Eskom Presentation

Total Page:16

File Type:pdf, Size:1020Kb

Eskom Presentation Presentation to Portfolio Committee on Energy 15 March 2011 Eskom Holdings Ltd Update of Eskom’s Capital Expansion Programme Paul O’Flaherty Finance Director 2 1. Business overview 2. South Africa requirements and the capital expansion programme 3. Alignment with SA macro-economic principles 4. Costs and funding 5. Conclusion 3 Eskom at a glance • Strategic 100% state-owned electricity utility, strongly Eskom power grid(1) supported by the government • Vertically integrated across generation, transmission and distribution • Supplies approximately 95% of South Africa’s electricity (45% of the total electricity consumed in Africa) • 40 887 employees as at 31 December 2010 • Serves 3 000 industrial, 1 000 mining, 48 000 commercial, 84 000 agricultural and more than 4 million residential customers • 27 (including 1 nuclear) operational power stations with a Existing grid system Thermal power station Possible future grid system Future interconnection substation net maximum capacity of 40.87GW as at 31 March 2010 Future hydroelectric power station Nuclear power station Future thermal power station Future gas station Hydroelectric power station Gas power station • Total electricity sales of 218 591GWh and total revenues of Interconnection substation Town R71.21bn for the year ended 31 March 2010 (R71,6bn for 9 months ended 31 December 2010) Eskom’s net capacity mix – 31 March 2010 • Infrastructure includes 390,338km of power lines and Total: 40.87GW cables (all voltages) as at 31 March 2010 • Committed to build 17GW new generation capacity expected by 31 March 2018. This includes 5,032MW already commissioned as at 31 December 2010 (1) The map indicates the South African power network and interconnections with neighbouring countries 4 Generation • Operates Eskom’s generation plants Key figures • 27 power stations: 13 coal, 4 gas / liquid fuel turbines, Financial Year 2009 Financial Year 2010 6 hydro electric, 2 pump storage, 1 nuclear and 1 wind Net Capacity (MW) 40,506 40,870 • Total net capacity of 40,870MW as at 31 March 2010 Capacity from Coal (MW) 34,294 34,658 • Approximately 85% of net capacity is coal-fired Coal Share in Total Capacity 84.7% 84.8% Capacity from Nuclear (MW) 1,800 1,800 • Koeberg nuclear power plant Nuclear Share in Total Capacity 4.4% 4.4% Total Output (TWh) 229 233 • 1 800MW net capacity Production from Coal (TWh) 212 216 Coal Share in Total Output 92.6% 92.8% • 12 806GWh electricity produced from nuclear in Production from Nuclear (TWh) 13.0 12.8 year ended 31 March 2010 Nuclear Share in Total Output 5.7% 5.5% • 17 000MW of new capacity plans committed expected by 31 March 2018 (including already commissioned since 2005) Reserve margins • 10 896MW of new capacity to come from three projects 15% international norm • Medupi: 4 764MW coal-fired; first unit expected to be commissioned in 2012 and Eskom target • Kusile: 4 800MW coal-fired; first unit expected to be commissioned in 2014 • Ingula: 1 332MW pumped storage; expected to be commissioned in 2014 • Reserve margin of 15,1% for the nine months to31 December 2010, up from 5,6% as at 31 March 2008 and above international norms and Eskom’s target of 15% • No load shedding since April 2008 5 Transmission and Distribution Key Figures – 31 March 2010 • Total electricity sales of 218,591GWh and more than 4,46 million customers (including transmission 2010 Gross Electricity customers) as at 31 March 2010 2010 Sales Split Revenue Split Customers Total: 218,591GWh Total: R69,942m Total: 4.46 million • Directly provides electricity to 45% of all end users in South Africa • Country split into six regional distribution areas • Two main types of customers: • Redistributors: Mainly municipalities that sell electricity