<<

Luyster Creek Energy Project Public Participation Plan January 2010 Revised November 2010

Pursuant to the State Department of Environmental Conservation Commissioner's Policy CP-29, Environmental Justice and Permitting

Astoria Generating Company, L.P. USPOWERGEN 505 5th Avenue New York, NY 10017 USPOWERGEN

I. Project Description The Astoria Generating Company, L.P. (AGC), a USPowerGen (U5PG) Company, is proposing to update the Astoria Generating Station (AGS) with the addition of approximately 500 to 750 megawatts (MW) of new, cleaner, state-of-the-art, combined cycle, electric generation while reducing the actual net emissions of the entire facility (inclusive of the new equipment). Emissions reductions will be done by implementing enforceable permit limits at the existing AGS. As currently envisioned, depending on market conditions, the Project may be constructed in two phases of 250 to 375 MW or a single phase of 500 to 750MW.

BACKGROUND The existing AGS units are located on approximately 17 acres at 18-01 20th Avenue in Astoria, New York. They consist of three dual fueled (natural gas and No.6 oil) units, one natural gas unit, and a small emergency combustion turbine with a total capacity of approximately 1,300 MW. The location of the LCEP is at the AGS Fuel Oil Tank Farm (FOTF) on an adjacent parcel of approximately 12 acres that is 1,600 feet to the northeast of the existing units. The new combined cycle unit(s) would occupy approximately 7.5 acres on this parcel. A new above ground fuel oil tank would also be constructed on the fuel oil storage depot parcel for the storage of ultra low sulfur diesel (ULSD). Currently there is approximately 8 million gallons of No.6 oil storage at this site in four tanks for the existing boilers at AGS. Fuel is currently delivered by barge to the tanks from the adjacent A-I0 dock. The existing AGS units are currently utifized to meet electric demand and maintain the electric grid stability. The new LCEP will cause the older AGS units, as well as other less efficient plants in , to run less while allowing the newer, cleaner units to meet the continually growing electric demand within the City.

AGC believes that a coordinated improvement of the AGS by the addition of new cleaner technology is the most beneficial way to plan for the increasing load requirements of the City and the eventual retirement of older generating units, while reducing the environmental impacts of the existing units and other displaced facilities. Therefore, operation of the LCEP will result in significant environmental benefits and improve system reliability. The Project will also advance and is consistent with the goals set forth in the Draft State Energy Plan with respect to assuring system reliability, replacement of older capacity, greenhouse gas reductions, reduced electric costs and environmental improvements.

AGC evaluated several improvement opportunities including enhancing or replacing the existing equipment to achieve the goals of increased capacity with decreased environmental effects. In fact, a repowering of the facility was permitted under the Article X process in 2003. When USPG acquired AGe, it performed a technical and commercial review of the approved repowering project and determined that it was uneconomic to build the Project as proposed by the previous owners. AGC then commissioned an engineering firm to evaluate the feasibility of locating additional capacity close by the existing AGS units in a systematic phased approach to eliminate the features that made the approved project infeasible. Potential areas for new equipment were identified. Layouts of the maximum capacity that could fit on the locations were determined. The primary items that were to be optimized in a modified project were the avoidance of potential aquatic impacts, reduction of interference with existing operations, and minimization of other environmental concerns such as visual impact and water use. Ultimately, however, it was determined that a modified project close by the existing AGS units could not avoid interfering with existing utility infrastructure and would still require significant remediation and demolition. During demolition and construction activities, existing AGS units would have to be taken off line for substantial USPOWERGEN

Luyster Creek Energy Project Public Participotion Pion January 20I0 periods, with the resultant loss of revenue. In addition, a modified project was thought to be a significant enough departure from the approved project that a new permitting process would have to be started. These conditions resulted in the inability to develop an economic project in the same footprint approved for the project.

Once it was clear that an economic option was not viable dose by the existing AGS units, AGe looked more broadly to determine if a project could be developed in another location that avoided the fundamental issues that were detrimental to development at the original location. That led to the adjacent AGS FOTF. This site is currently in use for oil storage and houses several retired above ground storage tanks. Use of this site for the LCEP avoids removal of existing generation during the construction period, reduces the demolition and remediation costs compared to the original concepts and allows for a two phased build out if the market dictates.

As a result of the AGC evaluation, the following Project parameters have been determined:

1. The optimum location is FOTF parcel northeast of the existing AGS units.

2. Use of Siemens SCC6-S000F, GE Frame 7, or Mitsubishi SOlG combustion turbines in either a lx1 or 2X1 configuration, based on market conditions, with air cooled condensers and the lowest stack heights possible to achieve ambient air quality standards. see attached Figures 1 and 2.

