IEE: SRI: Dry Zone Urban Water and Sanitation Project

Total Page:16

File Type:pdf, Size:1020Kb

IEE: SRI: Dry Zone Urban Water and Sanitation Project Initial Environmental Examination Report Project Number: 37381-013 November 2012 Sri Lanka: DRY ZONE URBAN WATER AND SANITATION PROJECT - for Puttalam Water and Sanitation System Prepared by Project Management Unit for Dry Zone Urban Water and Sanitation Project, Colombo, Sri Lanka. For Water Supply and Drainage Board Ministry of Water Supply and Drainage, Sri Lanka. This report has been submitted to ADB by the Ministry of Water Supply and Drainage and is made publicly available in accordance with ADB’s public communications policy (2005). It does not necessarily reflect the views of ADB. I. INTRODUCTION A. Purpose of the Report The Dry Zone Urban Water and Sanitation Program (DZUWSP) is intended to facilitate sustainable development in disadvantaged districts in Sri Lanka. This will be achieved by investing in priority water supply and sanitation infrastructure in selected urban areas. Assistance will be targeted in those parts of the Northern and North-Western Provinces with the most acute shortages of drinking water and sanitation. Chosen urban areas are the towns of Mannar, Vavuniya, Puttalam and Chilaw. DZUWSP will be implemented over five years beginning in early 2009, and will be supported by ADB through a project loan and grant. The Ministry of Water Supply and Drainage (MWSD) is the Executing Agency (EA) for the program and NWSDB is the Implementing Agency (IA). DZUWSP will improve infrastructure through the development, design and implementation of subprojects in water supply and sanitation in each town. The Project has been classified by ADB as environmental assessment category B, where the component requiring greater attention is the Vavuniya water supply subproject (a 10.5 m high dam and 237 ha storage reservoir). The impacts of providing infrastructure in the four urban areas were assessed by four Initial Environmental Examination (IEE) reports (one for each location). For Vavuniya an Environmental Management Plan for the storage reservoir and a detailed Environmental Monitoring plan (EnvMoP) for the other less sensitive sub-components have been prepared. In the other three towns, where impacts will be less significant, and detailed Environmental Monitoring Plans have been prepared. Studies were conducted according to ADB Environment Policy (2002) and Environmental Assessment Guidelines (2003) and this document is the IEE report for Puttalam. B. Extent of IEE study 4Sri Lankan law and ADB policy require that the environmental impacts of development projects are identified and assessed as part of the planning and design process, and that action is taken to reduce those impacts to acceptable levels. This is done through the environmental assessment process, which has become an integral part of lending operations and project development and implementation worldwide. 1. ADB Policy ADB’s Environment Policy requires the consideration of environmental issues in all aspects of the Bank’s operations, and the requirements for Environmental Assessment are described in Operations Manual (OM) 20: Environmental Considerations in ADB Operations. This states that ADB requires environmental assessment of all project loans, program loans, sector loans, sector development program loans, financial intermediation loans and private sector investment operations. The nature of the assessment required for a project depends on the significance of its environmental impacts, which are related to the type and location of the project, the sensitivity, scale, nature and magnitude of its potential impacts, and the availability of cost-effective 1 mitigation measures. Projects are screened for their expected environmental impacts and are assigned to one of the following categories: Category A: Projects that could have significant environmental impacts. An Environmental Impact Assessment (EIA) is required. Category B: Projects that could have some adverse environmental impacts, but of less significance than those for category A. An Initial Environmental Examination (IEE) is required to determine whether significant impacts warranting an EIA are likely. If an EIA is not needed, the IEE is regarded as the final environmental assessment report. A Category B project may be classified as B-sensitive if it involves 1 environmentally sensitive activities . Such projects require IEE, but have the same requirements for disclosure and Environmental Management Plans as Category A. Category C: Projects that are unlikely to have adverse environmental impacts. No EIA or IEE is required, although environmental implications are reviewed. The Bank has classed this project as Category B and following normal procedure for project loans, one IEE was conducted for each urban area, covering all proposed subprojects in the town. A subproject comprises the infrastructure improvements in a particular sector (water supply or sewerage/sanitation). 