Environmental Monitoring Report SRI: National Highway Sector Project

Total Page:16

File Type:pdf, Size:1020Kb

Environmental Monitoring Report SRI: National Highway Sector Project Environmental Monitoring Report January – July 2012 SRI: National Highway Sector Project Prepared by the Road Development Authority, Ministry of Highways, Ports and Shipping for the Asian Development Bank. NATIONAL HIGHWAYS SECTOR PROJECT Semiannual progress report on environmental safeguards compliance For the period from January to July 2012 Prepared by National Highways Sector Project, Road Development Authority Ministry of Highways and Road Development Submitted to Sri Lanka Residence Mission, Asian Development Bank, Colombo August 2012 NATIONAL HIGHWAYS SECTOR PROJECT 1 ADB Loan No: 2217 SRI Semiannual progress report on environmental safeguards compliance From January to July 2012 National Highways Sector Project, Road Development Authority Ministry of Highways and Road Development August 2013 CONTENTS 2 List of figures and maps ii List of table iii List of abbreviations iv Executive Summary 1 1. Introduction 2 1.1 Supervision Consultants role in environmental safeguards compliance 3 2. Environmental approvals, licenses and permits 3 3. Ongoing construction activities 5 4. Environmental monitoring and mitigation measures adopted during the period 7 5. Rain fall data at each ICB subprojects 7 6. Subproject activities, environmental impacts and mitigation measures 7 7. Public complaints 8 8. Awareness of Sexually transmitted diseases (STD) and HIV/AIDS 8 9. Tree planting activities 9 10. Soil burrows area operation and rehabilitation 10 11. Disposal of soil/debris 10 12. Conclusion and further actions 10 LIST OF FIGURES & MAPS Figure 1: Location map of the sub-projects under NHSP v Figure 1:1 Photographs of Contrbertyact No. RDA/ADB/NHSP/ICB-01 12 Figure 1:2 Photographs of Contract No.RDA/ADB/NHSP/ICB-2 12 Figure 1:3 Photographs of Contract No.RDA/ADB/NHSP/ICB-3 13 3 Figure 1: 4 Photographs of Contract No. RDA/ADB/NHSP/ICB-5 13 Figure 1: 5 Photograph of Contract no: RDA/NHSP/HS-S1 14 Figure1: 6 Photograph of Contract no: RDA/NHSP/ PPMS 14 Figure: 2:1 Rainfall data of the month of June 2012 at ICB-1 subproject. 16 Figure 2:2 Rainfall data for 01st June to 30th June 2012 of ICB-05 subproject. 17 Figure 3:1 Photograph of plant sites of sub project ICB-1 21 Figure 3:2 Physical progress of work in ICB 1 subproject 23 Figure 3:3 Physical progress of work in ICB 1 subproject 24 Figure 3:4 Physical progress of work in ICB 3 subproject 28 Figure 3:5 Physical progress of work in ICB 3 subproject 29 Figure 3:6 Photograph of plant sites of sub project ICB-1 32 Figure: 4:1 IEC and TOT programm of sub project ICB-05 34 Figure: 4:2 Need Assessment of sub-project ICB-05 34 Figure: 5:1 Tree planting activity of Sub project ICB-1 36 Figure: 6:1 Borrow area situated at 110 km RHS of ICB-03 38 Figure 6:2 Borrow areas leveling of ICB-01 38 Figure: 6:3 Growth of native vegetation sub project ICB-1 38 Figure: 6:4 Existing large trees 38 Figure 7:1 Boulder fence and tree planting at soil disposal area along at the Uma-Oya- ICB-03 40 LIST OF TABLES Table: 8:1 Summary of the HIV/AIDS awareness programm 8 Table: 9:1 Summary of the tree planting activity in each sub-projects 9 Table: 3.1 Summary of the environmental mitigation measures of ICB-1 Subproject 19 Table: 3:2 Summary of the environmental mitigation measures of ICB-3 subproject 25 4 Table: 3:3 Summary of the environmental mitigation measures of ICB-5 Subproject 30 LIST Of APPENDICES Appendix: 1 Ongoing construction activities-Progress Photographs Appendix: 2 Rain fall data of each ICB subprojects Appendix: 3 Table of the observed environmental impacts and mitigation measures/ work progress Appendix: 4 Awareness of Sexually transmitted diseases (STD) and HIV/AIDS Appendix: 5 Tree planting activities Appendix: 6 Soil borrow area operation and rehabilitation: Appendix: 7 Disposal of soil/debris LIST OF