Clean Energy and Access Improvement Project

Total Page:16

File Type:pdf, Size:1020Kb

Clean Energy and Access Improvement Project Resettlement Planning Document Resettlement Plan Document Stage: Final Project Number: 39419 July 2008 SRI: Clean Energy and Access Improvement Project Prepared by Ceylon Electricity Board The resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA CEYLON ELECTRICITY BOARD NATIONAL GRID DEVELOPMENT PROJECT LOAN AGREEMENT NO: RESETTLEMENT AND COMPENSATION PLAN ENVIRONMENT UNIT CEYLON ELECTRICITY BOARD COLOMBO SRI LANAKA Abbreviations ADB - Asian Development Bank BoI - Board of Investment 0C - Celsius CEA - Central Environmental Authority CEB - Ceylon Electricity Board db(A) - A-Weighted sound measurement in decibels DS - Divisional Secretary EIA - Environmental Impact Assessment EPL - Environmental Protection License GIS - Gas Insulated Substation GN - Grama Niladhari GS - Grid Substation IEC - International Electrotechnical Commission IEE - Initial Environmental Examination IPP - Independent Power Producer km - kilometer kV - kilovolt LoI - Letter of Intent m - meter mm - millimeter MOH - Medical Officer of Health MVA - Megavolt Ampere MW - Megawatt NCRE - Non-Conventional Renewable Energy NGO - Non Government Organization NIRR - National Policy on Involuntary Resettlement NEA - National Environment Act PAA - Project Approving Agency PAC - Project Approving Committee PSS/e - Power System Simulation REA - Rapid Environmental Assessment ROW - Right of Way SEA - Sustainable Energy Authority SLBC - Sri Lanka Broadcasting Corporation SPPA - Small Power Purchase Agreement SPP - Small Power Producer VRR - Victoria, Randenigala, Rantembe W - Watt Page 1 Executive Summary This Resettlement and Compensation Plan covers the proposed National Grid Development Project of Ceylon Electricity Board, Sri Lanka, scheduled for implementation from year 2008. The Project consists of three subprojects, namely (1) Construction of the new System Control Centre (2) Augmentation of Grid Substations for the Absorption of Renewable Energy, and (3) Augmentation of Eight Grid Substations, Construction of Three New Grid Substations and Construction of Four New Transmission Lines. The Project is to be implemented with credit support from the Asian Development Bank. Subprojects 2 and 3 are expected to have certain environmental and social impacts, and Initial Environmental Examinations Reports have been prepared for these two subprojects. This resettlement and compensation plan covers both subprojects 2 and 3. Collectively, subprojects 2 and 3 include the augmentation of a total of fifteen Grid Substations (GSs), construction of four new GSs and the construction of five new transmission lines over new rights-of-way. Augmentation of Fifteen GSs: All the fifteen GSs to be augmented under this project would use land space available within the existing property owned by CEB at the respective locations. Apart from relocation or modification of CEB’s own buildings within each GSs, there will be no impacts on any land or buildings owned by members of public or other institutions. In certain GSs, shifting of the perimeter fence would be required, but would not use any land beyond CEB-owned property. Land filling would be required in some GSs to prepare the available space for the construction of the augmentation. Apart from attending to any unforeseen damages (such as possible damage to local roads during material transport) that may be caused during construction, there will be no relocation or compensation issues associated with GSs to be augmented. Construction of Four New GSs: In the selection of lands for new GSs a number of optional sites have been reviewed for each GS. In order to minimize the resettlement impacts, always preference is given to the Government owned lands to avoid resettlement of private dwellings and impacts on land use. Also particular attentions is given to the convenience of access to a transmission corridor which will avoid passing through built up areas and / or areas with special environmental concerns. Accordingly lands to locate these GSs have already been earmarked, and they will all be land owned by the government or government- owned institutions. Except for one unused building in one location, all the four blocks of land to locate the new GSs are unused and they are not in productive use either for living, commercial activity or for agriculture. Apart from