EPR (nuclear reactor)

Computer generated view of an EPR power plant

The EPR is a third generation pressurized water reac- tor (PWR) design. It has been designed and developed mainly by Framatome (now Areva NP) and Électricité de France (EDF) in France, and Siemens in Germany. In Europe this reactor design was called European Pres- surized Reactor, and the internationalized name was Evolutionary Power Reactor, but it is now simply named EPR by Areva. Four EPR units are under construction. The first two, in and France, are both facing costly construction delays (to at least 2018). Construction commenced on two Chinese units in 2009 and 2010.[1] The Chinese units were to start operation in 2014 and 2015,[2] but are now expected to come online in 2016 and 2017.[3]

1 Design

The main design objectives of the third generation EPR design are increased safety while providing enhanced economic competitiveness through improvements to pre- vious PWR designs scaled up to an electrical power out- put of around 1650 MWe (net)[4] with thermal power 4500 MWt. The reactor can use 5% enriched uranium oxide fuel, reprocessed uranium fuel and 100% mixed uranium plutonium oxide fuel. The EPR is the evolution- ary descendant of the Framatome N4 and Siemens Power Reactor pressure vessel of the EPR Generation Division “Konvoi” reactors.[5][6] The EPR design has several active and passive protection continues for 1 to 3 years after the reactor’s initial measures against accidents: shutdown (i.e., 300% redundancy) • Leaktight containment around the reactor • Four independent emergency cooling systems, each providing the required cooling of the decay heat that • An extra container and cooling area if a molten

1 2 2 OLKILUOTO 3 (AREVA’S FIRST PLANT)

core manages to escape the reactor (see containment building) • Two-layer concrete wall with total thickness 2.6 me- ters, designed to withstand impact by aeroplanes and internal overpressure

The EPR has a design maximum core damage frequency of 6.1 × 10−7 per plant per year.[7] The EPR was designed to use uranium more efficiently Olkiluoto-3 under construction in 2009. It is scheduled to start than older Generation II reactors, using approximately electricity production in 2018, a delay of nine years. 17% less uranium per unit of electricity generated than these older reactor technologies.[8] scheduled to go online in 2009,[13] but the project has The Union of Concerned Scientists referred to the EPR suffered many delays, and according to Areva operations in Dec 2007 as the only new reactor design under con- are expected to start in 2018.[14] The plant will have an sideration in the United States that "...appears to have the electrical power output of 1600 MWe (net).[4] The con- potential to be significantly safer and more secure against struction is a joint effort of French Areva and German [9] attack than today’s reactors.” Siemens AG through their common subsidiary Areva NP, On 4 November 2009, the nuclear power regulatory au- for Finnish operator TVO. Initial cost estimates were thorities in France, Finland and the United Kingdom is- about €3.7 billion,[15] but the project has since seen sev- sued a joint letter to Areva, citing serious problems with eral severe cost increments and delays. the EPR’s digital Instrumentation and Control systems (I&C).[10] The letter stated: 2.1 Progress “The issue is primarily around ensuring the adequacy of the safety systems (those used to In May 2006, construction delays of about one year were maintain control of the plant if it goes out- announced, following quality control problems across the side normal conditions), and their indepen- construction. In part the delays were due to the lack dence from the control systems (those used to of oversight of subcontractors inexperienced in nuclear operate the plant under normal conditions). construction.[16][17] The delays led to disappointing finan- Independence is important because, if a cial results for the Areva NP. It blamed delays on the safety system provides protection against the Finnish approach to approving technical documentation failure of a control system, then they should and designs.[18][19] not fail together. The EPR design, as origi- In December 2006, TVO announced construction was nally proposed by the licensees and the manu- about 18 months behind schedule so completion was now facturer, AREVA, doesn’t comply with the in- expected 2010–11, and there were reports that Areva was dependence principle, as there is a very high preparing to take a €500 million charge on its accounts degree of complex interconnectivity between for the delay.[20][21] the control and safety systems.” At the end of June 2007, it was reported that In 2013 EDF acknowledged the difficulties it was hav- Säteilyturvakeskus, the Finnish Radiation and Nuclear Safety Authority, had found a number of safety-related ing building the EPR design, with its head of produc- [22] tion and engineering, Hervé Machenaud, saying EDF had design and manufacturing 'deficiencies’. In August lost its dominant international position in design and con- 2007, a further construction delay of up to a year was re- struction of nuclear power stations. Machenaud indicated ported associated with construction problems in reinforc- EDF was considering designing two new lower powered ing the reactor building to withstand an airplane crash, and the timely supply of adequate documentation to the reactors, one with output of 1,500 MWe and the other [23][24][25] 1,000 MWe. Machenaud stated there would be a period Finnish authorities. of reflection on the best way to improve the EPR design In September 2007, TVO reported the construction de- to lower its price and incorporate post-Fukushima safety lay as “at least two years” and costs more than 25% improvements.[11] over budget.[26] Cost estimates by analysts for the over- run range up to €1.5 billion.[27] A further delay was announced in October 2008, mak- 2 Olkiluoto 3 (Areva’s first plant) ing the total delay three years, giving an expected online date of 2012.[28] The parties are in arbitration to resolve The construction of the Olkiluoto 3[12] power plant in a dispute over responsibility for the delays and final cost Finland commenced in August 2005. It was initially overruns.[29][30] 3

