CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 & Peterborough Minerals and Waste Site Specific Proposals DPD Examination

APPENDIX A – Schedule of Councils’ Proposed Changes that go to soundness

Reference Plan Reference Change No SSP S1 Paragraph 3.10 Amend to read:

The Mineral Planning Authorities are aware of the long standing plans for the proposed improvements of to the A14 trunk road between, Ellington to the west of Huntingdon and Fen Ditton to the northeast of , that will require exceptionally large quantities of sand and gravel. However, the Government has confirmed that it can not fund this scheme principally because in its current form, it is unaffordable. Approximately 2 million tonnes of sand and gravel will be required. However, Government has recognised the economic importance of this route and that congestion is a serious problem and therefore remain committed to developing a solution. Work has now begun on the Strategic Corridor Study with the aim of identifying a viable way forward, including exploring alternative methods for managing traffic volumes, considering potential delivery mechanisms, and any potential future improvements. A package of alternative proposals for improving the A14 are anticipated to be forthcoming during the lifetime of this Plan. Consequently Areas of Search for A14 borrowpits are proposed as it is still anticipated that mineral resources for some form of scheme will be needed within the lifetime of the Plan (up to 2026). The future release of mineral will be commensurate with the need for mineral for any improvements to the A14 only. Borrowpit allocations have, therefore, been identified for this project only. Any proposals to extend the life of these borrowpits to serve the open market will be resisted will be considered in the context of Core Strategy Policy CS13 Additional Mineral Extraction.

SSP S2 Policy SSP M2, Amend first sentence to read: Sand and Gravel Borrowpit The site specific Area of Search allocations for sand and gravel borrowpits to serve any future Allocations the A14 improvements upgrade only are:-

CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No Table: Amend Road Scheme Column (all rows) to read: Any Future A14 Improvements A14 Ellington to Fen Ditton, Cambridgeshire

A site profile for each sand and gravel borrowpit Area of Search allocation is provided in chapter 7.

SSP S3 Paragraph 3.30 Amend to read:

Borrowpits are extraction sites which supply a single project only for a temporary period. They arise where major civil engineering proposals come forward e.g. for road improvement schemes and where there are aggregate and other minerals available in the immediate area. The Minerals Planning Authorities are aware of the long standing plans for the proposed improvement of the one large road scheme which will require exceptionally large quantities of engineering clay of around 2.5 million cubic metres. This is the proposed improvement of the A14 trunk road between Ellington to the west of Huntingdon, and Fen Ditton to the northeast of Cambridge and the associated likely requirements for significant quantities of engineering clay for improvement works. However, the Government has confirmed that the current proposed A14 improvement scheme has now been withdrawn principally because it is unaffordable. Government has however recognised the economic importance of this strategic route and that congestion is a serious problem and therefore remain committed to developing a solution. Work has now begun on the Strategic Corridor Study with the aim of identifying a viable way forward, including exploring alternative methods for managing traffic volumes, considering potential delivery mechanisms, and any potential future improvements. A package of alternative proposals for improving the A14 are anticipated to be forthcoming during the lifetime of this Plan. Consequently Areas of Search for A14 borrowpits are proposed as it is still anticipated that mineral resources for some form of scheme will be needed at a point within the lifetime of the Plan (up to 2026). The future release of mineral will be commensurate with the need for mineral for any improvements

2 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No to the A14 only. Given that this is a significant quantity of material an exception is made and borrowpit allocations are identified for this project only. Any proposals to extend the life of these borrowpits to serve the open market will be resisted will be considered in the context of Core Strategy Policy CS13 Additional Mineral Extraction.

SSP S4 Policy SSP M7, Amend to read: Engineering Clay Borrowpit The site specific Area of Search allocations for engineering clay borrowpits to serve any future Allocations the A14 improvements upgrade only are:-

Table: Amend Road Scheme Column (all rows) to read: Any Future A14 Improvements A14 Ellington to Fen Ditton, Cambridgeshire

A site profile for each for engineering clay Area of Search allocation is provided in chapter 7.