THE pROJECT New York City requires a significant amount of generation be located in the City for system reliability. The existing AGS units are older, tess effident units that are used for reliability and high load days. Displacement of the older units with new higher efficiency units will provide a tremendous environmental benefit. In addition to the environmental benefit, the cost of production of electricity would be reduced due to the higher efficiency of the new unit(s). Load profiles and existing capacity resources in the City require that NYC have additional qUick start and intermediate load generation capability to meet demand. The LCEP will be designed to start up and shut down quickly and have greater operational flexibility than the standard combined cycle facilities currently installed in the Oty. This flexibility will reduce emissions during startup and allow the LCEP to be shut down if there are more economical sources rather than operate during uneconomic periods.

The LCEP consists of two distinct components: the installation of new combined cycle combustion turbine(s) and an emissions reduction strategy for the existing AGS. The improvement will be built on the FOTF parcel adjacent to the existing AGS within an area zoned for heavy manufactUring (industrial) use (M3-1). The new combustion turbines will be dual fuel-capable and bum natural gas as a primary fuel and ULSD as backup fuel to be used for up to approximately 30 days annually which will require the addition of a new oil storage tank.

Installation of the new units is being approached in a phased manner. Phase 1 will consist of the installation of a single new 250 to 375 MW combined cycle unit to be operational to meet the anticipated need for capacity in 2014. The potential emissions from this unit will be offset by the retirement of

Page 2 USPOWERGEN

Luyster Creek Energy Project Public Participation Pion January 2010 existing Unit 2 and an enforceable permit limitation on the remaining units (3, 4, and/or 5) effective upon commercial operation of the new unit. The reductions from the existing units plus the potential emission from the new unit will result in an overall net reduction of emissions. Phase 2 would include the addition of a second, new 250 to 375 MW combined cycle unit or another combustion turbine to operate with the phase 1 combined cycle unit, enforceable permit limitation on the remaining existing unit (3, 4, and/or 5) and/or shut down of another unit effective upon commercial operation of the new unit. The reductions and/or retirement of Unit 5, plus the emissions from the second new unit will result in an overall net reduction.

Market conditions may dictate that the amount of new capacity required in the timeframe, could require the entire 500 to 750 MW be build as one phase, In this case, one 500 to 750 MW combined cycle unit would be constructed. Effective upon commercial operation of the new unit, Unit 2 would be retired and enforceable permit limits and/or retirement of the remaining existing units would be completed such that the potential emissions from the new unit and remaining existing units will result in an overall net reduction.

All of Queens County, NY, including the AGS, is located in a nonattainment area for ozone (03) and particulate matter less than 2.5 microns in diameter (PM 2.s). The Environmental Protection Agency defines nonattainment areas as regions in which air pollution levels persistently exceed National Ambient Air Quality Standards. The LCEP will not trigger review under Prevention of Significant Deterioration or Nonattainment New Source Review regulations because AGC will commit to enforceable permit restrictions that limit new emissions to levels below significant increase thresholds.

Benefits of the Project are that it will provide additional cleaner electric generation while reducing the

actual net emissions for carbon monoxide (CO), nitrogen oxides (NOx), particulate matter (PM) including

PM less than 10 microns (PM lO), particulate matter less than 2.5 microns in diameter (PM 2.s), and sulfur oxides (SOx), which is a precursor to PM 2,s formation. NO.: is also a precursor to ozone formation. It will

also result in a decrease in carbon dioxide (C02), a greenhouse gas. Potential emissions resulting from the additional generating capacity will be offset by implementing the strategies described below. These actions will fully address community concerns and ensure that air emissions will be reduced by a combination of methods that may include but are not limited to:

1. Use high efficiency, low emission combined cycle combustion turbines for the Project.

2, Permit caps on the total emissions from the new combined cycle equipment.

3. Permit caps on the total emissions from the existing AGS units.

4. Shut down of existing units.

5. Permit cap on sulfur content of the oil for the Project.

6. The new combined cycle unites) will employ air cooling and result in a reduction in cooling water use by the existing AGS units,

Page 3 USPOWERGEN

Luyster Creek Energy Project Public Participation Pion January 201 0

AGe will be electrically interconnecting into the grid via existing connections from the rnrrent units. As such, the new unit interconnection should be easily achievable.

Though no significant adverse environmental impacts are anticipated as a result of the Project, AGe will prepare and submit a Draft Environmental Impact Statement (OBS) in order to fully address potential community concerns, including environmental justice issues. The DEIS will also include an alternatives analysis.

II. Other AGe Assets within the Community Currently, AGe owns three electric generating facilities within the confines of New York City including the AGS, the Narrows Generating Station (NGS, located In the Sunset Park area of Brooklyn), and the Gowanus Generating Station (GGS, located in the Sunset Park area of Brooklyn). The South Pier Improvement Project at the GGS which will add 100 MW of new efficient generation was recently (October 21, 2009) approved and permitted by the NYSDEC. This new facility will result in a net decrease of all air emissions in the Sunset Park area of Brooklyn, resulting in environmental improvements to the community. The emission reduction strategy under consideration or the LCEP Is based on the successful SPIP model.

