<<

Contract Provisions and Plans

For of:

HMA OVERLAY PROJECT (2019) #ESHMA19-1

SKAGIT COUNTY PUBLIC WORKS

SCOPE OF WORK

HMA Overlay Project (2019) #ESHMA19-1

Schedule A: McLean Road #44000 includes, but is not limited to: planing full length and width of existing asphalt for approximately 1.70 miles; hauling planings to a County determined site; placing and compacting a 0.15 ft. HMA Cl 3/8’ PG 58H-22 wearing course on the planed surface with a Material Transfer Device (MTD); pavement repair; placement of temporary pavement markers; providing erosion control; trimming and cleanup; traffic control; signage; and other work.

Schedule B: Cook Road #63000: includes, but is not limited to: planing and paving of existing for approximately 0.10 mile; hauling planings to a County determined site; placing and compacting a 0.15 ft. HMA Cl. 3/8” PG 58H-22 wearing course on the planed surface; pavement repair; working within BNSF right-of-way; placement of plastic pavement lines; replacement of traffic loops; providing erosion control; trimming and cleanup; traffic control; signage; and other work.

Schedule: All work to be completed within 25 working days from Notice to Proceed.

Measurement & Payment: Each item will be per the bid proposal.

PAGE

1 CONTENTS 2

3 4 INTRODUCTION------1 5 AMENDMENTS TO THE STANDARD SPECIFICATIONS

6 Section 1-01, Definitions and Terms ------1 7 Section 1-02, Bid Procedures and Conditions ------1 8 Section 1-03, Award and Execution of Contract ------2 9 Section 1-05, Control of Work ------3 10 Section 1-06, Control of Material ------4 11 Section 1-07, Legal Relations and Responsibilities to the Public ------5 12 Section 1-08, Prosecution and Progress ------9 13 Section 1-09, Measurement and Payment ------10 14 Section 2-02, Removal of Structures and Obstructions------10 15 Section 2-09, Structure Excavation ------10 16 Section 3-01, Production from Quarry and Pit Sites ------11 17 Section 4-04, Ballast and Crushed Surfacing ------11 18 Section 5-01, Pavement Rehabilitation ------11 19 Section 5-04, Hot Mix Asphalt ------14 20 Section 5-05, Cement Concrete Pavement ------49 21 Section 6-01, General Requirements for Structures ------50 22 Section 6-02, Concrete Structures ------51 23 Section 6-03, Steel Structures ------64 24 Section 6-05, Piling ------64 25 Section 6-07, Painting ------64 26 Section 6-08, Waterproofing ------69 27 Section 6-09, Modified Concrete Overlays ------78 28 Section 6-10, Concrete Barrier ------78 29 Section 6-11, Walls ------79 30 Section 6-12, Noise Barrier Walls ------79 31 Section 6-13, Structural Earth Walls ------80 32 Section 6-14, Geosynthetic Retaining Walls ------80 33 Section 6-15, Soil Nail Walls ------80

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 A PAGE

1 Section 6-16, Soldier Pile and Soldier Pile Tieback Walls------81 2 Section 6-18, Shotcrete Facing ------81 3 Section 6-19, Shafts ------81 4 Section 7-02, Culverts ------90 5 Section 7-05, Manholes, Inlets, Catch Basins, and Drywells ------90 6 Section 7-08, General Pipe Installation Requirements ------91 7 Section 8-01, Erosion Control and Water Pollution Control ------91 8 Section 8-02, Roadside Restoration------104 9 Section 8-04, , Gutters, and Spillways ------105 10 Section 8-06, Cement Concrete Driveway Entrances ------105 11 Section 8-07, Precast Traffic ------105 12 Section 8-11, Guardrail ------106 13 Section 8-14, Cement Concrete Sidewalks ------107 14 Section 8-16, Concrete Slope Protection ------107 15 SECTION 8-17, IMPACT ATTENUATOR SYSTEMS ------107 16 Section 8-20, Illumination, Traffic Signal Systems, Intelligent Transportation Systems, and 17 Electrical ------107 18 Section 8-21, Permanent Signing ------108 19 Section 8-22, Pavement Marking ------109 20 Section 9-00, Definitions and Tests ------109 21 Section 9-02, Bituminous Materials------110 22 Section 9-03, Aggregates ------111 23 Section 9-04, Joint and Crack Sealing Materials ------114 24 Section 9-05, Drainage Structures and Culverts ------115 25 Section 9-06, Structural Steel and Related Materials ------116 26 Section 9-07, Reinforcing Steel ------116 27 Section 9-08, Paints and Related Materials ------116 28 Section 9-13, Riprap, Quarry Spalls, Slope Protection, and Rock for Erosion and Scour 29 Protection and Rock Walls ------117 30 Section 9-14, Erosion Control and Roadside Planting ------118 31 Section 9-16, Fence and Guardrail ------118 32 Section 9-18, Precast Traffic Curb ------119 33 Section 9-20, Concrete Patching Material, Grout, and Mortar ------119 34 Section 9-21, Raised Pavement Markers (RPM) ------119 35 Section 9-26, Epoxy Resins ------120

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 B PAGE

1 Section 9-28, Signing Materials and Fabrication ------120 2 Section 9-29, Illumination, Signal, Electrical ------122 3 Section 9-33, Construction Geosynthetic ------132 4 Section 9-34, Pavement Marking Material ------132 5 SPECIAL PROVISIONS

6 DIVISION 1 7 GENERAL REQUIREMENTS

8 DESCRIPTION OF WORK ------136 9 Definitions ------136 10 BID PROCEDURES AND CONDITIONS ------138 11 Prequalification of Bidders ------138 12 Qualifications of Bidder ------138 13 Plans and Specifications ------138 14 Examination of Plans, Specifications and Site of Work ------139 15 General ------139 16 Proposal Forms ------139 17 Preparation of Proposal ------139 18 Recycled Materials Proposal ------139 19 Bid Deposit ------139 20 Withdrawing, Revising, or Supplementing Proposal ------140 21 Public Opening Of Proposal ------141 22 Irregular Proposals ------141 23 Disqualification of Bidders ------142 24 Pre Award Information ------142 25 AWARD AND EXECUTION OF CONTRACT ------143 26 Identical Bid Totals ------143 27 Execution of Contract ------143 28 Contract Bond ------143 29 Judicial Review ------144 30 SCOPE OF WORK ------145 31 Coordination of Contract Documents, Plans, Special Provisions, ------145 32 CONTROL OF WORK ------145 33 Conformity With and Deviations from Plans and Stakes ------145 34 Contractor Surveying - Roadway ------145

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 C PAGE

1 Superintendents, Labor and Equipment of Contractor ------148 2 Method of Serving Notices ------148 3 Water and Power ------148 4 Recycled Materials ------149 5 Laws to be Observed ------149 6 State Sales Tax ------150 7 Sanitation------151 8 General ------151 9 Load Limits ------151 10 Wages ------151 11 Utilities and Similar Facilities ------151 12 Public Liability and Property Damage Insurance ------152 13 Relations With Railroad ------156 14 Construction Under Traffic ------158 15 Prosecution and Progress ------160 16 Preliminary Matters ------160 17 Preconstruction Conference ------160 18 Hours of Work ------160 19 Subcontracting ------161 20 Prosecution of Work ------162 21 Notice to Proceed and Prosecution of Work ------162 22 PROSECUTION AND PROGRESS ------162 23 Liquidated Damages ------162 24 MEASUREMENT AND PAYMENT ------163 25 Weighing Equipment ------163 26 General Requirements for Weighing Equipment ------163 27 Measurement ------163 28 Force Account ------163 29 Time Limitation and Jurisdiction ------164 30 Claims $250,000 or Less ------164 31 Administration of Arbitration------164 32 TEMPORARY TRAFFIC CONTROL ------165 33 Traffic Control Management ------165 34 General ------165

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 D PAGE

1 Measurement ------165 2 Payment ------166 3 Item Bids with Lump Sum for Incidentals ------166 4 DIVISION 2 5 EARTHWORK

6 CLEARING, GRUBBING, AND ROADSIDE CLEANUP ------167 7 Description ------167 8 Preparation of Existing Surfaces ------167 9 Measurement ------167 10 Payment ------167 11 TRIMMING AND CLEANUP ------167 12 Description ------167 13 Construction Requirements ------167 14 DIVISION 5 15 SURFACE TREATMENTS AND PAVEMENTS

16 HOT MIX ASPHALT ------169 17 ESAL's ------171 18 DIVISION 8 19 MISCELLANEOUS CONSTRUCTION

20 EROSION CONTROL AND WATER POLLUTION CONTROL ------199 21 ILLUMINATION, TRAFFIC SIGNAL SYSTEMS, INTELLIGENT TRANSPORTATION 22 SYSTEMS, AND ELECTRICAL ------199 23 Description ------199 24 Materials ------199 25 Equipment List And Drawings ------199 26 Construction Requirements ------199 27 Conduit ------199 28 Junction Boxes, Cable Vaults, and Pull boxes ------200 29 Signal Systems ------201 30 Induction Loop Tests ------201 31 Measurement ------204 32 Payment ------204 33 APPENDICES ------205 34 STANDARD PLANS ------206

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 E 1 INTRODUCTION

2 The following Amendments and Special Provisions shall be used in conjunction with the 2018 3 Standard Specifications for Road, Bridge, and Municipal Construction. 4 5 AMENDMENTS TO THE STANDARD SPECIFICATIONS 6 7 The following Amendments to the Standard Specifications are made a part of this contract and 8 supersede any conflicting provisions of the Standard Specifications. For informational 9 purposes, the date following each Amendment title indicates the implementation date of the 10 Amendment or the latest date of revision. 11 12 Each Amendment contains all current revisions to the applicable section of the Standard 13 Specifications and may include references which do not apply to this particular project. 14 15 Section 1-01, Definitions and Terms 16 August 6, 2018

17 1-01.3 Definitions 18 The following new term and definition is inserted before the definition for “Shoulder”: 19 20 Sensitive Area – Natural features, which may be previously altered by human activity, 21 that are present on or adjacent to the project location and protected, managed, or 22 regulated by local, tribal, state, or federal agencies. 23 24 The following new term and definition is inserted after the definition for “Working Drawings”: 25 26 WSDOT Form – Forms developed and maintained by WSDOT that are required or 27 available for use on a project. These forms can be downloaded from the forms catalogue 28 at: 29 30 http://wsdot.wa.gov/forms/pdfForms.html 31 32 Section 1-02, Bid Procedures and Conditions 33 June 3, 2019

34 1-02.4(1) General 35 This section is supplemented with the following: 36 37 Prospective Bidders are advised that the Contracting Agency may include a partially 38 completed Washington State Department of Ecology (Ecology) Transfer of Coverage 39 (Ecology Form ECY 020-87a) for the Construction Stormwater General Permit (CSWGP) 40 as part of the Bid Documents. When the Contracting Agency requires the transfer of 41 coverage of the CSWGP to the Contractor, an informational copy of the Transfer of 42 Coverage and the associated CSWGP will be included in the appendices. As a condition 43 of Section 1-03.3, the Contractor is required to complete sections I, III, and VIII of the 44 Transfer of Coverage and return the form to the Contracting Agency. 45 46 The Contracting Agency is responsible for compliance with the CSWGP until the end of 47 day that the Contract is executed. Beginning on the day after the Contract is executed, 48 the Contractor shall assume complete legal responsibility for compliance with the CSWGP

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 1 1 and full implementation of all conditions of the CSWGP as they apply to the Contract 2 Work. 3 4 1-02.5 Proposal Forms 5 The first sentence of the first paragraph is revised to read: 6 7 At the request of a Bidder, the Contracting Agency will provide a physical Proposal Form 8 for any project on which the Bidder is eligible to Bid. 9 10 1-02.6 Preparation of Proposal 11 Item number 1 of the second paragraph is revised to read: 12 13 1. A unit price for each item (omitting digits more than two places to the right of the 14 decimal point), 15 16 In the third sentence of the fourth paragraph, “WSDOT Form 422-031” is revised to read 17 “WSDOT Form 422-031U”. 18 19 The following new paragraph is inserted before the last paragraph: 20 21 The Bidder shall submit with their Bid a completed Contractor Certification Wage Law 22 Compliance form (WSDOT Form 272-009). Failure to return this certification as part of 23 the Bid Proposal package will make this Bid Nonresponsive and ineligible for Award. A 24 Contractor Certification of Wage Law Compliance form is included in the Proposal Forms. 25 26 1-02.13 Irregular Proposals 27 Item 1(h) is revised to read: 28 29 h. The Bidder fails to submit Underutilized Disadvantaged Business Enterprise Good 30 Faith Effort documentation, if applicable, as required in Section 1-02.6, or if the 31 documentation that is submitted fails to demonstrate that a Good Faith Effort to meet 32 the Condition of Award was made; 33 34 Item 1(i) is revised to read the following three items: 35 36 i. The Bidder fails to submit a UDBE Bid Item Breakdown form, if applicable, as 37 required in Section 1-02.6, or if the documentation that is submitted fails to meet the 38 requirements of the Special Provisions; 39 40 j. The Bidder fails to submit UDBE Trucking Credit Forms, if applicable, as required in 41 Section 1-02.6, or if the documentation that is submitted fails to meet the 42 requirements of the Special Provisions; or 43 44 k. The Bid Proposal does not constitute a definite and unqualified offer to meet the 45 material terms of the Bid invitation. 46 47 Section 1-03, Award and Execution of Contract 48 January 2, 2018

49 1-03.3 Execution of Contract 50 The first paragraph is revised to read: 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 2 1 Within 20 calendar days after the Award date, the successful Bidder shall return the 2 signed Contracting Agency-prepared Contract, an insurance certification as required by 3 Section 1-07.18, a satisfactory bond as required by law and Section 1-03.4, the Transfer 4 of Coverage form for the Construction Stormwater General Permit with sections I, III, and 5 VIII completed when provided, and shall be registered as a contractor in the state of 6 Washington. 7 8 1-03.5 Failure to Execute Contract 9 The first sentence is revised to read: 10 11 Failure to return the insurance certification and bond with the signed Contract as required 12 in Section 1-03.3, or failure to provide Disadvantaged, Minority or Women’s Business 13 Enterprise information if required in the Contract, or failure or refusal to sign the Contract, 14 or failure to register as a contractor in the state of Washington, or failure to return the 15 completed Transfer of Coverage for the Construction Stormwater General Permit to the 16 Contracting Agency when provided shall result in forfeiture of the proposal bond or deposit 17 of this Bidder. 18 19 Section 1-05, Control of Work 20 August 6, 2018

21 1-05.5 Vacant 22 This section, including title, is revised to read: 23 24 1-05.5 Tolerances 25 Geometrical tolerances shall be measured from the points, lines, and surfaces defined in 26 Contract documents. 27 28 A plus (+) tolerance increases the amount or dimension to which it applies, or raises a 29 deviation from level. A minus (-) tolerance decreases the amount or dimension to which it 30 applies, or lowers a deviation from level. Where only one signed tolerance is specified (+ 31 or -), there is no specified tolerance in the opposing direction. 32 33 Tolerances shall not be cumulative. The most restrictive tolerance shall control. 34 35 Tolerances shall not extend the Work beyond the Right of Way or other legal boundaries 36 identified in the Contract documents. If application of tolerances causes the extension of 37 the Work beyond the Right of Way or legal boundaries, the tolerance shall be reduced for 38 that specific instance. 39 40 Tolerances shall not violate other Contract requirements. If application of tolerances 41 causes the Work to violate other Contract requirements, the tolerance shall be reduced 42 for that specific instance. If application of tolerances causes conflicts with other 43 components or aspects of the Work, the tolerance shall be reduced for that specific 44 instance. 45 46 1-05.9 Equipment 47 The following new paragraph is inserted before the first paragraph: 48 49 Prior to mobilizing equipment on site, the Contractor shall thoroughly remove all loose dirt 50 and vegetative debris from drive mechanisms, wheels, tires, tracks, buckets and 51 undercarriage. The Engineer will reject equipment from the site until it returns clean.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 3 1 2 This section is supplemented with the following: 3 4 Upon completion of the Work, the Contractor shall completely remove all loose dirt and 5 vegetative debris from equipment before removing it from the job site. 6 7 Section 1-06, Control of Material 8 August 7, 2017

9 This section is supplemented with the following new section and subsections: 10 11 1-06.6 Recycled Materials 12 The Contractor shall make their best effort to utilize recycled materials in the construction 13 of the project; the use of recycled concrete aggregate as specified in Section 1-06.6(1)A 14 is a requirement of the Contract. 15 16 The Contractor shall submit a Recycled Material Utilization Plan as a Type 1 Working 17 Drawing within 30 calendar days after the Contract is executed. The plan shall provide 18 the Contractor’s anticipated usage of recycled materials for meeting the requirements of 19 these Specifications. The quantity of recycled materials will be provided in tons and as a 20 percentage of the Plan quantity for each material listed in Section 9-03.21(1)E Table on 21 Maximum Allowable Percent (By Weight) of Recycled Material. When a Contract does 22 not include Work that requires the use of a material that is included in the requirements 23 for using materials the Contractor may state in their plan that no recycled materials are 24 proposed for use. 25 26 Prior to Physical Completion the Contractor shall report the quantity of recycled materials 27 that were utilized in the construction of the project for each of the items listed in Section 28 9-03.21. The report shall include hot mix asphalt, recycled concrete aggregate, recycled 29 glass, steel furnace slag and other recycled materials (e.g. utilization of on-site material 30 and aggregates from concrete returned to the supplier). The Contractor’s report shall be 31 provided on DOT Form 350-075 Recycled Materials Reporting. 32 33 1-06.6(1) Recycling of Aggregate and Concrete Materials 34 1-06.6(1)A General 35 The minimum quantity of recycled concrete aggregate shall be 25 percent of the total 36 quantity of aggregate that is incorporated into the Contract for those items listed in 37 Section 9-03.21(1)E Table on Maximum Allowable Percent (By Weight) of Recycled 38 Material that allow the use of recycled concrete aggregate. The percentage of 39 recycled material incorporated into the project for meeting the required percentage 40 will be calculated in tons based on the quantity of recycled concrete used on the 41 entire Contract and not as individual items. 42 43 If the Contractor’s total cost for Work with recycled concrete aggregate is greater 44 than without the Contractor may choose to not use recycled concrete aggregate. If 45 the Recycled Material Utilization Plan does not indicate the minimum usage of 46 recycled concrete aggregate required above, or if completed project quantities do 47 not meet the minimum usage required, the Contractor shall develop the following: 48 49 1. A cost estimate for each material listed in Section 9-03.21(1)E that is utilized 50 on the Contract. The cost estimate shall include the following: 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 4 1 a. The estimated costs for the Work for each material with 25 percent 2 recycled concrete aggregate. The cost estimate shall include for each 3 material a copy of the price quote from the supplier with the lowest total 4 cost for the Work. 5 6 b. The estimated costs for the Work for each material without recycled 7 concrete aggregate. 8 9 The Contractor’s cost estimates shall be submitted as an attachment to the Recycled 10 Material Utilization Plan, or with the Reporting form. 11 12 Section 1-07, Legal Relations and Responsibilities to the Public 13 August 6, 2018

14 1-07.5 Environmental Regulations 15 This section is supplemented with the following new subsections: 16 17 1-07.5(5) U.S. Army Corps of Engineers 18 When temporary fills are permitted, the Contractor shall remove fills in their entirety and 19 the affected areas returned to pre-construction elevations. 20 21 If a U.S. Army Corps of Engineers permit is noted in Section 1-07.6 of the Special 22 Provisions, the Contractor shall retain a copy of the permit or the verification letter (in the 23 case of a Nationwide Permit) on the worksite for the life of the Contract. The Contractor 24 shall provide copies of the permit or verification letter to all subcontractors involved with 25 the authorized work prior to their commencement of any work in waters of the U.S. 26 27 1-07.5(6) U.S. Fish/Wildlife Services and National Marine Fisheries Service 28 The Contracting Agency will provide fish exclusion and handling services if the Work 29 dictates. However, if the Contractor discovers any fish stranded by the project and a 30 Contracting Agency biologist is not available, they shall immediately release the fish into 31 a flowing stream or open water. 32 33 1-07.5(1) General 34 The first sentence is deleted and replaced with the following: 35 36 No Work shall occur within areas under the jurisdiction of resource agencies unless 37 authorized in the Contract. 38 39 The third paragraph is deleted. 40 41 1-07.5(2) State Department of Fish and Wildlife 42 This section is revised to read: 43 44 In doing the Work, the Contractor shall: 45 46 1. Not degrade water in a way that would harm fish, wildlife, or their habitat. 47 48 2. Not place materials below or remove them from the ordinary high water line 49 except as may be specified in the Contract. 50

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 5 1 3. Not allow equipment to enter waters of the State except as specified in the 2 Contract. 3 4 4. Revegetate in accordance with the Plans, unless the Special Provisions permit 5 otherwise. 6 7 5. Prevent any fish-threatening silt buildup on the bed or bottom of any body of 8 water. 9 10 6. Ensure continuous stream flow downstream of the Work area. 11 12 7. Dispose of any project debris by removal, burning, or placement above high- 13 water flows. 14 15 8. Immediately notify the Engineer and stop all work causing impacts, if at any time, 16 as a result of project activities, fish are observed in distress or a fish kill occurs. 17 18 If the Work in (1) through (3) above differs little from what the Contract requires, the 19 Contracting Agency will measure and pay for it at unit Contract prices. But if Contract 20 items do not cover those areas, the Contracting Agency will pay pursuant to Section 1- 21 09.4. Work in (4) through (8) above shall be incidental to Contract pay items. 22 23 1-07.5(3) State Department of Ecology 24 This section is revised to read: 25 26 In doing the Work, the Contractor shall: 27 28 1. Comply with Washington State Water Quality Standards. 29 30 2. Perform Work in such a manner that all materials and substances not specifically 31 identified in the Contract documents to be placed in the water do not enter 32 waters of the State, including wetlands. These include, but are not limited to, 33 petroleum products, hydraulic fluid, fresh concrete, concrete wastewater, 34 process wastewater, slurry materials and waste from shaft drilling, sediments, 35 sediment-laden water, chemicals, paint, solvents, or other toxic or deleterious 36 materials. 37 38 3. Use equipment that is free of external petroleum-based products. 39 40 4. Remove accumulations of soil and debris from drive mechanisms (wheels, 41 tracks, tires) and undercarriage of equipment prior to using equipment below the 42 ordinary high water line. 43 44 5. Clean loose dirt and debris from all materials placed below the ordinary high 45 water line. No materials shall be placed below the ordinary high water line 46 without the Engineer’s concurrence. 47 48 6. When a violation of the Construction Stormwater General Permit (CSWGP) 49 occurs, immediately notify the Engineer and fill out WSDOT Form 422-011, 50 Contractor ECAP Report, and submit the form to the Engineer within 48 hours 51 of the violation. 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 6 1 7. Once Physical Completion has been given, prepare a Notice of Termination 2 (Ecology Form ECY 020-87) and submit the Notice of Termination electronically 3 to the Engineer in a PDF format a minimum of 7 calendar days prior to submitting 4 the Notice of Termination to Ecology. 5 6 8. Transfer the CSWGP coverage to the Contracting Agency when Physical 7 Completion has been given and the Engineer has determined that the project 8 site is not stabilized from erosion. 9 10 9. Submit copies of all correspondence with Ecology electronically to the Engineer 11 in a PDF format within four calendar days. 12 13 1-07.5(4) Air Quality 14 This section is revised to read: 15 16 The Contractor shall comply with all regional clean air authority and/or State Department 17 of Ecology rules and regulations. 18 19 The air quality permit process may include additional State Environment Policy Act 20 (SEPA) requirements. Contractors shall contact the appropriate regional air pollution 21 control authority well in advance of beginning Work. 22 23 When the Work includes or renovation of any existing facility or structure that 24 contains Asbestos Containing Material (ACM) and/or Presumed Asbestos-Containing 25 Material (PACM), the Contractor shall comply with the National Emission Standards for 26 Hazardous Air Pollutants (NESHAP). 27 28 Any requirements included in Federal and State regulations regarding air quality that 29 applies to the “owner or operator” shall be the responsibility of the Contractor. 30 31 1-07.7(1) General 32 The first sentence of the third paragraph is revised to read: 33 34 When the Contractor moves equipment or materials on or over Structures, culverts or 35 pipes, the Contractor may operate equipment with only the load-limit restrictions in 36 Section 1-07.7(2). 37 38 The first sentence of the last paragraph is revised to read: 39 40 Unit prices shall cover all costs for operating over Structures, culverts and pipes. 41 42 1-07.9(1) General 43 The last sentence of the sixth paragraph is revised to read: 44 45 Generally, the Contractor initiates the request by preparing standard form 1444 Request 46 for Authorization of Additional Classification and Rate, available at 47 https://www.dol.gov/whd/recovery/dbsurvey/conformance.htm, and submitting it to the 48 Engineer for further action. 49 50 1-07.9(2) Posting Notices 51 The second sentence of the first paragraph (up until the colon) is revised to read: 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 7 1 The Contractor shall ensure the most current edition of the following are posted: 2 3 In items 1 through 10, the revision dates are deleted. 4 5 1-07.11(2) Contractual Requirements 6 In this section, “creed” is revised to read “religion”. 7 8 Item numbers 1 through 9 are revised to read 2 through 10, respectively. 9 10 After the preceding Amendment is applied, the following new item number 1 is inserted: 11 12 1. The Contractor shall maintain a Work site that is free of harassment, humiliation, fear, 13 hostility and intimidation at all times. Behaviors that violate this requirement include 14 but are not limited to: 15 16 a. Persistent conduct that is offensive and unwelcome. 17 18 b. Conduct that is considered to be hazing. 19 20 c. Jokes about race, gender, or sexuality that are offensive. 21 22 d. Unwelcome, unwanted, rude or offensive conduct or advances of a sexual 23 nature which interferes with a person’s ability to perform their job or creates an 24 intimidating, hostile, or offensive work environment. 25 26 e. Language or conduct that is offensive, threatening, intimidating or hostile based 27 on race, gender, or sexual orientation. 28 29 f. Repeating rumors about individuals in the Work Site that are considered to be 30 harassing or harmful to the individual’s reputation. 31 32 1-07.11(5) Sanctions 33 This section is supplemented with the following: 34 35 Immediately upon the Engineer’s request, the Contractor shall remove from the Work site 36 any employee engaging in behaviors that promote harassment, humiliation, fear or 37 intimidation including but not limited to those described in these specifications. 38 39 1-07.11(6) Incorporation of Provisions 40 The first sentence is revised to read: 41 42 The Contractor shall include the provisions of Section 1-07.11(2) Contractual 43 Requirements (1) through (5) and the Section 1-07.11(5) Sanctions in every subcontract 44 including procurement of materials and leases of equipment. 45 46 1-07.15(1) Spill Prevention, Control, and Countermeasures Plan 47 The last sentence of the first paragraph is revised to read: 48 49 An SPCC Plan template and guidance information is available at 50 http://www.wsdot.wa.gov/environment/technical/disciplines/hazardous-materials/spill- 51 prevent-report. 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 8 1 1-07.18 Public Liability and Property Damage Insurance 2 Item number 1 is supplemented with the following new sentence: 3 4 This policy shall be kept in force from the execution date of the Contract until the Physical 5 Completion Date. 6 7 Section 1-08, Prosecution and Progress 8 June 1, 2017

9 1-08.1 Subcontracting 10 The sixth and seventh paragraphs are revised to read: 11 12 On all projects, the Contractor shall certify to the actual amounts paid to all firms that were 13 used as Subcontractors, lower tier subcontractors, manufacturers, regular dealers, or 14 service providers on the Contract. This includes all Disadvantaged, Minority, Small, 15 Veteran or Women’s Business Enterprise firms. This Certification shall be submitted to 16 the Engineer on a monthly basis each month between Execution of the Contract and 17 Physical Completion of the Contract using the application available at: 18 https://wsdot.diversitycompliance.com. A monthly report shall be submitted for every 19 month between Execution of the Contract and Physical Completion regardless of whether 20 payments were made or work occurred. 21 22 The Contractor shall comply with the requirements of RCW 39.04.250, 39.76.011, 23 39.76.020, and 39.76.040, in particular regarding prompt payment to Subcontractors. 24 Whenever the Contractor withholds payment to a Subcontractor for any reason including 25 disputed amounts, the Contractor shall provide notice within 10 calendar days to the 26 Subcontractor with a copy to the Contracting Agency identifying the reason for the 27 withholding and a clear description of what the Subcontractor must do to have the 28 withholding released. Retainage withheld by the Contractor prior to completion of the 29 Subcontractors work is exempt from reporting as a payment withheld and is not included 30 in the withheld amount. The Contracting Agency’s copy of the notice to Subcontractor for 31 deferred payments shall be submitted to the Engineer concurrently with notification to the 32 Subcontractor. 33 34 1-08.1(1) Prompt Payment, Subcontract Completion and Return of Retainage 35 Withheld 36 In item number 5 of the first paragraph, “WSDOT” is revised to read “Contracting Agency”. 37 38 The last sentence in item number 11 of the first paragraph is revised to read: 39 40 The Contractor may also require any documentation from the Subcontractor that is 41 required by the subcontract or by the Contract between the Contractor and Contracting 42 Agency or by law such as affidavits of wages paid, and material acceptance certifications 43 to the extent that they relate to the Subcontractor’s Work. 44 45 Item number 12 of the first paragraph is revised to read: 46 47 12. If the Contractor fails to comply with the requirements of the Specification and the 48 Subcontractor’s retainage or retainage bond is wrongfully withheld, the Contractor 49 will be subject to the actions described in No. 7 listed above. The Subcontractor may 50 also seek recovery against the Contractor under applicable prompt pay statutes in 51 addition to any other remedies provided for by the subcontract or by law.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 9 1 2 1-08.5 Time for Completion 3 In item 2c of the last paragraph, “Quarterly Reports” is revised to read “Monthly Reports”. 4 5 Section 1-09, Measurement and Payment 6 August 6, 2018

7 1-09.2(1) General Requirements for Weighing Equipment 8 The last paragraph is supplemented with the following: 9 10 When requested by the Engineer, the Contractor’s representative shall collect the tickets 11 throughout the day and provide them to the Engineer’s designated receiver, not later than 12 the end of shift, for reconciliation. Tickets for loads not verified as delivered will receive 13 no pay. 14 15 1-09.2(2) Specific Requirements for Batching Scales 16 The last sentence of the first paragraph is revised to read: 17 18 Batching scales used for concrete or hot mix asphalt shall not be used for batching 19 other materials. 20 21 1-09.10 Payment for Surplus Processed Materials 22 The following sentence is inserted after the first sentence of the second paragraph: 23 24 For Hot Mix Asphalt, the Plan quantity and quantity used will be adjusted for the quantity 25 of Asphalt and quantity of RAP or other materials incorporated into the mix. 26 27 Section 2-02, Removal of Structures and Obstructions 28 April 2, 2018

29 2-02.3(3) Removal of Pavement, Sidewalks, Curbs, and Gutters 30 In item number 3 of the first paragraph, the second sentence is revised to read: 31 32 For concrete pavement removal, a second vertical full depth relief saw cut offset 12 to 18 33 inches from and parallel to the initial saw cut is also required, unless the Engineer allows 34 otherwise. 35 36 Section 2-09, Structure Excavation 37 April 2, 2018

38 2-09.2 Materials 39 In the first paragraph, the references to “” and “Aggregates for Portland 40 Cement Concrete” are revised to read: 41 42 Cement 9-01 43 Fine Aggregate for Concrete 9-03.1(2) 44 45 2-09.3(3)D Shoring and Cofferdams 46 The first sentence of the sixth paragraph is revised to read: 47

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 10 1 Structural shoring and cofferdams shall be designed for conditions stated in this Section 2 using methods shown in Division I Section 5 of the AASHTO Standard Specifications for 3 Highway Bridges Seventeenth Edition – 2002 for allowable stress design, or the AASHTO 4 LRFD Bridge Design Specifications for load and resistance factor design. 5 6 Section 3-01, Production from Quarry and Pit Sites 7 April 2, 2018

8 3-01.1 Description 9 The first paragraph is revised to read: 10 11 This Work shall consist of manufacturing and producing crushed and screened 12 aggregates including pit run aggregates of the kind, quality, and grading specified for use 13 in the construction of concrete, hot mix asphalt, crushed surfacing, maintenance rock, 14 ballast, gravel base, gravel backfill, gravel borrow, riprap, and bituminous surface 15 treatments of all descriptions. 16 17 Section 4-04, Ballast and Crushed Surfacing 18 April 2, 2018

19 4-04.3(5) Shaping and Compaction 20 This section is supplemented with the following new paragraph: 21 22 When using 100% Recycled Concrete Aggregate, the Contractor may submit a written 23 request to use a test point evaluation for compaction acceptance testing in lieu of 24 compacting to 95% of the standard density as determined by the requirements of Section 25 2-03.3(14)D. The test point evaluation shall be performed in accordance with SOP 738. 26 27 Section 5-01, Cement Concrete Pavement Rehabilitation 28 January 3, 2017

29 In this section, “portland cement” is revised to read “cement”. 30 31 5-01.2 Materials 32 In the first paragraph, the following item is inserted after the item “Joint Sealants”: 33 34 Closed Cell Foam Backer Rod 9-04.2(3)A 35 36 5-01.3(1)A Concrete Mix Designs 37 This section, including title, is revised to read: 38 39 5-01.3(1)A Mix Designs 40 The Contractor shall use either concrete patching materials or cement concrete for the 41 rehabilitation of cement concrete pavement. Concrete patching materials shall be used 42 for spall repair and dowel bar retrofitting and cement concrete shall be used for concrete 43 panel replacement. 44 45 5-01.3(1)A1 Concrete Patching Materials 46 Item number 1 is revised to read: 47

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 11 1 1. Materials – The prepackaged concrete patching material and the aggregate 2 extender shall conform to Section 9-20. 3 4 5-01.3(1)A2 Portland Cement Concrete 5 This section, including title, is revised to read: 6 7 5-01.3(1)A2 Cement Concrete for Panel Replacement 8 Cement concrete for panel replacement shall meet the requirements of Sections 5-05.3(1) 9 and 5-05.3(2) and be air entrained with a design air content of 5.5 percent. Cement 10 concrete for panel replacement may use rapid hardening hydraulic cement meeting the 11 requirements of Section 9-01.2(2). Rapid hardening hydraulic cement will be considered 12 a cementitious material for the purpose of calculating the water/cementitious materials 13 ratio and the minimum cementitious materials requirement. 14 15 5-01.3(1)B Equipment 16 This section’s title is revised to read: 17 18 Equipment for Panel Replacement 19 20 5-01.3(2)B Portland Cement Concrete 21 This section’s title is revised to read: 22 23 Cement Concrete for Panel Replacement 24 25 This section is supplemented with the following new subsection: 26 27 5-01.3(2)B1 Conformance to Mix Design 28 Acceptance of cement concrete pavement for panel replacement shall be in accordance 29 with Section 5-01.3(2)B. The cement, coarse, and fine aggregate weights shall be within 30 the tolerances of the mix design in accordance with Section 5-05.3(1). 31 32 5-01.3(2)B1 Rejection of Concrete 33 This section is renumbered as follows: 34 35 5-01.3(2)B2 Rejection of Concrete 36 37 5-01.3(4) Replace Portland Cement Concrete Panel 38 This section’s title is revised to read: 39 40 Replace Cement Concrete Panel 41 42 5-01.3(8) Sealing Existing Transverse and Longitudinal Joints 43 This section’s title is revised to read: 44 45 Sealing Existing Longitudinal and Transverse Joint 46 47 The first paragraph is revised to read: 48 49 The Contractor shall clean and seal existing longitudinal and transverse joints where 50 shown in the Plans or as marked by the Engineer. 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 12 1 The first sentence of the second paragraph is revised to read: 2 3 Old sealant and incompressible material shall be completely removed from the joint to the 4 depth of the new reservoir with a diamond blade saw in accordance with the detail shown 5 in the Standard Plans. 6 7 The fifth paragraph is revised to read: 8 9 Immediately prior to sealing, the cracks shall be blown clean with dry oil-free compressed 10 air. If shown in the Plans, a backer rod shall be placed at the base of the sawn reservoir. 11 The joints shall be completely dry before the sealing installation may begin. Immediately 12 following the air blowing and backer rod placement, if required, the sealant material shall 13 be installed in conformance to manufacturer’s recommendations and in accordance 14 with Section 5-05.3(8)B. 15 16 5-01.3(9) Portland Cement Concrete Pavement Grinding 17 This section’s title is revised to read: 18 19 Cement Concrete Pavement Grinding 20 21 5-01.3(11) Concrete Slurry and Grinding Residue 22 The last sentence of the first paragraph is revised to read: 23 24 Slurry shall not be allowed to drain into an area open to traffic, off of the paved surface, 25 into any drainage structure, water of the state, or wetlands. 26 27 The following new sentence is inserted at the end of the second paragraph: 28 29 The Contractor shall submit copies of all disposal tickets to the Engineer within 5 calendar 30 days. 31 32 5-01.4 Measurement 33 The fourth paragraph is revised to read: 34 35 Sealing existing longitudinal and transverse joint will be measured by the linear foot, 36 measured along the line of the completed joint. 37 38 5-01.5 Payment 39 The Bid item “Sealing Transverse and Longitudinal Joints”, per linear foot and the paragraph 40 following Bid item are revised to read: 41 42 “Sealing Existing Longitudinal and Transverse Joint”, per linear foot. 43 44 The unit Contract price per linear foot for “Sealing Existing Longitudinal and Transverse 45 Joint”, shall be full payment for all costs to complete the Work as specified, including 46 removing incompressible material, preparing and sealing existing transverse and 47 longitudinal joints where existing transverse and longitudinal joints are cleaned and for all 48 incidentals required to complete the Work as specified. 49

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 13 1 Section 5-04, Hot Mix Asphalt 2 April 3, 2017

3 This section (and all subsections) is revised to read: 4 5 This Section 5-04 is written in a style which, unless otherwise indicated, shall be 6 interpreted as direction to the Contractor. 7 8 5-04.1 Description 9 This Work consists of providing and placing one or more layers of plant-mixed hot mix 10 asphalt (HMA) on a prepared foundation or base, in accordance with these Specifications 11 and the lines, grades, thicknesses, and typical cross-sections shown in the Plans. The 12 manufacture of HMA may include warm mix asphalt (WMA) processes in accordance with 13 these Specifications. 14 15 HMA shall be composed of asphalt binder and mineral materials as required, and may 16 include reclaimed asphalt pavement (RAP) or reclaimed asphalt shingles (RAS), mixed 17 in the proportions specified to provide a homogeneous, stable, and workable mix. 18 19 5-04.2 Materials 20 Provide materials as specified in these sections: 21 22 Asphalt Binder 9-02.1(4) 23 Cationic Emulsified Asphalt 9-02.1(6) 24 Anti-Stripping Additive 9-02.4 25 Warm Mix Asphalt Additive 9-02.5 26 Aggregates 9-03.8 27 Reclaimed Asphalt Pavement (RAP) 9-03.8(3)B 28 Reclaimed Asphalt Shingles (RAS) 9-03.8(3)B 29 Mineral Filler 9-03.8(5) 30 Recycled Material 9-03.21 31 Joint Sealants 9-04.2 32 Closed Cell Foam Backer Rod 9-04.2(3)A 33 34 5-04.2(1) How to Get an HMA Mix Design on the QPL 35 Comply with each of the following: 36 37 • Develop the mix design in accordance with WSDOT SOP 732. 38 39 • Develop a mix design that complies with Sections 9-03.8(2) and 9-03.8(6). 40 41 • Develop a mix design no more than 6 months prior to submitting it for QPL 42 evaluation. 43 44 • Submit mix designs to the WSDOT State Materials Laboratory in Tumwater, 45 including WSDOT Form 350-042. 46 47 • Include representative samples of the materials that are to be used in the 48 HMA production as part of the mix design submittal. 49 50 • Identify the brand, type, and percentage of anti-stripping additive in the mix 51 design submittal.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 14 1 2 • Include with the mix design submittal a certification from the asphalt binder 3 supplier that the anti-stripping additive is compatible with the crude source 4 and the formulation of asphalt binder proposed for use in the mix design. 5 6 • Do not include warm mix asphalt (WMA) additives when developing a mix 7 design or submitting a mix design for QPL evaluation. The use of warm mix 8 asphalt (WMA) additives is not part of the process for obtaining approval for 9 listing a mix design on the QPL. Refer to Section 5-04.2(2)B. 10 11 The Contracting Agency’s basis for approving, testing, and evaluating HMA mix 12 designs for approval on the QPL is dependent on the contractual basis for 13 acceptance of the HMA mixture, as shown in Table 1. 14 Table 1 Basis for Contracting Agency Evaluation of HMA Mix Designs for Approval on the QPL Contractual Basis Basis for Contracting Contracting Agency for Acceptance of Agency Approval of Materials Testing for HMA Mixture (see Mix Design for Evaluation of the Mix Section 5-04.3(9)) Placement on QPL Design The Contracting Agency will test the mix design WSDOT Standard Statistical Evaluation materials for compliance Practice QC-8 with Sections 9-03.8(2) and 9-03.8(6). The Contracting Agency may elect to test the mix Review of Form 350-042 design materials, or for compliance with Visual Evaluation evaluate in accordance Sections 9-03.8(2) and with WSDOT Standard 9-03.8(6) Practice QC-8, at its sole discretion. 15 16 If the Contracting Agency approves the mix design, it will be listed on the QPL for 12 17 consecutive months. The Contracting Agency may extend the 12 month listing 18 provided the Contractor submits a certification letter to the Qualified Products 19 Engineer verifying that the aggregate source and job mix formula (JMF) gradation, 20 and asphalt binder crude source and formulation have not changed. The Contractor 21 may submit the certification no sooner than three months prior to expiration of the 22 initial 12 month mix design approval. Within 7 calendar days of receipt of the 23 Contractor’s certification, the Contracting Agency will update the QPL. The maximum 24 duration for approval of a mix design and listing on the QPL will be 24 months from 25 the date of initial approval or as approved by the Engineer. 26 27 5-04.2(1)A Mix Designs Containing RAP and/or RAS 28 Mix designs are classified by the RAP and/or RAS content as shown in Table 2. 29 Table 2 Mix Design Classification Based on RAP/RAS Content RAP/RAS Classification RAP/RAS Content1

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 15 Low RAP/No RAS 0% ≤ RAP% ≤ 20% and RAS% = 0% High RAP/Any RAS 20% < RAP% ≤ Maximum Allowable RAP2 and/or 0% < RAS% ≤ Maximum Allowable RAS2 1Percentages in this table are by total weight of HMA 2See Table 4 to determine the limits on the maximum amount RAP and/or RAS. 1 2 5-04.2(1)A1 Low RAP/No RAS – Mix Design Submittals for Placement 3 on QPL 4 For Low RAP/No RAS mix designs, comply with the following additional 5 requirements: 6 7 1. Develop the mix design with or without the inclusion of RAP. 8 9 2. The asphalt binder grade shall be the grade indicated in the Bid 10 item name or as otherwise required by the Contract. 11 12 3. Submit samples of RAP if used in development of the mix design. 13 14 4. Testing RAP or RAS stockpiles is not required for obtaining 15 approval for placing these mix designs on the QPL. 16 17 5-04.2(1)A2 High RAP/Any RAS - Mix Design Submittals for 18 Placement on QPL 19 For High RAP/Any RAS mix designs, comply with the following additional 20 requirements: 21 22 1. For mix designs with any RAS, test the RAS stockpile (and RAP 23 stockpile if any RAP is in the mix design) in accordance with Table 24 3. 25 26 2. For High RAP mix designs with no RAS, test the RAP stockpile in 27 accordance with Table 3. 28 29 3. For mix designs with High RAP/Any RAS, construct a single 30 stockpile for RAP and a single stockpile for RAS and isolate 31 (sequester) these stockpiles from further stockpiling before 32 beginning development of the mix design. Test the RAP and RAS 33 during stockpile construction as required by item 1 and 2 above. 34 Use the test data in developing the mix design, and report the test 35 data to the Contracting Agency on WSDOT Form 350-042 as part 36 of the mix design submittal for approval on the QPL. Account for 37 the reduction in asphalt binder contributed from RAS in 38 accordance with AASHTO PP 78. Do not add to these stockpiles 39 after starting the mix design process. 40 Table 3

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 16 Test Frequency of RAP/RAS During RAP/RAS Stockpile Construction For Approving a High RAP/Any RAS Mix Design for Placement on the QPL Test Frequency1 Test for Test Method • 1/1000 tons of RAP (minimum Asphalt Binder FOP for AASHTO of 10 per mix Content and Sieve T 308 design) and Analysis of Fine and • 1/100 tons of and Coarse FOP for WAQTC T RAS (minimum Aggregate 27/T 11 of 10 per mix design) 1“tons”, in this table, refers to tons of the reclaimed material before being incorporated into HMA. 1 2 4. Limit the amount of RAP and/or RAS used in a High RAP/Any RAS 3 mix design by the amount of binder contributed by the RAP and/or 4 RAS, in accordance with Table 4. 5 Table 4 Maximum Amount of RAP and/or RAS in HMA Mixture Maximum Amount of Binder Contributed from: RAP RAS 40%1 minus contribution of 20%2 binder from RAS 1 Calculated as the weight of asphalt binder contributed from the RAP as a percentage of the total weight of asphalt binder in the mixture. 2 Calculated as the weight of asphalt binder contributed from the RAS as a percentage of the total weight of asphalt binder in the mixture. 6 7 5. Develop the mix design including RAP, RAS, recycling agent, and 8 new binder. 9 10 6. Extract, recover, and test the asphalt residue from the RAP and 11 RAS stockpiles to determine the percent of recycling agent and/or 12 grade of new asphalt binder needed to meet but not exceed the 13 performance grade (PG) of asphalt binder required by the 14 Contract. 15 16 a. Perform the asphalt extraction in accordance with AASHTO T 17 164 or ASTM D 2172 using reagent grade solvent. 18 19 b. Perform the asphalt recovery in accordance with AASHTO R 20 59 or ASTM D 1856. 21 22 c. Test the recovered asphalt residue in accordance with 23 AASHTO R 29 to determine the asphalt binder grade in 24 accordance with Section 9-02.1(4). 25

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 17 1 d. After determining the recovered asphalt binder grade, 2 determine the percent of recycling agent and/or grade of new 3 asphalt binder in accordance with ASTM D 4887. 4 5 e. Test the final blend of recycling agent, binder recovered from 6 the RAP and RAS, and new asphalt binder in accordance with 7 AASHTO R 29. The final blended binder shall meet but not 8 exceed the performance grade of asphalt binder required by 9 the Contract and comply with the requirements of Section 9- 10 02.1(4). 11 12 7. Include the following test data with the mix design submittal: 13 14 a. All test data from RAP and RAS stockpile construction. 15 16 b. All data from testing the recovered and blended asphalt 17 binder. 18 19 8. Include representative samples of the following with the mix 20 design submittal: 21 22 a. RAP and RAS. 23 24 b. 150 grams of recovered asphalt residue from the RAP and 25 RAS that are to be used in the HMA production. 26 27 5-04.2(1)B Commercial HMA - Mix Design Submittal for Placement on 28 QPL 29 For HMA used in the Bid item Commercial HMA, in addition to the requirements 30 of 5-04.2(1) identify the following in the submittal: 31 32 1. Commercial HMA 33 34 2. Class of HMA 35 36 3. Performance grade of binder 37 38 4. Equivalent Single Axle Load (ESAL) 39 40 The Contracting Agency may elect to approve Commercial HMA mix designs 41 without evaluation. 42 43 5-04.2(1)C Mix Design Resubmittal for QPL Approval 44 Develop a new mix design and resubmit for approval on the QPL when any of 45 the following changes occur. When these occur, discontinue using the mix 46 design until after it is reapproved on the QPL. 47 48 1. Change in the source of crude petroleum used in the asphalt binder. 49 50 2. Changes in the asphalt binder refining process. 51 52 3. Changes in additives or modifiers in the asphalt binder.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 18 1 2 4. Changes in the anti-strip additive, brand, type or quantity. 3 4 5. Changes to the source of material for aggregate. 5 6 6. Changes to the job mix formula that exceed the amounts as described 7 in item 2 of Section 9-03.8(7), unless otherwise approved by the 8 Engineer. 9 10 7. Changes in the percentage of material from a stockpile, when such 11 changes exceed 5% of the total aggregate weight. 12 13 a. For Low RAP/No RAS mix designs developed without RAP, 14 changes to the percentage of material from a stockpile will be 15 calculated based on the total aggregate weight not including the 16 weight of RAP. 17 18 b. For Low RAP/No RAS mix designs developed with RAP, changes 19 to the percentage of material from a stockpile will be calculated 20 based on the total aggregate weight including the weight of RAP. 21 22 c. For High RAP/Any RAS mix designs, changes in the percentage 23 of material from a stockpile will be based on total aggregate weight 24 including the weight of RAP (and/or RAS when included in the 25 mixture). 26 27 Prior to making any change in the amount of RAS in an approved mix design, 28 notify the Engineer for determination of whether a new mix design is required, 29 and obtain the Engineer’s approval prior to implementing such changes. 30 31 5-04.2(2) Mix Design – Obtaining Project Approval 32 Use only mix designs listed on the Qualified Products List (QPL). Submit WSDOT 33 Form 350-041 to the Engineer to request approval to use a mix design from the QPL. 34 Changes to the job mix formula (JMF) that have been approved on other contracts 35 may be included. The Engineer may reject a request to use a mix design if production 36 of HMA using that mix design on any contract is not in compliance with Section 5- 37 04.3(11)D, E, F, and G for mixture or compaction. 38 39 5-04.2(2)A Changes to the Job Mix Formula 40 The approved mix design obtained from the QPL will be considered the starting 41 job mix formula (JMF) and shall be used as the initial basis for acceptance of 42 HMA mixture, as detailed in Section 5-04.3(9). 43 44 During production the Contractor may request to adjust the JMF. Any 45 adjustments to the JMF will require approval of the Engineer and shall be made 46 in accordance with item 2 of Section 9-03.8(7). After approval by the Engineer, 47 such adjusted JMF’s shall constitute the basis for acceptance of the HMA 48 mixture. 49 50 5-04.2(2)B Using Warm Mix Asphalt Processes 51 The Contractor may, at the Contractor’s discretion, elect to use warm mix 52 asphalt (WMA) processes for producing HMA. WMA processes include organic

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 19 1 additives, chemical additives, and foaming. The use of WMA is subject to the 2 following: 3 4 • Do not use WMA processes in the production of High RAP/Any RAS 5 mixtures. 6 • Before using WMA processes, obtain the Engineer’s approval using 7 WSDOT Form 350-076 to describe the proposed WMA process. 8 9 5-04.3 Construction Requirements 10 5-04.3(1) Weather Limitations 11 Do not place HMA for wearing course on any Traveled Way beginning October 1st 12 through March 31st of the following year, without written concurrence from the 13 Engineer. 14 15 Do not place HMA on any wet surface, or when the average surface temperatures 16 are less than those specified in Table 5, or when weather conditions otherwise 17 prevent the proper handling or finishing of the HMA. 18 Table 5 Minimum Surface Temperature for Paving Compacted Wearing Course Other Courses Thickness (Feet) Less than 0.10 55°F 45°F 0.10 to 0.20 45°F 35°F More than 0.20 35°F 35°F 19 20 5-04.3(2) Paving Under Traffic 21 These requirements apply when the Roadway being paved is open to traffic. 22 23 In hot weather, the Engineer may require the application of water to the pavement to 24 accelerate the finish rolling of the pavement and to shorten the time required before 25 reopening to traffic. 26 27 During paving operations, maintain temporary pavement markings throughout the 28 project. Install temporary pavement markings on the Roadway prior to opening to 29 traffic. Temporary pavement markings shall comply with Section 8-23. 30 31 5-04.3(3) Equipment 32 5-04.3(3)A Mixing Plant 33 Equip mixing plants as follows. 34 35 1. Use tanks for storage and preparation of asphalt binder which: 36 37 • Heat the contents by means that do not allow flame to contact the 38 contents or the tank, such as by steam or electricity. 39 40 • Heat and hold contents at the required temperatures. 41 42 • Continuously circulate contents to provide uniform temperature 43 and consistency during the operating period. 44

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 20 1 • Provide an asphalt binder sampling valve, in either the storage 2 tank or the supply line to the mixer. 3 4 2. Provide thermometric equipment: 5 6 • In the asphalt binder feed line near the charging valve at the mixer 7 unit, capable of detecting temperature ranges expected in the 8 HMA and in a location convenient and safe for access by 9 Inspectors. 10 11 • At the discharge chute of the drier to automatically register or 12 indicate the temperature of the heated aggregates, and situated in 13 full view of the plant operator. 14 15 3. When heating asphalt binder: 16 17 • Do not exceed the maximum temperature of the asphalt binder 18 recommended by the asphalt binder supplier. 19 20 • Avoid local variations in heating. 21 22 • Provide a continuous supply of asphalt binder to the mixer at a 23 uniform average temperature with no individual variations 24 exceeding 25°F. 25 26 4. Provide a mechanical sampler for sampling mineral materials 27 that: 28 29 • Meets the crushing or screening requirements of Section 1-05.6. 30 31 5. Provide HMA sampling equipment that complies with WSDOT 32 T168. 33 34 • Use a mechanical sampling device installed between the 35 discharge of the silo and the truck transport, approved by the 36 Engineer, or 37 38 • Platforms or devices to enable sampling from the truck transport 39 without entering the truck transport for sampling HMA. 40 41 6. Provide for setup and operation of the Contracting Agency’s field 42 testing: 43 44 • As required in Section 3-01.2(2). 45 46 7. Provide screens or a lump breaker: 47 48 • When using any RAP or any RAS, to eliminate oversize RAP or 49 RAS particles from entering the pug mill or drum mixer. 50

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 21 1 5-04.3(3)B Hauling Equipment 2 Provide HMA hauling equipment with tight, clean, smooth metal beds and a 3 cover of canvas or other suitable material of sufficient size to protect the HMA 4 from adverse weather. Securely attach the cover to protect the HMA whenever 5 the weather conditions during the work shift include, or are forecast to include, 6 precipitation or an air temperature less than 45°F. 7 8 Prevent HMA from adhering to the hauling equipment. Spray metal beds with an 9 environmentally benign release agent. Drain excess release agent prior to filling 10 hauling equipment with HMA. Do not use petroleum derivatives or other coating 11 material that contaminate or alter the characteristics of the HMA. For hopper 12 trucks, operate the conveyer during the process of applying the release agent. 13 14 5-04.3(3)C Pavers 15 Use self-contained, power-propelled pavers provided with an internally heated 16 vibratory that is capable of spreading and finishing courses of HMA in 17 lane widths required by the paving section shown in the Plans. 18 19 When requested by the Engineer, provide written certification that the paver is 20 equipped with the most current equipment available from the manufacturer for 21 the prevention of segregation of the coarse aggregate particles. The certification 22 shall list the make, model, and year of the paver and any equipment that has 23 been retrofitted to the paver. 24 25 Operate the screed in accordance with the manufacturer’s recommendations 26 and in a manner to produce a finished surface of the required evenness and 27 texture without tearing, shoving, segregating, or gouging the mixture. Provide 28 a copy of the manufacturer’s recommendations upon request by the Contracting 29 Agency. Extensions to the screed will be allowed provided they produce the 30 same results, including ride, density, and surface texture as obtained by the 31 primary screed. In the Travelled Way do not use extensions without both augers 32 and an internally heated vibratory screed. 33 34 Equip the paver with automatic screed controls and sensors for either or both 35 sides of the paver. The controls shall be capable of sensing grade from an 36 outside reference line, sensing the transverse slope of the screed, and providing 37 automatic signals that operate the screed to maintain the desired grade and 38 transverse slope. Construct the sensor so it will operate from a reference line or 39 a mat referencing device. The transverse slope controller shall be capable of 40 maintaining the screed at the desired slope within plus or minus 0.1 percent. 41 42 Equip the paver with automatic feeder controls, properly adjusted to maintain a 43 uniform depth of material ahead of the screed. 44 45 Manual operation of the screed is permitted in the construction of irregularly 46 shaped and minor areas. These areas include, but are not limited to, gore areas, 47 road approaches, tapers and left-turn channelizations. 48 49 When specified in the Contract, provide reference lines for vertical control. Place 50 reference lines on both outer edges of the Traveled Way of each Roadway. 51 Horizontal control utilizing the reference line is permitted. Automatically control 52 the grade and slope of intermediate lanes by means of reference lines or a mat

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 22 1 referencing device and a slope control device. When the finish of the grade 2 prepared for paving is superior to the established tolerances and when, in the 3 opinion of the Engineer, further improvement to the line, grade, cross-section, 4 and smoothness can best be achieved without the use of the reference line, a 5 mat referencing device may be substituted for the reference line. Substitution of 6 the device will be subject to the continued approval of the Engineer. A joint 7 matcher may be used subject to the approval of the Engineer. The reference line 8 may be removed after completion of the first course of HMA when approved by 9 the Engineer. Whenever the Engineer determines that any of these methods are 10 failing to provide the necessary vertical control, the reference lines will be 11 reinstalled by the Contractor. 12 13 Furnish and install all pins, brackets, tensioning devices, wire, and accessories 14 necessary for satisfactory operation of the automatic control equipment. 15 16 If the paving machine in use is not providing the required finish, the Engineer 17 may suspend Work as allowed by Section 1-08.6. 18 19 5-04.3(3)D Material Transfer Device or Material Transfer Vehicle 20 Use a material transfer device (MTD) or material transfer vehicle (MTV) to 21 deliver the HMA from the hauling equipment to the paving machine for any lift in 22 (or partially in) the top 0.30 feet of the pavement section used in traffic lanes. 23 However, an MTD/V is not required for HMA placed in irregularly shaped and 24 minor areas such as tapers and turn lanes, or for HMA mixture that is accepted 25 by Visual Evaluation. At the Contractor’s request the Engineer may approve 26 paving without an MTD/V; the Engineer will determine if an equitable adjustment 27 in cost or time is due. If a windrow elevator is used, the Engineer may limit the 28 length of the windrow in urban areas or through intersections. 29 30 To be approved for use, an MTV: 31 32 1. Shall be a self-propelled vehicle, separate from the hauling vehicle or 33 paver. 34 35 2. Shall not connected to the hauling vehicle or paver. 36 37 3. May accept HMA directly from the haul vehicle or pick up HMA from a 38 windrow. 39 40 4. Shall mix the HMA after delivery by the hauling equipment and prior to 41 placement into the paving machine. 42 43 5. Shall mix the HMA sufficiently to obtain a uniform temperature 44 throughout the mixture. 45 46 To be approved for use, an MTD: 47 48 1. Shall be positively connected to the paver. 49 50 2. May accept HMA directly from the haul vehicle or pick up HMA from a 51 windrow. 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 23 1 3. Shall mix the HMA after delivery by the hauling equipment and prior to 2 placement into the paving machine. 3 4 4. Shall mix the HMA sufficiently to obtain a uniform temperature 5 throughout the mixture. 6 7 5-04.3(3)E Rollers 8 Operate rollers in accordance with the manufacturer’s recommendations. When 9 requested by the Engineer, provide a Type 1 Working Drawing of the 10 manufacturer’s recommendation for the use of any roller planned for use on the 11 project. Do not use rollers that crush aggregate, produce pickup or washboard, 12 unevenly compact the surface, displace the mix, or produce other undesirable 13 results. 14 15 5-04.3(4) Preparation of Existing Paved Surfaces 16 Before constructing HMA on an existing paved surface, the entire surface of the 17 pavement shall be clean. Entirely remove all fatty asphalt patches, grease drippings, 18 and other deleterious substances from the existing pavement to the satisfaction of 19 the Engineer. Thoroughly clean all pavements or bituminous surfaces of dust, soil, 20 pavement grindings, and other foreign matter. Thoroughly remove any cleaning or 21 solvent type liquids used to clean equipment spilled on the pavement before paving 22 proceeds. Fill all holes and small depressions with an appropriate class of HMA. 23 Level and thoroughly compact the surface of the patched area. 24 25 Apply a uniform coat of asphalt (tack coat) to all paved surfaces on which any course 26 of HMA is to be placed or abutted. Apply tack coat to cover the cleaned existing 27 pavement with a thin film of residual asphalt free of streaks and bare spots. Apply a 28 heavy application of tack coat to all joints. For Roadways open to traffic, limit the 29 application of tack coat to surfaces that will be paved during the same working shift. 30 Equip the spreading equipment with a thermometer to indicate the temperature of 31 the tack coat material. 32 33 Do not operate equipment on tacked surfaces until the tack has broken and cured. 34 Repair tack coat damaged by the Contractor’s operation, prior to placement of the 35 HMA. 36 37 Unless otherwise approved by the Engineer, use cationic emulsified asphalt CSS-1, 38 CSS-1h, STE-1, or Performance Graded (PG) asphalt for tack coat. The CSS-1 and 39 CSS-1h may be diluted with water at a rate not to exceed one part water to one part 40 emulsified asphalt. Do not allow the tack coat material to exceed the maximum 41 temperature recommended by the asphalt supplier. 42 43 When shown in the Plans, prelevel uneven or broken surfaces over which HMA is to 44 be placed by using an asphalt paver, a motor patrol grader, or by hand raking, as 45 approved by the Engineer. 46 47 5-04.3(4)A Crack Sealing 48 5-04.3(4)A1 General 49 When the Proposal includes a pay item for crack sealing, seal all cracks ¼ 50 inch in width and greater. 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 24 1 Cleaning: Ensure that cracks are thoroughly clean, dry and free of all loose 2 and foreign material when filling with crack sealant material. Use a hot 3 compressed air lance to dry and warm the pavement surfaces within the 4 crack immediately prior to filling a crack with the sealant material. Do not 5 overheat pavement. Do not use direct flame dryers. Routing cracks is not 6 required. 7 8 Sand Slurry: For cracks that are to be filled with sand slurry, thoroughly mix 9 the components and pour the mixture into the cracks until full. Add additional 10 CSS-1 cationic emulsified asphalt to the sand slurry as needed for 11 workability to ensure the mixture will completely fill the crack. Strike off the 12 sand slurry flush with the existing pavement surface and allow the mixture 13 to cure. Top off cracks that were not completely filled with additional sand 14 slurry. Do not place the HMA overlay until the slurry has fully cured. 15 16 Hot Poured Sealant: For cracks that are to be filled with hot poured 17 sealant, apply the material in accordance with these requirements and the 18 manufacturer's recommendations. Furnish a Type 1 Working Drawing of the 19 manufacturer's product information and recommendations to the Engineer 20 prior to the start of work, including the manufacturer’s recommended 21 heating time and temperatures, allowable storage time and temperatures 22 after initial heating, allowable reheating criteria, and application temperature 23 range. Confine hot poured sealant material within the crack. Clean any 24 overflow of sealant from the pavement surface. If, in the opinion of the 25 Engineer, the Contractor’s method of sealing the cracks with hot poured 26 sealant results in an excessive amount of material on the pavement surface, 27 stop and correct the operation to eliminate the excess material. 28 29 5-04.3(4)A2 Crack Sealing Areas Prior to Paving 30 In areas where HMA will be placed, use sand slurry to fill the cracks. 31 32 5-04.3(4)A3 Crack Sealing Areas Not to be Paved 33 In areas where HMA will not be placed, fill the cracks as follows: 34 35 1. Cracks ¼ inch to 1 inch in width - fill with hot poured sealant. 36 37 2. Cracks greater than 1 inch in width – fill with sand slurry. 38 39 5-04.3(4)B Soil Residual Herbicide 40 Where shown in the Plans, apply one application of an approved soil residual 41 herbicide. Comply with Section 8-02.3(3)B. Complete paving within 48 hours of 42 applying the herbicide. 43 44 Use herbicide registered with the Washington State Department of Agriculture 45 for use under pavement. Before use, obtain the Engineer’s approval of the 46 herbicide and the proposed rate of application. Include the following information 47 in the request for approval of the material: 48 49 1. Brand Name of the Material, 50 51 2. Manufacturer, 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 25 1 3. Environmental Protection Agency (EPA) Registration Number, 2 3 4. Material Safety Data Sheet, and 4 5 5. Proposed Rate of Application. 6 7 5-04.3(4)C Pavement Repair 8 Excavate pavement repair areas and backfill these with HMA in accordance with 9 the details shown in the Plans and as staked. Conduct the excavation 10 operations in a manner that will protect the pavement that is to remain. Repair 11 pavement not designated to be removed that is damaged as a result of the 12 Contractor’s operations to the satisfaction of the Engineer at no cost to the 13 Contracting Agency. Excavate only within one lane at a time unless approved 14 otherwise by the Engineer. Do not excavate more area than can be completely 15 backfilled and compacted during the same shift. 16 17 Unless otherwise shown in the Plans or determined by the Engineer, excavate 18 to a depth of 1.0 feet. The Engineer will make the final determination of the 19 excavation depth required. 20 21 The minimum width of any pavement repair area shall be 40 inches unless 22 shown otherwise in the Plans. Before any excavation, sawcut the perimeter of 23 the pavement area to be removed unless the pavement in the pavement repair 24 area is to be removed by a pavement grinder. 25 26 Excavated materials shall be the property of the Contractor and shall be 27 disposed of in a Contractor-provided site off the Right of Way or used in 28 accordance with Sections 2-02.3(3) or 9-03.21. 29 30 Apply a heavy application of tack coat to all surfaces of existing pavement in the 31 pavement repair area, in accordance with Section 5-04.3(4). 32 33 Place the HMA backfill in lifts not to exceed 0.35-foot compacted depth. 34 Thoroughly compact each lift by a mechanical tamper or a roller. 35 36 5-04.3(5) Producing/Stockpiling Aggregates, RAP, & RAS 37 Produce aggregate in compliance with Section 3-01. Comply with Section 3-02 38 for preparing stockpile sites, stockpiling, and removing from stockpile each of 39 the following: aggregates, RAP, and RAS. Provide sufficient storage space for 40 each size of aggregate, RAP and RAS. Fine aggregate or RAP may be uniformly 41 blended with the RAS as a method of preventing the agglomeration of RAS 42 particles. Remove the aggregates, RAP and RAS from stockpile(s) in a manner 43 that ensures minimal segregation when being moved to the HMA plant for 44 processing into the final mixture. Keep different aggregate sizes separated until 45 they have been delivered to the HMA plant. 46 47 5-04.3(5)A Stockpiling RAP or RAS for High RAP/Any RAS Mixes 48 Do not place any RAP or RAS into a stockpile which has been sequestered 49 for a High RAP/Any RAS mix design. Do not incorporate any RAP or RAS 50 into a High RAP/Any RAS mixture from any source other than the stockpile 51 which was sequestered for approval of that particular High RAP/Any RAS 52 mix design.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 26 1 2 RAP that is used in a Low RAP/No RAS mix is not required to come from a 3 sequestered stockpile. 4 5 5-04.3(6) Mixing 6 The asphalt supplier shall introduce anti-stripping additive, in the amount 7 designated on the QPL for the mix design, into the asphalt binder prior to 8 shipment to the asphalt mixing plant. 9 10 Anti-strip is not required for temporary work that will be removed prior to Physical 11 Completion. 12 13 Use asphalt binder of the grade, and from the supplier, in the approved mix 14 design. 15 16 Prior to introducing reclaimed materials into the asphalt plant, remove wire, 17 nails, and other foreign material. Discontinue use of the reclaimed material if the 18 Engineer, in their sole discretion, determines the wire, nails, or other foreign 19 material to be excessive. 20 21 Size RAP and RAS prior to entering the mixer to provide uniform and thoroughly 22 mixed HMA. If there is evidence of the RAP or RAS not breaking down during 23 the heating and mixing of the HMA, immediately suspend the use of the RAP or 24 RAS until changes have been approved by the Engineer. 25 26 After the required amount of mineral materials, RAP, RAS, new asphalt binder 27 and recycling agent have been introduced into the mixer, mix the HMA until 28 complete and uniform coating of the particles and thorough distribution of the 29 asphalt binder throughout the mineral materials, RAP and RAS is ensured. 30 31 Upon discharge from the mixer, ensure that the temperature of the HMA does 32 not exceed the optimum mixing temperature shown on the approved Mix Design 33 Report by more than 25°F, or as approved by the Engineer. When a WMA 34 additive is included in the manufacture of HMA, do not heat the WMA additive 35 (at any stage of production including in binder storage tanks) to a temperature 36 higher than the maximum recommended by the manufacturer of the WMA 37 additive. 38 39 A maximum water content of 2 percent in the mix, at discharge, will be allowed 40 providing the water causes no problems with handling, stripping, or flushing. If 41 the water in the HMA causes any of these problems, reduce the moisture 42 content. 43 44 During the daily operation, HMA may be temporarily held in approved storage 45 facilities. Do not incorporate HMA into the Work that has been held for more than 46 24 hours after mixing. Provide an easily readable, low bin-level indicator on the 47 storage facility that indicates the amount of material in storage. Waste the HMA 48 in storage when the top level of HMA drops below the top of the cone of the 49 storage facility, except as the storage facility is being emptied at the end of the 50 working shift. Dispose of rejected or waste HMA at no expense to the 51 Contracting Agency. 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 27 1 5-04.3(7) Spreading and Finishing 2 Do not exceed the maximum nominal compacted depth of any layer in any 3 course, as shown in Table 6, unless approved by the Engineer: 4 Table 6 Maximum Nominal Compacted Depth of Any Layer Other than Wearing HMA Class Wearing Course Course 1 inch 0.35 feet 0.35 feet ¾ and ½ inch 0.30 feet 0.35 feet 3 ⁄8 inch 0.15 feet 0.15 feet 5 6 Use HMA pavers complying with Section 5-04.3(3) to distribute the mix. On 7 areas where irregularities or unavoidable obstacles make the use of mechanical 8 spreading and finishing equipment impractical, the paving may be done with 9 other equipment or by hand. 10 11 When more than one JMF is being utilized to produce HMA, place the material 12 produced for each JMF with separate spreading and compacting equipment. Do 13 not intermingle HMA produced from more than one JMF. Each strip of HMA 14 placed during a work shift shall conform to a single JMF established for the class 15 of HMA specified unless there is a need to make an adjustment in the JMF. 16 17 5-04.3(8) Aggregate Acceptance Prior to Incorporation in HMA 18 Sample aggregate for meeting the requirements of Section 3-04 prior to being 19 incorporated into HMA. (The acceptance data generated for the Section 3-04 20 acceptance analysis will not be commingled with the acceptance data generated 21 for the Section 5-04.3(9) acceptance analysis.) Aggregate acceptance samples 22 shall be taken as described in Section 3-04. Aggregate acceptance testing will 23 be performed by the Contracting Agency. Aggregate contributed from RAP 24 and/or RAS will not be evaluated under Section 3-04. 25 26 For aggregate that will be used in HMA mixture which will be accepted by 27 Statistical Evaluation, the Contracting Agency’s acceptance of the aggregate 28 will be based on: 29 30 1. Samples taken prior to mixing with asphalt binder, RAP, or RAS; 31 32 2. Testing for the materials properties of fracture, uncompacted void 33 content, and sand equivalent; 34 35 3. Evaluation by the Contracting Agency in accordance with Section 3-04, 36 including price adjustments as described therein. 37 38 For aggregate that will be used in HMA which will be accepted by Visual 39 Evaluation, evaluation in accordance with items 1, 2, and 3 above is at the 40 discretion of the Engineer. 41 42 5-04.3(9) HMA Mixture Acceptance 43 The Contracting Agency will evaluate HMA mixture for acceptance by one of two 44 methods as determined from the criteria in Table 7. 45

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 28 Table 7 Basis of Acceptance for HMA Mixture Visual Evaluation Statistical Evaluation • Commercial HMA • All HMA mixture placed at any other than that location accepted by Visual • Any HMA placed in: Evaluation o sidewalks o road approaches ditches Criteria o slopes for o paths Selecting o trails the o gores Evaluation o prelevel Method o o temporary pavement1 o pavement repair • Other nonstructural applications of HMA as approved by the Engineer 1 Temporary pavement is HMA that will be removed before Physical Completion of the Contract. 1 2 5-04.3(9)A Test Sections 3 This Section applies to HMA mixture accepted by Statistical Evaluation. A 4 test section is not allowed for HMA accepted by Visual Evaluation. 5 6 The purpose of a test section is to determine whether or not the Contractor’s 7 mix design and production processes will produce HMA meeting the 8 Contract requirements related to mixture. Construct HMA mixture test 9 sections at the beginning of paving, using at least 600 tons and a maximum 10 of 1,000 tons or as specified by the Engineer. Each test section shall be 11 constructed in one continuous operation. 12 13 5-04.3(9)A1 Test Section – When Required, When to Stop 14 Use Tables 8 and 9 to determine when a test section is required, 15 optional, or not allowed, and to determine when performing test 16 sections may end. Each mix design will be evaluated independently for 17 the test section requirements. If more than one test section is required, 18 each test section shall be evaluated separately by the criteria in table 19 8 and 9. 20 Table 8 Criteria for Conducting and Evaluating HMA Mixture Test Sections (For HMA Mixture Accepted by Statistical Evaluation) Low RAP/No High RAP/Any RAS RAS

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 29 Is Mixture Test At Contractor’s Section Optional or Mandatory1 Option Mandatory? Waiting period after paving the test 4 calendar days2 4 calendar days2 section. Meet “Results Provide samples Required to Stop and respond to What Must Happen Performing Test WSDOT test to Stop Performing Sections” in Table 9 results required by Test Sections? for High RAP/Any Table 9 for Low RAS. RAP/No RAS. 1If a mix design has produced an acceptable test section on a previous contract (paved in the same calendar year, from the same plant, using the same JMF) the test section may be waived if approved by the Engineer. 2This is to provide time needed by the Contracting Agency to complete testing and the Contractor to adjust the mixture in response to those test results. Paving may resume when this is done.