As of May 2009, the plant was at least three and a half the welds inspected in the secondary containment steel years behind schedule and more than 50 percent over- liner are not in accordance with norms, and that cracks budget. Areva and the utility involved “are in bitter dis- have been found in the concrete base. EDF stated that pute over who will bear the cost overruns and there is a progress was being made on these issues raised very early real risk now that the utility will default”.[31] In August in construction;[44] however, on 21 May ASN ordered a 2009, Areva announced €550 million additional provi- suspension of concrete pouring on the site.[45] A month sions for the build, taking plant costs to €5.3 billion, and later concreting work resumed after ASN accepted EDF’s wiped out interim operating profits for the first half-year corrective action plan which included external oversight of 2009.[32] checks.[46] The dome of the containment structure was topped In May 2009 professor Stephen Thomas reported that af- out in September 2009.[33] 90% of procurement, 80% ter 18 months of construction and after a series of qual- of engineering works and 73% of civil works were ity control problems, the project is “more than 20 per- completed.[34] cent over budget and EDF is struggling to keep it on [31] In June 2010, Areva announced €400 million of fur- schedule”. ther provisions, taking the cost overrun to €2.7 bil- In August 2010 the regulator, ASN, reported further lion. The timescale slipped to the end of 2012 from welding problems on the secondary containment steel June 2012,[35][36] Areva’s Overruns at Finnish Nuclear liner.[47] The same month EDF announced that costs had Plant Approach Initial Cost with operation set to start in increased 50% to €5 billion, and commissioning was de- 2013.[37] In December 2011, TVO announced a further layed by about two years to 2014.[47] [38] delay to August 2014. As of July 2012, the plant was In July 2011 EDF announced that the estimated costs had scheduled to start electricity production no earlier than escalated to €6 billion and that completion of construc- 2015, a schedule slippage of at least six years.[39] In De- tion was delayed to 2016[48] cember 2012 Areva’s Chief Executive estimated costs to €8 billion.[40] On 3 December 2012 EDF announced that the estimated costs had escalated to €8.5 billion[49] In September 2014 Areva announced that operations would start in 2018.[14] In December 2012 the Italian power company Enel an- nounced it was relinquishing its 12.5% stake in the project, and 5 future EPRs, so would be reimbursed its 3 Flamanville 3 (EDF’s first plant) project stake of €613 million plus interest.[50][51] In November 2014 EDF announced that completion of See also: Nuclear power in France construction was delayed to 2017 due to delays in com- ponent delivery by Areva.[52] First concrete was poured for the demonstration EPR re- In April 2015 Areva informed the French nuclear regula- actor at the Flamanville Nuclear Power Plant on 6 De- tor that anomalies had been detected in the reactor vessel cember 2007.[41] As the name implies this will be the steel, causing “lower than expected mechanical toughness [3] third nuclear reactor on the Flamanville site and the sec- values”. Further tests are underway. In July 2015 The ond instance of an EPR being built. Electrical output will Daily Telegraph reported that Areva had been aware of [53] be 1630 MWe (net)[4] and the project involves around this problem since 2006. [42] €3.3 billion of capital expenditure from EDF. In June 2015 multiple faults in cooling system safety valves were discovered by ASN.[54] 3.1 Progress In September 2015 EDF announced that the estimated costs had escalated to €10.5 billion, and the start-up of From 19 October 2005 to 18 February 2006 the project the reactor was delayed to the fourth quarter of 2018.[55] was submitted to a national public debate. On 4 May 2006 the decision was made by EDF’s Board of Directors to continue with the construction. 4 Taishan 1 & 2 (CGNPC’s first Between 15 June and 31 July 2006 the unit underwent a plants) public enquiry, which rendered a “favorable opinion” on [43] the project. That summer site preparation works be- See also: Nuclear power in China gan.

