Galloper Wind Farm Eastern Super Grid Transformer Project Environmental Statement – Chapter 3 Project Details February 2014 Document Reference – GWF/25/02/2014

Total Page:16

File Type:pdf, Size:1020Kb

Galloper Wind Farm Eastern Super Grid Transformer Project Environmental Statement – Chapter 3 Project Details February 2014 Document Reference – GWF/25/02/2014 Galloper Wind Farm Eastern Super Grid Transformer Project Environmental Statement – Chapter 3 Project Details February 2014 Document Reference – GWF/25/02/2014 Galloper Wind Farm Limited CONTENTS Page 3 PROJECT DETAILS 3.1 Introduction 1 3.2 Outline Project Description 2 3.3 Alternatives Considered 2 3.4 Onshore Substation 3 3.5 Items to be Constructed under the DCO 4 3.6 Cabling 7 3.7 Sealing End Compound, Gantries, and Overhead Lines 7 3.8 Changes to the Galloper Wind Farm Onshore Site 7 3.9 Project Programme 8 3.10 Pre-Construction Site Investigations 8 3.11 Onshore Construction 9 3.12 Environmental Management during Construction 9 3.13 Commissioning 10 3.14 Substation Overview 10 3.15 Decommissioning 11 3.16 Local Community Relations 11 3.17 References 11 Figures Figure 3.1 Plan and elevation of Eastern Super Grid Transformer 5 Figure 3.2 Galloper Layout showing proposed redundant elements 6 Appendices 3.1 Galloper Wind Farm Construction Code of Practice Galloper Wind Farm – Eastern Super Grid Transformer Project Environmental Statement – Chapter 3 Project Details Final February 2014 3 PROJECT DETAILS 3.1 Introduction 3.1.1 This chapter of the Environmental Statement (ES) presents the details of the Galloper Wind Farm (GWF) Eastern Super Grid Transformer (ESGT) scheme and describes the construction, operation, maintenance and decommissioning components of the project, which would primarily comprise: • Securely fenced ESGT compound containing the following plant (see Figure 3.1): o One 400/132kVsuper grid transformer including cooling bank (s) o Transformer bund o Transformer noise enclosure o 3 single phase x 132kV cable sealing ends o 3 x 132kV and 3 x 400kV surge arrestor o One three phase x 132kV and one three phase x 400kV earth switch o 3 x 400kV current transformer o One three phase x 400kV circuit breaker o One three phase x 400kV disconnector o 9 x 400kV post insulator o 3 x 400kV voltage transformer o Hard standing including a standing (service) area o Gravelled areas o 1 x oil water separator including penstock valve and sampling chamber • Three single phase 1 x 132kV underground cables (i.e. one three phase circuit) connecting the existing Leiston substation to the ESGT cable sealing ends(see figure 1.2 for this and the following elements) • Underground cable connection between the GWF substation and the existing Leiston substation • Diversion of existing underground District Network Operator (DNO) supply which passes through ESGT area • Landscaping • Permanent and temporary access roads • Service corridors, including telecommunications, water, and connection to the local electricity network 3.1.2 In addition, the western most sealing end compound, which was consented as part of the GWF Development Consent Order (DCO), will be constructed immediately to the south of the ESGT compound. A temporary construction compound and associated temporary works such as an access track from the existing site access road and from the construction compound to the ESGT will be required and will be located within an area consented under the DCO as a temporary construction area. 3.1.3 The details provided in this chapter are based on the latest knowledge and information available at the time of production of this ES. A detailed design exercise will be undertaken before construction which will result in a refinement of the design but the compound would not exceed to maximum parameters described in this chapter. In some cases, specific information relating to the ESGT is not available (for example, the exact method of construction will not be confirmed until contracts have been tendered and awarded). As such, the construction methodology provided is based on similar projects. Galloper Wind Farm – Eastern Super Grid Transformer Project Environmental Statement – Chapter 3 Project Details Final February 2014 3.1.4 The ESGT will replace the requirement for the Leiston B substation which was to be constructed within Sizewell Wents woodland (Figure 3.2. The ESGT will transform the voltage and allow the electricity generated by GWF to be fed into the 400kV transmission network. The ESGT compound, at 0.57ha (including the consented sealing end compound) will be smaller than Leiston B. The original GWF scheme would have required 1.61ha of woodland to be felled to make room for the substation, cable corridors, and access road. The ESGT compound will require approximately 0.17ha of woodland to be removed – the underground cable between the GWF compound and the Leiston A substation will be laid along the consented access road and will not require any further trees to be felled. 