to residential customers. Eskom bills the municipality; the municipalities are responsible for billing and collecting their own tariffs • Direct customers: Industrial, commercial, mining, agricultural and residential consumers Energy Losses • Key Sales and Customer Service unit (‘KSACS’) NERSA 2010 deals with customers using more than 100GWh of 2008 2009 2010 Target energy per year Distribution losses 5.47% 5.46% 5.87% <=6.00% • At 31 December 2010, KSACS had approximately 130 customers accounting for Transmission losses 3.13% 3.08% 3.25% <=3.30% 38.6% of total revenues Total Eskom losses 8.00% 7.94% 8.45% <=8.76% • A member of Southern African Power Pool (“SAPP”) • Overall energy losses of 8,45% in FY2010, within the regulator’s (NERSA) allowed target of 8.76% 6 1. Business overview 2. South Africa requirements and the capital expansion programme 3. Alignment with SA macro-economic principles 4. Costs and Funding 5. Conclusion 7 IRP 2010 – balanced scenario 8 The future • South Africa needs to create ~40 800MW of new electricity capacity by 2030 – more than doubling the current requirements • This assumes decommissioning of 10 000MW of existing capacity • There will be two periods in the next 20 years when the risk of supply interruptions significantly increases in South Africa • from 2011-2013, and then again … • from 2018-2024 • South Africa needs to take urgent action in 2010 in order to ensure security of supply for the country for the next 20 years 9 Eskom Capital Expansion Programme – began in 2005 Mpumalanga Return-to-service (RTS) New Baseload Peaking & Renewables Refurbishment Transmission Komati Medupi Ankerlig Arnot 765 KV projects Camden Kusile Gourikwa Central projects Grootvlei Ingula Northern projects Sere Cape projects 3,720MW 9,564MW 3,516MW 300MW 4,000km Commissions of new stations First Unit Last Unit 17,000MW of new capacity (5,032MW commissioned ) Medupi 2012 2016 Kusile 2014 2018 4,000km of required transmission Ingula 2014 2014 network (3,103km commissioned) Medupi is the first coal-generating plant in Africa to use supercritical power generation technology 10 Progress to date (as at 31 December 2010) • To date, a large amount of construction work has been completed, adding ~5,031.8 MW, ~3,103.40 km of transmission network, and ~15,670 sub-stations . Megawatts 125 MW of capacity 452.5 1,769.9 1,042.6 5,031.8 1,351.8 0 290 Transmission 278.80 Km line 600.30 418.30 480 430 3,103.40 237 659 Substations 3,940 1,630 MVAs 1,375 1,355 1,000 1,090 5,280 15,670 FY FY FY FY FY FY FY Total 2004/5 2005/6 2006/7 2007/8 2008/9 2009/10 2010/11 11 Of the new capacity being installed, baseload coal-fired power stations account for 73%, while the peaking portfolio (OCGT, pumped storage, wind) will contribute the remaining 27% Of the coal-fired power stations, all but Medupi are located in the Mpumalanga province. Medupi is in Lephalale (Limpopo province). Medupi Kusile Arnot Peaking Komati Grootvlei Camden Ingula New coal Return To Service Sere Ankerlig Gourikwa Capacity upgrade 12 Key Transmission projects Medupi integration East Grid 765kV Ingula integration Cape corridor Southern Grid 765kV 13 13 While there is quite some progress already, there is a lot more construction work to be done in this programme The main technical KPIs are on track. Installed to date Not yet installed 29% MW MW installed ~5,031.8 ~12,188.5 ~17 220.3 78% Km Transmission lines installed ~3,103.4 ~896.6 ~4 000 76% MVAs Substation ~15,670 ~4,930 projects ~20 600 14 Focus is now on Medupi, Kusile, and Ingula - the first units will come on line between 2012 and 2014 Construction activities 1st unit commissioned Fully commissioned started December 2012 Mid 2016 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Fully 1st Unit commissioned Construction Construction