In December 2007 construction of the unit itself began. In 2006, there was a bidding in process to build four new This was expected to last 54 months. nuclear reactors in China,[56] Areva SA lost this bid in In April 2008 the French nuclear safety agency (Au- favor of Westinghouse Electric Company to build four torité de sûreté nucléaire, ASN) reported that a quarter of AP1000 reactors, because of its refusal to transfer the 4 6 LOST OPPORTUNITIES expertise and knowledge to China. agreement had been reached regarding the nuclear plants In February 2007 Areva won a deal, worth about €8 to be built on the site of Hinkley Point C. EDF Group and billion[57] ($10.5 billion) for two EPRs located in Taishan, the UK Government agreed on the key commercial terms Guangdong Province in southern China, in spite of stick- of the investment contract. The final investment decision ing to its previous conditions.[58] If achieved, this would was conditional on completion of the remaining key steps, make the Taishan EPRs about half the current projected including the agreement of the European Commission. final cost of Olkiluoto. The General Contractor and On 8 October 2014 the European Commission an- Operator is the China Guangdong Nuclear Power Com- nounced their agreement of the construction and energy pany. In November 2007, French president Nicolas production of Hinkley Point C nuclear power plant with Sarkozy signed a $12 billion deal that will allow the third 16 out of 28 commissioners agreeing with the go ahead and fourth EPR units to be constructed in China.[59] of the construction.

4.1 Progress 5.2 France

The construction of the first reactor at Taishan started In July 2008 the French President announced a second officially on 18 November 2009, and the second on 15 [60] EPR would be built in France due to high oil and gas April 2010. Construction of each unit is planned to prices.[73] Penly was chosen as the site in 2009, with con- take 46 months, significantly faster and cheaper than the [74] [61] struction planned to start in 2012. However, in 2011, first two EPRs in Finland and France. This means the following the Fukushima Daiichi nuclear disaster, EDF unit should have been finished in March 2014. postponed public consultations.[75] In 2013, EDF con- The vessel of the first reactor has been installed in June firmed there was no start plan for Penly, as current de- 2012.[62] mand did not warrant it.[76] In 2014 the build was reported to be running over two years late, mainly due to key component delays and 5.3 India project management issues.[63] In 2015, EDF reported that the first reactor was likely to See also: Nuclear power in India come online by the end of the year.[64] In February 2009, the Nuclear Power Corporation of In- dia (NPCIL) signed a memorandum of understanding 5 Possible future power plants with Areva to set up two 1650 MWe reactors at Jaitapur in Maharashtra. 5.1 United Kingdom In December 2010, NPCIL signed a framework agree- ment with Areva for 2 EPRs and 25 years’ supply of nu- See also: Nuclear power in the United Kingdom clear fuel.[77] The contract and pricing is yet to be fi- nalised. Construction is unlikely to start soon because of The EPR is undergoing Generic Design Assessment regulatory issues and difficulty in sourcing major compo- by the Office for Nuclear Regulation, along with the nents from Japan due to India not being a signatory to the [78] Westinghouse AP1000.[65] Interim Design Acceptance Nuclear Non-Proliferation Treaty. Confirmations were postponed until lessons from the NPCIL has ambitions to build up to 9900MW at the Jaita- Fukushima Daiichi nuclear disaster had been taken into pur site, equating to 6 EPRs.[79][80] account.[66] EDF bought British Energy in 2009. EDF planned to build 4 new EPRs,[67] subject to electricity pric- 6 Lost opportunities ing agreement with the government.[68][69] NuGeneration also wants to build new nuclear power, possibly 2 EPRs 6.1 Abu Dhabi or 3 AP1000s.[70] Areva has signed a strategic partnership with Rolls-Royce See also: Nuclear power in the United Arab Emirates to support the build of EPRs.[71] On 19 March 2013 plan- ning consent for Hinkley Point C nuclear power station In March 2008, French president Nicolas Sarkozy was given, but difficult negotiations with the UK govern- reached an agreement with the UAE cabinet that “outlines ment about electricity pricing, and project financing with a cooperation framework for the assessment and possible private investors, needed to be concluded before building [72] use of nuclear energy for peaceful ends.” This agreement starts. was not a contract for EPR construction by any of the On 21 October 2013, EDF Energy announced that an French nuclear companies, Total S.A., Suez or Areva.[81] 6.4 Finland 5

