Council Paper No. IDC 24/2021

Progress Report of Major Projects in Islands District

Civil Engineering and Development Department Sustainable Office April 2021

Progress Report of Major Projects in Islands District (as at 31 December 2020)

Contents Page

(1) Objectives 2 (2) Community Facilities Works 3 (3) Port and Reclamation Works 8 (4) Roads Works 11 (5) Drainage Works 18 (6) Water Works 28 (7) Others 30 (8) Appendix – Location Plan of some major works in Islands District

(1) Objectives

(i) This report contains project information provided by relevant government departments up to 31 December 2020, unless otherwise specified. (ii) Projects include  Items completed from 1 January 2020 to end 2020;  Items in progress; and  Items expected to commence in /after 2021

ArchSD: Architectural Services Department SDEV: Secretary for Development CEDD: Civil Engineering and Development Department SEN: Secretary for Environment DSD: Drainage Services Department STH: Secretary for Transport and Housing EDB: Bureau WSD: Water Supplies Department HyD: Highways Department

Page 2 (2) Community Facilities Works Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date (M/Yr) Date (M/Yr) Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ Organization

414RO Improvement Under SDEV Under Under The proposed Improvement works at , works at Mui Wo – Review Phase 2 Stage 2 and Phase 3 works includes the B CEDD Review Review Remaining Phases reprovisioning of cooked food market, reprovisioning of public toilet and 4 dry goods stalls, reprovisioning of cargo loading and unloading area at the ex-concrete batching plant site, improvement to south waterfront promenade, construction of landscape deck, reprovisioning of covered cycle parking area (providing about 1900 cycle parking spaces) and car park (providing about 60 to 70

parking spaces for private car), improvement of Entrance Plaza, and reprovisioning of public transport interchange and refuse collection point.

We conducted the public consultation and collected public views on the latest layout plan from October 2020 to March 2021. This included meeting with major stakeholders, distribution of information leaflets and

suggestion forms to all

members and Mui Wo residents as well as setting up street booth at major locations in

Mui Wo. We are studying the public views collected.

(Notes: Details of the project were updated in March 2021.)

Page 3 (2) Community Facilities Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization 417RO Improvement Under SDEV Under Under Improvement works at , Phase 2 B works Review CEDD Review Review Stage 2 mainly cover two proposed at Tai O footbridges for improving local (Phase 2 Stage 2 and connectivity. Detailed design of Phase remaining 2 Stage 2 works is in progress. works) Improvement Works at Tai O,

remaining works mainly cover works

for improving facilities to help preserve the heritage and facilitate visitors’ appreciation of natural attributes of Tai O. The preliminary design is in

progress.

Improvement Works at Tai O, Phase 2 Stage 2

Page 4 (2) Community Facilities Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

5052CG Greening Master 367.6 SDEV 12/2020 end 2023 The study of Islands GMP commenced in Plan (GMP)s of the 2012. Formulation of the GMPs was A (50.0 CEDD Southwest and completed and support was received from the Islands District Council on the implementation Northeast New for Islands of the GMP works. Territories – priority District) greening works CEDD updated the Islands District Council the proposed greening works and implementation programme by way of information paper circulation in March 2019. Funding application was approved on 14 July 2020 and the works commenced in end December 2020.

Tung Chung GMP Focal Area

Cheung Chau GMP Focal Area

Page 5 (2) Community Facilities Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

Peng Chau and GMP Focal Areas

Page 6 (2) Community Facilities Works Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

7E91RG Minor Improvement 0.5 SDEV 02/2018 01/2020 Minor improvement works at Chung Works at Ma Wan includes beautification of Public D CEDD Chung Pier, beautification and updating of information shown on an existing village map, beautification of an existing footbridge, installation of wayfinding facilities, and beautification of building facade.

Page 7 (3) Port and Reclamation Works Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

799CL Tung Chung New 729.5 SDEV 06/2016 06/2024 The proposed Tung Chung New Town Town Extension – Extension (TCNTE) will cover areas on the A CEDD Detailed Design and eastern and western flanks of the existing Tung Chung New Town. It will provide about Site Investigation 62,100 residential flats for a population of 814CL Tung Chung New 20,210.0 12/2017 12/2023 about 184,000. Town Extension – The reclamation and advance works Reclamation and A commenced in December 2017. Parcels of Advance Works land were handed over to for public housing development. The funding application for the first phase of

859CL Tung Chung New 19,332.9 2021 Q2 Target for site formation and infrastructure works was Tung Chung East Extension Area Town Extension – completion approved by Finance Committee of the A Site formation in about 7 and Infrastructure years with Legislative Council in February 2021. Works phased completion from 2024 The detailed design for the remaining phase of onwards site formation and infrastructure works is in progress.