commissioned 1st unit commissioned Fully commissionedFully commissioned January 2014 activities started activities started September 2014OctoberDecember 207 2014 October 2017 DecemberOctober 207 2018 •Medupi Power Station Kusile Power Station Ingula Power Station •Execution partner: Execution partner: Road works •Coal supply Coal supply Civil works •Boiler Boiler •Turbine Main Civils •Enabling Civils Infrastructure Turbine B&E Quanza •Main Civils Enabling Civils Dam construction Concor -WBHO •Generator transformers -Silver Rock Generator transformers Edwin 15 Build programme overview Medupi Kusile Ingula Project Summary Project Summary Project Summary ► Greenfields Project – Lephalale ► Greenfields Project – Delmas ► Greenfields Project – Ladysmith (Limpopo Province) (Mpumalanga Province) (KwaZulu Natal Province) ► 6 Unit Coal Fired Power Station ► 6 Unit Coal Fired Power Station ► 4 Unit pumped storage power station ► Planned capacity 4,764MW ► Planned capacity 4,800MW ► Planned capacity 1,352MW Financial & Economic Impact Financial & Economic Impact Financial & Economic Impact ► Projected project cost to ► Projected project cost to completion ► Projected project cost to completion ~R98.900 bn (excl. ~R121,000 bn (excl. IDC) completion ~R21.377 bn (excl. IDC) ► Estimated 25% impact on Delmas IDC) ► Estimated 95% impact on town GDP ► Estimated 7% impact on Lephalale town GDP Ladysmith town GDP Project Schedule Project Schedule Project Schedule ► Construction commenced March ► Construction commenced Mid 2008 2007 ► Construction commenced Mid ► First Unit planned to be 2006 ► First Unit planned to be commissioned December 2014 commissioned December 2012 ► First Unit planned to be ► Subsequent Units 2 & 3 at 12 month commissioned January 2014 ► Subsequent Units at 6 to 9 month intervals and Units 4, 5 & 6 at 8 ► Subsequent Units at 3 month intervals thereafter months thereafter intervals thereafter ► Last Unit planned for ► Last Unit planned for ► Last Unit planned for commissioning late 2015, mid commissioning during December commissioning during September 2016 2018 2014 16 Build programme overview Return to Service Transmission Mpumalanga & Other Projects Summary Project Summary Projects Summary - Mpumalanga ► Refurbishment and return to service of ► Transformers – 20 600 MVAs: ► Major refurbishments of existing and previously moth-balled coal fired •765kv (Planned: 12,000 MVAs) operational power stations, i.e.
Recommended publications
  • The Case of Kusile FINAL
    THE EXTERNAL COST OF COAL -FIRED POWER GENERATION: The case of Kusile Prepared by: • Business Enterprises at University of Pretoria (Pty(Pty)) LLtLtdtdd Prepared for: • Greenpeace Africa and Greenpeace International DATE: 29 September 2011 PO Box 14679 Hatfield 0028 University of Pretoria Main Campus, Prospect Street, Hatfield, Graduate Centre, Ground Floor, Entrance 1.82 T: +27 (12) 420 4245 F: +27 (12) 362 5270 TABLE OF CONTENTS 1. Introduction 5 2. Background, problem statement and study limitations 7 3. The externality cost of coal-fired power generation: a sectoral overview 9 3.1 Health 9 3.2 Climate change 11 3.3 Water 13 3.4 Mining 15 4. Results 17 5. Conclusion 19 6. References 21 NOTE: For access to the annexes listed below, please refer to the Greenpeace Africa website: www.greenpeaceafrica.org Annex 0 (Background): Coal and coal-fired power generation in South Africa Annex 1: The health costs of coal-fired power generation in South Africa Annex 2: Climate change: the opportunity cost of Medupi and Kusile power stations Annex 3: Estimating the opportunity cost of water for the Kusile and Medupi coal-fired electricity power plants in South Africa Annex 4: The external costs of coal mining: the case of collieries supplying Kusile power station ACKNOWLEDGEMENTS The authors gratefully acknowledge comments provided by the Greenpeace Africa and Greenpeace International review teams, and by four workshop panellists, Prof Jane Olwoch, Prof Kuku Voyi, Prof Ban Farrell and Mr Meiring du Plessis. This research was financially supported
