ENVIRONMENTAL SCOPING REPORT (ESR)

Photo for illustration only (Karibib Police Station)

ENVIRONMENTAL SCOPING REPORT (ESR) FOR A FUEL STORAGE FACILITY (DIESEL DEPOT = 92 CUBIC), ON ERF 163, LAFRENZ, WINDHOEK

October 2020

Tortoise Environmental Consultants(TEC)

DOCUMENT INFORMATION

Environmental Scoping Report (ESR) for a Diesel Depot Title (92 cubic) on Erf 163, Lafrenz, Windhoek

ECC Application APP - 001941 Reference number Listed Activity Activity 9.4 Storage and Handling of Dangerous Good

The storage and handling of a dangerous goods, including petrol, diesel, liquid petroleum gas or paraffin, in containers with a combined capacity of more than 30 cubic meters at any location

Erf 163, Lafrenz, Windhoek Location Proponent Ocean Bunker Petroleum Services Contact person: Charlet P.O. Box 98414 Pelican Square, Windhoek Tel: +264 Mobile: +264 813754566 E-mail: [email protected] Author: Signature Date 08 October 2020 Mr. Ipeinge Mundjulu (EAP)1

Reviewer: 12 October 2020 Mr. Jonas Heita (EAP)

Copy Right: “This document may only be used for the intended purpose. Unauthorized use, duplication, plagiarism or copying without referencing is prohibited”

1 EAP – Environmental Assessment Practitioner

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek

Tortoise Environmental Consultants(TEC)

ACRONYMS ACRONYMS

BID Background Information Document DEA Department of Environmental Affairs DSR Draft Scoping Report EA Environmental Assessment EAP Environmental Assessment Practitioner ECC Environmental Clearance Certificate ECO Environmental Compliance Officer EIA Environmental Impact Assessment EMA Environmental Management Act (No. 7 of 2007) EMP Environmental Management Plan I&APs Interested and Affected Parties MEFT Ministry of Environment, Forestry and Tourism PPE Personal Protective Equipment SM Site Manager TEC Tortoise Environmental Consultants

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek

Tortoise Environmental Consultants(TEC) Table of Contents 1. INTRODUCTION ...... 1 1.1. Terms of Reference...... 1 1.2. What is an EIA? ...... 1 1.3. EIA Process ...... 1 1.4. Identification and Mitigation of Impacts ...... 1 1.5. Purpose of the EIA Scoping Exercise ...... 1 1.6. Rehabilitation ...... 2 1.7. Scope and Purpose of this Report ...... 2 1.8. Alternatives Considered ...... 2 1.9. Environmental versus Economic Development ...... 3 1.10. Application for ECC ...... 4 1.11. Environmental Assessment Practitioner ...... 4 2 PROJECT INFORMATION...... 5 2.1 Project Location ...... 5 2.2 Site Layout ...... 6 2.3 Proposed Tank Design ...... 7 3 LEGAL and developmental FRAMEWORK ...... 8 3.1 Compliance to the EMP to the Environmental Management Act ...... 8 3.2 Listed Activities ...... 8 3.3 Extended developmental and Legal Framework ...... 9 4 IMPACT ASSESSMENT METHODOLOGY ...... 11 4.1 Assessment of Impact Significance ...... 11 4.2 Impact Assessment Criteria ...... 11 4.3 Mitigation Measures ...... 12 4.4 Mitigation Hierarchy...... 13 5 ENVIRONMENTAL IMPACT ASSESSMENT ...... 14 5.1 Landscape Alteration ...... 14 5.2 Access Roads ...... 14 5.3 Oil Spills (Pollution) ...... 15 5.4 Pollution: Noise and Dust ...... 15 5.5 Socio-Economic Environment ...... 16 6 PUBLIC PARTICIPATION PROCESSESS ...... 17 6.1 Local Authority Consultation ...... 17 6.2 Public Meeting ...... 17

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek

Tortoise Environmental Consultants(TEC) 7 CONCLUSION and Recommendation ...... 18 8 References ...... 18 9 APPENDICES...... 18 9.1 Background Information Document (BID) ...... 18 9.2 Newspaper Adverts ...... 18 9.3 Comments and Response Report...... 18 9.4 EAP CV ...... 18 9.5 Environmental Management Plan (EMP) ...... 18

FIGURES

Figure 2-1: Overview Location of the fuel storage facility ...... 5 Figure 2-3: Existing infrastructure of the proposed diesel depot, Erf 163, Lafrenz, Windhoek 5 Figure 2-5: Site Layout for Diesel depot, Erf 163, Lafrenz, Windhoek ...... 6 Figure 2-6: Proposed Tank Design for the Diesel depot, Erf 163, Lafrenz, Windhoek ...... 7 Figure 4-1.Mitigation Hierarchy ...... 13

TABLES

Table 1-1. Project alternatives ...... 2 Table 3-1: Listed Activities triggered by the proposed project ...... 9 Table 3-2: Policies, Plans and Strategies ...... 9 Table 4-1: Assessment criteria for the evaluation of impacts ...... 11

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek

Tortoise Environmental Consultants(TEC) 1. INTRODUCTION

1.1. Terms of Reference

Ocean Bunker Petroleum Services hereby submit an application for an Environmental Clearance Certificate (ECC) for the proposed construction of a Diesel Depot (92 cubic).

The proposed fuel storage facility (diesel depot) is located on Erf. 163, Lafrenz, Windhoek (figure 2.1).

GPS coordinates: Latitude: -22.50856817 & Longitude: 17.06715641

1.2. What is an EIA?

An Environmental Impact Assessment (EIA) is a tool to manage negative environmental impacts that may arise from the proposed development and is aimed at guiding the proposed activities to be more environmental friendly and to comply with the provisions of the Environmental Management Act (Act No.7 of 2007).

The aim of the EIA is to reduce negative impacts (effects) and maximize positive impacts, through the adoption of best environmental practices and application of the precautionary principle

1.3. EIA Process

An EIA is a systematic process of identifying, predicting, evaluating and mitigating the potential environmental and social effects that may arise from the activities of a proposed project.

1.4. Identification and Mitigation of Impacts

The backbone of the EIA report entails identification of impacts (whether real or perceived) and recommendations on suitable mitigation measures to ensure compliance with the principles of environmental management and highlight risks and measures to ensure an environmentally friendly development.

1.5. Purpose of the EIA Scoping Exercise

The purpose of this EIA scoping exercise is to:

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek 1

Tortoise Environmental Consultants(TEC)

a) Provide description of the proposed activity; b) Describe the affected environment (proposed area), a) Identify potential environmental impacts / aspects of concern; b) Describe the methodology followed to assess the potential impacts; c) Mitigate negative impacts that may arise from the proposed project

1.6. Rehabilitation

The EIA should not only focus on mitigating the impacts of the activity during the active operations but also should go further and recommend rehabilitation measures at project closure (when activities cease). Rehabilitation measures should not be parked waiting for project closure but should be implemented form the beginning and incrementally throughout the project lifespan.

1.7. Scope and Purpose of this Report

The purpose of this report is to present the findings of the EIA for the proposed fuel storage facility activities, as part of the application of the Environmental Clearance Certificate (ECC).

The environmental assessment has been undertaken in accordance with the requirements of the Environmental Management Act, 2007 and the EIA Regulations.

1.8. Alternatives Considered

As stipulated in the Environmental Management Act (EMA) and EIA regulations, alternatives should be considered during the project design, to determine if an alternative site (different locality) or alternative project (different activity), or alternative design would yield better environmental and socio-economic benefits.

Table 1-1. Project alternatives

Description Chosen Alternative Advantages Disadvantage Option

“Early Detection of Leaks – • The tank can For the Above The biggest advantage of be vandalized company to ground fuel an Above Ground Fuel if not protected Yes install a fuel tank Storage Tank is that visual storage tank • The tank can inspections are possible as be prone to

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek 2

Tortoise Environmental Consultants(TEC) above the opposed to an physical ground underground storage tank damage such where a leak can go as wind rain, undetected for a long time lighting etc. if not properly Easy Access for installed. Inspections & Replacement – The installation of above ground tank at project site enable for regular inspection and maintenance. ‘Furthermore an Above Ground Fuel Storage Tank can be moved from one location to another location if a business relocates. • Difficult to monitor for leakages • Can cause underground For the • Not prone to vandalism, pollution for a company to physical destruction such Underground long time before install a fuel as wind, rain lighting or fuel tank leakages are storage tank any other physical detected under ground damages • Difficult and expensive to relocate if the need arises

1.9. Environmental versus Economic Development

Namibia’s economy is highly dependent on a healthy environment and striking a balance in meeting demands for economic development (e.g fuel storage facility) and maintaining biological diversity can be a challenge. Therefore, it is of utmost importance that the environment and development sectors should work together and identify synergies.