1 Table 9 Results Required to Stop Performing HMA Mixture Test Sections1 (For HMA Mixture Accepted by Statistical Evaluation) Type of HMA Test Property Low RAP/No High RAP/Any RAS RAS Minimum PFi of 0.95 based on the criteria Gradation None4 in Section 5- 04.3(9)B42 Minimum PFi of 0.95 based on the criteria Asphalt Binder None4 in Section 5- 04.3(9)B42 Minimum PFi of 0.95 based on the criteria 4 Va None in Section 5- 04.3(9)B42 Hamburg Wheel These tests will Meet requirements Track not be done as of Section 9- Indirect Tensile part of Test 03.8(2).3 Strength Section. Nonstatistical Aggregates Evaluation in Sand Equivalent accordance with the Uncompacted Void None3 requirements of Content Section 3-043 Fracture

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 30 1In addition to the requirements of this table, acceptance of the HMA mixture used in each test section is subject to the acceptance criteria and price adjustments for Statistical Evaluation (see Table 9a). 2Divide the test section lot into three sublots, approximately equal in size. Take one sample from each sublot, and test each sample for the property in the first column. 3Take one sample for each test section lot. Test the sample for the properties in the first column. 4Divide the test section lot into three sublots, approximately equal in size. Take one sample from each sublot, and test each sample for the property in the first column. There are no criteria for discontinuing test sections for these mixes; however, the contractor must comply with Section 5-04.3(11)F before resuming paving. 1 2 5-04.3(9)A2 Test Section – Evaluating the HMA Mixture in a Test 3 Section 4 The Engineer will evaluate the HMA mixture in each test section for 5 rejection, acceptance, and price adjustments based on the criteria in 6 Table 9a using the data generated from the testing required by Table 9. 7 Each test section shall be considered a separate lot. 8 Table 9a Acceptance Criteria for HMA Mixture Placed in a Test Section (For HMA Mixture Accepted by Statistical Evaluation) Type of HMA Test Property Low RAP/No High RAP/Any RAS RAS Gradation Statistical Asphalt Binder Statistical Evaluation Evaluation Va Hamburg Wheel Pass/Fail for the Track requirements of N/A Indirect Tensile Section 9-03.8(2)1 Strength Nonstatistical Nonstatistical HMA Aggregate Evaluation in Evaluation in Sand Equivalent accordance with the accordance with Uncompacted Void requirements of the requirements Content Section 3-04 of Section 3-04 1Failure to meet the specifications for Hamburg and/or IDT will cause the mixture in the test section to be rejected. Refer to Section 5-04.3(11). 9 10 5-04.3(9)B Mixture Acceptance – Statistical Evaluation 11 5-04.3(9)B1 Mixture Statistical Evaluation – Lots and Sublots 12 HMA mixture which is accepted by Statistical Evaluation will be 13 evaluated by the Contracting Agency dividing that HMA tonnage into 14 mixture lots, and each mixture lot will be evaluated using stratified 15 random sampling by the Contracting Agency sub-dividing each mixture

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 31 1 lot into mixture sublots. All mixture in a mixture lot shall be of the same 2 mix design. The mixture sublots will be numbered in the order in which 3 the mixture (of a particular mix design) is paved. 4 5 Each mixture lot comprises a maximum of 15 mixture sublots, except: 6 7 • The final mixture lot of each mix design on the Contract will 8 comprise a maximum of 25 sublots. 9 • A mixture lot for a test section will consist of three sublots. 10 11 Each mixture sublot shall be approximately uniform in size with the 12 maximum mixture sublot size as specified in Table 10. The quantity of 13 material represented by the final mixture sublot of the project, for each 14 mix design on the project, may be increased to a maximum of two times 15 the mixture sublot quantity calculated. 16 Table 10 Maximum HMA Mixture Sublot Size For HMA Accepted by Statistical Evaluation HMA Original Plan Quantity Maximum Sublot Size (tons)2 (tons)1 < 20,000 1,000 20,000 to 30,000 1,500 >30,000 2,000 1 “Plan quantity” means the plan quantity of all HMA of the same class and binder grade which is accepted by Statistical Evaluation. 2 The maximum sublot size for each combination of HMA class and binder grade shall be calculated separately. 17 18 • For a mixture lot in progress with a mixture CPF less than 19 0.75, a new mixture lot will begin at the Contractor’s request 20 after the Engineer is satisfied that material conforming to the 21 Specifications can be produced. See also Section 5- 22 04.3(11)F. 23 24 • If, before completing a mixture lot, the Contractor requests a 25 change to the JMF which is approved by the Engineer, the 26 mixture produced in that lot after the approved change will be 27 evaluated on the basis of the changed JMF, and the mixture 28 produced in that lot before the approved change will be 29 evaluated on the basis of the unchanged JMF; however, the 30 mixture before and after the change will be evaluated in the 31 same lot. Acceptance of subsequent mixture lots will be 32 evaluated on the basis of the changed JMF. 33 34 5-04.3(9)B2 Mixture Statistical Evaluation – Sampling 35 Comply with Section 1-06.2(1). 36 37 Samples of HMA mixture which is accepted by Statistical Evaluation 38 will be randomly selected from within each sublot, with one sample per 39 sublot. The Engineer will determine the random sample location using

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 32 1 WSDOT Test Method T 716. The Contractor shall obtain the sample 2 when ordered by the Engineer. The Contractor shall sample the HMA 3 mixture in the presence of the Engineer and in accordance with FOP 4 for WAQTC T 168. 5 6 5-04.3(9)B3 Mixture Statistical Evaluation – Acceptance Testing 7 Comply with Section 1-06.2(1). 8 9 The Contracting Agency will test the mixture sample from each sublot 10 (including sublots in a test section) for the properties shown in Table 11 11. 12 Table 11 Testing Required for each HMA Mixture Sublot Test Procedure Performed by Va WSDOT SOP Engineer 731 Asphalt Binder Content FOP for Engineer AASHTO T 308 Gradation: Percent Passing FOP for Engineer 1½″, 1″, ¾″, ½″, ⅜″, No. 4, WAQTC No. 8, No. 200 T 27/T 11 13 14 The mixture samples and tests taken for the purpose of determining 15 acceptance of the test section (as described in Section 5-04.3(9)A) 16 shall also be used as the test results for acceptance of the mixture 17 described in 5-04.3(9)B3, 5-04.3(9)B4, 5-04.3(9)B5, and 5-04.3(9)B6. 18 19 5-04.3(9)B4 Mixture Statistical Evaluation – Pay Factors 20 Comply with Section 1-06.2(2). 21 22 The Contracting Agency will determine a pay factor (PFi) for each of 23 the properties in Table 11, for each mixture lot, using the quality level 24 analysis in Section 1-06.2(2)D. For Gradation, a pay factor will be 25 calculated for each of the sieve sizes listed in Table 11 which is equal 26 to or smaller than the maximum allowable aggregate size (100 percent 27 passing sieve) of the HMA mixture. The USL and LSL shall be 28 calculated using the Job Mix Formula Tolerances (for Statistical 29 Evaluation) in Section 9-03.8(7). 30 31 If a constituent is not measured in accordance with these 32 Specifications, its individual pay factor will be considered 1.00 in 33 calculating the Composite Pay Factor (CPF). 34 35 5-04.3(9)B5 Mixture Statistical Evaluation – Composite Pay 36 Factors (CPF) 37 Comply with Section 1-06.2(2). 38 39 In accordance with Section 1-06.2(2)D4, the Contracting Agency will 40 determine a Composite Pay Factor (CPF) for each mixture lot from the 41 pay factors calculated in Section 5-04.3(9)B4, using the price

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 33 1 adjustment factors in Table 12. Unless otherwise specified, the 2 maximum CPF for HMA mixture shall be 1.05. 3 Table 12 HMA Mixture Price Adjustment Factors Constituent Factor “f” All aggregate passing: 1½″, 1″, ¾″, ½″, 2 ⅜″ and No.4 sieves All aggregate passing No. 8 sieve 15 All aggregate passing No. 200 sieve 20 Asphalt binder 40 Air Voids (Va) 20 4 5 5-04.3(9)B6 Mixture Statistical Evaluation – Price Adjustments 6 For each HMA mixture lot, a Job Mix Compliance Price Adjustment will 7 be determined and applied, as follows: 8 9 JMCPA = [0.60 x (CPF – 1.00)] x Q x UP 10 11 Where 12 13 JMCPA = Job Mix Compliance Price Adjustment for a given lot of 14 mixture ($) 15 CPF = Composite Pay factor for a given lot of mixture 16 (maximum is 1.05) 17 Q = Quantity in a given lot of mixture (tons) 18 UP = Unit price of the HMA in a given lot of mixture ($/ton) 19 20 5-04.3(9)B7 Mixture Statistical Evaluation – Retests 21 The Contractor may request that a mixture sublot be retested. To 22 request a retest, submit a written request to the Contracting Agency 23 within 7 calendar days after the specific test results have been posted 24 to the website or emailed to the Contractor, whichever occurs first. The 25 Contracting Agency will send a split of the original acceptance sample 26 for testing by the Contracting Agency to either the Region Materials 27 Laboratory or the State Materials Laboratory as determined by the 28 Engineer. The Contracting Agency will not test the split of the sample 29 with the same equipment or by the same tester that ran the original 30 acceptance test. The sample will be tested for a complete gradation 31 analysis, asphalt binder content, and Va, and the results of the retest 32 will be used for the acceptance of the HMA mixture in place of the 33 original mixture sublot sample test results. The cost of testing will be 34 deducted from any monies due or that may come due the Contractor 35 under the Contract at the rate of $250 per sample. 36 37 5-04.3(9)C Vacant 38 39 5-04.3(9)D Mixture Acceptance – Visual Evaluation 40 Visual Evaluation of HMA mixture will be by visual inspection by the 41 Engineer or, in the sole discretion of the Engineer, the Engineer may sample 42 and test the mixture. 43

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 34 1 5-04.3(9)D1 Mixture Visual Evaluation – Lots, Sampling, Testing, 2 Price Adjustments 3 HMA mixture accepted by Visual Evaluation will not be broken into lots 4 unless the Engineer determines that testing is required. When that 5 occurs, the Engineer will identify the limits of the questionable HMA 6 mixture, and that questionable HMA mixture shall constitute a lot. Then, 7 the Contractor will take samples from the truck, or the Engineer will 8 take core samples from the roadway at a minimum of three random 9 locations from within the lot, selected in accordance with WSDOT Test 10 Method T 716, taken from the roadway in accordance with WSDOT 11 SOP 734, and tested in accordance with WSDOT SOP 737. The 12 Engineer will test one of the samples for all constituents in Section 5- 13 04.3(9)B3. If all constituents from that test fall within the Job Mix 14 Formula Tolerances (for Visual Evaluation) in Section 9-03.8(7), the lot 15 will be accepted at the unit Contract price with no further evaluation. 16 17 When one or more constituents fall outside those tolerance limits, the 18 other samples will be tested for all constituents in Section 5-04.3(9)B3, 19 and a Job Mix Compliance Price Adjustment will be calculated in 20 accordance with Table 13. 21 Table 13 Visual Evaluation – Out of Tolerance Procedures Comply with the Following Pay Factors1 Section 5-04.3(9)B4 Composite Pay Factors2 Section 5-04.3(9)B5 Price Adjustments Section 5-04.3(9)B6 1The Visual Evaluation tolerance limits in Section 9-03.8(7) will be used in the calculation of the PFi. 2The maximum CPF shall be 1.00. 22 23 5-04.3(9)E Mixture Acceptance – Notification of Acceptance Test 24 Results 25 The results of all mixture acceptance testing and the Composite Pay Factor 26 (CPF) of the lot after three sublots have been tested will be available to the 27 Contractor through The Contracting Agency’s website. 28 29 The Contracting Agency will endeavor to provide written notification (via 30 email to the Contractor’s designee) of acceptance test results through its 31 web-based materials testing system Statistical Analysis of Materials (SAM) 32 within 24 hours of the sample being made available to the Contracting 33 Agency. However, the Contractor agrees: 34 35 1. Quality control, defined as the system used by the Contractor to 36 monitor, assess, and adjust its production processes to ensure 37 that the final HMA mixture will meet the specified level of quality, 38 is the sole responsibility of the Contractor. 39 40 2. The Contractor has no right to rely on any testing performed by the 41 Contracting Agency, nor does the Contractor have any right to rely 42 on timely notification by the Contracting Agency of the Contracting 43 Agency’s test results (or statistical analysis thereof), for any part

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 35 1 of quality control and/or for making changes or correction to any 2 aspect of the HMA mixture. 3 4 3. The Contractor shall make no claim for untimely notification by the 5 Contracting Agency of the Contracting Agency’s test results or 6 statistical analysis. 7 8 5-04.3(10) HMA Compaction Acceptance 9 For all HMA, the Contractor shall comply with the General Compaction 10 Requirements in Section 5-04.3(10)A. The Contracting Agency will evaluate all 11 HMA for compaction compliance with one of the following - Statistical Evaluation, 12 Visual Evaluation, or Test Point Evaluation - determined by the criteria in Table 13 14: 14 Table 14 Criteria for Determining Method of Evaluation for HMA Compaction1 Test Point Statistical Evaluation Visual Evaluation of Evaluation of HMA of HMA Compaction is HMA Compaction is Compaction is Required For: Required For: Required For: • Any HMA for which • “HMA for • Any HMA not the specified course Preleveling…” meeting the thickness is greater • “HMA for criteria for than 0.10 feet, and Pavement Statistical the HMA is in: Repair…” Evaluation or o traffic lanes, Visual Evaluation including but not limited to: • ramp lanes • truck climbing lanes • weaving lanes • speed change lanes 1This table applies to all HMA, and shall be the sole basis for determining the acceptance method for compaction. 15 16 The Contracting Agency may, at its sole discretion, evaluate any HMA for 17 compliance with the Cyclic Density requirements of Section 5-04.3(10)B. 18 19 5-04.3(10)A HMA Compaction – General Compaction Requirements 20 Immediately after the HMA has been spread and struck off, and after 21 surface irregularities have been adjusted, thoroughly and uniformly 22 compact the mix. The completed course shall be free from ridges, ruts, 23 humps, depressions, objectionable marks, and irregularities and shall 24 conform to the line, grade, and cross-section shown in the Plans. If 25 necessary, alter the JMF in accordance with Section 9-03.8(7) to achieve 26 desired results. 27

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 36 1 Compact the mix when it is in the proper condition so that no undue 2 displacement, cracking, or shoving occurs. Compact areas inaccessible to 3 large compaction equipment by mechanical or hand tampers. Remove HMA 4 that becomes loose, broken, contaminated, shows an excess or deficiency 5 of asphalt, or is in any way defective. Replace the removed material with 6 new HMA, and compact it immediately to conform to the surrounding area. 7 8 The type of rollers to be used and their relative position in the compaction 9 sequence shall generally be the Contractor’s option, provided the specified 10 densities are attained. An exception shall be that pneumatic tired rollers 11 shall be used for compaction of the wearing course beginning October 1st 12 of any year through March 31st of the following year. Coverage with a steel 13 wheel roller may precede pneumatic tired rolling. Unless otherwise 14 approved by the Engineer, operate rollers in the static mode when the 15 internal temperature of the mix is less than 175°F. Regardless of mix 16 temperature, do not operate a roller in a mode that results in checking or 17 cracking of the mat. 18 19 On bridge decks and on the five feet of roadway approach immediately 20 adjacent to the end of bridge/back of pavement seat, operate rollers in static 21 mode only. 22 23 5-04.3(10)B HMA Compaction – Cyclic Density 24 Low cyclic density areas are defined as spots or streaks in the pavement 25 that are less than 90 percent of the theoretical maximum density. At the 26 Engineer’s discretion, the Engineer may evaluate the HMA pavement for 27 low cyclic density, and when doing so will follow WSDOT SOP 733. A $500 28 Cyclic Density Price Adjustment will be assessed for any 500-foot section 29 with two or more density readings below 90 percent of the theoretical 30 maximum density. 31 32 5-04.3(10)C HMA Compaction Acceptance – Statistical Evaluation 33 HMA compaction which is accepted by Statistical Evaluation will be based 34 on acceptance testing performed by the Contracting Agency, and statistical 35 analysis of those acceptance tests results. This will result in a Compaction 36 Price Adjustment. 37 38 5-04.3(10)C1 HMA Compaction Statistical Evaluation – Lots and 39 Sublots 40 HMA compaction which is accepted by Statistical Evaluation will be 41 evaluated by the Contracting Agency dividing the project into 42 compaction lots, and each compaction lot will be evaluated using 43 stratified random sampling by the Contracting Agency sub-dividing 44 each compaction lot into compaction sublots. All mixture in any 45 individual compaction lot shall be of the same mix design. The 46 compaction sublots will be numbered in the order in which the mixture 47 (of a particular mix design) is paved. 48 49 Each compaction lot comprises a maximum of 15 compaction sublots, 50 except for the final compaction lot of each mix design on the Contract, 51 which comprises a maximum of 25 sublots. 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 37 1 Each compaction sublot shall be uniform in size as shown in Table 15, 2 except that the last compaction sublot of each day may be increased 3 to a maximum of two times the compaction sublot quantity calculated. 4 Minor variations in the size of any sublot shall not be cause to invalidate 5 the associated test result. 6 Table 15 HMA Compaction Sublot Size HMA Original Plan Quantity Compaction Sublot Size (tons)1 (tons) <20,000 100 20,000 to 30,000 150 >30,000 200 1 In determining the plan quantity tonnage, do not include any tons accepted by test point evaluation. 7 8 The following will cause one compaction lot to end prematurely and a 9 new compaction lot to begin: 10 11 • For a compaction lot in progress with a compaction CPF less 12 than 0.75, a new compaction lot will begin at the Contractor’s 13 request after the Engineer is satisfied that material 14 conforming to the Specifications can be produced. See also 15 Section 5-04.3(11)F. 16 17 All HMA which is paved on a bridge and accepted for compaction by 18 Statistical Evaluation will compose a bridge compaction lot. If the 19 contract includes such HMA on more than one bridge, compaction will 20 be evaluated on each bridge individually, as separate bridge 21 compaction lots. 22 23 Bridge compaction sublots will be determined by the Engineer subject 24 to the following: 25 26 • All sublots on a given bridge will be approximately the same 27 size. 28 29 • Sublots will be stratified from the lot. 30 31 • In no case will there be less than 3 sublots in each bridge 32 compaction lot. 33 34 • No sublot will exceed 50 tons. 35 36 • Compaction test locations will be determined by the Engineer 37 in accordance with WSDOT FOP for AASHTO T716. 38 39 5-04.3(10)C2 HMA Compaction Statistical Evaluation – 40 Acceptance Testing 41 Comply with Section 1-06.2(1). 42

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 38 1 The location of HMA compaction acceptance tests will be randomly 2 selected by the Contracting Agency from within each sublot, with one 3 test per sublot. The Contracting Agency will determine the random 4 sample location using WSDOT Test Method T 716. 5 6 Use Table 16 to determine compaction acceptance test procedures and 7 to allocate compaction acceptance sampling and testing 8 responsibilities between the Contractor and the Contracting Agency. 9 HMA cores shall be taken or nuclear density testing shall occur after 10 completion of the finish rolling, prior to opening to traffic, and on the 11 same day that the mix is placed. 12 Table 16 HMA Compaction Acceptance Testing Procedures and Responsibilities When Contract Includes Bid When Contract Does Not Item “HMA Core Include Bid Item “HMA Core –

– Roadway” or Roadway” or “HMA Core – “HMA Core – Bridge”4 Bridge”4 Nuclear Basis for Test: Cores Cores3 Density Gauge3 Contracting Contractor shall Agency will take take cores1 cores1 using using WSDOT WSDOT SOP SOP 7342 Contracting In-Place 734 Agency, using Contracting Density Contracting WSDOT FOP Agency will Determined by: Agency will for AASHTO T determine core determine core 355 density using density using FOP for FOP for AASHTO T 166 AASHTO T 166 Theoretical Maximum Contracting Agency, using FOP for AASHTO T 209 Density Determined by: Rolling Average of Theoretical Contracting Agency, using WSDOT SOP 729 Maximum Densities Determined by: Contracting Percent Contracting Contracting Agency, using Compaction in Agency, using Agency, using WSDOT FOP Each Sublot WSDOT SOP WSDOT SOP for AASHTO T Determined by: 736 736 355

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 39 1The core diameter shall be 4-inches unless otherwise approved by the Engineer. 2The Contractor shall take the core samples in the presence of the Engineer, at locations designated by the Engineer, and deliver the core samples to the Contracting Agency. 3The Contracting Agency will determine, in its sole discretion, whether it will take cores or use the nuclear density gauge to determine in- place density. Exclusive reliance on cores for density acceptance is generally intended for small paving projects and is not intended as a replacement for nuclear gauge density testing on typical projects. 4The basis for test of all compaction sublots in a bridge compaction lot shall be cores. These cores shall be taken by the Contractor when the Proposal includes the bid item “HMA Cores – Bridge”. When there is no bid item for “HMA Cores – Bridge”, the Engineer will be responsible for taking HMA cores for all compaction sublots in a bridge compaction lot. In either case, the Engineer will determine core location, in-place density of the core, theoretical maximum density, rolling average of theoretical maximum density, and percent compaction using the procedure called for in this Section. 1 2 When using the nuclear density gauge for acceptance testing of 3 pavement density, the Engineer will follow WSDOT SOP 730 for 4 correlating the nuclear gauge with HMA cores. When cores are 5 required for the correlation, coring and testing will be by the Contracting 6 Agency. When a core is taken for gauge correlation at the location of a 7 sublot, the relative density of the core will be used for the sublot test 8 result and is exempt from retesting. 9 10 5-04.3(10)C3 HMA Statistical Compaction – Price Adjustments 11 For each HMA compaction lot (that is accepted by Statistical 12 Evaluation) which has less than three compaction sublots, for which all 13 compaction sublots attain a minimum of 91 percent compaction 14 determined in accordance with WSDOT FOP for AASHTO T 355 (or 15 WSDOT SOP 736 when provided by the Contract), the HMA will be 16 accepted at the unit Contract price with no further evaluation. 17 18 For each HMA compaction lot (that is accepted by Statistical 19 Evaluation) which does not meet the criteria in the preceding 20 paragraph, the compaction lot shall be evaluated in accordance with 21 Section 1-06.2(2) to determine the appropriate Compaction Price 22 Adjustment (CPA). All of the test results obtained from the acceptance 23 samples from a given compaction lot shall be evaluated collectively. 24 Additional testing by either a nuclear density gauge or cores will be 25 completed as required to provide a minimum of three tests for 26 evaluation. 27 28 For the statistical analysis in Section 1-06.2, use the following values: 29 30 x = Percent compaction of each sublot 31 USL = 100 32 LSL= 91 33

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 40 1 Each CPA will be determined as follows: 2 3 CPA = [0.40 x (CPF – 1.00)] x Q x UP 4 5 Where 6 7 CPA = Compaction Price Adjustment for the compaction lot ($) 8 CPF = Composite Pay Factor for the compaction lot (maximum 9 is 1.05) 10 Q = Quantity in the compaction lot (tons) 11 UP = Unit price of the HMA in the compaction lot ($/ton) 12 13 5-04.3(10)C4 HMA Statistical Compaction – Requests for 14 Retesting 15 For a compaction sublot that has been tested with a nuclear density 16 gauge that did not meet the minimum of 91 percent of the theoretical 17 maximum density in a compaction lot with a CPF below 1.00 and thus 18 subject to a price reduction or rejection, the Contractor may request 19 that a core, taken at the same location as the nuclear density test, be 20 used for determination of the relative density of the compaction sublot. 21 The relative density of the core will replace the relative density 22 determined by the nuclear density gauge for the compaction sublot and 23 will be used for calculation of the CPF and acceptance of HMA 24 compaction lot. When cores are taken by the Contracting Agency at the 25 request of the Contractor, they shall be requested by noon of the next 26 workday after the test results for the compaction sublot have been 27 provided or made available to the Contractor. Traffic control shall be 28 provided by the Contractor as requested by the Engineer. Failure by 29 the Contractor to provide the requested traffic control will result in 30 forfeiture of the request for retesting. When the CPF for the compaction 31 lot based on the results of the cores is less than 1.00, the Contracting 32 Agency will deduct the cost for the coring from any monies due or that 33 may become due the Contractor under the Contract at the rate of $200 34 per core and the Contractor shall pay for the cost of the traffic control. 35 36 5-04.3(10)D HMA Compaction – Visual Evaluation 37 Visual Evaluation will be the basis of acceptance for compaction of the Bid 38 items “HMA for Pavement Repair Cl. ___ PG ___”and “HMA for Prelevelling 39 Class___ PG___”. This HMA shall be thoroughly compacted to the 40 satisfaction of the Engineer. HMA that is used to prelevel wheel ruts shall 41 be compacted with a pneumatic tire roller. 42 43 5-04.3(10)E HMA Compaction – Test Point Evaluation 44 When compaction acceptance is by Test Point Evaluation, compact HMA 45 based on a test point evaluation of the compaction train. Perform the test 46 point evaluation in accordance with instructions from the Engineer. The 47 number of passes with an approved compaction train, required to attain the 48 maximum test point density, shall be used on all subsequent paving. 49

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 41 1 5-04.3(10)F HMA Compaction Acceptance – Notification of 2 Acceptance Test Results 3 The obligations and responsibilities for notifying the Contractor of 4 compaction acceptance test results are the same as for mixture acceptance 5 test results. See Section 5-04.3(9)E. 6 7 5-04.3(11) Reject Work 8 This Section applies to HMA and all requirements related to HMA (except 9 aggregates prior to being incorporated into HMA). For rejection of aggregate 10 prior to its incorporation into HMA refer to Section 3-04. 11 12 5-04.3(11)A Reject Work – General 13 Work that is defective or does not conform to Contract requirements shall 14 be rejected. The Contractor may propose, in writing, alternatives to removal 15 and replacement of rejected material. Acceptability of such alternative 16 proposals will be determined at the sole discretion of the Engineer. 17 18 5-04.3(11)B Rejection by Contractor 19 The Contractor may, prior to acceptance sampling and testing, elect to 20 remove any defective material and replace it with new material. Any such 21 new material will be sampled, tested, and evaluated for acceptance. 22 23 5-04.3(11)C Rejection Without Testing (Mixture or Compaction) 24 The Engineer may, without sampling, reject any batch, load, or section of 25 Roadway that appears defective. Material rejected before placement shall 26 not be incorporated into the pavement. 27 28 No payment will be made for the rejected materials or the removal of the 29 materials unless the Contractor requests the rejected material to be tested. 30 If the Contractor requests testing, acceptance will be by Statistical 31 Evaluation, and a minimum of three samples will be obtained and tested. 32 When uncompacted material is required for testing but not available, the 33 Engineer will determine random sample locations on the roadway in 34 accordance with WSDOT Test Method T 716, take cores in accordance with 35 WSDOT SOP 734, and test the cores in accordance with WSDOT SOP 737. 36 37 If the CPF for the rejected material is less than 0.75, no payment will be 38 made for the rejected material; in addition, the cost of sampling and testing 39 shall be borne by the Contractor. If the CPF is greater than or equal to 0.75, 40 the cost of sampling and testing will be borne by the Contracting Agency. If 41 the material is rejected before placement and the CPF is greater than or 42 equal to 0.75, compensation for the rejected material will be at a CPF of 43 0.75. If rejection occurs after placement and the CPF is greater than or 44 equal to 0.75, compensation for the rejected material will be at the 45 calculated CPF with an addition of 25 percent of the unit Contract price 46 added for the cost of removal and disposal. 47 48 5-04.3(11)D Rejection – A Partial Sublot (Mixture or Compaction) 49 In addition to the random acceptance sampling and testing, the Engineer 50 may also isolate from a mixture or compaction sublot any material that is 51 suspected of being defective in relative density, gradation or asphalt binder 52 content. Such isolated material will not include an original sample location.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 42 1 The Contracting Agency will obtain a minimum of three random samples of 2 the suspect material and perform the testing. When uncompacted material 3 is required for testing but is not available, the Engineer will select random 4 sample locations on the roadway in accordance with WSDOT Test Method 5 T 716, take cores samples in accordance with WSDOT SOP 734, and test 6 the material in accordance with WSDOT SOP 737. The material will then be 7 statistically evaluated as an independent lot in accordance with Section 1- 8 06.2(2). 9 10 5-04.3(11)E Rejection – An Entire Sublot (Mixture or Compaction) 11 An entire mixture or compaction sublot that is suspected of being defective 12 may be rejected. When this occurs, a minimum of two additional random 13 samples from this sublot will be obtained. When uncompacted material is 14 required for the additional samples but the material has been compacted, 15 the Contracting Agency will take and test cores from the roadway as 16 described in Section 5-04.3(11)D. The additional samples and the original 17 sublot will be evaluated as an independent lot in accordance with Section 18 1-06.2(2). 19 20 5-04.3(11)F Rejection - A Lot in Progress (Mixture or Compaction) 21 The Contractor shall shut down operations and shall not resume HMA 22 placement until such time as the Engineer is satisfied that material 23 conforming to the Specifications can be produced when: 24 25 1. the Composite Pay Factor (CPF) of a mixture or compaction lot in 26 progress drops below 1.00 and the Contractor is taking no 27 corrective action, or 28 29 2. the Pay Factor (PFi) for any constituent of a mixture or compaction 30 lot in progress drops below 0.95 and the Contractor is taking no 31 corrective action, or 32 33 3. either the PFi for any constituent (or the CPF) of a mixture or 34 compaction lot in progress is less than 0.75. 35 36 5-04.3(11)G Rejection – An Entire Lot (Mixture or Compaction) 37 An entire lot with a CPF of less than 0.75 will be rejected. 38 39 5-04.3(12) Joints 40 5-04.3(12)A HMA Joints 41 5-04.3(12)A1 Transverse Joints 42 Conduct operations such that placement of the top or wearing course 43 is a continuous operation or as close to continuous as possible. 44 Unscheduled transverse joints will be allowed, but the roller may pass 45 over the unprotected end of the freshly laid HMA only when the 46 placement of the course is discontinued for such a length of time that 47 the HMA will cool below compaction temperature. When the Work is 48 resumed, cut back the previously compacted HMA to produce a slightly 49 beveled edge for the full thickness of the course. 50 51 Construct a temporary wedge of HMA on a 50H:1V where a transverse 52 joint as a result of paving or planing is open to traffic. Separate the HMA

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 43 1 in the temporary wedge from the permanent HMA upon which it is 2 placed by strips of heavy wrapping paper or other methods approved 3 by the Engineer. Remove the wrapping paper and trim the joint to a 4 slightly beveled edge for the full thickness of the course prior to 5 resumption of paving. 6 7 Waste the material that is cut away and place new HMA against the 8 cut. Use rollers or tamping irons to seal the joint. 9 10 5-04.3(12)A2 Longitudinal Joints 11 Offset the longitudinal joint in any one course from the course 12 immediately below by not more than 6 inches nor less than 2 inches. 13 Locate all longitudinal joints constructed in the wearing course at a lane 14 line or an edge line of the Traveled Way. Construct a notched wedge 15 joint along all longitudinal joints in the wearing surface of new HMA 16 unless otherwise approved by the Engineer. The notched wedge joint 17 shall have a vertical edge of not less than the maximum aggregate size 18 nor more than ½ of the compacted lift thickness, and then taper down 19 on a slope not steeper than 4H:1V. Uniformly compact the sloped 20 portion of the HMA notched wedge joint. 21 22 On one-lane ramps a longitudinal joint may be constructed at the center 23 of the traffic lane, subject to approval by the Engineer, if: 24 25 1. The ramp must remain open to traffic, or 26 27 2. The ramp is closed to traffic and a hot-lap joint is constructed. 28 29 a. Two paving machines shall be used to construct the hot- 30 lap joint. 31 32 b. The pavement within 6 inches of the hot-lap joint will not 33 be excluded from random location selection for 34 compaction testing. 35 36 c. Construction equipment other than rollers shall not 37 operate on any uncompacted HMA. 38 39 When HMA is placed adjacent to cement concrete pavement, construct 40 longitudinal joints between the HMA and the cement concrete 41 pavement. Saw the joint to the dimensions shown on Standard Plan A- 42 40.10 and fill with joint sealant meeting the requirements of Section 9- 43 04.2. 44 45 5-04.3(12)B Bridge Paving Joint Seals 46 5-04.3(12)B1 HMA Sawcut and Seal 47 Prior to placing HMA on the bridge deck, establish sawcut alignment 48 points at both ends of the bridge paving joint seals to be placed at the 49 bridge ends, and at interior joints within the bridge deck when and 50 where shown in the Plans. Establish the sawcut alignment points in a 51 manner that they remain functional for use in aligning the sawcut after 52 placing the HMA overlay.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 44 1 2 Submit a Type 1 Working Drawing consisting of the sealant 3 manufacturer’s application procedure. 4 5 Construct the bridge paving joint seal as specified in the Plans and in 6 accordance with the detail shown in the Standard Plans. Construct the 7 sawcut in accordance with Section 5-05.3(8). Apply the sealant in 8 accordance with Section 5-05.3(8)B and the manufacturer’s application 9 procedure. 10 11 5-04.3(12)B2 Paved Panel Joint Seal 12 Construct the paved panel joint seal in accordance with the 13 requirements specified in Section 5-04.3(12)B1 and the following 14 requirement: 15 16 1. Clean and seal the existing joint between concrete panels in 17 accordance with Section 5-01.3(8) and the details shown in 18 the Standard Plans. 19 20 5-04.3(13) Surface Smoothness 21 The completed surface of all courses shall be of uniform texture, smooth, 22 uniform as to crown and grade, and free from defects of all kinds. The completed 23 surface of the wearing course shall not vary more than ⅛ inch from the lower 24 edge of a 10-foot straightedge placed on the surface parallel to the centerline. 25 The transverse slope of the completed surface of the wearing course shall vary 26 not more than ¼ inch in 10 feet from the rate of transverse slope shown in the 27 Plans. 28 29 When deviations in excess of the above tolerances are found that result from 30 a high place in the HMA, correct the pavement surface by one of the 31 following methods: 32 33 1. Remove material from high places by grinding with an approved 34 grinding machine, or 35 36 2. Remove and replace the wearing course of HMA, or 37 38 3. By other method approved by the Engineer. 39 40 Correct defects until there are no deviations anywhere greater than the 41 allowable tolerances. 42 43 Deviations in excess of the above tolerances that result from a low place in the 44 HMA and deviations resulting from a high place where corrective action, in the 45 opinion of the Engineer, will not produce satisfactory results will be accepted 46 with a price adjustment. The Engineer shall deduct from monies due or that may 47 become due to the Contractor the sum of $500.00 for each and every section of 48 single traffic lane 100 feet in length in which any excessive deviations described 49 above are found. 50 51 When portland cement concrete pavement is to be placed on HMA, the surface 52 tolerance of the HMA shall be such that no surface elevation lies above the Plan

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 45 1 grade minus the specified Plan depth of portland cement concrete pavement. 2 Prior to placing the portland cement concrete pavement, bring any such 3 irregularities to the required tolerance by grinding or other means approved by 4 the Engineer. 5 6 When utility appurtenances such as manhole covers and valve boxes are 7 located in the Traveled Way, pave the Roadway before the utility appurtenances 8 are adjusted to the finished grade. 9 10 5-04.3(14) Planing Bituminous Pavement 11 Plane in such a manner that the underlying pavement is not torn, broken, or 12 otherwise damaged by the planing operation. Delamination or raveling of the 13 underlying pavement will not be construed as damage due to the Contractor’s 14 operations. Pavement outside the limits shown in the Plans or designated by the 15 Engineer that is damaged by the Contractor’s operations shall be repaired to the 16 satisfaction of the Engineer at no additional cost to the Contracting Agency. 17 18 For mainline planing operations, use equipment with automatic controls and with 19 sensors for either or both sides of the equipment. The controls shall be capable 20 of sensing the grade from an outside reference line, or a mat-referencing device. 21 The automatic controls shall have a transverse slope controller capable of 22 maintaining the mandrel at the desired transverse slope (expressed as a 23 percentage) within plus or minus 0.1 percent. 24 25 Remove all loose debris from the planed surface before opening the planed 26 surface to traffic. The planings and other debris resulting from the planing 27 operation shall become the property of the Contractor and be disposed of in 28 accordance with Section 2-03.3(7)C, or as otherwise allowed by the Contract. 29 30 5-04.3(15) Sealing Pavement Surfaces 31 Apply a fog seal where shown in the Plans. Construct the fog seal in accordance 32 with Section 5-02.3. Unless otherwise approved by the Engineer, apply the fog 33 seal prior to opening to traffic. 34 35 5-04.3(16) HMA Road Approaches 36 Construct HMA approaches at the locations shown in the Plans or where staked 37 by the Engineer, in accordance with Section 5-04. 38 39 5-04.4 Measurement 40 HMA Cl. ___ PG ___, HMA for ___ Cl. ___ PG ___, and Commercial HMA will 41 be measured by the ton in accordance with Section 1-09.2, with no deduction being made 42 for the weight of asphalt binder, mineral filler, or any other component of the HMA. If the 43 Contractor elects to remove and replace HMA as allowed by Section 5-04.3(11), the 44 material removed will not be measured. 45 46 Roadway cores will be measured per each for the number of cores taken. 47 48 Crack Sealing-LF will be measured by the linear foot along the line of the crack. 49 50 Soil residual herbicide will be measured by the mile for the stated width to the nearest 51 0.01 mile or by the square yard, whichever is designated in the Proposal. 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 46 1 Pavement repair excavation will be measured by the square yard of surface marked prior 2 to excavation. 3 4 Asphalt for fog seal will be measured by the ton, as provided in Section 5-02.4. 5 6 Longitudinal joint seals between the HMA and cement concrete pavement will be 7 measured by the linear foot along the line and slope of the completed joint seal. 8 9 HMA sawcut and seal, and paved panel joint seal, will be measured by the linear foot 10 along the line and slope of the completed joint seal. 11 12 Planing bituminous pavement will be measured by the square yard. 13 14 Temporary pavement marking will be measured by the linear foot as provided in Section 15 8-23.4. 16 17 Water will be measured by the M gallon as provided in Section 2-07.4. 18 19 5-04.5 Payment 20 Payment will be made for each of the following Bid items that are included in the Proposal: 21 22 “HMA Cl. ___ PG ___”, per ton. 23 “HMA for Approach Cl. ___ PG ___”, per ton. 24 “HMA for Preleveling Cl. ___ PG ___”, per ton. 25 “HMA for Pavement Repair Cl. ___ PG ___”, per ton. 26 “Commercial HMA”, per ton. 27 The unit Contract price per ton for “HMA Cl. ___ PG ___”, “HMA for Approach Cl. ___ 28 PG ___”, “HMA for Preleveling Cl. ___ PG ___”, “HMA for Pavement Repair Cl. ___ 29 PG ___”, and “Commercial HMA” shall be full compensation for all costs, including 30 anti-stripping additive, incurred to carry out the requirements of Section 5-04 except 31 for those costs included in other items which are included in this Subsection and 32 which are included in the Proposal. 33 34 “Crack Sealing-FA”, by force account. 35 “Crack Sealing-FA” will be paid for by force account as specified in Section 1-09.6. 36 For the purpose of providing a common Proposal for all Bidders, the Contracting 37 Agency has entered an amount in the Proposal to become a part of the total Bid by 38 the Contractor. 39 40 “Crack Sealing-LF”, per linear foot. 41 The unit Contract price per linear foot for “Crack Sealing-LF” shall be full payment for 42 all costs incurred to perform the Work described in Section 5-04.3(4)A. 43 44 “Soil Residual Herbicide ____ ft. Wide”, per mile, or 45 “Soil Residual Herbicide”, per square yard. 46 The unit Contract price per mile or per square yard for “Soil Residual Herbicide” shall 47 be full payment for all costs incurred to obtain, provide and install herbicide in 48 accordance with Section 5-04.3(4)B. 49 50 “Pavement Repair Excavation Incl. Haul”, per square yard. 51 The unit Contract price per square yard for “Pavement Repair Excavation Incl. Haul” 52 shall be full payment for all costs incurred to perform the Work described in Section

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 47 1 5-04.3(4)C with the exception, however, that all costs involved in the placement of 2 HMA shall be included in the unit Contract price per ton for “HMA for Pavement 3 Repair Cl. ___ PG ___”, per ton. 4 5 “Asphalt for Fog Seal”, per ton. 6 Payment for “Asphalt for Fog Seal” is described in Section 5-02.5. 7 8 “Longitudinal Joint Seal”, per linear foot. 9 The unit Contract price per linear foot for “Longitudinal Joint Seal” shall be full 10 payment for all costs incurred to construct the longitudinal joint between HMA and 11 cement concrete pavement, as described in Section 5-04.3(12)B. 12 13 “HMA Sawcut And Seal”, per linear foot. 14 The unit Contract price per linear foot for “HMA Sawcut And Seal” shall be full 15 payment for all costs incurred to perform the Work described in Section 5- 16 04.3(12)B1. 17 18 “Paved Panel Joint Seal”, per linear foot. 19 The unit Contract price per linear foot for “Paved Panel Joint Seal” shall be full 20 payment for all costs incurred to perform the Work described in Section 5- 21 04.3(12)B2. 22 23 “Planing Bituminous Pavement”, per square yard. 24 The unit Contract price per square yard for “Planing Bituminous Pavement” shall be 25 full payment for all costs incurred to perform the Work described in Section 5- 26 04.3(14). 27 28 “Temporary Pavement Marking”, per linear foot. 29 Payment for “Temporary Pavement Marking” is described in Section 8-23.5. 30 31 “Water”, per M gallon. 32 Payment for “Water” is described in Section 2-07.5. 33 34 “Job Mix Compliance Price Adjustment”, by calculation. 35 “Job Mix Compliance Price Adjustment” will be calculated and paid for as described 36 in Section 5-04.3(9)B6 and 5-04.3(9)D1. 37 38 “Compaction Price Adjustment”, by calculation. 39 “Compaction Price Adjustment” will be calculated and paid for as described in Section 40 5-04.3(10)C3. 41 42 “HMA Core – Bridge”, per each. 43 The unit Contract price per each for “HMA Core – Bridge” shall be full payment for all 44 costs, including traffic control, associated with taking HMA density cores in pavement 45 that is on a bridge deck. 46 47 “HMA Core – Roadway”, per each. 48 The unit Contract price per each for “HMA Core – Roadway” shall be full payment for 49 all costs, including traffic control, associated with taking HMA density cores in 50 pavement that is not on a bridge deck. 51 52 “Cyclic Density Price Adjustment”, by calculation.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 48 1 “Cyclic Density Price Adjustment” will be calculated and paid for as described in 2 Section 5-04.3(10)B. 3 4 Section 5-05, Cement Concrete Pavement 5 January 3, 2017

6 5-05.3(1) Concrete Mix Design for Paving 7 In last sentence of the second paragraph of item number 1, the reference to “Section 9-01.2(4)” 8 is revised to read “Section 9-01.2(1)B”. 9 10 The following is inserted after item number 2: 11 12 3. Mix Design Modifications - The Contractor may initiate adjustments to the 13 aggregate proportions of the approved mix design. An adjustment in both the fine 14 and coarse aggregate batch target weights of plus or minus 200 pounds per cubic 15 yard will be allowed without resubmittal of the mix design. The adjusted aggregate 16 weights shall become the new batch target weights for the mix design. 17 18 Item number 3 is renumbered to 4 and revised (up until the table) to read: 19 20 4. Conformance to Mix Design - Cement and coarse and fine aggregate weights shall 21 be within the following tolerances of the batch target weights of the mix design: 22 Portland Cement Concrete Batch Weights Cement +5% -1% Coarse Aggregate +2% -2% Fine Aggregate +2% -2% 23 24 5-05.3(3)B Mixing Equipment 25 The last sentence of item number 4 is revised to read: 26 27 Plant-mixed concrete may be transported in nonagitated vehicles provided that the 28 concrete is in a workable condition when placed and: 29 30 a. discharge is completed within 45 minutes after the introduction of mixing water 31 to the cement and aggregates, or 32 33 b. discharge is completed within 60 minutes after the introduction of mixing water 34 to the cement and aggregates, provided the concrete mix temperature is 70°F 35 or below during placement, or 36 37 c. discharge is completed within 60 minutes after the introduction of mixing water 38 to the cement and aggregates, provided the mix contains an approved set 39 retarder at the manufacturer’s minimum dosage rate. 40 41 5-05.3(6) Subgrade 42 This section, including title, is revised to read: 43

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 49 1 5-05.3(6) Surface Preparation 2 The Subgrade surface shall be prepared and compacted a minimum of 3 feet beyond 3 each edge of the area which is to receive concrete pavement in order to accommodate 4 the slip-form equipment. 5 6 Concrete shall not be placed during a heavy rainfall. Prior to placing concrete: 7 8 1. The surface shall be moist; 9 10 2. Excess water (e.g., standing, pooling or flowing) shall be removed from the 11 surface. 12 13 3. The surface shall be clean and free of any deleterious materials. 14 15 4. The surface temperature shall not exceed 120°F or be frozen. 16 17 5-05.3(7)A Slip-Form Construction 18 The second sentence of the first paragraph is revised to read: 19 20 The alignment and elevation of the paver shall be regulated from outside reference lines 21 established for this purpose, or by an electronic control system capable of controlling the 22 line and grade within required tolerances. 23 24 Section 6-01, General Requirements for Structures 25 January 5, 2015

26 6-01.6 Load Restrictions on Bridges Under Construction 27 The first sentence of the second paragraph is revised to read: 28 29 If necessary and safe to do so, and if the Contractor requests it through a Type 2E 30 Working Drawing, the Engineer may allow traffic on a bridge prior to completion. 31 32 In the second paragraph, item number 3 (up until the colon) is revised to read: 33 34 3. Provide stress calculations under the design criteria specified in the AASHTO LRFD 35 Bridge Design Specifications, current edition, including at a minimum the following: 36 37 6-01.9 Working Drawings 38 This section is revised to read: 39 40 All Working Drawings required for bridges and other Structures shall conform to Section 41 1-05.3. 42 43 6-01.10 Utilities Supported by or Attached to Bridges 44 In the second paragraph, “bridge structures” is revised to read “bridges”. 45 46 6-01.14 Premolded Joint Filler 47 In the second paragraph, the first sentence is revised to read: 48 49 The Contractor may substitute for the nails any adhesive acceptable to the Engineer. 50

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 50 1 Section 6-02, Concrete Structures 2 August 7, 2017

3 6-02.2 Materials 4 The item “Elastomeric Bearing Pads” is revised to read “Fabricated Bridge Bearing 5 Assemblies”. 6 7 6-02.3(2) Proportioning Materials 8 In the sixth paragraph, the reference to “Section 9-01.2(4)” is revised to read “9-01.2(1)B”. 9 10 6-02.3(2)A Contractor Mix Design 11 The following new sentence is inserted after the first sentence of the third paragraph: 12 13 The mix design submittal shall also include test results no older than one year showing 14 that the Aggregates do not contain Deleterious Substances in accordance with Section 9- 15 03. 16 17 6-02.3(2)A1 Contractor Mix Design for Concrete Class 4000D 18 Item number 4 of the first paragraph is deleted. 19 20 Items number 5, 6, and 7 of the first paragraph are renumbered to 4, 5, and 6, respectively. 21 22 The following new sentence is inserted after the second sentence of the last paragraph: 23 24 Mix designs using shrinkage reducing admixture shall state the specific quantity required. 25 26 The following new sentence is inserted before the last sentence of the last paragraph: 27 28 Testing samples of mixes using shrinkage reducing admixture shall use the admixture 29 amount specified in the mix design submittal. 30 31 6-02.3(2)B Commercial Concrete 32 The last sentence of the first paragraph is revised to read: 33 34 Commercial concrete does not require mix design or source approvals for cement, 35 aggregate, and other admixtures. 36 37 6-02.3(5)G Sampling and Testing for Temperature, Consistency and Air 38 Content 39 The last three paragraphs are revised to read: 40 41 Sampling and testing will be performed before concrete placement from the first load. 42 Concrete shall not be placed until all tests have been completed by the Engineer, and the 43 results indicate that the concrete is within acceptable limits. If the concrete is not within 44 acceptable limits, sampling and testing will continue before concrete placement for each 45 load until one load meets all of the applicable acceptance requirements. After one test 46 indicates that the concrete is within specified limits, the concrete may be placed and the 47 sampling and testing frequency may decrease to one for every 100 cubic yards. Sampling 48 shall be performed in accordance with FOP for WAQTC TM 2 and random samples shall 49 be selected in accordance with WSDOT T 716. After the first acceptable load of concrete,

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 51 1 up to ½ cubic yard may be placed from subsequent loads to be tested prior to testing for 2 acceptance. 3 4 When the results for any subsequent acceptance test indicates that the concrete as 5 delivered and approved by the Contractor for placement does not conform to the specified 6 limits, the sampling and testing frequency will be resumed for each load. Whenever one 7 subsequent test indicates that the concrete is within the specified limits, the random 8 sampling and testing frequency of one for every 100 cubic yards may resume. 9 10 Sampling and testing for a placement of one class of concrete consisting of 50 cubic yards 11 or less will be as listed above, except that after one set of tests indicate that the concrete 12 is within specified limits, the remaining concrete to be placed may be accepted by visual 13 inspection. 14 15 6-02.3(6)A1 Hot Weather Protection 16 This section is revised to read: 17 18 The Contractor shall provide concrete within the specified temperature limits. Cooling of 19 the coarse aggregate piles by sprinkling with water is permitted provided the moisture 20 content is monitored and the mixing water is adjusted for the free water in the aggregate. 21 Shading or cooling aggregate piles (sprinkling of fine aggregate piles with water is not 22 allowed). If sprinkling of the coarse aggregates is to be used, the piles moisture content 23 shall be monitored and the mixing water adjusted for the free water in the aggregate. In 24 addition, when removing the coarse aggregate, it shall be removed from at least 1 foot 25 above the bottom of the pile. Refrigerating mixing water; or replacing all or part of the 26 mixing water with crushed ice, provided the ice is completely melted by placing time. 27 28 If air temperature exceeds 90°F, the Contractor shall use water spray or other accepted 29 methods to cool all concrete-contact surfaces to less than 90°F. These surfaces include 30 forms, reinforcing steel, steel beam flanges, and any others that touch the mix. 31 32 6-02.3(6)A2 Cold Weather Protection 33 This section is revised to read: 34 35 Concrete shall be maintained at or above a temperature of 40°F during the first seven 36 days of the Cold Weather Protection Period and at or above a temperature of 35°F during 37 the remainder of the Cold Weather Protection Period. Cold weather protection 38 requirements do not apply to concrete in shafts and piles placed below the ground line. 39 40 Prior to placing concrete in cold weather, the Contractor shall submit a Type 2 Working 41 Drawing with a written procedure for cold weather concreting. The procedure shall detail 42 how the Contractor will adequately cure the concrete and prevent the concrete 43 temperature from falling below the minimum temperature. Extra protection shall be 44 provided for areas especially vulnerable to freezing (such as exposed top surfaces, 45 corners and edges, thin sections, and concrete placed into steel forms). Concrete 46 placement will only be allowed if the Contractor’s cold weather protection plan has been 47 accepted by the Engineer. 48 49 Prior to concrete placement, the Contractor shall review the 7-day temperature 50 predictions for the job site from the Western Region Headquarters of the National Weather 51 Service (www.wrh.noaa.gov). When temperatures below 35°F are predicted, the 52 Contractor shall:

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 52 1 2 1. Install temperature sensors in each concrete placement. One sensor shall be 3 installed for every 100 cubic yards of concrete placed. Sensors shall be installed 4 at locations directed by the Engineer, and shall be placed 1.5 inches from the 5 face of concrete. 6 7 2. Immediately after concrete placement, temperature sensors shall be installed 8 on the concrete surface at locations directed by the Engineer. One sensor shall 9 be installed for every 100 cubic yards of concrete placed. 10 11 Temperatures shall be measured and recorded a minimum of every hour for the duration 12 of the Cold Weather Protection Period. Temperature data shall be submitted to the 13 Engineer as a Type 1 Working Drawing within three days following the end of the Cold 14 Weather Protection Period. 15 16 For each day that the concrete temperature falls below 40°F during the first seven days 17 of the Cold Weather Protection Period, no curing time is awarded for that day and the 18 Cold Weather Protection Period is extended for one additional day. If the concrete 19 temperature falls below 35°F during the Cold Weather Protection Period, the concrete 20 may be rejected by the Engineer. 21 22 6-02.3(7) Concrete Exposed to Sea Water 23 This section including title is revised to read: 24 25 6-02.3(7) Vacant 26 27 6-02.3(8) Concrete Exposed to Alkaline Soils or Water 28 This section including title is revised to read: 29 30 6-02.3(8) Vacant 31 32 6-02.3(10)D4 Monitoring Bridge Deck Concrete Temperature After Placement 33 This section is revised to read: 34 35 The Contractor shall measure and record the concrete temperature and ambient 36 temperature a minimum of every hour for seven calendar days after concrete placement. 37 The Contractor shall place two temperature sensors in the bridge deck at locations 38 specified by the Engineer. The Contractor shall measure ambient temperature near the 39 locations where concrete temperature is being measured. When the bridge deck is being 40 enclosed and heated to meet cold weather requirements, ambient temperature readings 41 shall be taken within the enclosure. The Contractor shall submit the concrete temperature 42 and ambient temperature data as a Type 1 Working Drawing in spreadsheet format within 43 14 calendar days from placing the bridge deck concrete. 44 45 The Contractor shall submit a Type 1 Working Drawing consisting of the type and model 46 of each device and the method used to measure and record the temperatures. 47 48 6-02.3(13)A Strip Seal Expansion Joint System 49 The first paragraph is revised to read: 50 51 The Contractor shall submit Type 2 Working Drawings consisting of the strip seal 52 expansion joint shop drawings. These plans shall include, at a minimum, the following:

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 53 1 2 1. Plan, elevation, and sections of the joint system and all components, with 3 dimensions and tolerances. 4 5 2. All material designations. 6 7 3. Manufacturer’s written installation procedure. The installation procedure shall 8 indicate how the extrusions set into the two sides of the joint will be allowed to 9 move independently of one another. 10 11 4. Corrosion protection system used on the metal components. 12 13 5. Locations of welded shear studs, lifting mechanisms, temperature setting 14 devices, and construction adjustment devices. 15 16 6. Method of sealing the system to prevent leakage of water through the joint. 17 18 7. Details of the temporary supports for the steel extrusions while the 19 encapsulating concrete of the headers is placed and cured. 20 21 8. The gland installation procedure, including the means and methods used to 22 install the gland and assure correct seating of the gland within the steel 23 extrusions. 24 25 The following new paragraph is inserted after the third paragraph: 26 27 If the gland is installed in the field, the Contractor shall have the services of a strip seal 28 expansion joint system manufacturer’s technical representative physically present at the 29 job site. The manufacturer’s technical representative shall train the Contractor’s 30 personnel performing the field installation of the gland, provide technical assistance for 31 installing the gland, and observe and inspect the installation of at least the first complete 32 joint. 33 34 The second to last paragraph is deleted. 35 36 6-02.3(14)D General Requirements for Concrete Surface Finishes Produced by 37 Form Liners 38 The first two sentences of the third paragraph are deleted. 39 40 6-02.3(16) Plans for Falsework and 41 The last sentence of the first paragraph is revised to read: 42 43 A submittal is not required for footing or retaining wall formwork if the concrete placement 44 is 4 feet or less in height. 45 46 The second to last paragraph is revised to read: 47 48 The Contractor shall furnish associated design calculations to the Engineer as part of the 49 submittal. The design calculations shall include the structural and geotechnical design of 50 the foundation and shall show the stresses and deflections in all load-carrying members 51 that are part of the falsework system. Construction details which may be shown in the 52 form of sketches on the calculation sheets shall be shown in the falsework or formwork

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 54 1 drawings as well. Falsework or formwork plans will not be accepted in cases where it is 2 necessary to refer to the calculation sheets for information needed for complete 3 understanding of the falsework and formwork plans or how to construct the falsework and 4 formwork. 5 6 The last paragraph is deleted. 7 8 6-02.3(17)D Falsework Support Systems: Piling, Temporary Concrete 9 Footings, Timber Mudsills, Manufactured Shoring Towers, Caps, and Posts 10 This section, including title, is revised to read: 11 12 6-02.3(17)D Falsework Support Systems: Foundations, Manufactured 13 Shoring Towers, Caps, and Posts 14 Foundations for falsework shall be designed for conditions stated in this Section using 15 methods shown in the AASHTO Standard Specifications for Highway Bridges 16 Seventeenth Edition – 2002 for allowable stress design, the AASHTO LRFD Bridge 17 Design Specifications for load and resistance factor design or the AASHTO Guide Design 18 Specifications for Bridge Temporary Works. Allowable stresses for materials shall not 19 exceed stresses and conditions allowed by Section 6-02.3(17)B. 20 21 6-02.3(17)D1 Piling 22 This section including title is revised to read: 23 24 6-02.3(17)D1 Vacant 25 26 6-02.3(17)D2 Temporary Concrete Footings and Timber Mudsills 27 This section including title is revised to read: 28 29 6-02.3(17)D2 Vacant 30 31 6-02.3(17)D4 Manufactured Shoring Tower Systems and Devices 32 The fifth paragraph is deleted. 33 34 6-02.3(17)D5 Cross-Braced Type Base Frames 35 This section is deleted in its entirety. 36 37 6-02.3(17)D6 Ladder Type Base Frames 38 This section is deleted in its entirety. 39 40 6-02.3(17)D7 Intermediate Strength Shoring 41 This section is deleted in its entirety. 42 43 6-02.3(17)D8 Heavy-Duty Shoring Systems 44 This section is deleted in its entirety. 45 46 6-02.3(17)K Concrete Forms on Steel Spans 47 In the last paragraph, “ASTM A325” is revised to read “ASTM F3125 Grade A325”. 48 49 6-02.3(17)N Removal of Falsework and Forms 50 The fifth paragraph is deleted. 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 55 1 6-02.3(19)A Vacant 2 This section, including title, is revised to read: 3 4 6-02.3(19)A Submittals of Acceptance Test Reports and Certificates 5 The Contractor shall submit the following production samples and test reports and 6 certificates for fabricated bridge bearing assemblies as applicable: 7 1 8 1. A Type 2 Working Drawing consisting of a six-inch square by ⁄8-inch thick 9 sample of PTFE taken from the lot of production material. 10 11 2. A Type 2 Working Drawing consisting of a six-inch square by 1-inch thick sample 12 of pre-formed fabric pad taken from the lot of production material. 13 14 3. Type 1 Working Drawings consisting of Manufacturers’ Certificates of 15 Compliance for the PTFE, polyether urethane, pre-formed fabric pad duck, 16 silicone grease, epoxy gel, and resin filler. 17 18 4. Type 1 Working Drawings consisting of certified mill test reports for all steel and 19 stainless steel in the bearing assemblies. 20 21 5. Type 1 Working Drawings consisting of certified test reports confirming that the 22 pre-formed fabric pads meet the specific requirements of proof load. 23 24 6-02.3(24)A Field Bending 25 This section (excluding the tables) is revised to read: 26 27 Field bending of AASHTO M31 Grade 60 and ASTM A706 Grade 60 reinforcement shall 28 be done in accordance with the requirements of this section. Field bending of all other 29 reinforcement shall require a Type 2 Working Drawing showing the bend radii, bending 30 and heating procedures, and any inspection or testing requirements. 31 32 Field bending shall not be done on reinforcement within the top or bottom third of column 33 lengths or within plastic hinge regions identified in the Plans. Field bending shall not be 34 done on bar sizes No. 14 or No. 18. 35 36 In field-bending steel reinforcing bars, the Contractor shall: 37 38 1. Make the bend gradually using a bending tool equipped with a bending diameter 39 as listed in Table 1. Bending shall not be done by means of hammer blows and 40 pipe sleeves. When bending to straighten a previously bent bar, move a hickey 41 bar progressively around the bend. 42 43 2. Apply heat as described below for bending bar sizes No. 6 through No. 11 and 44 for bending bar sizes No. 5 and smaller when the bars have been previously 45 bent. Previously unbent bars of sizes No. 5 and smaller may be bent without 46 heating when the bar temperature is 40°F or higher. When previously unbent 47 bars of sizes No. 5 and smaller have a bar temperature lower than 40°F, they 48 shall be heated to within the range of 100°F to 150°F prior to bending. In applying 49 heat for field-bending steel reinforcing bars, the Contractor shall: 50 51 a. Avoid damage to the concrete by insulating any concrete within 6 inches of 52 the heated bar area;

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 56 1 2 b. Apply two heat tips simultaneously at opposite sides of bar sizes No. 7 or 3 larger; 4 5 c. Heat the bar to within the required temperature range shown in Table 2 as 6 verified by using temperature-indicating crayons or other suitable means; 7 8 d. Heat a minimum bar length as shown in Table 3. Locate the heated section 9 of the bar to include the entire bending length; 10 11 e. Bend immediately after the required temperature range has been achieved. 12 Maintain the bar within the required temperature range during the entire 13 bending process; 14 15 f. Do not cool bars artificially with water, forced air, or other means. 16 17 3. Limit any bend or straightening to these maximum angles: 135 degrees for bar 18 sizes No. 8 or smaller, and 90 degrees for bar sizes No. 9 through No. 11. 19 20 4. Repair epoxy coating on epoxy coated bars in accordance with Section 6- 21 02.3(24)H. 22 23 6-02.3(25) Girders 24 Under the heading “Prestressed Girder”, the second sentence is deleted. 25 26 6-02.3(25)A Shop Drawings 27 The sixth paragraph is deleted. 28 29 6-02.3(25)F Prestress Release 30 The last two sentences of the last paragraph are deleted and replaced with the following single 31 sentence: 32 33 This request shall be submitted as a Type 2E Working Drawing analyzing changes in 34 vertical deflection, girder lateral stability and concrete stresses in accordance with Section 35 6-02.3(25)L2. 36 37 6-02.3(25)H Finishing 38 Item number 2 in the first paragraph is revised to read: 39 40 2. The bottoms, sides, and tops of the lower flanges on all girders, including the top of 41 the bottom slab between the tub girder webs. 42 43 6-02.3(25)I Fabrication Tolerances 44 Items 4 and 5 in the first paragraph are revised to read: 45 46 4. Flange Depth: ± ¼ inch 47 48 5. Strand Position: 49 50 Individual strands: ± ¼ inch 51 52 Bundled strands: ± ½ inch

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 57 1 2 Harped strand group center of gravity at the girder ends: ± 1 inch 3 4 Items 7, 8, 9 and 10 in the first paragraph are revised to read: 5 6 7. Position of an Interior Void, vertically and horizontally: ± ½ inch. 7 8 8. Bearing Recess (center of recess to girder end): ± ⅝ inch. 9 10 9. Girder Ends (deviation from square or designated skew): 11 12 Horizontal: ± ⅛ inch per foot of girder width, up to a maximum of ± ½ inch 13 3 14 Vertical: ± ⁄16 inch per foot of girder depth, up to a maximum of ± 1 inch 15 16 10. Bearing Area Deviation from Plane (in length or width of bearing): ± ⅛ inch 17 18 Items 14 and 15 in the first paragraph are revised to read: 19 20 14. Local smoothness of any surface: ± ¼ inch in 10 feet. 21 22 15. Differential Camber between Girders in a Span (measured in place at the job site): 23 For wide flange deck and deck bulb Cambers shall be equalized when tee girders with a cast-in-place the differences in cambers between reinforced concrete deck: adjacent girders exceeds ± ¾ inch For wide flange deck, deck bulb tee Cambers shall be equalized when and slab girders without a cast-in- the differences in cambers between place reinforced concrete deck: adjacent girders exceeds ± ¼ inch 24 25 Item 17 in the first paragraph is revised to read: 26 27 17. Position of Lifting Embedments: ± 3 inches longitudinal, ± ¼ inch transverse. 28 29 6-02.3(25)J Horizontal Alignment 30 This section is revised to read: 31 32 The Contractor shall check and record the horizontal alignment (sweep) of each girder at 33 the following times: 34 35 1. Initial – Upon removal of the girder from the casting bed 36 37 2. Shipment – Within 14 days prior to shipment; and 38 39 3. Erection – After girder erection and cutting temporary top strands but prior to 40 any equalization, welding ties or placement of diaphragms. 41 42 Horizontal alignment of the top and bottom flanges shall be checked and recorded. 43 Alternatively, the Contractor may check and record the horizontal alignment of the web 44 near mid-height of the girder. Each check shall be made by measuring the maximum 45 offset at mid-span relative to a chord that starts and stops at the girder ends. The 46 Contractor shall check and record the alignment at a time when the girder is not influenced

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 58 1 by temporary differences in surface temperature. Records for the initial check (item 1 2 above) shall be included in the Contractor’s prestressed concrete certificate of 3 compliance. Records for all other checks shall be submitted as a Type 1 Working Drawing. 4 5 For each check (Items 1 to 3 above), the alignment shall not be offset more than ⅛ inch 6 for each 10 feet of girder length. Girders not meeting this tolerance for the shipment check 7 (Item 2 above) shall require an analysis of girder lateral stability and stresses in 8 accordance with Section 6-02.3(25)L1. The Contractor shall perform this analysis and 9 submit it as a Type 2E Working Drawing prior to shipment of the girder. Any girder that 1 10 exceeds an offset of ⁄8 inch for each 10 feet of girder length for the erection check (Item 1 11 3 above) shall be corrected at the job site to the ⁄8 inch maximum offset per 10 feet of 12 girder length before concrete is placed into the diaphragms. The Contractor shall submit 13 a Type 2 Working Drawing for any required corrective action. 14 15 The maximum distance between the side of a prestressed concrete slab girder, or the 16 edge of the top flange of a wide flange deck, wide flange thin deck or deck bulb tee girder, 17 and a chord that extends the full length of the girder shall be ±½ inch after erection (Item 18 3 above). 19 20 6-02.3(25)K Vertical Deflection 21 Items 2 and 3 in the first paragraph are revised to read: 22 23 2. Shipment – Within 14 days prior to shipment; 24 25 3. Erection – After girder erection and cutting temporary top strands but prior to any 26 equalization, welding ties or placement of diaphragms. 27 28 The following new paragraph is inserted after the second paragraph: 29 30 Girders with vertical deflections not meeting the limit shown in the Plans for the shipment 31 check (Item 2 above) shall require an analysis of girder lateral stability and stresses in 32 accordance with Section 6-02.3(25)L1. The Contractor shall perform this analysis and 33 submit it as a Type 2E Working Drawing prior to shipment. 34 35 The following new sentence is inserted after the second sentence of the fourth to last 36 paragraph: 37 38 Any diaphragms are assumed to be placed. 39 40 The last three paragraphs are deleted and replaced with the following: 41 42 If the girder vertical deflection measured for the erection check (Item 3 above) is not 43 between the lower “D” dimension bound shown in the Plans and the upper “D” dimension 44 bound shown in the Plans plus ¾ inches, the Engineer may require corrective action. The 45 Contractor shall submit a Type 2 Working Drawing for any required corrective action. 46 47 6-02.3(25)L Handling and Storage 48 The second paragraph is revised to read: 49 50 For strand lift loops, only ½-inch diameter or 0.6-inch diameter strand conforming to 51 Section 9-07.10 shall be used, and a minimum 2-inch diameter straight pin of a shackle 52 shall be used through the loops. Multiple loops shall be held level in the girder during

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 59 1 casting in a manner that allows each loop to carry its share of the load during lifting. The 2 minimum distance from the end of the girder to the centroid of the strand lift loops shall 3 be 3 feet. The loops for all prestressed concrete girders, with the exception of prestressed 4 concrete slab girders, shall project a minimum of 1′-6″ from the top of the girder. The loops 5 for prestressed concrete slab girders shall project a minimum of 4 inches. Loops shall 6 extend to within 3 inches clear of the bottom of the girder, terminating with a 9-inch long 7 90-degree hook. Loads on individual loops shall be limited to 12 kips, and all girders shall 8 be picked up at a minimum angle of 60 degrees from the top of the girder. 9 10 The third sentence of the fourth paragraph is revised to read: 11 12 Alternatively, these temporary strands may be post-tensioned provided the strands are 13 stressed on the same day that the permanent prestress is released into the girder and 14 the strands are tensioned prior to lifting the girder. 15 16 The second to last sentence of the fourth paragraph is revised to read: 17 18 When the post-tensioned alternative is used, the Contractor shall be responsible for 19 properly sizing the anchorage plates, and configuring the reinforcement adjacent to the 20 anchorage plates, to prevent bursting or splitting of the concrete in the top flange. 21 22 The second to last paragraph is deleted. 23 24 This section is supplemented with the following new subsections: 25 26 6-02.3(25)L1 Girder Lateral Stability and Stresses 27 The Contractor shall be responsible for safely lifting, storing, shipping and erecting 28 prestressed concrete girders. 29 30 The Contract documents may provide shipping and handling details for girders including 31 lifting embedment locations (L), shipping support locations (L1 and L2), minimum shipping 32 support rotational spring constants (Kθ), minimum shipping support center-to-center 33 wheel spacings (Wcc), vertical deflections and number of temporary top strands. These 34 shipping and handling details have been determined in accordance with Section 6- 35 02.3(25)L2. 36 37 The Contractor shall submit a Type 2E Working Drawing analyzing girder lateral stability 38 and concrete stresses during lifting, storage, shipping and erection in accordance with 39 Section 6-02.3(25)L2 in the following cases: 40 41 1. Any of the analysis assumptions listed in Section 6-02.3(25)L2 are invalid. 42 Determination of validity shall be made by the Contractor, except that analysis 43 assumptions shall be considered invalid if the actual values are outside of the 44 provided tolerances. 45 46 2. The Contractor intends to alter the shipping and handling details provided in the 47 Contract documents. 48 49 3. The Contract documents do not provide shipping and handling details. 50

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 60 1 6-02.3(25)L2 Lateral Stability and Stress Analysis 2 Analysis for girder lateral stability and concrete stresses during lifting, storage, shipping 3 and erection shall be in accordance with the PCI Recommended Practice for Lateral 4 Stability of Precast, Prestressed Concrete Bridge Girders, First Edition, Publication CB- 5 02-16-E and the AASHTO LRFD Bridge Design Specifications edition identified in the 6 Contract documents. The following design criteria shall be met: 7 8 1. Factor of Safety against cracking shall be at least 1.0 9 10 2. Factor of Safety against failure shall be at least 1.5 11 12 3. Factor of Safety against rollover shall be at least 1.5 13 14 4. Allowable concrete stresses shall be as specified in Section 6-02.3(25)L3 15 16 The analysis shall address any effects on girder vertical deflection (camber), “A” 17 dimensions at centerline of bearings and deck screed cambers (C). 18 19 Shipping and handling details provided in the Contract documents have been determined 20 using the following analysis assumptions: 21 22 1. Girder dimensions, strand locations and lifting embedment locations are within 23 the tolerances specified in Section 6-02.3(25)I 24 25 2. Girder horizontal alignment (sweep) is within the tolerance specified in Section 26 6-02.3(25)J 27 28 3. Girder vertical deflection (camber) at midspan is less than or equal to the value 29 shown in the Plans for shipping 30 31 4. Minimum concrete compressive strength at release (f’ci) has been reached 32 before initial lifting from casting bed. Minimum concrete compressive strength at 33 28 days (f’c) has been reached before shipping. 34 35 5. Height of girder bottom above roadway at shipping supports is less than or equal 36 to 72 inches 37 38 6. Height of shipping support roll center above roadway is 24 inches, ± 2 inches 39 40 7. Shipping support longitudinal placement (L1 and L2) tolerance is ± 6 inches 41 42 8. Shipping support lateral placement tolerance is ±1 inches 43 44 9. Shipping supports provide the minimum shipping support rotational spring 45 constant (Kθ) and minimum shipping support center-to-center wheel spacings 46 (W cc) shown in the Plans 47 48 10. For shipping at highway speeds a ± 20% dynamic load allowance (impact) is 49 included with a typical roadway superelevation of 2% 50 51 11. For turning at slow speeds, no dynamic load allowance (impact) is included with 52 a maximum roadway superelevation of 6%

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 61 1 2 12. Wind, centrifugal and seismic forces are not considered 3 4 6-02.3(25)L3 Allowable Stresses 5 Prestressed concrete girder stresses shall be limited to the following values at all stages 6 of construction and in service: 7 Condition Stress Location Allowable Stress (ksi) Temporary Tensile In areas without bonded Stress at reinforcement sufficient . ′ . Transfer to resist the tensile force 0 0948� ��� 0 2 and Lifting in the concrete � ≤ from In areas with bonded Casting reinforcement sufficient . ′ Bed to resist the tensile force 0 24� ��� in the concrete � Compressive All locations ′ 0.65��� Temporary Tensile In areas without bonded Stress at reinforcement sufficient . ′ . Shipping to resist the tensile force 0 0948� �� 0 2 and in the concrete � ≤ Erection In areas with bonded reinforcement sufficient . ′ to resist the tensile force 0 19� �� in the concrete � In areas with bonded reinforcement sufficient to resist the tensile force ′ in the concrete when 0.24� �� shipping at 6% superelevation, without � impact Compressive All locations ′ 0.65�� Final Tensile Precompressed tensile 0.0 Stresses zone at Service Compressive Effective prestress and . ′ Load permanent loads 0 45�� Effective prestress, ′ permanent loads and 0.60�� transient (live) loads Final Compressive Fatigue I Load Stresses Combination plus one- . ′ at Fatigue half effective prestress 0 40�� Load and permanent loads Variables are as defined in the AASHTO LRFD Bridge Design Specifications. 8 9 6-02.3(25)M Shipping 10 The last four paragraphs are deleted and replaced with the following: 11

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 62 1 Girder lateral stability and stresses during shipping shall be in accordance with Section 2 6-02.3(25)L1. 3 4 If the Contractor elects to assemble spliced prestressed concrete girders into shipping 5 configurations not shown in the Contract documents, the Contractor shall submit a Type 6 2E Working Drawing analyzing girder lateral stability and concrete stresses in accordance 7 with Section 6-02.3(25)L2 before shipping. 8 9 6-02.3(25)N Prestressed Concrete Girder Erection 10 The second sentence of the first paragraph is revised to read: 11 12 The erection plan shall conform to Section 6-02.3(25)L1. 13 14 The last paragraph is revised to read: 15 16 Stop plates and dowel bars for prestressed concrete girders shall be set with either epoxy 17 grout conforming to Section 9-26.3 or type IV epoxy bonding agent conforming to Section 18 9-26.1. 19 20 6-02.3(25)O Girder to Girder Connections 21 The second paragraph is revised to read: 22 23 Prestressed concrete girders shall be constructed in the following sequence: 24 25 1. If required, deflections shall be equalized in accordance with the Contractor’s 26 equalization plan. 27 28 2. Any intermediate diaphragms shall be placed and any weld ties shall be welded 29 in accordance with Section 6-03.3(25). Welding ground shall be attached directly 30 to the steel plates being welded when welding the weld-ties. 31 32 3. Any keyways between adjacent girders shown in the Plans to receive grout shall 33 be filled flush with the surrounding surfaces using a grout conforming to Section 34 9-20.3(2). 35 36 4. Equalization equipment shall not be removed and other construction equipment 37 shall not be placed on the structure until intermediate diaphragms and keyway 38 grout have attained a minimum compressive strength of 2,500 psi. 39 40 6-02.3(26)D2 Test Block Dimensions 41 The first sentence is revised to read: 42 43 The dimensions of the test block perpendicular to the tendon in each direction shall be 44 the smaller of twice the minimum edge distance or the minimum spacing specified by the 45 special anchorage device manufacturer, with the stipulation that the over 46 any confining reinforcing steel or supplementary skin reinforcement shall be appropriate 47 for the project-specific application and circumstances. 48 49 6-02.3(26)E2 Ducts for External Exposed Installation 50 In the first paragraph, “ASTM D3350” is revised to read “ASTM D3035”. 51 52 In the fourth paragraph, "ASTM D3505" is revised to read "ASTM D3035".

