<<

Public Consultation Revised Restoration Plans Shapfell

September 2018 Quarry Shapfell Quarry 2 Public Consultation: Revised Restoration Plans Introduction

This brochure is provided by Tata Steel which is updating plans to fully restore Shapfell Quarry in .

As part of the plans, Tata Steel is The existing restoration plan was approved in 2008. proposing to withdraw an existing This plan is no longer practically achievable or planning application for further extraction environmentally preferable as it would involve draining the water and infilling of the large waterbody void. and deepening of the Quarry. The updated restoration plan will ensure sensitive and progressive restoration of the Quarry. The purpose of this brochure is to provide you with an update on activities at Shapfell Quarry and There will be no deepening or lateral extension to provide details of the updated draft restoration of the Quarry as part of the proposals. Tata Steel plan. Tata Steel is providing you with an opportunity believes it is important to return the land to the over the coming weeks to provide feedback on the landowner in a suitably restored condition. updated restoration plan before planning applications are submitted to .

We thank you for taking time to read the information and for your feedback. More information about how you can get in touch is provided. Background

Limestone has been quarried from Shapfell since 1962 and through this work the Quarry has become a major employer in the local area, contributing considerably to the local economy.

As part of the proposals it is intended to continue production at the Works site so there will be no loss of employment. However, the use of the Quarry has lessened in recent years and the Works are now largely operated using limestone from other quarries.

3 Shapfell Quarry today Shapfell history 1962: Quarrying began at Shapfell

1996: Original restoration plan approved Over time, two sites have operated at Shapfell; the Quarry which is located to the 2008: An application was submitted east of the M6, and the Works site located to the west of the M6. The site location to extend the quarry plan below illustrates the relationship between the Quarry and the Works site. The entire site comprises approximately 120 hectares (297 acres) of land. 2009: Active drilling and shot blasting ceased at the Quarry (although a limited These sites have been linked since the opening of the quarry, with quarried stone amount of already quarried stone has been being transported from the Quarry to the Works site. There, stone is crushed, processed for the ongoing restoration) washed and burnt; ready to be used in the steelmaking process. This product has been a part of the wider UK steel industry for more than 55 years. 2014: Additional information submitted to Cumbria Council Since 2009, Tata Steel has primarily imported limestone from other sources including the nearby Beck Quarry and from Derbyshire. This has enabled 2018: The current application will be the Works site to continue production. As part of the washing process, withdrawn and new applications submitted a mixture of clay and small limestone particles are generated. This provides for restoration an entirely natural calcareous limestone material ideally suited to the restoration of Shapfell Quarry.

Options have been explored for continuing to quarry limestone from Shapfell, but the decision has been taken not to pursue this deepening or lateral extension of the Quarry. Instead to continue with the full restoration of the site and to return the land to the landowner in a suitably restored condition.

Site Location

Shap Village

M6

The works Site

The Quarry Site

Shapfell Quarry 4 Public Consultation: Revised Restoration Plans A new The revised restoration restoration plan plan will: • Take approximately 18 years to complete and be implemented in phases to respect existing wildlife habitats In 2008, the current restoration scheme was approved for the Quarry site. This restoration plan required the whole quarry void to be refilled. • Restore the site levels to those of the surrounding area to the south, Approximately 37ha (91.5 acres) of the quarry has already been restored reconnecting the quarry to the in accordance with the approved scheme. However, other parts of the site, surrounding landscape (including including the main quarry void, are yet to be fully restored. the SSSI to the south)

Why is a new restoration plan needed? • Retain the large waterbody to the east of the site which has become an important Since the existing restoration plan was approved, the conditions of the site and local habitat for some species its landform have changed. In particular, the main quarry void has formed a large waterbody covering an area of approximately 30 hectares. This area of the site has • Install a new footpath to encourage become a habitat for wildlife. Water levels have also been monitored over the years recreational enjoyment of the area and the water level has stabilised meaning that the waterbody is now an important (subject to the landowner’s permission, feature of the landscape. and subject to agricultural requirements)

The new restoration plan has been prepared taking into account these changed • Include planting of mixed native conditions of the site. The updated restoration plan has been designed to retain woodland species. and protect the waterbody, as well as to maximise the amount of land reserved for nature conservation.

