Section 6 Formulation of Airport Master Rehabilitation Plan

Total Page:16

File Type:pdf, Size:1020Kb

Section 6 Formulation of Airport Master Rehabilitation Plan SECTION 6 FORMULATION OF AIRPORT MASTER REHABILITATION PLAN Preparatory Survey on the Project for Nadzab (Lae) Airport Rehabilitation JICA Independent State of Papua New Guinea NAC SECTION 6: FORMULATION OF AIRPORT MASTER REHABILITATION PLAN 6.1 Confirmation on Airside Separation Requirements 1) Existing Airside Separation Distances At the existing Nadzab airport, separation distance between the runway center line and the parallel taxiway centerline is approx. 213 m, and the parallel taxiway centerline and the apron taxiway centerline is approx. 180 m. Distance between passenger terminal building and apron is approx. 6.5 m and apron depth is approx. 85 m as illustrated below. 85000 Apron Depth Baseline 6350 77500 7500 173600 213300 20135 150000 Runway Strip Apron TW Apron Stand Parallel TW Runway B737-800 B737-800 B737-800 B737-800 Terminal Figure 6.1-1 Existing Separations between Facilities 2) Examination of Airside Separation Distance Requirements Examination as to whether the site conditions allow layout of the runway, parallel taxiway, apron edge taxiway, aircraft parking stands and the passenger terminal building with adequate separation distances for the instrument approach runway accommodating the design aircraft in accordance with ICAO Annex 14, has been carried out. The design aircraft (combination of aircraft simultaneously operational) are as follows: B737-800 on the apron edge taxiway and B737-800 or smaller parked on the apron or vice versa; B777-200 on the apron edge taxiway and B737-800 parked on the apron or vice versa; and B777-200 on the apron edge taxiway and B777-200 parked on the apron for the long-term. Result of the examination is as follows: i) The separation distance between the existing runway and parallel taxiway is 213.3m which is more than enough to meet ICAO requirement for Code 4E (182.5m). ii) The distance between the existing parallel taxiway centerline and the existing passenger terminal building is approximately 265m. In between the parallel taxiway and terminal building, an apron edge taxiway, aircraft parking stand and an area for GSE and piping need to be provided to accommodate simultaneous operation of B777-200 in the long-term. The minimum distance for this requirement in accordance with ICAO are as shown below: 6-1 Preparatory Survey on the Project for Nadzab (Lae) Airport Rehabilitation JICA Independent State of Papua New Guinea NAC Distance between a parallel taxiway to an apron edge taxiway; 80m. Distance between an apron edge taxiway and B777-200 parked on a stand; 47.5m. Length of B777-200 parked on a stand; 64m. Area for GSE and piping; 25m. Total; 216.5m < 265m. 123000 Apron Depth 25000 111500 128450 213300 64000 47500 11500 min distance is 80m 150000 Runway Strip Apron TW Apron Stand Parallel TW Runway B777-200 B777-200 B777-200 Terminal Figure 6.1-2 Confirmation on Airside Separations for Simultaneous Operation by B777-200 Therefore, it can be concluded that, from airside separation distance viewpoint, aircraft parking stands and an apron edge taxiway capable of accommodating B777-200 simultaneously can be developed phase by phase starting from those capable of accommodating B737-800 simultaneously or simultaneous operation by B737-800 and B777-200. 6-2 Preparatory Survey on the Project for Nadzab (Lae) Airport Rehabilitation JICA Independent State of Papua New Guinea NAC 6.2 Location of New Passenger Terminal Building and New Apron As the existing passenger terminal building (PTB) is old and narrow, the proposed new passenger terminal building needs to be developed as soon as possible, but without adversely affecting operation of the existing terminal and apron. With regard to the location of proposed new passenger terminal, there could be two options as shown below: Develop the new terminal to the west of the existing PTB (Option A);and Develop the new terminal to the east of the existing PTB (Option B). New PTB Location Option A New PTB Location Option B Existing PTB Existing PTB Existing apron Existing Apron Demolish existing apron Construct new apron of Construct new apron for and construct new cement concrete propeller-driven aircraft cement concrete apron pavement Construct new apron taxiway of cement concrete pavement Construct new apron taxiway of cement concrete pavement Reinforce Reinforce Reinforce Reinforce existing existing existing existing taxiway taxiway taxiway taxiway Option A Option B Figure 6.2-1 Alternative Location of New PTB Options Table 6.2-1 shows comparison of two options. The Option B is more advantageous than Option A in terms of the efficiency and economy in construction and future expansion, among others, and therefore has been chosen as the preferred option. 