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 63 1 2 6-02.3(26)G Tensioning 3 Item number 1 of the second paragraph is revised to read: 4 5 1. All concrete has reached a compressive strength of at least 4,000 psi or the strength 6 specified in the Plans. When tensioning takes place prior to 28-day compressive 7 strength testing on concrete sampled in accordance with Section 6-02.3(25)H, 8 compressive strength shall be verified on field cured cylinders in accordance with the 9 FOP for AASHTO T23. 10 11 6-02.3(27)A Use of Self-Consolidating Concrete for Precast Units 12 Item number 2 of the first paragraph is revised to read: 13 14 2. Precast reinforced concrete three-sided structures, box culverts and split box 15 culverts in accordance with Section 7-02.3(6). 16 17 Section 6-03, Steel Structures 18 January 3, 2017

19 6-03.3(33) Bolted Connections 20 In this section, “AASHTO M253” is revised to read “ASTM F3125 Grade A490”, “ASTM F1852” 21 is revised to read “ASTM F3125 Grade F1852”, and “ASTM A325” is revised to read “ASTM 22 F3125 Grade A325”. 23 24 In the headings of Table 3, “A 325” is revised to read “ASTM F3125 Grade A325”. 25 26 In the headings of Table 3, “M 253” is revised to read “ASTM F3125 Grade A490”. 27 28 Section 6-05, Piling 29 January 2, 2018

30 6-05.3(9)A Pile Driving Equipment Approval 31 The fourth sentence of the second paragraph is revised to read: 32 33 For prestressed concrete piles, the allowable driving stress in kips per square inch shall

34 be 0.095 plus prestress in tension, and 0.85f’c minus prestress in compression, 35 where f’c is the concrete compressive strength in kips per square inch. 𝑐𝑐 36 ∙ �𝑓𝑓′ 37 Section 6-07, Painting 38 August 7, 2017

39 6-07.3(2) Submittals 40 This section is revised to read: 41 42 The Contractor shall submit a painting plan consisting of one comprehensive submittal 43 including all components described in this Section. The Contractor shall submit Type 2 44 Working Drawings of the painting plan components. 45 46 For shop application of paint, the painting plan shall include the documents and samples 47 listed in Sections 6-07.3(2)B, 6-07.3(2)C, and 6-07.3(2)E. 48

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 64 1 For field application of paint, the painting plan shall include the documents and samples 2 listed in Section 6-07.3(2)A through 6-07.3(2)F. 3 4 6-07.3(2)A Work Force Qualifications Submittal Component 5 Item number 2 is revised to read: 6 7 2. Resumé of qualifications and contact information for the Contractor’s on-site 8 supervisors. Each on-site supervisor shall have 3 years’ minimum of industrial 9 painting field experience with 1 year minimum of field supervisory or management 10 experience in bridge painting projects. 11 12 6-07.3(2)D Hazardous Waste Containment, Collection, Testing, and Disposal 13 Submittal Component 14 This section is revised to read: 15 16 The hazardous waste containment, collection, testing, and disposal submittal component 17 of the painting plan shall include the following: 18 19 1. Abrasive blasting containment system attachment and support in accordance 20 with Section 6-07.3(10)A, with a complete description of each attachment 21 device. 22 23 2. Details of jobsite material storage facilities and containment waste storage 24 facilities, including location, security, and environmental control. 25 26 3. Methods and materials used to contain, collect, and dispose of all containment 27 waste and all construction-related waste, including transportation of waste. 28 29 4. Details of the containment waste sampling plan conforming to WAC 173-303 for 30 waste designated as dangerous waste or extremely hazardous waste. 31 32 5. The name of, and contact information for, the accredited analytical laboratory 33 performing the testing of the containment waste samples in accordance with 34 Section 6-07.3(10)F. 35 36 6. Process for tracking the disposal of hazardous waste, including a sample form 37 of the tracking documentation. 38 39 7. When a wind speed threshold is specified, a description of the method to lower 40 or withdraw tarps, plastic exterior, and other containment components 41 presenting an exposed face to wind, and the estimated time required to 42 accomplish this action. 43 44 8. Provisions for dust and debris collection, ventilation, and auxiliary lighting within 45 the containment system. 46 47 6-07.3(2)E Cleaning and Surface Preparation Equipment Submittal Component 48 This section, including title, is revised to read: 49 50 6-07.3(2)E Cleaning and Surface Preparation Submittal Component 51 The cleaning and surface preparation submittal component of the painting plan shall 52 include the following:

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 65 1 2 1. Details of the abrasive blast cleaning operation, including: 3 4 a. Description of the abrasive blast cleaning procedure. 5 6 b. Type, manufacturer, and brand of abrasive blast material and all associated 7 additives, including Materials Safety Data Sheets (MSDS). 8 9 c. Description of the abrasive blast cleaning equipment to be used. 10 11 6-07.3(3)A Quality Control and Quality Assurance for Shop Application of 12 Paint 13 In this section, “approved” is revised to read “accepted”. 14 15 6-07.3(3)B Quality Control and Quality Assurance for Field Application of Paint 16 The first sentence of the first paragraph is revised to read: 17 18 For field application of paint, the Contractor shall conduct quality control inspections as 19 required by SSPC-PA 1, using the personnel and the processes outlined in the painting 20 plan. 21 22 The second paragraph is revised to read: 23 24 A Type 1 Working Drawing consisting of the Contractor’s daily quality control report, 25 signed and dated by the Contractor’s quality control inspector, accompanied by copies of 26 the test results of quality control tests performed on the work covered by the daily quality 27 control report, shall be submitted before the end of the next day’s work shift. 28 29 In the third paragraph, “approval” is revised to read “acceptance”. 30 31 Item number 2 of the fourth paragraph is deleted. 32 33 In the fourth paragraph, items 3, 4 and 5 are renumbered to 2, 3 and 4, respectively. 34 35 6-07.3(9)F Shop Surface Cleaning and Preparation 36 In the first sentence, “approved” is revised to read “accepted”. 37 38 6-07.3(9)G Application of Shop Primer Coat 39 In the first sentence of the first paragraph, “approval” is revised to read “acceptance”. 40 41 The last sentence of the first paragraph is revised to read: 42 43 Primer shall be applied with the spray nozzles and pressures recommended by the 44 manufacturer of the paint system, to attain the film thicknesses specified. 45 46 In the third paragraph, the first sentence is revised to read: 47 48 The Contractor shall provide access to the steel to permit inspection by the Engineer. 49 50 6-07.3(9)I Application of Field Coatings 51 The following new paragraph is inserted before to the first paragraph: 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 66 1 An on-site supervisor shall be present for each work shift at the bridge site. 2 3 In the fourth paragraph (after the preceding Amendment is applied), “approved” is deleted from 4 the first sentence. 5 6 The first sentence of the last paragraph is revised to read: 7 8 All paint damage that occurs shall be repaired in accordance with the manufacturer’s 9 written recommendations. 10 11 6-07.3(10)A Containment 12 The first four paragraphs are deleted and replaced with the following three paragraphs: 13 14 The containment system shall be in accordance with SSPC Technology Guide No. 6, 15 Guide for Containing Surface Preparation Debris Generated During Paint Removal 16 Operations Class 1. The containment system shall fully enclose the steel to be painted 17 and not allow any material to escape the containment system. The Contractor shall 18 protect the surrounding environment from all debris or damage resulting from the 19 Contractor’s operations. 20 21 Except as otherwise specified in the Contract, the containment length shall not exceed 22 the length of a span (defined as pier to pier). The containment system shall not cause any 23 damage to the existing structure. Attachment devices shall not mark or otherwise damage 24 the steel member to which they are attached. Field-welding of attachments to the existing 25 structure will not be allowed. The Contractor shall not drill holes into the existing structure 26 or through existing structural members except as shown in the Contractor’s painting plan 27 Working Drawing submittal. 28 29 Emissions shall be assessed by Visible Emission Observations (Method A) in SSPC 30 Technology Update No. 7 Section 6.2 and shall be limited to the Level A Acceptance 31 Criteria Option Level 0 Emissions standard. If visible emissions occur or if failure to the 32 containment system occurs or if signs of failure to the containment system are present, 33 the Contractor shall stop work immediately. Work shall not resume until the failure has 34 been corrected to the satisfaction of the Engineer. 35 36 6-07.3(10)B Bird Guano, Fungus, and Vegetation Removal 37 The last paragraph is revised to read: 38 39 Bird guano, bird nesting materials, fungus, and vegetative growth shall be disposed of at 40 a land disposal site accepted by the Engineer. The Contractor shall submit a Type 1 41 Working Drawing consisting of a copy of the disposal receipt, which shall include a 42 description of the disposed material. 43 44 6-07.3(10)C Dry Cleaning 45 This section is revised to read: 46 47 Dry cleaning shall include removal of accumulated dirt and debris on the surfaces to be 48 painted. Collected dirt and debris shall be disposed of at a land disposal site accepted by 49 the Engineer. The Contractor shall submit a Type 1 Working Drawing consisting of a copy 50 of the disposal receipt, which shall include a description of the disposed material. 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 67 1 6-07.3(10)D Surface Preparation Prior to Overcoat Painting 2 The second paragraph is revised to read: 3 4 Following any preparation by SSPC-SP1, all steel surfaces to be painted shall be 5 prepared in accordance with SSPC-SP 7, brush-off blast cleaning. Surfaces inaccessible 6 to brush-off blast shall be prepared in accordance with SSPC-SP 15, commercial grade 7 power tool cleaning, as allowed by the Engineer. 8 9 The first sentence of the third paragraph is revised to read: 10 11 Following brush-off blast cleaning, the Contractor shall perform spot abrasive blast 12 cleaning in accordance with SSPC-SP 6, commercial blast cleaning. 13 14 In the fifth sentence of the third paragraph, “approved” is revised to read “accepted”. 15 16 The second sentence of the last paragraph is deleted. 17 18 6-07.3(10)F Collecting, Testing, and Disposal of Containment Waste 19 The third, fourth and fifth paragraphs are deleted and replaced with the following two new 20 paragraphs: 21 22 Containment waste is defined as all paint chips and debris removed from the steel surface 23 and all abrasive blast media, as contained by the containment system. After all waste 24 from the containment system has been collected, the Contractor shall collect 25 representative samples of the components that field screening indicates are lead- 26 contaminated material. The Contractor shall collect at least one representative sample 27 from each container. The Contractor may choose to collect a composite sample of each 28 container, but the composite sample must consist of several collection points (a minimum 29 of 3 random samples) that are representative of the entire contents of the container and 30 representative of the characteristics of the type of waste in the container. In accordance 31 with WAC 173–303-040, a representative sample means “a sample which can be 32 expected to exhibit the average properties of the sample source.” 33 34 The debris shall be tested for metals using the Toxicity Characteristics Leaching 35 Procedure (TCLP) and EPA Methods 1311 and 6010. At a minimum, the materials should 36 be analyzed for the Resource Conservation and Recovery Act (RCRA) 8 Metals (arsenic, 37 barium, cadmium, chromium, lead, mercury, selenium, and silver). Pursuant to the 38 Dangerous Waste (DW) Regulations Chapter 173-303-90(8)(c) WAC, “Any waste that 39 contains contaminants which occur at concentrations at or above the DW threshold must 40 be designated as DW.” All material within each individual container or containment 41 system that designates as DW shall be disposed of at a legally permitted Subtitle C 42 Hazardous Waste Landfill. All material within each individual container or containment 43 system that designate below the DW threshold, will be designated as “Solid Waste” and 44 shall be disposed of at a legally permitted Subtitle D Landfill. Disposal shall be in 45 accordance with WAC 173-303 for waste designated “Dangerous Waste” and pursuant to 46 WAC 173-350 for waste designated as “Solid Waste”. 47 48 The first sentence of the fifth to last paragraph is revised to read: 49 50 The Contractor shall submit a Type 1 Working Drawing consisting of two copies of the 51 transmittal documents or bill of lading listing the waste material shipped from the 52 construction site to the waste disposal site.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 68 1 2 6-07.3(10)G Treatment of Pack Rust and Gaps 3 In this section, “approved by the Engineer” is revised to read “accepted by the Engineer”. 4 5 6-07.3(10)H Paint System 6 In the last paragraph, “approved” is revised to read “allowed”. 7 8 6-07.3(10)I Paint Color 9 In the last sentence, “approved” is revised to read “allowed”. 10 11 6-07.3(10)J Mixing and Thinning Paint 12 In the third paragraph, “approved” is revised to read “allowed”. 13 14 6-07.3(10)O Applying Field Coatings 15 The following new paragraph is inserted before the first paragraph: 16 17 An on-site supervisor shall be present for each work shift at the bridge site. 18 19 In the sixth paragraph (after the preceding Amendment is applied), “approved” and “approval” 20 are revised to read “accepted” and “acceptance”, respectively. 21 22 In the seventh paragraph (after the preceding Amendment is applied), “approval” is revised to 23 read “concurrence”. 24 25 The second sentence of the last paragraph is revised to read: 26 27 Any plank removal or cutting shall be done with the concurrence of the Engineer. 28 29 6-07.3(10)P Field Coating Repair 30 In the second to last sentence, “approved” is revised to read “accepted”. 31 32 The last sentence is deleted. 33 34 6-07.3(11)A Painting of Galvanized Surfaces 35 In the last sentence, “approval” is revised to read “acceptance”. 36 37 6-07.5 Payment 38 The following new paragraph is inserted after the paragraph following the Bid item “Cleaning 39 and Painting - _____”, lump sum: 40 41 When a weather station is specified, all costs in connection with furnishing, installing, 42 operating, and removing the weather station, including furnishing mounting hardware and 43 repeaters, accessories and wireless display console units, processing and submitting 44 daily weather data reports, maintenance and upkeep, shall be included in the lump sum 45 Contract price for “Cleaning And Painting – _____”. 46 47 Section 6-08, Waterproofing 48 January 3, 2017

49 This section and all subsections, including title, is revised to read: 50

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 69 1 6-08 Bituminous Surfacing on Structure Decks 2 6-08.1 Description 3 This Work consists of removing and placing Hot Mix Asphalt (HMA) or Bituminous 4 Surface Treatment (BST) directly on or over a Structure. This Work also includes 5 performing concrete bridge deck repair, applying waterproofing membrane, and 6 sealing paving joints. 7 8 6-08.2 Materials 9 Materials shall meet the requirements of the following sections: 10 11 Bituminous Surface Treatment 5-02.2 12 Hot Mix Asphalt 5-04.2 13 Joint Sealants 9-04.2 14 Closed Cell Foam Backer Rod 9-04.2(3)A 15 Waterproofing Membrane (Deck Seal) 9-11 16 Bridge Deck Repair Material 9-20.5 17 18 6-08.3 Construction Requirements 19 6-08.3(1) Definitions 20 Adjusted Removal Depth – the Bituminous Pavement removal depth specified 21 by the Engineer to supersede the Design Removal Depth after review of the 22 Contractor survey of the existing Bituminous Pavement grade profile. 23 24 Bituminous Pavement – the surfacing material containing an asphalt binder. 25 26 Design Removal Depth – the value shown in the "pavement schedule" or 27 elsewhere in the Plans to indicate the design thickness of Bituminous Pavement 28 to be removed. 29 30 Final Grade Profile – the compacted finished grade surface of completed 31 Bituminous Pavement surfacing consisting of a vertical profile and 32 superelevation cross-slope, developed by the Engineer for Grade Controlled 33 Structure Decks based on the Contractor survey. 34 35 Grade Controlled – a Structure Deck requiring restriction of Bituminous 36 Pavement work, including restriction of pavement removal methods and 37 restriction of overlay pavement thicknesses. 38 39 Structure Deck – the bridge deck (concrete or timber), bridge approach slab, 40 top of concrete box culvert, or other concrete surfaces over or upon which 41 existing Bituminous Pavement is removed and new Bituminous Pavement is 42 applied. 43 44 6-08.3(2) Contractor Survey for Grade Controlled Structure Decks 45 Prior to removing existing Bituminous Pavement from a Grade Controlled 46 Structure Deck, the Contractor shall complete a survey of the existing surface 47 for use in establishing the existing cross section and grade profile elevations. 48 When removal of Bituminous Pavement is to be achieved by rotary 49 milling/planing, the Contractor’s survey shall also include the depths of the 50 existing surfacing at each survey point. 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 70 1 The Contractor is responsible for all calculations, surveying, installation of 2 control points, and measuring required for setting, maintaining and resetting 3 equipment and materials necessary for the construction of the overlay to the 4 Final Grade Profile. 5 6 6-08.3(2)A Survey Requirements 7 The Contractor shall establish at least two primary survey control points for 8 controlling actual Bituminous Pavement removal depth and the Final Grade 9 Profile. Horizontal control shall be by station and offset which shall be tied 10 to either the Roadway centerline or the Structure centerline. Vertical control 11 may be an assumed datum established by the Contractor. 12 13 Primary control points shall be described by station or milepost and offset 14 on the baseline selected by the Contractor. The Contractor may expand the 15 survey control information to include secondary horizontal and vertical 16 control points as needed for the project. 17 18 Survey information collected shall include station or milepost, offset, and 19 elevation for each lane line and curb line. Survey information shall be 20 collected at even 20 foot station intervals, and along the centerline of each 21 bridge expansion joint. The survey shall extend 300’-0” beyond the bridge 22 back of pavement seat or end of Structure Deck. The survey information 23 shall include the top of Bituminous Pavement elevation and, when rotary 24 milling/planing equipment is used, the corresponding depth of Bituminous 25 Pavement to the Structure Deck. The Contractor shall ensure a surveying 26 accuracy to within ± 0.01 feet for vertical control and ± 0.2 feet for horizontal 27 control. 28 29 Voids in HMA created by the Contractor’s Bituminous Pavement depth 30 measurements shall be filled by material conforming to Section 9-20 or 31 another material acceptable to the Engineer. 32 33 6-08.3(2)B Survey Submittal 34 The Contractor's survey records shall include descriptions of all survey 35 control points including station/milepost, offset, and elevations of all 36 secondary control points. The Contractor shall maintain survey records of 37 sufficient detail to allow the survey to be reproduced. The Contractor shall 38 submit a Type 2 Working Drawing consisting of the compiled survey records 39 and information. Survey data shall be submitted as an electronic file in 40 Microsoft Excel format. 41 42 6-08.3(2)C Final Grade Profile and Adjusted Removal Depth 43 Based on the results of the survey, the Engineer may develop a Final Grade 44 Profile and Adjusted Removal Depth. If they are developed, the Final Grade 45 Profile and Adjusted Removal Depth will be provided to the Contractor 46 within three working days after receiving the Contractor's survey 47 information. When provided, the Adjusted Removal Depth supersedes the 48 Design Removal Depth to become the Bituminous Pavement removal depth 49 for that Structure Deck. 50

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 71 1 6-08.3(3) General Bituminous Pavement Removal Requirements 2 The Contractor shall remove Bituminous Pavement and associated deck repair 3 material from Structure Decks to the horizontal limits shown in the Plans and to 4 either the specified or adjusted Bituminous Pavement removal depth as 5 applicable. 6 7 Removal of Bituminous Pavement within 12-inches of existing permanent 8 features that limit the reach of the machine or the edge of the following items 9 shall be by hand or by hand operated (nominal 30-pounds class) power tools: 10 existing bridge expansion joint headers; steel expansion joint assemblies; 11 concrete butt joints between back of pavement seats and bridge approach slabs, 12 bridge drain assemblies; thrie beam post steel anchorage assemblies fastened 13 to the side or top of the Structure Deck. 14 15 When removing Bituminous Pavement with a planer, Section 5-04.3(14) shall 16 apply. If the planer contacts the Structure Deck in excess of the specified planing 17 depth tolerance, or contacts steel reinforcing bars at any time, the Contractor 18 shall immediately cease planing operations and notify the Engineer. Planing 19 operations shall not resume until completion of the appropriate adjustments to 20 the planing machine and receiving the Engineer’s concurrence to resume. 21 22 6-08.3(4) Partial Depth Removal of Bituminous Pavement from Structure 23 Decks 24 The depth of surfacing removal, as measured to the bottom of the lowest milling 25 groove generated by the rotary milling/planing machine shall be +0.01, -0.02- 26 feet of the specified or Adjusted Removal Depth as applicable. 27 28 6-08.3(5) Full Depth Removal of Bituminous Pavement from Structure 29 Decks 30 6-08.3(5)A Method of Removal 31 The Contractor shall perform full depth removal by a method that does not 32 damage or remove the Structure Deck in excess of the specified Bituminous 33 Pavement removal tolerance. The Contractor shall submit a Type 2 34 Working Drawing consisting of the proposed methods and equipment to be 35 used for full depth removal. 36 37 6-08.3(5)B Planer Requirements for Full Depth Removal 38 The final planed surface shall have a finished surface with a tolerance of 39 +0.01, -0.02 feet within the planed surface profile, as measured from a 10- 40 foot straight edge. Multiple passes of planing to achieve smoothness will 41 not be allowed. 42 43 In addition to Section 6-08.3(3), the planing equipment shall conform to the 44 following additional requirements: 45 46 1. The cutting tooth spacing on the rotary milling head shall be less 47 than or equal to ¼ inch. 48 49 2. The rotary milling/planing machine shall have cutting teeth that 50 leave a uniform plane surface at all times. All teeth on the mill 3 51 head shall be kept at a maximum differential tolerance of ⁄8-inch

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 72 1 between the shortest and longest tooth, as measured by a straight 2 edge placed the full width of the rotary milling head. 3 4 3. Cutting tips shall be replaced when 30 percent of the total length 5 of the cutting tip material remains. 6 7 Prior to each day’s Bituminous Pavement removal operations, the 8 Contractor shall confirm to the satisfaction of the Engineer that the rotary 9 head cutting teeth are within the specified tolerances. 10 11 6-08.3(5)C Structure Deck Cleanup after Bituminous Pavement 12 Removal 13 Waterproofing membrane that is loose or otherwise not firmly bonded to the 14 Structure Deck shall be removed as an incidental component of the Work 15 of surfacing removal. Existing waterproofing membrane bonded to the 16 Structure Deck need not be removed. 17 18 6-08.3(6) Repair of Damage due to Bituminous Pavement Removal 19 Operations 20 All concrete bridge deck, pavement seat, and steel reinforcing bar damage due 21 to the Contractor’s surfacing removal operations shall be repaired by the 22 Contractor in accordance with Section 1-07.13, and as specified below. 23 24 Damaged concrete in excess of the specified Bituminous Pavement removal 25 tolerance shall be repaired in accordance with Section 6-08.3(7), with the bridge 26 deck repair material placed to the level of the surrounding bridge deck and 27 parallel to the final grade paving profile. 28 29 Damaged steel reinforcing bar shall be repaired as follows: 30 31 1. Damage to steel reinforcing bar resulting in a section loss less than 20- 32 percent of the bar with no damage to the surrounding concrete shall be 33 left in place and shall be repaired by removing the concrete to a depth 34 ¾-inches around the top steel reinforcing bar and placing bridge deck 35 repair material accepted by the Engineer to the level of the bridge deck 36 and parallel to the final grade paving profile. 37 38 2. Damage to steel reinforcing bar resulting in a section loss of 20-percent 39 or more in one location, bars partially or completely removed from the 40 bridge deck, or where there is a lack of bond to the concrete, shall be 41 repaired by removing the adjacent concrete and splicing a new bar of 42 the same size. Concrete shall be removed to provide a ¾-inch 43 minimum clearance around the bars. The splice bars shall extend a 44 minimum of 40 bar diameters beyond each end of the damage. 45 46 6-08.3(7) Concrete Deck Repair 47 This Work consists of repairing the concrete deck after Bituminous Pavement 48 has been removed. 49 50 6-08.3(7)A Concrete Deck Preparation 51 The Contractor, with the Engineer, shall inspect the exposed concrete deck 52 to establish the extent of bridge deck repair in accordance with Section 6-

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 73 1 09.3(6), except item 4 in Section 6-09.3(6) does not apply. Areas of 2 Structure Deck left with existing well bonded waterproof membrane after full 3 depth Bituminous Pavement removal are exempt from this inspection 4 requirement. 5 6 All loose and unsound concrete within the repair area shall be removed with 7 jackhammers or chipping hammers no more forceful than the nominal 30 8 pounds class, or other mechanical means acceptable to the Engineer, and 9 operated at angles less than 45 degrees as measured from the surface of 10 the deck to the tool. If unsound concrete exists around the existing steel 11 reinforcing bars, or if the bond between concrete and steel reinforcing bar 12 is broken, the Contractor shall remove the concrete to provide a ¾ inch 13 minimum clearance to the bar. The Contractor shall take care to prevent 14 damage to the existing steel reinforcing bars and concrete to remain. 15 16 After removing sufficient concrete to establish the limits of the repair area, 17 the Contractor shall make ¾ inch deep vertical saw cuts and maintain 18 square edges at the boundaries of the repair area. The exposed steel 19 reinforcing bars and concrete in the repair area shall be abrasive blasted 20 and blown clean just prior to placing the bridge deck repair material. 21 22 6-08.3(7)B Ultra-Low Viscosity, Two-Part Liquid, Polyurethane-Hybrid 23 24 The ultra-low viscosity, two-part liquid, polyurethane-hybrid polymer 25 concrete shall be mixed in accordance with the manufacturer’s 26 recommendations. 27 28 Aggregate shall conform to the gradation limit requirements recommended 29 by the manufacturer. The aggregate and the ultra-low viscosity, two-part 30 liquid, polyurethane-hybrid polymer concrete shall be applied to the repair 31 areas in accordance with the sequence and procedure recommended by 32 the manufacturer. 33 34 All repairs shall be float finished flush with the surrounding surface within a 1 35 tolerance of ⁄8 inch of a straight edge placed across the full width and 36 breadth of the repair area. 37 38 6-08.3(7)C Pre-Packaged Cement Based Repair Mortar 39 The Contractor shall mix the pre-packaged cement based repair mortar 40 using equipment, materials and proportions, batch sizes, and process as 41 recommended by the manufacturer. 42 43 All repairs shall be float finished flush with the surrounding surface within a 1 44 tolerance of ⁄8 inch of a straight edge placed across the full width and 45 breadth of the repair area. 46 47 6-08.3(7)D Cure 48 All bridge deck repair areas shall be cured in accordance with the 49 manufacturer's recommendations and attain a minimum compressive 50 strength of 2,500 psi before allowing vehicular and foot traffic on the repair 51 and placing waterproofing membrane on the bridge deck over the repair. 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 74 1 6-08.3(8) Waterproof Membrane for Structure Decks 2 This work consists of furnishing and placing a waterproof sheet membrane 3 system over a prepared Structure Deck prior to placing an HMA overlay. The 4 waterproof membrane system shall consist of a sheet membrane adhered to the 5 Structure Deck with a primer. 6 7 The Contractor shall comply with all membrane manufacturer’s installation 8 recommendations. 9 10 6-08.3(8)A Structure Deck Preparation 11 The Structure Deck and ambient air temperatures shall be above 50°F and 12 the Structure Deck shall be surface-dry at the time of the application of the 13 primer and membrane. 14 15 All areas of a Structure Deck that have fresh cast bridge deck concrete less 16 than 28 days old (not including bridge deck repair concrete placed in 17 accordance with Section 6-08.3(7)) shall cure for a period of time 18 recommended by the membrane manufacturer, or as specified by the 19 Engineer, before application of the membrane. 20 21 The entire Structure Deck and the sides of the curb and expansion joint 22 headers to the height of the HMA overlay shall be free of all foreign material 23 such as dirt, grease, etc. Prior to applying the primer or sheet membrane, 24 all dust and loose material shall be removed from the Structure Deck with 25 compressed air. All surface defects such as spalled areas, cracks, 26 protrusions, holes, sharp edges, ridges, etc., and other surface 27 imperfections greater than ¼ inch in width shall be corrected prior to 28 application of the membrane. 29 30 6-08.3(8)B Applying Primer 31 The primer shall be applied to the cleaned deck surfaces at the rate 32 according to the procedure recommended by the membrane manufacturer. 33 All surfaces to be covered by the membrane shall be thoroughly and 34 uniformly coated with primer. Structure Deck areas left with existing well 35 bonded waterproof membrane after bituminous surfacing removal shall 36 receive an application of primer in accordance with the membrane 37 manufacturer’s recommendations. Precautionary measures shall be taken 38 to ensure that pools and thick layers of primer are not left on the deck 39 surface. The membrane shall not be applied until the primer has cured or 40 volatile material has substantially dissipated, in accordance with the 41 membrane manufacturer’s recommendations. 42 43 The primer and waterproof membrane shall extend from the bridge deck up 44 onto the curb face and expansion joint header face the thickness of the HMA 45 overlay. The membrane shall adhere to the vertical surface. 46 47 6-08.3(8)C Placing Waterproof Membrane 48 Membrane application shall begin at the low point on the deck, and continue 49 in a lapped shingle pattern. The overlap shall be a minimum of six inches 50 or greater if recommended by the membrane manufacturer. Membrane 51 seams shall be sealed as recommended by the membrane manufacturer.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 75 1 Hand rollers or similar tools shall be used on the applied membrane to 2 assure firm and uniform contact with the primed Structure surfaces. 3 4 The fabric shall be neatly cut and contoured at all expansion joints and 5 drains. The cuts at bridge drains shall be two right angle cuts made to the 6 inside diameter of the bridge deck drain outlet, after which the corners of 7 the waterproof membrane shall be turned down into the drains and laid in a 8 coating of primer. 9 10 6-08.3(8)D Membrane Repair and Protection 11 The waterproof membrane will be visually inspected by the Engineer for 12 uniformity, tears, punctures, bonding, bubbles, wrinkles, voids and other 13 defects. All such deficiencies shall be repaired in accordance with the 14 membrane manufacturer’s recommendations prior to placement of the HMA 15 overlay. 16 17 The membrane material shall be protected from damage due to the paving 18 operations in accordance with the membrane manufacturer’s 19 recommendations. No traffic or equipment except that required for the 20 actual waterproofing and paving operations will be permitted to travel or rest 21 on the membrane until it is covered by the HMA overlay. The use of 22 windrows is not allowed for laydown of HMA on a membrane. 23 24 Where waterproofing membrane is placed in stages or applied at different 25 times, a strip of temporary paper shall be used to protect the membrane 26 overlap from the HMA hand removal methods. 27 28 6-08.3(9) Placing Bituminous Pavement on Structure Decks 29 HMA overlay shall be applied on Grade Controlled Structure Decks using 30 reference lines for vertical control in accordance with Section 5-04.3(3)C. 31 32 The compacted elevation of the HMA overlay on Structure Decks shall be within 33 ± 0.02 feet of the specified overlay thickness or Final Grade Profile as applicable. 34 Deviations from the final grade paving profile in excess of the specified tolerance 35 and areas of non-conforming surface smoothness shall be corrected in 36 accordance with Section 5-04.3(13). 37 38 Final grade Roadway transitions to a Structure Deck with Bituminous Pavement 39 shall not exceed a 0.20 percent change in grade in accordance with the bridge 40 deck transition for HMA overlay Standard Plan, unless shown otherwise in the 41 Plans. 42 43 Final grade compacted HMA elevations shall be higher than an adjacent 1 44 concrete edge by ¼ inch ± ⁄8 inch at all expansion joint headers and concrete 45 butt joints as shown in the concrete to asphalt butt joint details of the bridge 46 paving joint seals Standard Plan. This also applies to steel edges within the limits 47 of the overlay such as bridge drain frames and steel joint riser bars at bridge 48 expansion joints. 49 50 6-08.3(9)A Protection of Structure Attachments and Embedments 51 The Contractor is responsible for protecting all Structure attachments and 52 embedments from the application of BST and HMA.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 76 1 2 Drainage inlets that are to remain open, and expansion joints, shall be 3 cleaned out immediately after paving is completed. Materials passing 4 through expansion joints shall be removed from the bridge within 10 working 5 days. 6 7 All costs incurred by the Contractor in protective measures and clean up 8 shall be included in the unit Contract prices for the associated Bid items of 9 Work. 10 11 6-08.3(10) HMA Compaction on Structure Decks 12 Compaction of HMA on Structure Decks shall be in accordance with Section 5- 13 04.3(10). 14 15 Work rejected in accordance with Section 5-04.3(11) shall include the materials, 16 work, and incidentals to repair an existing waterproof membrane damaged by 17 the removal of the rejected work. 18 19 6-08.3(11) Paved Panel Joint Seals and HMA Sawcut and Seal 20 Bridge paving joint seals shall be installed in accordance with Section 5- 21 04.3(12)B and the details shown in the Plans and Standard Plans. 22 23 When concrete joints are exposed after removal of Bituminous Pavement, the 24 joints shall be cleaned and sealed in accordance with Section 5-01.3(8) and the 25 paved panel joint seal details of the bridge paving joint seals Standard Plan, 26 including placement of the closed cell backer rod at the base of the cleaned joint. 27 If waterproofing membrane is required, the membrane shall be slack or folded 28 at the concrete joint to allow for Structure movements without stress to the 29 membrane. After placement of the HMA overlay, the second phase of the paved 30 panel joint seal shall be completed by sawing the HMA and sealing the sawn 31 joint in accordance with Section 5-04.3(12)B2. 32 33 6-08.4 Measurement 34 Removing existing Bituminous Pavement from Structure Decks will be measured by 35 the square yard of Structure Deck surface area with removed overlay. 36 37 Bridge deck repair will be measured by the square foot surface area of deck concrete 38 removed with the measurement taken at the plane of the top mat of steel reinforcing 39 bars. 40 41 Waterproof membrane will be measured by the square yard surface area of Structure 42 Deck and curb and header surface area covered by membrane. 43 44 6-08.5 Payment 45 Payment will be made for each of the following Bid items when they are included in 46 the Proposal: 47 48 “Structure Surveying”, lump sum. 49 50 “Removing Existing Overlay From Bridge Deck___”, per square yard. 51 The unit Contract price per square yard for "Removing Existing Overlay From 52 Bridge Deck___”, shall be full pay for performing the Work as specified for full

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 77 1 removal of Bituminous Pavement on Structure Decks, including the removal of 2 existing waterproof membrane and disposing of materials. 3 4 “Bridge Deck Repair Br. No.___”, per square foot. 5 The unit Contract price per square foot for "Bridge Deck Repair Br. No.___" shall 6 be full pay for performing the Work as specified, including removing and 7 disposing of the concrete within the repair area and furnishing, placing, finishing, 8 and curing the repair concrete. 9 10 “Waterproof Membrane Br. No.___”, per square yard. 11 The unit Contract price per square yard for "Waterproof Membrane Br. No.___" 12 shall be full pay for performing the Work as specified, including repairing any 13 damaged or defective waterproofing membrane and repair of damaged HMA 14 overlay. 15 16 Section 6-09, Modified Concrete Overlays 17 April 4, 2016

18 6-09.3(8)A Quality Assurance for Microsilica Modified and Modified 19 Concrete Overlays 20 The first sentence of the first paragraph is revised to read the following two new sentences: 21 22 The Engineer will perform slump, temperature, and entrained air tests for acceptance in 23 accordance with Section 6-02.3(5)D and as specified in this Section after the Contractor 24 has turned over the concrete for acceptance testing. Concrete samples for testing shall 25 be supplied to the Engineer in accordance with Section 6-02.3(5)E. 26 27 The last paragraph is deleted. 28 29 6-09.3(8)B Quality Assurance for Latex Modified Concrete Overlays 30 The first two paragraphs are deleted and replaced with the following: 31 32 The Engineer will perform slump, temperature, and entrained air tests for acceptance in 33 accordance with Section 6-02.3(5)D and as specified in this Section after the Contractor 34 has turned over the concrete for acceptance testing. The Engineer will perform testing as 35 the concrete is being placed. Samples shall be taken on the first charge through each 36 mobile mixer and every other charge thereafter. The sample shall be taken after the first 37 2 minutes of continuous mixer operation. Concrete samples for testing shall be supplied 38 to the Engineer in accordance with Section 6-02.3(5)E. 39 40 The second to last sentence of the last paragraph is revised to read: 41 42 Recommendations made by the technical representative on or off the jobsite shall be 43 adhered to by the Contractor. 44 45 Section 6-10, Concrete Barrier 46 August 6, 2018

47 6-10.2 Materials 48 In the first paragraph, the reference to “Portland Cement” is revised to read: 49 50 Cement 9-01

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 78 1 2 6-10.3(6) Placing Concrete Barrier 3 The first two sentences of the first paragraph are revised to read: 4 5 barriers Type 2, Type 4, Type F, precast single slope barrier, and 6 transitions shall rest on a paved foundation shaped to a uniform grade and section. The 7 foundation surface for precast concrete barriers Type 2, Type 4, Type F, precast single 8 slope barrier, and transitions shall meet this test for uniformity: When a 10-foot 9 straightedge is placed on the surface parallel to the centerline for the barrier, the surface 10 shall not vary more than ¼ inch from the lower edge of the straightedge. 11 12 Section 6-11, Reinforced Concrete Walls 13 April 2, 2018

14 6-11.2 Materials 15 In the first paragraph, the reference to “Aggregates for Portland Cement Concrete” is revised 16 to read: 17 18 Aggregates for Concrete 9-03.1 19 20 Section 6-12, Noise Barrier Walls 21 August 6, 2018

22 6-12.2 Materials 23 In the first paragraph, the reference to “Aggregates for Portland Cement Concrete” is revised 24 to read: 25 26 Aggregates for Concrete 9-03.1 27 28 The first paragraph is supplemented with the following new material reference: 29 30 Noise Barrier Wall Access Door 9-06.17 31 32 6-12.3(9) Access Doors and Concrete Landing Pads 33 The second paragraph is deleted and replaced with the following: 34 35 All frame and door surfaces, except stainless steel surfaces, shall be painted in 36 accordance with Section 6-07.3(9). Primer shall be applied to all non-stainless steel 37 surfaces. All primer coated exposed metal surfaces shall be field painted with the 38 remaining Section 6-07.3(9)A paint system coats. The top coat, when dry, shall match the 39 color specified in the Plans or Special Provisions. 40 41 This section is supplemented with the following: 42 43 Access door deadbolt locks shall be capable of accepting a Best CX series core. The 44 Contractor shall furnish and install a spring-loaded construction core lock with each lock. 45 The Engineer will furnish the permanent Best CX series core for the Contractor to install 46 at the conclusion of the project. 47

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 79 1 Section 6-13, Structural Earth Walls 2 August 6, 2018

3 6-13.2 Materials 4 In the first paragraph, the reference to “Aggregates for Portland Cement Concrete” is revised 5 to read: 6 7 Aggregates for Concrete 9-03.1 8 9 6-13.3(4) Precast Concrete Facing Panel and Concrete Block Fabrication 10 Item number 1 of the sixth paragraph is revised to read: 11 1 12 1. Vertical dimensions shall be ± ⁄16 inch of the Plan dimension, and the rear height 13 shall not exceed the front height. 14 15 Item number 3 of the sixth paragraph is revised to read: 16 17 3. All other dimensions shall be ± ¼ inch of the Plan dimension. 18 19 Section 6-14, Geosynthetic Retaining Walls 20 April 2, 2018

21 6-14.2 Materials 22 In the first paragraph, the references to “Portland Cement” and “Aggregates for Portland 23 Cement Concrete” are revised to read: 24 25 Cement 9-01 26 Aggregates for Concrete 9-03.1 27 28 Section 6-15, Soil Nail Walls 29 January 15, 2015

30 6-15.3(3) Submittals 31 The first paragraph (excluding the numbered list) is revised to read: 32 33 The Contractor shall submit Type 2 Working Drawings of the following information: 34 35 6-15.3(6) Soil Nailing 36 In the first paragraph, the last sentence is revised to read: 37 38 Damaged or defective encapsulation shall be repaired in accordance with the 39 manufacturer’s recommendations. 40 41 The eighth paragraph is revised to read: 42 43 If sections of the wall are constructed at different times than the adjacent soil nail sections, 44 the Contractor shall use stabilizing berms, temporary slopes, or other measures 45 acceptable to the Engineer, to prevent sloughing or failure of the adjacent soil nail 46 sections. 47

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 80 1 6-15.3(8) Soil Nail Testing and Acceptance 2 In the first paragraph, the second sentence is revised to read: 3 4 The Contractor shall submit Type 1 Working Drawings of all test data. 5 6 The last sentence of the seventh paragraph is revised to read: 7 8 The Contractor shall submit Type 2E Working Drawings of the reaction frame. 9 10 6-15.3(8)A Verification Testing 11 In the third paragraph, the first sentence is revised to read: 12 13 The Contractor shall submit Type 2E Working Drawings consisting of design details of the 14 verification testing, including the system for distributing test load pressures to the 15 excavation surface and appropriate nail bar size and reaction plate. 16 17 Section 6-16, Soldier Pile and Soldier Pile Tieback Walls 18 April 2, 2018

19 6-16.2 Materials 20 In the first paragraph, the reference to “Aggregates for Portland Cement Concrete” is revised 21 to read: 22 23 Aggregates for Concrete 9-03.1 24 25 Section 6-18, Shotcrete Facing 26 January 2, 2018

27 6-18.3(3) Testing 28 In the last sentence of the first paragraph, “AASHTO T 24” is revised to read “ASTM C1604”. 29 30 6-18.3(3)B Production Testing 31 In the last sentence, “AASHTO T 24” is revised to read “ASTM C1604”. 32 33 6-18.3(4) Qualifications of Contractor’s Personnel 34 In the last sentence of the second paragraph, “AASHTO T 24” is revised to read “ASTM 35 C1604”. 36 37 Section 6-19, Shafts 38 January 3, 2017

39 6-19.3 Construction Requirements 40 This section is supplemented with the following new subsection: 41 42 6-19.3(10) Engineer’s Final Acceptance of Shafts 43 The Engineer will determine final acceptance of each shaft, based on the nondestructive 44 QA test results and analysis for the tested shafts, and will provide a response to the 45 Contractor within 3 working days after receiving the test results and analysis submittal. 46 47 6-19.3(1)B Nondestructive Testing of Shafts 48 This section’s content is deleted and replaced with the following new subsections:

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 81 1 2 6-19.3(1)B1 Nondestructive Quality Assurance (QA) Testing of Shafts 3 Unless otherwise specified in the Special Provisions, the Contractor shall perform 4 nondestructive QA testing of shafts, except for those constructed completely in the dry. 5 Either crosshole sonic log (CSL) testing in accordance with ASTM D 6760 or thermal 6 integrity profiling (TIP) testing in accordance with ASTM D 7949 shall be used. 7 8 6-19.3(1)B2 Nondestructive Quality Verification (QV) Testing of Shafts 9 The Contracting Agency may perform QV nondestructive testing of shafts that have been 10 QA tested by the Contractor. The Contracting Agency may test up to ten percent of the 11 shafts. The Engineer will identify the shafts selected for QV testing and the testing 12 method the Contracting Agency will use. 13 14 The Contractor shall accommodate the Contracting Agency’s nondestructive testing. 15 16 6-19.3(2) Shaft Construction Submittal 17 This section is revised to read: 18 19 The shaft construction submittal shall be comprised of the following four components: 20 construction experience; shaft installation narrative; shaft slurry technical assistance; and 21 nondestructive QA testing personnel. The submittals shall be Type 2 Working Drawings, 22 except the shaft slurry technical assistance and nondestructive QA testing personnel 23 submittals shall be Type 1. 24 25 This section is supplemented with the following new subsection: 26 27 6-19.3(2)D Nondestructive QA Testing Organization and Personnel 28 The Contractor shall submit the names of the testing organizations, and the names of the 29 personnel who will conduct nondestructive QA testing of shafts. The submittal shall 30 include documentation that the qualifications specified below are satisfied. For TIP 31 testing, the testing organization is the group that performs the data analysis and produces 32 the final report. The testing organizations and the testing personnel shall meet the 33 following minimum qualifications: 34 35 1. The testing organization shall have performed nondestructive tests on a 36 minimum of three deep foundation projects in the last two years. 37 38 2. Personnel conducting the tests for the testing organization shall have a minimum 39 of one year experience in nondestructive testing and interpretation. 40 41 3. The experience requirements for the organization and personnel shall be 42 consistent with the testing methods the Contractor has selected for 43 nondestructive testing of shafts. 44 45 4. Personnel preparing test reports shall be a Professional Engineers, licensed 46 under Title 18 RCW, State of Washington, and in accordance with WAC 196-23- 47 020. 48 49 6-19.3(3) Shaft Excavation 50 The second paragraph is revised to read: 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 82 1 Shaft excavation shall not be started until the Contractor has received the Engineer’s 2 acceptance for the reinforcing steel centralizers required when the casing is to be pulled 3 during concrete placement. 4 5 This section is supplemented with the following: 6 7 Except as otherwise noted, the Contractor shall not commence subsequent shaft 8 excavations until receiving the Engineer’s acceptance of the first shaft, based on the 9 results and analysis of the nondestructive testing for the first shaft. The Contractor may 10 commence subsequent shaft excavations prior to receiving the Engineer’s acceptance of 11 the first shaft, provided the following condition is satisfied: 12 13 The Engineer permits continuing with shaft construction based on the Engineer’s 14 observations of the construction of the first shaft, including, but not limited to, 15 conformance to the shaft installation narrative in accordance with Section 6-19.3(2)B, 16 and the Engineer’s review of Contractor’s daily reports and Inspector’s daily logs 17 concerning excavation, steel reinforcing bar placement, and concrete placement. 18 19 6-19.3(5)B Steel Reinforcing Bar Cage Centralizers 20 This section is supplemented with the following new sentence: 21 22 The Contractor shall furnish and install additional centralizers as required to maintain the 23 specified concrete cover throughout the length of the shaft. 24 25 6-19.3(5)C Concrete Cover Over Steel Reinforcing Bars 26 In the table, the second column (including heading) is revised to read: 27 Minimum Concrete Cover, and Concrete Cover Tolerance, Except at Permanent Slip Casing (Inches) 3, -1½ 4, -2 4, -2 6, -3 28 29 The following new paragraph is inserted after the table: 30 31 The concrete cover tolerances specified above apply to the concrete cover specified in 32 the Plans, even if it exceeds the minimum concrete cover. 33 34 6-19.3(6) Access Tubes for Crosshole Sonic Log (CSL) Testing 35 This section title is revised to read: 36 37 6-19.3(6) Contractor Furnished Accessories for Nondestructive QA Testing 38 39 This section is supplemented with the following three new subsections: 40 41 6-19.3(6)D Shafts Requiring Thermal Wire 42 The Contractor shall furnish and install thermal wire in all shafts receiving the thermal wire 43 method of TIP testing, except as otherwise noted in Section 6-19.3(1)B1. 44

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 83 1 6-19.3(6)E Thermal Wire and Thermal Access Points (TAPs) 2 The thermal wire and associated couplers shall be obtained from the source specified in 3 the Special Provisions. 4 5 The Contractor shall securely attach the thermal wire to the interior of the reinforcement 6 cage of the shaft in conformance with the supplier’s instructions. At a minimum, one 7 thermal wire shall be furnished and installed for each foot of shaft diameter, rounded to 8 the nearest whole number, as shown in the Plans. The number of thermal wires for shaft 9 diameters specified as "X feet 6 inches" shall be rounded up to the next higher whole 10 number. The thermal wires shall be placed around the shaft, inside the spiral or hoop 11 reinforcement, and tied to the vertical reinforcement with plastic "zip" ties at a maximum 12 spacing of 2-feet. Steel tie wire shall not be used. 13 14 The thermal wire shall be installed in straight alignment and taut, but with enough slack 15 to not be damaged during reinforcing cage lofting. The wires shall be as near to parallel 16 to the vertical axis of the reinforcement cage as possible. The thermal wire shall extend 17 from the bottom of the reinforcement cage to the top of the shaft, with 15-feet of slack 18 wire provided above the top of shaft. Care shall be taken to prevent damaging the thermal 19 wires during reinforcement cage installation and concrete placement operations in the 20 shaft excavation. 21 22 After completing shaft reinforcement cage fabrication at the site and prior to installation 23 of the cage into the shaft excavation, the Contractor shall install and connect thermal 24 access points (TAPs) to the thermal wires. The TAPs shall record data for at least one 25 hour after the cage is placed in the excavation to measure the slurry temperature and 26 enable the steel and slurry temperatures to equilibrate prior to placing concrete in the 27 shaft. The TAPs shall record and store data every 15 minutes. The TAPs shall remain 28 active for a minimum of 36 hours. 29 30 Prior to beginning concrete placement the TAPs shall be checked to ensure they are 31 recording data and that the wires have not been damaged. If a TAP unit is not functioning 32 due to a damaged wire, the Contractor shall repair or replace the wire. If a TAP unit fails 33 or a wire breaks after concrete placement has started, the Contractor shall not stop the 34 concrete placement operation to repair the wire. 35 36 6-19.3(6)F Use of Access Tubes for TIP Testing Under the Thermal Probe 37 Method 38 The Contractor may use access tubes for TIP testing under the thermal probe method. 39 Access tubes shall be cared for in accordance with Section 6-19.3(6)C. Prior to TIP testing 40 under the thermal probe method, the water in each tube shall be removed, collected, and 41 stored in an insulated container. The access tube shall be blown dry and swabbed to 42 remove residual water. After TIP testing, the collected and stored tube water shall be 43 introduced back into the access tube. New potable water may be used, provided the water 44 temperature is not more than 10°F cooler than the average concrete temperature 45 measured by the probe. 46 47 6-19.3(6)A Shafts Requiring CSL Access Tubes 48 This section, including title, is revised to read: 49

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 84 1 6-19.3(6)A Shafts Requiring Access Tubes 2 The Contractor shall furnish and install access tubes in all shafts receiving CSL testing or 3 the thermal probe method of TIP testing, except as otherwise noted in Section 6- 4 19.3(1)B1. 5 6 6-19.3(6)B Orientation and Assembly of the CSL Access Tubes 7 This section’s title is revised to read: 8 9 6-19.3(6)B Orientation and Assembly of the Access Tubes 10 11 6-19.3(6)C Care for CSL Access Tubes from Erection through CSL Testing 12 This section’s title is revised to read: 13 14 6-19.3(6)C Care for Access Tubes from Erection Through Nondestructive 15 QA Testing 16 17 The second sentence is revised to read: 18 19 The Contractor shall keep all of a shaft’s access tubes full of water through the completion 20 of nondestructive QA testing of that shaft. 21 22 6-19.3(7)A Concrete Class for Shaft Concrete 23 This section is revised to read: 24 25 Shaft concrete shall be Class 5000P conforming to Section 6-02. 26 27 6-19.3(7)B Concrete Placement Requirements 28 The last sentence of the last paragraph is revised to read: 29 30 The Section 6-02.3(6) restriction for 5 feet maximum free fall shall not apply to placement 31 of concrete into a shaft. 32 33 6-19.3(7)I Requirements for Placing Concrete Above the Top of Shaft 34 This section is revised to read: 35 36 Concrete shall not be placed above the top of shaft (for column splice zones, columns, 37 footings, or shaft caps) until the Contractor receives the Engineer’s acceptance of 38 nondestructive QA testing, if performed at that shaft, and acceptance of the shaft. 39 40 6-19.3(9) Nondestructive Testing of Shafts (Crosshole Sonic Log (CSL) 41 Testing) 42 This section, including title, is revised to read: 43 44 6-19.3(9) Nondestructive QA Testing of Shafts 45 The Contractor shall provide nondestructive QA testing and analysis on all shafts with 46 access tubes or thermal wires and TAPs facilitating the testing (See Section 6-19.3(1)B). 47 The testing and analysis shall be performed by the testing organizations identified by the 48 Contractor’s submittal in accordance with Section 6-19.3(2)D. 49 50 The Engineer may direct that additional testing be performed at a shaft if anomalies or a 51 soft bottom are detected by the Contractor’s testing. If additional testing at a shaft

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 85 1 confirms the presence of a defect(s) in the shaft, the testing costs and the delay costs 2 resulting from the additional testing shall be borne by the Contractor in accordance with 3 Section 1-05.6. If the additional testing indicates that the shaft has no defect, the testing 4 costs and the delay costs resulting from the additional testing will be paid by the 5 Contracting Agency in accordance with Section 1-05.6, and, if the shaft construction is on 6 the critical path of the Contractor’s schedule, a time extension equal to the delay created 7 by the additional testing will be granted in accordance with Section 1-08.8. 8 9 6-19.3(9)A Schedule of CSL Testing 10 This section, including title, is revised to read: 11 12 6-19.3(9)A TIP Testing Using Thermal Probes or CSL Testing 13 If selected as the nondestructive QA testing method by the Contractor, TIP testing using 14 thermal probes, or CSL testing shall be performed after the shaft concrete has cured at 15 least 96 hours. Additional curing time prior to testing may be required if the shaft concrete 16 contains admixtures, such as set retarding admixture or water-reducing admixture, added 17 in accordance with Section 6-02.3(3). The additional curing time prior to testing required 18 under these circumstances shall not be grounds for additional compensation or extension 19 of time to the Contractor in accordance with Section 1-08.8. 20 21 6-19.3(9)B Inspection of CSL Access Tubes 22 This section’s title is revised to read: 23 24 6-19.3(9)B Inspection of Access Tubes 25 26 6-19.3(9)C Engineer’s Final Acceptance of Shafts 27 This section, including title, is revised to read: 28 29 6-19.3(9)C TIP Testing With Thermal Wires and TAPs 30 If selected as the nondestructive QA testing method by the Contractor, TIP testing with 31 thermal wires and TAPs (See Section 6-19.3(6)E) shall be performed. The TIP testing 32 shall commence at the beginning of the concrete placement operation, recording 33 temperature readings at 15-minute intervals until the peak temperature is captured in the 34 data. Additional curing time may be required if the shaft concrete contains admixtures, 35 such as set retarding admixture or water-reducing admixture, added in accordance with 36 Section 6-02.3(3). The additional curing time required under these circumstances shall 37 not be grounds for additional compensation or extension of time to the Contractor in 38 accordance with Section 1-08.8. 39 40 TIP testing shall be conducted at all shafts in which thermal wires and TAPs have been 41 installed for thermal wire analysis (Section 6-19.3(6)A). 42 43 6-19.3(9)D Requirements to Continue Shaft Excavation Prior to Acceptance of 44 First Shaft 45 This section, including title, is revised to read: 46 47 6-19.3(9)D Nondestructive QA Testing Results Submittal 48 The Contractor shall submit the results and analysis of the nondestructive QA testing for 49 each shaft tested. The Contractor shall submit the test results within three working days 50 of testing. Results shall be a Type 1 Working Drawing presented in a written report. 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 86 1 TIP reports shall include: 2 3 1. A map or plot of the wire/tube location within the shaft and their position relative 4 to a known and identifiable location, such as North. 5 6 2. Graphical displays of temperature measurements versus depth of each wire or 7 tube for the analysis time selected, overall average temperature with depth, 8 shaft radius or diameter with depth, concrete cover versus cage position with 9 depth, and effective radius. 10 11 3. The report shall identify unusual temperatures, particularly significantly cooler 12 local deviations from the overall average. 13 14 4. The report shall identify the location and extent where satisfactory or 15 questionable concrete is identified. 16 17 a. Satisfactory (S) - 0 to 6% Effective Radius Reduction and Cover Criteria 18 Met 19 20 b. Questionable (Q) - Effective Local Radius Reduction > 6%, Effective Local 21 Average Diameter Reduction > 4%, or Cover Criteria Not Met 22 23 5. Variations in temperature between wire/tubes (at each depth) which in turn 24 correspond to variations in cage alignment. 25 26 6. Where shaft specific construction information is available (e.g. elevations of the 27 top of shaft, bottom of casing, bottom of shaft, etc.), these values shall be noted 28 on all pertinent graphical displays. 29 30 CSL reports shall include: 31 32 1. A map or plot of the tube location within the shaft and their position relative to a 33 known and identifiable location, such as North. 34 35 2. Graphical displays of CSL Energy versus Depth and CSL signal arrival time 36 versus depth or velocity versus depth. 37 38 3. The report shall identify the location and extent where good, questionable, and 39 poor concrete is identified, where no signal was received, or where water is 40 present. 41 42 a. Good (G) - No signal distortion and decrease in signal velocity of 10% or 43 less is indicative of good quality concrete. 44 45 b. Questionable (Q) - Minor signal distortion and a lower signal amplitude with 46 a decrease in signal velocity between 10% and 20%. 47 48 c. Poor (P) - Severe signal distortion and much lower signal amplitude with a 49 decrease in signal velocity of 20% or more. 50 51 d. No Signal (NS) - No signal was received. 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 87 1 e. Water (W) - A measured signal velocity of nominally V = 4,800 to 5,000 fps. 2 3 All QA test reports will provide a recommendation to accept the shaft as-is, 4 recommendation for further review by the Engineer, or will provide a plan for further 5 testing, investigation or repair to address any deficiencies identified by the testing. 6 7 6-19.3(9)E Additional CSL Testing 8 This section, including title, is revised to read: 9 10 6-19.3(9)E Vacant 11 12 6-19.3(9)I Requirements for CSL Access Tubes and Cored Holes After CSL 13 Testing 14 This section’s title is revised to read: 15 16 6-19.3(9)I Requirements for Access Tubes and Cored Holes After CSL 17 Testing 18 19 6-19.4 Measurement 20 This section is revised to read: 21 22 Constructing shafts will be measured by the linear foot. The linear foot measurement will 23 be calculated using the top of shaft elevation and the bottom of shaft elevation for each 24 shaft as shown in the Plans. 25 26 Rock excavation for shaft, including haul, will be measured by the linear foot of shaft 27 excavated. The linear feet measurement will be computed using the top of the rock line, 28 defined as the highest bedrock point within the shaft diameter, and the bottom elevation 29 shown in the Plans. 30 31 QA shaft test will be measured once per shaft tested. 32 33 6-19.5 Payment 34 This section is revised to read: 35 36 Payment will be made for the following Bid items when they are included in the Proposal: 37 38 “Constructing___Diam. Shaft”, per linear foot. 39 The unit Contract price per linear foot for “Constructing___Diam. Shaft” shall be full 40 pay for performing the Work as specified, including: 41 42 1. Soil excavation for shaft, including all costs in connection with furnishing, 43 mixing, placing, maintaining, containing, collecting, and disposing of all 44 mineral, synthetic and water slurry, and disposing of groundwater collected 45 by the excavated shaft. 46 47 2. Furnishing and placing temporary shaft casing, including temporary casing 48 in addition to the required casing specified in the Special Provisions, and 49 including all costs in connection with completely removing the casing after 50 completing shaft construction. 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 88 1 3. Furnishing permanent casing for shaft. 2 3 4. Placing permanent casing for shaft. 4 5 5. Casing shoring, including all costs in connection with furnishing and 6 installing casing shoring above the specified upper limit for casing shoring 7 but necessary to provide for sufficient water head pressure to resist artesian 8 water pressure present in the shaft excavation, removing casing shoring, 9 and placing seals when required. 10 11 6. Furnishing and placing steel reinforcing bar and epoxy-coated steel 12 reinforcing bar, including furnishing and installing steel reinforcing bar 13 centralizers. 14 15 7. Installation of CSL tubes or thermal wires. 16 17 8. Furnishing, placing and curing concrete to the top of shaft or to the 18 construction joint at the base of the shaft-column splice zone as applicable. 19 20 Payment for “Constructing___Diam. Shaft” will be made upon Engineer acceptance 21 of the shaft, including completion of satisfactory QA shaft tests as applicable. 22 23 “Rock Excavation For Shaft Including Haul”, per linear foot. 24 When rock excavation is encountered, payment for rock excavation is in addition to 25 the unit Contract price per linear foot for “Constructing___Diam. Shaft” 26 27 “Shoring Or Extra Excavation Cl. A - ___”, lump sum. 28 The lump sum Contract price for “Shoring Or Extra Excavation Cl. A - ___” shall be 29 full pay for performing the Work as specified, including all costs in connection with all 30 excavation outside the limits specified for soil and rock excavation for shaft including 31 haul, all temporary telescoping casings, and all temporary casings beyond the limits 32 of required temporary casing specified in the Special Provisions. 33 34 “QA Shaft Test”, per each. 35 The unit Contract price per each for “QA Shaft Test” shall be full pay for performing 36 the Work as specified, including operating all associated accessories necessary to 37 record and process data and develop the summary QA test reports. Section 1-04.6 38 does not apply to this bid item. 39 40 “Removing Shaft Obstructions”, estimated. 41 Payment for removing, breaking-up, or pushing aside shaft obstructions, as defined 42 in Section 6-19.3(3)E, will be made for the changes in shaft construction methods 43 necessary to deal with the obstruction. The Contractor and the Engineer shall 44 evaluate the effort made and reach agreement on the equipment and employees 45 utilized, and the number of hours involved for each. Once these cost items and their 46 duration have been agreed upon, the payment amount will be determined using the 47 rate and markup methods specified in Section 1-09.6. For the purpose of providing 48 a common proposal for all Bidders, the Contracting Agency has entered an amount 49 for the item “Removing Shaft Obstructions” in the Bid Proposal to become a part of 50 the total Bid by the Contractor. 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 89 1 If drilled shaft tools, cutting teeth, casing or Kelly bar is damaged as a result of the 2 obstruction removal work, the Contractor will be compensated for the costs to repair 3 this equipment in accordance with Section 1-09.6. 4 5 If shaft construction equipment is idled as a result of the Work required to deal with 6 the obstruction and cannot be reasonably reassigned within the project, then standby 7 payment for the idled equipment will be added to the payment calculations. If labor 8 is idled as a result of the Work required to deal with the obstruction and cannot be 9 reasonably reassigned within the project, then all labor costs resulting from 10 Contractor labor agreements and established Contractor policies will be added to the 11 payment calculations. 12 13 The Contractor shall perform the amount of obstruction Work estimated by the 14 Contracting Agency within the original time of the Contract. The Engineer will 15 consider a time adjustment and additional compensation for costs related to the 16 extended duration of the shaft construction operations, provided: 17 18 1. The dollar amount estimated by the Contracting Agency has been 19 exceeded, and 20 21 2. The Contractor shows that the obstruction removal Work represents a delay 22 to the completion of the project based on the current progress schedule 23 provided in accordance with Section 1-08.3. 24 25 26 Section 7-02, Culverts 27 April 2, 2018

28 7-02.2 Materials 29 In the first paragraph, the references to “Portland Cement” and “Aggregates for Portland 30 Cement Concrete” are revised to read: 31 32 Cement 9-01 33 Aggregates for Concrete 9-03.1 34 35 7-02.3(6)A4 Excavation and Bedding Preparation 36 The first sentence of the third paragraph is revised to read: 37 38 The bedding course shall be a 6-inch minimum thickness layer of culvert bedding material, 39 defined as granular material either conforming to Section 9-03.12(3) or to AASHTO 40 Grading No. 57 as specified in Section 9-03.1(4)C. 41 42 Section 7-05, Manholes, Inlets, Catch Basins, and Drywells 43 August 6, 2018

44 7-05.3 Construction Requirements 45 The fourth sentence of the third paragraph is deleted. 46

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 90 1 Section 7-08, General Pipe Installation Requirements 2 April 2, 2018

3 7-08.3(3) Backfilling 4 The fifth sentence of the fourth paragraph is revised to read: 5 6 All compaction shall be in accordance with the Compaction Control Test of Section 2- 7 03.3(14)D except in the case that 100% Recycled Concrete Aggregate is used. 8 9 The following new sentences are inserted after the fifth sentence of the fourth paragraph: 10 11 When 100% Recycled Concrete Aggregate is used, the Contractor may submit a written 12 request to use a test point evaluation for compaction acceptance. Test Point evaluation 13 shall be performed in accordance with SOP 738. 14 15 Section 8-01, Erosion Control and Water Pollution Control 16 April 2, 2018

17 8-01.1 Description 18 This section is revised to read: 19 20 This Work consists of furnishing, installing, maintaining, removing and disposing of best 21 management practices (BMPs), as defined in the Washington Administrative Code (WAC) 22 173-201A, to manage erosion and water quality in accordance with these Specifications 23 and as shown in the Plans or as designated by the Engineer. 24 25 The Contracting Agency may have a National Pollution Discharge Elimination System 26 Construction Stormwater General Permit (CSWGP) as identified in the Contract Special 27 Provisions. The Contracting Agency may or may not transfer coverage of the CSWGP to 28 the Contractor when a CSWGP has been obtained. The Contracting Agency may not 29 have a CSWGP for the project but may have another water quality related permit as 30 identified in the Contract Special Provisions or the Contracting Agency may not have 31 water quality related permits but the project is subject to applicable laws for the Work. 32 Section 8-01 covers all of these conditions. 33 34 8-01.2 Materials 35 The first paragraph is revised to read: 36 37 Materials shall meet the requirements of the following sections: 38 39 Corrugated Polyethylene Drain Pipe 9-05.1(6) 40 Quarry Spalls 9-13 41 Erosion Control and Roadside Planting 9-14 42 Construction Geotextile 9-33 43 44 8-01.3(1) General 45 This section is revised to read: 46 47 Adaptive management shall be employed throughout the duration of the project for the 48 implementation of erosion and water pollution control permit requirements for the current 49 condition of the project site. The adaptive management includes the selection and 50 utilization of BMPs, scheduling of activities, prohibiting unacceptable practices,

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 91 1 implementing maintenance procedures, and other managerial practices that when used 2 singularly or in combination, prevent or reduce the release of pollutants to waters of the 3 State. The adaptive management shall use the means and methods identified in this 4 section and means and methods identified in the Washington State Department of 5 Transportation’s Temporary Erosion and Sediment Control Manual or the Washington 6 State Department of Ecology’s Stormwater Management Manuals for construction 7 stormwater. 8 9 The Contractor shall install a high visibility fence along the site preservation lines shown 10 in the Plans or as instructed by the Engineer. 11 12 Throughout the life of the project, the Contractor shall preserve and protect the delineated 13 preservation area, acting immediately to repair or restore any fencing damaged or 14 removed. 15 16 All discharges to surface waters shall comply with surface water quality standards as 17 defined in Washington Administrative Code (WAC) Chapter 173-201A. All discharges to 18 the ground shall comply with groundwater quality standards WAC Chapter 173-200. 19 20 The Contractor shall comply with the CSWGP when the project is covered by the CSWGP. 21 Temporary Work, at a minimum, shall include the implementation of: 22 23 1. Sediment control measures prior to ground disturbing activities to ensure all 24 discharges from construction areas receive treatment prior to discharging from 25 the site. 26 27 2. Flow control measures to prevent erosive flows from developing. 28 29 3. Water management strategies and pollution prevention measures to prevent 30 contamination of waters that will be discharged to surface waters or the ground. 31 32 4. Erosion control measures to stabilize erodible earth not being worked. 33 34 5. Maintenance of BMPs to ensure continued compliant performance. 35 36 6. Immediate corrective action if evidence suggests construction activity is not in 37 compliance. Evidence includes sampling data, olfactory or visual evidence such 38 as the presence of suspended sediment, turbidity, discoloration, or oil sheen in 39 discharges. 40 41 To the degree possible, the Contractor shall coordinate this temporary Work with 42 permanent drainage and erosion control Work the Contract requires. 43 44 Clearing, grubbing, excavation, borrow, or fill within the Right of Way shall never expose 45 more erodible earth than as listed below: 46 Western Washington Eastern Washington (West of the Cascade (East of the Cascade Mountain Crest) Mountain Crest) May 1 through April 1 through 17 Acres 17 Acres September 30 October 31

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 92 October 1 November 1 through April 5 Acres through March 5 Acres 30 31 1 2 The Engineer may increase or decrease the limits based on project conditions. 3 4 Erodible earth is defined as any surface where soils, grindings, or other materials may be 5 capable of being displaced and transported by rain, wind, or surface water runoff. 6 7 Erodible earth not being worked, whether at final grade or not, shall be covered within the 8 specified time period (see the table below), using BMPs for erosion control. 9 Western Washington Eastern Washington (West of the Cascade (East of the Cascade Mountain Crest) Mountain Crest) October 1 October 1 2 days 5 days through April through June maximum maximum 30 30 November 1 May 1 to 7 days 10 days through March September 30 maximum maximum 31 10 11 When applicable, the Contractor shall be responsible for all Work required for compliance 12 with the CSWGP including annual permit fees. 13 14 If the Engineer, under Section 1-08.6, orders the Work suspended, the Contractor shall 15 continue to comply with this division during the suspension. 16 17 Nothing in this Section shall relieve the Contractor from complying with other Contract 18 requirements. 19 20 8-01.3(1)A Submittals 21 This section’s content is deleted. 22 23 This section is supplemented with the following new subsection: 24 25 8-01.3(1)A1 Temporary Erosion and Sediment Control 26 A Temporary Erosion and Sediment Control (TESC) plan consists of a narrative section 27 and plan sheets that meets the Washington State Department of Ecology’s Stormwater 28 Pollution Prevention Plan (SWPPP) requirement in the CSWGP. Abbreviated TESC plans 29 are not required to include plan sheets and are used on small projects that disturb soil 30 and have the potential to discharge but are not covered by the CSWGP. The contract 31 uses the term “TESC plan” to describe both TESC plans and abbreviated TESC plans. 32 When the Contracting Agency has developed a TESC plan for a Contract, the narrative 33 is included in the appendix to the Special Provisions and the TESC plan sheets, when 34 required, are included in the Contract Plans. The Contracting Agency TESC plan will not 35 include off-site areas used to directly support construction activity. 36 37 The Contractor shall either adopt the TESC Plan in the Contract or develop a new TESC 38 Plan. If the Contractor adopts the Contracting Agency TESC Plan, the Contractor shall 39 modify the TESC Plan to meet the Contractor’s schedule, method of construction, and to 40 include off-site areas that will be used to directly support construction activity such as