    [Show full text]
  • Construction First in Portable Sanitation
    Construction First in Portable Sanitation Sanitech is the leading portable sanitation company in South Africa with branches nationwide and is renowned for its service excellence and superior product technology. Sanitech was the first portable toilet hire company to supply sanitation facilities to areas where no sanitation infrastructure existed. Experience counts and Sanitech understands the importance of choosing a trusted supplier with an outstanding track record. With more than two decades of local experience and the global support of Waco International, Sanitech is the only toilet hire company with the necessary national fleet to maintain a competitive edge. Fast and Efficient Site Solutions Sanitech currently provides ablution facilities to a substantial number of construction and industrial projects throughout the country, improving both the hygiene standards and productivity on these sites. Their services include: • Supply of fresh, clean water to the units • On-site toilet cleaning and servicing to agreed timescales • Short and long term rental of portable toilets and mobile • Replenishment of toilet rolls and soap and paper hand towels ablution units Current industry projects include: • Braamhoek Dam • Glencore Mines • Aveng Mine • Avon Power Station • Anglo Mines • Xstrata Mine • Thukela Water Project • Impumelelo Mine • Shiva Uranium • Cornubia Development • Shondoni Mine • Sasol Sigma Mine • Dube Tradeport • Total Coal Mine • Sasol Wax Phase 1 & 2 • Kouga Wind Farm • Kusile Power Station • Matlosana Mall • Dedisa Power Plant Special Projects • Sibanye Mine Construction • Sasol Synfuels • Wescoal Mine • Lethabo Power Station • PetroSA Orca Rig • Stefanutti Stocks Mine • R377 Road Construction Comprehensive Health and Safety Programme Sanitech’s world-class SHE management system is driven by Waco International Corporate Standards and helps to meet health and safety responsibilities by protecting their most valuable resources – employees, customers, communities and the environment that sustains us all.
    [Show full text]
  • Proposed Coal-Fired Power Stations and Associated Infrastructure in the Waterberg, Limpopo
    Report No: [4793A/402719] ENVIRONMENTAL IMPACT ASSESSMENT PROCESS: PROPOSED COAL-FIRED POWER STATIONS AND ASSOCIATED INFRASTRUCTURE IN THE WATERBERG, LIMPOPO FINAL SCOPING REPORT March 2009 LEAD CONSULTANT PROPONENT Ninham Shand (Pty) Ltd. Eskom Holdings Ltd. 81 Church Street Eskom Generation PO Box 1347 Megawatt Park Cape Town Maxwell Drive 8000 Sandton, 2199 Tel: (021) 481 2400 Tel: (011) 800 3501 Fax: (021) 424 5588 Fax : (011) 800 5140 Email: [email protected] Website : www.eskom.co.za PROPOSED COAL-FIRED POWER STATIONS IN THE WATERBERG, LIMPOPO: SCOPING REPORT Page i PROJECT DETAILS DEAT REFERENCE NO. : 12/12/20/1255 TITLE : FINAL SCOPING REPORT AUTHORS : Louise Corbett, Ashwin West, Brett Lawson SUBCONSULTANTS : AirShed Planning Professionals Golder Associates Groundwater Consulting Services InfoTox Ivuzi Johnny van Schalkwyk (Private Consultant) Jongens Keet Associates Makecha Development Association Ndodana Consulting Engineers Ptersa Environmental Management Consultants Riscom Smith, Summers, Ndlovu Associates Strategic Environmental Focus Urban-Econ Zitholele Consulting CLIENT : Eskom Holdings Limited (Generation Division) REPORT STATUS : Final REPORT NUMBER : 4793A/402719 REPORT DATE : 31 March 2009 ................................................ ………........................................... LOUISE CORBETT ASHWIN WEST (Pr. Sci Nat) Environmental Practitioner Associate: Environmental Discipline Group ................................................ BRETT LAWSON (Cert. EAPSA)(Pr Sci Nat) Associate: Environmental Discipline
