Box 32, Wekweètì, NT X0E 1W0 Tel: 867-713-2500 Fax: 867-713-2502 (Main)

#1-4905 48th Street, Yellowknife, NT X1A 3S3 Tel: 867-765-4592 Fax: 867-669-9593

October 15, 2012 File: W2009X0002

Mr. Ron Breadmore Project Manager – Tlicho Region Department of Indian Affairs and Northern Development Contaminants & Remediation Directorate 5103 – 48th St. Waldron Building PO Box 1500 Yellowknife, NT X1A 2R3 Email: [email protected]

Dear Mr. Breadmore,

Final Clearance of Land Use Permit W2009X0002 – North Inca Mine Remediation Project

The Wek’èezhìi Land and Water Board met on October 15, 2012 to discuss the final clearance of Land Use Permit W2009X0002. No fees were associated with this land use permit.

The final clearance of Land Use Permit W2009X0002 has been granted pursuant to section 33 of the Mackenzie Valley Land Use Regulations and our files are now closed. If you have any questions, please contact Roberta Judas, Regulatory Technician at (867) 713-2500 or by email at [email protected].

Sincerely,

Violet Camsell-Blondin Chair

Copied to: Charlene Coe for Darnell McCurdy, South Mackenzie District Office, AANDC

Box 32, Wekweètì, NT X0E 1W0 Tel: 867-713-2500 Fax: 867-713-2502 (Main)

#1-4905 48th Street, Yellowknife, NT X1A 3S3 Tel: 867-765-4592 Fax: 867-765-4593 www.wlwb.ca

STAFF REPORT

Company: Aboriginal Affairs and Northern Development Canada (AANDC), Contaminants and Remediation Directorate (CARD). Location: North Inca Mine Remediation Project Application: W2009X0002

Date Prepared: September 20, 2012 Meeting Date: October 15, 2012

Subject: Final Clearance of Land Use Permit

Purpose/Report Summary The purpose of this report is to present to the Board a notice from AANDC to discontinue Land Use Permit W2009X0002 and proceed with final clearance. Background WLWB issued land use permit on March 19, 2009 with an expiry date of March 18 2014. The Permittee has indicated that it has completed its Remediation of the North Inca site in March of 2010, and as per section 37 (1) subject to subsection (2) where a permittee wishes to discontinue a land use operation at any time prior to the date of completion set out in the permit, the permittee shall give a notice of discontinuance in writing to the Board and, where the land use operation is being carried out on private lands, to the landowner, indicating the date on which it is proposed to discontinue the operation.

AANDC CARD submitted their final plan on July, of 2012 (See attachment #1), followed by a Notice of Discontinuation letter on August 8, 2012 (see attachment #2). AANDC Inspector Clint Ambrose submitted a recommendation supporting final clearance of this permit on August 8, 2012. Comments In an email dated August 8 2012 from AANDC Inspector Clint Ambrose regarding the final plan submitted by AANDC – CARD for Land Use Permit W2009X0002, he recommended: (See attachment #3)

“The final plan for the above noted land use permit has been reviewed by the undersigned Inspector and appears to be correct. With the submission of the s.37 discontinuation notice to the Board today, it is hereby recommended that the WLWB issue a letter of clearance to the Permittee pursuant to s.33 of the Mackenzie Valley Land Use Regulations.”

Security N/A

Conclusion There appears to be no concerns that would prohibit the final clearance of land use permit W2009X0002.

Recommendation Board staff recommends the Board approve the final clearance of land use permit W2009X0002.

Respectfully submitted,

Roberta Judas Regulatory Technician

Attachments: 1. Final Plan 2. Notice of Discontinuation Letter 3. Inspectors Recommendation

NORTH INCA MINE REMEDIATION PROJECT

FINAL PLAN UNDER LAND USE PERMIT W2009X0002

Submitted to: Wek’eezhii Land and Water Board

Submitted by: Contaminants and Remediation Directorate Aboriginal Affairs and Northern Development Canada July 2012

Table of Contents I Final Plan Format and Context ...... 1 II Background ...... 1 III Land Use Permit Chronology ...... 2 IV Intended/Actual Land Use ...... 3 1. Applicant’s name and mailing address ...... 3 2. Head Office Address ...... 3 3. Other Personnel (subcontractors, contractors, company staff etc.) ...... 3 4. Eligibility ...... 5 5. Summary of Operations ...... 5 a) Describe purpose, nature and location of all activities ...... 5 b) Please indicate if a camp is set up ...... 16 6. Summary of potential environmental and resource impacts (describe the effects of the proposed land use operation on land, water, flora and fauna and related socio- economic impacts)...... 16 7. Proposed Restoration Plan ...... 17 8. Other rights, licenses or permits related to this permit application (mineral rights, timber permits, water licenses) ...... 18 a) Other rights, licenses or permits ...... 18 b) Roads- Is this to be a pioneered road? Has the route been laid out or ground- truthed? ...... 18 9. Proposed disposal methods ...... 19 a) Garbage ...... 19 b) Sewage (Sanitary and Grey Water) ...... 19 c) Brush and trees ...... 19 d) Overburden (organic soils, waste materials, etc.) ...... 19 10. Equipment (includes , pumps etc.) ...... 19 11. Fuels ...... 21 12. Containment fuel spill contingency plans ...... 22 13. Method of fuel transfer (to other tanks, vehicles etc) ...... 22 14. Period of operation (includes time to cover all phases of project work applied for, including restoration) ...... 22 15. Period of permit (up to 5 years with a maximum of 2 years extension) ...... 23 V LAND USE ...... 23