In May 2009, US President Barack Obama signed a sim- application in July 2007 for a proposed third unit at the ilar agreement with the UAE. The deal, which has not Calvert Cliffs Nuclear Power Plant in Maryland. How- yet been ratified by the US Congress, pledges US aid in ever, both proposals were subsequently cancelled. the development of a civilian nuclear energy program in In April 2009, Missouri legislators balked at preconstruc- the UAE. Contracts for reactors were not given, nor was tion rate increases, prompting AmerenUE to suspend there any guarantee made that US companies would re- [90][91] [82] plans for its reactor. In July 2010, Constellation En- ceive them. ergy Group cut spending on UniStar for the Calvert Cliffs In December 2009 the United Arab Emirates declined Nuclear Power Plant because of uncertainties for a loan both the American and French bids and awarded a con- guarantee from the U.S. Department of Energy,[92][93] tract for construction of four non-EPR plants (APR- and subsequently pulled out of the project.[94] In Octo- 1400) to a South Korean group including Korea Electric ber 2008, Areva announced that it will partner with US Power Corporation, Hyundai Engineering and Construc- defense firm Northrop Grumman to establish a US$380 tion, Samsung and Doosan Heavy Industries.[83] million facility to construct modules and assemblies for After losing this order, Areva is considering whether it the EPR and US-EPR reactors at Northrop Grumman’s Newport News Shipyard in Virginia.[95][96] The project should reintroduce the marketing of a smaller and simpler [97] second-generation reactor design alongside the EPR, for was suspended indefinitely in May 2011. countries that are new to nuclear power.[84] As of 2011 Areva and Mitsubishi Heavy Industries offer a smaller 6.4 Finland 1100MWe ATMEA1 Generation III PWR.[85] See also: 6.2 Italy In 2010 the Finnish parliament decided to allow two new See also: Nuclear power in Italy reactors. Both TVO and Fennovoima were consider- ing the EPR.[98][99] In December 2013 Fennovoima con- firmed it had selected a Russian AES-2006 VVER pres- On 24 February 2009, Italy and France agreed to study [100] the feasibility of building 4 new nuclear power stations surized water reactor in preference to the EPR. in Italy.[86] Following this, on 3 August 2009, EDF and Enel established a joint venture, Sviluppo Nucleare Italia, 6.5 The Czech Republic to study the feasibility of building at least four EPRs.[87] However, in the 2011 referendum, soon after the In October 2012 CEZ announced that Areva was elim- Fukushima nuclear disaster, Italians voted to abrogate the inated from the tender for the construction of 2 reac- new regulations permitting nuclear power in Italy. Abro- tors for Temelin nuclear plant. Areva failed to comply gation of laws is put in effect when at least 50%+1 elec- with legal requirements of the tender.[101] In April 2014 tors make a valid vote and a majority of these voters are CEZ cancelled a tender, because of low power prices and in favour of abrogation. In this referendum there was a government’s decision refusal of guarantees for energy 55% valid voter turnout and 94% voted to abrogate the price.[102] new regulations.

6.3 United States 7 See also • See also: Nuclear power in the United States Economics of new nuclear power plants • Nuclear power by country The US-EPR, the version of the EPR submitted to the U.S. regulator,[88] is one of the competitors for the next generation of nuclear plants in the United States, along 8 References with the AP1000 and the ESBWR. In February 2015 Areva asked to suspend the Design Certification Appli- [1] Geert De Clercq (31 July 2014). “EDF hopes French EPR cation Review process at the U.S. Nuclear Regulatory will launch before Chinese reactors”. Reuters. Retrieved Commission (NRC).[88] It had been under review there 9 December 2014. with expectation to submit an application for final de- sign approval and standard design certification since 14 [2] Symbolic milestone for Finnish EPR, World Nuclear December 2007.[89] UniStar, Amarillo Power, PPL Corp News, 24 October 2013. and AmerenUE announced plans to file a Combined Con- [3] “Flamanville EPR vessel anomalies under scrutiny”. struction and Operating License application in 2008 for World Nuclear News. 7 April 2015. Retrieved 11 April the US-EPR at its Callaway plant. UniStar filed a partial 2015. 6 8 REFERENCES

[4] “New Build Field Report” (PDF). Areva. 6 October 2010. [24] Nuclear industry’s flagship plant delayed again, Huliq, 11 p. 4. Retrieved 5 March 2011. August 2007.

[5] Andrew Teller (2 February 2010). “The EPR Reac- [25] Areva delay threatens China contract, MSNBC, 10 August tor: Evolution to Gen III+ based on proven technology” 2007. (PDF). Areva. Retrieved 19 July 2010. [26] Alan Katz (5 September 2007). “Nuclear Bid to Rival [6] “EPR – Areva brochure” (PDF). Areva NP. May 2005. Coal Chilled by Flaws, Delay in Finland”. Bloomberg. Retrieved 2 January 2008. Retrieved 17 June 2008.