2. National Law The requirement for Environmental Assessment in Sri Lanka is established by the National Environment Act (1981), and the procedures are defined in the EIA Regulations (1993). The regulations specify activities for which environmental assessment is mandatory, and those that could occur within certain DZUWSP subprojects are as follows: 3 2 Groundwater extraction of over 500,000 m /day ; 3 2 A Water Treatment Plant with a capacity of over 500,000 m /day ; 3 Laying more than 1 km of pipes ; Projects that involve relocation of more than 100 people; and Projects that fall within sensitive area(s). Sensitive areas are defined in the EIA Regulations as: Any erodable area declared under the Soil Conservation Act (1951, 1953); Any Flood Area declared under the Flood Protection Ordinance (1924, 1955) and any Flood Protection Area declared under the Sri Lanka Land Reclamation and Development Corporation Act (1968, 1982); Any reservation beyond the Full Supply Level of a reservoir; 1 A project may be deemed environmentally sensitive by ADB if it is near environmentally 2 sensitive areas, or involves: deforestation or loss of biodiversity; involuntary resettlement issues; processing, handling and disposal of toxic and hazardous substances; or other environmentally sensitive activities that also may be of concern to a wide group of external stakeholders. 2 The Central Environment Authority is currently considering a proposal to lower these limits to 3 500 m /day. 3 This applies to wastewater projects but not water supply. Any archaeological reserve, ancient or protected monument as defined or declared under the Antiquities Ordinance (1965); Any area declared under the Botanic Gardens Ordinance (1928, 1973); Areas within, or less than 100 m from the boundaries of, any area declared under the National Heritage and Wilderness Act (1988): the Forest Ordinance; Areas within, or less than 100 m from the boundaries of, any area declared as a Sanctuary under the Fauna and Flora Protection Ordinance (1937); Areas within, or less than 100 m from the high flood level contour of, a public lake as defined by the Crown Lands Ordinance (1947, 1949, 1956) including those declared under Section 71 of the Ordinance; Areas 60 m or less from the bank of a public stream as defined in the Crown Lands Ordinance, with a width of more than 25 m at any point. The requirement for EIA and the level of study required are determined by the Provincial 4 Environment Authority (PEA) after submission by the proponent of a Project Information Document (PID), plus supporting information if relevant. There are two possible outcomes: Categorical Exclusion: the activity is not on the list of prescribed projects in the EIA regulations, is not in or near a sensitive area, has not been the subject of public protest, and it is clear from the PID and supporting information that the project will have no significant environmental impacts. Environmental Clearance is granted (with or without conditions) and the project may proceed; 4 All other projects require Environmental Assessment and the CEA or PEA establishes a Scoping Committee to decide on the level of study (IEE or EIA) and prepare Terms of Reference (ToR). Alternatively, if the project lies wholly within the jurisdiction of a single Government agency (eg UDA) CEA/PEA may refer the project to this authority (as the Project Approving Agency) to administer the EIA process. A Technical Review Committee reviews the completed IEE or EIA report and recommends whether Environmental Clearance should be granted. The final decision is made by CEA. The urban areas selected under this program have populations of between 40,000 and 120,000, so the infrastructure subprojects are relatively small, and groundwater abstraction and water treatment will not be of the scale quoted in the EIA regulations as requiring environmental 3 assessment. Components