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 93 1 equipment staging yards, material storage areas, or borrow areas. Contractor TESC 2 Plans shall include all high visibility fence delineation shown on the Contracting Agency 3 Contract Plans. All TESC Plans shall meet the requirements of the current edition of the 4 WSDOT Temporary Erosion and Sediment Control Manual M 3109 and be adaptively 5 managed as needed throughout construction based on site inspections and discharge 6 samples to maintain compliance with the CSWGP. The Contractor shall develop a 7 schedule for implementation of the TESC work and incorporate it into the Contractor’s 8 progress schedule. 9 10 The Contractor shall submit their TESC Plan (either the adopted plan or new plan) and 11 implementation schedule as Type 2 Working Drawings. At the request of the Engineer, 12 updated TESC Plans shall be submitted as Type 1 Working Drawings. 13 14 8-01.3(1)B Erosion and Sediment Control (ESC) Lead 15 This section is revised to read: 16 17 The Contractor shall identify the ESC Lead at the preconstruction discussions and in the 18 TESC Plan. The ESC Lead shall have, for the life of the Contract, a current Certificate of 19 Training in Construction Site Erosion and Sediment Control from a course approved by 20 the Washington State Department of Ecology. The ESC Lead must be onsite or on call at 21 all times throughout construction. The ESC Lead shall be listed on the Emergency 22 Contact List required under Section 1-05.13(1). 23 24 The ESC Lead shall implement the TESC Plan. Implementation shall include, but is not 25 limited to: 26 27 1. Installing, adaptively managing, and maintaining temporary erosion and 28 sediment control BMPs to assure continued performance of their intended 29 function. Damaged or inadequate BMPs shall be corrected immediately. 30 31 2. Updating the TESC Plan to reflect current field conditions. 32 33 3. Discharge sampling and submitting Discharge Monitoring Reports (DMRs) to 34 the Washington State Department of Ecology in accordance with the CSWGP. 35 36 4. Develop and maintain the Site Log Book as defined in the CSWGP. When the 37 Site Log Book or portion thereof is electronically developed, the electronic 38 documentation must be accessible onsite. As a part of the Site Log Book, the 39 Contractor shall develop and maintain a tracking table to show that identified 40 TESC compliance issues are fully resolved within 10 calendar days. The table 41 shall include the date an issue was identified, a description of how it was 42 resolved, and the date the issue was fully resolved. 43 44 The ESC Lead shall also inspect all areas disturbed by construction activities, all on-site 45 erosion and sediment control BMPs, and all stormwater discharge points at least once 46 every calendar week and within 24-hours of runoff events in which stormwater discharges 47 from the site. Inspections of temporarily stabilized, inactive sites may be reduced to once 48 every calendar month. The Washington State Department of Ecology’s Erosion and 49 Sediment Control Site Inspection Form, located at https://ecology.wa.gov/Regulations- 50 Permits/Permits-certifications/Stormwater-general-permits/Construction-stormwater- 51 permit, shall be completed for each inspection and a copy shall be submitted to the 52 Engineer no later than the end of the next working day following the inspection.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 94 1 2 8-01.3(1)C Water Management 3 This section is supplemented with the following new subsections: 4 5 8-01.3(1)C5 Water Management for In-Water Work Below Ordinary High 6 Water Mark (OHWM) 7 Work over surface waters of the state (defined in WAC 173-201A-010) or below the 8 OHWM (defined in RCW 90.58.030) must comply with water quality standards for surface 9 waters of the state of Washington. 10 11 8-01.3(1)C6 Environmentally Acceptable Hydraulic Fluid 12 All equipment containing hydraulic fluid that extends from a bridge deck over surface 13 waters of the state or below the OHWM, shall be equipped with an environmentally 14 acceptable hydraulic fluid. The fluid shall meet specific requirements for biodegradability, 15 aquatic toxicity, and bioaccumulation in accordance with the United States Environmental 16 Protection Agency (EPA) publication EPA800-R-11-002. Acceptance shall be in 17 accordance with Section 1-06.3, Manufacturer’s Certification of Compliance. 18 19 The designation of environmentally acceptable hydraulic fluid does not mean fluid spills 20 are acceptable. The Contractor shall respond to spills to land or water in accordance with 21 the Contract. 22 23 8-01.3(1)C7 Turbidity Curtain 24 All Work for the turbidity curtain shall be in accordance with the manufacturer’s 25 recommendations for the site conditions. Removal procedures shall be developed and 26 used to minimize silt release and disturbance of silt. The Contractor shall submit a Type 27 2 Working Drawing, detailing product information, installation and removal procedures, 28 equipment and workforce needs, maintenance plans, and emergency repair/replacement 29 plans. 30 31 Turbidity curtain materials, installation, and maintenance shall be sufficient to comply with 32 water quality standards. 33 34 The Contractor shall notify the Engineer 10 days in advance of removing the turbidity 35 curtain. All components of the turbidity curtain shall be removed from the project. 36 37 8-01.3(1)C1 Disposal of Dewatering Water 38 This section is revised to read: 39 40 When uncontaminated groundwater is encountered in an excavation on a project it may 41 be infiltrated within vegetated areas of the right of way not designated as Sensitive Areas 42 or incorporated into an existing stormwater conveyance system at a rate that will not 43 cause erosion or flooding in any receiving surface water. 44 45 Alternatively, the Contractor may pursue independent disposal and treatment alternatives 46 that do not use the stormwater conveyance system provided it is in compliance with the 47 applicable WACs and permits. 48 49 8-01.3(1)C2 Process Wastewater 50 This section is revised to read: 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 95 1 Wastewater generated on-site as a byproduct of a construction process shall not be 2 discharged to surface waters of the State. Some sources of process wastewater may be 3 infiltrated in accordance with the CSWGP with concurrence from the Engineer. Some 4 sources of process wastewater may be disposed via independent disposal and treatment 5 alternatives in compliance with the applicable WACs and permits. 6 7 8-01.3(1)C3 Shaft Drilling Slurry Wastewater 8 This section is revised to read: 9 10 Wastewater generated on-site during shaft drilling activity shall be managed and disposed 11 of in accordance with the requirements below. No shaft drilling slurry wastewater shall be 12 discharged to surface waters of the State. Neither the sediment nor liquid portions of the 13 shaft drilling slurry wastewater shall be contaminated, as detectable by visible or olfactory 14 indication (e.g., chemical sheen or smell). 15 16 1. Water-only shaft drilling slurry or water slurry with accepted flocculants may be 17 infiltrated on-site. Flocculants used shall meet the requirements of Section 9- 18 14.5(1) or shall be chitosan products listed as General Use Level Designation 19 (GULD) on the Washington State Department of Ecology’s stormwater treatment 20 technologies webpage for construction treatment. Infiltration is permitted if the 21 following requirements are met: 22 23 a. Wastewater shall have a pH of 6.5 – 8.5 prior to discharge. 24 25 b. The amount of flocculant added to the slurry shall be kept to the minimum 26 needed to adequately settle out solids. The flocculant shall be thoroughly 27 mixed into the slurry. 28 29 c. The slurry removed from the shaft shall be contained in a leak proof cell or 30 tank for a minimum of 3 hours. 31 32 d. The infiltration rate shall be reduced if needed to prevent wastewater from 33 leaving the infiltration location. The infiltration site shall be monitored 34 regularly during infiltration activity. All wastewater discharged to the ground 35 shall fully infiltrate and discharges shall stop before the end of each work 36 day. 37 38 e. Drilling spoils and settled sediments remaining in the containment cell or 39 tank shall be disposed of in accordance with Section 6-19.3(4)F. 40 41 f. Infiltration locations shall be in upland areas at least 150 feet away from 42 surface waters, wells, on-site sewage systems, aquifer sensitive recharge 43 areas, sole source aquifers, well head protection areas, and shall be 44 marked on the plan sheets before the infiltration activity begins. 45 46 g. Prior to infiltration, the Contractor shall submit a Shaft Drilling Slurry 47 Wastewater Management and Infiltration Plan as a Type 2 Working 48 Drawing. This Plan shall be kept on-site, adapted if needed to meet the 49 construction requirements, and updated to reflect what is being done in the 50 field. The Working Drawing shall include, at a minimum, the following 51 information: 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 96 1 i. Plan sheet showing the proposed infiltration location and all surface 2 waters, wells, on-site sewage systems, aquifer-sensitive recharge 3 areas, sole source aquifers, and well-head protection areas within 150 4 feet. 5 6 ii. The proposed elevation of soil surface receiving the wastewater for 7 infiltration and the anticipated phreatic surface (i.e., saturated soil). 8 9 iii. The source of the water used to produce the slurry. 10 11 iv. The estimated total volume of wastewater to be infiltrated. 12 13 v. The accepted flocculant to be used (if any). 14 15 vi. The controls or methods used to prevent surface wastewater runoff 16 from leaving the infiltration location. 17 18 vii. The strategy for removing slurry wastewater from the shaft and 19 containing the slurry wastewater once it has been removed from the 20 shaft. 21 22 viii. The strategy for monitoring infiltration activity and adapting methods to 23 ensure compliance. 24 25 ix. A contingency plan that can be implemented immediately if it becomes 26 evident that the controls in place or methods being used are not 27 adequate. 28 29 x. The strategy for cleaning up the infiltration location after the infiltration 30 activity is done. Cleanup shall include stabilizing any loose sediment 31 on the surface within the infiltration area generated as a byproduct of 32 suspended solids in the infiltrated wastewater or soil disturbance 33 associated with BMP placement and removal. 34 35 2. Shaft drilling mineral slurry, synthetic slurry, or slurry with polymer additives not 36 allowed for infiltration shall be contained and disposed of by the Contractor at 37 an accepted disposal facility in accordance with Section 2-03.3(7)C. Spoils that 38 have come into contact with mineral slurry shall be disposed of in accordance 39 with Section 6-19.3(4)F. 40 41 8-01.3(1)C4 Management of Off-Site Water 42 This section is revised to read: 43 44 Prior to clearing and grubbing, the Contractor shall intercept all sources of off-site surface 45 water and overland flow that will run-on to the project. Off-site surface water run-on shall 46 be diverted through or around the project in a way that does not introduce construction 47 related pollution. It shall be diverted to its preconstruction discharge location in a manner 48 that does not increase preconstruction flow rate and velocity and protects contiguous 49 properties and waterways from erosion. The Contractor shall submit a Type 2 Working 50 Drawing consisting of the method for performing this Work. 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 97 1 8-01.3(1)E Detention/Retention Pond Construction 2 This section is revised to read: 3 4 Whether permanent or temporary, ponds shall be constructed before beginning other 5 grading and excavation Work in the area that drains into that pond. Detention/retention 6 ponds may be constructed concurrently with grading and excavation when allowed by the 7 Engineer. Temporary conveyances shall be installed concurrently with grading in 8 accordance with the TESC Plan so that newly graded areas drain to the pond as they are 9 exposed. 10 11 8-01.3(2)F Dates for Application of Final Seed, Fertilizer, and Mulch 12 In the table, the second column heading is revised to read: 13 14 Eastern Washington1 15 (East of the Cascade Mountain Crest) 16 17 Footnote 1 in the table is revised to read: 18 19 Seeding may be allowed outside these dates when allowed or directed by the Engineer. 20 21 8-01.3(5) Plastic Covering 22 The first sentence of the first paragraph is revised to read: 23 24 Erosion Control – Plastic coverings used to temporarily cover stockpiled materials, 25 slopes or bare soils shall be installed and maintained in a way that prevents water from 26 intruding under the plastic and prevents the plastic cover from being damaged by wind. 27 28 8-01.3(7) Stabilized Construction Entrance 29 The first paragraph is revised to read: 30 31 Temporary stabilized construction entrance shall be constructed in accordance with the 32 Standard Plans, prior to construction vehicles entering the roadway from locations that 33 generate sediment track out on the roadway. Material used for stabilized construction 34 entrance shall be free of extraneous materials that may cause or contribute to track out. 35 36 8-01.3(8) Street Cleaning 37 This section is revised to read: 38 39 Self-propelled pickup street sweepers shall be used to remove and collect dirt and other 40 debris from the Roadway. The street sweeper shall effectively collect these materials and 41 prevent them from being washed or blown off the Roadway or into waters of the State. 42 Street sweepers shall not generate fugitive dust and shall be designed and operated in 43 compliance with applicable air quality standards. Material collected by the street sweeper 44 shall be disposed of in accordance with Section 2-03.3(7)C. 45 46 When allowed by the Engineer, power broom sweepers may be used in non- 47 environmentally sensitive areas. The broom sweeper shall sweep dirt and other debris 48 from the roadway into the work area. The swept material shall be prevented from entering 49 or washing into waters of the State. 50 51 Street washing with water will require the concurrence of the Engineer. 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 98 1 8-01.3(12) Compost Socks 2 The first two sentences of the first paragraph are revised to read: 3 4 Compost socks are used to disperse flow and sediment. Compost socks shall be installed 5 as soon as construction will allow but before flow conditions create erosive flows or 6 discharges from the site. Compost socks shall be installed prior to any mulching or 7 compost placement. 8 9 8-01.3(13) Temporary Curb 10 The second to last sentence of the second paragraph is revised to read: 11 12 Temporary curbs shall be a minimum of 4 inches in height. 13 14 8-01.3(14) Temporary Pipe Slope Drain 15 The third and fourth paragraphs are revised to read: 16 17 The pipe fittings shall be water tight and the pipe secured to the slope with metal posts, 18 wood stakes, sand bags, or as allowed by the Engineer. 19 20 The water shall be discharged to a stabilized conveyance, sediment trap, stormwater 21 pond, rock splash pad, or vegetated strip, in a manner to prevent erosion and maintain 22 water quality compliance. 23 24 The last paragraph is deleted. 25 26 8-01.3(15) Maintenance 27 This section is revised to read: 28 29 Erosion and sediment control BMPs shall be maintained or adaptively managed as 30 required by the CSWGP until the Engineer determines they are no longer needed. When 31 deficiencies in functional performance are identified, the deficiencies shall be rectified 32 immediately. 33 34 The BMPs shall be inspected on the schedule outlined in Section 8-01.3(1)B for damage 35 and sediment deposits. Damage to or undercutting of BMPs shall be repaired 36 immediately. 37 38 In areas where the Contractor’s activities have compromised the erosion control functions 39 of the existing grasses, the Contractor shall overseed at no additional cost to the 40 Contracting Agency. 41 42 The quarry spalls of construction entrances shall be refreshed, replaced, or screened to 43 maintain voids between the spalls for collecting mud and dirt. 44 45 Unless otherwise specified, when the depth of accumulated sediment and debris reaches 46 approximately ⅓ the height of the BMP the deposits shall be removed. Debris or 47 contaminated sediment shall be disposed of in accordance with Section 2-03.3(7)C. 48 Clean sediments may be stabilized on-site using BMPs as allowed by the Engineer. 49 50 8-01.3(16) Removal 51 This section is revised to read: 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 99 1 The Contractor shall remove all temporary BMPs, all associated hardware and associated 2 accumulated sediment deposition from the project limits prior to Physical Completion 3 unless otherwise allowed by the Engineer. When the temporary BMP materials are made 4 of natural plant fibers unaltered by synthetic materials the Engineer may allow leaving the 5 BMP in place. 6 7 The Contractor shall remove BMPs and associated hardware in a way that minimizes soil 8 disturbance. The Contractor shall permanently stabilize all bare and disturbed soil after 9 removal of BMPs. If the installation and use of the erosion control BMPs have compacted 10 or otherwise rendered the soil inhospitable to plant growth, such as construction 11 entrances, the Contractor shall take measures to rehabilitate the soil to facilitate plant 12 growth. This may include, but is not limited to, ripping the soil, incorporating soil 13 amendments, or seeding with the specified seed. 14 15 At the request of the Contractor and at the sole discretion of the Engineer the CSWGP 16 may be transferred back to the Contracting Agency. Approval of the Transfer of Coverage 17 request will require the following: 18 19 1. All other Work required for Contract Completion has been completed. 20 21 2. All Work required for compliance with the CSWGP has been completed to the 22 maximum extent possible. This includes removal of BMPs that are no longer 23 needed and the site has undergone all Stabilization identified for meeting the 24 requirements of Final Stabilization in the CSWGP. 25 26 3. An Equitable Adjustment change order for the cost of Work that has not been 27 completed by the Contractor. 28 29 4. Submittal of the Washington State Department of Ecology Transfer of Coverage 30 form (Ecology form ECY 020-87a) to the Engineer. 31 32 If the Engineer approves the transfer of coverage back to the Contracting Agency, the 33 requirement in Section 1-07.5(3) for the Contractor’s submittal of the Notice of 34 Termination form to the Washington State Department of Ecology will not apply. 35 36 8-01.4 Measurement 37 This section’s content is deleted and replaced with the following new subsections: 38 39 8-01.4(1) Lump Sum Bid for Project (No Unit Items) 40 When the Bid Proposal contains the item “Erosion Control and Water Pollution 41 Prevention” there will be no measurement of unit or force account items for Work defined 42 in Section 8-01 except as described in Sections 8-01.4(3) and 8-01.4(4). Also, except as 43 described in Section 8-01.4(3), all of Sections 8-01.4(2) and 8-01.5(2) are deleted. 44 45 8-01.4(2) Item Bids 46 When the Proposal does not contain the items “Erosion Control and Water Pollution 47 Prevention”, Section 8-01.4(1) and 8-01.5(1) are deleted and the Bid Proposal will contain 48 some or all of the following items measured as noted. 49 50 ESC lead will be measured per day for each day that an inspection is made and a 51 report is filed. 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 100 1 Biodegradable erosion control blanket and plastic covering will be measured by the 2 square yard along the ground slope line of surface area covered and accepted. 3 4 Turbidity curtains will be measured by the linear foot along the ground line of the 5 installed curtain. 6 7 Check dams will be measured per linear foot one time only along the ground line of 8 the completed check dam. No additional measurement will be made for check dams 9 that are required to be rehabilitated or replaced due to wear. 10 11 Stabilized construction entrances will be measured by the square yard by ground 12 slope measurement for each entrance constructed. 13 14 Tire wash facilities will be measured per each for each tire wash installed. 15 16 Street cleaning will be measured by the hour for the actual time spent cleaning 17 pavement, refilling with water, dumping and transport to and from cleaning locations 18 within the project limits, as authorized by the Engineer. Time to mobilize the 19 equipment to or from the project limits on which street cleaning is required will not be 20 measured. 21 22 Inlet protections will be measured per each for each initial installation at a 23 drainage structure. 24 25 Silt fence, gravel filter, compost berms, and wood chip berms will be measured by 26 the linear foot along the ground line of the completed barrier. 27 28 Wattles and compost socks will be measured by the linear foot. 29 30 Temporary curbs will be measured by the linear foot along the ground line of the 31 completed installation. 32 33 Temporary pipe slope drains will be measured by the linear foot along the flow line 34 of the pipe. 35 36 Coir logs will be measured by the linear foot along the ground line of the completed 37 installation. 38 39 Outlet protections will be measured per each initial installation at an outlet location. 40 41 Tackifiers will be measure by the acre by ground slope measurement. 42 43 8-01.4(3) Reinstating Unit Items with Lump Sum Erosion Control and 44 Water Pollution Prevention 45 The Contract Provisions may establish the project as lump sum, in accordance with 46 Section 8-01.4(1) and also include one or more of the items included above in Section 8- 47 01.4(2). When that occurs, the corresponding measurement provision in Section 8- 48 01.4(2) is not deleted and the Work under that item will be measured as specified. 49

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 101 1 8-01.4(4) Items not included with Lump Sum Erosion Control and Water 2 Pollution Prevention 3 Compost blanket will be measured by the square yard by ground slope surface area 4 covered and accepted. 5 6 Mulching will be measured by the acre by ground slope surface area covered and 7 accepted. 8 9 Seeding, fertilizing, liming, mulching, and mowing, will be measured by the acre by ground 10 slope measurement. 11 12 Seeding and fertilizing by hand will be measured by the square yard by ground slope 13 measurement. No adjustment in area size will be made for the vegetation free zone 14 around each plant. 15 16 Fencing will be measured by the linear foot along the ground line of the completed fence. 17 18 8-01.5 Payment 19 This section’s content is deleted and replaced with the following new subsections: 20 21 8-01.5(1) Lump Sum Bid for Project (No Unit Items) 22 Payment will be made for the following Bid item when it is included in the Proposal: 23 24 “Erosion Control and Water Pollution Prevention”, lump sum. 25 26 The lump sum Contract price for “Erosion Control and Water Pollution Prevention” 27 shall be full pay to perform the Work as described in Section 8-01 except for costs 28 compensated by Bid Proposal items inserted through Contract Provisions as 29 described in Section 8-01.4(2). Progress payments for the lump sum item “Erosion 30 Control and Water Pollution Prevention” will be made as follows: 31 32 1. The Contracting Agency will pay 15 percent of the bid amount for the initial 33 set up for the item. Initial set up includes the following: 34 35 a. Acceptance of the TESC Plan provided by the Contracting Agency or 36 submittal of a new TESC Plan, 37 38 b. Submittal of a schedule for the installation of the BMPs, and 39 40 c. Identifying water quality sampling locations. 41 42 2. 70 percent of the bid amount will be paid in accordance with Section 1-09.9. 43 44 3. Once the project is physically complete and copies of the all reports 45 submitted to the Washington State Department of Ecology have been 46 submitted to the Engineer, and, if applicable, transference of the CSWGP 47 back to the Contracting Agency is complete, the remaining 15 percent of 48 the bid amount shall be paid in accordance with Section 1-09.9. 49 50 8-01.5(2) Item Bids 51 “ESC Lead”, per day. 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 102 1 “Turbidity Curtain”, per linear foot. 2 3 “Biodegradable Erosion Control Blanket”, per square yard. 4 5 “Plastic Covering”, per square yard. 6 7 “Check Dam”, per linear foot. 8 9 “Inlet Protection”, per each. 10 11 “Gravel Filter Berm”, per linear foot. 12 13 “Stabilized Construction Entrance”, per square yard. 14 15 “Street Cleaning”, per hour. 16 17 “Silt Fence”, per linear foot. 18 19 “Wood Chip Berm”, per linear foot. 20 21 “Compost Berm”, per linear foot. 22 23 “Wattle”, per linear foot. 24 25 “Compost Sock”, per linear foot. 26 27 “Coir Log”, per linear foot. 28 29 “Temporary Curb”, per linear foot. 30 31 “Temporary Pipe Slope Drain”, per linear foot. 32 33 “Temporary Seeding”, per acre. 34 35 “Outlet Protection”, per each. 36 37 “Tackifier”, per acre. 38 39 “Erosion/Water Pollution Control”, by force account as provided in Section 1-09.6. 40 41 Maintenance and removal of erosion and water pollution control devices including 42 removal and disposal of sediment, stabilization and rehabilitation of soil disturbed 43 by these activities, and any additional Work deemed necessary by the Engineer to 44 control erosion and water pollution will be paid by force account in accordance with 45 Section 1-09.6. 46 47 To provide a common Proposal for all Bidders, the Contracting Agency has entered an 48 amount in the Proposal to become a part of the Contractor’s total Bid. 49

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 103 1 8-01.5(3) Reinstating Unit Items with Lump Sum Erosion Control and 2 Water Pollution Prevention 3 The Contract may establish the project as lump sum, in accordance with Section 8-01.4(1) 4 and also reinstate the measurement of one or more of the items described in Section 8- 5 01.4(2), except for Erosion/Water Pollution Control, by force account. When that occurs, 6 the corresponding payment provision in Section 8-01.5(2) is not deleted and the Work 7 under that item will be paid as specified. 8 9 8-01.5(4) Items not included with Lump Sum Erosion Control and Water 10 Pollution Prevention 11 Payment will be made for each of the following Bid items when they are included in the 12 Proposal: 13 14 “Compost Blanket”, per square yard. 15 16 “Mulching”, per acre 17 18 “Mulching with PAM”, per acre 19 20 “Mulching with Short-Term Mulch”, per acre. 21 22 “Mulching with Moderate-Term Mulch”, per acre. 23 24 “Mulching with Long-Term Mulch”, per acre. 25 26 “Seeding, Fertilizing and Mulching”, per acre. 27 28 “Seeding and Fertilizing”, per acre. 29 30 “Seeding and Fertilizing by Hand”, per square yard. 31 32 “Second Application of Fertilizer”, per acre. 33 34 “Liming”, per acre. 35 36 “Mowing”, per acre. 37 38 “Seeding and Mulching”, per acre. 39 40 “High Visibility Fence”, per linear foot. 41 42 Section 8-02, Roadside Restoration 43 January 2, 2018

44 8-02.2 Materials 45 The reference to the material “Soil” is revised to read “Topsoil”. 46 47 8-02.5 Payment 48 The following new paragraph is inserted following the Bid item “Plant Selection ___”, per each: 49

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 104 1 The unit Contract price for “Plant Selection ___”, per each shall be full pay for all Work to 2 perform the work as specified within the planting area prior to planting for weed control, 3 planting area preparation and installation of plants with initial watering. 4 5 The paragraph following the Bid item “PSIPE ___”, per each is revised to read: 6 7 The unit Contract price for “PSIPE ___”, per each, shall be full pay for all Work to perform 8 the work as specified within the planting area for weed control and planting area 9 preparation, planting, cleanup, and water necessary to complete planting operations as 10 specified to the end of first year plant establishment. 11 12 Section 8-04, Curbs, Gutters, and Spillways 13 April 2, 2018

14 8-04.2 Materials 15 In the first paragraph, the reference to “Portland Cement” is revised to read: 16 17 Cement 9-01 18 19 8-04.3(1) Cement Concrete Curbs, Gutters, and Spillways 20 The first paragraph is supplemented with the following: 21 22 Roundabout truck apron cement concrete curb and gutter shall be constructed with air 23 entrained concrete Class 4000 conforming to the requirements of Section 6-02. 24 25 Section 8-06, Cement Concrete Driveway Entrances 26 April 2, 2018

27 8-06.2 Materials 28 In the first paragraph, the reference to “Portland Cement” is revised to read: 29 30 Cement 9-01 31 32 8-06.3 Construction Requirements 33 The first paragraph is revised to read: 34 35 Cement concrete driveway approaches shall be constructed with air entrained concrete 36 Class 4000 conforming to the requirements of Section 6-02 or Portland Cement or 37 Blended Hydraulic Cement Concrete Pavement conforming to the requirements of 38 Section 5-05. 39 40 Section 8-07, Precast Traffic Curb 41 April 2, 2018

42 8-07.3(1) Installing Curbs 43 The first sentence of the first paragraph is revised to read: 44 45 The curb shall be firmly bedded for its entire length and breadth on a mortar bed 46 conforming to Section 9-20.4(3) composed of one part Portland cement or blended 47 hydraulic cement and two parts sand. 48

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 105 1 The fourth paragraph is revised to read: 2 3 All joints between adjacent pieces of curb except joints for expansion and/or drainage as 4 designated by the Engineer shall be filled with mortar composed of one part Portland 5 cement or blended hydraulic cement and two parts sand. 6 7 Section 8-11, Guardrail 8 August 6, 2018

9 8-11.3(1)C Terminal and Anchor Installation 10 The first paragraph is revised to read: 11 12 All excavation and backfilling required for installation of anchors shall be performed in 13 accordance with Section 2-09, except that the costs thereof shall be included in the unit 14 Contract price for the anchor installed. 15 16 The first sentence of the second to last paragraph is revised to read: 17 18 Assembly and installation of Beam Guardrail Non-flared Terminals for Type 31 guardrail 19 shall be supervised at all times by a manufacturer’s representative, or an installer who 20 has been trained and certified by the manufacturer. 21 22 The last paragraph is revised to read: 23 24 Beam Guardrail Non-flared Terminals for Type 31 guardrail shall meet the crash test and 25 evaluation criteria in the Manual for Assessing Safety Hardware (MASH). 26 27 8-11.4 Measurement 28 The third paragraph is revised to read: 29 30 Measurement of beam guardrail _____ terminal will be per each for the 31 completed terminal. 32 33 The fourth paragraph is revised to read: 34 35 Measurement of beam guardrail Type 31 buried terminal Type 2 will be per linear foot for 36 the completed terminal. 37 38 The sixth paragraph is revised to read: 39 40 Measurement of beam guardrail anchor Type 10 will be per each for the completed 41 anchor, including the attachment of the anchor to the guardrail. 42 43 8-11.5 Payment 44 The Bid item “Beam Guardrail Anchor Type ___”, per each is revised to read “Beam Guardrail 45 Anchor Type 10”, per each. 46 47 The Bid item “Beam Guardrail Buried Terminal Type 1”, per each is deleted from this section. 48 49 The Bid item “Beam Guardrail Buried Terminal Type 2”, per linear foot and the following 50 paragraph are revised to read: 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 106 1 “Beam Guardrail Type 31 Buried Terminal Type 2”, per linear foot. 2 3 The unit Contract price per linear foot for “Beam Guardrail Type 31 Buried Terminal Type 4 2” shall be full payment for all costs to obtain and provide materials and perform the Work 5 as described in Section 8-11.3(1)C. 6 7 Section 8-14, Cement Concrete Sidewalks 8 April 2, 2018

9 8-14.2 Materials 10 In the first paragraph, the reference to “Portland Cement” is revised to read: 11 12 Cement 9-01 13 14 In the second paragraph, each reference to “Federal Standard 595” is revised to read “SAE 15 AMS Standard 595”. 16 17 Section 8-16, Concrete Slope Protection 18 April 2, 2018

19 8-16.2 Materials 20 In the first paragraph, the last two material references are revised to read: 21 22 Poured Portland Cement or Blended Hydraulic Cement 23 Concrete Slope Protection 9-13.5(2) 24 Pneumatically Placed Portland Cement or Blended 25 Hydraulic Cement Concrete Slope Protection 9-13.5(3) 26 27 SECTION 8-17, IMPACT ATTENUATOR SYSTEMS 28 April 5, 2010

29 8-17.4 Measurement 30 The first paragraph is supplemented with the following new sentence: 31 32 Only the maximum number of temporary impact attenuators installed at any one time 33 within the project limits will be measured for payment. 34 35 8-17.5 Payment 36 In the second paragraph following the bid item “Resetting Impact Attenuator”, the first sentence 37 is revised to read: 38 39 If an impact attenuator is damaged by a third party, repairs shall be made in accordance 40 with Section 1-07.13(4) under the Bid item “Reimbursement For Third Party Damage”. 41 42 Section 8-20, Illumination, Traffic Signal Systems, Intelligent Transportation 43 Systems, and Electrical 44

45 8-20.1(1) Regulations and Code

46 The last paragraph is revised to read:

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 107 1 2 Persons performing electrical Work shall be certified in accordance with and supervised 3 as required by RCW 19.28.161. Proof of certification shall be worn at all times in 4 accordance with WAC 296-46B-942. Persons failing to meet these certification 5 requirements may not perform any electrical work, and shall stop any active electrical 6 work, until their certification is provided and worn in accordance with this Section. 7 8 9 8-20.3(4) Foundations 10 The second sentence of the first paragraph is revised to read: 11 12 Concrete for Type II, III, IV, V, and CCTV signal standards and light standard foundations 13 shall be Class 4000P and does not require air entrainment. 14 15 8-20.3(5)A General 16 The last two sentences of the last paragraph is deleted. 17 18 This section is supplemented with the following: 19 20 All conduits shall include a pull tape with the equipment grounding conductor. The pull 21 tape shall be attached to the conduit near the end bell or grounded end bushing, or to 22 duct plugs or caps if present, at both ends of the conduit. 23 24 8-20.3(8) Wiring 25 The seventeenth paragraph is supplemented with the following: 26 27 Pulling tape shall meet the requirements of Section 9-29.1(10). Pull string may not be 28 used. 29 30 Section 8-21, Permanent Signing 31 August 3, 2015

32 8-21.2 Materials 33 This section is revised to read: 34 35 Materials shall meet the requirements of the following sections: 36 37 Roadside Sign Structures 9-06.16 38 Permanent Signs 9-28 39 Sign Support Structures 9-28.14 40 41 The Contractor shall submit a Manufacturer’s Certificate of Compliance for all permanent 42 signs; a copy of the Manufacturer’s Certificate of Compliance shall be available at the 43 fabricator’s plant. Permanent signs will be inspected at the fabricator’s plant prior to 44 shipment to the project unless otherwise accepted by the Engineer. Signs without an 45 approved decal shall not be installed on the project with the exception of double-faced 46 signs which do not receive decals or fabricator’s stickers. 47 48 8-21.3(9)F Foundations 49 The first sentence of the first paragraph is revised to read: 50 51 The excavation and backfill shall conform to the requirements of Section 2-09.3.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 108 1 2 Section 8-22, Pavement Marking 3 August 7, 2017

4 8-22.3(6) Removal of Pavement Markings 5 This section is revised to read: 6 7 Pavement markings to be removed shall be obliterated until all blemishes caused by 8 the pavement marking removal conform to the coloration of the adjacent pavement. 9 10 Grinding to remove pavement markings in their entirety is allowed in areas designated for 11 applications of either Hot Mix Asphalt (HMA) or Bituminous Surface Treatment (BST). 12 Pavement marking removal shall be performed from April 1st through September 30th and 13 only in those areas that shall be paved within the same time window as the grinding, 14 unless otherwise allowed by the Engineer in writing. 15 16 For all cement concrete pavement and areas that will not be overlaid with hot mix asphalt 17 or BST, grinding is allowed to a depth just above the pavement surface and then Water 18 blasting or shot blasting shall be required to remove the remaining pavement markings. 19 20 If in the opinion of the Engineer, the pavement is materially damaged by pavement 21 marking removal, such damage shall be repaired by the Contractor in accordance with 22 Section 1-07.13(1). Sand or other material deposited on the pavement as a result of 23 removing lines and markings shall be removed as the Work progresses to avoid 24 hazardous conditions. Accumulation of sand or other material which might interfere with 25 drainage will not be permitted. 26 27 8-22.4 Measurement 28 The first two sentences of the fourth paragraph are revised to read: 29 30 The measurement for “Painted Wide Lane Line”, “Plastic Wide Lane Line”, “Profiled 31 Plastic Wide Lane Line”, “Painted Barrier Center Line”, “Plastic Barrier Center Line”, 32 “Painted Stop Line”, “Plastic Stop Line”, “Painted Wide Dotted Entry Line”, or “Plastic 33 Wide Dotted Entry Line” will be based on the total length of each painted, plastic or 34 profiled plastic line installed. No deduction will be made for the unmarked area when the 35 marking includes a broken line such as, wide broken lane line, drop lane line, wide dotted 36 lane line or wide dotted entry line. 37 38 8-22.5 Payment 39 The following two new Bid items are inserted after the Bid item “Plastic Crosshatch Marking”, 40 per linear foot: 41 42 “Painted Wide Dotted Entry Line”, per linear foot. 43 44 “Plastic Wide Dotted Entry Line”, per linear foot. 45 46 Section 9-00, Definitions and Tests 47 January 7, 2019

48 9-00.4 Sieves for Testing Purposes 49 This section is revised to read: 50

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 109 1 Test sieves shall be made of either: (1) woven wire cloth conforming to ASTM E11, or (2) 2 square-hole, perforated plates conforming to ASTM E323. 3 4 9-00.7 Galvanized Hardware, AASHTO M 232 5 The first sentence is revised to read: 6 7 An acceptable alternate to hot-dip galvanizing in accordance with AASHTO M 232 will be 8 zinc coatings mechanically deposited in accordance with ASTM B695, providing the 9 minimum thickness of zinc coating is not less than that specified in AASHTO M 232, and 10 the process will not produce hydrogen embrittlement in the base metal. 11 12 Section 9-02, Bituminous Materials 13 April 6, 2015

14 9-02.1(4) Performance Graded Asphalt Binder (PGAB) 15 The first paragraph is supplemented with the following: 16 17 For HMA with greater than 20 percent RAP by total weight of HMA or any amount of RAS 18 the new asphalt binder, recycling agent and recovered asphalt (RAP and/or RAS) when 19 blended in the proportions of the mix design shall meet the PGAB requirements of 20 AASHTO M 320 Table 1 for the grade of asphalt binder specified by the Contract. 21 22 This section is supplemented with the following: 23 24 The recycling agent used to rejuvenate the recovered asphalt from recycled asphalt 25 pavement (RAP) and reclaimed asphalt shingles (RAS) shall meet the specifications in 26 Table 1: 27 Table 1 RA 1 RA 5 RA 25 ASTM Test Test Min. Max. Min. Max. Min. Max. Method Viscosity @ D2170 or 50 150 200 800 1000 4000 140˚F cSt D2171 Flashpoint D92 400 400 400 COC, ˚F Saturates, D2007 30 30 30 Wt. % Specific D70 or Report Report Report Gravity D2198 Tests on Residue D2872 from RTFC Viscosity 3 3 3 Ratio1 Mass 4 4 4 Change ± % 1Viscosity Ratio = RTFC Viscosity @ 140˚F, cSt Original Viscosity @ 140˚F, cSt 28 29

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 110 1 9-02.1(6)A Polymerized Cationic Emulsified Asphalt CRS-2P 2 In the ninth row of the table, “Test” is revised to read “Tests”. 3 4 The eleventh row in the table is revised to read: 5 Elastic Recovery % T 3012 50 6 7 The last two rows of the table are deleted. 8 9 Footnote 2 below the table is revised to read: 10 11 2 The residue material for T 301 shall come from the modified distillation per note 1. 12 13 Footnote 3 below the table is deleted. 14 15 The last paragraph is deleted. 16 17 Section 9-03, Aggregates 18 August 7, 2017

19 9-03.1(1) General Requirements 20 In this section, each reference to “Section 9-01.2(3)” is revised to read “Section 9-01.2(1)A”. 21 22 This first paragraph is supplemented with the following: 23 24 Reclaimed aggregate may be used if it complies with the specifications for Portland 25 Cement Concrete. Reclaimed aggregate is aggregate that has been recovered from 26 plastic concrete by washing away the cementitious materials. 27 28 9-03.1(2) Fine Aggregate for Portland Cement Concrete 29 This section is revised to read: 30 31 Fine aggregate shall consist of natural sand or manufactured sand, or combinations 32 thereof, accepted by the Engineer, having hard, strong, durable particles free from 33 adherent coating. Fine aggregate shall be washed thoroughly to meet the specifications. 34 35 9-03.1(2)A Deleterious Substances 36 This section is revised to read: 37 38 The amount of deleterious substances in the washed aggregate shall be tested in 39 accordance with AASHTO M 6 and not exceed the following values: 40 41 Material finer than No. 200 Sieve 2.5 percent by weight 42 Clay lumps and friable particles 3.0 percent by weight 43 Coal and lignite 0.25 percent by weight 44 Particles of specific gravity less than 2.00 1.0 percent by weight. 45 46 Organic impurities shall be tested in accordance with AASHTO T 21 by the glass 47 color standard procedure and results darker than organic plate no. 3 shall be 48 rejected. A darker color results from AASHTO T 21 may be used provided that when 49 tested for the effect of organic impurities on strength of mortar, the relative strength 50 at 7 days, calculated in accordance with AASHTO T 71, is not less than 95 percent.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 111 1 2 9-03.1(4) Coarse Aggregate for Portland Cement Concrete 3 This section is revised to read: 4 5 Coarse aggregate for concrete shall consist of gravel, crushed gravel, crushed stone, or 6 combinations thereof having hard, strong, durable pieces free from adherent coatings. 7 Coarse aggregate shall be washed to meet the specifications. 8 9 9-03.1(4)A Deleterious 10 This section, including title, is revised to read: 11 12 9-03.1(4)A Deleterious Substances 13 The amount of deleterious substances in the washed aggregate shall be tested in 14 accordance with AASHTO M 80 and not exceed the following values: 15 16 Material finer than No. 200 1.01 percent by weight 17 Clay lumps and Friable Particles 2.0 percent by weight 18 Shale 2.0 percent by weight 19 Wood waste 0.05 percent by weight 20 Coal and Lignite 0.5 percent by weight 21 Sum of Clay Lumps, Friable Particles, and 22 Chert (Less Than 2.40 specific gravity SSD) 3.0 percent by weight 23 24 1If the material finer than the No. 200 sieve is free of clay and shale, this percentage 25 may be increased to 1.5. 26 27 9-03.1(4)C Grading 28 The following new sentence is inserted at the beginning of the last pargraph: 29 30 Where coarse aggregate size 467 is used, the aggregate may be furnished in at least two 31 separate sizes. 32 33 9-03.1(5) Combined Aggregate Gradation for Portland Cement Concrete 34 This section is revised to read: 35 36 As an alternative to using the fine aggregate sieve grading requirements in Section 9- 37 03.1(2)B, and coarse aggregate sieve grading requirements in Section 9-03.1(4)C, a 38 combined aggregate gradation conforming to the requirements of Section 9-03.1(5)A may 39 be used. 40 41 9-03.1(5)A Deleterious Substances 42 This section is revised to read: 43 3 44 The amount of deleterious substances in the washed aggregates ⁄8 inch or larger shall 3 45 not exceed the values specified in Section 9-03.1(4)A and for aggregates smaller than ⁄8 46 inch they shall not exceed the values specified in Section 9-03.1(2)A. 47 48 9-03.1(5)B Grading 49 The first paragraph is deleted. 50

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 112 1 9-03.8(2) HMA Test Requirements 2 In the table in item number 3, the heading “Statistical and Nonstatistical” is revised to read 3 “Statistical”. 4 5 9-03.8(7) HMA Tolerances and Adjustments 6 In the table in item number 1, the column titled “Nonstatistical Evaluation” is deleted. 7 8 In the table in item 1, the last column titled “Commercial Evaluation” is revised to read “Visual 9 Evaluation”. 10 11 9-03.11(1) Streambed Sediment 12 The following three new sentences are inserted after the first sentence of the first paragraph: 13 14 Alternate gradations may be used if proposed by the Contractor and accepted by the 15 Engineer. The Contractor shall submit a Type 2 Working Drawing consisting of 0.45 16 power maximum density curve of the proposed gradation. The alternate gradation shall 17 closely follow the maximum density line and have Nominal Aggregate Size of no less than 18 1½ inches or no greater than 3 inches. 19 20 9-03.12(4) Gravel Backfill for Drains 21 The following new sentence is inserted at the beginning of the second paragraph: 22 23 As an alternative, AASHTO grading No. 57 may be used in accordance with Section 9- 24 03.1(4)C. 25 26 9-03.12(5) Gravel Backfill for Drywells 27 The following new sentence is inserted at the beginning of the second paragraph: 28 29 As an alternative, AASHTO grading No. 4 may be used in accordance with Section 9- 30 03.1(4)C. 31 32 9-03.21(1)B Concrete Rubble 33 This section, including title, is revised to read: 34 35 9-03.21(1)B Recycled Concrete Aggregate 36 Recycled concrete aggregates are coarse aggregates manufactured from hardened 37 concrete mixtures. Recycled concrete aggregate may be used as coarse aggregate or 38 blended with coarse aggregate for Commercial Concrete. Recycled concrete aggregate 39 shall meet all of the requirements for coarse aggregate contained in Section 9-03.1(4) or 40 9-03.1(5). In addition to the requirements of Section 9-03.1(4) or 9-03.1(5), recycled 41 concrete shall: 42 43 1. Contain an aggregated weight of less than 1 percent of adherent fines, 44 vegetable matter, plastics, plaster, paper, gypsum board, metals, fabrics, wood, 45 tile, glass, asphalt (bituminous) materials, brick, porcelain or other deleterious 46 substance(s) not otherwise noted; 47 48 2. Be free of components such as chlorides and reactive materials that are 49 detrimental to the concrete, unless mitigation measures are taken to prevent 50 recurrence in the new concrete; 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 113 1 3. Have an absorption of less than 10 percent when tested in accordance with 2 AASHTO T 85. 3 4 4. Be considered mechanically fractured and therefore be considered part of the 5 total fracture calculation as determined by the FOP for AASHTO T 335. 6 7 Recycled concrete aggregate shall be in a saturated condition prior to mixing. 8 9 Recycled concrete aggregate shall not be placed below the ordinary high water mark of 10 any surface water of the State. 11 12 9-03.21(1)D Recycled Steel Furnace Slag 13 This section title is revised to read: 14 15 Steel Slag 16 17 9-03.21(1)E Table on Maximum Allowable Percent (By Weight) of Recycled 18 Material 19 20 In the Hot Mix Asphalt column, each value of “20” is revised to read “25”. 21 22 The last column heading “Steel Furnace Slag” is revised to read “Steel Slag”. 23 24 The following new row is inserted after the second row: 25 Coarse Aggregate for Commercial Concrete 9-03.1(4) 0 100 0 0 26 27 28 Section 9-04, Joint and Crack Sealing Materials 29 January 3, 2017

30 This section is supplemented with the following two new subsections: 31 32 9-04.11 Butyl Rubber Sealant 33 Butyl rubber sealant shall conform to ASTM C 990. 34 35 9-04.12 External Sealing Band 36 External sealing band shall by Type III B conforming to ASTM C 877. 37 38 9-04.1(2) Premolded Joint Filler for Expansion Joints 39 This section is supplemented with the following: 40 41 As an alternative to the above, a semi-rigid, non-extruding, resilient type, closed-cell 42 polypropylene foam, preformed joint filler with the following physical properties as tested 43 to AASHTO T 42 Standard Test Methods may be used. 44 Closed-Cell Polypropylene Foam Preformed Joint Filler Physical Property Requirement Test Method Water Absorption < 1.0% AASHTO T 42 Compression Recovery > 80% AASHTO T 42 Extrusion < 0.1 in. AASHTO T 42

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 114 Density > 3.5 lbs./cu.ft. AASHTO T 42 Water Boil (1 hr.) No expansion AASHTO T 42 Hydrochloric Acid Boil (1 hr.) No disintegration AASHTO T 42 Heat Resistance °F 392°F± 5°F ASTM D 5249 1 2 9-04.2(1) Hot Poured Joint Sealants 3 This section’s content is deleted and replaced with the following new subsections: 4 5 9-04.2(1)A Hot Poured Sealant 6 Hot poured sealant shall be sampled in accordance with ASTM D5167 and tested in 7 accordance with ASTM D5329. 8 9 9-04.2(1)A1 Hot Poured Sealant for Cement Concrete Pavement 10 Hot poured sealant for cement concrete pavement shall meet the requirements of 11 ASTM D6690 Type IV, except for the following: 12 13 1. The Cone Penetration at 25°C shall be 130 maximum. 14 15 2. The extension for the Bond, non-immersed, shall be 100 percent. 16 17 9-04.2(1)A2 Hot Poured Sealant for Bituminous Pavement 18 Hot poured sealant for bituminous pavement shall meet the requirements of ASTM 19 D6690 Type I or Type II. 20 21 9-04.2(1)B Sand Slurry for Bituminous Pavement 22 Sand slurry is mixture consisting of the following components measured by total weight: 23 24 1. Twenty percent CSS-1 emulsified asphalt, 25 26 2. Two percent portland cement, and 27 28 3. Seventy-eight percent fine aggregate meeting the requirements of 9-03.1(2)B 29 Class 2. Fine aggregate may be damp (no free water). 30 31 9-04.2(2) Poured Rubber Joint Sealer 32 The last paragraph is deleted. 33 34 9-04.4(1) Rubber Gaskets for Concrete Pipes and Precast Manholes 35 “AASHTO M 198” is revised to read “ASTM C 990”. 36 37 9-04.4(3) Gaskets for Aluminum or Steel Culvert or Storm Sewer Pipe 38 In the last sentence, “AASHTO M 198” is revised to read “ASTM C 990”. 39 40 Section 9-05, Drainage Structures and Culverts 41 April 7, 2014

42 9-05.13 Ductile Iron Sewer Pipe 43 The first paragraph is deleted. 44

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 115 1 Section 9-06, Structural Steel and Related Materials 2 January 3, 2017

3 9-06.5(3) High-Strength Bolts 4 In this section, “ASTM A325” is revised to read “ASTM F3125 Grade A325”, “ASTM A490” is 5 revised to read “ASTM F3125 Grade A490”, and “ASTM F1852” is revised to read “ASTM 6 F3125 Grade F1852”. 7 8 In the fifth paragraph, “ASTM-A325” is revised to read “ASTM F3125”. 9 10 9-06.12 Bronze Castings 11 In this section, “AASHTO M107” is revised to read “ASTM B22”. 12 13 9-06.16 Roadside Sign Structures 14 In the first paragraph, “ASTM A325” is revised to read “ASTM F3125 Grade A325”. 15 16 Section 9-07, Reinforcing Steel 17 August 1, 2016

18 9-07.1(1)A Acceptance of Materials 19 The first sentence of the first paragraph is revised to read: 20 21 Reinforcing steel manufacturers shall comply with the National Transportation 22 Product Evaluation Program (NTPEP) Work Plan for Reinforcing Steel (rebar) 23 Manufacturers. 24 25 The first sentence of the second paragraph is revised to read: 26 27 Steel reinforcing bar manufacturers use either English or a Metric size designation while 28 stamping rebar. 29 30 9-07.1(2) Bending 31 The first two sentences of the first paragraph are deleted and replaced with the following two 32 new sentences: 33 34 Steel reinforcing bars shall be cut and bent cold to the shapes shown on the Plans. 35 Fabrication tolerances shall be in accordance with ACI 315. 36 37 Section 9-08, Paints and Related Materials 38 January 5, 2015

39 9-08.1(2)H Top Coat, Single Component, Moisture-Cured Polyurethane 40 The second paragraph is revised to read: 41 42 Color and Gloss: As specified in the Plans or Special Provisions 43 44 The last item in the requirements list is revised to read: 45 46 The top coat shall be a gloss or semi-gloss 47

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 116 1 9-08.1(8) Standard Colors 2 The second paragraph is deleted. 3 4 The third paragraph is revised to read: 5 6 Unless otherwise specified, all top or finish coats shall be gloss or semi-gloss, with the 7 paint falling within the range of greater than 70 for gloss and 35 to 70 for semi-gloss on 8 the 60-degree gloss meter. 9 10 Section 9-13, Riprap, Quarry Spalls, Slope Protection, and Rock for Erosion 11 and Scour Protection and Rock Walls 12 April 2, 2018

13 9-13.1(1) General 14 The last paragraph is revised to read: 15 16 Riprap and quarry spalls shall be free from segregation, seams, cracks, and other defects 17 tending to destroy its resistance to weather and shall meet the following test requirements: 18 19 9-13.5 Concrete Slope Protection 20 This section is revised to read: 21 22 Concrete slope protection shall consist of reinforced portland cement or blended hydraulic 23 cement concrete poured or pneumatically placed upon the slope with a rustication joint 24 pattern or semi-open concrete masonry units placed upon the slope closely adjoining 25 each other. 26 27 9-13.5(2) Poured Portland Cement Concrete Slope Protection 28 This section’s title is revised to read: 29 30 Poured Portland Cement or Blended Hydraulic Cement Concrete Slope 31 Protection 32 33 9-13.5(3) Pneumatically Placed Portland Cement Concrete Slope Protection 34 This section’s title is revised to read: 35 36 Pneumatically Placed Portland Cement or Blended Hydraulic Cement 37 Concrete Slope Protection 38 39 The first paragraph is revised to read: 40 41 Cement – This material shall be portland cement or blended hydraulic cement as 42 specified in Section 9-01. 43 44 9-13.7(1) Rock for Rock Walls and Chinking Material 45 The first paragraph (up until the colon) is revised to read: 46 47 Rock for rock walls and chinking material shall be hard, sound and durable material, 48 free from seams, cracks, and other defects tending to destroy its resistance to weather, 49 and shall meet the following test requirements: 50

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 117 1 Section 9-14, Erosion Control and Roadside Planting 2 August 6, 2018

3 9-14.4(2) Hydraulically Applied Erosion Control Products (HECPs) 4 In Table 1, the last four rows are deleted. 5 6 9-14.4(2)A Long-Term Mulch 7 The first paragraph is supplemented with the following: 8 9 Products containing cellulose fiber produced from paper or paper components will not be 10 accepted. 11 12 Table 2 is supplemented with the following new rows: 13 Water Holding Capacity ASTM D 7367 800 percent minimum Organic Matter Content AASHTO T 267 90 percent minimum Seed Germination ASTM D 7322 Long Term Enhancement 420 percent minimum 14 15 16 9-14.4(2)B Moderate-Term Mulch 17 This section is revised to read: 18 19 Within 48 hours of application, the Moderate-Term Mulch shall bond with the soil surface 20 to create a continuous, absorbent, flexible, erosion-resistant blanket. Moderate-Term 21 Mulch shall effectively perform the intended erosion control function in accordance with 22 Section 8-01.3(1) for a minimum of 3 months, or until temporary vegetation has been 23 established, whichever comes first. 24 25 Moderate-Term Mulch shall not be used in conjunction with permanent seeding. 26 27 9-14.4(2)C Short-Term Mulch 28 This section is revised to read: 29 30 Short-Term Mulch shall effectively perform the intended erosion control function in 31 accordance with Section 8-01.3(1) for a minimum of 2 months, or until temporary 32 vegetation has been established, whichever comes first. Short-Term Mulch shall not be 33 used in conjunction with permanent seeding. 34 35 Section 9-16, Fence and Guardrail 36 August 6, 2018

37 9-16.3(1) Rail Element 38 The last sentence of the first paragraph is revised to read: 39 40 All rail elements shall be formed from 12-gage steel except for thrie beam reducer 41 sections, reduced length thrie beam rail elements, thrie beams used for bridge rail 42 retrofits, and Design F end sections, which shall be formed from 10-gage steel. 43 44 9-16.3(5) Anchors 45 The last paragraph is revised to read:

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 118 1 2 Cement grout shall conform to Section 9-20.3(4) and consist of one part portland cement 3 or blended hydraulic cement and two parts sand. 4 5 Section 9-18, Precast Traffic Curb 6 April 2, 2018

7 9-18.1(1) Aggregates and Proportioning 8 Item number 1 of the first paragraph is revised to read: 9 10 1. Portland cement or blended hydraulic cement shall conform to the requirements of 11 Section 9-01 except that it may be Type I portland cement conforming to AASHTO M 12 85. 13 14 Section 9-20, Concrete Patching Material, Grout, and Mortar 15 January 3, 2017

16 This section is supplemented with the following new subsection: 17 18 9-20.5 Bridge Deck Repair Material 19 Bridge deck repair material shall be either an ultra-low viscosity, two-part liquid, 20 polyurethane-hybrid polymer concrete, or a pre-packaged cement based repair mortar, 21 conforming to the following requirements: 22 23 1. Minimum compressive strength of 2,500 psi, in accordance with ASTM C 109. 24 25 2. Total soluble chloride ion content by mass of product shall conform to the limits 26 specified in Section 6-02.3(2) for reinforced concrete. 27 28 3. Permeability of less than 2,000 coulombs at 56-days in accordance with 29 AASHTO T 277. 30 31 If pre-packaged deck repair material does not include coarse aggregate, the Contractor 32 shall extend the mix with coarse aggregate as recommended by the manufacturer. 33 34 Section 9-21, Raised Pavement Markers (RPM) 35 January 2, 2018

36 9-21.2 Raised Pavement Markers Type 2 37 This section’s content is deleted. 38 39 9-21.2(1) Physical Properties 40 This section, including title, is revised to read: 41 42 9-21.2(1) Standard Raised Pavement Markers Type 2 43 The marker housing shall contain reflective faces as shown in the Plans to reflect incident 44 light from either a single or opposite directions and meet the requirements of ASTM D 45 4280 including Flexural strength requirements. 46 47 9-21.2(2) Optical Requirements 48 This section, including title, is revised to read:

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 119 1 2 9-21.2(2) Abrasion Resistant Raised Markers Type 2 3 Abrasion Resistant Raised Markers Type 2 shall comply with Section 9-21.2(1) and meet 4 the requirements of ASTM D 4280 with the following additional requirement: The 5 coefficient of luminous intensity of the markers shall be measured after subjecting the 6 entire lens surface to the test described in ASTM D 4280 Section 9.5 using a sand drop 7 apparatus. After the exposure described above, retroreflected values shall not be less 8 than 0.5 times a nominal unblemished sample. 9 10 9-21.2(3) Strength Requirements 11 This section is deleted in its entirety. 12 13 Section 9-26, Epoxy Resins 14 January 7, 2019

15 9-26.1(1) General 16 The following new sentence is inserted after the first sentence of the first paragraph: 17 18 For pre-packaged cartridge kits, the epoxy bonding agent shall meet the requirements of 19 ASTM C881 when mixed according to manufacturer instructions, utilizing the 20 manufacturer’s mixing nozzle. 21 22 9-26.1(2) Packaging and Marking 23 The first sentence of the first paragraph is revised to read: 24 25 The components of the epoxy system furnished under these Specifications shall be 26 supplied in separate containers or pre-packaged cartridge kits that are non-reactive with 27 the materials contained. 28 29 The second paragraph is revised to read: 30 31 Separate containers shall be marked by permanent marking that identify the formulator, 32 “Component A” (contains the Epoxy Resin) and “Component B” (Contains the Curing 33 Agent), type, grade, class, lot or batch number, mixing instructions and the quantity 34 contained in pounds or gallons as defined by these Specifications. 35 36 The following new paragraph is inserted after the second paragraph: 37 38 Pre-packaged cartridge kits shall be marked by permanent marking that identify the 39 formulator, type, grade, class, lot or batch number, mixing instructions and the quantity 40 contained in ounces or milliliters as defined by these Specifications. 41 42 Section 9-28, Signing Materials and Fabrication 43 April 2, 2018

44 9-28.10 Vacant 45 This section, including title, is revised to read: 46 47 9-28.10 Digital Printing 48 Transparent and opaque durable inks used in digital printed sign messages shall be as 49 recommended by the manufacturer. When properly applied, digital printed colors shall

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 120 1 have a warranty life of the base retroreflective sign sheeting. Digital applied colors shall 2 present a smooth surface, free from foreign material, and all messages and borders shall 3 be clear and sharp. Digital printed signs shall conform to 70% of the retroreflective 4 minimum values established for its type and color. Digitally printed signs shall meet the 5 daytime color and luminance, and nighttime color requirements of ASTM D 4956. No 6 variations in color or overlapping of colors will be permitted. Digital printed permanent 7 traffic signs shall have an integrated engineered match component clear protective 8 overlay recommended by the sheeting manufacturer applied to the entire face of the sign. 9 On Temporary construction/maintenance signs printed with black ink only, the protective 10 overlay film is optional, as long as the finished sign has a warranty of a minimum of three 11 years from sign sheeting manufacturer. 12 13 All digital printed traffic control signs shall be an integrated engineered match component 14 system. The integrated engineered match component system shall consist of 15 retroreflective sheeting, durable ink(s), and clear overlay film all from the same 16 manufacturer applied to aluminum substrate conforming to Section 9-28.8. 17 18 The sign fabricator shall use an approved integrated engineered match component 19 system as listed on the Qualified Products List (QPL). Each approved digital printer shall 20 only use the compatible retroreflective sign sheeting manufacturer’s engineered match 21 component system products. 22 23 Each retroreflective sign sheeting manufacturer/integrated engineered match component 24 system listed on the QPL shall certify a department approved sign fabricator is approved 25 to operate their compatible digital printer. The sign fabricator shall re-certify annually with 26 the retroreflective sign manufacturer to ensure their digital printer is still meeting 27 manufacturer’s specifications for traffic control signs. Documentation of each re- 28 certification shall be submitted to the QPL Engineer annually. 29 30 9-28.11 Hardware 31 The last paragraph is revised to read: 32 33 All steel parts shall be galvanized in accordance with AASHTO M111. Steel bolts and 34 related connecting hardware shall be galvanized in accordance with ASTM F 2329. 35 36 9-28.14(2) Steel Structures and Posts 37 The first sentence of the third paragraph is revised to read: 38 39 Anchor rods for sign bridge and cantilever sign structure foundations shall conform to 40 Section 9-06.5(4), including Supplemental Requirement S4 tested at -20°F. 41 42 In the second sentence of the fourth paragraph, “AASHTO M232” is revised to read “ASTM F 43 2329”. 44 45 The first sentence of the fifth paragraph is revised to read: 46 47 Except as otherwise noted, steel used for sign structures and posts shall have a controlled 48 silicon content of either 0.00 to 0.06 percent or 0.15 to 0.25 percent. 49 50 The last sentence of the last paragraph is revised to read: 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 121 1 If such modifications are contemplated, the Contractor shall submit a Type 2 Working 2 Drawing of the proposed modifications. 3 4 Section 9-29, Illumination, Signal, Electrical 5 August 7, 2017

6 9-29.2 Junction Boxes, Cable Vaults, and Pull Boxes 7 This section is supplemented with the following new subsections: 8 9 9-29.2(5) Testing Requirements 10 The Contractor shall provide for testing of junction boxes, cable vaults and pull boxes. 11 Junction boxes, cable vaults and pull boxes shall be tested by an independent materials 12 testing facility, and a test report issued documenting the results of the tests performed. 13 14 For each junction box, vault and pull box type, the independent testing laboratory shall 15 meet the requirements of AASHTO R 18 for Qualified Tester and Verified Test Equipment. 16 The test shall be conducted in the presence of a Professional Engineer, licensed under 17 Title 18 RCW, State of Washington, in the branch of Civil or Structural, and each test 18 sheet shall have the Professional Engineer’s original signature, date of signature, original 19 seal, and registration number. One copy of the test report shall be furnished to the 20 Contracting Agency certifying that the box and cover meet or exceed the loading 21 requirements for that box type, and shall include the following information: 22 23 1. Product identification. 24 25 2. Date of testing. 26 27 3. Description of testing apparatus and procedure. 28 29 4. All load deflection and failure data. 30 31 5. Weight of box and cover tested. 32 33 6. Upon completion of the required test(s) the box shall be loaded to failure or to 34 the maximum load possible on the testing machine (70,000 pounds minimum). 35 36 7. A brief description of type and location of failure or statement that the testing 37 machine reached maximum load without failure of the box. 38 39 9-29.2(5)A Standard Duty Boxes and Vaults 40 Standard Duty Concrete Junction Boxes, Cable Vaults, and Pull Boxes shall be load 41 tested to 22,500 pounds. The test load shall be applied uniformly through a 10 by 10 42 by 1-inch steel plate centered on the lid. The test load shall be applied and released 43 ten times, and the deflection at the test load and released state shall be recorded for 44 each interval. At each interval the junction box shall be inspected for lid deformation, 45 failure of the lid/frame welds, vertical and horizontal displacement of the lid/frame, 46 cracks, and concrete spalling. 47 48 Concrete junction boxes will be considered to have withstood the test if none of the 49 following conditions are exhibited: 50

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 122 1 1. Permanent deformation of the lid or any impairment to the function of the 2 lid. 3 4 2. Vertical or horizontal displacement of the lid frame. 5 6 3. Cracks wider than 0.012 inches that extend 12 inches or more. 7 8 4. Fracture or cracks passing through the entire thickness of the concrete. 9 10 5. Spalling of the concrete. 11 12 9-29.2(5)B Retrofit Security Lids for Standard Duty Concrete Junction Boxes 13 Security lids used to retrofit existing Standard Duty Concrete Junction Boxes shall 14 be tested as follows: 15 16 1. The security lid shall be installed on any appropriately sized box that is 17 currently approved on the Qualified Products List. 18 19 2. The security lid and box assembly shall be load tested in accordance with 20 Section 9-29.2(5)A. After the ten load cycles but before loading to failure, 21 the security lid shall be fully opened and removed to verify operability. 22 23 3. The locking mechanism(s) shall be tested as follows: 24 25 a. The locking mechanism shall be cycled 250 times (locked, then 26 unlocked again) at room temperature (60-80°F). If there is more than 27 one identical locking mechanism, only one needs to be cycled in this 28 manner. 29 30 b. Temperature changes should be limited to no more than 60°F per hour. 31 32 c. The security lid shall be cooled to and held at -30°F for 15 minutes. The 33 locking mechanism shall then be cycled once to verify operation at this 34 temperature. 35 36 d. The security lid shall be heated to and held at 120-122°F for 15 37 minutes. The locking mechanism shall then be cycled once to verify 38 operation at this temperature. 39 40 e. The security lid shall be temperature adjusted to and held at 110°F and 41 95% humidity for 15 minutes. The locking mechanism shall then be 42 cycled once to verify operation at this temperature and humidity. 43 44 9-29.2(5)C Standard Duty Non-Concrete Junction Boxes 45 Non-concrete Junction Boxes shall be tested as defined in the ANSI/SCTE 77 Tier 46 15 test method using the test load of 22,500 pounds (minimum) in place of the design 47 load during testing. In addition, the Contractor shall provide a Manufacturer 48 Certificate of Compliance for each non-concrete junction box installed. 49 50 9-29.2(5)D Heavy-Duty Boxes and Vaults 51 Heavy-Duty Junction Boxes, Cable Vaults, and Pull Boxes shall be load tested to 52 46,000 pounds. The test load shall be applied vertically through a 10 by 20 by 1-inch

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 123 1 steel plate centered on the lid with an orientation both on the long axis and the short 2 axis of the junction box. The test load shall be applied and released ten times on 3 each axis. The deflection at the test load and released state shall be recorded for 4 each interval. At each interval the test box shall be inspected for lid deformation, 5 failure of the lid or frame welds, vertical and horizontal displacement of the lid frame, 6 cracks, and concrete spalling. After the twentieth loading interval the test shall be 7 terminated with a 60,000 pound load being applied vertically through the steel plate 8 centered on the lid and with the long edge of steel plate orientated parallel to the long 9 axis of the box. 10 11 Heavy-Duty Junction Boxes will be considered to have withstood the 46,000 pound 12 test if none of the following conditions are exhibited: 13 14 1. Permanent deformation of the lid or any impairment to the function of the 15 lid. 16 17 2. Vertical or horizontal displacement of the lid frame. 18 19 3. Cracks wider than 0.012 inches that extend 12 inches or more. 20 21 4. Fracture or cracks passing through the entire thickness of the concrete. 22 23 5. Spalling of the concrete. 24 25 Heavy-Duty Junction Boxes will be considered to have withstood the 60,000 pound 26 test if all of the following conditions are exhibited: 27 28 1. The lid is operational. 29 30 2. The lid is securely fastened. 31 32 3. The welds have not failed. 33 34 4. Permanent dishing or deformation of the lid is ¼ inch or less. 35 36 5. No buckling or collapse of the box. 37 38 9-29.2(1) Standard Duty and Heavy Duty Junction Boxes 39 This section, including title, is revised to read: 40 41 9-29.2(1) Junction Boxes 42 For the purposes of this Specification concrete is defined as portland cement concrete 43 and non-concrete is all others. 44 45 The Contractor shall provide shop drawings for all components, hardware, lid, frame, 46 reinforcement, and box dimensions. The shop drawings shall be prepared by (or under 47 the supervision of) a Professional Engineer, licensed under Title 18 RCW, State of 48 Washington, in the branch of Civil or Structural. Each sheet shall carry the following: 49 50 1. Professional Engineer’s original signature, date of signature, original seal, and 51 registration number. If a complete assembly drawing is included which

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 124 1 references additional drawing numbers, including revision numbers for those 2 drawings, then only the complete assembly drawing is required to be stamped. 3 4 2. The initials and dates of all participating design professionals. 5 6 3. Clear notation of all revisions including identification of who authorized the 7 revision, who made the revision, and the date of the revision. 8 9 Design calculations shall carry on the cover page, the Professional Engineer’s original 10 signature, date of signature, original seal, and registration number. 11 12 For each type of junction box, or whenever there is a change to the junction box design, 13 a proof test, as defined in this Specification, shall be performed and new shop drawings 14 submitted. 15 16 9-29.2(1)A Standard Duty Junction Boxes 17 This section is revised to read: 18 19 Standard Duty Junction Boxes are defined as Type 1, 2 and 8 junction boxes and shall 20 have a minimum load rating of 22,500 pounds and be tested in accordance with Section 21 9-29.2(5). A complete Type 8 Junction Box includes the spread footing shown in the 22 Standard Plans. All Standard Duty Junction Boxes placed in sidewalks, walkways, and 23 shared use paths shall have slip resistant surfaces. Non-slip lids and frames shall be hot 24 dip galvanized in accordance with AASHTO M111. 25 26 9-29.2(1)A1 Concrete Junction Boxes 27 The Standard Duty Concrete Junction Box steel frame, lid support, and lid shall be 28 painted with a black paint containing rust inhibiters or painted with a shop applied, 29 inorganic zinc primer in accordance with Section 6-07.3, or hot-dip galvanized in 30 accordance with AASHTO M 111. 31 32 Concrete used in Standard Duty Junction Boxes shall have a minimum compressive 33 strength of 6,000 psi when reinforced with a welded wire hoop, or 4,000 psi when 34 reinforced with welded wire fabric or fiber reinforcement. The frame shall be 35 anchored to the box by welding headed studs ⅜ by 3 inches long, as specified in 36 Section 9-06.15, to the frame. The wire fabric shall be attached to the studs and 37 frame with standard tie practices. The box shall contain ten studs located near the 38 centerline of the frame and box wall. The studs shall be placed one anchor in each 39 corner, one at the middle of each width and two equally spaced on each length of the 40 box. 41 42 Materials for Type 1, 2, and 8 Concrete Junction Boxes shall conform to the following: 43 Materials Requirement Concrete Section 6-02 Reinforcing Steel Section 9-07 Fiber Reinforcing ASTM C1116, Type III Lid ASTM A786 diamond plate steel Slip Resistant Lid ASTM A36 steel Frame ASTM A786 diamond plate steel or ASTM A36 steel Slip Resistant Frame ASTM A36 steel

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 125 Lid Support ASTM A36 steel, or ASTM A1011 SS Grade 36 (or higher) Handle & Handle support ASTM A36 steel, or ASTM A1011 CS (Any Grade) or SS (Any Grade) Anchors (studs) Section 9-06.15 Bolts, Studs, Nuts, Washers ASTM F593 or A193, Type 304 or 316, or Stainless Steel grade 302, 304, or 316 steel in accordance with approved shop drawing Locking and Latching In accordance with approved shop drawings Mechanism Hardware and Bolts 1 2 9-29.2(1)A2 Non-Concrete Junction Boxes 3 Material for the non-concrete junction boxes shall be of a quality that will provide for 4 a similar life expectancy as portland cement concrete in a direct burial application. 5 6 Type 1, 2, and 8 non-concrete junction boxes shall have a Design Load of 22,500 7 pounds and shall be tested in accordance with Section 9-29.2(5). Non-concrete 8 junction boxes shall be gray in color and have an open bottom design with 9 approximately the same inside dimensions, and present a load to the bearing surface 10 that is less than or equal to the loading presented by the concrete junction boxes 11 shown in the Standard Plans. Non-concrete junction box lids shall include a pull slot 12 and embedded 6 by 6 by ¼-inch steel plate, and shall be secured with two ½ inch 13 stainless steel Penta-head bolts recessed into the cover. The tapped holes for the 14 securing bolts shall extend completely through the box to prevent accumulation of 15 debris. Bolts shall conform to ASTM F593, stainless steel. 16 17 9-29.2(1)B Heavy-Duty Junction Boxes 18 The first paragraph is revised to read: 19 20 Heavy-Duty Junction Boxes are defined as Type 4, 5, and 6 junction boxes and shall be 21 concrete and have a minimum vertical load rating of 46,000 pounds without permanent 22 deformation and 60,000 pounds without failure when tested in accordance with Section 23 9-29.2(5). 24 25 9-29.2(1)C Testing Requirements 26 This section is deleted in its entirety. 27 28 9-29.2(2) Small Cable Vaults, Standard Duty Cable Vaults, Standard Duty Pull 29 Boxes, and Heavy Duty Pull Boxes 30 This section, including title, is revised to read: 31 32 9-29.2(2) Cable Vaults and Pull Boxes 33 Cable Vaults and Pull Boxes shall be constructed as a concrete box and as a concrete 34 lid. The lids for Cable Vaults and Pull Boxes shall be interchangeable and both shall fit 35 the same box as shown in the Standard Plans. 36 37 The Contractor shall provide shop drawings for all components, including concrete box, 38 Cast Iron Ring, Ductile Iron Lid, Steel Rings, and Lid. In addition, the shop drawings shall 39 show placement of reinforcing steel, knock outs, and any other appurtenances. The shop 40 drawing shall be prepared by or under the direct supervision of a Professional Engineer,

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 126 1 licensed under Title 18 RCW, State of Washington, in the branch of Civil or Structural. 2 Each sheet shall carry the following: 3 4 1. Professional Engineer’s original signature, date of signature, original seal, and 5 registration number. If a complete assembly drawing is included which 6 references additional drawing numbers, including revision numbers for those 7 drawings, then only the complete assembly drawing is required to be stamped. 8 9 2. The initials and dates of all participating design professionals. 10 11 3. Clear notation of all revisions including identification of who authorized the 12 revision, who made the revision, and the date of the revision. 13 14 Design calculations shall carry on the cover page, the Professional Engineer’s original 15 signature, date of signature, original seal, and registration number. 16 17 For each type of box or whenever there is a change to the Cable Vault or Pull box design, 18 a proof test, as defined in this Specification, shall be performed and new shop drawings 19 submitted. 20 21 9-29.2(2)A Small Cable Vaults, Standard Duty Cable Vaults, and Standard Duty 22 Pull Boxes 23 This section’s title is revised to read: 24 25 9-29.2(2)A Standard Duty Cable Vaults and Pull Boxes 26 27 The first paragraph is revised to read: 28 29 Standard Duty Cable Vaults and Pull Boxes shall be concrete and have a minimum load 30 rating of 22,500 pounds and be tested in accordance with Section 9-29.2(5). For the 31 purposes of this Section, Small Cable Vaults are considered a type of Standard Duty 32 Cable Vault. 33 34 The first sentence of the second paragraph is revised to read: 35 36 Concrete for Standard Duty Cable Vaults and Pull Boxes shall have a minimum 37 compressive strength of 4,000 psi. 38 39 The first sentence of the third paragraph is revised to read: 40 41 All Standard Duty Cable Vaults and Pull Boxes placed in sidewalks, walkways, and 42 shared-use paths shall have slip-resistant surfaces. 43 44 The fourth paragraph (up until the colon) is revised to read: 45 46 Materials for Standard Duty Cable Vaults and Pull Boxes shall conform to the following: 47 48 9-29.2(2)B Heavy-Duty Cable Vaults and Pull Boxes 49 The first paragraph is revised to read: 50 51 Heavy-Duty Cable Vaults and Pull Boxes shall be constructed of concrete having a 52 minimum compressive strength of 4,000 psi, and have a minimum vertical load rating of