The plan is to withdraw the existing undetermined planning application to extend the use of the quarry and submit two Section 73 applications. The Section 73 applications are required to amend conditions attached to the existing planning permissions. The applications will seek agreement for a revised restoration plan and an extension to the timescale for completing the restoration. This new agreement will facilitate the phased restoration of the Quarry set out in this brochure.

5 LEGEND LEGEND Quarry boundary Shap Fell Quarry planning application boundary A new Proposed Contours

Shap Fell Works boundaryPreviously restored areas of quarry

Existing Public Right of Way (PRoW) restoration plan Existing Contours Proposed footpath New Contours Proposed semi-improved grassland and basic finish slope Cliff edge

Section of cliff to be 320 Proposed bare ground The plan on this page provides a visual guide as retained. Previously restored areas of quarry Proposed gravel island

to how we are proposing to restore Shapfell Quarry. Existing Public RightProposed of Way mixed native woodland Proposed native woodland species mix: 305 The plan is in the draft stages and is being informed by 25% Quercus petraea (Sessile Oak) Proposed ephemeral marsh/ shallow scrape 310 Proposed footpath ongoing technical surveys, the evolving conditions of 15% Fagus sylvatica (Beech) 10% Acer campestre (Field Maple) 315 315 310 Proposed semi-improved grassland and basic flush slope the site and discussions with Cumbria County Council. 5% Carpinus betulus (Hornbeam)

10% Betula pendula (Silver Birch) 320 Proposed bare ground 10% Pinus sylvestris (Scots Pine) 325 15% Sorbus aucuparia (Mountain Ash) Proposed gravel islands 10% Crataegus monogyna (Hawthorn) 305

Proposed mixed native woodland 350

330 320 Proposed ephemeral marshy/shallow scrape 355 Section of cliff to be retained.

325 Proposed footpath to link public rights of way.

315

325

HARDENDALE365 NAB

355 310

335

305 360 340

310 305

320 Indicative wet flush flows 02 23/08/18 THIRD ISSUE CN DL DL 01 03/08/18 SECOND ISSUE CN DL DL during heavy rainfall. 350 00 06/07/18 FIRST ISSUE CN DL DL 345

330 Rev. Date Amendments N Drwn Chkd Appd

320

THE NAB 325

365 305

360

335 330

COAST TO COAST FOOTPATH

305

360

315 Four Ways House, Tel: +44 (0) 161 236 2757

325 310 310 57 Hilton Street, 355 Fax: +44 (0) 161 236 7029 Manchester, Email: [email protected] M1 2EJ. 00 05/07/2018 FIRST ISSUE CN DL DL 335 Web: www.rsk.co.uk

LEGEND 340 LEGEND Rev. Date Amendment DrawnChkd. Appd. Client

330 Quarry boundary 305

Shap Fell Quarry planning application boundary 350 320 TATA Steel UK Ltd. Proposed Contours 345

330 330 335 325 320 Section of low cliff to be Shap Fell Works boundaryPreviously restored areas of quarry

retained. 330 335 Existing Public Right of Way (PRoW) 325 Existing Contours WATERS Project Title FARM

HARDENDALE Proposed footpath 330 Client New Contours Proposed bund and Levels raised to match Shap Fell Quarry Proposed semi-improved grassland and basic hibernacula for Great SSSI to the south. 330 TATA STEEL UK LTD

finish slope Crested Newts, 320 Cliff edge amphibians and reptiles.

Section of cliff to be 320 Proposed bare ground 325 Project Title 300 retained. Previously restored areas of quarry Drawing Title Proposed gravel island SHAP FELL QUARRY Restoration Plan Existing Public RightProposed of Way mixed native woodland 325 Proposed native woodland species mix:

305 320 Drawing Title 25% Quercus petraea (Sessile Oak) Proposed ephemeral marsh/ shallow scrape 300 310 Proposed footpath RESTORATION 15% Fagus sylvatica (Beech) SHAP