ABBREVIATIONS ADB Asian Development Bank CEA Central Environmental Authority CRE Chief Residential Engineer DF Department of Forestry DWLC Department of Wild Life Conservation EA Environmental Assessment EIA Environmental Impact Assessment EMP Environmental Management Plan EMOP Environmental Monitoring Plan EPL Environmental Protection License 5 ES Environmental Specialist ESD Environmental & Social Division, RDA GSMB Geological Survey and Mines Bureau IEE Initial Environmental Examination IEER Initial Environmental Examination Report IML Industrial Mining License NHSP National Highway Sector Project PMU Project Management Unit RE Residential Engineer SC Supervision Consultant 6 ICB 4 – A006 Habarana – Kantale ICB 1- A012 (44 km) Puttalama – Nochchiyagama (50 km)+Ext. of (32km) ICB 2 – A026 Udathenna - Mahiyangana (40.8 km) ICB 3 – A005 ICB 5 に A004 Nuwara Eliya - Badulla (54.3 km) Nugegoda - Homagama Figure 1.1. Location map of selected road sections to be developed under NHSP National Highways Sector Project Semiannual Progress Report on Environmental Monitoring 7 January to July 2012 Executive Summary This report is the 8th semiannual report on environmental safeguards compliance of the seven subprojects under Asian Development Bank (ADB) funded National Highways Sector Project (NHSP). The reporting period is from January to July 2012. The five sub projects under NHSP are; 01. Puttalam-Nochchiyagama section of Puttalam Anuradhapura Trincomalee(A012) road (50 kms): ICB 1. (Extended section-Nochchiyagama to Anuradhapura, length of 32 km) 02. Udathenna-Mahiyangana section of Kandy-Mahiyangana-Padiyathalawa(A026) road (46 km): ICB- 2. 03. Nuwara Eliya-Badulla section of Peradeniya-Badulla-Chenkaladi(A005) road (57.6 km): ICB- 3. 04. Habarana-Kantale section of Ambepussa-Kurunegala-Trincomalee(A006) road (44 km): ICB- 4 and 05. Nugegoda-Homagama section of Colombo-Rathnapura-Wellawaya-Batticaloa(A004) road (12.1km): ICB- 5. In additional to above sub projects, construction of Highway Secretariat Building (Stage-1 and 2) is also handled by the NHSP and following road sections have been selected as a pilot project for Performance Base Maintenance. 1. Road Section from 60+000 to 96+000 km of Colombo椴Rathnapura椴Wellawaya椴Batticoloa Road (A-004). 2. Road section from 0+00 Km to 72 Km of Avissawella椴Hatton椴Nuwaraeliya Road (A-007). Construction works of the ICB-04 and ICB-02 have been completed and handed over to the RDA. The construction works are progressing in subprojects ICB-01(from 53 km to 83 km of A012 road), ICB -03 and ICB-05. Emission of dust (specially in dry weather period) due to road works was the most prominent problem in the reporting period. The Highway Secretariat Building is being finished its stage 1 and 2 construction works and the Performance Base Maintenance Project activities have also been implemented. There were no any adverse environmental issues recorded in the reporting period. 8 1. Introduction The following road sections have been selected for rehabilitate and improvement under National Highways Sector Project (NHSP). The project is funded by Asian Development Bank (ADB) through Loan 2217 (Sri). 01. Puttalam-Nochchiyagama section of Puttalam Anuradhapura Trincomalee (A012) road (50 kms): ICB 1. The additional sections for improvement are (1)From 53 km to 70 km (Nochchiyagama to Anuradhapura) (2) Service Road, Villu Road and original Puttalam-Trincomalee Road from 0 km to 2.6 km, (total 4.49 kms) (3) Pandulagama to Lion Pillar from 70 km to 76.75 km,(4) Jaffna Junction to Matale junction from 79.6 km to 83 km (3.4 kms) 02. Udathenna to Mahiyangana section of Kandy Mahiyangana Padiyathalawa (A026) road (40.8 km): ICB- 2. 03. Nuwara Eliya to Badulla section of Peradeniya, Badulla ,Chenkaladi (A005) road (54.9 km): ICB- 3. 