Logan Enhancement Project

Logan Enhancement Project

Widening Existing Transversely Stressed Concrete Bridges on Logan Enhancement Project Muhammad Shariq Senior Structural Engineer - GHD Palisa Huoth Senior Structural Engineer - GHD Presentation Overview Background Case Study Design Image place holder Construction Recommendations Background Supply Demand • Increased Demand • Need of more improved and efficient systems • Brownfield Infrastructure upgrades • Maximising the utilisation of existing assets Enhanced Safety • BRIDGE WIDENINGS Reduced Congestion • Provisions for Future widening Efficient Motorway Enhanced network Connectivity Project | Logan Enhancement Project (LEP) - QLD • Transurban Queensland $512 million project • Widening sections of the Logan and Gateway motorways. Brisbane Team and key stakeholders CLIENT ROAD AUTHORITY CONTRACTOR INDEPENDENT VERIFIER DESIGN JOINT VENTURE Logan Enhancement Project (LEP) - QLD Highlights: • Improving key congestion hot spots: • Logan Motorway • Mt Lindesay Highway • Beaudesert Road interchange and the Wembley Road • Logan Motorway interchange BR03 Widening • Constructing new south-facing on and off-ramps on the Gateway Motorway at Compton Road Key Objectives: • Sustainability & Optimisation, • Future proofing • Minimising Construction Impact • Safety Logan Enhancement Project (LEP) - QLD Workflow • Tender Design Tender • Detail Design Design Detail Design based on and further Construction • Further Investigation reference investigations design • Construction Detail Design Delivery Developed Substantial Final Detail Issued for Concept Design Detail Design Design Construction 25% Design 65% Design 85% Design 100% Design Case Study – Scrubby Creek Bridge (BR03) • Dual Carriageway • 8 Spans • Prestressed DUs • Transversely post- tensioned • Total Length170m • 8 Driven Piles • Built 1996 Previous Conditional Assessments • TMR Level 2 Inspection report 2008 and 2012 • TMR Level 1 Inspection report 2015 • Rehabilitation of Deck Surfacing and Pier 4 Expansion Joint 2015 Southbound• Non Level-destructive 2 Inspection- Water Integrity leaks, Vegetation Testing at Headstock, Partial Replacement of Expansion Joints Northbound Level 2 Inspection- Crack on Surfacing and Vegetation at Headstocks Design | Scrubby Creek Bridges (Plan) NORTH EXISTING BRIDGE ORIGINAL WIDENING WIDENING PROVISION LOGAN BRISBANE Image place holder EXISTING BRIDGE WIDENING BR03 SCRUBBY CREEK PLAN Design | Scrubby Creek Bridges (Cross-section) Original Widening provision in the middle Image place holder Detailed Design (Connecting Superstructure) General arrangement of stressing bar through deck units • Interface Deck Unit • Coupling of PT bars • Accessible for Maintenance Detailed Design (Connecting Substructure) • Rigid connection • Post Installed Dowels • Composite Connection Design Challenges and considerations For 2 no.s PT bars on Scrubby Creek Bridges that were identified as condition state of 3 in previous NDT report as per • Available Information and gaps SWTC. Undertake design check • Connection of the existing and new structure and core out, remove bars for visual assessment, unless other bars identified as more representative • Design for each of the construction stages Are the bars in No further rectification work satisfactory condition required for the remaining PT based on visual bars • Bridge Loadings inspection Yes No Identify the location and assess the nature of the • Integrity of transverse PT bars observed defects. Assess overall bar condition and Level 2 inspection assessment, apply engineering judgement to determine appropriate actions Provide a desktop analysis Bridge capacity Yes advising client of future adequate without maintenance requirements for Category 3 bars? PT bar monitoring and replacements No Core out, remove and replace the worst Condition State 3 PT bar Yes The actual condition No Any additional of the PT bar and Category 3 PT bars grout satisfactory? identified? Yes No No further rectification work required for the remaining PT bars Further Investigations and Construction Condition of Existing Structure • Non Destructive Testing • Categorise Condition • Confirmation of Condition • Undertaken by specialist Contractor • Piles not driven to set • Cast in place piles required for design Construction | Key Challenges and Solutions Staging Solution • Staged construction • Alignment Image place holder • Consideration of sight distance (effects of anti- gawk screens) • Limited access- worked within construction program Construction | Key Challenges and Solutions Proximity Solution • Mitigated risks of damage to existing pile Image place holder • Worked with Contractor to devise solution • Removed pile for increased tolerance Construction | Key Challenges and Solutions Tie-in Existing Solution • Adjustable mortar pad heights Figure 1: Typical Cross section Image place holder • Oversized voids • Alignment adjusted • Worked with Construction to modify dowel design Figure 2: Abutment Dowelling Recommendations • Not as ‘simple’ as it appears • Clients - Provide as much record information as possible • Designers - Ongoing and early engagement between Asset Owner, Authorities, Image place holder Contractor, Reviewers and Designers • Communicate design sensitivity • Authorities - Plan for future Construction | Current status • Commenced in June 2017 • Enhanced Safety • Expected Completed Mid 2019 • Enhanced Connectivity Image place holder www.ghd.com.

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    21 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us