will not be located in protected or sensitive areas and no people will be relocated. However two of the water supply subprojects (Chilaw and Vavuniya) involve the construction of structures across a river or stream to impound water, which is considered as a prescribed activity under the National Environmental Act/Provincial Environmental Act (NEA/PEA), and will thus require an EIA/IEE. Furthermore, if during detailed designs the location of proposed tube wells for the Mannar water supply scheme is within or 100 m away from the Giants Tank Sanctuary, this too would be considered as a prescribed activity and would require an EIA/IEE.The regulations may also apply to the other urban water supply 4 In the North-Western Province (which includes Chilaw and Puttalam)
Recommended publications
  • Ensuring Sustainability in Sri Lanka's Growing Hotel Industry
    Ensuring Sustainability in Sri Lanka’s Growing Hotel Industry 2013 IFC Disclaimer “This publication may contain advice, opinions, and statements of various information providers and content providers. IFC does not represent or endorse the accuracy or reliability of any advice, opinion, statement or other information provided by any information provider or content provider, or any user of this publication or other person or entity.” Prepared on behalf of IFC - World Bank Group by PricewaterhouseCoopers (Private) Limited, Sri Lanka and PricewaterhouseCoopers (Private) Limited, India Table of Contents 01 The Sri Lankan Hotel Industry - An Overview 05 1.1. Tourism in Sri Lanka’s Economy 05 1.2. Classification of Tourist Accommodation 06 1.3. Tourist Hotels 07 02 Sri Lanka’s Highly Diverse Hotel Industry 10 2.1. Boutique Villas and Hotels 12 Over 100 New Hotels 2.2. Guesthouses 12 03 2.3. Tourist Hotels 13 15 Under Construction 2.4. Home Stay Units / Bungalows / 14 3.1. Boutique Villas and Hotels - 16 Rented Homes and Apartments Under Construction 3.2. Guesthouses - Under Construction 17 3.3. Tourist Hotels - Under Construction 17 3.4. Resorts - Under-construction 18 04 Resource Utilization in Sri Lanka - An Overview 19 Resource Utilization in Sri 4.1. Power and Energy Sector 19 05 4.2. Power Sector 21 Lankan Hotels 27 4.3. Water Sector 24 5.1. Energy and Water Consumption 28 4.4. Solid Waste Generation 25 5.2. Waste Generation and Management 30 5.3. Resource Efficiency Potential 31 5.4. Resource Efficiency Measures Taken by a 32 Few Sri Lankan Hotels 5.5.
    [Show full text]
  • Spatial Dimensions of Conflict-Induced Internally Displaced Population in the Puttalam District of Sri Lanka from 1980 to 2012 Deepthi Lekani Waidyasekera
    University of North Dakota UND Scholarly Commons Theses and Dissertations Theses, Dissertations, and Senior Projects 12-1-2012 Spatial Dimensions of Conflict-Induced Internally Displaced Population in the Puttalam District of Sri Lanka from 1980 to 2012 Deepthi Lekani Waidyasekera Follow this and additional works at: https://commons.und.edu/theses Recommended Citation Waidyasekera, Deepthi Lekani, "Spatial Dimensions of Conflict-Induced Internally Displaced Population in the Puttalam District of Sri Lanka from 1980 to 2012" (2012). Theses and Dissertations. 668. https://commons.und.edu/theses/668 This Thesis is brought to you for free and open access by the Theses, Dissertations, and Senior Projects at UND Scholarly Commons. It has been accepted for inclusion in Theses and Dissertations by an authorized administrator of UND Scholarly Commons. For more information, please contact [email protected]. SPATIAL DIMENSIONS OF CONFLICT-INDUCED INTERNALLY DISPLACED POPULATION IN THE PUTTALAM DISTRICT OF SRI LANKA FROM 1980 TO 2012 by Deepthi Lekani Waidyasekera Bachelor of Arts, University of Sri Jayawardanapura,, Sri Lanka, 1986 Master of Science, University of Moratuwa, Sri Lanka, 2001 A Thesis Submitted to the Graduate Faculty of the University of North Dakota In partial fulfilment of the requirements For the degree of Master of Arts Grand Forks, North Dakota December 2012 Copyright 2012 Deepthi Lekani Waidyasekera ii PERMISSION Title Spatial Dimensions of Conflict-Induced Internally Displaced Population in the Puttalam District of Sri Lanka from 1980 to 2012 Department Geography Degree Master of Arts In presenting this thesis in partial fulfillment of the requirements for a graduate degree from the University of North Dakota, I agree that the library of the University shall make it freely available for inspection.
