<<

1/9/2020

Bryan/College Station MPO Initiated Projects

January 9, 2020 Bryan/College Station Real Estate Association Luncheon

Daniel Rudge MPO Executive Director

1

#81 – FM 2818 (Harvey Mitchell Pkwy.)

Project Description Congestion Score Limits From: FM 60 39.19 Limits To: FM 2154 Safety Score Project Description: Widen , quadrant 50 or other, raised median & bicycle/pedestrian Technical Score facilities 89.19 YOE Project Cost Final Ranking $ 27,150,000 1

Project Ranking: First Five Years (2015 ‐ 2019)

YOE MPO TxDOT Facility & Funding 2014 Construction YOE Total Project Cost Project Limits Project Description Base Project Project Project Length Source(s) Estimate Estimate Year

FM 2818 (S) ‐ From FM 60 Widen road, quadrant intersection or other, raised 81 2399‐01‐074 MPO $ 25,400,000 2017 $ 27,150,000 2.25 mi To FM 2154 median & bicycle/pedestrian facilities

2

1 1/9/2020

FM 2818 • Schematic Design complete • Construction Documents to be completed early 2020 • Construction anticipated mid 2020 – early 2022

3

From FHWA’s “Restricted Crossing U‐turn Informational Guide”

4

2 1/9/2020

ONE BIG ADVANTAGE IS... • The “super ” can be transformed into frontage for a freeway (when the time is right)

5

#24 – FM 158 (William J. Bryan)

Project Description Congestion Score Limits From: BS 6‐R (Texas 40.54 Ave.) Limits To: SH 6 Safety Score

Project Description: 18.75 Construct controlled access raised medians & pedestrian Technical Score facilities 59.29 YOE Project Cost Final Ranking $ 11,900,000 2

Project Ranking: Second Five Years (2020 ‐ 2024)

YOE MPO Facility & Funding 2014 Construction YOE Total Project Cost TxDOT Project Project Limits Project Description Base Project Project Length Source(s) Estimate Estimate Year

FM 158 ‐ From BS 6‐R Construct controlled access raised medians, add 24 0212‐03‐050 MPO$ 8,000,000 2020$ 11,900,000 1.85 mi To SH 6 signals and pedestrian facilities

6

3 1/9/2020

7

#49 – State 6

Project Description Congestion Score Limits From: State Highway 50.00 21 Limits To: State Highway 40 Safety Score

Project Description: Widen 4 50.00 to 6 lanes Technical Score 100.00 YOE Project Cost Final Ranking $ 174,320,000 3

Project Ranking: Second Five Years (2020 ‐ 2024)

2014 YOE MPO Facility & Funding YOE Total Project TxDOT Project Project Limits Project Description Construction Base Project Project Length Source(s) Cost Estimate Estimate Year

SH 6 ‐ From SH 21 To SH 40 Widen from 4 to 6 lanes, frontage road 49 0049‐12‐110 State & MPO $ 148,172,000 2020$ 174,320,000 11.0 mi expansion and other improvements

8

4 1/9/2020

State Highway 6 Improvements

 Just beginning design phase  Most likely split into two projects  Project One: Upgrade deficient interchanges  Project Two: Expand to six lanes with:  Improved frontage roads (bike/ped additions)  Collector/Distributor lanes

9

SH 6 After Construction

10

5 1/9/2020

SH 6 After Construction

11

SH 6 After Construction

12

6 1/9/2020

#27 – FM 2347 (Wellborn Rd)

Project Description Congestion Score At: FM 2154 (George Bush 1.35 Dr.)/UPRR Safety Score Project Description: Construct multimodal single‐ 37.50 point urban (SPUI) Technical Score 38.85 YOE Project Cost Final Ranking $ 57,300,000* * This project is not fully funded 5

Project Ranking: Final Fifteen Years (2025 ‐ 2039) YOE MPO Facility & Funding 2014 Construction YOE Total Project Cost TxDOT Project Project Limits Project Description Base Project Project Length Source(s) Estimate Estimate Year FM 2347 At FM 2154 & Union Construct multimodal Single Point Urban Interchane 27 3138‐01‐020 State & MPO$ 25,000,000 2031$ 57,300,000 1 mi Pacific Railroad ()

13

Looking Southwest From Kyle Field

Below‐Ground Concept for Bush‐Wellborn Intersection

14

7 1/9/2020

Tell Us What You Think – Phase 2!

• Phase 1 survey said the public prefers a below‐ground option to an above‐ ground option. • Phase 1 respondents said they want the project done right, even if there is traffic pain. • Phase 2 – Go back to the public and ask: What is the right balance between seeing construction and increased travel times due to intersection closure?  Understand the travel route and schedule options.  Seeing equipment ‐ Is it OK if we keep traffic lanes open?  Close intersection & increase travel times – How long can we accept long travel times?  Setting expectations ‐ Bush‐Wellborn is one piece of the puzzle – this project will NOT fix all of our traffic problems.

15

16

8 1/9/2020

Thank You!

January 9, 2020 Bryan/College Station Real Estate Association Luncheon

Daniel Rudge MPO Executive Director

17

Contact Information

Contact Daniel Rudge at: Email: [email protected] [email protected] Phone: (979) 260-5298x1001 Fax: (979) 260-5225 Or come visit him at: Bryan-College Station MPO 309 North Washington Suite 14 Bryan, TX 77803

18

9