EAST-WEST TIE TRANSMISSION PROJECT AMENDED ENVIRONMENTAL ASSESSMENT REPORT

APPENDIX 16-III Heritage Impact Assessment

September 2018 Project No. 1536607/2000/2219 Ministry of Tourism, Ministère du Tourisme, Culture and Sport de la Culture et du Sport Heritage Program Unit Unité des programmes patrimoine Programs and Services Branch Direction des programmes et des services 401 Bay Street, Suite 1700 401, rue Bay, Bureau 1700 Toronto ON M7A 0A7 Toronto ON M7A 0A7 Tel: 416 314 7182 Tél: 416 314 7182 Fax: 416 212 1802 Téléc: 416 212 1802

August 3, 2018 (EMAIL ONLY)

Corrine Miller, Senior Environmental Advisor NextBridge Infrastructure E: [email protected]

RE: MTCS file #: 0000483 Proponent: Nextbridge Infrastructure Subject: East-West Tie Line Transmission Project Heritage Impact Assessment Location: District of Thunder Bay,

Dear Adam Wright:

This office has reviewed the Heritage Impact Assessment prepared by Golder Associates Ltd. dated July 13, 2018.

The Report recommends the following:

Construction Phase:

o Avoid the Angler Internment Camp; . Prohibit use of ATV trail west of the existing Hydro One transmission corridor as a temporary access road. o If this section of trail must be used as an access road, the following actions should be prohibited: . Improvements beyond basic re-surfacing; . Excavation; and . Removing existing access road infrastructure. o If cultural material such as artifacts are found while making improvements to the trail or during use of the temporary access route, implement the Project Discovery of Heritage or Archaeological Resources Contingency Plan. o Site plan control and communication; o The Angler Internment Camp site should be clearly marked on project mapping and communicated to all project personnel for avoidance during construction phases of the Project.

Operation Phase:

o Site plan control and communication; . The Angler Internment Camp site should be clearly marked on project mapping and communicated to all project personnel for avoidance during operation phases of the Project. o If cultural material such as artifacts are found while making improvements to the trail or during use of the temporary access route, enact the Project Discovery of Heritage or Archaeological Resources Contingency Plan

In addition, a contingency plan has been developed in case of unexpected discoveries of cultural heritage resources not previously identified and is discussed in section 8.1.5 of the report. The activities will be implemented in the event previously unidentified cultural heritage resources are suspected or encountered.

Based on the information contained in the Report, the Ministry is satisfied that the heritage assessment process and reporting are consistent with the applicable heritage assessment requirements.

Please note that the Ministry makes no representation or warranty as to the completeness, accuracy or quality of the heritage assessment report (please see Note 1).

This letter does not waive any requirements under the Ontario Heritage Act.

This letter does not constitute approval of the project. Approvals or licences for the project may be required under other statutes and regulations. Please ensure that you obtain all required approvals and/or licences.

If new information or substantive project changes arise after issuance of this letter, additional assessment or reporting may be required. If additional reporting or revisions are required, they should be submitted to the Ministry for review. Upon completion of that review, the Ministry will determine if any revisions to the content of this letter are required.

Should you have any questions or require any further information, please do not hesitate to contact me.

Sincerely,

Jeff Elkow Heritage Planner [email protected]

Copied to: Adam Wright, Special Project Officer, MECP [email protected]

Henry Cary, Golder Associates [email protected]

Karla Barboza, (A) Team Lead, Heritage, MTCS [email protected]

It is the sole responsibility of proponents to ensure that any information and documentation submitted as part of their EA report or file is accurate. MTCS makes no representation or warranty as to the completeness, accuracy or quality of the any checklists, reports or supporting documentation submitted as part of the EA process, and in no way shall MTCS be liable for any harm, damages, costs, expenses, losses, claims or actions that may result if any checklists, reports or supporting documents are discovered to be inaccurate, incomplete, misleading or fraudulent.

Please notify MTCS if archaeological resources are impacted by EA project work. All activities impacting archaeological resources must cease immediately, and a licensed archaeologist is required to carry out an archaeological assessment in accordance with the Ontario Heritage Act and the Standards and Guidelines for Consultant Archaeologists.

If human remains are encountered, all activities must cease immediately and the local police as well as the Cemeteries Regulation Unit of the Ministry of Government and Consumer Services must be contacted. In situations where human remains are associated with archaeological resources, MTCS should also be notified to ensure that the site is not subject to unlicensed alterations which would be a contravention of the Ontario Heritage Act.

Note 1: In no way will the Ministry be liable for any harm, damages, costs, expenses, losses, claims or actions that may result: (a) if the Report or its recommendations are discovered to be inaccurate, incomplete, misleading or fraudulent; or (b) from the issuance of this letter. Further measures may need to be taken in the event that additional heritage resources are identified or the Report is otherwise found to be inaccurate, incomplete, misleading or fraudulent. REPORT Heritage Impact Assessment East-West Tie Transmission Project

Submitted to: NextBridge Infrastructure LP Att: Corinne Miller Senior Environmental Advisor 390 Bay Street, Suite 1720 Toronto, Ontario M5H 2Y2NextBridge

Submitted by: Golder Associates Ltd. 1931 Robertson Road Ottawa, Ontario, K2H 5B7 Canada

+1 (613) 592 9600

1536607-2000-R01

July 13, 2018 July 13, 2018 1536607-2000-R01

Distribution List

1 e-copy - NextBridge Infrastructure LP

1 e-copy - Golder

i

July 13, 2018 1536607-2000-R01

Executive Summary

This Executive Summary highlights the key points; for complete information and results the reader should examine the report in full.

In December 2015, NextBridge Infrastructure LP retained Golder Associates Ltd. (Golder) to provide a number of services for an Environmental Assessment (EA) of the East-West Tie Transmission Project, a proposed 450-km long double-circuit 230 kV transmission line in northwestern Ontario between the Lakehead Transformer Station in the Municipality of Shuniah, near the City of Thunder Bay, to the Wawa Transformer Station located east of the Municipality of Wawa. To address potential impacts to cultural heritage resources, Golder provided a preliminary screening and assessment of the effects for the Environmental Assessment Report for the East-West Tie Transmission Project (Section 16: Cultural Heritage Resources), then conducted a Heritage Impact Assessment (HIA) for cultural heritage resources identified during the preliminary screening.

During the preliminary screening, seven potential cultural heritage sites were identified to be at risk of direct impact. These included six mines and quarries, and an internment camp for Japanese-Canadians and German Prisoners of War established during the Second World War known as the ‘Angler Internment Camp’. During preparation of this HIA, an eighth cultural heritage resource was identified —the Aguasabon River and Hays Lake near the community of .

Evaluation of these sites using the criteria prescribed in Ontario Regulation 9/06 determined that:  The Gananoque Vein Gold Mine and Halonen Fluorite Mine could not be evaluated since the sites could not be found within the Project Local Study Area. It is possible the sites are not in the LSA and/or the sites have been reclaimed by the forest.  The Molybdenite Lake Prospect and Bishop Lead Occurrence mine sites are not of cultural heritage value or interest since they do not meet any criteria of O. Reg. 9/06;  The Angler/Petrunka and Mackenzie Quarry sites are not of cultural heritage value or interest since they do not meet any criteria of O. Reg. 9/06;  The Angler Internment Camp is of cultural heritage value or interest since it meets six criteria of O. Reg. 9/06; and  The Aguasabon River and Hays Lake is of cultural heritage value or interest since it meets two criteria of O. Reg. 9/06.

ii

July 13, 2018 1536607-2000-R01

Golder determined that the Project will not have an adverse direct or indirect impact on the cultural heritage value of the Aguasabon River and Hays Lake. However, this HIA also determined that, without mitigation measures the Angler Internment Camp is at risk of direct adverse impact from the Project. Golder therefore recommends the following actions prior to and during construction.  Avoidance: Project operations should avoid the Angler Internment Camp;  Site plan control and communication: The Angler Internment Camp should be clearly marked on project mapping and communicated to all project personnel for avoidance during construction; and,  Monitoring and contingency planning: Periodic monitoring should be conducted during construction to ensure that the Angler Internment Camp is being avoided, and the ‘Discovery of Heritage or Archaeological Resources Contingency Plan’ in Section 6.4 of the Construction Environmental Protection Plan (Appendix 4- II of the EA Report) should be followed during construction in the area adjacent to the Angler Internment Camp.

iii

July 13, 2018 1536607-2000-R01

Study Limitations

Golder Associates Ltd. (Golder) has prepared this report in a manner consistent with the guidance developed by the Ontario Ministry of Tourism, Culture and Sport (MTCS), Culture Division, Programs and Services Branch, Heritage Program Unit, subject to the time limits and physical constraints applicable to this report. No other warranty, expressed or implied is made.

This report has been prepared for the specific site, design objective, developments and purpose described to Golder by NextBridge Infrastructure LP (the Client). The factual data, interpretations and recommendations pertain to a specific project as described in this report and are not applicable to any other project or site location.

The information, recommendations and opinions expressed in this report are for the sole benefit of the Client. No other party may use or rely on this report or any portion thereof without Golder’s express written consent. If the report was prepared to be included for a specific permit application process, then upon the reasonable request of the Client, Golder may authorize in writing the use of this report by the regulatory agency as an Approved User for the specific and identified purpose of the applicable permit review process. Any other use of this report by others is prohibited and is without responsibility to Golder. The report, all plans, data, drawings and other documents as well as electronic media prepared by Golder are considered its professional work product and shall remain the copyright property of Golder, who authorizes only the Client and Approved Users to make copies of the report, but only in such quantities as are reasonably necessary for the use of the report by those parties. The Client and Approved Users may not give, lend, sell, or otherwise make available the report or any portion thereof to any other party without the express written permission of Golder. The Client acknowledges the electronic media is susceptible to unauthorized modification, deterioration and incompatibility and therefore the Client cannot rely upon the electronic media versions of Golder’s report or other work products.

Unless otherwise stated, the suggestions, recommendations and opinions given in this report are intended only for the guidance of the Client in the design of the specific project.

iv

July 13, 2018 1536607-2000-R01

Project Personnel

Project Director Danny da Silva, B.Sc., B.A.Sc., P.Eng., Principal, Project Director

Project Manager Tamara Skillen, BES, MPA, Associate, Project Manager

Project Coordinator Julie Carignan, B.Sc., RPF, Environmental Specialist, Project Coordinator

Task Manager Henry Cary, Ph.D., CAHP, Cultural Heritage Specialist

Report Production Benjamin Holthof, M.M.A., M.Pl., CAHP, Cultural Heritage Specialist

Henry Cary, Ph.D., CAHP

Research Shannen Stronge, M.A., Cultural Heritage Specialist

Benjamin Holthof, M.M.A., M.Pl., CAHP,

Henry Cary, Ph.D., CAHP

Field Investigation Benjamin Holthof, M.M.A., M.Pl., CAHP

Stephen Jarrett, M.A., Cultural Heritage Specialist

Mapping and Illustrations Jennie Byron, B.Sc., GIS Analyst

Senior Review Hugh Daechsel, M.A. Principal, Senior Archaeologist

Proponent Contact

NextBridge Infrastructure LP Corinne Miller, Senior Environmental Advisor 390 Bay Street, Suite 1720 Toronto, Ontario, M5H 2Y2

Acknowledgements

Library and Archives Canada

University of British Columbia Library, Rare Books and Special Collections, Japanese Canadian Photograph Collection.

Western University, Michael O’Hagan, Ph.D. Candidate, History

v

July 13, 2018 1536607-2000-R01

Table of Contents

1.0 INTRODUCTION ...... 1

2.0 SCOPE AND METHOD...... 3

2.1 Input from Consultation and Engagement ...... 4

3.0 CULTURAL HERITAGE RESOURCE SCREENING SUMMARY...... 6

4.0 PLANNING, LEGAL, AND REGULATORY CONTEXT ...... 8

4.1 Federal and International Heritage Policies ...... 8

4.2 Provincial Heritage Policies ...... 9

4.2.1 Environmental Assessment Act ...... 9

4.2.2 Planning Act and Provincial Policy Statement ...... 9

4.2.3 Ontario Heritage Act and Ontario Regulation 9/06 ...... 10

4.2.4 Provincial Guidance ...... 12

5.0 GEOGRAPHIC AND HISTORICAL CONTEXT ...... 13

5.1 Geographic Context ...... 13

5.2 Regional Historical Context ...... 13

5.2.1 European Exploration and Trade (1600s to circa 1850) ...... 13

5.2.2 Euro-Canadian Settlement (circa 1850 to present) ...... 14

5.2.3 Municipality of Wawa ...... 15

5.2.4 Town of Marathon ...... 16

5.2.5 Township of Terrace Bay ...... 16

5.2.6 Township of Nipigon ...... 16

5.2.7 City of Thunder Bay ...... 17

5.2.8 Lumber ...... 17

5.2.9 Mine and Quarry ...... 18

5.2.10 Internment Camps ...... 19

5.3 History of Potential Cultural Heritage Sites in the LSA ...... 21

5.3.1 Mine and Quarry Sites ...... 30

vi

July 13, 2018 1536607-2000-R01

5.3.1.1 Gananoque Vein Gold Mine (1897 – 1899) ...... 30 5.3.1.2 Molybdenite Lake Prospect (1905 – 1964) ...... 30 5.3.1.3 Angler Granite Quarry/ Petrunka (1929 – 1960s) ...... 31 5.3.1.4 Halonen Fluorite Mine (1974 – 1986) ...... 31 5.3.1.5 Bishop Lead Occurrence ...... 31 5.3.1.6 Mackenzie Quarry (1880s) ...... 32

5.3.2 Angler Internment Camp ...... 32

5.3.3 Aguasabon River and Hays Lake ...... 35

6.0 AFFECTED ENVIRONMENT ...... 36

6.1 Gananoque Vein Gold Mine ...... 36

6.2 Molybdenite Lake Prospect ...... 37

6.3 Angler/Petrunka Granite Quarry ...... 39

6.4 Halonen Fluorite Mine ...... 41

6.5 Bishop Lead Occurrence ...... 42

6.6 Mackenzie Quarry ...... 44

6.7 Angler Internment Camp ...... 45

6.8 Aguasabon River and Hays Lake ...... 50

7.0 CULTURAL HERITAGE EVALUATION ...... 51

7.1 Gananoque Vein Gold Mine ...... 51

7.2 Molybdenite Lake Prospect ...... 51

7.3 Angler/Petrunka Granite Quarry ...... 52

7.4 Halonen Fluorite Mine ...... 53

7.5 Bishop Lead Occurrence ...... 54

7.6 Mackenzie Quarry ...... 55

7.7 Angler Internment Camp ...... 56

7.8 Aguasabon River and Hays Lake ...... 58

7.9 Evaluation Results ...... 59

8.0 IMPACT ASSESSMENT ...... 60

8.1 Project Description ...... 60

vii

July 13, 2018 1536607-2000-R01

8.1.1 Access Roads ...... 60

8.1.2 Temporary Construction Workspaces ...... 61 8.1.2.1 Storage Yards ...... 61 8.1.2.2 Laydown Yards ...... 61 8.1.2.3 Construction Camps ...... 62 8.1.2.4 Construction Easements ...... 62

