Appendix A – Major Flood Control Projects

Table 1.1 Major Drainage Projects in Northern NT (Completed Projects)

Project Title Construction Length Start Date Compl. Brief Description Location of Significant Cost ($M) (km) Date Improvements and Benefits

Regulation of 390 4 12/2001 11/2006 Training of Shenzhen Lo Wu, Yuen Leng Chai, Shenzhen River, stage 3 River upstream of Nam Hang, , Lo Wu to Lo Shue Leng Muk Wu, Muk Wu Nga Yiu, Lo Shue Ling,

Rural drainage 203 4.2 11/1998 12/2001 Construction of San Wai Barracks, Kwan Tei, rehabilitation scheme, drainage channels and Wang Leng, Hung Leng, stage 1, phase 1A – box culvert Leng Tsai, rehabilitation works at (about 170 m) Wang Shan Keuk San Tsuen, Ng Tung River Wu, Shan Tong, San Tong Po

Rural drainage 156 4.9 04/1999 12/2001 Construction of Hang Tau Tai Po, Hang Tau, rehabilitation scheme, drainage channel Cheung Lek, Lin Tong Mei, stage 1, phase 1B – Tsiu Keng Lo Wai, rehabilitation works at Tsiu Keng Pang Uk, Sheung Yue River Tsiu Keng San Wai, Chan Uk Po

Rural drainage 197 1.7 05/2003 04/2006 Drainage Chow Tin Tsuen, rehabilitation scheme – rehabilitation works at Ta Kwu Ling Village, drainage rehabilitation Ping Yuen River Kan Tau Wai, Fung Wong Wu, works at Lei Uk, Tong Fong, Ping Yuen River and Shui Hau Mo Fan Heung Stream (NNT Portion)

Drainage improvement 208 1.8 06/2005 09/2008 Construction of Ma Wat and north of for Ma Wat River at drainage channels in Hong Lok Yuen Kau Lung Hang Ma Wat and north of Hong Lok Yuen

River training works for 756 4.6 08/1999 03/2003 Training of drainage Fu Tei Au, Wa Shan, the Upper River Indus re-entered channel Ting Tsuen, Shek Wu San Tsuen, Wu Nga Lok Yeung, Ma Shi Po, Siu Hang San Tsuen, Siu Hang Tsuen, Kan Lung Tsuen, San Wai, San Uk Tsuen

Shek Wu Hui 891 1.7 09/1998 02/2002 River training in Area Tsung Yuen, Ho Sheung Heung, Development Package 4, 30 Ying Kong engineering works

River training works for 258 2.6 03/1999 03/2001 Construction of Lo Wu, Tak Yuet Lau, Shek Ma, the Lower drainage channel Ngam Pin, Pai Tau Lo, River Indus and Ho Sheung Heung, Tong Kok, River Beas Shek Tsai Leng, Kwu Tung, Ying Kong Appendix A – Major Flood Control Projects

Table 1.2 Major Drainage Projects in Northern NT (Projects Under Construction)

Project Title Construction Length Start Date Compl. Brief Description Location of Significant Cost ($M) (km) Date Improvements and Benefits

Drainage improvement 332 5.2 12/2006 End 2012 Construction of Ping Kong, works in Ping Kong, drainage channels Kau Lung Hang, Yuen Leng, Kau Lung Hang, and box culverts in Nam Wa Po and Yuen Leng, Nam Wa Po and Ping Kong, Tai Hang areas Tai Hang areas Kau Lung Hang, Yuen Leng, Nam Wa Po and Tai Hang areas

Drainage improvement 135 3.5 06/2007 End 2012 Construction of , works in Lung Yeuk Tau, drainage channels and Kwan Tei South and Kwan Tei South and box culverts in Leng Tsai Leng Tsai, Lung Yeuk Tau, Kwan Tei South and Leng Tsai