3.2 Outline Project Description 3.2.1 As outlined in Chapter 1, Introduction, the ESGT project comprises a development of a substation compound including a Super Grid Transformer (SGT) and associated balance of plant within the GWF onshore site to the east of two existing substations. 3.2.2 Details of the project components considered for assessment are provided throughout this chapter, along with descriptive information on the methods associated with the construction, operation and decommissioning of these components. This information has been used to inform the technical chapters contained within this ES and is considered to represent the Project’s ‘development envelope’. 3.2.3 The other onshore infrastructure such as the Galloper substation will be constructed as planned and consented through the GWF DCO, with a number of exceptions which are outlined in Section 3.7. The location of the ESGT compound is described in Chapter 2, Site Description and Land Use. 3.3 Alternatives Considered 3.3.1 The ESGT is proposed as an alternative to the proposed Leiston B substation which was consented under the GWF DCO. Leiston B substation was to be constructed within the Sizewell Wents woodland and would have led to the loss of a total of 1.61ha of semi- mature woodland. Included in this figure, a cable corridor would have been required, running from the northern edge of Leiston B around the two existing substations and into the two sealing end compounds. The location of Leiston B and the associated cable corridor is shown in Figure 3.2. 3.3.2 The ESGT will only necessitate a small area of woodland to be felled (approximately 0.17ha), primarily consisting of immature trees. The compound will include the western most sealing end compound and therefore will only require a short cable corridor to connect into the Leiston substation. This will not require the removal of any woodland habitat. The proposed location of the ESGT compound is shown in Figure 1.1. 3.3.3 Underground cabling will be installed through Sizewell Wents woodland to connect the GWF substation with the Leiston A substation. The cabling will run along the consented permanent access road through the woodland and will not necessitate any further tree felling. Galloper Wind Farm – Eastern Super Grid Transformer Project Environmental Statement – Chapter 3 Project Details Final February 2014 3.4 Onshore Substation 3.4.1 The proposed location of the ESGT compound is within an area of semi-natural grassland predominately used for grazing, located to the east of the two existing GGOWF and Leiston substations. 3.4.2 The ESGT will contain one super grid transformer (SGT) and one 400kV breaker whereas Leiston B would have contained two SGTs. Two 400kV breakers, 132 kV switchboard and associated buildings and auxiliary plant. 3.4.3 The SGT will be the largest single piece of plant within the ESGT compound. It will be connected to the 400kV overhead line system via a series of plant shown in Figure 3.1. The equipment to be provided in the ESGT along with the approximate heights are listed in Table 3.1 below. The equipment is listed in the order in which it will be installed in the ESGT compound, from north to south. Each item is shown in plan and elevation on Figure 3.1 .It should be noted that the layout is preliminary and will be subject to detailed design and micrositing before construction commences. Table 3.1 Plant to be provided in the ESGT compound Description Number required Approximate height 132kV cable sealing end 3 4.3m 132kV earth switch 3 4m 132kV surge arrestor 3 4m 400/132kV super grid transformer 1 6.2m including cooling bank 400kV surge arrestor 3 6.8 400kV earth switch 3 7.3m 400kV current transformer 3 7.3m 400kV circuit breaker 3 7.3m 400kV disconnector 3 7.3m 400kV post insulator 3 7.3m 400kV voltage transformer 3 7.3m Gantry (within consented sealing end 1 12m compound) Note: an additional 6 post insulators will be included in the sealing end compound and were consented under the GWF DCO. 3.4.4 All of the equipment in the ESGT compound will be air insulated which means that it will be built outside and not housed in a building. The super grid transformer itself will be contained in a noise enclosure. 3.4.5 The 400/132kV super grid transformer will be protected by a bund wall which will offer containment for 110% of the volume of oil held in the transformer, compliant with The Control of Pollution (Oil Storage) (England) Regulations 2001. 3.4.6 The ESGT compound will be surrounded by an electrified fence which will be 3.6m high. The fence will be of steel palisade type with an electric pulse system mounted on top. A section drawing of the proposed fencing is included on Figure 3.1. Galloper Wind Farm – Eastern Super Grid Transformer Project Environmental Statement – Chapter 3 Project Details Final February 2014 3.4.7 The ESGT will be accessed via the existing site access road which services the Leiston and GGOWF substation compounds.