unforeseen issues that may arise during construction, there are no relocation and compensation issues to be addressed at this stage of project planning and approval. Construction of Five New Transmission Lines: This Resettlement and Compensation plan first explains the process of selecting the new rights-of-way for transmission lines. Initially, a number of map based routing options were considered for each new transmission line, with the primary focus on avoiding / minimizing the impacts on human settlements / built up areas, forest and wild life reserves, places of cultural / historical importance, social infrastructure (eg. playgrounds, schools, hospitals etc.) and areas of high grown trees. Among them, the Resettlement and Compensation Plan presents three best optional routes for each corridor, and compares their impacts in terms of land use, human settlements and areas of special concerns (forest reserves). Then the selected option is presented along with Page 2 an estimate of impacts. Typical impacts of new transmission corridors would be (a) loss of vegetation (b) land-use restrictions by way of limitations to building heights and height of trees (c) land-use restrictions at tower footings. CEB would not be purchasing the land along the new rights-of-way including the tower footings but would compensate the owners/users for the lost vegetation, but allow lower-height agricultural activities (such as paddy, tea, cinnamon) to continue. However, special cases would be considered and compensated accordingly. The plan then explains the process of public involvement in finalising the transmission line corridor during the environmental evaluation conducted under the Sri Lanka Environmental Act. It explains the legal process for issuing notices to the public about the planned activity and lines to be drawn across their lands, the appeal procedure and the grievance redress mechanisms, and the role and responsibilities of CEB and other government institutions in the process. It also explains the process of evaluation of damages to vegetation and agriculture, at the inception as well and during construction. Finally the report explains the monitoring mechanism for compliance by CEB staff and contractors, to the conditions stipulated in the environmental approval and the provisions in this report. As a result of careful selection of line routes that have been already identified and explained in this report, and the subsequent public consultation and the appeal procedure, this National Grid Development Project, at this stage, is not expected to cause any involuntary relocation of persons from their dwellings. CEB would ensure that maximum efforts would be made to avoid involuntary relocation even if unforeseen constraints occur in the field during setting out of the lines and tower footings. As such, this report focuses more on the aspects of compensation to land owners and users for lost vegetation and long-term restrictions on land-use along the line corridors to be established under this project. This report follows the guidelines established by the Asian Development Bank for involuntary resettlement and compensation. 3 CONTENTS 1 INTRODUCTION 8 1.1 Small Power Producers using NCRE Sources 10 1.2 Constraints of CEB Grid to Absorb Renewable Energy 11 2 PROJECT SCOPE AND LAND USE 11 2.1 Summary Scope of the Project 11 2.2 Detailed Scope of Subproject 2 13 2.2.2 Augmentation of Existing Grid Substations 13 2.2.3 Construction of New Mahiyangana GS and 132kV Transmission Line between Rantambe and Mahiyangana 14 2.3 Detailed Scope of Subproject 3 15 2.3.1 Augmentation of Existing Grid Substations 15 2.3.2 New Grid Substations 16 2.3.3 New Transmission Lines 17 2.4 Land Use for the Project 17 2.4.1 New System Control Centre and Grid Substations to be Augmented 17 2.4.2 New Transmission Lines 19 2.5 Type of Project and the Category 25 2.6 Study Methodology, Scope and Limitations 26 3 MINIMISATION OF IMPACTS AND MITIGATORY MEASURES 27 3.1 Measures to Minimise Impacts 27 3.1.1 Grid Substations to be Augmented 27 3.1.2 New Grid Substations to be Established 27 3.1.3 Strategy to Minimise Impacts of New Transmission Lines 27 3.2 Optional Routes for Transmission Lines 28 3.3 Key Effects on Resettlement and Land Use 38 3.4 Mitigation of Impacts on Selected Routes 40 4 SOCIO ECONOMIC CONDITIONS IN PROJECT AREAS 41 4.1 Subproject 2 42 4.1.1 Socio-economic Conditions along the Rantembe-Mahiyangana Line 42 4.2 Subproject 3 46 4.2.1 Socio-economic Conditions along Galle- Matara 132 kV Transmission Line 46 4.2.2 Socio-economic Conditions along Habarana-Valachchenai 132 kV Line 48 4.2.3 Socio-economic Conditions along Puttalam-Maho 132 kV Transmission Line 50 4.2.4 Socio-economic Conditions along Ukuwela-Pallekelle 132 kV Transmission Line 52 5 COMPLIANCE WITH POLICIES, LEGAL REQUIREMENTS AND PROCEDURES 54 4 5.1 Sri Lanka Legal Requirements and Procedures 54 5.1.1 Environmental Acts and Regulations 54 5.1.2 Electricity Act and Regulations 55 5.1.3 Involuntary Resettlement Policy of Sri Lanka 55 5.1.4 Environmental Approval