786CL Tung Chung New Under Under Under (Notes: Details of the project were updated in Town Extension – Review Review Review March 2021.) -2C Site Formation B and Infrastructure Works – Remaining Works

Tung Chung West Extension Area

Page 8 (3) Port and Reclamation Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

5101CX Improvement Works at 15.0 SDEV 05/2020 2025 Q4 Improvement works at Public Yung Shue Wan Public Pier, Yi O Pier and Ma Wan Chung Pier were D CEDD Pier, Shek Tsai Wan consulted in the meeting of Traffic and Pier, Yi O Pier and Ma Wan Chung Pier – Transport Committee of Islands District Design and Council on 22 July 2019 and 22 March 2021, Construction respectively. The members supported the works in general. The investigation study of the proposed improvement works at Yung Shue Wan Public Pier, Yi O Pier and Ma Wan Chung Pier has been completed. CEDD will continue with

the detailed design and ground investigation works, as well as proceed with statutory gazettal of the improvement scheme under the Foreshore and Sea-bed (Reclamations) Ordinance (Cap 127) with a view to commencing the works in 2022. (Notes: Details of the project were updated in March 2021.)

5051TF Reconstruction of 72.4 STH 04/2020 Second half of The project aims to reconstruct the Pak Kok Pak Kok Pier on 2022 Pier on Lamma Island. A Lamma Island CEDD Approval of funding application of the project by the Legislative Council Finance Committee was obtained on 28 February 2020. The construction works commenced in April 2020.

Page 9 (3) Port and Reclamation Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

5768CL Studies Related to 550.4 SDEV 2021 Q2 2024 Q4 The scope of study comprises: Artificial Islands in A CEDD (anticipated) (anticipated) (a) a detailed planning and engineering study the Central Waters for the artificial islands around ; (b) a transport infrastructure study; (c) collection of information on waters within and in the vicinity of the possible artificial islands near and South for future reference

in long-term planning; and (d) associated site investigation including supervision.

Page 10 (4) Road Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

781CL Infrastructural 284.8 STH 11/2017 12/2020 The project is to provide supporting Works for infrastructure works for public housing A CEDD Development in development in Area 54, Tung Chung, Area 54, Tung including construction of new Chung carriageway, footpaths, cycle track and parking area, amenity areas, bus lay-bys and sewerage works. The works commenced in November 2017 for completion in two stages. The proposed footpaths, cycle track, cycle parking area and bus layby to the north of Ying Hei Road were substantially completed in July 2019. The remaining works including the proposed new carriageway and sewerage works were substantially completed in December 2020.

Page 11 (4) Road Works Head of

Item No Estimated Bureau & Commencement Completion Photo/Drawing & Title Cost responsible Date Date Scope of Works/ Notes ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

857TH – Chek 44,798.4 STH 06/2013 The Southern The project comprises the construction of a dual two-lane Lap Kok Link Connection viaduct between the HZMB HKBCF and North Lantau A HyD (TM-CLKL) – and Northern (Southern Connection), the construction of a dual two- Connection of construction works lane sub-sea tunnel between Tuen Mun Area 40 and the the TM-CLKL were HZMB HKBCF (Northern Connection) and the commissioned construction of associated structures, and ancillary in October works. 2018 and December 2020 respectively

Page 12 (4) Road Works

Head of Estimated Bureau & Commencement Completion Item No Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing & ($M) Dept/ (M/Yr) (M/Yr) Cat. Organization

6850TH New Wang Tong 99.7 STH 09/2020 2024 Q1 The Project mainly includes the River Bridge construction of a twin-bridge of (tentative) A HyD approximately 35m in length comprising a footbridge and a cycle bridge with clear widths of 2m and 3.5m respectively across Wang Tong River in Mui Wo, and demolition of the existing Wang Tong River Bridge.

The works commenced on 28 September 2020.

Page 13 (4) Road Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

6101TX Provision of 118.0 STH 11/2015 01/2020 The project aims to provide lift facilities for the Universal Access following three public footbridges/subway in D HyD Facilities at Public Islands district: Footbridges, i. Footbridge across Yu Tung Road and Chung Elevated Walkways Yan Road (Structure No. NF328); & Subways Package ii. Footbridge across Yu Tung Road near Tung 2 – Investigation, Chung Ha Ling Pei (Structure No. Design and NF332); and Construction iii. Pedestrian subway across Shun Tung Road near Lantau North Divisional Police Station (Structure No. NS230). The project commenced in November 2015 and the progress of works is as follows:- Structure No.of Completion Progress of No. Lifts Date Works NF328 3 January Lift 1:Opened for 2020 public use in July 2019 (Actual) Lift 2:Opened for public use in November 2018. Lift 3:Opened for public use in January 2020 NF332 2 August Lift 1:Opened for 2018 public use in August (Actual) 2018. Lift 2:Opened for public use in August 2018. NS230 2 October Lift 1:Opened for 2019 public use in October (Actual) 2018. Lift 2:Opened for public use in October 2019

Page 14 (4) Road Works Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

6101TX Provision of 17.8 STH 06/2020 2022 Q2 The project includes retrofit a lift for Walkway Universal Access No. ID01 across Ying Hei Road near the (tentative) D Facilities at HyD Visionary and Caribbean Coast under the Second Footbridges, Phase of the Universal Accessibility Programme. Elevated Walkways The project commenced in June 2020 and the and Subways foundation works are in progress. Package 3 – Investigation, Design and Construction

Page 15 (4) Road Works Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

6100TX Walkway Covers in 19.4 STH 08/2020 2022 Q2 The project comprises the construction of Islands District walkway covers of about 360m long at Chui (tentative) D HyD Kwan Drive, On Tung Street and Shun Tung Road in Islands District. The project commenced on 3 August 2020.