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 127 1 46,000 pounds without permanent deformation and 60,000 pounds without failure when 2 tested in accordance with Section 9-29.2(5). 3 4 9-29.2(3) Structure Mounted Junction Boxes 5 The first and second paragraphs are revised to read: 6 7 Surface mounted junction boxes and concrete embedded junction boxes installed in cast- 8 in-place structures shall be stainless steel NEMA 4X. 9 10 Concrete embedded junction boxes installed in structures constructed by slip forming 11 shall be stainless steel NEMA 3R and shall be adjustable for depth, with depth adjustment 12 bolts, which are accessible from the front face of the junction box with the lid installed. 13 14 9-29.3(1) Fiber Optic Cable 15 This section is revised to read: 16 17 All fiber optic cables shall be single mode fiber optic cables unless otherwise specified in 18 the Contract. All fiber optic cables shall meet the following requirements: 19 20 1. Compliance with the current version of ANSI/ICEA S-87-640. A product data 21 specification sheet clearly identifying compliance or a separate letter from 22 manufacturer to state compliance shall be provided. 23 24 2. Cables shall be gel free, loose tube, low water peak, and all dielectric with no 25 metallic component. 26 27 3. Cables shall not be armored unless specified in the Contract. 28 29 4. Cables shall be approved for mid-span entries and be rated by the manufacturer 30 for outside plant (OSP) use, placement in underground ducts, and aerial 31 installations. 32 33 5. Fiber counts shall be as specified in the Contract. 34 35 6. Fibers and buffer tubes shall be color coded in accordance with the current 36 version of EIA/TIA-598. 37 38 7. Fibers shall not have any factory splices. 39 40 8. Outer Jacket shall be Type M (Medium Density Polyethylene). Outer jacket shall 41 be free from holes, splits, blisters, or other imperfections and must be smooth 42 and concentric as is consistent with the best commercial practice. 43 44 9. A minimum of one (1) rip cord is required for each cable. 45 46 10. Cable markings shall meet the following additional requirements: 47 48 a. Color shall be white or silver. 49 50 b. Markings shall be approximately 3 millimeters (118 mils) in height, and 51 dimensioned and spaced to produce good legibility. 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 128 1 c. Markings shall include the manufacturer’s name, year of manufacture, the 2 number of fibers, the words “OPTICAL CABLE”, and sequential length 3 marks. 4 5 d. Sequential length markings shall be in meters or feet, spaced at intervals 6 not more than 1 meter or 2 feet apart, respectively. 7 8 e. The actual cable length shall not be shorter than the cable length marking. 9 The actual cable length may be up to 1% longer than the cable length 10 marking. 11 12 f. Cables with initial markings that do not meet these requirements will not be 13 accepted and may not be re-marked. 14 15 11. Short term tensile strength shall be a minimum of 600 pounds (1bs). Long term 16 tensile strength shall be a minimum of 180 pounds (1bs). Tensile strength shall 17 be achieved using a fiberglass reinforced plastic (FRP) central member and / or 18 aramid yarns. 19 20 12. All cables shall be new and free of material or manufacturing defects and 21 dimensional non-uniformity that would: 22 23 a. Interfere with the cable installation using accepted cable installation 24 practices; 25 26 b. Degrade the transmission performance or environmental resistance after 27 installation; 28 29 c. Inhibit proper connection to interfacing elements; 30 31 d. Otherwise yield an inferior product. 32 33 13. The fiber optic cables shall be shipped on reels with a drum diameter at least 20 34 times the diameter of the cable, in order to prevent damage to the cable. The 35 reels shall be substantial and constructed so as to prevent damage during 36 shipment and handling. Reels shall be labeled with the same information 37 required for the cable markings, with the exception that the total length of cable 38 shall be marked instead of incremental length marks. Reels shall also be labeled 39 with the type of cable. 40 41 This section is supplemented with the following new subsection: 42 43 9-29.3(1)B Multimode Optical Fibers 44 Where multimode fiber optic cables are specified in the Contract, the optical fibers shall 45 be one of the following types, as specified in the Contract: 46 47 a. Type OM1, meeting the requirements of EIA/TIA 492-AAAA-A or ISO/IEC 11801. 48 The fiber core diameter shall be 62.5 µm. 49 50 b. Type OM2, meeting the requirements of EIA/TIA 492-AAAB-A or ISO/IEC 11801. 51 The fiber core diameter shall be 50 µm. 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 129 1 All multimode optical fibers shall have a maximum attenuation of 3.0 dB/km at 850nm and 2 1.0 dB/km at 1300nm. Completed cable assemblies shall be rated for 1000BaseLX 3 Ethernet communications. 4 5 9-29.3(1)A Singlemode Fiber Optic Cable 6 This section is revised to read: 7 8 Single-Mode optical fibers shall be EIA/TIA 492-CAAB or ISO/IEC 11801 Type OS2, low 9 water peak zero dispersion fibers, meeting the requirements of ITU-T G.652.D. 10 11 9-29.6 Light and Signal Standards 12 The third paragraph is revised to read: 13 14 Light standard, signal standards, slip base hardware and foundation hardware shall be 15 hot dip galvanized in accordance with AASHTO M 111 and AASHTO M 232. Where 16 colored standards are required, standards shall be powder-coated after galvanizing in 17 accordance with Section 6-07.3(11). The standard color shall be as specified in the 18 Contract. 19 20 9-29.6(1) Steel Light and Signal Standards 21 In the first paragraph, “ASTM A325” is revised to read “ASTM F3125 Grade A325”. 22 23 9-29.6(2) Slip Base Hardware 24 In this section, “ASTM A325” is revised to read “ASTM F3125 Grade A325”. 25 26 9-29.7(2) Fused Quick-Disconnect Kits 27 The table is supplemented with the following new row: 28 LED* 10A 10A 20A 29 30 The following footnote is inserted after the table: 31 32 * Applies to all LED luminaires, regardless of wattage. Fuses for LED luminaires shall 33 be slow blow. 34 35 9-29.10 Luminaires 36 The first sentence of the third paragraph is revised to read: 37 38 All luminaires shall be provided with markers for positive identification of light source type 39 and wattage in accordance with ANSI C136.15-2011, with the exception that LED 40 luminaires shall be labeled with the wattage of their conventional luminaire equivalents – 41 the text “LED” is optional. 42 43 The table in the fourth paragraph is revised to read: 44 Conventional Lamp Conventional Wattage Equivalent LED Wattage Legend Legend 70 7 7E 100 10 10E 150 15 15E 175 17 17E

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 130 200 20 20E 250 25 25E 310 31 31E 400 40 40E 700 70 70E 750 75 75E 1,000 X1 X1E 1 2 9-29.13(10)C NEMA Controller Cabinets 3 Item number 6 of the first paragraph is revised to read: 4 5 6. LED light strips shall be provided for cabinet lighting. Each LED light strip shall be 6 approximately 12 inches long, have a minimum output of 320 lumens, and have a 7 color temperature of 4100K (cool white) or higher. Two light strips shall be provided. 8 One light strip shall be ceiling mounted and oriented parallel to the door face. The 9 second light strip shall be mounted under the lower shelf, such that the output 10 terminal landings are illuminated. Lighting shall not interfere with the proper 11 operation of any other ceiling or shelf mounted equipment. All lighting fixtures shall 12 energize automatically when any door is opened. Each door switch shall be labeled 13 “Light”. 14 15 9-29.13(10)D Cabinets for Type 170E and 2070 Controllers 16 Item number 6 of the first paragraph is revised to read: 17 18 6. LED light strips shall be provided for cabinet lighting, powered from the Equipment 19 breaker on the Power Distribution Assembly. Each LED light strip shall be 20 approximately 12 inches long, have a minimum output of 320 lumens, and have a 21 color temperature of 4100K (cool white) or higher. There shall be two light strips for 22 each rack within the cabinet. Lighting shall be ceiling mounted – rack mounted 23 lighting is not permitted. One light strip shall be installed above the front of the rack, 24 oriented parallel to the door face, and placed such that the front of the rack and the 25 rack mounted equipment is illuminated. The second light strip shall be installed 26 above the rear of the rack, oriented perpendicular to the door face, and placed such 27 that the interior of the rack is illuminated. Lighting shall not interfere with the proper 28 operation of any other ceiling mounted equipment. All lighting fixtures above a rack 29 shall energize automatically when either door to that respective rack is opened. Each 30 door switch shall be labeled “Light”. 31 32 9-29.13(12) ITS Cabinet 33 Item number 6 of the first paragraph is revised to read: 34 35 6. LED light strips shall be provided for cabinet lighting, powered from the Equipment 36 breaker on the Power Distribution Assembly. Each LED light strip shall be 37 approximately 12 inches long, have a minimum output of 320 lumens, and have a 38 color temperature of 4100K (cool white) or higher. There shall be two light strips for 39 each rack within the cabinet. Lighting shall be ceiling mounted – rack mounted 40 lighting is not permitted. One light strip shall be installed above the front of the rack, 41 oriented parallel to the door face, and placed such that the front of the rack and the 42 rack mounted equipment is illuminated. The second light strip shall be installed 43 above the rear of the rack, oriented perpendicular to the door face, and placed such 44 that the interior of the rack is illuminated. Lighting shall not interfere with the proper 45 operation of any other ceiling mounted equipment. All lighting fixtures above a rack

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 131 1 shall energize automatically when either door to that respective rack is opened. Each 2 door switch shall be labeled “Light”. 3 4 9-29.25 Amplifier, Transformer, and Terminal Cabinets 5 Item 2C is revised to read: 6 7 c. Transformer up to 12.5 KVA 20″ 48″ 24″ 8 Transformer 12.6 to 35 KVA 30″ 60″ 32″ 9 10 The following new sentence is inserted before the last sentence of item number 10: 11 12 There shall be an isolation breaker on the input (line) side of the transformer, and a 13 breaker array on the output (load) side. 14 15 Section 9-33, Construction Geosynthetic 16 August 6, 2018

17 9-33.4(1) Geosynthetic Material Approval 18 The second sentence of the first paragraph is revised to read: 19 20 If the geosynthetics material is not listed in the current WSDOT QPL, a Manufacturer’s 21 Certificate of Compliance including Certified Test Reports of each proposed geosynthetic 22 shall be submitted to the State Materials Laboratory in Tumwater for evaluation. 23 24 The last paragraph is revised to read: 25 26 Geosynthetics used as reinforcement in permanent geosynthetic retaining walls, 27 reinforced slopes, reinforced embankments, and other geosynthetic reinforcement 28 applications require proof of compliance with the National Transportation Product 29 Evaluation Program (NTPEP) in accordance with AASHTO Standard Practice R 69, 30 Standard Practice for Determination of Long-Term Strength for Geosynthetic 31 Reinforcement. 32 33 Section 9-34, Pavement Marking Material 34 January 5, 2015

35 9-34.2 Paint 36 The second paragraph is revised to read: 37 38 Blue and black paint shall comply with the requirements of yellow paint in Section 9- 39 34.2(4) and Section 9-34.2(5), with the exception that blue and black paints do not need 40 to meet the requirements for titanium dioxide, directional reflectance, and contrast ratio. 41 42 9-34.4 Glass Beads for Pavement Marking Materials 43 In the third paragraph, the table titled “Metal Concentration Limits” is revised to read: 44 Metal Concentration Limits Element Test Method Max. Parts Per Million (ppm) Arsenic EPA 3052 SW-846 6010C 10.0 Barium EPA 3052 SW-846 6010C 100.0 Cadmium EPA 3052 SW-846 6010C 1.0

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 132 Chromium EPA 3052 SW-846 6010C 5.0 Lead EPA 3052 SW-846 6010C 50.0 Silver EPA 3052 SW-846 6010C 5.0 Mercury EPA 3052 SW-846 7471B 4.0 1 2 3 9-34.5 Temporary Pavement Marking Tape 4 This section is revised to read: 5 6 Biodegradable tape with paper backing is not allowed. 7 8 This section is supplemented with the following new sub-sections: 9 10 9-34.5(1) Temporary Pavement Marking Tape – Short Duration 11 Temporary pavement marking tape for short duration shall conform to ASTM D4592 Type 12 II except that black tape, black mask tape and the black portion of the contrast removable 13 tape, shall be non-reflective. 14 15 9-34.5(2) Temporary Pavement Marking Tape – Long Duration 16 Temporary pavement marking tape for long duration shall conform to ASTM D4592 Type 17 I. Temporary pavement marking tape for long duration, except for black tape, shall have 18 a minimum initial coefficient of retroreflective luminance of 200 mcd*m-2*lx-1 when 19 measured in accordance with ASTM E 2832 or ASTM E 2177. Black tape, black mask 20 tape and the black portion of the contrast removable tape, shall be non-reflective. 21 22 9-34.6 Temporary Raised Pavement Markers 23 This section’s title is revised to read: 24 25 Temporary Flexible Raised Pavement Markers 26 27 The second paragraph is deleted. 28 29

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 133 1 This page has been left blank intentionally.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 134 1 2 INTRODUCTION TO THE SPECIAL PROVISIONS 3 4 (August 14, 2013 APWA GSP) 5 6 The work on this project shall be accomplished in accordance with the Standard Specifications 7 for Road, Bridge and Municipal Construction, 2018 edition, as issued by the Washington State 8 Department of Transportation (WSDOT) and the American Public Works Association (APWA), 9 Washington State Chapter (hereafter “Standard Specifications”). The Standard 10 Specifications, as modified or supplemented by the Amendments to the Standard 11 Specifications and these Special Provisions, all of which are made a part of the Contract 12 Documents, shall govern all of the Work. 13 14 These Special Provisions are made up of both General Special Provisions (GSPs) from 15 various sources, which may have project-specific fill-ins; and project-specific Special 16 Provisions. Each Provision either supplements, modifies, or replaces the comparable 17 Standard Specification, or is a new Provision. The deletion, amendment, alteration, or addition 18 to any subsection or portion of the Standard Specifications is meant to pertain only to that 19 particular portion of the section, and in no way should it be interpreted that the balance of the 20 section does not apply. 21 22 The project-specific Special Provisions are not labeled as such. The GSPs are labeled under 23 the headers of each GSP, with the effective date of the GSP and its source. For example: 24 25 (March 8, 2013 APWA GSP) 26 (April 1, 2013 WSDOT GSP) 27 (May 1, 2013 SkagitR GSP) 28 29 Also incorporated into the Contract Documents by reference are: 30 • Manual on Uniform Traffic Control Devices for Streets and Highways, currently adopted 31 edition, with Washington State modifications, if any 32 • Standard Plans for Road, Bridge and Municipal Construction, WSDOT/APWA, current 33 edition 34 35 Contractor shall obtain copies of these publications, at Contractor’s own expense. 36 37

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 135 1 2 Division 1 3 General Requirements 4 5 DESCRIPTION OF WORK 6 (March 13, 1995) 7 8 Schedule A: McLean Road 9 10 Schedule B: Cook Road 11 12 This Contract provides for improvement of two Skagit County Roads, all in accordance with 13 the attached Contract Plans, these Contract Provisions, and the 2018 Standard Specifications. 14 15 Schedule A includes, but is not limited to: planing full length and width of existing asphalt for 16 approximately 1.70 miles; hauling planings to a County determined site; placing and 17 compacting a 0.15 ft. HMA Cl. ⅜” PG 58H-22 wearing course on the planed surface with a 18 Material Transfer Device (MTD); pavement repair; placement of temporary pavement markers; 19 providing erosion control; trimming and cleanup; traffic control; signage; and other work. 20 21 Schedule B includes, but is not limited to: planing and paving of existing road surface for 22 approximately 0.10 mile; hauling planings to a County determined site; placing and 23 compacting a 0.15 ft. HMA Cl. ⅜” PG 58H-22 wearing course on the planed surface; pavement 24 repair; working within BNSF Railway right-of-way; placement of plastic pavement lines; 25 replacement of traffic loops; providing erosion control; trimming and cleanup; traffic control; 26 signage; and other work. 27 28 1-01.3 Definitions 29 (January 4, 2016 APWA GSP) 30 31 Delete the heading Completion Dates and the three paragraphs that follow it, and replace 32 them with the following: 33 34 Dates 35 Bid Opening Date 36 The date on which the Contracting Agency publicly opens and reads the Bids. 37 Award Date 38 The date of the formal decision of the Contracting Agency to accept the lowest 39 responsible and responsive Bidder for the Work. 40 Contract Execution Date 41 The date the Contracting Agency officially binds the Agency to the Contract. 42 Notice to Proceed Date 43 The date stated in the Notice to Proceed on which the Contract time begins. 44 Substantial Completion Date 45 The day the Engineer determines the Contracting Agency has full and unrestricted 46 use and benefit of the facilities, both from the operational and safety standpoint, any 47 remaining traffic disruptions will be rare and brief, and only minor incidental work, 48 replacement of temporary substitute facilities, plant establishment periods, or 49 correction or repair remains for the Physical Completion of the total Contract.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 136 1 Physical Completion Date 2 The day all of the Work is physically completed on the project. All documentation 3 required by the Contract and required by law does not necessarily need to be 4 furnished by the Contractor by this date. 5 Completion Date 6 The day all the Work specified in the Contract is completed and all the obligations of 7 the Contractor under the contract are fulfilled by the Contractor. All documentation 8 required by the Contract and required by law must be furnished by the Contractor 9 before establishment of this date. 10 Final Acceptance Date 11 The date on which the Contracting Agency accepts the Work as complete. 12 13 Supplement this Section with the following: 14 15 All references in the Standard Specifications, Amendments, or WSDOT General Special 16 Provisions, to the terms “Department of Transportation”, “Washington State 17 Transportation Commission”, “Commission”, “Secretary of Transportation”, “Secretary”, 18 “Headquarters”, and “State Treasurer” shall be revised to read “Contracting Agency”. 19 20 All references to the terms “State” or “state” shall be revised to read “Contracting 21 Agency” unless the reference is to an administrative agency of the State of Washington, 22 a State statute or regulation, or the context reasonably indicates otherwise. 23 24 All references to “State Materials Laboratory” shall be revised to read “Contracting 25 Agency designated location”. 26 27 All references to “final contract voucher certification” shall be interpreted to mean the 28 Contracting Agency form(s) by which final payment is authorized, and final completion 29 and acceptance granted. 30 31 Additive 32 A supplemental unit of work or group of bid items, identified separately in the Bid 33 Proposal, which may, at the discretion of the Contracting Agency, be awarded in addition 34 to the base bid. 35 36 Alternate 37 One of two or more units of work or groups of bid items, identified separately in the Bid 38 Proposal, from which the Contracting Agency may make a choice between different 39 methods or material of construction for performing the same work. 40 41 Business Day 42 A business day is any day from Monday through Friday except holidays as listed in 43 Section 1-08.5. 44 45 Contract Bond 46 The definition in the Standard Specifications for “Contract Bond” applies to whatever 47 bond form(s) are required by the Contract Documents, which may be a combination of a 48 Payment Bond and a Performance Bond. 49 50 Contract Documents 51 See definition for “Contract”. 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 137 1 Contract Time 2 The period of time established by the terms and conditions of the Contract within which 3 the Work must be physically completed. 4 5 Notice of Award 6 The written notice from the Contracting Agency to the successful Bidder signifying the 7 Contracting Agency’s acceptance of the Bid Proposal. 8 9 Notice to Proceed 10 The written notice from the Contracting Agency or Engineer to the Contractor authorizing 11 and directing the Contractor to proceed with the Work and establishing the date on which 12 the Contract time begins. 13 14 Traffic 15 Both vehicular and non-vehicular traffic, such as pedestrians, bicyclists, wheelchairs, and 16 equestrian traffic. 17 18 1-02 BID PROCEDURES AND CONDITIONS 19 20 1-02.1 Prequalification of Bidders 21 22 Delete this section and replace it with the following: 23 24 1-02.1 Qualifications of Bidder 25 (January 24, 2011 APWA GSP) 26 27 Before award of a public works contract, a bidder must meet at least the minimum 28 qualifications of RCW 39.04.350(1) to be considered a responsible bidder and qualified to 29 be awarded a public works project. 30 31 1-02.2 Plans and Specifications 32 (June 27, 2011 APWA GSP) 33 34 Delete this section and replace it with the following: 35 36 Information as to where Bid Documents can be obtained or reviewed can be found in the 37 Call for Bids (Advertisement for Bids) for the work. 38 39 After award of the contract, plans and specifications will be issued to the Contractor at no 40 cost as detailed below: 41 To Prime Contractor No. of Sets Basis of Distribution Reduced plans (11" x 17") 4 Furnished automatically upon award. Contract Provisions 4 Furnished automatically upon award.

Large plans (e.g., 22" x 34") 2 Furnished only upon request.

42

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 138 1 Additional plans and Contract Provisions may be obtained by the Contractor from the 2 source stated in the Call for Bids, at the Contractor’s own expense. 3 4 1-02.4 Examination of Plans, Specifications and Site of Work 5 6 1-02.4(1) General 7 (August 15, 2016 APWA GSP Option B) 8 9 The first sentence of the last paragraph is revised to read: 10 11 Any prospective Bidder desiring an explanation or interpretation of the Bid Documents, 12 shall request the explanation or interpretation in writing by close of business, 5 13 business days preceding the bid opening to allow a written reply to reach all 14 prospective Bidders before the submission of their Bids. 15 16 1-02.5 Proposal Forms 17 (July 31, 2017 APWA GSP) 18 19 Delete this section and replace it with the following: 20 21 The Proposal Form will identify the project and its location and describe the work. It will 22 also list estimated quantities, units of measurement, the items of work, and the materials 23 to be furnished at the unit bid prices. The bidder shall complete spaces on the proposal 24 form that call for, but are not limited to, unit prices; extensions; summations; the total bid 25 amount; signatures; date; and, where applicable, retail sales taxes and acknowledgment 26 of addenda; the bidder’s name, address, telephone number, and signature; the bidder’s 27 UDBE/DBE/M/WBE commitment, if applicable; a State of Washington Contractor’s 28 Registration Number; and a Business License Number, if applicable. Bids shall be 29 completed by typing or shall be printed in ink by hand, preferably in black ink. The 30 required certifications are included as part of the Proposal Form. 31 32 The Contracting Agency reserves the right to arrange the proposal forms with alternates 33 and additives, if such be to the advantage of the Contracting Agency. The bidder shall 34 bid on all alternates and additives set forth in the Proposal Form unless otherwise 35 specified. 36 37 1-02.6 Preparation of Proposal 38 39 Add the following new section 1-02.6(1): 40 41 1-02.6(1) Recycled Materials Proposal 42 (January 4, 2016 APWA GSP) 43 44 The Bidder shall submit with the Bid, its proposal for incorporating recycled materials into 45 the project, using the form provided in the Contract Provisions. 46 47 1-02.7 Bid Deposit 48 (March 8, 2013 APWA GSP) 49 50 Supplement this section with the following: 51 52 Bid bonds shall contain the following:

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 139 1 1. Contracting Agency-assigned number for the project; 2 2. Name of the project; 3 3. The Contracting Agency named as obligee; 4 4. The amount of the bid bond stated either as a dollar figure or as a percentage which 5 represents five percent of the maximum bid amount that could be awarded; 6 5. Signature of the bidder’s officer empowered to sign official statements. The signature 7 of the person authorized to submit the bid should agree with the signature on the 8 bond, and the title of the person must accompany the said signature; 9 6. The signature of the surety’s officer empowered to sign the bond and the power of 10 attorney. 11 12 If so stated in the Contract Provisions, bidder must use the bond form included in the 13 Contract Provisions. 14 15 If so stated in the Contract Provisions, cash will not be accepted for a bid deposit. 16 17 1-02.9 Delivery of Proposal 18 (July 14, 2016 SkagitR) 19 20 Delete Section 1-02.9 and replace it with the following: 21 22 Each proposal shall be submitted in a sealed envelope, with the Project Name and Project 23 Number as stated in the Call for Bids clearly marked on the outside of the envelope, or 24 as otherwise required in the Bid Documents, to ensure proper handling and delivery. 25 26 The Contracting Agency will not open or consider any Bid Proposal that is received after 27 the time specified in the Call for Bids for receipt of Bid Proposals, or received in a location 28 other than that specified in the Call for Bids. 29 30 1-02.10 Withdrawing, Revising, or Supplementing Proposal 31 (July 23, 2015 APWA GSP) 32 33 Delete this section, and replace it with the following: 34 35 After submitting a physical Bid Proposal to the Contracting Agency, the Bidder may 36 withdraw, revise, or supplement it if: 37 38 1. The Bidder submits a written request signed by an authorized person and 39 physically delivers it to the place designated for receipt of Bid Proposals, and 40 2. The Contracting Agency receives the request before the time set for receipt of 41 Bid Proposals, and 42 3. The revised or supplemented Bid Proposal (if any) is received by the Contracting 43 Agency before the time set for receipt of Bid Proposals. 44 45 If the Bidder’s request to withdraw, revise, or supplement its Bid Proposal is received 46 before the time set for receipt of Bid Proposals, the Contracting Agency will return the 47 unopened Proposal package to the Bidder. The Bidder must then submit the revised or 48 supplemented package in its entirety. If the Bidder does not submit a revised or 49 supplemented package, then its bid shall be considered withdrawn. 50

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 140 1 Late revised or supplemented Bid Proposals or late withdrawal requests will be date 2 recorded by the Contracting Agency and returned unopened. Mailed, emailed, or faxed 3 requests to withdraw, revise, or supplement a Bid Proposal are not acceptable. 4 5 1-02.12 Public Opening Of Proposal 6 (July 14, 2016 SkagitR) 7 8 Section 1-02.12 is supplemented with the following: 9 10 Sealed bids shall be received at the time and location specified in the Call for Bids, unless 11 modified by addenda. 12 13 1-02.13 Irregular Proposals 14 (June 20, 2017 APWA GSP) 15 16 Delete this section and replace it with the following: 17 18 1. A Proposal will be considered irregular and will be rejected if: 19 a. The Bidder is not prequalified when so required; 20 b. The authorized Proposal form furnished by the Contracting Agency is not 21 used or is altered; 22 c. The completed Proposal form contains any unauthorized additions, deletions, 23 alternate Bids, or conditions; 24 d. The Bidder adds provisions reserving the right to reject or accept the award, 25 or enter into the Contract; 26 e. A price per unit cannot be determined from the Bid Proposal; 27 f. The Proposal form is not properly executed; 28 g. The Bidder fails to submit or properly complete a Subcontractor list, if 29 applicable, as required in Section 1-02.6; 30 h. The Bidder fails to submit or properly complete an Underutilized 31 Disadvantaged Business Enterprise Certification, if applicable, as required in 32 Section 1-02.6; 33 i. The Bidder fails to submit written confirmation from each UDBE firm listed on 34 the Bidder’s completed UDBE Utilization Certification that they are in 35 agreement with the bidder’s UDBE participation commitment, if applicable, as 36 required in Section 1-02.6, or if the written confirmation that is submitted fails 37 to meet the requirements of the Special Provisions; 38 j The Bidder fails to submit UDBE Good Faith Effort documentation, if 39 applicable, as required in Section 1-02.6, or if the documentation that is 40 submitted fails to demonstrate that a Good Faith Effort to meet the Condition 41 of Award was made; 42 k. The Bid Proposal does not constitute a definite and unqualified offer to meet 43 the material terms of the Bid invitation; or 44 l. More than one Proposal is submitted for the same project from a Bidder 45 under the same or different names. 46 47 2. A Proposal may be considered irregular and may be rejected if: 48 a. The Proposal does not include a unit price for every Bid item; 49 b. Any of the unit prices are excessively unbalanced (either above or below the 50 amount of a reasonable Bid) to the potential detriment of the Contracting 51 Agency; 52 c. Receipt of Addenda is not acknowledged;

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 141 1 d. A member of a joint venture or partnership and the joint venture or 2 partnership submit Proposals for the same project (in such an instance, both 3 Bids may be rejected); or 4 e. If Proposal form entries are not made in ink. 5 6 1-02.14 Disqualification of Bidders 7 (May 17, 2018 APWA GSP, Option A) 8 9 Delete this section and replace it with the following: 10 11 A Bidder will be deemed not responsible if the Bidder does not meet the mandatory bidder 12 responsibility criteria in RCW 39.04.350(1), as amended. 13 14 The Contracting Agency will verify that the Bidder meets the mandatory bidder 15 responsibility criteria in RCW 39.04.350(1). To assess bidder responsibility, the 16 Contracting Agency reserves the right to request documentation as needed from the 17 Bidder and third parties concerning the Bidder’s compliance with the mandatory bidder 18 responsibility criteria. 19 20 If the Contracting Agency determines the Bidder does not meet the mandatory bidder 21 responsibility criteria in RCW 39.04.350(1) and is therefore not a responsible Bidder, the 22 Contracting Agency shall notify the Bidder in writing, with the reasons for its determination. 23 If the Bidder disagrees with this determination, it may appeal the determination within two 24 (2) business days of the Contracting Agency’s determination by presenting its appeal and 25 any additional information to the Contracting Agency. The Contracting Agency will 26 consider the appeal and any additional information before issuing its final determination. 27 If the final determination affirms that the Bidder is not responsible, the Contracting Agency 28 will not execute a contract with any other Bidder until at least two business days after the 29 Bidder determined to be not responsible has received the Contracting Agency’s final 30 determination. 31 32 1-02.15 Pre Award Information 33 (August 14, 2013 APWA GSP) 34 35 Revise this section to read: 36 37 Before awarding any contract, the Contracting Agency may require one or more of these 38 items or actions of the apparent lowest responsible bidder: 39 1. A complete statement of the origin, composition, and manufacture of any or all 40 materials to be used, 41 2. Samples of these materials for quality and fitness tests, 42 3. A progress schedule (in a form the Contracting Agency requires) showing the order 43 of and time required for the various phases of the work, 44 4. A breakdown of costs assigned to any bid item, 45 5. Attendance at a conference with the Engineer or representatives of the Engineer, 46 6. Obtain, and furnish a copy of, a business license to do business in the city or county 47 where the work is located. 48 7. Any other information or action taken that is deemed necessary to ensure that the 49 bidder is the lowest responsible bidder. 50 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 142 1 1-03 AWARD AND EXECUTION OF CONTRACT 2 3 1-03.1(1) Identical Bid Totals 4 (January 4, 2016 APWA GSP) 5 6 Revise this section to read: 7 8 After opening Bids, if two or more lowest responsive Bid totals are exactly equal, then 9 the tie-breaker will be the Bidder with an equal lowest bid, that proposed to use the 10 highest percentage of recycled materials in the Project, per the form submitted with the 11 Bid Proposal. If those percentages are also exactly equal, then the tie-breaker will be 12 determined by drawing as follows: Two or more slips of paper will be marked as follows: 13 one marked “Winner” and the other(s) marked “unsuccessful”. The slips will be folded to 14 make the marking unseen. The slips will be placed inside a box. One authorized 15 representative of each Bidder shall draw a slip from the box. Bidders shall draw in 16 alphabetic order by the name of the firm as registered with the Washington State 17 Department of Licensing. The slips shall be unfolded and the firm with the slip marked 18 “Winner” will be determined to be the successful Bidder and eligible for Award of the 19 Contract. Only those Bidders who submitted a Bid total that is exactly equal to the lowest 20 responsive Bid, and with a proposed recycled m aterials percentage that is exactly equal 21 to the highest proposed recycled materials amount, are eligible to draw. 22 23 1-03.3 Execution of Contract 24 (June 19, 2019 SkagitR) 25 26 Revise this section to read: 27 28 Copies of the Contract Provisions, including the unsigned Form of Contract, will be 29 available for signature by the successful bidder on the first business day following award. 30 The number of copies to be executed by the Contractor will be determined by the 31 Contracting Agency. 32 33 Within ten (10) calendar days after the award date, the successful bidder shall return the 34 signed Contracting Agency-prepared contract, an insurance certification as required by 35 Section 1-07.18, and a satisfactory bond as required by law and Section 1-03.4. Before 36 execution of the contract by the Contracting Agency, the successful bidder shall provide 37 any pre-award information the Contracting Agency may require under Section 1-02.15. 38 39 Until the Contracting Agency executes a contract, no proposal shall bind the Contracting 40 Agency nor shall any work begin within the project limits or within Contracting Agency- 41 furnished sites. The Contractor shall bear all risks for any work begun outside such areas 42 and for any materials ordered before the contract is executed by the Contracting Agency. 43 44 If the bidder experiences circumstances beyond their control that prevents return of the 45 contract documents within the calendar days after the award date stated above, the 46 Contracting Agency may grant up to a maximum of ten (10) additional calendar days for 47 return of the documents, provided the Contracting Agency deems the circumstances 48 warrant it. 49 50 51 1-03.4 Contract Bond

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 143 1 (July 23, 2015 APWA GSP) 2 3 Delete the first paragraph and replace it with the following: 4 5 The successful bidder shall provide executed payment and performance bond(s) for the 6 full contract amount. The bond may be a combined payment and performance bond; or 7 be separate payment and performance bonds. In the case of separate payment and 8 performance bonds, each shall be for the full contract amount. The bond(s) shall: 9 1. Be on Contracting Agency-furnished form(s); 10 2. Be signed by an approved surety (or sureties) that: 11 a. Is registered with the Washington State Insurance Commissioner, and 12 b. Appears on the current Authorized Insurance List in the State of Washington 13 published by the Office of the Insurance Commissioner, 14 3. Guarantee that the Contractor will perform and comply with all obligations, duties, 15 and conditions under the Contract, including but not limited to the duty and obligation 16 to indemnify, defend, and protect the Contracting Agency against all losses and 17 claims related directly or indirectly from any failure: 18 a. Of the Contractor (or any of the employees, subcontractors, or lower tier 19 subcontractors of the Contractor) to faithfully perform and comply with all contract 20 obligations, conditions, and duties, or 21 b. Of the Contractor (or the subcontractors or lower tier subcontractors of the 22 Contractor) to pay all laborers, mechanics, subcontractors, lower tier 23 subcontractors, material person, or any other person who provides supplies or 24 provisions for carrying out the work; 25 4. Be conditioned upon the payment of taxes, increases, and penalties incurred on the 26 project under titles 50, 51, and 82 RCW; and 27 5. Be accompanied by a power of attorney for the Surety’s officer empowered to sign 28 the bond; and 29 6. Be signed by an officer of the Contractor empowered to sign official statements (sole 30 proprietor or partner). If the Contractor is a corporation, the bond(s) must be signed 31 by the president or vice president, unless accompanied by written proof of the 32 authority of the individual signing the bond(s) to bind the corporation (i.e., corporate 33 resolution, power of attorney, or a letter to such effect signed by the president or vice 34 president). 35 36 1-03.7 Judicial Review 37 (November 30, 2018 APWA GSP) 38 39 Revise this section to read: 40 41 Any decision made by the Contracting Agency regarding the Award and execution of the 42 Contract or Bid rejection shall be conclusive subject to the scope of judicial review 43 permitted under Washington Law. Such review, if any, shall be timely filed in the Superior 44 Court of the county where the Contracting Agency headquarters is located, provided that 45 where an action is asserted against a county, RCW 36.01.050 shall control venue and 46 jurisdiction. 47

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 144 1 2 1-04 SCOPE OF WORK 3 4 1-04.2 Coordination of Contract Documents, Plans, Special Provisions, 5 Specifications, and Addenda 6 (March 13, 2012 APWA GSP) 7 8 Revise the second paragraph to read: 9 10 Any inconsistency in the parts of the contract shall be resolved by following this order of 11 precedence (e.g., 1 presiding over 2, 2 over 3, 3 over 4, and so forth): 12 1. Addenda, 13 2. Proposal Form, 14 3. Special Provisions, 15 4. Contract Plans, 16 5. Amendments to the Standard Specifications, 17 6. Standard Specifications, 18 7. Contracting Agency’s Standard Plans or Details (if any), and 19 8. WSDOT Standard Plans for Road, Bridge, and Municipal Construction. 20 21 1-05 Control of Work 22 23 1-05.4 Conformity With And Deviations From Plans And Stakes 24 25 Section 1-05.4 is supplemented with the following: 26 27 1-05.4 Conformity With and Deviations from Plans and Stakes 28 29 Supplement this section with the following: 30 31 (August 7, 2017) 32 Contractor Surveying - Roadway 33 Copies of the Contracting Agency provided primary survey control data are available for 34 the bidder's inspection at the office of the Engineer. 35 36 The Contractor shall be responsible for setting, maintaining, and resetting all alignment 37 stakes, slope stakes, and grades necessary for the construction of the roadbed, drainage, 38 surfacing, paving, channelization and pavement marking, illumination and signals, 39 guardrails and barriers, and signing. Except for the survey control data to be furnished 40 by the Contracting Agency, calculations, surveying, and measuring required for setting 41 and maintaining the necessary lines and grades shall be the Contractor's responsibility. 42 43 The Contractor shall inform the Engineer when monuments are discovered that were not 44 identified in the Plans and construction activity may disturb or damage the monuments. 45 All monuments noted on the plans “DO NOT DISTURB” shall be protected throughout the 46 length of the project or be replaced at the Contractors expense. 47 48 Detailed survey records shall be maintained, including a description of the work 49 performed on each shift, the methods utilized, and the control points used. The record

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 145 1 shall be adequate to allow the survey to be reproduced. A copy of each day's record shall 2 be provided to the Engineer within three working days after the end of the shift. 3 4 The meaning of words and terms used in this provision shall be as listed in "Definitions of 5 Surveying and Associated Terms" current edition, published by the American Congress 6 on Surveying and Mapping and the American Society of Civil Engineers. 7 8 The survey work shall include but not be limited to the following: 9 10 1. Verify the primary horizontal and vertical control furnished by the Contracting 11 Agency, and expand into secondary control by adding stakes and hubs as well 12 as additional survey control needed for the project. Provide descriptions of 13 secondary control to the Contracting Agency. The description shall include 14 coordinates and elevations of all secondary control points. 15 16 2. Establish, the centerlines of all alignments, by placing hubs, stakes, or marks on 17 centerline or on offsets to centerline at all curve points (PCs, PTs, and PIs) and 18 at points on the alignments spaced no further than 50 feet. 19 20 3. Establish clearing limits, placing stakes at all angle points and at intermediate 21 points not more than 50 feet apart. The clearing and grubbing limits shall be 5 22 feet beyond the toe of a fill and 10 feet beyond the top of a cut unless otherwise 23 shown in the Plans. 24 25 4. Establish grading limits, placing slope stakes at centerline increments not more 26 than 50 feet apart. Establish offset reference to all slope stakes. If Global 27 Positioning Satellite (GPS) Machine Controls are used to provide grade control, 28 then slope stakes may be omitted at the discretion of the Contractor 29 30 5. Establish the horizontal and vertical location of all drainage features, placing 31 offset stakes to all drainage structures and to pipes at a horizontal interval not 32 greater than 25 feet. 33 34 6. Establish roadbed and surfacing elevations by placing stakes at the top of 35 subgrade and at the top of each course of surfacing. Subgrade and surfacing 36 stakes shall be set at horizontal intervals not greater than 50 feet in tangent 37 sections, 25 feet in curve sections with a radius less than 300 feet, and at 10- 38 foot intervals in intersection radii with a radius less than 10 feet. Transversely, 39 stakes shall be placed at all locations where the roadway slope changes and at 40 additional points such that the transverse spacing of stakes is not more than 12 41 feet. If GPS Machine Controls are used to provide grade control, then roadbed 42 and surfacing stakes may be omitted at the discretion of the Contractor. 43 44 7. Establish intermediate elevation benchmarks as needed to check work 45 throughout the project. 46 47 8. Provide references for paving pins at 25-foot intervals or provide simultaneous 48 surveying to establish location and elevation of paving pins as they are being 49 placed. 50 51 9. For all other types of construction included in this provision, (including but not 52 limited to channelization and pavement marking, illumination and signals,

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 146 1 guardrails and barriers, and signing) provide staking and layout as necessary to 2 adequately locate, construct, and check the specific construction activity. 3 4 10. Contractor shall determine if changes are needed to the profiles or roadway 5 sections shown in the Contract Plans in order to achieve proper smoothness 6 and drainage where matching into existing features, such as a smooth transition 7 from new pavement to existing pavement. The Contractor shall submit these 8 changes to the Engineer for review and approval 10 days prior to the beginning 9 of work. 10 11 The Contractor shall provide the Contracting Agency copies of any calculations and 12 staking data when requested by the Engineer. 13 14 To facilitate the establishment of these lines and elevations, the Contracting Agency will 15 provide the Contractor with primary survey control information consisting of descriptions 16 of two primary control points used for the horizontal and vertical control, and descriptions 17 of two additional primary control points for every additional three miles of project length. 18 Primary control points will be described by reference to the project alignment and the 19 coordinate system and elevation datum utilized by the project. In addition, the Contracting 20 Agency will supply horizontal coordinates for the beginning and ending points and for 21 each Point of Intersection (PI) on each alignment included in the project. 22 23 The Contractor shall ensure a surveying accuracy within the following tolerances: 24 25 Vertical Horizontal 26 Slope stakes ±0.10 feet ±0.10 feet 27 Subgrade grade stakes set 28 0.04 feet below grade ±0.01 feet ±0.5 feet 29 (parallel to alignment) 30 ±0.1 feet 31 (normal to alignment) 32 33 Stationing on roadway N/A ±0.1 feet 34 Alignment on roadway N/A ±0.04 feet 35 Surfacing grade stakes ±0.01 feet ±0.5 feet 36 (parallel to alignment) 37 ±0.1 feet 38 (normal to alignment) 39 40 Roadway paving pins for 41 surfacing or paving ±0.01 feet ±0.2 feet 42 (parallel to alignment) 43 ±0.1 feet 44 (normal to alignment) 45 46 The Contracting Agency may spot-check the Contractor's surveying. These spot-checks 47 will not change the requirements for normal checking by the Contractor. 48 49 When staking roadway alignment and stationing, the Contractor shall perform 50 independent checks from different secondary control to ensure that the points staked are 51 within the specified survey accuracy tolerances. 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 147 1 The Contractor shall calculate coordinates for the alignment. The Contracting Agency will 2 verify these coordinates prior to issuing approval to the Contractor for commencing with 3 the work. The Contracting Agency will require up to seven calendar days from the date 4 the data is received. 5 6 Contract work to be performed using contractor-provided stakes shall not begin until the 7 stakes are approved by the Contracting Agency. Such approval shall not relieve the 8 Contractor of responsibility for the accuracy of the stakes. 9 10 Stakes shall be marked in accordance with Standard Plan A10.10. When stakes are 11 needed that are not described in the Plans, then those stakes shall be marked, at no 12 additional cost to the Contracting Agency as ordered by the Engineer. 13 14 Payment 15 Payment will be made for the following bid item when included in the proposal: 16 17 "Roadway Surveying", lump sum. 18 19 The lump sum contract price for "Roadway Surveying" shall be full pay for all labor, 20 equipment, materials, and supervision utilized to perform the Work specified, including 21 any resurveying, checking, correction of errors, replacement of missing or damaged 22 stakes, and coordination efforts. 23 24 1-05.13 Superintendents, Labor and Equipment of Contractor 25 (August 14, 2013 APWA GSP) 26 27 Delete the sixth and seventh paragraphs of this section. 28 29 1-05.15 Method of Serving Notices 30 (March 25, 2009 APWA GSP)

31 Revise the second paragraph to read: 32 33 All correspondence from the Contractor shall be directed to the Project Engineer. All 34 correspondence from the Contractor constituting any notification, notice of protest, notice 35 of dispute, or other correspondence constituting notification required to be furnished 36 under the Contract, must be in paper format, hand delivered or sent via mail delivery 37 service to the Project Engineer's office. Electronic copies such as e-mails or 38 electronically delivered copies of correspondence will not constitute such notice and will 39 not comply with the requirements of the Contract. 40 41 Add the following new section 42 43 1-05.16 Water and Power 44 (October 1, 2005 APWA GSP) 45 46 The Contractor shall make necessary arrangements, and shall bear the costs for power 47 and water necessary for the performance of the work, unless the contract includes power 48 and water as a pay item. 49

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 148 1 1-06.6 Recycled Materials 2 (January 4, 2016 APWA GSP) 3 4 Delete this section, including its subsections, and replace it with the following: 5 6 The Contractor shall make their best effort to utilize recycled materials in the construction 7 of the project. Approval of such material use shall be as detailed elsewhere in the 8 Standard Specifications. 9 10 Prior to Physical Completion the Contractor shall report the quantity of recycled materials 11 that were utilized in the construction of the project for each of the items listed in Section 12 9-03.21. The report shall include hot mix asphalt, recycled concrete aggregate, recycled 13 glass, steel furnace slag and other recycled materials (e.g. utilization of on-site material 14 and aggregates from concrete returned to the supplier). The Contractor’s report shall be 15 provided on DOT form 350-075 Recycled Materials Reporting. 16 17 1-07.1 Laws to be Observed 18 (October 1, 2005 APWA GSP) 19 20 Supplement this section with the following: 21 22 In cases of conflict between different safety regulations, the more stringent regulation 23 shall apply. 24 25 The Washington State Department of Labor and Industries shall be the sole and 26 paramount administrative agency responsible for the administration of the provisions of 27 the Washington Industrial Safety and Health Act of 1973 (WISHA). 28 29 The Contractor shall maintain at the project site office, or other well known place at the 30 project site, all articles necessary for providing first aid to the injured. The Contractor 31 shall establish, publish, and make known to all employees, procedures for ensuring 32 immediate removal to a hospital, or doctor’s care, persons, including employees, who 33 may have been injured on the project site. Employees should not be permitted to work 34 on the project site before the Contractor has established and made known procedures 35 for removal of injured persons to a hospital or a doctor’s care. 36 37 The Contractor shall have sole responsibility for the safety, efficiency, and adequacy of 38 the Contractor’s plant, appliances, and methods, and for any damage or injury resulting 39 from their failure, or improper maintenance, use, or operation. The Contractor shall be 40 solely and completely responsible for the conditions of the project site, including safety 41 for all persons and property in the performance of the work. This requirement shall apply 42 continuously, and not be limited to normal working hours. The required or implied duty of 43 the Engineer to conduct construction review of the Contractor’s performance does not, 44 and shall not, be intended to include review and adequacy of the Contractor’s safety 45 measures in, on, or near the project site. 46 47

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 149 1 1-07.2 State Taxes 2 3 Delete this section, including its sub-sections, in its entirety and replace it with the following: 4 5 1-07.2 State Sales Tax 6 (June 27, 2011 APWA GSP) 7 8 The Washington State Department of Revenue has issued special rules on the State 9 sales tax. Sections 1-07.2(1) through 1-07.2(3) are meant to clarify those rules. The 10 Contractor should contact the Washington State Department of Revenue for answers to 11 questions in this area. The Contracting Agency will not adjust its payment if the 12 Contractor bases a bid on a misunderstood tax liability. 13 14 The Contractor shall include all Contractor-paid taxes in the unit bid prices or other 15 contract amounts. In some cases, however, state retail sales tax will not be included. 16 Section 1-07.2(2) describes this exception. 17 18 The Contracting Agency will pay the retained percentage (or release the Contract Bond if 19 a FHWA-funded Project) only if the Contractor has obtained from the Washington State 20 Department of Revenue a certificate showing that all contract-related taxes have been 21 paid (RCW 60.28.051). The Contracting Agency may deduct from its payments to the 22 Contractor any amount the Contractor may owe the Washington State Department of 23 Revenue, whether the amount owed relates to this contract or not. Any amount so 24 deducted will be paid into the proper State fund. 25 26 1-07.2(1) State Sales Tax — Rule 171 27 28 WAC 458-20-171, and its related rules, apply to building, repairing, or improving streets, 29 roads, etc., which are owned by a municipal corporation, or political subdivision of the 30 state, or by the United States, and which are used primarily for foot or vehicular traffic. 31 This includes storm or combined sewer systems within and included as a part of the 32 street or road drainage system and power lines when such are part of the roadway 33 lighting system. For work performed in such cases, the Contractor shall include 34 Washington State Retail Sales Taxes in the various unit bid item prices, or other contract 35 amounts, including those that the Contractor pays on the purchase of the materials, 36 equipment, or supplies used or consumed in doing the work. 37 38 1-07.2(2) State Sales Tax — Rule 170 39 40 WAC 458-20-170, and its related rules, apply to the constructing and repairing of new or 41 existing buildings, or other structures, upon real property. This includes, but is not 42 limited to, the construction of streets, roads, highways, etc., owned by the state of 43 Washington; water mains and their appurtenances; sanitary sewers and sewage 44 disposal systems unless such sewers and disposal systems are within, and a part of, a 45 street or road drainage system; telephone, telegraph, electrical power distribution lines, 46 or other conduits or lines in or above streets or roads, unless such power lines become a 47 part of a street or road lighting system; and installing or attaching of any article of 48 tangible personal property in or to real property, whether or not such personal property 49 becomes a part of the realty by virtue of installation. 50 51 For work performed in such cases, the Contractor shall collect from the Contracting 52 Agency, retail sales tax on the full contract price. The Contracting Agency will

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 150 1 automatically add this sales tax to each payment to the Contractor. For this reason, the 2 Contractor shall not include the retail sales tax in the unit bid item prices, or in any other 3 contract amount subject to Rule 170, with the following exception. 4 5 Exception: The Contracting Agency will not add in sales tax for a payment the Contractor 6 or a subcontractor makes on the purchase or rental of tools, machinery, equipment, or 7 consumable supplies not integrated into the project. Such sales taxes shall be included 8 in the unit bid item prices or in any other contract amount. 9 10 1-07.2(3) Services 11 12 The Contractor shall not collect retail sales tax from the Contracting Agency on any 13 contract wholly for professional or other services (as defined in Washington State 14 Department of Revenue Rules 138 and 244). 15 16 1-07.4 Sanitation 17 18 1-07.4(1) General 19 (July 14, 2016 SkagitR) 20 21 Section 1-07.4(1) is supplemented with the following: 22 23 The Contractor shall provide employees with portable sanitary stations on site. These portable 24 sanitary stations shall comply with all State Department of Health or other agency 25 requirements; shall be kept clean, neat and sanitized; and shall not create any public nuisance. 26 27 1-07.7 Load Limits 28 29 1-07.9 Wages 30 31 Section 1-07.9(1) is supplemented with the following: 32 33 (January 9, 2019) 34 The Federal wage rates incorporated in this contract have been established by the 35 Secretary of Labor under United States Department of Labor General Decision No. 36 WA190001. 37 38 The State rates incorporated in this contract are applicable to all construction 39 activities associated with this contract. 40 41 1-07.17 Utilities and Similar Facilities 42 43 Section 1-07.17 is supplemented with the following: 44 45 (April 2, 2007) 46 Locations and dimensions shown in the Plans for existing facilities are in accordance with 47 available information obtained without uncovering, measuring, or other verification. 48 49 The following addresses and telephone numbers of utility companies known or suspected 50 of having facilities within the project limits are supplied for the Contractor's convenience: 51 52 Puget Sound Energy

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 151 1 Contact: Jane Major 2 1660 Park Lane 3 Burlington, WA. 98233 4 360-766-5571 5 6 Frontier Communications 7 Contact: James Strago 8 1329 State Street 9 Burlington, WA. 98233 10 425-327-8118 11 12 Public Utility District No. 1 of Skagit County 13 Contact: Mike Benton 14 1415 Freeway Drive 15 Mount Vernon, WA. 98273 16 360-424-7104 17 18 Cascade Natural Gas 19 Emergency Call: 888-522-1130 20 Contact: Ted McCammant 21 1520 S. Second St. 22 Mount Vernon, WA 98273 23 360-708-4689 24 25 Black Rock Cable 26 [email protected] 27 28 Comcast Cable 29 [email protected] 30 31 Qwest Local Network 32 Contact: Gary for locates (206)473-0736 or Scott (360)441-2913 33 34 All Stream Fiber Optic 35 Subcontractor: Dennis Gearhart of Plantec Cable Management 36 14241 NE Woodinville Duvall Road PMB 305 Woodinville, WA 98072 37 Office and Emergency: (360) 305-2114 38 39 Utility Location Center 40 (One Call Center) 41 1-800-424-5555 42 43 1-07.18 Public Liability and Property Damage Insurance 44 45 Delete this section in its entirety, and replace it with the following: 46 47 1-07.18 Insurance 48 (January 4, 2016 APWA GSP) 49 50 1-07.18(1) General Requirements 51 A. The Contractor shall procure and maintain the insurance described in all subsections of 52 section 1-07.18 of these Special Provisions, from insurers with a current A. M. Best

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 152 1 rating of not less than A-: VII and licensed to do business in the State of Washington. 2 The Contracting Agency reserves the right to approve or reject the insurance provided, 3 based on the insurer’s financial condition. 4 5 B. The Contractor shall keep this insurance in force without interruption from the 6 commencement of the Contractor’s Work through the term of the Contract and for thirty 7 (30) days after the Physical Completion date, unless otherwise indicated below. 8 9 C. If any insurance policy is written on a claims made form, its retroactive date, and that of 10 all subsequent renewals, shall be no later than the effective date of this Contract. The 11 policy shall state that coverage is claims made, and state the retroactive date. Claims- 12 made form coverage shall be maintained by the Contractor for a minimum of 36 months 13 following the Completion Date or earlier termination of this Contract, and the Contractor 14 shall annually provide the Contracting Agency with proof of renewal. If renewal of the 15 claims made form of coverage becomes unavailable, or economically prohibitive, the 16 Contractor shall purchase an extended reporting period (“tail”) or execute another form of 17 guarantee acceptable to the Contracting Agency to assure financial responsibility for 18 liability for services performed. 19 20 D. The Contractor’s Automobile Liability, Commercial General Liability and Excess or 21 Umbrella Liability insurance policies shall be primary and non-contributory insurance as 22 respects the Contracting Agency’s insurance, self-insurance, or self-insured pool 23 coverage. Any insurance, self-insurance, or self-insured pool coverage maintained by the 24 Contracting Agency shall be excess of the Contractor’s insurance and shall not contribute 25 with it. 26 27 E. The Contractor shall provide the Contracting Agency and all additional insureds with 28 written notice of any policy cancellation, within two business days of their receipt of such 29 notice. 30 31 F. The Contractor shall not begin work under the Contract until the required insurance has 32 been obtained and approved by the Contracting Agency 33 34 G. Failure on the part of the Contractor to maintain the insurance as required shall 35 constitute a material breach of contract, upon which the Contracting Agency may, after 36 giving five business days’ notice to the Contractor to correct the breach, immediately 37 terminate the Contract or, at its discretion, procure or renew such insurance and pay any 38 and all premiums in connection therewith, with any sums so expended to be repaid to the 39 Contracting Agency on demand, or at the sole discretion of the Contracting Agency, 40 offset against funds due the Contractor from the Contracting Agency. 41 42 H. All costs for insurance shall be incidental to and included in the unit or lump sum prices 43 of the Contract and no additional payment will be made. 44 45 1-07.18(2) Additional Insured 46 All insurance policies, with the exception of Workers Compensation, and of Professional 47 Liability and Builder’s Risk (if required by this Contract) shall name the following listed 48 entities as additional insured(s) using the forms or endorsements required herein: 49 . the Contracting Agency and its officers, elected officials, employees, agents, and 50 volunteers 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 153 1 The above-listed entities shall be additional insured(s) for the full available limits of liability 2 maintained by the Contractor, irrespective of whether such limits maintained by the 3 Contractor are greater than those required by this Contract, and irrespective of whether the 4 Certificate of Insurance provided by the Contractor pursuant to 1-07.18(4) describes limits 5 lower than those maintained by the Contractor. 6 7 For Commercial General Liability insurance coverage, the required additional insured 8 endorsements shall be at least as broad as ISO forms CG 20 10 10 01 for ongoing 9 operations and CG 20 37 10 01 for completed operations. 10 11 1-07.18(3) Subcontractors 12 The Contractor shall cause each Subcontractor of every tier to provide insurance coverage 13 that complies with all applicable requirements of the Contractor-provided insurance as set 14 forth herein, except the Contractor shall have sole responsibility for determining the limits of 15 coverage required to be obtained by Subcontractors. 16 17 The Contractor shall ensure that all Subcontractors of every tier add all entities listed in 18 1-07.18(2) as additional insureds, and provide proof of such on the policies as required by 19 that section as detailed in 1-07.18(2) using an endorsement as least as broad as ISO CG 20 20 10 10 01 for ongoing operations and CG 20 37 10 01 for completed operations. 21 22 Upon request by the Contracting Agency, the Contractor shall forward to the Contracting 23 Agency evidence of insurance and copies of the additional insured endorsements of each 24 Subcontractor of every tier as required in 1-07.18(4) Verification of Coverage. 25 26 1-07.18(4) Verification of Coverage 27 The Contractor shall deliver to the Contracting Agency a Certificate(s) of Insurance and 28 endorsements for each policy of insurance meeting the requirements set forth herein when 29 the Contractor delivers the signed Contract for the work. Failure of Contracting Agency to 30 demand such verification of coverage with these insurance requirements or failure of 31 Contracting Agency to identify a deficiency from the insurance documentation provided shall 32 not be construed as a waiver of Contractor’s obligation to maintain such insurance. 33 34 Verification of coverage shall include: 35 1. An ACORD certificate or a form determined by the Contracting Agency to be equivalent. 36 2. Copies of all endorsements naming Contracting Agency and all other entities listed in 37 1-07.18(2) as additional insured(s), showing the policy number. The Contractor may 38 submit a copy of any blanket additional insured clause from its policies instead of a 39 separate endorsement. 40 3. Any other amendatory endorsements to show the coverage required herein. 41 4. A notation of coverage enhancements on the Certificate of Insurance shall not satisfy 42 these requirements – actual endorsements must be submitted. 43 44 Upon request by the Contracting Agency, the Contractor shall forward to the Contracting 45 Agency a full and certified copy of the insurance policy(s). If Builders Risk insurance is 46 required on this Project, a full and certified copy of that policy is required when the 47 Contractor delivers the signed Contract for the work. 48

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 154 1 1-07.18(5) Coverages and Limits 2 The insurance shall provide the minimum coverages and limits set forth below. Contractor’s 3 maintenance of insurance, its scope of coverage, and limits as required herein shall not be 4 construed to limit the liability of the Contractor to the coverage provided by such insurance, 5 or otherwise limit the Contracting Agency’s recourse to any remedy available at law or in 6 equity. 7 8 All deductibles and self-insured retentions must be disclosed and are subject to approval by 9 the Contracting Agency. The cost of any claim payments falling within the deductible or self- 10 insured retention shall be the responsibility of the Contractor. In the event an additional 11 insured incurs a liability subject to any policy’s deductibles or self-insured retention, said 12 deductibles or self-insured retention shall be the responsibility of the Contractor. 13 14 1-07.18(5)A Commercial General Liability 15 Commercial General Liability insurance shall be written on coverage forms at least as broad 16 as ISO occurrence form CG 00 01, including but not limited to liability arising from premises, 17 operations, stop gap liability, independent contractors, products-completed operations, 18 personal and advertising injury, and liability assumed under an insured contract. There shall 19 be no exclusion for liability arising from explosion, collapse or underground property 20 damage. 21 22 The Commercial General Liability insurance shall be endorsed to provide a per project 23 general aggregate limit, using ISO form CG 25 03 05 09 or an equivalent endorsement. 24 25 Contractor shall maintain Commercial General Liability Insurance arising out of the 26 Contractor’s completed operations for at least three years following Substantial Completion 27 of the Work. 28 29 Such policy must provide the following minimum limits: 30 $1,000,000 Each Occurrence 31 $2,000,000 General Aggregate 32 $2,000,000 Products & Completed Operations Aggregate 33 $1,000,000 Personal & Advertising Injury each offence 34 $1,000,000 Stop Gap / Employers’ Liability each accident 35 36 1-07.18(5)B Automobile Liability 37 Automobile Liability shall cover owned, non-owned, hired, and leased vehicles; and shall be 38 written on a coverage form at least as broad as ISO form CA 00 01. If the work involves the 39 transport of pollutants, the automobile liability policy shall include MCS 90 and CA 99 48 40 endorsements. 41 42 Such policy must provide the following minimum limit: 43 $1,000,000 Combined single limit each accident 44 45 1-07.18(5)C Workers’ Compensation 46 The Contractor shall comply with Workers’ Compensation coverage as required by the 47 Industrial Insurance laws of the State of Washington. 48

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 155 1 1-07.18(6) Relations With Railroad 2 (April 1, 2013 WSDOT GSP) 3 4 Railroad Company, as used in the following specifications, shall be the railroad company 5 or companies, or railway company or companies specified in these Special Provisions. 6 The following provisions, though referring to a single Railroad Company, shall be 7 applicable to each of the following railroad companies or railway companies: 8 9 BNSF Railway Company 10 11 Protection of Railroad Property 12 The Contractor shall exercise care in all operations and shall, at the Contractor's 13 expense, protect the property of the Railroad Company and the Company’s 14 appurtenances, property in its custody, or persons lawfully upon its right of way, from 15 damage, destruction, interference or injury caused by the Contractor’s operations. 16 The Contractor shall prosecute the work to not interfere with the Railroad Company 17 or its appurtenances, or any of the Railroad Company's trains or facilities, and shall 18 complete the work to a condition that shall not interfere with or menace the integrity 19 or safe and successful operations of the Railroad Company or its appurtenances, or 20 any of the Railroad Company's trains or facilities. 21 22 The Contractor shall not transport equipment, machinery, or materials across the 23 Railroad Company's tracks, except at a public crossing, without the written consent 24 of the Railroad Company. 25 26 The Contractor shall keep the right of way and ditches of the Railroad Company open 27 and clean from any deposits or debris resulting from its operations. The Contractor 28 shall be responsible for the cost to clean and restore ballast of the Railroad Company 29 which is disturbed or becomes fouled with dirt or materials when such deposits or 30 damage result from the Contractor’s operations, except as provided elsewhere. 31 32 The Contractor's work shall be conducted in such a manner that there will be a 33 minimum of interference with the operation of railroad traffic. The Railroad Company 34 will specify what periods will be allowed the Contractor for executing any part of the 35 work in which the Railroad Company's tracks will be obstructed or made unsafe for 36 operation of railroad traffic. 37 38 In the event that an emergency occurs in connection with the work specified, the 39 Railroad Company reserves the right to do any and all work that may be necessary 40 to maintain railroad traffic. If the emergency is caused by the Contractor, the 41 Contractor shall pay the Railroad Company for the cost of such emergency work. 42 43 Protective services to protect the Railroad Company's facilities, property, and 44 movement of its trains or engines, including railroad flagging and other devices, may 45 be required by the Railroad Company as a result of the Contractor's operations. 46 47 The nature and extent of protective services, personnel and other measures required 48 will in all cases be determined by the Railroad Company. Nothing in these 49 specifications will limit the Railroad Company's right to determine and assign the 50 number of personnel, the classes of personnel for protective services, nor other 51 protective measures it deems necessary. 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 156 1 When, in the opinion of the Railroad Company, the services of flaggers or inspectors 2 are necessary for the protection of the Railroad Company's facilities by reason of the 3 Contractor's operations, the Railroad Company will furnish such flaggers or 4 inspectors as may be required. The Contractor shall notify the Railroad Company a 5 minimum of thirty (30) calendar days in advance of whenever the Contractor is about 6 to perform work within Railroad Company property or within 25 feet of the tracks to 7 enable the Railroad Company to provide flagging or other protective services. 8 9 The Railroad Company’s contact is: 10 11 Gregory Murphy (BNSF Flagger foreman) or 12 Karl Jay (Road Master): (360) 815-4643 13 14 No act of the Railroad Company in supervising or approving any work shall reduce 15 or in any way affect the liability of the Contractor for damages, expense, or cost which 16 may result to the Railroad Company from the construction of this Contract. 17 18 Unless otherwise provided, all personnel assigned by the Railroad Company, other 19 than those engaged in performing work by the Railroad Company as listed under 20 Construction Work by Railroad Company, will be considered protective personnel. 21 22 In general, the Railroad Company will furnish protective services whenever any of 23 the Contractor's operations take place within or near railroad right of way and, in the 24 opinion of the Railroad Company's representative, could endanger railroad facilities 25 or create a hazard to railroad operations. 26 27 The Railroad Company’s policy for assignment of railroad flaggers requires that the 28 flagging position is established for fixed work days and times. Any railroad flagging 29 performed outside of these parameters may be subject to overtime costs. The 30 Contractor shall verify with the Railroad Company what categories of railroad flagging 31 constitute overtime work, and obtain prior authorization from the Project Engineer 32 before coordinating with the Railroad Company for flagging requiring overtime 33 payments. 34 35 The Contractor shall submit to the Railroad Company and the Project Engineer, in 36 writing, an itinerary of work within the Railroad Company’s right of way or otherwise 37 requiring a Railroad Company flagger for the following week. If such work spans 38 multiple weeks, the itinerary shall be provided in advance of each work week. 39 40 41 Add the following new section: 42 43 1-07.18(7) Additional Railroad Requirements 44 45 A. Contractor shall have a background investigation performed on all of its employees, 46 subcontractors and agents who will be performing any services on railroad property 47 under this Agreement. The background screening shall at a minimum meet the criteria 48 defined by the e-RAILSAFE program outlined at http://www.e-railsafe.com in addition 49 to any other applicable regulatory requirements. The e-RAILSAFE program uses rail 50 industry background screening standards. Contractor shall obtain consent from all 51 employees screened in compliance with the e-RAILSAFE program criteria to release 52 completed background information to BNSF. Contractor shall be subject to periodic

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 157 1 audit to ensure compliance. Contractor shall not permit any of its employees, 2 subcontractors or agents to perform services on property hereunder who are not 3 approved under e-RAILSAFE program standards. Railroad shall have the right to deny 4 entry onto its premises to any of Contractor's employees, subcontractors or agents 5 who do not display the authorized identification badge issued by a background 6 screening service meeting the standards set forth for the e-RAILSAFE program or who 7 pose a threat, in Railroad's reasonable opinion, to the safety or security of Railroad's 8 operations. Contractors shall ensure its employees, subcontractors, and agents are 9 U.S. citizens or legally working in this country under a work VISA. 10 11 1-07.23(1) Construction Under Traffic 12 (July 14, 2016 SkagitR) 13 14 In the second paragraph of Section 1-07.23(1), the following new sentences are inserted 15 after the first sentence: 16 17 • No vehicle trip through the work zone may be stopped for more than 10 minutes 18 without the prior approval of the Engineer. 19 20 21 • The Contractor’s operations shall not halt traffic either on or within 25 feet of the 22 BNSF Railroad tracks on Cook Road. 23 24 Section 1-07.23(1) is supplemented with the following: 25 26 (January 2, 2012) 27 Work Zone Clear Zone 28 The Work Zone Clear Zone (WZCZ) applies during working and nonworking 29 hours. The WZCZ applies only to temporary roadside objects introduced by the 30 Contractor’s operations and does not apply to preexisting conditions or 31 permanent Work. Those work operations that are actively in progress shall be in 32 accordance with adopted and approved Traffic Control Plans, and other contract 33 requirements. 34 35 During nonworking hours equipment or materials shall not be within the WZCZ 36 unless they are protected by permanent guardrail or temporary concrete barrier. 37 The use of temporary concrete barrier shall be permitted only if the Engineer 38 approves the installation and location. 39 40 During actual hours of work, unless protected as described above, only 41 materials absolutely necessary to construction shall be within the WZCZ and 42 only construction vehicles absolutely necessary to construction shall be allowed 43 within the WZCZ or allowed to stop or park on the shoulder of the roadway. 44 45 The Contractor's nonessential vehicles and employees private vehicles shall not 46 be permitted to park within the WZCZ at any time unless protected as described 47 above. 48 49 Deviation from the above requirements shall not occur unless the Contractor 50 has requested the deviation in writing and the Engineer has provided written 51 approval. 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 158 1 Minimum WZCZ distances are measured from the edge of traveled way and will 2 be determined as follows: 3 Regulatory Distance From Posted Speed Traveled Way (Feet) 35 mph or less 10 * 40 mph 15 45 to 55 mph 20 60 mph or greater 30 4 * or 2-feet beyond the outside edge of sidewalk 5 6 Minimum Work Zone Clear Zone Distance 7 8 9 10 (******) 11 There shall be no restrictions or interruptions for traffic on the day prior to a holiday or 12 holiday weekend through the last day of the holiday or holiday weekend. 13 14 Lane restrictions shall be held to a minimum time and length needed for the immediate 15 work. If the Engineer determines that the lane restrictions are causing congestion, the 16 Contractor shall be required to open all lanes to traffic until the congestion is eliminated 17 at no additional cost to the Contracting Agency. 18 19 Lane closures in the noted locations below shall be allowed only during the following 20 hours: 21 22 Schedule B: 23 Cook Road 24 Old Highway 99 North 25 Green Road: 26 27 Sun 7:00 pm to Mon 5:00 am 28 Mon 7:00 pm to Tues 5:00 am 29 Tues 7:00 pm to Wed 5:00 am 30 Wed 7:00 pm to Thurs 5:00 am 31 Thurs 7:00 pm to Fri 5:00 am 32 33 Should high volume hours differ from those specified as determined by the Engineer, the 34 Contractor shall be required to adjust the hours of work accordingly. Exceptions to these 35 restrictions may be considered by the Engineer on a case by case basis following a written 36 request by the Contractor. 37 38 When the Contractor’s construction operations are actually in progress, traffic may 39 be restricted to one lane, subject to the above specifications. 40 41 The Contractor’s operations shall not halt traffic either on or within 25 feet of the 42 BNSF Railroad tracks on Cook Road at any time. 43 44

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 159 1 Special events that generate increased traffic volumes may occur during the life of this 2 project. Lane restrictions may be denied if severe traffic congestion is expected. 3

4 1-08 PROSECUTION AND PROGRESS 5 6 Add the following new section: 7 8 1-08.0 Preliminary Matters 9 (May 25, 2006 APWA GSP) 10 11 Add the following new section: 12 13 1-08.0(1) Preconstruction Conference 14 (******) 15 16 Prior to the Contractor beginning the work, a preconstruction conference will be held 17 between the Contractor, the Engineer and such other interested parties as may be invited. 18 The purpose of the preconstruction conference will be: 19 20 1. To review the initial progress schedule; 21 2. To establish a working understanding among the various parties associated or 22 affected by the work; 23 3. To establish and review procedures for progress payment, notifications, 24 approvals, submittals, etc.; 25 4. To establish normal working hours for the work; 26 5. To review safety standards and any required traffic control; and 27 6. To discuss such other related items as may be pertinent to the work. 28 29 The Contractor shall prepare and submit at the preconstruction conference the following: 30 31 1. A breakdown of all lump sum items; 32 2. A preliminary schedule of working drawing submittals; and 33 3. A list of material sources for approval if applicable. 34 4. The SPCC plan. 35 5. The TESC plan 36 6. A list of Emergency Contacts including those for after working hours. 37 38 Add the following new section: 39 40 1-08.0(2) Hours of Work 41 (******) 42 43 Except in the case of emergency or unless otherwise approved by the Engineer, the 44 normal working hours for the Contract shall be any consecutive 8-hour period between 45 7:00 a.m. and 6:00 p.m. Monday through Friday, exclusive of a lunch break. Work hours 46 for “Schedule B” Cook Road shall be from 7:00 p.m. to 5:00 a.m. for all work requiring 47 lane closures. If the Contractor desires different than the normal working hours stated 48 above, the request must be submitted in writing prior to the preconstruction conference, 49 subject to the provisions below. The working hours for the Contract shall be established 50 at or prior to the preconstruction conference.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 160 1 2 All working hours and days are also subject to local permit and ordinance conditions (such 3 as noise ordinances). 4 5 If the Contractor wishes to deviate from the established working hours, the Contractor 6 shall submit a written request to the Engineer for consideration. This request shall state 7 what hours are being requested, and why. Requests shall be submitted for review no 8 later than five (5) days prior to the day(s) the Contractor is requesting to change the 9 hours. 10 11 If the Contracting Agency approves such a deviation, such approval may be subject to 12 certain other conditions, which will be detailed in writing. For example: 13 1. On non-Federal aid projects, requiring the Contractor to reimburse the Contracting 14 Agency for the costs in excess of straight-time costs for Contracting Agency 15 representatives who worked during such times. (The Engineer may require 16 designated representatives to be present during the work. Representatives who 17 may be deemed necessary by the Engineer include, but are not limited to: survey 18 crews; personnel from the Contracting Agency’s material testing lab; inspectors; 19 and other Contracting Agency employees or third party consultants when, in the 20 opinion of the Engineer, such work necessitates their presence.) 21 2. Considering the work performed on Saturdays, Sundays, and holidays as working 22 days with regard to the contract time. 23 3. Considering multiple work shifts as multiple working days with respect to contract 24 time even though the multiple shifts occur in a single 24-hour period. 25 4. If a 4-10 work schedule is requested and approved the non working day for the 26 week will be charged as a working day. 27 5. If Davis Bacon wage rates apply to this Contract, all requirements must be met and 28 recorded properly on certified payroll 29 30 1-08.1 Subcontracting 31 (May 30, 2019 APWA GSP, Option A) 32 33 Prior to any subcontractor or lower tier subcontractor beginning work, the Contractor shall 34 submit to the Engineer a certification (WSDOT Form 420-004) that a written agreement 35 between the Contractor and the subcontractor or between the subcontractor and any lower 36 tier subcontractor has been executed. This certification shall also guarantee that these 37 subcontract agreements include all the documents required by the Special Provision Federal 38 Agency Inspection. 39 40 A Subcontractor or lower tier Subcontractor will not be permitted to perform any work under 41 the contract until the following documents have been completed and submitted to the 42 Engineer: 43 44 1. Request to Sublet Work (WSDOT Form 421-012), and 45 2. Contractor and Subcontractor or Lower Tier Subcontractor Certification for Federal-aid 46 Projects (WSDOT Form 420-004). 47 48 The ninth paragraph, beginning with “On all projects, …” is revised to read: 49

