Covington’s US 190 Superstreet Statewide Traffic Engineer’s Meeting 2019
Penny Lala Johnathan Perry Clara Foshee Cristine Gowland UPERSTREET
www.dotd.la.gov Introduction
Penny Lala
www.dotd.la.gov US 190 Background Information
Covington, St. Tammany Parish 62,726 ADT in 2017 45mph, six-lane, divided urban arterial from I-12 to US 190 Business – Median width ~ 65’ Congested corridor Large cycle lengths
3 US 190 Background Information
Corridor can be divided into two sections: – I-12 to the Abita River Bridge • ~ 2 miles • 7 traditional signals • 6 U-turns with yield control • Dense driveway spacing • Heavy development
4 US 190 Background Information
Corridor can be divided into two sections: – Abita River Bridge to US 190 Business • ~ 1 mile • 3 full-access, two-way stop controlled intersections (80’ – 90’ wide) • 3 U-turns with yield control • Bordered by signalized corridor to the north • Driveways more spaced out • Less development
5 Previous Capacity Improvements
013-11-0026 – Let in January 2004 – Project Limits: I-12 to the Abita River Bridge – Widen US 190 from 4-lanes to 6-lanes – All existing full-access signals remained
6 Previous Capacity Improvements
H.000490 – Let in July 2005 – Project Limits: the Abita River Bridge to US 190 Business – Widen US 190 from 4-lanes to 6-lanes – All existing intersection control remained the same – Project constructed a 6-lane road to a 2-lane bridge
7 US 190 Existing Issues
Queuing of northbound and southbound thru traffic Some left turns over-capacity 6-lane highway to 2-lane bridge Poor lane utilization Cannot widen US 190 without impacting many businesses Traffic predominantly enters or exits US 190 at the intersections (not a lot of cross traffic)
8 US 190 Superstreet Traffic Study
Headquarters asked for routes to be studied as a Superstreet We were aware of development coming that was going to further break the broken roadway We proposed US 190 Covington Study was initiated in 2010 Study made recommendations involving both sections of US 190 Wal-Mart Marketplace development was initiated during the study, so the study incorporated the permit requirements Study completed in 2012 by Neel-Schaffer
9 US 190 Superstreet Scope Issues
Had to define limits on where the project would stop – Should have considered the signalized corridor immediately outside the limits Study assumed the entire corridor would be done at once – Not feasible during construction – How do you phase in the improvements?
10 US 190 Superstreet Public Meeting Meeting held June 18th, 2014 – DOTD Employees, State Officials and Public in attendance Received feedback and redesigned for an upcoming development – Worked with consultant to get trip numbers and include them in analysis – Additional intersection at Greengate added • Dual lefts onto the proposed connection • Developer had to widen connection to accept the dual lefts – U-turn locations modified to accommodate
11 Plan Development
Clara W. Foshee
www.dotd.la.gov Developing The Plan What should be done first? – Should the new signals be installed and activated first, or should all of the construction work be done first? – When should the new U-Turns be built and signalized? When should the old ones be closed? How will all of these signals be turned on? – 15 intersections where configuration and phasing/timings will change – 2 signalized intersections where only the equipment will change – How will all 17 signals, spanning across 3 miles of congested highway, be activated? How do we maintain access and flow during construction? – Lane closure restrictions? How tight do we make the restrictions?
13 What Should Be Done First? EXISTING SUPERSTREET 15
2 4
12
18
5 7 26 US 190 at Frontage Rd
14 How Do We Turn All These Signals On? Corridor broken into four groups for feasibility – Based on relationship of intersections to each other • Wanted to keep U-Turns grouped with their respective origin movement – Group size varied depending on density of signals and locations
(3 signals – 0.66 miles) (3 signals – 0.24 miles) (4 signals – 0.66 miles)
(7 signals – 1.07 miles)
15 7 signals – 1.07 miles long
2 Restricted-Access Intersections 3 U-Turn Only Intersections 2 Restricted-Access & U-Turn Intersections
Holiday Blvd
16 4 signals – 0.66 miles long
2 Restricted-Access Intersections 2 U-Turn Only Intersections
17 3 signals – 0.66 miles long
2 U-Turn Only Intersections 1 Restricted-Access Intersection
18 3 signals – 0.24 miles long
3 U-Turn Only Intersections
1 Unsignalized U-Turn Only Intersection 1 Signalized Restricted-Access Intersection 1 Signalized U-Turn Only Intersection
19 Desired Activation Order Wanted to start at North end of project and work our way South – Northern intersections provided more leeway with unexpected issues – Starting at the North end would make it easier to adjust offsets further down the corridor
(3 signals – 0.66 miles) (3 signals – 0.24 miles) (4 signals – 0.66 miles)
(7 signals – 1.07 miles)
20 How Do We Maintain Access & Flow? Lane Closure Restrictions – Need to be very strict – Need to be in effect at all times
One Exception – US 190 at Park Place Dr – Turn-lane closed for multiple weeks on EB approach – Cross-connectivity available – Best solution to undesirable situation
21 Adjustments During Plan Development Holiday Blvd Geometrics Corridor Timings – Proposed dual right-turns off side-street – Study Recommended Timings: • AM: 100 second cycles • PM: 100 second cycles – Timings in Field: • AM: 190 second cycles • PM: 180 second cycles – New Timings: • AM: 95 second cycles • PM: 90 second cycles B A
22 The Final Plan
23 Implementation Issues
Johnathan Perry, P.E.
