<<

I N S U L AT E D PA N E L S Table of Contents

Section 1 Available Panel Types, Joints and Profiles

Section 2 Job Site Requirements

Section 3 Fastener Applications, Installation Tools and Care of Finishes

Section 4 Installation Details Introduction Metl-Span III

Building Codes This installation guide is intended to provide Metl-Span customers and/ Site Conditions or their constructors with procedures and guidelines for the installation Material Components of Metl-Span insulated panels and Metl-Span components. Before using any of these suggested procedures, the installer should:

1. Check all applicable federal, state and local codes to verify compliance with the code. 2. Be certain that site conditions are such that safe working practices are strictly observed. 3. Consult with the General Contractor, Design Engineer, Architect and Owner to confirm that the suggested procedures are suitable for each specific installation. 4. Recognize that the substitution of components not supplied by Metl-Span, may require some procedures different from those recommended.

Water tightness All materials furnished by Metl-Span are subject to the published limited Expansion & Contraction warranty.

The details contained in the following pages are merely suggestions/ guidelines as to how Metl-Span materials can be installed. We believe all information presented is accurate, but it is not intended to cover all instances, building requirements, designs or codes. The details may require adaptations, changes or revisions for each since conditions will vary from one project to another and may be unique for each application.

Details shown in this manual are preferred by a consensus of installers, but are not necessarily the only way to achieve a certain connection. It is the responsibility of the designer, general contractor and installer to ensure that the following details are adapted to meet particular building requirements and to assure adequate water tightness. Metl-Span shall be held harmless from any and all claims arising from a lack of water tightness as a result of following these suggested typical detail drawings. The designer and installer must be aware of and allow for expansion and contraction of wall and roof panels when designing and /or installing panels and flashing. Introduction Metl-Span III

Structural Support Ensuring adequacy of anchoring panels to materials, structures, Field Cutting subgirts and cees/zees, shall be determined by the designer/installer and Oil Canning Metl-Span shall be held harmless against all claims resulting from any inadequacy.

The installer shall familiarize himself with all erection instructions before starting work. Before beginning erection of the panels the installer shall examine the substrate to ensure that all supporting members are straight, level, plumb and true in accordance with AISC minimum tolerances. Report any variations and potential problems to the architect. Do not start work until unsatisfactory conditions have been corrected.

The installer may utilize details provided and procedures recommended for installation of materials. Some field cutting of panels and flashings is expected of the installer and minor field corrections of materials is a part of normal erection work. Workmanship shall be to the best industry standards, and installation shall be performed by experienced craftsmen. Oil canning in the flat area of the panels is common to the industry and shall not be cause for product refusal.

SMACNA ( and Air Conditioning Contractors National Association) architectural sheet metal manual specifications shall govern for material and workmanship not shown. Introduction Metl-Span III

Paint Paint manufacturers do not warrant their coating products when the Warranty coatings are used as an interior finish. The paint industry has taken the Position position that they have no way of knowing what the intended use of a building interior will be. They also have no way of determining what various environments will be like. This is applicable to all paint finishes such as siliconized polyester, fluoropolymer (Kynar 500), PVC Plastisol, etc. when used as an interior paint coating.

Conversely, the life of an exterior paint finish can be much more readily predicted because paint manufacturers have tested their material in various locations throughout the United States. This field testing has been on-going for many years and has provided manufacturers sufficient evidence of the effect different exterior environments will have on their coatings. Therefore, they are able to offer 10 and 20 year warranties on coating adhesion, and certain degrees of chalk and fade for the exterior finish prorated over a period of time.

Metl-Span’s standard interior paint finish is a siliconized polyester paint coating. We also use this finish on the exterior of our panels and are extended a 20 year standard limited warranty by our paint supplier when the panels are exposed to the outside environment. If we use this same identical finish on the interior face of the panels we are not provided a warranty by our supplier, and therefore cannot extend an interior paint warranty to our customers.

Please be advised that Metl-Span does not offer any warranty whatsoever for paint finishes applied to the interior metal faces of its insulated panels.