Drainage improvement 162 3.6 12/2007 Mid 2012 Construction of Tai Po Tin, Ping Che, works in Tai Po Tin and drainage channels and Man Uk Pin and Ping Che of Ta Kwu Ling, box culverts in and Man Uk Pin and Tai Po Tin, Ping Che, Lin Ma Hang of Sha Tau Kok Man Uk Pin and Lin Ma Hang

Drainage improvement 213 3.1 11/2008 End 2011 Construction of Ki Lun Tsuen, Ma Tso Lung, in Ki Lun Tsuen, Ma Tso Lung, drainage channels and Ying Pun, Shek Tsai Leng and Ying Pun, Shek Tsai Leng and stormwater drains in Sha Ling Sha Ling in Ki Lun Tsuen, Ma Tso Lung, Ying Pun, Shek Tsai Leng and Sha Ling

Table 1.3 Major Drainage Projects in Northern NT (Projects Under Design/Planning)

Project Title Construction Length Start Date Compl. Brief Description Location of Significant Cost ($M) (km) Date Improvements and Benefits

Drainage improvement 314 1.9 Mid 2013 Mid 2016 Construction of Ping Che in Northern New Territories – drainage channels in Package C Ping Che and (remaining works) Ta Kwu Ling Appendix A – Major Flood Control Projects

Table 2.1: Major Drainage Projects in Northwestern NT (Completed Projects)

Project Title Construction Length Start Date Compl. Brief Description Location of Significant Cost ($M) (km) Date Improvements and Benefits

Yuen Long, , 202 2.3 12/2007 02/2011 Construction of Yuen Kong San Tsuen, and secondary drainage Cheung Po, Ma On Kong drainage channels in Kam Tin improvements, stage 1, phase 2B – remaining works

Yuen Long, Kam Tin, 139 3.2 06/2004 06/2007 Construction of Cheung Kong, Tai Kong Po, Ngau Tam Mei and secondary drainage Tsat Sing Kong, Ha Che, Tin Shui Wai drainage channels in Kam Tin San Wai Tsuen improvements, stage 1, and Ngau Tam Mei phase 2A – Kam Tina nd Ngau Tam Mei

Yuen Long, Kam Tin, 156 2.1 03/2007 11/2009 Construction of drainage Cheung Chun San Tsuen and Ngau Tam Mei and channels in Kam Tsin Wai Tin Shui Wai drainage Cheung Chun San Tsuen improvements, stage 1, and Kam Tsin Wai phase 2B – Cheung Chun San Tsuen and Kam Tsin Wai

Main drainage channel for 125 1.5 09/2003 03/2006 Construction of Lung Tin Tsuen, Yuen Long and Kam Tin – drainage channel in Lam Hau Tsuen Shan Ha Tsuen to Lung Tin Tsuen Lam Hau Tsuen section

Main drainage channels for 100 1.7 03/2000 12/2002 Construction of Yau Tam Mei Tsuen, Ngau Tam Mei, drainage channel from Yau Tam Mei San Tsuen, phase 2 – Ngau Tam Mei to Ngau Tam Mei to Wai Tsai Yau Mei San Tsuen section Yau Mei San Tsue

Village flood protection for 109 0.9 12/2001 12/2004 Construction of and Pok Wai Yuen Long, Kam Tin and floodwater pumping Ngau Tam Mei, station in Wang Chau; North West New Territories, and construction of stage 1 – remainder Pok Wai drainage channel

Yuen Long bypass floodway 432 3.8 01/2003 03/2006 Construction of , drainage channels in Tung Shing Lei, , Yuen Long South Small Traders New Village, Yeung Uk Tsuen, Chuk San Tsuen, Kong Tau San Tsuen, Shung Ching San Tsuen, Sham Chung Tsuen

San Tin Eastern Main 354 2.4 10/2002 04/2006 Construction of Drainage Channel the Eastern Main drainage channel in

Main drainage channels for 220 3.4 05/2001 07/2003 Construction of , Ng Ka Tsuen, Yuen Long and Kam Tin, drainage channels near Kam Tsin Wai, Nam Hing Lei, stage 2 – remainder Ng Ka Tsuen and Chung Sum Tsuen, Shek Tau Wai Pak Pin Tsuen, Uk Tau Tsuen, To Uk Tsuen, Shek Tau Wai, Tsz Tong Tsuen