8.1.3 Transmission Line ...... 62

8.1.4 Angler Re-Route ...... 67

8.1.5 Discovery of Cultural Heritage Resources Contingency Plan ...... 69

8.2 Project Phases ...... 70

8.2.1 Construction Phase ...... 70

8.2.2 Operation Phase ...... 71

9.0 IMPACT ASSESSMENT AND CONSERVATION RECOMMENDATIONS ...... 72

10.0 SUMMARY STATEMENT ...... 77

CLOSURE ...... 78

11.0 REFERENCES ...... 79

TABLES Table 1: Cultural Heritage Resources Spatial Boundaries ...... 3 Table 2: Molybdenite Lake Prospect O. Reg. 9/06 Evaluation ...... 51 Table 3: Angler/Petrunka Granite Quarry O. Reg. 9/06 Evaluation ...... 52 Table 4: Bishop Lead Occurrence O. Reg. 9/06 Evaluation ...... 54 Table 5: Mackenzie Quarry O. Reg. 9/06 Evaluation ...... 55 Table 6: Angler Internment Camp O. Reg. 9/06 Evaluation ...... 56 Table 7: Aguasabon River and Hays Lake O. Reg. 9/06 Evaluation ...... 58 Table 8: Angler Internment Camp - Assessment of Direct and Indirect Adverse Impacts Resulting from the Project ...... 73 Table 9: Aguasabon River and Hays Lake - Assessment of Direct and Indirect Adverse Impacts Resulting from the Project ...... 76

viii

July 13, 2018 1536607-2000-R01

FIGURES Figure 1: East-West Tie Transmission Project ...... 2 Figure 2: Gananoque Vein Gold Mine Site Location...... 22 Figure 3: Molybdenite Lake Prospect Site Location ...... 23 Figure 4: Angler/Petrunka Granite Quarry Site Location...... 24 Figure 5: Halonen Fluorite Mine Site Location...... 25 Figure 6: Bishop Lead Occurrence Site Location...... 26 Figure 7: Mackenzie Quarry Site Location...... 27 Figure 8: Angler Internment Camp Site Location...... 28 Figure 9: Aguasabon River and Hays Lake Location...... 29 Figure 10: Layout of Angler Internment Camp 1941-1946...... 33 Figure 11: Entrance Gate to the Angler Internment Camp (Library and Archives Canada)...... 34 Figure 12: Winter at the Angler Internment Camp (Japanese Canadian Photograph Collection, University of British Columbia Library)...... 34 Figure 13: Japanese Internees at the Angler Internment Camp (Japanese Canadian Photograph Collection, University of British Columbia Library)...... 35 Figure 14: View facing south of the location identified in AMIS as the Gananoque Vein Gold Mine Site...... 36 Figure 15: View facing west of large rocks and thick vegetation growth around the location identified in AMIS as the Gananoque Vein Gold Mine Site...... 37 Figure 16: View facing north of exposed and broken rock from the Molybdenite Lake Prospect explorations...... 38 Figure 17: View facing west of vegetation and rocks in one of the Molybdenite Lake Prospect mine trenches...... 38 Figure 18: View facing north along the CPR rail line running through the Angler Granite Quarry/Petrunka...... 39 Figure 19: View facing west from the centre of the existing transmission corridor of the area around the Angler/Petrunka Granite Quarry site...... 40 Figure 20: View facing north of rocks cut from the Angler/Petrunka Granite Quarry, view facing north...... 40 Figure 21: View facing east of a large mechanical winch or part of a crane near the site of the Angler/Petrunka Granite Quarry...... 41 Figure 22: View facing east of the forest at the site recorded in AMIS as the Halonen Fluorite Mine...... 42 Figure 23: View facing southwest of a dirt track through the forest next to the Bishop Lead Occurrence site...... 43 Figure 24: View facing east of the exposed rock from the walls of the pit at the Bishop Lead Occurrence...... 43 Figure 25: The landscape north of the Mackenzie Quarry, view facing northeast...... 44 Figure 26: The Mackenzie Quarry, view facing north...... 45 Figure 27: View facing east of dense forest between the Angler Internment Camp and the railway...... 46

ix

July 13, 2018 1536607-2000-R01

Figure 28: View facing southwest of the reforested area at the south extent of the Angler Internment Camp...... 46 Figure 29: View facing east over the Angler Creek valley towards the Angler Internment Camp...... 47 Figure 30: View facing north of a dump of metal artifacts including cans and pots between the Angler Internment Camp and railway line...... 47 Figure 31: View facing west of a poured concrete foundation of one of the internee quarters...... 48 Figure 32: View facing east of linear mounds at the approximate location of internment camp buildings...... 48 Figure 33: View facing southeast of a trench through the middle of the internment camp...... 49 Figure 34: View facing north of stove or chimney pipe and a wood lined pit, possibly a well near the site of former internee quarters...... 49 Figure 35: View facing southwest of a steel fencepost in a trench near the north end of the Internment Camp ...... 50 Figure 36: View facing north-northwest up the Aguasabon River/ Hays Lake from a point approximately 1.9 km south of the project footprint...... 50 Figure 40: Proposed Project Components relative to the Angler Internment Camp site...... 68 Figure 41: Angler Internment Camp Conservation Recommendations...... 75

APPENDICES APPENDIX A Statements of CHVI for the Angler Internment Camp, and the Aguasabon River and Hays Lake

x

July 13, 2018 1536607-2000-R01

1.0 INTRODUCTION In December 2015, NextBridge Infrastructure LP (NextBridge) retained Golder Associates Ltd. (Golder) to provide a number of services for an Environmental Assessment (EA) of the East-West Tie Transmission Project (the Project), a proposed 450-km long double-circuit 230 kV transmission line in northwestern Ontario between the Lakehead Transformer Station in the Municipality of Shuniah, near the City of Thunder Bay, to the Wawa Transformer Station located east of the Municipality of Wawa (Figure 1). The Project is identified as a priority by the Province of Ontario, and the Independent Electricity System Operator (IESO) has deemed it necessary to meet future electricity demand in northwestern Ontario. To address potential impacts to cultural heritage resources, Golder provided a preliminary screening and assessment of the effects for the Environmental Assessment Report for the East-West Tie Transmission Project (the amended EA Report, Section 16: Cultural Heritage Resources) (NextBridge 2018). Based on the results of this screening, NextBridge retained Golder to conduct a Heritage Impact Assessment (HIA).

Following guidelines and comments provided on the EA Report (NextBridge 2018) by the Ministry of Tourism, Culture and Sport (MTCS), and principles outlined in the Canada’s Historic Places Standards and Guidelines for the Conservation of Historic Places in Canada (2010), this HIA provides:  a summary of the cultural heritage resource screening conducted during the Environmental Assessment;  a background on the legislative framework, purpose and requirements of an HIA and the methods used to investigate and evaluate cultural heritage resources in the Local Study Area (LSA);  an overview of the LSA’s geographic context and history;  an inventory and evaluation of the potential cultural heritage resources identified in the LSA;  a description of the proposed Project and an assessment of its predicted impacts and residual effects on known or newly identified cultural heritage resources in the LSA; and  recommendations for future action.

1

LONG LAKE

LAKE NIPIGON

LONG LAKE

AGUASABON RIVER NIPIGON (! HALONEN FLUORITE MINE SITE KABINAKAGAMI LAKE !. HAYS LAKE DOG BISHOP LEAD ANGLER/PETRUNKA LAKE GRANITE QUARRY OCCURRENCE SITE !. ANGLER INTERNMENT (! CAMP SCHREIBER (! !. TERRACE BAY MARATHON (!

TRANSCANADA HIGHWAY WHITE RIVER (! MCKENZIE QUARRY !.

(! THUNDER BAY

C A N A D A MOLYBDENITE U . S . A . LAKE SITE !. WAWA (! !.

GANANOQUE VEIN GOLD MINE

LEGEND KEY MAP REFERENCE(S) Project Component Base Data Known or Potential Cultural Heritage Resource Site Location BASE DATA: MNRF LIO (2018), CANVEC (2017), DILLON (2014, 2015), MNDM (2017) !. Hudson Bay PROJECT COMPONENTS: PROVIDED BY NEXTBRIDGE (2018) Preferred Route Transmission Line (! Municipality Known or Potential Cultural Heritage Resource Site Location IMAGERY: THE STANDARD ESRI WORLD IMAGERY: ESRI, DIGITALGLOBE, GEOEYE, I-CUBED, M A N I T O B A 0 20 40 60 Highway EARTHSTAR GEOGRAPHICS, CNES/AIRBUS DS, USDA, USGS, AEX, GETMAPPING, AEROGRID, ³ IGN, IGP, SWISSTOPO, AND THE GIS USER COMMUNITY Local Road James PRODUCED BY GOLDER ASSOCIATES LTD. UNDER LICENSE FROM ONTARIO MINISTRY OF Bay 1:1,000,000 KILOMETRES NATURAL RESOURCES, © QUEENS PRINTER 2018 PROJECTION: TRANSVERSE MERCATOR DATUM: NAD 83 COORDINATE SYSTEM: UTM ZONE 16N O N T A R I O Q U É B E C CLIENT PROJECT HERITAGE IMPACT ASSESSMENT, EAST-WEST TIE

MARATHON THIS IF MEASUREMENT ISSHOWN, WHAT DOES SHEETTHE NOT SIZE MATCH HAS BEEN MODIFIEDANSI B FROM: J" TRANSMISSION PROJECT THUNDER BAY J" J" WAWA 25mm Lake Superior

OTTAWA YYYY-MM-DD 2018-07-11 TITLE Georgian J" Bay DESIGNED GOLDER JR U. S. A. Lake EAST-WEST TIE TRANSMISSION PROJECT Huron J" TORONTO Lake PREPARED GOLDER JB Lake Ontario Michigan Lake REVIEWED GOLDER BH Erie PROJECT NO. CONTROL REV. FIGURE APPROVED GOLDER HJD 1536607 1

PATH: S:\Clients\NextBridge\East_West_Tie\99_PROJ\1536607_EA\40_PROD\0040_HIA_Report\1536607-0040-HC-0001.mxd PATH: 2:49:22 PM PRINTED AT: 2018-07-11 ON: 1 0 July 13, 2018 1536607-2000-R01

2.0 SCOPE AND METHOD The scope of this HIA was defined by a geographic study area defined in the EA Report, MTCS guidance, and consultation with MTCS during the EA reporting.

For the EA, a Regional Study Area (RSA) and a LSA were defined around the Project footprint (Table 1). The RSA extends approximately 1 km on either side of the preferred right-of-way (ROW) for the transmission corridor. The LSA extends approximately 50 metres (m) from both sides of the proposed Project footprint (i.e. the ROW and related components such as access roads and laydown yards).

Table 1: Cultural Heritage Resources Spatial Boundaries Area Spatial Boundaries Description Rationale (ha) The Project footprint is the preferred route ROW, Designed to capture the potential direct laydown yards, storage yards, construction Project footprint 5,005 effects of the physical footprint of the camps, temporary construction easements, and Project new access roads The cultural heritage resources LSA was Includes the Project footprint and extends 50 m selected to encompass direct and indirect from the Project footprint boundary (i.e., up to Cultural heritage adverse effects on cultural heritage 16,478 64 m wide ROW, new and existing access resources LSA resources that may result from roads, laydown yards, staging areas, construction activity, site or landscape construction camps) alteration, or demolition Extends 1 km from the preferred route ROW boundary, 50 m from access roads, and 500 m The cultural heritage resources RSA was from the boundary of laydown areas, storage delineated to gain a broader Cultural heritage yards, and construction camps. The 50 m spatial understanding of Euro-Canadian 123,272 resources RSA boundary for access roads is limited to those historical land use in the region and to classified as new and improvement/widening account for potential refinements to the outside the 1 km cultural heritage resources Project RSA LSA = Local Study Area; ROW = right-of-way; RSA = Regional Study Area.

During the construction phase, the Project footprint and LSA will include temporary construction laydown areas, storage yards, construction camps and temporary construction roads. During the operation phase of the Project, the footprint and LSA will include the transmission lines, towers and the necessary permanent access roads to access the tower structures for maintenance. The transmission ROW will be maintained with limited vegetation growth during the entire operational phase.

Known and potential cultural heritage resources within both the RSA and LSA were identified on the basis of the MTCS Criteria for Evaluating Potential for Built Heritage Resources and Cultural Heritage Landscapes (2016) (the MTCS Checklist, described in Section 4.2.4) and MTCS Guidelines on the Man-Made Heritage Component of Environmental Assessments (1980). Known and potential cultural heritage resources in the RSA and LSA were described in Section 16 –Cultural Heritage Resources— of the East-West Tie Transmission Project Environmental Assessment Report (‘the EA Report’, NextBridge 2018) and have been summarized in Section 3.0 of this report. Known or potential cultural heritage resources identified within the LSA were recommended for further evaluation and impact assessment.

The cultural heritage evaluation and impact assessment was limited to sites of Euro-Canadian heritage following consultation with MTCS Heritage Planner Joseph Muller on September 22, 2016. First Nations sites and cultural

3

July 13, 2018 1536607-2000-R01

heritage resources were addressed in Section 15 –Archaeological Resources— and Section 17 –Indigenous Current Use of Lands and Resources for Traditional Purposes— in the EA Report (NextBridge 2018).

To conduct this HIA, Golder:  summarized the cultural heritage screening from the EA and outlined which known and potential cultural heritage resources required attention in this HIA and which were determined to fall outside of the Project footprint or for other reasons would not require further cultural heritage study;  researched archival and published sources relevant to the history and geographic context of the RSA;  examined aerial photographs, satellite imagery, fly-over video, and the Geographic Information System (GIS) based Abandoned Mine Information System (AMIS) database for evidence of potential cultural heritage resources in the LSA;  undertook a field investigation to inventory and document known and potential cultural heritage resources identified in the LSA in the EA Report (NextBridge 2018), and to understand the wider landscape context;  evaluated potential cultural heritage resources for ‘cultural heritage value or interest’ (CHVI) using the criteria prescribed in Ontario Regulation 9/06 (O. Reg. 9/06); and  assessed the risk of adverse impact to sites of CHVI using MTCS and other guidance. A number of primary and secondary sources, including historic maps, aerial imagery, photographs, and research articles were accessed from the National Air Photo Library, Library and Archives Canada, Archives of Ontario, and online sources.

This HIA drew on public consultation and engagement completed as part of the EA, the details of which are outlined in Section 2 of the EA, and summarized in Section 2.1 below. Relevant input was considered for both the cultural heritage screening conducted as part of the EA (Section 16) and this assessment. Public consultation for the project is documented in Appendices 2-III and 2-IX of the EA Report (NextBridge 2018). These appendices were updated in June 2018 and will be made available to the MTCS.

Preliminary field reconnaissance of the Project footprint was conducted by helicopter and on foot by Cultural Heritage Specialist Stephen Jarrett from October 25 to 26, 2016. Field investigations of identified sites were carried out by Cultural Heritage Specialist Benjamin Holthof between August 1 and August 3, 2017. This included photographing the sites identified in the EA Report and their setting with a Canon Rebel T3i camera and iPad 2 linked to the Collector for ArcGIS application. Guidance on identifying and evaluating cultural heritage resources was drawn from the MTCS Ontario Heritage Tool Kit and the U.S. National Parks Service National Register Bulletin Guidelines for Identifying, Evaluating and Registering Historic Mining Properties (Nobel and Spude 1997).

2.1 Input from Consultation and Engagement

Consultation and engagement for the Project considered Indigenous communities, regulatory agencies, property owners, interest holders, Crown interests and the general public. Consultation activities are described in Section 2 of the amended EA Report. The draft, final, and amended EA Reports were each subject to a public review and comment period. The following concerns related to areas of cultural importance and potential cultural heritage resources were raised during consultation and engagement and from comments received on the draft, final, and amended EA Reports.

4

July 13, 2018 1536607-2000-R01

 Ministry of Tourism, Culture and Sport (MTCS) expressed concern that potential downstream effects had not been assessed.  The Township of Terrace Bay identified the Aguasabon River as a valued natural feature of special value to the people of Terrace Bay and surrounding area and Mill Road in the Township of Terrace Bay as a historic corridor.  The Town of Marathon identified Mink Falls as an important tourist site and Port Munro, a former pulpwood storage harbour as a potential cultural heritage resource.  The Town of Marathon noted the Angler Creek World War II Internment camp, where Japanese-Canadian internees and German prisoners of war were held, and possible cemetery plots located on Angler Creek as a potential cultural heritage resource.  The Town of Marathon identified Pic River, used historically for log driving, as a potential cultural heritage resource.  Important cultural sites identified by Indigenous communities are considered in the Indigenous current use of lands and resources for traditional purposes assessment (Section 17.7 of the amended EA Report).  MTCS indicated that clarification should be sought from the Ministry of Natural Resources and Forestry (MNRF) to determine whether there are cultural heritage resources within any of the eight forest management units crossed by the project. The MNRF was contacted and asked to verify whether it has identified specific cultural heritage value or interest associated with the eight forest management units, or specific cultural heritage sites in the forest management units. In its email response dated July 9, 2018, the MNRF did not raise any heritage concerns. These comments were taken into consideration for the cultural heritage resource screening, which is described in Section 3.

5

July 13, 2018 1536607-2000-R01

3.0 CULTURAL HERITAGE RESOURCE SCREENING SUMMARY The cultural heritage resources screening undertaken during the EA was used throughout the planning process to refine the preferred route of the Project and avoid cultural heritage resources where possible. All known and potential cultural heritage resources identified during the EA include:  The Terry Fox commemorative plaque at Mile Post 3339 on the TransCanada Highway;  25 abandoned mine and quarry sites that are over 40 years old (Table 16-4 in the EA);  Port Munro, a former pulpwood storage harbour, near the Town of Marathon;  The Pic River;  The Aguasabon River, in Terrace Bay;  Mill Road, in Terrace Bay;  Mink Falls, east of Neys Provincial Park;  Canoe routes;  The Angler Internment Camp;  831 buildings, an unknown number of which are over 40 years old; and  Cultural Heritage Landscapes related to the Group of Seven. Mink Falls and Mill Road were identified during consultation and engagement (EA Section 16.1); however, both are outside of the Project RSA and well outside of the area that may be impacted by the Project. Known and potential cultural heritage resources identified during the EA, but are not within the LSA and will therefore not be impacted by the project include:  The Terry Fox commemorative plaque at Mile Post 3339 on the TransCanada Highway;  19 of the 25 abandoned mine and quarry sites that are over 40 years old;  Port Munro;  The 831 buildings identified; and  Group of Seven cultural heritage landscapes. Preliminary consultation by Dillon (2014) identified the Aguasabon River, specifically the Aguasabon Falls and gorge as a significant natural feature and tourist attraction that may have potential CHVI. The falls and gorge are outside of the RSA, but the Aguasabon River and Hays Lake –the impoundment lake behind the Hays Lake control dam in the community of Terrace Bay— is crossed by the Project approximately 6 km north of community of Terrace Bay. Research for this HIA found that the River was altered by power generation projects in the mid- 20th century and may have potential cultural heritage value or interest for its connection to power generation and the creation of the Terrace Bay community.

6

July 13, 2018 1536607-2000-R01

Potential cultural heritage resources in or crossed by the Project in the LSA include:  The Aguasabon River;  The Pic River;  Canoe routes;  The Angler Internment Camp; and  Six abandoned mine and quarry sites. The Pic River was identified during consultation by Dillon (2015) as having potential cultural heritage value or interest associated with logging. There is also a national historic site of Canada –the Pic River Site— that consists of four archaeological sites next to the River approximately 12 km downstream (south) from the LSA and well outside of the area that would be impacted by the Project. No known historic logging sites were identified along the River in the RSA or LSA. This was determined through background research, examination of aerial photographs, a flyover of the project footprint by Cultural Heritage Specialist Stephen Jarrett in November 2016 and engagement activities undertaken as part of the EA. The Pic River in the LSA was determined to have very low potential for cultural heritage value or interest related to logging.