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek 3

Tortoise Environmental Consultants(TEC) Development takes place on land (in the environment) and hence the quest for economic development requires a trade-off with certain parts of the environment in-order for the development to be realized. Meaning, for development to take place, some part of the environment will be affected. However, it is of utmost importance that such impacts are mitigated through the EMP.

The aim of environmental assessments is to guide the proposed fuel storage facility (diesel depot) and to mitigate potential negative impacts that may arise (e.g soil and ground water pollution).

1.10. Application for ECC

Upon completion, the EIA Scoping Report and Environmental Management Plan (EMP), will be submitted to the Environmental Commissioner in the Ministry of Environment, Forestry and Tourism (MET), for review and decision, in accordance with Section 8 of the EIA Regulations.

1.11. Environmental Assessment Practitioner

Tortoise Environmental Consultants (TEC) has been appointed to carry out the requisite Environmental Impact Assessment (EIA) and develop an Environmental Management Plan (EMP).

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek 4

Tortoise Environmental Consultants(TEC) 2 PROJECT INFORMATION

2.1 Project Location

The fuel storage facility fuel storage facility is located within the town boundaries, albeit on the outskirts of the current township infrastructure development (figure 2.1).

Figure 2-1: Overview Location of the fuel storage facility

Figure 2-2: Existing infrastructure of the proposed diesel depot, Erf 163, Lafrenz, Windhoek

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek 5

Tortoise Environmental Consultants(TEC) 2.2 Site Layout

E R F 1 6 2

C

O

S

N D I E S E L T A N K 2

T D I E S E L T A N K 1

T

O

A

R

I

N

E

E

W

R

A S

R

E P D

H U

I

O E

M

U S

P

E

S L

E 2

E

E

R

R

F

F

6

1

4

6

2

1

E

6

R

3

F

P

D

U

I

E

M

S

P

E

L

1

P

D

U

I

E

M

S

P

E

L 3

O F F I C E S & T O I L E

C O N T A I N E R S T S

G

O

L

(

O

P

R

I

L

P

E

/

D

A

A

R

N

I

S

O

E

E

F

S

O

E

C

R

E

L

R

A

P

/

T

T

R

C

E

O

H

I

P

F

N

I

O

S

T

Z

1

E

N

6

D

-

O

3

W

N

F

-

I

E

R

N

E

W

E

D

R

M M

R E N E N D

X H

F S A B U R U D G E R S I N T N

R E E T S

D

H

I T

O T R U C K S

C

I

6

I

O

N

I

E

P

S

L

G E

5 O U T

E

A

S

L

B

)

K

E

U

L R

T R U C K S D

G I N

E

E

P

R

O

S

T

T R

. Figure 2-3: Site Layout for Diesel depot, Erf 163, Lafrenz, Windhoek

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek 6

Tortoise Environmental Consultants(TEC) 2.3 Proposed Tank Design

Design Data Design Standard SANS 10131:2004 Shell Material 6mm SANS 50025-2 GrS355JR Flanges ANSI B 16.5 150ASA Mild Steel Piping SANS 62-1 & SANS 62-2 Leak Test 45 kPa Internal Pneumatic Pressure External Surface Preparation Sandblast SA 2.5 External Coating Paint - Forgeweld Gray External Surface Coating Test DFT @ 75µm Gaskets 3mm Non-asbestos Fibre Ring Tank Volume (Calculated) ±23.24 m3 Tank Weight (Calculated) ±3220 kg Overall Length (Calculated) ±5510 mm

DO NOT SCALE DRAWING REVISION 01

NAME SIGNATURE DATE PROPRIETARY AND CONFIDENTIAL DRAWN THE INFORMATION CONTAINED IN THIS P Pienaar PHP 10/5/2016 DRAWING IS THE SOLE PROPERTY OF FORGEWELD (PTY) LTD. ANY CHKD J Mataboge JM 10/5/2016 REPRODUCTION IN PART OR AS A WHOLE WITHOUT THE WRITTEN PERMISSION OF FORGEWELD (PTY) LTD IS PROHIBITED. APPV

TITLE: DWG NO. A3 FORGEWELD STD - 23kL AST BFTANK135-rev1 3D View SHEET 1 OF 6

Design Data Design Standard SANS 10131:2004 Shell Material 6mm SANS 50025-2 GrS355JR Flanges ANSI B 16.5 150ASA Mild Steel Piping SANS 62-1 & SANS 62-2 Leak Test 45 kPa Internal Pneumatic Pressure External Surface Preparation Sandblast SA 2.5 External Coating Paint - Forgeweld Gray External Surface Coating Test DFT @ 75µm Gaskets 3mm Non-asbestos Fibre Ring Tank Volume (Calculated) ±46.03 m3 Tank Weight (Calculated) ±5420 kg Overall Length (Calculated) ±10910 mm

DO NOT SCALE DRAWING REVISION 01

NAME SIGNATURE DATE PROPRIETARY AND CONFIDENTIAL DRAWN THE INFORMATION CONTAINED IN THIS P Pienaar PHP 3/11/2016 DRAWING IS THE SOLE PROPERTY OF FORGEWELD (PTY) LTD. ANY CHKD J Mataboge JM 3/11/2016 REPRODUCTION IN PART OR AS A WHOLE WITHOUT THE WRITTEN PERMISSION OF FORGEWELD (PTY) LTD IS PROHIBITED. APPV

TITLE: DWG NO. FORGEWELD STD - 46kL AST LONG BFTANK275-rev1 A3

3D View SHEET 1 OF 7

Figure 2-4: Proposed Tank Design for the Diesel depot, Erf 163, Lafrenz, Windhoek

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek 7

Tortoise Environmental Consultants(TEC) 3 LEGAL AND DEVELOPMENTAL FRAMEWORK

This chapter outlines the regulatory framework applicable to the proposed project. Table 2 provides an overview of applicable policies, plans and strategies and Table 3.1 provides a list of applicable legislation in .

3.1 Compliance to the EMP to the Environmental Management Act

Section 27 of the Environmental Management Act 2007 (Act No. 7 of 2007) (EMA) provides a list of activities that may not be undertaken without an Environmental Clearance Certificate (ECC) (herein referred to as: listed activities). The proposed expansion of the hospital triggers the following listed activities.

The EMP should conform to the provisions of the Environmental Management Act (EMA), Act No. 7 of 2007 and EIA regulations of 2012 (Government Notice: 30).

The EIA Regulations defines a ‘Management Plan’ as:

“…a plan that describes how activities that may have significant impacts on the environment are to be mitigated controlled and monitored.”

3.2 Listed Activities

Listed Activities may not be undertaken without an Environmental Clearance Certificate (ECC), and hence an Environmental Impact Assessment (EIA) is required.

As the organ of state responsible for management and protection of its natural resources, the MET: DEA is committed to pursuing the principles of environmental management. The EMA provides a list of activities that require an EIA and the proposed fuel storage facility is among the listed activities or activities that may not be conducted without at ECC. The purpose of listed activities for projects is to ensure that the associated impacts on the environment are carefully considered.

The proposed continuation of fuel storage facility triggers a number of Listed Activities as set out in the Environmental Management Act, 2007 (Act No. 7 of 2007) (herein referred to as the EMA) and the Environmental Impact Assessment Regulation, 2007 (No. 30 of 2011) (herein referred to as the EIA Regulations).

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek 8

Tortoise Environmental Consultants(TEC)

Table 3-1: Listed Activities triggered by the proposed project

Activity Description of the Activity Operation of the Activity Activity 9.4 The storage and handling of a The project entails the Storage and dangerous goods, including petrol, handling and storage Handling of diesel, liquid petroleum gas or paraffin, of dangerous good. Dangerous in containers with a combined capacity Good of more than 30 cubic meters at any location.