In accordance with Commissioner Policy 29 (CP-29) of the NYSDEC, the sections that follow outline the steps that AGe will undertake to inform the local community and the broader public about the Project and to invite vigorous partidpation in the permitting and environmental review processes.

RELEVANT GEOGRAPHIC CONTEXT The existing AGS units and the lCEP are located in an area NYSDEC has identified as a Potential Environmental Justice Area (PEJA). Therefore, AGC has reviewed the CP·29 guidelines in preparing a proactive, enhanced program for engaging community organizations and residents in the Astoria, Queens area. The Project location is shown below.

Page 4 USPOWERGEN

Luyster Creek Energy Project Public Participation Plan January 2010

AGe recognizes that this Project takes place within a neighborhood context where priorities and plans for future development may be established.

III. AGe Contact and Central Communication AGe will establish a website specifically for the LeEP. The website will provide:

• Reports and analyses on the LeEP

• Preparatory materials for public briefings and meetings

• Fact sheets and Frequently Asked Questions (FAQs) in the languages predominant in the Astoria area of Queens

• Summary reports from public meetings

• Regular reports to NYSDEC on implementation of the Public Participation Plan

• Draft and final Environmental Impact Statements (EIS) as they are completed

• Contact information for AGe representatives

• Functionality for receiving and posting public comments on the LCEP

Page 5 USPOWERGEN Luyster Creek Energy Project Public Participation PIon January 201 0

For those who do not have access to the internet, documents will be placed in convenient repositories and there will be a toll*free number set up to receive comments and questions.

On a monthly or bi·monthly basis, the schedule to be agreed upon with stakeholders, AGe will prepare progress reports, as further discussed in Section VII below, which will summarize the outreach activities during the previous period and respond to comments and questions collected on the website or by phone. Summary responses to major themes and issues raised on the website may be addressed, as appropriate, at public meetings described in detail below.

The primary contact and leader of this process for AGC will be:

David Perri Astoria Generating Company, LP. a US PowerGen Company 505 Fifth Avenue, 21 51 Floor New York, N.Y. 10017 212-792-0651 [email protected]

IV. Stakeholders

A draft set of stakeholders is attached as Appendix A. It includes those organizations listed on the NYSDEC website as organizations active in environmental justice in Astoria; local institutions and other organizations intended to provide wide coverage of a community that is ethnically, socially and religiously diverse, As necessary, the list will be supplemented as the Project proceeds and will be divided into Primary and Secondary Stakeholders, as described in NYSDEC guidance or other subgroupings as suggested in initial meetings. Except for meeting notices which will be sent via email and US mail as described below, each Stakeholder will be asked whether they prefer to receive materials via email or US mail. v. Meeting Postings and Notifications Relative to Permitting Process

For distribution of information about public meetings as well as background and follow~up documentation, AGC will follow the procedures outlined below.

Notification

Meetings will be announced at least three weeks in advance via email and US mail to the stakeholder list and postings on the AGe website. Public notice of the meetings will also be given in appropriate local weekly newspapers and one daily newspaper of general circulation.

TIming

Meetings will be scheduled for weekday nights that do not coincide with major religious or secular holidays, after working hours, generally during the period between 6:00 and 9:00 pm, unless otherwise determined as a result of discussion with stakeholders.

Page 6 USPOWERGEN

Luyster Creek Energy Project Public Participation Pion January 2010

Location

AGe will work with stakeholders to select a location optimally suited for community participation.

Translation

Translation into Greek and Spanish and other languages if necessary, will be available at meetings upon request. At stakeholders request, AGe will arrange for a briefing on the DEIS in one of these two predominant non-English languages.

Basic meeting materials - fact sheets, FAQs and meeting announcements - will be produced and distributed in predominant local languages.

Preparatory Materials

Background materials prepared for public meetings will be mailed to the stakeholder list via email or US mail, as preferred, at least a week in advance of the meeting in question and posted on the AGC website. For the first briefing and subsequent public meeting, these materials will include:

•A brochure and FAQ explaining the LCEP

•A permitting schedule

• An explanation of the Public Participation process

The DEIS will be released before the second public meeting (see schedule below).

As necessary, AGC may also include responses to specific inquiries or concerns that have arisen in postings on the website or by phone.

Summary and FoIIQw~Up Information

A transcript in English of the proceedings at each public meeting will be prepared and posted on the AGC website.