04. Habarana to Kantale section of Ambepussa ,Kurunegala,Trincomalee (A006) road (44 km): ICB- 4 and 05. Nugegoda to Homagama section of Colombo Rathnapura, Wellawaya, Batticaloa (A004) road: ICB- 5. And following road sections have been selected for the Performance Base Maintenance such as 1. Colombo Rathnapura Wellawaya Batticoloa Road (A-004) from 60 Km to 96 km. 2. Avissawella Hatton Nuwaraeliya Road (A-007) from 0+00 Km to 72 km. Initial Environmental Examinations (IEE) had been carried out for all above subprojects except the Secretariat Building project and Performance Base Maintenance Contract. The impacts identified and mitigation measures suggested under the section Screening of Potential Impacts and Mitigation Measures of each Initial Environmental Examination Report (IEER) were summarized in to an Environmental Management Plan (EMP). An Environmental Monitoring Plan (EMOP) was also prepared for each subprojects that includes information on environmental parameters to be monitored, Location, time and frequency, cost for sampling and stage of subproject on which the monitoring should be conducted. The EMOP is considered to be a useful tool to monitor the implementation of mitigation measures and EMP. The EMP and EMOP of the approved IEERs of the five subprojects were incorporated into respective bid documents. The contractor is responsible of implementing the EMP and EMOP. The Supervision Consultant {(SC), SCOTT WILSON KIRKPATRICK & CO. LTD, UK (in association with) RDC, Sri Lanka} working under the Project Management Unit (PMU) is directly supervising the contractor in implementing the EMP. The PMU have the overall responsibility of monitoring the implementation of EMP. Implementation of the EMP of each contract is monitored by the SC on a monthly basis. 9 This report presents the status of environmental safeguards compliance with respect to each sub projects, for the period from January to July 2012. Information presented in this report is mainly based on observations made during monthly field inspections jointly carried out by the employer, engineer and the contractor. 1.1. Supervision Consultants role in environmental safeguards compliance As per task 2.10 on EMP and social impact mitigation requirements of appendix A of Tech form 4, the Team Leader (TL)/ Chief Residential Engineer (CRE)/ Residential Engineer (RE) with the ES of SC are responsible for assessment of the contractors proposed methods in relation with the stipulated EMP.
Recommended publications
  • Ensuring Sustainability in Sri Lanka's Growing Hotel Industry
    Ensuring Sustainability in Sri Lanka’s Growing Hotel Industry 2013 IFC Disclaimer “This publication may contain advice, opinions, and statements of various information providers and content providers. IFC does not represent or endorse the accuracy or reliability of any advice, opinion, statement or other information provided by any information provider or content provider, or any user of this publication or other person or entity.” Prepared on behalf of IFC - World Bank Group by PricewaterhouseCoopers (Private) Limited, Sri Lanka and PricewaterhouseCoopers (Private) Limited, India Table of Contents 01 The Sri Lankan Hotel Industry - An Overview 05 1.1. Tourism in Sri Lanka’s Economy 05 1.2. Classification of Tourist Accommodation 06 1.3. Tourist Hotels 07 02 Sri Lanka’s Highly Diverse Hotel Industry 10 2.1. Boutique Villas and Hotels 12 Over 100 New Hotels 2.2. Guesthouses 12 03 2.3. Tourist Hotels 13 15 Under Construction 2.4. Home Stay Units / Bungalows / 14 3.1. Boutique Villas and Hotels - 16 Rented Homes and Apartments Under Construction 3.2. Guesthouses - Under Construction 17 3.3. Tourist Hotels - Under Construction 17 3.4. Resorts - Under-construction 18 04 Resource Utilization in Sri Lanka - An Overview 19 Resource Utilization in Sri 4.1. Power and Energy Sector 19 05 4.2. Power Sector 21 Lankan Hotels 27 4.3. Water Sector 24 5.1. Energy and Water Consumption 28 4.4. Solid Waste Generation 25 5.2. Waste Generation and Management 30 5.3. Resource Efficiency Potential 31 5.4. Resource Efficiency Measures Taken by a 32 Few Sri Lankan Hotels 5.5.