    [Show full text]
  • Transmission Ten-Year Development Plan 2013-2022 Transmission Ten-Year Plan 2013 – 2022 > FOREWORD by GROUP EXECUTIVE
    Transmission Ten-Year Development Plan 2013-2022 Transmission Ten-Year Plan 2013 – 2022 > FOREWORD BY GROUP EXECUTIVE “I would also like to take this opportunity to thank the team that has worked and continues to work on the development of these plans.” A reliable electricity supply of acceptable quality is essential for the developed by Eskom and IPPs must be connected to the network. economic development of South Africa. It is also a prerequisite The first two phases of preferred bidders for the Department for socio-economic development, as it paves the way to access to of Energy’s REFIT renewable energy programme (wind, solar education, improved nutrition and health care, and jobs, amongst photovoltaic, solar thermal, etc.) have been announced to help others. The transmission system plays a vital role in the delivery meet South Africa’s commitment to reduce carbon emissions. of a reliable, high quality electricity supply throughout South Africa Thirdly, new loads need to be connected to the network. and the region, by delivering electricity in bulk to load centres The provision of a reliable electricity supply, which will enable South and very large end-users. From there, the distribution networks Africa to meet its economic growth targets, requires significant owned by Eskom and municipalities deliver electricity to end-users. capital investment, which is ultimately funded by electricity The transmission system needs to be well-maintained to deliver a consumers through the tariff. There is a need for stakeholders reliable supply of electricity, and it also needs to be strengthened to understand what is required to ensure a reliable and secure to meet changing customer needs.
    [Show full text]
  • Transmission Development Plan 2020-2029 FOREWORD by GROUP EXECUTIVE
    Transmission Development Plan 2020-2029 FOREWORD BY GROUP EXECUTIVE “As we do our best to meet our commitments in terms of the TDP, we will certainly face challenges; however, our hope is that, through collaboration, we can all own this plan and support its funding and execution in order to co-create an energy future in support of the economic growth of our country.” Segomoco Scheppers i FOREWORD BY GROUP EXECUTIVE The growth and development of our country’s economy to meet the growth in demand, and supply the future generation pattern. demands of a 21st century lifestyle relies heavily on a secure and With regard to cross-border Transmission inter connectors, our analysis reliable supply of electricity at affordable prices. It is obvious that people highlights the need to strengthen a number of our cross-border whose homes, workplaces, schools, and clinics are connected to the Transmission lines into neighbouring countries, in order to support grid for the first time will find their lives transformed for the better in increased cross-border electricity trade. This is expected to result in ways they could never previously have imagined. reduced upward pressure on tariffs and improved security of electricity supply both in South Africa and the region. The bulk of South Africa’s electricity is still produced by Eskom’s coal- fired power stations located in the coalfields of the Mpumalanga The benefits of a reliable and secure electricity supply to South Africa Highveld and near Lephalale, but the landscape for power generation is must be weighed against the associated costs to ensure that electricity rapidly changing.