SSP S5 Policy SSP W1 - Amend entry for Warboys Industrial Estate as follows: Waste Recycling and Recovery Area of Search column: Facilities (Non No Yes landfill), Warboys Industrial Estate In Vessel Composting column; Yes No

Inert Waste Recycling column: Yes No

SSP S6 Implementation & There are numerous suggested amendments to the Implementation and Monitoring table which Monitoring Table include:

3 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No for Mineral & Replacing the term ‘Consultation Areas’ with ‘Safeguarding Areas’ in Indicator 1 as set out in Waste allocations Appendix A and Updating the Implementation & Monitoring Table to take account of the changes and policies being proposed, including a new indicator to monitor ‘A14 Improvement Projects’ as set out in Appendix A.

The full list of changes are set out in Appendix A.

SSP S7 Section 7, Map for Amend map to show revised existing mineral and waste consent area & consultation area as Site M1A under follows: Heading 7.1.1 – Cottenham (M9E)

(See larger map at the end of schedule)

SSP S8 Section 7, Map for Amend map to show revised allocation amended to remove the Scheduled Monuments from the Site M1F under allocation (i.e. the four barrows in the 3 monuments in the southern area of the allocation): Heading 7.1.6 – Pode Hole and Eye/Thorney (M9R)

4 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No

(See larger map at the end of schedule)

SSP S9 Section 7, Title 7.2 Amend titles to read: for Sand and 7.2 Area of Search Allocations for Sand and Gravel Borrowp Pits - Site Gravel borrowpit Profiles Site Profiles Area of Search Allocations for Sand and Gravel Borrowp Pits Allocations

SSP S10 Paragraph 7.16 Amend Paragraph 7.16, first sentence, to read: and related table The extent of the Area of Search allocations for sand and gravel allocations borrowpits are is shown on the maps that follow.

Table: Amend Road Scheme Column to read: Any Future A14 Improvements A14 Ellington to Fen Ditton, Cambridgeshire

SSP S11 Site Profile M2A, Amend to read: Galley Hill

5 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No Fenstanton Site Name: Galley Hill, Fenstanton Southern Site (Area of Search) (Southern Site), Description of Proposed Use: Mineral Extraction: Area of Search for a Sand and Gravel Summary BorrowPpit for any future improvements of the A14 upgrade Estimated Reserve: Approximately 0.1 million tonnes Area: 25.8 (ha) Approximate Timescale: Extraction to be linked to any future improvements of the A14 upgrade District: Huntingdonshire Parish: Fenstanton & Hemingford Grey Grid Ref: TL 298 681

SSP S12 Site Profile M2A - Amend 1st bullet point to read: Galley Hill Fenstanton (M9I), • Suitable as borrowpit for any future A14 upgrade improvements only Paragraph 7.18, Implementation Add additional bullet point to the list of implementation issues: Issues • The release of mineral will be commensurate with the need for mineral for any future improvements to the A14 only

SSP S13 Site Profile M2B - Amend to read: Oxholme Farm, Summary Site Name: Oxholme Farm (Area of Search) Description of Proposed Use: Mineral Extraction: Area of Search for a Sand and gGravel Bborrowpit for any future improvements of the A14 upgrade Estimated Reserve: 1.5 million tonnes Area: 61.3 (ha) Approximate Timescale: Extraction to be linked to any future improvements of the A14

6 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No upgrade District: Huntingdonshire Parish: Fenstanton Grid Ref: TL 300 676

SSP S14 Site Profile M2B - Amend 1st bullet point to read: Oxholme Farm • Suitable as borrowpit for any future A14 upgrade improvements only (M9I), Paragraph 7.20, Amend 2nd bullet point to read: Implementation • Route of A14 upgrade In the event of off road improvements involving a new road Issues crossing this borrowpit site, the route of any new road (including slip roads) should to be safeguarded against mineral extraction

Add additional bullet point to the list of implementation issues: The release of mineral will be commensurate with the need for mineral for any future improvements to the A14 only SSP S15 Site Profile M2C - Amend to read: South West Brampton, Site Name: South West Brampton (Area of Search) Summary Description of Proposed Use: Mineral Extraction: Area of Search for a Sand and Gravel Borrowp Pit for any future improvements of the A14 upgrade only. Estimated Reserve: Approximately 2 million tonnes Area: 53.3 (ha) Approximate Timescale: Extraction to be linked to any future improvements of the A14 upgrade works District: Huntingdonshire Parish: Brampton Grid Ref: TL 202 694