www.dotd.la.gov Issues Discovered During Preconstruction
What order would the contractor activate signals? When would detection be installed? There was confusion when ordering the total quantities for the project – TSIs were provided for two existing intersections that were not fully accounted for in the Final Plans – Only the new signal equipment quantities were added to plans for these intersections (controllers, pods, fiber, etc.) Travel time studies needed before construction started
25 Travel Time Studies
Direction Range (min.) Avg. (min.) Period Pre-Construction (4/2018) NB 7-15 10.9 AM SB 5-15 10.8 NB 12-32 17.8 PM SB v 7-19 14.4 During Construction (3/2019) NB v - - AM SB v - - NB 10.5-13.5 12.1 PM SB 10-13 11.5
26 Issues Discovered During Construction Adjacent Signalized Corridors Signal Issues – Timings – Controllers – Cabinet Access – Equipment Placement – Signal Head Visibility Sequence of Construction Issues Signage Issues Striping Issues Other Issues
27 Adjacent Corridor Issues
Existing signalized corridors adjacent to project – Signal system north of the bridge (3 full-access) – Signal system coordinated with superstreet (4 full-access and 2 restricted-access)
28 Signal Issues - Timings
District was responsible for adjustment of signals – Green time adjustments – Offset coordination (build as we go instead of backtracking later) District had to time the existing corridor to the north to match Superstreet timings before activation
29 Signal Issues - Controllers
Controller clocks drifting, AKA “Dirty Power” Signals did not force off at the correct time – what can we do? – Re-time the entire corridor? – Adjust the NTCIP Yield Value in all controllers? • Trial-and-Error method to get the internal Easy-Calcs to match the Force-Offs on the TSIs
30 Signal Issues – Cabinet Access
31 Signal Issue – Equipment Placement
32 Signal Issues – Head Visibility
33 Sequence of Construction Issues Signal work performed before earth work – Lead to damaged equipment
34 Signage Issues - Lack of Adequate Signage
35 Signage Issues – Conflicting Information
36 Striping Issues – Stop Bar Placement
37 Striping Issues - Lane Utilization
38 Striping Issues - Lane Utilization
Non-Uniform Pavement – 3 different pavements on one approach Misleading Traffic Control Devices – Cones give impression that inside lane is closed Lack of Striping – No temporary striping to guide motorists
39 Other Issues - Environmental Impacts
40 Other Issues – Illegal Movements Permitted Movements – Rights-In/Thrus – Lefts-In/Rights-Out Illegal Movements – NB & SB U-Turns from Left-Turn Lanes Observations at one intersection: – 2 Hour PM Period – 52 NB Illegal U-Turns – 14 SB Illegal U-Turns
41 Other Issues – Illegal Movements
42 Local News Review
43 Lessons Learned
Cristine Gowland, P.E.
www.dotd.la.gov Next Steps and Conclusions Signal Coordination Ongoing Public Outreach Public Opinion Measures of Success
45 Signal Coordination Current: Future (Eventually): Coordination of both Independent coordination of northbound and southbound northbound and southbound traffic simultaneously traffic Not as efficient as two, one-way Too many cabinets to split (17 facilities now versus 29 individual) Controlling full access signal on Need to try independent rings in north side same controller Pattern Offsets menu allows for different offsets to be assigned to each ring
46 Ongoing Public Outreach
MyDOTD notifications issued Public Meeting was removed from Webpage and had to be re-added Public Information Group created a graphic of the corridor and posted it Numerous phone call and email questions and complaints Troop L wanted to meet with local businesses on corridor for a “Safety Meeting”
47 Local Business Outreach - Troop L
DOTD contacted State Police Troop L concerning enforcement of illegal U-turns Troop wanted to perform outreach to local businesses before heavy enforcement Troop proposed a joint effort with DOTD – The Troop would talk about safety – DOTD would speak about Superstreet
48 Local Business Outreach - Troop L
The presentation has been given to two separate groups at Cantium and one large group at Chevron Most people in the room where there because they wanted to be. . . Reached 300 corridor drivers so far
49 Old Five-Phased Signal Timing
180-Second (3-Minute) Signal Cycles
50 New Two-Phased Signal Timing
90-Second (1.5-Minute) Signal Cycles
51 Why Are U-Turns Not Allowed Here?
Potential crashes with right turners Delays for right turners because
side street has to brake to avoid CRASH crashes Delays for left turns because they have to slow down to make the U-turn movement CRASH U-turns have separate, designated areas
52 Public Opinion - Facebook
53 Public Opinion - Resolution
54 Measures of Success Follow-up travel time studies planned Before/after crash analysis planned (longterm) Implementation of adjacent projects –I-12 widening to south –US 190 widening of Bogue Falaya Bridge to north Public Opinion (decline of negative feedback) One more presentation to discuss results ~ 2024?
55 Questions?
www.dotd.la.gov