    [Show full text]
  • World Bank Document
    Document of The World Bank FOR OFFICIAL USE ONLY Public Disclosure Authorized Report No: 3 8 147 - LK PROJECT APPRAISAL DOCUMENT ON A Public Disclosure Authorized PROPOSED CREDIT IN THE AMOUNT OF SDR 21.7 MILLION (US$32 MILLION EQUIVALENT) TO THE DEMOCRATIC SOCIALIST REPUBLIC OF SRI LANKA FOR A PUTTALAM HOUSING PROJECT Public Disclosure Authorized JANUARY 24,2007 Sustainable Development South Asia Region Public Disclosure Authorized This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization. CURRENCY EQUIVALENTS (Exchange Rate Effective December 13,2006) Currency Unit = Sri Lankan Rupee 108 Rupees (Rs.) = US$1 US$1.50609 = SDR 1 FISCAL YEAR January 1 - December 31 ABBREVIATIONS AND ACRONYMS ADB Asian Development Bank LTF Land Task Force AG Auditor General LTTE Liberation Tigers ofTamil Eelam CAS Country Assistance Strategy NCB National Competitive Bidding CEB Ceylon Electricity Board NGO Non Governmental Organization CFAA Country Financial Accountability Assessment NEIAP North East Irrigated Agriculture Project CQS Selection Cased on Consultants Qualifications NEHRP North East Housing Reconstruction Program CSIA Continuous Social Impact Assessment NPA National Procurement Agency CSP Camp Social Profile NPV Not Present Value CWSSP Community Water Supply and Sanitation NWPEA North Western Provincial Environmental Act Project DMC District Monitoring Committees NWPRD NorthWest Provincial Roads Department
    [Show full text]
  • CHAP 9 Sri Lanka
    79o 00' 79o 30' 80o 00' 80o 30' 81o 00' 81o 30' 82o 00' Kankesanturai Point Pedro A I Karaitivu I. Jana D Peninsula N Kayts Jana SRI LANKA I Palk Strait National capital Ja na Elephant Pass Punkudutivu I. Lag Provincial capital oon Devipattinam Delft I. Town, village Palk Bay Kilinochchi Provincial boundary - Puthukkudiyiruppu Nanthi Kadal Main road Rameswaram Iranaitivu Is. Mullaittivu Secondary road Pamban I. Ferry Vellankulam Dhanushkodi Talaimannar Manjulam Nayaru Lagoon Railroad A da m' Airport s Bridge NORTHERN Nedunkeni 9o 00' Kokkilai Lagoon Mannar I. Mannar Puliyankulam Pulmoddai Madhu Road Bay of Bengal Gulf of Mannar Silavatturai Vavuniya Nilaveli Pankulam Kebitigollewa Trincomalee Horuwupotana r Bay Medawachchiya diya A d o o o 8 30' ru 8 30' v K i A Karaitivu I. ru Hamillewa n a Mutur Y Pomparippu Anuradhapura Kantalai n o NORTH CENTRAL Kalpitiya o g Maragahewa a Kathiraveli L Kal m a Oy a a l a t t Puttalam Kekirawa Habarane u 8o 00' P Galgamuwa 8o 00' NORTH Polonnaruwa Dambula Valachchenai Anamaduwa a y O Mundal Maho a Chenkaladi Lake r u WESTERN d Batticaloa Naula a M uru ed D Ganewatta a EASTERN g n Madura Oya a G Reservoir Chilaw i l Maha Oya o Kurunegala e o 7 30' w 7 30' Matale a Paddiruppu h Kuliyapitiya a CENTRAL M Kehelula Kalmunai Pannala Kandy Mahiyangana Uhana Randenigale ya Amparai a O a Mah Reservoir y Negombo Kegalla O Gal Tirrukkovil Negombo Victoria Falls Reservoir Bibile Senanayake Lagoon Gampaha Samudra Ja-Ela o a Nuwara Badulla o 7 00' ng 7 00' Kelan a Avissawella Eliya Colombo i G Sri Jayewardenepura
    [Show full text]
  • Evaluation of Agriculture and Natural Resources Sector in Sri Lanka