7 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No SSP S16 Site Profile M2C - Amend 1st bullet point to read: South West Brampton (M9T), • Suitable as borrowpit for any future A14 upgrade improvements only Paragraph 7.22, Implementation Add additional bullet point to the list of implementation issues: Issues • The release of mineral will be commensurate with the need for mineral for any future improvements to the A14 only

Amend 9th bullet point to read:

• Route of A14 In the event of off road improvements involving a new road crossing this borrowpit site, the route of any new road (including slip roads) should to be safeguarded from against mineral extraction • SSP S17 Site Profile M2D Amend to read: West of Brampton, Summary Site Name: West of Brampton (Area of Search) Description of Proposed Use: Mineral Extraction: Area of Search for a Sand and Gravel potential Borrowp Pit for any future improvements of the A14 upgrade only. Estimated Reserve: Approximately 1 million tonnes Area: 82.04 (ha) Approximate Timescale: Extraction to be linked to any future improvements of the A14 upgrade works District: Huntingdonshire Parish: Brampton Grid Ref: TL 194 699 SSP S18 Site Profile M2D - Amend 1st bullet point to read:

8 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No West of Brampton (M9T), Paragraph • Suitable for borrowpit and ancillary uses for any future A14 upgrade improvements 7.24, only Implementation Issues Add additional bullet point to the list of implementation issues:

• The release of mineral will be commensurate with the need for mineral for any future improvements to the A14 only

Amend 9th bullet point to read:

• Route of A14 In the event of off road improvements involving a new road crossing this borrowpit site, the route of any new road (including slip roads) should to be safeguarded from against mineral extraction

SSP S19 Site Profile M2E - Amend to read: Weybridge Farm, Summary Site Name: Weybridge Farm, Alconbury (Area of Search) Description of Proposed Use: Minerals Extraction: Area of Search for a Sand and Gravel Borrowpit for any future improvements of the A14 upgrade only. Estimated Reserve: Approximately 0.2 million tonnes Area: 16.3 (ha) Approximate Timescale: Extraction to be linked to any future improvements of the A14 upgrade works District: Huntingdonshire Parish: Alconbury Grid Ref: TL 182 721

9 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No SSP S20 Site Profile M2E - Amend 1st bullet point to read: Weybridge Farm, Alconbury (M9Z), • Suitable as a borrowpit for any future the A14 upgrade improvements only Paragraph 7.26, Implementation Add additional bullet point to the list of implementation issues: Issues • The release of mineral will be commensurate with the need for mineral for any future improvements to the A14 only

SSP S21 Document C03, Amend to read: Site Profile M2F - Woolpack Farm, Site Name: Woolpack Farm, Galley Hill (Area of Search) Galley Hill, Description of Proposed Use: Mineral Extraction: Area of Search for a Sand and Ggravel Summary Bborrowpit for any future improvements of the A14 upgrade only. Estimated Reserve: Approximately 1.5 million tonnes Area: 62.7 ha Approximate Timescale: Extraction to be linked to any future improvements of the A14 upgrade District: Huntingdonshire Parish: Hemingford Grey Grid Ref: TL 295 682

SSP S22 Site Profile M2F - Amend 1st bullet point to read: Woolpack Farm, Galley Hill (M9I), • Suitable for borrowpit for any future A14 upgrade improvements only Paragraph 7.28, Implementation Add additional bullet point to the list of implementation issues: Issues

10 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No • The release of mineral will be commensurate with the need for mineral for any future improvements to the A14 only

SSP S23 Section 7, Title Amend titles to read: 7.7, Clay borrowpit 7.7 Area of Search Allocations for Engineering Clay Borrowp Pits - Site site profiles Profiles Area of Search Allocations for Engineering Clay Borrowpits Allocations SSP S24 Paragraph 7.37 Amend Paragraph 7.37, first sentence, to read: and related table The extent of the Area of Search allocations for engineering clay borrowpits to serve any future improvements of the scheme are shown on the inset maps that follow.