Recommended publications
  • Asia Pacific Super Grid – Solar Electricity Generation, Storage and Distribution
    DOI 10.1515/green-2012-0013 Green 2012; 2(4): 189–202 Andrew Blakers*, Joachim Luther and Anna Nadolny Asia Pacific Super Grid – Solar electricity generation, storage and distribution Abstract: This paper explores the large scale transmission tries have rapidly growing economies leading to rapidly of solar electricity to Southeast Asia from Australia. growing energy demand (2). The continent of Australia Despite the expense and losses incurred in long distance has a population of 23 million people and an average pop- transmission of Australian solar electricity, it appears to ulation density of 3 people per square kilometer. Australia be competitive with locally produced solar electricity is well endowed with indigenous energy resources. In par- because of high insolation levels in Australia. Supplemen- ticular, Australia has immense solar energy resources in tation of locally produced electricity (both from renewable the centre and northwest (3). and conventional sources) with power from Australia, to- A glance at the South East Asian page of a world atlas gether with substantial integrated energy storage, would shows a long and narrow chain of islands between Austra- allow a high solar electricity fraction to be achieved in lia and the Malay Peninsula. Major desert regions exist to Southeast Asia. the north (central China) and south (central and north west Australia). This dipole suggests the possibility of Keywords: solar energy, HVDC, photovoltaics, energy storage, transporting large quantities of solar electricity to South renewable energy East Asia via high voltage cables from large solar farms located in Australia, and solar and wind farms in China. PACS® (2010). 88.05.Lg The latitudes are 20°S and 40°N respectively, which would provide seasonal balance to the solar resource from each region.
    [Show full text]
  • Power Grid Connection and Its Technical Issues
    Power Grid Connection and its Technical Issues The fourth in a 2020 series of webinars from the Clean Energy Ministerial Regional and Global Energy Interconnection Initiative May 26, 2020 1200(GMT)/2000(GMT+8, Beijing Time) Duration: 1 hour Event Link: https://meeting.tencent.com/s/5WUWiqfd9c1a(Conference ID: 950 855 652) Speaker: Prof. Ryuichi Yokoyama (Waseda University) The webinar will address: ➢ What are the current status and challenges of power grid connection in Japan and the rest of the world? ➢ Which technical performance is better in High Voltage Direct Current transmission regarding Line Commuted Converter (LCC) or Voltage Source Converter(VSC) ? ➢ What impacts does the COV-19 have on the development of energy interconnection in future? Ryuichi Yokoyama is a Professor Emeritus of Waseda University, a Life Fellow of IEEE, a Senior Life Member of IEE of Japan, a member of CIGRE. He is also Chairman of Standardization Commissions of Electric Apparatus in METI Japan. He received the degrees of B.S., M.S., and Ph.D. in electrical engineering from Waseda University, Tokyo, Japan, in 1968, 1970, and 1974 respectively. After working in Mitsubishi Research Institute, from 1978 through 2007, he was a professor in the Faculty of Technology of Tokyo Metropolitan University. Since 2007, he had been a professor of the Graduate School of Environment and Energy Engineering in Waseda University. His fields of interests include planning, operation, control and optimization of large-scale environment and energy systems, and economic analysis and risk management of deregulated power markets. About the Regional and Global Energy Interconnection (RGEI) Initiative The RGEI Initiative was established at the 9th Clean Energy Ministerial meeting in Copenhagen/Malmö in May 2018.
