<<

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT,

CHAPTER TERMS OF REFERENCE (TOR) OF 2 THE EIA STUDY

2.0 INTRODUCTION

The Terms of Reference (TOR) for the preparation of the Environmental Impact Assessment (EIA) Study for the “Proposed Pan-Island Link 1 Highway Project, Penang” was prepared and submitted to the Department of Environment (DOE) Penang on 11 March 2016. It was endorsed by the DOE Putrajaya via a letter Ref. AS(PN)50/013/500/047 Jld. 2 ( ) dated 22 November 2016 as shown in Appendix 2. The validity period for the TOR was for one (1) year starting 22 November 2016.

Subsequently, a letter requesting for an extension to the TOR validity period was submitted to DOE Putrajaya on 16 November 2017. An extension of 3 months was sought because extra time was needed to finalize the alignment for the PIL1 Highway at the Bukit Bendera section in Penang Hills (to avoid sensitive areas) and also to obtain JPS approval of the PIL1 Highway alignment along Sg. Ara and Sg. Kluang leading to the LCE Interchange in (Appendix 2).

The contents of the TOR and the DOE TOR Approval Conditions are summarized below.

TERMS OF REFERENCE (TOR)

2.1 PROJECT TITLE

This Terms of Reference is for the preparation of the Environmental Impact Assessment (EIA) Study for the “Proposed Pan-Island Link 1 Highway Project, Penang”. Henceforth, it shall be referred to as the PIL1 Project.

2.2 EIA CONSULTANT AND EIA STUDY TEAM MEMBERS

The consultant undertaking the EIA study is Wiranda (M) Sdn Bhd.

The contact details are as follows:

WIRANDA (M) SDN BHD

No. 3374, Jalan 18/31,

2 - 1

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

Taman Sri Serdang, 43300 Seri Kembangan, Selangor Darul Ehsan. Tel: 03-8942 3413 Fax: 03-8948 5912 Contact Person: Mr. Shamsol Azhar bin Ismail (General Manager)

The members in the EIA Study team are as shown in Table 1.2.1 (in Chapter 1).

2.3 SCOPE OF PROJECT

The proposed PIL1 Highway Project comprise a new highway that will be built to link the Gurney Drive area in the northern part of and through the Penang Hills to Bayan Lepas in the south. This new highway will provide an alternative north-south road link in addition to the existing Tun Dr. (LCE) Expressway.

The PIL1 Highway consists of several components as follows:

i. Elevated road sections (viaducts), ii. Tunnel sections, and iii. An embankment road section.

The total length of the highway is 19.5 km. It shall start at the Gurney Drive area within the reclaimed area of Phase 2 in the northern part of Penang Island and end in Bayan Lepas at the Tun Dr. Lim Chong Eu Expressway in the south.

The viaduct sections of the proposed PIL1 Highway shall traverse heavily built-up urban areas in the northern and mid-southern segments and also along river reserves in the southern part. The tunnel sections will cut through the Penang Hills in the middle part of the proposed new Highway.

Therefore the proposed activity falls under “Prescribed Activity 20(c) First Schedule: “Construction of road, tunnel or bridge traversing or adjacent or near to environmentally sensitive areas” and “Prescribed Activity 13(b) Second Schedule: “Construction of road, tunnel or bridge traversing an area with slope greater than or equal to 350” of Subparagraph 3(1) and (4) of the Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order, 2015. Hence the proposed PIL1 Project falls under the Second Schedule of the Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order, 2015.

2 - 2

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

2.4 PROJECT ALTERNATIVES AND ENVIRONMENTAL IMPACTS

The principal objective of the proposed PIL1 Highway project is to provide an alternative north-south highway link in addition to the existing Tun Dr. Lim Chong Eu (LCE) Expressway. This is because the LCE, being the sole pragmatic/sensible route for north-south bound traffic (Georgetown - Bayan Lepas and Penang International Airport), is heavily congested with traffic daily, especially during peak hours. The proposed new highway is anticipated to effectively reduce travelling time as well as related transportation costs between these two areas since it will by-pass the LCE and other frequently congested local roads in the city area. PIL1 will be a non-tolled Highway.

The whole highway corridor (19.2 km) traverses across flat and slightly undulating terrain as well as hilly mountainous areas. In order to minimize adverse environmental and social impacts, the elevated highway or viaduct design will be adopted over much of the highway length (9.7 km or 50.52%) which cuts across flat and slightly undulating terrain. These areas are also densely populated areas. Only 1.7 km (8.85%) of embankment roads will be constructed close to the hilly areas. The hilly mountainous areas will be traversed by tunnels (7.8 km or 40.63%).