3.3 Extended developmental and Legal Framework

In addition to the EMA and the Environmental Assessment Policy, there exists a host of legal and policy documents and guidelines that must be considered when undertaking an EIA as indicated in table 3.2, below. The proponent has the responsibility to ensure that the fuel storage facility operations conforms to all other National developmental plans and legal framework.

Table 3-2: Policies, Plans and Strategies

Policy / Plan Relevance Applicability to the Proposed Project 5th National Outlines the country’s The proposed project is a Development Plan National Development development that forms (NDP) and Vision Plans (NDPs), in line part of the bigger picture 2030 with the Harambee of achieving economic Prosperity Plan (HPP) progression, social and vision 2030 transformation and environmental sustainability.

Agriculture as a pillar for social well-being, through food production, household income and improved livelihoods

Table 3.2: Other Legal Instruments / National Statutes

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek 9

Tortoise Environmental Consultants(TEC) National Statutes Relevance Applicability to the Proposed Project Environmental Promotes Sustainable Environmental Assessment Policy development and Protection (1995) Environmental Conservation emphasize the importance of environmental assessments as a key tool towards environmental sustainability Soil Conservation, Makes provision for the Monitor and apply the 1969 (Act 76 of 1969) prevention and control of soil conservation and the Soil soil erosion mechanisms Conservation Amendment Act (Act 38 of 1971) Forest Act 12 of 2001 To provide for the Forestry permits maybe Forest Act protection of the required for vegetation Regulations 2015 environment and the clearing control and management of forest. Relevant sections: - Approval required for the clearance of vegetation on more than 15 hectares (Section 23, subsection 1 (b)). Public Health Act (Act Advocates for Public Health Personal Protective No. 36 of 1919) and safety Equipment (PPE) The Occupational Advocates for employee In the working context Safety and Health Act and public safety, health “SAFETY” implies “free No. 11 of 2007 from danger” Local Authority Act Advocates for inclusive Ensure communication No. 23 of 1992 socio-economic and necessary Government Notice of development approvals to township No.116 of 1992. developmental activities

National Heritage Act, The Act provides provision No heritage features No. 27 of 2004. of the protection and were observed within or conservation of places and around the site. objects with heritage Procedures and significance. mitigation measures presented in the EMP should be applied

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek 10

Tortoise Environmental Consultants(TEC)

4 IMPACT ASSESSMENT METHODOLOGY

4.1 Assessment of Impact Significance

The significance of an impact is determined by considering and measuring the temporal and spatial scales and magnitude of the project and the specific activities associated with the project.

The assessment of the environmental impacts of development activities should strive to be objective and impartial at all times. However, environmental assessment processes can be exposed to subjectivity inherent in attempting to measure significance.

The determination of the significance of an impact depends on both the context (spatial and temporal scale) and intensity of that impact.

4.2 Impact Assessment Criteria

For each impact, the EXTENT (spatial scale), MAGNITUDE and DURATION will be described. These criteria would be used to ascertain the SIGNIFICANCE of the impact, firstly in the case of no mitigation and then with the most effective mitigation measure/s in place. The mitigation described in the Scoping Report would represent the full range of plausible and pragmatic measures.

Table 4-1: Assessment criteria for the evaluation of impacts

CRITERIA CATEGORY DESCRIPTION National Beyond a 20km radius of the site

Regional Within a 20 km radius of the site

Extent or spatial influence of Local Within a 2 km radius of the centre of the site impact Site On site or within the boundaries of the

specific property Zero

Natural and/ or social functions and/ or High Magnitude of processes are severely altered impact (at the Natural and/ or social functions and/ or Medium indicated spatial processes are notably altered scale) Natural and/ or social functions and/ or Low processes are slightly altered

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek 11

Tortoise Environmental Consultants(TEC)

Natural and/ or social functions and/ or Very Low processes are negligibly altered Natural and/ or social functions and/ or Zero processes remain unaltered Zero Zero time

Short Term Up to 18 months Duration of Medium 0-5 years (after operation) impact Term Long Term 5- 10 years (after operation)

Permanent More than 10 years (after operation) Estimated greater than 95 % chance of the Definite impact occurring. Estimated 50 to 95% chance of the impact Very likely occurring Estimated 5 to 50 % chance of the impact Probability Fairly likely occurring. Estimated less than 5 % chance of the Unlikely impact occurring. Zero Definitely no chance of occurrence Wealth of information on and sound Certain understanding of the environmental factors potentially influencing the impact. Reasonable amount of useful information on and relatively sound understanding of Confidence Sure the environmental factors potentially influencing the impact. Limited useful information on and Unsure understanding of the environmental factors potentially influencing this impact. The activity will lead to an impact that is Irreversible permanent. Reversibility The impact is reversible, within a period of Reversible 10 years.

4.3 Mitigation Measures

For each impact assessed, mitigation measures should be identified to reduce and/ or avoid negative impacts. These mitigation measures are also incorporated in the Environmental Management Plan (EMP) to ensure that they are implemented throughout the lifespan of the proposed activity. The EMP forms part of the Scoping

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek 12

Tortoise Environmental Consultants(TEC)

Report, and upon project approval, the implementation thereof, would become a binding requirement.

4.4 Mitigation Hierarchy

Actions to mitigate a potential impact can be done in as systematic manner as guided by what is referred to as Mitigation Hierarchy (Figure 4.1).

From the onset, the positive impacts of the proposed activity should be enhanced, however, where an impact in is inevitable, the following sequence should be followed.

Impact avoidance: This step is most effective when applied at an early stage of project conceptualization and planning. It can be achieved by: ● Not undertaking certain projects or elements that could result in adverse impacts; ● Avoiding areas that are environmentally sensitive; and ● Putting in place preventative measures to stop adverse impacts from occurring. Impact minimisation: This step is usually taken during impact identification and prediction to limit or reduce the degree, extent, magnitude, or duration of adverse impacts. It can be achieved by: ● Scaling down or relocating the proposal; ● Redesigning elements of the project; and ● Taking supplementary measures to manage the impacts. Impact compensation: This step is usually applied to remedy unavoidable residual adverse impacts. It can be achieved by: ● Rehabilitation of the affected site or environment, for example, by habitat enhancement; ● Restoration of the affected site or environment to its previous state or better; and ● Replacement of the same resource values at another location (off-set), for example, by wetland engineering to provide an equivalent area to that lost to drainage or infill. Figure 4-1.Mitigation Hierarchy

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek 13

Tortoise Environmental Consultants(TEC) 5 ENVIRONMENTAL IMPACT ASSESSMENT

This section presents the potential impacts that may arise from the proposed fuel storage facility activities. The full mitigation measures are presented in the EMP.

5.1 Landscape Alteration

With the excavations and establishment of borrow pits, the fuel storage facility activity has potential to alter (change) the natural view of the landscape

IMPACT DESCRIPTION: Digging and Excavating Predicted for Excavations (specific activity) Dimension Rating Degree to Duration Permanent Reversibility: which Extent Site specific impact can Reversible Magnitude Low be mitigated: Probability Fairly likely High MITIGATION: • If possible rrehabilitate the site after construction

5.2 Access Roads

Establishment or creation of access roads to transport and from the borrow pit to the town.

IMPACT DESCRIPTION: Access Roads Predicted for Establishment of Road Tracks (specific activity) Dimension Rating Degree to Duration Permanent Reversibility: which Extent Site specific impact can Reversible Magnitude Low be mitigated: Probability Very likely High MITIGATION: • Use existing municipal access roads

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek 14

Tortoise Environmental Consultants(TEC) 5.3 Oil Spills (Pollution)

Soil pollution may occur as a result of oil leakages, fuel, or lubricants from the machinery and vehicles.

IMPACT DESCRIPTION Soil Pollution Predicted for (specific activity / Oil Leakages from Machinery project phase) Dimension Rating Degree to Duration Short-term Reversibility: which Extent Local impact can Reversible Magnitude Low be mitigated: Probability Definite Medium MITIGATION: • There must be an oil spill response kit on site. Workers should be properly trained on dangers oil pollutions and response actions; • If an oil spill occurs, collect the contaminated soil, store in drums or appropriate structures and dispose at approved waste disposal site; • Ensure all vehicles / machinery are well service, install drip trays and conduct regular leak inspection

5.4 Pollution: Noise and Dust

The proponent should ensure noise from excavator machinery and transportation trucks is kept below the recommended noise levels of -85dB (A).