Page 16 (4) Road Works Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

5782CL Engineering Study 130.2 SDEV 2021 Q2 2023 Q4 The scope of study comprises: 1 on Road P1 (Tai Ho (a) an investigation study and the A CEDD (anticipated) (anticipated) – Sunny Bay preliminary design for the works relating to the Road P1 (Tai Ho – Section) Sunny Bay Section) that mainly consists of the following works components –

(i) a carriageway of approximately 9.5 km long that extends from the Tai Ho Interchange to Sunny Bay and connects to the North Lantau

Highway (NLH) and the proposed Route 11, which involves viaduct(s), tunnel(s) and reclamation works; and

(ii) the associated building, civil, structural, marine, electrical and mechanical, landscaping 2 , and environmental protection and mitigation works; and

(b) the associated site investigation works and works supervision.

1 The investigation study includes a review of the findings of previous studies, and impact assessments on environment, traffic, geotechnical, marine, heritage and other related aspects.

2 The investigation study covers the consideration of building cycle tracks and promenades along appropriate road section(s).

Page 17 (5) Drainage Works Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

381DS Construction of 1,362.6 SEN 08/2016 Phase 1 The project comprises the construction of additional sewage (new rising additional sewage rising mains, rehabilitation A DSD rising mains and main) of the existing sewage rising main and rehabilitation of the modification of related facilities between Tung existing sewage 06/2023 Chung and Siu Ho Wan. rising main between Tung Chung and Siu Phase 2 Phase 1 works commenced in August 2016. Ho Wan (rehabilitation The works are in progress and about 85% completed. of existing rising main)

12/2025

163CD Drainage 216.0 SDEV 08/2020 2022 Q4 The project comprises construction of about improvement works 900m long drains and box culverts at the A at DSD northern side of and Terminal in order to relieve the potential flood risk in Ngong Ping area. Construction works commenced in August 2020 for completion in 2022 Q4 tentatively.

Page 18 (5) Drainage Works

Head of Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

422DS Outlying Islands 133.7 SEN 11/2018 2022 Q4 The project aims at providing a public sewage sewerage stage 2 – collection system for the unsewered areas in DSD A village Peng Chau in order to improve the water sewerage phase 2 quality of nearby watercourses and the package 1 hygiene condition of six unsewered areas (formerly (Nam Wan San Tsuen, Tai Yat San Tsuen 343DS-1) (part), Wai Tsai Tseng San Tsuen, Central Peng Chau, Nam Wan Shan Ting Tsuen, and Tung Wan Village (part). Construction works commenced in November 2018 for completion in 2022 Q4.

Page 19 (5) Drainage Works Head of Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

343DS Outlying Islands Under SEN 2023 Q4 2025 Q4 The project aims at providing a public sewage sewerage stage 2 – Review collection system for the unsewered areas in B Peng Chau village DSD Peng Chau in order to improve the water sewerage phase 2 quality of nearby watercourses and the remaining works hygiene condition of five unsewered areas (Shan Ting Tsuen, Tai Lung Tsuen, Wai Tsai Tsuen, Tai Yat San Tsuen (remaining part) and Tung Wan Village (remaining part)). Detailed design of the project is in progress.

353DS Outlying Islands Under SEN 2021 Q4 2026 Q2 The scope of works mainly comprises the sewerage stage 2 – Review construction of sewers for Luk Tei Tong and B extension of DSD Ma Po Tsuen, and one sewage pumping station sewerage system to with associated twin rising mains at Luk Tei other unsewered villages in Mui Wo – Tong. Village Sewerage The project is at the detailed design stage. Works at Luk Tei Tong and Ma Po Tsuen

Page 20 (5) Drainage Works Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

437DS Outlying Islands 2,606.9 SEN 11/2020 3/2026 The project mainly comprises upgrading the sewerage stage 2 – sewage treatment facilities at the existing A DSD upgrading of Cheung Cheung Chau sewage treatment works and the (formerly Chau sewage Pak She sewage pumping station. 354DS-1) treatment and disposal facilities

354DS -2 Outlying Islands Under SEN 2023 Q3 2029 Q2 The project mainly comprises the provision of

sewerage stage 2 – Review public sewerage for the unsewered areas in B DSD upgrading of Tai O Cheung Chau and Tai O, and upgrading the sewage disposal and sewage treatment facilities at the existing Tai treatment facilities O sewage treatment works. and sewage collection facilities for Tai O and Detailed design of the project is in progress. Cheung Chau