305 FELL Drawn Date Checked Date MASTERPLANApproved Date 10% Acer campestre (Field Maple) 315 315 CN 06\07\18 DL 06\07\18 DL 06\07\18 310 Proposed semi-improved grassland and basic flush slope WORKS 315 5% Carpinus betulus (Hornbeam) Drawn Date Checked Date Approved Date Scale: NTS CNOriginal 05/07/18 Size DL 05/07/18Status DL 05/07/18 A1 For Issue 10% Betula pendula (Silver Birch) 320 Proposed bare ground Existing access track to 320 Scale Orig Size Status 10% Pinus sylvestris (Scots Pine) 325 be reduced in width to 3m Scale as shown A1 DRAFT Drawing No. Rev. to enable maintenance 661739_04_02 Drawing No. 02 Rev. 15% Sorbus aucuparia (Mountain Ash) Proposed gravel islands access. 661739_04_02 00 305 10% Crataegus monogyna (Hawthorn) File Path RSK(MLs)661739_04_02 Proposed mixed native woodland Scale as shown

0 50 100 150 200 250 300m 350

330 320 Proposed ephemeral marshy/shallow scrape

Source:Source: Esri, Esri, DigitalGlobe, DigitalGlobe, GeoEye, Earthstar GeoEye, Geographics, Earthstar CNES/Airbus Geographics, DS, USDA, USGS, CNES/Airbus AeroGRID, IGN, DS, and the USDA, GIS user USGS, communit yAeroGRID, (2018). IGN, and the GIS user community (2018). 355 Section of cliff to be retained.

325 Proposed footpath to link

public rights of way. Shapfell Quarry

315 325 365 6

HARDENDALE NAB Public Consultation: Revised Restoration Plans

355 310

335

305 360 340

310 305

320 Indicative wet flush flows 02 23/08/18 THIRD ISSUE CN DL DL 01 03/08/18 SECOND ISSUE CN DL DL during heavy rainfall. 350 00 06/07/18 FIRST ISSUE CN DL DL 345

330 Rev. Date Amendments N Drwn Chkd Appd

320

THE NAB 325

365 305

360

335 330 M6 MOTORWAY

COAST TO COAST FOOTPATH

305

360

315 Four Ways House, Tel: +44 (0) 161 236 2757

325 310 310 57 Hilton Street, 355 Fax: +44 (0) 161 236 7029 Manchester, Email: [email protected] M1 2EJ. 00 05/07/2018 FIRST ISSUE CN DL DL 335 Web: www.rsk.co.uk

340

Rev. Date Amendment DrawnChkd. Appd. Client

330 305

350 320 TATA Steel UK Ltd. 345

330 330 335 325 320 Section of low cliff to be

retained. 330 335 325 WATERS Project Title

FARM 330 Client Proposed bund and Levels raised to match Shap Fell Quarry hibernacula for Great SSSI to the south. 330 TATA STEEL UK LTD

Crested Newts, 320

amphibians and reptiles.

325 Project Title 300

Drawing Title SHAP FELL QUARRY Restoration Plan 325

320 Drawing Title

300 RESTORATION SHAP 305 Drawn Date Checked Date MASTERPLANApproved Date FELL CN 06\07\18 DL 06\07\18 DL 06\07\18 WORKS 315 Drawn Date Checked Date Approved Date Scale: NTS CNOriginal 05/07/18 Size DL 05/07/18Status DL 05/07/18 Existing access track to A1 For Issue 320 ODDENDALE Scale Orig Size Status be reduced in width to 3m Scale as shown A1 DRAFT Drawing No. Rev. to enable maintenance 661739_04_02 Drawing No. 02 Rev. access. 661739_04_02 00 File Path RSK(MLs)661739_04_02

Scale as shown 0 50 100 150 200 250 300m

Source:Source: Esri, Esri, DigitalGlobe, DigitalGlobe, GeoEye, Earthstar GeoEye, Geographics, Earthstar CNES/Airbus Geographics, DS, USDA, USGS, CNES/Airbus AeroGRID, IGN, DS, and the USDA, GIS user USGS, communit yAeroGRID, (2018). IGN, and the GIS user community (2018). LEGEND LEGEND Quarry boundary Shap Fell Quarry planning application boundary Proposed Contours

Shap Fell Works boundaryPreviously restored areas of quarry

Existing Public Right of Way (PRoW) Existing Contours HARDENDALE Proposed footpath New Contours Proposed semi-improved grassland and basic finish slope Cliff edge