6-3 Preparatory Survey on the Project for Nadzab (Lae) Airport Rehabilitation JICA Independent State of Papua New Guinea NAC Table 6.3-1 Comparison of Two New PTB Location Options Option A Option B Summary New PTB is to be located almost equidistant New PTB is to be located to the east of the from the apron edges, offering shorter existing PTB so that new terminal walking distance for passengers. construction would not obstruct operation of the existing terminal. Phasing and As the existing and new PTB are horizontally New PTB may be constructed independently Construction overlapped, the construction work needs to be from existing PTB. Period phased and longer time period required. Future The existing control tower could be an Ample area is available on both sides of the Expansion obstruction for future expansion of new PTB. new PTB for future expansion. Utilization of Part of existing PTB may be utilized as Existing PTB may be utilized as tentative Existing PTB tentative cargo terminal in the short-term but cargo terminal in the short to medium-term. needs to be demolished in the medium-term Further utilization in the long-term may for PTB expansion. require refurbishment which could be costly. Car Park Existing car park may be utilized, but it needs Additional car park will need to be developed significant rehabilitation and cost saving in front of new PTB. would be minimal. Aircraft Part of existing apron will need to be Operation of existing apron would not be Parking Apron demolished and new concrete pavement affected by construction of new PTB and constructed, which could prevent efficient and apron. smooth operation of PTB and apron. In The existing apron can be maintained as is addition, new apron pavement, at least (rehabilitation required) and utilized in future. equivalent to the demolished part, needs to be constructed, resulting in additional cost. Advantage This option could offer shorter walking Minimum adverse impact on operation of distance to passengers existing PTB and apron and no obstruction embarking/disembarking the aircraft on the for future expansion to both sides. apron. Existing PTB may be utilized as tentative cargo terminal. Disadvantage This option is time consuming and more Walking distance of passengers on apron costly in construction. would be longer, but provision of canopy Future expansion could be hindered by the could mitigate this problem. existing control tower. Conclusion Not preferable. Preferred option. 6-4 Preparatory Survey on the Project for Nadzab (Lae) Airport Rehabilitation JICA Independent State of Papua New Guinea NAC 6.3 Runway Extension As discussed in Subsection 5.4.1, extension of the runway may be required in future to accommodate medium to long-haul international flights. The runway length requirement together with direction of runway extension should be carefully examined in close cooperation with Air Niugini and other operating airlines as precise examination on the one-engine failure aircraft operation can only be made by the operating airlines. 6.4 Layout of Other Major Facilities 1) Cargo Terminal Building At present, air cargo handling is being carried out inside the existing passenger terminal. Upon completion of the new passenger terminal construction, the existing passenger terminal may be converted to the cargo terminal building as it has adequate space to meet forecast future cargo demand (short to medium-term). In the long-term, a new cargo terminal building will need to be constructed to accommodate both domestic and international cargo demand. As majority of the air cargo will still be transported by passenger aircraft, the new cargo terminal building should be located close to the passenger aircraft apron. Possible location of the new cargo terminal building would be to the western side of the existing passenger terminal (cargo terminal in the short-term) where a new terminal may be developed while maintaining the cargo terminal operation. 2) Control Tower It has been proposed to utilize the existing control tower after refurbishment in the short-term, however the tower is already 40 years old and a new control tower will be required in future. Possible location of the new control tower could be to the west of the existing tower near the existing rescue and fire-fighting station. Attention should be paid to ensure meeting line-of-sight requirement to the future extended runway end. 3) Rescue and Fire-fighting Station It has been proposed to construct a new rescue and fire-fighting station to ensure level of protection and timely response in case of emergency. Proposed location of the new rescue and fire-fighting station is in the eastern side of the exiting station where a direct access to the runway via Taxiway B is achievable. 6-5 Preparatory Survey on the Project for Nadzab (Lae) Airport Rehabilitation JICA Independent State of Papua New Guinea NAC 4) NAC Administration Building It has been proposed that a new NAC Administration Building complete with monitoring, communication and control system should be built near the existing administration building in order to ensure safe and efficient airport operations. 6.5 Airport Master Rehabilitation/Development Plan Figure 6.5-1 shows proposed short-term Nadzab Airport Master Rehabilitation Plan, and Figure 6.5-2 shows proposed short-term Terminal Facilities Rehabilitation Plan.