IMPACT DESCRIPTION Noise and Dust Predicted for Extraction and transportations of the sand and (specific activity / concrete project phase) Dimension Rating Degree to Duration Short term Reversibility: which Extent Local impact can Reversible Magnitude Medium be mitigated: Probability Definite High MITIGATION: • Use dust suppression measures to mitigate dust impacts • Provide dust masks and ear muffs to machinery operators EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek 15

Tortoise Environmental Consultants(TEC)

5.5 Socio-Economic Environment

IMPACT DESCRIPTION Socio-economic Predicted for (specific activity / Development and Employment Opportunities project phase) Dimension Rating Degree to Duration Long and Short- term Reversibility: which Extent National & Local impact can Irreversible Magnitude Medium be mitigated: Probability Definite Medium MITIGATION: • Employ local labour as far as possible • Establish on the job training and other capacity development training programs

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek 16

6 PUBLIC PARTICIPATION PROCESSESS

Public consultation is a requirement by law (EMA No 7 of 2007) to be incorporated into an EIA process, hence it is a fundamental part of the EIA. Public consultation ensures robust decision making by involving Interested and Affected Parties (I&APs). The PPP has therefore been structured to provide I&APs an opportunity to gain more information on the proposed project and for them to provide inputs through the review of documents/reports, and to flag any issue of concern during the PPP process.

6.1 Local Authority Consultation

Consultations were done with the ORTC during the EIA field assessment exercise, through which due information and documentation were provided to the Environmental Assessment Practitioner (EAP).

6.2 Public Meeting

• The fuel storage facility activity is an already existing activity and the scoping exercise is more of a corrective measure to ensure compliance with the Environmental Management Act (Act. No,7 of 2007) and the Environmental Impact Assessment (EIA) regulations of 2012.

• No one registered as an Interested and Affected Party (I&AP)

• No one turned up at the meeting

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek 17

7 CONCLUSION AND RECOMMENDATION

An aboveground fuel tanks are common for business and farm operation. They are the most safest when it comes to handling of fuel. The proposed tank capacity is relatively small at 25 cubic meters. The aspect of oil spill, fire risk, tank leakage and land /water pollution are well addressed in the EMP. Henceforth, with the adequate implementation of this EMP, the operation of the proposed fuel tank will not pose any environmental threat.

This study recommends to the approving authority for the project to be approved and be issued with an environmental clearance certificate.

8 REFERENCES

Burke, A. (2011). Eleven Steps to Mining Rehabilitation, Windhoek, Namibia

Madyise, T. (2013) Case studies of environmental impacts of fuel storage facility and gravel extraction for urban development, Gaborone, Botswana

9 APPENDICES

9.1 Background Information Document (BID)

9.2 Newspaper Adverts

9.3 Comments and Response Report

9.4 EAP CV

9.5 Environmental Management Plan (EMP)

EIA Scoping Report – Erf 163, Diesel Depot, Lafrenz, Windhoek 18

BACKGROUND INFORMATION DOCUMENT (BID)

Design Data Design Standard SANS 10131:2004 Shell Material 6mm SANS 50025-2 GrS355JR Flanges ANSI B 16.5 150ASA Mild Steel Piping SANS 62-1 & SANS 62-2 Leak Test 45 kPa Internal Pneumatic Pressure External Surface Preparation Sandblast SA 2.5 External Coating Paint - Forgeweld Gray External Surface Coating Test DFT @ 75µm Gaskets 3mm Non-asbestos Fibre Ring Tank Volume (Calculated) ±23.24 m3 Tank Weight (Calculated) ±3220 kg Overall Length (Calculated) ±5510 mm

DO NOT SCALE DRAWING REVISION 01 NAME SIGNATURE DATE PROPRIETARY AND CONFIDENTIAL DRAWN P Pienaar 10/5/2016 THE INFORMATION CONTAINED IN T HIS PHP DRAWING IS THE SOLE PROPERTY OF FORGEWELD (PTY) LTD. ANY CHKD J Mataboge JM 10/5/2016 REPRODUCTION IN PART OR AS A WHOLE WITHOUT THE WRITTEN PERMISSION OF ENVIRONMENTALFO RGIMPACTEWELD (PTY) LTD IS PROHIBITED. ASSESSMENTAPPV (EIA) AND TITLE: DWG NO. A3 FORGEWELD STD - 23kL AST BFTANK135-rev1 ENVIRONMENTAL MANAGEMENT PLAN3D View (EMP) FORSHEET 1 O F 6 A DIESEL DEPOT (92 CUBIC), ON ERF 163, LAFRENZ, WINDHOEK

PROPONENT OCEAN BUNKER PETROLEUM SERVICES

September 2020

Tortoise Environmental Consultants(TEC)

DOCUMENT INFORMATION

Background Information Document (BID) for a Diesel Title Depot (92 cubic) on Erf 163, Lafrenz, Windhoek

ECC Application APP - 001941 Reference number Listed Activity Activity 9.4 Storage and Handling of Dangerous Good

The storage and handling of a dangerous goods, including petrol, diesel, liquid petroleum gas or paraffin, in containers with a combined capacity of more than 30 cubic meters at any location

Erf 163, Lafrenz, Windhoek Location Proponent Ocean Bunker Petroleum Services Contact person: Charlet P.O. Box 98414 Pelican Square, Windhoek Tel: +264 Mobile: +264 813754566 E-mail: [email protected] Author: Signature Date 19 September 2020 Mr. Ipeinge Mundjulu (EAP)1

Reviewer: 19 September 2020 Mr. Jonas Heita (EAP)

Copy Right: “This document may only be used for the intended purpose. Unauthorized use, duplication, plagiarism or copying without referencing is prohibited”

1 EAP – Environmental Assessment Practitioner

BID, Erf 163, Diesel Depot, Lafrenz, Windhoek

Tortoise Environmental Consultants(TEC)

TABLE OF CONTENT

1. PROJECT INFORMATION...... 1

1.1 Introduction...... 1

1.2 Purpose of the BID ...... 1

1.3 Background ...... 1

2. PROJECT INFORMATION...... 3

2.1 Project Location ...... 3

2.2 Site Layout ...... 3

2.3 Proposed Tank Design ...... 5

3. Compliance and LEGAL FRAMEWORK...... 6

3.1 Compliance to the EMP ...... 6

3.2 Environmental Management Act (No.7 of 2007) ...... 6

3.3 EMP Requirements ...... 6

3.4 Listed Activities ...... 7

4. THE EIA PROCESS ...... 8

4.1 EIA PROCESS FLOW ...... 8

4.1.1 Public Participation Process (PPP) ...... 9

4.1.2 Stakeholders Consultation Process ...... 10

4.1.3 The Importance Of Registration as an I&AP ...... 10

4.1.4 Registration as an I&AP ...... 10

BID, Erf 163, Diesel Depot, Lafrenz, Windhoek

Tortoise Environmental Consultants(TEC)

FIGURES

Figure 2-1: Propose Location of the diesel depot, Erf 163, Lafrenz, Windhoek ...... 3

Figure 2-2: Site Layout for Diesel depot, Erf 163, Lafrenz, Windhoek ...... 4

Figure 2-3: Proposed Tank Design for the Diesel depot, Erf 163, Lafrenz, Windhoek .... 5

Figure 4-1: EIA flow diagram ...... 8

TABLES

Table 3-1: EMP Requirements as outlined in Section 8 of the EIA Regulations ...... 6

Table 3-1: Listed Activities triggered by the proposed project ...... 7

BID, Erf 163, Diesel Depot, Lafrenz, Windhoek

Tortoise Environmental Consultants(TEC)

1. PROJECT INFORMATION

1.1 Introduction

Tortoise Environmental Consultancy (TEC) is undertaking an Environmental Impact Assessment (EIA) for the proposed construction of a Diesel Depot (92 cubic) on Erf 163, Lafrenz, Windhoek.

1.2 Purpose of the BID

The purpose of the Background Information Document (BID) is to provide a brief description of the proposed activity and to enable Interested and Affected Parties (I&AP’s) to participate in the EIA process, and comment on the environmental, social and economic aspects relating to the project.

As guided by the EIA regulations, the Public Participation Process (PPP) entails Newspaper adverts, site notices and distribution of the BID. If you have any comments to the proposed project, please send comments to: [email protected].