    [Show full text]
  • From Super Grid Transformers to Supercars
    Young Freight Forwarder 2018 From Super Grid Transformers to Supercars 28th April 2018 From Super Grid Transformers to Supercars Contents Introduction ............................................................................................................................................ 3 Import Case Study – 180 tonne Super Grid Transformer .............................................................. 5 Project Description ........................................................................................................................... 5 Cargo Details and Dimensions ....................................................................................................... 6 Key Requirements ............................................................................................................................ 6 Areas of Consideration When Tailoring Our Solution ................................................................. 7 Port Selection and Route Restrictions .......................................................................................... 8 To Crane or Not to Crane ............................................................................................................... 8 Specialist Road Haulage ............................................................................................................... 10 Delivery Site Restrictions and Installation .................................................................................. 11 Delivery of the Project ..................................................................................................................
    [Show full text]
  • Europe's Supergrid
    PROTECTING EUROPEAN CIVILISATION: EUROPE’S SUPERGRID Eddie O’Connor Marcos Byrne Introduction 1. What Europe will look like in 2050. I. What will our electrical demand be? II. How influential will rooftop solar and storage be? III. What effect will electric vehicles have on this demand? IV. How will the demand be met by renewables? 2. What Resources are available to meet this demand. I. Where will the main sources of generation be located? II. How can we access the areas of great potential? 3. How we can distribute this renewable energy. I. How do we interconnect countries with great wind and/or solar resources with those with weaker renewable resources? II. What are the challenges involved? Hemispheric Temperature Change – Annual Mean Hemispheric Temperature Change - 5-Year Running Mean 1.4 1.2 Northern Hemishpere 5-Year Running Mean 1 Southern Hemisphere 5-Year Running Mean 0.8 0.6 0.4 0.2 0 -0.2 Hemispheric Temperature Change (C) Change Temperature Hemispheric -0.4 -0.6 1880 1900 1920 1940 1960 1980 2000 2020 EU 2020 Strategy and the Paris Climate Agreement • 20% reduction in greenhouse gas emissions (from 1990 levels). • 20% of EU energy from renewables • This target varies between countries depending on their starting points. • 20% increase in energy efficiency. • The 2020 strategy feeds into future targets such as reducing EU emissions by 40% by 2040. • All EU countries are also part of the Paris Climate Agreement. Source: UNEP What does European demand look like now? EU Electricity Generation by Fuel Type 4,000 3,500 3,335 3,269
    [Show full text]
  • A Road Map to Deliver Smart Grid in the UK Simon Skillings
    A Road Map to Deliver Smart Grid in the UK Simon Skillings Summary The concept of a ‘smart grid’ involves the combination of instrumentation, communications and analytics that allows power network infrastructure to be operated in a dynamic and efficient manner as opposed to the ‘passive’ operational approach which is currently the norm in the UK. There exists general consensus that the challenges of climate change and system security, in particular the ability to accommodate significant volumes of decentralised and renewable generation, requires that the network infrastructure must be upgraded to enable smart operation. Failure to do so will act as a major obstacle in the transition to a low carbon economy. A second important aspect of network development involves the construction of a number of strategic interconnections across the North Sea to create a new off-shore grid. This opens up the opportunity to more fully exploit the vast untapped potential of off-shore wind energy. However, there are a series of obstacles which have hitherto hindered progress in upgrading the network. In particular, the current regulatory regime is not well designed to encourage network operators to embrace new technological opportunities and this is exacerbated by the extent of the risk and uncertainty involved. The government has a key role to play in injecting the necessary momentum by providing strong direction to the regulator on the outcomes that must be delivered. In addition, the government needs to ensure the appropriate financing routes are in place that will enable Ofgem to set a regulatory framework that leads to a low cost of capital for investors whilst retaining the necessary management incentives on network operators to deliver the required outcomes.