    Evaluation Working Paper Sri Lanka Country Assistance Program Evaluation: Agriculture and Natural Resources Sector Assistance Evaluation August 2007 Supplementary Appendix A Operations Evaluation Department CURRENCY EQUIVALENTS (as of 01 August 2007) Currency Unit — Sri Lanka rupee (SLR) SLR1.00 = $0.0089 $1.00 = SLR111.78 ABBREVIATIONS ADB — Asian Development Bank GDP — gross domestic product ha — hectare kg — kilogram TA — technical assistance UNDP — United Nations Development Programme NOTE In this report, “$” refers to US dollars. Director General Bruce Murray, Operations Evaluation Department (OED) Director R. Keith Leonard, Operations Evaluation Division 1, OED Evaluation Team Leader Njoman Bestari, Principal Evaluation Specialist Operations Evaluation Division 1, OED Operations Evaluation Department CONTENTS Page Maps ii A. Scope and Purpose 1 B. Sector Context 1 C. The Country Sector Strategy and Program of ADB 11 1. ADB’s Sector Strategies in the Country 11 2. ADB’s Sector Assistance Program 15 D. Assessment of ADB’s Sector Strategy and Assistance Program 19 E. ADB’s Performance in the Sector 27 F. Identified Lessons 28 1. Major Lessons 28 2. Other Lessons 29 G. Future Challenges and Opportunities 30 Appendix Positioning of ADB’s Agriculture and Natural Resources Sector Strategies in Sri Lanka 33 Njoman Bestari (team leader, principal evaluation specialist), Alvin C. Morales (evaluation officer), and Brenda Katon (consultant, evaluation research associate) prepared this evaluation working paper. Caren Joy Mongcopa (senior operations evaluation assistant) provided administrative and research assistance to the evaluation team. The guidelines formally adopted by the Operations Evaluation Department (OED) on avoiding conflict of interest in its independent evaluations were observed in the preparation of this report.
    [Show full text]
  • Dry Zone Urban Water and Sanitation Project – Additional Financing (RRP SRI 37381)
    Dry Zone Urban Water and Sanitation Project – Additional Financing (RRP SRI 37381) DEVELOPMENT COORDINATION A. Major Development Partners: Strategic Foci and Key Activities 1. In recent years, the Asian Development Bank (ADB) and the Government of Japan have been the major development partners in water supply. Overall, several bilateral development partners are involved in this sector, including (i) Japan (providing support for Kandy, Colombo, towns north of Colombo, and Eastern Province), (ii) Australia (Ampara), (iii) Denmark (Colombo, Kandy, and Nuwaraeliya), (iv) France (Trincomalee), (v) Belgium (Kolonna–Balangoda), (vi) the United States of America (Badulla and Haliela), and (vii) the Republic of Korea (Hambantota). Details of projects assisted by development partners are in the table below. The World Bank completed a major community water supply and sanitation project in 2010. Details of Projects in Sri Lanka Assisted by the Development Partners, 2003 to Present Development Amount Partner Project Name Duration ($ million) Asian Development Jaffna–Killinochchi Water Supply and Sanitation 2011–2016 164 Bank Dry Zone Water Supply and Sanitation 2009–2014 113 Secondary Towns and Rural Community-Based 259 Water Supply and Sanitation 2003–2014 Greater Colombo Wastewater Management Project 2009–2015 100 Danish International Kelani Right Bank Water Treatment Plant 2008–2010 80 Development Agency Nuwaraeliya District Group Water Supply 2006–2010 45 Towns South of Kandy Water Supply 2005–2010 96 Government of Eastern Coastal Towns of Ampara
    [Show full text]
  • (COVID-19) - Situation Report – 02.06.2021– 10 A.M