The BID contains:

a) brief description of the project b) Project location; c) The Public Participation Processes (PPP), as guided by the EIA regulations of 2012; d) Guidelines for stakeholder participation in the EIA process.

1.3 Background

The proponent (Ocean Bunker Petroleum Services) intends to construct a Diesel Depot (92 cubic) on Erf 163, Lafrenz, Windhoek.

In terms of the Environmental Management Act of 2007 (Act No. 7 of 2007) and the Environmental Impact Assessment Regulation (Government Notice No. 30 of 2012), the proposed project triggers the following listed activities that may not be undertaken without an Environmental Clearance Certificate hence the need for an EIA Scoping Excercise.

1 BID, Erf 163, Diesel Depot, Lafrenz, Windhoek

Tortoise Environmental Consultants(TEC)

Table 1: List of activities in the EIA regulation concerning the proposed project.

Activity Description of the Activity Operation of the Activity Activity 9.4 The storage and handling of a The project entails the Storage and dangerous goods, including petrol, handling and storage Handling of diesel, liquid petroleum gas or of dangerous good. Dangerous paraffin, in containers with a combined Good capacity of more than 30 cubic meters at any location. Activity 9.5 Construction of filling stations or any Construction of the Storage and other facility for the underground and service station Handling of aboveground storage of dangerous Dangerous goods, including petrol, diesel, liquid, Good petroleum, gas or paraffin Activity 10.1 (a) Oil, water, gas and petrochemical and Installation of Infrastructures other bulk supply pipelines; Municipal bulk services Activity 10.1 (b) Public roads To be upgraded to Infrastructures interlocked surface road

Given the above listed activities, the EIA process shall be undertaken to assess and determine the possible environmental, social and economic impacts that this project may arise from this project. As required under the provisions of the regulation 21 (2) (Government Notice No. 30 of 2012), a Background Information Document (BID) has been developed and disseminated to I&APs.

2 BID, Erf 163, Diesel Depot, Lafrenz, Windhoek

Tortoise Environmental Consultants(TEC)

2. PROJECT INFORMATION

2.1 Project Location

The proposed site for the Diesel depot is Erf 163, Lafrenz, Windhoek (figure 2.1).

Figure 2-1: Propose Location of the diesel depot, Erf 163, Lafrenz, Windhoek

2.2 Site Layout

3 BID, Erf 163, Diesel Depot, Lafrenz, Windhoek

Tortoise Environmental Consultants(TEC)

E R F 1 6 2

C

O

S

N D I E S E L T A N K 2

T D I E S E L T A N K 1

T

O

A

R

I

N

E

E

W

R

A S

R

E P D

H U I

O E

M

U S

P E

S L

E 2

E

E

R

R

F

F

6

1

4

6

2

1

E

6

R

3

F

P

D

U

I

E

M

S

P

E

L

1

P

D

U

I

E

M

S

P

E

L 3

O F F I C E S & T O I L E T

C O N T A I N E R S S

G

O

L

(

O

P

R

I

L

P

E

/

D

A

A

R

N

I

S

O

E

E

F

S

O

E

C

R

E

L

R

A

P

/

T

T

R

C

E

O

H

I

P

F

N

I

O

S

T

Z

1

E

N

6

D

-

O

3

W

N

F

-

I

E

R

N

E

W

E

D

R

M M

R E N E N D

S X H

F A B U R U D G E R S I

N T N

R E E T S

D

H

I T

O T R U C K S

C

I

6

I

O

N

I

E

P

S

L

G E

5 O U T

E

A

S

L

B

)

K

E

U

L R

T R U C K S D

G I N

E

E

P

R

O

S

T

T R

. Figure 2-2: Site Layout for Diesel depot, Erf 163, Lafrenz, Windhoek 4 BID, Erf 163, Diesel Depot, Lafrenz, Windhoek

Tortoise Environmental Consultants(TEC)

2.3 Proposed Tank Design

Design Data Design Standard SANS 10131:2004 Shell Material 6mm SANS 50025-2 GrS355JR Flanges ANSI B 16.5 150ASA Mild Steel Piping SANS 62-1 & SANS 62-2 Leak Test 45 kPa Internal Pneumatic Pressure External Surface Preparation Sandblast SA 2.5 External Coating Paint - Forgeweld Gray External Surface Coating Test DFT @ 75µm Gaskets 3mm Non-asbestos Fibre Ring Tank Volume (Calculated) ±23.24 m3 Tank Weight (Calculated) ±3220 kg Overall Length (Calculated) ±5510 mm

DO NOT SCALE DRAWING REVISION 01

NAME SIGNATURE DATE PROPRIETARY AND CONFIDENTIAL DRAWN THE INFORMATION CONTAINED IN THIS P Pienaar PHP 10/5/2016 DRAWING IS THE SOLE PROPERTY OF FORGEWELD (PTY) LTD. ANY CHKD J Mataboge JM 10/5/2016 REPRODUCTION IN PART OR AS A WHOLE WITHOUT THE WRITTEN PERMISSION OF FORGEWELD (PTY) LTD IS PROHIBITED. APPV

TITLE: DWG NO. A3 FORGEWELD STD - 23kL AST BFTANK135-rev1 3D View SHEET 1 OF 6

Design Data Design Standard SANS 10131:2004 Shell Material 6mm SANS 50025-2 GrS355JR Flanges ANSI B 16.5 150ASA Mild Steel Piping SANS 62-1 & SANS 62-2 Leak Test 45 kPa Internal Pneumatic Pressure External Surface Preparation Sandblast SA 2.5 External Coating Paint - Forgeweld Gray External Surface Coating Test DFT @ 75µm Gaskets 3mm Non-asbestos Fibre Ring Tank Volume (Calculated) ±46.03 m3 Tank Weight (Calculated) ±5420 kg Overall Length (Calculated) ±10910 mm

DO NOT SCALE DRAWING REVISION 01

NAME SIGNATURE DATE PROPRIETARY AND CONFIDENTIAL DRAWN THE INFORMATION CONTAINED IN THIS P Pienaar PHP 3/11/2016 DRAWING IS THE SOLE PROPERTY OF FORGEWELD (PTY) LTD. ANY CHKD J Mataboge JM 3/11/2016 REPRODUCTION IN PART OR AS A WHOLE WITHOUT THE WRITTEN PERMISSION OF FORGEWELD (PTY) LTD IS PROHIBITED. APPV

TITLE: DWG NO. FORGEWELD STD - 46kL AST LONG BFTANK275-rev1 A3

3D View SHEET 1 OF 7

Figure 2-3: Proposed Tank Design for the Diesel depot, Erf 163, Lafrenz, Windhoek 5 BID, Erf 163, Diesel Depot, Lafrenz, Windhoek

Tortoise Environmental Consultants(TEC)

3. COMPLIANCE AND LEGAL FRAMEWORK

3.1 COMPLIANCE TO THE EMP

The EMP is binding to the proponent, and all contractors / sub-contractors. This implies that each and every entity that may have any kind of engagement or involved in / with the activities of the proposed diesel depot activities should comply with the EMP throughout the project lifespan. Non-compliance may have serious consequences e.g License withdrawal.

3.2 ENVIRONMENTAL MANAGEMENT ACT (NO.7 OF 2007)

Section 27 of the Environmental Management Act 2007 (Act No. 7 of 2007) (EMA) provides a list of activities that may not be undertaken without an Environmental Clearance Certificate (ECC) (herein referred to as: listed activities). The proposed expansion of the hospital triggers the following listed activities.

The EMP should conform to the provisions of the Environmental Management Act (EMA), Act No. 7 of 2007 and EIA regulations of 2012 (Government Notice: 30).

The EIA Regulations defines a ‘Management Plan’ as:

“…a plan that describes how activities that may have significant impacts on the environment are to be mitigated controlled and monitored.”

3.3 EMP REQUIREMENTS

Table 3-1: EMP Requirements as outlined in Section 8 of the EIA Regulations

Requirement

(j) a draft management plan, which includes – (aa) information on any proposed management, mitigation, protection or remedial measures to be undertaken to address the effects on the environment that have been identified including objectives in respect of the rehabilitation of the environment and closure;

6 BID, Erf 163, Diesel Depot, Lafrenz, Windhoek

Tortoise Environmental Consultants(TEC)

(bb) as far as is reasonably practicable, measures to rehabilitate the environment affected by the undertaking of the activity or specified activity to its natural or predetermined state or to a land use which conforms to the generally accepted principle of sustainable development; and

(cc) a description of the manner in which the applicant intends to modify, remedy, control or stop any action, activity or process which causes pollution or environmental degradation remedy the cause of pollution or degradation and migration of pollutants.