    [Show full text]
  • World Bank Document
    Document of The World Bank FOR OFFICIAL USE ONLY Public Disclosure Authorized Report No: 3 8 147 - LK PROJECT APPRAISAL DOCUMENT ON A Public Disclosure Authorized PROPOSED CREDIT IN THE AMOUNT OF SDR 21.7 MILLION (US$32 MILLION EQUIVALENT) TO THE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA FOR A PUTTALAM HOUSING PROJECT Public Disclosure Authorized JANUARY 24,2007 Sustainable Development South Asia Region Public Disclosure Authorized This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization. CURRENCY EQUIVALENTS (Exchange Rate Effective December 13,2006) Currency Unit = Sri Lankan Rupee 108 Rupees (Rs.) = US$1 US$1.50609 = SDR 1 FISCAL YEAR January 1 - December 31 ABBREVIATIONS AND ACRONYMS ADB Asian Development Bank LTF Land Task Force AG Auditor General LTTE Liberation Tigers ofTamil Eelam CAS Country Assistance Strategy NCB National Competitive Bidding CEB Ceylon Electricity Board NGO Non Governmental Organization CFAA Country Financial Accountability Assessment NEIAP North East Irrigated Agriculture Project CQS Selection Cased on Consultants Qualifications NEHRP North East Housing Reconstruction Program CSIA Continuous Social Impact Assessment NPA National Procurement Agency CSP Camp Social Profile NPV Not Present Value CWSSP Community Water Supply and Sanitation NWPEA North Western Provincial Environmental Act Project DMC District Monitoring Committees NWPRD NorthWest Provincial Roads Department
    [Show full text]
  • Clean Energy and Access Improvement Project
    Resettlement Planning Document Resettlement Plan Document Stage: Final Project Number: 39419 July 2008 SRI: Clean Energy and Access Improvement Project Prepared by Ceylon Electricity Board The resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA CEYLON ELECTRICITY BOARD NATIONAL GRID DEVELOPMENT PROJECT LOAN AGREEMENT NO: RESETTLEMENT AND COMPENSATION PLAN ENVIRONMENT UNIT CEYLON ELECTRICITY BOARD COLOMBO SRI LANAKA Abbreviations ADB - Asian Development Bank BoI - Board of Investment 0C - Celsius CEA - Central Environmental Authority CEB - Ceylon Electricity Board db(A) - A-Weighted sound measurement in decibels DS - Divisional Secretary EIA - Environmental Impact Assessment EPL - Environmental Protection License GIS - Gas Insulated Substation GN - Grama Niladhari GS - Grid Substation IEC - International Electrotechnical Commission IEE - Initial Environmental Examination IPP - Independent Power Producer km - kilometer kV - kilovolt LoI - Letter of Intent m - meter mm - millimeter MOH - Medical Officer of Health MVA - Megavolt Ampere MW - Megawatt NCRE - Non-Conventional Renewable Energy NGO - Non Government Organization NIRR - National Policy on Involuntary Resettlement NEA - National Environment Act PAA - Project Approving Agency PAC - Project Approving Committee PSS/e - Power System Simulation REA - Rapid Environmental Assessment ROW - Right of Way SEA - Sustainable Energy Authority SLBC - Sri Lanka Broadcasting Corporation SPPA - Small Power Purchase Agreement SPP - Small Power Producer VRR - Victoria, Randenigala, Rantembe W - Watt Page 1 Executive Summary This Resettlement and Compensation Plan covers the proposed National Grid Development Project of Ceylon Electricity Board, Sri Lanka, scheduled for implementation from year 2008.
    [Show full text]
  • CHAP 9 Sri Lanka
    79o 00' 79o 30' 80o 00' 80o 30' 81o 00' 81o 30' 82o 00' Kankesanturai Point Pedro A I Karaitivu I. Jana D Peninsula N Kayts Jana SRI LANKA I Palk Strait National capital Ja na Elephant Pass Punkudutivu I. Lag Provincial capital oon Devipattinam Delft I. Town, village Palk Bay Kilinochchi Provincial boundary - Puthukkudiyiruppu Nanthi Kadal Main road Rameswaram Iranaitivu Is. Mullaittivu Secondary road Pamban I. Ferry Vellankulam Dhanushkodi Talaimannar Manjulam Nayaru Lagoon Railroad A da m' Airport s Bridge NORTHERN Nedunkeni 9o 00' Kokkilai Lagoon Mannar I. Mannar Puliyankulam Pulmoddai Madhu Road Bay of Bengal Gulf of Mannar Silavatturai Vavuniya Nilaveli Pankulam Kebitigollewa Trincomalee Horuwupotana r Bay Medawachchiya diya A d o o o 8 30' ru 8 30' v K i A Karaitivu I. ru Hamillewa n a Mutur Y Pomparippu Anuradhapura