    Epidemiology Unit Ministry of Health 231, De Saram Place, Colombo 10, Sri Lanka Tele: (+94 11) 2695112, 2681548, 4740490, 4740491, 4740492 Fax: (+94 11) 2696583 E-mail: [email protected], [email protected] Web: www.epid.gov.lk Coronavirus disease 2019 (COVID-19) - Situation Report – 02.06.2021– 10 a.m. An outbreak of pneumonia of unknown reason was first reported on 31st December 2019 from Wuhan City in Hubei Province of China. On 7th Jan 2020, it was diagnosed as “Novel Corona Virus”. On 30/01, WHO has declared it as a Public Health Emergency of COVID-19 Vaccination 1st Dose 2nd Dose International Concern (PHEIC). On 11/02/2020 the WHO Covishield Vaccine 925242 348582 renamed the disease as COVID-19 and on 11/03/2020 declared Sinopharm Vaccine 797205 2435 as pandemic. The incubation period is reported as 2-14 days. Patients identified in last 24H Sputnik V 44189 - Total Confirmed 2877 Cumulative Cases per 1 COVID-19 deaths per 1 Country .Returnees (+ close contacts) Sri Lankans 32 million population million population from other countries Foreigners 0 Sri Lanka 8680 70 Kandakadu Rehab. Center detainees and their contacts 0 India 20214 236 Hospital samples (admitted with clinical signs/symptoms) 0 Singapore 10751 5.4 1180 36 New Year Cluster 2845 Australia South East Asian Region 15635 199 Prison cluster 0 Details of COVID 19 diagnosed patients – Last 24H District 1st Wave 2nd 3rd Wave Total Colombo 174 Wave32123 16518 48815 Number COVID Discharged Number Number Gampaha 51 18483 14163 32697 inward as at 19 from the of deaths inward/waiting Kalutara 72 6986 12630 19688 yesterday-10 Positive hospital – – last 24H to admit as at Kandy 19 5710 4437 10166 am – last last 24H today-10 am Kurunagala 30 3191 6113 9334 Galle 4 2645 5091 7740 24H Ratnapura 9 3654 4023 7686 25670* 2877 1504 43 27000 Matara 4 1544 2750 4298 *Discharges of the private hospitals/ITC and prison hospital were deducted.
    [Show full text]
  • Puttalam Lagoon System an Environmental and Fisheries Profile
    REGIONAL FISHERIES LIVELIHOODS PROGRAMME FOR SOUTH AND SOUTHEAST ASIA (RFLP) --------------------------------------------------------- An Environmental and Fisheries Profile of the Puttalam Lagoon System (Activity 1.4.1 : Consolidate and finalize reports on physio-chemical, geo-morphological, socio-economic, fisheries, environmental and land use associated with the Puttalam lagoon ecosystem) For the Regional Fisheries Livelihoods Programme for South and Southeast Asia Prepared by Sriyanie Miththapala (compiler) IUCN, International Union for Conservation of Nature, Sri Lanka Country Office October 2011 REGIONAL FISHERIES LIVELIHOODS PROGRAMME FOR SOUTH AND SOUTHEAST ASIA (RFLP) – SRI LANKA An Environmental and Fisheries Profile of the Puttalam Lagoon System (Activity 1.4.1- Consolidate and finalize reports on physio-chemical, geo-morphological, socio-economic, fisheries, environment and land use associated with Puttalam lagoon ecosystem) For the Regional Fisheries Livelihoods Programme for South and Southeast Asia Prepared by Sriyanie Miththapala (compiler) IUCN, International Union for Conservation of Nature, Sri Lanka Country Office October 2011 i Disclaimer and copyright text This publication has been made with the financial support of the Spanish Agency of International Cooperation for Development (AECID) through an FAO trust-fund project, the Regional Fisheries Livelihoods Programme (RFLP) for South and Southeast Asia. The content of this publication does not necessarily reflect the opinion of FAO, AECID, or RFLP. All rights reserved. Reproduction and dissemination of material in this information product for educational and other non-commercial purposes are authorized without any prior written permission from the copyright holders provided the source is fully acknowledged. Reproduction of material in this information product for resale or other commercial purposes is prohibited without written permission of the copyright holders.