Main drainage channels 280 3.1 08/1999 03/2004 Construction of Kam Tin San Tsuen, for Yuen Long and drainage channel from , Kiu Tau Tsuen, Kam Tin stage 2 – Kam Tin San Tsuen Pang Ka Tsuen, Kam Tin San Tsuen to to Wan Toi Shan San Tsuen, Wang Toi Shan section Wang Toi Shan

Main drainage channels 210 3.5 07/1999 03/2002 Construction of , Tai Hong Tsuen, for Yuen Long and drainage channel from Shek Wu Tong, Tin Sam Tsuen, Kam Tin stage 2 – Kam Tin Road to Tai Kek Tai Kek Kam Tin Road to Tai Kek section

Main drainage channels 359 2.3 11/1999 03/2005 Construction of Yau Mei San Tsuen, for Ngau Tam Mei phase 1 – drainage channels from Chuk Yuen Tsuen, Yau Mei San Tsuen to Yau Mei San Tsuen to Man Yuen Chuen Tai Sang Wai section Tai Sang Wai

Village flood protection 122 - 11/2000 03/2003 Construction of Chuk Yuen Tsuen and for Chuk Yuen Tsuen and floodwater pumping Ha San Wai Ha San Wai, station in Chuk Yuen Tsuen North West New Territories and Ha San Wai

Village flood protection for 146 - 12/2001 08/2005 Construction of Mai Po Lo Wai, Mai Po Lo Wai, floodwater pumping Mai Po San Tsuen, Mai Po San Tsuen, stations in Mai Po Lo Wai, Ma Tin Tsuen and Ma Tin Tsuen and , Ma Tin Tsuen and Shui Pin Wai North West New Territories Shui Pin Wai Appendix A – Major Flood Control Projects

Table 2:2 Major Drainage Projects in Northwestern NT (Projects under Construction)

Project Title Construction Length Start Date Compl. Brief Description Location of Significant Cost ($M) (km) Date Improvements and Benefits

------

Table 2:3 Major Drainage Projects in Northwestern NT (Projects under Design/Planning)

Project Title Construction Length Start Date Compl. Brief Description Location of Significant Cost ($M) (km) Date Improvements and Benefits

Drainage improvement in 418 0.6 End 2015 End 2020 Drainage improvement Western San Tin Northern New Territories – to the western main drainage improvement in drainage channel San Tin in San Tin Appendix A – Major Flood Control Projects

Table 3.1 Major Drainage Projects in West Kowloon (Completed Projects)

Project Title Construction Length Start Date Compl. Brief Description Location of Significant Cost ($M) (km) Date Improvements and Benefits

West Kowloon drainage 686 23 12/1999 12/2004 Improvement of Tsim Sha Tsui, Mong Kok, improvement, stage 2 23km of Tai Kok Tsui, Lai Chi Kok, phase 1 works stormwater drains Cheung Sha Wan, Sham Shui Po

West Kowloon drainage 1201 11 01/2001 08/2007 Construction of Yau Ma Tei, Mong Kok, improvement, stage 2 Tai Hang Tung flood Tai Kok Tsui, Sham Shui Po phase 2 and stage 3 stage scheme and phase 1 works Kai Tak stormwater transfer tunnel and improvement of 11km of stormwater drains

Table 3.2 Major Drainage Projects in West Kowloon (Projects under Construction)

Project Title Construction Length Start Date Compl. Brief Description Location of Significant Cost ($M) (km) Date Improvements and Benefits

West Kowloon drainage 1669 3.7 11/2008 Mid 2012 Construction of Sham Shui Po, improvement – drainage tunnel Cheung Sha Wan and Lai Chi Kok Lai Chi Kok drainage tunnel

Table 3.3 Major Drainage Projects in West Kowloon (Projects under Design/Planning)

Project Title Construction Length Start Date Compl. Brief Description Location of Significant Cost ($M) (km) Date Improvements and Benefits