The existing land use in the proposed new highway corridor contains heavily built-up and populated urban areas with many amenities (such as schools, temples, shrines, residential and business premises, eateries, high rise buildings, utility services, etc.). The proposed alignment also passes near or cuts through hilly areas (parkland, Penang Funicular Rail at Bukit Bendera, Kok Lek Si Temple, Dam, small shrines, low rise and high rise buildings, etc.) and along sensitive river reserves (holding squatter houses, fishermen boat mooring areas and tour boat operator stores). The local roads in the vicinity of the proposed new highway corridor invariably have high daily traffic flows.

Therefore, the anticipated environmental impacts shall be related to social issues (e.g. land/property acquisition, relocation/resettlement, places of worship, squatter houses, plight of fishermen and tour boat operators, environmental annoyance – noise, vibration, dust, traffic congestion, public safety) and environmentally related issues – noise, vibration, air pollution, water pollution, traffic congestion, safety, and flash floods.

Consequently, the project’s alternatives shall be examined to select the best option/alternative to reduce/minimize any adverse social and environmental impacts. The alternatives examined shall be in terms of the following:

a. Proposed highway alignment option. b. Viaduct vs At-Grade road option. c. Tunnelling methods.

2 - 3

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

d. No Project Option.

a. Highway Alignment Option

The overall lay-out of the PIL1 Highway is shown in Figure 2.4.1. Sections of the highway corridor are shown in Table 2.4.1. The sections show, more clearly, the types of land use along the corridor, including potential encumbrances.

Tun Dr Awang IC

Tun Dr LCE IC

Figure 2.4.1. PIL 1 Highway - Overall Layout

2 - 4

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

Table 2.4.1. PIL1 Corridor Sections

1 Gurney Expressway to Youth Park – Viaduct V1 (Elevated Road0 Along Existing Road Corridor

The PIL1 highway starts from the Gurney Expressway round-about and runs along Jalan Bagan Jermal and Jalan Gottlieb towards Youth Park. It then continues in a south westerly direction into Youth Park to reach the Utama Interchange. This section is 2.3 km long. It comprise a viaduct (dual 3 carriageway) which runs on the existing road (Jalan Bagan Jermal and Jalan Gottlieb). One Interchange (Utama Interchange) is provided in this section. (Note. The Gurney Interchange will be developed and constructed by another party)

2 - 5

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

2 Youth Park to Air Itam (Kek Lok Si) – Tunnel 1 – 4.4 km. Twin tunnel each with 3 lanes.

From Youth Park, the alignment tunnels through , traversing in the south westerly direction and exits at Air Itam. The tunnel section comprise a twin tunnel each with 3 lanes and fitted with cross passage.

2 - 6

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

3 From Kek Lok Si – Short Viaduct V2 0.3 km

This section consists of a short viaduct (dual 3 carriageway) beginning from the tunnel exit near Air Itam to travel in a southerly direction towards . Tunnelling starts again just after the viaduct. Laterally, the first tunnel alignment is approx. 600 m away from the Air Itam Dam and approx. 350 m from the Temple grounds.

2 - 7

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

4 Tunnel 2 – 1.6 km. From Air Itam to Paya Terubong. Twin tunnel each with 3 lanes.

Tunel 2 starts after the viaduct near the Kek Lok Si Temple. The tunnel exits near the Emerald Heights Condominium at Paya Terubong. From this point, the highways consists of a viaduct section until it reaches the Paya Terubong Interchange and continues towards Taman Suria in Paya Terubong. The cemetery will not be affected.

2 - 8

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

5 Paya Terubong to – Viaduct Section V3 -0.8 km

The viaduct starts after the tunnel exit near Emerald Heights . The Paya Terubong Interchange is located in this section. It will link PIL1 to Jalan Paya Terubong. Jalan Paya Terubong will be upgraded to a four (4) lane dual carriageway until Lebuhraya Thean Teik.

2 - 9

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

6 Tunnel 3 : Paya Terubong to Relau – Tunnel 3.4 km. Twin tunnel each with 3 lanes.

The tunnel alignment extends in a southwards direction from Taman Suria Vista in Paya Terubong towards Jalan Tun Sardon and exits near the Relau Interchange. The alignment then takes the form of an embankment road (1.8 km) and a viaduct (0.8 km) and continues towards the south to connect with another tunnel section near Sg. Ara.