    [Show full text]
  • National Grid Electricity Transmission Nationalgrid Annual Summary 2014/15 Network Innovation Allowance
    National Grid Electricity Transmission nationalgrid Annual Summary 2014/15 Network Innovation Allowance Click here to enter Welcome 02 This is the second Annual Summary of National Grid Electricity Transmission’s Welcome(NGET) projects under the Network Innovation Allowance (NIA). 2014/15 has been a year of enhanced focus on innovation in Electricity Transmission, with a Strategy number of successful initiatives implemented into our ways of working. update We have further enhanced our innovation our organisational design review for capabilities and partnerships, delivering innovation. This will provide enhanced a balanced consumer-value focused clarity of responsibilities and accountabilities portfolio of projects through our Network for selecting, prioritising and delivering Innovation Allowance (NIA). We have also innovation projects and implementing Our portfolio of innovation projects been successful in securing funding for our successful outcomes into day-to-day covers the full spectrum of our strategic Smart Frequency Control (EFCC) Network business operations. A panel of Directors priorities, with work progressing on Innovation Competition (NIC) project. from all of National Grid’s UK RIIO-regulated opportunities reflecting long-term and Innovation can be summed up as the business has been established with short-term potential. To leverage the best act of matching what is needed with what accountability for our UK technology and value for GB consumers we have been is possible, to deliver a better outcome. innovation strategy. The energy systems in Great Britain (GB) proactively sharing the knowledge gained are undergoing fundamental changes. from our research and innovation activities This, coupled with the changing ways in with other network owners. This has been which consumers use energy, means that We have done some done through a knowledge sharing forum what is needed to maintain safe, reliable fantastic work in innovation for the Onshore and Offshore Transmission and affordable energy is rapidly evolving.
    [Show full text]
  • Using of HVDC Technology in Super Grids Ines Bula University for Business and Technology, [email protected]
    University of Business and Technology in Kosovo UBT Knowledge Center UBT International Conference 2017 UBT International Conference Oct 27th, 3:00 PM - 4:30 PM Using of HVDC Technology in Super Grids Ines Bula University for Business and Technology, [email protected] Valmira Hoxha University for Business and Technology, [email protected] Edin Bula University for Business and Technology, [email protected] Follow this and additional works at: https://knowledgecenter.ubt-uni.net/conference Part of the Bioresource and Agricultural Engineering Commons Recommended Citation Bula, Ines; Hoxha, Valmira; and Bula, Edin, "Using of HVDC Technology in Super Grids" (2017). UBT International Conference. 142. https://knowledgecenter.ubt-uni.net/conference/2017/all-events/142 This Event is brought to you for free and open access by the Publication and Journals at UBT Knowledge Center. It has been accepted for inclusion in UBT International Conference by an authorized administrator of UBT Knowledge Center. For more information, please contact [email protected]. Using of HVDC Technology in Super Grids Ines Bula1, Valmir Hoxha2, Edin Bula 3 1,2,3 UBT – Higher Education Institution, Lagjja Kalabria, 10000 p.n., Prishtine, Kosovo {ines.bula, valmir.hoxha}@ubt-uni.net; [email protected], Abstract. This paper describes the HVDC system, its organization, as well as advantages over the AC system. Implementation of this system will help to make Europe sustainable energy independent which will require a renewable generation portfolio where much of this portfolio will be fueled by wind and will be developed offshore as it is presented in this paper.
    [Show full text]
  • Solutions for Smart and Super Grids with HVDC and FACTS
    Technical article ■ Authors: M. Claus, D. Retzmann, D. Sörangr, K. Uecker Solutions for Smart and Super Grids with HVDC and FACTS Answers for energy. Content 0. Abstract 3 I. Introduction 3 II. HVDC and FACTS Technologies 3 A HVDC Developments 4 B FACTS Developments 5 III. Security and Sustainability of Power Supply with HVDC and FACTS 5 A Neptune HVDC Project – USA 5 B Basslink HVDC – Australia 6 C Prospects of HVDC in India 6 D Prospects of HVDC in China 7 E HVDC and FACTS in parallel Operation 8 F Prospects of VSC HVDC 9 IV. Conclusions 9 V. References 12 2 17th Conference of the Electric Power Supply Industry 27 - 31 October 2008 Solutions for Smart and Super Grids with HVDC and FACTS M. Claus, D. Retzmann1, D. Sörangr, K. Uecker Siemens AG Erlangen, Germany [email protected] Abstract— Deregulation and privatization are posing new grid of the future must be secure, cost-effective and challenges to high-voltage transmission systems. High-voltage environmentally compatible [2]. The combination of these power electronics, such as HVDC (High Voltage Direct Current) three tasks can be tackled with the help of ideas, intelligent and FACTS (Flexible AC Transmission Systems), provide the solutions as well as innovative technologies. The combination necessary features to avoid technical problems in heavily loaded of these three tasks can be solved with the help of ideas, power systems; they increase the transmission capacity and system stability very efficiently and assist in preventing intelligent solutions as well as innovative technologies. cascading disturbances. Environmental constraints, such as Innovative solutions with HVDC and FACTS have the energy saving, loss minimization and CO2 reduction, will also potential to cope with the new challenges.
