EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, for Eastern Steel Sdn. Bhd. Date: October 2019

CHAPTER 6 EXISTING ENVIRONMENT

6.1 INTRODUCTION This section highlights the existing environmental condition in three (3) major components, namely physicochemical, biological and human within the Project’s vicinity.

Information presented here is primarily to present an overview of existing environmental conditions surrounding the project site within 5 km radius which is then assessed for identification of the environmental receptors due to this Project and any concerned existing conditions that are likely to be impacted by the Project implementation. For the EIA Study, the Zone of Study extends for five (5) km radius from the boundary of the Project Site.

[Zone of Study – is the boundary of the study area for baseline data collection. Zone of Study may not be the same as the Zone of Impact for assessment conducted. In the event, the assessment impacts are found extended or beyond the Zone of Study, this will be addressed accordingly]

Assessment of the existing environmental condition will be documented according to site surveys and published secondary data (i.e. maps, reports, local plans) made available by the relevant government agencies. Following sections presents the existing information gathered via available documents.

6.2 PHYSICAL ENVIRONMENT 6.2.1 Site Physical Setting

The proposed Project lies within existing IISM premise. The entire IISM is located at Lot 6293, 6294, 60129, 60130 and 60131 within establish heavy industrial area, Teluk Kalung Industrial Estate (TKIE) in Kemaman, Terengganu. The location of IISM Plant is as shown in Chapter 1, Figure 1-1. The land is owned by the Eastern Steel with total land area of approximately 1,208 ac. The nearest township is Town, which located about 10 km to the south. Town is about 25 km away northeast of the Project. The Project site presently falls under Kemaman and the District of Kemaman and is under administrative area of Majlis Perbandaran Kemaman (MPK).

6.2.2 Topography

Project site is located in Teluk Kalung Industrial Estate (TKIE). The TKIE stretched from the area around Bukit Setongkol (north) to the coast near Kemaman Port. The original topography of the Project site was low lying and flat area with an elevation of lower than 20 m, as it was previously swampland. Topography map of Project Site is shown in Figure 6-1.

Page 6-1

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

However, over the time, the area has been filled to the desired platform level and well developed where a large tract of the industrial area is sited on flat surface. Hence, current topography of the Eastern Steel is relatively flat with the highest level is at 98.3m at southern section and 92.0m at northern section.

6.2.3 Geology

The TKIE is underlained by predominantly unconsolidated sediment from the Quaternary age. The sediment consists of clay, silt and sandy material with accompanying lenses interbedded with main soil layers. Based on the Geology Map of Peninsular , the underlaying soil composition of the Project site is characterized as peat, humic clay and silt (Figure 6-2).

6.2.4 Soil

Based on the Reconnaissance Soil Map of Peninsular Malaysia, the underlying soil composition of the Project site is characterized as peat. Table 6-1 tabulate baseline result of soil investigation study conducted in December 2007 and generalized soil map of Project site is illustrated in Figure 6-3.

Table 6-1 Soil investigation Results

Soil Description Depth BH 1 BH 2 BH 3 Very soft, dark brown Very soft, dark grey Very soft, dark grey 1-5 meter clayey silt with some clayey silt with some clayey silt sand sand Very soft to soft, Loose to medium Very soft to soft, dark medium stiff, dark dense, light grey, silty 6-20 meter grey, sandy silt grey to light brown, medium to coarse clayey and sandy silt grained sand Medium to very stiff, Medium stiff, light 21-30 meter light grey, gravelly brown and white - sand silt sandy silt Below 30 Hard, light grey, Hard, brown and light - meter gravelly sandy silt grey sandy silt Sources: Eastern Steel DEIA, 2008.

Page 6-2

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

N

Not to Scale

Source: Topography Map, Published by the Director of National Mapping, Malaysia.

Legend:

Project Site

River

Contour

Figure 6-1 Topography

Page 6-3

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

N

Not to Scale

Legend

Project Site

QUATERNARY

Marine and continental deposits; clay, slit, sand, peat with minor gravel. Basalt of Early Pleistocene age in the area.

UNICONSOLIDATED DEPOSITS

Peat, humic clay and silt

Source: Geological Map of Peninsular Malaysia, 8th Edition, 1985 by Head of Director, Department of Mineral and Geoscience Malaysia

Figure 6-2 Geology Map

Page 6-4

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

N

Not to Scale

Legend

Project Site

7 Yellow-Grey Podzolic soils with Laterites and Red-Yellow Podzolic soils on residual materials from argillaceous and mixed sediments, and acid igneous rocks

3a Gley soils on marine clays (Saline Gley soils and Acid Chukai Sulphate soils)

Source Generalized Soil Map of Peninsular Malaysia, 1970.

Figure 6-3 Soil Map

Page 6-5

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

6.3 EXISTING LAND USE The existing land use section below presents the following: • Land use status of the proposed Project Site • Land use status surrounding 1-5km from the Project site boundary

6.3.1 Existing Project Site Land Use Status

The Project site lies within the present premise occupied by the Eastern Steel and it is located within the Teluk Kalung Industrial Estate (TKIE). The entire Eastern Steel is located on Lot 6093, 6094, 60129 60130 and 60131; and IISM occupies total land area of approximately 1,208 acres of industrial estate. TKIE is one of the developing industrial areas in the Terengganu in which presently occupied by steel mills, chemical and petrochemical industries, etc. Villages and residential area and other amenities such as schools and mosque mostly are more concentrated at the northern and southern part (1 km to 5 km away and beyond from Project site).

A land use survey has been undertaken for the study area that extends up to 5 km radius of the project site in order to establish the existing land use pattern. The land use settings within 5 km radius of the Project site comprises mainly peat swamp forest, industrial lots, where residential areas and institutions are concentrated around the Chukai Town and Town.

The existing land development for the Project site and Kemaman are referred to the Rancangan Tempatan Daerah Kemaman (Pengubahan) 2011-2020. The existing land use for 1-5km and future land use are shown in Figure 6-4 and Figure 6-5, respectively.

Plate 6-1 to 6-7 presents the Eastern Steel facilities within project site; and the surrounding activities in Plate 6-8 to 6-14.

Page 6-6

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Plate 6-1

Eastern Steel Sdn Bhd Main Entrance. (4°17'10.9"N 103°26'04.5"E)

Plate 6-2

Iron Making Plant

Plate 6-3

Continues Slab Casting Area

Page 6-7

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Plate 6-4

Sinter Plant

Plate 6-5

Oxygen Plant

Plate 6-6

Raw Materials Yard Area

Page 6-8

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Plate 6-7

CO Gas Holder Area

Plate 6-8

Pesona Asli Sdn Bhd (0.1 km; South)

Page 6-9

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Plate 6-9

Tosoh Advanced Materials Sdn Bhd (1.8 km; East)

Plate 6-10

SK Bukit Kuang (2 km; South)

Plate 6-11

KBC (3.5 km; South East)

Page 6-10

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Plate 6-12

TATI University College (4 km; South)

Plate 6-13

SK Telok Kalong (4.2 km; East)

Plate 6-14

Petronas Gas Export Terminal (5 km; South East)

Page 6-11

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

6.3.2 Land Use within 1 km Radius

The Eastern Steel has been allocated in established industrial area. Immediate industrial area neighbours to this project site is the Pesona Asli which is located beside the Eastern Steel toward the south. Meanwhile other industries located approximately in 1km radius is located in the MIEL Teluk Kalung Industrial Area as listed in Table 6-2 and most of these industries is mostly engineering companies and fabricators. About 500m to the south-eastern boundary of the Project site is large piece of empty land committed for industrial development. No residential, institutional or commercial was found within 1km radius of Project Site.

Table 6-2 List of industries, residential, sensitive receptor (0-1km Radius)

Approximate Distance Direction from No Name from Project Site (km) Project Site

Industrial

1 Pesona Asli 0.1 South

2 Pioneer Engineering Sdn Bhd 0.4 East

3 Alam Dingin 0.4 East

4 Cr Asia Malaysia 0.55 East

5 HHA Associates Sdn Bhd 0.55 East

6 Hap Seng Building Materials Sdn Bhd 0.6 East

7 Zulkifli Ngah Engineering Sdn Bhd 0.7 East

8 Voss Workshop 0.7 East

9 WHS Global Engineering Sdn Bhd 0.9 East

10 Daya Secadyme Sdn Bhd 0.9 East

11 Handal Offshore Services 0.9 East

12 LJ Supply & Engineering Services Sdn Bhd 1.0 East Source(s): Land use survey, 2018-2019.

6.3.3 Land Use within 1-3 km Radius

Presently the land uses within 1-3km are occupied by industrial, institutions, residential, and amenities (Table 6-3). The industrial area mainly located in Teluk Kalung Industrial

Page 6-12

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Area. Within the 1-3km from the project site, residential such as Perumahan Bukit Kuang, Kg. Bukit Takar, Kg. Jong Berlabuh, Kg. Bukit Kuang, Kg. Bukit Anak Dara, Kg. Pengkalan Cicar and Kg. Pengkalan Cicar 2. There are Masjid, Clinic and School located 2.0 km to 2.6 km from the Project site.

Table 6-3 List of Industries, Residential and Institution (1-3km Radius) Approximate Distance from Direction from Project No Name Project Site (km) Site Industrial 1 Qualitest Engineering Sdn Bhd 1.1 East 2 MIEL Teluk Kalung Industrial Area 1.3 East 3 Optimistic Organic Sdn Bhd 1.4 East 4 UMW Fabritech Sdn Bhd 1.4 East 5 Tosoh Advanced Material Sdn Bhd 1.6 East 6 Malay-Sino Chemical 2.0 East 7 Huntsman Tioxide (M) Sdn Bhd 2.5 South East Residential 8 Perumahan Bukit Kuang 2.05 South 9 Kg. Bukit Takar 2.3 West 10 Kg. Jong Berlabuh 2.35 North West 11 Kg. Bukit Kuang 2.4 South East 12 Kg. Bukit Anak Dara 2.45 North East 13 Kg. Pengkalan Cicar 2 2.6 South 14 Kg. Pengkalan Cicar 2.95 South Institution & Others 15 Masjid Bukit Kuang 2.0 South 16 SK Bukit Kuang 2.0 South 17 Klinik Seda Bukit Kuang 2.05 South 18 SMK Bukit Kuang 2.5 South 19 SK Bukit Anak Dara 2.6 North Source(s): Land use survey, 2018-2019.

6.3.4 Land Use within 3-5 km Radius

The industries found within 3-5km radius are found towards the south east of Project Site which are Perwaja Steel Sdn Bhd, Kemaman Bitumen Company (KBC), Kemaman Port and Petronas Gas Export Terminal. Most of traditional villages were found within 3- 5km are Kg. Padang Kemunting, Kg. Paya, Kg. Sg. Terjun, Kg. Teluk Mengkuang, Kg Air, Kg. Baharu Mak Cili, Kg. Pancur, Kg. Bakau Tinggi, Kg. Teluk Kalung, Kg. Besut, Kg. Gong Limau, Kg. Peng. Yak Yah and Kg. Darat Kijal. Institutional, healthcare

Page 6-13

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019 facilities and amenities for 3-5km are tabulated in Table 6-4. For commercial and Utility, Giant Superstore Kijal and Bukit Takar Sanitary Landfill which are located respectively about 4.0 km and 3.4 km from the project site. The Cukai town was observed located more than 5.0 km toward the south from the Project. The existing land uses within 3- 5km of residential, institution, amenities and recreation within this area are tabulated in Table 6-4.

Table 6-4 List of Industrial, Residential, Institution and Amenities in 3-5km Radius

Approximate Distance from Direction from Project No Name Project Site (km) Site Industrial 1 Perwaja Steel Sdn Bhd 3.5 South East 2 Kemaman Bitumen Company (KBC) 3.5 South East 3 Kemaman Port 4.8 South East 4 Petronas Gas Bhd Tanjung Sulong 5.0 South East Residential 5 Kg. Padang Kemunting 3.4 3.4/ North West 6 Kg. Paya 3.45 3.45/ South 7 Kg. Sg. Terjun 3.5 3.5/ South East 8 Kg. Air 3.55 3.55/ South West 9 Kg. Baharu Mak Cili 3.8 3.8/ South West 10 Kg. Teluk Mengkuang 3.9 3.9/ South East 11 Kg. Bakau Tinggi 3.95 3.95/ South 12 Kg. Teluk Kalung 4.2 4.2/ East 13 Kg. Pancur 4.35 4.35/ East 14 Kg. Besut 4.4 4.4/ South 15 Kg. Gong Limau 4.75 4.75/ South 16 Kg. Darat Kijal 4.8 4.8/ North East 17 Kg. Jaya 4.95 4.95/ South West 18 Kg. Kuala Kemaman 5.0 5.0/ South West 19 Kg. Peng. Yak Yah 5.0 5.0/ West Commercial 20 Giant Superstore Kijal 4.0 North East Utility 21 Bukit Takar Sanitary Lanfill 3.4 South West Institution & Others 22 Mini Zoo Kemaman 3.3 West 23 SK Sultan Ismail & SMK Sultan Ismail 4.0 South 24 TATI University College 4.0 East

Page 6-14

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Approximate Distance from Direction from Project No Name Project Site (km) Site 25 SMK Kijal 4.15 North East 26 SK Telok Kalong 4.2 East 27 Darul Iman Training Centre (DITC) 4.5 South East Source(s): Google Map, 2019

6.3.5 Agriculture land

The main agricultural land found within 5km vicinity of the project site is rubber plantations. These rubber plantations can be found within Kemajuan Tanah Bukit Anak Dara, Kemajuan Tanah Bukit Setongkol and Bukit Pelanduk and Kemajuan Tanah Kg. Tabuan.

6.3.6 Peat Swamp Forest

Kemaman Reserve Forest is the main peat Swamp forest located western boundary of the Project site. There is also some peat swamp can be found in southern, eastern and northwest portion of the Project site.

6.4 FUTURE LAND USE Future land use surrounding the Eastern Steel is shown in Figure 6-5 based on the Rancangan Tempatan Daerah Kemaman (Pengubahan) 2011-2020 and has gazetted the area for industrial area. Since this area has been developed, hence there is no major change in the land use in near future, where the Project site will be surrounded with industrial lots.

6.4.1 Teluk Kalung

MDK has a plan to build 1.6-hectare Town and Business Centre as an expansion of the existing commercial area at Teluk Kalung area. This area will consist of shop houses at the 28.37 hectares which has been gazette as commercial area. It will be located about 2 km south from the Project site. It is estimated about 1,915 new houses unit will be built up to 2015 to capture the increase in population and demand from local and Cukai town. An area of 229.84 hectare has been identified to be potentially developed. The area is located 2.5-3.0 km east of the project site. MDK also committed to add numbers of public facilities such as clinic, library, mosque, post office and hall due to the increase in population at the Teluk Kalung area. The area will be concentrated to the south of the Project site.

Page 6-15

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

6.4.2 Kijal

To enhance the function of Kijal as Small District Centre, MDK planned to build Kijal rest area (R&R) at an area of 0.91 hectare. It will be located along Federal Road, about 2 km from the Project site. The R&R will comprise of shop lots, restaurant and public toilets. New residential area of 738.21 hectare will be developed at Kijal. Low to medium density houses will be built at Kg. Bukit Anak Dara, Bandar Baru Kijal and Bukit Penunjuk which is at northeast from the Project site.

Page 6-16

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Figure 6-4 Existing Land Use 1-5 km

Page 6-17

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

N

Not to Scale LEGEND:

Residential Commercial Industrial Flood Barrier Agriculture ESSB Land Forest Institution and Public facility Waterbody Buffer zone Eastern Steel Land River Flood Barrier

Source: Kemaman Local Plan (Amendment) 2011-2020

Figure 6-5 Future Land Use

Page 6-18

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

6.5 METEOROLOGY The general climate of the Project site is similar to the rest of Peninsular Malaysia being equatorial with high annual rainfall and relatively uniform high humidity and temperature or commonly known as hot and humid. There is a seasonal rhythm controlled largely by the synoptic wind system. According to Dale, 1956, 1959, four seasons can be recognized within any year: -

a) Northeast Monsoon (November until March) b) Intermonsoonal or transitional season (April to May) c) Southwest Monsoon (May to September) d) Intermonsoonal of transitional season (October to early November)

The climate information obtained is based on data collected from the nearest meteorological station, Hospital Kemaman Meteorological station (Latitude: 4o 13’ 53” N and Longitude: 103o 25’ 14” E) and Kertih Meteorological station (Latitude: 4o 32’ 24” N and Longitude: 103o 25’ 45” E). The data was collected from year 2008 to 2018 for Hospital Kemaman Meteorological station and from year 2016 to 2018 for Kerteh Meteorological station. The wind data from Kerteh Meteorological station was observed starting only from year 2016. Hospital Kemaman is situated approximately 6.5 km from the Project site boundary, meanwhile Kerteh Station is located approximately at 27 km.

6.5.1 Rainfall

The data for rainfall and number of rain day are from year 2008 to year 2018. The average annual rainfall was between 2008 and 2018 is 2714 mm with annual mean rain day of 174 days. The monthly rainfall and rain days peaks during the Northeast- monsoon season which is in December where mean monthly rainfall and rain day were recorded highest at 1730 mm (24 days) (Chart 6-1).