    [Show full text]
  • Tebogo Mapinga
    Tebogo Mapinga KEY EXPERIENCE Professional Registrations: • SACNASP (115518) Tebogo is is a professional evironmental scientist with 11years’ experience in the environmental management field in both public and private sectors. Her competencies lie in management and co-ordination of environmental projects, environmental impact assessments, compliance monitoring ensuring compliance to legislation and guidelines and public participation for small and large scale projects. Occupation: PROJECT EXPERIENCE • Snr. Environmental Scientist 2017 Thabamesti Coal Fired Power Station Permitting 2017 Richards Bay CCPP Power Project Environmental Screening and Environmental Impact Assessment – EIA 2017 Roggeveld Wind Farm Environmental Management Programme (EMPr) Amendment and all work Specialisation: required to reach financial close- permitting (Building Energy and G7) 2017 Klawer Wind Farm • Project Management EMPr Amendment and all work required to reach financial close- permitting • Environmental Authorisations (Building Energy and G7) • Environmental Management 2017 Roggeveld Wind Farm • The review of BARs, EIARs, Environmental Management Programme (EMPr) Amendment and all work and EMPr’s required to reach financial close- permitting (Building Energy and G7) 2017 Adams PV Facility Upgrading of Charles Street All work required to reach financial close- permitting (Aurora Power Solutions Education: (Pty) 2016 Bellatrix PV Facility • BSc (Zoology and Physiology), All work required to reach financial close- permitting (Aurora Power Solutions 2007 (Pty)
    [Show full text]
  • Eskom's Financial Crisis and the Viability of Coal-Fired Power in South
    ESKOM’S FINANCIAL CRISIS AND THE VIABILITY OF COAL-FIRED POWER IN SOUTH AFRICA IMPLICATIONS FOR KUSILE AND THE OLDER COAL-FIRED POWER STATIONS Grové Steyn, Jesse Burton, Marco Steenkamp Contact: [email protected] 15 November 2017 ACKNOWLEDGEMENTS This study benefitted from the support of numerous parties. It was funded by a grant from the European Climate Foundation. We acknowledge the support from the Institute for Energy Economics and Financial Analysis (IEEFA) and, in particular our collaboration with David Schlissel. We also acknowledge the role of a wide range of stakeholders and industry participants who granted us interviews and without whose support we would not have been able to undertake the project.1 We thank the Council for Scientific and Industrial Research (CSIR) Energy Centre for undertaking the system level analysis for this project. All errors remain ours. This study should be cited as: Steyn, G, Burton, J, Steenkamp, M (2017) "Eskom’s financial crisis and the viability of coal-fired power in South Africa: Implications for Kusile and the older coal- fired power stations" Meridian Economics, Cape Town: South Africa. 1 Given the sensitive nature of the issues under consideration, and the difficulties currently experienced at Eskom, it was necessary to agree upfront that the names of interviewees will not be disclosed. © Meridian Economics 2017 | ii EXECUTIVE SUMMARY 1. Should Eskom cancel part of its power station construction programme to reduce costs? The South African power system has reached a 2. Should
    [Show full text]
  • Enviroserv Chloorkop Landfill Site Expansion Project Wetland, Soil and Land Capability Specialist Study Report
    ENVIROSERV CHLOORKOP LANDFILL SITE EXPANSION PROJECT WETLAND, SOIL AND LAND CAPABILITY SPECIALIST STUDY REPORT Report No.: JW100/19/6007-25 May 2019 Internet presence: www.jaws.co.za Synopsis EnviroServ Waste Management (Pty) Ltd own the existing Chloorkop Landfill Site (CLS) and operate it in terms of a waste management licence (Ref: 16/2/7/A230/D17/Z1). Municipal solid waste is received from the Midrand area, including the City of Johannesburg and the Ekurhuleni Metropolitan Municipality. The CLS is located in the Chloorkop Industrial area on Portion 63 of Klipfontein 12-IR and is accessed from Marsala Road. The waste body at the CLS has finite airspace, defined by the permitted footprint, height and design parameters and will not be able to receive waste once it reaches airspace capacity. EnviroServ is proposing to expand the CLS in order to provide additional airspace for ongoing disposal of municipal solid waste. The proposal is to expand the Chloorkop Landfill Site onto adjacent properties (Erf 334 and 335 of Chloorkop Extension 6), CLS Expansion Project. The concept is to establish engineered, Class B waste disposal cells on the target properties for ongoing disposal of municipal solid waste. The additional waste disposal cells would join with the current CLS waste body. The facility will include a small Material Recovery Facility for the separation of clean recyclables from the waste. Supporting infrastructure would be integrated with the CLS and/or redeveloped as appropriate. A municipal road, Anker Street, separates part of the expansion area from the CLS and thus a phased approach is likely.
