Construction of San Shek Wan N LA N LO YAN N Yung Shue Wan, Shek Tsai( Tong Po Chau ) R Tong Fuk SOUTH Yi O San MAN CHEUNG PO A C SHAN LUK CHAU WAN AP LEI PAI Tsuen 5J71CG Works in Ngong Ping H R C Sham Shui 5 R sewage treatment works, associated Kok Yung shue LUK CHAU Wan, Yi O and Ma Wan Chung A M YUNG SHUE Wan R CHI MA WAN PENINSULA M P WAN ip 5 A el 5 Yi O Kau Shui Hau submarine outfall and Pui O ine L 5 Lo Tik - Investigation Tsuen SHEK PIK TONG FUK MIU WAN Tai Wan 5101CX - Study for Pier Improvement at Tai Long Wan MONG TUNG T Ko Long San Tsuen Wan Ha Keng LING WUI SHAN Tsuen S TAI HOM SHAM WAN E sewerageMong Tung works Tai Long W 5 20 Yung Shue Wan, Shek Tsai Wan, C Wan TUNG WAN Hung TAI LONG 10 Tung Wan Power Station Shing Ye Luk Chau WAN EL Mei N TAI KWAI 5 Village TAI LONG AN ROUND ISLAND Yi O and Ma Wan Chung Sea Ranch CH WAN CHA KWO WAN ( Ngan Chau ) A CHAU ST 10 ( Kai Yet Kok ) 5 A Tsin Yue Wan YI LONG M 5 A 20 - Investigation 9100WX - Uprating of Cheung Sha WAN AD CHEUNG CHAU C

TUNG WAN 10 5 Water Treatment Works PICNIC BAY 5 LO KEI WAN CHEUNG (Sok Kwu Wan) CHAU WAN 354DS-1 10- Outlying Islands sewerage stage 2 - Lo So Shing SHAM SHUI PAI HA MEI WAN FA PENG Mo Tat NAM TAM Sok Kwu Old Village upgrading of Cheung Chau sewage LING KOK FAN LAU SAI WAN Wan SHAN 5 10 FAN LAU Kau Ling Chung Cheung Po FAN LAU 10 TUNG WAN Tsai Cave treatment and disposal facilities 20 426DS - Rehabilitation of underground sewers10 10 LAMMA ISLAND To Macau 7E34RG - Spa and Resort Development SHEKat Cheung KWU Sha stage 1 CHAU Fan Lau Kok PAK TSO TUNG O WAN 10 10 10 WAN and Soko Islands - Feasibility Study Tung O (Distributed in various locations 397DS - Outlying Islands sewerage stage 2 L MOUNT STENHOUSE 5 AN TA ( Shan Tei Tong ) in Islands District) U 10 «n¤ C - Lamma village sewerage phase 2, package 1 7100CX - Planning & Engineering Study on Future HA Ha Mei Tsui NN EL 0 2 354DS-2 - Outlying Islands sewerage stage 2 - Lamma Island 180CD - Rehabilitation of underground stormwater 7D67CL Land Use at Ex-Lamma Quarry Area upgrading of Tai O sewage disposal and SHAM WAN drains stage 1 10 - Feasibility Study 5 treatment facilities and sewage collection Yuen Kok CHEUNG 10 (Distributed in various locations MUK TAU Tai Kok 10 facilities for Tai O and Cheung Chau in Islands District) YUEN CHAU 20 355DS - Outlying Islands sewerage stage 2 20

10 - Lamma village sewerage phase 2, package 2 5 5 5001BX - Landslip Prevention and Mitigation Programme (LPMitP) SOKO ISLANDS 10 10

10 (Distributed in various locations in Islands District) 10 5101CX - Greening Master Plan (GMP)s of the 5

YUEN KONG 5G66CG South West New Territories (SWNT) Sheung Tsuen CHAU 10

5768CL - Strategic Studies for Artificial Islands in the - Consultancy Study10 & Site Investigation

10

Central Waters ( Location see page 12) 5

2 0 20 10

¹Ï«h drawing title ¶µ¥Ø item no. ¿ì¨ office ¥i«ùÄò¤j ¤ñ scale A3 SUSTAINABLE LANTAU OFFICE

Progress Report of Major Projects in Islands District 2019 - Projects Location Plan 1 : 100 000

drawing no. ¤g¤ì¤uµ ¹Ï«h CIVIL ENGINEERING AND SLO-Z0203 DEVELOPMENT DEPARTMENT

SLO-Z0203.dgn A3 420MM X 297MM