Some building interior environments are unusually aggressive or conditions within a building require frequent wash-down of walls and ceilings with chemical cleaners. In these instances, we suggest that you contact us directly for recommendations on other types of finshes or metal substrates, such as stainless , that would be better suited for these areas. Panel Joints Metl-Span III

(CF) Concealed Fastener Exterior

Joint Types

CF-36 With Fluted Exterior Profile

Exterior

CF-30, CF-36, CF-42, CF-30A, CF-36A With Mesa, Light Mesa* and Architectural Exterior Profiles

Exterior

CF-44 With Fluted Exterior Profile

Exterior

CF-45 With Mesa and Light Mesa* Exterior Profile

Refer to bulletin 07410/MET * Note: Light Mesa is available only on 2”, 2 1/2”, 3” and 4” Metl-Span III for available thicknesses. panel and joint types. 1.1 Panel Joints Metl-Span III

SL and SLR Joint Types

SL-44 Wall Joint

SL-45 Wall Joint

SLR-45 Roof Joint

Refer to bulletin M-S III SL for available panel and joint types. 1.2 Panel Types Metl-Span III

(CF) Concealed Fastener Panel Profiles

CF-36 With Fluted Exterior Profile

CF-30, CF-36, CF-42 CF-30A, CF-36A With Mesa, Light Mesa and Architectural Exterior Profiles

CF-44 With Fluted Exterior Profile

CF-45 With Mesa and Light Mesa Exterior Profile

Refer to bulletin 07410/MET Metl-Span III for available panel and joint types. 1.3 Panel Types Metl-Span III

SL and SLR Panel Profiles

SL-44 With Fluted Exterior Profile

SL-45 With Mesa and Light Mesa Profile for Partition, Ceiling and Exterior Applications

SLR-45 Exterior Roof

Refer to bulletin M-S III SL for available panel and joint types. 1.4 Job Site Requirements Metl-Span III

Job Site Metl-Span assures the utmost quality in production and shipment of all Panel Storage products. The following must be checked prior to receiving at the job site: Foundation and Steel 1. Panel Storage Customer must have ample storage space to receive packages. This will prevent delays in unloading panels. Area where packages are stored must be level and free from standing water. Panels should be stored in areas with easy access to the location where they will be installed.

2. Foundation and Steel Before receiving panels, customer should check foundation and steel to ensure it is square and level. All support girts must be in place and plumb. Checking these items will help reduce on-site storage and help the installer schedule his panel shipments properly.

All panels are carefully arranged for continuous wrapping. Every precaution is taken to secure placement of panels on trailers or in containers to prevent damage during transport. Damage obtained during shipment should be reported to Metl-Span. Customers should inspect the shipment when received. Carefully check to make sure item numbers on packing list correspond with panels. If there is any variance, please make notes on the bill of lading when signing for delivery approval and contact Metl-Span Shipping Department as soon as possible.

2.1 Job Site Requirements Metl-Span III

Handling and Storage Handling and storage of panels on site should be given extreme care. Label Information Packaging and blocking of panels has been specifically designed so when unloading panels, the forks on a forklift should be placed under center of the package. Metl-Span does not recommend the use of an overhead crane to unload panels. Metl-Span does not take any responsibility for damage obtained from mishandling of panels. Additional Blocks should be placed under the panel blocks to elevate packages for proper drainage, and packages should be slit at the bottom for proper ventilation and to prevent water stains from forming on the panel faces.

Label Information on Packaging

1. Packing list shows contents of each package .

2. Factory Mutual Label for Metl-Span III Panels.

3. Label indicating that panel packages must be slit at base for panel ventilation. 2.2 Fastener Applications Metl-Span III

Proper Use of 300 Series Selection of Fastener Stainless Steel Self-Tapping Screws Since 300 series stainless steel screws cost about three times as much as screws, great care should be used to select the proper screw and to apply it correctly to avoid costly screw failure.

Application Guidance

A good grade of carbon steel sheeting screw properly hardened can be carelessly used without damage to the screw. Also, Type A and Type AB carbon steel screws can be used in structural sections of considerable thickness. In addition to this, the same hole size can be used for a wide range of steel thicknesses. This is not true of 300 series stainless steel screws because they cannot be heat treated and they require care in application.

1. Type of Screw

For fastening panel to structure, typically Type B or BP should be used. In light sections (approximately 14 gauge or lighter) Type AB or A can be used.

2. Size of Hole

The following recommendations are based on the assumption that the lighter gauge structural sections (11 gauge and lighter) would be high strength steel - 50,000 psi minimum yield. If ordinary hot rolled steel such as ASTM A-36 is used, the selection of the type of screw and hole size will not be so critical. In heavier sections (3/16” and heavier) it is generally assumed that structural steel ASTM A-36 will be used. Holes should be drilled with 135 degree split point as follows:

Sheet to structure for Type B, BP or AB and # 14-10 Type A (See table on page 3.2)

3.1 Fastener Applications Metl-Span III

Proper Use of 300 Series Thickness of Steel Size of Type of Screw Stainless Steel 18 Gauge 3/16” Drill B, BP, AB, A Self-Tapping Screws 16 Gauge #9 Drill B, BP, AB, A

14 Gauge #9 Drill B, BP, AB, A

12 Gauge #3 Drill B, BP

11 Gauge #2 Drill B, BP

Over 11 Gauge thru 3/8” #1 Drill B, BP

Over 3/8” Thickness .231 Drill B, BP

An electric screw gun (approx. 600 rpm) is preferred. High speed impact tools are not good with these stainless steel screws. If they are used, great care must be exercised.