Table: Amend Road Scheme Column to read: Any Future A14 Improvements A14 Ellington to Fen Ditton, Cambridgeshire

SSP S25 Site Profile M7A - Amend to read: Boxworth End Farm, North of Site Name: Boxworth End Farm, North of Trinity Foot Junction (Area of Search) Trinity Foot Jnct, Description of Proposed Use: Clay and general fill borrowpit for any future improvements of Summary the A14 Estimated Reserve: 117,500 m3 Area: 11.9 (ha) Approximate Timescale: Jan 2012 – Jan 2015 Extraction to be linked to any future improvements of the A14 District: Parish: Swavesey (adjacent to parishes Boxworth & Conington) Grid Ref: TL 354 663

11 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No

SSP S26 Site Profile M7A - Amend 1st bullet point to read: Boxworth End Farm, North of • Suitable as a borrowpit for any future A14 upgrade improvements only Trinity Foot, Paragraph 7.40, Amend 2nd bullet point to read: Implementation Issues • Route of A14 upgrade In the event of off road improvements involving a new road crossing this borrowpit site, the route of any new road (including slip roads) should be safeguarded against mineral extraction

Add additional bullet point to the list of implementation issues:

• The release of mineral will be commensurate with the need for mineral for any future improvements to the A14 only

SSP S27 Site Profile M7B - Amend to read: Brickyard Farm, Boxworth, Site Name: Brickyard Farm, Boxworth (Area of Search) Summary Description of Proposed Use: Clay - and general fill for borrowpit for any future improvements of the A14 upgrade Estimated Reserve: 75,000 m3 Area: 104.6 (ha) Approximate Timescale: Jan 2012 – Jan 2015 Extraction to be linked to any future improvements of the A14 District: South Cambridgeshire Parish: Boxworth (Conington (S), Swavesey, fFen Drayton & are adjacent parishes) Grid Ref: TL 349 657

12 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No SSP S28 Site Profile M7B - Amend 1st bullet point to read: Brickyard Farm, Boxworth, • Suitable as a borrowpit for any future A14 upgrade improvements only Paragraph 7.42, Implementation Amend 2nd bullet point to read: Issues • Route of A14 In the event of off road improvements involving a new road crossing this borrowpit site, the route of any new road (including slip roads) should be safeguarded against mineral extraction

Add additional bullet point to the list of implementation issues:

• The release of mineral will be commensurate with the need for mineral for any future improvements to the A14 only

SSP S29 Site Profile M7C - Amend to read: New Barns Farm, Conington, Site Name: New Barns Farm, Conington, (Area of Search) Summary Description of Proposed Use: Clay - and general fill borrowpit for any future improvements of the A14 upgrade Estimated Reserve: 50,000 m3 Area: 129.9 (ha) Approximate Timescale: Aug 2012 – Aug 2014 Extraction to be linked to any future improvements of the A14 District: South Cambridgeshire Parish: Conington (S) (adjacent to Boxworth, Swavesey & Fen Drayton parishes) Grid Ref: TL 336 664

13 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No

SSP S30 Site Profile M7C - Amend 1st bullet point to read: New Barns Farm, Conington. • Suitable as a borrowpit for any future the A14 upgrade improvements only

Paragraph 7.44, nd Implementation Amend 2 bullet point to read: Issues • Route of the A14 upgrade In the event of off road improvements involving a new road crossing this borrowpit site, the route of any new road (including slipways) should be safeguarded against mineral extraction

Add additional bullet point to the list of implementation issues:

• The release of mineral will be commensurate with the need for mineral for any future improvements to the A14 only

SSP S31 Site Profile M7D - Amend to read: North Bar Hill, Noon Folly Farm, Site Name: North Bar Hill, Noon Folly Farm (Area of Search) Summary Description of Proposed Use: Clay - and general fill borrowpit for any future improvements of the A14 upgrade Estimated Reserve: 2,500 m3 Area: 9.9 (ha) Approximate Timescale: Jan 2012 – Nov 2015 Extraction to be linked to any future improvements of the A14 District: South Cambridgeshire Parish: Swavesey & Longstanton (adjacent to Lolworth & Bar Hill) Grid Ref: TL 380 644