2 - 10

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

7 Tunnel 4 Relau – 0.7 km. Exits at Sg. Ara. to Tun Dr. Lim Chong Eu Expressway – Viaduct (V4) 4.2 km along river Sg. Ara & Sg. Kluang.

The Fourth Tunnel exits through the south portal at Sungai Ara and then swings to the south- east direction, passing through the Desa Ara residential area. The alignment continues in a south east direction and runs on the green strip along the river reserve (Sg. Ara and Sg. Kluang) until it reaches the LCE Expressway. The Awang Interchange is located in this section.

2 - 11

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

8 TunDr. Lim Chong Eu Interchange

The alignment (viaduct) runs along the river reserve of Sg. Kluang until it meets the Tun LCE Interchange.

Examination of the information in Figure 2.4.1 and Table 2.4.1 coupled with the primary land use survey information carried out in the study area indicates potential encumbrances along the proposed alignment with respect to land/property acquisition, public safety, environmental nuisance, removal and resettlement of squatters and relocation of fishermen boat mooring sites and tour boat operator storage sheds. The potential encumbrances in the Penang Hill section relate to earth disturbance, potential soil erosion and earth movements, and the subsequent impacts on water quality, noise and vibration, air pollution, traffic congestion and safety issues to residents living near the project corridor.

Therefore, alternative alignments shall be examined that would avert or minimize the potential adverse impacts.

2 - 12

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

b. Viaduct vs at-Grade Road

This option shall examine the pros and cons of adopting the highway design using the At- Grade road or the elevated road (viaduct) approach against the potential impacts. The comparison shall take into account the land use and physical characteristics of the roads in the study area, junctions (signalised or un-signalized), turn-ins and turn-outs and the adjacent developments along the roadsides. The factors that will be considered shall include road speed and the LOS at specific locations (if available). Other factors that shall be considered will include:

 the availability of land  constructability  land acquisition  construction costs  social impacts c. Tunneling Method

Various tunnelling methods will be explored for tunnel construction.

Selection of tunnelling method depends on multiple factors, for example, the type of rock, the bore size, accessibility condition and geological condition. These multiples factors will influence economic of each tunnelling method and speed of the tunnelling works.

It is important that the correct tunnelling method is selected so that it can be constructed in the most efficient and safe manner.

For the PIL1 Project, the prospective tunnelling method that will be considered includes:

 Drill & Blast method - Full face method - Heading and bench method - Drift method - Pilot tunnel method

 Hard TBM method  Cut-Cover method  Immersed tube method

2 - 13

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

The pros and cons of some of the tunneling methods mentioned above shall be considered taking into consideration the geological and soil conditions in the study area. The selection shall be based on technical and costs considerations. d. No Project Option

The No Project option will cause major road transport issues on Penang Island in the long run as summarized in the Penang Transport Master Plan (PTMP). Rapid urban development coupled with strong economic growth will place greater demands on the road transportation system in the future. Efficient road systems provide economic and social opportunities and benefits that results in positive multiplier effects such as better accessibility to markets, employment and additional investments. When road systems are deficient in terms of capacity or reliability, they can have an economic costs such as reduced or missed opportunities and lower quality of life.

2.5 SIGNIFICANT ENVIRONMENTAL IMPACTS TO BE STUDIED

For the purpose of describing the environmental impacts that can be associated with the PIL1 Project development, the whole alignment shall be divided into three (3) sections as shown in Figure 2.5.1. The division is based on topographical and land use features in the proposed Project alignment. The 3 sections are as follows:

Section A covers the length from the Gurney roundabout to the north portal of the first tunnel. This stretch comprise flat to slightly rolling terrain and consists of densely developed and populated areas.

Section B covers the length from the first tunnel to the south portal of Tunnel 4 at Sg. Ara. This stretch consists of undulating to hilly areas and is less densely developed with sizeable tracts of forest and scrubland areas. The proposed alignment passes through Penang Hill and skirts around the heavily populated and developed areas in Paya Terubong, Air Hitam and Relau.

Section C covers the length from the south portal of Tunnel 4 to the LCE Expressway. This stretch consists of slightly rolling to flat terrain and is densely developed and populated. A specific description of the potential impacts according to the major project components and project construction activities is presented in Table 2.5.1.

2 - 14

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

Figure 2.5.1. Sections A, B and C of the proposed PIL1 Alignment (for the purpose of reporting environmental impacts and mitigation measures)

2 - 15

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

Table 2.5.1. General Assessment of Potential Impacts Imposed by the Project Activities

Activity Significance Remarks

Topographical and Significant and beneficial Generates useful information for safe Soil/Geotechnical Surveys design of Project facilities.