[7] EPR Level 1 Probabilistic Safety Assessment. Author: UK [27] Areva-Siemens sees Olkiluoto 3 reactor operational in EPR. summer 2011, CNN, 31 December 2007.

[8] http://books.google.ie/books?id=LZ7zBwWLyLEC& [28] “3-year delay expected at Finnish nuclear plant”. Interna- pg=PA121&lpg=PA121&dq=ipsr+ tional Herald Tribune. 17 October 2008. Retrieved 17 reactor&source=bl&ots=RjrcdZBH5t&sig= October 2008. CFdyY4mBX774oMKN2D-Z2OAiZKk&hl=en& sa=X&ei=C5gvUdSXA5GThgft44DQAw&ved= [29] Peggy Hollinger (16 October 2008). “Areva in talks with 0CD4Q6AEwAg#v=onepage&q=ipsr%20reactor& TVO over EPR delays”. Financial Times. Retrieved 17 f=false page 126. 3 Rs of Nuclear Power: Reading, October 2008. Recycling, and Reprocessing Making a Better ... By Jan [30] Suoninen, Sakari (31 December 2008). “Finland nuclear Forsythe reactor costs headed to arbitration – TVO”. Reuters. Re- [9] “Nuclear Power in a Warming World” (PDF). Union of trieved 5 January 2009. Concerned Scientists. [31] U.K. Expert: U.S. is Not Losing International 'Race' on [10] “Joint Regulatory Position Statement on the EPR Pres- Nuclear Power With France and Other Nations surised Water Reactor” (PDF). UK Health and Safety Ex- [32] Peggy Hollinger (31 August 2009). “Finnish reactor pro- ecutive. Dec 2007. visions hit Areva profits”. Financial Times. Retrieved 1 [11] “EDF eyes development of new, smaller reactors - pa- September 2009. pers”. Reuters. 21 March 2013. Retrieved 18 April 2013. [33] “Olkiluoto 3: EPR dome installed”. AREVA NC. 6 Au- [12] OLKILUOTO 3 PROJECT by AREVA gust 2009. Retrieved 1 November 2009.

[13] CHRONOLOGY OF OLKILUOTO 3 PROJECT by [34] “AREVA – Olkiluoto 3 : EPR dome installed”. YouTube. AREVA 10 August 2008. Retrieved 29 November 2009.

[14] “Olkiluoto 3 startup pushed back to 2018”. World Nuclear [35] Dorothy Kosich (29 June 2010). “S&P downgrades News. 1 September 2014. Retrieved 1 September 2014. French nuclear-uranium giant AREVA on weakened prof- itability”. Mineweb. Retrieved 6 July 2010. [15] EPR IN FINLAND: FOUNDATION STONE-LAYING DAY AT OLKILUOTO 3 by AREVA [36] François de Beaupuy. Areva’s Overruns at Finnish Nu- clear Plant Approach Initial Cost Bloomberg Business- [16] Regulator reports as OL3 delays reach one year, 19 July week, 24 June 2010. 2006, by Nuclear Engineering International. [37] “Start-up of Finnish EPR pushed back to 2013”. World [17] Concrete composition delays Finland’s Olkiluoto 3, Nu- Nuclear News. 8 June 2010. Retrieved 28 June 2010. clear Engineering International, 9 May 2006. [38] Ando, Ritsuko (21 December 2011). “Finland’s Olkiluoto [18] Areva’s first half results hit by Olkiluoto 3 delays, 2 Octo- 3 reactor delayed to August 2014”. Reuters. Retrieved 21 ber 2006, by Nuclear Engineering International. December 2011.

[19] European Pressurised Reactor at Olkiluoto 3, Finland – [39] “Olkiluoto 3 delayed beyond 2014”. World Nuclear Brief & Interim Review of the Porosity and Durability News. 17 July 2012. Retrieved 31 July 2012. Properties of the In Situ Cast Concrete at the Olkiluoto EPR Construction Site, June 2006, Large & Associates. [40] “Costs of Finland’s Olkiluoto nuclear reactor go up yet again”. Nuclear-news. 14 December 2012. Retrieved 6 [20] Finland nuclear reactor delayed again, Associated Press, September 2013. 4 December 2006. [41] Nuclear Engineering International. Flamanville 3 concrete [21] Areva to take 500 mln eur charge for Finnish reactor de- poured. lay, Forbes, 5 December 2006. [42] “EDF Official Site – Flamanville 3”. Edf.fr. Retrieved 19 [22] Nuclear industry revival hits roadblocks, New Scientist, 29 April 2012. June 2007. Retrieved 5 July 2007. [43] “Public inquiry commission favors plan to build [23] Dates revised again for Olkiluoto 3, World Nuclear News, Flamanville-3 EPR”. Nucleonics Week. 5 October 2006. 10 August 2007. Retrieved 17 June 2008. 7