Page 21 (5) Drainage Works Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

355DS Outlying Islands Under SEN 2021 Q4 2026 Q2 The scope of works mainly comprises the sewerage stage 2 – Review construction of sewers for 7 unsewered areas B Lamma village DSD in Yung Shue Wan (Tai Yuen Village (part), sewerage phase 2, Ko Long (part), Wang Long, Tai Wan San package 2 Tsuen, Tai Wan Kau Tsuen, Long Tsai Tsuen and Hung Shing Ye) and construction of 2 sewage pumping stations. The project was gazetted on 27 September 2019. An amendment gazette was published on 19 June 2020. Subject to approval of funding application for the project, the works will commence in 2021 Q4 for completion in

2026 Q2.

Page 22 (5) Drainage Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

433DS Construction of San 1,688.8 SEN 2021 Q1 2026 Q3 The project aims at providing public sewerage Shek Wan sewage at South Lantau. It mainly comprises the DSD treatment works, construction of a secondary sewage treatment associated submarine A works at San Shek Wan with associated outfall and Pui O (formerly sewerage works submarine outfall, trunk sewer from Pui O to 331DS- , village sewers at Lo Uk and a 1) sewage pumping station at Pui O The works are scheduled for commencement in 2021 Q1.

331DS Outlying Islands Under SEN 2023 Q3 2028 Q4 The project aims at providing public sewerage Sewerage Stage 2 – Review at South Lantau. It mainly comprises the B South Lantau DSD construction of trunk sewers along the South Sewerage Works Lantau Road and village sewers,at Shui Hau, (Remaining Works) Tong Fuk, Cheung Sha, San Shek Wan, Pui O and Ham Tin. Detailed design is in progress.

Page 23 (5) Drainage Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

426DS Rehabilitation of 514.7 SEN 01/2019 2022 Q4 Stage 1 of the projects comprise 110 km of underground sewers condition survey and about 18 km of A (7.0 for DSD stage 1 rehabilitation of the underground sewers and Islands and District) stormwater drains over the territory. Among these, the proposed works in Islands District 180CD Rehabilitation of comprises condition survey of about 700 m A underground SDEV stormwater drains and rehabilitation of about 400 m of stage 1 DSD underground sewers and stormwater drains. Works contracts under items 426DS and

180CD commenced in January 2019 for the completion in the 4th quarter of 2022 tentatively.

Page 24 (5) Drainage Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

415DS Cheung Chau Under SEN 2024 Q3 2028 Q2 The scope of the Project mainly comprises the Development, Review construction of sewers for four unsewered B DSD improvement to areas in Cheung Chau Old Town, namely existing roads and Lung Tsai Tsuen, Ko Shan Tsuen, Tai Tsoi drains in Cheung Chau Old Town - Yuen Kui and Pak She San Tsuen. Remaining Engineering Works

Page 25 (5) Drainage Works Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

Remaining Works include rehabilitation of 172CD Rehabilitation of 702.7 SDEV 2021 Q2 2025 Q4 Underground about 19 km of stormwater drains in Central B Stormwater Drains – (3.0 DSD & Western, , Eastern, Southern, Remaining Works for Islands Islands, Tuen Mun, Yuen Long, North, Tai District) Po, Sha Tin, Kwun Tong and Sai Kung districts.

Among them, the proposed works in Islands District comprise rehabilitation of about 100m stormwater drains.

Stormwater Drains proposed to be rehabilitated

Page 26 (5) Drainage Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

414DS Rehabilitation of Under SEN 2022 Q3 2027 Q1 Remaining Works include rehabilitation of Underground Review about 6 km of underground sewers in Central B DSD Sewers – Remaining & Western, Wan Chai, Eastern, Southern, Works Islands, Tuen Mun, Yuen Long, North, Tai Po, Sha Tin, Kwun Tong and Sai Kung districts.

Among them, the proposed works in Islands District comprise rehabilitation of about 40m sewers. Sewers proposed to be rehabilitated

Page 27 (6) Water Works Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

9100WX Uprating of Cheung 18.4 SDEV 2020 Q3 2022 Q2 The project comprises uprating of Cheung Sha Sha Water water treatment works from its nominal output D (main WSD (main works) (main works) of 6,000 cu.m. to 7,500 cu.m per day. The Treatment Works works) works will involve addition, modification and/or retrofitting of water treatment units, and

15.0 associated civil, structural, geotechnical, (associated 2021 Q3 2023 Q2 mechanical and electrical works within the mainlaying (associated (associated existing WSD’s Land Allocation for Cheung works) mainlaying mainlaying Sha Water Treatment Works. works) works) Besides, mainlaying of 1.6km long of diameter

250mm along South Lantau Road to meet fire- fighting flow requirement.

365WF-2 Siu Ho Wan Water Under SDEV 2021 Q3 2027 Q4 The project comprises expansion of the Siu Ho Treatment Works Wan Water Treatment Works to increase its B review WSD Extension – Main water treatment capacity from 150,000 m3 per Works day to 300,000 m3 per day, and increase correspondingly in the transfer capacity of the associated raw water supply systems. The investigation study, design and associated site investigation works for the project commenced in August 2018.

Page 28 (6) Water Works

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization 300.2 356WF Uprating of Tung SDEV 12/2017 2021 Q2 This project comprises construction of Tung Chung fresh water Chung No.2 Fresh Water Service Reservoir A WSD supply system with a capacity of approximate 40,000 m3 and connection of proposed Tung Chung No. 2 Fresh Water Service Reservoir to existing fresh water distribution network. Advance works commenced in December 2017 whereas Contract No. 4/WSD/17 commenced in February 2018 and is anticipated to be completed in 2021.