Engineering Designs Significant and beneficial Will ensure the structural stability of PIL1 components

Environmental Impact Significant and beneficial Generate useful data and Assessment Study information to guide the route of the PIL1 Project, and to define adequate mitigation and abatement measures to be inculcated in the Project designs and operations.

Employment Opportunities Nominal scale Beneficial impacts enhanced if State and local companies and local residents are engaged to carry out surveys/studies.

Property / Land Acquisition Local, short to long term To prevent any delays to the work moderate adverse impacts program, negotiations must be started with the affected parties in the early stage of the Project planning with the involvement of appropriate mediators and arbitrators. Any litigations must be settled as soon as possible.

Site Preparation Local and short to intermediate Moderate to significant amount of term; moderate to significant earthworks need to be carried for adverse impacts pier construction along the existing roads, hill embankments and river reserves. Also at sites of construction of Interchanges. Significant waste soil and rock removal during tunnel construction. Traffic disturbances along Jln. Bagan Jermal, Jln. Gottlieb and other public roads indicated. Dust and noise impacts indicated. Well-founded mitigation measures shall be adopted.

2 - 16

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

Activity Significance Remarks

Pier construction. Any adverse impacts can be Ambient air and water quality, noise Installation of Machinery controlled to reasonable levels. and vibration status in areas and Construction Works. surrounding the Project corridor Need to control run-off could be compromised at times. discharges from the work sites; Hoardings along the work sites may establish ESCP/LD-P2M2 adequately limit dispersion of noise Construction of support control measures and monitor and dust to surrounding residential services (Batching plant, performances; reduce noise areas. Comprehensive monitoring of Crusher plant, casting yard, emissions; control dust noise generation and transmission storage yard/areas, CLQ) dispersions. recommended. Potential impacts on receptors in the surrounding areas need to be monitored. Mitigation measures to be adopted.

Transport of Construction Transient impacts; adverse No significant impacts expected on Materials, Equipment and impacts can be controlled to water quality, air quality, and public Viaduct components. minimal levels; some positive health. Transport of construction Viaduct installation. business impacts. Local short materials, project components and term impacts. other equipment by trucks are not expected to cause significant traffic circulation impacts if carefully planned, monitored and controlled. Need to avoid overloading of paved roads and road structures and peak traffic hours. Mitigation measures can control potential adverse effects.

Tunneling Construction Any adverse impacts can be Ambient air and water quality, noise operations – Drill & Blast controlled to reasonable levels. and vibration status in areas Method. Construction of Need to control run-off and surrounding the Project site could be other discharges from the work Interchanges. compromised. Hoardings along the sites; establish ESCP and work sites may adequately limit monitor performances; reduce noise emissions; control dust dispersion of noise and dust to dispersions. Monitor vibration surrounding residential areas. levels and fly rock occurrence. Comprehensive monitoring of noise generation and vibration transmission recommended. Potential impacts on receptors in the surrounding areas need to be monitored. Fly rock incidents to be monitored and controlled. Blasting control and safety issues highlighted.

2 - 17

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

Activity Significance Remarks

Mitigation measures to be implemented as listed in report.

Disposal of Construction Could generate adverse Appropriate mitigation measures can Debris and Wastes impacts if inadequately planned be implemented to safeguard air and and if prior approval not water quality; public health, safety obtained from Local and welfare, and ecological Authorities. Local and short and resources. List of mitigation long term impacts. measures to control adverse impacts to be presented in report.

Temporary Construction Minimal to insignificant local Implement control measures to avoid Workers Camp (CLQ) and short term adverse conflicts between foreign labor and impacts. local residents. Some opportunities generated for local business (rental of accommodation and food supplies). Adequate mitigation measures can be implemented to reduce adverse environmental impacts to tolerable levels.

Operation of concrete Could generate adverse Hoardings along the work sites may batching plant, crusher impacts if inadequately adequately limit dispersion of noise plants, casting yard, planned. and dust to surrounding residential maintenance yard, storage areas. Comprehensive monitoring yard, and waste disposal recommended. sites Ambient air quality and noise Appropriate mitigation measures can status in surrounding areas be implemented to safeguard air and could be compromised at water quality; public health, safety times. and welfare. List of mitigation measures to be presented in report.

Employment Generation and Significant O&M expenditures Business Development benefiting local and regional service Opportunities. Positive companies. Also opportunities for beneficial impacts. Local local residents to be gainfully short/long term impacts. employed.