Table 6-5 Summary Record of Rainfall and Rain Day

Rainfall (mm) Jan Feb Mar April May Jun July Aug Sep Oct Nov Dec Annual Mean 332.9 79.9 198.9 84.6 164.5 103.4 138.7 165.7 192.3 268.1 500.1 736 2714.1 Max Rainfall 687.0 249.0 540.6 239.8 351.0 202.8 233.6 295.6 310.2 572.0 1060.8 1730 6472.8 Min Rainfall 75.6 10.8 12.0 3.8 33.4 23.8 10.8 15.2 90.0 47.8 193.4 374.6 891.2 Highest Year 2018 2013 2009 2009 2009 2014 2013 2012 2012 2011 2009 2014 2014 Lowest Year 2016 2010 2016 2016 2016 2010 2008 2008 2010 2014 2012 2008 2016 No of Rain Day Jan Feb Mar April May Jun July Aug Sep Oct Nov Dec Annual Mean 18.7 11.0 12.8 11.6 13.9 10.0 12.7 14.5 15.6 20.8 22.5 24.0 174 Max Rain Day 23 20 27 20 22 18 19 20 23 26 27 27 27 Min Rain Day 14 5 3 3 8 5 5 9 7 14 19 18 3 2011 2011 & Highest Year 2011 2016 2011 2009 2009 2017 2010 2015 2012 2018 2011 & 2012 2012 2014 2008 2014 & Lowest Year 2014 2010 2016 & 2016 2011 2011 2011 2011 2014 & 2017 2016 2016 2013 Source: Meteorological Department, 2008-2018. Note: 1) Def. means Defective Value

Page 6-19

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Chart 6-1 Graph for Rainfall and Rain Day

6.5.2 Temperature and Relative Humidity

Table 6-6 shows the summary record for the temperature and relative humidity for year 2008 to 2018 at Hospital Kemaman Station. The mean daily temperature recorded for these 11 years ranged from 25.0°C (mean daily minimum) to 29.4°C (mean daily maximum) while the annual 24 hours mean temperature was recorded 27.3°C. Hence, based on the record, May and April are the hottest month. The annual mean relative humidity for 24 hours was 85.0%. The highest and lowest humidity were recorded in December and April with readings of 85.9% and 82.9% respectively. Chart 6-2 shows the long-term 24-hour mean annual temperature.

6.5.3 Wind

The annual wind rose is based on the principal annual wind directions and speeds averaged over the period 2016 to 2018 at Kerteh Station (Chart 6-3). The annual mean speed recorded is 1.6 m/s and the percentage frequency of calm is 19.0%. The predominant wind was blowing from north with percentage of 41.3%, where the wind data indicated that 36.0% of the wind speed was between 0.3 to 1.5 m/s, 30.9% in the range of 1.6 m/s to 3.3 m/s,13.6% between 3.4 m/s to 5.4 m/s and the balance was in category of 5.5 m/s to 7.9 m/s.

Meanwhile for seasonal wind, generally it blows in all directions. However, the wind tends to predominant in certain direction depending on the monsoon period. During

Page 6-20

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

April, October, November – March period, the prevailing wind tend to be from north, while in May – September, the wind is from south.

Table 6-6 Summary Record of Temperature and Relative Humidity

Temperature (ºC) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Annual 24 Hr. Mean 25.9 26.6 27.3 28.2 28.4 28.3 27.8 27.7 27.6 27.2 26.5 26.1 27.3 Max. Temp 27.8 27.7 28.1 29.4 29.4 29.0 28.3 28.1 27.9 27.6 27.1 27.2 29.4 Min. Temp 25.0 25.8 26.5 27.6 27.7 27.7 27.2 27.4 27.2 26.8 25.9 25.4 25.0 2010 2008 Highest Year 2016 2010 & 2016 2016 2015 2015 2018 2015 & 2012 2015 2016 2016 2010 2011 2008 2011 2009 Lowest Year 2014 2015 2011 & 2009 2008 2008 & 2012 & & 2010 2014 2012 2012 2012 2011 Relative Humidity (%) Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Annual 24 Hr. Mean 82.9 78.8 78.8 78.2 79.1 79.4 79.4 79.3 79.5 82.3 86.3 86.7 80.8 Max RH 88.6 85.6 83.9 80.7 82.1 82.3 82.3 81.9 82.2 86.6 90.8 89.9 90.8 Min RH 79.4 73.4 74.3 74.6 74.1 75.7 74.7 74.7 75.7 77.8 81.1 82.0 73.4 Highest Year 2018 2013 2011 2009 2008 2008 2013 2015 2017 2017 2016 2016 2016 Lowest Year 2009 2018 2018 2018 2018 2010 2018 2018 2018 2018 2018 2018 2018 Source: Meteorological Department, 2008-2018.

Chart 6-2 Graph for Temperature & Relative Humidity

Page 6-21

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

This page has been intentionally left blank.

Page 6-22

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Chart 6-3 Wind Rose Diagram

Source: Meteorological Department Malaysia, 2019.

Page 6-23

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

6.6 HYDROLOGY The Project site is currently occupied with secondary forest vegetation and within the catchment of Sg. Cukai. Figure 6-6 shows the hydrology flow scheme to downstream of Sg. Cukai. The Project site falls under the Kuantan Hydrological region, which covers an area of approximately 3740 km2. The nearest river is Sg. Cukai, located least than 1 km to the west of the Project Site which flowing toward South and eventually join with Sg. Kemaman and finally discharges in the South China Sea. Sg. Ibuk is found flowing from north to the south at the west part about Project site about 3.17 km before confluence into Sg. Cukai. But no water intake points nearby the project site. The water intake points located at Loji Air Cherul (4º 6' 35" N 103º 11' 50" E) and Loji Air Bukit Sah (4°13'00.0"N 103°19'10.0"E).

The drainage system for stormwater and premise parameter drains flows toward the existing 5 Sedimentation/Detention Ponds within the IISM before discharged into Sg. Teluk Kalung and into Sg. Ruang. The drainage system of the Proposed Project as shown in Figure 6-8 and Figure 6-9. A separated drainage system is designed for process water and other process related areas and this does not mixed with the storm water. Current sewage will be treated in the existing septic tank for a total population 138 PE of which has been approved by IWK by letter dated 2nd Sept 2014, ref. no.: IWK/C/TR007/12/084. Detail approval and location of existing and proposed septic location is appended in Appendix C. Water sensitive receptors within 500 m of Project site is presented in Table 6-7.

Table 6-7 Water Sensitive Receptors Surrounding Project Site

Distance Water Sensitive Receptors 0 m to 1000 m Sg. Chukai Sg. Teluk Kalung Sg. Ruang 1000 m to 5000 m Sg. Kemaman South China Sea

6.7 GROUNDWATER

There are no groundwater schemes within the Project site. Based on the National Water Resources Study 2000-2050 for Terengganu, the nearest groundwater investigation study was conducted in Kg. Beris Merga, Kijal which is approximately 12 km from the Project site. The suggested yield for this well is 22 m3/hr. however, according to DID Kemaman confirmed that the well was not further developed due to poor groundwater yield.

Page 6-24

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Hydrogeologcial map of Project Site as illustrated in Figure 6-7 shows that, there is an active well at Cukai with very high potential aquifer and usage of the well is for industrial usage. No water analysis is conducted for this well. The proposed project is located in designated industrial area and no groundwater well is used in this area or in the village nearby. In addition, the IISM Plant also not generate process water and do not use groundwater for cooling process.

N

Not to Scale

LEGEND:

Project Site

Water Flow from Project Site River

Note: Not to scale Source: Topography Map, Published by the Director of National Mapping, Malaysia

Figure 6-6 Hydrological System of Sg. Chukai

Page 6-25

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

N

Not to Scale

LEGEND:

Project Site

WELL STATUS & TUBE WELL WITH YIELD

Active; > 10.0 m3/hr - ≤ 20.0 m3/hr

WELL USAGE

Industrial

QUALITY & POTABILITY OF WATER

No water analysis

GENERALISED AQUIFER POTENTIAL

Very high

LITHOLOGY Unconsolidated Deposits

Peat, humic clay and silt

Source: Hydrogeology Map, Published by the Director of Mineral & Geosciences, Malaysia

Figure 6-7 Hydrogeological System at Cukai

Page 6-26

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

This page has been intentionally left blank.

Page 6-27

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

N To Sg. Teluk Kalung To Sg. Teluk Kalung ST4 Not to Scale ST5

LEGEND: Industrial

Water Flow Direction

To Sg. Cukai

ST2

ST1

To Sg. Cukai

ST3 Note: Not to scale Source: Eastern Steel, 2019 To Sg.Ruang

Figure 6-8 Road and Drainage Layout of Proposed Project (Lot 6294)

Page 6-28

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

N

LEGEND: Industrial

Water Flow Direction

Note: Not to scale To Sg. Source: Eastern Steel, 2019

Teluk Kalung

Figure 6-9 Road and Drainage Layout of Proposed Project (Worker Quarter and Administrative Building)

Page 6-29

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

6.8 BASELINE ENVIRONMENTAL MONITORING

6.8.1 Ambient Air Quality

Ambient air quality monitoring was carried out at five (5) selected locations (Figure 6- 10). These monitoring locations were selected based on the sensitive receptors surrounding the Project site. Ambient air quality at four (4) sampling locations, A1, A2, A3 and A4 have been monitored since 2015. While one additional sampling location, A5, was monitored on 10th-11th June 2019. Monitoring results are summarized in Table 6-8 and compared with Malaysian Ambient Air Quality Standards (MAAQS) 2020. Detail descriptions of the ambient monitoring locations and parameters monitored are tabulated as followed:

Monitoring Description Coordinates Parameters Station At an open space. Southwest [N 04°17’07.65”; A1 of the Project Site, near to E 103°25’24.54”] Raw Material Yard At an open space. Kg Bukit [N 04°19’31.76”; PM , PM , SO , A2 Anak Dara, Northeast of the 10 2.5 2 E 103°26’39.10”] NO , CO, Heavy Project Site 2 Metals (Cd, Cr, At an open space. Kawasan [N 04°15’54.68”; Cu, Fe, Pb, Hg), A3 Perumahan Bukit Kuang, E 103°25’57.69”] Dioxin & Furan South of the Project Site and VOCs Proposed Worker Quarter in [N 04°17’37.77”; A4 New Phase E 103°25’58.51”] Kg Baharu Mak Cili (near to [N 04°15’19.53”; A5 Surau As-Soliheen) E 103°24’14.19”]

The ambient air quality monitoring results are compared with the baseline data in Y2008 as well as ambient air quality standard value by 2020 (Standard 2020) as stipulated in Malaysian Ambient Air Quality Standards (MAAQS) 2013. The detailed laboratory results are attached in Appendix D.

Based on the periodic ambient air quality monitoring results at A1 (Project Site), it 3 shown that PM10 level was mostly complied with the Standard Limit of 100 µg/m ; except in June 2019 which was detected 145 µg/m3. For the other months the 3 3 monitoring results ranging between 41 µg/m to 99 µg/m . PM2.5 monitoring results were ranging between 16 µg/m3 to 123 µg/m3. The high levels recorded were 65 µg/m3 and 123 µg/m3 in February 2019 and June 2019 respectively which exceed the Standard 3 Limit of 35 µg/m . The high level of dust (PM10 & PM2.5) is only detected occasionally and localized at the site. In July 2019, the PM10 and PM2.5 were detected well below the 3 3 limits at 50 µg/m and 23 µg/m respectively. Sulphur dioxide (SO2) and nitrogen dioxide

(NO2) were not detected in the monitoring exercise. For heavy metals, only Iron (Fe) was detected once in March 2019 with 1.25 µg/m3 and the rest of the heavy metals namely Cadmium (Cd), Chromium (Cr), Copper (Cu), Lead (Pb) and Mercury (Hg) were

Page 6-30

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019 not detected. Since no available ambient air standard limit for Fe in Malaysia, the Ontario’s Ambient Air Quality Criteria 2012 (OAAQC 2012) was used as reference limit. Where, the Fe level was well below the OAAQC 2012 reference limit of 4 µg/m3. Carbon monoxide (CO) was detected in very low level as compared with the Standard Limit of 10,000 mg/m3; mostly <0.5 mg/m3 and not more than 1 mg/m3.

3 As for A2 (Kg Bukit Anak Dara), PM10 complied with the Standard Limit of 100 µg/m with monitoring results ranging between 40 µg/m3 to 89 µg/m3. Meanwhile periodic 3 3 monitoring results for PM2.5 were ranging from 19 µg/m to 46 µg/m . Slight exceedances than the Standard Limit of 35 µg/m3 recorded in Jan 2019 (46 µg/m3), Feb 2019 (38 µg/m3), Mar 2019 (37 µg/m3), May 2019 (41 µg/m3), Jun 2019 (45 µg/m3) and 3 July 2019 (38 µg/m ). However, the PM2.5 results were fully complied with the limit of 50 3 µg/m set in the interim target 2 (IT-2) in 2018. SO2 and NO2 were not detected. Among heavy metals monitored, only Chromium (Cr) and Iron (Fe) were detected in low level in December 2018, March 2019 and June 2019. Cr was ranging between 0.03 µg/m3 - 0.070 µg/m3 and 0.54 µg/m3 - 1.59 µg/m3 for Fe. Since no available ambient air standard limit for both Cr and Fe in Malaysia, when compared with the OAAQC 2012 reference limits, both the Cr and Fe levels were well below the limit of 0.5 µg/m3 (Cr) and 4 µg/m3 (Fe). CO was detected in low level mostly <0.5-0.7 mg/m3.

At A3 (Kawasan Perumahan Bukit Kuang), monitoring results for PM10 were ranging between 42 µg/m3 to 93 µg/m3 which fully complied the Standard Limit of 100 µg/m3. As for PM2.5, October - December 2018 and July 2019 complied with the Standard Limit of 3 35 µg/m . Meanwhile for January – May 2019, the PM2.5 were exceeded the Standard 3 3 Limit of 35 µg/m but complied with the IT-2:2018 limit of 50 µg/m . PM2.5 in June 2019 3 was detected slightly higher than the IT-2:2018 limit with 53 µg/m . SO2 and NO2 were not detected. For heavy metals, Cr was detected only once in June 2019 (0.040 µg/m3) and Fe was detected in December 2018, March 2019 and June 2019 ranging between 0.09-0.90 µg/m3. Both the Cr and Fe levels were well below the OAAQC 2012 reference limits of 0.5 µg/m3 (Cr) and 4 µg/m3 (Fe). CO monitoring results was detected in low level mostly <0.5-0.7 mg/m3.

Periodic PM10 monitoring results at A4 (Proposed Worker Quarter in New Phase) were fully complied with the Standard Limit of 100 µg/m3 for September 2018 – July 2019.

While PM2.5, the results recorded in October and December 2018, January 2019, March 2019 and May 2019 were complied with the Standard Limit; ranging between 23-30 3 µg/m . The PM2.5 exceedances were detected in November 2018, February 2019, June 2019 and July 2019; however, the levels were still below the IT-2:2018 limit of 50 µg/m3. 3 SO2 was not detected while NO2 was detected in December 2018 (7 µg/m ) and 3 January 2019 (43 µg/m ). In which, NO2 was well below the Standard Limit of 280 µg/m3. For heavy metals, Cr and Pb were only detected in June 2019 which were 0.040 µg/m3 and 0.07 µg/m3 respectively. Fe was detected in December 2018, March 2019 and June 2019 which were 0.73 µg/m3, 0.16 µg/m3 and 0.56 µg/m3. The present of all these three heavy metals (Cr, Pb & Fe) are well below the respective Standard Limits/ OAAQC 2012 reference limits. CO monitoring results was detected in low level mostly <0.5-0.7 mg/m3.

Page 6-31

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

For this EIA study purpose, A5 (Kg Baharu Mak Cili) was monitored in June 2019. All the monitored parameters were fully complied with the Standard Limits. In which, PM10 3 3 and PM2.5 were detected at 73 µg/m and 34 µg/m respectively. SO2 and CO were not 3 3 detected. NO2 was detected at 35 µg/m . As for heavy metal, Cr (0.040 µg/m ) and Fe (0.67 µg/m3) were detected in low levels.

Additionally, in June 2019, there were three (3) addition parameters were sampled for all five (5) monitoring stations which are; Dioxin and Furan, Mercury (Hg) and Volatile Organic Compounds (VOCs). In which, VOCs were not detected (or below detection limit of 10 µg/m3) at all monitoring stations. Hg were detected at A2 and A5 with the value of 0.044 µg/m3 and 0.06 µg/m3; however, it was still below the OAAQC 2012 reference limit of 2 µg/m3. As for dioxin and furan, it was detected at very low concentration. At A1 was 0.000004 I-TEQ ng/m3 (min) - 0.000005 I-TEQ ng/m3 (max); at A2 was 0.000003 I-TEQ ng/m3 (min) - 0.000004 I-TEQ ng/m3 (max); at A3 were 0.000001 I-TEQ ng/m3 (min) - 0.000002 I-TEQ ng/m3 (max); at A4 were 0.000013 I-TEQ ng/m3 (min) - 0.000014 I-TEQ ng/m3 (min); and at A5 was 0.000005 I-TEQ ng/m3. The levels of dioxin and furan detected were well below the OAAQC 2012 reference limit of 0.1 pg TEQ/m3.

In overall, the ambient air quality in this area is generally good and well below the respective MAAQS 2020 and the OAAQC 2012 reference limits. Although, PM2.5 was occasionally detected slightly higher than MAAQS 2020 of 35 µg/m3. However, this shall be noted that this is due to various factors such as cumulative contribution from surrounding industrial activities in the Teluk Kalung Industrial Estate (TKIE), traffic passing by and also dry and hazy weather (especially in February 2019, where all stations were recorded exceeding the stipulated limit of 35 µg/m3). As such, the trend profile for PM10 and PM2.5 are illustrated in Graph 1 and Graph 2, respectively.