4. Screw Driving Suggestions

The best screws will withstand considerable abuse; however, they can be made to fail, even in the proper hole size.The hole should be drilled perpendicular to the structure and the screw should be driven in the same manner. If the screw is driven at an angle significantly different from which the hole is drilled, thread roll-over is likely. As the thickness of the structure increases, the need for straight becomes more important. If these precautions are not followed, the result may be partially stripped screws which will subsequently loosen with vibration, thus causing leaks.

300 series screws are all made from a special grade of high work harding stainless steel and provide the greatest resistance to thread failure. This includes Type A and AB screws which are frequently used on pre- engineered buildings for fastening sheet to structure. For this application, ordinary 305 stainless Type A or AB screws are not satisfactory because of a high rate of thread failure.

3.2 Fastener Applications Metl-Span III

Proper Installation In areas of high winds, excessive vibration and conditions created by and use of negative pressures due to thermal change, Fab-Lok fasteners should be Fab-Lok Fasteners used. Fab-Loks provide four clamping tines of holding power instead of relying on friction grip screws which may loosen and back-out under the above conditions.

Installation Procedure:

Select the proper Fab-lok for the application.

Size Grip Range Hole Size

10-4 .062”-.250” 3/8”

10-8 .250”-.500” 5/16”

10-12 .500”-.750” 5/16”

A Fab-Lok gun should be purchased from Fabco Fastening Systems for ease of installation. An alternate method of installation may be used, by holding the Fab-Lok sleeve with a 9/16” closed end and the screw with a clutch type screw gun. This may be more time consuming therefore, it is worth the expense of a Fab-Lok gun which has the appropriate sleeve holder.

3.3 Installation Tools Metl-Span III

Circular Saw For modification of panel lengths. Carbide blades are required to cut through panel faces and foam.

Power Drill Used for panel fastening and pilot holes through steel girts and panel facings.

Fab-Lok Screw Gun For attaching panels to girts from the building interior for Fab-Lok fasteners.

Reciprocating Saw To trim panels and make window, door and louver openings.

Caulk Gun For applying caulk to panel joints. Rechargeable powered guns are available at building centers.

Power Shears For trimming metal, flashings, gutter, etc.

Hammer Drill For attaching base channel and flashing to the foundation.

Power For trimming panel skin and cutting thermal breaks.

Caution: Any metal filings or burrs should be cleaned off the metal surface of panels to prevent rust from forming on the paint. 3.4 Maintenance Metl-Span III

Maintenance and Care Proper installation and maintenance are extremely important in obtaining of Metl-Span the very best service and appearance from pre-painted metal surfaces. Pre-Painted Surfaces The following information should be read carefully before engaging in any of the operations below.

I. Installation and Storage

II. Cleaning of Painted Surfaces

III. Touch-up Repair of Field Surface Scratches

I. Installation and Storage

Pre-Painted formed sheets must be protected from moisture until installation. When metal surfaces are tightly nested together and exposed to moisture and heat, oxidation (rusting) of the metal substrate can begin. In the case of galvanized steel, a white powder will be formed which is the normal sacrificial reaction of the zinc coating. Oxidation of this type can take place underneath the paint film. The following steps should be taken to control this type of storage damage.

1. Keep exterior storage time at the job site to a minimum.

2. Cover and slant bundles of sheets to ensure drainage of rainwater. Make sure no sags exist. Cut outer wrapping to avoid condensation build-up inside package.

Proper handling and stacking should be observed when moving panels to prevent abrasions. During installation, a frequent cause of damage is the dragging of whole panels or edges and corners across other panels. When damage occurs, sacrificial action of the zinc coating will retard red rusting, even if both the paint and galvanized coatings are cut through. If the appearance is damaged sufficiently, a touch-up operation may be necessary.

Improper cutting and drilling of pre-painted surfaces can cause bad rust spotting. Hot chips from drilling operations, saws or cutting discs, may embed in the paint finish.