I Final Plan Format and Context

The Review of Land Use and Final Plan for Land Use Permit W2009X0002 has been prepared to provide a synopsis of the history of the land use area, a review of the chronology of the issuance of the Land Use Permit (LUP), a review of the intended/actual land use at the site and a plan describing actual land use within the permitted area. The intent of this Plan is to provide the context of the LUP application/issuance, describe the intended activities (as provided in the application) compared to the executed activities and provide the Final Plan as required under Section 33 of the Territorial Land Use Regulations.

II Background

The North Inca Mine was an advanced gold exploration property that operated between 1945 and 1949. On-site exploration activities included geological mapping, surface diamond drilling (9,700 metres (m)), sinking an exploration shaft to a depth of 98 m, and underground diamond drilling (2,800 m). Review of site records indicates that there had not been significant exploration activity on-site between 1949 and the remediation of the North Inca site. The Department of Indian Affairs and Northern Development (DIAND) Contaminants and Remediation Directorate (CARD) oversaw the assessment and remediation of the North Inca Mine site. The location of North Inca is provided on Figure 1. The configuration of the Colomac winter road, used for the transportation of materials to and from the North Inca site, is provided on Figure 2.

Figure 1 North Inca Area

______1 Land Use Permits W2009X0002 Final Plan July, 2012 Figure 2 Colomac/North Inca Winter Road

III Land Use Permit Chronology

January 26th, 2009

CARD submitted an application to the Wek’èezhìi Land and Water Board (WLWB) for a LUP for North Inca Remediation.

March 19th, 2009

WLWB issues W2009X0002 to CARD. Permit expires March 18th, 2014.

July 3rd, 2009

CARD notifies WLWB and the DIAND Resource Management Officer (Clint Ambrose) of the inability to achieve the 100 metre set back from the ordinary high water mark of Indin Lake for the camp set-up and fuel storage, as outlined in the LUP. The Inspector provided written confirmation that DIAND-CARD was authorized to store fuel and construct a grey water sump 30 metres from the ordinary high water mark of Indin Lake, with the condition that secondary containment (i.e. drip trays) be implemented for fuel transfer locations.

______2 Land Use Permits W2009X0002 Final Plan March, 2012

IV Intended/Actual Land Use

This Section provides a review of the land use details of the North Inca site provided in the application, compared to details of the actual activities that occurred through the land use activities. The information that was provided in the application is indented and italicized, with the description of actual activities/updated information immediately following.

1. Applicant’s name and mailing address Ron Breadmore INAC-AINC Contaminants and Remediation Directorate P.O. Box 1500 Yellowknife, NT X1A 2R3 Fax number: (867) 669-2721 Telephone number: (867) 669-2743

The applicant information has remained current throughout the project. Indian and Northern Affairs Canada and its French translation (INAC-AINC) were abbreviated in the application. Three Departmental titles have been used through land use documentation: Department of Indian Affairs and Northern Development (DIAND - the legal Department name), Indian and Northern Affairs Canada (INAC - the former Federal Identity Program Department name) and Aboriginal Affairs and Northern Development Canada (AANDC - the Federal Identity Program Department name effective June 13th, 2011). DIAND or AANDC are the currently accepted names.

2. Head Office Address Same as above. Field supervisor: To be provided to the Board when a contractor has been selected to undertake the remediation work at North Inca. Radiotelephone: Fax number: To be provided when a contractor has been selected. Telephone number: To be provided when a contractor has been selected.

The Head Office address for the Applicant stayed the same as previously provided. The Field Supervisors were personnel from: Tlicho Engineering and Environmental Services (TEES) P.O. Box 758 Yellowknife, NT X1A 2N6 Fax: 867-920-7328 Telephone: 867-920-7288

3. Other Personnel (subcontractors, contractors, company staff etc.) The Remediation of North Inca will be done by a contractor selected through a competitive government contracting process. It is anticipated that the contract will be awarded by the end of February 2009. ______3 Land Use Permits W2009X0002 Final Plan March, 2012

Specifications to complete the work North Inca have been developed and will form the basis of proposals submitted by interested contractors. In the proposal submitted by the successful contractor the number of people required to complete the work, the types and number of equipment and fuel requirements will be listed.

For the purpose of this application people requirements, equipment types and numbers as well as fuel requirements have been estimated.

Once the contractor has been selected this information can be submitted to the Wek’èezhìi Land and Water Board.

Based upon the type of work and level of effort required to remediate the North Inca Site, it is anticipated that a work force of 15-20 people will be on site for a period of approximately 12 weeks. The range of suggested workers on site is listed below. 1 Superintendent 1 foreman 1 site clerk/medic 5 labourers 2 equipment operators 1 HD Mechanic/welder 1 departmental representative 2 wildlife monitors 1 surveyor (part time)

Number of work days to accomplish this project equates to 84 days (10 hrs/day).