14 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No SSP S32 Site Profile M7D - Amend 1st bullet point to read: North Bar Hill, Noon Folly Farm • Suitable for use as borrowpit for any future A14 upgrade improvements only (M9P), Paragraph 7.46, Amend 2nd bullet point to read: Implementation Issues • No mineral extraction will be permitted on the line of the A14 upgrade In the event of off road improvements involving a new road crossing this borrowpit site, the route of any new road (including slipways) should be safeguarded against mineral extraction

Add additional bullet point to the list of implementation issues:

• The release of mineral will be commensurate with the need for mineral for any future improvements to the A14 only

SSP S33 Site Profile M7E - Amend to read: North Dry Drayton Junction, Slate Site Name: North Dry Drayton Junction, Slate Hall Farm (Area of Search) Hall Farm, Description of Proposed Use: Clay - and Ggeneral Ffill borrowpit for any future improvements Summary of the A14 upgrade Estimated Reserve: 245,000 m3 Area: 27.9 (ha) Approximate Timescale: Jan 2012 – April 2014 Extraction to be linked to any future improvements of the A14 District: South Cambridgeshire Parish: Oakington & Westwick, Girton (adjacent to parish Dry Drayton) Grid Ref: TL 401 628

15 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No SSP S34 Site Profile M7E - North Dry Drayton • Suitable for borrowpit for any future A14 upgrade improvements only Junction, Slate Hall Farm, Amend 7th bullet point to read: Paragraph 7.48, Implementation • No mineral extraction will not be permitted on the line of the A14 upgrade route In the Issues event of off road improvements involving a new road crossing this borrowpit site, the route of any new road (including slipways) should be safeguarded against mineral extraction

Add additional bullet point to the list of implementation issues:

• The release of mineral will be commensurate with the need for mineral for any future improvements to the A14 only

SSP S35 Site Profile M7F - Amend to read: North Junction 14, Grange Farm, Site Name: North Junction 14, Grange Farm (Area of Search) Summary Description of Proposed Use: Clay borrow Ppit for any future improvements of the A14 upgrade Estimated Reserve: 125,000 m3 Area: 35.8 (ha) Approximate Timescale: Jan 2012 – Nov 2015 Extraction to be linked to any future improvements of the A14 District: South Cambridgeshire Parish: Girton Grid Ref: TL 408 625

16 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No SSP S36 Site Profile M7F - Amend 1st bullet point to read: North Junction 14, Grange Farm, • Suitable for borrowpit use for any future A14 upgrade improvements only Paragraph 7.50, Implementation Amend 5th bullet point to read: Issues • No mineral extraction will be permitted on the proposed A14 route In the event of off road improvements involving a new road crossing this borrowpit site, the route of any new road (including slip roads) should be safeguarded against mineral extraction

Add additional bullet point to the list of implementation issues:

• The release of mineral will be commensurate with the need for mineral for any future improvements to the A14 only

SSP S37 Site Profile M7G - Amend to read: South Junction 14, Girton, Madingley, Site Name: South Junction 14, Girton, Madingley (Area of Search) Summary Description of Proposed Use: Clay – and general fill borrowpit for any future improvements of the A14 upgrade Estimated Reserve: 90,000 m3 Area: 29.8 (ha) Approximate Timescale: Jan 2012 – Nov 2015 Extraction to be linked to any future improvements of the A14 District: South Cambridgeshire Parish: Girton - Madingley Grid Ref: TL 408 614

17 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No SSP S38 Site Profile M7G - Amend 1st bullet point to read: South Junction 14, Girton, Madingley, • Suitable for use as a borrowpit for any future the A14 upgrade improvements only Paragraph 7.52, Implementation Amend 2nd bullet point to read: Issues • No mineral extraction will be permitted on line of A14 upgrade In the event of off road improvements involving a new road crossing this borrowpit site, the route of any new road (including slip roads) should be safeguarded against mineral extraction

Add additional bullet point to the list of implementation issues:

• The release of mineral will be commensurate with the need for mineral for any future improvements to the A14 only