Kantalai n o NORTH CENTRAL Kalpitiya o g Maragahewa a Kathiraveli L Kal m a Oy a a l a t t Puttalam Kekirawa Habarane u 8o 00' P Galgamuwa 8o 00' NORTH Polonnaruwa Dambula Valachchenai Anamaduwa a y O Mundal Maho a Chenkaladi Lake r u WESTERN d Batticaloa Naula a M uru ed D Ganewatta a EASTERN g n Madura Oya a G Reservoir Chilaw i l Maha Oya o Kurunegala e o 7 30' w 7 30' Matale a Paddiruppu h Kuliyapitiya a CENTRAL M Kehelula Kalmunai Pannala Kandy Mahiyangana Uhana Randenigale ya Amparai a O a Mah Reservoir y Negombo Kegalla O Gal Tirrukkovil Negombo Victoria Falls Reservoir Bibile Senanayake Lagoon Gampaha Samudra Ja-Ela o a Nuwara Badulla o 7 00' ng 7 00' Kelan a Avissawella Eliya Colombo i G Sri Jayewardenepura
    [Show full text]
  • Evaluation of Agriculture and Natural Resources Sector in Sri Lanka
    Evaluation Working Paper Sri Lanka Country Assistance Program Evaluation: Agriculture and Natural Resources Sector Assistance Evaluation August 2007 Supplementary Appendix A Operations Evaluation Department CURRENCY EQUIVALENTS (as of 01 August 2007) Currency Unit — Sri Lanka rupee (SLR) SLR1.00 = $0.0089 $1.00 = SLR111.78 ABBREVIATIONS ADB — Asian Development Bank GDP — gross domestic product ha — hectare kg — kilogram TA — technical assistance UNDP — United Nations Development Programme NOTE In this report, “$” refers to US dollars. Director General Bruce Murray, Operations Evaluation Department (OED) Director R. Keith Leonard, Operations Evaluation Division 1, OED Evaluation Team Leader Njoman Bestari, Principal Evaluation Specialist Operations Evaluation Division 1, OED Operations Evaluation Department CONTENTS Page Maps ii A. Scope and Purpose 1 B. Sector Context 1 C. The Country Sector Strategy and Program of ADB 11 1. ADB’s Sector Strategies in the Country 11 2. ADB’s Sector Assistance Program 15 D. Assessment of ADB’s Sector Strategy and Assistance Program 19 E. ADB’s Performance in the Sector 27 F. Identified Lessons 28 1. Major Lessons 28 2. Other Lessons 29 G. Future Challenges and Opportunities 30 Appendix Positioning of ADB’s Agriculture and Natural Resources Sector Strategies in Sri Lanka 33 Njoman Bestari (team leader, principal evaluation specialist), Alvin C. Morales (evaluation officer), and Brenda Katon (consultant, evaluation research associate) prepared this evaluation working paper. Caren Joy Mongcopa (senior operations evaluation assistant) provided administrative and research assistance to the evaluation team. The guidelines formally adopted by the Operations Evaluation Department (OED) on avoiding conflict of interest in its independent evaluations were observed in the preparation of this report.
    [Show full text]
  • Fisheries and Environmental Profile of Chilaw Estuary
    REGIONAL FISHERIES LIVELIHOODS PROGRAMME FOR SOUTH AND SOUTHEAST ASIA (RFLP) --------------------------------------------------------- Fisheries and environmental profile of Chilaw lagoon: a literature review (Activity 1.3.1 Prepare fisheries and environmental profile of Chilaw lagoon using secondary data and survey reports) For the Regional Fisheries Livelihoods Programme for South and Southeast Asia Prepared by Leslie Joseph Co-management consultant June 2011 DISCLAIMER AND COPYRIGHT TEXT "This publication has been made with the financial support of the Spanish Agency of International Cooperation for Development (AECID) through an FAO trust-fund project, the Regional Fisheries Livelihoods Programme (RFLP) for South and Southeast Asia. The content of this publication does not necessarily reflect the opinion of FAO, AECID, or RFLP.” All rights reserved. Reproduction and dissemination of material in this information product for educational and other non-commercial purposes are authorized without any prior written permission from the copyright holders provided the source is fully acknowledged. Reproduction of material in this information product for resale or other commercial purposes is prohibited without written permission of the copyright holders. Applications for such permission should be addressed to: Chief Electronic Publishing Policy and Support Branch Communication Division FAO Viale delle Terme di Caracalla, 00153 Rome, Italy or by e-mail to: [email protected] © FAO 2011 Bibliographic reference For bibliographic purposes, please