During the EA a large number of formal and informal canoe routes were identified as potential cultural heritage resources (EA Section 16.5.2.3.3). Most canoe routes outside of Provincial Parks are informal, although any navigable waterway could be an historic and contemporary canoe route. During consultation with communities and First Nations crossed by the Project as part of the EA, no specific canoe routes with known or potential cultural heritage value or interest were identified. Concerns expressed during consultation about canoe routes focused around continued access to canoe routes during construction, potential physical impacts construction could have on portages, and potential impacts to viewscapes. Artifacts of cultural heritage value associated with portage sites are likely to be archaeological and have been addressed as part of the archaeological assessment for the Project. Potential impacts to viewscapes in areas of concern were avoided or minimized through the EA process in consultation with the MNRF and resulted in changes to the Project footprint (e.g., removing laydown yards and relocating towers near provincial parks). Nextbridge’s Environmental Protection Plan (Appendix 4-II of the EA Report) outlines mitigation measures to ensure impacts on canoe portage routes will be minimal.

Section 16 of the EA Report (NextBridge 2018) found that the LSA contains seven sites with potential CHVI and recommended a CHER and HIA for each (combined into this HIA). These sites include the:  Angler Camp World War II Internment Camp (1941 to 1946);  Gananoque Vein Gold Mine (1897 to 1899);  Molybdenite Lake Prospect (1905 to 1964);  Angler Granite Quarry/ Petrunka (1929 to 1960s);  Halonen Fluorite Mine (1974 to 1986);  Mackenzie Quarry (1880s); and  Bishop Lead Occurrence (unknown date of operation). In addition to the sites identified in the EA, during work to complete this HIA Golder found that the Aguasabon River has potential CHVI and included it in this assessment. All eight sites are illustrated on Figure 1.

7

July 13, 2018 1536607-2000-R01

4.0 PLANNING, LEGAL, AND REGULATORY CONTEXT Cultural heritage resources are recognized, protected, and managed through a number of provincial and municipal planning and policy regimes. Although these have varying levels of priority, they are generally considered for decision-making in the cultural heritage environment. The relevant guidance, legislation, and policies are described below.

Ontario Planning Act Provincial Policy Ontario Statement Heritage Act 2014

Environmental Local Municipal Assessment LSA Heritage Policy Act

Provincial and municipal policies relevant to the heritage conservation in the LSA

4.1 Federal and International Heritage Policies Many provincial and municipal policies align in approach to the Canada’s Historic Places Standards and Guidelines for the Conservation of Historic Places in Canada (Canada’s Historic Places 2010), which was drafted in response to international and national agreements such as the 1964 International Charter for the Conservation and Restoration of Monuments and Sites (Venice Charter), 1979 Australia ICOMOS Charter for Places of Cultural Significance (Burra Charter, updated 2013), and 1983 Canadian Appleton Charter for the Protection and Enhancement of the Built Environment. The national Standards and Guidelines defines three conservation ‘treatments’ — preservation, rehabilitation, and restoration— and outlines the process, and required and recommended actions, to meet the objectives for each treatment for a range of cultural heritage resources.

At the international level, the International Council on Monuments and Sites (ICOMOS) has developed guidance on heritage impact assessments for world heritage properties, which also provide ‘best practice’ approaches for historic assets (ICOMOS 2011).

Although the Project crosses First Nations reserve lands that are administered as federal lands, none of the cultural heritage resources identified in this HIA is located on First Nations or other lands under federal heritage planning, legal or regulatory control.

8

July 13, 2018 1536607-2000-R01

4.2 Provincial Heritage Policies 4.2.1 Environmental Assessment Act The Environmental Assessment Act (2010) was legislated to ensure that Ontario’s environment is protected, conserved, and wisely managed. Under the Environmental Assessment Act, ‘environment’ includes natural elements such as air, land, water and plant and animal life, and also the ‘social, economic and cultural conditions that influence the life of humans or a community’, and ‘any building, structure, machine or other device or thing made by humans’. To determine the potential environmental effects of a new development, the EA process was created to standardize decision-making.

Prior to construction, the Project requires EA approval from the Ministry of Environment and Climate Change (MOECC) pursuant to the Environmental Assessment Act (Government of Ontario 1990). Specifically, Ontario Regulation 116/01 (O. Reg. 116/01) under the Environmental Assessment Act requires transmission line projects that are greater than 115 kilovolt (kV) and less than 500 kV, and greater than, or equal to, 50 km in length, to undergo an Individual EA. 4.2.2 Planning Act and Provincial Policy Statement The Ontario Planning Act (1990) and associated Provincial Policy Statement, 2014 (PPS 2014) provide the legislative imperative for heritage conservation in land use planning and offers guidance for what shall be conserved and what constitutes a built heritage resource and cultural heritage landscape. Both documents identify conservation of resources of significant architectural, cultural, historical, archaeological, or scientific interest as a provincial interest, and PPS 2014 further recognizes that protecting cultural heritage and archaeological resources has economic, environmental, and social benefits, and contributes to the long-term prosperity, environmental health, and social well-being of Ontarians. The Planning Act serves to integrate this interest with planning decisions at the provincial and municipal level, and states that decisions affecting land use planning ‘shall be consistent with’ PPS 2014.

The importance of identifying and evaluating built heritage and cultural heritage landscapes is recognized in two sections of PPS 2014:  Section 2.6.1 – ‘Significant built heritage resources and significant heritage landscapes shall be conserved’; and  Section 2.6.3 – ‘Planning authorities shall not permit development and site alteration on adjacent lands to protected heritage property except where the proposed development and site alteration has been evaluated and it has been demonstrated that the heritage attributes of the protected heritage property will be conserved.’

9

July 13, 2018 1536607-2000-R01

PPS 2014 defines significant as resources ‘determined to have cultural heritage value or interest for the important contribution they make to our understanding of the history of a place, an event, or a people’, and conserved as ‘the identification, protection, management and use of built heritage resources, cultural heritage landscapes, and archaeological resources in a manner that ensures their cultural heritage value of interest is retained under the Ontario Heritage Act.’ Built heritage resources, cultural heritage landscapes, heritage attributes, and protected heritage property are also defined in the PPS:  Built heritage resources: a building, structure, monument, installation or any manufactured remnant that contributes to a property’s cultural heritage value or interest as identified by a community, including an Aboriginal [Indigenous] community. Built heritage resources are generally located on property that has been designated under Parts IV or V of the Ontario Heritage Act (OHA), 1990, or included on local, provincial and/or federal registers.  Cultural heritage landscapes: a defined geographical area that may have been modified by human activity and is identified as having cultural heritage value or interest by a community, including an Aboriginal [Indigenous] community. The area may involve features such as structures, spaces, archaeological sites or natural elements that are valued together for their interrelationship, meaning or association. Examples may include, but are not limited to, heritage conservation districts designated under the Ontario Heritage Act; villages, parks, gardens, battlefields, main streets and neighbourhoods, cemeteries, trailways, viewsheds, natural areas and industrial complexes of heritage significance; and areas recognized by federal or international designation authorities (e.g., a National Historic Site or District designation, or a UNESCO World Heritage Site).  Heritage attribute: the principal features or elements that contribute to a protected heritage property’s cultural heritage value or interest, and may include the property’s built or manufactured elements, as well as natural landforms, vegetation, water features, and its visual setting (including significant views or vistas to or from a ‘protected heritage property’).  Protected heritage property: property designated under Parts IV, V or VI of the Ontario Heritage Act; property subject to a heritage conservation easement under Parts II or IV of the Ontario Heritage Act; property identified by the Province and prescribed public bodies as provincial heritage property under the Standards and Guidelines for Conservation of Provincial Heritage Properties; property protected under federal legislation, and UNESCO World Heritage Sites. 4.2.3 Ontario Heritage Act and Ontario Regulation 9/06 The Province and municipalities are enabled to conserve significant individual properties and areas through the Ontario Heritage Act (OHA). Under Part III of the OHA, compliance with the Standards and Guidelines for the Conservation of Provincial Heritage Properties is mandatory for provincially-owned and administered heritage properties, and holds the same authority for ministries and prescribed public bodies as a Management Board or Cabinet directive.

For municipalities, Part IV and Part V of the OHA enables the minister or a municipal council to ‘designate’ individual properties (Part IV), or properties within a heritage conservation district (HCD) (Part V), as being of ‘cultural heritage value or interest’ (CHVI). Evaluation for CHVI under the OHA is guided by Ontario Regulation 9/06 (O. Reg. 9/06), which prescribes the criteria for determining cultural heritage value or interest and for properties of Provincial significance by Ontario Regulation 10/06 (O. Reg. 10/06), which prescribes the criteria for determining cultural heritage value or interest of provincial significance.

10

July 13, 2018 1536607-2000-R01

The O. Reg. 9/06 criteria are as follows:

1) The property has design value or physical value because it:

i) is a rare, unique, representative or early example of a style, type, expression, material or construction method;

ii) displays a high degree of craftsmanship or artistic merit; or

iii) demonstrates a high degree of technical or scientific achievement.

2) The property has historic value or associative value because it:

i) has direct associations with a theme, event, belief, person, activity, organization, or institution that is significant to a community;

ii) yields, or has the potential to yield information that contributes to an understanding of a community or culture; or

iii) demonstrates or reflects the work or ideas of an architect, artist, builder, designer, or theorist who is significant to a community.

3) The property has contextual value because it:

i) is important in defining, maintaining or supporting the character of an area; ii) is physically, functionally, visually or historically linked to its surroundings; or iii) is a landmark.

The O. Reg. 10/06 criteria are:

1) The property represents or demonstrates a theme or pattern in Ontario’s history.

2) The property yields, or has the potential to yield, information that contributes to an understanding of Ontario’s history.

3) The property demonstrates an uncommon, rare or unique aspect of Ontario’s cultural heritage.

4) The property is of aesthetic, visual or contextual importance to the province.

5) The property demonstrates a high degree of excellence or creative, technical or scientific achievement at a provincial level in a given period.

6) The property has a strong or special association with the entire province or with a community that is found in more than one part of the province. The association exists for historic, social, or cultural reasons or because of traditional use.

7) The property has a strong or special association with the life or work of a person, group or organization of importance to the province or with an event of importance to the province.

8) The property is located in unorganized territory and the Minister determines that there is a provincial interest in the protection of the property.

11

July 13, 2018 1536607-2000-R01

If a property meets one or more of these criteria, it may be eligible for designation under Part IV, Section 29 of the OHA.

Designated properties, which are formally described and recognized through by-law, must then be included on a ‘Register’ maintained by the municipal clerk. At a secondary level, a municipality may ‘list’ a property on the register to indicate its potential CHVI. Importantly, designation or listing in most cases applies to the entire property, not just individual structures or features. 4.2.4 Provincial Guidance The Province, through the MTCS, has developed a series of products to advise municipalities, organizations, and individuals on heritage protection and conservation. One product used primarily for EAs is the MTCS Criteria for Evaluating Potential for Built Heritage Resources and Cultural Heritage Landscapes: A Checklist for the Non-Specialist (MTCS Checklist) (2016). This checklist helps to identify if a project area contains, or is adjacent to known cultural heritage resources, provides general direction on identifying potential built heritage resources and cultural heritage landscapes, and aids in determining the next stages of evaluation and assessment.

One criterion listed on the MTCS Checklist is if a property contains buildings or structures over 40 years old at the time of assessment. This 40 year ‘rule of thumb’ does not automatically assign cultural heritage value or interest or protection to buildings and structures older than 40 years, or exclude those built in the last 40 years, but assumes that a property’s heritage potential increases with age. If the ‘rule of thumb’ identifies potential cultural heritage resources in a study area, the MTCS Checklist advises that a Cultural Heritage Evaluation Report (CHER) be completed to evaluate if the built element or landscape meets the O. Reg. 9/06 criteria. If the MTCS Checklist further indicates that known or potential for heritage resources will be impacted by the proposed development in a study area, investigation as part of a HIA is usually necessary.

More detailed guidance on identifying, evaluating, and assessing impact to built heritage resources and cultural heritage landscapes is provided in the Ontario Heritage Tool Kit series. Of these, Heritage Resources in the Land Use Planning Process (MTCS 2006) provides an outline for the contents of a HIA, which it defines as:  ‘a study to determine if any cultural resources (including those previously identified and those found as part of the site assessment) are impacted by a specific proposed development or site alteration. It can also demonstrate how the cultural resource will be conserved in the context of redevelopment or site alteration. Mitigative or avoidance measures or alternative development or site alteration approaches may be recommended.’

Criteria to identify cultural landscapes is provided in greater detail in the Guidelines on the Man-Made Heritage Component of Environmental Assessments (1980:7), while recording and documentation procedures are outlined in the Guideline for Preparing the Cultural Heritage Resource Component of Environmental Assessments (1992: 3-7). The latter document also stresses the importance of identifying and gauging the cumulative effects of a Class EA development (MTCS 1992:8).

12

July 13, 2018 1536607-2000-R01

5.0 GEOGRAPHIC AND HISTORICAL CONTEXT 5.1 Geographic Context The geology of the LSA includes the Southern Craton and Superior Province (Ontario Geologic Survey 1991), which is primarily granitic or gneissic bedrock, with intrusive areas of less acidic metavolcanic and metasedimentary rock and formations of basalt and other volcanic rocks. Greenstone, siltstone, and shale are also present in the geology, terrain, and soils (Sutcliffe 1991). The LSA is also in the Port Arthur Hills and Abitibi Upland physiographic divisions of the James Region of the Precambrian Canadian Shield (Bostock 2014). The Abitibi Uplands form a rocky landscape scattered with lakes and large areas covered by deposits from glaciation, whereas the Port Arthur Hills around the City of Thunder Bay consist of ridges produced by folded sequences of diabase sills and sedimentary rocks (Thurston 1991). Soils in the area are varied and include glaciolacustrine deposits, flood plains, remnants of terraces, gravel, sand and organic peats.

The Project crosses the Lake Abitibi, Nipigon, Temagami, and Pigeon River ecoregions of the Ontario Shield Ecozone (Crins et al. 2009), which are typified by a moist and cold climate, although Lake Superior has a moderating effect on the temperature and precipitation. The forest throughout the LSA consists of mixed and boreal forest. 5.2 Regional Historical Context 5.2.1 European Exploration and Trade (1600s to circa 1850) European exploration of northern Ontario in the Lake Superior region began in the 17th century with the French. The first known explorers on the lake were Pierre Esprit Radisson and Médard Chouart, who set off from Quebec in 1658 and returned two years later with “a rich cargo of furs and the knowledge that the best furs could be obtained to the north and west of Superior” (Stuart 2003:16).

As French exploration and trade increased, many Frenchmen married First Nation women, and their children, who became known as Métis, established a unique identity that was both connected to, and distinct from, European and First Nation cultures (Steckley and Cummins 2008).

English interest in the area officially began on May 2, 1670, when the Hudson’s Bay Company (HBC) was incorporated by Royal Charter as “The Governor and Company of Adventurers of England trading into Hudson’s Bay.” The charter also included a monopoly over trade, particularly for furs, with Indigenous groups in areas where rivers and streams flow into Hudson Bay. This area was called Prince Rupert’s Land and included 3.9 million km2.

In response, the French built posts between 1687 and 1713 on Lake Superior at what are now the City of Thunder Bay, the Township of Nipigon, and Michipicoten, and openly fought the English for control of the fur trade in northern Ontario (Chisholm and Gutsche 1998). An uneasy peace was established after the signing of the Treaty of Utrecht in 1713, the main goal of which was to end the War of Spanish Succession between Britain and France (Miquelon 2001). As a concession, France agreed to surrender the area around Hudson Bay, including the English trading posts they had annexed (Stuart 2003). After the Seven Years War ended with the Treaty of Paris in 1763, North America was ceded to the British, and the French posts on Lake Superior were abandoned to independent traders.

13

July 13, 2018 1536607-2000-R01

Prior to 1900, the fur trade was a driving force in the economic development of northern Ontario (Baldwin 1976). Depleted beaver stocks in southern areas required traders to venture further north and west to procure a plentiful supply of furs (Morse 1979). For traders based in Montreal, the logistical challenges grew as the distances to transport furs and trade items became greater. By 1778, many independent traders had merged into loose unions that would coalesce as the North West Company (NWC) in 1784 (Morse 1979). The HBC entered into direct competition with the NWC on Lake Superior by building trading posts in 1795 (Chisholm and Gutsche 1998). The NWC countered in 1803 by building a new fort called Fort William at its Lake Superior headquarters, in what is now the City of Thunder Bay. Declining fur returns during this time also forced the HBC and NWC to change their trading policies from river mouth trading to establishing permanent posts farther inland (Morse 1979). From the early part of the 1770s until 1821, competition between the HBC and NWC was fierce. With both companies unable to sustain the prolonged and intense competitions, they amalgamated into a single operation under the overall banner of the HBC (Klimko 1994). Extensive trade in northern Ontario continued throughout the 18th and 19th centuries, but gradually the HBC shifted its focus towards western Canada, and abandoned many of the trading posts and forts in northern Ontario.