    [Show full text]
  • Features of Power System and Issues on International Connection in Japan
    Features of Power System and Issues on International Connection in Japan Ryuichi YOKOYAMA 横山 隆一 Waseda University 早稲田大学 名誉教授 1 Copyright: Ryuichi Yokoyama, Waseda University, Japan Outline of Presentation ・ Future Electric Power Grids for Effective Use of Sustainable Energy ・ Super Grid for Cross-Reginal Electricity Transfer ・ Features of Power System and Issues on International Connection in Japan 2 Copyright: Ryuichi Yokoyama, Waseda University, Japan Future Electric Power Grids for Effective Use of Sustainable Energy 3 Copyright: Ryuichi Yokoyama, Waseda University, Japan Paradigm Shift toward Best Energy Mix from Nuclear-Centered Generation Mix Generation Mix based on Large Scale Plants Thermal Plant Hydro Plant Residence Factory Wind Tsunami Nuclear Plant Generation 2011 Storage Storage Transmission Distribution Distribution Network Substation PV Generation Network Energy Saving Local Generation Best Energy Mix based on Distributed Generation and Network Generation Generation Battery Energy Storage GE with Fossil Energy with Sustainable Energy Lead Battery Ni-MH Battery - - e → 放 電 e → 負負 極 極 正正 極 極 ↑ e - e - ↓ H 2 O H 2 O N iO O H ← e - 水 素 H + - LNG Thermal Plant (1GW) - - e - → OH OH N i( O H ) 2 水 素 吸 蔵 合 金 オ キ シ 水 酸 化 ニ ッ ケ ル - Gas Combined Cycle (0.3GW) EDLC Li-Ion Battery 電子 - → e 放 電 - Gas Engine (10KW – 1MW) 負 極 正 極 Li+ - IGCC (Clean Coal Generation) 炭素材料 (黒鉛層間化合物) 遷移金属酸化物 - Fuel Cell 空のLi+サイト 4 Copyright: Ryuichi Yokoyama, Waseda University, Japan Issues in Power System Operation by Large Scale Instillation of Sustainable Energy ○ By large scale installation of sustainable energy such as PV generation, new problems in power grids ; Excess energy, Voltage increase and Shortage of frequency control capacity occur.
    [Show full text]
  • Scientific American: a Power Grid for the Hydrogen Economy 08/16/2006 06:42 PM
    Scientific American: A Power Grid for the Hydrogen Economy 08/16/2006 06:42 PM June 26, 2006 A Power Grid for the Hydrogen Economy Cryogenic, superconducting conduits could be connected into a "SuperGrid" that would simultaneously deliver electrical power and hydrogen fuel By Paul M. Grant, Chauncey Starr and Thomas J. Overbye On the afternoon of August 14, 2003, electricity failed to arrive in New York City, plunging the eight million inhabitants of the Big Apple--along with 40 million other people throughout the northeastern U.S. and Ontario--into a tense night of darkness. After one power plant in Ohio had shut down, elevated power loads overheated high-voltage lines, which sagged into trees and short-circuited. Like toppling dominoes, the failures cascaded through the electrical grid, knocking 265 power plants offline and darkening 24,000 square kilometers. That incident--and an even more extensive blackout that affected 56 million people in Italy and Switzerland a month later-- called attention to pervasive problems with modern civilization's vital equivalent of a biological circulatory system, its interconnected electrical networks. In North America the electrical grid has evolved in piecemeal fashion over the past 100 years. Today the more than $1-trillion infrastructure spans the continent with millions of kilometers of wire operating at up to 765,000 volts. Despite its importance, no single organization has control over the operation, maintenance or protection of the grid; the same is true in Europe. Dozens of utilities must cooperate even as they compete to generate and deliver, every second, exactly as much power as customers demand--and no more.