Page 29 (7) Others

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

7100CX Planning & 29.9 SDEV 01/2012 03/2020 The study includes the formulation of various land 7D67CL Engineering Study use options for the ex-Lamma Quarry at Sok Kwu PlanD D on Future Land Use Wan in Lamma Island, and the related planning and & at Ex-Lamma Quarry engineering study as well as environmental impact Area – Feasibility CEDD assessment. Study For formulating the development mode, the Government is actively considering making use of private developers’ capacity in providing infrastructure and ancillary facilities for the development. The “Market Sounding Out and Invitation for Development Proposal Exercise for Development at Ex-Lamma Quarry Area at Sok Kwu Wan, Lamma Island” (the Exercise) was

completed.

Taking into account the findings of the Exercise,

different land use initiatives, implementation arrangement of infrastructure and land uses, cost

effectiveness of the development as well as the views collected in previous two stage Community

Engagement, the Government will consider the

way forward of the ex-Lamma Quarry development and the associated follow up actions.

Page 30 (7) Others

Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

770CL Planning, 63.4 SDEV 01/2015 12/2020 The project comprises a planning, engineering and A engineering and architectural study for the proposed commercial PlanD architectural study development and the development of other for topside & economic activities at the boundary development at Hong crossing facilities (HKBCF) island of Hong Kong- CEDD Kong boundary -Macao Bridge (HZMB) and the associated crossing facilities site investigation works. island of Hong

Kong-Zhuhai-Macao Bridge In view of the latest planning and development in airport and its nearby areas, the Airport Authority

Hong Kong (AAHK) accepted the invitation by the Government to submit a proposal for the topside development at the Hong Kong Boundary Crossing Facilities (HKBCF) Island. AAHK submitted the report for the study on the proposed topside development at HKBCF Island covering various airport-related business. The Government has accepted a number of proposals put forward by AAHK to formulate the planning and land use of the HKBCF Island. AAHK will continue to follow up the development at HKBCF Island.

Page 31 (7) Others Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

5290RS Expansion of 41.6 SDEV 12/2016 09/2020 The project comprises construction of new Mountain Bike Trail mountain bike trails (MBTs) and practice A CEDD Networks in Mui facilities in South Lantau, which includes: Wo and Chi Ma (i) a new practice ground, with MBTs for Wan, South Lantau different skill level requirements and attractive technical features, to be located at

a hill top near Lai Chi Yuen Tsuen with supporting facilities;

(ii) MBTs joining two ends of the existing

Chi Ma Wan MBT to form a circular network; Expansion of Mountain Bike Trail Networks in Mui Wo and Chi (iii) a gathering place near Mui Wo Ma Wan, South Lantau – Location Plan trailhead at Mui Wo Pier Road;

(iv) MBTs from Mui Wo trailhead to the

proposed practice ground; and

(v) associated geotechnical, landscape and ancillary works.

Part of the construction works commenced in end 2016. The main works contract also commenced in November 2017 and was substantially completed in September 2020.

Proposed Practice Ground at a Hilltop near Lai Chi Yuen Tsuen

Page 32 (7) Others Head of

Item No Estimated Bureau & Commencement Completion & Title Cost responsible Date Date Scope of Works/ Notes Photo/Drawing ( ) Cat. $M Dept/ (M/Yr) (M/Yr) Organization

5101CX Expansion of Under SDEV April 2020 Under The project comprises: Mountain Bike Review Review 1. new mountain bike trails connecting D Trail Networks CEDD (Remaining Phase) Mui Wo and Pui O as well as and Other Minor associated supporting facilities; Improvement Works in South 2. removal of an illegal concrete structure Lantau - Design at a section of natural stream in Pui O and Construction Au to restore the natural environment; and 3. reinstate the retaining wall and footpath outside the Silvermine Bay Beach Resort.

The detailed design commenced in April 2020

Page 33 (7) Others

Head of

Item No Estimated Bureau & Commencement Completion & Cat. Title Cost responsible Date (M/Yr) Date Scope of Works/ Notes Photo/Drawing ($M) Dept/ (M/Yr) Organization

Landslip Prevention and Mitigation (LPMit) 5001BX Landslip 1,160 SDEV 2010 On-going Prevention and works for 175 man-made slopes and 22 natural D Mitigation (Estimated CEDD hillside study areas in Islands District were Programme expenditur completed. (LPMitP) e for Financial The LPMit works for 8 man-made slopes and Year 7 natural hillside study areas in Islands District 2021/22) are in progress.

The details of man-made slopes are:  1 Slope No. 14NW-D/R130 at Hi Shi Road, Cheung Chau;  1 Slope No. 14NW-D/R44 at Sai Wan Road, Cheung Chau;

 1 Slope No. 13NW-B/F148 at Road, ;  1 Slope No. 14NW-D/R98 at Lung Tsai Tsuen, Cheung Chau;  2 Slopes No. 9SE-B/C64 and 9SE- B/C65 at Shun Tung Road, Tung Chung;  1 Slope No. 14NW-D/R298 at Pak She San Tsuen, Cheung Chau; and  1 Slope No. 14NW-D/R193 at Lung Tsai Tsuen Road, Cheung Chau.