Following public meetings, a set of follow-up documents will be mailed to those participants who sign in via e-mail or US mail, as preferred by the participant, and posted on the AGC website. These documents, which may be made part of the next scheduled progress report as reqUired in Section VII below, will include:

•A meeting summary and/or minutes

• Responses to specific issues or concerns raised during the meetings

• Updates on AGe's work and on the public outreach process

Reminders and/or revisions to the meeting schedule, time or location

Page 7 USPOWERGEN

Luyster Creek Energy Project Public Participation PIon January 2010

VI. Public Briefings and Dialogues The meetings described below capture only the more structured elements of Public Participation. AGe anticipates a dynamic process that will indude additional meetings as circumstances dictate, the development of working groups for specific tasks if necessary, and informal meetings with individual stakeholders or 5ubgroupings of community representatives. AGe's primary representative will stand ready to respond to questions and concerns on an ongoing basis. To the maximum extent, formal and informal engagement with the community will be documented and included in reporting.

1. Formal Briefing Prior to State Environmental Quality Review (SERR) Scoping Meeting

Date - To be Determined

AGe will hold a formal briefing on its plans for the LCEP with elected officials and key Stakeholders with a role in protecting the local environment. Participants will be asked to review and comment on the draft list of Stakeholders (Appendix A) and on the public outreach process proposed in this document. 1he further meetings below represent major milestones in the SEQR process. Partidpants in this initial briefing will be asked to consider whether any additional forum or representative working group would be helpful. The outreach process wilt be updated based upon their comments.

In addition, stakeholders will be invited to tour the Project site for a direct experience of the existing AGS units and the location and impact of the state of the art generators.

2. Public Meeting 1; SEaR 5copjng Process

Date - To be Determined

Representatives of AGC will present in detail the plans for the LCEP and outline the anticipated impacts on local energy systems and the environment. They will also review in detail the SEQR process and the permitting schedule. The meeting will provide an opportunity for community organizations to discuss impacts of the lCEP on their constituents among the diverse array of Astoria's religious, social and ethnic groups. The SEQR scoping process establishes the environmental issues that the DEIS will focus on, the methodology to be used, and the parameters for study of alternatives and mitigation strategies. While the lead agency will circulate the scope for public comment, this first public meeting will provide a formal vehicle for discussion and gathering of public input that will shape the scope of the EIS.

Stakeholders will also to comment on AGe's plans for further public outreach. Following the meeting, the outreach plan will be revised to reflect stakeholder input. Once finalized, the final DEIS scope will be drculated to Stakeholders. AGC may invite the key stakeholders to play an active role in later public outreach meetings.

A draft scope will be circulated in advance of the public meeting as discussed in section IV above.

3. public Meeting 2: Draft EIS

Date - To be Determined

Page 8 USPOWERGEN

Luyster Creek Energy Project Public Participation Plan January 2010

AGe will hold a meeting to discuss the results of the DEIS for the lCEP, The DEIS will be shared in advance of the meeting, as well as fact sheets translated into predominant neighborhood languages conveying the results in summary form.

At the meeting representatives of AGe will give a presentation that conveys the results of the DEIS in a concise format. Participating stakeholders will be divided into break-out groups for facilitated small group discussion. At the end of the meeting, output from small discussion groups will be shared in summary form with the full assembly of participants.

As discussed above, each of these meetings may be preceded or followed by additional informal meetings with key stakeholders in person and via teleconference. These outreach efforts will be documented and included in reporting.

VII. Document Repositories Full documentation, covering every public document produced for the LCEP and transcripts of pubHc briefings, will be stored at the public libraries located the Queens Borough Public Library, 89-11 Merrick Boulevard, Jamaica, NY 11432 and the Queens Borough Branch Library Astoria Branch, 14-01 , , NY 11101. The same materials will be made available on the AGC website (www.USPowerGen.com). Stakeholders, as well as other interested parties, will be encouraged to store in the same locations any documents they produce pertaining to the permitting of the LCEP so that the repositories include documentation of the full public dialogue.

VIII. Progress Reports

AGC anticipates written updates to the Lead Agency monthly or bi-monthly. The reports will include any public documents produced during the previous period, transcripts of any formal public meetings, descriptions of other outreach activities, and any other work completed in the permitting process. The progress reports without the bulky attachments will be mailed to stakeholders via email or US mail, as preferred. The progress reports with all attachments will be posted on the AGC website and placed in the repositories.

IX. Final Report

Upon receipt of the permit, AGC will prepare a final report on public participation in the permitting process with the full record of documents produced for the process and transcripts of meetings included as appendices. If permits are received and work proceeds on schedule, AGC anticipates completion of this report after receipt of all permits.

A summary of the report will be mailed to the stakeholder list via email or US mail, as preferred.