3.4 LISTED ACTIVITIES

Listed Activities may not be undertaken without an Environmental Clearance Certificate (ECC), and hence an Environmental Impact Assessment (EIA) is required.

As the organ of state responsible for management and protection of its natural resources, the MET: DEA is committed to pursuing the principles of environmental management. The EMA provides a list of activities that require an EIA and the proposed the proposed diesel depot is among the listed activities or activities that may not be conducted without at ECC. The purpose of listed activities for projects is to ensure that the associated impacts on the environment are carefully considered.

The proposed continuation of the proposed diesel depot triggers a number of Listed Activities as set out in the Environmental Management Act, 2007 (Act No. 7 of 2007) (herein referred to as the EMA) and the Environmental Impact Assessment Regulation, 2007 (No. 30 of 2011) (herein referred to as the EIA Regulations).

Table 3-2: Listed Activities triggered by the proposed project Activity Applicability Activity 9.4 Storage and Handling The storage and handling of a dangerous of Dangerous Good goods, including petrol, diesel, liquid petroleum gas or paraffin, in containers with a combined capacity of more than 30 cubic meters at any location.

7 BID, Erf 163, Diesel Depot, Lafrenz, Windhoek

Tortoise Environmental Consultants(TEC)

4. THE EIA PROCESS

4.1 EIA PROCESS FLOW

An EIA is a process of identifying, predicting, evaluating and mitigating the effects (negative impacts) of a proposed project on the natural and human environment. The aim of the EIA process is to apply the principles of environmental management to the proposed activities, reduce negative impacts and increase the positive effects arising from a proposed project, and provide an opportunity for the public to comment on the proposed activity.

The EIA Process entails the assessment and description of the study area, recommended site or affected environment. The EIA further investigates and identifies potential impacts that may arise from the proposed activity. Figure 1 below describes the EIA process.

For each and every impact that is deemed significant, mitigation measures will be developed and will be outlined in the Environmental Management Plan (EMP).

Figure 4-1: EIA flow diagram 8 BID, Erf 163, Diesel Depot, Lafrenz, Windhoek

Tortoise Environmental Consultants(TEC)

The backbone of the EIA report entails identification of impacts (whether real or perceived) and recommendations on suitable mitigation measures to ensure compliance with the principles of environmental management and highlight risks and measures to ensure an environmentally friendly development.

4.1.1 Public Participation Process (PPP)

As stipulated in the EIA Regulations, the Public Participation Process (PPP) is a pre-requisite and forms an integral component of an ecological assessment process. The PPP is important to ensure that all stakeholders are informed of the project at hand and that potential environmental effects, and that squabbles/disagreements and potential delays to the project are avoided.

As guided by the EIA regulations, the Public Participation Process (PPP) entails notification of the proposed activity via Newspaper adverts, site notices and distribution of the BID, EIA Scoping Report (ESR) and Environmental Management Plan (EMP) to Interested and Affected Parties (I&APs). Comments made during the public participation should be captured and addressed in the EIA Scoping report and EMP respectively. The public consultation process will be guided by the steps outlined in the table below:

Table 2: Tasks to be undertaken for the Public Participation Process (PPP) Sub-tasks Activities Identification of Identify key stakeholders and develop a database for Stakeholders Interested and Affected Parties (I&AP) Authority Authority consultation entails discussions with consultation representatives from the relevant authorities, at National, Regional and Local governance levels. These may include Ministries, Government agencies, Regional Council, Fisheries, Mining, Tourism sector, Health, Education, farmers, Police etc. Newspaper Adverts will be placed in the local media to sensitize the adverts public about the project and to invite interested parties to register as I&APs. Public A stakeholder consultation is a key component of an Participation environmental assessment process. Meetings (PPP) Stakeholders will be invited to stakeholders’ consultation meetings. Firstly, to inform them about the project and

9 BID, Erf 163, Diesel Depot, Lafrenz, Windhoek

Tortoise Environmental Consultants(TEC)

secondly, to capture and incorporate their comments / concerns. Information regarding compensation procedures to affected landowners can also be discussed. It is expected that the public participation process (PPP) will yield valuable information and it is important to foster a good relationship with the community and other stakeholders from the onset. Public consultation Issues raised during the public consultations process will be (Draft Reports) captured in the Comments and Reponses Report (CRR)

4.1.2 Stakeholders Consultation Process

The public will be notified through Newspaper adverts (4 x Newspaper adverts), and a Notice board will be placed at the site. The commenting period for the project will be 14 days from the newspaper adverts.

The meeting provides a platform for the public to comment on the project. All registered I&APs shall be provided with the draft scoping and EMP reports.

4.1.3 The Importance Of Registration as an I&AP

Registering as an Interested or Affected Party (I&AP) affords you an opportunity to be updated about the project and to comment on the proposed activity.

Your comments are important and will not just add value, but may provide information that is perhaps not available to the consultant (e.g. local knowledge).

4.1.4 Registration as an I&AP

To register as an I&AP and/or provide comments to the proposed development, please send your communication to: [email protected] or call + (264) 811 220 114

The Deadline for submission of comments is 02 September 2020

10 BID, Erf 163, Diesel Depot, Lafrenz, Windhoek

05 - 11 November 2020 lifting the lid Page. 21

NOTICE OF ENVIRONMENTAL NOTICE OF ENVIRONMENTAL ASSESSMENT AND ASSESSMENT AND PUBLIC PARTICIPATION PROCESS PUBLIC PARTICIPATION PROCESS Notice is hereby given to all potential Interested and Notice is hereby given to all potential Interested and Affected Parties (I&APs) that an application will be Affected Parties (I&APs) that an application will be made to the Environmental Commissioner in terms made to the Environmental Commissioner in terms of the Environmental Management Act (No. 7 of of the Environmental Management Act (No. 7 of 2007) and the Environmental Impact Assessment 2007) and the Environmental Impact Assessment Regulations (GN 30 of 6 February 2012) for the Regulations (GN 30 of 6 February 2012) for the following: following: Project Tittle: Proposed Rezoning of Portion A of Erf 1518 Tseiblaagte Ext. 2, Keetmanshoop- Karas Project Tittle: Proposed Subdivision of Portions Region-Namibia A and B of ERF 187 Tseiblaagte into 11 erven and more, Keetmanshoop- Karas Region-Namibia Proposed Development: 05 November 2020 -Closure of Portion A of Erf 1518 Tseiblaagte, Proposed Development: Extension 2 as ‘Public Open Space’. -Rezoning of portion, A of erf 1518 Tseiblaagte, Subdivision of ERF 187 into 11 Erven and more and Extension 2 Thirteenth and Thirty First Avenue and creation of access road. Twenty Seventh Street from ‘public open space’ to ‘residential 2’ with a density of 1:150m2 Proponent: Keetmanshoop Municipality Proponent: Knowledge Solution Consultancy cc To register or request for documents please submit To register or request for documents please submit your name, contact information and interest in the your name, contact information and interest in the project, in writing to the Environmental Assessment project, in writing to the Environmental Assessment Practitioner (EAP): CARS FOR SALE Practitioner (EAP): NB: A public meeting will he held on 21 November NB: A public meeting will he held on 21 November 2020. 2020.