SSP S39 Site Profile M7H - Amend to read: South of Trinity Foot Junction – Site Name: South of Trinity Foot Junction – East (Area of Search) East, Summary Description of Proposed Use: Clay and general fill borrowpit for any future improvements of the A14 Estimated Reserve: 202,500 m3 Area: 6.1 (ha) Approximate Timescale: Jan 2012 – Jan 2015 Extraction to be linked to any future improvements of the A14 District: South Cambridgeshire Parish: Swavesey (adjacent to parishes Boxworth & Conington) Grid Ref: TL 371 645

18 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No SSP S40 Site Profile M7H - Amend 1st bullet point to read: South of Trinity Foot Junction – • Suitable for use as a borrowpit for any future the A14 upgrade improvements only East, Paragraph 7.54, Amend 2nd bullet point to read: Implementation Issues • Route of the A14 In the event of off road improvements involving a new road crossing this borrowpit site, the route of any new road (including slip roads) should be safeguarded against mineral extraction

Add additional bullet point to the list of implementation issues:

• The release of mineral will be commensurate with the need for mineral for any future improvements to the A14 only

SSP S41 Site Profile M7I - Amend to read: South Trinity Foot Junction – West, Site Name: South Trinity Foot Junction – West (Area of Search) Summary Description of Proposed Use: Clay - and general fill borrowpit for any future improvements of the A14 upgrade Estimated Reserve: 175,000 m3 Area: 5.9 (ha) Approximate Timescale: Jan 2012 – Jan 2015 Extraction to be linked to any future improvements of the A14 District: South Cambridgeshire Parish: Lolworth (adjacent to Boxworth & Swavesey) Grid Ref: TL 366 649

19 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No SSP S42 Site Profile M7I - Amend 1st bullet point to read: South Trinity Foot Junction – West, • Suitable for use as borrowpit for any future A14 upgrade improvements only Paragraph 7.56, Implementation Amend 2nd bullet point to read: Issues • Route of the proposed A14 upgrade In the event of off road improvements involving a new road crossing this borrowpit site, the route of any new road (including slip roads) should be safeguarded against mineral extraction

Add additional bullet point to the list of implementation issues:

• The release of mineral will be commensurate with the need for mineral for any future improvements to the A14 only

20 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No SSP S43 Section 7, Map for Amend map to show revised allocation area and consultation area as follows: Site M8B under heading 7.8.2 – Dimmock’s Cote Quarry, Wicken (M9H)

SSP S44 Site Profile W1H, Amend to read: Cross Leys Description of Proposed Use: Waste Management Inert Landfill and Inert Waste Processing Quarry, Wittering, Type: Inert landfill Summary. Estimated Voidspace: 433,333 m3 Area: 29.3 ha Approximate Timescale: From 20110 onwards District: Peterborough Location Details: Quarry is situated on southern side of the A47, to the west of Bedford Purlieus. Grid Ref: TL 048 999

21 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No

SSP S45 Section 8, Map for Amend map boundary of existing permitted site, take account of unavailable land and then Site W1I under amend the consultation area as follows: heading 8.1.9 – Dogsthorpe, Former Brickworks.

(See larger map at the end of schedule)

SSP S46 Site Profile W1I, Amend to read: Dogsthorpe, Summary. Description of Proposed Use: Major Waste Management Development: • Suitable new technologies • household recycling centre • waste transfer • inert waste recycling • In-Vessel Composting Type: New technologies, household recycling centre, waste transfer, inert waste recycling Area: 21.7 18.8(ha)

22 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No Approximate Timescale: Waste management development and possible relocation of exiting Household Recycling Centre 2010 onwards District: Peterborough Location Details: Located on the eastern edge of the urban area of Peterborough off the A47/A1073 roundabout on the primary road network. Grid Ref: TF 205 020

SSP S47 Site Profile W1N Amend to read: Hampton, Peterborough, Description of Proposed Use: Waste Management dDevelopment: Summary. • Materials Recovery Facility • Household Recycling Centre • In Vessel Composting • Specialist • New Waste Management Technologies Type: Wide range of uses including • Mixed Stream Recycling • In Vessel composting • New Waste Management Technologies Area: 3.4 ha Approximate Timescale: 2010 – 2015 District: Peterborough Location details: East of London Road, South of A1139 (Fletton Parkway) Grid Ref: TL 193 959