Recommended publications
  • Spatial Dimensions of Conflict-Induced Internally Displaced Population in the Puttalam District of Sri Lanka from 1980 to 2012 Deepthi Lekani Waidyasekera
    University of North Dakota UND Scholarly Commons Theses and Dissertations Theses, Dissertations, and Senior Projects 12-1-2012 Spatial Dimensions of Conflict-Induced Internally Displaced Population in the Puttalam District of Sri Lanka from 1980 to 2012 Deepthi Lekani Waidyasekera Follow this and additional works at: https://commons.und.edu/theses Recommended Citation Waidyasekera, Deepthi Lekani, "Spatial Dimensions of Conflict-Induced Internally Displaced Population in the Puttalam District of Sri Lanka from 1980 to 2012" (2012). Theses and Dissertations. 668. https://commons.und.edu/theses/668 This Thesis is brought to you for free and open access by the Theses, Dissertations, and Senior Projects at UND Scholarly Commons. It has been accepted for inclusion in Theses and Dissertations by an authorized administrator of UND Scholarly Commons. For more information, please contact [email protected]. SPATIAL DIMENSIONS OF CONFLICT-INDUCED INTERNALLY DISPLACED POPULATION IN THE PUTTALAM DISTRICT OF SRI LANKA FROM 1980 TO 2012 by Deepthi Lekani Waidyasekera Bachelor of Arts, University of Sri Jayawardanapura,, Sri Lanka, 1986 Master of Science, University of Moratuwa, Sri Lanka, 2001 A Thesis Submitted to the Graduate Faculty of the University of North Dakota In partial fulfilment of the requirements For the degree of Master of Arts Grand Forks, North Dakota December 2012 Copyright 2012 Deepthi Lekani Waidyasekera ii PERMISSION Title Spatial Dimensions of Conflict-Induced Internally Displaced Population in the Puttalam District of Sri Lanka from 1980 to 2012 Department Geography Degree Master of Arts In presenting this thesis in partial fulfillment of the requirements for a graduate degree from the University of North Dakota, I agree that the library of the University shall make it freely available for inspection.
    [Show full text]
  • CHAPTER 4 Perspective of the Colombo Metropolitan Area 4.1 Identification of the Colombo Metropolitan Area
    Urban Transport System Development Project for Colombo Metropolitan Region and Suburbs CoMTrans UrbanTransport Master Plan Final Report CHAPTER 4 Perspective of the Colombo Metropolitan Area 4.1 Identification of the Colombo Metropolitan Area 4.1.1 Definition The Western Province is the most developed province in Sri Lanka and is where the administrative functions and economic activities are concentrated. At the same time, forestry and agricultural lands still remain, mainly in the eastern and south-eastern parts of the province. And also, there are some local urban centres which are less dependent on Colombo. These areas have less relation with the centre of Colombo. The Colombo Metropolitan Area is defined in order to analyse and assess future transport demands and formulate a master plan. For this purpose, Colombo Metropolitan Area is defined by: A) areas that are already urbanised and those to be urbanised by 2035, and B) areas that are dependent on Colombo. In an urbanised area, urban activities, which are mainly commercial and business activities, are active and it is assumed that demand for transport is high. People living in areas dependent on Colombo area assumed to travel to Colombo by some transport measures. 4.1.2 Factors to Consider for Future Urban Structures In order to identify the CMA, the following factors are considered. These factors will also define the urban structure, which is described in Section 4.3. An effective transport network will be proposed based on the urban structure as well as the traffic demand. At the same time, the new transport network proposed will affect the urban structure and lead to urban development.