Page 34 (7) Others Head of

Item No Estimated Bureau & Commencement Completion & Cat. Title Cost responsible Date (M/Yr) Date (M/Yr) Scope of Works/ Notes Photo/Drawing ($M) Dept/ Organization

The details of natural hillside study areas are:  1 Study Area No. 13NW-B/SA6 near Keung Shan Road, Lantau Island;  2 Study Areas No. 10SW-A/SA1 and 10SW-C/SA1 near Wang Tong, Lantau Island;  1 Study Area No. 13NW-B/SA4 near , Lantau Island;  1 Study Area No. 9SW-D/SA1 near Wang Hang Tsuen, Lantau Island;  1 Study Areas No. 15NW-C/SA1 near Sok Kwu Wan, Lamma Island; and  1 Study Area No. 10SW-B/HPSA1 near Shing Ka Road, Peng Chau.

CEDD plan to progressively commence the LPMit works for another 12 man-made slopes in Islands District in the coming year. The works are scheduled to commence in the 2nd quarter of 2021 and they will be completed by the 2nd quarter of 2022.

Page 35 SM UG GL ER ( S M ' a R ID Ts GE z SHA TIN K Sun Chui So Kwun en g SIU LANG ) HEIGHTS Estate Tan TAI LAM CHUNG Yau Kom Tau Tin Sam SHUI 5 D 1 A 5 P O ip R e R C l in R PO e GOLDEN HILL Kak Tin 2 Estate I A SIU LAM T PEARL ISLAND R D 10 OA 10 R P 770CL - Planning, engineering and architectural study for topside developmenti at p e K l EA in P e Hin Keng 5 C 5 20 R ( Mong Hau Shek ) Wong Uk LE Kwai Shing Estate Estate C AST 10 C KWAI CHUNG Hong Kong boundary crossing facilities island of Hong Kong-Zhuhai-Macao Bridge NGA YING 5 AD M Ngau Kok CHAU RO A Cheung 5101CX - Improvement Works at Yung Shue Wan Public Pier, W Wan AMAH ROCK A Shue Tau 5 UN 10 N M 20 C TUEN H PAK CHAU Brothers Point A 30 N Shek Tsai Wan Pier, Yi O Pier and Ma Wan Chung Pier ( Tai Lam Kok ) N 10 E 5 5 L R 5782CL - Engineering Study on Road P1 A 0 PAK WAN M 3 B Reservoirs 0 L 2 SHEK WAN E - RDesign and Construction

857TH - Tuen Mun - Link (TM-CLKL) - construction works 10

Tin Liu 5 E RIDG Cheung Hong (Tai Ho - Sunny Bay Section) B MA ING TS Estate C R MA WAN H A N R 20 N E 30 L Shek Lei Tau 10 HA KWAI CHUNG EAGLE'S NEST Kwai Shek KAM CHUK ( Tsim Shan ) 30 KOK 2 0 3 Container 5 San Po Tsui Kau Wa K Terminal A P R Keng 5 TAI WO PING 4 S H U Cemetery 20 I 4 781CL - Infrastructural Works for Development in Area 54, Tung Chung e n i 10 l M e p U i N 10 1 P TANG LUNG SO UK 2 Oil Depot 5 0 20 3 TAU HOM 0

10 SIU MO TO 9 10 LAI CHI KOK SHEK KIP 3 0 5 5 6101TX - Provision of UniversalCHEUNG Access Facilities at Public Footbridges, Elevated CHEUNG SHA WAN MEI 5 Tso Wan 3 5 SOK u 5 KOWLOON 6101TX - Provision of Universal Access Facilities at Public Footbridges, Elevated ca 30 Ma 3 THE BROTHERS 1 0 To 5 0 TONG 2 Walkways & Subways Package 2 - Investigation, Design0 and Construction TAI MO TO Container Terminal Pro R po Luk Keng 0 se 2 Ngong 1 d SHAM SHUI PO Walkways & Subways Package 3 - Investigation, Design and Construction R KOWLOON 5 Tsuen a Shuen Au Fa Peng ilw WAN Power Station a CITY 10 y 10 Oil Depot

5 3 0

Mong Tung TSZ KAN CHAU 20 Hang 5 381DS - Construction ( ofP additional sewage rising mains and rehabilitation of the E C N h N o Y Container Terminal k ' MA TAU S

K o B WAI YAM O A AY Y PUN SHAN HW W IG existing sewagea rising main between Tung Chung and Siu Ho Wan H n Sham Shui Kok AU SHEK TAI KOK 5052CG - Greening Master Plan (GMP)s of the Southwest and Northeast ANT ) ( Ngong Shuen Chau ) L Power Station MONG KOK TH TSUI NOR - priority greening works 10 KOWLOON 2 ay 0 TO KWA Runw