Because trading posts moved frequently, and some were run by independent merchants, it is difficult to estimate the exact number in a given area. Although some trading posts became permanent settlements, most survive as archaeological sites, owing to their expedient construction and short-lived occupations.

Seven trading posts in six locations were known to operate along the north shore of Lake Superior between the City of Thunder Bay and Michipicoten. From west to east, these include Pointe de Meuron (HBC post, date unknown), Fort Kaministiquia (French post, circa 1678 – later replaced by Fort William), Fort William (NWC post, circa 1804), Red Rock House (HBC post, circa 1820), Fort Camanistigoyan (French post, circa 1678), Fort Pic (NWC post, circa 1790) and Fort Michipicoten (French post, circa 1750) (Voorhis 1930). Mapping of fur trade posts is not comprehensive or accurate; however, descriptions of these trading posts suggest none was located in the vicinity of the Project. 5.2.2 Euro-Canadian Settlement (circa 1850 to present) Settlement by Euro-Canadians in northern Ontario for farming, forestry, mining and other forms of resource extraction began around the middle of the 19th century. This was substantially enabled by completion of a railway from Toronto to Collingwood on Georgian Bay in 1855 and construction of a canal at Sault Ste. Marie the same year for marine transport from Lake Huron to Lake Superior (Bray 1984). At first, travel and trade around the north shore of Lake Superior relied on the water routes, but this began to change in the 1880s with the construction of the Canadian Pacific Railway (CPR). By 1884, the CPR finished its route across the north end of the lake. Construction of the railway relied on marine transportation, and small ports were built approximately 100 km apart along the north shore of Lake Superior to deliver supplies for railway construction, leading to the development of small communities and tracks or roads to support the railway. Other rail lines included the Algoma Central Railway, and the Temiskaming and Northern Ontario Railway (Chisholm and Gutsche 1998).

Census records from 1871 list 15,000 people inhabiting northern Ontario, clustered in a few settlements, primarily Bruce Mines and Sault Ste. Marie. By 1911, largely as a result of new railways, the population had increased to 215,000 people scattered over a wide geographical area (Bray 1984). Government policy in the early 20th century drove much of the development of northern Ontario through infrastructure creation and geological surveys. Aviation also played a role after World War I in aiding survey of difficult terrain and supplying remote communities.

14

July 13, 2018 1536607-2000-R01

Rail infrastructure, including roads, was difficult to build in northern Ontario due to challenging terrain and environmental conditions. As early as 1912, the Province began to fund roads, bridges and transportation facilities in northern Ontario, and by 1930 the “Nipigon Highway” between Port Arthur and the Township of Nipigon opened (Bagnato and Shragge 1984). The Trans-Canada highway began with federal funding in 1949, but progress was slow, with the section between the Agawa River and the Town of Marathon not completed until 1956. A complete highway across Northern Ontario, and connected to the Municipality of Wawa, was operational by 1960 (Bagnato and Shragge 1984).

Agriculture has aided the development of northern Ontario, although climate and soil conditions limit the region’s capacity to support a viable agricultural economy. The majority of the area around the Project is unsuitable for large-scale agriculture use since the typical soil formation on the Canadian Shield produces sharply undulating terrain with minimal overburden and large areas of exposed bedrock. Despite these challenges, agricultural settlement has occurred on small areas of fertile land close to mining and lumbering centres such as Sault Ste. Marie, the City of Thunder Bay, and on Manitoulin Island (Brozowski et.al. 1984). These farms were vital for supplying lumber and mining industry workers and their horses with an affordable food source.

The Ontario government actively promoted the agricultural potential of the north in the last quarter of the 19th century and attracted a large number of prospective farmers to settle in the region. However, by the Great Depression, the regional agricultural economy was in decline, partly because of wider developments in the industry and also due to the difficulties of farming in the harsh climate (Brozowski et.al. 1984). In 1931, nearly 2.8 million acres of land were under cultivation in northern Ontario, but fifty years later this had dropped to 1.2 million acres, an indication that viable agricultural opportunities were limited.

It was the lumbering and mining industries that propelled population growth during the early and mid-20th century from 215,000 in 1921 to 722,000 in 1961 (Bray 1984:14). The 2011 Canada Census data indicated that the population of northern Ontario was just over 750,000 and clustered in regional centres (Statistics Canada 2011). 5.2.3 Municipality of Wawa The community of Wawa is a remote northern Ontario population centre located in the Municipality of Wawa (formerly Township of Michipicoten) within the Algoma District. Located 265 km north of Sault Ste. Marie, the community was home to 2,634 individuals in 2011 (Statistics Canada 2011).

The community of Wawa derives its name from the Ojibwa word for “wild goose,” which was first given to Wawa Lake where the community was established (Municipality of Wawa 2017). Surveyed in 1899, the community began as a mining town based on a gold discovery on the south shore of Lake Wawa two years earlier. The gold rush in Wawa lasted until 1906, with at least nineteen new gold mines developing in the area during the 1920s and 1930s. The gold industry in the area fluctuated throughout the remainder of the 20th century with a declining market in the 1990s prompting the closure of all but one mine, River Gold.

Coincidental with the original gold discovery was finding iron ore deposits in the area (Municipality of Wawa 2017). Francis Hector Clergue began operations at the Helen Mine, Ontario’s first large scale iron ore mine, in 1900. This mine was the largest producer of iron ore in Canada until 1918, and remained operational until 1950. Due to competitive international markets throughout the 1990s, ore mining ceased in the Wawa area in 1998.

For many years, direct access to Wawa was limited to steamboat, air, and the Algoma Central Railway from Hawk Junction to Sault Ste. Marie (Municipality of Wawa 2017). This finally changed in 1960 when a 96.5 km stretch of the Trans-Canada Highway was completed between Agawa River and Wawa; this section was the most expensive Ontario portion of the highway to be constructed. Now easily accessible, the community of Wawa has transformed into a centre for tourism and outdoor recreational activities, which are serviced by motels, stores, service stations, parking areas, paved roads, and other services.

15

July 13, 2018 1536607-2000-R01

5.2.4 Town of Marathon The Town of Marathon is a remote northern Ontario community located on the Peninsula Harbour of Lake Superior within the Thunder Bay District. Incorporated as a town in 1988, Marathon is presently home to 3,273 individuals (Payne and Welch 2017; Statistics Canada 2016). Key industries in the town include mining, forestry, residential and business services, and residential development. The Town of Marathon emerged in the early 1880s from CPR plans to establish a rail line along the mountainous north shore of Lake Superior from Heron Bay to Prince Arthur’s Landing (MDHSM n.d.; Payne and Welch 2017). In 1883, Peninsula Harbour was selected as a key docking location for men and rail supplies, and a community known by the same name quickly developed in the area. A warehouse and railroad station were erected in the community, followed by several houses and a hotel. At the peak of railway construction, Peninsula Harbour was thought to have a population of approximately 12,000, but this dropped drastically when the railway was complete in 1885. Gazetteer listings from 1895 and 1908 report Peninsula Harbour as a post village with a population of 100, and a store, hotel, and telegraph and express offices being the only commercial enterprises in the area. By 1935, the census of the community was just 23. Not until 1944, when a company called Marathon Corporation built a pulp mill in the area, did the population rise, reaching 2,500 by 1946. The town’s name was then changed to Marathon to honour its principal company. Marathon Corporation sold the mill in 1959, after which it changed hands numerous times before being closed in 2009 due to bankruptcy. Following discovery of the Hemlo gold deposit in 1981, two gold mines were opened in the area and the community of Marathon became a mining town, with many other businesses opening in support of this industry. Although industries have diversified in recent years, gold mining remains an important source of employment for the Town of Marathon. 5.2.5 Township of Terrace Bay During construction of the CPR in the 1880s, a ballast pit was excavated near the Black River at the site of the present day Township of Terrace Bay (Barry 1984:12). In the early 20th century a yard track and passing track were added next to the mainline and the site became known as Black Siding. A fire ranger may have been stationed at Black Siding from as early as 1897 until the track fire ranger service was discontinued in 1923 (Barry 1984:12). In the 1930s, the Hydro-Electric Power Commission of Ontario (HEPCO) redirected the flow of the from its path north to James Bay, through Long Lake into the Black River and to Lake Superior. The Black River was renamed the Aguasabon River at that time (Barry 1984:12). In 1947, Terrace Bay was made an improvement district and the Longlac Pulp and Paper Company started to build a large pulp mill and a new town at the site (Barry 1984:12). By the end of 1948, 230 houses had been built in the new community. The Aguasabon Generating Station was operational in 1948 (OPG 2018). The mill was completed in 1950 and at this time the population of the town reached 2000 residents (Barry 1984:12). On July 1, 1959 Terrace Bay officially became a municipality (Old Time Trains 2009). 5.2.6 Township of Nipigon The Township of Nipigon is a remote northern Ontario municipality of the Thunder Bay District. Located 98 km northeast of Thunder Bay, the township was home to 1,642 in 2016 (Statistics Canada 2016). A European presence in Nipigon began in 1679 when Claude Greysolon Dulhut established a trading post at the mouth of the Nipigon River (Township of Nipigon 2017). However, development of the area did not occur until the HBC built the post known as the Red Rock House in 1859 (Arthurs 1984). During the 1860s, the post functioned as a trans-shipment point where boats could unload their cargo for transportation up the Nipigon River. By 1871, the status of Red Rock House was upgraded, and shortly thereafter began period of rapid expansion fueled by renowned fishing and an increase in mining along the northern shore of Lake Superior. When the CPR constructed a station in Nipigon during the 1880s, the trading post blossomed into a village, which by 1895 featured a hotel, three general stores, a church, and telegraph and express offices (Lovell 1895). Nipigon was incorporated as a township in 1909 (Township of Nipigon 2017).

16

July 13, 2018 1536607-2000-R01

5.2.7 City of Thunder Bay Incorporated as a city in 1970 from the amalgamation of the Cities of Fort William and Port Arthur and the adjacent Townships of Neebing and McIntyre, the City of Thunder Bay is located on the west shore of Lake Superior in the District of Thunder Bay, Ontario. The City of Thunder Bay is home to 107,909 people (Statistics Canada 2016), and the key industries include forestry, tourism, agriculture, railcar construction, ship repair, and specialized equipment assembly for the resource-based industries.

Thunder Bay traces its origins to 1679 when the French constructed Fort Caministigoyan beside the Kaministiquia River (City of Thunder Bay 2017; Kemp 2017). However, permanent European settlement did not occur in the area until 1803 when Fort William was constructed. This fort functioned as the centre of the NWC’s fur-trading empire until the company amalgamated with the HBC in 1821 and the area declined in importance. By the mid- 19th century, settlement of the area was being fueled by the mining industry, with finds of copper, silver and gold proving lucrative to the local population. Development of Fort William continued unchallenged until 1870 when Prince Arthur’s Landing (originally known as “the Depot”) to the northeast was selected as the origin of the Dawson Road to Fort Garry in the west. As a result, Prince Arthur’s Landing outpaced the development of its neighbour because of its better docking facilities and the discovery of silver, but after construction of the CPR line through Fort William in 1875, the two communities developed at a similar rate. The landing was incorporated as the Town of Port Arthur in 1884, with Fort William being incorporated six years later. Both settlements were granted civic charters in 1907, and by 1910, the population of the City of Port Arthur was recorded at 14,900, while 14,000 lived in the City of Fort William (Union Publishing Company 1910). Both cities remained separate entities until 1970 when they amalgamated to form the City of Thunder Bay. 5.2.8 Lumber The lumber industry was pivotal for developing northern Ontario from the mid-19th century to the present day. Lumbering in the area is commonly grouped into three overlapping periods: an initial phase from the 1870s to early 1900s focussed on large white pine and white spruce for the global timber market; a second phase from 1900 onward typified by a shift to spruce for pulp and paper, primarily for newspaper in the eastern United States; and a third phase beginning in the mid-20th century marked by adoption of the combustion engine to power new equipment, revolutionizing many aspects of the industry (Smith 1984).

The first phase of the lumber industry from the 1870s to 1900s focused on white spruce and white pine primarily because of the distances to market. To be profitable, the value of the timber had to outweigh the costs of bringing trees to distant markets, and the large white pine and white spruce trees of northern Ontario met this criterion. Lumberjacks would haul large trees to the rivers with teams of horses and live in semi-permanent camps that included bunkhouses, cookhouses, horse barns, smithies, and storage sheds (Bogue 2007). The remnants of these camps may be present as debris scatters on the surface or ruins.

The second phase to supply the eastern United States with pulp for making newspaper was aided by the easily pulped softwood spruce abundant in northern Ontario. By the 1920s, lumbering in northern Ontario was devoted almost entirely to the pulp and paper industry. Larger, more permanent, and complex mill operations were required for pulping, resulting in long-term investment in the area and a need for a permanent labour force. This, in turn, spurred further settlement in the region.

Mechanization in the third phase of the lumber industry emerged in the mid-20th century with the invention of the chainsaw and increased availability of heavy tracked vehicles. Chainsaws increased productivity in felling trees by approximately 25% over axes and handsaws, and the combination of bulldozer and crane called a “skidder” replaced horses by the 1960s. Roads slowly outpaced waterways as the primary form of transport and also facilitated workers to commute to work and have greater choice in where they lived.

17

July 13, 2018 1536607-2000-R01

With World War II came renewed demand for resources overseas, but also perceived security risks on the home front. During the war, German prisoners of war (POWs) and Japanese Canadians were detained at camps across the country, including several permanent and temporary camps along the north shore of Lake Superior. Camps at the Township of Red Rock, Neys, and Angler Creek (see section 5.2.10 below) were seen as so inhospitable that a successful escape was unlikely. Both German POWs and Japanese Canadian internees were put to work in the logging industry at these camps. 5.2.9 Mine and Quarry Mining played an important role in northern Ontario’s development and settlement. Early Euro-Canadian mining and quarrying activity in Ontario was a small industry originally focused on local or regional needs. Building materials such as stone, gravel, sand and clay for construction were abundant and quarrying activities for these materials common (Republic of Mining 2010). Mining for metals occurred on a limited scale and some of the earliest mining activities included mining and smelting iron in local deposits in southern Ontario for the manufacture of basic iron tools (Republic of Mining 2010 and Wylie 1986:47-48).

At first, the mineral wealth of the Canadian Shield was exploited intermittently due to several factors including challenges in accessing Ontario’s north, an accessible labour force, technological challenges in separating minerals from ore, the difficulty in finding mineral resources in the dense wilderness and the lack of any support infrastructure. Mine operations had to be entirely self-sufficient and had no local source of labour or food and supplies to draw from (Newell 2011:59). Early mining explorations tended to explore and test for mineral deposits along the shoreline and then wait for a time –often for years— before it was feasible to develop the site (Newell 2011:60).

Copper mining on the American side of Lake Superior in the 1840s led to official interest in prospecting and developing mining at sites in Ontario. A few copper mines were established at this time, but the one mine that had substantial production was at Bruce Mines (MTCS 1972:146). The development of mining in northern Ontario in the 1840s was a contributing factor to the conclusion of the Robinson Treaty in 1850. Oil and natural gas were discovered in Southwestern Ontario in the 1850s. Large salt deposits were discovered in 1863 (MTCS 1972:147). The development of the Ontario mining industry in the north coincided with the development of the railway, the publication of the Geology of Canada in 1842, the establishment of universities with geology departments and mining engineer training from the 1850s and advances in mining technologies that occurred around the middle to the end of the 19th century.

The latter half of the 19th century saw many small-scale mining developments across Ontario, starting along the south edge of the Canadian Shield and gradually moving north. Large scale mining developments including some large-scale extraction of iron ores began around 1865. Some silver and gold deposits were discovered around the 1870s in northwestern Ontario —including the Silver Islet mine— and opened up surrounding areas for further prospecting but mining activity was limited (MTCS 1972:150-151). In 1890, the Ontario government began supporting mine development through the Bureau of Mines, which also sponsored classes in prospecting and provided some specialized equipment to miners (Gilbert 1984).

Around the end of the 19th century non-precious metals other than iron –which could be found throughout the Province— became important for the first time as mining and processing technologies advanced to make commercial use of these minerals viable. The construction of railways throughout northern Ontario led to more discoveries and opened up the north for further prospecting and mine development. Mines started to become more extensive underground operations and Canada started to become an exporter of minerals (Wylie 1986:49).

18

July 13, 2018 1536607-2000-R01

In the 1880s nickel and copper discoveries in the Sudbury Basin were exploited. In the 1890s significant iron deposits were found around Wawa during a small gold rush in the area. Silver was discovered at Cobalt in 1903. Major finds of gold were discovered at Timiskaming around 1906 and at Red Lake and Central Patricia –in northwestern Ontario— in 1925 (MTCS 1972:154-157). By 1914, Ontario was the leading mining province in the country, accounting for 40% of production and employing 11,000 workers. A boom in demand for minerals during the First World War dropped after the Armistice and growth in the industry slowed during the interwar years (Gilbert 1984).

Small-scale gold mining operations throughout the province underwent a resurgence during the Great Depression of the 1930s due to high prices for gold and low overhead costs. This development revived precious metal mining in some areas and opened some new areas of the province but this resurgence of small scale type of mining operations was brief (MTCS 1972:158). Advances in technology including aircraft to get prospectors to sites quickly and remote sensing technologies such as the magnetometer led to more finds but involved greater expense that gave larger, well-financed mining companies an advantage (Republic of Mining 2010).