3.5 Maintenance Metl-Span III

Maintenance and Care Even though panels themselves are not cut, chips from adjacent steel of Metl-Span work may embed in the paint surface. These chips will rust and form Pre-Painted Surfaces unsightly red spots on the painted surface that may become larger than the original chip. When saws, drill or cutting discs are used, the painted surface should be protected with a non-flammable cover. Also, prepainted panels installed next to a panel being cut or any panels nearby should be covered or removed if possible.

Brush off any chips of steel from the painted surface. If they are embedded they should be dislodged mechanically. Brushing with a stiff fiber brush may be adequate. Care should be taken by workmen to avoid stepping on or exerting pressure against any steel chips which tend to get embedded in the paint film.

II. Cleaning Paint Surfaces

Although the factory applied finishes are very durable and will last many years, eventually it may be desirable to thoroughly clean or repaint them.

Dirt build-up may cause apparent discoloration of the paint when it has been exposed to dirt laden atmospheres for long periods of time. Slight chalking may cause some change in appearance in areas of strong sunlight. A good cleaning will often restore the appearance of these buildings and render repainting unnecessary. An occasional light cleaning will help maintain a good appearance.

In many cases, simply washing the building with plain water using hoses or pressure sprays will be adequate. In areas where heavy dirt deposits dull the surface, a solution of water and detergent (1/3 cup Tide per gallon of water for example) may be used. A soft bristle brush with a long handle may be useful. A clear water rinse should follow. Mildew may occur in areas subject to high humidity, especially on dirt and spore deposits. This is not normally a problem on clean surfaces, however, due to the high inherent mildew resistance of baked-on finishes. To remove mildew the following solution is recommended:

1/3 cup detergent (e.g. Tide)

3.6

Maintenance Metl-Span III

Maintenance and Care 2/3 cup tri-sodium phosphate (e.g. Soilex) of Metl-Span Pre-Painted Surfaces 1 quart sodium hypochlorite 5% solution (e.g. Clorox)

3 quarts water

Strong solvents and type cleaners should be avoided. Caulking compounds, oil, grease, tars, wax and similar substances can be removed by wiping with a cloth soaked with mineral spirits. Wipe only contaminated areas and follow with detergent cleaning and thorough rinsing.

III. Touch-up Repair of Installed Surface Scratches

1. Surface Preparation:

A. Edges of deep scratches should be lightly sanded or feathered with #400 grit sand paper. B. Scratches and areas immediately adjacent should be wiped with lint free cloth dampened in mineral spirits. C. Allow area to dry thoroughly before applying touch-up.

2. Touch-up Application:

A. Check touch-up paint for correct match before applying to damaged areas. B. Shake and stir paint before applying. C. Apply touch-up paint to damaged area in thin coatings at a time.

3. Precautions:

A. Protect eyes, face and hands from direct contact with touch-up paint and /or solvents. B. Provide good ventilation in work area. C. Enforce NO SMOKING. Remove all sources of ignition. These coatings and solvents are FLAMMABLE.

3.7 Installation Metl-Span III Procedures Wall Panel Joint Installation Procedure

To ensure a proper vapor barrier and water tightness apply 1/4” bead of sealant in both grooves of the panel for commercial and industrial buildings. For cold storage buildings the sealant should be applied in the female groove of the Warm Side Wafer Head exterior surface of the panel. Push the Continuous Butyl Self Tapping Screw cartridge in the direction in which you are Bead Sealant at all Girt Attachments applying sealant.

Starting at a corner, erect the first wall panel with the male edge of the panel to the right when viewed from the outside of the building. Place panel in position, plumb panel and fasten to all applicable structural members. Place second panel in position and raise the edge of the panel being inserted in the first panel about 6”. Push the second panel into the first panel, with the edge METL-SPAN raised, until fully engaged. Tap on the Insulated Wall Panels upper free edge of the second panel until panel falls in final position. Check to ensure it is square and level.

For the “Concealed Fastener” type joint, lead with the male edge. Fasten panel to the girt with self-tapping screws through the male edge. Additional fastening may be required depending on girt spacing. Follow the steps above to complete the installation.

Continuous Butyl Bead Sealant Warm Side

METL-SPAN Insulated Wall Panels 4.1 Installation Metl-Span III Procedures Wall Panel Attachment Installation Procedure

METL-SPAN Insulated Place panel in final position. Check alignment, Wall Panel then drill a hole through the girt 5” in from each joint and 11” on center. If steel is pre- 10 - 4 FAB-LOK punched or pre-drilled, spacing of holes must Expansion Fastener be 9” on center. If beam/girt clips are used, 4 Per Panel- Quantity drill holes 9” from each joint and one hole in May Change Based on Girt Spacing the center of the panel. It is very important that clips be installed as shown below.