    [Show full text]
  • Performance Report 2014 (A Brief Performance Report of the Key Sections and the Provincial Offices Belong to the Department of Archaeology)
    Performance Report 2014 (A brief performance report of the key sections and the provincial offices belong to The Department of Archaeology) Project Monitoring & Evaluation Division (Planning Division) Department of Archaeology Colombo - 07 Table of contents Page number Department of Archaeology (Vision, Mission, Objectives) 157 - 160 Exploration and Documentation Division 161 - 166 Excavation Division 167 - 171 Museum Services Division 172 - 174 Architectural Conservation Division 175 - 185 Chemical Preservation Division 186 - 190 Epigraphy and Numismatics Division 191 - 193 Maintenance Division 194 - 204 Promotional Division 205 - 207 Accounts Division 208 - 209 Administration Division 210 - 214 Project Monitoring & Evaluation Division 215 - 219 Legal Division 220 - 229 Performance Report - 2014 157 Department of Archaeology Vision The vision of the Department of Archaeology of Sri Lanka is to promote proper management of Sri Lanka‟s archeological heritage. Mission The mission of the Department of Archaeology of Sri Lanka is to function as Sri Lanka‟s apex institution and chief regulatory body for the management of its archaeological heritage. Objectives In order to fulfill its mission, the objectives of the Department of Archaeology of Sri Lanka are; 1) Development of resources (i.) Human (ii.) Institutional 2) Protection of the total archaeological heritage of Sri Lanka 3) Inventorisation of the archaeological heritage of Sri Lanka (i.) Archaeological sites and Monuments (ii.) Movable antiquities 4) Enhancement of public awareness
    [Show full text]
  • Dry Zone Urban Water and Sanitation Project – Additional Financing (RRP SRI 37381)
    Dry Zone Urban Water and Sanitation Project – Additional Financing (RRP SRI 37381) DEVELOPMENT COORDINATION A. Major Development Partners: Strategic Foci and Key Activities 1. In recent years, the Asian Development Bank (ADB) and the Government of Japan have been the major development partners in water supply. Overall, several bilateral development partners are involved in this sector, including (i) Japan (providing support for Kandy, Colombo, towns north of Colombo, and Eastern Province), (ii) Australia (Ampara), (iii) Denmark (Colombo, Kandy, and Nuwaraeliya), (iv) France (Trincomalee), (v) Belgium (Kolonna–Balangoda), (vi) the United States of America (Badulla and Haliela), and (vii) the Republic of Korea (Hambantota). Details of projects assisted by development partners are in the table below. The World Bank completed a major community water supply and sanitation project in 2010. Details of Projects in Sri Lanka Assisted by the Development Partners, 2003 to Present Development Amount Partner Project Name Duration ($ million) Asian Development Jaffna–Killinochchi Water Supply and Sanitation 2011–2016 164 Bank Dry Zone Water Supply and Sanitation 2009–2014 113 Secondary Towns and Rural Community-Based 259 Water Supply and Sanitation 2003–2014 Greater Colombo Wastewater Management Project 2009–2015 100 Danish International Kelani Right Bank Water Treatment Plant 2008–2010 80 Development Agency Nuwaraeliya District Group Water Supply 2006–2010 45 Towns South of Kandy Water Supply 2005–2010 96 Government of Eastern Coastal Towns of Ampara
    [Show full text]
  • Download PDF 638 KB
    Working Paper 58 Developing Effective Institutions for Water Resources Management : A Case Study in the Deduru Oya Basin, Sri Lanka P. G. Somaratne K. Jinapala L. R. Perera B. R. Ariyaratne, D. J. Bandaragoda and Ian Makin International Water Management Institute i IWMI receives its principal funding from 58 governments, private foundations, and international and regional organizations known as the Consultative Group on International Agricultural Research (CGIAR). Support is also given by the Governments of Ghana, Pakistan, South Africa, Sri Lanka and Thailand. The authors: P.G. Somaratne, L. R. Perera, and B. R. Ariyaratne are Senior