Sirius/ Avanza Toyota, 2015, Isuzu KB 2.4, Petrol, panel van, 110000km. Manual, 14000 km, Manual, N$ 29500 N$109 500 EAP: Tendai E Kasinganeti EAP: Tendai E Kasinganeti Phone: +264813634904 Phone: +264813634904 CALL: 081 220 8176 Email: [email protected] Email: [email protected] 29 Oct - 04 Nov 2020 lifting the lid Page. 25

PUBLIC INVITATION Every energy ENVIRONMENTAL IMPACT ASSESSMENT FOR THE PROPOSED BRICK MAKING PROJECT AT LISELO COMMUNAL AREA OF ZAMBEZI REGION pty(LTD) Notice is hereby given to all Interested and Affected Parties (I & APs) that an application will be made to the Environmental 100% Namibian owned Commissioner in terms of Environmental Management Act (No. 7 of 2007) and its Regulation (2012) for the following Empowerement company intended activity

Project Name: BRICK MAKING PROJECT Project Locations: Liselo Communal Area in Zambezi region Vacancies: Proponent: Pumba Bricks & Construction CC 1. Engineer Reponsible for Project Description: The Proposed projects entails brick Power, Energy generation, making and related brick making activities on a 1.5 hectares Pumba Bricks & Construction CC has appointed NYEPEZ telecomunications, Design and Consultancy CC to conduct an Environmental Impact construction of towers and power Assessment for the proposed development All Interested and Affected Parties (I & APs) are encouraged to lines register and raise concerns or provide comments and opinions on or before 30 November 2020. Background Information 2. Chief technical officer, responsible Document (BID) document will be provided upon indication as an I&AP. for technical operations of the

Proposed Public Consultation meeting date: 15 December company 2020 Venue: Liselo area (Liselo-subkhuta) @ 08h30 3. Manager Finance Should you wish to register as I & AP, please contact the NYEPEZ CC CONSULTANT. 4. Human resources officer Cell: +264814554221 /+264812317252 Email: [email protected] Tel : +264 81 123 79857 Email: [email protected]

Broadcasting Engineer

QUALIFICATIONS & REQUIREMENTS

Education and Experience

• BA / BS / BFA degree in film studies, cinematography, motion graphics, design or related field is required. • MFA or other advanced training / certification is preferred. • Minimum 7+ years of professional video shooting experience is required; with both studio and location experience. • Extensive experience working with 4K+ workflows. • Extensive, demonstrated experience working with artificial lighting. • Extensive, demonstrated experience working with 3 axis gimbals; DJI Ronin, DJI Osmo, etc. • Experience directing.

Required Licenses

FAA Part 107 drone license with experience shooting with drones is required.

Skills and Abilities

• Proven technical acumen and technical curiosity; advanced-level production, shooting, and advanced editing skills. • Excellent detail orientation with regards to video preparation and file management. • Excellent sound design and timing. • Excellent eye for color. • Proficient in key photographic techniques: exposure, composition, focus and lenses. • Ability to direct productions • Ability to keep up to date on best practices and tools in the video space, ensuring standards remain high and techniques are cutting edge. • Ability to light entire vehicles, as well as, individual parts. • Skilled in Microsoft Office. • Skilled at video editing in Adobe Premiere, Final Cut, or Resolve. • Mechanical aptitude and the ability to use hand tools. • Technical acumen to rig cameras and vehicles including 3 axis gimbals (Ronin, Zhiyun Crane 2, Osmo, etc).

If you interested in applying Please Email to : [email protected] Tel: +264 811 4406 02 Find us on website www.cltv.live Twitter: @corporatelifes2 LinkedIn: Corporate Lifestyle Facebook on corporate & lifestyle tv YouTube: CLTv Namibia Instagram handle on cl_tv_ 6 NEWS Thursday 29 October 2020 NEW ERA Swanu promises to tackle land-use controls n Albertina Nakale and building rural value supply chains,” Iijambo maintained. S an election promise, Swanu has According to him, the profit-driven privatisation undertaken to reduce restrictions on land of urban spaces displaces thousands from use with the ultimate goal of integrating economically desirable parts of the city to the theA city’s income workforce into the urban fabric. periphery. The party has fielded candidates in various Furthermore, he alluded there are cost and local authorities and regional councils ahead of benefits analysis of socio-economic dislocations, next month’s elections. The elections are slated as well as financing the re-housing of displaced for 25 November. residents in good neighbourhoods. Swanu President Tangeni Iijambo said all the For Swanu, Iijambo said, infrastructure is a people of Namibia have the right to decent housing public good. and this dream will only be realised under a socialist “The land belongs to the state and if there is an NAMIBIA VOTES Swanu government. increased effective land supply, the cost of land He stressed the problem area is the land, adding will be reduced. Swanu will build houses for the urbanisation through informal settlements without masses and blend them into the mainstream living 2020 adequate planning and service provision frustrates of the city life, provide physical infrastructure and potential for productivity and liveability. enabling regulatory environment to lower land The land question… Swanu President Tangeni Iijambo. Photo: Nampa “If the land is converted to more efficient costs by making land accessible to all the citizens,” use and rightly owned, it can be a good source he promised. of survival. The government can contain rural- Iijambo said the party is now at the height of its to the investigation officer at Outapi, urban migration by boosting the rural economy campaign activities, with teams organising various Two nabbed for while the second suspect was arrested to enhance productivity and liveability; promote meetings in Otavi, Kalahari, and Eiseb 10 for the at his homestead in the Oshana regional sovereignty in terms of food security coming weekend. - [email protected] region. They are charged with five hunting game counts ranging from hunting of protected game, hunting a game park or nature reserve, transporting n Loide Jason of game meat without a permit, as well as the possession of a firearm Local diplomats to monitor polls The police in the Omusati region without a licence. have arrested two men for allegedly “The suspect utilised rifle and n Kuzeeko Tjitemisa authority elections normally don’t attract foreign illegally hunting protected game. ammunition to shoot and kill the observers. They don’t apply and we don’t invite According to the regional crime animals. They ignored all three Electoral Commission of Namibia chief electoral them. Foreign observers are normally interested in investigations coordinator, Deputy provision police roadblocks on officer Theo Mujoro has said the commission is the Presidential and National Assembly elections,” Commissioner Moses Simaho, Onamatanga-Uutsathima gravel currently processing applications of diplomats Mujoro told New Era yesterday. the offences were committed on road on 17 October by diverting who have applied to observe the regional council However, he said, the commission has received 17 October 2020 around 18h00 at from Okahao gravel road into the and local authority elections set for next month. applications from various missions in the country, Omutambowomawe and Okaonde bush road to avoid arrest by the “Traditionally, regional council and local wanting to observe the elections, which are areas in the Ruacana constituency. police and further abandoned the currently being considered. He said the suspects used their vehicle in the bushes at Onamakaka In less than a month, Namibians are heading  private vehicle to transport illegally  to the polls to elect new regional council and village,” he9/4 )said.+ VAT No.: 3632029-01-5 hunted game meat, of which the The police, however, managed toReg: CC/2003/2222 local authority councillors who will serve for police recovered one carcass of eland, seize one of the firearmsE-mail: allegedly [email protected] five years. A considerable number of candidates, three duikers, a dik-dik, a rabbitWe do and care for usedyour Sightin the commission of the political parties and associations have registered a bow white bird. crime, while the vehicle was also to participate in the polls. Simaho yesterday told New Era impounded. The two suspects were This year, a record of 93 the main suspect in the matter was due to appear in court yesterday. independent candidates will arrested after he handed himself over - [email protected] participate in the upcoming NAMIBIA VOTES elections, a significant jump from five who contested the 2015 vote. According to the electoral commission, 2020 it received a total of 493 candidates to contest in the country’s 121 constituencies, of which 93 were independent candidates. From the 493, 423 were   9/4)+ VAT No.: 3632029-01-5 Theo Mujoro male candidates, while 70 are female. Reg: CC/2003/2222 We do care for your Sight E-mail: [email protected]