Caution: Panels must be attached at all applicable girts during installation. Securing panels at top and bottom only, may cause the panels to bow and it might be impossible to return the panels to their normal position.

Structural Steel Not by METL-SPAN

10-12 FAB-LOK Expansion Fastener 2/Clip

Two Hole Beam/Girt Clip 3/Panel - Quantity May Change Based on Girt Spacing

METL-SPAN INCORRECT Insulated Wall Panel 4.2 Installation Metl-Span III Procedures Wall Panel Attachment Installation Procedure NOTE: REFER TO LOAD TABLES Place panel in final position. Check FOR MAXIMUM ALLOWABLE alignment, then drill a hole through the SPACING OF HORIZONTAL GIRTS inside male leg of the panel and girt. Place the wall clip over the extended leg and insert a wafer head fastener in the hole and tighten until assembly is snug. Structural Steel Not by METL-SPAN Note: High windload requirements may necessitate the use of additional fasteners 14 Gauge such as Fab-Loks to meet the specified Galvanized "U" or "S" code. Clip Caution: 1/4 x 14 Carbon Panels must be attached at all Steel, Wafer Head applicable girts during installation. Screw, One Per Joint, Per Girt Securing panels at top and bottom only, may cause the panels to bow and METL-SPAN it might be impossible to return the Insulated Wall panels to their normal position. Panel

Equal Equal Equal

Exterior FAB-LOK Concealed Fastener Expansion Fastener 14 Gauge Concealed One Per Joint Per Fastener Clip Steel Crossing 4.3 Installation Metl-Span III Procedures Roof Panel Joint Installation Procedure

1/4 - 14 x 7/8" Continuous Sealant Tape Apply 1/4” bead of tube sealant to the Self - Drill Screw (Between Rib Overlap) female groove to ensure a positive vapor 6" O.C. barrier. Push tube in the direction in Exterior Roof which you are applying the sealant. Rib Batten Trim Apply continuous sealant tape between rib overlap. Support next panel over roof steel and move into position. Raise male overlap slightly and slide panel into final position. Place batten over rib and screw down 6” on center. Overlap battens 1” to METL-SPAN 2” and apply tube sealant at all laps. Insulated Roof Continuous Butyl Panels Bead Sealant

4.4 Installation Metl-Span III Procedures Roof Panel Joint Installation Procedure

Snap on Apply 1/4” bead of tube sealant to the Roof Batten 18 Gauge Galvanized female groove to ensure a positive vapor Clip 3" Wide barrier. Push tube in the direction in 1/4 - 14 x 7/8" 48" O.C. Self - Drill Screws which you are applying the sealant. 6" O.C. Pop Each Side Apply continuous sealant tape between of Clip to Square up rib overlap. Support next panel over roof Batten steel and move into position. Raise male overlap slightly and slide panel into final position. Place saddle clip over the rib at 48” on center and screw down with a #14 x 7/8” self-drill screw. Snap battens Continuous Sealant on over the clips and square up. Overlap Tape (Between Rib the battens 1” to 2” and apply tube METL-SPAN Overlap) Insulated Roof sealant at all overlaps. A pop rivet must Continuous Butyl Panels be installed on each side of the rib at Bead Sealant every clip location to prevent the batten from twisting.

4.5 Installation Metl-Span III Procedures Roof Panel Attachment Installation Procedure

Position panel over roof steel and check squareness. Drill proper size hole 5” to 6” in from panel joint and insert expansion fastener. FOR PROPER USE of expansion fastener PLEASE refer to the fastener section in this manual.

METL-SPAN Insulated 10 - 4 FAB-LOK Roof Panel Expansion Fastener 11" O.C. - Quantity May Change Based on Girt Spacing

Structural Steel Not by METL-SPAN

4.6 Installation Metl-Span III Procedures Base Attachment Installation Procedure

METL-SPAN Apply sealant tape to the back side of the Insulated Panel Butyl Bead Sealant . Peel protective cover off the tape. Position channel in-place. Fasten channel Field Cut to the foundation with fasteners at 36” on Thermal center through sealant tape. Slide panel in Break channel to its final position. Screw the Poly Slip Sheet inside leg of the channel to interior face Not by of the panel at 12” on center. After all Pourable Caulk METL-SPAN panels are in-place, pour pourable caulk Pop Rivet 16 Gauge 12" O.C. into the gap between the exterior leg of Galvanized the channel and panel. Do not try to fill Base Cover Facia Channel channel in one shot. Wait at least 24 hours after first application and fill channel to the top with the second Butyl Caulk application. Take precaution not to splatter caulking over the exterior face of the panel. Shore panel from exterior prior Fasteners 36" O.C. Continuous to pouring curb. Not by METL-SPAN Sealant Tape