TOTAL: (Number of persons on site) It is estimated that a total number of 17 people will be on the site, for a total of 1183 person days.

The equipment used for the North Inca Remediation is detailed in item 10. Fuel requirements are described in item 11. The work days required to complete the remediation was as follows: From March 20th, 2009 to March 29th, 2010 Contractor - TEES, 792 person days Departmental Representative – SENES Inc. – 97 person days DIAND – Project team site visits and Inspector visits – approximately 5 person days Public Works and Government Services Canada (PWGSC) – Site visits – approximately 5 person days Total estimate over life of permit = 899 man days

______4 Land Use Permits W2009X0002 Final Plan March, 2012

4. Eligibility (Refer to section 18 of the Mackenzie Valley Land Use Regulations) a)(i) a)(ii) a)(iii) b)(i) X b)(ii)

Based on section 18 of the Mackenzie Valley Land Use Regulations, AANDC was eligible for this land use permitting based on Section 18, sub-section b), item (i), specifically: 18. A person is eligible for a permit who (b) in any other case, (i) has a right to occupy the land and who contracts to have the land-use operation carried out.

5. Summary of Operations

a) Describe purpose, nature and location of all activities The remediation of the site is to be carried out in accordance with the North Inca Remedial Action Plan. The following general activities are planned: • Close the opening to the underground and fill in surface trench; • Regrade rock pile along the shoreline; • Demolish any remaining infrastructure and treat debris as required; and, • Collect and consolidate any waste and debris on site for removal.

Please see attached Appendix B of the land use application for a general description of remediation activities. More in-depth information and can be found in Section 1.2 of the North Inca Remedial Action Plan. No new roads on-site or infrastructure are proposed; some maintenance and upkeep of remediation measures is expected. Equipment and materials will be brought to the site via the Colomac winter road; a small spur road will be built to gain access to the site.

Note: the Appendix B referenced above was the Appendix B of the application. The remediation of the North Inca Site was carried out in accordance with PWGSC contract documentation. These documents were based on the Remedial Action Plan (RAP) for North Inca, which was submitted with the application. The primary purpose of the civil works activities over the duration of the land use permit was to remediate the mine site and ensure the protection of local and downstream environments.

The site work was completed between March 2009 and March 2010. The Contractor mobilized equipment and materials during the March 2009 winter season. The 2009 winter season included partial set-up of the camp, removal of the designated and hazardous materials and demolition of buildings and structures. The summer construction season ran from June 2009 to August 2009, with completion of the structure demolition, debris removal/stockpiling, contaminated soil removal/stockpiling, construction of the mine opening seal and re-grading earthworks. The final off-site

______5 Land Use Permits W2009X0002 Final Plan March, 2012

transportation and disposal of stockpiled materials and complete site demobilization was concluded during the March 2010 winter season.

One final activity that was completed in March 2011 was the removal of the D3 dozer that was found between the North Inca and the Diversified Mine Sites. The D3 was dragged over a pre-existing trail to the shoreline. It was loaded onto a truck and shipped by Winter Road to the Mine Heritage facility in Yellowknife, where it is currently on display. A small oil stain that had been identified under the D3 will be remediated as part of the remediation of the Diversified Mine Site.

March/April 2009 Winter Season TEES commenced site activities March 20th, 2009, basing their operation out of the Colomac Mine site camp. CJ Contracting, a subcontractor of TEES, cleared snow off the ice between the Colomac winter road and the site (for the spur road to the site) to permit access to the North Inca Mine site areas.

The 2009 winter work was completed between March 20th and April 9th, 2009. The activities carried out included: • Construction of a site access spur road off of the main Colomac winter road for the winter season work; • Snow removal; • Initial site survey; • Removal of designated substances and hazardous materials from the buildings; • Demolition of building structures and preparation of equipment for off-site transport; • Debris removal (e.g. steel bed debris from the camp site, small miscellaneous steel materials) from the mine site; • Burning of untreated wood debris; • Consolidation of empty drums; • Transportation of building debris to the Colomac Site; • Off-site transportation of heritage items to Yellowknife; • Transportation of asbestos-containing materials to Colomac site for disposal in the Spruce Lake Disposal Cell; • Off-site transportation of hazardous paint and equipment to a Hazardous Waste facility; • Transportation of empty drums to the Colomac Site; • Mobilization of summer work materials and equipment; and • Demobilization of equipment intended for only the winter program.