    [Show full text]
  • Technical Tour To: Kusile Power Station Eskom, Witbank - South Africa, 4 October 2019
    Technical Tour to: Kusile Power Station Eskom, Witbank - South Africa, 4 October 2019 Kusile Power Station Technical Visit and Tour Shuttle bus from Misty Hills Country Hotel, 69 Drift Blvd, Muldersdrift, Johannesburg, South African , at 06:30 on Friday 4 October 2019 Return via shuttle bus by 14:00 Register from registration page Kusile Power Station Kusile is a coal-fired power station close to the existing Kendal Power Station in the NKANGALA DISTRICT of the Mpumalanga Province. The Kusile site is about 1 355 hectares in size, and is located on the Hartbeesfontein and Klipfontein farms. Kusile is the most advanced coal-fired power plant project in Eskom after Medupi power station in Lephalale where construction commenced in 2007. The station will consist of six units each rated at approximately 800 MW installed capacity giving a total of 4800 MW. As such it will be one of the largest coal-fired power stations in the world, once finished. The power station will be coal fired, with the coal supplied by Anglo Coal (New Largo and Zondagfontein collieries). The combination of the resources is expected to yield not less than 800 million sales tons over a period of not less than 47 years. Kusile will be the first power station in South Africa to have Flue Gas Desulphurization (FGD) installed. FGD is the current state-of-the art technology used to remove oxides of sulphur (SOx), e.g. sulphur dioxide (SO2), from the exhaust flue gases in power plants that burn coal or oil. This technology is fitted as an atmospheric emmission abatement technology, in line with current international practice, to ensure compliance with air quality standards, especially since the power station is located in a priority airshed.
    [Show full text]
  • Boom and Bust 2016: Tracking the Global Coal Plant Pipeline
    Boom and Bust 2016 TRACKING THE GLOBAL COAL PLANT PIPELINE Christine Shearer, Nicole Ghio, Lauri Myllyvirta, Aiqun Yu, and Ted Nace BOOM AND BUST ABOUT COALSWARM and Gregor Allensworth of GreenInfo Network, with support from Tim Sinnott of GreenInfo Network. CoalSwarm is a global network of researchers seeking to develop collaborative informational resources on coal impacts and alternatives. AUTHORS Current projects include identifying and This report was prepared by Christine Shearer, Nicole mapping proposed and existing coal projects worldwide, Ghio, Lauri Myllyvirta, Aiqun Yu, and Ted Nace. Christine including plants, mines, and infrastructure. Shearer is the Senior Researcher of CoalSwarm. Nicole Ghio is a Senior Campaign Representative for Sierra Club’s ABOUT THE SIERRA CLUB International Climate Program. Lauri Myllyvirta is Senior Global Campaigner, Coal and Air Pollution, at Greenpeace. The Sierra Club is America’s largest and most Aiqun Yu is an independent journalist and a researcher for influential grassroots environmental organiza- CoalSwarm. Ted Nace is Director of CoalSwarm. tion, with more than 2.4 million members and supporters. In addition to helping people from all backgrounds explore nature and our outdoor heritage, ACKNOWLEDGMENTS the Sierra Club works to promote clean energy, safeguard the The authors wish to thank Bob Burton (CoalSwarm), Tim health of our communities, protect wildlife, and preserve Buckley (IEEFA), Ashish Fernandes (Greenpeace), Elif our remaining wild places through grassroots activism, pub- Gündüzyeli (CAN Europe), Sherri Liang (Sierra Club), Vrinda lic education, lobbying, and legal action. Manglik (Sierra Club), and Neha Mathew (Sierra Club) for research assistance and editorial review. ABOUT GREENPEACE The report was designed by Charlene Will.