Section of cliff to be 320 Proposed bare ground retained. Previously restored areas of quarry Proposed gravel island

Existing Public RightProposed of Way mixed native woodland Proposed native woodland species mix: 305 25% Quercus petraea (Sessile Oak) Proposed ephemeral marsh/ shallow scrape 310 Proposed footpath 15% Fagus sylvatica (Beech)

10% Acer campestre (Field Maple) 315 315 310 Proposed semi-improved grassland and basic flush slope 5% Carpinus betulus (Hornbeam)

10% Betula pendula (Silver Birch) 320 Proposed bare ground 10% Pinus sylvestris (Scots Pine) 325 15% Sorbus aucuparia (Mountain Ash) Proposed gravel islands 10% Crataegus monogyna (Hawthorn) 305

Proposed mixed native woodland 350

330 320 Proposed ephemeral marshy/shallow scrape 355 Section of cliff to be retained.

325 Proposed footpath to link public rights of way.

315

325

HARDENDALE365 NAB

355 310

335 Existing waterbody

305 360 340

310 305

320 Indicative wet flush flows 02 23/08/18 THIRD ISSUE CN DL DL 01 03/08/18 SECOND ISSUE CN DL DL during heavy rainfall. 350 00 06/07/18 FIRST ISSUE CN DL DL 345

330 Rev. Date Amendments N Drwn Chkd Appd

320

THE NAB 325

365 305

360

335 330 M6 MOTORWAY

COAST TO COAST FOOTPATH

305

360

315 Four Ways House, Tel: +44 (0) 161 236 2757

325 310 310 57 Hilton Street, 355 Fax: +44 (0) 161 236 7029 Manchester, Email: [email protected] M1 2EJ. 00 05/07/2018 FIRST ISSUE CN DL DL 335 Web: www.rsk.co.uk

340

Rev. Date Amendment DrawnChkd. Appd. Client

330 305

350 320 TATA Steel UK Ltd. 345

330 330 335 325 320 Section of low cliff to be

retained. 330 335 325 WATERS Project Title

FARM 330 Client Proposed bund and Levels raised to match Shap Fell Quarry hibernacula for Great SSSI to the south. 330 TATA STEEL UK LTD

Crested Newts, 320

amphibians and reptiles.

325 Project Title 300

Drawing Title SHAP FELL QUARRY Restoration Plan 325

320 Drawing Title

300 RESTORATION SHAP 305 Drawn Date Checked Date MASTERPLANApproved Date FELL CN 06\07\18 DL 06\07\18 DL 06\07\18 WORKS 315 Drawn Date Checked Date Approved Date Scale: NTS CNOriginal 05/07/18 Size DL 05/07/18Status DL 05/07/18 Existing access track to A1 For Issue 320 ODDENDALE Scale Orig Size Status be reduced in width to 3m Scale as shown A1 DRAFT Drawing No. Rev. to enable maintenance 661739_04_02 Drawing No. 02 Rev. access. 661739_04_02 00 File Path RSK(MLs)661739_04_02

Scale as shown 0 50 100 150 200 250 300m

Source:Source: Esri, Esri, DigitalGlobe, DigitalGlobe, GeoEye, Earthstar GeoEye, Geographics, Earthstar CNES/Airbus Geographics, DS, USDA, USGS, CNES/Airbus AeroGRID, IGN, DS, and the USDA, GIS user USGS, communit yAeroGRID, (2018). IGN, and the GIS user community (2018).

7 Phasing plan The completion of each phase will be followed by a five year aftercare period, within which the restoration process will be carefully monitored. It is also proposed to undertake an The plans below show how the sensitive and progressive restoration plan can be annual site walkover, attended by delivered in phases. Although the full restoration is expected to take 18 years, the technical experts including the County vast majority of the land will be restored and returned to the landowner in the next Council’s appointed Ecologist and ten years. Geotechnical specialist. This will help to track the progress of the restoration. The phasing has been designed to restore the slope areas safely, avoiding winter periods where possible to respect local ecology such as wintering birds. Weekend activity will also be avoided where possible, to limit any disturbance to neighbours.