June/ July/ August 2009 Summer Season TEES mobilized their 2-person start-up crew and a 3-person Discovery Services (DMS) crew to the North Inca site on June 22nd, 2009 to begin construction of the camp. The first TEES work crew and the PWGSC department representative were transported to the site on June 29th, 2009. All summer access to the site was via float plane. ______6 Land Use Permits W2009X0002 Final Plan March, 2012

The summer construction program was completed August 13th, 2009. The activities carried out included: • Construction and start-up of the camp; • Mobilization of crew, supplies, materials and equipment; • Structure demolition; • Burning of the wood debris; • Removal and consolidation of debris from Debris Dump areas; • Construction and maintenance of site access roads; • Reshaping waste rock at the edge of Indin lake; • Backfilling the mine site exploration trench; • Excavation and consolidation of petroleum hydrocarbon impacted soil; • Excavation and consolidation of potentially acid generating waste rock; • Excavation and consolidation of polycyclic aromatic hydrocarbon impacted soil/ ash; and • Construction of the concrete cap seal for the mine opening.

March 2010 Winter Season The winter remediation work close-out and demobilization commenced March 8th, 2010. The winter program and overall site work was completed March 29th, 2010. The close- out activities carried out included: • Transportation of hazardous materials to the Colomac site for staging and subsequent disposal at the designated Hazardous Waste facility; • Transportation of the consolidated debris to the Colomac site for disposal; • Transportation of PHC contaminated soil to the Colomac site for treatment; • Final site clean-up; and • Demobilization of all equipment and materials off-site.

The summary of the specific activities completed as part of the remediation work is shown in the following Table. Additional details are provided in the North Inca Remediation Completion Report in Appendix A.

______7 Land Use Permits W2009X0002 Final Plan March, 2012

Summary of Remediation Activities Completed Component Area Sub-Component Description Buildings, Mine Site Head-frame Wood debris was collected and burnt in containment. Infrastructure House Removed equipment, demolished building, hauled and disposed of debris in and Colomac landfill. Equipment Mine Dry Removed hazardous materials (ACM), demolished building, hauled and disposed of debris in Colomac landfill Powerhouse & Removed hazardous materials (ACM and equipment with leachable paint), Mechanics Shop demolished building, break-up foundations, hauled and disposed of debris in Colomac landfill. Powerhouse Removed hazardous materials (PAHs in residual ash), demolished building, (Blacksmith Shop) hauled and disposed of debris in Colomac landfill. Quonset Hut (with Removed contents, demolished building, hauled and disposed of debris in entrance room) Colomac landfill.

Water Tower Platform Demolished structure, hauled and disposed of debris in Colomac landfill. Utilidor Demolished structure, hauled and disposed of debris in Colomac landfill. Outhouse 1 Removed hazardous materials (ACM), demolished structure, hauled and disposed of debris in Colomac landfill. Boiler Concrete Pad Broke up foundation, hauled and disposed of debris in Colomac landfill. Boiler (equipment) Hauled away for off-site disposal. Camp Site Former Bunk House Posts removed and left undisturbed. Manager’s Cabin Removed lead paint, demolished building, burnt wood debris, hauled and disposed of ash in Colomac landfill. Radio Cabin Demolished structure, hauled and disposed of debris in Colomac landfill. Outhouse 2 Removed hazardous materials (ACM), demolished structure, hauled and disposed of debris in Colomac landfill. Outhouse 3 Removed hazardous materials (ACM), demolished structure, hauled and disposed of debris in Colomac landfill Utilidor Demolished structure, hauled and disposed of debris in Colomac landfill. Outlying Explosives Cabin Demolished structure, burnt wood debris, hauled and disposed of ash in Area Colomac landfill. Waste Assay Site Drum Dump Collected drums, hauled drums for processing at Colomac, crushed drums and Disposal Sites disposed of in Colomac landfill Outlying Debris Dump 1 Collected waste and debris, hauled and disposed of debris at Colomac landfill. Area Debris Dump 2 Collected waste and debris, hauled and disposed of debris at Colomac landfill. Debris Dump 3 Collected waste and debris, hauled and disposed of debris at Colomac landfill. Mine Site Debris Dump 4 Collected waste and debris, hauled and disposed of debris at Colomac landfill. Debris Dump 5 Collected waste and debris, hauled and disposed of debris at Colomac landfill.

Camp Site Misc. Drums Collected waste and debris, hauled and disposed of debris at Colomac landfill. Saw Mill Reclaimed and hauled to Yellowknife for the Mining Heritage Society. Fuel Storage Mine Site AST1 Hauled and disposed of in the Colomac landfill. Areas Camp Site AST2 Hauled and disposed of in the Colomac landfill. Mine Waste Assay Site East of Assay Building Removed rock core to Colomac for disposal. Rock Areas Mine Site Along Shore Shoreline re-shaped to reduce grade. Mine Mine Site Mine Shaft Concrete seal constructed. Openings Trench Backfilled with mine rock. Contaminated All Areas Petroleum Excavated, hauled to Colomac for biotreatment. Soils Hydrocarbon Contaminated Soils Designated All Areas Equipment and Removed all designated substances for disposal in Colomac landfill or in an Substances Buildings approved off-site facility.

Representative photos of work activities are provided in Photos 1 to 10.

