Appendix J: Project List This page intentionally left blank. USARW Region IRWMP Project Prioritization

Note: Project prioritization to be made available on the IRWM Plan webpage.

Project Agency/ Project Sponsor Projected Costs Goals

IMPROVE WATER SUPPLY RELIABILITY

City of San Bernardino Water Recycling San Bernardino Municipal Water Department 67,800,000

Big Bear Area Regional Wastewater Agency Plant Big Bear Area Regional Wastewater Agency 70,000,000

City of Beaumont WWTP City of Beaumont

City of Redlands WWTP City of Redlands

Henry N. Wochholz WWTP Yucaipa Valley Water District

IEUA Regional Treatment Plant 4 Utilities Agency

Central Feeder Pipeline San Bernardino Valley Municipal Water District $117,000,000

West End Pump Station San Bernardino Valley Municipal Water District $10,000,000

Riverside-Corona Feeder West Valley Water District $176,000,000

Erwin Lake Fire Flow Department of Water and Power

Yucaipa Connector San Bernardino Valley Municipal Water District $4,500,000

Medical Center No. 2 Reservoir San Bernardino Municipal Water Department $18,100,000

No Updates

Seven Oaks Dam Borrow Pit Recharge and Habitat Restoration Project San Bernardino Valley Water Conservation District $7,700,000

Installation of Groundwater Monitoring Wells in Forebay San Bernardino Valley Water Conservation District $640,000

Rialto-Colton Basin Groundwater Recharge Study San Bernardino Valley Municipal Water District $280,000

IMPROVEWATER SUPPLY RELIABILITY Alluvial Fan Development Guideline Water Resources Institute - State University San Bernadino

Pellesier Ranch Recharge and Water Treatment Plant City of Riverside Public Utilities $17,700,000

Groundwater Reclamation Interagency Project (GRIP) City of Redlands $9,100,000

Bunker Hill Basin Water Supply Reliability West Valley Water District $13,000,000

Santa Ana River Construction Area San Bernardino Valley Municipal Water District $122,000,000

Riverside North Recharge Basin City of Riverside Public Utilities $13,500,000 * Include: Completion of pre-feasibility study, environmental documentation, and expected implementation date

Project Agency/ Project Sponsor Projected Costs Goals

Active Recharge in the SAR Tributaries San Bernardino Valley Municipal Water District Uknown

Recycled Water System Expansion City of Redlands $4,858,700

Calimesa Recycled Water Conveyance Project Yucaipa Valley Water District

Beaumont Avenue Recharge Facility Water Agency $8,000,000

Stormwater Capture and Recharge City of Riverside Public Utilities $3,000,000

BALANCE FLOOD MANAGEMENT AND INCREASE STORMWATER RECHARGE

Cactus Basins #4 and #5 San Bernardino Parks Department $21,300,000

Cactus Basins #3 San Bernardino County Parks Department $21,300,000

Randall Basin San Bernardino County Parks Department $1,460,000

Sand/Warm Confluence San Bernardino County Parks Department

Wilson III Basin Project and Wilson Basin/Spreading Grounds City of Yucaipa $8,900,000 FLOODMANAGEMENT Opal Recharge and Flood Control Basin City of Redlands $26,000,000

Downtown Storm Drain Project City of Redlands $5,200,000

IMPROVE WATER QUALITY

Desalter and Brine Disposal Yucaipa Valley Water District $9,600,000

City of Beaumont Desalter City of B.

Sari Improvement Project

Big Bear Lake Management Plan Multiple Agencies $260,000

RIX Facility Basin Levee Project San Bernardino Municipal Water Department $3,300,000 IMPROVEWATER QUALITY Security Fencing of Groundwater Recharge Facilities San Bernardino Valley Water Conservation District $1,640,000

* Include: Completion of pre-feasibility study, environmental documentation, and expected implementation date Project Agency/ Project Sponsor Projected Costs Goals

IMPROVE HABITAT AND OPEN SPACE

Upper Santa Ana Watershed Alluvial Sage Scrub Habitat Restoration Mitigation San Bernardino Valley Water Conservation District Banking Construction Program Wash Habitat Conservation Plan San Bernardino Valley Water Conservation District $800,000

Warm Creek Restoration Project Inland Empire Resource Conservancy District $63,000

Removal of Invasive Plant Inland Empire Resource Conservancy District $300,000

San Timoteo Canyon State Park Habitat Conservation R.L.C. $5,500,000

Lytle Creek Watershed Assessment and Restoration Water Resources Institute - California State University San Bernadino $260,000

Combined SBKR and Water Recharge Enhancement - Wash Plan Implementation San Bernardino Valley Water Conservation District $1,371,101

Stanfield Marsh

Bogart Park Wetlands

BCV Forest Land Reserved IMPROVEHABITAT SPACE AND OPEN I.E. Sustainable Watershed Project

LIDS for Kids- Low Impact Development Inland Empire Resource Conservancy District $237,000

SAR Trail - Phase III San Bernardino County Parks Department

SAR Trail - Phase IV San Bernardino County Parks Department

* Include: Completion of pre-feasibility study, environmental documentation, and expected implementation date