Several large iron deposits and many finds of base metal were found and exploited in the 1940s to meet wartime and postwar demands for iron and steel. Exploration for uranium began in earnest during the war but private prospecting for radioactive materials was banned by the government in 1943 due to the strategic use of the material (World Nuclear Association 2018). In 1947, private prospecting was allowed once again and deposits of Uranium were found around Bancroft in the early 1950s and at Elliot Lake in 1953 (World Nuclear Association 2018). The demand for resources continued into the 1950s and 1960s. Investment and mechanization led to larger operations that could exploit deposits more effectively, and could pull new returns from old mines. In the 1970s the growth rate seen in the previous three decades faltered and competition from other parts of the world redirected investment away from northern Ontario. Mechanization has increased since then and with it has come different labour requirements.

Mining in Ontario has been constrained by transportation and technological challenges over the course of the last two centuries. The progression of mining in Ontario has followed advances in transportation and technology to get to, find and process the minerals. 5.2.10 Internment Camps During the First World War, the Canadian government initially established internment camps to detain civilians considered to be a security risk (Zimmerman 2015). Passing of the War Measures Act in 1914 gave the federal government broad powers to arrest, detain, exclude, and deport “enemy aliens” or foreign-born residents of Canada whose citizenship or country of birth was at war with the British Empire. In keeping with British policy at the time, roughly 85,000 individuals of German, Austro-Hungarian, Turkish, and Bulgarian descent were required to register and report regularly to the Canadian Government. Of these individuals, 8,579 men were interned, and twenty-four camps were created across Canada, administered first under the Department of Militia and Defence from 1914 to 1915, then by the Department of Justice from 1915 to 1920. These measures were soon recognized to be largely fueled by wartime hysteria and xenophobia rather than by real security risks, so by 1916 and 1917 the majority of the internees were released on parole if they agreed to remain loyal to the British Empire. The roughly 2,200 men that remained in the camps were primarily prisoners of war (POW), and were detained until the Treaty of Versailles was signed in June 1919; many did not return home until May 1920.

19

July 13, 2018 1536607-2000-R01

The War Measures Act was again invoked at the outbreak of the Second World War. The Defence of Canada Regulations, enacted on September 3, 1939 allowed for the suspension of civil liberties, regardless of one’s country of birth, and detaining any individuals suspected of behaving in a prejudicial manner towards public safety or the safety of the state (Zimmerman 2015; Melady 1981). As a result, many of German and Italian descent, as well as members of the Communist Party of Canada were targeted for internment. Unlike the internment practices of the First World War, the intent of this process was to restrict the internment operations to those few suspected troublemakers, rather than targeting entire ethic groups (Zimmerman 2015). Nevertheless, the later internment of Japanese Canadians strayed drastically from this goal.

The vast majority of Japanese Canadians residing in Canada during the Second World War were either born in Canada or were naturalized citizens (Zimmerman 2015). They supported the Canadian democratic system and were largely unaffected by Japanese propaganda, but after the Japanese attack on the US naval base of Pearl Harbor on December 7, 1941, many Canadians in British Columbia felt that Japanese Canadians were enemy sympathizers. By mid-December 1941, Japanese Canadians, regardless of their citizenship, were required to register with the government. The following year, in February 1942, the entire Japanese Canadian community in BC, under the guise of an evacuation, was uprooted from the coast and sent to inland work camps. Families were split up, with men, women and children distributed among camps in the British Columbia interior. About 750 men who refused to cooperate with the evacuation were sent to Ontario. Following the evacuation, the government confiscated and sold properties belonging to Japanese Canadians, sending a fraction of the funds to their former owners. Many Japanese Canadians remained interned until the end of the war.

When the war had begun, Canadian officials thought they would be responsible for internees that been detained in Canada (Zimmerman 2015). However, as fear and xenophobia grew, the British Government ordered roughly 75,000 enemy aliens living in Britain to be interned, and asked the Canadian government to accept POWs, enemy merchant seamen, and civilian internees. This, it was believed, would free up military personnel, reduce the stress on resources, and mitigate the threat of subversives in the event of a German invasion (Zimmerman 2015; Melady 1981). The Canadian government agreed, and the first internees and POWs began arriving in June 1940. From the commencement of the interment operations in 1939 to the end of war, Canada would host approximately 35,000 detainees. Initially unprepared for the influx, the first internment camps were hastily constructed. Eventually, twenty-six main internment camps were erected, with numerous smaller installations built to hold prisoners employed on farms, in factories, and as loggers. Identified by letter, and then later number designations, the camps were categorized by the specific type of internee they housed: civilian internees; merchant seamen; POW officers; and other ranks of POWs. However, combined camps were not uncommon, and in some cases entire groups of internees were replaced by those of a different designation.

There were three main POW/internment camps along the North Shore of Lake Superior and many temporary work camps. The three main camps included:  The Angler Internment Camp, also known as Camp X and Camp 101;  The Neys Internment Camp, also known as Camp W and Camp 100; and  The Red Rock/Schreiber Internment Camp, also known as Camp R.

20

July 13, 2018 1536607-2000-R01

5.3 History of Potential Cultural Heritage Sites in the LSA Eight potential cultural heritage resources were identified in the LSA. Six of the potential cultural heritage resource sites were mine or quarry sites, the seventh is the Angler Internment Camp and the eighth is the Aguasabon River and Hays Lake.

From east to west the six mine and quarry sites are:  Gananoque Vein Gold Mine, near Wawa (1897 to 1899) (Figure 2);  Molybdenite Lake Prospect, near Wawa (1905 to 1964) (Figure 3);  Angler/Petrunka Granite Quarry, north of the Town of Marathon (1929 to 1960s) (Figure 4);  Halonen Fluorite Mine, near Nipigon (1974 to 1986) (Figure 5);  Bishop Lead Occurrence, near Nipigon (first reported in 1929) (Figure 6); and  Mackenzie Quarry, east of the City of Thunder Bay (1880s) (Figure 7).

The Angler Internment Camp (1941-1946) is north of the Town of Marathon and close to the Angler/Petrunka Granite Quarry site. The camp is a registered archaeological site (DeIo-3; Figure 8). The Aguasabon River and Hays Lake is northwest of the community of Terrace Bay (Figure 9).

21

")

") D A O R S 00855 L L A ") F ") H !. IG ")") H ")

GANANOQUE VEIN GOLD MINE

F169 F170 F172 F171 F183 F185 F187 F173 F174 F175 F180 F184 F186 F176 F177 F178 F181 F182 !. F179

00874 00880 !.

00871 !. ")") ") ") 00872 ") 02948 ") !. !.

TRANSCANADA HIGHWAY

SOUTH MICHIPICOTEN RIVER-SUPERIOR SHORELINE CONSERVATION RESERVE

LEGEND KEY MAP REFERENCE(S) Project Component Base Data Abandoned Mines Information System (AMIS) Site BASE DATA: MNRF LIO (2018), CANVEC (2017), DILLON (2014, 2015), MNDM (2017) !. PROJECT COMPONENTS: PROVIDED BY NEXTBRIDGE (2018) Proposed Tower Location Highway IMAGERY: PROVIDED BY NEXTBRIDGE (2014); "/ !. Gananoque Vein Gold Mine Site Location 0 0.25 0.5 0.75 Main Road PRODUCED BY GOLDER ASSOCIATES LTD. UNDER LICENSE FROM ONTARIO MINISTRY OF Preferred Route ROW Building (MNRF, CanAcre) ³ NATURAL RESOURCES, © QUEENS PRINTER 2018 ! Transmission Line PROJECTION: TRANSVERSE MERCATOR DATUM: NAD 83 COORDINATE SYSTEM: UTM ZONE 16N Access Road Permanent for Operation 1:15,000 KILOMETRES Access Road - New Watercourse Access Road - Improvement/Widening Conservation Reserve CLIENT PROJECT Access Road Temporary for Construction Water Body HERITAGE IMPACT ASSESSMENT, EAST-WEST TIE Access Road - New TRANSMISSION PROJECT THIS IF MEASUREMENT ISSHOWN, WHAT DOES SHEETTHE NOT SIZE MATCH HAS BEEN MODIFIEDANSI B FROM: Access Road - Improvement/Widening WAWA 25mm Access Road - Existing J" YYYY-MM-DD 2018-07-10 TITLE Local Study Area DESIGNED GOLDER JR GANANOQUE VEIN GOLD MINE SITE LOCATION

PREPARED GOLDER JB

REVIEWED GOLDER BH PROJECT NO. CONTROL REV. FIGURE APPROVED GOLDER HJD 1536607 1

PATH: S:\Clients\NextBridge\East_West_Tie\99_PROJ\1536607_EA\40_PROD\0040_HIA_Report\1536607-0040-HC-0002.mxd PATH: 6:56:14 PM PRINTED 2018-07-10 ON: AT: 2 0 MOLYBDENITE LAKE !. 00870

LEGEND KEY MAP REFERENCE(S) Project Component Base Data Abandoned Mines Information System (AMIS) Site BASE DATA: MNRF LIO (2018), CANVEC (2017), DILLON (2014, 2015), MNDM (2017) !. PROJECT COMPONENTS: PROVIDED BY NEXTBRIDGE (2018) Access Road Temporary for Construction Watercourse IMAGERY: PROVIDED BY NEXTBRIDGE (2014); 0 0.25 0.5 0.75 Access Road - Improvement/Widening Water Body PRODUCED BY GOLDER ASSOCIATES LTD. UNDER LICENSE FROM ONTARIO MINISTRY OF ³ NATURAL RESOURCES, © QUEENS PRINTER 2018 Local Study Area PROJECTION: TRANSVERSE MERCATOR DATUM: NAD 83 COORDINATE SYSTEM: UTM ZONE 16N 1:15,000 KILOMETRES

CLIENT PROJECT HERITAGE IMPACT ASSESSMENT, EAST-WEST TIE TRANSMISSION PROJECT THIS IF MEASUREMENT ISSHOWN, WHAT DOES SHEETTHE NOT SIZE MATCH HAS BEEN MODIFIEDANSI B FROM:

WAWA 25mm J" YYYY-MM-DD 2018-07-10 TITLE DESIGNED GOLDER JR MOLYBDENITE LAKE PROSPECT SITE LOCATION

PREPARED GOLDER JB

REVIEWED GOLDER BH PROJECT NO. CONTROL REV. FIGURE APPROVED GOLDER HJD 1536607 1

PATH: S:\Clients\NextBridge\East_West_Tie\99_PROJ\1536607_EA\40_PROD\0040_HIA_Report\1536607-0040-HC-0003.mxd PATH: 6:58:52 PM PRINTED 2018-07-10 ON: AT: 3 0 WOLF CAMP LAKE HARE LAKE

WAY HIGH DA NA CA NS TRA

ANGLER/PETRUNKA GRANITE QUARRY

C262 C261 !. 03263 C263 C260 C264 C265 C266 C259 !. C267

LAKE C258 SUPERIOR SHORELINE C257 ") C268

C269 C256 C270 C255 !(

LAKE SUPERIOR C254 (LAC SUPÉRIEUR) ANGLER INTERNMENT CAMP

C253

CANADIAN PACIFIC RAILWAY

RED SUCKER POINT PROVINCIAL PARK (NATURE RESERVE CLASS)

LEGEND KEY MAP REFERENCE(S) Project Component Base Data Abandoned Mines Information System (AMIS) Site BASE DATA: MNRF LIO (2018), CANVEC (2017), DILLON (2014, 2015), MNDM (2017) !. PROJECT COMPONENTS: PROVIDED BY NEXTBRIDGE (2018) Proposed Tower Location Highway ") Building (MNRF, CanAcre) ANGLER INTERNMENT CAMP: HQS 7236-96-101 - CONSTRUCTION AND MAINTENANCE OF "/ 0 0.25 0.5 0.75 Local Road CAMPS. ANGLER, MICROFILM REEL C-5420, RG24, LIBRARY AND ARCHIVES CANADA. Access Road Temporary for Construction !( Known Cultural Heritage Resource ³ IMAGERY: PROVIDED BY NEXTBRIDGE (2014) Access Road - New Railway Angler/Petrunka Granite Quarry Site Location PRODUCED BY GOLDER ASSOCIATES LTD. UNDER LICENSE FROM ONTARIO MINISTRY OF !. 1:15,000 KILOMETRES NATURAL RESOURCES, © QUEENS PRINTER 2018 ! Transmission Line Access Road - Improvement/Widening Angler Internment Camp Area PROJECTION: TRANSVERSE MERCATOR DATUM: NAD 83 COORDINATE SYSTEM: UTM ZONE 16N Watercourse Access Road - Existing Angler Internment Camp Fence Line CLIENT PROJECT Preferred Route ROW Enhanced Management Area HERITAGE IMPACT ASSESSMENT, EAST-WEST TIE Laydown Yard Provincial Park TRANSMISSION PROJECT THIS IF MEASUREMENT ISSHOWN, WHAT DOES SHEETTHE NOT SIZE MATCH HAS BEEN MODIFIEDANSI B FROM: Temporary Construction Easement Water Body WAWA 25mm Local Study Area J" YYYY-MM-DD 2018-07-10 TITLE DESIGNED GOLDER JR ANGLER/PETRUNKA GRANITE QUARRY SITE LOCATION

PREPARED GOLDER JB

REVIEWED GOLDER BH PROJECT NO. CONTROL REV. FIGURE APPROVED GOLDER HJD 1536607 1

PATH: S:\Clients\NextBridge\East_West_Tie\99_PROJ\1536607_EA\40_PROD\0040_HIA_Report\1536607-0040-HC-0004.mxd PATH: 7:01:02 PM PRINTED 2018-07-10 ON: AT: 4 0 CAVERS LAKE

C021 C022 C023 C024 C007 C008 C009 C010 C011 C012 C013 C020 C015 C017 C018 C019 C014 C016

NISHIN LAKE ") ") HALONEN FLUORITE ")")") MINE

!. 03162

WABASTA LAKE

TRANSCANADA HIGHWAY LAKE SUPERIOR SHORELINE

LEGEND KEY MAP REFERENCE(S) Project Component Base Data Abandoned Mines Information System (AMIS) Site BASE DATA: MNRF LIO (2018), CANVEC (2017), DILLON (2014, 2015), MNDM (2017) !. PROJECT COMPONENTS: PROVIDED BY NEXTBRIDGE ( 2018) Proposed Tower Location Highway ") Building (MNRF, CanAcre) IMAGERY: PROVIDED BY NEXTBRIDGE (2014) "/ 0 0.25 0.5 0.75 Local Road PRODUCED BY GOLDER ASSOCIATES LTD. UNDER LICENSE FROM ONTARIO MINISTRY OF Access Road Permanent for Operation !. Halonen Fluorite Mine Site Location ³ NATURAL RESOURCES, © QUEENS PRINTER 2018 Access Road - New Railway PROJECTION: TRANSVERSE MERCATOR DATUM: NAD 83 COORDINATE SYSTEM: UTM ZONE 16N 1:15,000 KILOMETRES Access Road Temporary for Construction ! Transmission Line Access Road - New Watercourse CLIENT PROJECT Access Road - Improvement/Widening First Nation Expansion Area HERITAGE IMPACT ASSESSMENT, EAST-WEST TIE Access Road - Existing Enhanced Management Area TRANSMISSION PROJECT THIS IF MEASUREMENT ISSHOWN, WHAT DOES SHEETTHE NOT SIZE MATCH HAS BEEN MODIFIEDANSI B FROM: Preferred Route ROW Water Body 25mm

Local Study Area THUNDER BAY J" YYYY-MM-DD 2018-07-10 TITLE DESIGNED GOLDER JR HALONEN FLUORITE MINE SITE LOCATION

PREPARED GOLDER JB

REVIEWED GOLDER BH PROJECT NO. CONTROL REV. FIGURE APPROVED GOLDER HJD 1536607 1

PATH: S:\Clients\NextBridge\East_West_Tie\99_PROJ\1536607_EA\40_PROD\0040_HIA_Report\1536607-0040-HC-0005.mxd PATH: 7:01:08 PM PRINTED 2018-07-10 ON: AT: 5 0 INNES LAKE

WOLF LAKE

CAVERN LAKE PROVINCIAL PARK (NATURE RESERVE CLASS)

BISHOP LEAD OCCURRENCE 08456 !.