Research Officers; K. Jinapala is a Research Associate; D. J. Bandaragoda is a Principal Researcher, and Ian Makin is the Regional Director, Southeast Asia, all of the International Water Management Institute. Somaratne, P. G.; Jinapala, K.; Perera, L. R.; Ariyaratne, B. R.; Bandaragaoda, D. J.; Makin, I. 2003. Developing effective institutions for water resources management: A case study in the Deduru Oya Basin, Sri Lanka. Colombo, Sri Lanka: International Water Management Institute. / river basins / water resource management / irrigation systems / groundwater / water resources development / farming / agricultural development / rivers / fish farming / irrigation programs / poverty / irrigated farming / water shortage / pumps / ecology / reservoirs / water distribution / institutions / environment / natural resources / water supply / drought / land use / water scarcity / cropping systems / agricultural production
    [Show full text]
  • SFG1866 Public Disclosure Authorized
    JAELA TO PUTTALAM SECTION i SFG1866 Public Disclosure Authorized Social Impact Assessment For TRANSPORT CONNECTIVITY AND ASSET MANAGEMENT PROJECT Public Disclosure Authorized JaEla to Puttalam Section of Peliyagoda - Puttalam Road (A03) Public Disclosure Authorized Road Development Authority Public Disclosure Authorized MINISTRY OF HIGHER EDUCATION AND HIGHWAYS 2016 Resources Development Consultants (Pvt) Ltd. JAELA TO PUTTALAM SECTION ii TABLE OF CONTENTS TABLE OF CONTENTS ........................................................................................................ ii TABLE OF FIGURES ............................................................................................................. v TABLES .................................................................................................................................... v ACRONYMS .......................................................................................................................... vii EXECUTIVE SUMMARY ..................................................................................................... 1 CHAPTER 01: PROJECT BACKGROUND ........................................................................ 3 1.1 The Project ....................................................................................................................... 3 1.2 Description of the project ................................................................................................. 3 CHAPTER 02: OBJECTIVES AND METHODOLOGY...................................................
    [Show full text]
  • Lanka Government Network 2.0
    Lanka Government Network 2.0 Bandwidth Utilization Report Report for PSC – June 19th 2018 May April March Criteria Criteria 3 BW BW Site Value Criteria 2 Site Name 1 (Max- (BW Allocated Group (Rs.)**** Avg Max Avg Max Avg Max (Avg-C)** (Mbps) (Mbps) (Mbps) (Mbps) (Mbps) (Mbps) C)* Upgrade)*** Addalachchenai Divisional Secretariat 2 Mbps E 83,650.95 0.43 1.98 0.34 1.56 0.43 1.97 N/A N/A No Agalawatta Divisional Secretariat 2 Mbps E 83,650.95 0.59 1.99 0.34 1.99 0.28 1.92 N/A N/A No Agunukolapalassa Prison 2 Mbps E - 0.05 0.16 0.04 0.06 0.05 0.11 N/A N/A No Akkaraipattu Divisional Secretariat 2 Mbps E 78,460.95 0.13 1.82 0.04 0.19 0.05 0.45 N/A N/A No Akkaraipattu Zonal Education Office 2 Mbps E 81,860.95 0.08 1.05 0.05 0.14 0.05 0.20 N/A N/A No Akurana Divisional Secretariat 2 Mbps E 87,230.95 0.40 1.69 0.33 1.97 0.31 1.85 N/A N/A No Akuressa Divisional Secretariat 2 Mbps E 88,840.95 0.99 1.99 0.46 1.99 0.89 1.99 N/A N/A No Akuressa Pradeshiya Sabha 2 Mbps E 78,460.95 0.14 1.22 0.07 0.39 0.07 0.15 N/A N/A No Alawwa Divisional Secretariat 2 Mbps E 78,280.95 0.30 1.56 0.31 1.83 0.20 1.73 N/A N/A No Alayadivembu Divisional Secretariat 2 Mbps E 78,460.95 0.62 1.95 0.48 1.74 0.49 1.74 N/A N/A No Ambagamuwa Koralaya Divisional Secretariat 2 Mbps E 87,230.95 0.19 1.16 0.07 0.32 0.04 0.55 N/A N/A No Ambalangoda Divisional Secretariat 2 Mbps E 92,600.95 0.31 1.91 0.36 1.98 0.19 1.46 N/A N/A No Ambalangoda Zonal Education Office 2 Mbps E 78,280.95 0.22 1.81 0.09 1.17 0.23 1.93 N/A N/A No Ambangangakorale Divisional Secretariat 2 Mbps E 81,860.95
    [Show full text]