Page 9 USPOWERGEN

ApPENDIX A- STAKEHOLDERS

Revised November 2010

AI Gentile 30th Avenue Area Merchant Association 36-17 30th Avenue Astoria, NY 11103 Tel: 718-956-3366 Fax: 718-278-1766

Asbestos Workers Union Local 12 2519 43rd Avenue Long Island aty, NY 11101 Tel: 718-784-3456

Michael Gianaris Assembly Member 21·77 31 Street, Suite 107 Astoria, NY 11105 Tel: 718·545-3889 Fax: 718-545-3607 E-mail: [email protected]

Cathy Nolan Assembly Member 41·02 , Suite 26 Sunnyside, NY 11104 Tel: 718-784-3194 Fax: 718-472-0648 E-mail: [email protected]

Peter Iwanowicz Assistant Secretary for Environment State Capitol Albany, NY 12224 Tel: 518-402-8448 E-mail: [email protected]

Astoria Homeowners, Tenants and Business Civic Association 21·20 49th Street Astoria, NY 11105 Tel: 718-721-3690

Astoria Islamic Center Inc. 2221 33rd Street Astoria, NY 11105

Astoria Residents Reclaiming Our World (ARROW) P.O. Box 9060 Astoria, NY 11103 Tel: 718·595-2829 E-mail: [email protected]

Astoria Restoration Association 3128 Astoria, NY 11105 Tel: 718-726-0034 Fax: 718-726·0034 uSPOW ERG EN

Luyster Creek Energy Project Public Participation PIon January 2010

Karen Overton Astorla/UC Waterfront Parks! Astoria UC Catalyst Coordinator 35-30 35th 5treet Astoria, NY 11106 Tel: 718-706·8044 E-mail: [email protected]

Bangladesh American Association for Rehabilitation in New York 2363 5teinway Street Astoria, NY 11105 Tel: 718-278-8181 Fax: 718-278-8181 E-mail: [email protected]

BFFY 5teinway Senior Center 20-43 Astoria, NY 11105 Tel: 718-728-8473 Fax: 718-278-5301 E-mail: [email protected]

Blasters, Drill Runners &. Miners Local 29 4302 Ditmars Boulevard Astoria, NY 11105

Tom Klein Boilermakers Local No.5 24 Van SUcen Avenue Floral Park, NY 11001 Tel: 718-895-7722 Fax: 516-326-3435 E-mail: [email protected]

Steven Ludwlgsson Boilermakers local No.5 24 Van Silcen Avenue Floral Park, NY 11001 Tel: 516-326-2500 Fax: 516-326-3435

Bronx Community Board 1 3024 Third Avenue Bronx, NY 10455 Tel: 718-585-7117 Fax: 718-292-0558 E-mail: [email protected]

Bronx Community Board 2 1029 East 163rd Street Bronx, New York 10459 Tel: 718-328-9125 Fax: 718-991-4974 E-mail: [email protected]

Catholic War Veterans of the USA Inc 21 43 29th 5treet Astoria/ NY 11105

Cement and Conaete Wor1c:ers Union local #20 3636 33rd Street Astoria, NY 11106 Tel: 718-361-8131

Page 2 USPOWERGEN

Luyster Creek Energy Project Public Participation Plan January 2010

Marie Tomiali, Executive Director Central Astoria Local Development Corporation 25-69 38th Street Astoria, NY 11103 Phone: 718·728-7820 Fax: 718·728·7413 E-mail: [email protected]

Cephalonian Association Aenos Inc 23 17 29th Street Astoria, NY 11105 Tel: 718-204-8491

Garry Brown Chair New York Public Service Commission 3 Empire State Plaza Albany, NY 12223

Church of Christ Holy Spirit SCience of Mind World Mission Inc. 2106 35th Street, Apt SF Astoria, NY 11105

Jim Gennaro City Council Member 185-10 Union Turnpike Fresh Meadows, NY 11366 Tel: 718-217-4969 Fax: 718-217-4968 E-mail: [email protected]

Peter Valone Jr. City Councilman 22-45 31st Street, 2nd Floor Astoria, NY 11105 Tel: 718-274-0007 Fax: 718-274-6060 E-mail: [email protected]

Clean Air NY 342 Broadway, Suite 404 New York, NY 10013 Tel: 877-458-8247 E-mail: [email protected]

Coalition Helping Organize a Kleaner Environment (CHOKE) 33-60 21st Street Long Island City, NY 11106 Tel: 718-274-4767 Fax: 718-278-0919 E-mail: [email protected]

Cas Holloway Commissioner NYC Department of Environmental Protection 59-17 Flushing, NY 11373 Tel: 212-788-8235 Fax: 212-788-3229 E-mail: [email protected]

Communications Workers of America AFL-CIO (CWA) 28 10 Astoria Boulevard Long Island City, NY 11102

Page 3 USPOWERGEN

Luyster Creek Energy Prole,t Public Participation PIon January 2010

Richard M. Cherry, President and ceo Community Environmental Center 43-10 11th 5treet long Island City, NY 11101 Tel: 718·784-1444 x 107 Fax: 718-784-8347 E-mail: [email protected]

Edward Babor Congresswoman Carolyn Maloney 22·11 Astoria Boulevard Astoria, NY 11102 Tel: 718 932 1804 Fax: 718932 1805 E-mail: [email protected]