Recommended publications
  • Civil Aviation Development Investment Program (Tranche 3)
    Resettlement Due Diligence Reports Project Number: 43141-044 June 2016 PNG: Multitranche Financing Facility - Civil Aviation Development Investment Program (Tranche 3) Prepared by National Airports Corporation for the Asian Development Bank. This resettlement due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Table of Contents B. Resettlement Due Diligence Report 1. Madang Airport Due Diligence Report 2. Mendi Airport Due Diligence Report 3. Momote Airport Due Diligence Report 4. Mt. Hagen Due Diligence Report 5. Vanimo Airport Due Diligence Report 6. Wewak Airport Due Diligence Report 4. Madang Airport Due Diligence Report. I. OUTLINE FOR MADANG AIRPORT DUE DILIGENCE REPORT 1. The is a Due Diligent Report (DDR) that reviews the Pavement Strengthening Upgrading, & Associated Works proposed for the Madang Airport in Madang Province (MP). It presents social safeguard aspects/social impacts assessment of the proposed works and mitigation measures. II. BACKGROUND INFORMATION 2. Madang Airport is situated at 5° 12 30 S, 145° 47 0 E in Madang and is about 5km from Madang Town, Provincial Headquarters of Madang Province where banks, post office, business houses, hotels and guest houses are located.
    [Show full text]
  • Papua New Guinea
    PAPUA NEW GUINEA EMERGENCY PREPAREDNESS OPERATIONAL LOGISTICS CONTINGENCY PLAN PART 2 –EXISTING RESPONSE CAPACITY & OVERVIEW OF LOGISTICS SITUATION GLOBAL LOGISTICS CLUSTER – WFP FEBRUARY – MARCH 2011 1 | P a g e A. Summary A. SUMMARY 2 B. EXISTING RESPONSE CAPACITIES 4 C. LOGISTICS ACTORS 6 A. THE LOGISTICS COORDINATION GROUP 6 B. PAPUA NEW GUINEAN ACTORS 6 AT NATIONAL LEVEL 6 AT PROVINCIAL LEVEL 9 C. INTERNATIONAL COORDINATION BODIES 10 DMT 10 THE INTERNATIONAL DEVELOPMENT COUNCIL 10 D. OVERVIEW OF LOGISTICS INFRASTRUCTURE, SERVICES & STOCKS 11 A. LOGISTICS INFRASTRUCTURES OF PNG 11 PORTS 11 AIRPORTS 14 ROADS 15 WATERWAYS 17 STORAGE 18 MILLING CAPACITIES 19 B. LOGISTICS SERVICES OF PNG 20 GENERAL CONSIDERATIONS 20 FUEL SUPPLY 20 TRANSPORTERS 21 HEAVY HANDLING AND POWER EQUIPMENT 21 POWER SUPPLY 21 TELECOMS 22 LOCAL SUPPLIES MARKETS 22 C. CUSTOMS CLEARANCE 23 IMPORT CLEARANCE PROCEDURES 23 TAX EXEMPTION PROCESS 24 THE IMPORTING PROCESS FOR EXEMPTIONS 25 D. REGULATORY DEPARTMENTS 26 CASA 26 DEPARTMENT OF HEALTH 26 NATIONAL INFORMATION AND COMMUNICATIONS TECHNOLOGY AUTHORITY (NICTA) 27 2 | P a g e MARITIME AUTHORITIES 28 1. NATIONAL MARITIME SAFETY AUTHORITY 28 2. TECHNICAL DEPARTMENTS DEPENDING FROM THE NATIONAL PORT CORPORATION LTD 30 E. PNG GLOBAL LOGISTICS CONCEPT OF OPERATIONS 34 A. CHALLENGES AND SOLUTIONS PROPOSED 34 MAJOR PROBLEMS/BOTTLENECKS IDENTIFIED: 34 SOLUTIONS PROPOSED 34 B. EXISTING OPERATIONAL CORRIDORS IN PNG 35 MAIN ENTRY POINTS: 35 SECONDARY ENTRY POINTS: 35 EXISTING CORRIDORS: 36 LOGISTICS HUBS: 39 C. STORAGE: 41 CURRENT SITUATION: 41 PROPOSED LONG TERM SOLUTION 41 DURING EMERGENCIES 41 D. DELIVERIES: 41 3 | P a g e B. Existing response capacities Here under is an updated list of the main response capacities currently present in the country.
    [Show full text]
  • PNG: Civil Aviation Development and Investment Program- Tranche 3