[44] Geoffrey Lean and Jonathan Owen (13 April 2008). [62] “China: The Construction of the EPR reactor Unit 1 at “Defects found in nuclear reactor the French want to build Taishan Takes a Major Step Forward with the Installation in Britain”. The Independent (London). Retrieved 19 of the Vessel”. AREVA. 5 June 2012. Retrieved 5 June April 2004. 2012.

[45] “French nuke body partly halts work on new reactor”. [63] Steve Kidd (23 February 2015). “How serious are the de- Reuters. 27 May 2008. Retrieved 27 May 2008. lays in China’s nuclear programme?". Nuclear Engineer- ing International. Retrieved 8 March 2015. [46] “EdF allowed to continue concreting”. World Nuclear News. 20 June 2008. Retrieved 21 June 2008. [64] Patton, Dominique (29 January 2015). “UPDATE 2-EDF [47] Tara Patel (30 August 2010). “French Nuclear Watchdog says first Taishan nuclear plant to be ready end 2015”. Says EDF Has Problems With Flamanville EPR Liner”. Reuters. Retrieved 18 March 2015. Bloomberg. Retrieved 31 August 2010. [65] “New Nuclear Power Stations – Progress so far”. Health [48] “EDF delays Flamanville 3 EPR project”. Nuclear Engi- and Safety Executive. Retrieved 15 September 2009. neering International. 20 July 2011. Retrieved 21 July 2011. [66] “News – Taking GDA work forward in the light of the unprecedented events in Japan”. Hse.gov.uk. Retrieved [49] “Le coût de l'EPR de Flamanville encore revu à la hausse”. 19 April 2012. Le Monde. 3 December 2012. Retrieved 4 December 2012. [67] This website was built by the EDF Energy WCM. “Nuclear Generation”. Edfenergy.com. Retrieved 19 [50] “Enel Drops Participation in Flamanville EPR as Project April 2012. Costs Soar by $2.6B”. POWER. 6 December 2012. Re- trieved 14 August 2013. [68] Declan Lynch (18 April 2013). “EdF still undecided about Hinkley Point C go-ahead”. New Civil Engineer. [51] “Enel and Edf Terminate their cooperation on EPR in Retrieved 21 April 2013. France”. Enel. 4 December 2012. Retrieved 14 August 2013. [69] Andrew Trotman (18 April 2013). “EDF prepared to let [52] Michael Stothard (18 November 2014). “EDF in fresh de- UK nuclear talks fail”. Daily Telegraph. Retrieved 21 lay for flagship nuclear plant”. Financial Times. Retrieved April 2013. 21 November 2014. [70] “NuGen – About Nugen”. Nugeneration.com. Retrieved [53] Henry Samuel (9 July 2015). “Areva aware 'as early as 19 April 2012. 2006' of serious fault in nuclear reactor destined for UK”. Daily Telegraph. Retrieved 10 July 2015. [71] “Areva signs up Rolls-Royce for EPR”. Nuclear Engi- neering International. 11 March 2011. Retrieved 19 April [54] Henry Samuel (9 June 2015). “Faulty valves in new- 2012. generation EPR nuclear reactor pose meltdown risk, in- spectors warn”. Daily Telegraph. Retrieved 9 July 2015. [72] Dave Harvey (19 March 2013). “What price nuclear power? The final hurdle for Hinkley”. BBC. Retrieved [55] https://www.edf.fr/en/edf/press_release/ 19 March 2013. Flamanville-EPR-optimised-project-management-and-a-new-timetable [73] “Second new reactor for France”. World Nuclear News. [56] [email protected] (12 September 2004). 3 July 2008. Retrieved 3 July 2008. “Foreign energy giants bid for China’s nuclear contracts, 12 September 2004, ''People’s Daily''". People’s Daily. [74] AREVA’s announcement on two new EPRs in France. Retrieved 19 April 2012. [75] “France says Penly reactor on course despite delays”. [57] “Areva lands world’s biggest ever nuclear power order”. Reuters. 4 October 2011. Retrieved 5 October 2011. World Nuclear News. 26 November 2007. Retrieved 12 May 2013. [76] http://www.bfmtv.com/economie/ [58] “Signing of Areva EPR order in China delayed – French pas-depr-a-centrale-penly-439064.html source”. Forbes. 30 July 2007. Archived from the original [77] http://www.npcil.nic.in//pdf/news_07dec2010_ on 15 December 2008. Retrieved 1 August 2007. Business_Line.pdf [59] Nuclear Engineering International. Record-breaking deal for Areva/China Guangdong. [78] Makarand Gadgil (29 November 2011). “Jaitapur nuclear plant work may not start before 2014”. livemint.com. Re- [60] “China, People’s Republic of: Nuclear Power Reactors”. trieved 29 November 2011. PRIS database. International Atomic Energy Agency (IAEA). Retrieved 18 July 2010. [79] “N-plant in Jaitapur given green signal | PRAVASI TO- DAY : NRI NEWS : NRI HELP”. Pravasi Today. 29 [61] Patel, Tara; François de Beaupuy (24 November 2010). November 2010. Retrieved 19 April 2012. “China Builds Nuclear Reactor for 40% Less Than Cost in France, Areva Says”. Bloomberg. Retrieved 2 December [80] “Areva signs Jaitapur agreements”. World Nuclear News. 2010. 13 April 2015. Retrieved 14 April 2015. 8 9 EXTERNAL LINKS