Page 6-32

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Graph 1 PM10 Level in Ambient Air

Graph 2 PM2.5 Level in Ambient Air

Page 6-33

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-8 Ambient Air Quality Monitoring Results A1 At an open space. Southwest of the Project Site, near to Raw Material Yard (4°17'07.65"N; 103°25'24.54"E) Parameters Baseline Data Sep – Dec Malaysian Ambient Air Quality Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 1st 2nd 2018 Standards, 2020 Particulate Matter 100 µg/m3 21 16 41 - 67 47 99 67 57 66 145 50 10µm (PM10) (µg/m3) (24 hours averaging time) Particulate Matter 35 µg/m3 - - 16 - 32 24 65 33 24 35 123 23 2.5µm (PM2.5) (µg/m3) (24 hours averaging time) Sulphur Dioxide as 80 µg/m3 <14 17 <5 <5 <5 <5 <5 <5 <5 <5 SO2 (µg/m3) (24 hours averaging time) Nitrogen Dioxide as 280 µg/m3 <10 <10 <5 <5 <5 <5 <5 <5 <5 <5 NO2 (µg/m3) (1 hour averaging time) Carbon Monoxide as 10 mg/m3 - - <0.5 - 0.7 0.7 0.7 <0.5 <0.5 0.7 <0.5 1 CO (mg/m3) (8 hours averaging time) Cadmium as Cd *0.025 µg/m3 0.02 <0.01 - - - <0.03 - - <0.03 - (µg/m3) (24 hours averaging time) Chromium as Cr *0.5 µg/m3 <0.01 <0.01 - - - <0.03 - - <0.03 - (µg/m3) (24 hours averaging time) *50 µg/m3 Copper as Cu (µg/m3) - - - <0.03 - - <0.03 - (24 hours averaging time) *4 µg/m3 Iron as Fe (µg/m3) 0.04 0.03 - - - 1.25 - - <0.03 - (24 hours averaging time) 1.5 µg/m3 Lead as Pb (µg/m3) <0.01 <0.01 - - - <0.03 - - <0.03 - (3 Months averaging time) 0.000004 Dioxin and Furan (min- *0.1 pg TEQ/m3 ------max) (ng/m3) (24 hours averaging time) 0.000005 *2 µg/m3 Mercury (µg/m3) ------<0.0002 - (24 hours averaging time)

Page 6-34

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

A1 At an open space. Southwest of the Project Site, near to Raw Material Yard (4°17'07.65"N; 103°25'24.54"E) Parameters Baseline Data Sep – Dec Malaysian Ambient Air Quality Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 1st 2nd 2018 Standards, 2020 VOCs (µg/m3) ------<10 - - Note: 1. The 1st baseline data was conducted on March 2008 and the 2nd baseline data was conducted on July-August 2008. 2. *Ontario’s Ambient Air Quality Criteria 2012 Source: ESM, 2019

Page 6-35

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

A2 At an open space. Kg. Bukit Anak Dara, Northeast of the Project Site (4°19'31.76"N; 103°26'39.10"E) Parameters Baseline Data Sep – Dec Malaysian Ambient Air Quality Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 1st 2nd 2018 Standards, 2020 Particulate Matter 10µm 100 µg/m3 30 13 40 - 64 64 60 76 65 82 89 68 (PM10) (µg/m3) (24 hours averaging time) Particulate Matter 2.5µm 35 µg/m3 - - 19 - 46 46 38 37 34 41 45 38 (PM2.5) (µg/m3) (24 hours averaging time) Sulphur Dioxide as SO2 80 µg/m3 <14 31 <5 <5 <5 <5 <5 <5 <5 <5 (µg/m3) (24 hours averaging time) Nitrogen Dioxide as NO2 280 µg/m3 <10 <10 <5 <5 57 <5 <5 13 <5 <5 (µg/m3) (1 hour averaging time) Carbon Monoxide as CO 10 mg/m3 - - <0.5 - 0.7 0.7 0.7 0.7 0.7 0.7 <0.5 0.7 (mg/m3) (8 hours averaging time) *0.025 µg/m3 Cadmium as Cd (µg/m3) <0.01 <0.01 <0.002 - <0.03 - - <0.03 - - <0.03 - (24 hours averaging time) *0.5 µg/m3 Chromium as Cr (µg/m3) <0.01 <0.01 <0.005 - 0.03 - - 0.03 - - 0.07 - (24 hours averaging time) *50 µg/m3 Copper as Cu (µg/m3) - - <0.005 - <0.03 - - <0.03 - - <0.03 - (24 hours averaging time) *4 µg/m3 Iron as Fe (µg/m3) 0.03 0.04 <0.005 - 0.7 - - 0.54 - - 1.59 - (24 hours averaging time) 1.5 µg/m3 Lead as Pb (µg/m3) <0.01 <0.01 <0.005 - <0.03 - - <0.03 - - <0.03 - (3 Months averaging time) 0.000003 Dioxin and Furan (min - *0.1 pg TEQ/m3 ------max) (ng/m3) (24 hours averaging time) 0.000004 *2 µg/m3 Mercury (µg/m3) ------0.044 - (24 hours averaging time) VOCs (µg/m3) ------<10 - - Note: 1. The 1st baseline data was conducted on March 2008 and the 2nd baseline data was conducted on July-August 2008. 2. *Ontario’s Ambient Air Quality Criteria 2012 Source: ESM, 2019

Page 6-36

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

A3 At an open space. Kawasan Perumahan Bukit Kuang, South of the Project Site (4°15'54.68"N; 103°25'57.69"E) Parameters Sep – Dec Malaysian Ambient Air Quality Baseline Data Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 2018 Standards, 2020 Particulate Matter 10µm 100 µg/m3 38 42 - 68 83 78 70 72 65 93 50 (PM10) (µg/m3) (24 hours averaging time) Particulate Matter 2.5µm 35 µg/m3 - 20 - 36 49 45 36 41 38 53 19 (PM2.5) (µg/m3) (24 hours averaging time) Sulphur Dioxide as SO2 80 µg/m3 <14 <5 <5 <5 <5 <5 <5 <5 <5 (µg/m3) (24 hours averaging time) Nitrogen Dioxide as NO2 280 µg/m3 <10 <5 - 6 <5 <5 <5 <5 35 <5 <5 (µg/m3) (1 hour averaging time) Carbon Monoxide as CO 10 mg/m3 - <0.5 - 0.7 0.7 0.7 0.7 0.7 0.7 <0.5 0.7 (mg/m3) (8 hours averaging time) <0.002 - *0.025 µg/m3 Cadmium as Cd (µg/m3) <0.01 - - <0.03 - - <0.03 - <0.03 (24 hours averaging time) <0.005 - *0.5 µg/m3 Chromium as Cr (µg/m3) <0.01 - - <0.03 - - 0.040 - <0.03 (24 hours averaging time) <0.005 - *50 µg/m3 Copper as Cu (µg/m3) - - - <0.03 - - <0.03 - <0.03 (24 hours averaging time) *4 µg/m3 Iron as Fe (µg/m3) 0.03 <0.5 - 0.67 - - 0.09 - - 0.90 - (24 hours averaging time) <0.005 - 1.5 µg/m3 Lead as Pb (µg/m3) <0.01 - - <0.03 - - <0.03 - <0.03 (3 Months averaging time) 0.000001 Dioxin and Furan (min - max) *0.1 pg TEQ/m3 ------(ng/m3) (24 hours averaging time) 0.000002 *2 µg/m3 Mercury (µg/m3) ------<0.0002 - (24 hours averaging time) VOCs (µg/m3) ------<10 - - Note: 1. The baseline data was conducted in March 2008. 2. *Ontario’s Ambient Air Quality Criteria 2012 Source: ESM, 2019

Page 6-37

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

A4 Within Project Site, in New Phase (4°17’37.77” N; 103°25’58.51”E) Parameters Malaysian Ambient Air Quality Sep – Dec 2018 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Standards, 2020

Particulate Matter 10µm (PM10) 53 - 70 55 68 54 77 58 96 68 100 µg/m3 (24 hours averaging time) (µg/m3) Particulate Matter 2.5µm (PM2.5) 29 - 49 28 40 29 37 23 49 38 35 µg/m3 (24 hours averaging time) (µg/m3)

Sulphur Dioxide as SO2 (µg/m3) <5 <5 <5 <5 <5 <5 <5 <5 80 µg/m3 (24 hours averaging time)

Nitrogen Dioxide as NO2 (µg/m3) <5 - 7 43 <5 <5 <5 <5 <5 <5 280 µg/m3 (1 hour averaging time)

Carbon Monoxide as CO (mg/m3) <0.5 0.7 0.7 <0.5 <0.5 <0.5 <0.5 <5 10 mg/m3 (8 hours averaging time) *0.025 µg/m3 Cadmium as Cd (µg/m3) <0.002 - <0.03 - - <0.03 - - <0.03 - (24 hours averaging time) *0.5 µg/m3 Chromium as Cr (µg/m3) <0.005 - <0.03 - - <0.03 - - 0.04 - (24 hours averaging time) *50 µg/m3 Copper as Cu (µg/m3) <0.005 - <0.03 - - <0.03 - - <0.03 - (24 hours averaging time) *4 µg/m3 Iron as Fe (µg/m3) <0.005 - 0.73 - - 0.16 - - 0.56 - (24 hours averaging time) 1.5 µg/m3 Lead as Pb (µg/m3) <0.005 - <0.03 - - <0.03 - 0.07 - (3 Months averaging time) Dioxin and Furan (min - max) 0.000013 - *0.1 pg TEQ/m3 ------(ng/m3) 0.000014 (24 hours averaging time) *2 µg/m3 Mercury (µg/m3) ------<0.0002 - (24 hours averaging time) - VOCs (µg/m3) - - - - - <10 - - Note: *Ontario’s Ambient Air Quality Criteria 2012 Source: ESM, 2019

Page 6-38

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

A5 Kg. Baharu Mak Cili (near to Surau As-Soliheen) Parameters (4°15’19.53” N ; 103°24’14.19”E) Malaysian Ambient Air Quality Jun-19 Standards, 2020 100 µg/m3 Particulate Matter 10µm (PM10) (µg/m3) 73 (24 hours averaging time) 35 µg/m3 Particulate Matter 2.5µm (PM2.5) (µg/m3) 34 (24 hours averaging time) 80 µg/m3 Sulphur Dioxide as SO2 (µg/m3) <5 (24 hours averaging time) 280 µg/m3 Nitrogen Dioxide as NO2 (µg/m3) 35 (1 hour averaging time) 10 mg/m3 Carbon Monoxide as CO (mg/m3) <0.5 (8 hours averaging time) *0.025 µg/m3 Cadmium as Cd (µg/m3) <0.03 (24 hours averaging time) *0.5 µg/m3 Chromium as Cr (µg/m3) 0.04 (24 hours averaging time) *50 µg/m3 Copper as Cu (µg/m3) <0.03 (24 hours averaging time) *4 µg/m3 Iron as Fe (µg/m3) 0.67 (24 hours averaging time) 1.5 µg/m3 Lead as Pb (µg/m3) <0.03 (3 Months averaging time) *0.1 pg TEQ/m3 Dioxin and Furan (min - max) (ng/m3) 0.000005 - 0.000005 (24 hours averaging time) *2 µg/m3 Mercury (µg/m3) 0.06 (24 hours averaging time) VOCs (µg/m3) <10 - Note: *Ontario’s Ambient Air Quality Criteria 2012 Source: ESM, 2019

Page 6-39

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

6.8.2 STACK EMISSION QUALITY

Stack emission monitoring has been conducted quarterly by the client since May 2015 to July 2019, for nine (9) existing stacks as shown in Figure 6-12. Monitoring of dust particulates concentration in the stack flue gases was carried out using isokinetic sampling technique according to method described in Malaysian Standard 1596:2003. Details of these stacks and parameters monitored are summarized as follows: -

Stack ID. Source Description Parameters Monitored

A1 Sinter Plant: Dosing Bag-Filter Total Particulate Matter (Total PM)

Total Particulate Matter (Total PM), Sulfur Dioxide (SO2), Nitrogen Dioxide (NO2), Lead (Pb), Non- A2 Sinter Plant: Sinter Head ESP Methane Volatile Organic Compound (NMVOC), #Cadmium (Cd), #Chromium (Cr), #Iron (Fe), #Mercury (Hg), *Dioxin and Furan.

A3 Sinter Plant: Sinter Tail ESP & Bag-Filter Total Particulate Matter (Total PM)

B1 Iron Making Plant: Bunker Bag-Filter Total Particulate Matter (Total PM)

B2 Iron Making Plant: Cast House Bag-Filter Total Particulate Matter (Total PM)

Total Particulate Matter (Total PM), B3 Iron Making Plant: Hot Stove Sulfur Dioxide (SO₂) & Nitrogen Dioxide (NO₂)

B5 Iron Making Plant: Dust Collector Total Particulate Matter (Total PM)

B6 Iron Making Plant: Dust Collector Total Particulate Matter (Total PM)

C2 Steel Making Plant: Secondary Deduster Total Particulate Matter (Total PM)

Note: 1. Stack emission monitoring is conducted in quarterly basis, except *Dioxin and Furan is monitored once a year (yearly basis) for Stack A2. 2. For EIA study purposes, additional parameters namely #Cadmium (Cd), #Chromium (Cr), #Iron (Fe) and #Mercury (Hg) are monitored for Stack A2 (one-time off). 3. Written Notification for the existing stack has been submitted to DOE and acknowledgement was granted from DOE. DOE Letters are appended in Appendix E.

Stack emission monitoring results are tabulated in Table 6-9 – Table 6-11 and the detailed laboratory analysis reports are attached in Appendix D.

As tabulated in Table 6-9, the dust particulates concentration (as Total PM) monitored for all the stacks in July 2019 were complied with the permissible limit of 50 mg/m3, under the Environmental Quality (Clean Air) Regulations, 2014 (hereafter refer to CAR Page 6-40

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

2014); except for Stack B1 (Bag-Filter at Iron Making Plant Bunker). When compared with the past monitoring records, it showed that Stack A1 (Bag-Filter at Sinter Plant Dosing House), Stack B6 (Bag-Filter at Iron Making Plant Material Transfer Station 2) and Stack C2 (Bag-Filter at Steel Making Plant) were well complied with the permissible limit at all time. As for the rest of the stacks, high concentration of dust particulate matter over the emission limit of 50 mg/m3 was detected occasionally. This happened in year 2015 during the early stage of the testing and commissioning of the IISM; and also, in December 2018 and March 2019 when the IISM resumed its operation after temporary ceased of operation. Subsequently, Eastern Steel has carried out maintenance program for the air pollution control system in June 2019. With this, in July 2019 monitoring exercise, the dust emission quality for all the stacks have been improved and mostly complying the permissible limit. Continual improvement for the air pollution control system will be carried out by the Competent Person (CP) and closely monitored by the Eastern Steel Management to ensure the stack emission quality comply with the CAR 2014 limit.

Table 6-9 Stack Monitoring Results for Total PM Environmental Total PM Quality (mg/m3) Stack (Clean Air) Source Description ID May/ Regulations, Jun - Aug-15 Sep-18 Dec-18 Mar-19 Jul-19 2014 15 (mg/m3) Sinter Plant: Dosing A1 3.7 34.0 5.4 7.4 19.8 11.7 Bag-Filter Sinter Plant: Sinter A2 - - 13.1 89.3 16.0 33.3 Head ESP Sinter Plant: Sinter A3 35.6 183.8 16.7 13.5 150.5 7.8 Tail ESP & Bag-Filter Iron Making Plant: B1 20.9 19.8 22.0 190.1 53.3 56.3 Bunker Bag-Filter Iron Making Plant: B2 429.9 6.6 10.8 106.8 77.7 17.4 Cast House Bag-Filter 50 Iron Making Plant: Hot B3 *6.9 *22.5 *19.8 *14.0 *585.2 *6.3 Stove Iron Making Plant: B5 Material Transfer - - - - 110.9 1.5 Station 1 Bag-Filter Iron Making Plant: B6 Material Transfer - - - - 9.5 10.4 Station 2 Bag-Filter Steel Making Plant: C2 2.7 48.3 19.5 4.3 8.1 8.7 Secondary Deduster Note: 1. “-” means Not Available. 2. *Oxygen reference content is 3%. Source: ESM, 2019

Page 6-41

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

VOCs was only monitored for Stack A2 (Electrostatic Precipitator at Sinter Head). Table 6-10 summarized the VOCs result for September 2018 – July 2019. VOCs was not detected.

Table 6-10 Stack A2 Monitoring Results for VOCs

Stack A2 Environmental Quality (Clean Air) Results (mg/m3) Parameter Regulations, 2014 Sep-18 Dec-18 Mar-19 Jul-19 (mg/m3) Benzene <0.01 <0.01 <0.01 <0.01 Toluene <0.01 <0.01 <0.01 <0.01 Chlorobenzene <0.01 <0.01 <0.01 <0.01 Ethylbenzene <0.01 <0.01 <0.01 <0.01 m&p-Xylene <0.01 <0.01 <0.01 <0.01 o-Xylenes <0.01 <0.01 <0.01 <0.01 Styrene <0.01 <0.01 <0.01 <0.01 Isopropylbenzene <0.01 <0.01 <0.01 <0.01 n-Propylbenzene <0.01 <0.01 <0.01 <0.01 Bromobenzene <0.01 <0.01 <0.01 <0.01 1,3,5-Trimethylbenzene <0.01 <0.01 <0.01 <0.01 2-Chlorotoluene <0.01 <0.01 <0.01 <0.01 - 4-Clorotoluene <0.01 <0.01 <0.01 <0.01 tert-Butylbenzene <0.01 <0.01 <0.01 <0.01 1,2,4-Trimethylbenzene <0.01 <0.01 <0.01 <0.01 sec-Butylbenzene <0.01 <0.01 <0.01 <0.01 Isopropyltoluene <0.01 <0.01 <0.01 <0.01 1,3-Dichlorobenzene <0.01 <0.01 <0.01 <0.01 1,4-Dichlorobenzene <0.01 <0.01 <0.01 <0.01 n-Butylbenzene <0.01 <0.01 <0.01 <0.01 1,2-Dichlorobenzene <0.01 <0.01 <0.01 <0.01 1,2,4-Trichlorobenzene <0.01 <0.01 <0.01 <0.01 Napthalene <0.01 <0.01 <0.01 <0.01 1,2,3-Trichlorobenzene <0.01 <0.01 <0.01 <0.01 Total VOCs <0.01 <0.01 <0.01 <0.01 75 Source: ESM, 2019

Page 6-42

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Besides, for Stack A2, additional parameters such as SO2, NO2 and heavy metals were monitored. The results in Table 6-11 showed that SO2 was only detected once in July 2019 at very low concentration (6 mg/m3), which was well below the permissible limit of 3 500 mg/m . NO2 was not detected in July 2019. For heavy metals, Mercury (Hg), Cadmium (Cd) and Chromium (Cr) were not detected. Lead (Pb), Iron (Fe) and Copper (Cu) were detected in low concentrations; 0.23 mg/m3, 1.91 mg/m3 and 0.02 mg/m3 respectively.