4.7 Installation Metl-Span III Procedures Base Attachment

Continuous Base Installation Procedure METL-SPAN Angle Not By Insulated METL-SPAN Wall Panel Install base angle with fasteners at 36” on center. Line up vertical leg of the angle a 1/4-14 Self mininum of the thickness of the panel Tapping Screw 3/Panel in lows plus (+) 1/4”, from the edge of the Fastener 36" O.C. concrete. Apply sealant on back side of 1/4" x 1" Trim Not By the horizontal or vertical leg of the base Color to Match METL-SPAN flashing. Apply a bead of tube sealant to Panel. DO NOT the inside corner of the base flashing. CAULK, Allow Water to Drain Place panel in position and attach it to the Through angle with expansion fasteners or #14 self-tapping screws for the SL panels. Pop Rivet Attach the panel to the angle with a CF 12" O.C. clip and wafer head fastener for CF panels. Install the trim angle just above Continuous Base the base angle flashing with pop Angle Butyl Bead placed at 12” on center. Sealant Continuous Sealant Tape

METL-SPAN Insulated Wall Panel Continuous Base METL-SPAN Angle Not By Insulated 1/4" x 14 METL-SPAN Continuous Wall Panel Self Tapping Screw Base Angle 3/Panel in lows Expansion Fastener Not By Four Per Panel 1/4" x 1" Trim METL-SPAN Fastener at 36" O.C. Color to Match Not By METL-SPAN Panel. DO NOT CAULK, Allow Water to Drain Butyl Bead Sealant Pop Rivet Through 12" O.C. Pop Rivet 12" O.C. 1/4" X 1" Trim Color to Match Panel. DO NOT CAULK, Base Flashing Allow Water to Drain Through Continuous Fastener 36" O.C. Not By METL-SPAN Base Angle Continuous Butyl Sealant Tape Fastener at 36" O.C. Bead Sealant Continuous Not by METL-SPAN Sealant Tape 4.8 Installation Metl-Span III Procedures Exterior Corner Installation Procedure Loose Fill Insulation Not By METL-SPAN Cut male/female edges of starter panels. If edges are not cut, all gaps must be Exterior Trim Angle Facia Continuous filled with loose fill insulation. In cold Sealant Tape storage applications all gaps must be filled with field foamed polyurethane. In certain conditions, interior trim cannot be installed after panels are in place. In these conditions install interior trim on one Pop Rivet panel prior to panel installation. Cut 8" O.C. thermal break on interior face of panel extending to the outside. Place panel in Pop Rivet METL-SPAN 8" O.C. Insulated Wall position and fill gap between panels with Field Cut Panel loose fill insulation or field foamed Thermal Break polyurethane. Apply sealant tape to the two inside faces of the exterior corner Continuous flashing. Install flashing by pulling open Sealant Tape the two legs of the flashing. Attach with METL-SPAN fasteners at 8” on center through the Insulated Wall sealant tape. Panel

4.9 Installation Metl-Span III Procedures Stack Joint Installation Procedure

METL-SPAN Attach structural angles to girts at stack Insulated Wall joint location with structural fasteners Panel 12” on center. Install bottom course of panels in-place. Drill holes and insert 1/4" x 1" Trim FAB-LOK Expansion Fastener Color to Match expansion fastener. Apply sealant on top 4/Panel Panel. DO NOT of the interior edge of the panel. Install CAULK, Allow stack joint fascia with tape applied to Water to Drain Structural Steel inside face of the vertical leg. Apply a Through Not By METL-SPAN bead of tube sealant at the inside corner Pop Rivet of the stack joint fascia. Install the top 12" O.C. course of panels. Install the trim angle Butyl Bead just above the stack joint flashing with a Sealant Continuous Angle pop rivet placed at 12” on center. Not By METL-SPAN Stack Joint Flashing Expansion Fastener 4/Panel METL-SPAN Per Steel Crossing Insulated Wall Panel