______8 Land Use Permits W2009X0002 Final Plan March, 2012

SELECTED PHOTOS Photo 1 – Snow Clearing for Mobilization (20 March 2009)

Photo 2 – Ore Bucket for Mine Heritage Society (25 March 2009)

______9 Land Use Permits W2009X0002 Final Plan March, 2012

Photo 3 –Ingersoll-Rand Drifter for Mine Heritage Society (25 March 2009)

Photo 4 – Hoarding Around Mine Shaft (31 March 2009)

______10 Land Use Permits W2009X0002 Final Plan March, 2012

Photo 5 – Engineered Cap (September 2009)

Photo 6 – Former Location of the Mine Dry (3 April 2009)

______11 Land Use Permits W2009X0002 Final Plan March, 2012

Photo 7 – Burning of non-Treated Wood Debris (29 March 2009)

Photo 8 – Debris Removal from Debris Dumps 2 and 3 (14 July 2009)

______12 Land Use Permits W2009X0002 Final Plan March, 2012

Photo 9 – Debris Dumps 2 and 3 after Completion (30 July 2009)

Photo 10 – Petroleum-Impacted Soil Removal - AST 2 Location (12 August 2009)

______13 Land Use Permits W2009X0002 Final Plan March, 2012

Photo 11 – Re-Grading of the Waste Rock (11 July 2009)

Photo 12 – Re-graded Waste Rock with Camp in Background (5 July 2012)

______14 Land Use Permits W2009X0002 Final Plan March, 2012

Photo 13 – Demobilization of Debris (15 March 2010)

Photo 13 – Building Removal during Demobilization (27 March 2010)

______15 Land Use Permits W2009X0002 Final Plan March, 2012

b) Please indicate if a camp is set up A small temporary field camp will be set up to accommodate work crews during the remediation work. The contractor will determine what type of camp set up is required to support remediation efforts. Currently the best option for the camp would be on the east side of the peninsula with drinking water obtained from Indin Lake. Sewage wastes will be disposed of in a sump on site.

Domestic waste will be managed on site by a fuel fired EPA approved incinerator.

A shelter was erected during the March 2009 land use operations. This shelter contained a displayed copy of the LUP. DMS erected the temporary field camp between June 22nd and 29th, 2009. The camp was taken down and removed during the March 2010 demobilization.

The TEES field camp was located on the flat plateau level of the mine site area near the location of the former mine dry/hoist house locations; the sump was located at the back of the camp. The sump location was reviewed by DIAND Inspectors and written authorization provided July 3rd, 2009. Sewage from the pacto toilets was burnt daily and grey-water was disposed of in the sump. The land use area was kept clean at all times. Combustible camp garbage and debris were burnt daily in the camp incinerator.

Water for the camp was obtained from Indin Lake and the water intake was constructed with a screen. Water treatment was specified in the LUP by the Government of the Northwest Territories (GNWT) – Health. The contractor, TEES, tested the water from Indin Lake during the winter work program and confirmed that water quality met Health Canada (HC) Guidelines for Drinking Water Quality. Regular testing continued during the operation of the camp.

6. Summary of potential environmental and resource impacts (describe the effects of the proposed land use operation on land, water, flora and fauna and related socio-economic impacts).

Any impacts to the North Inca site will be positive. Please refer to the Remedial Action Plan (RAP) for a complete description of potential environmental and socio economic impacts from the project and prescribed mitigation measures.

Generally, impacts to the North Inca site were positive, with the removal of debris and environmental contaminants. Site work was completed in a manner which minimized effects on the land, water, flora and fauna. Plywood sheeting was used to support areas where there were signs of rutting due to All-Terrain Vehicle (ATV) use. Sediment and erosion controls, in the form of silt fences and floating turbidity curtains, were used for the work near the shoreline. ______16 Land Use Permits W2009X0002 Final Plan March, 2012

Interaction with the local fauna was avoided. For example, a bird nest was seen on the ground adjacent the access route to the Camp site. The area was sectioned off with warning tape to avoid disturbing the nest. Workers were made aware of the area. The GNWT-ENR Wildlife department was informed of the nest and saw no issue with working around the area. Photo 11 – a) Nest on Ground near Access Route, b) Nest Location Flagged to Prevent Disturbance

a b

7. Proposed Restoration Plan

This application is to authorize the remediation of the site. The site will be remediated to current acceptable measures which were agreed to by both the Government of Canada (through Indian and Northern Affairs) and through consultation with Tlicho representatives. As the project to be undertaken is such that will mean improvements to the site, any changes are assumed to be beneficial. All camp structures brought on to the site will be removed upon completion of the project and Land Use Permit. For the remediation details please Appendix B for a general overview and attached North Inca Remedial Action Plan.

Note: The Appendix B referred to in the above passage was the Appendix to the application. As the project was undertaken to remediate a former mine site, changes to the site have been beneficial. All camp structures brought on to the site were removed upon completion of the remediation project. The grey-water sump was backfilled and restored at the completion of site work. Land restoration was conducted as per Condition 26(1)(o) of the LUP, with all clean-up and restoration of the lands completed by the end of the remediation project.

______17 Land Use Permits W2009X0002 Final Plan March, 2012

8. Other rights, licenses or permits related to this permit application (mineral rights, timber permits, water licenses)

a) Other rights, licenses or permits

There are no existing rights, licenses or permits for this site.