[81] UAE endorses France nuclear deal – Joel Bowman – BBC [100] “Finland’s Fennovoima signs reactor deal with ”. News 10 March 2008. Reuters. 21 December 2013. Retrieved 12 January 2014.

[82] Despite Torture Video, U.S. and Emirates Sign Key Pact [101] CEZ excludes Areva from Temelin expansion tender – Mark Landler – The New York Times – 21 May 2009. [102] UPDATE 4-CEZ scraps tender to expand Temelin nuclear [83] Andrew England, Peggy Hollinger, Song Jung-a. “S. Ko- power plant reans win $20B UAE nuclear power contract”. Financial Times (CNN). Archived from the original on 14 January 2010. 9 External links [84] Peggy Hollinger (15 January 2010). “Areva considers producing cheaper reactors”. Financial Times. Retrieved • Official webpage 19 January 2010.

[85] Tara Patel (19 January 2011). “French Atmea Would Make Reactor ‘Credible’ Export, GDF Suez Says”. Bloomberg. Retrieved 21 June 2011.

[86] “Italy and France pen nuclear deal”. BBC. 24 February 2009. Retrieved 24 February 2009.

[87] Selina Williams, Liam Moloney (4 August 2009). “Enel, EDF to Build Nuclear Plants in Italy”. Wall Street Journal. Retrieved 9 August 2009.

[88] “US EPR plans suspended”. World Nuclear News. 6 March 2015. Retrieved 21 April 2015.

[89] “Design Certification Application Review – U.S. EPR”. Nuclear Regulatory Commission. Retrieved 3 July 2008.

[90] “Nuke plant is, well, nuked. Not gonna happen”. Prime- buzz.kcstar.com. Retrieved 19 April 2012.

[91] Terry Ganey. AmerenUE pulls plug on project Columbia Daily Tribune, 23 April 2009.

[92] Peter Behr (30 July 2010). “A Late Scramble to Fund 'Nuclear Renaissance' Kick-Start”. New York Times. Re- trieved 30 July 2010.

[93] “Constellation Energy cuts spending on Areva reactor ven- ture”. McClatchy-Tribune Information Services (Trading- Markets). 29 July 2010. Retrieved 30 July 2010.

[94] Peggy Hollinger (19 October 2010). “Energy: Cooling ambitions”. Financial Times. Retrieved 29 October 2010.

[95] “Dedicated nuclear component factory”. World Nuclear News. 24 October 2008. Retrieved 31 January 2009.

[96] Sonal Patel (1 December 2008). “AREVA inches closer to U.S. EPR construction”. POWER. Retrieved 31 January 2009.

[97] “Areva Halts Construction of Virginia Reactor Compo- nent Plant – Nuclear Power Industry News – Nuclear Power Industry News – Nuclear Street – Nuclear Power Portal”. Nuclear Street. 11 May 2011. Retrieved 19 April 2012.

[98] “TVO Plant type alternatives”. Tvo.fi. Retrieved 19 April 2012.