    [Show full text]
  • Dealer Centers
    Mobitel Branches Addresses Monday to Friday Saturday Sunday From To From To From To Mobitel Flagship Centre No. 108, W.A.D. Ramanayake Mw, Colombo 2 8.00 A.M. 7.00 P.M. 9.00 A.M. 5.00 P.M. 9.00 A.M. 5.00 P.M. M3 Experience Centre Excel World, 338, T.B. Jayah Mw, Colombo 10 9.30 A.M. 8.00 P.M. 9.30 A.M. 11.00 P.M. 9.30 A.M. 11.00 P.M. Colombo Branch No. 30, Queens Rd, Colombo 3 8.00 A.M. 6.00 P.M. 9.00 A.M. 5.00 P.M. 10.00 A.M. 5.00 P.M. Airport Arrival Branch Arrival Public Concourse, BIA, Katunayake 24 Hours Open Airport Departure Branch Shop No. 10, Departure Concourse, BIA, Katunayake Following Mobiltel Branches will be open on Sundays only for Registration/Re-Registration Anuradhapura Branch 213/7, Dhamsiri Building, Bank Place, Main Street, Anuradhapura 8.00 A.M. 6.00 P.M. 9.00 A.M. 4.00 P.M. *9.00 A.M. 4.00 P.M. Kandy Branch 141, Kotugodella Street, Kandy 8.00 A.M. 6.00 P.M. 9.00 A.M. 4.00 P.M. *9.00 A.M. 4.00 P.M. Kurunegala Branch 180C, Colombo Rd, Kurunegala 8.00 A.M. 6.00 P.M. 9.00 A.M. 4.00 P.M. *9.00 A.M. 4.00 P.M. Matara Branch No. 15, LGJ Building, Beach Road, Matara 8.00 A.M.
    [Show full text]
  • ADCHA/OFDA Yemen Complex Program
    FY 2011 AND ACTIVE HUMANITARIAN ASSISTANCE TO SRI LANKA FOR FLOODS AND THE COMPLEX EMERGENCY 10° NORTHERN 80° 81° KEY82° 10° !0 FAO A Kankesanturai Point Pedro USAID/OFDA USAID/FFP IOM USAID/OTI USAID/Sri Lanka a Kayts JaffnaJaffna Practical Action AC Jaffna State/PRM State/PM/WRA Sarvodaya AC A Agriculture and Food Security J H Sewalanka ACIJ Cash-for-Work OCHA } Demining B Kilinochchi World Vision C KilinochchiKilinochchi Economic Recovery and !0 Puthukkudiyiruppu C Market Systems ZOARamesvaram CIJ A Nanthi Humanitarian Coordination WFP MullaittivuMullaittivu Kadal B and Information Management Mullaittivu Vellankulam Mankulam DAI a Logistics and Emergency Talaimannar a FAO Nedunkeni Relief Supplies A NORTHERNNORTHERN Antares9° Foundation Puliyankulam Mental Health Support for 9° Mannar Humanitarian Workers UNHCR VavuniyaVavuniya Pulmoddai G MannarMannar G Protection DDG } Paraiyanalankulam Yan Vavuniya Oya I Shelter and Settlements FSD } Silavatturai TrincomaleeTrincomalee Title II Emergency HALO Trust } Kebitigollewa Pan Kulam Nilaveli Food Assistance MAG Water, Sanitation, and Hygiene } Medawachchiya !0 J Trincomalee MLI } Horowupotana 09/30/11 AnuradhapuraAnuradhapura EASTERN Pomparippu Anuradhapura Kantale Aruvi Sarvodaya Yan Oya ACJ Aru Kalpitiya Maragahawewa Sewalanka Kala NORTH-CENTRALNORTH-CENTRAL ACJ Oya PolonnaruwaPolonnaruwa FAO A SC/US Kekirawa Minneriya a Puttalam ACTED H 8° PuttalamPuttalam 8° Polonnaruwa WFP Anamaduwa Dambulla DAI NORTH-WESTERNNORTH-WESTERN !0 a Gulf of BatticaloaBatticaloa UNHCR Deduru G Oya Mannar Oya
    [Show full text]
  • Mapping Coastal Landscapes in Sri Lanka - Report
    Mapping coastal landscapes in Sri Lanka - Report - contact : Jil Bournazel [email protected] November 2013 (reviewed April 2014) Table of Content List of Figures ...................................................................................................................ii List of Tables ....................................................................................................................ii Acronyms .........................................................................................................................ii Context ............................................................................................................................1 I- Aquaculture and mangrove forests in five areas of interest..........................................2 1-1 Study area ......................................................................................................2 1-2 Method ............................................................................................................3 