In summary the phases are expected to come forward as follows:

LEGEND

Shap Fell Quarry planning application boundary Existing HARDENDALE Phase 1 HARDENDALE Shap Fell Works boundary LEGEND

Phased Areas Shap Fell Quarry planning application boundary Existing HARDENDALE Phase 1 HARDENDALE Existing Contours Shap Fell Works boundary

New Contours Phased Areas

Cliff edge Existing Contours

1 Previously restored areasPhase of quarry 1 New Contours HARDENDALE NAB HARDENDALE NAB Existing Public Right of Way Cliff edge

1 Proposed footpath It is anticipated that the first phase (8.5 Previouslyha) restoredwill areas of quarrybegin in HARDENDALE NAB Proposed semi-improved grassland and basic flush slope HARDENDALE NAB Existing Public Right of Way

THE NAB THE NAB Proposed bare ground 2018/2019, enter the aftercare period inProposed 2021 footpath and return M6 MOTORWAY M6 MOTORWAY COAST TO COAST FOOTPATH COAST TO COAST FOOTPATH Proposed gravel islands Proposed semi-improved grassland and basic flush slope

THE NAB THE NAB Proposed mixed native woodlandto the landowner by 2026. Proposed bare ground M6 MOTORWAY M6 MOTORWAY COAST TO COAST FOOTPATH COAST TO COAST FOOTPATH Proposed ephemeral marshy/shallow scrape Proposed gravel islands

WATERS WATERS FARM FARM Levels raised to match SSSI Levels raised to match SSSI Proposed mixed native woodland to the south. to the south.

Proposed ephemeral marshy/shallow scrape

WATERS WATERS FARM FARM Levels raised to match SSSI Levels raised to match SSSI to the south. to the south.

SHAP SHAP FELL FELL WORKS WORKS

ODDENDALE ODDENDALE

01 23/08/18 SECOND ISSUE CN DL DL SHAP SHAP FELL FELL 00 02/08/18 FIRST ISSUE PC DL DL WORKS WORKS

ODDENDALE Rev. Date Amendments Drwn Chkd Appd ODDENDALE

01 23/08/18 SECOND ISSUE CN DL DL

00 02/08/18 FIRST ISSUE PC DL DL

Phase 2 HARDENDALE Phase 3 HARDENDALE Rev. Date Amendments Drwn Chkd Appd

Four Ways House, Tel: +44 (0) 161 236 2757 Phase 2 HARDENDALE Phase57 Hilton3 Street, HARDENDALE LEGEND Fax: +44 (0) 161 236 7029 Manchester, Email: [email protected] M1 2EJ. Web: www.rsk.co.uk Shap Fell Quarry planning application boundary Existing HARDENDALE Phase 1 HARDENDALE Four Ways House, Tel: +44 (0) 161 236 2757 Client 57 Hilton Street, Fax: +44 (0) 161 236 7029 Shap Fell Works boundary Manchester, Email: [email protected] TATA Steel UK Ltd. M1 2EJ. Web: www.rsk.co.uk Phased Areas 1 1 Phase 2 Client Existing Contours HARDENDALE NAB HARDENDALE NAB TATA Steel UK Ltd. 1 Project Title New Contours It is anticipated that1 the second phase (11.97 ha) will begin

Cliff edge HARDENDALE NAB Shap Fell Quarry HARDENDALE NAB

1 Project Title THE NAB THE NAB Previously restored areas inof quarry 2022, with the land expected to go into aftercare in 2024. 2 2

M6 MOTORWAY HARDENDALE NAB M6 MOTORWAY HARDENDALE NAB Shap Fell Quarry COAST TO COAST FOOTPATH COAST TO COAST FOOTPATH Existing Public Right of Way

Drawing Title THE NAB THE NAB Proposed footpath This will result in the complete restoration of the land in 2029. 2 2 Phasing Plan M6 MOTORWAY M6 MOTORWAY COAST TO COAST FOOTPATH COAST TO COAST FOOTPATH Proposed semi-improved grassland and basic flush slope Drawing Title THE NAB THE NAB 3