For Stack B3 (Hot Stove at Iron Making Plant), combustion gases namely SO2 and NO2 3 were monitored as well. In July 2019, SO2 was detected low at 29 mg/m while NO2 was not detected (Table 6-11).

In overall, for the exceedances in the selected stacks, Eastern Steel has committed to ensure the stack emission is always complying the permissible limit. Corrective action such as proper preventive measure and maintenance program will be carried out for all the stacks.

Page 6-43

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-11 Stack A2 and Stack B3 Monitoring Results for SO2, NO2 and Heavy Metals

3 Monitoring Results (mg/m ) Environmental Quality (Clean Air) Parameters Stack A2 Stack B3 Regulations, 2014

3 Sep-18 Dec-18 Mar-19 Jul-19 Jun-15 Aug-15 Sep-18 Dec-18 Mar-19 Jul-19 (mg/m )

Sulphur Dioxide as SO2 <1 <1 <1 6 <1 571 <1 <1 <1 29 500

Nitrogen Dioxide as NO2 <1 <1 33 <1 <1 10 <1 <1 <1 <1 400

Lead as Pb 0.13 4.72 3.63 0.23 ------1

Mercury as Hg - - - <0.001 ------

Cadmium as Cd - - - <0.005 ------

Chromium as Cr - - - <0.01 ------

Iron as Fe - - - 1.91 ------

Copper as Cu - - - 0.02 ------Note: Limit values are referred to Third Schedule [Regulation 13], Limit under Category B Production and Processing of Ferrous Metals (Iron and Steel Mill), Environmental Quality (Clean Air) Regulations, 2014. Source: ESM, 2019

Page 6-44

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

6.8.3 Ambient Noise

Plant boundary noise level monitoring was carried out quarterly at four (4) stations; at northeast corner of the plant boundary (N1), at southeast corner of the plant boundary (N2), at southwest of the plant boundary (N3) and at the northwest of the plant boundary (N4) (Figure 6-10). The noise level monitoring results are presented in Table 6-12 whilst the detailed laboratory results are attached in Appendix D.

Monitoring Description Coordinates Station [N 04°17’33.48”; N1 Northeast corner of the Plant Boundary E 103°26’08.02”] [N 04°16’53.21”; N2 Southeast corner of the Plant Boundary E 103°26’03.38”] [N 04°16’53.97”; N3 Southwest of the Plant Boundary E 103°25’25.56”] [N 04°17’32.33”; N4 Northwest of the Plant Boundary E 103°25’44.19”]

In June 2019, the average LAeq noise level during daytime at all stations were ranging from 52 dBA - 59.2 dBA, which were complied with the stipulated limit 65 dBA in the EIA Approval Condition No.36, and proposed limit of 70 dBA as per the Approved EMP (Operation) 2015 and The Planning Guidelines for Environmental Noise Limits and Control under category Designated Industrial Zones.

During the night-time monitoring, the average LAeq noise levels in June 2019 were ranging from 49.1 dBA - 58.2 dBA. The results were found slightly exceed the stipulated limit 55 dBA in the EIA Approval Condition No.36; however, when compared to The Planning Guidelines for Environmental Noise Limits and Control under category Designated Industrial Zones which have been proposed in the Approved EMP (Operation) 2015, night time noise levels complied with the proposed limit of 60 dBA.

When compared with the previous records, it can be concluded that the noise measurement results at the plant boundary were fully complied with the Planning Guidelines for Environmental Noise Limits and Control under category Designated Industrial Zones. It is consistent with the IISM operation within the established Teluk Kalung Industrial Estate (TKIE) for heavy industry.

Possible noise sources observed during both daytime and night-time were mainly attributed from the plant operational activities, transportation of raw materials and products, as well as equipment and machinery noise. Besides, substantial contribution is from the traffic noise along the main road.

Page 6-45

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-12 Noise Level Monitoring Results

Average LAeq [dB(A)] N2 N1 N3 N4 At Southeast corner of the plant At Northeast corner of the plant At Southwest of the plant boundary At Northwest of the plant boundary boundary Date boundary (4°16’53.97”N; 103°25’25.56”E) (4°17’32.33”N; 103°25’44.19”E) (4°16’53.21”N; 103°26’03.38”E) (4°17’33.48”N; 103°26’08.02”E)

Daytime Night Time Daytime Night Time Da ytime Night Tim e Dayt im e Night Time (7am to 10pm) (10pm to 7am) (7am to 10pm) (10pm to 7am) (7am to 10pm) (10pm to 7am) (7am to 10pm) (10pm to 7am)

August 2015 60.1 61.8 63.5 58.9 56.8 52.6 54.7 51.2

September 2018 57.6 52.0 52.0 51.1 51.1 49.8 59.9 57.0

December 2018 53.1 49.5 59.4 58.1 57.6 54.6 55.4 53

March 2019 58.8 55.5 60.9 59.0 55.8 54.9 58.0 57.5

June 2019 57.4 58.2 59.2 57.9 52.0 49.1 58.9 57.4

Stipulated Limit in the EIA Approval 65 dBA 55 dBA 65 dBA 55 dBA 65 dBA 55 dBA 65 dBA 55 dBA Condition No. 36 Proposed Limit in Approved EMP 70 dBA 60 dBA 70 dBA 60 dBA 70 dBA 60 dBA 70 dBA 60 dBA (operation) 2015 Source: ESM, 2019

Page 6-46

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

6.8.4 Receiving Water Quality

For this EIA study, the periodic water quality monitoring results of the receiving waterway from the Project site are summarized and presented here. Water samples and analysis were conducted at five (5) water monitoring stations as listed below and shown in Figure 6-10.

Monitoring Description Coordinates Station [N 04°17’33.5”; W1 Sg. Teluk Kalung, upstream of Project Site E 103°26’11.2”] [N 04°17’33.7”; W2 Sg. Teluk Kalung, downstream of Project Site E 103°25’51.7”] [N 04°17’55.1”; W3 Sg. Cukai, upstream of Project Site E 103°24’26.7”] [N 04°16’32.0”; W4 Sg. Ruang, upstream of Project Site E 103°25’46.0] [N 04°16’23.0”; W5 Confluence of Sg. Cukai and Sg. Ruang, downstream of Project Site E 103°25’00.8”]

The samples were analyzed for the Full Standard B parameters of Environmental Quality (Industrial Effluent) Regulations 2009 and the results will then be compared against with the Class III limit of the National Water Quality Standards for Malaysia.

The summary of the results is as tabulated in Table 6-13 and the detailed laboratory analysis results are attached in Appendix D. In which, the baseline monitoring results in year 2008 were also tabulated for reference.

In general, the periodic water quality monitoring results were mostly complied with the Class III limits of the National Water Quality Standards (NWQS) with some exceedances detected for pH and ammoniacal nitrogen (NH3-N). Meanwhile, most of the parameters were not detected in these sampling exercises for all monitoring stations which are BOD, Phenol, Free Chlorine, Sulfide, oil and grease, Formaldehyde and selected heavy metals (i.e. Hg, Cd, Cr6+, Cr3+, As, CN, Pb, Cu, Ni, Sn and Se).

The water quality for W1 (Sg Teluk Kalung, Upstream of the Project site) in March 2019 showed that the pH level was alkali with value of 10.1 and later in June 2019 was detected at 7.7, which was relatively neutral similar with previous quarters. Since the W1 station is located at upstream of project site, therefore this exceptional high value of pH water not contributed from the Project site. DO level was detected better than the Class III limits of 3-5 mg/l in March 2019 (6.1 mg/l) and June 2019 (5.3 mg/l). This was constantly maintained when compared with the baseline data. BOD was not detected, and COD was detected below than the Class III limit of 50 mg/l. Among the metals monitored and analyzed for, only Mn, Zn, B, Fe, Ag, Al and Ba were detected present while the rest were not detected. Mn was found above the Class III limit of 0.1 mg/l in August 2015, September 2018 and December 2018 with 0.43 mg/l, 0.47 mg/l Page 6-47

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019 and 0.17 mg/l. However, it was below detection limit in March 2019 while in June 2019 detected at 0.08 mg/l. Ag was detected occasionally at 0.03 mg/l in August 2018 and June 2019. Fe were detected below the Class III limit in March 2019 and June 2019.

Ammoniacal Nitrogen (NH3-N) was detected above the Class III limit of 0.9 mg/l in March 2019 (1.0 mg/l) while in June 2019 was below the Class III limit with 0.5 mg/l.

Ammoniacal Nitrogen (NH3-N) was fluctuated with 1.4 mg/l (August 2015), 0.8 mg/l (September 2018) and 5.8 mg/l (December 2018). This was contributed by the upstream activities i.e. from the decay of discharged organic compound from the neighbour industries.

Further down the Sg Teluk Kalung at W2 (Downstream of the Project site), the water was relatively neutral with pH 7 (March 2019) and pH 7.8 (June 2019); which is better when compared with the previous years in 2008 and 2018 (pH 3.45-3.75). DO was slightly better than the Class III limit while concentration of COD and TSS were detected below the Class III limits, at 14 – 81 mg/l and 52 - 64 mg/l respectively. Metals that present in trace amount were Mn (0.08 mg/l), Cu (0.04 mg/l), Zn (0.03-0.19 mg/l), B (2.0 mg/l), Fe (0.5-0.74 mg/l), Al (0.58 mg/l) and Ag (0.06 mg/l). Fluoride (F) and colour were detected at 0.6-0.9 mg/l and 10-30 TCU, respectively. Ammoniacal

Nitrogen (NH3-N) was exceeded the Class III limit of 0.9 mg/l with reading of 1-4.8 mg/l.

W3 is located at upstream of Project site, at Sg Cukai. Analysis results showed that the water quality for W3 was relatively acidic in September 2018 and December 2018 with pH 4.6 and pH 4.3. Since W3 is located at upstream of the Project site hence no indication from the Project site and this may cause by upstream activities. However, the water become neutral (pH 7.1) in both March 2019 and June 2019. DO was slightly better than the Class III limit while BOD was below detection limit. Other parameters were complied with Class III limit with either in low concentration or not detected. Except for Ammoniacal Nitrogen (NH3-N), which was fluctuated from 0.7 mg/l (March 2019) to 9.1 mg/l (June 2019) similar for previous quarters.

The water quality at W4 (Sg Ruang, upstream of the Project site) was observed slightly polluted and fall in between Class II - Class III category. The water was neutral (pH 7.1 - 7.7). BOD was not detected where DO, COD and TSS were detected at 5.3 - 5.6 mg/l, 25-91 mg/l and 46 - 68 mg/l, respectively. For the metal monitored, infrequent exceedances were only detected for Mn, Fe and Ag. Ammoniacal Nitrogen

(NH3-N) was detected well above the Class III limit of 0.9 mg/l with concentration of 0.5 - 0.8 mg/l.

At the confluence point of Sg. Cukai and Sg. Ruang, downstream of Project Site (W5), the water quality for W5 was slightly polluted and fall in between Class II - Class III category. The pH reading was detected at pH 7.4 – 7.8. DO was slightly better than the Class III limit with 5.4 mg/l. COD was detected below the Class III limit in March 2019 (23 mg/l) but exceeded the limit in June 2019 (94 mg/l). Most likely the high concentration of COD was contributed from Sg Ruang, upstream of the Project site as

Page 6-48

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019 it was detected high at W4 (91 mg/l). All other parameters including the metals monitored and analyzed for were complied with the respective Class III limits. Also, the

Ammoniacal Nitrogen (NH3-N) was detected within 0.2 - 0.3 mg/l, well below the Class III limit of 0.9 mg/l.

In overall, the water quality in the vicinity of the Project site were fall in Class II – Class III category. In addition, it shall be noted that the operation of Eastern Steel IISM is mainly dry process and does not generate any process effluent. Hence, it is consistent with the water quality at W5 where the final receiving point for the Project site is tested slightly polluted and fall in between Class II - Class III category.

The trend profiles for COD, TSS, Ammoniacal Nitrogen, Manganese and Iron concentration are illustrated in Graph 3 to 7.

Graph 3 COD Concentration in water samples

Page 6-49

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Graph 4 TSS Concentraation in water samples

Graph 5 Ammoniacal Nitrigen Concentration in water samples

Page 6-50

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Graph 6 Manganese Concentration in water samples

Graph 7 Iron Concentration in water samples

Page 6-51

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-13 Water Quality Results

1Class III W1 Parameter Unit Standard B Limit Sg. Teluk Kalung, upstream of project site (4°17’33.5” N; 103°26’11.2”E) Baseline Baseline Baseline Baseline Monitoring Date - - - Mar-08 Mar-08 Jul-08 Jul-08 Aug -15 Sep-18 Dec-18 Mar-19 Jun-19 Low Tide (8.30am) High Tide (3.55pm) Low Tide (8.15am) High Tide (3.45pm) pH - 5.5-9.0 5.0-9.0 7.1 7.3 3.9 4.0 6.5 7.3 7.2 10.1 7.7 Temperature °C 40 - 29 32 27.5 32 26.3 25.3 25.1 25.8 26.7 Dissolved Oxygen (DO) mg/l - 3-5 6.0 5.6 6.45 6.7 6.7 - 6.4 6.1 5.3 Biochemical Oxygen Demand (BOD) mg/l 50 6 2 3 9 4 <2 <2 <2 <2 <2 Chemical Oxygen Demand (COD) mg/l 200 50 13 13 54 57 41 13 20 17 33 Total Suspended Solids (TSS) mg/l 100 150 14 34 72 91 43 6 14 9 47 Mercury (Hg) mg/l 0.05 0.004 - - - - <0.001 <0.001 <0.001 <0.001 <0.001 Cadmium (Cd mg/l 0.02 0.01 - - - - <0.01 <0.01 <0.01 <0.01 <0.01 Chromium Hexavalent (Cr6+) mg/l 0.05 1.4 - - - - <0.01 <0.01 <0.01 <0.01 <0.01 Chromium Trivalent (Cr3+) mg/l 1.0 2.5 - - - - <0.01 <0.01 <0.01 <0.01 <0.01 Arsenic (As) mg/l 0.10 0.4 - - - - <0.001 <0.001 <0.001 <0.001 <0.001 Cyanide (CN) mg/l 0.10 0.6 - - - - <0.02 <0.02 <0.02 <0.02 <0.02 Lead (Pb) mg/l 0.5 0.02 - - - - <0.02 <0.02 <0.02 <0.02 <0.02 Copper (Cu) mg/l 1.0 - - - - - 0.02 <0.01 <0.01 <0.01 0.04 Manganese (Mn) mg/l 1.0 0.1 - - - - 0.43 0.47 0.17 <0.01 0.08 Nickel (Ni) mg/l 1.0 0.9 - - - - <0.01 <0.01 <0.01 <0.01 <0.01 Tin (Sn) mg/l 1.0 0.004 - - - - <0.004 <0.004 <0.004 <0.004 <0.004 Zinc (Zn) mg/l 2.0 0.4 - - - - 0.15 0.15 0.07 0.02 0.07 Boron (B) mg/l 4.0 - - - - - <0.1 0.2 0.2 0.8 2.0 Iron (Fe) mg/l 5.0 1 - - - - 16.7 1.58 3.58 0.82 0.46 Silver (Ag) mg/l 1.0 0.0002 - - - - 0.03 <0.01 <0.01 <0.01 0.03 Aluminium (Al) mg/l 15 - - - - - 1.93 0.67 0.85 <0.05 0.34 Selenium (Se) mg/l 0.5 0.25 - - - - <0.005 <0.005 <0.005 <0.005 <0.005 Barium (Ba) mg/l 2.0 - - - - - <0.05 <0.05 0.24 <0.05 <0.05 Fluoride (F) mg/l 5.0 10 - - - - 1.0 0.2 0.4 0.5 1.0 Phenol mg/l 1.0 - - - - - <0.001 <0.001 <0.001 <0.001 <0.1

Free Chlorine (Cl2) mg/l 2.0 - - - - - <0.1 <0.1 <0.1 <0.01 <0.1 Sulfide (S2-) mg/l 0.50 - - - - - <0.05 <0.05 <0.05 0.05 <0.05 Oil and Grease (O&G) mg/l 10 N - - - - <1 <1 <1 <1 <1

Ammoniacal Nitrogen (NH3-N) mg/l 20 0.9 - - - - 1.4 0.8 5.8 1 0.5 Color TCU 200 - - - - - 10 5 10 20 20 Count/ Formaldehyde 2.0 - - - - - <0.1 <0.1 <0.1 <0.1 <0.1 100ml 76 73 52 56 76 74 75 74 Water Quality Index (WQI) - - - Class III Class III Class III Class III Class III - Class III Class III Class III Slightly Polluted Slightly Polluted Polluted Polluted Slightly Polluted Slightly Polluted Slightly Polluted Slightly Polluted Note: 1. Class III limit means parameter limits of Class III in the National Water Quality Standards for Malaysia by Department of Environment (DOE) 2. N means free from visible film, sheen, discoloration and deposits. 3. < means less than the minimum detectable limit or not detected (ND). 4. TCU means True Color Unit Source: ESM, 2019