Council on the Environment of NYC 51 Chambers Street, Room 228 New York NY 10007 Tel: 212-788-7900 Fax: 212-788-7913 E-mail: [email protected]

Jonathan Szott Councilman Peter Vallone Jr. 22-45 31st Street Astoria, NY 11105 Tel: 718-274-4500 Fax: 718-726-0357 E-mail: [email protected]

Cypreco of America Inc 2350 27th 5treet Astoria, NY 11105

Tom Congdon Deputy secretary for Energy State Capitol Albany, NY 12224 E-mail: [email protected]

Earthjustice 156 William Street, Suite 800 New York, NY 10038 Tel: 212-791-1881 x 224 Fax: 212-918-1556

EI Diario La Prensa 1 Metrotech center, 18th Floor Brooklyn, NY 11201

Excavators' 731 Property Corp (Excavators Union Local 731) 3411 35th Avenue Astoria, NY 11106 Tel: 718-706-0720

Page 4 USPOWERGEN

Luyster Creek Energy Project Public Participation PIon January 2010

Federation of Hellenic Societies of Greater New York Inc. 2251 29th Street Astoria, NY 11105 Tel: 718-204-6500 Fax: 718-204-8986

Federation of Italian-American Organizations of Queens Inc. 29·21 21st Avenue Astoria, NY 11105

Free Apostolic Church of Pentecost 2047 Steinway Street Astoria, NY 11105 Tel: 718-841-9291

Giannitsa Association Megas Alexandros Inc 2226 23rd Street Astoria, NY 11105

Greater Astoria Historical Society 35-20 Broadway, 4th Floor long Island City, NY 11106 Tel: 718-278-0700

Greek American Broadcasting Info & Cultural Activities Corporation 20 12 20th Street Astoria, NY 11105

Greek American Home Owners of New York Inc. 23·24 31st Street Astoria, NY 11105

Demetres Beryeles Greek Cultural Center 26-80 30th Street Astoria, NY 11102 Tel: 718-726-7329 E-mail: [email protected]

Katie Elman Green Shores 25-11 34th Street, Apt 3F Astoria, NY 11103 Tel: 917-497-6273 E+mail: elmank@yahoo,com

International Brotherhood of Electrical Workers (IBEW) 158+11 Harry Van Arsdale Avenue, 4th Floor Flushing, NY 11365 Tel: 718-591-4000 Fax: 718-380-8998

International Brotherhood of Teamsters 3609 21st Avenue Astoria, NY 11105

Page 5 USPOWERGEN

Luysfer Creek Energy Project Public Participotion Pion January 2010

Iron Workers Locals 40 & 36 Joint 35*23 36th Street Astoria, NY 11106 Tel: 718-433-4195

Kefalos Society of America Inc. 2043 Steinway Street Astoria, NY 11105 Tel: 718-358-1133

Kid Krazy Early Childhood Development Center Annex 21·3521 Avenue Astoria, NY 11105 Tel: 718-545-5728 Fax: 718-545-5840 E-mail: [email protected]

Kiwanis International 2131 Shore Boulevard Astoria, NY 11105

Marcia Bystryn league of Conservation Voters 30 Broad Street New York, NY 10004-2909 Tel: 212-361-6350 Fax: 212-361-6363 E-mail: [email protected]

UCIAstoria Journal 69-60 Grand Avenue Maspeth, NY 11378

Michael Cavanaugh Local 740 Millwrights and Machinery Erectors 89-07 Atlantic Avenue Woodhaven, NY 11421 Tel: 718,849-3636 E-mail: mcavanaugh740@verizon,net

Local 807 Labor-Management Health Pension Funds 3243 49th Street Astoria, NY 11103 Tel: 718-274-5353

Local 891 3641 28th Street Long Island City, NY 11106

Materials For The Arts 33,00 Northern Boulevard, 3rd Floor Long Island City, NY 11101 Tel: 718-729-3001 Fax: 718-729-3941 E-mail: info@mfta,nyc.gov

Page 6 USPOWERGEN

Luyster Creek Energy Project Public Participation Pion January 2010

Dr. Robert Kulikowski, Director Mayor's Office of Environmental Coordination 2538roadway, 14th Floor New York, NY 10007 E-mail: [email protected]

Adam Freed Mayor's Office of Sustainability 253 Broadway, 10th Floor New York, NY 10007 Tel: 212-788-1400 Fax: 212-788-7558 E-mail: [email protected]

Carolyn Maloney Member of Congress 28-11 Astoria Boulevard Astoria, NY 11102-1933 Tel: 718-932-1804 Fax: 718-932-1805 E-mail: [email protected]

Muslim American Society of Queens 3513 23rd Avenue Astoria, NY 11105

National Coalition of Physicians for Healthcare Awareness Inc 2202 Steinway Street Astoria, NY 11105

Ashok Gupta Natural Resources Defense Council 40 West 20th Street New York, NY 10011 Tel: 212-727-2700 Fax: 212-727-1773 E-mail: [email protected]