    Initial Environmental Examination Project No.: 43141-044 Document Stage: Final April 2016 PNG: Civil Aviation Development and Investment Program- Tranche 3 Runway Extension, Terminal Relocation and Associated Works – Momote Airport, Manus Province Prepared by National Airports Corporation for the Asian Development Bank. This Initial Environmental Examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or Staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. P a g e | ii TABLE OF CONTENTS LIST OF ABBREVIATIONS ........................................................................................................ iii EXECUTIVE SUMMARY ........................................................................................................... iv I. INTRODUCTION ................................................................................................................ 1 II. DESCRIPTION OF THE PROJECT ................................................................................... 4 III. DESCRIPTION OF EXISTING ENVIRONMENT .............................................................. 10 IV. SCREENING ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ................
    [Show full text]
  • PNG: Sustainable Highlands Highway Investment Program -Tranche 2
    Initial Environmental Examination Project Number: 48444 Date: February 2020 Document status: Draft PNG: Sustainable Highlands Highway Investment Program -Tranche 2 Volume I: Erap River Bridge (Km 46+500) to Kabalipi River (Km 288 + 100) Prepared by the Department of Works (DOW) for Asian Development Bank This Initial Environmental Examination (Volume I) is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. ii CURRENCY EQUIVALENTS (as of February 2020) Currency Unit – Kina (K) K1.00 = $0.294 $1.00 = K3.396 ABBREVIATIONS ADB – Asian Development Bank AIDS – Acquired Immunodeficiency Syndrome AP – Affected Persons BOD – Biochemical Oxygen Demand CEMP – Contractor’s Environmental Management Plan CEPA – Conservation and Environmental Protection Authority CSC – Construction Supervision Consultant DC – Design Consultant DFAT – Department of Foreign Affairs and Trade of the Government of Australia DMS – Detailed Measurement Survey DNPM – Department of National Planning and Monitoring DOW – Department of Works EARF – Environmental Assessment and Review Framework EHSG _ Environmental Health and Safety Guidelines EHSO _ Environment,
    [Show full text]
  • 48444-004: Sustainable Highlands
    Initial Environmental Examination (Updated as of August 2019) Project Number: 48444-004 Date: August 2019 Document status: Updated Version PNG: Sustainable Highlands Highway Investment Program – Tranche 1 Prepared by the Department of Works (DOW) for the Asian Development Bank This Initial Environmental Examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or Staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. CURRENCY EQUIVALENTS (As of 31 July 2019) Currency Unit – Kina (K) K1.00 = $ 0.2945 $1.00 = K3.3956 ABBREVIATIONS ADB – Asian Development Bank AEP – Aggregate Extraction Plan AIDS – Acquired Immunodeficiency Syndrome BOD - Biochemical Oxygen Demand BOQ – Bill of Quantities CEMP - Contractor’s Environmental Management Plan CEPA – Conservation and Environmental Protection Authority CEPA-MD – CEPA-Managing Director CRVA _ Climate Risk Vulnerability Assessment CSC - Construction Supervision Consultant DLPP - Department of Lands and Physical Planning DMR – Department of Mineral Resources DNPM - Department of National Planning and Monitoring DOW – Department of Works EARF – Environmental Assessment and Review Framework EHSG _ Environmental Health and Safety Guidelines
    [Show full text]
  • CONDITIONS of USE DOCUMENT As at 1St January 2013