SSP S48 Site Profile W1AA Amend to read: Storey’s Bar Road, Fengate, Description of Proposed Use: Waste Management development

23 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No Summary. Waste Recycling and Recovery – range of potential uses including: • Materials Recovery Facility • In Vessel composting • Energy from Waste Facilities • New waste Management Technologies Type: Waste Recycling and Recovery – range of potential uses including: Mixed Stream Recycling Facilities, In Vessel composting, Energy from Waste Facilities, New Waste Management Technologies

SSP S49 Site Profile W1AE Amend to read: - Warboys Industrial Estate, Site Name: Warboys Industrial Estate, Warboys (Area of Search) Warboys (W8BE), Description of Proposed Use: Waste Recycling and Recovery. Potential uses include: Summary • Materials Recovery Facility • In Vessel Composting • Inert Waste Recycling • New waste management technologies Area: 14.1 ha Approximate Timescale: Dependant of demand and market forces District: Huntingdonshire Parish: Wistow and Warboys Grid Ref: TL 297 785

SSP S50 Section 8, Map for Area of Search to be added over the remaining area covered by M1A as follows: Site W2B under Heading 8.2.2 – Cottenham (W8K)

24 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Reference Plan Reference Change No

(See larger map at the end of schedule) SSP S51 Site Profile W4B - Amend to read: Thornhaugh I, Thornhaugh Description of Proposed Use: Waste Management Stable Non Reactive Hazardous Waste (W8J), Site Profile Landfill with complementary non-hazardous waste disposal Type: Stable non reactive hazardous waste disposal Estimated Voidspace: 1,125,000 m3 Area: 7.7 ha Approximate Timescale: From 2015 onwards District: Peterborough Location Details: Quarry is situated on southern side of the A47, adjacent to Bedford Purlieus to the west. Site is approximately 1 km to the west of Wansford village and 1 km to the south west of Thornhaugh village. Home Farm dwellings lie to the north of the A47 and the quarry Grid Ref: TL 048 999

25 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Amended M1A Map (re change SSP S7):

26 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Amended M1F Map (re change SSP S8):

27 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Amended W1I Map (re change SSP S45):

28 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Amended W2B Map (re change SSP S50):

29 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Change ref SSP6

Appendix A

Section 6 Implementation & Monitoring Table for Mineral and Waste allocations and policies

30 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

What will be monitored? How and When Related Policies Related Objectives Implementation Partners 1) Development on identified, Monitor the Register of Planning SSP M1, SSP M2, SSP Obj M1, Obj M2, Obj M3, Obj allocated or safeguarded sites, Permissions (monthly). M4, SSP M5, SSP M7, M5, Areas of Search, Transport SSP M8, SSP M9. Zones, associated Consultation Annual Survey of Mineral and Safeguarding Areas and WWTW Waste Operators. SSP W1, SSP W2, Obj W1, Obj W2, Obj W3, Obj Safeguarding Areas shown in the W5, Obj W14, Obj W17, Obj Site Specific Proposals and Core Site monitoring (minimally SSP W3, SSP W4, W19 Strategy DPDs annual). SSP W6, SSP W7, Obj BF/LF1, Obj BF/LF2, Obj Other sources - Environment BF/LF3, Obj BF/LF7, Agency, Natural , RSPB, SSP W8 Land Registry, District Planning

Authorities SSP T1, SSP T2

CS1-CS12, CS14-CS17, CS19, CS20, CS21, CS23, CS30, CS31

2) Minerals and Waste Monitor the Register of Planning SSP M3, SSP M6. Obj M1, Obj M2, Obj M3, development outside of identified, Permissions (monthly). allocated or safeguarded sites, SSP W5, Obj W1, Obj W2, Obj W3, Obj Areas of Search, Transport Annual Survey of Mineral and W4, Obj W5, Obj W14, Obj W17 Zones , associated Consultation Waste Operators. CS1-CS4, CS6 –CS13,CS18, Areas and WWTW Safeguarding CS21, CS23 Obj BF/LF1, Obj BF/LF2, Obj Areas shown in the Site Specific Site monitoring (minimally BF/LF3 Proposals and Core Strategy annual). DPDs Other sources - Environment