2 - 18

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

Activity Significance Remarks

Commissioning and Project Non consequential. Project Proponent and appointed Start-Up Project Engineers and Contractor capable of monitoring and trouble shooting abnormal operations.

Employment Generation Positive beneficial impacts. Substantial business and and Business Development Local short/long term impacts. employment opportunities may be Opportunities generated if State wide participation is given first choice.

Gaseous Emissions Impacts are localized and Potential emission loads high if traffic (Operations Stage) intermittent short term stalls on the highway or tunnel duration. ventilation is inoperative. However, resulting impacts on neighboring residential areas will be minimal. Traffic flow and ventilation control equipment to be well monitored and maintained.

Noise and vibration Tolerable noise and vibration Comprehensive assessment and level impact especially if proper monitoring recommended to acoustic and other mitigation determine effectiveness of control measures are applied. Impact measures and the extent of residual localized and of long term increases in ambient noise and duration. vibration levels with traffic flow increases during operations stage. Noise levels at nearest residential unit expected to be insignificant if recommended mitigation measures applied.

Occupational Health and Safety and health issues related Reference to Malaysian regulations. Safety to workers operating and maintaining the PIL1 Highway. Localized and potential long term impacts.

2 - 19

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

Activity Significance Remarks

Night time construction Can be beneficial for reducing Main advantage primarily reduced traffic disruptions; also has traffic volume at night, less many concerns. E.g safety, inconvenience for traveling public quality and lighting. and lower temperatures. Needs well- organized public relations campaign.

Safety control measures important.

Operational Failures and Equipment shutdown due to Depending on the duration of Abnormal Conditions electrical and mechanical abnormal conditions and operational failures; disruption in electrical failures; significant impacts on traffic supplies; theft and vandalism of flow. Adverse air quality impacts equipment; flooding of tunnel could also occur in the local area. neighborhood.

Aesthetics Change in landscape features, At certain sections, the PIL1 Highway from natural forest is located within residential areas. environment to concrete Vegetative landscaping features can structures may have some help mitigate adverse visual impacts. adverse impacts on local residents in the Penang Hill area. However, negative impacts localized i.e. for residential units facing the PIL1 Highway.

Employment Opportunities Moderate beneficial impacts on Significant O&M expenditures and Spin-Off Business local and regional scale on long benefiting both, local and regional term basis. service companies. Also opportunities for local residents to be gainfully employed.

2.5.1 Significant Impacts to be Studied

The significant potential impacts are anticipated to occur primarily during the Construction Phase. Some residual impacts may arise during the Operations Phase. The impacts mirror the project activities shown in Table 2.5.2.

2 - 20

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

The steps most likely to generate significant impacts during the Project development are as follows:

Table 2.5.2. Project Activity and Significant Impacts

Nos. Project Activity Significant Issues - Impacts To be Studied (Some relevant factors)

Final alignment - survey Land/property acquisition; relocation; resettlement; compensation; tribunals. National Land Code (Penang and Malacca Titles) (Amendment) Act, 1965 (Act 55 of 1965). Site preparation Traffic control; erosion & sedimentation control (ESCP; LD-P2M2); safety; dust; noise; wastes; transport; water quality. Pier construction Traffic control; erosion & sedimentation control Viaduct construction (ESCP; LD-P2M2); safety; dust; noise; vibration; Interchange construction wastes; transport; water quality; flash floods Tunnel portal construction Noise; vibration; erosion & sedimentation control (ESCP; LD-P2M2); traffic; safety; water quality; landslips. Main tunneling works Noise; vibration; erosion & sedimentation control (ESCP; LD-P2M2); traffic; safety; water quality; landslips. Embankment road construction Traffic control; erosion & sedimentation control (ESCP; LD-P2M2); safety; dust; noise; wastes; transport; water quality. Support services - construction Traffic control; erosion & sedimentation control and operation. (ESCP; LD-P2M2); safety; dust; noise; wastes; transport; water quality. Operations stage Noise; employment; abnormal incidents mgmt.

2.6 STUDY BOUNDARIES

The study area falls in the Timur Laut and Barat Daya Districts which are under Majlis Bandaraya Pulau Pinang. The EIA Study shall focus on the Zones of Impact that will be identified in the study area. The width of the PIL1 Project corridor (ROW) along its’ whole alignment is estimated to be about 30m.

2.6.1 Zone of Impact and Sensitive Receptors

The primary zone of impact along the linear corridor of the PIL 1 Highway is demarcated as an area extending outwards 250 m on the left side and 250 m on the right side of the ROW

2 - 21

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

boundary of the PIL 1 Highway corridor through any given area in Penang Island. For secondary impacts, the zone of impact extends to 2000m on both sides from the ROW boundary of the PIL 1 Highway corridor.