[99] “Current | Fennovoima signed technical development agreements with Areva and Toshiba | Current | Fen- novoima Oy”. Fennovoima.com. 20 December 2010. Retrieved 19 April 2012. 9

10 Text and image sources, contributors, and licenses

10.1 Text

• EPR (nuclear reactor) Source: https://en.wikipedia.org/wiki/EPR_(nuclear_reactor)?oldid=679421324 Contributors: Maury Markowitz, Heron, Fred Bauder, Kokamomi, Andrewa, Katana0182, Tobias Bergemann, Wwoods, Brockert, Tweenk, Chowbok, Oneiros, Hydrox, Rama, Vsmith, Rbk, Berkut, Pavel Vozenilek, Bender235, Kbh3rd, Alansohn, Hektor, John Quiggin, Lectonar, Rwendland, Vuo, DV8 2XL, Dan100, Lofor, Mazca, Buxtehude, BD2412, Keithpickering, Rjwilmsi, Wikiliki, Ysangkok, BjKa, Okto8, Simesa, Limulus, Shad- dack, Crf, Sardanaphalus, SmackBot, Cutter, Markus Schweiss~enwiki, Eskimbot, Chris the speller, Ottawakismet, Hibernian, Colonies Chris, Racklever, JonHarder, Theanphibian, Enr-v, Giancarlo Rossi, Acdx, Mu2, Mion, Ohconfucius, Skapur, CmdrObot, Cydebot, Kampulus, Cuhlik, Q43, DumbBOT, Roger Roger, Thijs!bot, Cranch, Gralo, Hirnbeiss~enwiki, Michael A. White, Ratherthanlater, Mactin, LessayCatus, AlmostReadytoFly, Magioladitis, Prestonmcconkie, Beagel, R'n'B, CommonsDelinker, Largeassociates, Rod57, STBotD, Usp, Andy Marchbanks, Johnfos, Jkstark, Mishlai, Robert1947, AlleborgoBot, Michael Frind, Sovxx, Deanlaw, Eiland, Watti Renew, Lwnf360, MelonBot, Crowsnest, DumZiBoT, TomPointTwo, Dubmill, Addbot, Felix König, Qjim, Zorrobot, ChNPP, Yobot, AnomieBOT, Jim1138, Jan.derijke, Xqbot, Svict4, FrescoBot, Citation bot 1, Watchpup, Full-date unlinking bot, Dtaylor46`6, Trappist the monk, Kreator007, RjwilmsiBot, Ripchip Bot, John of Reading, Boundarylayer, Dwalin, ZéroBot, Mantha.satish, Wieralee, H3llBot, Sachinvenga, CrimsonBoli, Helpful Pixie Bot, Llaarrss, Asauers, Asdfghjkuytrewrtrtetertdfbgvc, Khazar2, Jaspermogg, Tony Mach, Joein- wiki, SomeFreakOnTheInternet, Zepat, Adirlanz, ArbolIntl, Monkbot, Jacobellis96, Gabepatterson755 and Anonymous: 107

10.2 Images

• File:Crystal_energy.svg Source: https://upload.wikimedia.org/wikipedia/commons/1/14/Crystal_energy.svg License: LGPL Contribu- tors: Own work conversion of Image:Crystal_128_energy.png Original artist: Dhatfield • File:EPR_OLK3_lage.jpg Source: https://upload.wikimedia.org/wikipedia/commons/3/38/EPR_OLK3_lage.jpg License: CC-BY-SA- 3.0 Contributors: www.framatome-anp.com Original artist: Framatome ANP • File:EPR_pressure_vessel.png Source: https://upload.wikimedia.org/wikipedia/commons/e/ee/EPR_pressure_vessel.png License: CC BY 3.0 Contributors: Own work by the original uploader (Original text: I created this work entirely by myself.) Original artist: ChNPP (talk) • File:OL3.jpg Source: https://upload.wikimedia.org/wikipedia/commons/5/5e/OL3.jpg License: Public domain Contributors: Own work Original artist: kallerna • File:Radioactive.svg Source: https://upload.wikimedia.org/wikipedia/commons/b/b5/Radioactive.svg License: Public domain Contribu- tors: Created by Cary Bass using Adobe Illustrator on January 19, 2006. Original artist: Cary Bass • File:Symbol_list_class.svg Source: https://upload.wikimedia.org/wikipedia/en/d/db/Symbol_list_class.svg License: Public domain Con- tributors: ? Original artist: ? • File:Symbol_template_class.svg Source: https://upload.wikimedia.org/wikipedia/en/5/5c/Symbol_template_class.svg License: Public domain Contributors: ? Original artist: ?

10.3 Content license

• Creative Commons Attribution-Share Alike 3.0