4.10 Installation Metl-Span III Procedures Side Wall Eave Installation Procedure Roof Rib Closure Plug Set in Bed Loose Fill Insulation Apply sealant to the exterior face of Continuous of Butyl Caulk Not By METL-SPAN perimeter steel. Position wall panel in- Sealant Tape place. Drill holes for #14 self-tapping Gutter Strap METL-SPAN One per Panel at Sealant Tape screws through the center flute and the Insulated Roof Center of Panel two flutes adjacent to the panel joint. Panel Insert fastener. Install roof panel, holding Gutter and Strap the 1” from the exterior face of the wall panel. Fill all gaps with loose fill insulation. Drill holes for expansion fasteners and insert fasteners. Insert flute plug at all exterior panel flutes, and cover 10-4 FAB-LOK with sealant tape. Apply tape to bottom Expansion Fastener side of roof overhang. Apply sealant to 4/Panel roof closure plug and insert plug in gap 1/4" - 14 Self-Tapping Screw between the closure trim and skin Closure Trim 3/Panel in lows overhang. Install closure trim with fasteners at 8” on center through sealant Pop Rivet 8" O.C. tape. Install gutter with stitch screws Structural Steel Angle through roof overhang at 10” on center. Continuous Not By METL-SPAN Sealant Tape Use one gutter strap per panel and screw METL-SPAN strap to panel skin through mastic. Flute Plug Insulated Wall Panel

4.11 Installation Metl-Span III Procedures Side Wall Eave Installation Procedure Foam Closure set Foam Closure Loose Fill Trim Insulation in Sealant Tape Attach continuous angle at the base of Not By METL-SPAN perimeter steel. Angle can be pre- METL-SPAN Insulated Roof punched at 9” o.c. or drill angle and panel Panel after panel installation. Insert expansion fasteners. Apply continuous bead of Eave Flashing sealant on interior edge of wall panel. Install roof panel. Hold back the end of the panel 1” from the exterior face of the Flute Plug wall panel. Insert flute closure plugs along face of wall panel. Apply sealant Pop Rivet One Hole Beam Girt Clip, 3/Panel tape over face of panel and over closure 8" O.C. plugs. 10-8 FAB-LOK Continuous Expansion Fastener On the roof measure 12” from the eave. Sealant Tape One per Clip Apply sealant tape over face of roof panel at that location. Apply sealant tape over roof closure. Insert roof closure in closure Structural Steel trim with tape facing the trim. Install Not By METL-SPAN closure trim over the roof panel with roof METL-SPAN Insulated Wall 10-8 FAB-LOK closure over the tape on the roof panel. Panel Expansion Fastener Attach at 8” o.c. Apply sealant tape over 4/Panel the closure trim covering panel ribs. Install eave flashing with screws at 10” o.c. through tape. Overlap flashing 2” and apply sealant at all overlaps.

4.12 Installation Metl-Span III Procedures Rake Wall Eave Installation Procedure 1/4-14 x 7/8" Continuous Self Drill Screw Sealant Tape 8" O.C. METL-SPAN Apply sealant tape or tube sealant on Insulated Roof vertical and horizontal surface of the Loose Fill Panel Insulation purlin closure at the wall/roof Not By intersection. Install wall panel. Attach METL-SPAN steel with expansion fasteners or #14 self-tapping screws. Install roof panel Continuous Sealant with male edge of panel facing the Tape exterior of the building. Attach roof panels to purlins, running perpendicular Pop Rivet to roof panel. Apply tape sealant. Insert 8" O.C. closure plug at all panel flutes and run tape sealant over closure plugs. Apply tape sealant over roof panels. Flute Plug Install rake flashing with self-drilling Eave screws through sealant tape at 8” on Flashing center. Overlap fascia 2” and seal all 1/4 x 14 Carbon Steel Self Tapping Screw overlaps. 15" O.C. Structural Steel METL-SPAN Not By METL-SPAN Insulated Wall Panel

4.13 Installation Metl-Span III Procedures Side Wall Eave Membrane Installation Procedure Lap Sealant Splicing Cement Flashing Not By Not By METL-SPAN METL-SPAN Not By Place Panel in position. Attach panel to Metal Cleat METL-SPAN structural steel with #14 self-tapping Gravel Stop Not By Roof Membrane screws or expansion fasteners. Insert flute Facia METL-SPAN Not By plugs at all flutes at the exterior surface 1/4-14 x 7/8" METL-SPAN of the panel. Apply tape sealant on the Self Drill interior face of panel cap. Place panel cap Screw 8"O.C. over the panel. Hold cap open prior to placement. Attach cap to panel with sheet Continuous metal screws at 12” on center. Seal roof Sealant Tape membrane on top of cap. Install gravel Flute Plug stop fascia by hooking exterior leg over Wood Blocking panel cap and fastening the horizontal leg Not By METL-SPAN to wood blocking. Apply membrane 1/4" x 14 flashing over fascia and seal all seams. Self Tapping Fastener Screw 15" O.C. Not By METL-SPAN METL-SPAN Structural Steel Insulated Wall Not By Panel METL-SPAN