    [Show full text]
  • Census Codes of Administrative Units Western Province Sri Lanka
    Census Codes of Administrative Units Western Province Sri Lanka Province District DS Division GN Division Name Code Name Code Name Code Name No. Code Western 1 Colombo 1 Colombo 03 Sammanthranapura 005 Western 1 Colombo 1 Colombo 03 Mattakkuliya 010 Western 1 Colombo 1 Colombo 03 Modara 015 Western 1 Colombo 1 Colombo 03 Madampitiya 020 Western 1 Colombo 1 Colombo 03 Mahawatta 025 Western 1 Colombo 1 Colombo 03 Aluthmawatha 030 Western 1 Colombo 1 Colombo 03 Lunupokuna 035 Western 1 Colombo 1 Colombo 03 Bloemendhal 040 Western 1 Colombo 1 Colombo 03 Kotahena East 045 Western 1 Colombo 1 Colombo 03 Kotahena West 050 Western 1 Colombo 1 Colombo 03 Kochchikade North 055 Western 1 Colombo 1 Colombo 03 Jinthupitiya 060 Western 1 Colombo 1 Colombo 03 Masangasweediya 065 Western 1 Colombo 1 Colombo 03 New Bazaar 070 Western 1 Colombo 1 Colombo 03 Grandpass South 075 Western 1 Colombo 1 Colombo 03 Grandpass North 080 Western 1 Colombo 1 Colombo 03 Nawagampura 085 Western 1 Colombo 1 Colombo 03 Maligawatta East 090 Western 1 Colombo 1 Colombo 03 Khettarama 095 Western 1 Colombo 1 Colombo 03 Aluthkade East 100 Western 1 Colombo 1 Colombo 03 Aluthkade West 105 Western 1 Colombo 1 Colombo 03 Kochchikade South 110 Western 1 Colombo 1 Colombo 03 Pettah 115 Western 1 Colombo 1 Colombo 03 Fort 120 Western 1 Colombo 1 Colombo 03 Galle Face 125 Western 1 Colombo 1 Colombo 03 Slave Island 130 Western 1 Colombo 1 Colombo 03 Hunupitiya 135 Western 1 Colombo 1 Colombo 03 Suduwella 140 Western 1 Colombo 1 Colombo 03 Keselwatta 145 Western 1 Colombo 1 Colombo
    [Show full text]
  • Ongoing Project Details
    Ongoing Project Details Development TEC Loan Amount Project Name Objective Partner (USD Mn) (USD Mn) Agriculture Fisheries ADB Northern Province Sustainable PDA will finance consultancy services to undertake detail engineering design which 1.59 1.30 Fisheries Development Project, include the updating of cost, updating of social safeguard assessments and Project Design Advance (PDA) preparation of bidding documents and supporting bidding process. Sub Total - Fisheries 1.59 1.30 Agriculture ADB Mahaweli Water Security Investment The following three investment projects will be implemented under the above 432.00 360.00 Program investment program. Tranche 1 - USD 190 Mn (i) Upper Elahera Canal Project Tranche 2- USD 242 Mn Construction of 9 km Kaluganga-Morgahakanda Transfer Canal to transfer water from Kaluganga reservoir to Moragahakanda Reservoirs and Upper Elehera Canals to connect Moragahakanda Reservoir to the existing reservoirs; Huruluwewa, Manakattiya, Eruwewa and Mahakanadarawa. (ii) North Western Province Canal Project Construction of 96 km of new and upgraded canals, including a new 940 m tunnel and two new 25 m tall dams will be constructed under NWPCP to transfer water from the Dambulu Oya and existing Nalanda and Wemedilla Reservoirs to North Western Province. (iii) Minipe Left Bank Canal Rehabilitation Project Heightening the headwork’s, construction of new automatic downstream- controlled intake gates to the left bank canal; construction of new emergency spill weirs to both left and right bank canals; rehabilitation of 74 km Minipe Left Bank Canal, including regulator and spill structures. 1 of 24 Ongoing Project Details Development TEC Loan Amount Project Name Objective Partner (USD Mn) (USD Mn) IDA Agriculture Sector Modernization Objective is to support increasing Agricultural productivity, improving market 125.00 125.00 Project access and enhancing value addition of small holder farmers and agribusinesses in the project areas.