AD RO 08479 !. E AK L D N A

R O 08455 E V R R !. CA N R

E

LAKEHEAD REGION V CONSERVATION A C BISHOPS AUTHORITY LAKE CAVERN LAKE

B014 MACDONALDS LAKE B001 B013 B002 B003 B004 A135 B005 B007 B008 B006 B009 B010 B011 B012

A134

LEGEND KEY MAP REFERENCE(S) Project Component Base Data Abandoned Mines Information System (AMIS) Site BASE DATA: MNRF LIO (2018), CANVEC (2017), DILLON (2014, 2015), MNDM (2017) !. PROJECT COMPONENTS: PROVIDED BY NEXTBRIDGE (2018) Proposed Tower Location Local Road IMAGERY: PROVIDED BY NEXTBRIDGE (2014); THE STANDARD ESRI WORLD IMAGERY: ESRI, "/ !. Bishop Lead Occurrence Site Location 0 0.25 0.5 0.75 Watercourse DIGITALGLOBE, GEOEYE, I-CUBED, EARTHSTAR GEOGRAPHICS, CNES/AIRBUS DS, USDA, Access Road Permanent for Operation ³ USGS, AEX, GETMAPPING, AEROGRID, IGN, IGP, SWISSTOPO, AND THE GIS USER COMMUNITY Access Road - New Conservation Authority PRODUCED BY GOLDER ASSOCIATES LTD. UNDER LICENSE FROM ONTARIO MINISTRY OF 1:15,000 KILOMETRES Provincial Park NATURAL RESOURCES, © QUEENS PRINTER 2018 Access Road Temporary for Construction PROJECTION: TRANSVERSE MERCATOR DATUM: NAD 83 COORDINATE SYSTEM: UTM ZONE 16N Access Road - New Water Body CLIENT PROJECT Access Road - Improvement/Widening HERITAGE IMPACT ASSESSMENT, EAST-WEST TIE Access Road - Existing TRANSMISSION PROJECT THIS IF MEASUREMENT ISSHOWN, WHAT DOES SHEETTHE NOT SIZE MATCH HAS BEEN MODIFIEDANSI B FROM: Preferred Route ROW 25mm

Laydown Yard THUNDER BAY J" YYYY-MM-DD 2018-07-10 TITLE Local Study Area DESIGNED GOLDER JR BISHOP LEAD OCCURRENCE SITE LOCATION

PREPARED GOLDER JB

REVIEWED GOLDER BH PROJECT NO. CONTROL REV. FIGURE APPROVED GOLDER HJD 1536607 1

PATH: S:\Clients\NextBridge\East_West_Tie\99_PROJ\1536607_EA\40_PROD\0040_HIA_Report\1536607-0040-HC-0006.mxd PATH: 7:01:30 PM PRINTED 2018-07-10 ON: AT: 6 0 R O G E R D G A C A O M R

A012 A013 ")") ") ") A014 ") ") ")") LAKEHEAD REGION ") ") A015 ") ") CONSERVATION ") AUTHORITY A016 ") ") ")

A017

MACKENZIE QUARRY Y A018 IFIC RAILWA CANADIAN PAC !. 00457 A019 A020 A021 A022 A023 A024 A025 A026 A027 TERRY FOX MILE !( 3339 POST

TRANSCANADA HIGHWAY

")

")") ") ") ")") ")D A ") O ") ")R N E G U A LA H KESH CED ORE DRIVE AR B AY R O A LAKE SUPERIOR D (LAC SUPÉRIEUR)

LEGEND KEY MAP REFERENCE(S) Project Component Base Data Abandoned Mines Information System (AMIS) Site BASE DATA: MNRF LIO (2018), CANVEC (2017), DILLON (2014, 2015), MNDM (2017) !. PROJECT COMPONENTS: PROVIDED BY NEXTBRIDGE (2018) Proposed Tower Location Highway ") Building (MNRF, CanAcre) IMAGERY: PROVIDED BY NEXTBRIDGE (2014) "/ 0 0.25 0.5 0.75 Local Road PRODUCED BY GOLDER ASSOCIATES LTD. UNDER LICENSE FROM ONTARIO MINISTRY OF Access Road Temporary for Construction !( Known Cultural Heritage Resource ³ NATURAL RESOURCES, © QUEENS PRINTER 2018 Access Road - New Railway PROJECTION: TRANSVERSE MERCATOR DATUM: NAD 83 COORDINATE SYSTEM: UTM ZONE 16N !. Mackenzie Quarry Site Location 1:15,000 KILOMETRES Access Road - Improvement/Widening ! Transmission Line Watercourse Access Road - Existing CLIENT PROJECT Preferred Route ROW Conservation Authority HERITAGE IMPACT ASSESSMENT, EAST-WEST TIE Laydown Yard Water Body TRANSMISSION PROJECT THIS IF MEASUREMENT ISSHOWN, WHAT DOES SHEETTHE NOT SIZE MATCH HAS BEEN MODIFIEDANSI B FROM: Storage Yard 25mm

Local Study Area THUNDER BAY J" YYYY-MM-DD 2018-07-10 TITLE DESIGNED GOLDER JR MACKENZIE QUARRY SITE LOCATION

PREPARED GOLDER JB

REVIEWED GOLDER BH PROJECT NO. CONTROL REV. FIGURE APPROVED GOLDER HJD 1536607 1

PATH: S:\Clients\NextBridge\East_West_Tie\99_PROJ\1536607_EA\40_PROD\0040_HIA_Report\1536607-0040-HC-0007.mxd PATH: 6:47:04 PM PRINTED 2018-07-10 ON: AT: 7 0 C260 C261 LAKE SUPERIOR C262 SHORELINE

!. 03263 AY TRA IGHW NSCANADA H C263

C264

C265

LAKE SUPERIOR SHORELINE

LAKE SUPERIOR C266 SHORELINE

LAKE SUPERIOR (LAC SUPÉRIEUR)

")

!( C267

C A N ANGLER CREEK A D INTERNMENT CAMP I A N P A C I F I C R A I LW

A C268 Y

LEGEND KEY MAP REFERENCE(S) Project Component Base Data Abandoned Mines Information System (AMIS) Site BASE DATA: MNRF LIO (2018), CANVEC (2017), DILLON (2014, 2015), MNDM (2017) !. PROJECT COMPONENTS: PROVIDED BY NEXTBRIDGE ( 2018) Proposed Tower Location Highway ANGLER INTERNMENT CAMP: HQS 7236-96-101 - CONSTRUCTION AND MAINTENANCE OF "/ !( Known Cultural Heritage Resource 0 0.25 0.5 0.75 Railway CAMPS. ANGLER, MICROFILM REEL C-5420, RG24, LIBRARY AND ARCHIVES CANADA. Access Road Temporary for Construction ") Building (MNRF, CanAcre) ³ IMAGERY: PROVIDED BY NEXTBRIDGE (2018) Access Road - New ! Transmission Line PRODUCED BY GOLDER ASSOCIATES LTD. UNDER LICENSE FROM ONTARIO MINISTRY OF Angler Internment Camp Area 1:10,000 KILOMETRES Watercourse NATURAL RESOURCES, © QUEENS PRINTER 2017 Access Road - Improvement/Widening Angler Internment Camp Fence Line PROJECTION: TRANSVERSE MERCATOR DATUM: NAD 83 COORDINATE SYSTEM: UTM ZONE 16N Enhanced Management Area Access Road - Existing CLIENT PROJECT Water Body Preferred Route ROW HERITAGE IMPACT ASSESSMENT, EAST-WEST TIE Laydown Yard TRANSMISSION PROJECT THIS IF MEASUREMENT ISSHOWN, WHAT DOES SHEETTHE NOT SIZE MATCH HAS BEEN MODIFIEDANSI B FROM: Temporary Construction Easement 25mm Local Study Area YYYY-MM-DD 2018-07-10 TITLE DESIGNED GOLDER JR ANGLER INTERNMENT CAMP SITE LOCATION WAWA J" PREPARED GOLDER JB

REVIEWED GOLDER BH PROJECT NO. CONTROL REV. FIGURE APPROVED GOLDER HJD 1536607 1

PATH: S:\Clients\NextBridge\East_West_Tie\99_PROJ\1536607_EA\40_PROD\0040_HIA_Report\1536607-0040-HC-0008.mxd PATH: 6:35:08 PM PRINTED 2018-07-10 ON: AT: 8 0 AGUASABON C106 C107 RIVER

C108

C109 C110 C111 C112 C113 C114 C115 C116 C117 C118 C119 C120 C121

C122 C123

HAYS LAKE

LEGEND KEY MAP REFERENCE(S) Project Component Base Data BASE DATA: MNRF LIO (2017), CANVEC (2017), DILLON (2014, 2015), MNDM (2017) PROJECT COMPONENTS: PROVIDED BY NEXTBRIDGE (NOVEMBER 2017) Proposed Tower Location Local Road IMAGERY: PROVIDED BY NEXTBRIDGE (2014); THE STANDARD ESRI WORLD IMAGERY: ESRI, "/ 0 0.25 0.5 0.75 ! Transmission Line DIGITALGLOBE, GEOEYE, I-CUBED, EARTHSTAR GEOGRAPHICS, CNES/AIRBUS DS, USDA, Access Road Permanent for Operation ³ USGS, AEX, GETMAPPING, AEROGRID, IGN, IGP, SWISSTOPO, AND THE GIS USER COMMUNITY Access Road - New Known Cultural Heritage Resource PRODUCED BY GOLDER ASSOCIATES LTD. UNDER LICENSE FROM ONTARIO MINISTRY OF 1:15,000 KILOMETRES NATURAL RESOURCES, © QUEENS PRINTER 2017 Access Road - Improvement/Widening PROJECTION: TRANSVERSE MERCATOR DATUM: NAD 83 COORDINATE SYSTEM: UTM ZONE 16N

Access Road Temporary for Construction CLIENT PROJECT Access Road - New HERITAGE IMPACT ASSESSMENT, EAST-WEST TIE Access Road - Improvement/Widening TRANSMISSION PROJECT THIS IF MEASUREMENT ISSHOWN, WHAT DOES SHEETTHE NOT SIZE MATCH HAS BEEN MODIFIEDANSI B FROM: Access Road - Existing 25mm

Preferred Route ROW THUNDER BAY J" YYYY-MM-DD 2018-07-10 TITLE Local Study Area DESIGNED GOLDER JR AGUASABON RIVER AND HAYS LAKE

PREPARED GOLDER JB

REVIEWED GOLDER BH PROJECT NO. CONTROL REV. FIGURE APPROVED GOLDER HJD 1536607 1

PATH: S:\Clients\NextBridge\East_West_Tie\99_PROJ\1536607_EA\40_PROD\0040_HIA_Report\1536607-0040-HC-0012.mxd PATH: 6:50:46 PM PRINTED 2018-07-10 ON: AT: 9 0 July 13, 2018 1536607-2000-R01

5.3.1 Mine and Quarry Sites 5.3.1.1 Gananoque Vein Gold Mine (1897 – 1899) In 1897, on the shore of Wawa Lake, a gold-laced quartz vein was discovered which led to a gold rush around Wawa (Rowe 2012). Most of the gold production that resulted from this gold rush slowed by 1906; however, gold mining has remained active in the area ever since. The gold rush led to finds of iron and the establishment of a significant local iron mining industry.

In 1897, shortly after the discovery of gold near Wawa, the Gananoque Gold Mining Company co-owned by J. Legge of Gananoque and S. Barton of Sault Ste. Marie, Ontario, excavated a 16 m-long (53 foot-long) tunnel into the hillside and a second 13 m-long (42 foot-long) tunnel into the face of the cliff above the main tunnel (Boyd 1899:101). It is likely that J. Legge was Joshua Legge Jr., a farmer and politician in the Town of Gananoque and Township of the Front of Leeds and Lansdown in the 1860s and 1870s (Leavitt, Thad. W.H. 1879:128).

Consolidated Bellekeno Mines Ltd. conducted mapping, sampling and ground geophysics at the site in 1962, and in 1970 Pango Gold Mines Ltd. also conducted mapping and ground geophysics on the site. From 1979 to 1983, Canabec Explorations Ltd. conducted very low frequency electromagnetic (VLFEM), magnetometer surveying and mapping. Overall, activity at the site involved excavating a vein of quartz to retrieve gold in the late 1890s (AMIS file 00874). 5.3.1.2 Molybdenite Lake Prospect (1905 – 1964) Molybdenite is a sulfide compound of Molybdenum and was first purified and described in the late 18th century. It was a scientific curiosity until the late 19th century when experiments in steel alloys demonstrated that it had similar properties to tungsten in making steel by adding strength, hardness, weldability, toughness, elevated temperature strength and corrosion resistance (IMOA n.d). Molybdenum was in high demand during both world wars (IMOA n.d.).

One of the earliest cases of molybdenite mining in Ontario occurred at the Harvey Hill Mine in Leeds, Canada East in 1863 (Freeman 1993) as a by-product of copper mining. A few hundred tonnes were produced during the First World War and then production dropped off until the Second World War when a few hundred tonnes were produced again. Production remained low through the 1950s and abruptly rose in the mid-1960s to over 15,000 tonnes a year and peaked in the early 1970s (Natural Resources Canada 2002:11).

The Molybdenite Lake Prospect began with shallow trenching in 1905. In 1939 the Superior Molybdenum Company Ltd. conducted more trenching and drilling. Approximately 120 tons of ore was removed from the site in 1939 and the average grade of the shipment was 0.5% molybdenite. International Ranwick Ltd. undertook sampling in 1958. Geological and magnetometer surveys of the site were done by D.P. Sing of Sault Ste. Marie in 1964 (Johnston 1968: 17, and AMIS file 03063). The area around Molybdenite Lake has long been prospected for many types of minerals (Ontario Geological Survey 1981). The International Nickle Company of Canada examined the property in 1964-1965. Drilling results were unfavorable and no development work has been done on this claim since (Ontario Geological Survey 1981).

30

July 13, 2018 1536607-2000-R01

5.3.1.3 Angler Granite Quarry/ Petrunka (1929 – 1960s) Intermittent quarrying activity started in the general area around Marathon in the late 1880s when the CPR railway was built. The CPR extracted stone for construction of railway bridges over the Pic and Little Pic Rivers from two quarries in the Marathon area (Geology Ontario 1988:8). The Angler Granite Quarry site is within a larger granite quarry claim area known as the Canadian Black #1 property, a large area with approximately 30 granite quarry claim sites (Geology Ontario 1988:2). The site was an open-cut granite quarry close to the CPR railway tracks. The mineral claim at the Angler Granite Quarry site was staked in 1929 by Mr. H. England. Angler Granites Ltd. took some test blocks from the site in 1931. There were some problems encountered with the quarrying operations –exactly what sort of problems is unknown— and Angler Granites ceased operations by 1932 (Geology Ontario 1988:8). The claim was staked again in 1961 by James Aldridge and transferred to the Angler Mining Company Ltd. The Angler Mining Company drilled cores from 1963 to 1965 but did not remove any rock. In 1985, the claim was staked by D. Petrunka and in 1988 was optioned to the company Cold Springs Granite Canada Ltd. The claim was returned to D. Petrunka in 1995 (AMIS file 03263). 5.3.1.4 Halonen Fluorite Mine (1974 – 1986) Fluorite is a mineral made of calcium fluoride and can be found throughout the world. It is often found in a vein deposit with metallic minerals or with mineral deposits with hydrothermal origins. Fluorite has been used as a flux in making steel, it has ornamental purposes and is a useful mineral in making opalescent glass, enamels, hydrofluoric acid. The mineral can also be used to make high performance lenses for telescopes and cameras (New World Encyclopedia 2017). Ontario’s fluorite deposits were first mined around 1905 (Guillet 1964:1). A Department of Mines report from 1964 stated that Fluorite is a minor constituent in some of the many silver bearing calcite veins along the north shore of Lake Superior and that the veins are usually small, thin and only 5-10% of a vein usually contains the mineral (Guillett 1964:55).

The Halonen Fluorite Mine site was staked by J.E. Halonen of Schreiber in 1974 and an exploratory trench was excavated at that time. Mining activities including stripping and blasting to uncover the veins occurred intermittently over the years from 1974 through 1986 (AMIS file 03162). 5.3.1.5 Bishop Lead Occurrence Mineral exploration in the Dorion Wolf Lake area including Glen Township occurred in the late 19th century and discovered lead-zinc deposits in a fault along early Precambrian granite rock and Late Precambrian Sibley group rock (Ontario Division of Mines 1975). The Bishop Lead Occurrence is one of the sites on this fault. Mining activity at this site included test pits and a shaft to mine for lead. The 38th Annual Report of the Ontario Department of Mines of 1929 lists the Bishop claims, claims 5 and 6L in Dorion Township and unsurveyed territory. The Bishop claims are described as northeast of the shaft of the Dorion mine along the same fault as the Dorion Mine fault. The report describes the “old Bishop shaft” as a shaft sunk approximately 100 feet (Hawley 1929:71). There was some limited production from this shaft in 1929 (AMIS file 08479).

The shaft was still open in 1984, however by 2000 the shaft was nearly filled and the adit had partially collapsed (AMIS file 08479).

31

July 13, 2018 1536607-2000-R01

5.3.1.6 Mackenzie Quarry (1880s) The Mackenzie Quarry was a granite aggregate quarry from the 1880s. Fifty-five men were employed at the quarry and extracted 800 to 900 cubic yards of material per month in 1883-1884. Granite from this quarry was used by the CPR for bridges during construction of the transcontinental railway line (Mineral Deposit Inventory for Ontario MDI52A10NE00040, AMIS file 00457). 5.3.2 Angler Internment Camp The Angler Internment Camp, also known as Camp X and Camp 101, was a German POW and Japanese-Canadian internment camp located to the north of Angler Creek, near the Town of Marathon, Thunder Bay District. A plan of the camp titled Layout of Internment Camp X shows four H-shaped prisoners’ quarters, a kitchen and dining room, hospital building, detention building, barber and tailor shop, and recreation building located within the fenced enclosure (Figure 10 to Figure 12). An office building and guardhouse were located at the gate to the enclosure and numerous buildings were on the west, including an Officers’ Mess, two Officers’ quarters, Non-Commissioned Officers’ (N.C.O.) quarters, guards’ quarters, a hospital building, recreation building, guards’ mess, storage buildings, a garage, barn, and a supply depot.