Jennifer Powers Natural Resources Defense Council 40 West 20th Street New York, NY 10011 Tel: 212-727-2700 Fax: 212-727-1773 E-mail: [email protected]

New York City Asthma Partnership 2 Lafayette Street, Box eN 36A New York, NY 10007 Tel: 212-513-0528 Fax: 212-676-2071 E-mail: [email protected]

New York Daily News 450 West 33rd Street New York, NY 10001 Tel: 212-210-2100

Page 7 USPOWERGEN

lvyster Creek Energy Project Public Participation Pion January 2010

Ross MacWhinney &. Melissa Reburiano, Project Coordinators New York Public Interest Research Group (NVPIRG) Queens College Chapter City University of New York 65-30 Student Union Building, Room 8-22 Flushing, NY 11367 Tel: 718-997-3954 E-mail: [email protected]

Jason Chin-Fatt, Project Coordinator New York Public Interest Research Group (NVPIRG) Queensborough Community College Chapter 222+05 56th Avenue Student Union Building, Basement Bayside, NY 11364 Tel: 718-225-9121 E-mail: [email protected]

Rajendra Addepali New York State Department of Public Service 3 Empire State Plaza Albany, NY 12223

NY 1 News 75 Ninth Avenue New York, NY 10011 Tel: 212-379-3311

NY Power Authority 123 White Plains, NY 10601-3170 Tel: 914-287-4271 E-mail: [email protected]

John Liu NYC Comptroller One Centre Street New York, NY 10007 Tel: 212~669-3500 Fax: 212-669-2707 E-mail: [email protected]

Amanda M. Burden, Director NYC Department of Planning 22 Reade Street New York, NY 10007 Tel: 212-720-3200 Fax: 212-720-3219 E-mail: [email protected]

Toby Ann Stavisky NYS Senator 144-36 Willets Point Boulevard Flushing, NY 11357 Tel: 718-445-0004 Fax: 718-445-8398 E-mail: [email protected]

Page 8 USPOWERGEN

Luyster (reele Energy Project Public Participation Pion JOl'lUory 2010

Pancyprian Association Inc 2315 31st Street Astoria, NY 11105 Tel: 718-278-9729

Peniel Baptist Church Inc. 1954 38th Street Astoria, NY 11105 Tel: 718-956-4732

Polish Navy Veterans Association of America Inc. 2208 5teinway Street Astoria, NY 11105

Mary Faye Private Citizen 311 77th Street Jackson Heights, NY E·mail: [email protected]

Bill de Blasia Pubic Advocate 1 Centre Street, 15th Roor New York, NY 10007 Tel: 212-669-7200 Fax: 212-669-4701 E-mail: [email protected]

Helen Marshall Queens Borough President 120-55 Queens Boulevard Kew Gardens, NY 11424 Tel: 718-286-3000 Fax: 718-286-2876 E-mail: [email protected]

Jack Friedman Queens Chamber of Commerce 7520 Astoria Boulevard Flushing, NY 11370-1131 Tel: 718-898-8500 Fax: 718-898-8599 E-mail: [email protected]

Queens Chronicle P.O. Box 74-7769 Rego Pari<, NY 11374 Tel: 718-205-8000

Joan Asselin, Lucille Hartmann 36·01 35th Avenue Astoria, NY 11106 Tel: 718-786-3335 Fax: 718-786-3368 E-mail: [email protected]

Page 9 USPOWERGEN

Luyster Creek Energy Project Public Participation PIon January 2010

Gloria D'Amico Queens County Clerk's office 88·11 , 1st floor Jamaica, NY 11439

Queens Courier SChneps Publications Inc 38-15 Bell Boulevard Bayside, NY 11361 Tel: 718-224-5863 Fax: 718-224-5441 E·mai1: [email protected]

Queens Philharmonic 2028 27th Street Astoria, NY 11105

Queens Tribune 174-15 Horace Harding Expressway Fresh Meadows, NY 11365 Tel: 718-357-7400

Reserve Officers Association of the United states 2139 38th Street Astoria, NY 11105

Sacred Patriarchal &. Stavropegial Orothodox Monastary of st. Irene 3604 23rd Avenue Astoria, NY 11105 Tel: 718-626-6225

James Gallagher, senior Vice President for Energy Economic Development Corporation 110 William Street New York, NY 10038 E-mail: [email protected]

Sons of Italy in America 2037 28th Street Astoria, NY 11105

South East Queens Concerned Neighbors P.O. Box 200600 South Ozone Park, NY 11420

Roy Wilkins Park Southern Queens Park Association 177th Street & Baisley Boulevard Jamaica, NY 11434 Tel: 718-276-4630 Fax: 718-276-4630 E-mail: [email protected]