    [Show full text]
  • Chatting Sri Lanka: Powerful Communications in Colonial Times
    Chatting Sri Lanka: Powerful Communications in Colonial Times Justin Siefert PhD 2016 Chatting Sri Lanka: Powerful Communications in Colonial Times Justin Siefert A thesis submitted in partial fulfilment of the requirements of the Manchester Metropolitan University for the degree of Doctor of Philosophy Department of History, Politics and Philosophy Manchester Metropolitan University 2016 Abstract: The thesis argues that the telephone had a significant impact upon colonial society in Sri Lanka. In the emergence and expansion of a telephone network two phases can be distinguished: in the first phase (1880-1914), the government began to construct telephone networks in Colombo and other major towns, and built trunk lines between them. Simultaneously, planters began to establish and run local telephone networks in the planting districts. In this initial period, Sri Lanka’s emerging telephone network owed its construction, financing and running mostly to the planting community. The telephone was a ‘tool of the Empire’ only in the sense that the government eventually joined forces with the influential planting and commercial communities, including many members of the indigenous elite, who had demanded telephone services for their own purposes. However, during the second phase (1919-1939), as more and more telephone networks emerged in the planting districts, government became more proactive in the construction of an island-wide telephone network, which then reflected colonial hierarchies and power structures. Finally in 1935, Sri Lanka was connected to the Empire’s international telephone network. One of the core challenges for this pioneer work is of methodological nature: a telephone call leaves no written or oral source behind.
    [Show full text]
  • The Tragedy of Mount Lavinia Beach
    The tragedy of Mount Lavinia beach Charitha Pattiaratchi1, Nadiya Azmy2 and Asha de Vos1, 2 1The Oceans Institute, University of Western Australia, 35 Stirling Highway, M470, Crawley WA, 6009, Australia 2Oceanswell, 9 Park Gardens, Colombo 5, Sri Lanka Email: [email protected] and [email protected] Key points 1. Sand nourishment of Mount Lavinia beach appears to have no tangible outcomes with respect to aims of the project. The exercise appears to have been undertaken without adequate planning, detailed studies and ignoring basic coastal engineering principles. 2. The Coast Conservation Department has stated that the aim of the project is to create a 15 m beach at Wellawatte through the sand engine method. Here, 150,000 m3 of sand was placed on Mount Lavinia beach and is expected to be transported to Wellawatte. 3. A considerable amount of money has been spent. It is expected, through design or otherwise, that the majority of the sand will be washed away from Mount Lavinia beach after the south-west monsoon season. 4. The coastline between Mount Lavinia and Wellawatte has remained relatively stable for many decades albeit with seasonal changes. 5. The sand deposited at Mount Lavinia has to pass three major natural and artificial structures: Rock at Aponso Avenue and the training groynes at the two canal outlets at Dehiwala and Wellawatte. 6. The percentage of sand deposited at Mount Lavinia making it as far as Wellawatte is likely to be small and certainly not large enough to create a 15 m beach. Also consider that the existing seasonal change in the beach is larger than 15 m per annum.
    [Show full text]
  • Lions Clubs International Club Membership Register
    LIONS CLUBS INTERNATIONAL CLUB MEMBERSHIP REGISTER SUMMARY THE CLUBS AND MEMBERSHIP FIGURES REFLECT CHANGES AS OF JULY 2017 MEMBERSHI P CHANGES CLUB CLUB LAST MMR FCL YR TOTAL IDENT CLUB NAME DIST NBR COUNTRY STATUS RPT DATE OB NEW RENST TRANS DROPS NETCG MEMBERS 3846 025586 COLOMBO HOST REP OF SRI LANKA 306 A1 4 07-2017 32 0 0 0 0 0 32 3846 025591 DEHIWALA MT LAVINIA REP OF SRI LANKA 306 A1 4 07-2017 39 0 0 0 0 0 39 3846 025592 GALLE REP OF SRI LANKA 306 A1 4 07-2017 46 0 0 0 0 0 46 3846 025604 MORATUWA RATMALANA LC REP OF SRI LANKA 306 A1 4 07-2017 35 0 0 0 -1 -1 34 3846 025611 PANADURA REP OF SRI LANKA 306 A1 4 07-2017 32 0 0 0 0 0 32 3846 025614 WELLAWATTE REP OF SRI LANKA 306 A1 4 07-2017 32 0 0 0 -4 -4 28 3846 030299 KOLLUPITIYA REP OF SRI LANKA 306 A1 4 07-2017 17 0 0 0 0 0 17 3846 032756 MORATUWA REP OF SRI LANKA 306 A1 4 07-2017 50 0 0 0 -2 -2 48 3846 036615 TANGALLE REP OF SRI LANKA 306 A1 4 07-2017 30 0 0 0 0 0 30 3846 038353 KOTELAWALAPURA REP OF SRI LANKA 306 A1 4 06-2017 28 0 0 0 0 0 28 3846 041398 HIKKADUWA REP OF SRI LANKA 306 A1 4 06-2017 20 0 0 0 0 0 20 3846 041399 WADDUWA REP OF SRI LANKA 306 A1 4 07-2017 38 0 0 0 0 0 38 3846 043171 BALAPITIYA REP OF SRI LANKA 306 A1 4 06-2017 14 0 0 0 0 0 14 3846 043660 MORATUWA MORATUMULLA REP OF SRI LANKA 306 A1 4 07-2017 20 0 0 0 0 0 20 3846 045938 KALUTARA CENTRAL REP OF SRI LANKA 306 A1 4 06-2017 21 0 0 0 0 0 21 3846 046170 GALKISSA REP OF SRI LANKA 306 A1 4 07-2017 43 1 0 0 0 1 44 3846 048945 DEHIWALA METRO REP OF SRI LANKA 306 A1 4 07-2017 20 0 0 0 0 0 20 3846 051562 ALUTHGAMA