    [Show full text]
  • 'Supersmart Grid' Could Connect up Renewable Energy Across Europe
    4 June 2009 ‘SuperSmart Grid’ could connect up renewable energy across Europe Renewable energy could help Europe meet twin goals: a more secure energy supply and climate change mitigation. A recent study describes a new approach to electricity distribution in the form of a ‘SuperSmart Grid’. This supports both long-distance transmission and decentralised energy generation and could enable a 100 per cent renewable electricity system by 2050. A major problem with renewable energy, such as wind and solar power, is that supply is often intermittent, causing fluctuations and strain on the grid system. In addition, the current European grid system is unable to meet rising energy demands and needs to be transformed. Proposals for overcoming these problems include 1) a large-scale grid to transmit electricity from renewable sources over long distances, a ‘Super Grid’, and 2) decentralising production of renewable electricity from distributed, small installations, such as micro turbines, fuel cells or biogas digesters: a ‘Smart Grid’. The researchers, working under the EU CIRCE project1, suggest that these two proposals could be combined to create the SuperSmart Grid (SSG). This would transmit electricity over a wide area and connect up smaller, distributed generation installations. An efficient SSG would also even out any fluctuations over a wide area. The authors argue that a 100 per cent renewable electricity system is necessary if Europe is to meet its target of reducing greenhouse gas emissions by 60-80 per cent, compared with pre-industrial levels by 2050, (in line with the policy to limit the global average temperature increase to not more than 2ºC) and that the SSG would enable this system.
    [Show full text]
  • The Prospect for an Australian–Asian Power Grid: a Critical Appraisal
    energies Review The Prospect for an Australian–Asian Power Grid: A Critical Appraisal Edward Halawa 1,2,*, Geoffrey James 3, Xunpeng (Roc) Shi 4,5 ID , Novieta H. Sari 6,7 and Rabindra Nepal 8 1 Barbara Hardy Institute, School of Engineering, University of South Australia, Mawson Lakes, SA 5095, Australia 2 Centre for Renewable Energy, Research Institute for the Environment and Livelihoods, Charles Darwin University, Darwin, NT 0909, Australia 3 Institute for Sustainable Futures, University of Technology Sydney, Ultimo, NSW 2007, Australia; [email protected] 4 Australia China Relations Institute, University of Technology Sydney, Ultimo, NSW 2007, Australia; [email protected] 5 Energy Studies Institute, National University of Singapore, Singapore 119077, Singapore 6 Department of Communication, Universitas Nasional, Jakarta 12520, Indonesia; [email protected] 7 The School of Geography, Politics and Sociology, Newcastle University, Newcastle upon Tyne NE1 7RU, UK 8 School of Economics and Finance, Massey University, Auckland Campus, Albany 0632, New Zealand; [email protected] * Correspondence: [email protected]; Tel.: +61-8-8302-3329 Received: 17 October 2017; Accepted: 11 January 2018; Published: 15 January 2018 Abstract: Australia is an energy net self-sufficient country rich in energy resources, from fossil-based to renewable energy. Australia, a huge continent with low population density, has witnessed impressive reduction in energy consumption in various sectors of activity in recent years. Currently, coal and natural gas are two of Australia’s major export earners, yet its abundant renewable energy resources such as solar, wind, and tidal, are still underutilized. The majority of Asian countries, on the other hand, are in the middle of economic expansion, with increasing energy consumption and lack of energy resources or lack of energy exploration capability becoming a serious challenge.
    [Show full text]