Page 6-52

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

1Class III W3 Unit Standard B W2 Parameter Limit Sg. Cukai, upstream of project site - - Sg. Teluk Kalung, downstream of project site (4°17’33.7”N; 103°25’51.7”E) - (4°17’55.1”N; 103°24’26.7”E) Baseline Baseline Monitoring Date - - - Mar-08 Mar-08 Aug -15 Sep-18 Dec-18 Mar-19 Jun-19 Sep -18 Dec-18 Mar-19 Jun-19 Low Tide (8.50am) High Tide (4.20pm) pH - 5.5-9.0 5.0-9.0 3.75 3.45 3.6 6.4 7.1 7 7.8 4.6 4.3 7.1 7.1 Temperature °C 40 - 28.0 32.5 26.1 25.1 25.5 26.1 26.5 25.2 25 25.8 25.9 Dissolved Oxygen (DO) mg/l - 3-5 5.55 5.55 6.7 - 6.2 5.7 5.2 - 5.8 6.2 5.4 Biochemical Oxygen Demand (BOD) mg/l 50 6 7 6 <2 <2 <2 <2 <2 <2 <2 <2 <2 Chemical Oxygen Demand (COD) mg/l 200 50 61 57 47 10 37 14 81 17 21 22 33 Total Suspended Solids (TSS) mg/l 100 150 74 65 34 12 8 52 64 3 12 28 16 Mercury (Hg) mg/l 0.05 0.004 ND (<0.001) ND (<0.001) <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 Cadmium (Cd mg/l 0.02 0.01 ND (<0.003) ND (<0.003) <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 Chromium Hexavalent (Cr6+) mg/l 0.05 1.4 ND (<0.02) ND (<0.02) <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 Chromium Trivalent (Cr3+) mg/l 1.0 2.5 ND (<0.02) ND (<0.02) <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 Arsenic (As) mg/l 0.10 0.4 ND (<0.01) ND (<0.01) <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 Cyanide (CN) mg/l 0.10 0.6 ND (<0.02) ND (<0.02) <0.02 <0.02 <0.02 <0.02 <0.002 <0.02 <0.02 <0.02 <0.02 Lead (Pb) mg/l 0.5 0.02 ND (<0.02) 0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 Copper (Cu) mg/l 1.0 - 0.025 0.017 0.02 <0.01 <0.01 <0.01 0.04 <0.01 <0.01 0.03 <0.01 Manganese (Mn) mg/l 1.0 0.1 0.180 0.148 0.44 0.29 0.08 <0.01 0.08 0.11 0.04 0.02 0.09 Nickel (Ni) mg/l 1.0 0.9 0.02 0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 Tin (Sn) mg/l 1.0 0.004 ND (<0.01) ND (<0.01) <0.004 <0.004 <0.004 <0.004 <0.004 <0.004 <0.004 <0.004 <0.004 Zinc (Zn) mg/l 2.0 0.4 0.137 0.141 0.18 0.12 0.03 0.03 0.19 0.07 0.03 0.05 0.07 Boron (B) mg/l 4.0 - 0.059 0.037 <0.1 0.4 1 <0.1 2.0 0.3 1 3.2 1.5 Iron (Fe) mg/l 5.0 1 5.51 3.14 18.7 6.97 6.26 0.5 0.74 0.58 2.79 0.34 0.62 Silver (Ag) mg/l 1.0 0.0002 - - 0.08 <0.01 <0.01 <0.01 0.06 <0.01 <0.01 <0.01 <0.01 Aluminium (Al) mg/l 15 - - - 1.36 0.40 0.58 <0.05 0.58 0.86 0.62 <0.05 0.43 Selenium (Se) mg/l 0.5 0.25 - - <0.005 <0.005 <0.005 <0.005 <0.005 <0.005 <0.005 <0.005 <0.005 Barium (Ba) mg/l 2.0 - - - <0.05 <0.05 0.16 <0.05 <0.05 <0.05 1.31 <0.05 <0.05 Fluoride (F) mg/l 5.0 10 - - 1.0 0.2 0.4 0.6 0.9 <0.1 0.6 0.1 0.3 Phenol mg/l 1.0 - ND (<0.001) 0.001 <0.001 <0.001 <0.001 <0.001 <0.1 <0.001 <0.001 <0.001 <0.1

Free Chlorine (Cl2) mg/l 2.0 - ND (<0.02) ND (<0.02) <0.1 <0.1 <0.1 <0.01 <0.1 <0.1 <0.1 <0.01 <0.1 Sulfide (S2-) mg/l 0.50 - ND (<0.1) ND (<0.1) <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 Oil and Grease (O&G) mg/l 10 N ND ND <1 <1 <1 <1 <1 <1 <1 <1 <1

Ammoniacal Nitrogen (NH3-N) mg/l 20 0.9 0.28 0.22 0.8 0.7 4.8 1 4.8 0.7 3.8 0.7 9.1 Color TCU 200 - - - 5 150 100 10 30 10 10 20 20 Formaldehyde Count/100ml 2.0 - - - <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 68 71 65 67 61 64 58 81 58 81 Class III Class III Class III Class III Water Quality Index (WQI) - - Class III Class III Class III Class II Class III - Class II Slightly Slightly Slightly Slightly Slightly Polluted Slightly Polluted Polluted Clean Polluted Clean Polluted Polluted Polluted Polluted Note: 1. Class III limit means parameter limits of Class III in the National Water Quality Standards for Malaysia by Department of Environment (DOE) 2. N means free from visible film, sheen, discoloration and deposits. 3. < means less than the minimum detectable limit or not detected (ND). 4. TCU means True Color Unit Source: ESM, 2019

Page 6-53

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

W4 Parameter Unit Standard B 1Class III Limit Sg. Ruang, upstream of project site (4°16’32.0”N; 103°25’46.0”E) Baseline Baseline Baseline Baseline Monitoring Date - - - Mar-08 Mar-08 Jul-08 Jul-08 Aug -15 Sep-18 Dec-18 Mar-19 Jun-19 Low Tide (9.10am) High Tide (4.35pm) Low Tide (9.20am) High Tide (4.50pm) pH - 5.5-9.0 5.0-9.0 6.75 6.7 6.4 6.3 4.1 6.6 6.8 7.1 7.7 Temperature °C 40 - 29.5 31 28 32.5 26.4 25.1 25.2 25.9 26.1 Dissolved Oxygen (DO) mg/l - 3-5 5.55 5.7 6.05 6.05 5.1 - 5.9 5.6 5.3 Biochemical Oxygen Demand (BOD) mg/l 50 6 3 2 6 6 <2 <2 <2 <2 <2 Chemical Oxygen Demand (COD) mg/l 200 50 19 10 51 47 42 12 32 25 91 Total Suspended Solids (TSS) mg/l 100 150 40 32 32 44 17 4 12 68 46 Mercury (Hg) mg/l 0.05 0.004 ND (<0.001) ND (<0.001) ND (<0.001) ND (<0.001) <0.001 <0.001 <0.001 <0.001 <0.001 Cadmium (Cd mg/l 0.02 0.01 ND (<0.005) ND (<0.005) ND (<0.003) ND (<0.005) <0.01 <0.01 <0.01 <0.01 <0.01 Chromium Hexavalent (Cr6+) mg/l 0.05 1.4 ND (<0.02) ND (<0.02) ND (<0.02) ND (<0.02) <0.01 <0.01 <0.01 <0.01 <0.01 Chromium Trivalent (Cr3+) mg/l 1.0 2.5 ND (<0.02) ND (<0.02) ND (<0.02) ND (<0.02) <0.01 <0.01 <0.01 <0.01 <0.01 Arsenic (As) mg/l 0.10 0.4 ND (<0.01) ND (<0.01) ND (<0.01) ND (<0.01) <0.001 <0.001 <0.001 <0.001 <0.001 Cyanide (CN) mg/l 0.10 0.6 ND (<0.02) ND (<0.02) ND (<0.02) ND (<0.02) <0.02 <0.02 <0.02 <0.02 <0.02 Lead (Pb) mg/l 0.5 0.02 ND (<0.02) ND (<0.02) 0.02 0.03 <0.02 <0.02 <0.02 <0.02 <0.02 Copper (Cu) mg/l 1.0 - 0.009 0.009 0.013 0.010 0.03 <0.01 <0.01 0.03 0.04 Manganese (Mn) mg/l 1.0 0.1 0.056 0.187 0.035 0.035 0.64 0.33 0.27 0.13 0.03 Nickel (Ni) mg/l 1.0 0.9 ND (<0.02) ND (<0.02) 0.01 ND(<0.01) <0.01 <0.01 <0.01 <0.01 <0.01 Tin (Sn) mg/l 1.0 0.004 ND (<0.01) ND (<0.01) ND (<0.01) ND (<0.01) <0.004 <0.004 <0.004 <0.004 <0.004 Zinc (Zn) mg/l 2.0 0.4 0.162 0.610 0.084 0.084 0.09 0.06 0.02 0.05 0.07 Boron (B) mg/l 4.0 - 1.152 0.964 0.409 0.655 0.2 0.4 1 3.4 2.4 Iron (Fe) mg/l 5.0 1 2.39 3.58 3.39 1.46 8.43 0.82 4.21 1.3 0.25 Silver (Ag) mg/l 1.0 0.0002 - - - - 0.27 <0.01 <0.01 0.03 0.02 Aluminium (Al) mg/l 15 - - - - - <0.05 0.29 0.91 0.12 0.35 Selenium (Se) mg/l 0.5 0.25 - - - - <0.005 <0.005 <0.005 <0.005 <0.005 Barium (Ba) mg/l 2.0 - - - - - <0.05 <0.05 5.44 <0.05 <0.05 Fluoride (F) mg/l 5.0 10 - - - - 1.1 0.4 0.4 0.2 1.6 Phenol mg/l 1.0 - ND (<0.001) ND (<0.001) ND (<0.001) ND (<0.001) <0.001 <0.001 <0.001 <0.001 <0.1

Free Chlorine (Cl2) mg/l 2.0 - ND (<0.02) ND (<0.02) ND (<0.02) ND (<0.02) <0.1 <0.1 <0.1 <0.01 <0.1 Sulfide (S2-) mg/l 0.50 - ND (<0.1) ND (<0.1) ND (<0.1) ND (<0.1) <0.05 <0.05 <0.05 <0.05 <0.05 Oil and Grease (O&G) mg/l 10 N ND ND ND ND <1 <1 <1 <1 <1

Ammoniacal Nitrogen (NH3-N) mg/l 20 0.9 0.18 0.25 0.09 0.06 3.1 0.8 3.3 0.5 0.8 Color TCU 200 - - - - - 5 20 30 20 10 Formaldehyde Count/100ml 2.0 - - - - - <0.1 <0.1 <0.1 <0.1 <0.1 83 86 79 80 60 72 77 66 Water Quality Index (WQI) - - Class II Class II Class II Class II Class III - Class III Class II Class III Clean Clean Slightly Polluted Slightly Polluted Slightly Polluted Slightly Polluted Slightly Polluted Slightly Polluted Note: 1. Class III limit means parameter limits of Class III in the National Water Quality Standards for Malaysia by Department of Environment (DOE) 2. N means free from visible film, sheen, discoloration and deposits. 3. < means less than the minimum detectable limit or not detected (ND). 4. TCU means True Color Unit Source: ESM, 2019

Page 6-54

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

W5 Parameter Unit Standard B 1Class III Limit At the confluence of Sg. Chukai and Sg. Ruang downstream of project site (4°16’23.0”N; 103°25’00.8”E) Baseline Baseline Baseline Baseline Monitoring Date - - - Mar-08 Mar-08 Jul-08 Jul-08 Aug -15 Sept - 18 Dec-18 Mar-19 Jun-19 Low Tide (10.45am) High Tide (6.20pm) Low Tide (11.10am) High Tide (6.30pm) pH - 5.5-9.0 5.0-9.0 7.45 6.95 7.05 7.0 6.4 6.8 6.8 7.4 7.8 Temperature °C 40 - 30 30 29.5 30.5 26.4 25.2 25.2 26.2 26.2 Dissolved Oxygen (DO) mg/l - 3-5 5.5 3.0 6.6 6.75 5.1 - 6.1 5.4 5.4 Biochemical Oxygen Demand (BOD) mg/l 50 6 2 2 7 8 <2 <2 <2 <2 <2 Chemical Oxygen Demand (COD) mg/l 200 50 10 10 71 54 35 19 24 23 94 Total Suspended Solids (TSS) mg/l 100 150 14 20 20 14 6 6 14 60 52 Mercury (Hg) mg/l 0.05 0.004 ND (<0.001) ND (<0.001) ND (<0.001) ND (<0.001) <0.001 <0.001 <0.001 <0.001 <0.001 Cadmium (Cd mg/l 0.02 0.01 ND (<0.005) ND (<0.005) ND (<0.003) ND (<0.005) <0.01 <0.01 <0.01 <0.01 <0.01 Chromium Hexavalent (Cr6+) mg/l 0.05 1.4 ND (<0.02) ND (<0.02) ND (<0.02) ND (<0.02) <0.01 <0.01 <0.01 <0.01 <0.01 Chromium Trivalent (Cr3+) mg/l 1.0 2.5 ND (<0.02) ND (<0.02) ND (<0.02) ND (<0.02) <0.01 <0.01 <0.01 <0.01 <0.01 Arsenic (As) mg/l 0.10 0.4 ND (<0.01) ND (<0.01) ND (<0.01) ND (<0.01) <0.001 <0.001 <0.001 <0.001 <0.001 Cyanide (CN) mg/l 0.10 0.6 ND (<0.02) ND (<0.02) ND (<0.02) ND (<0.02) <0.02 <0.02 <0.02 <0.02 <0.02 Lead (Pb) mg/l 0.5 0.02 ND (<0.02) ND (<0.02) ND (<0.02) 0.02 <0.02 <0.02 <0.02 <0.02 <0.02 Copper (Cu) mg/l 1.0 - 0.011 0.020 0.014 0.012 0.02 0.01 <0.01 0.03 0.03 Manganese (Mn) mg/l 1.0 0.1 0.118 0.085 0.006 0.005 0.30 0.14 0.13 0.04 0.04 Nickel (Ni) mg/l 1.0 0.9 ND (<0.02) 0.01 0.01 0.01 <0.01 <0.01 <0.01 <0.01 <0.01 Tin (Sn) mg/l 1.0 0.004 ND (<0.01) ND (<0.01) ND (<0.01) ND (<0.01) <0.004 <0.004 <0.004 <0.004 <0.004 Zinc (Zn) mg/l 2.0 0.4 0.555 0.418 0.05 0.032 0.06 0.06 0.02 0.05 0.06 Boron (B) mg/l 4.0 - 0.019 0.139 1.320 1.272 0.3 0.6 0.8 3.5 1.8 Iron (Fe) mg/l 5.0 1 2.64 1.70 0.66 0.19 0.62 0.75 3.06 0.5 0.28 Silver (Ag) mg/l 1.0 0.0002 - - - - 0.03 0.02 <0.01 <0.01 0.02 Aluminium (Al) mg/l 15 - - - - - <0.05 0.40 0.32 <0.05 0.19 Selenium (Se) mg/l 0.5 0.25 - - - - <0.005 <0.005 <0.005 <0.005 <0.005 Barium (Ba) mg/l 2.0 - - - - - <0.05 <0.05 <0.05 <0.05 <0.05 Fluoride (F) mg/l 5.0 10 - - - - 1.2 0.4 0.7 0.2 1.8 Phenol mg/l 1.0 - ND (<0.001) ND (<0.001) ND (<0.001) 0.001 <0.001 <0.001 <0.001 <0.001 0.1

Free Chlorine (Cl2) mg/l 2.0 - ND (<0.02) ND (<0.02) ND (<0.02) ND (<0.02) <0.1 <0.1 <0.1 <0.01 <0.1 Sulfide (S2-) mg/l 0.50 - 0.1 0.2 ND (<0.1) ND (<0.1) <0.05 <0.05 <0.05 <0.05 <0.05 Oil and Grease (O&G) mg/l 10 N ND ND ND ND <1 <1 <1 <1 <1

Ammoniacal Nitrogen (NH3-N) mg/l 20 0.9 0.05 0.06 0.12 0.06 1.6 0.8 2.8 0.2 0.3 Color TCU 200 - - - - - 5 5 30 20 10 Formaldehyde Count/100ml 2.0 - - - - - <0.1 <0.1 <0.1 <0.1 <0.1 89 79 78 81 74 75 79 72 Water Quality Index (WQI) - Class II Class II Class II Class II Class III - Class III Class II Class III Clean Slightly Polluted Slightly Polluted Clean Slightly Polluted Slightly Polluted Slightly Polluted Slightly Polluted Note: 1. Class III limit means parameter limits of Class III in the National Water Quality Standards for Malaysia by Department of Environment (DOE) 2. N means free from visible film, sheen, discoloration and deposits. 3. < means less than the minimum detectable limit or not detected (ND). 4. TCU mean True Color Unit Source: ESM 2019

Page 6-55

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

6.8.5 Retention Pond Discharge Quality

Monitoring of silt trap discharge for Oil & Grease (O&G) and Total Suspended Solids (TSS) were sampled at the final discharge outlet of retention ponds; namely Pond 1 (ST1), Pond 2 (ST2), Pond 3 (ST3), Pond 4 (ST4) and Pond 5 (ST5) as shown in Figure 6-11. The monitoring has been conducted quarterly and summary of results is shown in Table 6-14. For the EIA study, although there is no industrial effluent discharge from the site, additional round of monitoring was conducted for full Standard B parameters of Environmental Quality (Industrial Effluent) Regulations 2009 as baseline data for the Project. The results are presented in Table 6-15.

Monitoring Station Description Coordinates ST1 Silt Trap No. 1 [N 04°17’31.9”; E 103°26’06.5”] ST2 Silt Trap No. 2 [N 04°17’31.5”; E 103°25’46.4”] ST3 Silt Trap No. 3 [N 04°16’52.5”; E 103°26’03.2”] ST4 Silt Trap No. 4 [N 04°17’14.4”; E 103°25’25.3”] ST5 Silt Trap No. 5 [N 04°16’59.0”; E 103°25’25.5”]

Refer to periodic results, oil and grease were not detected (<1 mg/l) in all these ponds. The water samples collected at these slit traps showed that TSS concentration was complied with the permissible limit of 100 mg/l. In June 2019, there were no discharge recorded in ST1, ST2, ST3 and ST4. In summary, TSS recorded for ST1, ST2, ST3, ST4 and ST5 were 2 - 17 mg/l, <2 - 8 mg/l, 5 - 60 mg/l, 5 - 19 mg/l and 4 - 28 mg/l respectively.

Besides, for the full Standard B parameters testing and analysis, monitoring was conducted once for all 5 retention ponds; in September 2019 for ST1 to ST4 and June 2019 for ST5. When compared with the Standard B of the Environmental Quality (Industrial Effluent) Regulations 2009, all the water samples were well below the stipulated standard limit. Except for boron, detected slightly higher than limit of 4 mg/l in ST1.

Refer to the results, the pH level at all retention ponds complied with the Standard B Limit of 5.5-9.0 which were ranging between 7.64 to 8.89. DO results within the range of 5.7-6.28 mg/l.