4.14 Installation Metl-Span III Procedures Roof Ridge Installation Procedure

Ridge Flashing Continuous Insert flute plug at interior panel joints. 1/4-14 x 7/8" Sealant Tape Self-Drill Screw Foam Closure Apply tape to interior ridge fascia and 1/4-14 x 7/8" Four per Trim set in Sealant attach fascia to the panel with screws at 8” Tape Self-Drill Screw Four per Trim on center through sealant tape. Fill gap with loose fill insulation. Measure 12” from center line of ridge in both directions. Apply sealant tape over the face of the roof panel at those locations. Apply sealant tape over roof closure. Insert roof closure in closure trim with tape facing the trim. Install trim over the roof panel with roof Loose Fill Insulation closure over tape on roof panel. Attach at Not By 8” on center. Apply sealant tape over the Flute METL-SPAN closure trim covering panel ribs. Install 10-4 FAB-LOK Plug Continuous ridge flashing with screws at 10” on center Expansion Fastener Sealant Tape through tape. Overlap flashing 2” and seal Structural Steel 4/Panel per Steel Not By METL-SPAN Crossing all overlaps.

4.15 Installation Metl-Span III Procedures Roof Panel Butt Joint Installation Procedure

METL-SPAN 10-4 S.S. FAB-LOK With 1" Neoprene Insulated Roof Bonded Washer at Expansion Fastener, Install angle with roof structural Panel 4" O.C. In Low Mesa Profile fasteners. Apply tape sealant or tube sealant over angle. Place lower course of panels in position. Insert closure plug at joint. Drill holes for expansion fasteners and insert fasteners. Apply two continuous 3/8” beads of tube sealant over ribs and additional beads on either side of rib. Install upper course panel with top skin extension over lower course panel. Drill 5/16” holes 4” on center. Insert Fab-Lok expansion fasteners to skins together. Apply an exterior Two Continuous bead of high quality sealant over seam. 3/8" Beads of Urethane Sealant 10-4 FAB-LOK Expansion Fastener 4/Panel Structural Steel Not By METL-SPAN

4.16 Installation Metl-Span III Procedures Wall Opening Installation Procedure METL-SPAN 1/4 x 14 Carbon Steel, 14 Gauge Insulated Wall Wafer Head Screw Measure off the door or window size over Galvanized Panel One per Joint per Girt face of panel as shown by dotted lines. "U" or "S" Minimum 1 1/2" From Clip Bottom of Panel Have enough clearance for all door or window parts. Drill pilot holes at upper 1/4" x 1" left and upper right corners of the Panel Trim Color Flute Plug opening. Transfer hole locations to the to Match Panel Continuous interior face of the panel with a sharp DO NOT CAULK, pointed tool. Cut face of panel with a Allow Water to Sealant Tape Drain Through sabre saw or a nibbler. Remove foam with sharp knife or blade. Cut base angle. Pop Rivet Install header and jamb fascia sealing 12" O.C. edges of panel. Install door header and trim per door manufacturer’s recommen- dations.

Continuous Butyl Drip Bead Sealant Flashing Door Header Silicone Sealant Not By METL-SPAN Not By METL-SPAN

Pilot Holes to Start Cuts

4.17 Installation Metl-Span III Procedures Wall Opening

Door Jamb Installation Procedure Not By METL-SPAN Measure off the door or window size over face of panel as shown by dotted lines in on page 4.17. Have enough clearance for all door or window parts. Drill pilot holes at upper left and upper right corners of the opening. Transfer hole locations to the interior face of the panel with a sharp pointed tool. Cut face Jamb Flashing of panel with a sabre saw or a nibbler. Not By METL-SPAN Remove foam with sharp knife or blade. Cut base angle. Install header, jamb and sill fascia sealing edges of panel.

Continuous Silicone Caulk Not By METL-SPAN

Continuous Sealant Tape

Flute Plug Pop Rivet 12" O.C.

Window Sill Not By METL-SPAN Continuous Silicone Bead Sealant Not By METL-SPAN

Sill Flashing

Flute Plug Structural Steel Metal Cleat Not By METL-SPAN Not By METL-SPAN 1/4 - 14 Self Tapping Screw With Washer Pop Rivet 8" O.C.

Continuous METL-SPAN Sealant Tape Insulated Wall Panel 4.18 1497 N. Kealy Lewisville, Texas 75057 TEL 972 221 6656 TEL 877 585 9969 FAX 972 436 0648 [email protected] www.metlspan.com © 2002 Metl-Span I, Limited, Lewisville, Texas, USA