WATERS WATERS Proposed bare ground FARM FARM Phasing Plan M6 MOTORWAY M6 MOTORWAY COAST TO COAST FOOTPATH Levels raised to match SSSI COAST TO COAST FOOTPATH Levels raised to match SSSI to the south. to the south. Drawn Date Checked Date Approved Date PC 02\08\18Proposed gravelDL islands 02\08\18 DL 02\08\18 3

WATERS Scale: NTSWATERS Original Size Status FARM FARMProposed mixed native woodland Levels raised to match SSSI A1 For Issue Levels raised to match SSSI to the south. to the south. Drawn Date Checked Date Approved Date PC 02\08\18 DL 02\08\18 DL 02\08\18 Drawing No. Proposed ephemeral marshy/shallow scrape Rev. SHAP SHAP 661739_04_05 01 FELL WATERS FELL WATERS Scale: NTS Original Size Status WORKS FARM WORKS FARM A1 For Issue Levels raised to match SSSI Levels raised to match SSSI to the south. ODDENDALE to the south. ODDENDALE Drawing No. Rev. SHAP SHAP 661739_04_05 01 FELL FELL WORKS WORKS

ODDENDALE ODDENDALE Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS user community (2018). SHAP SHAP FELL FELL WORKS WORKS

ODDENDALE ODDENDALE Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS user community (2018). 01 23/08/18 SECOND ISSUE CN DL DL

00 02/08/18 FIRST ISSUE PC DL DL

Rev. Date Amendments Drwn Chkd Appd

Phase 2 HARDENDALE Phase 3 HARDENDALE

Four Ways House, Tel: +44Phase (0) 161 236 2757 3 57 Hilton Street, Fax: +44 (0) 161 236 7029 Manchester, Email: [email protected] M1 2EJ. Web: The www.rsk.co.uk third phase (10.95 ha) will take place across the full duration Client

TATA Steel UK Ltd.

1 1 of the restoration. The aftercare period will be staggered over the

HARDENDALE NAB HARDENDALE NAB Project Title final 5 years, with completion expected in 2037. Shap Fell Quarry

THE NAB THE NAB 2 2

M6 MOTORWAY M6 MOTORWAY COAST TO COAST FOOTPATH COAST TO COAST FOOTPATH Drawing Title The timescales provided are indicative and could be affected Phasing Plan

3 by changing ecological and weather conditions. WATERS WATERS FARM FARM Levels raised to match SSSI Levels raised to match SSSI to the south. to the south. Drawn Date Checked Date Approved Date PC 02\08\18 DL 02\08\18 DL 02\08\18

Scale: NTS Original Size Status A1 For Issue

Drawing No. Rev. SHAP SHAP 661739_04_05 01 FELL FELL WORKS WORKS

ODDENDALE ODDENDALE

Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS user community (2018).

Shapfell Quarry 8 Public Consultation: Revised Restoration Plans Technical details

The draft restoration plan has been informed by a number of technical studies, as well as the existing conditions and parameters of the site.

Some of these are summarised below.

Environmental designations Part of the south-eastern corner is located within the Fell Site of Specific Scientific Interest (SSSI). The draft restoration plan has been designed to improve the quality of habitat within and adjacent to the SSSI.

Transport and highways Following the very limited activity at the Quarry post-2009, Tata Steel has continued to develop the use of rail where possible for both imported and outgoing products. The vast majority of Tata Steel’s product is transported by rail. All operations are expected to continue as normal. Neighbours to the Quarry site are very important, so Tata Steel will continue to actively monitor and work with the local authorities to ensure this activity is kept at a safe level.

Landscape and visual impact A Landscape Management Plan will be implemented to ensure that the landscape is restored effectively. Technical and survey work that has already been undertaken indicates that the restoration will improve the quality of the existing habitat within the Quarry boundaries, as well as some of the areas adjacent to it.

As the restoration will be phased, the changes to the landscape and the visual impact these will have will be incremental. As the site is not located close to a residential area, the visual impact will be primarily limited to the Public Right of Way (PRoW) network located within the local area. The quarry will be most visible from relatively short duration views from the PRoW in the Yorkshire Dales National Park to the east of the site.

It is our expert’s view that the revised restoration scheme will ultimately have a beneficial landscape and visual impact on the area.

Air quality / noise An air quality management plan focussing on dust control will be developed in liaison with the County Council, and this will include the appropriate mitigation measures.