    [Show full text]
  • Data 3 : Flood Damage Survey Results the Study on Storm Water Drainage Plan for the Colombo Metropolitan Region in the Democratic Socialist Republic of Sri Lanka
    DATA 3 : FLOOD DAMAGE SURVEY RESULTS THE STUDY ON STORM WATER DRAINAGE PLAN FOR THE COLOMBO METROPOLITAN REGION IN THE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA FINAL REPORT VOLUME V : DATA BOOK DATA 3 : FLOOD DAMAGE SURVEY RESULTS TABLE OF CONTENTS Page 1. Locations of Identified Inundation Areas............................................................D3-1 2. Questionnaires.....................................................................................................D3-2 3. List of Questionnaire Survey Locations (1/13 - 13/13).......................................D3-7 4. Identified Inundation Areas and Questionnaires.................................................D3-20 5. Identified Inundation Areas and Questionnaires by District ...............................D3-21 6. Identified Inundation Areas and Questionnaires by Local Authority: Gampaha District.................................................................................................D3-22 7. Identified Inundation Areas and Questionnaires by Local Authority: Colombo District .................................................................................................D3-23 8. Identified Inundation Areas and Questionnaires by Local Authority: Kalutara District ..................................................................................................D3-24 9. Observation of Identified Inundation Areas: Area Classification .......................D3-25 10. Observation of Identified Inundation Areas: Density of Housing/Building ........D3-26 11. Observation
    [Show full text]
  • 2020 Telephone Directory 2016
    www.ceb.lk 2020 TELEPHONE DIRECTORY 2016 TELEPHONE DIRECTORY Published by Desinged & Printed by Ceylon Printers PLC Publicity Unit, Business & Operational Strategy Branch Ceylon Electricity Board II CEYLON ELECTRICITY BOARD GENERAL NUMBERS 011-2324471 – 8 (With Extensions to Branches in Head Office Building) CONTENTS PAGE Branch Index ...................................................................................................................................................................................................... iv - x Ministry of Power & Renewable Energy ................................................................................................................................................... 01 - 02 Members of the Board .................................................................................................................................................................................... 03 - 05 General Manager .............................................................................................................................................................................................. 06 - 08 Asset Management Division ........................................................................................................................................................................ 09 - 15 Corporate Strategy Division ........................................................................................................................................................................
    [Show full text]
  • Humanitarian Operation Factual Analysis July 2006 – May 2009
    HUMANITARIAN OPERATION FACTUAL ANALYSIS JULY 2006 – MAY 2009 MINISTRY OF DEFENCE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA HUMANITARIAN OPERATION FACTUAL ANALYSIS JULY 2006 – MAY 2009 MINISTRY OF DEFENCE JULY 2011 DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA Humanitarian Operation—Factual Analysis TABLE OF CONTENTS Page I. EXECUTIVE SUMMARY 1 A. Overview of this Report 1 B. Overview of the Humanitarian Operation 1 PART ONE II. BACKGROUND 4 A. Overview of the LTTE 4 B. LTTE Atrocities against Civilians 6 C. Use of Child Soldiers by the LTTE 10 D. Ethnic Cleansing Carried out by the LTTE 10 E. Attacks on Democracy by the LTTE 11 F. The Global Threat posed by the LTTE 11 G. Proscription of the LTTE 12 III. SIZE AND SCOPE OF THE LTTE 13 A. Potency of the LTTE 13 B. Number of Cadres 14 C. Land Fighting Forces 14 D. The Sea Tiger Wing 17 E. The Air Tiger Wing 20 F. Black Tiger (Suicide) Wing 22 G. Intelligence Wing 22 H. Supply Network 23 I. International Support Mechanisms 25 J. International Criminal Network 27 – iii – Humanitarian Operation—Factual Analysis Page IV. GOVERNMENT EFFORTS FOR A NEGOTIATED SETTLEMENT 28 A. Overview 28 B. The Thimpu Talks – July to August 1985 29 C. The Indo-Lanka Accord – July 1987 30 D. Peace Talks – May 1989 to June 1990 32 E. Peace Talks – October 1994 to April 1995 33 F. Norwegian-Facilitated Peace Process – February 2002 to January 2008 35 G. LTTE Behaviour during 2002–2006 37 PART TWO V. RESUMPTION OF HOSTILITIES 43 VI. THE WANNI OPERATION 52 VII.