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 161 1 The Contractor shall certify to the actual amount received from the Contracting Agency 2 and amounts paid to all firms that were used as Subcontractors, lower tier 3 subcontractors, manufacturers, regular dealers, or service providers on the Contract. 4 This includes all Disadvantaged, Minority, Small, Veteran or Women’s Business 5 Enterprise firms. This Certification shall be submitted to the Engineer on a monthly basis 6 each month between Execution of the Contract and Physical Completion of the Contract 7 using the application available at: https://wsdot.diversitycompliance.com. A monthly 8 report shall be submitted for every month between Execution of the Contract and 9 Physical Completion regardless of whether payments were made or work occurred. 10 11 1-08.4 Prosecution of Work 12 13 Delete this section and replace it with the following: 14 15 1-08.4 Notice to Proceed and Prosecution of Work 16 (July 23, 2015 APWA GSP) 17 18 Notice to Proceed will be given after the contract has been executed and the contract 19 bond and evidence of insurance have been approved and filed by the Contracting 20 Agency. The Contractor shall not commence with the work until the Notice to Proceed 21 has been given by the Engineer. The Contractor shall commence construction activities 22 on the project site within ten days of the Notice to Proceed Date, unless otherwise 23 approved in writing. The Contractor shall diligently pursue the work to the physical 24 completion date within the time specified in the contract. Voluntary shutdown or slowing 25 of operations by the Contractor shall not relieve the Contractor of the responsibility to 26 complete the work within the time(s) specified in the contract. 27 28 When shown in the Plans, the first order of work shall be the installation of high visibility 29 fencing to delineate all areas for protection or restoration, as described in the Contract. 30 Installation of high visibility fencing adjacent to the roadway shall occur after the 31 placement of all necessary signs and traffic control devices in accordance with 1-10.1(2). 32 Upon construction of the fencing, the Contractor shall request the Engineer to inspect the 33 fence. No other work shall be performed on the site until the Contracting Agency has 34 accepted the installation of high visibility fencing, as described in the Contract. 35 36 (March 13, 1995) 37 This project shall be physically completed within ***Twenty-Five (25)*** working days. 38 39 Prosecution and Progress 40 41 1-08.9 Liquidated Damages 42 (August 14, 2013 APWA GSP) 43 44 Section 1-08.9 is supplemented with the following: 45 46 (******) 47 Unplanned disruptions to the Intelligent Transportation System (ITS) will result in impacts 48 to the traveling public, increase fuel consumption, vehicle operating costs, pollution, and 49 other inconveniences and harm. 50

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 162 1 Accordingly, the Contractor agrees: 2 3 1. To pay $250.00 liquidated damages per 15 minutes for each 15 minute period 4 that the Contractor fails to restore the proper operation of an existing ITS 5 element following an unplanned disruption as specified in the subsection 6 Existing System Disruption and Restoration of the Special Provision 7 Illumination, Traffic Signal Systems, and Electrical. 8 9 2. To authorize the Engineer to deduct these liquidated damages from any money 10 due or coming to the Contractor. 11 12 13 Revise the fourth paragraph to read: 14 15 When the Contract Work has progressed to Substantial Completion as defined in the 16 Contract, the Engineer may determine that the work is Substantially Complete. The 17 Engineer will notify the Contractor in writing of the Substantial Completion Date. For 18 overruns in Contract time occurring after the date so established, the formula for 19 liquidated damages shown above will not apply. For overruns in Contract time occurring 20 after the Substantial Completion Date, liquidated damages shall be assessed on the 21 basis of direct engineering and related costs assignable to the project until the actual 22 Physical Completion Date of all the Contract Work. The Contractor shall complete the 23 remaining Work as promptly as possible. Upon request by the Project Engineer, the 24 Contractor shall furnish a written schedule for completing the physical Work on the 25 Contract. 26 27 1-09 Measurement and Payment 28 29 1-09.2 Weighing Equipment 30 31 1-09.2(1) General Requirements for Weighing Equipment 32 (July 23, 2015 APWA GSP, Option 2) 33 34 Revise item 4 of the fifth paragraph to read: 35 36 4. Test results and scale weight records for each day’s hauling operations are provided 37 to the Engineer daily. Reporting shall utilize WSDOT form 422-027, Scaleman’s 38 Daily Report, unless the printed ticket contains the same information that is on the 39 Scaleman’s Daily Report Form. The scale operator must provide AM and/or PM tare 40 weights for each truck on the printed ticket. 41 42 1-09.2(5) Measurement 43 (May 2, 2017 APWA GSP) 44 45 Revise the first paragraph to read: 46 47 Scale Verification Checks – At the Engineer’s discretion, the Engineer may perform 48 verification checks on the accuracy of each batch, hopper, or platform scale used in 49 weighing contract items of Work. 50 51 1-09.6 Force Account

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 163 1 (October 10, 2008 APWA GSP) 2 3 Supplement this section with the following: 4 5 The Contracting Agency has estimated and included in the Proposal, dollar amounts for 6 all items to be paid per force account, only to provide a common proposal for Bidders. All 7 such dollar amounts are to become a part of Contractor's total bid. However, the 8 Contracting Agency does not warrant expressly or by implication, that the actual amount 9 of work will correspond with those estimates. Payment will be made on the basis of the 10 amount of work actually authorized by Engineer. 11 12 1-09.11(3) Time Limitation and Jurisdiction 13 (November 30, 2018 APWA GSP) 14 15 Revise this section to read: 16 17 For the convenience of the parties to the Contract it is mutually agreed by the parties that 18 any claims or causes of action which the Contractor has against the Contracting Agency 19 arising from the Contract shall be brought within 180 calendar days from the date of final 20 acceptance (Section 1-05.12) of the Contract by the Contracting Agency; and it is further 21 agreed that any such claims or causes of action shall be brought only in the Superior Court 22 of the county where the Contracting Agency headquarters is located, provided that where 23 an action is asserted against a county, RCW 36.01.050 shall control venue and jurisdiction. 24 The parties understand and agree that the Contractor’s failure to bring suit within the time 25 period provided, shall be a complete bar to any such claims or causes of action. It is further 26 mutually agreed by the parties that when any claims or causes of action which the 27 Contractor asserts against the Contracting Agency arising from the Contract are filed with 28 the Contracting Agency or initiated in court, the Contractor shall permit the Contracting 29 Agency to have timely access to any records deemed necessary by the Contracting 30 Agency to assist in evaluating the claims or action. 31 32 1-09.13(3) Claims $250,000 or Less

33 (October 1, 2005 APWA GSP) 34 35 Delete this section and replace it with the following: 36 37 The Contractor and the Contracting Agency mutually agree that those claims that total 38 $250,000 or less, submitted in accordance with Section 1-09.11 and not resolved by 39 nonbinding ADR processes, shall be resolved through litigation unless the parties mutually 40 agree in writing to resolve the claim through binding arbitration. 41 42 1-09.13(3)A Administration of Arbitration 43 (November 30, 2018 APWA GSP) 44 45 Revise the third paragraph to read: 46 47 The Contracting Agency and the Contractor mutually agree to be bound by the decision of 48 the arbitrator, and judgment upon the award rendered by the arbitrator may be entered in 49 the Superior Court of the county in which the Contracting Agency’s headquarters is 50 located, provided that where claims subject to arbitration are asserted against a county, 51 RCW 36.01.050 shall control venue and jurisdiction of the Superior Court. The decision of

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 164 1 the arbitrator and the specific basis for the decision shall be in writing. The arbitrator shall 2 use the Contract as a basis for decisions. 3 4 1-10 Temporary Traffic Control 5 6 1-10.2 Traffic Control Management 7 8 1-10.2(1) General 9 10 Section 1-10.2(1) is supplemented with the following: 11 12 (January 3, 2017) 13 Only training with WSDOT TCS card and WSDOT training curriculum is recognized 14 in the State of Washington. The Traffic Control Supervisor shall be certified by one 15 of the following: 16 17 The Northwest Laborers-Employers Training Trust 18 27055 Ohio Ave. 19 Kingston, WA 98346 20 (360) 297-3035 21 22 Evergreen Safety Council 23 12545 135th Ave. NE 24 Kirkland, WA 98034-8709 25 1-800-521-0778 26 27 The American Traffic Safety Services Association 28 15 Riverside Parkway, Suite 100 29 Fredericksburg, Virginia 22406-1022 30 Training Dept. Toll Free (877) 642-4637 31 Phone: (540) 368-1701 32 33 1-10.4 Measurement 34 35 1-10.4(2) Item Bids With Lump Sum for Incidentals 36 (March 22, 2018 SkagitR) 37 38 The third paragraph of Section 1-10.4(2) is revised to read: 39 40 “Traffic Control Labor” will be measured by the hour. Time spent on activities other 41 than those described herein will not be measured under this item. Hours will be 42 measured for each person engaged in any one of the following activities: 43 44 • Flagging and Spotting. Hours will be measured for each flagging or spotting 45 station, shown on an approved Traffic Control Plan, when that station is staffed 46 in accordance with Section 1-10.3(1)A. When a flagging station is staffed on 47 an intermittent basis, no deduction will be made in measured hours provided 48 that the person staffing the station is in a standby mode and is not performing 49 other duties. 50 51 • Operating a pilot vehicle during one-way piloted traffic control. 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 165 1 • Operating a traffic control vehicle or a chase vehicle during a rolling slowdown 2 operation. 3 4 • Operating a vehicle or placing/removing traffic control devices during the setup 5 or takedown of a lane closure. Performing preliminary work to prepare for 6 placing and removing these devices. 7 8 • Operating any of the moving traffic control equipment, or adjusting signing 9 during a mobile operation as described in Section 1-10.3(2)D. 10 11 • Placing and removing Class B construction signs. Performing preliminary work 12 to prepare for placing and removing these signs. 13 14 • Relocation of Portable Changeable Message Signs within the project limits. 15 16 • Installing and removing Barricades, Traffic Safety Drums, Barrier Drums, 17 Cones, Tubular Markers and Warning Lights and Flashers to carry out 18 approved Traffic Control Plan(s). Performing preliminary work to prepare for 19 installing these devices. 20 21 1-10.5 Payment 22 23 1-10.5(2) Item Bids with Lump Sum for Incidentals 24 (July 14, 2016 SkagitR) 25 26 The second paragraph of Section 1-10.5(2) is revised to read: 27 28 The lump sum contract payment shall be full compensation for all costs incurred 29 by the Contractor in performing the contract work defined in Section 1-10.2(1)B 30 and Section 1-10.3(2)E. 31 32 The fifth, and sixth paragraphs have been revised to read: 33 34 ” Traffic Control Labor”, per hour. 35 36 The unit contract price, when applied to the number of units measured for this 37 item in accordance with Section 1-10.4(2), shall be full compensation for all 38 costs incurred by the Contractor in performing the contract work defined in 39 Section 1-10.3(1)A and as specifically described for this item in Section 1- 40 10.4(2). 41

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 166 1 2 Division 2 3 Earthwork 4 5 2-01 Clearing, Grubbing, and Roadside Cleanup 6 7 2-01.1 Description 8 (May 07, 2019 SkagitR) 9 10 Add the following new Section: 11 12 (******) 13 2-01.1(1) Preparation of Existing Surfaces 14 (October 12, 2016 SkagitR) 15 16 All pavements, bituminous surfaces, concrete surfaces, and shoulders shall be thoroughly 17 cleaned of dust, soil, plant or organic material, pavement grindings, and other foreign 18 matter. 19 20 2-01.4 Measurement 21 (October 12, 2016 SkagitR) 22 23 Section 2-01.4 is supplemented with the following: 24 25 There is no separate unit bid item for “Preparation of Existing Surfaces”. 26 27 2-01.5 Payment 28 (October 12, 2016 SkagitR) 29 30 Section 2-01.5 is supplemented with the following: 31 32 All labor and materials associated with “Preparation of Existing Surfaces” shall be 33 included in the associated unit bid price for bid item “HMA Cl. ⅜” PG 58H-22”. 34 35 2-11 Trimming and Cleanup 36 37 2-11.1 Description 38 (July 14, 2016 SkagitR) 39 40 Section 2-11.1 is revised to read: 41 42 This Work consists of dressing and trimming the entire Roadway(s) improved under the 43 Contract, including frontage roads, connecting ramps, auxiliary lanes, and approach roads. 44 This Work extends to roadbeds, shoulders, lawns and ditches. 45 46 The Contractor shall also trim and clean up the staging areas and any other area the 47 Contractor uses for construction operations. 48 49 2-11.3 Construction Requirements 50 (July 14, 2016 SkagitR) 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 167 1 Item number four in the first paragraph of Section 2-11.3 is revised to read: 2 3 4. Remove and dispose of all weeds, brush, refuse, rocks, asphalt chunks, survey 4 stakes, and any other debris that lie on the roadbed, shoulders, ditches, and slopes. 5

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 168 1 2 Division 5 3 Surface Treatments and Pavements 4 5 5-04 Hot Mix Asphalt 6 (July 18, 2018 APWA GSP) 7 8 Delete Section 5-04 and amendments, Hot Mix Asphalt and replace it with the following: 9 10 5-04.1 Description 11 This Work shall consist of providing and placing one or more layers of plant-mixed hot 12 mix asphalt (HMA) on a prepared foundation or base in accordance with these 13 Specifications and the lines, grades, thicknesses, and typical cross-sections shown 14 in the Plans. The manufacture of HMA may include warm mix asphalt (WMA) processes 15 in accordance with these Specifications. WMA processes include organic additives, 16 chemical additives, and foaming. 17 18 HMA shall be composed of asphalt binder and mineral materials as may be required, 19 mixed in the proportions specified to provide a homogeneous, stable, 20 and workable mixture. 21 22 5-04.2 Materials 23 Materials shall meet the requirements of the following sections: 24 Asphalt Binder 9-02.1(4) 25 Cationic Emulsified Asphalt 9-02.1(6) 26 Anti-Stripping Additive 9-02.4 27 HMA Additive 9-02.5 28 Aggregates 9-03.8 29 Recycled Asphalt Pavement 9-03.8(3)B 30 Mineral Filler 9-03.8(5) 31 Recycled Material 9-03.21 32 Portland Cement 9-01 33 Sand 9-03.1(2) 34 (As noted in 5-04.3(5)C for crack sealing) 35 Joint Sealant 9-04.2 36 Foam Backer Rod 9-04.2(3)A 37 The Contract documents may establish that the various mineral materials required for 38 the manufacture of HMA will be furnished in whole or in part by the Contracting Agency. 39 If the documents do not establish the furnishing of any of these mineral materials by the 40 Contracting Agency, the Contractor shall be required to furnish such materials in the 41 amounts required for the designated mix. Mineral materials include coarse and fine 42 aggregates, and mineral filler. 43 44 The Contractor may choose to utilize recycled asphalt pavement (RAP) in the production 45 of HMA. The RAP may be from pavements removed under the Contract, if any, or 46 pavement material from an existing stockpile. 47

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 169 1 The Contractor may use up to 20 percent RAP by total weight of HMA with no additional 2 sampling or testing of the RAP. The RAP shall be sampled and tested at a frequency of 3 one sample for every 1,000 tons produced and not less than ten samples per project. 4 The asphalt content and gradation test data shall be reported to the Contracting Agency 5 when submitting the mix design for approval on the QPL. The Contractor shall include 6 the RAP as part of the mix design as defined in these Specifications. 7 8 The grade of asphalt binder shall be as required by the Contract. Blending of asphalt 9 binder from different sources is not permitted. 10 11 The Contractor may only use warm mix asphalt (WMA) processes in the production of 12 HMA with 20 percent or less RAP by total weight of HMA. The Contractor shall submit to 13 the Engineer for approval the process that is proposed and how it will be used in the 14 manufacture of HMA. 15 16 Production of aggregates shall comply with the requirements of Section 3-01. 17 Preparation of stockpile site, the stockpiling of aggregates, and the removal of 18 aggregates from stockpiles shall comply with the requirements of Section 3-02. 19 20 5-04.2(1) How to Get an HMA Mix Design on the QPL 21 If the contractor wishes to submit a mix design for inclusion in the Qualified Products List 22 (QPL), please follow the WSDOT process outlined in Standard Specification 5-04.2(1). 23 24 5-04.2(1)A Vacant 25 26 5-04.2(2) Mix Design – Obtaining Project Approval 27 No paving shall begin prior to the approval of the mix design by the Engineer. 28 29 Nonstatistical evaluation will be used for all HMA not designated as Commercial HMA 30 in the contract documents. 31 32 Commercial evaluation will be used for Commercial HMA and for other classes of HMA 33 in the following applications: sidewalks, road approaches, ditches, slopes, paths, trails, 34 gores, prelevel, and pavement repair. Other nonstructural applications of HMA accepted 35 by commercial evaluation shall be as approved by the Project Engineer. Sampling and 36 testing of HMA accepted by commercial evaluation will be at the option of the Project 37 Engineer. The Proposal quantity of HMA that is accepted by commercial evaluation will 38 be excluded from the quantities used in the determination of nonstatistical evaluation. 39 40 Nonstatistical Mix Design. Fifteen days prior to the first day of paving the contractor 41 shall provide one of the following mix design verification certifications for Contracting 42 Agency review; 43 44 • The WSDOT Mix Design Evaluation Report from the current WSDOT QPL, or 45 one of the mix design verification certifications listed below. 46 • The proposed HMA mix design on WSDOT Form 350-042 with the seal and 47 certification (stamp & sig-nature) of a valid licensed Washington State 48 Professional Engineer.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 170 1 • The Mix Design Report for the proposed HMA mix design developed by a 2 qualified City or County laboratory that is within one year of the approval date.** 3 4 The mix design shall be performed by a lab accredited by a national authority such as 5 Laboratory Accreditation Bureau, L-A-B for Construction Materials Testing, The 6 Construction Materials Engineering Council (CMEC’s) ISO 17025 or AASHTO 7 Accreditation Program (AAP) and shall supply evidence of participation in the AASHTO: 8 resource proficiency sample program. 9 10 Mix designs for HMA accepted by Nonstatistical evaluation shall; 11 12 • Have the aggregate structure and asphalt binder content determined in 13 accordance with WSDOT Standard Operating Procedure 732 and meet the 14 requirements of Sections 9-03.8(2), except that Hamburg testing for ruts and 15 stripping are at the discretion of the Engineer, and 9-03.8(6). 16 • Have anti-strip requirements, if any, for the proposed mix design determined in 17 accordance with AASHTO T 283 or T 324, or based on historic anti-strip and 18 aggregate source compatibility from previous WSDOT lab testing. 19 20 At the discretion of the Engineer, agencies may accept verified mix designs older than 12 21 months from the original verification date with a certification from the Contractor that the 22 materials and sources are the same as those shown on the original mix design. 23 24 Commercial Evaluation Approval of a mix design for “Commercial Evaluation” will be 25 based on a review of the Contractor’s submittal of WSDOT Form 350-042 (For 26 commercial mixes, AASHTO T 324 evaluation is not required) or a Mix Design from the 27 current WSDOT QPL or from one of the processes allowed by this section. Testing of the 28 HMA by the Contracting Agency for mix design approval is not required. 29 30 For the Bid Item Commercial HMA, the Contractor shall select a class of HMA and 31 design level of Equivalent Single Axle Loads (ESAL’s) appropriate for the required use. 32 33 ESAL's 34 The number of ESAL's for the design and acceptance of the HMA shall 35 be *** 2.44 *** million. 36 37 38 5-04.2(2)B Using Warm Mix Asphalt Processes 39 The Contractor may elect to use additives that reduce the optimum mixing temperature 40 or serve as a compaction aid for producing HMA. Additives include organic additives, 41 chemical additives and foaming processes. The use of Additives is subject to the 42 following: 43 44 • Do not use additives that reduce the mixing temperature more than allowed in 45 Section 5-04.3(6) in the production of mixtures. 46 • Before using additives, obtain the Engineer’s approval using WSDOT Form 350- 47 076 to describe the proposed additive and process. 48 49 5-04.3 Construction Requirements

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 171 1 2 5-04.3(1) Weather Limitations 3 Do not place HMA for wearing course on any Traveled Way beginning October 1st 4 through March 31st of the following year without written concurrence from the Engineer. 5 6 Do not place HMA on any wet surface, or when the average surface temperatures are 7 less than those specified below, or when weather conditions otherwise prevent the 8 proper handling or finishing of the HMA. 9 10 Minimum Surface Temperature for Paving Compacted Thickness Wearing Course Other Courses (Feet)

Less than 0.10 55◦F 45◦F

0.10 to .20 45◦F 35◦F

More than 0.20 35◦F 35◦F

11 12 5-04.3(2) Paving Under Traffic 13 When the Roadway being paved is open to traffic, the requirements of this Section 14 shall apply. 15 16 The Contractor shall keep intersections open to traffic at all times except when paving 17 the intersection or paving across the intersection. During such time, and provided that 18 there has been an advance warning to the public, the intersection may be closed for the 19 minimum time required to place and compact the mixture. In hot weather, the Engineer 20 may require the application of water to the pavement to accelerate the finish rolling of the 21 pavement and to shorten the time required before reopening to traffic. 22 23 Before closing an intersection, advance warning signs shall be placed and signs shall 24 also be placed marking the detour or alternate route. 25 26 During paving operations, temporary pavement markings shall be maintained throughout 27 the project. Temporary pavement markings shall be installed on the Roadway prior to 28 opening to traffic. Temporary pavement markings shall be in accordance with Section 8- 29 23. 30 31 All costs in connection with performing the Work in accordance with these requirements, 32 except the cost of temporary pavement markings, shall be included in the unit Contract 33 prices for the various Bid items involved in the Contract. 34 35 5-04.3(3) Equipment 36 37 5-04.3(3)A Mixing Plant 38 Plants used for the preparation of HMA shall conform to the following requirements:

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 172 1 2 1. Equipment for Preparation of Asphalt Binder – Tanks for the storage of 3 asphalt binder shall be equipped to heat and hold the material at the required 4 temperatures. The heating shall be accomplished by steam coils, electricity, or 5 other approved means so that no flame shall be in contact with the storage tank. 6 The circulating system for the asphalt binder shall be designed to ensure proper 7 and continuous circulation during the operating period. A valve for the purpose of 8 sampling the asphalt binder shall be placed in either the storage tank or in the 9 supply line to the mixer. 10 2. Thermometric Equipment – An armored thermometer, capable of detecting 11 temperature ranges expected in the HMA mix, shall be fixed in the asphalt binder 12 feed line at a location near the charging valve at the mixer unit. The thermometer 13 location shall be convenient and safe for access by Inspectors. The plant shall 14 also be equipped with an approved dial-scale thermometer, a mercury actuated 15 thermometer, an electric pyrometer, or another approved thermometric 16 instrument placed at the discharge chute of the drier to automatically register or 17 indicate the temperature of the heated aggregates. This device shall be in full 18 view of the plant operator. 19 3. Heating of Asphalt Binder – The temperature of the asphalt binder shall not 20 exceed the maximum recommended by the asphalt binder manufacturer nor shall 21 it be below the minimum temperature required to maintain the asphalt binder in a 22 homogeneous state. The asphalt binder shall be heated in a manner that will 23 avoid local variations in heating. The heating method shall provide a continuous 24 supply of asphalt binder to the mixer at a uniform average temperature with no 25 individual variations exceeding 25°F. Also, when a WMA additive is included in 26 the asphalt binder, the temperature of the asphalt binder shall not exceed the 27 maximum recommended by the manufacturer of the WMA additive. 28 4. Sampling and Testing of Mineral Materials – The HMA plant shall be equipped 29 with a mechanical sampler for the sampling of the mineral materials. The 30 mechanical sampler shall meet the requirements of Section 1-05.6 for the 31 crushing and screening operation. The Contractor shall provide for the setup and 32 operation of the field testing facilities of the Contracting Agency as provided for in 33 Section 3-01.2(2). 34 5. Sampling HMA – The HMA plant shall provide for sampling HMA by one of the 35 following methods: 36 a. A mechanical sampling device attached to the HMA plant. 37 b. Platforms or devices to enable sampling from the hauling vehicle without 38 entering the hauling vehicle. 39 40 5-04.3(3)B Hauling Equipment 41 Trucks used for hauling HMA shall have tight, clean, smooth metal beds and shall have a 42 cover of canvas or other suitable material of sufficient size to protect the mixture from 43 adverse weather. Whenever the weather conditions during the work shift include, or are 44 forecast to include, precipitation or an air temperature less than 45°F or when time from 45 loading to unloading exceeds 30 minutes, the cover shall be securely attached to protect 46 the HMA. 47 48 The contractor shall provide an environmentally benign means to prevent the HMA 49 mixture from adhering to the hauling equipment. Excess release agent shall be drained

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 173 1 prior to filling hauling equipment with HMA. Petroleum derivatives or other coating 2 material that contaminate or alter the characteristics of the HMA shall not be used. For 3 live bed trucks, the conveyer shall be in operation during the process of applying the 4 release agent. 5 6 5-04.3(3)C Pavers 7 HMA pavers shall be self-contained, power-propelled units, provided with an internally 8 heated vibratory screed and shall be capable of spreading and finishing courses of HMA 9 plant mix material in lane widths required by the paving section shown in the Plans. 10 11 The HMA paver shall be in good condition and shall have the most current equipment 12 available from the manufacturer for the prevention of segregation of the HMA mixture 13 installed, in good condition, and in working order. The equipment certification shall list 14 the make, model, and year of the paver and any equipment that has been retrofitted. 15 16 The screed shall be operated in accordance with the manufacturer’s recommendations 17 and shall effectively produce a finished surface of the required evenness and texture 18 without tearing, shoving, segregating, or gouging the mixture. A copy of the 19 manufacturer’s recommendations shall be provided upon request by the Contracting 20 Agency. Extensions will be allowed provided they produce the same results, including 21 ride, density, and surface texture as obtained by the primary screed. Extensions without 22 augers and an internally heated vibratory screed shall not be used in the Traveled Way. 23 24 When specified in the Contract, reference lines for vertical control will be required. Lines 25 shall be placed on both outer edges of the Traveled Way of each Roadway. Horizontal 26 control utilizing the reference line will be permitted. The grade and slope for intermediate 27 lanes shall be controlled automatically from reference lines or by means of a mat 28 referencing device and a slope control device. When the finish of the grade prepared for 29 paving is superior to the established tolerances and when, in the opinion of the Engineer, 30 further improvement to the line, grade, cross-section, and smoothness can best be 31 achieved without the use of the reference line, a mat referencing device may be 32 substituted for the reference line. Substitution of the device will be subject to the 33 continued approval of the Engineer. A joint matcher may be used subject to the approval 34 of the Engineer. The reference line may be removed after the completion of the first 35 course of HMA when approved by the Engineer. Whenever the Engineer determines that 36 any of these methods are failing to provide the necessary vertical control, the reference 37 lines will be reinstalled by the Contractor. 38 39 The Contractor shall furnish and install all pins, brackets, tensioning devices, wire, and 40 accessories necessary for satisfactory operation of the automatic control equipment. 41 42 If the paving machine in use is not providing the required finish, the Engineer may 43 suspend Work as allowed by Section 1-08.6. Any cleaning or solvent type liquids spilled 44 on the pavement shall be thoroughly removed before paving proceeds. 45 46 5-04.3(3)D Material Transfer Device or Material Transfer Vehicle 47 A Material Transfer Device/Vehicle (MTD/V) shall only be used with the Engineer’s 48 approval, unless other-wise required by the contract.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 174 1 2 Where an MTD/V is required by the contract, the Engineer may approve paving without 3 an MTD/V, at the request of the Contractor. The Engineer will determine if an equitable 4 adjustment in cost or time is due. 5 6 When used, the MTD/V shall mix the HMA after delivery by the hauling equipment and 7 prior to laydown by the paving machine. Mixing of the HMA shall be sufficient to obtain a 8 uniform temperature throughout the mixture. If a windrow elevator is used, the length of 9 the windrow may be limited in urban areas or through intersections, at the discretion of 10 the Engineer. 11 12 To be approved for use, an MTV: 13 14 1. Shall be self-propelled vehicle, separate from the hauling vehicle or paver. 15 2. Shall not be connected to the hauling vehicle or paver. 16 3. May accept HMA directly from the haul vehicle or pick up HMA from a windrow. 17 4. Shall mix the HMA after delivery by the hauling equipment and prior to 18 placement into the paving machine. 19 5. Shall mix the HMA sufficiently to obtain a uniform temperature throughout the 20 mixture. 21 22 To be approved for use, an MTD: 23 24 1. Shall be positively connected to the paver. 25 2. May accept HMA directly from the haul vehicle or pick up HMA from a windrow. 26 3. Shall mix the HMA after delivery by the hauling equipment and prior to 27 placement into the paving machine. 28 4. Shall mix the HMA sufficiently to obtain a uniform temperature throughout the 29 mixture. 30 31 5-04.3(3)E Rollers 32 Rollers shall be of the steel wheel, vibratory, oscillatory, or pneumatic tire type, in good 33 condition and capable of reversing without backlash. Operation of the roller shall be in 34 accordance with the manufacturer’s recommendations. When ordered by the Engineer 35 for any roller planned for use on the project, the Contractor shall provide a copy of the 36 manufacturer’s recommendation for the use of that roller for compaction of HMA. The 37 number and weight of rollers shall be sufficient to compact the mixture in compliance 38 with the requirements of Section 5-04.3(10). The use of equipment that results in 39 crushing of the aggregate will not be permitted. Rollers producing pickup, washboard, 40 uneven compaction of the surface, displacement of the mixture or other undesirable 41 results shall not be used. 42 43 5-04.3(4) Preparation of Existing Paved Surfaces 44 When the surface of the existing pavement or old base is irregular, the Contractor shall 45 bring it to a uniform grade and cross-section as shown on the Plans or approved by the 46 Engineer.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 175 1 2 Preleveling of uneven or broken surfaces over which HMA is to be placed may be 3 accomplished by using an asphalt paver, a motor patrol grader, or by hand raking, as 4 approved by the Engineer. 5 6 Compaction of preleveling HMA shall be to the satisfaction of the Engineer and may 7 require the use of small steel wheel rollers, plate compactors, or pneumatic rollers to 8 avoid bridging across preleveled areas by the compaction equipment. Equipment used 9 for the compaction of preleveling HMA shall be approved by the Engineer. 10 11 Before construction of HMA on an existing paved surface, the entire surface of the 12 pavement shall be clean. All fatty asphalt patches, grease drippings, and other 13 objectionable matter shall be entirely removed from the existing pavement. All 14 pavements or bituminous surfaces shall be thoroughly cleaned of dust, soil, pavement 15 grindings, and other foreign matter. All holes and small depressions shall be filled with an 16 appropriate class of HMA. The surface of the patched area shall be leveled and 17 compacted thoroughly. Prior to the application of tack coat, or paving, the condition of 18 the surface shall be approved by the Engineer. 19 20 A tack coat of asphalt shall be applied to all paved surfaces on which any course of HMA 21 is to be placed or abutted; except that tack coat may be omitted from clean, newly paved 22 surfaces at the discretion of the Engineer. Tack coat shall be uniformly applied to cover 23 the existing pavement with a thin film of residual asphalt free of streaks and bare spots at 24 a rate between 0.02 and 0.10 gallons per square yard of retained asphalt. The rate of 25 application shall be approved by the Engineer. A heavy application of tack coat shall be 26 applied to all joints. For Roadways open to traffic, the application of tack coat shall be 27 limited to surfaces that will be paved during the same working shift. The spreading 28 equipment shall be equipped with a thermometer to indicate the temperature of the tack 29 coat material. 30 31 Equipment shall not operate on tacked surfaces until the tack has broken and cured. If 32 the Contractor’s operation damages the tack coat it shall be repaired prior to placement 33 of the HMA. 34 35 The tack coat shall be CSS-1, or CSS-1h emulsified asphalt. The CSS-1 and CSS-1h 36 emulsified asphalt may be diluted once with water at a rate not to exceed one part water 37 to one part emulsified asphalt. The tack coat shall have sufficient temperature such that 38 it may be applied uniformly at the specified rate of application and shall not exceed the 39 maximum temperature recommended by the emulsified asphalt manufacturer. 40 41 5-04.3(4)A Crack Sealing 42 43 5-04.3(4)A1 General 44 When the Proposal includes a pay item for crack sealing, seal all cracks ¼ inch in width 45 and greater. 46 47 Cleaning: Ensure that cracks are thoroughly clean, dry and free of all loose and foreign 48 material when filling with crack sealant material. Use a hot compressed air lance to dry

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 176 1 and warm the pavement surfaces within the crack immediately prior to filling a crack with 2 the sealant material. Do not overheat pavement. Do not use direct flame dryers. Routing 3 cracks is not required. 4 5 Sand Slurry: For cracks that are to be filled with sand slurry, thoroughly mix the 6 components and pour the mixture into the cracks until full. Add additional CSS-1 cationic 7 emulsified asphalt to the sand slurry as needed for workability to ensure the mixture will 8 completely fill the cracks. Strike off the sand slurry flush with the existing pavement 9 surface and allow the mixture to cure. Top off cracks that were not completely filled with 10 additional sand slurry. Do not place the HMA overlay until the slurry has fully cured. 11 12 The sand slurry shall consist of approximately 20 percent CSS-1 emulsified asphalt, 13 approximately 2 percent portland cement, water (if required), and the remainder clean 14 Class 1 or 2 fine aggregate per section 9-03.1(2). The components shall be thoroughly 15 mixed and then poured into the cracks and joints until full. The following day, any cracks 16 or joints that are not completely filled shall be topped off with additional sand slurry. After 17 the sand slurry is placed, the filler shall be struck off flush with the existing pavement 18 surface and allowed to cure. The HMA overlay shall not be placed until the slurry has 19 fully cured. The requirements of Section 1-06 will not apply to the portland cement and 20 sand used in the sand slurry. 21 22 In areas where HMA will be placed, use sand slurry to fill the cracks. 23 24 In areas where HMA will not be placed, fill the cracks as follows: 25 26 1. Cracks ¼ inch to 1 inch in width - fill with hot poured sealant. 27 2. Cracks greater than 1 inch in width – fill with sand slurry. 28 29 Hot Poured Sealant: For cracks that are to be filled with hot poured sealant, apply the 30 material in accordance with these requirements and the manufacturer’s 31 recommendations. Furnish a Type 1 Working Drawing of the manufacturer’s product 32 information and recommendations to the Engineer prior to the start of work, including the 33 manufacturer’s recommended heating time and temperatures, allowable storage time 34 and temperatures after initial heating, allowable reheating criteria, and application 35 temperature range. Confine hot poured sealant material within the crack. Clean any 36 overflow of sealant from the pavement surface. If, in the opinion of the Engineer, the 37 Contractor’s method of sealing the cracks with hot poured sealant results in an excessive 38 amount of material on the pavement surface, stop and correct the operation to eliminate 39 the excess material. 40 41 5-04.3(4)A2 Crack Sealing Areas Prior to Paving 42 In areas where HMA will be placed, use sand slurry to fill the cracks. 43 44 5-04.3(4)A3 Crack Sealing Areas Not to be Paved 45 In areas where HMA will not be placed, fill the cracks as follows: 46 47 A. Cracks ¼ inch to 1 inch in width - fill with hot poured sealant.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 177 1 B. Cracks greater than 1 inch in width – fill with sand slurry. 2 3 5-04.3(4)B Vacant 4 5 5-04.3(4)C Pavement Repair 6 The Contractor shall excavate pavement repair areas and shall backfill these with HMA 7 in accordance with the details shown in the Plans and as marked in the field. The 8 Contractor shall conduct the excavation operations in a manner that will protect the 9 pavement that is to remain. Pavement not designated to be removed that is damaged as 10 a result of the Contractor’s operations shall be repaired by the Contractor to the 11 satisfaction of the Engineer at no cost to the Contracting Agency. The Contractor shall 12 excavate only within one lane at a time unless approved otherwise by the Engineer. The 13 Contractor shall not excavate more area than can be completely finished during the 14 same shift, unless approved by the Engineer. 15 16 Unless otherwise shown in the Plans or determined by the Engineer, excavate to a depth 17 of 1.0 feet. The Engineer will make the final determination of the excavation depth 18 required. The minimum width of any pavement repair area shall be 40 inches unless 19 shown otherwise in the Plans. Before any excavation, the existing pavement shall be 20 sawcut or shall be removed by a pavement grinder. Excavated materials will become the 21 property of the Contractor and shall be disposed of in a Contractor-provided site off the 22 Right of Way or used in accordance with Sections 2-02.3(3) or 9-03.21. 23 24 Asphalt for tack coat shall be required as specified in Section 5-04.3(4). A heavy 25 application of tack coat shall be applied to all surfaces of existing pavement in the 26 pavement repair area. 27 28 Placement of the HMA backfill shall be accomplished in lifts not to exceed 0.35-foot 29 compacted depth. Lifts that exceed 0.35-foot of compacted depth may be accomplished 30 with the approval of the Engineer. Each lift shall be thoroughly compacted by a 31 mechanical tamper or a roller. 32 33 5-04.3(5) Producing/Stockpiling Aggregates and RAP 34 Aggregates and RAP shall be stockpiled according to the requirements of Section 3-02. 35 Sufficient storage space shall be provided for each size of aggregate and RAP. Materials 36 shall be removed from stockpile(s) in a manner to ensure minimal segregation when 37 being moved to the HMA plant for processing into the final mixture. Different aggregate 38 sizes shall be kept separated until they have been delivered to the HMA plant. 39 40 5-04.3(5)A Vacant 41 42 5-04.3(6) Mixing 43 After the required amount of mineral materials, asphalt binder, recycling agent and anti- 44 stripping additives have been introduced into the mixer the HMA shall be mixed until 45 complete and uniform coating of the particles and thorough distribution of the asphalt 46 binder throughout the mineral materials is ensured. 47

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 178 1 When discharged, the temperature of the HMA shall not exceed the optimum mixing 2 temperature by more than 25°F as shown on the reference mix design report or as 3 approved by the Engineer. Also, when a WMA additive is included in the manufacture of 4 HMA, the discharge temperature of the HMA shall not exceed the maximum 5 recommended by the manufacturer of the WMA additive. A maximum water content of 2 6 percent in the mix, at discharge, will be allowed providing the water causes no problems 7 with handling, stripping, or flushing. If the water in the HMA causes any of these 8 problems, the moisture content shall be reduced as directed by the Engineer. 9 10 Storing or holding of the HMA in approved storage facilities will be permitted with 11 approval of the Engineer, but in no event shall the HMA be held for more than 24 hours. 12 HMA held for more than 24 hours after mixing shall be rejected. Rejected HMA shall be 13 disposed of by the Contractor at no expense to the Contracting Agency. The storage 14 facility shall have an accessible device located at the top of the cone or about the third 15 point. The device shall indicate the amount of material in storage. No HMA shall be 16 accepted from the storage facility when the HMA in storage is below the top of the cone 17 of the storage facility, except as the storage facility is being emptied at the end of the 18 working shift. 19 20 Recycled asphalt pavement (RAP) utilized in the production of HMA shall be sized prior 21 to entering the mixer so that a uniform and thoroughly mixed HMA is produced. If there is 22 evidence of the recycled asphalt pavement not breaking down during the heating and 23 mixing of the HMA, the Contractor shall immediately suspend the use of the RAP until 24 changes have been approved by the Engineer. After the required amount of mineral 25 materials, RAP, new asphalt binder and asphalt rejuvenator have been introduced into 26 the mixer the HMA shall be mixed until complete and uniform coating of the particles and 27 thorough distribution of the asphalt binder throughout the mineral materials, and RAP is 28 ensured. 29 30 5-04.3(7) Spreading and Finishing 31 The mixture shall be laid upon an approved surface, spread, and struck off to the grade 32 and elevation established. HMA pavers complying with Section 5-04.3(3) shall be used 33 to distribute the mixture. Unless otherwise directed by the Engineer, the nominal 34 compacted depth of any layer of any course shall not exceed the following: 35 36 HMA Class 1” 0.35 feet 37 HMA Class ¾” and HMA Class ½” 38 wearing course 0.30 feet 39 other courses 0.35 feet 40 HMA Class ⅜” 0.15 feet 41 42 On areas where irregularities or unavoidable obstacles make the use of mechanical 43 spreading and finishing equipment impractical, the paving may be done with other 44 equipment or by hand. 45 46 When more than one JMF is being utilized to produce HMA, the material produced for 47 each JMF shall be placed by separate spreading and compacting equipment. The 48 intermingling of HMA produced from more than one JMF is prohibited. Each strip of HMA

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 179 1 placed during a work shift shall conform to a single JMF established for the class of HMA 2 specified unless there is a need to make an adjustment in the JMF. 3 4 5-04.3(8) Aggregate Acceptance Prior to Incorporation in HMA 5 For HMA accepted by nonstatistical evaluation the aggregate properties of sand 6 equivalent, uncompacted void content and fracture will be evaluated in accordance with 7 Section 3-04. Sampling and testing of aggregates for HMA accepted by commercial 8 evaluation will be at the option of the Engineer. 9 10 5-04.3(9) HMA Mixture Acceptance 11 Acceptance of HMA shall be as provided under nonstatistical, or commercial evaluation. 12 13 Nonstatistical evaluation will be used for the acceptance of HMA unless Commercial 14 Evaluation is specified. 15 16 Commercial evaluation will be used for Commercial HMA and for other classes of HMA 17 in the following applications: sidewalks, road approaches, ditches, slopes, paths, trails, 18 gores, prelevel, temporary pavement, and pavement repair. Other nonstructural 19 applications of HMA accepted by commercial evaluation shall be as approved by the 20 Engineer. Sampling and testing of HMA accepted by commercial evaluation will be at the 21 option of the Engineer. 22 23 The mix design will be the initial JMF for the class of HMA. The Contractor may request a 24 change in the JMF. Any adjustments to the JMF will require the approval of the Engineer 25 and may be made in accordance with this section. 26 27 HMA Tolerances and Adjustments 28 1. Job Mix Formula Tolerances – The constituents of the mixture at the time of 29 acceptance shall be within tolerance. The tolerance limits will be established as 30 follows: 31 For Asphalt Binder and Air Voids (Va), the acceptance limits are determined 32 by adding the tolerances below to the approved JMF values. These values 33 will also be the Upper Specification Limit (USL) and Lower Specification Limit 34 (LSL) required in Section 1-06.2(2)D2 Property Non-Statistical Evaluation Commercial Evaluation Asphalt Binder +/- 0.5% +/- 0.7% Air Voids, Va 2.5% min. and 5.5% max N/A 35 For Aggregates in the mixture: 36 a. First, determine preliminary upper and lower acceptance limits by applying the 37 following tolerances to the approved JMF. Aggregate Percent Non-Statistical Commercial Passing Evaluation Evaluation 1”, ¾”, ½”, and ⅜” sieves +/- 6% +/- 8% No. 4 sieve +/-6% +/- 8% No. 8 Sieve +/- 6% +/-8% No. 200 sieve +/- 2.0% +/- 3.0% 38 b. Second, adjust the preliminary upper and lower acceptance limits determined 39 from step (a) the minimum amount necessary so that none of the aggregate 40 properties are outside the control points in Section 9-03.8(6). The resulting

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 180 1 values will be the upper and lower acceptance limits for aggregates, as well as 2 the USL and LSL required in Section 1-06.2(2)D2. 3 2. Job Mix Formula Adjustments – An adjustment to the aggregate gradation or 4 asphalt binder content of the JMF requires approval of the Engineer. Adjustments 5 to the JMF will only be considered if the change produces material of equal or 6 better quality and may require the development of a new mix design if the 7 adjustment exceeds the amounts listed below. 8 a. Aggregates –2 percent for the aggregate passing the 1½″, 1″, ¾″, ½″, ⅜″, and 9 the No. 4 sieves, 1 percent for aggregate passing the No. 8 sieve, and 0.5 10 percent for the aggregate passing the No. 200 sieve. The adjusted JMF shall 11 be within the range of the control points in Section 9-03.8(6). 12 b. Asphalt Binder Content – The Engineer may order or approve changes to 13 asphalt binder content. The maximum adjustment from the approved mix 14 design for the asphalt binder content shall be 0.3 percent 15 16 5-04.3(9)A Vacant 17 18 5-04.3(9)B Vacant 19 20 5-04.3(9)C Mixture Acceptance – Nonstatistical Evaluation 21 HMA mixture which is accepted by Nonstatistical Evaluation will be evaluated by the 22 Contracting Agency by dividing the HMA tonnage into lots. 23 24 5-04.3(9)C1 Mixture Nonstatistical Evaluation – Lots and Sublots 25 A lot is represented by randomly selected samples of the same mix design that will be 26 tested for acceptance. A lot is defined as the total quantity of material or work produced 27 for each Job Mix Formula placed. Only one lot per JMF is expected. A sublot shall be 28 equal to one day’s production or 800 tons, whichever is less except that the final sublot 29 will be a minimum of 400 tons and may be increased to 1200 tons. 30 31 All of the test results obtained from the acceptance samples from a given lot shall be 32 evaluated collectively. If the Contractor requests a change to the JMF that is approved, 33 the material produced after the change will be evaluated on the basis of the new JMF for 34 the remaining sublots in the current lot and for acceptance of subsequent lots. For a lot 35 in progress with a CPF less than 0.75, a new lot will begin at the Contractor’s request 36 after the Engineer is satisfied that material conforming to the Specifications can be 37 produced. 38 39 Sampling and testing for evaluation shall be performed on the frequency of one sample 40 per sublot. 41 42 5-04.3(9)C2 Mixture Nonstatistical Evaluation Sampling 43 Samples for acceptance testing shall be obtained by the Contractor when ordered by the 44 Engineer. The Contractor shall sample the HMA mixture in the presence of the Engineer 45 and in accordance with AASH-TO T 168. A minimum of three samples should be taken 46 for each class of HMA placed on a project. If used in a structural application, at least one 47 of the three samples shall to be tested.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 181 1 2 Sampling and testing HMA in a Structural application where quantities are less than 400 3 tons is at the discretion of the Engineer. 4 5 For HMA used in a structural application and with a total project quantity less than 800 6 tons but more than 400 tons, a minimum of one acceptance test shall be performed. In 7 all cases, a minimum of 3 samples will be obtained at the point of acceptance, a 8 minimum of one of the three samples will be tested for conformance to the JMF: 9 10 • If the test results are found to be within specification requirements, additional 11 testing will be at the Engineer’s discretion. 12 • If test results are found not to be within specification requirements, additional 13 testing of the remaining samples to determine a Composite Pay Factor (CPF) shall 14 be performed. 15 16 5-04.3(9)C3 Mixture Nonstatistical Evaluation – Acceptance Testing

17 Testing of HMA for compliance of Va will at the option of the Contracting Agency. If 18 tested, compliance of Va will use WSDOT SOP 731. 19 20 Testing for compliance of asphalt binder content will be by WSDOT FOP for AASHTO T 21 308. 22 23 Testing for compliance of gradation will be by FOP for WAQTC T 27/T 11. 24 25 5-04.3(9)C4 Mixture Nonstatistical Evaluation – Pay Factors 26 For each lot of material falling outside the tolerance limits in 5-04.3(9), the Contracting 27 Agency will determine a Composite Pay Factor (CPF) using the following price 28 adjustment factors: 29 Table of Price Adjustment Factors

Constituent Factor “f”

All aggregate passing: 1½″, 1″, ¾″, ½″, ⅜″ and 2 No.4 sieves All aggregate passing No. 8 sieve 15

All aggregate passing No. 200 sieve 20

Asphalt binder 40

Air Voids (Va) (where applicable) 20 30 31 Each lot of HMA produced under Nonstatistical Evaluation and having all constituents 32 falling within the tolerance limits of the job mix formula shall be accepted at the unit 33 Contract price with no further evaluation. When one or more constituents fall outside the 34 nonstatistical tolerance limits in the Job Mix Formula shown in Table of Price Adjustment 35 Factors, the lot shall be evaluated in accordance with Section 1-06.2 to determine the 36 appropriate CPF. The nonstatistical tolerance limits will be used in the calculation of the

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 182 1 CPF and the maximum CPF shall be 1.00. When less than three sublots exist, backup 2 samples of the existing sublots or samples from the Roadway shall be tested to provide 3 a minimum of three sets of results for evaluation. 4 5 5-04.3(9)C5 Vacant 6 7 5-04.3(9)C6 Mixture Nonstatistical Evaluation – Price Adjustments 8 For each lot of HMA mix produced under Nonstatistical Evaluation when the calculated 9 CPF is less than 1.00, a Nonconforming Mix Factor (NCMF) will be determined. The 10 NCMF equals the algebraic difference of CPF minus 1.00 multiplied by 60 percent. The 11 total job mix compliance price adjustment will be calculated as the product of the NCMF, 12 the quantity of HMA in the lot in tons, and the unit Contract price per ton of mix. 13 14 If a constituent is not measured in accordance with these Specifications, its individual 15 pay factor will be considered 1.00 in calculating the Composite Pay Factor (CPF). 16 17 5-04.3(9)C7 Mixture Nonstatistical Evaluation - Retests 18 The Contractor may request a sublot be retested. To request a retest, the Contractor 19 shall submit a written request within 7 calendar days after the specific test results have 20 been received. A split of the original acceptance sample will be retested. The split of the 21 sample will not be tested with the same tester that ran the original acceptance test. The 22 sample will be tested for a complete gradation analysis, asphalt binder content, and, at 23 the option of the agency, Va. The results of the retest will be used for the acceptance of 24 the HMA in place of the original sublot sample test results. The cost of testing will be 25 deducted from any monies due or that may come due the Contractor under the Contract 26 at the rate of $500 per sample. 27 28 5-04.3 (9)D Mixture Acceptance – Commercial Evaluation 29 If sampled and tested, HMA produced under Commercial Evaluation and having all 30 constituents falling within the tolerance limits of the job mix formula shall be accepted at 31 the unit Contract price with no further evaluation. When one or more constituents fall 32 outside the commercial tolerance limits in the Job Mix Formula shown in 5-04.3(9), the 33 lot shall be evaluated in accordance with Section 1-06.2 to determine the appropriate 34 CPF. The commercial tolerance limits will be used in the calculation of the CPF and the 35 maximum CPF shall be 1.00. When less than three sublots exist, backup samples of the 36 existing sublots or samples from the street shall be tested to provide a minimum of three 37 sets of results for evaluation. 38 39 For each lot of HMA mix produced and tested under Commercial Evaluation when the 40 calculated CPF is less than 1.00, a Nonconforming Mix Factor (NCMF) will be 41 determined. The NCMF equals the algebraic difference of CPF minus 1.00 multiplied by 42 60 percent. The Job Mix Compliance Price Adjustment will be calculated as the product 43 of the NCMF, the quantity of HMA in the lot in tons, and the unit Contract price per ton of 44 mix. 45 46 If a constituent is not measured in accordance with these Specifications, its individual 47 pay factor will be considered 1.00 in calculating the Composite Pay Factor (CPF). 48

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 183 1 5-04.3(10) HMA Compaction Acceptance 2 HMA mixture accepted by nonstatistical evaluation that is used in traffic lanes, including 3 lanes for intersections, ramps, truck climbing, weaving, and speed change, and having a 4 specified compacted course thickness greater than 0.10-foot, shall be compacted to a 5 specified level of relative density. The specified level of relative density shall be a 6 Composite Pay Factor (CPF) of not less than 0.75 when evaluated in accordance with 7 Section 1-06.2, using a LSL of 92.0 (minimum of 92 percent of the maximum density). 8 The maximum density shall be determined by WSDOT FOP for AASHTO T 729. The 9 specified level of density attained will be determined by the evaluation of the density of 10 the pavement. The density of the pavement shall be determined in accordance with 11 WSDOT FOP for WAQTC TM 8, except that gauge correlation will be at the discretion of 12 the Engineer, when using the nuclear density gauge and WSDOT SOP 736 when using 13 cores to determine density. 14 15 Tests for the determination of the pavement density will be taken in accordance with the 16 required procedures for measurement by a nuclear density gauge or roadway cores after 17 completion of the finish rolling. 18 19 If the Contracting Agency uses a nuclear density gauge to determine density the test 20 procedures FOP for WAQTC TM 8 and WSDOT SOP T 729 will be used on the day the 21 mix is placed and prior to opening to traffic. 22 23 Roadway cores for density may be obtained by either the Contracting Agency or the 24 Contractor in accordance with WSDOT SOP 734. The core diameter shall be 4-inches 25 minimum, unless otherwise approved by the Engineer. Roadway cores will be tested by 26 the Contracting Agency in accordance with WSDOT FOP for AASHTO T 166. 27 28 If the Contract includes the Bid item “Roadway Core” the cores shall be obtained by the 29 Contractor in the presence of the Engineer on the same day the mix is placed and at 30 locations designated by the Engineer. If the Contract does not include the Bid item 31 “Roadway Core” the Contracting Agency will obtain the cores. 32 33 For a lot in progress with a CPF less than 0.75, a new lot will begin at the Contractor’s 34 request after the Engineer is satisfied that material conforming to the Specifications can 35 be produced. 36 37 HMA mixture accepted by commercial evaluation and HMA constructed under conditions 38 other than those listed above shall be compacted on the basis of a test point evaluation 39 of the compaction train. The test point evaluation shall be performed in accordance with 40 instructions from the Engineer. The number of passes with an approved compaction 41 train, required to attain the maximum test point density, shall be used on all subsequent 42 paving. 43 44 HMA for preleveling shall be thoroughly compacted. HMA that is used for preleveling 45 wheel rutting shall be compacted with a pneumatic tire roller unless otherwise approved 46 by the Engineer. 47 48 Test Results

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 184 1 For a sublot that has been tested with a nuclear density gauge that did not meet the 2 minimum of 92 percent of the reference maximum density in a compaction lot with a CPF 3 below 1.00 and thus subject to a price reduction or rejection, the Contractor may request 4 that a core be used for determination of the relative density of the sublot. The relative 5 density of the core will replace the relative density determined by the nuclear density 6 gauge for the sublot and will be used for calculation of the CPF and acceptance of HMA 7 compaction lot. 8 9 When cores are taken by the Contracting Agency at the request of the Contractor, they 10 shall be requested by noon of the next workday after the test results for the sublot have 11 been provided or made available to the Contractor. Core locations shall be outside of 12 wheel paths and as determined by the Engineer. Traffic control shall be provided by the 13 Contractor as requested by the Engineer. Failure by the Contractor to provide the 14 requested traffic control will result in forfeiture of the request for cores. When the CPF for 15 the lot based on the results of the HMA cores is less than 1.00, the cost for the coring will 16 be deducted from any monies due or that may become due the Contractor under the 17 Contract at the rate of $200 per core and the Contractor shall pay for the cost of the 18 traffic control. 19 20 5-04.3(10)A HMA Compaction – General Compaction Requirements 21 Compaction shall take place when the mixture is in the proper condition so that no undue 22 displacement, cracking, or shoving occurs. Areas inaccessible to large compaction 23 equipment shall be compacted by other mechanical means. Any HMA that becomes 24 loose, broken, contaminated, shows an excess or deficiency of asphalt, or is in any way 25 defective, shall be removed and replaced with new hot mix that shall be immediately 26 compacted to conform to the surrounding area. 27 28 The type of rollers to be used and their relative position in the compaction sequence 29 shall generally be the Contractor’s option, provided the specified densities are attained. 30 Unless the Engineer has approved otherwise, rollers shall only be operated in the static 31 mode when the internal temperature of the mix is less than 175°F. Regardless of mix 32 temperature, a roller shall not be operated in a mode that results in checking or cracking 33 of the mat. Rollers shall only be operated in static mode on bridge decks. 34 35 5-04.3(10)B HMA Compaction – Cyclic Density 36 Low cyclic density areas are defined as spots or streaks in the pavement that are less 37 than 90 percent of the theoretical maximum density. At the Engineer’s discretion, the 38 Engineer may evaluate the HMA pavement for low cyclic density, and when doing so will 39 follow WSDOT SOP 733. A $500 Cyclic Density Price Adjustment will be assessed for 40 any 500-foot section with two or more density readings below 90 percent of the 41 theoretical maximum density. 42 43 5-04.3(10)C Vacant 44 45 5-04.3(10)D HMA Nonstatistical Compaction 46 47 5-04.3(10)D1 HMA Nonstatistical Compaction – Lots and Sublots

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 185 1 HMA compaction which is accepted by nonstatistical evaluation will be based on 2 acceptance testing performed by the Contracting Agency dividing the project into 3 compaction lots. 4 5 A lot is represented by randomly selected samples of the same mix design that will be 6 tested for acceptance. A lot is defined as the total quantity of material or work produced 7 for each Job Mix Formula placed. Only one lot per JMF is expected. A sublot shall be 8 equal to one day’s production or 400 tons, whichever is less except that the final sublot 9 will be a minimum of 200 tons and may be increased to 800 tons. Testing for compaction 10 will be at the rate of 5 tests per sublot per WSDOT T 738. 11 12 The sublot locations within each density lot will be determined by the Engineer. For a lot 13 in progress with a CPF less than 0.75, a new lot will begin at the Contractor’s request 14 after the Engineer is satisfied that material conforming to the Specifications can be 15 produced. 16 17 HMA mixture accepted by commercial evaluation and HMA constructed under conditions 18 other than those listed above shall be compacted on the basis of a test point evaluation 19 of the compaction train. The test point evaluation shall be performed in accordance with 20 instructions from the Engineer. The number of passes with an approved compaction 21 train, required to attain the maximum test point density, shall be used on all subsequent 22 paving. 23 24 HMA for preleveling shall be thoroughly compacted. HMA that is used to prelevel wheel 25 ruts shall be compacted with a pneumatic tire roller unless otherwise approved by the 26 Engineer. 27 28 5-04.3(10)D2 HMA Compaction Nonstatistical Evaluation – Acceptance Testing 29 The location of the HMA compaction acceptance tests will be randomly selected by the 30 Engineer from within each sublot, with one test per sublot. 31 32 5-04.3(10)D3 HMA Nonstatistical Compaction – Price Adjustments 33 For each compaction lot with one or two sublots, having all sublots attain a relative 34 density that is 92 percent of the reference maximum density the HMA shall be accepted 35 at the unit Contract price with no further evaluation. When a sublot does not attain a 36 relative density that is 92 percent of the reference maximum density, the lot shall be 37 evaluated in accordance with Section 1-06.2 to determine the appropriate CPF. The 38 maximum CPF shall be 1.00, however, lots with a calculated CPF in excess of 1.00 will 39 be used to offset lots with CPF values below 1.00 but greater than 0.90. Lots with CPF 40 lower than 0.90 will be evaluated for compliance per 5-04.3(11). Additional testing by 41 either a nuclear moisture-density gauge or cores will be completed as required to provide 42 a minimum of three tests for evaluation. 43 44 For compaction below the required 92% a Non-Conforming Compaction Factor (NCCF) 45 will be determined. The NCCF equals the algebraic difference of CPF minus 1.00 46 multiplied by 40 percent. The Compaction Price Adjustment will be calculated as the 47 product of CPF, the quantity of HMA in the compaction control lot in tons, and the unit 48 Contract price per ton of mix.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 186 1 2 5-04.3(11) Reject Work 3 4 5-04.3(11)A Reject Work General 5 Work that is defective or does not conform to Contract requirements shall be rejected. 6 The Contractor may propose, in writing, alternatives to removal and replacement of 7 rejected material. Acceptability of such alternative proposals will be determined at the 8 sole discretion of the Engineer. HMA that has been rejected is subject to the 9 requirements in Section 1-06.2(2) and this specification, and the Contractor shall submit 10 a corrective action proposal to the Engineer for approval. 11 12 5-04.3(11)B Rejection by Contractor 13 The Contractor may, prior to sampling, elect to remove any defective material and 14 replace it with new material. Any such new material will be sampled, tested, and 15 evaluated for acceptance. 16 17 5-04.3(11)C Rejection Without Testing (Mixture or Compaction) 18 The Engineer may, without sampling, reject any batch, load, or section of Roadway that 19 appears defective. Material rejected before placement shall not be incorporated into the 20 pavement. Any rejected section of Roadway shall be removed. 21 22 No payment will be made for the rejected materials or the removal of the materials 23 unless the Contractor requests that the rejected material be tested. If the Contractor 24 elects to have the rejected material tested, a minimum of three representative samples 25 will be obtained and tested. Acceptance of rejected material will be based on 26 conformance with the nonstatistical acceptance Specification. If the CPF for the rejected 27 material is less than 0.75, no payment will be made for the rejected material; in addition, 28 the cost of sampling and testing shall be borne by the Contractor. If the CPF is greater 29 than or equal to 0.75, the cost of sampling and testing will be borne by the Contracting 30 Agency. If the material is rejected before placement and the CPF is greater than or equal 31 to 0.75, compensation for the rejected material will be at a CPF of 0.75. If rejection 32 occurs after placement and the CPF is greater than or equal to 0.75, compensation for 33 the rejected material will be at the calculated CPF with an addition of 25 percent of the 34 unit Contract price added for the cost of removal and disposal. 35 36 5-04.3(11)D Rejection - A Partial Sublot 37 In addition to the random acceptance sampling and testing, the Engineer may also 38 isolate from a normal sublot any material that is suspected of being defective in relative 39 density, gradation or asphalt binder content. Such isolated material will not include an 40 original sample location. A minimum of three random samples of the suspect material will 41 be obtained and tested. The material will then be statistically evaluated as an 42 independent lot in accordance with Section 1-06.2(2). 43 44 5-04.3(11)E Rejection - An Entire Sublot 45 An entire sublot that is suspected of being defective may be rejected. When a sublot is 46 rejected a minimum of two additional random samples from this sublot will be obtained. 47 These additional samples and the original sublot will be evaluated as an independent lot 48 in accordance with Section 1-06.2(2).

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 187 1 2 5-04.3(11)F Rejection - A Lot in Progress 3 The Contractor shall shut down operations and shall not resume HMA placement until 4 such time as the Engineer is satisfied that material conforming to the Specifications can 5 be produced: 6 7 1. When the Composite Pay Factor (CPF) of a lot in progress drops below 1.00 and 8 the Contractor is taking no corrective action, or 9 2. When the Pay Factor (PF) for any constituent of a lot in progress drops below 10 0.95 and the Contractor is taking no corrective action, or 11 3. When either the PFi for any constituent or the CPF of a lot in progress is less 12 than 0.75. 13 14 5-04.3(11)G Rejection - An Entire Lot (Mixture or Compaction) 15 An entire lot with a CPF of less than 0.75 will be rejected. 16 17 5-04.3(12) Joints 18 19 5-04.3(12)A HMA Joints 20 21 5-04.3(12)A1 Transverse Joints 22 The Contractor shall conduct operations such that the placing of the top or wearing 23 course is a continuous operation or as close to continuous as possible. Unscheduled 24 transverse joints will be allowed and the roller may pass over the unprotected end of the 25 freshly laid mixture only when the placement of the course must be discontinued for such 26 a length of time that the mixture will cool below compaction temperature. When the Work 27 is resumed, the previously compacted mixture shall be cut back to produce a slightly 28 beveled edge for the full thickness of the course. 29 30 A temporary wedge of HMA constructed on a 20H:1V shall be constructed where a 31 transverse joint as a result of paving or planing is open to traffic. The HMA in the 32 temporary wedge shall be separated from the permanent HMA by strips of heavy 33 wrapping paper or other methods approved by the Engineer. The wrapping paper shall 34 be removed and the joint trimmed to a slightly beveled edge for the full thickness of the 35 course prior to resumption of paving. 36 37 The material that is cut away shall be wasted and new mix shall be laid against the cut. 38 Rollers or tamping irons shall be used to seal the joint. 39 40 5-04.3(12)A2 Longitudinal Joints 41 The longitudinal joint in any one course shall be offset from the course immediately 42 below by not more than 6 inches nor less than 2 inches. All longitudinal joints 43 constructed in the wearing course shall be located at a lane line or an edge line of the 44 Traveled Way. A notched wedge joint shall be constructed along all longitudinal joints in 45 the wearing surface of new HMA unless otherwise approved by the Engineer. The 46 notched wedge joint shall have a vertical edge of not less than the maximum aggregate 47 size or more than ½ of the compacted lift thickness and then taper down on a slope not

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 188 1 steeper than 4H:1V. The sloped portion of the HMA notched wedge joint shall be 2 uniformly compacted. 3 4 5-04.3(12)B Bridge Paving Joint Seals 5 6 5-04.3(12)B1 HMA Sawcut and Seal 7 Prior to placing HMA on the bridge deck, establish sawcut alignment points at both ends 8 of the bridge paving joint seals to be placed at the bridge ends, and at interior joints 9 within the bridge deck when and where shown in the Plans. Establish the sawcut 10 alignment points in a manner that they remain functional for use in aligning the sawcut 11 after placing the overlay. 12 13 Submit a Type 1 Working Drawing consisting of the sealant manufacturer’s application 14 procedure. 15 16 Construct the bridge paving joint seal as specified ion the Plans and in accordance with 17 the detail shown in the Standard Plans. Construct the sawcut in accordance with the 18 detail shown in the Standard Plan. Construct the sawcut in accordance with Section 5- 19 05.3(8)B and the manufacturer’s application procedure. 20 21 5-04.3(12)B2 Paved Panel Joint Seal 22 Construct the paved panel joint seal in accordance with the requirements specified in 23 section 5-04.3(12)B1 and the following requirement: 24 25 1. Clean and seal the existing joint between concrete panels in accordance with 26 Section 5-01.3(8) and the details shown in the Standard Plans. 27 28 5-04.3(13) Surface Smoothness 29 The completed surface of all courses shall be of uniform texture, smooth, uniform as to 30 crown and grade, and free from defects of all kinds. The completed surface of the 31 wearing course shall not vary more than ⅛ inch from the lower edge of a 10-foot 32 straightedge placed on the surface parallel to the centerline. The transverse slope of the 33 completed surface of the wearing course shall vary not more than ¼ inch in 10 feet from 34 the rate of transverse slope shown in the Plans. 35 36 When deviations in excess of the above tolerances are found that result from a high 37 place in the HMA, the pavement surface shall be corrected by one of the 38 following methods: 39 40 1. Removal of material from high places by grinding with an approved grinding 41 machine, or 42 2. Removal and replacement of the wearing course of HMA, or 43 3. By other method approved by the Engineer. 44 45 Correction of defects shall be carried out until there are no deviations anywhere greater 46 than the allowable tolerances.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 189 1 2 Deviations in excess of the above tolerances that result from a low place in the HMA and 3 deviations resulting from a high place where corrective action, in the opinion of the 4 Engineer, will not produce satisfactory results will be accepted with a price adjustment. 5 The Engineer shall deduct from monies due or that may become due to the Contractor 6 the sum of $500.00 for each and every section of single traffic lane 100 feet in length in 7 which any excessive deviations described above are found. 8 9 When utility appurtenances such as manhole covers and valve boxes are located in the 10 traveled way, the utility appurtenances shall be adjusted to the finished grade prior to 11 paving. This requirement may be waived when requested by the Contractor, at the 12 discretion of the Engineer or when the adjustment details provided in the project plan or 13 specifications call for utility appurtenance adjustments after the completion of paving. 14 15 Utility appurtenance adjustment discussions will be included in the Pre-Paving planning 16 (5-04.3(14)B3). Submit a written request to waive this requirement to the Engineer prior 17 to the start of paving. 18 19 5-04.3(14) Planing (Milling) Bituminous Pavement 20 The planning plan must be approved by the Engineer and a pre planning meeting must 21 be held prior to the start of any planing. See Section 5-04.3(14)B2 for information on 22 planning submittals. 23 24 Locations of existing surfacing to be planed are as shown in the Drawings. 25 26 Where planing an existing pavement is specified in the Contract, the Contractor must 27 remove existing surfacing material and to reshape the surface to remove irregularities. 28 The finished product must be a prepared surface acceptable for receiving an HMA 29 overlay. 30 31 Use the cold milling method for planing unless otherwise specified in the Contract. Do 32 not use the planer on the final wearing course of new HMA. 33 34 Conduct planing operations in a manner that does not tear, break, burn, or otherwise 35 damage the surface which is to remain. The finished planed surface must be slightly 36 grooved or roughened and must be free from gouges, deep grooves, ridges, or other 37 imperfections. The Contractor must repair any damage to the surface by the Contractor’s 38 planing equipment, using an Engineer approved method. 39 40 Repair or replace any metal castings and other surface improvements damaged by 41 planing, as determined by the Engineer. 42 43 A tapered wedge cut must be planed longitudinally along curb lines sufficient to provide a 44 minimum of 4 inches of curb reveal after placement and compaction of the final wearing 45 course. The dimensions of the wedge must be as shown on the Drawings or as specified 46 by the Engineer. 47

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 190 1 A tapered wedge cut must also be made at transitions to adjoining pavement surfaces 2 (meet lines) where butt joints are shown on the Drawings. Cut butt joints in a straight line 3 with vertical faces 2 inches or more in height, producing a smooth transition to the 4 existing adjoining pavement. 5 6 After planing is complete, planed surfaces must be swept, cleaned, and if required by the 7 Contract, patched and preleveled. 8 9 The Engineer may direct additional depth planing. Before performing this additional 10 depth planing, the Contractor must conduct a hidden metal in pavement detection survey 11 as specified in Section 5-04.3(14)A. 12 13 All planing material derived from the Contractor’s operations shall be delivered and 14 stockpiled at the following sites: 15 16 Schedule A: 17 The Hermway Heights Gravel Pit: 18 The entrance of which is located at the intersection of 19 Hermway Heights Road and State Route 534 20 located near: 21 20513 State Route 534 22 Mount Vernon, WA 23 24 Schedule A and Schedule B: 25 Butler Gravel Pit 26 18911 Kelleher Road 27 Burlington, WA 28 29 Butler Gravel Pit hours of operation are restricted to Monday through Saturday 30 6:30 A.M. to 5 P.M. Contractor shall coordinate with Skagit County for access 31 to the disposal locations outside of listed hours. 32 33 34 All details of the delivery, including the location within the pit for 35 stockpiling, shall be coordinated with the Engineer at least 5 working days 36 prior to delivery. 37 38 39 5-04.3(14)A Pre-Planing Metal Detection Check 40 Before starting planing of pavements, and before any additional depth planing required 41 by the Engineer, the Contractor must conduct a physical survey of existing pavement to 42 be planed with equipment that can identify hidden metal objects. 43 44 Should such metal be identified, promptly notify the Engineer. 45 46 See Section 1-07.16(1) regarding the protection of survey monumentation that may be 47 hidden in pavement. 48

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 191 1 The Contractor is solely responsible for any damage to equipment resulting from the 2 Contractor’s failure to conduct a pre-planing metal detection survey, or from the 3 Contractor’s failure to notify the Engineer of any hidden metal that is detected. 4 5 5-04.3(14)B Paving and Planing Under Traffic 6 7 5-04.3(14)B1 General 8 In addition the requirements of Section 1-07.23 and the traffic controls required in 9 Section 1-10, and unless the Contract specifies otherwise or the Engineer approves, the 10 Contractor must comply with the following: 11 12 1. Intersections: 13 a. Keep intersections open to traffic at all times, except when paving or planing 14 operations through an intersection requires closure. Such closure must be kept 15 to the minimum time required to place and compact the HMA mixture, or plane 16 as appropriate. For paving, schedule such closure to individual lanes or portions 17 thereof that allows the traffic volumes and schedule of traffic volumes required in 18 the approved traffic control plan. Schedule work so that adjacent intersections 19 are not impacted at the same time and comply with the traffic control restrictions 20 required by the Traffic Engineer. Each individual intersection closure or partial 21 closure, must be addressed in the traffic control plan, which must be submitted 22 to and accepted by the Engineer, see Section 1-10.2(2). 23 b. When planing or paving and related construction must occur in an 24 intersection, consider scheduling and sequencing such work into quarters of the 25 intersection, or half or more of an intersection with side street detours. Be 26 prepared to sequence the work to individual lanes or portions thereof. 27 c. Should closure of the intersection in its entirety be necessary, and no trolley 28 service is impacted, keep such closure to the minimum time required to place 29 and compact the HMA mixture, plane, remove asphalt, tack coat, and as 30 needed. 31 d. Any work in an intersection requires advance warning in both signage and a 32 number of Working Days advance notice as determined by the Engineer, to alert 33 traffic and emergency services of the intersection closure or partial closure. 34 e. Allow new compacted HMA asphalt to cool to ambient temperature before 35 any traffic is allowed on it. Traffic is not allowed on newly placed asphalt until 36 approval has been obtained from the Engineer. 37 2. Temporary centerline marking, post-paving temporary marking, temporary stop 38 bars, and maintaining temporary pavement marking must comply with Section 39 8-23. 40 3. Permanent pavement marking must comply with Section 8-22. 41 42 5-04.3(14)B2 Submittals – Planing Plan and HMA Paving Plan 43 The Contractor must submit a separate planing plan and a separate paving plan to the 44 Engineer at least 5 Working Days in advance of each operation’s activity start date. 45 These plans must show how the moving operation and traffic control are coordinated, as 46 they will be discussed at the pre-planing briefing and pre-paving briefing. When 47 requested by the Engineer, the Contractor must provide each operation’s traffic control 48 plan on 24 x 36 inch or larger size Shop Drawings with a scale showing both the area of