    CONDITIONS OF USE DOCUMENT As at 1st January 2013 National Airports Corporation Limited (NAC) National Airports Corporation Limited (NAC) is the owner and operator of the Papua New Guinea capital city and regional Airports directly servicing the capital city and regional Airports of Papua New Guinea. NAC is a State owned aviation enterprise established under and regulated by the Civil Aviation Act 2000 as amended (‗CA Act‘). NAC owns and operates 22 national Airports located throughout Papua New Guinea‘s main provincial headquarters and situated in Port Moresby, Nadzab, Mt Hagen, Tokua, Madang, Wewak, Gurney, Hoskins, Goroka, Kavieng, Buka, Momote, Vanimo, Tari, Mendi, Kundiawa, Wapenamanda, Kerema, Kiunga, Daru, Girua and Aropa. These Conditions of Use set out the standard operation conditions of use for all Air Operators at all NAC Airports throughout Papua New Guinea. Background Details NAC is owned by the people of Papua New Guinea through the trustee shareholding of the Minister for Treasury and Finance and the Minister for Civil Aviation of the Government of the Independent State of Papua New Guinea. With effect from the 1st day of January 2013, NAC agrees to supply Aeronautical Services to Air Operators and to allow Air Operators to enjoy Use of an Airport on a non-exclusive basis, in accordance with these Conditions of Use and in consideration of such supply, Air Operators agree to pay to NAC the Aeronautical Charges and agree to comply with all other obligations imposed on Air Operators by these Conditions of Use. .................................... Company Secretary NAC P.O 684 BOROKO, National Capital District Papua New Guinea Tel: + 675 324 4753 / 323 7924 / 323 670 Fax: + 675 325 0870 Email: [email protected] National Airports Corporation |Conditions of Use (i) Table of Contents 1.
    [Show full text]
  • Morobe & Madang Provinces
    © Lonely Planet Publications 124 lonelyplanet.com MOROBE & MADANG PROVINCES •• History 125 HISTORY Volcanic eruptions at Rabaul in 1937 Ancient axe heads that have been found sug- prompted a decision to move the capital of Morobe & Madang gest people have been living in this part of New Guinea to Lae, but WWII intervened PNG for about 40,000 years. Simbai settle- and instead Lae, Salamaua and Rabaul be- ments date back 15,000 years. Bilbil and Yabob came major Japanese bases. The Japanese also Provinces people in Madang Province are famous for took Madang. their pots, which they’ve been trading with In early 1943 the Japanese, reeling from Morobe peoples and Highlanders for eons. defeats at Milne Bay and the Kokoda Track, If you have just rolled down the pot-holed roads of the Highlands on an arse-spanking The first European to spend any length attempted to take Port Moresby by attacking PMV, Morobe and Madang, with their beaches and bays, will be as welcome as a shot of of time on the PNG mainland was Russian towards Wau, marching over the mountains quinine after a bout of malaria. biologist Nicolai Miklouho-Maclay. He ar- from Salamaua. The Battle of Wau was fought rived at Astrolabe Bay, south of the present hand-to-hand after the ammunition ran out, Geographically speaking they are similar – both rise from pristine beaches and bays of site of Madang, in 1871 and stayed for 15 with villagers watching in much the same way that foreign researchers (with an advanced Papua New Guinea’s northern coast into a series of thickly forested hills, imposing mountain months before leaving to regain his health, which was badly affected by malaria.