Page 10 USPOWERGEN

Luyster Creek Energy Project Public Participation Pion January 2010

Springfield Rosedale Community P.O. Box 220265 Rosedale, NY 11422 Tel: 718-723-6463 Fax: 718-361-3886

St. Irene Chrysovalantou Nursery &. Kindergarten 36-07 23 Avenue Astoria, NY 11105 Tel: 718-626·6225 Fax: 718-626-7665 E-mail: [email protected]

Kim Harriman State Capital State Capital Albany, NY 12224

George Onorato State Senator 28-11 Astoria Boulevard Long Island City, NY 11102 Tel: 718-545-9706 Fax: 718-726-2036 E-mail: [email protected]

Sullogos Nomou Magnislas Argonayte ltd 3811 Ditmars Boulevard 119 Astoria, NY 11105 Tel: 718-728-5887

Sunnyside Foundation for Community Planning It. Preservation 45-18 Skillman Avenue Sunnyside, NY 11104 Tel: 718-392-9139

Syllogos Kreton Minos Inc. 2227 33rd Street Astoria, NY 11105

The Hellenic Link Inc. 38-11 Ditmars Boulevard, Suite 278 Astoria, NY 11105

The Peoples Museum 2227 Crescent Street Astoria, NY 11105 Tel: 718-204-7941

Times Ledger Newspapers 41-02 Bell Boulevard, 2nd Floor Bayside, NY 11361 Tel: 718-229-0300

Page 11 USPOWERGEN

Luyster Creek Energy Project Public Participation Pion January 2010

Rosemary Poveromovo United Community Civic Association 22-32 81st Street Jackson Heights, NY 11370 Tel: 718-932-5415 Fax: 718-932-9014 E-mail: [email protected]

United Contractors Alliance 21-77 31st Street Astoria, NY 11105

United Piano Workers Union local 102 2810 Astoria Boulevard Long Island City, NY 11102 Tel: 718-728-1070

Elizabeth Yeampierre UPROSE 166A 22nd Street Brooklyn, NY 11232 Tel: 718-492-9307 E-mail: [email protected]

Charles B. Rangel US House of Representatives 163 West 125th Street, Room 737 New York, NY 10027 Tel: 212-663-3900 Fax: 212-663-4277

Charles SChumer US senate 757 Third Avenue, Room 1702 New York, NY 10017 Tel: 212-486-4430 Fax: 212-486-7693 E~mail: [email protected]

Kirsten Gillibrand US Senate 780 Third Avenue, Suite 2601 New York, NY 10017 Tel: 212-688-6262 Fax: 212-688-7444 E~mail: [email protected]

Utility Workers Union of America 5 West 37th Street, 7th Floor New York, NY 10018 Tel: 718-575-4400 Fax: 718-575-3852

James Slevio UWUA 1-2 5 West 37th Street New York, NY 10019 Tel: 212~S7S~4400 E~mail: james.slevin@uwua1 ~2.org

Page 12 USPOWERGEN Luyster Creek Energy ProJect Public Participation Plan January 2010

Western Queens Gazette 42-16 34th Avenue long Island City, NY 11101 Tel: 718-361-6161 Fax: 718-784-7552 E-mail: [email protected]

Zoodohos Pighl of Andros Society Inc 2119 28th Street Astoria, NY 11105

Email Contactsj

Julie Greenberg [email protected]) Asbid Rapp ([email protected]) Hali Canson ([email protected]) David Cohen ([email protected]) Eric Bergman ([email protected]) John Beck ([email protected]) Mark Pereria ([email protected]) Matthew Cindr ([email protected]) Shaun Campbell ([email protected]) [email protected] [email protected] [email protected] [email protected]

Lead Agency;

NYSDEC Kevin Kispert Jack Nasca E-mail: [email protected] E-mail: [email protected]

Stephen Tomasik Michelle Moore E-mail: [email protected] E-mail: [email protected]

project Team CUSpG, Nixon Peabody, ESS Group. Inc,):

USPG David Perri Barry Durham E-mail: [email protected] E-mail: [email protected]

John Reese Mark Sudbey E-mail: [email protected] E-mail: [email protected]

Uam Baker Jeff Hunter E-mail: [email protected] E-mail: [email protected]

Ralph Vanacore Craig Hart E-mail: [email protected] E-mail: [email protected]

Andy Oliver E-mail: [email protected]

Page 13 USPOWERGEN

Luyster Creek Energy Project Public PartkipOlion Plan Januory 2010

Nixon Peabody Scott Turner E-mail: [email protected]

ESS Group, Inc. Steve Wood Chris Rein E-mail: [email protected] E·mail: [email protected]

Additional Contactsj

NY Building Congress Dick Anderson Phone: 212·481·9230 E-mail: [email protected]

Assodation for a better NY Jen Hensley Phone: 212-835-2767 E-mail: [email protected]

Deputy Mayors Bob Steele Stephen Goldsmith E-mail: [email protected]

Poge 14