    [Show full text]
  • Puttalam Lagoon System an Environmental and Fisheries Profile
    REGIONAL FISHERIES LIVELIHOODS PROGRAMME FOR SOUTH AND SOUTHEAST ASIA (RFLP) --------------------------------------------------------- An Environmental and Fisheries Profile of the Puttalam Lagoon System (Activity 1.4.1 : Consolidate and finalize reports on physio-chemical, geo-morphological, socio-economic, fisheries, environmental and land use associated with the Puttalam lagoon ecosystem) For the Regional Fisheries Livelihoods Programme for South and Southeast Asia Prepared by Sriyanie Miththapala (compiler) IUCN, International Union for Conservation of Nature, Sri Lanka Country Office October 2011 REGIONAL FISHERIES LIVELIHOODS PROGRAMME FOR SOUTH AND SOUTHEAST ASIA (RFLP) – SRI LANKA An Environmental and Fisheries Profile of the Puttalam Lagoon System (Activity 1.4.1- Consolidate and finalize reports on physio-chemical, geo-morphological, socio-economic, fisheries, environment and land use associated with Puttalam lagoon ecosystem) For the Regional Fisheries Livelihoods Programme for South and Southeast Asia Prepared by Sriyanie Miththapala (compiler) IUCN, International Union for Conservation of Nature, Sri Lanka Country Office October 2011 i Disclaimer and copyright text This publication has been made with the financial support of the Spanish Agency of International Cooperation for Development (AECID) through an FAO trust-fund project, the Regional Fisheries Livelihoods Programme (RFLP) for South and Southeast Asia. The content of this publication does not necessarily reflect the opinion of FAO, AECID, or RFLP. All rights reserved. Reproduction and dissemination of material in this information product for educational and other non-commercial purposes are authorized without any prior written permission from the copyright holders provided the source is fully acknowledged. Reproduction of material in this information product for resale or other commercial purposes is prohibited without written permission of the copyright holders.
    [Show full text]
  • SRI LANKA a Hidden Displacement Crisis
    31 October 2012 SRI LANKA A hidden displacement crisis More than three years after the end of the 26-year armed conflict between the Sri Lankan armed forces and the Liberation Tigers of Tamil Eelam (LTTE), nearly 470,000 people displaced during its various stages have returned to their home areas. This does not mean, however, that there is no internal displacement in the country any more. As of the end of September 2012, more than 115,000 internally displaced people (IDPs) were still living in camps, with host communities or in transit sites, A cyclone hits the return areas in northern Sri Lanka where people who had been or had been relocated, often against their displaced by the armed conflict continue to live in make-shift shelters constructed from old tin sheets and tarpaulins several months after their return. will, to areas other than their places of (Photo: NRC/October 2012) origin. Among those registered as having returned, many have not been able to achieve a durable solu- tion but continue to face difficulties in accessing basic necessities such as shelter, food, water and sanitation, in rebuilding their livelihoods, and in exercising their civil rights. De-mining op- erations are still ongoing in livelihood areas. Unresolved land issues have been a major obstacle to durable solutions for IDPs and IDP returnees. Conflict-affected areas remain highly militarised, which has made progress towards achieving durable solutions more difficult. The military has become an important economic player and a key competitor of local people including returnees in the areas of agriculture, fishing, trade, and tourism.
    [Show full text]