31 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Agency, Natural England, RSPB, Land Registry, District Planning Authorities

3) Progress on implementation Monitor the Register of Planning As for 1) and 2) above, and Obj M1, Obj M2, Obj M7, Obj including restoration of identified Permissions (monthly). M9, Obj M11-M12, Obj M14-18 schemes as appropriate. the CS22, CS25, CS27, CS28 minerals and waste Annual Survey of Mineral and Obj W1, Obj W2, Obj developments identified by 1) & Waste Operators. W3, Obj W5, Obj W10, Obj W11, 2) above. Obj W14, Obj W18 Site monitoring (minimally annual). Obj BF/LF1 - Obj BF/LF12

Other sources - Environment Agency, Natural England, RSPB, Land Registry, District Planning Authorities

4) Site Availability. Monitor the Register of Planning SSP M1, SSP M2, SSP M4, Obj M1, Obj M2 Permissions (monthly). SSP M5, SSP M7, SSP M8 All site allocations will be Obj W1, Obj W2, Obj W3, Obj monitored annually, to report Annual Survey of Mineral and SSP W1, SSP W2, SSP W3, W5, Obj W14 the development status of each Waste Operators. SSP W4, SSP W6, SSP W7, site. This will also include SSP W8 Obj BF/LF1, Obj BF/LF2, Obj monitoring the loss of allocated Site monitoring (minimally BF/LF3 land to other forms of annual). SSP T1, SSP T2 development and changes to land ownership (where known) Six monthly review of Master CS1-CS12, CS14-CS17, CS19, which prevent development for Planning activity in designated CS20, CS21 the allocated use(s). Areas of Search.

Other sources - Environment Agency, Natural England, RSPB,

32 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Land Registry, District Planning Authorities

5) Key Assumptions Monitor the Register of Planning CS1, CS2, CS3, CS7, Obj M5, Obj M6, Obj M8 Permissions (monthly). CS14, CS15, CS22, The Waste Strategy is based on CS27, CS28, CS29 Obj W1, Obj W2, Obj key assumptions which are project Annual Survey of Mineral and W3, Obj W5, Obj W8 and site specific. It is vital that the Waste SSP W1, SSP W2 following key site specific waste Operators. projects are monitored to ensure Obj BF/LF2, Obj BF/LF3 strategy delivery: Site monitoring (minimally annual). • Implementation of strategic energy from waste facility Other sources - Environment by Peterborough Agency, Natural England, RSPB, Renewable Energy Ltd at Land Registry Eastern General Employment Area, Peterborough by 2013.

Capacity 650,000tpa.

• Implementation of in-vessel composting facility by Donarbons at Waterbeach, near Cambridge by 2011

Capacity 90,000tpa

• Implementation of materials recycling facility extension for Peterborough’s municipal solid waste by

33 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

Peterborough City Council at Eastern General Employment Area, Peterborough by 2011

Capacity 25,000tpa

• Implementation of materials recycling facility extension for commercial and industrial waste by Plasgran Ltd at Wimblington, Cambridgeshire by 2011.

Capacity 15,000tpa.

• Three long term construction and demolition waste recycling facilities at Block Fen / Langwood Fen with a combined capacity of 280,000tpa by 2026.

• Implementation of inert landfill disposal at Block Fen/ Langwood Fen. 8,400,000 m3 to 2026. (Site allocated in Core Strategy)

34 CABINET 12 DECEMBER 2011 ITEM 6 APPENDIX 2 Cambridgeshire & Peterborough Minerals and Waste Site Specific Proposals DPD Examination Schedule of Councils’ Proposed Changes APPENDIX A – Changes that go to soundness

6) Any Future A14 Improvement Reported annually SSP M2, SSP M7 Obj M1, Obj M2, Obj 8, Obj 9, Projects Obj M12, Obj M13, M14, Obj Other sources - Department M15, Obj M16, Obj M18 The Minerals Strategy includes a of Transport, Highways number of borrowpit Areas of Agency, Local Highways Search for any future A14 Authorities improvement projects. It is vital that any programme of works relating to the improvement of the A14 is regularly monitored (at least annually) and reported.

35