A burn permit application will be submitted by the contractor to reduce brush and non-hazardous wooden materials.

Rights, licenses or permits for this site were not established between the time of the application and the completion of remediation. Burn permits were obtained by the contractor for all required burning to reduce brush and non-hazardous wooden materials.

Prior to the application for the permit, Pine Valley Mining Corporation (PVMC) held Mineral Claims and leases that included or were near the North Inca site. PVMC also obtained a Storage Authorization Approval (MV2003X0024) on December 19th, 2006 for storage of equipment on the nearby Diversified property. The Claims and leases were transferred to George Stephenson by PVMC on June 1st, 2007. On September 21st, 2007, Mr. Stephenson withdrew his application for the assignment of the PVMC Land Use Permit.

A land application (#86 B/6-7-1) for a reserve was filed with the Lands Administration Division of AANDC. The reserve includes the North Inca shaft cap, trench re-graded area and waste rock re-graded area. The area of the application is shown on Figure 12.

b) Roads- Is this to be a pioneered road? Has the route been laid out or ground-truthed?

No. A small spur road (approx 500m) will be built onto the winter road to Colomac in order to access the North Inca Site. Contingency and mitigation measures are formed under that contract. Existing roads are to be cleared and utilized as required.

Maps of the existing Colomac Winter road route can be found in Appendix D of the Land Use Permit Application.

Note: The Appendix D referred to in the above passage was the Appendix to the application. No new roads were developed under this permit; pre-existing roads or trails across the bedrock were utilized to access areas of the site. Brushing of the existing roads was completed in compliance with Condition 26(1)(n) (Methods and Techniques for Debris and Brush Disposal) of the Land Use Permit. A small spur road (approx 500m) was built from the winter road to Colomac in order to access the North Inca Site for mobilization and demobilization.

______18 Land Use Permits W2009X0002 Final Plan March, 2012

9. Proposed disposal methods A small temporary camp is anticipated for this site, to be set up by the contractor. They will be required to provide the services outlined below.

a) Garbage Garbage will be incinerated daily, except plastics.

The resulting ash, plastics and non-hazardous waste will be transported from site for disposal in the Colomac Landfill.

Combustible garbage was incinerated daily. Plastics, ash and other non-combustible items were transported from the site for disposal in the Colomac Zone 2.5 Pit Landfill.

b) Sewage (Sanitary and Grey Water) A sump will be constructed on site for the disposal of sewage from the camp.

A sump was constructed on site for the disposal of grey-water sewage from the camp. Sewage from the Pacto toilets was burnt daily.

c) Brush and trees The brush and trees removed from clearing trails and existing roads will be windrowed and if site conditions permit burned in a controlled manner.

The brush and trees removed from clearing trails and existing roads were progressively disposed of by burning.

d) Overburden (organic soils, waste materials, etc.) N/A

The only disturbance of overburden was for the removal of contaminated soil.

10. Equipment (includes drills, pumps etc.) The list of potential equipment is as follows - the full list is to be provided by the contractor.

Type & Number Size Use small to medium sized Cat 320 or equivalent, This unit will be used for excavator c/ w toothed operating weight of tear down of buildings, bucket and thumb, approximately 15,000 kgs. breaking concrete hydraulic point breaker foundations, digging out soil and debris, reshaping of wasterock piles 1 rubber tired backhoe operating weight of Waste debris collection and approximately 10,000 kgs building demolition 1 welding/cutting unit Approximately 100kg For on site repairs and to ______19 Land Use Permits W2009X0002 Final Plan March, 2012

Type & Number Size Use cut various large metal pieces into workable unit 1 Walk-behind Compactor 610 kg Compacting Wasterock piles after re-grading 1 Bobcat approximately 2,000 kgs Waste debris collection and material movement 1 D3 Bulldozer operating weight of Re-shaping wasterock pile, approximately 16,000 kgs loading contaminated soil 1 Dumptruck operating weight of Transporting contaminated approximately 10,000 kg soil, tailings and/or waste rock. 1 Concrete mixer 2,100kg Prepare concrete for capping of mine opening 2 ATV type units with 2 ATV 4 wheel - Honda or For use as personal trailers equivalent, operating transport on site and to weight ~450 kgs hand collect small debris 2 ATV trailers - Honda or and items such as empty equivalent, operating fuel drums, batteries, etc. weight 70 kgs

The Departmental representative (DR) monitored and reported on the use of equipment at the North Inca site. They reported that the equipment used for the work was listed in the application.

The majority of equipment used on the North Inca project was contractor supplied. The exception was limited use of the Crown Equipment from the Colomac Project during winter operations. This included use of a Colomac Tandem Truck, for transport of materials from North Inca to Colomac for disposal, a pick-up truck for use of site personnel, a truck and float for movement of major equipment and a payloader for movement of heavy loads, bags, etc. This equipment use occurred at a period of low equipment usage at the Colomac site, so the Colomac project was not affected.