    [Show full text]
  • PNG: Sustainable Highlands Highway Investment Program -Tranche 2
    Initial Environmental Examination Project Number: 48444 Date: February 2020 Document status: Draft PNG: Sustainable Highlands Highway Investment Program -Tranche 2 Volume II: Jogi River Bridge (Km 298+900) to Waghi River Bridge (Km 463+900) Prepared by the Department of Works (DOW) for Asian Development Bank This Initial Environmental Examination ( Volume II) is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. CURRENCY EQUIVALENTS (as of February 2020) Currency Unit – Kina (K) K1.00 = $0.294 $1.00 = K3.396 ABBREVIATIONS ADB – Asian Development Bank AIDS – Acquired Immunodeficiency Syndrome AP Affected Persons BOD – Biochemical Oxygen Demand CEMP – Contractor’s Environmental Management Plan CEPA – Conservation and Environmental Protection Authority CSC – Construction Supervision Consultant DC – Design Consultant DFAT – Department of Foreign Affairs and Trade of the Government of Australia DMS – Detailed Measurement Survey DNPM – Department of National Planning and Monitoring DOW – Department of Works EARF – Environmental Assessment and Review Framework EHSG _ Environmental Health and Safety Guidelines EHSO _ Environment,
    [Show full text]
  • Manus Island a Living and Working Guide
    Manus Island A Living and Working Guide Version 8, May 2013 This is a department resource only and not for external distribution. The information contained within this guide is accurate at time of print, however environment, details, situations and procedures may have changed at time of reading. If in doubt regarding any of the information within this guide please contact IMA Workforce Management team at [email protected] for clarification. If you require additional hardcopies of this guide please contact IMA Workforce Management team at [email protected] Manus Guide, v.6, May 2013 2 Contents Foreword ................................................................................................. 5 Part 1: About Manus Island ..................................................................... 6 Location and geography .......................................................................................................................... 6 History ...................................................................................................................................................... 6 Climate ..................................................................................................................................................... 7 Time difference ........................................................................................................................................ 7 Language ................................................................................................................................................
    [Show full text]
  • Em204 2021 Anzac Day Pilgrimage Tour Sun 18 April
    EM204 2021 ANZAC DAY PILGRIMAGE TOUR SUN 18 APRIL – SUN 25 APRIL 2021 CORE TOUR 7 nights Port Moresby, Wewak, Lae, Rabaul, Bomana War Cemetery (dawn service) 2 nights optional pre-tour extension to Alotau (Milne Bay) 16-18 APRIL 3 nights optional post-tour extension to Popondetta, Kokoda, Buna/Gona 25-28 APRIL Fully escorted sign-up group tour, minimum 6 people for core tour and extensions, maximum 16. INTRODUCTION Attending the Anzac Day dawn service at Bomana War Cemetery outside Port Moresby is a “must” if you have any connection with or interest in Australia’s military history. It is a very emotionally moving experience. There before you, as you recite the Ode and sing Abide With Me in the semi-darkness, lie the actual graves of 3800 men and women who gave their lives for Australia, Britain and Papua New Guinea in wartime. This tour provides an opportunity to learn about the Bomana War Cemetery, find the graves of forbears and heroes and explore some of the locations where the Pacific Campaign unfolded and those now buried at Bomana saw action. This tour is fully escorted by one of our experienced company guides and features sites of World War 2 significance around Port Moresby, Wewak, Lae and Rabaul concluding with the Anzac Day dawn service at Bomana War Cemetery. There are optional extensions to Alotau (Milne Bay) and Popondetta (with excursions to Kokoda and the beach-heads around Buna and Gona). ECOTOURISM MELANESIA LTD TOUR COST 7 nights core tour Port Moresby Wewak Lae Rabaul: AUD 6925 per person (includes twin-share accom