TAI CHE 3 WAN 5 0 5 TUNG 5 HO MAN 5 5 365WF-2 - Siu Ho Wan Water Treatment Works Extension - Main Works 1 TIN Sam Pak 5052CG - Greening Master Plan (GMP)s of 2 Sze Pak YAU MA 10 TEI KING'S 5 PARK 5101CX - Improvement Works at Yung Shue Wan Public Pier, the Southwest and Northeast2 New Territories YI PAK AU 353DS - Outlying Islands sewerage stage 2 - extension10 of sewerage Shek Tsai Wan Pier, Yi O Pier and Ma Wan Chung Pier - priority greening works 10 DISCOVERYsystem BAY to other unsewered villages in Mui Wo - Luk Tei Tong ( Tai Pak Wan ) ay - Design and Construction Runw and Ma Po Tsuen Village sewerage system 10 10 TAI HO TSIM SHA TSUI WAN 3

20 9 0 10 2 C

r o ng s si s 6850TH - New Wang Tong River Bridge s O Pak Mong o Cr 7E91RG - Minor Improvement Works at Ma Wan Chung 10 5 H T

a r ur b C o o I rb u 5 a r N H V

TAI HO IM 5 n T Nim Shue er u SH t n U s n E e e Wan Village W DOUGLAS ROCK W l AN Ngau Kwu 0 0 1 1 SAI YING e 5 lin 5 pe Long Reservoir PUN Pi e 5 5 n 7 i SIU KAU l e p Cheung i P PENG CHAU 5 YI CHAU SHA LO WAN Yu Tung Sha Lan 0 5 10 d Tai Ho San 1 5 Fu Tung Court 5 San Tau Tsuen SAI WAN 1 20 TUNG CHUNG Estate 0 GREEN ISLAND Golf Course KAU YI CHAU UR CENTRAL BAY Ma Wan LPH SU NEL AN DISTRICT Chung CH H.K. University def qb 422DS - Outlying Islands sewerage stage 202 - 10 R San Shek Wan HUNG FA 5 Ma Wan NGAN 7 0 R Peng Chau village sewerage phase1 2KENNEDY TOWN 6100TX - Walkway Covers in Islands District TUNG CHUNG Shan Ha TAI SHUI HANG WAN CHAI 1

MOUNT DAVIS 5356WF - Uprating of Tung Chung Ngau Au New Tung package 1 SHAM SHEK 5 5 Chung Hang R R TSUEN R R R Race 786CL-2C - Tung Chung New Town Extension R Shek Lau Course SO KON PO Tung Wan k Wang Tong Kau Shat a Fresh Water Supply System R e Nim Yuen y Po Cemetery R P a Tau w Pak Ngan Wan m Lung Mei R ra 343DS - Outlying Islands sewerage stage 2 - T Wong Lung Heung Tsuen MT. GOUGH 799CL Hang ­»´ Sai Tso Wan R Pipeline Sham Wat Man Kok R Shek 1 R SILVER MINE BAY Peng Chau village sewerage phase 2 0 Tai Tei Tong Chung Hau 414RO - Improvement works at Mui Wo MAGAZINE Mun Kap 814CL HAPPY VALLEY 5 GAP POK WAN CHAI GAP R Pipeline FU LAM C MUI WO - Remaining Phases remaining works 859CL 2 0 MT. KELLETT Kau San Tei Luk Tei Tong 417RO - Improvement Works at Tai O LANTAU ISLAND 0 1 10 Reservoir 3 R MT. CAMERON SUNSHINE ISLAND 0 e MT. NICHOLSON n i C l 1 2 e 0 0 p i ( Chau Kung To ) P (Phase 2 Stage 2 and YI 5051TF - Reconstruction of Pak Kok Pier 414DS - Rehabilitation of Underground Sewers R TEI TONG TSAI Aberdeen NGONG PING 331DS - Outlying Islands( Tai Tung SewerageShan ) Stage 2 - Reservoirs C remaining works) NAM SHAN - Remaining Works on Lamma Island Shek Tsai Po Yim Tin South Lantau Sewerage Works R Statue of 5 WAH FU Hang Mei Luk Wu Buddha Mau Yuen ABERDEEN T C TAI O U Shui Tseng R HEI LING CHAU 1 N Ngau Kwu Wan G Cemetery Wan 5290RS - Expansion of Mountain Bike Trail Networks 5052CG - Greening Master Plan (GMP)s of ( Fung Wong Shan ) C 5 H e in 163CD - Drainage improvementU l KEUNG SHAN pe 20 Pi Golf Course N 10 R G SHEK PAI WAN R C R in Mui Wo and , South Lantau the Southwest and Northeast New Territories Wang Tong 5 Fan Kwai Tong Pui O Ocean Park Cheung Ting works at NgongR Ping BRICK HILL 5 O ( ) Nga Ying Kok A R 20 D - priority greening works CHI MA WAN C Pak Kok R Shap Long 5101CX - Expansion of Mountain Bike Trail Networks (Remaining Phase) E R def A C Ham Tin Kau Tsuen S 20 San Shek T R R Ngau Kwo Tin r Wan a R L R C Shap Long A A and Other Minor Improvement Works in South Lantau PUI O WAN M B le E b Chung Hau M R a 10 A D C E E N 5 1 0