1-3 Results ............................................................................................................5 II- Land cover changes in Puttalam lagoon .....................................................................7 2-1 1992/1994 data set .........................................................................................7 2-2 2012 data set ..................................................................................................7 2-3 Time series .....................................................................................................8
    [Show full text]
  • Reference Map
    SRI LANKA - Reference Map Tellippalai Point Pedro Chankanai Karaveddy J A F F N A Bay of Uduvil Bengal Kayts Kopai North Palk Strait Velanai Nallur Chavakachcheri Jaffna Maruthankerny Pallai Marelithurai Kandavalai Kilinochchi K I L I N O C H C H I Puthukudiyiruppu Palk Bay Mullaittivu MMUULLL AATTTTIIVVUU Tunukkai Oddusuddan INDIA Kokkilai Mannar N O R T H E R N Lagoon Adampam Padavi Siripura Gulf of Madhu Padawiya Mannar M A N N A R Kuchchaveli VAV U N I YA Yan Oya Silavatturai Vavuniya Gomarankadawala Kebitigollewa Elevation (meters) 5,000 and above Morawewa Trincomalee 4,000 - 5,000 Mahawilachchiya Horowupotana Tampalakamam Koddiyar Bay A N U R A D H A P U R A Periyakinniya 3,000 - 4,000 Mutur N O R T H C E N T R A L 2,500 - 3,000 Mihintale Seruvila 2,000 - 2,500 Anuradhapura Galenbindunuwewa T R I N C O M A L E E Nochchiyagama 1,500 - 2,000 Kala Oya Aruvi Aru Kalpitiya Verukal Nachchaduwa 1,000 - 1,500 Vannatavillu Puttalam 800 - 1,000 Lagoon PUTTALAM 600 - 800 Karuwalagaswewa Palugaswewa P O L O N N A R U WA Kekirawa 400 - 600 Puttalam Lankapura Nawagattegama Kudagalnewa 200 - 400 Welikanda 0 - 200 Anamaduwa Polonnaruwa Below sea level Mahakumbukkadawala Dambulla Mundal Mundel Lake P U T TA L A M Elahera B AT T I C A L O A Batticaloa Pallama Deduru Oya Madura Oya Arachchikattuwa M ATA L E Madura Oya Chilaw N O R T H W E S T E R N Reservoir E A S T E R N Madampe Matale Kurunegala Maha Oya Pahala Mahawewa Kalmunai Nattandiya C E N T R A L Sammanthurai Saintamaruthu Wennappuwa Oya Uhana Nintavur aha Dankotuwa M Kandy Ganga Mahaweli
    [Show full text]
  • Customer Name Town District Contact Number 1 Contact Number 2
    CONTACT CONTACT CUSTOMER NAME TOWN DISTRICT NUMBER 1 NUMBER 2 Victoriya Motors Ampara Ampara 0772250560 Asiri Motors Ampara Ampara 0772632898 Weligama Motors Ampara Ampara 0777570357 0632224416 A M N Motors Samanthurei Ampara 0756218131 Wijayadoru Amal Indu Shantha Dehiattakandiya Ampara 0776808080 J T Motors Akkaraipattu 02 Ampara 0777790316 Nandasena Motors Ampara Ampara 0632222416 Seedevi Motor Traders Anuradapura Anuradhapura 0771826040 0252235323 New Rajarata Motors Kekirawa Anuradhapura 0773425511 0254992020 Shan Motors Nochchiyagama Anuradhapura 0252257525 D. D. B. Service Station Eppawala Anuradhapura 0252249327 Indunila Multi Centre Rambewa Anuradhapura 0717597018 0252266500 Anura Motors Mahiyangana Badulla 0774954117 Samaru Motor Enterprises Welimada Badulla 0778793796 A M S Motors Mahiyanganaya Badulla 0552258420 0727673626 Shan Motors Mahiyangana Badulla 0715774331 Harshani Motors Badulla Badulla 0777593601 0552230700 Victory Motor Service Mahiyanganaya Badulla 0763800650 0552257315 Hero Motors Bandarawela Badulla 0777155836 0574926949 Faida Tyre House Welimada Badulla 0776508382 T R Engineering Co Ltd Bandarawela Badulla 0572230976 Pathman Motors Batticaloa Batticaloa 0773322371 0652222040 City Motors Kalmunai Batticaloa 0771105756 Thaya Motor Stores Batticaloa Batticaloa 0772241077 0652222156 Ashik Motors Valachchenei Batticaloa 0772633349 Sasis Motor Stores Batticaloa Batticaloa 7771421255 A I N Motors Homagama Colombo 0777711142 Sunbeam Eng & Overseas Trades Colombo 14 Colombo 0777363322 0772447337 Amila Motor Stores Kottawa
    [Show full text]