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 192 1 operation and sufficient detail of traffic beyond the area of operation where detour traffic 2 may be required. The scale on the Shop Drawings is 1 inch = 20 feet, which may be 3 changed if the Engineer agrees sufficient detail is shown. 4 5 The planing operation and the paving operation include, but are not limited to, metal 6 detection, removal of asphalt and temporary asphalt of any kind, tack coat and drying, 7 staging of supply trucks, paving trains, rolling, scheduling, and as may be discussed at 8 the briefing. 9 10 When intersections will be partially or totally blocked, provide adequately sized and 11 noticeable signage alerting traffic of closures to come, a minimum 2 Working Days in 12 advance. The traffic control plan must show where police officers will be stationed when 13 signalization is or may be, countermanded, and show areas where flaggers are 14 proposed. 15 16 At a minimum, the planing and the paving plan must include: 17 18 1. A copy of the accepted traffic control plan, see Section 1-10.2(2), detailing each 19 day’s traffic control as it relates to the specific requirements of that day’s planing 20 and paving. Briefly describe the sequencing of traffic control consistent with the 21 proposed planing and paving sequence, and scheduling of placement of 22 temporary pavement markings and channelizing devices after each day’s planing, 23 and paving. 24 2. A copy of each intersection’s traffic control plan. 25 3. Haul routes from Supplier facilities, and locations of temporary parking and 26 staging areas, including return routes. Describe the complete round trip as it 27 relates to the sequencing of paving operations. 28 4. Names and locations of HMA Supplier facilities to be used. 29 5. List of all equipment to be used for paving. 30 6. List of personnel and associated job classification assigned to each piece of 31 paving equipment. 32 7. Description (geometric or narrative) of the scheduled sequence of planing and of 33 paving, and intended area of planing and of paving for each day’s work, must 34 include the directions of proposed planing and of proposed paving, sequence of 35 adjacent lane paving, sequence of skipped lane paving, intersection planing and 36 paving scheduling and sequencing, and proposed notifications and coordinations 37 to be timely made. The plan must show HMA joints relative to the final pavement 38 marking lane lines. 39 8. Names, job titles, and contact information for field, office, and plant supervisory 40 personnel. 41 9. A copy of the approved Mix Designs. 42 10. Tonnage of HMA to be placed each day. 43 11. Approximate times and days for starting and ending daily operations. 44 45 5-04.3(14)B3 Pre-Paving and Pre-Planing Briefing 46 At least 2 Working Days before the first paving operation and the first planing operation, 47 or as scheduled by the Engineer for future paving and planing operations to ensure the

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 193 1 Contractor has adequately prepared for notifying and coordinating as required in the 2 Contract, the Contractor must be prepared to discuss that day’s operations as they relate 3 to other entities and to public safety and convenience, including driveway and business 4 access, garbage truck operations, Metro transit operations and working around 5 energized overhead wires, school and nursing home and hospital and other accesses, 6 other contractors who may be operating in the area, pedestrian and bicycle traffic, and 7 emergency services. The Contractor, and Subcontractors that may be part of that day’s 8 operations, must meet with the Engineer and discuss the proposed operation as it 9 relates to the submitted planing plan and paving plan, approved traffic control plan, and 10 public convenience and safety. Such discussion includes, but is not limited to: 11 12 1. General for both Paving Plan and for Planing Plan: 13 a. The actual times of starting and ending daily operations. 14 b. In intersections, how to break up the intersection, and address traffic control 15 and signalization for that operation, including use of peace officers. 16 c. The sequencing and scheduling of paving operations and of planing operations, 17 as applicable, as it relates to traffic control, to public convenience and safety, 18 and to other con-tractors who may operate in the Project Site. 19 d. Notifications required of Contractor activities, and coordinating with other 20 entities and the public as necessary. 21 e. Description of the sequencing of installation and types of temporary pavement 22 markings as it relates to planning and to paving. 23 f. Description of the sequencing of installation of, and the removal of, temporary 24 pavement patch material around exposed castings and as may be needed 25 g. Description of procedures and equipment to identify hidden metal in the 26 pavement, such as survey monumentation, monitoring wells, street car rail, and 27 castings, before planning, see Section 5-04.3(14)B2. 28 h. Description of how flaggers will be coordinated with the planing, paving, and 29 related operations. 30 i. Description of sequencing of traffic controls for the process of rigid pavement 31 base repairs. 32 j. Other items the Engineer deems necessary to address. 33 2. Paving – additional topics: 34 a. When to start applying tack and coordinating with paving. 35 b. Types of equipment and numbers of each type equipment to be used. If more 36 pieces of equipment than personnel are proposed, describe the sequencing of 37 the personnel operating the types of equipment. Discuss the continuance of 38 operator personnel for each type equipment as it relates to meeting 39 Specification requirements. 40 c. Number of JMFs to be placed, and if more than one JMF how the Contractor 41 will ensure different JMFs are distinguished, how pavers and MTVs are 42 distinguished if more than one JMF is being placed at the time, and how 43 pavers and MTVs are cleaned so that one JMF does not adversely influence 44 the other JMF. 45 d. Description of contingency plans for that day’s operations such as equipment 46 breakdown, rain out, and Supplier shutdown of operations. 47 e. Number of sublots to be placed, sequencing of density testing, and other 48 sampling and testing.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 194 1 2 5-04.3(15) Sealing Pavement Surfaces 3 Apply a fog seal where shown in the plans. Construct the fog seal in accordance with 4 Section 5-02.3. Unless otherwise approved by the Engineer, apply the fog seal prior to 5 opening to traffic. 6 7 5-04.3(16) HMA Road Approaches 8 HMA approaches shall be constructed at the locations shown in the Plans or where 9 staked by the Engineer. The Work shall be performed in accordance with Section 5-04. 10 11 5-04.4 Measurement 12 HMA Cl. ⅜ PG 58H-22, and Commercial HMA will be measured by the ton in accordance 13 with Section 1-09.2, with no deduction being made for the weight of asphalt binder, 14 mineral filler, or any other component of the mixture. If the Contractor elects to remove 15 and replace mix as allowed by Section 5-04.3(11), the material removed will not be 16 measured. 17 18 Roadway cores will be measured per each for the number of cores taken. 19 20 Preparation of untreated roadway will be measured by the mile once along the centerline 21 of the main line Roadway. No additional measurement will be made for ramps, Auxiliary 22 Lanes, service roads, Frontage Roads, or Shoulders. Measurement will be to the nearest 23 0.01 mile. 24 25 Soil residual herbicide will be measured by the mile for the stated width to the nearest 26 0.01 mile or by the square yard, whichever is designated in the Proposal. 27 28 Pavement repair excavation will be measured by the square yard of surface marked prior 29 to excavation. 30 31 Asphalt for prime coat will be measured by the ton in accordance with Section 1-09.2. 32 33 Prime coat aggregate will be measured by the cubic yard, truck measure, or by the ton, 34 whichever is designated in the Proposal. 35 36 Asphalt for fog seal will be measured by the ton, as provided in Section 5-02.4. 37 38 Longitudinal joint seals between the HMA and cement concrete pavement will be 39 measured by the linear foot along the line and slope of the completed joint seal. 40 41 Planing bituminous pavement will be measured by the square yard. 42 43 Temporary pavement marking will be measured by the linear foot as provided in Section 44 8-23.4. 45

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 195 1 Water will be measured by the M gallon as provided in Section 2-07.4. 2 3 5-04.5 Payment 4 Payment will be made for each of the following Bid items that are included in the 5 Proposal: 6 7 “HMA Cl. ⅜ PG 58H-22”, per ton. 8 9 “HMA for Approach Cl. ⅜_PG 58H-22”, per ton. 10 11 “HMA for Preleveling Cl. ⅜ PG 58H-22”, per ton. 12 13 “HMA for Pavement Repair Cl. ⅜ PG 58H-22”, per ton. 14 15 “Commercial HMA”, per ton. 16 17 The unit Contract price per ton for “HMA Cl. ⅜ PG 58H-22”, “HMA for Approach Cl. ⅜ 18 PG 58H-22”, “HMA for Preleveling Cl. ⅜ PG 58H-22”, “HMA for Pavement Repair Cl. ⅜ 19 PG 58H-22”, and “Commercial HMA” shall be full compensation for all costs, including 20 anti-stripping additive, incurred to carry out the requirements of Section 5-04 except for 21 those costs included in other items which are included in this Subsection and which are 22 included in the Proposal. 23 24 “Preparation of Untreated Roadway”, per mile. 25 26 The unit Contract price per mile for “Preparation of Untreated Roadway” shall be full pay 27 for all Work described under 5-04.3(4), with the exception, however, that all costs 28 involved in patching the Roadway prior to placement of HMA shall be included in the unit 29 Contract price per ton for “HMA Cl. ⅜_PG 58H-22” which was used for patching. If the 30 Proposal does not include a Bid item for “Preparation of Untreated Roadway”, the 31 Roadway shall be prepared as specified, but the Work shall be included in the Contract 32 prices of the other items of Work. 33 34 “Preparation of Existing Paved Surfaces”, per mile. 35 36 The unit Contract Price for “Preparation of Existing Paved Surfaces” shall be full pay for 37 all Work described under Section 5-04.3(4) with the exception, however, that all costs 38 involved in patching the Roadway prior to placement of HMA shall be included in the unit 39 Contract price per ton for “HMA Cl. ⅜ PG 58H-22” which was used for patching. If the 40 Proposal does not include a Bid item for “Preparation of Untreated Roadway”, the 41 Roadway shall be prepared as specified, but the Work shall be included in the Contract 42 prices of the other items of Work. 43 44 “Crack Sealing”, by force account. 45

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 196 1 “Crack Sealing” will be paid for by force account as specified in Section 1-09.6. For the 2 purpose of providing a common Proposal for all Bidders, the Contracting Agency has 3 entered an amount in the Proposal to become a part of the total Bid by the Contractor. 4 5 “Pavement Repair Excavation Incl. Haul”, per square yard. 6 7 The unit Contract price per square yard for “Pavement Repair Excavation Incl. Haul” 8 shall be full payment for all costs incurred to perform the Work described in Section 5- 9 04.3(4) with the exception, however, that all costs involved in the placement of HMA 10 shall be included in the unit Contract price per ton for “HMA for Pavement Repair Cl. ⅜ 11 PG 58H-22”, per ton. 12 13 “Asphalt for Prime Coat”, per ton. 14 15 The unit Contract price per ton for “Asphalt for Prime Coat” shall be full payment for all 16 costs incurred to obtain, provide and install the material in accordance with Section 5- 17 04.3(4). 18 19 “Prime Coat Agg.”, per cubic yard, or per ton. 20 21 The unit Contract price per cubic yard or per ton for “Prime Coat Agg.” shall be full pay 22 for furnishing, loading, and hauling aggregate to the place of deposit and spreading the 23 aggregate in the quantities required by the Engineer. 24 25 “Asphalt for Fog Seal”, per ton. 26 27 Payment for “Asphalt for Fog Seal” is described in Section 5-02.5. 28 29 “Longitudinal Joint Seal”, per linear foot. 30 31 The unit Contract price per linear foot for “Longitudinal Joint Seal” shall be full payment 32 for all costs incurred to perform the Work described in Section 5-04.3(12). 33 34 “Planing Bituminous Pavement”, per square yard. 35 36 The unit Contract price per square yard for “Planing Bituminous Pavement” shall be full 37 payment for all costs incurred to perform the Work described in Section 5-04.3(14). 38 39 “Temporary Pavement Marking”, per linear foot. 40 41 Payment for “Temporary Pavement Marking” is described in Section 8-23.5. 42 43 “Water”, per M gallon. 44 45 Payment for “Water” is described in Section 2-07.5.

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 197 1 2 “Job Mix Compliance Price Adjustment”, by calculation. 3 4 “Job Mix Compliance Price Adjustment” will be calculated and paid for as described in 5 Section 5-04.3(9)C6. 6 7 “Compaction Price Adjustment”, by calculation. 8 9 “Compaction Price Adjustment” will be calculated and paid for as described in Section 5- 10 04..3(10)D3. 11 12 “Roadway Core”, per each. 13 14 The Contractor’s costs for all other Work associated with the coring (e.g., traffic control) 15 shall be incidental and included within the unit Bid price per each and no additional 16 payments will be made. 17 18 “Cyclic Density Price Adjustment”, by calculation. 19 20 “Cyclic Density Price Adjustment” will be calculated and paid for as described in Section 21 5-04.3(10)B. 22

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 198 1 2 Division 8 3 Miscellaneous Construction 4 5 8-01 Erosion Control and Water Pollution Control

6 7 8-01.3 Construction Requirements 8 (June 1, 2017 SkagitR) 9 10 (******) 11 Section 8-01.3 is supplemented with the following: 12 13 At the Preconstruction Meeting, the Contractor shall submit the temporary erosion and 14 sediment control (TESC) Plan. The TESC Plan shall include the identification of the ESC 15 Lead. 16 17 8-20 Illumination, Traffic Signal Systems, Intelligent Transportation Systems, 18 and Electrical 19 20 8-20.1 Description 21 22 Section 8-20.1 is supplemented with the following: 23 24 This work consists of furnishing, installing, and testing 13 Type 3 induction loops, one heavy 25 duty junction box Type 4, and raising one Junction Box to grade. 26 27 8-20.2 Materials 28 29 8-20.2(1) Equipment List And Drawings 30 31 Section 8-20.2(1) is supplemented with the following: 32 33 (NWR November 13, 1996) 34 Manufacturer’s data for materials proposed for use in the contract which require 35 approval shall be submitted in one complete package. 36 37 8-20.3 Construction Requirements 38 39 8-20.3(5) Conduit 40 41 Section 8-20.3(5) is supplemented with the following: 42 43 Conduit Seal, Detectable Tape and Location Wire 44 Upon installation of wiring, all conduits entering pad mounted cabinets, all conduit 45 entering ITS hubs, and all ITS conduit 2 inches in diameter or larger shall be sealed 46 with an approved mechanical plug at both ends of the conduit run. Installation of 47 mechanical plugs shall conform to the manufacturer’s recommendations. Upon 48 installation of wiring at other locations, conduit shall be sealed with duct seal. Upon 49 installation of the pull string, spare conduit shall be plugged. 50

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 199 1 A pull string rated for 200 lbs. or greater shall be installed in all spare conduits. 2 3 Detectable underground warning tape shall be placed 12-inches above all innerduct 4 installed in trenches. 5 6 Location 14 AWG stranded orange USE insulated wire shall be placed in conjunction 7 with all innerduct installed in trenches. The location wire shall be placed directly 8 above the conduit containing innerduct in single conduit installations or between the 9 conduits containing innerduct in multiple conduit installations. 10 11 Location wire routed into pull boxes or cable vaults shall be attached to the “C” 12 channel or the cover hinge bracket with stainless steel bolts and straps. A 1-foot loop 13 of locate wire shall be provided above the channel as shown in the Plans. 14 15 8-20.3(6) Junction Boxes, Cable Vaults, and Pull boxes 16 17 Section 8-20.3(6) is supplemented with the following: 18 19 (NWR February 11, 2013) 20 Unless otherwise noted in the Plans or approved by the Engineer, junction boxes, 21 cable vaults and pull boxes shall not be placed within the traveled way or paved 22 shoulders. 23 24 All junction boxes, cable vaults, and pull boxes placed within the traveled way or 25 paved shoulders shall be heavy-duty. 26 27 Wiring shall not be pulled into any conduit until all associated junction boxes have 28 been adjusted to, or installed in, their final grade and location, unless installation is 29 necessary to maintain system operation. If wire is installed for this reason, sufficient 30 slack shall be left to allow for future adjustment. 31 32 Prior to installing new cables or reinstalling existing cables into new or existing cable 33 vaults, pull boxes or junction boxes, the cable vault, pull box or junction box shall be 34 cleaned of all dirt and debris. 35 36 When junction boxes, cable vaults and pull boxes are installed or adjusted prior to 37 construction of finished grade, pre-molded joint filler for expansion joints may be 38 placed around the junction boxes, cable vaults and pull boxes. The joint filler shall be 39 removed prior to adjustment to finished grade. 40 41 The six-inch gravel pad required in Standard Plan J-40.10.01 and J-40.30.00 shall 42 be maintained. When existing junction boxes do not have this gravel pad, it shall be 43 installed as part of the adjustment to finished grade. 44 45 Heavy-duty Type 4, 5 and 6 junction boxes, cable vaults and pull boxes shall be 46 installed in accordance with the following: 47 48 1. Excavation for junction boxes, cable vaults and pull boxes shall be sufficient 49 to leave one foot in the clear between their outer surface and the earth bank. 50 51 2. Junction boxes, cable vaults and pull boxes shall be installed on a level 6- 52 inch layer of crushed surfacing top course, in accordance with 9-03.9(3),

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 200 1 placed on a compacted or undisturbed foundation. The crushed surfacing 2 shall be compacted in accordance with Section 2-09.3(1)E. 3 4 3. After installation, the lid/cover shall be kept bolted down during periods 5 when work is not actively in progress at the junction box, cable vault or pull 6 box. 7 8 4. Before closing the lid/cover, the lid/cover and the frame/ring shall be 9 thoroughly brushed and cleaned of all debris. There shall be absolutely no 10 visible dirt, sand or other foreign matter between the bearing surfaces. 11 12 5. When the lid/cover is closed for the final time, a liberal coating of anti-seize 13 compound shall be applied to the bolts and nuts and the lid shall be securely 14 tightened. 15 16 6. Hinges on the Type 4, 5 and 6 junction boxes shall be located on the side 17 of the box, which is nearest to adjacent shoulder. Hinges shall allow the lid 18 to open 180 degrees. 19 20 8-20.3(14) Signal Systems 21 22 8-20.3(14)C Induction Loop Vehicle Detectors 23 24 Section 8-20.3(14)C is supplemented with the following: 25 26 (NWR August 16, 2010) 27 Round Loops 28 Round loops shall be constructed in accordance with the following requirements: 29 30 1. Loop conductor and lead in cable shall conform to these Special 31 Provisions. 32 33 2. Round sawcuts shall be six feet in diameter and shall be constructed 34 using equipment designed for cutting round loops. The equipment shall 35 use a concave, diamond-segmented blade. The sawcuts shall be 36 normal to the pavement surface and shall be a minimum of 0.25 inches 37 wide. The sawcut depth shall be a minimum of 2 5/8 inches and a 38 maximum of three inches measured at any point along the perimeter, 39 except on bridge decks. Other methods of constructing the round 40 sawcut, such as anchoring a router or flat blade saw, will not be 41 allowed. 42 43 3. The bottom of the sawcut shall be smooth. No edges created by 44 differences in sawcut depths will be allowed. 45 46 4. All sawcut corners shall be rounded to a minimum 1.5 inch radius. 47 48 5. All sawcuts shall be cleaned with a 1000 psi high pressure washer as 49 certified by the manufacturer's label on the machine or as measured by 50 an in line pressure gauge. Wash water and slurry shall be vacuumed 51 out and the sawcut shall be blown dry with compressed air. Disposal of 52 the wash water and slurry shall comply with the requirements of

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 201 1 Section 1-07.5(3) and the Special Provision LEGAL RELATIONS AND 2 RESPONSIBILITIES TO THE PUBLIC. 3 4 6. Loops shall be installed after grinding and prior to the final lift of 5 roadway surfacing material. 6 7 7. The conductor shall be installed one turn on top of the previous turn. 8 All turns shall be installed in a clockwise direction. The conductors shall 9 be secured to prevent floating with 2-inch lengths of high temperature 10 foam backer rod sized for a snug fit. The backer rod shall be spaced at 11 2-foot intervals around the perimeter of the sawcut and at corners. 12 13 8. Installation of the sealant shall completely encapsulate the loop 14 conductors. A minimum of one inch of sealant shall be provided 15 between the top of the conductors and the top of the sawcut. The top 16 of the sealant shall be flush to 1/8 inch below the top of the sawcut. 17 18 9. Use of kerosene solvent is prohibited. 19 20 (NWR October 16, 2006) 21 Preformed Loops 22 Where indicated in the Plans, detector loops shall be preformed. 23 24 Preformed detector loops and homeruns located in bridge roadway slabs shall 25 be supported at a depth of 1 to 1-1/2 inches below the finished grade and one 26 inch minimum above the top layer of steel reinforcing bars. Preformed detector 27 loops and homeruns shall be supported by metal or plastic chair supports 28 conforming to Section 6-02.3(24)C. The loops shall be supported every 12 29 inches at a minimum. Loops and homeruns shall be tie wrapped and anchored 30 so that they remain at a depth 1 to 1-1/2 inches below the finished grade and 31 one inch minimum above the top layer of steel reinforcing bars. 32 33 Preformed detector loops and homeruns located in cement concrete pavement, 34 outside of bridge roadway slabs, shall be supported at a depth of four to six 35 inches below the finished grade with plastic chair supports meeting the 36 requirements of Section 6-02.3(24)C. The loops shall be supported every 12 37 inches at a minimum. Loops and homeruns shall be tie wrapped and anchored 38 with epoxy coated rebar stakes so that they remain at a depth four to six inches 39 below the finished grade. Epoxy coated rebar stakes shall be driven a minimum 40 of four inches into the subgrade. 41 42 Preformed detector loops and homeruns located in hot mix asphalt shall be 43 installed after all grinding and prior to paving the final lift of asphalt. 44 45 1. Round sawcuts shall be six feet in diameter and shall be constructed 46 using equipment designed for cutting round loops. The equipment shall 47 use a concave, diamond-segmented blade. The sawcut shall be normal 48 to the pavement surface and shall be a minimum of 0.1 inches wider 49 than the preformed detector loop. The sawcut depth shall be a 50 minimum of one inch and a maximum of two inches measured at any 51 point along the perimeter, except on bridge decks. Other methods of

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 202 1 constructing the round sawcut, such as anchoring a router or flat blade 2 saw, will not be allowed. 3 4 2. The bottom of the sawcut shall be smooth. No edges created by 5 differences in sawcut depths will be allowed. 6 7 3. All sawcut corners shall be rounded to a minimum 1.5 inch radius. 8 9 4. All sawcuts shall be cleaned with a 1000 psi high pressure washer as 10 certified by the manufacturer's label on the machine or as measured by 11 an in line pressure gauge. Wash water and slurry shall be vacuumed 12 out and the sawcut shall be blown dry with compressed air. Disposal of 13 the wash water and slurry shall comply with the requirements of 14 Section 1-07.5(3) and the Special Provision LEGAL RELATIONS AND 15 RESPONSIBILITIES TO THE PUBLIC. 16 17 5. The preformed detector loops shall be secured to prevent floating with 18 2-inch lengths of high temperature foam backer rod sized for a snug fit. 19 The backer rod shall be spaced at 2-foot intervals around the perimeter 20 of the sawcut and at corners. 21 22 6. Installation of the sealant shall completely encapsulate the preformed 23 detector loops. A minimum of 1/2 inch of sealant shall be provided 24 between the top of the preformed detector loop and the top of the 25 sawcut. The top of the sealant shall be flush to 1/8 inch below the top 26 of the sawcut. 27 28 7. Use of kerosene solvent is prohibited. 29 30 The loop manufacturer shall mark the wire ends clearly with start and finish. 31 32 A minimum of six inches of hose assembly and two feet of slack homerun wire 33 with the hose removed shall be coiled in the junction box. 34 35 Each successive preformed detector loop shall be installed with the homeruns 36 twisted in alternating directions. 37 38 8-20.3(14)D Test for Induction Loops and Lead-in Cable 39 40 Section 8-20.3(14)D is supplemented with the following: 41 42 (NWR October 5, 2009) 43 Induction Loop Tests 44 Test A and Test D are revised as follows: 45 46 Test A – The DC resistance between the 2 lead-in cable wires, including the 47 loop, shall be measured by a volt ohmmeter. The resistance shall not 48 exceed 5-ohms or lower the Q of the circuit below 5 where Q is equal to the 49 “Inductive Impedance @ 50 kHz” divided by “Resistance”. 50 51 Test D - An inductance test shall be made to determine the inductance level 52 of each inductance loop. The Contractor shall record the inductance level

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 203 1 of each inductance loop installed on the project and shall furnish the findings 2 to the Engineer. An induction level, as measured from the controller cabinet, 3 below 50-microhenries is considered a failure. 4 5 (NWR October 5, 2009) 6 Existing Lead-in Cable Test 7 When new induction loops are scheduled to be installed and spliced to an 8 existing two-conductor shielded detector lead-in cable, the Contractor shall 9 perform the following: 10 11 1. Disconnect the existing detector lead-in cable in the controller cabinet 12 and at the loop splice. 13 2. Megger test both detector lead-in cable conductors. A resistance 14 reading of less than 100-megohms is considered a failure. 15 3. Detector lead-in cables that fail the test shall be replaced and then 16 retested. 17 4. After final testing of the detector lead-in cable, the loop installation shall 18 be completed and the loop system tested according to Tests A, C and 19 D. 20 5. Connect the detector lead-in cables in the controller cabinet. 21 22 8-20.4 Measurement 23 24 (******) 25 26 Section 8-20.4 is supplemented with the following: 27 28 “Traffic Signal Systems” will be measured per Lump Sum for complete installation. 29 30 8-20.5 Payment 31 32 (******) 33 34 Section 8-20.5 is supplemented with the following: 35 36 “Traffic Signal System”, per Lump Sum 37 The unit contract price shall be full compensation for all labor, materials, equipment and 38 testing associated with the installation of traffic loops identified in the contract plans and 39 the associated lead-in conduit, along with the testing of the loops, replacement and 40 adjustment of junction boxes, including the removal of the existing junction box and the 41 adjustment of conduit stub outs, shall be included in Lump Sum price. 42 43

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 204 1 2 Appendices 3 (January 2, 2012)

4 The following appendices are attached and made a part of this contract: 5 6 *** As below *** 7 8 APPENDIX A: 9 Standard Plans 10 11 APPENDIX B: 12 Wage Rates 13 Washington State Prevailing Wage Rates 14 15 APPENDIX C: 16 Construction Contract and Contract Bond - Information Only 17 18 APPENDIX D: 19 Proposal Forms – Information Only 20 21 APPENDIX E: 22 Vicinity Map and Plans 23 24 25

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 205 1 2 (January 3, 2017) 3 Standard Plans

4 The State of Washington Standard Plans for Road, Bridge and Municipal Construction M21- 5 01 transmitted under Publications Transmittal No. PT 16-048, effective August 1, 2016 is made 6 a part of this contract. 7 8 The Standard Plans are revised as follows: 9 10 A-30.15 11 DELETED 12 13 A-40.10 14 Section View, PCCP to HMA Longitudinal Joint, callout, was – “Sawed Groove ~ Width 15 3/16” (IN) MIN. to 5/16” (IN) MAX. ~ Depth 1” (IN) MIN. ~ see Std. Spec. 5-04.3(12)B” is 16 revised to read; “Sawed Groove ~ Width 3/16” (IN) MIN. to 5/16” (IN) MAX. ~ Depth 1” 17 (IN) MIN. ~ see Std. Spec. Section 5-04.3(12)A2” 18 19 A-50.10 20 Sheet 2 of 2, Plan, with Single Slope Barrier, reference C-14a is revised to C-70.10 21 22 A-50.20 23 Sheet 2 of 2, Plan, with Anchored Barrier, reference C-14a is revised to C-70.10 24 25 A-50.30 26 Sheet 2 of 2, Plan (top), reference C-14a is revised to C-70.10 27 28 A-60.30 29 Note 4, was – “If the ACP and membrane is to be removed from the bridge deck, see GSP 30 023106 for deck preparation before placing new membrane.” Is revised to read; “If the 31 ACP and membrane is to be removed from the bridge deck, see GSP 6- 32 02.3(10)D.OPT6.GB6 for deck preparation before placing new membrane.” 33 34 B-10.20 and B-10.40 35 Substitute “step” in lieu of “handhold” on plan 36 37 B-15.60 38 Table, Maximum Knockout Size column, 120” Diam., 42” is revised to read; 96” 39 40 B-25.20 41 Add Note 7. See Standard Specification Section 8-04 for Curb and Gutter requirements 42 43 B-40.40 44 Note 2, was – “When bolt-down grates are specified in the Contract, provide two slots in 45 the grate that are centered with the holes in the frame. Location of bolt-down slots varies 46 among different manufacturers.” Is revised to read; ”Bolt-down capability is required on 47 all frames, grates, and covers, unless specified otherwise in the Contract. Provide 2 holes 48 in the frame that are vertically aligned with the grate or cover slots. The frame shall accept 49 the 5/8” (in) – 11 NC x 2” (in) Allen head cap screw by being tapped, or other approved 50 mechanism. Location of bolt-down holes varies by manufacturers.” 51

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 206 1 B-55.20 2 Metal Pipe elevation, title is revised to read; “Metal Pipe and Steel Rib Reinforced 3 Polyethylene Pipe” 4 5 B-90.40 6 Offset & Bend details, add the subtitle, “Plan View” above titles 7 8 C-16a 9 Note 1, reference C-28.40 is revised to C-20.10 10 11 C-16b 12 Note 3, reference C-28.40 is revised to C-20.10 13 14 C-22.14 15 Note 3, formula, was: “Elevation G = (Elevation S – D x (0.1) + 28” is revised to read: 16 “Elevation G = (Elevation S – D x (0.1) + 28/12” 17 18 C-22.16 19 Note 3, formula, was: “Elevation G = (Elevation S – D x (0.1) + 31” is revised to read: 20 “Elevation G = (Elevation S – D x (0.1) + 31/12” 21 22 C-22.41 23 DELETED 24 25 D-10.10 26 Wall Type 1 may be used if no traffic barrier is attached on top of the wall. Walls with traffic 27 barriers attached on top of the wall are considered non-standard and shall be designed 28 in accordance with the current WSDOT Bridge Design Manual (BDM) and the revisions 29 stated in the 11/3/15 Bridge Design memorandum. 30 31 D-10.15 32 Wall Type 2 may be used if no traffic barrier is attached on top of the wall. Walls with traffic 33 barriers attached on top of the wall are considered non-standard and shall be designed 34 in accordance with the current WSDOT BDM and the revisions stated in the 11/3/15 35 Bridge Design memorandum. 36 37 D-10.20 38 Wall Type 3 may be used in all cases. The last sentence of Note 6 on Wall Type 3 shall 39 be revised to read: The seismic design of these walls has been completed using a site 40 adjusted (effective) peak ground acceleration of 0.32g. 41 42 D-10.25 43 Wall Type 4 may be used in all cases. The last sentence of Note 6 on Wall Type 4 shall 44 be revised to read: The seismic design of these walls has been completed using a site 45 adjusted (effective) peak ground acceleration of 0.32g. 46 47 D-10.30 48 Wall Type 5 may be used in all cases. 49 50 D-10.35 51 Wall Type 6 may be used in all cases. 52

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 207 1 D-10.40 2 Wall Type 7 may be used if no traffic barrier is attached on top of the wall. Walls with traffic 3 barriers attached on top of the wall are considered non-standard and shall be designed 4 in accordance with the current WSDOT BDM and the revisions stated in the 11/3/15 5 Bridge Design memorandum. 6 7 D-10.45 8 Wall Type 8 may be used if no traffic barrier is attached on top of the wall. Walls with traffic 9 barriers attached on top of the wall are considered non-standard and shall be designed 10 in accordance with the current WSDOT BDM and the revisions stated in the revisions 11 stated in the 11/3/15 Bridge Design memorandum. 12 13 D-15.10 14 STD Plans D-15 series “Traffic Barrier Details for Reinforced Concrete Retaining Walls” 15 are withdrawn. Special designs in accordance with the current WSDOT BDM are required 16 in place of these STD Plans. 17 18 D-15.20 19 STD Plans D-15 series “Traffic Barrier Details for Reinforced Concrete Retaining Walls” 20 are withdrawn. Special designs in accordance with the current WSDOT BDM are required 21 in place of these STD Plans. 22 23 D-15.30 24 STD Plans D-15 series “Traffic Barrier Details for Reinforced Concrete Retaining Walls” 25 are withdrawn. Special designs in accordance with the current WSDOT BDM are required 26 in place of these STD Plans. 27 28 F-10.12 29 Section Title, was – “Depressed Curb Section” is revised to read: “Depressed Curb and 30 Gutter Section” 31 32 F-10.40 33 “EXTRUDED CURB AT CUT SLOPE”, Section detail - Deleted 34 35 F-10.42 36 DELETE – “Extruded Curb at Cut Slope” View 37 38 G-22.10 39 Sheet 2, Elevation , Three-Post Installation, Dimension, upper right, was – “.035” is 40 revised to read: “ 0.35X” 41 42 H-70.20 43 Sheet 2, Spacing Detail, Mailbox Support Type 1, reference to Standard Plan I-70.10 is 44 revised to H-70.10 45 46 J-3 47 DELETED 48 49 J-3b 50 DELETED 51 52 J-3C

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 208 1 DELETED 2 3 J-10.21 4 Note 18, was – “When service cabinet is installed within right of way fence, see Standard 5 Plan J-10.22 for details.” Is revised to read; “When service cabinet is installed within right 6 of way fence, or the meter base is mounted on the exterior of the cabinet, see Standard 7 Plan J-10.22 for details.” 8 9 J-10.22 10 Key Note 1, was – “Meter base per serving utility requirements~ as a minimum, the meter 11 base shall be safety socket box with factory-installed test bypass facility that meets the 12 requirements of EUSERC drawing 305.” Is revised to read; “Meter base per serving utility 13 requirements~ as a minimum, the meter base shall be safety socket box with factory- 14 installed test bypass facility that meets the requirements of EUSERC drawing 305. When 15 the utility requires meter base to be mounted on the side or back of the service cabinet, 16 the meter base enclosure shall be fabricated from type 304 stainless steel.” 17 Key Note 4, “Test with (SPDT Snap Action, Positive close 15 Amp – 120/277 volt “T” 18 rated). Is revised to read: “Test Switch (SPDT snap action, positive close 15 amp – 19 120/277 volt “T” rated).” 20 Key Note 14, was – “Hinged dead front with ¼ turn fasteners or slide latch.” Is revised to 21 read; “Hinged dead front with ¼ turn fasteners or slide latch. ~ Dead front panel bolts 22 shall not extend into the vertical limits of the breaker array(s).” 23 Key Note 15, was – “Cabinet Main Bonding Jumper. Buss shall be 4 lug tinned copper. 24 See Cabinet Main bonding Jumper detail, Standard Plan J-3b.“ is revised to read; 25 “Cabinet Main Bonding Jumper Assembly ~ Buss shall be 4 lug tinned copper ~ See 26 Standard Plan J-10.20 for Cabinet Main Bonding Jumper Assembly details.” 27 28 J-20.10 29 Add Note 5, “5. One accessible pedestrian signal assembly per pedestrian pushbutton 30 post.” 31 32 J-20.11 33 Sheet 2, Foundation Detail, Elevation, callout – “Type 1 Signal Pole” is revised to read: 34 “Type PS or Type 1 Signal Pole” 35 Sheet 2, Foundation Detail, Elevation, add note below Title, “(Type 1 Signal Pole Shown)” 36 Add Note 6, “6. One accessible pedestrian signal assembly per pedestrian pushbutton 37 post.” 38 39 J-20.26 40 Add Note 1, “1. One accessible pedestrian pushbutton station per pedestrian pushbutton 41 post.” 42 43 J-20.16 44 View A, callout, was – LOCK NIPPLE, is revised to read; CHASE NIPPLE 45 46 J-21.10 47 Sheet 1 of 2, Elevation view (Round), add dimension depicting the distance from the top 48 of the foundation to find 2 #4 reinforcing bar shown, to read; 3” CLR.. Delete “(TYP.)” from 49 the 2 ½” CLR. dimension, depicting the distance from the bottom of the foundation to find 50 2 # 4 reinf. Bar. 51 Sheet 1 of 2, Elevation view (Square), add dimension depicting the distance from the top 52 of the foundation to find 1 #4 reinforcing bar shown, to read; 3” CLR. Delete “(TYP.)” from

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 209 1 the 2 ½” CLR. dimension, depicting the distance from the bottom of the foundation to find 2 1 # 4 reinf. Bar. 3 Sheet 2 of 2, Elevation view (Round), add dimension depicting the distance from the top 4 of the foundation to find 2 #4 reinforcing bar shown, to read; 3” CLR. Delete “(TYP.)” from 5 the 2 ½” CLR. dimension, depicting the distance from the bottom of the foundation to find 6 2 # 4 reinf. Bar. 7 Sheet 2 of 2, Elevation view (Square), add dimension depicting the distance from the top 8 of the foundation to find 1 #4 reinforcing bar shown, to read; 3” CLR. Delete “(TYP.)” from 9 the 2 ½” CLR. dimension, depicting the distance from the bottom of the foundation to find 10 1 # 4 reinf. Bar. 11 Detail F, callout, “Heavy Hex Clamping Bolt (TYP.) ~ 3/4” (IN) Diam. Torque Clamping 12 Bolts (see Note 3)” is revised to read; “Heavy Hex Clamping Bolt (TYP.) ~ 3/4” (IN) Diam. 13 Torque Clamping Bolts (see Note 1)” 14 Detail F, callout, “3/4” (IN) x 2’ – 6” Anchor Bolt (TYP.) ~ Four Required (See Note 4)” is 15 revised to read; “3/4” (IN) x 2’ – 6” Anchor Bolt (TYP.) ~ Three Required (See Note 2)” 16 17 J-21.15 18 Partial View, callout, was – LOCK NIPPLE ~ 1 ½” DIAM., is revised to read; CHASE 19 NIPPLE ~ 1 ½” (IN) DIAM. 20 21 J-21.16 22 Detail A, callout, was – LOCKNIPPLE, is revised to read; CHASE NIPPLE 23 24 J-22.15 25 Ramp Meter Signal Standard, elevation, dimension 4’ - 6” is revised to read; 6’-0” 26 (2x) Detail A, callout, was – LOCK NIPPLE ~ 1 ½” DIAM. is revised to read; CHASE 27 NIPPLE ~ 1 ½” (IN) DIAM. 28 29 J-40.10 30 Sheet 2 of 2, Detail F, callout, “12 – 13 x 1 ½” S.S. PENTA HEAD BOLT AND 12” S. S. 31 FLAT WASHER” is revised to read; “12 – 13 x 1 ½” S.S. PENTA HEAD BOLT AND 1/2” 32 (IN) S. S. FLAT WASHER” 33 34 J-60.14 35 All references to J-16b (6x) are revised to read; J-60.11 36 37 K-80.30 38 In the NARROW BASE, END view, the reference to Std. Plan C-8e is revised to Std. Plan 39 K-80.35 40 41 M-11.10 42 Layout, dimension (from stop bar to “X”), was – 23’ is revised to read; 24’ 43 44 The following are the Standard Plan numbers applicable at the time this project was 45 advertised. The date shown with each plan number is the publication approval date 46 shown in the lower right-hand corner of that plan. Standard Plans showing different dates 47 shall not be used in this contract. 48 A-10.10-00...... 8/7/07 A-40.00-00...... 8/11/09 A-50.30-00…....11/17/08 A-10.20-00...... 10/5/07 A-40.10-03...... 12/23/14 A-50.40-00…....11/17/08 A-10.30-00...... 10/5/07 A-40.15-00...... 8/11/09 A-60.10-03...... 12/23/14 A-20.10-00...... 8/31/07 A-40.20-03...... 12/23/14 A-60.20-03...... 12/23/14

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 210 A-30.10-00...... 11/8/07 A-40.50-02...... 12/23/14 A-60.30-00...... 11/8/07 A-30.30-01...... 6/16/11 A-50.10-00…....11/17/08 A-60.40-00...... 8/31/07 A-30.35-00...... 10/12/07 A-50.20-01…...... 9/22/09 1 B-5.20-01...... 6/16/11 B-30.50-01...... 4/26/12 B-75.20-01...... 6/10/08 B-5.40-01...... 6/16/11 B-30.70-03...... 4/26/12 B-75.50-01...... 6/10/08 B-5.60-01...... 6/16/11 B-30.80-00...... 6/8/06 B-75.60-00...... 6/8/06 B-10.20-01...... 2/7/12 B-30.90-01...... 9/20/07 B-80.20-00...... 6/8/06 B-10.40-00...... 6/1/06 B-35.20-00...... 6/8/06 B-80.40-00...... 6/1/06 B-10.60-00...... 6/8/06 B-35.40-00...... 6/8/06 B-82.20-00...... 6/1/06 B-15.20-01...... 2/7/12 B-40.20-00...... 6/1/06 B-85.10-01...... 6/10/08 B-15.40-01...... 2/7/12 B-40.40-01...... 6/16/10 B-85.20-00...... 6/1/06 B-15.60-01...... 2/7/12 B-45.20-00...... 6/1/06 B-85.30-00...... 6/1/06 B-20.20-02...... 3/16/12 B-45.40-00...... 6/1/06 B-85.40-00...... 6/8/06 B-20.40-03...... 3/16/12 B-50.20-00...... 6/1/06 B-85.50-01...... 6/10/08 B-20.60-03...... 3/15/12 B-55.20-00...... 6/1/06 B-90.10-00...... 6/8/06 B-25.20-01...... 3/15/12 B-60.20-00...... 6/8/06 B-90.20-00...... 6/8/06 B-25.60-00...... 6/1/06 B-60.40-00...... 6/1/06 B-90.30-00...... 6/8/06 B-30.10-01...... 4/26/12 B-65.20-01...... 4/26/12 B-90.40-00...... 6/8/06 B-30.20-02...... 4/26/12 B-65.40-00...... 6/1/06 B-90.50-00...... 6/8/06 B-30.30-01...... 4/26/12 B-70.20-00...... 6/1/06 B-95.20-01...... 2/3/09 B-30.40-01...... 4/26/12 B-70.60-00...... 6/1/06 B-95.40-00...... 6/8/06 2 C-1...... 7/12/16 C-6...... 7/15/16 C-23.60-03...... 6/11/14 C-1a...... 7/14/15 C-6a...... 10/14/09 C.24.10-01...... 6/11/14 C-1b...... 7/14/15 C-6c...... 7/15/16 C-25.18-05...... 7/14/15 C-1c...... 7/12/16 C-6d...... 7/15/16 C-25.20-06...... 7/14/15 C-1d...... 10/31/03 C-6f...... 7/15/16 C-25.22-05...... 7/14/15 C-2...... 1/6/00 C-7...... 6/16/11 C-25.26-03...... 7/14/15 C-2a...... 6/21/06 C-7a...... 6/16/11 C-25.80-04...... 7/15/16 C-2b...... 6/21/06 C-8...... 2/10/09 C-40.14-02...... 7/2/12 C-2c...... 6/21/06 C-8a...... 7/25/97 C-40.16-02...... 7/2/12 C-2d...... 6/21/06 C-8b...... 2/29/16 C-40.18-02...... 7/2/12 C-2e...... 6/21/06 C-8e...... 2/21/07 C-70.10-01...... 6/17/14 C-2f...... 3/14/97 C-8f...... 6/30/04 C-75.10-01...... 6/11/14 C-2g...... 7/27/01 C-10...... 7/15/16 C-75.20-01...... 6/11/14 C-2h...... 3/28/97 C-16a...... 6/3/10 C-75.30-01...... 6/11/14 C-2i...... 3/28/97 C-20.10-03...... 7/14/15 C-80.10-01...... 6/11/14 C-2j...... 6/12/98 C-20.14-03...... 6/11/14 C-80.20-01...... 6/11/14 C-2k...... 7/12/16 C-20.15-02...... 6/11/14 C-80.30-01...... 6/11/14 C-2n...... 7/12/16 C-20.18-02...... 6/11/14 C-80.40-01...... 6/11/14 C-2o...... 7/13/01 C-20.19-02...... 6/11/14 C-80.50-00...... 4/8/12 C-2p...... 10/31/03 C-20.40-05...... 7/14/15 C-85.10-00...... 4/8/12 C-3...... 7/2/12 C-20.41-01...... 7/14/15 C-85.11-00...... 4/8/12 C-3a...... 10/4/05 C-20.42-05...... 7/14/15 C-85.14-01...... 6/11/14 C-3b...... 6/27/11 C-20.45.01...... 7/2/12 C-85.15-01...... 6/30/14 C-3c...... 6/27/11 C-22.14-04...... 7/15/16 C-85.16-01...... 6/17/14 C-4b...... 7/15/16 C-22.16-05...... 7/14/15 C-85-18-01...... 6/11/14 C-4e...... 7/15/16 C-22.40-05...... 7/15/16 C-85.20-01...... 6/11/14 C-4f...... 7/2/12 C-22.45-02...... 7/15/16 C-90.10-00...... 7/3/08 C-16b...... 6/3/10 3

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 211 D-2.04-00...... 11/10/05 D-2.48-00...... 11/10/05 D-3.17-02……5/9/16 D-2.06-01...... 1/6/09 D-2.64-01...... 1/6/09 D-4...... 12/11/98 D-2.08-00...... 11/10/05 D-2.66-00...... 11/10/05 D-6...... 6/19/98 D-2.14-00...... 11/10/05 D-2.68-00...... 11/10/05 D-10.10-01...... 12/2/08 D-2.16-00...... 11/10/05 D-2.80-00...... 11/10/05 D-10.15-01...... 12/2/08 D-2.18-00...... 11/10/05 D-2.82-00...... 11/10/05 D-10.20-00...... 7/8/08 D-2.20-00...... 11/10/05 D-2.84-00...... 11/10/05 D-10.25-00...... 7/8/08 D-2.32-00...... 11/10/05 D-2.86-00...... 11/10/05 D-10.30-00...... 7/8/08 D-2.34-01...... 1/6/09 D-2.88-00...... 11/10/05 D-10.35-00...... 7/8/08 D-2.36-03...... 6/11/14 D-2.92-00...... 11/10/05 D-10.40-01...... 12/2/08 D-2.42-00...... 11/10/05 D-3.09-00...... 5/17/12 D-10.45-01...... 12/2/08 D-2.44-00...... 11/10/05 D-3.10-01……5/29/13 D-15.10-01...... 12/2/08 D-2.60-00...... 11/10/05 D-3.11-03……6/11/14 D-15.20-03...... 5/9/16 D-2.62-00...... 11/10/05 D-3.15-02……6/10/13 D-15.30-01...... 12/02/08 D-2.46-01...... 6/11/14 D-3.16-02……5/29/13 1 E-1...... 2/21/07 E-4...... 8/27/03 E-2...... 5/29/98 E-4a...... 8/27/03 2 F-10.12-03...... 6/11/14 F-10.62-02...... 4/22/14 F-40.15-03...... 6/29/16 F-10.16-00...... 12/20/06 F-10.64-03...... 4/22/14 F-40.16-03...... 6/29/16 F-10.18-00...... 6/27/11 F-30.10-03...... 6/11/14 F-45.10-02...... 7/15/16 F-10.40-03...... 6/29/16 F-40.12-03...... 6/29/16 F-80.10-04...... 7/15/16 F-10.42-00...... 1/23/07 F-40.14-03...... 6/29/16 3 G-10.10-00...... 9/20/07 G-25.10-04...... 6/10/13 G-90.10-02……4/28/16 G-20.10-02...... 6/23/15 G-30.10-04...... 6/23/15 G-90.11-00……4/28/16 G-22.10-03...... 7/10/15 G-50.10-02...... 6/23/15 G-90.20-04……4/28/16 G-24.10-00...... 11/8/07 G-60.10-03...... 6/18/15 G-90.30-03……4/28/16 G-24.20-01...... 2/7/12 G-60.20-02...... 6/18/15 G-90.40-02……4/28/16 G-24.30-01...... 2/7/12 G-60.30-02...... 6/18/15 G-95.10-01...... 6/2/11 G-24.40-06.....2/29/16 G-70.10-03...... 6/18/15 G-95.20-02...... 6/2/11 G-24.50-03.....6/17/14 G-70.20-03...... 2/29/16 G-95.30-02...... 6/2/11 G-24.60-04.....6/23/15 G-70.30-03...... 2/29/16 4 H-10.10-00...... 7/3/08 H-32.10-00...... 9/20/07 H-70.10-01...... 2/7/12 H-10.15-00...... 7/3/08 H-60.10-01...... 7/3/08 H-70.20-01...... 2/16/12 H-30.10-00...... 10/12/07 H-60.20-01...... 7/3/08 H-70.30-02...... 2/7/12 5 I-10.10-01...... 8/11/09 I-30.20-00...... 9/20/07 I-40.20-00...... 9/20/07 I-30.10-02...... 3/22/13 I-30.30-01...... 6/10/13 I-50.20-01...... 6/10/13 I-30.15-02...... 3/22/13 I-30.40-01...... 6/10/13 I-60.10-01...... 6/10/13 I-30.16-00...... 3/22/13 I-30.60-00...... 5/29/13 I-60.20-01...... 6/10/13 I-30.17-00...... 3/22/13 I-40.10-00...... 9/20/07 I-80.10-02...... 7/15/16 6 J-10...... 7/18/97 J-26.20-00…..6/11/14 J-40.38-01...... 5/20/13 J-10.10-03……6/3/15 J-27.10-01…..7/21/16 J-40.39-00……5/20/13 J-10.15-01...... 6/11/14 J-27.15-00…..3/15/12 J-40.40-01……4/28/16 J-10.16-00……6/3/15 J-28.10-01...... 5/11/11 J-50.10-00…….6/3/11 J-10.17-00……6/3/15 J-28.22-00...... 8/07/07 J-50.11-00…….6/3/11 J-10.18-00……6/3/15 J-28.24-01...... 6/3/15 J-50.12-00…….6/3/11 J-10.20-01……6/1/16 J-28.26-01...... 12/02/08 J-50.15-00…….6/3/11

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 212 J-10.21-00……6/3/15 J-28.30-03...... 6/11/14 J-50.16-01…….3/22/13 J-10.22-00...... 5/29/13 J-28.40-02...... 6/11/14 J-50.20-00…….6/3/11 J-15.10-01...... 6/11/14 J-28.42-01...... 6/11/14 J-50.25-00…….6/3/11 J-15.15-02……7/10/15 J-28.43-00...... 6/11/14 J-50.30-00…….6/3/11 J-20.10-03...... 6/30/14 J-28.45-03...... 7/21/16 J-60.05-01…….7/21/16 J-20.11-02...... 6/30/14 J-28.50-03...... 7/21/16 J-60.11-00…....5/20/13 J-20.15-03...... 6/30/14 J-28.60-02...... 7/21/16 J-60.12-00…....5/20/13 J-20.16-02...... 6/30/14 J-28.70-02...... 6/1/16 J-60.13-00…....6/16/10 J-20.20-02...... 5/20/13 J-29.10-01...... 7/21/16 J-60.14-00……6/16/10 J-20.26-01...... 7/12/12 J-29.15-01...... 7/21/16 J-75.10-02……7/10/15 J-21.10-04...... 6/30/14 J-29.16-02...... 7/21/16 J-75.20-01……7/10/15 J-21.15-01...... 6/10/13 J-30.10-00…...6/18/15 J-75.30-02…….7/10/15 J-21.16-01...... 6/10/13 J-40.05-00……7/21/16 J-75.40-02……6/1/16 J-21.17-01...... 6/10/13 J-40.10-04…...4/28/16 J-75.41-01……6/29/16 J-21.20-01...... 6/10/13 J-40.20-03…...4/28/16 J-75.45-02……6/1/16 J-22.15-02...... 7/10/15 J-40.30-04……4/28/16 J-90.10-02…….4/28/16 J-22.16-03...... 7/10/15 J-40.35-01……5/29/13 J-90.20-02…….4/28/16 J-26.10-03…..7/21/16 J-40.36-01……5/20/13 J-90.21-01……4/28/16 J-26.15-01…..5/17/12 J-40.37-01……5/20/13 1 K-70.20-01...... 6/1/16 K-80.10-01...... 6/1/16 K-80.20-00.....12/20/06 K-80.30-00...... 2/21/07 K-80.35-00...... 2/21/07 K-80.37-00...... 2/21/07 2 L-10.10-02...... 6/21/12 L-40.10-02...... 6/21/12 L-70.10-01...... 5/21/08 L-20.10-03...... 7/14/15 L-40.15-01...... 6/16/11 L-70.20-01...... 5/21/08 L-30.10-02...... 6/11/14 L-40.20-02...... 6/21/12 3 M-1.20-03...... 6/24/14 M-9.60-00……..2/10/09 M-40.10-03...... 6/24/14 M-1.40-02...... 6/3/11 M-11.10-01...... 1/30/07 M-40.20-00...10/12/07 M-1.60-02...... 6/3/11 M-15.10-01...... 2/6/07 M-40.30-00...... 9/20/07 M-1.80-03...... 6/3/11 M-17.10-02...... 7/3/08 M-40.40-00...... 9/20/07 M-2.20-03...... 7/10/15 M-20.10-02...... 6/3/11 M-40.50-00...... 9/20/07 M-2.21-00……7/10/15 M-20.20-02...... 4/20/15 M-40.60-00...... 9/20/07 M-3.10-03...... 6/3/11 M-20.30-04...... 2/29/16 M-60.10-01...... 6/3/11 M-3.20-02...... 6/3/11 M-20.40-03...... 6/24/14 M-60.20-02...... 6/27/11 M-3.30-03...... 6/3/11 M-20.50-02...... 6/3/11 M-65.10-02...... 5/11/11 M-3.40-03...... 6/3/11 M-24.20-02...... 4/20/15 M-80.10-01...... 6/3/11 M-3.50-02...... 6/3/11 M-24.40-02...... 4/20/15 M-80.20-00...... 6/10/08 M-5.10-02...... 6/3/11 M-24.50-00...... 6/16/11 M-80.30-00...... 6/10/08 M-7.50-01...... 1/30/07 M-24.60-04...... 6/24/14 M-9.50-02...... 6/24/14 4 5

HMA OVERLAY (2019) Skagit County Project #ESHMA19-1 July 2019 213

APPENDIX A Standard Plans

APPENDIX B Wage Rates Washington State Prevailing Wage Rates

Page 1 of 18

State of Washington Department of Labor & Industries Prevailing Wage Section - Telephone 360-902-5335 PO Box 44540, Olympia, WA 98504-4540 Washington State Prevailing Wage The PREVAILING WAGES listed here include both the hourly wage rate and the hourly rate of fringe benefits. On public works projects, worker's wage and benefit rates must add to not less than this total. A brief description of overtime calculation requirements are provided on the Benefit Code Key. Journey Level Prevailing Wage Rates for the Effective Date: 7/8/2019

*Risk County Trade Job Classification Wage Holiday Overtime Note Class Skagit Asbestos Abatement Workers Journey Level $46.57 5D 1H View Skagit Boilermakers Journey Level $66.54 5N 1C View Skagit Brick Mason Journey Level $57.32 5A 1M View Skagit Brick Mason Pointer-Caulker-Cleaner $57.32 5A 1M View Skagit Building Service Employees Janitor $12.00 1 View Skagit Building Service Employees Shampooer $12.00 1 View Skagit Building Service Employees Waxer $12.00 1 View Skagit Building Service Employees Window Cleaner $12.00 1 View Skagit Cabinet Makers (In Shop) Journey Level $18.85 1 View Skagit Carpenters Acoustical Worker $60.04 5D 4C View Skagit Carpenters Bridge, Dock And Wharf $60.04 5D 4C View Carpenters Skagit Carpenters Carpenter $60.04 5D 4C View Skagit Carpenters Carpenters on Stationary $60.17 5D 4C View Tools Skagit Carpenters Creosoted Material $60.14 5D 4C View Skagit Carpenters Floor Finisher $60.04 5D 4C View Skagit Carpenters Floor Layer $60.04 5D 4C View Skagit Carpenters Scaffold Erector $60.04 5D 4C View Skagit Cement Masons Journey Level $60.07 7A 4U View Skagit Divers & Tenders Bell/Vehicle or Submersible $113.60 5D 4C View Operator (Not Under Pressure) Skagit Divers & Tenders Dive Supervisor/Master $76.33 5D 4C View Skagit Divers & Tenders Diver $113.60 5D 4C 8V View Skagit Divers & Tenders Diver On Standby $71.33 5D 4C View Skagit Divers & Tenders Diver Tender $64.71 5D 4C View Skagit Divers & Tenders Manifold Operator $64.71 5D 4C View Skagit Divers & Tenders Manifold Operator Mixed Gas $69.71 5D 4C View Skagit Divers & Tenders Remote Operated Vehicle $64.71 5D 4C View Operator/Technician Skagit Divers & Tenders Remote Operated Vehicle $60.29 5A 4C View Tender

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 7/8/2019 Page 2 of 18

Skagit Dredge Workers Assistant Engineer $56.44 5D 3F View Skagit Dredge Workers Assistant Mate (Deckhand) $56.00 5D 3F View Skagit Dredge Workers Boatmen $56.44 5D 3F View Skagit Dredge Workers Engineer $57.51 5D 3F View Skagit Dredge Workers Leverman, Hydraulic $58.67 5D 3F View Skagit Dredge Workers Mates $56.44 5D 3F View Skagit Dredge Workers Oiler $56.00 5D 3F View Skagit Drywall Applicator Journey Level $58.48 5D 1H View Skagit Drywall Tapers Journey Level $59.32 5P 1E View Skagit Electrical Fixture Journey Level $21.48 1 View Maintenance Workers Skagit - Inside Cable Splicer $71.52 7H 1E View Skagit Electricians - Inside Construction Stock Person $34.97 7H 1D View Skagit Electricians - Inside Journey Level $66.89 7H 1E View Skagit Electricians - Motor Shop Craftsman $15.37 1 View Skagit Electricians - Motor Shop Journey Level $14.69 1 View Skagit Electricians - Powerline Cable Splicer $79.60 5A 4D View Construction Skagit Electricians - Powerline Certified Line Welder $72.98 5A 4D View Construction Skagit Electricians - Powerline Groundperson $47.94 5A 4D View Construction Skagit Electricians - Powerline Heavy Line Equipment $72.98 5A 4D View Construction Operator Skagit Electricians - Powerline Journey Level Lineperson $72.98 5A 4D View Construction Skagit Electricians - Powerline Line Equipment Operator $62.06 5A 4D View Construction Skagit Electricians - Powerline Meter Installer $47.94 5A 4D 8W View Construction Skagit Electricians - Powerline Pole Sprayer $72.98 5A 4D View Construction Skagit Electricians - Powerline Powderperson $54.55 5A 4D View Construction Skagit Electronic Technicians Electronic Technicians $43.70 5B 1B View Journey Level Skagit Elevator Constructors Mechanic $94.22 7D 4A View Skagit Elevator Constructors Mechanic In Charge $101.73 7D 4A View Skagit Fabricated Precast Concrete Journey Level $13.50 1 View Products Skagit Fabricated Precast Concrete Journey Level - In-Factory $13.50 1 View Products Work Only Skagit Fence Erectors Fence Erector $41.45 7A 3I View Skagit Fence Erectors Fence Laborer $41.45 7A 3I View Skagit Flaggers Journey Level $41.45 7A 3I View Skagit Journey Level $64.56 7L 1Y View Skagit Heat & Frost Insulators And Journeyman $73.58 5J 4H View Asbestos Workers

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 7/8/2019 Page 3 of 18

Skagit Heating Equipment Mechanic $69.10 7F 1E View Mechanics Skagit Hod Carriers & Mason Journey Level $50.42 7A 3I View Tenders Skagit Industrial Power Vacuum Journey Level $12.00 1 View Cleaner Skagit Inland Boatmen Boat Operator $61.41 5B 1K View Skagit Inland Boatmen Cook $56.48 5B 1K View Skagit Inland Boatmen Deckhand $57.48 5B 1K View Skagit Inland Boatmen Deckhand Engineer $58.81 5B 1K View Skagit Inland Boatmen Launch Operator $58.89 5B 1K View Skagit Inland Boatmen Mate $57.31 5B 1K View Skagit Inspection/Cleaning/Sealing Cleaner Operator, Foamer $12.00 1 View Of Sewer & Water Systems Operator By Remote Control Skagit Inspection/Cleaning/Sealing Grout Truck Operator $12.00 1 View Of Sewer & Water Systems By Remote Control Skagit Inspection/Cleaning/Sealing Head Operator $12.78 1 View Of Sewer & Water Systems By Remote Control Skagit Inspection/Cleaning/Sealing Technician $12.00 1 View Of Sewer & Water Systems By Remote Control Skagit Inspection/Cleaning/Sealing Tv Truck Operator $12.00 1 View Of Sewer & Water Systems By Remote Control Skagit Insulation Applicators Journey Level $60.04 5D 4C View Skagit Journeyman $70.68 7N 1O View Skagit Laborers Air, Gas Or Electric Vibrating $48.90 7A 3I View Screed Skagit Laborers Airtrac Drill Operator $50.42 7A 3I View Skagit Laborers Ballast Regular Machine $48.90 7A 3I View Skagit Laborers Batch Weighman $41.45 7A 3I View Skagit Laborers Brick Pavers $48.90 7A 3I View Skagit Laborers Brush Cutter $48.90 7A 3I View Skagit Laborers Brush Hog Feeder $48.90 7A 3I View Skagit Laborers Burner $48.90 7A 3I View Skagit Laborers Caisson Worker $50.42 7A 3I View Skagit Laborers Carpenter Tender $48.90 7A 3I View Skagit Laborers Caulker $48.90 7A 3I View Skagit Laborers Cement Dumper-paving $49.81 7A 3I View Skagit Laborers Cement Finisher Tender $48.90 7A 3I View Skagit Laborers Change House Or Dry Shack $48.90 7A 3I View Skagit Laborers Chipping Gun (under 30 Lbs.) $48.90 7A 3I View Skagit Laborers Chipping Gun(30 Lbs. And $49.81 7A 3I View Over) Skagit Laborers Choker Setter $48.90 7A 3I View Skagit Laborers Chuck Tender $48.90 7A 3I View

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 7/8/2019 Page 4 of 18

Skagit Laborers Clary Power Spreader $49.81 7A 3I View Skagit Laborers Clean-up Laborer $48.90 7A 3I View Skagit Laborers Concrete Dumper/chute $49.81 7A 3I View Operator Skagit Laborers Concrete Form Stripper $48.90 7A 3I View Skagit Laborers Concrete Placement Crew $49.81 7A 3I View Skagit Laborers Concrete Saw Operator/core $49.81 7A 3I View Driller Skagit Laborers Crusher Feeder $41.45 7A 3I View Skagit Laborers Curing Laborer $48.90 7A 3I View Skagit Laborers Demolition: Wrecking & $48.90 7A 3I View Moving (incl. Charred Material) Skagit Laborers Ditch Digger $48.90 7A 3I View Skagit Laborers Diver $50.42 7A 3I View Skagit Laborers Drill Operator $49.81 7A 3I View (hydraulic,diamond) Skagit Laborers Dry Stack Walls $48.90 7A 3I View Skagit Laborers Dump Person $48.90 7A 3I View Skagit Laborers Epoxy Technician $48.90 7A 3I View Skagit Laborers Erosion Control Worker $48.90 7A 3I View Skagit Laborers Faller & Bucker Chain Saw $49.81 7A 3I View Skagit Laborers Fine Graders $48.90 7A 3I View Skagit Laborers Firewatch $41.45 7A 3I View Skagit Laborers Form Setter $48.90 7A 3I View Skagit Laborers Gabian Basket Builders $48.90 7A 3I View Skagit Laborers General Laborer $48.90 7A 3I View Skagit Laborers Grade Checker & Transit $50.42 7A 3I View Person Skagit Laborers Grinders $48.90 7A 3I View Skagit Laborers Grout Machine Tender $48.90 7A 3I View Skagit Laborers Groutmen (pressure) $49.81 7A 3I View including Post Tension Beams Skagit Laborers Guardrail Erector $48.90 7A 3I View Skagit Laborers Hazardous Waste Worker $50.42 7A 3I View (level A) Skagit Laborers Hazardous Waste Worker $49.81 7A 3I View (level B) Skagit Laborers Hazardous Waste Worker $48.90 7A 3I View (level C) Skagit Laborers High Scaler $50.42 7A 3I View Skagit Laborers Jackhammer $49.81 7A 3I View Skagit Laborers Laserbeam Operator $49.81 7A 3I View Skagit Laborers Maintenance Person $48.90 7A 3I View Skagit Laborers Manhole Builder-mudman $49.81 7A 3I View Skagit Laborers Material Yard Person $48.90 7A 3I View Skagit Laborers Motorman-dinky Locomotive $49.81 7A 3I View

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 7/8/2019 Page 5 of 18

Skagit Laborers Nozzleman (, $49.81 7A 3I View Green Cutter When Using Combination Of High Pressure Air & Water On Concrete & Rock, Sandblast, Gunite, Shotcrete, Water Bla Skagit Laborers Pavement Breaker $49.81 7A 3I View Skagit Laborers Pilot Car $41.45 7A 3I View Skagit Laborers Pipe Layer Lead $50.42 7A 3I View Skagit Laborers Pipe Layer/tailor $49.81 7A 3I View Skagit Laborers Pipe Pot Tender $49.81 7A 3I View Skagit Laborers Pipe Reliner $49.81 7A 3I View Skagit Laborers Pipe Wrapper $49.81 7A 3I View Skagit Laborers Pot Tender $48.90 7A 3I View Skagit Laborers Powderman $50.42 7A 3I View Skagit Laborers Powderman's Helper $48.90 7A 3I View Skagit Laborers Power Jacks $49.81 7A 3I View Skagit Laborers Railroad Spike Puller - Power $49.81 7A 3I View Skagit Laborers Raker - Asphalt $50.42 7A 3I View Skagit Laborers Re-timberman $50.42 7A 3I View Skagit Laborers Remote Equipment Operator $49.81 7A 3I View Skagit Laborers Rigger/signal Person $49.81 7A 3I View Skagit Laborers Rip Rap Person $48.90 7A 3I View Skagit Laborers Rivet Buster $49.81 7A 3I View Skagit Laborers Rodder $49.81 7A 3I View Skagit Laborers Scaffold Erector $48.90 7A 3I View Skagit Laborers Scale Person $48.90 7A 3I View Skagit Laborers Sloper (over 20") $49.81 7A 3I View Skagit Laborers Sloper Sprayer $48.90 7A 3I View Skagit Laborers Spreader (concrete) $49.81 7A 3I View Skagit Laborers Stake Hopper $48.90 7A 3I View Skagit Laborers Stock Piler $48.90 7A 3I View Skagit Laborers Tamper & Similar Electric, $49.81 7A 3I View Air & Gas Operated Tools Skagit Laborers Tamper (multiple & Self- $49.81 7A 3I View propelled) Skagit Laborers Timber Person - Sewer $49.81 7A 3I View (lagger, Shorer & Cribber) Skagit Laborers Toolroom Person (at Jobsite) $48.90 7A 3I View Skagit Laborers Topper $48.90 7A 3I View Skagit Laborers Track Laborer $48.90 7A 3I View Skagit Laborers Track Liner (power) $49.81 7A 3I View Skagit Laborers Traffic Control Laborer $44.33 7A 3I 8R View Skagit Laborers Traffic Control Supervisor $44.33 7A 3I 8R View Skagit Laborers Truck Spotter $48.90 7A 3I View Skagit Laborers Tugger Operator $49.81 7A 3I View Skagit Laborers $107.60 7A 3I 8Q View

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 7/8/2019 Page 6 of 18

Tunnel Work-Compressed Air Worker 0-30 psi Skagit Laborers Tunnel Work-Compressed Air $112.63 7A 3I 8Q View Worker 30.01-44.00 psi Skagit Laborers Tunnel Work-Compressed Air $116.31 7A 3I 8Q View Worker 44.01-54.00 psi Skagit Laborers Tunnel Work-Compressed Air $122.01 7A 3I 8Q View Worker 54.01-60.00 psi Skagit Laborers Tunnel Work-Compressed Air $124.13 7A 3I 8Q View Worker 60.01-64.00 psi Skagit Laborers Tunnel Work-Compressed Air $129.23 7A 3I 8Q View Worker 64.01-68.00 psi Skagit Laborers Tunnel Work-Compressed Air $131.13 7A 3I 8Q View Worker 68.01-70.00 psi Skagit Laborers Tunnel Work-Compressed Air $133.13 7A 3I 8Q View Worker 70.01-72.00 psi Skagit Laborers Tunnel Work-Compressed Air $135.13 7A 3I 8Q View Worker 72.01-74.00 psi Skagit Laborers Tunnel Work-Guage and Lock $50.52 7A 3I 8Q View Tender Skagit Laborers Tunnel Work-Miner $50.52 7A 3I 8Q View Skagit Laborers Vibrator $49.81 7A 3I View Skagit Laborers Vinyl Seamer $48.90 7A 3I View Skagit Laborers Watchman $37.67 7A 3I View Skagit Laborers Welder $49.81 7A 3I View Skagit Laborers Well Point Laborer $49.81 7A 3I View Skagit Laborers Window Washer/cleaner $37.67 7A 3I View Skagit Laborers - Underground General Laborer & Topman $48.90 7A 3I View Sewer & Water Skagit Laborers - Underground Pipe Layer $49.81 7A 3I View Sewer & Water Skagit Landscape Construction Landscape Laborer $37.67 7A 3I View Skagit Landscape Construction Landscape Operator $63.76 7A 3K 8X View Skagit Landscape Maintenance Groundskeeper $14.18 1 View Skagit Lathers Journey Level $58.48 5D 1H View Skagit Marble Setters Journey Level $57.32 5A 1M View Skagit Metal Fabrication (In Shop) Fitter $15.16 1 View Skagit Metal Fabrication (In Shop) Laborer $12.00 1 View Skagit Metal Fabrication (In Shop) Machine Operator $12.00 1 View Skagit Metal Fabrication (In Shop) Painter $12.00 1 View Skagit Metal Fabrication (In Shop) Welder $15.16 1 View Skagit Journey Level $61.54 5D 4C View Skagit Modular Buildings Journey Level $12.00 1 View Skagit Painters Journey Level $42.50 6Z 2B View Skagit Pile Driver Crew Tender/Technician $64.71 5D 4C View Skagit Pile Driver Hyperbaric Worker - $74.87 5D 4C View Compressed Air Worker 0-30.00 PSI

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 7/8/2019 Page 7 of 18

Skagit Pile Driver Hyperbaric Worker - $79.87 5D 4C View Compressed Air Worker 30.01 - 44.00 PSI Skagit Pile Driver Hyperbaric Worker - $83.87 5D 4C View Compressed Air Worker 44.01 - 54.00 PSI Skagit Pile Driver Hyperbaric Worker - $88.87 5D 4C View Compressed Air Worker 54.01 - 60.00 PSI Skagit Pile Driver Hyperbaric Worker - $91.37 5D 4C View Compressed Air Worker 60.01 - 64.00 PSI Skagit Pile Driver Hyperbaric Worker - $96.37 5D 4C View Compressed Air Worker 64.01 - 68.00 PSI Skagit Pile Driver Hyperbaric Worker - $98.37 5D 4C View Compressed Air Worker 68.01 - 70.00 PSI Skagit Pile Driver Hyperbaric Worker - $100.37 5D 4C View Compressed Air Worker 70.01 - 72.00 PSI Skagit Pile Driver Hyperbaric Worker - $102.37 5D 4C View Compressed Air Worker 72.01 - 74.00 PSI Skagit Pile Driver Journey Level $60.29 5D 4C View Skagit Pile Driver Manifold Operator (LST) $69.71 5D 4C View Skagit Journey Level $56.54 7Q 1R View Skagit Playground & Park Journey Level $12.00 1 View Equipment Installers Skagit & Pipefitters Journey Level $71.42 5A 1G View Skagit Power Equipment Operators Asphalt Plant Operators $64.83 7A 3K 8X View Skagit Power Equipment Operators Assistant Engineer $60.98 7A 3K 8X View Skagit Power Equipment Operators Barrier Machine (zipper) $64.26 7A 3K 8X View Skagit Power Equipment Operators Batch Plant Operator: $64.26 7A 3K 8X View concrete Skagit Power Equipment Operators Bobcat $60.98 7A 3K 8X View Skagit Power Equipment Operators Brokk - Remote Demolition $60.98 7A 3K 8X View Equipment Skagit Power Equipment Operators Brooms $60.98 7A 3K 8X View Skagit Power Equipment Operators Bump Cutter $64.26 7A 3K 8X View Skagit Power Equipment Operators Cableways $64.83 7A 3K 8X View Skagit Power Equipment Operators Chipper $64.26 7A 3K 8X View Skagit Power Equipment Operators Compressor $60.98 7A 3K 8X View Skagit Power Equipment Operators Concrete Finish Machine - $60.98 7A 3K 8X View Laser Screed Skagit Power Equipment Operators Concrete Pump - Mounted Or $63.76 7A 3K 8X View Trailer High Pressure Line Pump, Pump High Pressure Skagit Power Equipment Operators Concrete Pump: Truck Mount $64.83 7A 3K 8X View With Boom Attachment Over 42 M