Constructed at the site of the Ontario Highway Construction Camp No. 12, the first POWs arrived at Angler on January 10, 1941, with another 558 POWs arriving from the United Kingdom fifteen days later (Library and Archives Canada n.d.). By May 1942, 689 prisoners were interned at the camp. The German prisoners were transferred to Camp 133 on June 14, 1942, and 190 Japanese internees from the Vancouver Immigration Building entered Angler on June 19, 1942. They would remain here for the next four years. In November 1942, the camp reached its highest number of internees at 710 (Figure 13). The camp was closed on July 29, 1946, at which time the last of the internees were finally released.

The Angler Internment Camp is known as the site of the largest and most notorious escape attempt to occur in a Canadian POW camp during World War II (Melady 1981). On April 18, 1941, twenty-eight POWs broke out through a 1 m-wide and 50 m-long tunnel excavated beneath the southernmost barracks to just beyond the south wall of the wire fence. Twenty-four of the men were recaptured quickly, two were killed –and were reportedly buried at the camp— and the last two —Horst Liebeck and Karl Heinz-Grund— managed to board a passing train and travel to Medicine Hat, Alberta, before they were finally recaptured and returned to the Angler Internment Camp.

32

E

10 12

11 6 20 D 19 21 18 7 Layout of Angler Camp Legend

1. Kitchen and1. Dining Room 8 2. Qua 2. rters 3. Qua 3. rters 23 17 1 4. Qua 4. rters 13 9 5. Qua 5. rters 6. Hospital 6. 25 7. Detention 7. A 8. Barber and 8. Tailor Shop 9. Recrea 9. tion 24 16 2 10. Pum 10. House p 11. Office 11. 26 12. Tooland 12. Gua House rd 15 13. Power 13. House 14. Officer’s 14. Mess 3 15. Officer’s 15. Qua rters 16. Officer’s 16. Qua rters 14 17. Gua 17. Hospital rds 27 18. Qua 18. rters 19. N.C.O. QuaN.C.O. 19. rters 4 20. Gua 20. Recrea rds tion 21. Gua 21. Mess rds 22. R.C.R. Stores (not shown) (not Stores R.C.R. 22. 23. Wa 23. Tank ter 24. Pum 24. House p 5 25. Ga 25. rage 26. Supply 26. Depot 27. Barn 27. A. Gua A. Tower rd B. Gua B. Tower rd C C . GuaC. Tower rd B D . GuaD. Tower rd E. Gua E. Tower rd

LEGEND REFERENCE(S) Project Component AnglerIntermentCam Fence p Line KEYMAP BASEDATA:MN CAN MN RF(2018), LIO DILLONV 2015), EC DM(2017), (2014, (2017) PROJECTCOMPON ENPROV TS: IDEDBYNEXTBRIDGE (2018) Access Road Temporary for Construction AN GLERINTERN MENCAMP: T HQSCON - 7236-96-101 STRUCTIONAN DMAINTEN AN CEOF 0 25 50 75 AccessRoad Improvem - ent/Widening ³ CAMPS.AN GLER,MICROFILM REEL RG24,C-5420,LIBRARY AN ARCHIVES D CAN ADA. PRODUCEDBYGOLDER ASSOCIATES UNLTD. DERLICEN SEFROM ON TARIOMINISTRY OF LocaStudy l Area N ATURALRESOURCES, ©QUEEN PRINTER S 2018 !( 1:1,850 KILOMETRES PROJECTIONTRAN : SVERSEMERCATOR DATUM: NAD COORDINATE83 SYSTEM: UTM ZON 16N E

CLIEN T PROJECT HERITAGEIMPACT ASSESSMEN EAST-WEST T, TIE TRAN SMISSIONPROJECT B AN SI FROM: MODIFIED BEEN HAS SIZE SHEET THE NSHOW , IS WHAT MATCH NOT DOES T MEASUREMEN THIS IF 5 m 25m

WAWA J" YYYY-MM-DD 2018-07-10 TITLE DESIGN ED GOLDERJR LAYOUT OF ANGLER CAMP 1941-1946

PREPARED GOLDERJB

REVIEW ED GOLDERBH PROJECTNO. CON TROL REV. FIGURE APPROV ED GOLDERHJD 1536607 1

PATH: S:\Clients\N extBridge\East_W est_Tie\99_PROJ\1536607_EA\40_PROD\0040_HIA_Report\1536607-0040-HC-0009.mxd PRINTED ON : 2018-07-10 AT: 6:49:06 PM 6:49:06 AT: 2018-07-10 ON : PRINTED est_Tie\99_PROJ\1536607_EA\40_PROD\0040_HIA_Report\1536607-0040-HC-0009.mxd extBridge\East_W S:\Clients\N PATH: 10 0 July 13, 2018 1536607-2000-R01

Figure 11: Entrance Gate to the Angler Internment Camp (Library and Archives Canada).

Figure 12: Winter at the Angler Internment Camp (Japanese Canadian Photograph Collection, University of British Columbia Library).

34

July 13, 2018 1536607-2000-R01

Figure 13: Japanese Internees at the Angler Internment Camp (Japanese Canadian Photograph Collection, University of British Columbia Library). 5.3.3 Aguasabon River and Hays Lake In the 1930s, the Ontario Government and the Pulpwood Supply Company signed an agreement to divert water down Long Lake into Lake Superior in order to provide employment and open up an area north of Lake Superior for timber extraction (Peet and Day 1980:35). Between 1935-1938, the Hydro-Electric Power Commission of Ontario (HEPCO) cut a canal through the height of land and redirected the flow of the Kenogami River through Long Lake and the Aguasabon River into Lake Superior (Barry 1984:12). The Long Lake Diversion project involved the construction of the Kenogami River control dam 10 km north of Long Lake, the diversion canal and the Long Lake Control Dam at the south end of Long Lake (Peet and Day 1980:36). The Ontario government planned to divert enough water to more easily transport pulpwood and utilize the diverted water for power production at Niagara.

American resistance to an increase in Great Lakes water levels initially prevented Ontario from diverting more water than was required for transporting pulpwood (Peet and Day 1980:36). However, during World War 2 wartime requirements for power led to an exchange of diplomatic notes allowing Ontario to use the diverted water for power production and in 1950 the Niagara Treaty was signed guaranteeing use of the water (Peet and Day 1980:36). A second phase of hydropower project construction –the Aguasabon Generating Station and Hays Lake Dam— was started in 1945 and ran until 1948. In 1946, the Hays Lake Dam –a concrete gravity dam— was built (Terrace Bay Public Library n.d.) which connected several small lakes and the Aguasabon River and expanded the size of Hays Lake approximately 500 times. This dam provided power for the Longlac Pulp & Paper Company pulp mill and the newly created town of Terrace Bay. The mill began using the Hays Lake reservoir as the booming ground for logs (Peet and Day 1980:36).

35

July 13, 2018 1536607-2000-R01

6.0 AFFECTED ENVIRONMENT 6.1 Gananoque Vein Gold Mine The Gananoque Vein Gold Mine site is located within the Project footprint, approximately 6.25 km south of the Community of Wawa. It is recorded in the AMIS database on the south side of High Falls Road, adjacent to an existing Hydro One transmission corridor, and at the base of a steep slope.

The existing Hydro One transmission corridor is covered in low growing maintained vegetation including grasses, shrubs and blueberry bushes, while the surrounding area is thick pine forest (Figure 14). Large rocks cover the ground at the base of the slope, but no cultural features were noted (Figure 15).

The AMIS database describes two trenches and two adits1 at the base of the cliff that were visible during a 1992 survey, but in 2013 these features could not be located by staff at the Ministry of Mines and Northern Development. The site could also not be located during the field investigations conducted for this HIA. The site may therefore either be a distance from the point indicated in the AMIS database (due to errors when transcribing from paper maps to digital coordinates) or thick vegetation growth has completely obscured any surface features.

Approximate site of the Mine

High Falls Road.

Figure 14: View facing south of the location identified in AMIS as the Gananoque Vein Gold Mine Site.

1 An adit is a ‘horizontal passage driven from the surface for working or unwatering a mine’ (Noble and Spude 1997:29).

36

July 13, 2018 1536607-2000-R01

Figure 15: View facing west of large rocks and thick vegetation growth around the location identified in AMIS as the Gananoque Vein Gold Mine Site. 6.2 Molybdenite Lake Prospect The Molybdenite Lake Prospect site is associated with an access road 2.4 km north from the Project footprint and approximately 15 km northwest of the community of Wawa. A narrow track for an ATV or snowmobile trail winds through the forest from the TransCanada Highway and passes through the site. The mine site is on the south side of Molybdenite Lake, and consists of large areas with exposed rock surrounded by pine forest (Figure 16). Vegetation around the mine workings includes shrubs and grasses (Figure 17).

The AMIS database describes 12 shallow trenches approximately 1-m deep. Only one discernable trench was found during the site visit, with other visible signs of mine activity including the track in to the site, piles of earth alongside the track, and broken and exposed rock. The boundaries of the site are unclear; piles of dirt and broken rock that may be related to mining activity on the site are spread out over an area 2-km long beside the trail running alongside the southeast side of Molybdenite Lake. Broken and exposed rock could be evidence of trenching or stripping at various points in the area.

37

July 13, 2018 1536607-2000-R01

Figure 16: View facing north of exposed and broken rock from the Molybdenite Lake Prospect explorations.

Figure 17: View facing west of vegetation and rocks in one of the Molybdenite Lake Prospect mine trenches.

38

July 13, 2018 1536607-2000-R01

6.3 Angler/Petrunka Granite Quarry The Angler/Petrunka Granite Quarry is 8.8 m south from the Project footprint, both in and adjacent to the cleared ROW for a current Hydro One transmission corridor, and approximately 7 km northwest of the Town of Marathon. The CPR rail line runs through a rock cut approximately 125 m west of the quarry location, as indicated in the AMIS database, but this cut is not part of the quarry (Figure 18). The site is surrounded with thick pine forest, exposed rock and low lying wet areas (Figure 19), while the portion within the existing transmission corridor is covered in bushes and grasses, and has wet low areas between rock ridges.

The AMIS database describes an open cut quarry pit approximately 30 m × 30 m and 2 m deep with some equipment around the site. During the field investigations for this HIA, a number of rough-squared granite blocks and pieces of wooden crate or pallet were found close to the site, on the east side of the existing transmission corridor (Figure 20). A large pile of rough unshaped pieces of granite with drill marks, as well as artifacts such as a steel cable and part of a mechanical winch or crane, were found on the west side of the existing transmission corridor (Figure 21). The artifacts around the site were distributed over a large area and found in the existing transmission corridor and open areas either side of the ROW. However, the 30 m × 30 m open quarry pit described in the AMIS database was not found.

Figure 18: View facing north along the CPR rail line running through the Angler Granite Quarry/Petrunka.

39

July 13, 2018 1536607-2000-R01

Figure 19: View facing west from the centre of the existing transmission corridor of the area around the Angler/Petrunka Granite Quarry site.

Figure 20: View facing north of rocks cut from the Angler/Petrunka Granite Quarry, view facing north.

40

July 13, 2018 1536607-2000-R01

Figure 21: View facing east of a large mechanical winch or part of a crane near the site of the Angler/Petrunka Granite Quarry.

6.4 Halonen Fluorite Mine The Halonen Fluorite Mine is associated with an access road 76.6 m south from the Project footprint, and approximately 500 m north of the TransCanada Highway, 29 km west of the community of Schreiber, and 47 km east of the community of Nipigon. The site is on a narrow strip of land between two small lakes: Nishin Lake to the north, and Wabasta Lake to the south. The area is dense mixed forest with a large amount of deadfall and thick moss (Figure 22). A paved road runs past the site between the lakes.

The AMIS database describes a trench and some stripping, blasting, and drilling at the site. No trench or other evidence of mining activity was found during the site visit. It may be quite a distance from the point indicated in the AMIS database due to errors in the original posting, or may have been reclaimed by forest. No tangible elements of the mine workings were found.

41

July 13, 2018 1536607-2000-R01

Figure 22: View facing east of the forest at the site recorded in AMIS as the Halonen Fluorite Mine. 6.5 Bishop Lead Occurrence The Bishop Lead Occurrence is associated with an access road 890.8 m north from the Project footprint, within a few metres of a dirt track extending off Cavern Road, and approximately 10 km northwest of the community of Dorion. The site is surrounded by dense mixed forest with numerous deadfall (Figure 23).

The AMIS database describes a series of test pits, a trench, shaft and an adit from 1929. The dataset indicates that in 2000 the adit was partially collapsed and blocked by timbers. At that time the shaft had steep sides but was filled to within 1-m of the surface with a solid floor.

A pit with steep sides and solid base was found at the location where the adit is recorded in AMIS. The pit was full of deadfall and thick moss (Figure 24). No timbers were visible at the site, and although a pile of cut logs was found approximately 45m southeast of the pit, there is no evidence that it is connected with the mine. It is more likely that the logs were cut as part of clearing for the nearby road.

42

July 13, 2018 1536607-2000-R01

Figure 23: View facing southwest of a dirt track through the forest next to the Bishop Lead Occurrence site.

Figure 24: View facing east of the exposed rock from the walls of the pit at the Bishop Lead Occurrence.

43

July 13, 2018 1536607-2000-R01

6.6 Mackenzie Quarry The Mackenzie Quarry is 35.2 m north from the Project footprint, 450 m north of the TransCanada Highway, and approximately 13 km east of the City of Thunder Bay. Vegetation around the site consists of small evergreen trees, shrubs and grasses, and the topography site is gently rolling or flat (Figure 25).

The quarry is an approximately 50 m by 30 m rectangular cut into the west side of a large granite protrusion, and is associated with a depleted sand pit. During the field investigation for this HIA, large piles of broken rock were found in and around the quarry. (Figure 26).

Figure 25: The landscape north of the Mackenzie Quarry, view facing northeast.

44

July 13, 2018 1536607-2000-R01

Figure 26: The Mackenzie Quarry, view facing north. 6.7 Angler Internment Camp Angler Internment Camp is 200 m west of the Project footprint, immediately east of the CPR railway line, and approximately 5.5 km north of the Town of Marathon and on land owned by the Town. Part of the area is covered in dense forest with some areas of moss and lichen-covered rock outcrops (Figure 27). A large part of the camp location was reforested in the 1960s with pine trees planted in rows (Figure 28). On the banks of Angler Creek are wetland areas and dense vegetation (Figure 29). An existing ATV trail also runs through the former camp.

As identified during the field investigations for the HIA, remains of the camp visible on the surface include:  A large dump of metal cans and pots near the railway line (Figure 30);  Foundations from part of the northernmost internee quarters (Figure 31);  Earthworks, possibly indicating foundations, at the location of former buildings (Figure 32);  Trenches, possibly for drainage, near the location of fences and buildings (Figure 33);  A wood lined pit, possibly a well (Figure 34); and  Scatter of metal artifacts including fence posts, stovepipe/chimney, and plumbing pipes (Figure 34 and Figure 35).

Available research did not reveal a location of the graves of the two German POWs killed in an escape attempt at the camp. It is unknown if their bodies remain interred at the site, were moved to a new location when the camp closed, or if they were repatriated to Germany after the war. Field reconnaissance found no evidence of a cemetery at the site.

45

July 13, 2018 1536607-2000-R01

Figure 27: View facing east of dense forest between the Angler Internment Camp and the railway.

Figure 28: View facing southwest of the reforested area at the south extent of the Angler Internment Camp.

46

July 13, 2018 1536607-2000-R01

Figure 29: View facing east over the Angler Creek valley towards the Angler Internment Camp.

Figure 30: View facing north of a dump of metal artifacts including cans and pots between the Angler Internment Camp and railway line.

47

July 13, 2018 1536607-2000-R01

Figure 31: View facing west of a poured concrete foundation of one of the internee quarters.

Figure 32: View facing east of linear mounds at the approximate location of internment camp buildings.

48

July 13, 2018 1536607-2000-R01

Figure 33: View facing southeast of a trench through the middle of the internment camp.

Figure 34: View facing north of stove or chimney pipe and a wood lined pit, possibly a well near the site of former internee quarters.

49

July 13, 2018 1536607-2000-R01

. Figure 35: View facing southwest of a steel fencepost in a trench near the north end of the Internment Camp 6.8 Aguasabon River and Hays Lake The Aguasabon River and Hays Lake is a large impoundment lake north and west of the community of Terrace Bay. The project footprint crosses the impoundment lake approximately 6 km upstream of Terrace Bay. The soils around the lake are sandy. The boreal forest extends to the edge of the water in most places. The project footprint crosses the impoundment lake at a narrow spot approximately 200 m wide (see Figure 9). The landscape can be characterized as natural.

Approximate site where the Project crosses the River/Lake

Aguasabon River/Hays Lake

Figure 36: View facing north-northwest up the Aguasabon River/ Hays Lake from a point approximately 1.9 km south of the project footprint.

50

July 13, 2018 1536607-2000-R01

7.0 CULTURAL HERITAGE EVALUATION From the results of the historical research, consultation, and field investigations, the mine sites, the Angler Internment Camp and the Aguasabon River were evaluated to determine if they met the criteria for cultural heritage value or interest (CHVI) as prescribed in O. Reg. 9/06. The mine sites, the internment camp and the Aguasabon River are defined geographical areas modified by human activity. 7.1 Gananoque Vein Gold Mine During the field investigation for this HIA, the Gananoque Vein Gold Mine site could not be found within the LSA. In the absence of tangible remains, it cannot be evaluated as a cultural heritage resource or cultural heritage landscape. It is possible that site location information from the AMIS database is erroneous and the site is not in the Project LSA. The Ministry of Northern Development and Mines could not locate the site in 2013 (AMIS file 00874), so it is possible the site adits have been filled in or collapsed and been reclaimed by the forest. If this site is rediscovered during project work the Discovery of Cultural Heritage Resources Contingency Plan (Section 8.1.5 in this report) will be enacted and the site can be evaluated and impact assessment and mitigation can be developed at that time.