3 C 2 0 H 0 C Pak Kok 5101CX - ImprovementH WorksOcean Park at R - Design and Construction A 5 A N N C San Tsuen N YI O N 1 E E 30 0 L Shek 20 L AD CHEUNG SHA 5101CX - Improvement WorksShek Pikat RO Cheung Sha Wan Kok Tsui 10 Yung Shue Wan Public Pier, KEUNG SHAN L Reservoir U E MIDDLE ISLAND TA 433DS - Construction of San Shek Wan N LA N LO YAN N ( Tong Po Chau ) R Tong Fuk SOUTH Yi O San MAN CHEUNG PO A C SHAN LUK CHAU WAN Tsuen Yung Shue Wan Public Pier, H R C Shek Tsai Wan ShamPier, Shui Yi O Pier 5 R sewage treatment works, associated Kok Yung shue LUK CHAU A YUNG SHUE Wan Shek Tsai Wan Pier, Yi O Pier M R CHI MA WAN PENINSULA M and Ma Wan Chung Pier P WAN ip 5 A el 5 Yi O Kau Shui Hau submarine outfall and Pui O ine L 5 Lo Tik Tsuen SHEK PIK TONG FUK MIU WAN Tai Wan Tai Long Wan MONG TUNG T Ko Long San Tsuen Wan and Ma Wan Chung Pier Ha Keng LING WUI SHAN Tsuen S - Design and Construction TAI HOM SHAM WAN E sewerageMong Tung works Tai Long W 5 20 C Wan TUNG WAN Hung - DesignTAI LONG and Construction 10 Tung Wan Power Station Shing Ye Luk Chau WAN EL Mei N TAI KWAI 5 Village TAI LONG AN ROUND ISLAND Sea Ranch CH WAN CHA KWO WAN ( Ngan Chau ) 172CD - Rehabilitation of Underground Sewers A 10 CHAU ST ( Kai Yet Kok ) 5 A Tsin Yue Wan YI LONG M 5 A 20 9100WX - Uprating of Cheung Sha WAN AD CHEUNG CHAU - Remaining Works C TUNG WAN 10 5 Water Treatment Works PICNIC BAY 5 (Distributed in various locations LO KEI WAN CHEUNG (Sok Kwu Wan) CHAU WAN 437DS - Outlying10 Islands sewerage stage 2 - Lo So Shing SHAM SHUI PAI HA MEI WAN in Islands District) FA PENG Mo Tat NAM TAM Sok Kwu Old Village upgrading of Cheung Chau sewage LING KOK FAN LAU SAI WAN Wan SHAN 5 10 FAN LAU Kau Ling Chung Cheung Po FAN LAU 1 TUNG WAN Tsai Cave treatment and disposal facilities 0 20 426DS - Rehabilitation of underground sewers10 10 LAMMA ISLAND To SHEK KWU stage 1 CHAU Fan Lau Kok PAK TSO TUNG O WAN 10 10 10 WAN (Distributed in various locations 5052CG - Greening Master Plan (GMP)s of Tung O

L 5 AN TA ( Shan Tei Tong ) in Islands District) U 10 the Southwest and Northeast New Territories «n¤ C 7100CX - Planning & Engineering Study on Future HA Ha Mei Tsui NN EL 0 2 354DS-2 - Outlying Islands sewerage stage 2 - - priority greening works Lamma Island 180CD - Rehabilitation of underground stormwater SIU 7D67CL Land Use at Ex-Lamma Quarry Area upgrading of Tai O sewage disposal and SHAM WAN drains stage 1 10 - Feasibility Study 5 treatment facilities and sewage collection Yuen Kok CHEUNG 10 (Distributed in various locations MUK TAU Tai Kok 10 facilities for Tai O and Cheung Chau in Islands District) YUEN CHAU 20 355DS - Outlying Islands sewerage stage 2 20

10 - Lamma village sewerage phase 2, package 2 5 5 5001BX - Landslip Prevention and Mitigation Programme (LPMitP) 10 10

10 (Distributed in various locations in Islands District) 10 415DS - Cheung Chau Development, improvement to existing roads and 5

YUEN KONG drains in Cheung Chau Old Town - remaining engineering works 0 Sheung Tsuen CHAU 1

5768CL - Strategic Studies for Artificial Islands in the 10

10

Central Waters ( Location see page 10) 5

2 0 20 10

¹Ï«h drawing title ¶µ¥Ø item no. ¿ì¨ office ¥i«ùÄò¤j ¤ñ scale A3 SUSTAINABLE LANTAU OFFICE

Progress Report of Major Projects in Islands District 2021 - Projects Location Plan 1 : 100 000

drawing no. ¤g¤ì¤uµ ¹Ï«h CIVIL ENGINEERING AND SLO-Z0711 DEVELOPMENT DEPARTMENT

SLO-Z0711.dgn A3 420MM X 297MM