Kapia Optics has the following available positions: Man held for raping another man

n Loide Jason Full Time Optometrist A 45-year-old man from Ogongo constituency The candidate should be: in the Omusati region appeared in court on i. Graduate of Bachelor of optometry Tuesday for the alleged rape of another man on Monday night. ii. Namibian or permanent residents and or having a PUBLIC NOTICE: According to the crime investigations valid work permit to work in Namibia coordinator for Omusati, Deputy Commissioner ENVIRONMENTAL IMPACT ASSESSMENT(EIA) FOR Moses Simaho, Araki Shekwaanyena, who was iii. Must have at least 5 years experience THE SETTING-UP OF A FUEL DEPOT (92 m3 DIESEL) AT iv. Must be able to perform all optometric duties NEUDAMM CAMPUS FARM, KHOMAS REGION. reportedly intoxicated at the time of the alleged & crime, was arrested at Okapya-kambidhi village. professionally INVITATION TO PUBLIC PARTICIPATION According to the police, the suspect went In accordance with the Environmental Management Act (No. with the 31-year-old victim to his house, where 7 of 2007) (EMA) and the Environmental Impact Assessment Suitably qualified candidates and who meet these (EIA) Regulations (Government Notice No 4878 of 2012), he allegedly committed the crime. notice is hereby given to all possible Interested and Affected In an unrelated matter, a 51-year-old man requirements can forward their complete CV with a Parties (I&APs) that an application will be made to the committed suicide at Omatwadiva village in the Environmental Commissioner for an environmental clearance covering letter to Kapia Optics cc, as follows: Okalongo constituency on Tuesday morning. P. O Box 574 Ondangwa or Project: Fuel Storage (Depot) He was found hanging from his bedroom Proponent: Ocean Bunker Petroleum Services ceiling with a plastic rope around his neck. Location: Erf. 163 Lafrenz Industrial Area, Windhoek The police said Hamunyela Jason committed email to [email protected] on or Public Meeting Date: 14 October 2020 Venue: Onsite Erf. 163 Lafrenz Industrial Area, Windhoek suicide after he reportedly assaulted his girlfriend before 13th November 2020. Time: 10H00 – 11H00 and sister, who sustained minor injuries. Deadline for submission of comments: 06 November 2020 The assaulted victims sought refuge at the Register as Interested & Affected Parties @ [email protected] or call +264 811 220114 neighbours and upon their return home, they OSHAKATI BRANCH ONDANGWA BRANCH GROOTFONTEIN BRANCH WALVIS BAY BRANCH BALHAI CENTER, 1346 FREEDOM SQUARE RD 814 TOIVO YA TOIVO STREET 144 SAM NUJOMA AVE found Jason’s lifeless body hanging from the FRANS INDONGO COMPLEX P.O. BOX 574 P.O. BOX 859 P.O. BOX 5431 The public meeting will be conducted in accordance with the TEL: +264 (0)65 22 01 69 TEL: +264 (0)65 24 05 29 TEL: +264 (0)67 24 09 60 TEL: +264 (0)64 22 17 53 ceiling. FAX: +264 (0)65 22 41 02 FAX: +264 (0)65 24 06 24 FAX: +264 (0)67 24 27 40 FAX: +264 (0)64 22 17 56 COVID-19 regulations OSHAKATI BRANCH ONDANGWA BRANCH GROOTFONTEIN BRANCH WALVIS BAY BRANCH PR No.: 0700000518794 BALHAI CENTER, PR No: 07000070133961346 FREEDOM SQUARE RD 814PR TOIVO No.: YA 0700000518778TOIVO STREET 144 SAM NUJOMA AVE PR No.: 0700000560634 FRANS INDONGO COMPLEX P.O. BOX 574 P.O. BOX 859 P.O. BOX 5431 TEL: +264 (0)65 22 01 69 TEL: +264 (0)65 24 05 29 TEL: +264 (0)67 24 09 60 TEL: +264 (0)64 22 17 53 FAX: +264 (0)65 22 41 02 FAX: +264 (0)65 24 06 24 FAX: +264 (0)67 24 27 40 FAX: +264 (0)64 22 17 56 PR No.: 0700000518794 PR No: 0700007013396 PR No.: 0700000518778 PR No.: 0700000560634 6 NEWS Thursday 5 November 2020 NEW ERA

NAMIBIA VOTES 2020

corruption,” he said. Before his resignation in May this Ex-Nudo SG year, Jahanika and long-serving Nudo constituency councillor joins PDM Vetaruhe Kandorozu were accused of having campaigned against the party during last year’s Presidential n Kuzeeko Tjitemisa and National Assembly elections - an allegation that last month resulted in Former National Unity Democratic the firing of Kandorozu from the party. Organisation secretary general Meundju Jahanika was a member of parliament Jahanika announced yesterday he on the Nudo ticket between 2005 -2020 has joined the Popular Democratic and had previously served as Nudo Great expectations… Three water tanks donated to Post 3 Secondary School. Movement (PDM) six months after he director and deputy secretary for Photo: Nampa resigned from Nudo. Jahanika, who information and publicity. was at odds with the current Nudo He was also a Swapo secretary for leadership before his resignation, said information and mobilisation for the he defected to PDM because he sees it as Otjinene district between 1992 -2000 Epukiro candidates a non-tribal but democratic movement. before defecting to Nudo. highlight poll promises “PDM also has zero tolerance on victims of SGBV and where these already Muteka exits, she will make the community more ZOMBOUVAPA - Candidates On his part, Itele Kambirongo from aware of them. vying for Epukiro constituency’s IPC said he will focus on the improvement Muteka also said that she will initiate a councillor position have of educational programmes in schools. advocates campaign that will aim to train teachers, Ohighlighted education, employment “I will create an exchange programme lecturers, other school and university creation and agriculture as important for for learners with other schools in the rent-to-own staff, and students on SGBV once elected the constituency’s development. country. Motivational speeches and into office. “I will ensure that the systems National Unity Democratic Organisation parental involvement will be key as well,” are in place in schools and universities to (Nudo), Popular Democratic Movement Kambirongo added. scheme identify and refer survivors and children (PDM), Independent Patriots for Change The Swapo party’s Piniel Packy Pakarae n Kuzeeko Tjitemisa who are at risk of SGBV,” said the Swapo (IPC), the Swapo Party and independent told Nampa his prime target in terms of youthful candidate. candidate Sandie Tjaronda will compete development is to change the administration Furthermore, Muteka said she will for the position in the local authority in the constituency office. Swapo candidate for the Windhoek West constituency Emma Muteka wants to promote urban and modern agriculture elections slated for 25 November. Pakarae said he would involve villages to ensure food security among the PDM’s Jacqueline Makono told Nampa in the Constituency Development bring in a rent-to-own scheme that will allow tenants renting a dwelling to buy constituency residents. in a recent interview she will prioritise Committee (CDC) by forming a Local This, she said, will commence with the improvement of agriculture, Development Committee (LCD). the home within a specific period. The 30-year-old Muteka launched the promotion and sensitisation of urban youth employment and education if “The LDC will comprise representation agriculture through backyard gardens, elected. from all villages, unlike the current her campaign document titled ‘The Windhoek West Chapter’ in the capital skills development, and seed production. Makono said the three areas seem to be CDC which consists of Omaueuonjanda “To perfect this, I will engage neglected as there is a lack of agricultural residents only,” Pakarae said. yesterday. “Housing remains a challenge for our stakeholders in the production, and projects and incentives, while the majority Nudo’s Kenikejanda Kandetu said ensure that residents are equipped with the of the youth are unemployed and there is no people are tired of Swapo in Epukiro as residents, particularly the youth. With rent-to-own, residents commit to renting necessary skills required for agriculture,” vocational education in the constituency. no development is taking place in the she said. Also, she said if elected, she Tjaronda said areas such as health, constituency. a property for a specific period, with the option of buying it before the lease will establish a socio-economic support education, agriculture, housing, “Nudo will be the only party to programme that will be achieved through infrastructure development, environmental bring change to Epukiro as it will fight expires,” said Muteka. In the document, Muteka said she will the creation of platforms for residents to conservation and resettlement will get his corruption in regional governance. I showcase their talents. attention. will promote business initiatives, youth actively work towards the prevention and response to sexual and gender-based To achieve this, Muteka said an He said the constituency suffers from employment and electrifying of all villages informal market will be established a developmental deficit and that can be through renewable energy,” Kandetu said. violence by among others encouraging and forming of community-based accompanied by constituency market attributed to structural and policy challenges. He further said that network coverage days and other economic activities for “The quest for development will require needs to be strengthened in Epukiro, networks among persons of concern. She said she will also work with partner small scale residents. deliberate targeted interventions,” Tjaronda while more clinics are also needed. – [email protected] said. -Nampa organisations to create safe spaces for

Drugs worth N$400 000 seized More than 80 suspects were The drugs seized include 26.4 arrested on drug-related matters kilogrammes of cannabis, 254 across the country in the month mandrax tablets, 226 grams of of October and drugs worth nearly cocaine powder and 63 units of crack N$413 000 were seized. cocaine. The suspects included In a statement, police 80 Namibians, three Angolans spokesperson Deputy and one Congolese national. Commissioner Kauna Shikwambi “The police still encourages the said 84 suspects were arrested public to continue reporting drug- between 1 and 31 October and related activities happening in their drugs valued at N$413 940 were communities,” said Shikwambi. seized over the same period. -Nampa

Caught out… Law enforcement officers have seized drugs worth over N$400 000 in October. Photo: Nampa