Summary of Crown Assets Used at North Inca Description of Comments Crown Asset Tandem Truck Used February 15 – 28, 2010 – from Colomac Crown inventory. Returned to Colomac in good condition at the end of use. Used for transport of North Inca wastes from North Inca to the disposal areas at Colomac. As this equipment was already at the Colomac site, use of this equipment saved considerable mobilization costs without impacting the operations at Colomac. Pick-up Truck Used February 8 - 28, 2010 – from Colomac Crown inventory. Returned to Colomac in good condition at the end of use. The pick-up truck was used to transport personnel from Colomac to North Inca (North Inca personnel stayed at Colomac accommodations), as a weather haven while on the North Inca site, and for general transportation between North Inca and Colomac. . As this equipment was already at the Colomac site, use of this equipment saved considerable mobilization costs without impacting the operations at Colomac.

______20 Land Use Permits W2009X0002 Final Plan March, 2012

Description of Comments Crown Asset Truck and Used February 15 - 28, 2010 – from Colomac Crown inventory. Returned to Colomac in float good condition at the end of use. This equipment was used for staging other heavy equipment, both Crown and contractor owned, between North Inca and Colomac. It was also used in conjunction with the Tandem Truck to transport materials from North Inca to Colomac for disposal. As this equipment was already at the Colomac site, use of this equipment saved considerable mobilization costs without impacting the operations at Colomac. Loader Used February 15 - 28, 2010 – from Colomac Crown inventory. Returned to Colomac in good condition at the end of use. The loader was used for loading material into the Tandem Truck and onto the float for transport to Colomac for disposal. Some general scraping and clean-up was also completed with this equipment. As this equipment was already at the Colomac site, use of this equipment saved considerable mobilization costs without impacting the operations at Colomac.

11. Fuels

11. Fuels () Number of Capacity of containers Location containers Diesel x 1 100,000 Litres (~60,000 North Inca litres to be brought in to Site site) Gasoline x 4 45 gal drums North Inca Site Aviation fuel Propane x 1 100 lb unit North Inca Site Other

The work fuel storage containers were placed at the interior edge (farthest edge from Lake) of the mine site area. CARD notified WLWB and the DIAND Resource Management Officer (Clint Ambrose) of the inability to achieve the 100 metre set back from the ordinary high water mark of Indin Lake for the fuel storage. The Inspector provided written confirmation that DIAND-CARD was authorized to store fuel 30 metres from the ordinary high water mark of Indin Lake, with the condition that secondary containment (i.e. drip trays) be implemented for fuel transfer locations and under fuel drums used for fuel supply to heater units for tents in the camp.

All container outlets were sealed, except the outlet in use. Spill kits were available on site and secondary containment was in place under fuel drums. The diesel fuel storage tanks were a 4,500 litre (L) horizontal double walled tank and a 9000-L vertical double walled tank. Additional gasoline and diesel was stored on-site in 45 gallon drums. Secondary containment was placed under all transfer nozzles, valves, etc. Five 100 pound propane tanks were also kept on-site. Aviation fuel was not stored on site as planes re-fuelled at Colomac. No fuel spills were reported.

______21 Land Use Permits W2009X0002 Final Plan March, 2012

12. Containment fuel spill contingency plans

A draft Spill Contingency Plan, with MSDS sheets, is included with the application in Appendix C. The successful contractor will be asked to prepare a Spill Contingency Plan that meets or exceeds the requirements of this plan. The plan must be submitted to INAC before any work occurs on site. This plan will be forwarded to the Wek'eezhii Land and Water Board and Inspectors before any site activities occur.

Spill kits will be available on site and secondary containment will be in place under the fuel drums that are supplying the pumps. All tanks will be double walled green tanks. Secondary containment will be placed under all transfer nozzles, valves, etc.

Note: Aviation fuel will not be stored on site - any planes requiring fuel will go to Colomac for re-fueling.

The Contingency Plan and Reporting Practices for Oil and Hazardous Material Spill (TEES, 2009) was submitted to the DIAND South MacKenzie District Office on June 30th, 2009. The contingency plan and spill kits were in place during all remediation work to respond to any potential spills.

13. Method of fuel transfer (to other tanks, vehicles etc)

Electric Pump, API certified hose, couplings, sliptanks on flatbed or trailer.

Fuel was transferred to on-site equipment using dispensers and electric pumps, in accordance with fuel management standard operating procedures. API certified hose, couplings, and slip-tanks on flatbed or trailer were also used.

14. Period of operation (includes time to cover all phases of project work applied for, including restoration)

It is anticipated that equipment and materials will be mobilized to the site in March 2009. The remediation work will take place during the summer of 2009 with equipment and materials demobilized on the 2010 winter road.

Work on the North Inca Remediation was completed in three phases. The 2009 winter program was completed between March 20th and April 9th, 2009. The 2009 summer program extended from June 22nd, 2009 to August 13th, 2009. The 2010 winter program was completed between March 8th, 2010 and March 29th, 2010. The D3 Dozer was removed from the North Inca site in February 2011, and taken to the Mine Heritage Society in Yellowknife. Arrangements have been made for recovery of hydrocarbon ______22 Land Use Permits W2009X0002 Final Plan March, 2012

impacted soil from a leak under the D3. The soil will be manually excavated and treated with hydrocarbon impacted soils from the Diversified Mine site.