The BOD was not detected at all retention ponds whereas at ST3 it was detected at 3 mg/l which below the Standard B Limit of 50mg/l. As for COD, the concentration was detected below the Standard B Limit which were ranging between 21 mg/l to 51 mg/l. TSS were detected at 20 mg/l (ST1), 17 mg/l (ST2), 25 mg/l (ST3), 16 mg/l (ST4) and 26 mg/l (ST5) which complied with Standard B Limit of 100 mg/l.

Page 6-56

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Heavy metals analysed for all retention ponds showed that most of these heavy metals namely Mercury, Cadmium, Chromium, Arsenic, Cyanide, Lead, Copper, Nickel, Tin, Selenium and Barium were not detected. However, Boron was detected above the Standard B Limit of 4 mg/l at ST1 which was 4.3 mg/l whereas others were complied and at ST3 was not detected. Iron was detected ranging between 0.15 mg/l to 1.8 mg/l while silver was not detected at ST1 and ST5. Aluminium was not detected at all retention ponds except at ST5 which was 0.22 mg/l.

Fluoride was detected at 1.6 mg/l (ST1), 0.9 mg/l (ST2), 2 mg/l (ST3), 0.2 mg/l (ST4 & ST5) while phenol was detected ranging between 0.1-0.3 mg/l. Free chlorine, sulphide, Oil and Grease and formaldehyde were not detected.

Ammoniacal Nitrogen was detected below the Standard B Limit of 20 mg/l between the range of 0.1 mg/l to 4.4 mg/l.

Page 6-57

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-14 Retention Pond Discharge Quality Results for TSS & Oil and Grease

ST1 ST2 ST3 ST4 ST5 (Silt Trap No. 1) (Silt Trap No. 2) (Silt Trap No. 3) (Silt Trap No. 4) (Silt Trap No. 5) Date 4°17'31.9"N; 103°26'06.5"E 4°17'31.5"N; 103°25'46.4"E 4°16'52.5"N; 103°26'03.2"E 4°17'14.4"N; 103°25’25.3"E 4°16’59.0’’N; 103°25'25.5"E TSS Oi l & Grease TSS Oil & Grease TSS Oil & Grease TSS Oil & Grease TSS Oil & Grease (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) Aug 2015 11 <1 <2 <1 60 <1 19 <1 28 <1 Sept 2018 2 <1 2 <1 5 <1 5 <1 6 <1 Dec 2018 17 <1 6 <1 6 <1 18 <1 4 <1 Mar 2019 8 <1 8 <1 38 <1 16 <1 14 <1 Jun 2019 No Discharge No Discharge No Discharge No Discharge No Discharge No Discharge No Discharge No Discharge 26 <1 DOE Limit 100 10* 100 10* 100 10* 100 10* 100 10* Note: 1. DOE limit as stipulated in EIA Approval Condition No. 32. 2. *Proposed limits in Approved EMP (Operation) 2015 3. .”<” means less than the minimum detectable limit or not detected. Source: ESM, 2019

Page 6-58

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-15 Retention Pond Discharge Quality Results

Results Standard Parameters Units ST1 ST2 ST3 ST4 ST5 B (Sep-19) (Sep-19) (Sep-19) (Sep-19) (Jun-19) pH value - 7.64 8.1 8.89 7.41 8.0 5.5-9.0 Biochemical Oxygen Demand mg/l <2 <2 3 <2 <2 50 @ 5 days at 20 oC Chemical Oxygen Demand mg/l 23 21 36 24 51 200 Total Suspended Solids mg/l 20 17 25 16 26 100 Mercury as Hg mg/l <0.001 <0.001 <0.001 <0.001 <0.001 0.05 Cadmium as Cd mg/l <0.01 <0.01 <0.01 <0.01 <0.01 0.02 Chromium Hexavalent as Cr6+ mg/l <0.01 <0.01 <0.01 <0.01 <0.01 0.05 Chromium Trivalent as Cr3+ mg/l <0.01 <0.01 <0.01 <0.01 <0.01 1.0 Arsenic as As mg/l <0.001 <0.001 <0.001 <0.001 <0.001 0.10 Cyanide as CN mg/l <0.02 <0.02 <0.02 <0.02 <0.02 0.10 Lead as Pb mg/l <0.02 <0.02 <0.02 <0.02 <0.02 0.5 Copper as Cu mg/l <0.01 <0.01 <0.01 <0.01 <0.01 1.0 Manganese as Mn mg/l <0.01 <0.01 0.12 <0.01 <0.01 1.0 Nickel as Ni mg/l <0.01 <0.01 <0.01 <0.01 <0.01 1.0 Tin as Sn mg/l <0.004 <0.004 <0.004 <0.004 <0.004 1.0 Zinc as Zn mg/l 0.04 0.02 0.06 0.05 0.05 2.0 Boron as B mg/l 4.3 <0.1 1.4 0.2 1.8 4.0 Iron as Fe mg/l 0.15 0.45 1.8 0.48 0.22 5.0 Silver as Ag mg/l <0.01 0.01 0.06 0.01 <0.01 1.0 Aluminium as Al mg/l <0.05 <0.05 <0.05 <0.05 0.22 15 Selenium as Se mg/l <0.005 <0.005 <0.005 <0.005 <0.005 0.5 Barium as Ba mg/l <0.05 <0.05 <0.05 <0.05 <0.05 2.0 Fluoride as F mg/l 1.6 0.9 2 0.2 0.2 5.0 Phenol mg/l 0.1 0.1 0.2 0.3 0.1 1.0

Free Chlorine as Cl2 mg/l <0.1 <0.1 <0.1 <0.1 <0.1 2.0 Sulfide as S2- mg/l <0.05 <0.05 <0.05 <0.05 <0.05 0.50 Oil & Grease mg/l <1 <1 <1 <1 <1 10 Dissolved Oxygen mg/l 5.78 5.98 5.78 6.28 5.7 - Ammoniacal Nitrogen as N mg/l 4.4 0.7 4 0.5 0.1 20 Color ADMI 5 5 5 5 8 200 (pH 8.0) (pH 8.1) (pH 8.2) (pH 8.0) (pH 8.0) Formaldehyde mg/l <0.1 <0.1 <0.1 <0.1 <0.1 2.0 Flowrate m3/hr - - 80.78 - 2.03 - Note: 1. ”<” means less than the minimum detectable limit or not detected. Source: ESM, 2019

Page 6-59

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

6.8.6 Groundwater Quality

For baseline reference, groundwater quality monitoring was carried in June 2019 at the three (3) stations; as listed below and illustrated in Figure 6-11.

Monitoring Description Coordinates Station [N 04°28’67.85”; G1 At Open Space near to Sinter Plant Area. E 103°42’74.97”] [N 04°28’32.88”; G2 At Raw Material Yard near to Wash Trough E 103°42’64.37”] [N 04°28’ 30.52”; G3 At Southwest of the Project Site, near to Raw Material Yard E 103°42’38.12”]

The groundwater results are shown in Table 6-16. Since the groundwater quality standards for Malaysia is still not established yet hence the results will be compared with the National Guidelines for Raw Drinking Water Quality, Revised December 2010 as the benchmark. The detailed laboratory analysis results are attached in Appendix D

The groundwater quality monitoring results were generally complied with the National Guidelines for Raw Drinking Water Quality.

For the physical and aggregate properties, there are a few parameters that were being conducted; conductivity, pH value, temperature, total dissolved solids, total hardness as CaCO3, turbidity and colour. The conductivity was within the range of 3130 – 7370 μS/cm. All the 3 groundwater samples (G1-G3) was slightly acidic with the pH range of 5.8 – 6.2 at temperature range of 23.5 – 23.7°C. The total dissolved solids for all three points were above the Raw Drinking Water Quality limit of 1000 mg/l. G2 contain the highest total dissolved solids of 5210 mg/l meanwhile G1 and

G3 were 1730 mg/l and 1720 mg/l respectively. For the total hardness as CaCO3, only G1 and G3 complied with the Raw Drinking Water Quality which does not exceed the limit of 500 mg/l meanwhile in G2, it measured at 688 mg/l. In term of turbidity, all three groundwater samples exceed the Raw Drinking Water Quality limit of 5 NTU; G1 (1000 NTU), G2 (1820 NTU) and G3 (1070 NTU). While, the colour is measured with value of 1000 TCU for G1 and 1400 TCU for G2 and G3, all above 15 TCU. Chemical oxygen demand (COD) for G1, G2 and G3 were 50 mg/l, 52 mg/l and 88 mg/l respectively.

For the aggregate organics, the parameter that conducted were anionic surfactants as MBAS, biochemical oxygen demand (BOD), mineral oils and total phenols. Only biochemical oxygen demand (BOD) was detected with the value of 20 mg/l for G1 and G2 meanwhile for G3 was 42 mg/l.

The inorganic and non-metallic properties parameter were ammonia, chloride, fluoride, nitrate, nitrite, sulphate and total cyanide. Total cyanide was not present in Page 6-60

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019 all three monitoring points; while, ammonia and chloride were detected exceed the limit in all three monitoring stations. Whereas, the ammonia levels were 6.94 mg/l for G1, 12.1 mg/l for G2 and 7.63 mg/l for G3 which exceed the limit of 1.5 mg/l. The chloride level for G1, G2 and G3 were 490 mg/l, 2310 mg/l and 442 mg/l respectively which exceed the permissible limit of 250 mg/l. Fluoride at G1 and G3 complied with the limit with the value of 0.2 mg/l meanwhile at G2 it exceeds the limit with the value of 0.7 mg/l. For nitrate, it was not detected at G1 meanwhile at G2 and G3, the levels were 0.68 mg/l and 0.35 mg/l respectively which comply with the limit of 10mg/l. The value for nitrate at G1, G2 and G3 were 0.02 mg/l, 0.03 mg/l and 0.02 mg/l respectively. Sulphate was ranging from 7 mg/l to 66 mg/l, which were below the limit of 250 mg/l.

Parameters that conducted for metals and major cations were arsenic, chromium, cadmium, copper, iron, lead, magnesium, manganese, mercury, nickel, selenium, silver, sodium and zinc. Cadmium, mercury, selenium and silver were not detected at all monitoring groundwater. Arsenic was below the limit at G3 (0.0091 mg/l) and above the limit of 0.01 mg/l at G1 and G2. Chromium and copper were all below the limit of 0.05 mg/l and 1.00 mg/l. Iron at G1, G2 and G3 was above the limit of 0.3 mg/L with 28.3 mg/l, 205 mg/l and 109 mg/l respectively. G1 and G2 shown that the lead levels were 0.0536 mg/l and 0.0256 mg/l which above the limit of 0.01 mg/l. Magnesium present at G1. G2 and G3 were 33.7 mg/l, 109 mg/l and 19.2 mg/l respectively. Nickel was detected in low concentration at G1 (0.0030 mg/l), G2 (0.0016 mg/l) and not detected at G3. Sodium levels were above the limit of 200 mg/l in all monitoring stations, where G1 (237 mg/l), G2 (937 mg/l) and G3 (206 mg/l). Zinc was measured complied with the limit of 3 mg/l in all samples.

The parameter for Phenoxy Acetic Acid Herbicides were MCPA, 2,4-D (dichlorophenoxy acetic acid), 2,4,5-T and 2,4-DB. None of these herbicides were detected in all monitoring point. The parameter for Pesticides were Aldrin and Dieldrin, Chlordane, Endosulfan, Lindane, Hexachlorobenzene (HCB), Heptachlor, 4,4'-DDT and Methoxychlor. None of these pesticides were detected. The amount of total coliform count in G1 and G3 were 3.6 MPN/100ml meanwhile in G2 the amount was 9.2 MPN/100ml. Escherichia coli was detected only in G2 with the value of 6.9 MPN/100ml.

Overall, since there is no available of the baseline data prior to the IISM in operation, hence these groundwater quality results shall be used as the baseline reference only. As for the results, although it was not comparative with the Raw Drinking Water Quality, however, it shall be noted that Eastern Steel had no plan on groundwater extraction for water consumption. The main water source is from SATU.

Page 6-61

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-16 Groundwater Quality Results Sample ID GW1 GW2 GW3 National Sampling Date/ Time 19-Jun-2019 00:00 19-Jun-2019 00:00 19-Jun-2019 00:00 Guidelines for Compound Method LOR Unit KL1906061-001 KL1906061-002 KL1906061-003 Raw Drinking Water Quality Physical and Aggregate Properties Conductivity APHA2510B 1 μS/cm 3150 7370 3130 - pH Value APHA4500H+B 0.1 pH Unit 5.8 6.2 6.1 6.5-9.0 Temperature APHA2550B 0.1 °C 23.7 23.7 23.5 - Total Dissolved Solids APHA2540C 1 mg/l 1730 5210 1720 1000 Total Hardness as APHA2340B 0.1 mg/l 223 688 168 500 CaCO3 Turbidity APHA2130B 1.0 NTU 1000 1820 1070 5 NTU Colour (True) APHA2120B 5 TCU 1000 1400 1400 15 TCU Aggregate Organics Anionic Surfactants as APHA5540C 0.05 mg/l <0.05 <0.05 <0.05 - MBAS Biochemical Oxygen APHA5210B 1 mg/l 20 20 42 - Demand Mineral oils APHA5520F 0.06 mg/l <0.06 <0.06 <0.06 0.3 Total Phenols APHA5530B&D 0.001 mg/l <0.001 <0.001 <0.001 0.002 Inorganic and Nonmetallic Properties Ammonia as N APHA4500 NH3 0.01 mg/l 6.94 12.1 7.63 1.5 G Chloride APHA4500-Cl-E 1 mg/l 490 2310 442 250 Fluoride APHA4500F D 0.1 mg/l 0.2 0.7 0.2 0.4-0.6 Nitrate as N APHA4500- 0.01 mg/l <0.01 0.68 0.35 10 NO3-H Nitrite as N APHA4500- 0.01 mg/l 0.02 0.03 0.02 - NO2-B Sulphate CH117-11 1 mg/l 7 66 19 250 Total Cyanide APHA4500CN 0.050 mg/l <0.050 <0.050 <0.050 0.07 C&E

Page 6-62

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Metals and Major Cations Arsenic APHA3125B 0.0010 mg/l 0.0115 0.0120 0.0091 0.01 Cadmium APHA3125B 0.0005 mg/l <0.0005 <0.050 <0.050 0.003 Chromium APHA3125B 0.0010 mg/l 0.0039 0.0031 0.0016 0.05 Copper APHA3125B 0.0010 mg/l 0.0033 0.0025 0.0010 1.0 Iron APHA3125B 0.0010 mg/l 28.3 205 109 0.3 Lead APHA3125B 0.0010 mg/l 0.0536 0.0256 0.0051 0.01 Magnesium APHA3125B 0.1 mg/l 33.7 109 19.2 150 Manganese APHA3125B 0.0010 mg/l 2.74 2.25 0.874 0.1 Mercury APHA3125B 0.0010 mg/l <0.0010 <0.0010 <0.0010 0.001 Nickel APHA3125B 0.0010 mg/l 0.0030 0.0016 <0.0010 0.02 Selenium APHA3125B 0.0020 mg/l <0.0020 <0.0020 <0.0020 0.01 Silver APHA3125B 0.0010 mg/l <0.0010 <0.0010 <0.0010 0.05 Sodium APHA3120B 0.1 mg/l 237 937 206 200 Zinc APHA3125B 0.0010 mg/l 0.0376 0.0869 0.0178 3 Phenoxy Acetic Acid Herbicides MCPA In House LCMS 10 μg/l <10 <10 <10 0.002 2,4-D In House LCMS 10 μg/l <10 <10 <10 0.03 (dichlorophenoxy acetic acid) 2.4.5-T In House LCMS 10 μg/l <10 <10 <10 0.009 2.4-DB In House LCMS 10 μg/l <10 <10 <10 0.09 Pesticides Aldrin and Dieldrin USEPA8270C 0.00002 mg/l <0.00002 <0.00002 <0.00002 0.00003 Chlordane USEPA8270C 0.00005 mg/l <0.00005 <0.00005 <0.00005 0.0002 Endosulfan USEPA8270C 0.00005 mg/l <0.00005 <0.00005 <0.00005 0.03 Lindane USEPA8270C 0.00005 mg/l <0.00005 <0.00005 <0.00005 0.002 Hexachlorobenzene USEPA8270C 0.00005 mg/l <0.00005 <0.00005 <0.00005 0.001 (HCB) Heptachlor USEPA8270C 0.00005 mg/l <0.00005 <0.00005 <0.00005 0.00003 4.4’-DDT USEPA8270C 0.00005 mg/l <0.00005 <0.00005 <0.00005 0.002 Methoxychlor USEPA8270C 0.00005 mg/l <0.00005 <0.00005 <0.00005 0.02 Microbiological Testing Total Coliform Count APHA9221B 1.1 MPN/100ml 3.6 9.2 3.6 Must not be Page 6-63

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

detected in any 100 ml sample Escherichia coli MB-17-59 1.1 MPN/100mL <1.1 6.9 <1.1 0 in 100 m Subcontracting: Radionuclides Gross alpha Subcon 0.01 Bq/L <0.03 <0.04 <0.02 0.1 Bq/l Gross beta Subcon 0.01 Bq/L 0.22 ± 0.02 0.23 ± 0.02 0.26 ± 0.02 1.0 Bq/l Subcontracting: Pesticides Alachlor LCMS 0.00005 mg/L <0.00005 <0.00005 <0.00005 0.02 Aldicarb LCMS 0.00005 mg/L <0.00005 <0.00005 <0.00005 0.01 Permethrin LCMS 0.00001 mg/L <0.00001 <0.00001 <0.00001 0.02 Carbofuran LCMS 0.00005 mg/L <0.00005 <0.00005 <0.00005 0.007 Standard A: Environmental Quality (Industrial Effluents) Chemical Oxygen APHA5220D 1 mg/L 50 52 88 - Demand

Source: ALS, 2019

Page 6-64

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

This page has been intentionally left blank.