In the long term, restoring the quarry to a more natural environment will have beneficial effects on dust levels in the local area.

As the site is located in a rural area with just a few residential properties nearby, any noise impacts will be kept to a minimum level for these properties. A Noise and Vibration Management Plan (NVMP) will be developed as advised by the County Council to ensure that the appropriate mitigation takes place.

9 Tata Steel in the community

Tata Steel is a major employer in the local area, employing around 50 local staff at Shapfell. It contributes to the regional economy in business rates each year and over the years have donated approximately £15,000 to local schools and community projects.

The Tata Steel Shapfell team has been actively engaged with the local communities in and around Shap and the local villages for a number of years, providing donations and support to local worthy and charitable causes, and undertaking volunteer work.

Some examples include:

• Donating stone and several weeks of volunteer support to help create a local memorial garden in Shap village

• Supporting local schools – including donating prizes and money to support IT developments at Shap C of E Primary School, a dragon competition used to acknowledge our links to South Wales steelmaking, a donation to help Orton C of E Primary School install a sound system, and a donation towards a cycle shelter to help encourage cycling to school

• The installation (with Hanson) of an electronic speed sign in the village

• Providing stone and labour on a project to build a cairn linking Scotland and

• Providing stone to build defences against local river bank flood erosion

• A donation towards a sensory room at James Rennie School in Carlisle

• Other volunteer work - including helping with young enterprise initiatives at local schools and helping at triathlons.

Shapfell Quarry 10 Public Consultation: Revised Restoration Plans Next steps

Tata Steel and its project team of specialists are Tell us what you think undertaking a number of technical surveys to help inform the plans. There are a number of ways you can get in touch. You can: We would like to hear what you think of the plans and if you have any thoughts on how they can be improved. • Complete the feedback postcard provided in this brochure and send via Freepost This brochure is also available to view in digital form on • Email us at [email protected] the website www.shapfellconsultation.co.uk along with the answers to some Frequently Asked Questions. • Visit the website at www.shapfellconsultation.co.uk • Call us on Freephone 0808 168 8296

Please ensure feedback is received by Tuesday 25th September 2018

Please note that this consultation relates only to the restoration scheme area.

Your feedback

Q1: I support the updated restoration plan Q5: Do you have any further comments? Please use the space provided.

Q2: I believe that the updated plans will improve and enhance the area

Q3: I agree that Shapfell Quarry makes a valuable contribution to the Please tick here if you would like to attend one of the open events. local area Please ensure you provide an email address or phone number so we can contact you to confirm. Tuesday 18th September Monday 24th September

Q4: Tata Steel is keen to continue playing an active role in the community. If you would like us to keep in touch with you please add your Do you have any suggestions or ideas of how Tata Steel can do this? details below. Name ...... Address ...... Postcode ...... Email ...... Phone ......

The information you provide will be used only for the purposes of keeping you informed about the project and for understanding public opinion on the project. It will be stored securely until determination of the project. Following determination, this information will be deleted. Your information will be shared only with Tata Steel and the relevant local authority where there is a legal obligation to do so. It will not be forwarded on to a third party. You can contact us at any time to request the deletion of your information. Please contact us at [email protected] What happens next

We will carefully consider all feedback received while preparing the updated restoration plans and aim to submit the Section 73 applications to Cumbria County Council later this year. Upon completion of the restoration the land will be returned to the landowner.

Come and meet us

If you would like to find out more about how Shapfell If you would like to attend one of these open events is currently operated or ask us any questions about please ensure you register your interest in advance. the proposed restoration plan, we are holding several You can do this on the website, by emailing open events at the offices at the Shapfell Works site. [email protected], by calling 0808 168 8296 or by returning the postcard The events will take place on: provided. We will contact you directly in advance of your preferred event with further details. Tuesday 18th September 2018 between 1 - 3pm & 5.30 – 7.30pm We thank you for reading this brochure and are grateful for your time. If you have any questions Monday 24th September 2018 please do not hesitate to contact us. between 1 - 3pm & 5.30 – 7.30pm

Shapfell Quarry Consultation Freepost RTEH-HCTJ-RRBK Turley 1 New York Street Manchester M1 4HD