No further land operations are anticipated at the North Inca site.

15. Period of permit (up to 5 years with a maximum of 2 years extension)

2 years

Land Use Permit MV2009X0002 was granted for a period of 5 years, and expires March 18th, 2014.

V LAND USE

Over the duration of this land use permit, a number of land use activities were undertaken. Waste consolidation and impacted soil remediation was completed. The site was already negatively impacted by the previous mine development, so the activities under this permits were in support of overall site remediation and improvement.

In accordance with Section 33 of the Territorial Land Use Regulations, the following plans are provided: a) Lands subjected to the land use operation; b) Lines, trails and cleared areas used during land use operations; and c) Excavations and other works and places.

Also provided in this section is a calculation of the territorial lands used in this operation and an aerial photograph showing the lands subject to the land use operation.

______23 Land Use Permits W2009X0002 Final Plan March, 2012

______24 Land Use Permits W2009X0002 Final Plan July, 2012

Figure 4 North Inca Mine Site (Dotted Line Shows the Site Road, Solid Red Lines are Site Trails and Remedial Action Shown in Red Text)

Figure 5 North Inca Camp Site (with Remedial Action Shown in Red)

______25 Land Use Permits W2009X0002 Final Plan July, 2012

Figure 7 North Inca Camp Site (with Remedial Action Shown in Red)

Figure 7 North Inca Assay Site (with Remedial Action Shown in Red)

______26 Land Use Permits W2009X0002 Final Plan March, 2012

______27 Land Use Permits W2009X0002 Final Plan March, 2012

______28 Land Use Permits W2009X0002 Final Plan March, 2012

______29 Land Use Permits W2009X0002 Final Plan March, 2012

______30 Land Use Permits W2009X0002 Final Plan March, 2012

______31 Land Use Permits W2009X0002 Final Plan March, 2012

Total Estimated Land Use Under Permit LAND USE ACTIVITY APPROX. AREA USED (m2) i) Powerhouse Excavation 126 m2 ii) Hoist House Excavation 10 m2 iii) Assay Building Excavation 16 m2 iv) AST 1 Excavation 12 m2 v) AST 2 Excavation 16 m2 vi) Waste Rock Re-grade 535 m2 vii) Exploration Trench Back-fill 8 m2 viii) Shaft Cover 4.5 m2 ix) Waste Rock Shoreline Armouring 22.5 m2 x) Trails (from map - estimated at 2 m wide) 4250m2 TOTAL 5000 m2 or 0.5 ha

SUMMARY

Land Use Permits MV2009X0002 allowed for the completion of a number of land use activities related to successful remediation of the North Inca mine site between March 2009 and March 2010. The Contaminants and Remediation Directorate would like to acknowledge the hard work and support of all WLWB staff and DIAND’s Operations Directorate during this period.

______32 Land Use Permits W2009X0002 Final Plan March, 2012

Roberta Judas

From: Brett Wheler [[email protected]] Sent: September-07-12 5:37 PM To: 'Roberta Judas' Subject: FW: North Inca Mine Remediation Project - Final Plan under Land Use Permit W2009X0002

From: Clint Ambrose [mailto:[email protected]] Sent: August-08-12 7:57 PM To: [email protected] Cc: Andrew Richardson; Charlene Coe; Malcolm Robb; Nahum Lee; Ron Breadmore; [email protected] Subject: Re: North Inca Mine Remediation Project - Final Plan under Land Use Permit W2009X0002

Brett,

The final plan for the above noted land use permit has been reviewed by the undersigned Inspector and appears to be correct.

With the submission of the s.37 discontinuation notice to the Board today, it is hereby recommended that the WLWB issue a letter of clearance to the Permittee pursuant to s.33 of the Mackenzie Valley Land Use Regulations.

If you have any questions or concerns, please do not hesitate to contact Nahum Lee at 669.2757 or myself at the numbers below.

Regards,

Clint

------Clint Ambrose Resource Management Officer III (Inspector) South Mackenzie District Aboriginal Affairs and Northern Development Canada TEL: (867) 669-2794 CELL: (867) 446-0769 FAX: (867) 669-2720 [email protected]

#16 Yellowknife Airport (Mailing) 140 Bristol Ave. (Street) Yellowknife, NT X1A 3T2

>>> Andrew Richardson 7/31/2012 12:15 PM >>> Hi Brett,

1 Attached is a copy of the North Inca Mine Remediation Project - Final Plan under Land Use Permit W2009X0002. Please accept this report as our submission under the requirements specified in Section 29 of the Mackenzie Valley Land Use Regulations.

If you have questions or concerns, contact me or Ron Breadmore.

Cheers,

------Andrew Richardson Project Officer - Tli Cho Region Contaminants & Remediation Directorate Department of Indian Affairs and Northern Development 5103-48th Street, P.O Box 1500 Yellowknife, NT X1A 1N5 Tel: (867) 669-2772 Fax:(867) 669- 2721 e-mail: [email protected]

______Information from ESET Smart Security, version of virus signature database 7437 (20120901) ______

The message was checked by ESET Smart Security. http://www.eset.com

2