West Kowloon drainage 308 2.8 Early 2015 End 2017 Inter-reservoir Lai Chi Kok, Cheung Sha Wan improvement – Transfer Scheme and Sham Shui Po Inter-Reservoir Transfer Scheme Appendix A – Major Flood Control Projects

Table 4: Achievements of Major Flood Prevention Projects in Other Areas

Project Title Construction Length Start Date Compl. Brief Description Location of Significant Cost ($M) (km) Date Improvements and Benefits

Projects completed

Drainage improvement in 158 2 03/2007 09/2009 Construction of Sha Ha, Pak Kong, Sai Kung drainage channels Ho Chung, Sai Kung Town

Drainage improvement in 191 11 04/2007 08/2010 Construction of Hung Hom, Ma Tau Wai, East Kowloon – stormwater drains Kowloon City, Kwun Tong, package B phase 2 San Po Kong

Drainage improvement in 199 N/A 06/2006 09/2009 Construction of Sheung Wan Northern Island – stormwater pumping Sheung Wan stormwater station pumping station

Drainage improvement in 190 5.6 05/2005 01/2009 Construction of drains Tsim Sha Tsui, To Kwa Wan, East Kowloon – package A and box culverts Wong Tai Sin, Yau Tong

Drainage improvement in 222 5.6 05/2006 02/2010 Construction of Hung Hom, Kowloon City East Kowloon – stormwater drains and San Po Kong package B phase 1 and box culverts

Projects under construction

Drainage improvement in 3381 18 11/2007 Mid 2012 Construction of Causeway Bay, Wan Chai, Northern Hong Kong Island – stormwater drainage Central, Sheung Wan, Hong Kong West drainage tunnel tunnel Kennedy Town

Drainage improvement in 373 4.4 07/2008 End 2012 Construction of Chai Wan, Shau Kei Wan, Northern Hong Kong Island – stormwater drains North Point, Causeway Bay, western lower catchment works Wan Chai, Central, Sheung Wan, Kennedy Town

Drainage improvement works in 253 9.8 02/2010 Early 2014 Construction of Tai Po Town Areas, Tung Tsz, Shuen Wan, Tai Po stormwater drains, Shuen Wan, Wai Ha, box culvert and a Ting Kok Road stormwater pumping station

Drainage improvement in 1486 5.35 12/2007 Early 2013 Construction of Tsuen Wan and Kwai Chung Tsuen Wan, Kwai Chung stormwater drainage and Tsing Yi – Tsuen Wan tunnel drainage tunnel

Reconstruction and rehabilitation 1602 0.6 10/2011 Mid 2017 Reconstruction, Kowloon City, San Po Kong of Kai Tak Nullah from improvement, Po Kong Village Road to widening, decking, Tung Kwong Road rehabilitation and landscaping of a section of Kai Tak Nullah

Drainage improvement works in 569 4.4 09/2007 Mid 2012 Construction of drainge Upper Lam Tsuen River, upper Lam Tsuen River, channels and box-culvert She Shan River, She Shan River, upper Tai Po River, upper Tai Po River, Ping Long Ping Long and Kwun Hang and Kwun Hang

Happy Valley underground 1066 NA 10/2011 Early 2018 Construction of an Happy Valley stormwater storage scheme underground storage tank with a pumping station within the Happy Valley Recreation Ground

Reconstruction and rehabilitation 159 0.1 08/2010 End 2012 Construction of box Kowloon City, San Po Kong of Kai Tak Nullah from culvert and local Po Kong Village Road to widening of Tung Kwong Road – stage 1 Choi Hung Road

Projects under design

Drainage improvement in 260 4.6 04/2013 Early 2016 Construction of The Peak, Pokfulam, Tin Wan, Southern Hong Kong Island - stormwater drains Aberdeen, Wong Chuk Hang, package 2 Shouson Hill and Stanley

Drainage improvement works 137 0.9 08/2013 End 2016 Construction of Ngong Ping at Ngong Ping stormwater drains and box culverts