    [Show full text]
  • Water Hungry Coal: Burning South Africa's Water to Produce Electricity
    Water hungry coal Burning South Africa’s water to produce electricity “Among the many things that I learnt as president was the centrality of water in the social, political and economic affairs of the country, the continent and the world.” Nelson Mandela, World Summit on Sustainable Development, Johannesburg, 2002 Report 2012 © Greenpeace / Oswald Chikosi 2011. For more information contact: [email protected] Lead author: Melita Steele Contributing author: Nina Schulz Edited by: Fiona Musana, Nina Schulz Acknowledgements: Lauri Myllyvirta, David Santillo, Sanjiv Gopal, Olivia Langhoff, Ferrial Adam, Ruth Mhlanga, Michael Baillie, Mbong Akiy Published in October 2012 Greenpeace Africa 10A and 10B Clamart House, Clamart Road, Richmond Johannesburg, South Africa Postal Address: Greenpeace Africa PostNet Suite 125 Private Bag X09, Melville Johannesburg, 2109 South Africa Tel: +27 (0)11 482 4696 Fax: +27 (0)11 482 8157 Website: www.greenpeaceafrica.org Designed by: Kai.Toma Creatives Printed on 100% recycled post-consumer paper with vegetable based inks. Executive Summary 3 1. Background 6 1.1. Water scarcity 6 1.2. Looming conflicts over water 7 1.3. Climate Change 8 1.4. Making the coal-water connection 8 1.5. Water: the foundation of life 10 1.6. Coal versus water as a strategic resource 12 2. The thirsty, polluting coal process 13 2.1. The water impacts of coal production 13 2.2. The water impacts of coal combustion at coal-fired power stations 14 2.3. Water contamination by Acid Mine Drainage 15 3. Eskom’s “efficiency” efforts 18 3.1. Eskom’s thirst for water: incremental efficiency and pollution reduction measures 18 4.
    [Show full text]
  • Electricity MARCH 2017 2 Report Edited by Sheila Barradas, David Shepherd and Ria Theron
    Electricity MARCH 2017 2 Creamer Media’s Electricity Report March 2017 A review of South Africa’s electricity sector Picture by WBHO The material contained in this report was compiled by Mariaan Webb and the Research Unit of Creamer Media (Pty) Ltd, based in Johannesburg. Special credit is given to Creamer Media’s Terence Creamer, whose articles were widely used in the compilation of this report. The information in this report is correct as of March 14, 2017. Report edited by Sheila Barradas, David Shepherd and Ria Theron. Ordering information To subscribe to Research Channel Africa or purchase this report contact: Creamer Media (Pty) Ltd Tel +27 11 622 3744 Email [email protected] Cover picture by Duane Daws 3 Creamer Media’s Electricity Report March 2017 Table of Contents � List of abbreviations and acronyms 4 � Key developments 6 � Overview 8 � State-owned electricity provider Eskom 9 – Generation developments 10 • Nuclear power 12 – Capacity expansion 13 • Medupi 13 • Kusile 15 • Ingula 15 – Financial status and tariffs 16 – Coal supply 20 – Environmental impact 23 � Independent power producers 25 – Renewable energy 25 – Coal baseload 29 – Gas to power 30 – Cogeneration 31 – Peaker projects 31 � Electricity planning 32 – Nuclear 35 � Demand initiatives 38 � Transmission 40 � Distribution and electrification 41 – Electricity theft 42 � Southern African Power Pool 43 � Outlook 45 � Sources 47 Picture by Bloomberg by Picture 4 Creamer Media’s Electricity Report March 2017 List of abbreviations and acronyms BEE black economic
    [Show full text]