Widening Existing Transversely Stressed Concrete Bridges on Logan Enhancement Project
Muhammad Shariq Senior Structural Engineer - GHD Palisa Huoth Senior Structural Engineer - GHD Presentation Overview
Background
Case Study
Design Image place holder
Construction
Recommendations Background Supply Demand
• Increased Demand
• Need of more improved and efficient systems
• Brownfield Infrastructure upgrades
• Maximising the utilisation of existing assets Enhanced Safety • BRIDGE WIDENINGS Reduced Congestion • Provisions for Future widening
Efficient Motorway Enhanced network Connectivity Project | Logan Enhancement Project (LEP) - QLD
• Transurban Queensland $512 million project • Widening sections of the Logan and Gateway motorways. Brisbane
Team and key stakeholders
CLIENT ROAD AUTHORITY
CONTRACTOR INDEPENDENT VERIFIER
DESIGN JOINT VENTURE Logan Enhancement Project (LEP) - QLD
Highlights: • Improving key congestion hot spots: • Logan Motorway • Mt Lindesay Highway • Beaudesert Road interchange and the Wembley Road • Logan Motorway interchange BR03 Widening
• Constructing new south-facing on and off-ramps on the Gateway Motorway at Compton Road
Key Objectives: • Sustainability & Optimisation, • Future proofing • Minimising Construction Impact • Safety Logan Enhancement Project (LEP) - QLD
Workflow
• Tender Design Tender • Detail Design Design Detail Design based on and further Construction • Further Investigation reference investigations design • Construction
Detail Design Delivery
Developed Substantial Final Detail Issued for Concept Design Detail Design Design Construction 25% Design 65% Design 85% Design 100% Design Case Study – Scrubby Creek Bridge (BR03)
• Dual Carriageway • 8 Spans • Prestressed DUs • Transversely post- tensioned • Total Length170m • 8 Driven Piles • Built 1996 Previous Conditional Assessments
• TMR Level 2 Inspection report 2008 and 2012 • TMR Level 1 Inspection report 2015 • Rehabilitation of Deck Surfacing and Pier 4 Expansion Joint 2015
Southbound• Non Level-destructive 2 Inspection- Water Integrity leaks, Vegetation Testing at Headstock, Partial Replacement of Expansion Joints
Northbound Level 2 Inspection- Crack on Surfacing and Vegetation at Headstocks Design | Scrubby Creek Bridges (Plan)
NORTH EXISTING BRIDGE
ORIGINAL WIDENING WIDENING PROVISION
LOGAN BRISBANE
Image place holder EXISTING BRIDGE
WIDENING
BR03 SCRUBBY CREEK PLAN Design | Scrubby Creek Bridges (Cross-section)
Original Widening provision in the middle
Image place holder Detailed Design (Connecting Superstructure)
General arrangement of stressing bar through deck units
• Interface Deck Unit • Coupling of PT bars • Accessible for Maintenance Detailed Design (Connecting Substructure)
• Rigid connection • Post Installed Dowels • Composite Connection Design Challenges and considerations
For 2 no.s PT bars on Scrubby Creek Bridges that were identified as condition state of 3 in previous NDT report as per • Available Information and gaps SWTC.
Undertake design check • Connection of the existing and new structure and core out, remove bars for visual assessment, unless other bars identified as more representative • Design for each of the construction stages
Are the bars in No further rectification work satisfactory condition required for the remaining PT based on visual bars • Bridge Loadings inspection Yes
No Identify the location and assess the nature of the • Integrity of transverse PT bars observed defects. Assess overall bar condition and Level 2 inspection assessment, apply engineering judgement to determine appropriate actions
Provide a desktop analysis Bridge capacity Yes advising client of future adequate without maintenance requirements for Category 3 bars? PT bar monitoring and replacements
No
Core out, remove and replace the worst Condition State 3 PT bar
Yes
The actual condition No Any additional of the PT bar and Category 3 PT bars grout satisfactory? identified?
Yes No
No further rectification work required for the remaining PT bars Further Investigations and Construction Condition of Existing Structure
• Non Destructive Testing • Categorise Condition • Confirmation of Condition
• Undertaken by specialist Contractor • Piles not driven to set • Cast in place piles required for design Construction | Key Challenges and Solutions
Staging
Solution • Staged construction
• Alignment Image place holder • Consideration of sight distance (effects of anti- gawk screens)
• Limited access- worked within construction program Construction | Key Challenges and Solutions
Proximity
Solution
• Mitigated risks of damage to
existing pile Image place holder
• Worked with Contractor to devise solution
• Removed pile for increased tolerance Construction | Key Challenges and Solutions
Tie-in Existing
Solution
• Adjustable mortar pad heights Figure 1: Typical Cross section Image place holder • Oversized voids
• Alignment adjusted
• Worked with Construction to modify dowel design
Figure 2: Abutment Dowelling Recommendations
• Not as ‘simple’ as it appears
• Clients - Provide as much record information as possible
• Designers - Ongoing and early engagement between Asset Owner, Authorities, Image place holder Contractor, Reviewers and Designers
• Communicate design sensitivity
• Authorities - Plan for future Construction | Current status
• Commenced in June 2017 • Enhanced Safety
• Expected Completed Mid 2019 • Enhanced Connectivity
Image place holder www.ghd.com