    [Show full text]
  • Guidance Notes for Staff New to Ramu Agri-Industries
    GUIDANCE NOTES FOR STAFF NEW TO RAMU AGRI-INDUSTRIES LIMITED PAPUA NEW GUINEA September 2009 CONTENTS 1 Page No INTRODUCTION PART A PAPUA NEW GUINEA 1 The Country 1 2 The Climate 2 3 Brief History 3 4 Government 5 5 The Economy 6 6 Development 7 7 Population, People, Culture 8 PART B RAMU AGRI-INDUSTRIES LIMITED 1 Outline of the Project 9 PART C GENERAL INFORMATION 1 Entry Visas and Work Permits 10 2 Medical Requirements before Departure 11 3 Facilities for Babies 12 4 Baggage, Freight and Insurance 13 5 Journey to PNG 15 6 Currency 16 7 Banking and Remittances 17 8 Communications 18 9 Personal Security and Insurance 19 10 Housing 20 11 Services 22 12 Domestic Staff 23 13 Shopping 24 14 Health and Medical Facilities 26 15 Clothing 27 16 Recreation 28 17 Schooling 29 18 Private Transport 30 19 Employment for Wives 31 20 Pets 32 21 Hours of Work 33 1 This Ed 6 12.01.2010 / Printed 12-Jan-10. A DJD and Jengreg production APPENDICES 1. Maps of Lae and Madang 2. Reading List and Information Websites 3. Cost of living data 4 Public Holidays 5 Furniture lists 6 Temporary kit list PART A INTRODUCTION These notes are produced for prospective expatriate staff of Ramu Agri-Industries Limited, especially those who have not previously visited Papua New Guinea. Every effort is made to ensure that the information given is accurate and to this end amendments are issued from time to time. Nevertheless, it is inevitable that certain details may be slightly out of date by the time the notes are read.
    [Show full text]
  • PNG Air & SIL Aviation P2-MCH & P2-SID De Havilland Canada DHC
    FINAL SHORT SUMMARY REPORT AIC 17-2001 PNG Air & SIL Aviation P2-MCH & P2-SID de Havilland Canada DHC-8-102 & Quest Kodiak 100 Reciprocal track airspace proximity incident 6.8 nm West of Nadzab Airport Morobe Province PAPUA NEW GUINEA 2 June 2017 i AIC 17-2001 About the AIC The Accident Investigation Commission (AIC) is an independent statutory agency within Papua New Guinea (PNG). The AIC is governed by a Commission and is entirely separate from the judiciary, transport regulators, policy makers and service providers. The AIC's function is to improve safety and public confidence in the aviation mode of transport through excellence in: independent investigation of aviation accidents and other safety occurrences within the aviation system; safety data recording and analysis; and fostering safety awareness, knowledge and action. The AIC is responsible for investigating accidents and other transport safety matters involving civil aviation, in PNG, as well as participating in overseas investigations involving PNG registered aircraft. A primary concern is the safety of commercial transport, with particular regard to fare-paying passenger operations. The AIC performs its functions in accordance with the provisions of the PNG Civil Aviation Act 2000 (As Amended), and the Commissions of Inquiry Act 1951, and in accordance with Annex 13 to the Convention on International Civil Aviation. The object of a safety investigation is to identify and reduce safety-related risk. AIC investigations determine and communicate the safety factors related to the transport safety matter being investigated. It is not a function of the AIC to apportion blame or determine liability.
    [Show full text]