The sensitive receptors are identified as all persons living or working or passing through or performing an act in the Zone of Impact.

For the PIL 1 Project support sites (temporary batching plant, casting yards, crusher plants, storage yards, CLQ, and waste disposal areas), the sensitive receptors include all persons living or working or passing through or performing an act within an area 2000m circumference from the boundary of the PIL1 Project support site.

2.6.2 Assessment of Impact

The potential significant impacts that shall be studied are as follows:

Impact Element Study Methodology

Socio-economic impact Social survey; public meeting; Focused Group Discussion (FGD) Noise Noise level monitoring; Modelling Studies Vibration Vibration level monitoring Air quality (Dust) Air quality monitoring; Modelling Studies Erosion & Sedimentation Estimation of soil erosion rates using RUSLE Monitor ESCP/LD-P2M2 control system performance Water quality Water quality monitoring Hydrology & Floods Impacts to river conveyance; Modelling Studies Wastes Waste Inventory and Records – EQ (Scheduled Wastes) Reg. 2005 Traffic / Transport Road performance – e.g. LOS; Modelling Studies Safety Public complaints; Accident records

2.7 ASSESSMENT STANDARDS

The criteria for evaluating environmental quality or satisfactory performance of a control procedure / system shall be by comparison with an established norm and/or Standard as shown in Table 2.7.1.

2 - 22

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

Table 2.7.1. Criteria for Assessing Environmental Quality

Determinant Norm/Standard Air quality Malaysian Ambient Air Quality Standards 2013 (MAAQS 2013) Noise level Planning Guidelines for Environmental Noise Limits and Control Second Edition (2007) - Department of Environment, . Vibration Vibration dose value (VDV) as recommended by British Standard BS 6472:1992 used for assessment of annoyance. Vibration threshold level for human perception – method in BS 6472: 1992. Water quality National Water Quality Standard (NWQS) Scheduled Wastes EQ (Scheduled Wastes) Reg. 2005 Soil erosion Erosion and Sediment Control Plan (ESCP) LD-P2M2 measures

2.8 TIMELINE OF STUDIES

The timeline of studies for the different components of the EIA Study is as shown in Table 2.8.1.

Table 2.8.1. EIA Study Timeline

EIA Study Executor Location Period/Date Method Component (Submit To)

Water quality A&A Laboratory As in Figure 8 March - 10 March Standard 6.16.1 (a) to 2016 and 17 March Methods (APHA) 6.16.1 (b) in 2016 Section 6 Noise level A&A Laboratory As in Figure 8 March - 20 March Standard 6.1.15 (a) to 2016 (Station N1 to Methods (APHA) 6.1.15 (e) in N48) Section 6 Vibration level Spectrum As in Figure 8 March - 30 March Standard Laboratories Sdn 6.1.15 (a) to 2016 (Station V1 to Methods (APHA) Bhd 6.1.15 (e) in V48) Section 6 Air quality A&A Laboratory As in Figure 21 to 30 April 2016 Standard 6.1.15 (a) to (for Station A1 to Methods (APHA) 6.1.15 (e) in A9) Section 6 23 to 26 May 2016 (for Station A10 to A12) Social Surveys / As in Figure 6.4.4 20 February 2016 to Field surveys FGDs W(M)SB and Figure 6.4.5 7 April 2016 In-situ public meetings & FGDs

2 - 23

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

PAT (DOE Penang) W(M)SB-SRS (DOE Penang) 26 February 2016 DOE Guideline TOR (DOE Penang) W(M)SB-SRS (DOE Penang) 15 November 2016 DOE Guideline Draft EIA Report W(M)SB-SRS (Penang State Dec 2017 DOE Guideline Government) Final EIA Report W(M)SB-SRS (DOE Penang) Jan 2018 DOE Guideline

2.9 CONSIDERATION OF CONCURRENT PROJECTS

Bayan Lepas Light Rail Transit (LRT) Project EIA Second Schedule. July 2017.

2.10 DESCRIPTION OF MODELLING TOOLS/ASSESSMENT METHODOLOGIES

The modelling tools and assessment methodologies that will be adopted for this EIA Study are shown in Table 2.10.

Table 2.10.1. Modelling Tools and Assessment Methodologies Adopted for this EIA Study

Topic Modelling Tool

Noise RLS-90 Guideline on Road Noise Protection; Noise Propagation - SoundPLAN software.