Page 6-65

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

N

LEGEND: Ambient Air Quality A1 Southwest of Project site A2 Kg. Bukit Anak Dara A3 Perumahan Bukit Kuang A4 New worker housing area A5 Kg. Baharu Mak Cili Noise Level N1 North corner N2 Southeast corner N3 Southwest corner N4 Northwest corner Surface Water Quality W1 Sg. Teluk Kalung (upstream) W2 Sg. Teluk Kalung (downstream) W3 Sg. Cukai (upstream) W4 Sg. Ruang (upstream) W5 Confluence of Sg. Cukai and Sg. Ruang

Source: Eastern Steel, 2019

Figure 6-10 Baseline Monitoring Location (Air, Noise & Water)

Page 6-66

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

N

LEGEND: Silt Trap Water Quality ST1 Silt Trap No.1 ST2 Silt Trap No.2 ST3 Silt Trap No.3 ST4 Silt Trap No.4 ST5 Silt Trap No.5 Groundwater Quality

At Open Space near to Sinter G1 Plant Head Deduster Area.

At Raw Material Yard near to G2 Wash Trough

Southwest of the Project Site, G3 near to Raw Material Yard

Source: Eastern Steel, 2019

Figure 6-11 Baseline Monitoring Location (Silt Trap & Groundwater)

Page 6-67

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

N

LEGEND: Sinter Plant A1 Bagfilter at Dosing House A2 Electrostatic Precipitator (ESP) at Sinter Head A3 Combined System of Electrostatic Precipitator (ESP) & Bagfilter at Sinter Tail Iron Making Plant B1 Bagfilter at Bunker Bunker B2 Bagfilter at Casting House B3 Bagfilter at Dry Method Deduster Material Transfer Station B5 Bagfilter at Station 1 B6 Bagfilter at Station 2 Steel Making Plant C1 Scrubber C2 Secondary Dedusting

Source: Eastern Steel, 2019

Figure 6-12 Baseline Monitoring Location (Stack)

Page 6-68

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

6.8.7 Scheduled and Non-Scheduled Waste Record

a) Scheduled Waste Generation Record

Based on the inventory record, the quantity of scheduled wastes generated from the existing plant operation is summarized in Table 6-17. Scheduled wastes generated are being managed following the requirements under the Environmental Quality (Scheduled Wastes) Regulation 2005.

Table 6-17 Quantity of Scheduled Waste Generated Average Code SW Description Quantity (MT/month) SW305 Spent lubricating oil 0.1 SW306 Spent hydraulic oil 1.6 Disposed containers, bags or equipment SW409 contaminated with chemicals, pesticides, mineral oil 1.1 or scheduled waste Total 2.8 Source: Eastern Steel, 2019

b) Solid Waste Generation Record

Solid waste generated at Eastern Steel is consisting of domestic type of waste and general office waste, which is produced mainly from administration building and canteen. After the 3Rs segregation, the quantity of solid/domestic waste generated at site is as tabulated in Table 6-18. The solid waste from the IISM Plant are collected 2 times a week by appointed contractor and disposed at the nearest approved landfill at Bukit Takar.

Table 6-18 Estimation of Domestic Waste Generation Waste Avg. Weight (kg/month) kg/year Domestic Waste 300 3,600

Page 6-69

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

6.9 ENVIRONMENTAL PERFORMANCE COMPLIANCE STATUS

The latest Environmental Compliance Audit (ECA) which assesses the existing plant’s compliance with the Environmental Quality Act 1974 and its accompanying regulations and related approvals was conducted on 21 March 2019 by an independent third-party auditor.

Based on the audit findings, only one (1) non-compliance report (NCR) raised during the audit session, as described in Table 6-19.

Table 6-19 ECA 2019 Findings Non-Compliances Description (NCR) Oil spillage observed at the temporary scheduled waste storage area (Auxiliary)

NCR 01/01/19

Corrective action on NCR has been made by the Eastern Steel on 21st March 2019 where the oil spill collector tank has been located back to the area with cover on it to avoid rain fall water.

The ECA report concluded that five (5) good practices have been applied in IISM Plant and there are two (2) area need for improvement which is 1) Scheduled waste storage area (Sinter Plant) – operator needs to have inventory; separate new oil and used oil; build a ramp at the store entrance and paste label of the storage name outside; and 2) Operator is recommended to expedite the CEMS installation and operation.

The summary of the ECA is appended in Appendix G together with the corrective action report that has been done.

Page 6-70

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

6.10 SOCIO-ECONOMIC

6.10.1 Socio-Economic and Human Environment

Existing socio-economics and human environment made up the sociological descriptions of the proposed Project, which encompasses both the baseline conditions within site and its surrounding area. Features within and surrounding the project site are acquired from site visits, whilst additional information was obtained from available published data on Majlis Perbandaran Kemaman (MPK) and Department of Statistic Malaysia (DOS).

6.10.2 Total Population

The proposed project site is located in Kemaman, under planning zone of the Majlis Perbandaran Kemaman (MPK). Planning zone of MPK is divided into eleven (11) small planning block known as BP with an administrative area of 253,559.9 hectares. In year 2010 MPK has total population of 167,824 people, with annual growth rate 5.5%. Total population under MPK areas by district until 2010 was tabulated in Table 6-20.

Table 6-20 Total Population by District (000’)

Authority 2000 2005 2010 Annual Growth Rate (%) MPK 137,070 158,660 167,824 5.5 Source: Department of Statistics Malaysia, 2010

Total population of Kemaman is expected to growth rapidly due to it location within East Coast Economic Region (ECER).

6.10.3 Age

In terms of age distribution, a large percentage (50.6%) of the population in Kemaman under MPK administrative area are in the actively working adults age group whilst about just small amount (20.8%) consist of young adults, about 23.1% consist of children and a small percentage (5.6%) consist of semi retirees and retiree (refer Table 6-21).

Page 6-71

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-21 Population in Kemaman by Age Group, 2010 Age Range Population Percentage (%) 0-9 years 38,479 23.1 10-19 years 34,694 20.8 20-39 years 52,509 31.5 40- 59 years 31,792 19.1 60 years and above 9,276 5.6 Total 166,750 100 Source: Department of Statistics Malaysia, 2010

6.10.4 Gender Distribution

Based on the breakdown of gender, the percentage of total male population is higher at 52.6% of total the Kemaman population, as compared to the female population which accounts for 47.4%. The higher numbers of males could be due to presence of male workers in the industries and estates within the Kemaman area who are also residing in the area.

Table 6-22 Population in Kemaman by Gender, 2010

Gender Population Percentage (%) Male 87,768 52.6 Female 78,982 47.4 Total 166,750 100 Source: Department of Statistics Malaysia, 2010

6.10.5 Ethnicity

The majority of the population in Kemaman are Malaysians with only about 2.9% non- Malaysians. Malays and Bumiputera make up more than third-quarter proportion (94.8%) of Malaysians, followed by Chinese (4.2%), Indians (0.5%) and others (0.2%). Please refer Table 6-23.

Page 6-72

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-23 Population in Kemaman by Nationality and Ethnicity, 2010

Nationality Ethnicity Population Percentage (%) Malays 153,472 94.8* Other Bumiputera 699 0.4* Malaysian Chinese 6,800 4.2* Indians 729 0.5* Others 259 0.2* Total Malaysian 161,959 97.1 Total Non-Malaysian 4,791 2.9 Overall Total 100.0 Note: *Percentage of total Malaysians Source: Department of Statistics Malaysia, 2010

Malays settlements is mostly in traditional Malay villages. Meanwhile the Chinese community in Kemaman, can consider as large community following the development of town due to the area of petroleum and natural gas. As minor population ethnic in Kemaman, Indians normally settlement at rubber estates and working in rubber estates and factories.

6.11 EXISTING PUBLIC HEALTH

6.11.1 Morbidity Statistics

Morbidity statistics on diseases related to the environment were obtained from Klinik Kesihatan Kijal, Klinik Kesihatan Batu 2.5 and Hospital Kemaman for a period of 1 year from January to December 2018. Table 6-24 shows the disease cases related to air pollution seen at Klinik Kesihatan Kijal in 2018. Eye and respiratory diseases as represented by conjunctivitis, upper respiratory tract infections, asthma and tuberculosis made up 5.3% and 16.7% of all adult and children cases, respectively. Cardiovascular diseases as represented only by hypertension made up 8.7% of all adult cases.

Table 6-25 gives the disease cases related to water pollution seen at Klinik Kesihatan Kijal in 2018. Only one food poisoning case was reported at the clinic which made up only 0.006% of all adult cases. Therefore, waterborne and foodborne diseases are not very common in the area.

Animal vectors and reservoirs may be associated with a poorly managed environment. Often, discarded containers that are improperly disposed or the presence of water within homes and surroundings may become excellent breeding sites for the mosquitoes which transmit diseases. Table 6-26 gives the disease cases related to animal vectors and reservoirs seen at Klinik Kesihatan Kijal in 2018. Only two dengue fever cases were reported, and they made up only 0.01% of all adult cases. Therefore, vectorborne diseases are also uncommon in the area.

Page 6-73

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-27 gives the skin disease cases seen at Klinik Kesihatan Kijal in 2018. Of all these skin diseases, dermatitis and eczema, and urticaria are allergic forms of skin reactions that may be exacerbated by allergens and irritants that may be present in air pollution or dust. The skin disease cases made up 1.5% and 6.4% of all adult and children cases, respectively. The most common skin disease reported was disorders of skin appendages.

Table 6-28 shows the disease cases related to air pollution seen at Klinik Kesihatan Batu 2.5 in 2018. Eye and respiratory diseases as represented by conjunctivitis, upper respiratory tract infections, influenza, asthma, tuberculosis and pneumonia made up 6.6% and 22.7% of all adults and children cases, respectively. Cardiovascular diseases as represented by hypertension, heart failure, ischaemic heart disease and cerebrovascular accident made up 0.2% of all adult cases.

Table 6-29 gives the disease cases related to water pollution seen at Klinik Kesihatan Batu 2.5 in 2018. There was no water pollution related disease reported in this area for both adult and children.

Table 6-30 shows the diseases cases related to animal vectors and reservoirs seen at Klinik Kesihatan Batu 2.5. Only dengue fever cases were reported which made up only 0.02% and 0.009% of all adult and children cases, respectively.

Table 6-31 give the morbidity statistics on skin disease cases seen at Klinik Kesihatan Batu 2.5 in 2018. Dermatitis and eczema were the most common types of skin diseases reported among adults, while cutaneous abscess/ furuncle and carbuncle, and cellulitis were the common types of skin diseases reported among children in this area. These skin diseases made up of 1.6% and 3.6% of all adults and children cases, respectively.

The following morbidity statistics are regarding diseases related to the environment which were obtained from Hospital Kemaman for a period of one year, from January 2018 until December 2018. Table 6-32 shows the disease cases related to air pollution seen at Hospital Kemaman in 2018. Eye and respiratory diseases as represented by conjunctivitis, upper respiratory tract infections, asthma, tuberculosis, pneumonia and lung cancer made up 6.3% and 7.6% of all adults and children cases, respectively. Cardiovascular diseases as represented by hypertension, heart failure, ischaemic heart disease and cerebrovascular accident made up of 2.0% and 0.03% of all adult and children cases, respectively.

Table 6-33 gives the disease cases related to water pollution seen at Hospital Kemaman in 2018. The water pollution related diseases as represented by dysenteries and food poisoning made up of 0.5% and 3.8% of all adult and children cases, respectively. Compared to adult, children reported a higher percentage of water pollution related diseases.

Table 6-34 shows the diseases cases related to animal vectors and reservoirs seen at Hospital Kemaman. Dengue fever and malaria disease cases were reported, in which dengue fever is the most common vector borne disease reported. These animal vector and reservoir related disease cases made up of 1.1% and 1.0% of all adult and children cases, respectively.

Page 6-74

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-35 give the morbidity statistics on skin disease cases seen at Hospital Kemaman in 2018. The skin diseases as represented by cutaneous abscess/ furuncle and carbuncle, cellulitis, urticaria, disorders of skin appendages and erythemas made up of 0.1% and 0.06% of all adults and children cases, respectively.

Table 6-36 shows the prevalence rates of selected communicable diseases in Daerah Kemaman in 2018, in comparison with the prevalence of these diseases in Malaysia in 2017. The prevalence rates for the waterborne, foodborne, vectorborne and zoonotic diseases were generally much lower than the nation’s rate. This means that these communicable diseases are not major health issues reported in this district.

Page 6-75

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-24: Disease Cases Related to Air Pollution Seen at Klinik Kesihatan Kijal in 2018.

Conj. URTI Inf. Asth. TB Pneu. Bron. Emphy Lung HPT HF IHD CVA *Total

Ca (all patients) Year Month A C A C A C A C A C A C A C A C A C A C A C A C A C A C J 10 5 22 42 0 0 28 32 1 0 0 0 0 0 0 0 0 0 117 0 0 0 0 0 0 0 1770 439 F 10 14 21 58 0 0 23 15 2 0 0 0 0 0 0 0 0 0 124 0 0 0 0 0 0 0 1690 414 M 14 14 26 29 0 0 15 19 0 0 0 0 0 0 0 0 0 0 103 0 0 0 0 0 0 0 681 388 A 22 10 17 15 0 0 21 22 0 0 0 0 0 0 0 0 0 0 118 0 0 0 0 0 0 0 1851 379 M 34 15 15 10 0 0 21 21 0 0 0 0 0 0 0 0 0 0 116 0 0 0 0 0 0 0 1103 324

J 35 7 23 10 0 0 25 15 0 0 0 0 0 0 0 0 0 0 95 0 0 0 0 0 0 0 1015 295

2018 J 23 8 39 37 0 0 28 28 0 0 0 0 0 0 0 0 0 0 172 0 0 0 0 0 0 0 1422 300 A 19 11 28 29 0 0 17 13 0 0 0 0 0 0 0 0 0 0 128 0 0 0 0 0 0 0 1734 371 S 15 17 35 23 0 0 25 15 0 0 0 0 0 0 0 0 0 0 121 0 0 0 0 0 0 0 1547 379 O 16 3 35 28 0 0 24 16 1 0 0 0 0 0 0 0 0 0 113 0 0 0 0 0 0 0 757 330 N 18 10 44 47 0 0 27 16 0 0 0 0 0 0 0 0 0 0 108 0 0 0 0 0 0 0 1552 398 D 19 10 37 45 0 0 27 15 0 0 0 0 0 0 0 0 0 0 119 0 0 0 0 0 0 0 1306 319

Total 235 124 342 373 0 0 281 227 4 0 0 0 0 0 0 0 0 0 1434 0 0 0 0 0 0 0 16428 4336 Conj. : Conjunctivitis Emphy. : Emphysema URTI : Upper respiratory tract infections Lung Ca : Lung cancer Inf. : Influenza HPT : Hypertension Asth : Asthma HF : Heart failure TB : Tuberculosis IHD : Ischaemic heart disease Pneu. : Pneumonia CVA : Cerebrovascular accident/stroke Bron. : Chronic bronchitis

*Total (all patients): Total attendance of all patients at the clinic during that month. A: Adult C: Children

Page 6-76

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-25: Disease Cases Related to Water Pollution Seen at Klinik Kesihatan Kijal in 2018. *Total Dys. Chol. Typ. Hep. A Polio. Food Year Month (all patients) A C A C A C A C A C A C A C Jan 0 0 0 0 0 0 0 0 0 0 0 0 1770 439 Feb 0 0 0 0 0 0 0 0 0 0 0 0 1690 414 Mar 0 0 0 0 0 0 0 0 0 0 0 0 681 388 Apr 0 0 0 0 0 0 0 0 0 0 0 0 1851 379 May 0 0 0 0 0 0 0 0 0 0 0 0 1103 324 June 0 0 0 0 0 0 0 0 0 0 0 0 1015 295 2018 July 0 0 0 0 0 0 0 0 0 0 0 0 1422 300 Aug 0 0 0 0 0 0 0 0 0 0 0 0 1734 371 Sep 0 0 0 0 0 0 0 0 0 0 0 0 1547 379 Oct 0 0 0 0 0 0 0 0 0 0 1 0 757 330 Nov 0 0 0 0 0 0 0 0 0 0 0 0 1552 398 Dec 0 0 0 0 0 0 0 0 0 0 0 0 1306 319 Total 0 0 0 0 0 0 0 0 0 0 1 0 16428 4336

Dys. : Dysenteries Chol. : Cholera Typ. : Typhoid and paratyphoid Hep. A : Hepatitis A Polio. : Acute poliomyelitis Food. : Food poisoning

*Total (all patients): Total attendance of all patients at the clinic during that month. A: Adult C: Children

Page 6-77

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-26: Disease Cases Related to Animal Vectors and Reservoirs Seen at Klinik Kesihatan Kijal in 2018. *Total Year Month YF DF DHF Mal. Typ. Plag. Rab. (all patients) A C A C A C A C A C A C A C A C Jan 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1770 439 Feb 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1690 414 Mar 0 0 0 0 0 0 0 0 0 0 0 0 0 0 681 388 Apr 0 0 1 0 0 0 0 0 0 0 0 0 0 0 1851 379 May 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1103 324 June 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1015 295 2018 July 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1422 300 Aug 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1734 371 Sep 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1547 379 Oct 0 0 0 0 0 0 0 0 0 0 0 0 0 0 757 330 Nov 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1552 398 Dec 0 0 1 0 0 0 0 0 0 0 0 0 0 0 1306 319 Total 0 0 2 0 0 0 0 0 0 0 0 0 0 0 16428 4336

YF : Yellow fever DF : Dengue fever DHF : Dengue haemorrhagic fever Mal. : Malaria Typ. : Typhus Plag. : Plague Rab. : Rabies

*Total (all patients): Total attendance of all patients at the clinic during that month. A: Adult C: Children

Page 6-78

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-27: Skin Disease Cases Seen at Klinik Kesihatan Kijal in 2018.