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 7/8/2019 Page 8 of 18

Skagit Power Equipment Operators Concrete Pump: Truck Mount $64.26 7A 3K 8X View With Boom Attachment Up To 42m Skagit Power Equipment Operators Conveyors $63.76 7A 3K 8X View Skagit Power Equipment Operators Cranes friction: 200 tons and $66.80 7A 3K 8X View over Skagit Power Equipment Operators Cranes: 100 tons through 199 $65.48 7A 3K 8X View tons, or 150’ of boom (including jib with attachments) Skagit Power Equipment Operators Cranes: 20 Tons Through 44 $64.26 7A 3K 8X View Tons With Attachments Skagit Power Equipment Operators Cranes: 200 tons- 299 tons, $66.15 7A 3K 8X View or 250’ of boom including jib with attachments Skagit Power Equipment Operators Cranes: 300 tons and over or $66.80 7A 3K 8X View 300’ of boom including jib with attachments Skagit Power Equipment Operators Cranes: 45 Tons Through 99 $64.83 7A 3K 8X View Tons, Under 150' Of Boom (including Jib With Attachments) Skagit Power Equipment Operators Cranes: A-frame - 10 Tons $60.98 7A 3K 8X View And Under Skagit Power Equipment Operators Cranes: Friction cranes $66.15 7A 3K 8X View through 199 tons Skagit Power Equipment Operators Cranes: through 19 tons with $63.76 7A 3K 8X View attachments, A-frame over 10 tons Skagit Power Equipment Operators Crusher $64.26 7A 3K 8X View Skagit Power Equipment Operators Deck Engineer/Deck Winches $64.26 7A 3K 8X View (power) Skagit Power Equipment Operators Derricks, On Building Work $64.83 7A 3K 8X View Skagit Power Equipment Operators Dozers D-9 & Under $63.76 7A 3K 8X View Skagit Power Equipment Operators Drill Oilers: Auger Type, $63.76 7A 3K 8X View Truck Or Crane Mount Skagit Power Equipment Operators Drilling Machine $65.48 7A 3K 8X View Skagit Power Equipment Operators Elevator And Man-lift: $60.98 7A 3K 8X View Permanent And Shaft Type Skagit Power Equipment Operators Finishing Machine, Bidwell $64.26 7A 3K 8X View And Gamaco & Similar Equipment Skagit Power Equipment Operators Forklift: 3000 Lbs And Over $63.76 7A 3K 8X View With Attachments Skagit Power Equipment Operators Forklifts: Under 3000 Lbs. $60.98 7A 3K 8X View With Attachments Skagit Power Equipment Operators Grade Engineer: Using Blue $64.26 7A 3K 8X View Prints, Cut Sheets, Etc Skagit Power Equipment Operators Gradechecker/Stakeman $60.98 7A 3K 8X View Skagit Power Equipment Operators Guardrail Punch $64.26 7A 3K 8X View Skagit Power Equipment Operators $64.83 7A 3K 8X View

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 7/8/2019 Page 9 of 18

Hard Tail End Dump Articulating Off- Road Equipment 45 Yards. & Over Skagit Power Equipment Operators Hard Tail End Dump $64.26 7A 3K 8X View Articulating Off-road Equipment Under 45 Yards Skagit Power Equipment Operators Horizontal/Directional Drill $63.76 7A 3K 8X View Locator Skagit Power Equipment Operators Horizontal/Directional Drill $64.26 7A 3K 8X View Operator Skagit Power Equipment Operators Hydralifts/Boom Trucks Over $63.76 7A 3K 8X View 10 Tons Skagit Power Equipment Operators Hydralifts/Boom Trucks, 10 $60.98 7A 3K 8X View Tons And Under Skagit Power Equipment Operators Loader, Overhead 8 Yards. & $65.48 7A 3K 8X View Over Skagit Power Equipment Operators Loader, Overhead, 6 Yards. $64.83 7A 3K 8X View But Not Including 8 Yards Skagit Power Equipment Operators Loaders, Overhead Under 6 $64.26 7A 3K 8X View Yards Skagit Power Equipment Operators Loaders, Plant Feed $64.26 7A 3K 8X View Skagit Power Equipment Operators Loaders: Elevating Type Belt $63.76 7A 3K 8X View Skagit Power Equipment Operators Locomotives, All $64.26 7A 3K 8X View Skagit Power Equipment Operators Material Transfer Device $64.26 7A 3K 8X View Skagit Power Equipment Operators Mechanics, All (leadmen - $65.48 7A 3K 8X View $0.50 Per Hour Over Mechanic) Skagit Power Equipment Operators Motor Patrol Graders $64.83 7A 3K 8X View Skagit Power Equipment Operators Mucking Machine, Mole, $64.83 7A 3K 8X View Tunnel Drill, Boring, Road Header And/or Shield Skagit Power Equipment Operators Oil Distributors, Blower $60.98 7A 3K 8X View Distribution & Mulch Seeding Operator Skagit Power Equipment Operators Outside Hoists (Elevators And $63.76 7A 3K 8X View Manlifts), Air Tuggers, Strato Skagit Power Equipment Operators Overhead, Bridge Type $64.26 7A 3K 8X View Crane: 20 Tons Through 44 Tons Skagit Power Equipment Operators Overhead, Bridge Type: 100 $65.48 7A 3K 8X View Tons And Over Skagit Power Equipment Operators Overhead, Bridge Type: 45 $64.83 7A 3K 8X View Tons Through 99 Tons Skagit Power Equipment Operators Pavement Breaker $60.98 7A 3K 8X View Skagit Power Equipment Operators Pile Driver (other Than Crane $64.26 7A 3K 8X View Mount) Skagit Power Equipment Operators Plant Oiler - Asphalt, Crusher $63.76 7A 3K 8X View Skagit Power Equipment Operators Posthole Digger, Mechanical $60.98 7A 3K 8X View Skagit Power Equipment Operators Power Plant $60.98 7A 3K 8X View Skagit Power Equipment Operators Pumps - Water $60.98 7A 3K 8X View

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 7/8/2019 Page 10 of 18

Skagit Power Equipment Operators Quad 9, Hd 41, D10 And Over $64.83 7A 3K 8X View Skagit Power Equipment Operators Quick Tower - No Cab, Under $60.98 7A 3K 8X View 100 Feet In Height Based To Boom Skagit Power Equipment Operators Remote Control Operator On $64.83 7A 3K 8X View Rubber Tired Earth Moving Equipment Skagit Power Equipment Operators Rigger and Bellman $60.98 7A 3K 8X View Skagit Power Equipment Operators Rigger/Signal Person, $63.76 7A 3K 8X View Bellman (Certified) Skagit Power Equipment Operators Rollagon $64.83 7A 3K 8X View Skagit Power Equipment Operators Roller, Other Than Plant Mix $60.98 7A 3K 8X View Skagit Power Equipment Operators Roller, Plant Mix Or Multi-lift $63.76 7A 3K 8X View Materials Skagit Power Equipment Operators Roto-mill, Roto-grinder $64.26 7A 3K 8X View Skagit Power Equipment Operators Saws - Concrete $63.76 7A 3K 8X View Skagit Power Equipment Operators Scraper, Self Propelled $64.26 7A 3K 8X View Under 45 Yards Skagit Power Equipment Operators Scrapers - Concrete & Carry $63.76 7A 3K 8X View All Skagit Power Equipment Operators Scrapers, Self-propelled: 45 $64.83 7A 3K 8X View Yards And Over Skagit Power Equipment Operators Service Engineers - $63.76 7A 3K 8X View Equipment Skagit Power Equipment Operators Shotcrete/Gunite Equipment $60.98 7A 3K 8X View Skagit Power Equipment Operators Shovel , Excavator, Backhoe, $63.76 7A 3K 8X View Tractors Under 15 Metric Tons Skagit Power Equipment Operators Shovel, Excavator, Backhoe: $64.83 7A 3K 8X View Over 30 Metric Tons To 50 Metric Tons Skagit Power Equipment Operators Shovel, Excavator, Backhoes, $64.26 7A 3K 8X View Tractors: 15 To 30 Metric Tons Skagit Power Equipment Operators Shovel, Excavator, Backhoes: $65.48 7A 3K 8X View Over 50 Metric Tons To 90 Metric Tons Skagit Power Equipment Operators Shovel, Excavator, Backhoes: $66.15 7A 3K 8X View Over 90 Metric Tons Skagit Power Equipment Operators Slipform Pavers $64.83 7A 3K 8X View Skagit Power Equipment Operators Spreader, Topsider & $64.83 7A 3K 8X View Screedman Skagit Power Equipment Operators Subgrader Trimmer $64.26 7A 3K 8X View Skagit Power Equipment Operators Tower Bucket Elevators $63.76 7A 3K 8X View Skagit Power Equipment Operators Tower Crane Up To 175' In $65.48 7A 3K 8X View Height Base To Boom Skagit Power Equipment Operators Tower Crane: over 175’ $66.15 7A 3K 8X View through 250’ in height, base to boom Skagit Power Equipment Operators Tower Cranes: over 250’ in $66.80 7A 3K 8X View height from base to boom

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 7/8/2019 Page 11 of 18

Skagit Power Equipment Operators Transporters, All Track Or $64.83 7A 3K 8X View Truck Type Skagit Power Equipment Operators Trenching Machines $63.76 7A 3K 8X View Skagit Power Equipment Operators Truck Crane Oiler/driver - $64.26 7A 3K 8X View 100 Tons And Over Skagit Power Equipment Operators Truck Crane Oiler/Driver $63.76 7A 3K 8X View Under 100 Tons Skagit Power Equipment Operators Truck Mount Portable $64.26 7A 3K 8X View Conveyor Skagit Power Equipment Operators Welder $64.83 7A 3K 8X View Skagit Power Equipment Operators Wheel Tractors, Farmall $60.98 7A 3K 8X View Type Skagit Power Equipment Operators Yo Yo Pay Dozer $64.26 7A 3K 8X View Skagit Power Equipment Operators- Asphalt Plant Operators $64.83 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Assistant Engineer $60.98 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Barrier Machine (zipper) $64.26 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Batch Plant Operator, $64.26 7A 3K 8X View Underground Sewer & Water Concrete Skagit Power Equipment Operators- Bobcat $60.98 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Brokk - Remote Demolition $60.98 7A 3K 8X View Underground Sewer & Water Equipment Skagit Power Equipment Operators- Brooms $60.98 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Bump Cutter $64.26 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Cableways $64.83 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Chipper $64.26 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Compressor $60.98 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Concrete Finish Machine - $60.98 7A 3K 8X View Underground Sewer & Water Laser Screed Skagit Power Equipment Operators- Concrete Pump - Mounted Or $63.76 7A 3K 8X View Underground Sewer & Water Trailer High Pressure Line Pump, Pump High Pressure Skagit Power Equipment Operators- Concrete Pump: Truck Mount $64.83 7A 3K 8X View Underground Sewer & Water With Boom Attachment Over 42 M Skagit Power Equipment Operators- Concrete Pump: Truck Mount $64.26 7A 3K 8X View Underground Sewer & Water With Boom Attachment Up To 42m Skagit Power Equipment Operators- Conveyors $63.76 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Cranes friction: 200 tons and $66.80 7A 3K 8X View Underground Sewer & Water over Skagit $65.48 7A 3K 8X View

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 7/8/2019 Page 12 of 18

Power Equipment Operators- Cranes: 100 tons through 199 Underground Sewer & Water tons, or 150’ of boom (including jib with attachments) Skagit Power Equipment Operators- Cranes: 20 Tons Through 44 $64.26 7A 3K 8X View Underground Sewer & Water Tons With Attachments Skagit Power Equipment Operators- Cranes: 200 tons- 299 tons, $66.15 7A 3K 8X View Underground Sewer & Water or 250’ of boom including jib with attachments Skagit Power Equipment Operators- Cranes: 300 tons and over or $66.80 7A 3K 8X View Underground Sewer & Water 300’ of boom including jib with attachments Skagit Power Equipment Operators- Cranes: 45 Tons Through 99 $64.83 7A 3K 8X View Underground Sewer & Water Tons, Under 150' Of Boom (including Jib With Attachments) Skagit Power Equipment Operators- Cranes: A-frame - 10 Tons $60.98 7A 3K 8X View Underground Sewer & Water And Under Skagit Power Equipment Operators- Cranes: Friction cranes $66.15 7A 3K 8X View Underground Sewer & Water through 199 tons Skagit Power Equipment Operators- Cranes: through 19 tons with $63.76 7A 3K 8X View Underground Sewer & Water attachments, A-frame over 10 tons Skagit Power Equipment Operators- Crusher $64.26 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Deck Engineer/Deck Winches $64.26 7A 3K 8X View Underground Sewer & Water (power) Skagit Power Equipment Operators- Derricks, On Building Work $64.83 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Dozers D-9 & Under $63.76 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Drill Oilers: Auger Type, $63.76 7A 3K 8X View Underground Sewer & Water Truck Or Crane Mount Skagit Power Equipment Operators- Drilling Machine $65.48 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Elevator And Man-lift: $60.98 7A 3K 8X View Underground Sewer & Water Permanent And Shaft Type Skagit Power Equipment Operators- Finishing Machine, Bidwell $64.26 7A 3K 8X View Underground Sewer & Water And Gamaco & Similar Equipment Skagit Power Equipment Operators- Forklift: 3000 Lbs And Over $63.76 7A 3K 8X View Underground Sewer & Water With Attachments Skagit Power Equipment Operators- Forklifts: Under 3000 Lbs. $60.98 7A 3K 8X View Underground Sewer & Water With Attachments Skagit Power Equipment Operators- Grade Engineer: Using Blue $64.26 7A 3K 8X View Underground Sewer & Water Prints, Cut Sheets, Etc Skagit Power Equipment Operators- Gradechecker/Stakeman $60.98 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Guardrail Punch $64.26 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- $64.83 7A 3K 8X View Underground Sewer & Water

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 7/8/2019 Page 13 of 18

Hard Tail End Dump Articulating Off- Road Equipment 45 Yards. & Over Skagit Power Equipment Operators- Hard Tail End Dump $64.26 7A 3K 8X View Underground Sewer & Water Articulating Off-road Equipment Under 45 Yards Skagit Power Equipment Operators- Horizontal/Directional Drill $63.76 7A 3K 8X View Underground Sewer & Water Locator Skagit Power Equipment Operators- Horizontal/Directional Drill $64.26 7A 3K 8X View Underground Sewer & Water Operator Skagit Power Equipment Operators- Hydralifts/Boom Trucks Over $63.76 7A 3K 8X View Underground Sewer & Water 10 Tons Skagit Power Equipment Operators- Hydralifts/Boom Trucks, 10 $60.98 7A 3K 8X View Underground Sewer & Water Tons And Under Skagit Power Equipment Operators- Loader, Overhead 8 Yards. & $65.48 7A 3K 8X View Underground Sewer & Water Over Skagit Power Equipment Operators- Loader, Overhead, 6 Yards. $64.83 7A 3K 8X View Underground Sewer & Water But Not Including 8 Yards Skagit Power Equipment Operators- Loaders, Overhead Under 6 $64.26 7A 3K 8X View Underground Sewer & Water Yards Skagit Power Equipment Operators- Loaders, Plant Feed $64.26 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Loaders: Elevating Type Belt $63.76 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Locomotives, All $64.26 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Material Transfer Device $64.26 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Mechanics, All (leadmen - $65.48 7A 3K 8X View Underground Sewer & Water $0.50 Per Hour Over Mechanic) Skagit Power Equipment Operators- Motor Patrol Graders $64.83 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Mucking Machine, Mole, $64.83 7A 3K 8X View Underground Sewer & Water Tunnel Drill, Boring, Road Header And/or Shield Skagit Power Equipment Operators- Oil Distributors, Blower $60.98 7A 3K 8X View Underground Sewer & Water Distribution & Mulch Seeding Operator Skagit Power Equipment Operators- Outside Hoists (Elevators And $63.76 7A 3K 8X View Underground Sewer & Water Manlifts), Air Tuggers, Strato Skagit Power Equipment Operators- Overhead, Bridge Type $64.26 7A 3K 8X View Underground Sewer & Water Crane: 20 Tons Through 44 Tons Skagit Power Equipment Operators- Overhead, Bridge Type: 100 $65.48 7A 3K 8X View Underground Sewer & Water Tons And Over Skagit Power Equipment Operators- Overhead, Bridge Type: 45 $64.83 7A 3K 8X View Underground Sewer & Water Tons Through 99 Tons Skagit Power Equipment Operators- Pavement Breaker $60.98 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Pile Driver (other Than Crane $64.26 7A 3K 8X View Underground Sewer & Water Mount)

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 7/8/2019 Page 14 of 18

Skagit Power Equipment Operators- Plant Oiler - Asphalt, Crusher $63.76 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Posthole Digger, Mechanical $60.98 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Power Plant $60.98 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Pumps - Water $60.98 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Quad 9, Hd 41, D10 And Over $64.83 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Quick Tower - No Cab, Under $60.98 7A 3K 8X View Underground Sewer & Water 100 Feet In Height Based To Boom Skagit Power Equipment Operators- Remote Control Operator On $64.83 7A 3K 8X View Underground Sewer & Water Rubber Tired Earth Moving Equipment Skagit Power Equipment Operators- Rigger and Bellman $60.98 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Rigger/Signal Person, $63.76 7A 3K 8X View Underground Sewer & Water Bellman (Certified) Skagit Power Equipment Operators- Rollagon $64.83 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Roller, Other Than Plant Mix $60.98 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Roller, Plant Mix Or Multi-lift $63.76 7A 3K 8X View Underground Sewer & Water Materials Skagit Power Equipment Operators- Roto-mill, Roto-grinder $64.26 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Saws - Concrete $63.76 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Scraper, Self Propelled $64.26 7A 3K 8X View Underground Sewer & Water Under 45 Yards Skagit Power Equipment Operators- Scrapers - Concrete & Carry $63.76 7A 3K 8X View Underground Sewer & Water All Skagit Power Equipment Operators- Scrapers, Self-propelled: 45 $64.83 7A 3K 8X View Underground Sewer & Water Yards And Over Skagit Power Equipment Operators- Service Engineers - $63.76 7A 3K 8X View Underground Sewer & Water Equipment Skagit Power Equipment Operators- Shotcrete/Gunite Equipment $60.98 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Shovel , Excavator, Backhoe, $63.76 7A 3K 8X View Underground Sewer & Water Tractors Under 15 Metric Tons Skagit Power Equipment Operators- Shovel, Excavator, Backhoe: $64.83 7A 3K 8X View Underground Sewer & Water Over 30 Metric Tons To 50 Metric Tons Skagit Power Equipment Operators- Shovel, Excavator, Backhoes, $64.26 7A 3K 8X View Underground Sewer & Water Tractors: 15 To 30 Metric Tons Skagit Power Equipment Operators- Shovel, Excavator, Backhoes: $65.48 7A 3K 8X View Underground Sewer & Water Over 50 Metric Tons To 90 Metric Tons

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 7/8/2019 Page 15 of 18

Skagit Power Equipment Operators- Shovel, Excavator, Backhoes: $66.15 7A 3K 8X View Underground Sewer & Water Over 90 Metric Tons Skagit Power Equipment Operators- Slipform Pavers $64.83 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Spreader, Topsider & $64.83 7A 3K 8X View Underground Sewer & Water Screedman Skagit Power Equipment Operators- Subgrader Trimmer $64.26 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Tower Bucket Elevators $63.76 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Tower Crane Up To 175' In $65.48 7A 3K 8X View Underground Sewer & Water Height Base To Boom Skagit Power Equipment Operators- Tower Crane: over 175’ $66.15 7A 3K 8X View Underground Sewer & Water through 250’ in height, base to boom Skagit Power Equipment Operators- Tower Cranes: over 250’ in $66.80 7A 3K 8X View Underground Sewer & Water height from base to boom Skagit Power Equipment Operators- Transporters, All Track Or $64.83 7A 3K 8X View Underground Sewer & Water Truck Type Skagit Power Equipment Operators- Trenching Machines $63.76 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Truck Crane Oiler/driver - $64.26 7A 3K 8X View Underground Sewer & Water 100 Tons And Over Skagit Power Equipment Operators- Truck Crane Oiler/Driver $63.76 7A 3K 8X View Underground Sewer & Water Under 100 Tons Skagit Power Equipment Operators- Truck Mount Portable $64.26 7A 3K 8X View Underground Sewer & Water Conveyor Skagit Power Equipment Operators- Welder $64.83 7A 3K 8X View Underground Sewer & Water Skagit Power Equipment Operators- Wheel Tractors, Farmall $60.98 7A 3K 8X View Underground Sewer & Water Type Skagit Power Equipment Operators- Yo Yo Pay Dozer $64.26 7A 3K 8X View Underground Sewer & Water Skagit Power Line Clearance Tree Journey Level In Charge $49.96 5A 4A View Trimmers Skagit Power Line Clearance Tree Spray Person $47.37 5A 4A View Trimmers Skagit Power Line Clearance Tree Tree Equipment Operator $49.96 5A 4A View Trimmers Skagit Power Line Clearance Tree Tree Trimmer $44.57 5A 4A View Trimmers Skagit Power Line Clearance Tree Tree Trimmer Groundperson $33.60 5A 4A View Trimmers Skagit Refrigeration & Air Journey Level $70.71 5A 1G View Conditioning Mechanics Skagit Residential Brick Mason Journey Level $32.30 1 View Skagit Residential Carpenters Journey Level $23.34 1 View Skagit Residential Cement Masons Journey Level $20.67 1 View Skagit Residential Drywall Journey Level $45.05 5D 4C View Applicators Skagit Residential Drywall Tapers Journey Level $34.10 1 View

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 7/8/2019 Page 16 of 18

Skagit Residential Electricians Journey Level $34.22 1 View Skagit Residential Glaziers Journey Level $43.00 7L 1H View Skagit Residential Insulation Journey Level $18.03 1 View Applicators Skagit Residential Laborers Journey Level $20.98 1 View Skagit Residential Marble Setters Journey Level $32.30 1 View Skagit Residential Painters Journey Level $17.05 1 View Skagit Residential Plumbers & Journey Level $44.34 5A 1G View Pipefitters Skagit Residential Refrigeration & Journey Level $41.01 5A 1G View Air Conditioning Mechanics Skagit Residential Sheet Metal Journey Level $27.01 1 View Workers Skagit Residential Soft Floor Layers Journey Level $30.31 1 View Skagit Residential Sprinkler Fitters Journey Level $32.87 1 View (Fire Protection) Skagit Residential Stone Masons Journey Level $32.30 1 View Skagit Residential Terrazzo Workers Journey Level $32.30 1 View Skagit Residential Terrazzo/Tile Journey Level $35.85 1 View Finishers Skagit Residential Tile Setters Journey Level $32.30 1 View Skagit Journey Level $31.84 1 View Skagit Sheet Metal Workers Journey Level (Field or Shop) $69.10 7F 1E View Skagit Shipbuilding & Ship Repair New Construction $36.36 7V 1 View Boilermaker Skagit Shipbuilding & Ship Repair New Construction Carpenter $36.36 7V 1 View Skagit Shipbuilding & Ship Repair New Construction Crane $36.36 7V 1 View Operator Skagit Shipbuilding & Ship Repair New Construction $36.36 7V 1 View Skagit Shipbuilding & Ship Repair New Construction Heat & $73.58 5J 4H View Frost Insulator Skagit Shipbuilding & Ship Repair New Construction Laborer $36.36 7V 1 View Skagit Shipbuilding & Ship Repair New Construction Machinist $36.36 7V 1 View Skagit Shipbuilding & Ship Repair New Construction Operating $36.36 7V 1 View Engineer Skagit Shipbuilding & Ship Repair New Construction Painter $36.36 7V 1 View Skagit Shipbuilding & Ship Repair New Construction Pipefitter $36.36 7V 1 View Skagit Shipbuilding & Ship Repair New Construction Rigger $36.36 7V 1 View Skagit Shipbuilding & Ship Repair New Construction Sheet $36.36 7V 1 View Metal Skagit Shipbuilding & Ship Repair New Construction Shipfitter $36.36 7V 1 View Skagit Shipbuilding & Ship Repair New Construction $36.36 7V 1 View Warehouse/Teamster Skagit Shipbuilding & Ship Repair New Construction Welder / $36.36 7V 1 View Burner Skagit Shipbuilding & Ship Repair Ship Repair Boilermaker $44.95 7X 4J View Skagit Shipbuilding & Ship Repair Ship Repair Carpenter $44.95 7X 4J View Skagit Shipbuilding & Ship Repair Ship Repair Crane Operator $44.06 7Y 4K View

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 7/8/2019 Page 17 of 18

Skagit Shipbuilding & Ship Repair Ship Repair Electrician $44.95 7X 4J View Skagit Shipbuilding & Ship Repair Ship Repair Heat & Frost $73.58 5J 4H View Insulator Skagit Shipbuilding & Ship Repair Ship Repair Laborer $44.95 7X 4J View Skagit Shipbuilding & Ship Repair Ship Repair Machinist $44.95 7X 4J View Skagit Shipbuilding & Ship Repair Ship Repair Operating $44.06 7Y 4K View Engineer Skagit Shipbuilding & Ship Repair Ship Repair Painter $44.95 7X 4J View Skagit Shipbuilding & Ship Repair Ship Repair Pipefitter $44.95 7X 4J View Skagit Shipbuilding & Ship Repair Ship Repair Rigger $44.95 7X 4J View Skagit Shipbuilding & Ship Repair Ship Repair Sheet Metal $44.95 7X 4J View Skagit Shipbuilding & Ship Repair Ship Repair Shipwright $44.95 7X 4J View Skagit Shipbuilding & Ship Repair Ship Repair Warehouse / $44.06 7Y 4K View Teamster Skagit Sign Makers & Installers Journey Level $16.03 1 View (Electrical) Skagit Sign Makers & Installers Journey Level $13.28 1 View (Non-Electrical) Skagit Soft Floor Layers Journey Level $49.43 5A 3J View Skagit Solar Controls For Windows Journey Level $12.00 1 View Skagit Sprinkler Fitters (Fire Journey Level $78.39 5C 1X View Protection) Skagit Stage Rigging Mechanics (Non Journey Level $13.23 1 View Structural) Skagit Stone Masons Journey Level $57.32 5A 1M View Skagit Street And Parking Lot Journey Level $15.00 1 View Sweeper Workers Skagit Surveyors Assistant Construction Site $62.71 7A 3K 8X View Surveyor Skagit Surveyors Assistant Construction Site $62.71 7A 3K 8X View Surveyor Skagit Surveyors Chainman $58.93 7A 3C 8P View Skagit Surveyors Construction Site Surveyor $63.76 7A 3K 8X View Skagit Telecommunication Telecom Technician Journey $43.70 5B 1B View Technicians Level Skagit Telephone Line Construction Cable Splicer $41.22 5A 2B View - Outside Skagit Telephone Line Construction Hole Digger/Ground Person $23.12 5A 2B View - Outside Skagit Telephone Line Construction Installer (Repairer) $39.53 5A 2B View - Outside Skagit Telephone Line Construction Special Aparatus Installer I $41.22 5A 2B View - Outside Skagit Telephone Line Construction Special Apparatus Installer II $40.41 5A 2B View - Outside Skagit Telephone Line Construction Telephone Equipment $41.22 5A 2B View - Outside Operator (Heavy) Skagit Telephone Line Construction Telephone Equipment $38.36 5A 2B View - Outside Operator (Light)

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 7/8/2019 Page 18 of 18

Skagit Telephone Line Construction Telephone Lineperson $38.36 5A 2B View - Outside Skagit Telephone Line Construction Television Groundperson $21.92 5A 2B View - Outside Skagit Telephone Line Construction Television $29.13 5A 2B View - Outside Lineperson/Installer Skagit Telephone Line Construction Television System Technician $34.68 5A 2B View - Outside Skagit Telephone Line Construction Television Technician $31.18 5A 2B View - Outside Skagit Telephone Line Construction Tree Trimmer $38.36 5A 2B View - Outside Skagit Terrazzo Workers Journey Level $52.61 5A 1M View Skagit Tile Setters Journey Level $52.61 5A 1M View Skagit Tile, Marble & Terrazzo Finisher $43.44 5A 1B View Finishers Skagit Traffic Control Stripers Journey Level $46.23 7A 1K View Skagit Truck Drivers Asphalt Mix Over 16 Yards $57.81 5D 3A 8L View Skagit Truck Drivers Asphalt Mix To 16 Yards $56.97 5D 3A 8L View Skagit Truck Drivers Dump Truck $56.97 5D 3A 8L View Skagit Truck Drivers Dump Truck & Trailer $57.81 5D 3A 8L View Skagit Truck Drivers Other Trucks $57.81 5D 3A 8L View Skagit Truck Drivers - Ready Mix Transit Mix $57.81 5D 3A 8L View Skagit Well Drillers & Irrigation Irrigation Pump Installer $12.00 1 View Pump Installers Skagit Well Drillers & Irrigation Oiler $12.00 1 View Pump Installers Skagit Well Drillers & Irrigation Well Driller $12.00 1 View Pump Installers

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx 7/8/2019 Benefit Code Key – Effective 3/3/2019 thru 8/30/2019

************************************************************************************************************ Overtime Codes

Overtime calculations are based on the hourly rate actually paid to the worker. On public works projects, the hourly rate must be not less than the prevailing rate of wage minus the hourly rate of the cost of fringe benefits actually provided for the worker.

1. ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE.

B. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

C. The first two (2) hours after eight (8) regular hours Monday through Friday and the first ten (10) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other overtime hours and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

D. The first two (2) hours before or after a five-eight (8) hour workweek day or a four-ten (10) hour workweek day and the first eight (8) hours worked the next day after either workweek shall be paid at one and one-half times the hourly rate of wage. All additional hours worked and all worked on Sundays and holidays shall be paid at double the hourly rate of wage.

E. The first two (2) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other hours worked Monday through Saturday, and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

F. The first two (2) hours after eight (8) regular hours Monday through Friday and the first ten (10) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other overtime hours worked, except Labor Day, shall be paid at double the hourly rate of wage. All hours worked on Labor Day shall be paid at three times the hourly rate of wage.

G. The first ten (10) hours worked on Saturdays and the first ten (10) hours worked on a fifth calendar weekday in a four- ten hour schedule, shall be paid at one and one-half times the hourly rate of wage. All hours worked in excess of ten (10) hours per day Monday through Saturday and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

H. All hours worked on Saturdays (except makeup days if work is lost due to inclement weather conditions or equipment breakdown) shall be paid at one and one-half times the hourly rate of wage. All hours worked Monday through Saturday over twelve (12) hours and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

I. All hours worked on Sundays and holidays shall also be paid at double the hourly rate of wage.

J. The first two (2) hours after eight (8) regular hours Monday through Friday and the first ten (10) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked over ten (10) hours Monday through Saturday, Sundays and holidays shall be paid at double the hourly rate of wage.

K. All hours worked on Saturdays and Sundays shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid at double the hourly rate of wage.

M. All hours worked on Saturdays (except makeup days if work is lost due to inclement weather conditions) shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

N. All hours worked on Saturdays (except makeup days) shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. 1 Benefit Code Key – Effective 3/3/2019 thru 8/30/2019

Overtime Codes Continued

1. O. The first ten (10) hours worked on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays, holidays and after twelve (12) hours, Monday through Friday and after ten (10) hours on Saturday shall be paid at double the hourly rate of wage.

P. All hours worked on Saturdays (except makeup days if circumstances warrant) and Sundays shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid at double the hourly rate of wage.

Q. The first two (2) hours after eight (8) regular hours Monday through Friday and up to ten (10) hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked in excess of ten (10) hours per day Monday through Saturday and all hours worked on Sundays and holidays (except Christmas day) shall be paid at double the hourly rate of wage. All hours worked on Christmas day shall be paid at two and one-half times the hourly rate of wage.

R. All hours worked on Sundays and holidays shall be paid at two times the hourly rate of wage.

S. The first two (2) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays and all other overtime hours worked, except Labor Day, shall be paid at double the hourly rate of wage. All hours worked on Labor Day shall be paid at three times the hourly rate of wage.

U. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays (except Labor Day) shall be paid at two times the hourly rate of wage. All hours worked on Labor Day shall be paid at three times the hourly rate of wage.

V. All hours worked on Sundays and holidays (except Thanksgiving Day and Christmas day) shall be paid at one and one-half times the hourly rate of wage. All hours worked on Thanksgiving Day and Christmas day shall be paid at double the hourly rate of wage.

W. All hours worked on Saturdays and Sundays (except make-up days due to conditions beyond the control of the employer)) shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid at double the hourly rate of wage.

X. The first four (4) hours after eight (8) regular hours Monday through Friday and the first twelve (12) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked over twelve (12) hours Monday through Saturday, Sundays and holidays shall be paid at double the hourly rate of wage. When holiday falls on Saturday or Sunday, the day before Saturday, Friday, and the day after Sunday, Monday, shall be considered the holiday and all work performed shall be paid at double the hourly rate of wage.

Y. All hours worked outside the hours of 5:00 am and 5:00 pm (or such other hours as may be agreed upon by any employer and the employee) and all hours worked in excess of eight (8) hours per day (10 hours per day for a 4 x 10 workweek) and on Saturdays and holidays (except labor day) shall be paid at one and one-half times the hourly rate of wage. (except for employees who are absent from work without prior approval on a scheduled workday during the workweek shall be paid at the straight-time rate until they have worked 8 hours in a day (10 in a 4 x 10 workweek) or 40 hours during that workweek.) All hours worked Monday through Saturday over twelve (12) hours and all hours worked on Sundays and Labor Day shall be paid at double the hourly rate of wage.

Z. All hours worked on Saturdays and Sundays shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid the straight time rate of pay in addition to holiday pay.

2 Benefit Code Key – Effective 3/3/2019 thru 8/30/2019

Overtime Codes Continued

2. ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE.

B. All hours worked on holidays shall be paid at one and one-half times the hourly rate of wage.

C. All hours worked on Sundays shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid at two times the hourly rate of wage.

F. The first eight (8) hours worked on holidays shall be paid at the straight hourly rate of wage in addition to the holiday pay. All hours worked in excess of eight (8) hours on holidays shall be paid at double the hourly rate of wage.

G. All hours worked on Sunday shall be paid at two times the hourly rate of wage. All hours worked on paid holidays shall be paid at two and one-half times the hourly rate of wage including holiday pay.

H. All hours worked on Sunday shall be paid at two times the hourly rate of wage. All hours worked on holidays shall be paid at one and one-half times the hourly rate of wage.

O. All hours worked on Sundays and holidays shall be paid at one and one-half times the hourly rate of wage.

R. All hours worked on Sundays and holidays and all hours worked over sixty (60) in one week shall be paid at double the hourly rate of wage.

U. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked over 12 hours in a day or on Sundays and holidays shall be paid at double the hourly rate of wage.

W. The first two (2) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other hours worked Monday through Saturday, and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. On a four-day, ten- hour weekly schedule, either Monday thru Thursday or Tuesday thru Friday schedule, all hours worked after ten shall be paid at double the hourly rate of wage. The first eight (8) hours worked on the fifth day shall be paid at one and one-half times the hourly rate of wage. All other hours worked on the fifth, sixth, and seventh days and on holidays shall be paid at double the hourly rate of wage.

3. ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE.

A. Work performed in excess of eight (8) hours of straight time per day, or ten (10) hours of straight time per day when four ten (10) hour shifts are established, or forty (40) hours of straight time per week, Monday through Friday, or outside the normal shift, and all work on Saturdays shall be paid at time and one-half the straight time rate. Hours worked over twelve hours (12) in a single shift and all work performed after 6:00 pm Saturday to 6:00 am Monday and holidays shall be paid at double the straight time rate of pay. Any shift starting between the hours of 6:00 pm and midnight shall receive an additional one dollar ($1.00) per hour for all hours worked that shift. The employer shall have the sole discretion to assign overtime work to employees. Primary consideration for overtime work shall be given to employees regularly assigned to the work to be performed on overtime situations. After an employee has worked eight (8) hours at an applicable overtime rate, all additional hours shall be at the applicable overtime rate until such time as the employee has had a break of eight (8) hours or more.

C. Work performed in excess of eight (8) hours of straight time per day, or ten (10) hours of straight time per day when four ten (10) hour shifts are established, or forty (40) hours of straight time per week, Monday through Friday, or outside the normal shift, and all work on Saturdays shall be paid at one and one-half times the hourly rate of wage. All work performed after 6:00 pm Saturday to 5:00 am Monday and Holidays shall be paid at double the hourly rate of wage. After an employee has worked eight (8) hours at an applicable overtime rate, all additional hours shall be at the applicable overtime rate until such time as the employee has had a break of eight (8) hours or more.

3 Benefit Code Key – Effective 3/3/2019 thru 8/30/2019

Overtime Codes Continued

3. E. All hours worked Sundays and holidays shall be paid at double the hourly rate of wage. Each week, once 40 hours of straight time work is achieved, then any hours worked over 10 hours per day Monday through Saturday shall be paid at double the hourly wage rate.

F. All hours worked on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sunday shall be paid at two times the hourly rate of wage. All hours worked on paid holidays shall be paid at two and one-half times the hourly rate of wage including holiday pay.

H. All work performed on Sundays between March 16th and October 14th and all Holidays shall be compensated for at two (2) times the regular rate of pay. Work performed on Sundays between October 15th and March 15th shall be compensated at one and one half (1-1/2) times the regular rate of pay.

I. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. In the event the job is down due to weather conditions during a five day work week (Monday through Friday,) or a four day-ten hour work week (Tuesday through Friday,) then Saturday may be worked as a voluntary make-up day at the straight time rate. However, Saturday shall not be utilized as a make-up day when a holiday falls on Friday. All hours worked Monday through Saturday over twelve (12) hours and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

J. All hours worked between the hours of 10:00 pm and 5:00 am, Monday through Friday, and all hours worked on Saturdays shall be paid at a one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

K. Work performed in excess of eight (8) hours of straight time per day, or ten (10) hours of straight time per day when four ten (10) hour shifts are established, or forty (40) hours of straight time per week, Monday through Friday, or outside the normal 5 am to 6pm shift, and all work on Saturdays shall be paid at one and one-half times the hourly rate of wage. All work performed after 6:00 pm Saturday to 5:00 am Monday and Holidays, and all hours worked in excess of twelve (12) hours in a single shift shall be paid at double the hourly rate of wage.

After an employee has worked eight (8) hours at an applicable overtime rate, all additional hours shall be at the applicable overtime rate until such time as the employee has had a break of eight (8) hours or more. When an employee returns to work without at least eight (8) hours time off since their previous shift, all such time shall be a continuation of shift and paid at the applicable overtime rate until he/she shall have the eight (8) hours rest period.

4. ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE.

A. All hours worked in excess of eight (8) hours per day or forty (40) hours per week shall be paid at double the hourly rate of wage. All hours worked on Saturdays, Sundays and holidays shall be paid at double the hourly rate of wage.

B. All hours worked over twelve (12) hours per day and all hours worked on holidays shall be paid at double the hourly rate of wage.

C. On Monday through Friday, the first four (4) hours of overtime after eight (8) hours of straight time work shall be paid at one and one half (1-1/2) times the straight time rate of pay, unless a four (4) day ten (10) hour workweek has been established. On a four (4) day ten (10) hour workweek scheduled Monday through Thursday, or Tuesday through Friday, the first two (2) hours of overtime after ten (10) hours of straight time work shall be paid at one and one half (1-1/2) times the straight time rate of pay. On Saturday, the first twelve (12) hours of work shall be paid at one and one half (1-1/2) times the straight time rate of pay, except that if the job is down on Monday through Friday due to weather conditions or other conditions outside the control of the employer, the first ten (10) hours on Saturday may be worked at the straight time rate of pay. All hours worked over twelve (12) hours in a day and all hours worked on Sunday and Holidays shall be paid at two (2) times the straight time rate of pay.

4 Benefit Code Key – Effective 3/3/2019 thru 8/30/2019

Overtime Codes Continued

4. D. All hours worked in excess of eight (8) hours per day or forty (40) hours per week shall be paid at double the hourly rate of wage. All hours worked on Saturday, Sundays and holidays shall be paid at double the hourly rate of pay. Rates include all members of the assigned crew.

EXCEPTION: On all multipole structures and steel transmission lines, switching stations, regulating, capacitor stations, generating plants, industrial plants, associated installations and substations, except those substations whose primary function is to feed a distribution system, will be paid overtime under the following rates:

The first two (2) hours after eight (8) regular hours Monday through Friday of overtime on a regular workday, shall be paid at one and one-half times the hourly rate of wage. All hours in excess of ten (10) hours will be at two (2) times the hourly rate of wage. The first eight (8) hours worked on Saturday will be paid at one and one-half (1-1/2) times the hourly rate of wage. All hours worked in excess of eight (8) hours on Saturday, and all hours worked on Sundays and holidays will be at the double the hourly rate of wage.

All overtime eligible hours performed on the above described work that is energized, shall be paid at the double the hourly rate of wage.

E. The first two (2) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other hours worked Monday through Saturday, and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

On a four-day, ten-hour weekly schedule, either Monday thru Thursday or Tuesday thru Friday schedule, all hours worked after ten shall be paid at double the hourly rate of wage. The Monday or Friday not utilized in the normal four- day, ten hour work week, and Saturday shall be paid at one and one half (1½) times the regular shift rate for the first eight (8) hours. All other hours worked Monday through Saturday, and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

F. All hours worked between the hours of 6:00 pm and 6:00 am, Monday through Saturday, shall be paid at a premium rate of 20% over the hourly rate of wage. All hours worked on Sundays shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid at double the hourly rate of wage.

G. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked Monday through Saturday over twelve (12) hours and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

H. The first two (2) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other overtime hours worked, except Labor Day, and all hours on Sunday shall be paid at double the hourly rate of wage. All hours worked on Labor Day shall be paid at three times the hourly rate of wage.

I. The First eight (8) hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked in excess of eight (8) per day on Saturdays shall be paid at double the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

J. The first eight (8) hours worked on a Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked in excess of eight (8) hours on a Saturday shall be paid at double the hourly rate of wage. All hours worked over twelve (12) in a day, and all hours worked on Sundays and Holidays shall be paid at double the hourly rate of wage.

K. All hours worked on a Saturday shall be paid at one and one-half times the hourly rate of wage, so long as Saturday is the sixth consecutive day worked. All hours worked over twelve (12) in a day Monday through Saturday, and all hours worked on Sundays and Holidays shall be paid at double the hourly rate of wage.

5 Benefit Code Key – Effective 3/3/2019 thru 8/30/2019

4. L. The first twelve (12) hours worked on a Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked on a Saturday in excess of twelve (12) hours shall be paid at double the hourly rate of pay. All hours worked over twelve (12) in a day Monday through Friday, and all hours worked on Sundays shall be paid at double the hourly rate of wage. All hours worked on a holiday shall be paid at one and one-half times the hourly rate of wage, except that all hours worked on Labor Day shall be paid at double the hourly rate of pay.

M. All hours worked on Sunday and Holidays shall be paid at double the hourly rate. Any employee reporting to work less than nine (9) hours from their previous quitting time shall be paid for such time at time and one-half times the hourly rate.

N. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays, and all work performed between the hours of midnight (12:00 AM) and eight AM (8:00 AM) every day shall be paid at double the hourly rate of wage.

O. All hours worked between midnight Friday to midnight Sunday shall be paid at one and one-half the hourly rate of wage. After an employee has worked in excess of eight (8) continuous hours in any one or more calendar days, all additional hours shall be at the applicable overtime rate until such time as the employee has had a break of six (6) hours or more. All hours worked on Holidays shall be paid at double the hourly rate of wage.

P. All hours worked on Holidays shall be paid at one and one-half times the hourly rate of wage.

Q. The first four (4) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked over twelve (12) hours Monday through Saturday shall be paid at double the hourly rate. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

R. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage, so long as Saturday is the sixth consecutive day worked. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

S. All hours worked on Saturdays and Holidays shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays shall be paid at double the hourly rate of wage.

T. The first two (2) hours of overtime for hours worked Monday-Friday shall be paid at one and one-half times the hourly rate of wage. All hours worked in excess of ten (10) hours per day shall be paid at double the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. For work on Saturday which is scheduled prior to the end of shift on Friday, the first six (6) hours work shall be paid at one and one-half times the hourly rate of wage, and all hours over (6) shall be paid double the hourly rate of wage. For work on Saturday which was assigned following the close of shift on Friday, all work shall be paid at double the hourly rate of wage.

U. The first four (4) hours after eight (8) regular hours Monday through Friday and the first twelve (12) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. (Except on makeup days if work is lost due to inclement weather, then the first eight (8) hours on Saturday may be paid the regular rate.) All hours worked over twelve (12) hours Monday through Saturday, and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage.

Holiday Codes

5. A. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, and Christmas Day (7).

B. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, the day before Christmas, and Christmas Day (8). 6 Benefit Code Key – Effective 3/3/2019 thru 8/30/2019

Holiday Codes Continued

5. C. Holidays: New Year's Day, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (8).

D. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday and Saturday after Thanksgiving Day, And Christmas Day (8).

H. Holidays: New Year's Day, Memorial Day, Independence Day, Thanksgiving Day, the Day after Thanksgiving Day, And Christmas (6).

I. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day (6).

J. Holidays: New Year's Day, Memorial Day, Independence Day, Thanksgiving Day, Friday after Thanksgiving Day, Christmas Eve Day, And Christmas Day (7).

K. Holidays: New Year’s Day, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday After Thanksgiving Day, The Day Before Christmas, And Christmas Day (9).

L. Holidays: New Year’s Day, Martin Luther King Jr. Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, And Christmas Day (8).

N. Holidays: New Year's Day, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, The Friday After Thanksgiving Day, And Christmas Day (9).

P. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday And Saturday After Thanksgiving Day, The Day Before Christmas, And Christmas Day (9). If A Holiday Falls On Sunday, The Following Monday Shall Be Considered As A Holiday.

Q. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day (6).

R. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Day After Thanksgiving Day, One-Half Day Before Christmas Day, And Christmas Day. (7 1/2).

S. Paid Holidays: New Year's Day, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, And Christmas Day (7).

T. Paid Holidays: New Year's Day, Washington’s Birthday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, The Friday After Thanksgiving Day, Christmas Day, And The Day Before Or After Christmas (9).

Z. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (8).

6. A. Paid Holidays: New Year’s Day, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (8).

E. Paid Holidays: New Year's Day, Day Before Or After New Year's Day, Presidents Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, and a Half- 7 Benefit Code Key – Effective 3/3/2019 thru 8/30/2019

Day On Christmas Eve Day. (9 1/2).

Holiday Codes Continued

6. G. Paid Holidays: New Year's Day, Martin Luther King Jr. Day, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, and Christmas Eve Day (11).

H. Paid Holidays: New Year's Day, New Year’s Eve Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday After Thanksgiving Day, Christmas Day, The Day After Christmas, And A Floating Holiday (10). I. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday After Thanksgiving Day, And Christmas Day (7).

6. T. Paid Holidays: New Year's Day, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, The Friday After Thanksgiving Day, The Last Working Day Before Christmas Day, And Christmas Day (9).

Z. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, And Christmas Day (7). If a holiday falls on Saturday, the preceding Friday shall be considered as the holiday. If a holiday falls on Sunday, the following Monday shall be considered as the holiday.

7. A. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday and Saturday after Thanksgiving Day, And Christmas Day (8). Any Holiday Which Falls On A Sunday Shall Be Observed As A Holiday On The Following Monday. If any of the listed holidays falls on a Saturday, the preceding Friday shall be a regular work day.

B. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday and Saturday after Thanksgiving Day, And Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

C. Holidays: New Year's Day, Martin Luther King Jr. Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

D. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Veteran’s Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (8). Unpaid Holidays: President’s Day. Any paid holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any paid holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

E. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

F. Holidays: New Year’s Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, the last working day before Christmas day and Christmas day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

G. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day (6). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday.

8 Benefit Code Key – Effective 3/3/2019 thru 8/30/2019

Holiday Codes Continued

7. H. Holidays: New Year's Day, Martin Luther King Jr. Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, the Last Working Day before Christmas Day and Christmas Day (9). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

I. Holidays: New Year's Day, President’s Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day, The Friday After Thanksgiving Day, The Day Before Christmas Day And Christmas Day (9). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

J. Holidays: New Year's Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day and Christmas Day (6). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

K. Holidays: New Year's Day, Memorial Day, Independence Day, Thanksgiving Day, the Friday and Saturday after Thanksgiving Day, And Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

L. Holidays: New Year's Day, Memorial Day, Labor Day, Independence Day, Thanksgiving Day, the Last Work Day before Christmas Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

M. Paid Holidays: New Year's Day, The Day after or before New Year’s Day, President’s Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, And the Day after or before Christmas Day (10). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

N. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. When Christmas falls on a Saturday, the preceding Friday shall be observed as a holiday.

P. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday.

Q. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, the Last Working Day before Christmas Day and Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. If any of the listed holidays falls on a Saturday, the preceding Friday shall be a regular work day.

R. Paid Holidays: New Year's Day, the day after or before New Year’s Day, President’s Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, and the day after or before Christmas Day (10). If any of the listed holidays fall on Saturday, the preceding Friday shall be observed as the holiday. If any of the listed holidays falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated accordingly.

S. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, Christmas Day, the Day after Christmas, and A Floating Holiday (9). If any of the listed holidays falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated accordingly.

9 Benefit Code Key – Effective 3/3/2019 thru 8/30/2019

Holiday Codes Continued

7. T. Paid Holidays: New Year's Day, the Day after or before New Year’s Day, President’s Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, and The Day after or before Christmas Day. (10). If any of the listed holidays falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated accordingly. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

V. Holidays: New Year's Day, President’s Birthday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, the day before or after Christmas, and the day before or after New Year’s Day. If any of the above listed holidays falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated accordingly.

W. Holidays: New Year's Day, Day After New Year’s, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Eve Day, Christmas Day, the day after Christmas, the day before New Year’s Day, and a Floating Holiday.

X. Holidays: New Year's Day, Day before or after New Year’s Day, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, and the day before or after Christmas day. If a holiday falls on a Saturday or on a Friday that is the normal day off, then the holiday will be taken on the last normal workday. If the holiday falls on a Monday that is the normal day off or on a Sunday, then the holiday will be taken on the next normal workday.

Y. Holidays: New Year's Day, Presidents’ Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, and Christmas Day. (8) If the holiday falls on a Sunday, then the day observed by the federal government shall be considered a holiday and compensated accordingly.

Z. Holidays: New Year's Day, President’s Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day, The Friday After Thanksgiving Day, And Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday.

15. A. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, the day before Christmas Day and Christmas Day. (8) Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday.

B. Holidays: New Year's Day, Martin Luther King Jr. Day, President’s Day, Memorial Day, Independence Day, Labor Day, Veteran’s Day, Thanksgiving Day, and Christmas Day. (9)

C. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, the day before Christmas Day and Christmas Day. (8)

D Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, Christmas Day, and the day after Christmas.

10 Benefit Code Key – Effective 3/3/2019 thru 8/30/2019

Note Codes

8. D. Workers working with supplied air on hazmat projects receive an additional $1.00 per hour.

L. Workers on hazmat projects receive additional hourly premiums as follows -Level A: $0.75, Level B: $0.50, And Level C: $0.25.

M. Workers on hazmat projects receive additional hourly premiums as follows: Levels A & B: $1.00, Levels C & D: $0.50.

N. Workers on hazmat projects receive additional hourly premiums as follows -Level A: $1.00, Level B: $0.75, Level C: $0.50, And Level D: $0.25.

P. Workers on hazmat projects receive additional hourly premiums as follows -Class A Suit: $2.00, Class B Suit: $1.50, Class C Suit: $1.00, And Class D Suit $0.50.

Q. The highest pressure registered on the gauge for an accumulated time of more than fifteen (15) minutes during the shift shall be used in determining the scale paid.

R. Effective August 31, 2012 – A Traffic Control Supervisor shall be present on the project whenever flagging or spotting or other traffic control labor is being utilized. A Traffic Control Laborer performs the setup, maintenance and removal of all temporary traffic control devices and construction signs necessary to control vehicular, bicycle, and pedestrian traffic during construction operations. Flaggers and Spotters shall be posted where shown on approved Traffic Control Plans or where directed by the Engineer. All flaggers and spotters shall possess a current flagging card issued by the State of Washington, Oregon, Montana, or Idaho. These classifications are only effective on or after August 31, 2012.

S. Effective August 31, 2012 – A Traffic Control Supervisor shall be present on the project whenever flagging or spotting or other traffic control labor is being utilized. Flaggers and Spotters shall be posted where shown on approved Traffic Control Plans or where directed by the Engineer. All flaggers and spotters shall possess a current flagging card issued by the State of Washington, Oregon, Montana, or Idaho. This classification is only effective on or after August 31, 2012.

T. Effective August 31, 2012 – A Traffic Control Laborer performs the setup, maintenance and removal of all temporary traffic control devices and construction signs necessary to control vehicular, bicycle, and pedestrian traffic during construction operations. Flaggers and Spotters shall be posted where shown on approved Traffic Control Plans or where directed by the Engineer. All flaggers and spotters shall possess a current flagging card issued by the State of Washington, Oregon, Montana, or Idaho. This classification is only effective on or after August 31, 2012.

U. Workers on hazmat projects receive additional hourly premiums as follows – Class A Suit: $2.00, Class B Suit: $1.50, And Class C Suit: $1.00. Workers performing underground work receive an additional $0.40 per hour for any and all work performed underground, including operating, servicing and repairing of equipment. The premium for underground work shall be paid for the entire shift worked. Workers who work suspended by a rope or cable receive an additional $0.50 per hour. The premium for work suspended shall be paid for the entire shift worked. Workers who do “pioneer” work (break open a cut, build road, etc.) more than one hundred fifty (150) feet above grade elevation receive an additional $0.50 per hour.

11 Benefit Code Key – Effective 3/3/2019 thru 8/30/2019

Note Codes Continued

8. V. In addition to the hourly wage and fringe benefits, the following depth and enclosure premiums shall be paid. The premiums are to be calculated for the maximum depth and distance into an enclosure that a diver reaches in a day. The premiums are to be paid one time for the day and are not used in calculating overtime pay.

Depth premiums apply to depths of fifty feet or more. Over 50' to 100' - $2.00 per foot for each foot over 50 feet. Over 101' to 150' - $3.00 per foot for each foot over 101 feet. Over 151' to 220' - $4.00 per foot for each foot over 220 feet. Over 221' - $5.00 per foot for each foot over 221 feet.

Enclosure premiums apply when divers enter enclosures (such as pipes or tunnels) where there is no vertical ascent and is measured by the distance travelled from the entrance. 25’ to 300’ - $1.00 per foot from entrance. 300’ to 600’ - $1.50 per foot beginning at 300’. Over 600’ - $2.00 per foot beginning at 600’.

W. Meter Installers work on single phase 120/240V self-contained residential meters. The Lineman/Groundmen rates would apply to meters not fitting this description.

X. Workers on hazmat projects receive additional hourly premiums as follows - Class A Suit: $2.00, Class B Suit: $1.50, Class C Suit: $1.00, and Class D Suit: $0.50. Special Shift Premium: Basic hourly rate plus $2.00 per hour.

When due to conditions beyond the control of the Employer or when an owner (not acting as the contractor), a government agency or the contract specifications requires that work can only be performed outside the normal 5 am to 6pm shift, then the special shift premium will be applied to the basic hourly rate. When an employee works on a special shift, they shall be paid a special shift premium for each hour worked unless they are in OT or Double-time status. (For example, the special shift premium does not waive the overtime requirements for work performed on Saturday or Sunday.)

12

APPENDIX C Construction Contract and Contract Bond-Informational Only

CONSTRUCTION CONTRACT AGREEMENT

THIS AGREEMENT, effective upon the date of mutual execution, is made and entered into between Skagit County, Washington, and ______, hereinafter called the Contractor.

WITNESSETH: That in consideration of the terms and conditions contained herein and attached and made a part of this agreement, the parties hereto covenant and agree as follows:

I. The Contractor shall do all work and furnish all tools, materials, equipment, and transportation required for the construction of HMA Overlay Project (2019) #ESHMA19-1 in accordance with and as described in the attached plans and specifications and the Washington State Department of Transportation Standard Specifications for Road, Bridge, and Municipal Construction M 41-10 2018 edition, which are by this reference incorporated herein and made a part hereof, and shall perform any changes to the work in accord with the Contract Documents.

II. The Contractor shall provide and bear the expense of all equipment, work, and labor of any sort whatsoever that may be required for the transfer of materials and for constructing and completing the work provided for in this contract and every part thereof and shall guarantee said materials and work for a period of one year after substantial completion of this contract, except as may be modified by the plans, specifications and/or contract documents.

III. Skagit County, Washington, hereby promises and agrees with the Contractor to retain and does retain the Contractor to provide the materials and to do and cause to be done the above- described work and to complete and finish the same according to the attached plans and specifications and the terms and conditions herein contained, and hereby contracts to pay for the same according to the attached specifications and the schedule of prices bid and hereto attached, at the time and in the manner and upon the conditions provided for in this contract.

IV. The Contractor for himself/herself, and for his/her heirs, executors, administrators, successors, and assigns, does hereby agree to full performance of all covenants required of the Contractor in the contract.

V. It is further provided that no liability shall attach to Skagit County by reason of entering into this contract, except as provided herein.

IN WITNESS WHEREOF the Contractor has executed this instrument on the day and year first below written, and the Authorized Official has caused this instrument to be executed by and in the name of Skagit County the day and year first above written.

CONTRACTOR

Signature ______Mailing Address:

Printed ______

Title ______

Date ______Telephone No. (___) ____-____

DATED this _____ day of ______, 2019.

BOARD OF COUNTY COMMISSIONERS SKAGIT COUNTY, WASHINGTON

Lisa Janicki, Chair

Ron Wesen, Commissioner

Kenneth A. Dahlstedt, Commissioner

Attest:

Clerk of the Board For contracts under $5,000: Authorization per Resolution R20030146

Recommended: County Administrator

Department Head

Approved as to form:

Civil Deputy Prosecuting Attorney

Approved as to indemnification:

Risk Manager

Approved as to budget:

Budget & Finance Director

CONTRACT BOND

KNOW ALL MEN BY THESE PRESENTS, that Skagit County, a Municipal Corporation of Washington, has awarded ______of ______, as Principal, and ______as Surety, are jointly and severally held and bound unto the County of Skagit in the penal sum of ______($______), dollars, for the payment of which we jointly and severely bind ourselves, our heirs, executors, administrators, and assigns, and successors and assigns, firmly by these presents.

THE CONDITION of this bond is such that whereas, on the ______day of ______A.D., 2019, the said Principal, herein, executed a certain contract with the County of Skagit by the items, conditions and provisions of which contract the said ______, Principal, herein agree to furnish all material and do certain work, to wit: That ______will undertake and complete the construction of

HMA OVERLAY PROJECT (2019) #ESHMA19-1

according to the maps, plans and specifications made a part of said contract, which contract as so executed, is hereunto attached, is now referred to and by reference is incorporated herein and made a part hereof as fully for all purposes as if here set forth at length. The bond shall cover all approved change orders as if they were in the original contract.

NOW, THEREFORE, if the Principal herein shall faithfully and truly observe and comply with the terms, conditions and provisions of said contract in all respects and shall well and truly and fully do and perform all matters and things by ______(principal) undertaken to be performed under said contract, upon the terms proposed therein, and within the time prescribed therein, and until the same is accepted, and shall pay all laborers, mechanics, subcontractors and material men, and all persons who shall supply such contractor or subcontractor with provisions and supplies for the carrying on of such work, and shall in all respects faithfully perform said contract according to law, then this obligation to be void, otherwise to remain in full force and effect.

WITNESS our hands this ______day of ______, 2019.

______

______

______(Principal)

______

______

______Attorney-in-Fact, Surety

______Name and Address Local Office of Agent

APPROVED AS TO FORM APPROVED AS TO FORM RICH WEYRICH JESSICA NEIL HOYSON Skagit County Prosecuting Attorney Skagit County Risk Manager

BY: ______Approving Authority

DATE: ______, 2019

______SURETY BOND NUMBER CONTRACT NUMBER

______

APPENDIX D Proposal Forms-Informational Only

Proposal for Bidding Purposes

For Construction of: ONLY

HMA OVERLAY PROJECT (2019) #ESHMA19-1

SKAGIT COUNTY PUBLIC WORKS

INFORMATIONAL SKAGIT COUNTY Public Works Department 1800 Continental Place Mount Vernon, WA 98273

PROPOSAL

HMA OVERLAY PROJECT (2019) #ESHMA19-1

All bid envelopes must be plainly marked on the outside, “Sealed Bid, HMA Overlay Project (2019) #ESHMA19-1

Sealed Bids will be received at the following location before the specified time:

Bids may be hand delivered to: The Reception Desk of Skagit County Commissioners Office, located at 1800 Continental Place, Mount Vernon, WA.

Bids may be mailed to: Skagit County Commissioners 1800 Continental Place, Suite 100 Mount Vernon, Washington, 98273

The bid opening date for this project will be Monday, August 8, 2019. The bids will be publicly opened and read after 2:00 p.m. on this date.

Bid Advertisement: Skagit Valley Herald – July 25 and August 1, 2019

ENTIRE PROPOSAL TO BE RETURNED AS YOUR BID PACKAGE

FAILURE TO SIGN OR COMPLETE ALL INFORMATION ON THE FORMS PROVIDED CAN RESULT IN REJECTION OF THE PROPOSAL AS NON-RESPONSIVE INFORMATIONAL ONLY

HMA Overlay Project (2019) Skagit County Project #ESHMA19-1 July 2019 1 of 11 PROPOSAL

BOARD OF SKAGIT COUNTY COMMISSIONERS MOUNT VERNON, WASHINGTON 98273

Attention:

This certifies that the undersigned has examined the locations of:

HMA OVERLAY PROJECT (2019) #ESHMA19-1 and that the plans, specifications and contract governing the work embraced in this improvement, and the method by which payment will be made for said work is understood. The undersigned hereby proposes to undertake and complete the work embraced in this improvement, or as much thereof as can be completed with the money available in accordance with the said plans, specifications, and contract, and the following schedule of rates and prices:

Note: for work performed on this project the contractor should refer to Section 1-07.2(1) of the contract provisions and Department of Revenue Rule #171.

(Note: Unit prices for all items, all extensions, and total amount of bid shall be shown. All entries must be typed or entered in ink.)

HMA OVERLAY PROJECT (2019) #ESHMA19-1

Item Unit of Description Spec QTY No. Measure Unit Price Total Price

Schedule A: McLean Road

A-1 MOBILIZATION 1-09.7 1.00 LS $______.___ $______.___

A-2 ROADWAY SURVEYING 1-05.4 1.00 LS $______.___ $______.___

A-3 SPCC PLAN 1-07.15(1) 1.00 LS $______.___ $______.___

UNANTICIPATED SITE A-4 1-09.6 SP EST DOL WORKINFORMATIONAL $______ONLY1.00_ $______2,500.00_

OTHER TEMPORARY A-5 1-10.5(2) 1.00 LS TRAFFIC CONTROL $______.___ $______.___

HMA Overlay Project (2019) Skagit County Project #ESHMA19-1 July 2019 2 of 11 Item Unit of Description Spec QTY No. Measure Unit Price Total Price

TRAFFIC CONTROL A-6 1-10.5(2) 1.00 LS SUPERVISOR $______.___ $______.___

CONSTRUCTION SIGNS A-7 1-10.5(2) 704.00 SF CLASS A $______.___ $______.___

TRAFFIC CONTROL A-8 1-10.5(2)SP 850.00 HR LABOR $______.___ $______.___

TRIMMING AND A-9 2-11.5 1.00 LS CLEANUP $______.___ $______.___

CRUSHED SURFACING A-10 5-04.3(5)E 3,570.00 TON BASE COURSE $______.___ $______.___

PAVEMENT REPAIR A-11 EXCAVATION INCL. 5-04.5 11,583.00 SY $______.___ $______.___ HAUL

PLANING BITUMINOUS A-12 5-04.5 SP 38,410.00 SY PAVEMENT $______.___ $______.___

HMA FOR PAVEMENT A-13 REPAIR CL. 3/8 IN. 5-04.5 2,770.00 TON $______.___ $______.___ PG-58H-22

A-14 HMA CL. 3/8” PG 58H-22 5-04.5 SP 5,190.00 TON $______.___ $______.___

A-15 ESC LEAD 8-01.5 17 DAY $______.___ $______.___

A-16 INLET PROTECTION 8-01.5 5 EA $______.___ $______.___

EROSION/WATER A-17 8-01.5 SP 1 LS POLLUTIONINFORMATIONAL CONTROL $______ONLY .___ $______.___ PLASTIC CROSSWALK A-18 8-22.5 240.00 SF LINE $______.___ $______.___

HMA Overlay Project (2019) Skagit County Project #ESHMA19-1 July 2019 3 of 11 Item Unit of Description Spec QTY No. Measure Unit Price Total Price

A-19 PLASTIC STOP LINE 8-22.5 196.00 LF $______.___ $______.___

TEMPORARY A-20 PAVEMENT MARKING – 8-23.5 47,310.00 LF $______.___ $______.___ SHORT DURATION

Subtotal Schedule A $______.___

Item Unit of Description Spec QTY No. Measure Unit Price Total Price

Schedule B: Cook Road

B-1 MOBILIZATION 1-09.7 1.00 LS $______.___ $______.___

B-2 ROADWAY SURVEYING 1-05.4 1.00 LS $______.___ $______.___

B-3 SPCC PLAN 1-07.15(1) 1.00 LS $______.___ $______.___

UNANTICIPATED SITE B-4 1-09.6 SP EST DOL WORK $______1.00_ $______2,500.00_

B-5 OTHER TEMPORARY 1-10.5(2) 1.00 LS TRAFFIC CONTROL $______.___ $______.___

TRAFFIC CONTROL B-6 INFORMATIONAL1-10.5(2) 1.00 LS ONLY SUPERVISOR $______.___ $______.___

CONSTRUCTION SIGNS B-7 1-10.5(2) 496.00 SF CLASS A $______.___ $______.___

HMA Overlay Project (2019) Skagit County Project #ESHMA19-1 July 2019 4 of 11 Item Unit of Description Spec QTY No. Measure Unit Price Total Price

TRAFFIC CONTROL B-8 1-10.5(2) 550.00 HR LABOR $______.___ $______.___

TRIMMING AND B-9 2-11.5 1.00 LS CLEANUP $______.___ $______.___

CRUSHED SURFACING B-10 5-04.3(5)E 290.00 TON BASE COURSE $______.___ $______.___

PAVEMENT REPAIR B-11 EXCAVATION INCL. 5-04.5 932.00 SY $______.___ $______.___ HAUL

PLANING BITUMINOUS B-12 5-04.5 SP 1,640.00 SY PAVEMENT $______.___ $______.___

HMA FOR PAVEMENT B-13 REPAIR CL. 3/8 IN. 5-04.5 220.00 TON $______.___ $______.___ PG 58H-22

B-14 HMA CL. 3/8” PG 58H-22 5-04.5 SP 300.00 TON $______.___ $______.___

B-15 ESC LEAD 8-01.5 8.00 DAY $______.___ $______.___

B-16 INLET PROTECTION 8-01.5 2.00 EA $______.___ $______.___

EROSION/WATER B-17 8-01.5 SP 1.00 LS POLLUTION CONTROL $______.___ $______.___

TRAFFIC SIGNAL B-18 8-20.5 1.00 LS SYSTEM $______.___ $______.___

B-19 PLASTIC LINE 8-22.5 2,120.00 LF INFORMATIONAL$______ONLY .___ $______.___ PLASTIC WIDE LANE B-20 8-22.5 160.00 LF LINE $______.___ $______.___

HMA Overlay Project (2019) Skagit County Project #ESHMA19-1 July 2019 5 of 11 Item Unit of Description Spec QTY No. Measure Unit Price Total Price

B-21 PLASTIC STOP LINE 8-22.5 86.00 LF $______.___ $______.___

PLASTIC TRAFFIC B-22 8-22.5 3.00 EA ARROW $______.___ $______.___

TEMPORARY B-23 PAVEMENT MARKING – 8-23.5 2,650.00 LF $______.___ $______.___ SHORT DURATION

Subtotal Schedule B $______.___

TOTAL BID $______.___

FOR WORK PERFORMED ON THIS PROJECT THE CONTRACTOR SHOULD REFER TO SECTION 1-07.2(1) OF THE CONTRACT PROVISIONS AND DEPARTMENT OF REVENUE RULE #171.

INFORMATIONAL ONLY

HMA Overlay Project (2019) Skagit County Project #ESHMA19-1 July 2019 6 of 11 PROPOSAL – Signature Page

The bidder is hereby advised that by signature of this proposal he/she is deemed to have acknowledged all requirements and signed all certificates contained herein.

The undersigned hereby agrees to pay labor not less than the prevailing rates of wages in accordance with the requirements of the special provisions for this project.

A proposal guaranty in an amount of five percent (5%) of the total bid based upon the approximate estimate of quantities at the above prices and in the form as indicated below is attached hereto:

CASHIER’S CHECK In the amount of $______Dollars

CERTIFIED CHECK In the amount of $______Dollars (Payable to Skagit County) PROPOSAL BOND In the amount five percent (5%) of the total bid.

Receipt is hereby acknowledged of Addendum(s) No. (s) , , &

Signature of Authorized Officials(s):

Proposal Must Be Signed

PRINT NAME

Firm Name:

Address:

Telephone No.:

State of Washington Contractor’s License No. UBI No. Employment Security Department No.

Note: (1) This proposal form is not transferable and any alteration of the firm’s name entered hereon without prior permission from the Skagit County will be cause for considering the proposal irregular and subsequent rejection of the bid. (2) Please refer to Section 1-02.6 of the Standard Specifications, “Preparation of Proposal”, or “Article 4” of the InstructionINFORMATIONAL to Bidders for building construction jobs. ONLY BID PROPOSAL MUST BE SIGNED.

FAILURE TO SIGN OR COMPLETE ALL INFORMATION CAN RESULT IN REJECTION OF THE PROPOSAL AS NON-RESPONSIVE.

HMA Overlay Project (2019) Skagit County Project #ESHMA19-1 July 2019 7 of 11

SUBMIT THE ENCLOSED PROPOSAL BOND FORM WITH YOUR PROPOSAL

USE OF OTHER FORMS MAY SUBJECT YOUR BID TO REJECTION

INFORMATIONAL ONLY

HMA Overlay Project (2019) Skagit County Project #ESHMA19-1 July 2019 8 of 11 PROPOSAL BOND

KNOW ALL MEN BY THESE PRESENTS, That we, ______of ______as principal, and the ______a corporation duly organized under the laws of the State of ______, and authorized to do business in the State of Washington, as surety, are held and firmly bound unto Skagit County in the full and penal sum of five (5) percent of the total amount of the bid proposal of said principal for the work hereinafter described for the payment of which, well and truly to be made, we bind our heirs, executors, administrators and assigns, and successors and assigns, firmly by these presents.

The condition of this bond is such, that whereas the principal herein is herewith submitting his or its sealed proposal for the following highway construction, to wit:

HMA Overlay Project (2019) #ESHMA19-1 said bid and proposal, by reference thereto, being made a part hereof.

NOW THEREFORE, If the said proposal bid by said principal be accepted, and the contract be awarded to said principal, and if said principal shall duly make and enter into and execute said contract and shall furnish bond as required by Skagit County within a period of twenty (20) days from and after said award, exclusive of the day of such award, then this obligation shall be null and void, otherwise it shall remain and be in full force and effect.

IN TESTIMONY WHEREOF, The principal and surety have caused these presents to be signed and sealed this ______day of ______, 2019.

______

______(Principal)

INFORMATIONAL ONLY_ (Surety) (Attorney-in-fact)

HMA Overlay Project (2019) Skagit County Project #ESHMA19-1 July 2019 9 of 11 Failure to return this Declaration as part of the bid proposal package will make the bid nonresponsive and ineligible for award.

NON-COLLUSION DECLARATION

I, by signing the proposal, hereby declare, under penalty of perjury under the laws of the United States that the following statements are true and correct:

1. That the undersigned person(s), firm, association or corporation has (have) not, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in connection with the project for which this proposal is submitted. 2. That by signing the signature page of this proposal, I am deemed to have signed and to have agreed to the provisions of this declaration.

NOTICE TO ALL BIDDERS

To report rigging activities call:

1-800-424-9071

The U.S. Department of Transportation (USDOT) operates the above toll-free “hotline” Monday through Friday, 8:00 a.m. to 5:00 p.m., eastern time. Anyone with knowledge of possible bid rigging, bidder collusion, or other fraudulent activities should use the “hotline” to report such activities.

The “hotline” is part of USDOT’s continuing effort to identify and investigate highway construction contract fraud and abuse and is operated under the direction of the USDOT Inspector General. All information will be treated confidentially and caller anonymity will be respected. INFORMATIONAL ONLY

SR DOT Form 272-036I EF 07/2011 10 of 11 Certification of Compliance with Wage Payment Statutes

The bidder hereby certifies that, within the three-year period immediately preceding the bid solicitation date (July 25, 2018), the bidder is not a “willful” violator, as defined in RCW 49.48.082, of any provision of chapters 49.46, 49.48, or 49.52 RCW, as determined by a final and binding citation and notice of assessment issued by the Department of Labor and Industries or through a civil judgment entered by a court of limited or general jurisdiction.

I certify under penalty of perjury under the laws of the State of Washington that the foregoing is true and correct.

Bidder’s Business Name

Signature of Authorized Official*

Printed Name

Title

Date City State

Check One: Sole Proprietorship ☐ Partnership ☐ Joint Venture ☐ Corporation ☐

State of Incorporation, or if not a corporation, State where business entity was formed: INFORMATIONAL ONLY If a co-partnership, give firm name under which business is transacted:

* If a corporation, proposal must be executed in the corporate name by the president or vice-president (or any other corporate officer accompanied by evidence of authority to sign). If a co-partnership, proposal must be executed by a partner.

11 of 11

APPENDIX E Vicinity Map and Plans