Air quality CALROAD ViewTM (Version 6.2.6) developed by Lakes Environmental Software. CALINE4 Air Quality Model. (Colorado Department of Public Health and Environment (2005). SCREEN3 Stationary Source Modeling Guidance.)

Traffic Capture Rate Analysis Highway Capacity Software Soil Erosion RUSLE Erosion and Sediment Control Plan (ESCP) LD-P2M2 (DOE, Govt. of Malaysia) Hydrology Calibrated HEC-HMS model - used to analyze the hydrologic and hydraulic behavior of current catchment characteristics and to simulate the impact of future development to potential flooding problems. EXTRAN hydraulic flow routing model in XP- SWMM. Socio-economic Survey Random sampling method SPSS

2 - 24

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

2.11 POSSIBLE MITIGATION MEASURES

Some possible mitigation measures or Best Management Practices (BMPs) sourced from other similar projects could be applied for this PIL1 Project. Several examples are presented in Table 2.11.1.

Table 2.11.1. Possible Mitigation Measures that are Applicable for the PIL1 Project

Potential Impact Possible Mitigation Measures / BMPs Topic Socio-economy  Publicise the Public Consultations Bureau (PCB) to register and coordinate all actions on all socio-economic issues and public complaints.  Special briefing sessions to affected people. Air pollution (dust)  Water spray (mist);  Regularly wash down the work areas.  Wash trough at exit point from all work sites.  Monitor dust levels at specific work sites. Noise pollution  Erect temporary noise barriers cum hoardings.  Monitor noise levels at work sites. Vibration  Use low vibration bore piling or Hand dug cassion or Injection type piling - depending on geological, soil and topographical conditions on site.  Monitor vibration levels at work sites (where deemed necessary). Water pollution  Sediment basin/traps and other practicable BMPs should be installed concurrently with the site preparation activities.  Check that all ESCP and LD-P2M2 control instruments are in place and working properly.  Clear all roadside drains and other waterways of debris to allow free flow of run-off.  Buffers (10 – 20m) shall be established alongside existing waterways around the work site.

Soil Erosion  All wastes and construction materials (e.g. sand, aggregates, etc.) stored on site must be properly protected from weather elements and removed from the work site to the waste disposal area as soon as possible.  After earthworks are completed, any exposed area should be close turfed or stabilized as soon as possible.  Earthwork activities shall be avoided during the rainy season (Nov. – Feb.) and during heavy rainfall events. Plan the construction works accordingly.  Sediment basin/traps and other practicable BMPs should be installed during site preparation.  All run-off must be captured into a silt trap before discharge to nearby water courses (ESCP; LD-P2M2) Traffic  Prepare and implement Site Specific Traffic Management Plan at the different work sites. Use trained personnel to operate the TMP.  Traffic diversion plans to be vetted and approved by the Local Authority.

2 - 25

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

Potential Impact Possible Mitigation Measures / BMPs Topic  Transport of materials and wastes to be controlled to avoid peak hour traffic and to use approved routes only to/from the designated locations.  Road diversions and lane reductions shall be clearly marked and traffic to

be controlled using flagmen at the affected locations during peak hours.

Health  Carry out fogging of the work sites weekly (dengue control) EHS  Employ competent EO in the work site. Management  Employ qualified Safety & Health supervisor in the work site.

2.12 DOE TOR ENDORSEMENT CONDITIONS

The following items/issues are highlighted in the TOR Endorsement Letter:

No. Item Condition 2 i) Kajian EIA bagi cadangan projek Kajian tersebut hendaklah merangkumi huraian projek lebuhraya Express bermula dari lengkap, jelas dan terperinci, konsep projek, kajian Gurney Drive dan berakhir di impak dan cadangan langkah-langkah kawalan yang persimpangan Lebuhraya LCE berkesan. dengan panjang jajaran 19.5 KM.

ii) Kajian EIA hendaklah dijalankan Langkah-langkah kawalan pencemaran yang secara kuantitatif, komprehensif dicadangkan perlu dijelaskan dengan spesifik dan terperinci bagi isu-isu kritikal yang dikenalpasti seperti berikut:

a. Hakisan Tanah dan Langkah Mitigasi (LDP2M2) b. Banjir, Sumber Air dan Pemendapan c. Permodelan Kualiti Air d. Permodelan Impak Bunyi e. Penilaian Impak Gegaran f. Status sosio-ekonomi, dan g. Penilaian aliran trafik

iii) Pelan Struktur Negeri atau Pelan Cadangan pembangunan perlu selaras dengan Pelan Rancangan Tempatan (Local Plan) Struktur Negeri atau Pelan Rancangan Tempatan (Local Plan) bagi kawasan berkenaan yang hendaklah dirujuk dan dinyatakan di dalam Laporan EIA.