Year Month Cutan. Cell. Derm. Psor. Urti. Dis. Eryth. Rad. *Total (all patients) A C A C A C A C A C A C A C A C A C Jan 0 0 0 0 0 0 0 0 6 2 11 22 0 0 0 0 1770 439 Feb 1 0 0 0 0 1 0 0 9 3 13 11 0 0 0 0 1690 414 Mar 0 0 0 0 0 1 0 0 3 0 12 19 0 0 0 0 681 388 Apr 0 0 1 0 0 0 0 0 5 2 15 17 0 0 0 0 1851 379 May 0 0 0 0 0 0 0 0 7 6 16 24 0 0 0 0 1103 324 June 0 0 0 0 0 0 0 0 4 5 19 19 0 0 0 0 1015 295 2018 July 0 0 0 0 0 0 0 0 3 2 13 12 0 0 0 0 1422 300 Aug 0 0 0 0 0 0 0 0 1 4 17 19 0 0 0 0 1734 371 Sep 0 0 1 0 0 0 0 0 5 3 11 21 0 0 0 0 1547 379 Oct 0 0 0 0 0 0 0 0 8 2 19 27 0 0 0 0 757 330 Nov 0 0 0 0 0 0 0 0 3 3 19 22 0 0 0 0 1552 398 Dec 0 0 0 0 0 0 0 0 5 3 21 29 0 0 0 0 1306 319 Total 1 0 2 0 0 2 0 0 59 35 186 242 0 0 0 0 16428 4336

Cutan. : Cutaneous abscess/furuncle and carbuncle Urti. : Urticaria Cell. : Cellulitis Dis. : Disorders of skin appendages Derm. : Dermatitis and eczema Eryth. : Erythemas Psor. : Psoriasis Rad. : Radiodermatitis and other radiation-related disorders of the skin and subcutaneous tissue

Total (All Patients): Total attendance of all patients at the clinic during that month. A: Adult C: Children

Page 6-79

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-28: Disease Cases Related to Air Pollution Seen at Klinik Kesihatan Batu 2.5 in 2018.

Conj. URTI Inf. Asth. TB Pneu. Bron. Emphy Lung HPT HF IHD CVA *Total

Ca (all patients) Year Month A C A C A C A C A C A C A C A C A C A C A C A C A C A C J 7 3 157 154 17 22 1 1 1 0 8 5 0 0 0 0 0 0 5 0 0 0 0 0 1 0 3932 872 F 10 5 189 150 16 19 2 1 0 0 6 7 0 0 0 0 0 0 10 0 0 0 0 0 0 0 5348 1449 M 9 4 199 201 14 19 1 0 2 0 9 5 0 0 0 0 0 0 8 0 1 0 1 0 0 0 4017 1309 A 11 2 201 215 20 20 3 3 1 0 5 4 0 0 0 0 0 0 6 0 0 0 2 0 3 0 5078 1451 M 12 5 178 198 23 23 2 5 1 0 7 8 0 0 0 0 0 0 6 0 0 0 1 0 0 0 3400 1451

J 9 4 213 211 19 21 1 4 1 0 4 7 0 0 0 0 0 0 5 0 0 0 0 0 2 0 2088 499

2018 J 10 5 199 187 21 34 0 1 1 0 4 9 0 0 0 0 0 0 7 0 0 0 1 0 1 0 3567 1109 A 5 1 193 176 23 32 2 2 0 0 6 8 0 0 0 0 0 0 8 0 0 0 2 0 0 0 4242 509 S 7 2 145 137 24 56 1 0 1 0 5 7 0 0 0 0 0 0 1 0 0 0 1 0 0 0 3151 610 O 11 2 156 187 25 32 1 4 0 0 4 5 0 0 0 0 0 0 5 0 0 0 0 0 1 0 2365 753 N 10 4 167 199 21 26 0 3 0 0 5 4 0 0 0 0 0 0 4 0 1 0 0 0 1 0 3188 773 D 5 1 183 156 19 29 2 1 2 0 3 3 0 0 0 0 0 0 3 0 0 0 0 0 0 0 2644 777 Total 106 38 2379 2171 242 313 16 25 10 0 66 72 0 0 0 0 0 0 68 0 2 0 8 0 9 0 43020 11562 Conj. : Conjunctivitis Emphy. : Emphysema URTI : Upper respiratory tract infections Lung Ca : Lung cancer Inf. : Influenza HPT : Hypertension Asth. : Asthma HF : Heart failure TB : Tuberculosis IHD : Ischaemic heart disease Pneu. : Pneumonia CVA : Cerebrovascular accident/stroke Bron. : Chronic bronchitis

*Total (all patients): Total attendance of all patients at the clinic during that month.

A: Adult C: Children

Page 6-80

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-29: Disease Cases Related to Water Pollution Seen at Klinik Kesihatan Batu 2.5 in 2018. Year Month *Total Dys. Chol. Typ. Hep. A Polio. Food (all patients) A C A C A C A C A C A C A C Jan 0 0 0 0 0 0 0 0 0 0 0 0 3932 872 Feb 0 0 0 0 0 0 0 0 0 0 0 0 5348 1449 Mar 0 0 0 0 0 0 0 0 0 0 0 0 4017 1309 Apr 0 0 0 0 0 0 0 0 0 0 0 0 5078 1451 May 0 0 0 0 0 0 0 0 0 0 0 0 3400 1451 June 0 0 0 0 0 0 0 0 0 0 0 0 2088 499 2018 July 0 0 0 0 0 0 0 0 0 0 0 0 3567 1109 Aug 0 0 0 0 0 0 0 0 0 0 0 0 4242 509 Sep 0 0 0 0 0 0 0 0 0 0 0 0 3151 610 Oct 0 0 0 0 0 0 0 0 0 0 0 0 2365 753 Nov 0 0 0 0 0 0 0 0 0 0 0 0 3188 773 Dec 0 0 0 0 0 0 0 0 0 0 0 0 2644 777 Total 0 0 0 0 0 0 0 0 0 0 0 0 43020 11562

Dys. : Dysenteries Chol. : Cholera Typ. : Typhoid and paratyphoid Hep. A : Hepatitis A Polio. : Acute poliomyelitis Food. : Food poisoning

*Total (all patients): Total attendance of all patients at the clinic during that month. A: Adult C: Children

Page 6-81

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-30: Disease Cases Related to Animal Vectors and Reservoirs Seen at Klinik Kesihatan Batu 2.5 in 2018. *Total Year Month YF DF DHF Mal. Typ. Plag. Rab. (all patients) A C A C A C A C A C A C A C A C Jan 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3932 872 Feb 0 0 2 0 0 0 0 0 0 0 0 0 0 0 5348 1449 Mar 0 0 1 0 0 0 0 0 0 0 0 0 0 0 4017 1309 Apr 0 0 1 0 0 0 0 0 0 0 0 0 0 0 5078 1451 May 0 0 1 1 0 0 0 0 0 0 0 0 0 0 3400 1451 June 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2088 499 2018 July 0 0 1 0 0 0 0 0 0 0 0 0 0 0 3567 1109 Aug 0 0 2 0 0 0 0 0 0 0 0 0 0 0 4242 509 Sep 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3151 610 Oct 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2365 753 Nov 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3188 773 Dec 0 0 1 0 0 0 0 0 0 0 0 0 0 0 2644 777 Total 0 0 9 1 0 0 0 0 0 0 0 0 0 0 43020 11562

YF : Yellow fever DF : Dengue fever DHF : Dengue haemorrhagic fever Mal. : Malaria Typ. : Typhus Plag. : Plague Rab. : Rabies

*Total (all patients): Total attendance of all patients at the clinic during that month. A: Adult C: Children

Page 6-82

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-31: Skin Disease Cases Seen at Klinik Kesihatan Batu 2.5 in 2018. *Total Year Month Cutan. Cell. Derm. Psor. Urti. Dis. Eryth. Rad. (all patients) A C A C A C A C A C A C A C A C A C Jan 13 8 14 9 23 11 1 0 22 10 0 0 3 2 0 0 3932 872 Feb 10 9 11 7 18 6 2 0 17 9 0 0 2 3 0 0 5348 1449 Mar 11 10 12 11 17 7 0 0 19 7 0 0 1 4 0 0 4017 1309 Apr 15 13 16 12 19 4 2 0 15 5 0 0 1 2 0 0 5078 1451 May 14 18 15 10 17 8 2 0 14 6 0 0 3 4 0 0 3400 1451 June 13 11 18 9 18 9 1 1 12 8 0 0 2 3 0 0 2088 499 2018 July 12 7 15 6 16 6 0 0 13 4 0 0 1 2 0 0 3567 1109 Aug 11 9 13 8 20 4 3 0 10 5 0 0 4 1 0 0 4242 509 Sep 13 6 14 5 18 2 2 1 09 3 0 0 3 0 0 0 3151 610 Oct 11 10 12 9 19 5 1 1 11 4 0 0 2 3 0 0 2365 753 Nov 12 15 12 14 17 7 2 0 14 5 0 0 2 1 0 0 3188 773 Dec 13 12 18 11 23 8 1 0 13 6 0 0 1 2 0 0 2644 777 Total 124 128 111 111 225 77 17 3 169 73 0 0 25 26 0 0 43020 11562

Cutan. : Cutaneous abscess/furuncle and carbuncle Urti. : Urticaria Cell. : Cellulitis Dis. : Disorders of skin appendages Derm. : Dermatitis and eczema Eryth. : Erythemas Psor. : Psoriasis Rad. : Radiodermatitis and other radiation-related disorders of the skin and subcutaneous tissue *Total (All Patients): Total attendance of all patients at the clinic during that month.

A: Adult C: Children

Page 6-83

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-32: Disease Cases Related to Air Pollution Seen at Hospital Kemaman in 2018.

Conj. URTI Inf. Asth. TB Pneu. Bron. Emphy Lung HPT HF IHD CVA *Total

Ca (all patients) Year Month A C A C A C A C A C A C A C A C A C A C A C A C A C A C J 0 0 6 13 0 0 25 35 0 0 45 13 0 0 0 0 5 0 9 1 7 0 0 0 9 0 1081 579 F 0 0 6 7 0 0 24 31 0 0 60 8 0 0 0 0 1 0 7 0 5 0 1 0 4 0 921 539 M 0 0 6 4 0 0 22 24 0 0 38 8 0 0 0 0 0 0 8 0 2 0 1 0 12 0 1077 613 A 0 0 6 2 0 0 13 25 0 0 45 7 0 0 0 0 1 0 3 0 1 0 0 0 10 0 1075 574 M 0 0 7 2 0 0 23 18 0 0 24 23 0 0 0 0 0 0 4 0 8 0 0 0 9 0 1086 559 J 0 0 4 3 0 0 21 33 0 0 27 8 0 0 0 0 2 0 5 0 6 1 0 0 10 0 1017 569

2018 J 0 0 1 2 0 0 21 41 1 0 45 16 0 0 0 0 0 0 4 0 3 0 0 0 9 0 1117 666 A 1 0 0 4 0 0 20 21 0 0 22 21 0 0 0 0 0 0 8 0 5 0 0 0 13 0 1101 638 S 0 0 0 2 0 0 20 20 0 0 37 8 0 0 0 0 2 0 11 0 4 0 0 0 13 0 1118 584 O 0 0 4 4 0 0 26 29 1 0 39 17 0 0 0 0 1 0 8 0 5 0 0 0 6 0 1154 635 N 0 0 2 4 0 0 31 35 0 0 41 21 0 0 0 0 3 0 11 0 10 0 0 0 12 0 1130 645 D 0 0 3 4 0 0 20 21 0 0 66 12 0 0 0 0 1 0 7 0 8 0 2 0 6 0 1123 571

Total 1 0 45 51 0 0 266 333 2 0 489 162 0 0 0 0 16 0 85 1 64 1 4 0 113 0 13000 7172

Conj. : Conjunctivitis Emphy. : Emphysema URTI : Upper respiratory tract infections Lung Ca : Lung cancer Inf. : Influenza HPT : Hypertension Asth. : Asthma HF : Heart failure TB : Tuberculosis IHD : Ischaemic heart disease Pneu. : Pneumonia CVA : Cerebrovascular accident/stroke Bron. : Chronic bronchitis

*Total (all patients): Total attendance of all patients at the clinic during that month.

A: AdultC: Children

Page 6-84

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-33: Disease Cases Related to Water Pollution Seen at Hospital Kemaman in 2018. Year Month *Total Dys. Chol. Typ. Hep. A Polio. Food (all patients) A C A C A C A C A C A C A C Jan 2 15 0 0 0 0 0 0 0 0 0 0 1081 579 Feb 10 20 0 0 0 0 0 0 0 0 0 0 921 539 Mar 4 20 0 0 0 0 0 0 0 0 0 0 1077 613 Apr 3 7 0 0 0 0 0 0 0 0 0 1 1075 574 May 1 6 0 0 0 0 0 0 0 0 0 0 1086 559 June 9 7 0 0 0 0 0 0 0 0 0 0 1017 569 2018 July 5 22 0 0 0 0 0 0 0 0 0 0 1117 666 Aug 6 24 0 0 0 0 0 0 0 0 0 0 1101 638 Sep 9 26 0 0 0 0 0 0 0 0 0 0 1118 584 Oct 4 33 0 0 0 0 0 0 0 0 0 0 1154 635 Nov 9 43 0 0 0 0 0 0 0 0 0 0 1130 645 Dec 4 45 0 0 0 0 0 0 0 0 0 0 1123 571 Total 66 268 0 0 0 0 0 0 0 0 0 1 13000 7172

Dys. : Dysenteries Chol. : Cholera Typ. : Typhoid and paratyphoid Hep. A : Hepatitis A Polio. : Acute poliomyelitis Food. : Food poisoning

*Total (all patients): Total attendance of all patients at the clinic during that month. A: Adult C: Children

Page 6-85

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-34: Disease Cases Related to Animal Vectors and Reservoirs Seen at Hospital Kemaman in 2018. *Total Year Month YF DF DHF Mal. Typ. Plag. Rab. (all patients) A C A C A C A C A C A C A C A C Jan 0 0 4 8 0 0 0 0 0 0 0 0 0 0 1081 579 Feb 0 0 5 8 0 0 0 0 0 0 0 0 0 0 921 539 Mar 0 0 10 18 0 0 0 0 0 0 0 0 0 0 1077 613 Apr 0 0 12 7 0 0 0 0 0 0 0 0 0 0 1075 574 May 0 0 7 4 0 0 0 0 0 0 0 0 0 0 1086 559 June 0 0 15 3 0 0 0 0 0 0 0 0 0 0 1017 569 2018 July 0 0 9 3 0 0 0 0 0 0 0 0 0 0 1117 666 Aug 0 0 14 4 0 0 3 0 0 0 0 0 0 0 1101 638 Sep 0 0 12 4 0 0 0 0 0 0 0 0 0 0 1118 584 Oct 0 0 11 1 0 0 0 0 0 0 0 0 0 0 1154 635 Nov 0 0 18 10 0 0 0 0 0 0 0 0 0 0 1130 645 Dec 0 0 24 5 0 0 0 0 0 0 0 0 0 0 1123 571 Total 0 0 141 75 0 0 3 0 0 0 0 0 0 0 13000 7172

YF : Yellow fever DF : Dengue fever DHF : Dengue haemorrhagic fever Mal. : Malaria Typ. : Typhus Plag. : Plague Rab. : Rabies

*Total (all patients): Total attendance of all patients at the clinic during that month. A: Adult C: Children

Page 6-86

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-35: Skin Disease Cases Seen at Hospital Kemaman in 2018. *Total Year Month Cutan. Cell. Derm. Psor. Urti. Dis. Eryth. Rad. (all patients) A C A C A C A C A C A C A C A C A C Jan 1 0 1 0 0 0 0 0 1 0 0 0 0 0 0 0 1081 579 Feb 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 921 539 Mar 1 0 0 1 0 0 0 0 0 0 1 0 0 0 0 0 1077 613 Apr 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 1075 574 May 0 0 0 0 0 0 0 0 2 0 0 0 0 0 0 0 1086 559 June 0 0 1 1 0 0 0 0 0 0 1 0 0 0 0 0 1017 569 2018 July 0 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0 1117 666 Aug 0 0 2 0 0 0 0 0 0 0 0 0 0 0 0 0 1101 638 Sep 0 0 0 0 0 0 0 0 1 0 0 0 0 1 0 0 1118 584 Oct 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1154 635 Nov 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 1130 645 Dec 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1123 571 Total 3 0 5 3 0 0 0 0 5 0 3 0 1 1 0 0 13000 7172

Cutan. : Cutaneous abscess/furuncle and carbuncle Urti. : Urticaria Cell. : Cellulitis Dis. : Disorders of skin appendages Derm. : Dermatitis and eczema Eryth. : Erythemas Psor. : Psoriasis Rad. : Radiodermatitis and other radiation-related disorders of the skin and subcutaneous tissue

*Total (All Patients): Total attendance of all patients at the clinic during that month.

A: Adult C: Children

Page 6-87

EIA for the Proposed Development of 55MW Gas Fired Power Plant and Project No: P18006 New Plant Components at the Integrated Iron and Steel Mill, Teluk Kalung Revision: 0 Industrial Estate, Kemaman, Terengganu for Eastern Steel Sdn. Bhd. Date: October 2019

Table 6-36: Prevalence Rates of Selected Communicable Diseases in Daerah Kemaman in 2018.

Disease Number of cases Prevalence rates in 2018 Malaysia (2017)a

Waterborne and Foodborne Diseases

Cholera 0 0 0.01 Typhoid 0 0 0.59 Hepatitis A 0 0 0.47 Dysentery 0 0 0.37 Poliomyelitis 0 0 Food poisoning 1 0.47 42.25 Vectorborne and Zoonotic Diseases

Dengue fever 32 1.49 257.60 Dengue haemorrhagic fever 0 0 1.25 Chikungunya 0 0 NA Malaria 10 0.47 12.70 Filariasis 0 0 NA Typhus 0 0 0.06 Plague 0 0 0.02 Rabies 2 0.94 13.48 Leptospirosis 32 1.49 257.60 Note: Population of Daerah Kemaman in 2018: 214,200. Source: a Ministry of Health Malaysia (2018).

6.12 ROAD NETWORK The Project site is located in Teluk Kalung Industrial Estate (TKIE). The TKIE is accessible by the Federal Route 3, the main coastal road link to other major towns on the East Coast of Peninsular Malaysia, as well as by the Teluk Kalung Bypass Road. .

Page 6-88