i) Lokasi setiap stesen persampelan garis dasar hendaklah ditunjukkan dengan jelas. ii) Guna tanah semasa di sekitar tapak cadangan hendaklah dihuraikan dengan jelas dan menyertakan:-

2 - 26

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

No. Item Condition a. Pelan guna tanah terkini yang jelas, terperinci dan lengkap bersaiz A3 atau lebih besar dalam lingkungan 5 km dengan ditunjukkan radius bagi setiap 250m, 500m dan seteruskan kedudukan penempatan penduduk, kedudukan sungai, kawasan pertanian berhampiran dan penerima sensitif alam sekitar yang terlibat. b. Kedudukan kawasan sensitif alam sekitar lain seperti water intake point yang berdekatan perlu diambilkira di dalam kajian EIA.

iii) Data yang digunakan dalam kajian EIA hendaklah terkini.

iv) Stesen-stesen pensampelan Lokasi stesen-stesen pensampelan bagi pengukuran garis dasar untuk kesemua parameter yang akan dikaji hendaklah ditunjukkan dengan jelas di dalam pelan/peta. Pengukuran garis dasar bunyi bising bagi waktu siang hendaklah dijalankan dari 7.00 pagi hingga 10.00 malam manakala bagi waktu malam hendaklah dijalankan dari 10.00 malam hingga 7.00 pagi.

v) Peta guna tanah dan peta Peta guna tanah hendaklah disertakan dengan peta topografi topografi yang jelas menunjukkan topografi, terrain dan river basin di kawasan kajian.

vi) Pelan guna tanah Laporan EIA hendaklah menyertakan pelan guna tanah terkini, terperinci dan lengkap serta jelas menunjukkan penerima sensitif di sepanjang cadangan jajaran. vii) Komitment pemaju projek Komitment daripada pemaju projek untuk mengadakan langkah-langkah kawalan (mitigating measures) yang berkesan dan terbukti dapat meminimakan impak negatif kepada alam sekitar. viii) Pengurusan sisa pepejal dan sisa Penjelasan mengenai jumlah dan kaedah pengurusan bahan binaan sisa pepejal dan sisa bahan binaan daripada aktiviti cadangan projek ini yang merangkumi sisa biomas akibat kerja-kerja pembersihan hutan di kawasan yang melibatkan pembinaan terowong dan sisa bahan kerukan dari kerja-kerja bawah tanah yang dijalankan.

ix) Langkah-langkah kawalan Kesemua langkah kawalan yang dinyatakan di dalam laporan EIA termasuklah komponen LDP2M2 bagi

2 - 27

THE PROPOSED PAN ISLAND LINK 1 HIGHWAY PROJECT, PENANG

No. Item Condition kawalan air larian permukaan, hakisan & kelodakan dan pengairan yang perlu dikaji bagi setiap impak kritikal yang dijangkakan dan hendaklah project specific dan jelas supaya ianya boleh diterjemahkan di dalam Pelan Pengurusan Alam Sekitar (Environmental Management Plan, EMP) kelak untuk dilaksanakan secara berkesan dari segi pemantauan dan sebagainya. x) Komitmen pemaju projek untuk Komitmen daripada pemaju projek untuk memasang memasang alat kawalan alat kawalan pencemaran (pollution control pencemaran equipment) hakisan dan kelodakan yang berkesan dan terbukti perlu dijelaskan supaya dapat meminimakan impak negatif kepada alam sekeliling. Penyediaan dokumen ‘Emergency Response Plan’, (ERP) juga perlu dirancang diperingkat penyediaan Laporan EIA.

xi) Rujukan garispanduan Rujukan garispanduan - garispanduan yang berkaitan hendaklah berpandukan kepada garispanduan yang terkini terbitan Jabatan ini dan garispanduan- garispanduan terbitan Agensi lain yang berkaitan.

xii) Jadual Pelaksanaan Projek Jadual Pelaksanaan Projek hendaklah disertakan.

Jabatan ini juga ingin menarik perhatian pihak tuan bahawa pengesahan ke atas Bidang Rujukan ini hanya sah diterima pakai dalam tempoh satu (1) tahun dari tarikh surat ini dikeluarkan dan akan terbatal sekiranya Kajian EIA tidak dilaksanakan dalam tempoh tersebut.

2 - 28