7.2 Molybdenite Lake Prospect

Table 2: Molybdenite Lake Prospect O. Reg. 9/06 Evaluation Meets Criterion Criteria Rationale (Yes/No) Design Value or Physical Value This mine site is not rare, unique, representative or an early example of its type. The Molybdenite Lake Prospect involved trenching and sampling, both common methods of mineral extraction. Molybdenite has been mined in Ontario since the 1860s so this mine, which was actively Is a rare, unique, worked in 1939, is not an early example. This site does not portray or representative or early symbolize a type of mine site. Some evidence of the site remains include example of a style, type, No mounds of earth and rock, the track into the site, some trenches and expression, material or bare rock, but the built elements of the mine are gone along with construction method. artifacts. Not enough of the site remains to represent a mine of the period. The mineral is not common in this part of Ontario, but the site was not economically viable as illustrated by the short duration of mining activity at the site and subsequent testing that had unfavourable results. Displays a high degree of The site does not display craftsmanship or artistic merit in its design or craftsmanship or artistic No construction, evidence of the site is found in simple trenches and merit. stripped soil and rock. Demonstrates a high degree The site does not demonstrate a high degree of technical or scientific of technical or scientific No achievement: it was excavated or mined using common methods such as achievement. trenches and drilling. Historical Value or Associative Value There is no evidence to suggest the Molybdenite Lake Prosect site has Has direct associations with any direct associations with a theme, event, belief, person, activity, a theme, event, belief, organization or institution that is significant to a community or that there person, activity, organization, No are significant interrelationships between the site and surrounding area. or institution that is significant This site was mined in 1939 and molybdenum was likely being sought to to a community. support the war effort. However, there is no indication that molybdenite was in great demand in 1939. Later in the war demand for the mineral

51

July 13, 2018 1536607-2000-R01

Table 2: Molybdenite Lake Prospect O. Reg. 9/06 Evaluation Meets Criterion Criteria Rationale (Yes/No) grew; but this site was not mined, indicating that this site was not viable. This was a minor site in a vast mining area. Yields, or has the potential to Based on the limited physical evidence present at the mine, it is unlikely yield, information that to have the potential to yield information important to understanding a contributes to an No community or culture, nor further insight into the historical development understanding of a of the mining industry. community or culture. The mine does not demonstrate or reflect the work or ideas of significant Demonstrates or reflects the engineers, designers, theorists, architects, miners, or builders. There is work or ideas of an architect, no evidence to suggest that this site, the mining companies or any artist, builder, designer or No persons associated with this site made more than average contributions theorist who is significant to a to mining in Ontario and there is no evidence to suggest they are community. significant to a community. Contextual Value The site does not define or support the character of the area. Today the Is important in defining, character is heavily vegetated or reclaimed by the forest. Evidence of maintaining or supporting the No mining activity is limited to a few trenches, pits, piles of soil and rock and character of an area. exposed bedrock. The character of the surrounding area is a natural northern forest and lake environment. The site is functionally linked to occurrences of molybdenite, but this is not considered a historically or culturally significant relationship to the location. The site is a single instance of molybdenite mining in a large Is physically, functionally, forest area in northern Ontario, it does not have a relationship to the visually or historically linked No broader forest context. The site has no physical, functional, visual or to its surroundings. historical connections to other mine sites or mining activity in the area. It is a single isolated site in the forest that was actively mined for just a year. The site is not considered a landmark since it is remote, often obscured Is a landmark. No or covered in thick vegetation, and not considered a significant place by the nearest community.

7.3 Angler/Petrunka Granite Quarry

Table 3: Angler/Petrunka Granite Quarry O. Reg. 9/06 Evaluation Meets Criterion Criteria Rationale (Yes/No) Design Value or Physical Value The quarry is not rare, unique, representative or an early example of its type: common methods of granite extraction such as drilling and an open Is a rare, unique, cut in the rock were used at the site. The rock quarried from the site is representative or early common throughout the surrounding area. The Angler Granite quarry site example of a style, type, No is one of several staked in the area. This site does not portray or expression, material or symbolize a type of quarry site. Some evidence of the site remains construction method. including blocks of rock cut from the ground and a pit, but any built elements of the quarry are gone along with artifacts. Not enough of the site remains to represent a quarry of the period.

52

July 13, 2018 1536607-2000-R01

Table 3: Angler/Petrunka Granite Quarry O. Reg. 9/06 Evaluation Meets Criterion Criteria Rationale (Yes/No) Displays a high degree of The quarry does not display craftsmanship or artistic merit in its design or craftsmanship or artistic No construction. Evidence of the site is found in a simple open cut in the merit. rock and some rough-cut granite blocks left on the site. Demonstrates a high degree The quarry does not demonstrate a high degree of technical or scientific of technical or scientific No achievement: it was excavated using common methods and tools. achievement. Historical Value or Associative Value There is no evidence to suggest the Angler/Petrunka Granite Quarry site has any direct associations with a theme, event, belief, person, activity, Has direct associations with organization or institution that is significant to a community or that there a theme, event, belief, are significant interrelationships between the site and surrounding area. person, activity, organization, No The quarry was active for just a year and was one of several granite or institution that is significant claims in the area. There is no evidence to suggest that any of the to a community. people or companies that claimed, worked or tested at this site over the years are significant to a community. This was a minor site in a large area with many granite quarry claims. Based on the limited physical evidence present at the quarry site, it is Yields, or has the potential to unlikely to have the potential to yield information important to yield, information that understanding a community or culture, nor further insight into the contributes to an No historical development of the mining industry. This site was a small understanding of a ordinary, common type of quarrying operation found throughout northern community or culture. Ontario. The quarry does not demonstrate or reflect the work or ideas of Demonstrates or reflects the significant engineers, designers, theorists, architects, miners, or builders. work or ideas of an architect, There is no evidence to suggest that this site, the companies or any artist, builder, designer or No persons associated with this site made more than average contributions theorist who is significant to a to mining in Ontario and there is no evidence to suggest they are community. significant to a community. Contextual Value The quarry does not define or support the character of the area. Today Is important in defining, the character of part of the site is heavily vegetated and the rest is maintaining or supporting the No characterized by an existing transmission corridor full of grasses and character of an area. bushes. The site is next to a rock cut for the CP railway. The quarry is functionally linked to the stone in the area, but this is not considered a historically or culturally significant relationship to the Is physically, functionally, location. The site does not have a relationship to the broader forest visually or historically linked No context. The site has no physical, functional, visual or historical to its surroundings. connections to other quarry sites or activity in the area. It is an isolated site in the forest that was actively mined for just a single year. The quarry is not considered a landmark since it is remote, obscured or Is a landmark. No covered in thick vegetation, and not considered a significant place by the nearest community.

7.4 Halonen Fluorite Mine During the field investigation for this HIA, the Halonen Fluorite Mine site could not be found within the LSA. In the absence of tangible remains, it cannot be evaluated as a built heritage resource or cultural heritage landscape. It is possible that site location information from the AMIS database is erroneous and the site is not in the Project LSA. It is also possible evidence for trenching and drilling at the site has been reclaimed by the forest. If this site

53

July 13, 2018 1536607-2000-R01

is rediscovered during project work the Discovery of Cultural Heritage Resources Contingency Plan (Section 8.1.5 in this report) will be enacted and the site can be evaluated and impact assessment and mitigation can be developed at that time. 7.5 Bishop Lead Occurrence

Table 4: Bishop Lead Occurrence O. Reg. 9/06 Evaluation Meets Criterion Criteria Rationale (Yes/No) Design Value or Physical Value The site is not rare, unique, representative or an early example of its type: common methods of extraction including trenching and a shaft were Is a rare, unique, used at the site, and the minerals mined are relatively common representative or early throughout northern Ontario. This mine site is one of several occurrences example of a style, type, No along a fault in the area. This site does not portray or symbolize a type of expression, material or mine site. Some evidence of the site remains including a pit in the construction method. ground, but any built elements of the mine are gone along with artifacts. Not enough of the site remains to represent a mine of the period. Very little remains of the mine site. Displays a high degree of The site does not display craftsmanship or artistic merit in its design or craftsmanship or artistic No construction. All that remains of the site that could be found during field merit. investigation is a shallow pit in the ground. Demonstrates a high degree The site does not demonstrate a high degree of technical or scientific of technical or scientific No achievement: it involved the excavation of a shaft and pits, which are achievement. common mining activities. Historical Value or Associative Value There is no evidence to suggest the Bishop Lead Occurrence site has any direct associations with a theme, event, belief, person, activity, organization or institution that is significant to a community or that there are significant interrelationships between the site and surrounding area. The name Bishop was likely the name of the prospector or owner of the Has direct associations with mining outfit that excavated this site, however no information on who a theme, event, belief, Bishop was could be found. No information on anyone named Bishop person, activity, organization, No active in the mining industry at the time and in the area of the site could or institution that is significant be found. No evidence could be found to indicate that this person was to a community. significant to a community. Furthermore, production from this site was limited in duration indicating that this site was not economically viable over the long term. This was a minor and short duration site in a vast mining area and a small site with limited production along a fault that had other, productive lead mines. Yields, or has the potential to Based on the limited physical evidence present at the mine, it is unlikely yield, information that to have the potential to yield information important to understanding a contributes to an No community or culture, nor further insight into the historical development understanding of a of the mining industry. community or culture. The mine does not demonstrate or reflect the work or ideas of significant Demonstrates or reflects the engineers, designers, theorists, architects, miners, or builders. There is work or ideas of an architect, no evidence to suggest that this site, the mining company or any persons artist, builder, designer or No associated with this site made more than average contributions to mining theorist who is significant to a in Ontario and there is no evidence to suggest they are significant to a community. community.

54

July 13, 2018 1536607-2000-R01

Table 4: Bishop Lead Occurrence O. Reg. 9/06 Evaluation Meets Criterion Criteria Rationale (Yes/No) Contextual Value Is important in defining, The site does not define or support the character of the area. Today the maintaining or supporting the No area around the mine site is a heavily forested natural environment. character of an area. The site is functionally linked to its respective mineral deposits, but this is not considered a historically or culturally significant relationship to the location. The site does not have a relationship to the broader forest Is physically, functionally, context. The site has no physical, functional or visual connections to visually or historically linked No other mine sites or activity in the area. This site appears to be the only to its surroundings. one of the Bishop claims in the area to have been mined, there is no evidence of any significant historical connections between this mine and others in the area. It is an isolated site in the forest that was actively mined for just a single year. The site is not considered a landmark since it is remote, often obscured Is a landmark. No or covered in thick vegetation, and not considered a significant place by the nearest community.

7.6 Mackenzie Quarry

Table 5: Mackenzie Quarry O. Reg. 9/06 Evaluation Meets Criterion Criteria Rationale (Yes/No) Design Value or Physical Value The quarry is not rare, unique representative or early: common methods of quarrying were used at the site, and the rock extracted is common throughout the area and throughout northern Ontario. Mining activity in Is a rare, unique, the area began in the mid-19th century, predating this quarry by decades. representative or early The CPR quarried stone at many locations across northern Ontario for example of a style, type, No bridges and ballast stone. This site does not portray or symbolize a type expression, material or of quarry site. Some evidence of the site remains including the cut into construction method. the granite knob and mounds of earth and rock, but any built elements of the quarry are gone along with artifacts. Not enough of the site remains to represent a quarry of the period. The quarry does not display craftsmanship or artistic merit in its design or Displays a high degree of construction. It is an open cut into a knob of rock, which was a simple craftsmanship or artistic No and common method of quarrying rock that would have required an merit. average level of skill to accomplish. The quarry does not demonstrate a high degree of technical or scientific Demonstrates a high degree achievement: based on field investigation it appears that this site was of technical or scientific No excavated using common methods as rock was cut and excavated from achievement. an exposed knob of granite.

55

July 13, 2018 1536607-2000-R01

Table 5: Mackenzie Quarry O. Reg. 9/06 Evaluation Meets Criterion Criteria Rationale (Yes/No) Historical Value or Associative Value There is no evidence to suggest the Mackenzie Quarry site has any Has direct associations with direct associations with a theme, event, belief, person, activity, a theme, event, belief, organization or institution that is significant to a community or that there person, activity, organization, No are significant interrelationships between the site and surrounding area. or institution that is significant It was excavated in the 1880s to supply stone for the CPR railway; to a community. however, the CPR excavated quarries at many points along the route of the railway. Yields, or has the potential to The quarry is a cut in the rock, no machinery or equipment was found on yield, information that the site. Based on the limited physical evidence present at the quarry, it contributes to an No is unlikely to have the potential to yield information important to understanding of a understanding a community or culture, nor further insight into the community or culture. historical development of the mining or railway industry. Demonstrates or reflects the There is no evidence that the quarry demonstrates or reflects the work or work or ideas of an architect, ideas of significant engineers, designers, theorists, architects, miners, or artist, builder, designer or No builders. There is no evidence to suggest that this site, or any persons theorist who is significant to a associated with this site made more than average contributions to mining community. or railway history in Ontario. Contextual Value Is important in defining, The quarry does not define or support the character of the area. Today maintaining or supporting the No the character of the area around the quarry is an area of open space character of an area. covered in grasses and scrub bushes and trees. The quarry is functionally linked to the stone excavated from the site, but Is physically, functionally, this is not considered a historically or culturally significant relationship to visually or historically linked No the location. The stone from the quarry is common in the area and similar to its surroundings. stone was quarried at numerous locations throughout northern Ontario. The quarry is not considered a landmark and not considered a significant Is a landmark. No place by the nearest community.

7.7 Angler Internment Camp

Table 6: Angler Internment Camp O. Reg. 9/06 Evaluation Meets Criterion Criteria Rationale (Yes/No) Design Value or Physical Value Is a rare, unique, The Angler Internment Camp has physical or design value as one of very representative or early few internment camps in Canada and a representative example of a example of a style, type, Yes purpose-built camp (as opposed to modified existing site such as Fort expression, material or Henry National Historic Site of Canada) for both POWs and civilian construction method. internees. Displays a high degree of Since the Angler Internment Camp was expediently constructed for the craftsmanship or artistic No war years, there is no physical or photographic evidence that the Camp’s merit. buildings had a high degree of craftsmanship or artistic merit. Demonstrates a high degree As an expediently built facility, the Angler Internment Camp does not of technical or scientific No demonstrate a high degree of technical or scientific achievement. achievement.

56

July 13, 2018 1536607-2000-R01

Table 6: Angler Internment Camp O. Reg. 9/06 Evaluation Meets Criterion Criteria Rationale (Yes/No) Historical Value or Associative Value The Angler Internment Camp has direct associations with Canadian involvement in the Second World War and with the internment of POWs and civilians on home soil. Importantly, it is directly associated with the Japanese Canadian community and their treatment during the war, and is the site of the largest and most infamous POW escape attempt at a Has direct associations with Canadian POW camp. On a secondary level it is associated with the a theme, event, belief, Veterans Home Guard and internee labour in the logging industry and for person, activity, organization, Yes infrastructure construction. or institution that is significant to a community. The Historic Sites Branch of the former Ontario Division of Parks (now MTCS) did not recognize this Second World War period in its Military theme (Historic Sites Branch 1973:181), but this period is recognized as important in the Parks Canada System Plan under the broad theme of Governing Canada, and Military and Defence sub-theme (Parks Canada 2000:19). As an archaeological site and subject for historical research, the Angler Yields, or has the potential to Internment Camp has high potential to yield information contributing to yield, information that our understanding of Second World War internment policy, site selection, contributes to an Yes camp construction, and a wide variety of other topics such as daily life for understanding of a the internees and guards. It also has the potential to yield details on the community or culture. POW escape. Further research is required, but it is likely that the layout and design of Demonstrates or reflects the the Angler Internment Camp was designed by Canadian government work or ideas of an architect, engineers or architects who were influenced by mid-20th century artist, builder, designer or Yes theoretical and design concepts on: military geography and engineering; theorist who is significant to a large scale surveillance, social control, and open sightlines; and the community. construction and design of pre-fabricated buildings. Contextual Value Most of the standing structures of the Angler Internment Camp were removed when it was closed, and the area no longer has the cleared and Is important in defining, open vistas that were required when the camp was in operation. By maintaining or supporting the No contrast, the character of the area today is reclaimed forest and no character of an area. longer defined by the presence of a large internment camp or related infrastructure. In a broad sense the Angler Internment Camp is functionally linked to its remote, isolated northern environment, and is physically and functionally linked to the CPR line and Angler Creek, the former for access and the Is physically, functionally, latter as a source of potable water. It is also historically linked to other visually or historically linked Yes POW and internment camps across Canada, including the Red Rock to its surroundings. Camp and Neys Camps on the north shore of Lake Superior. Its visual connections have been compromised by vegetation growth and reclamation since its closure. Although little of the Angler Internment Camp is evident on the surface Is a landmark. Yes and is obscured by thick vegetation, the camp was identified during consultation as an important cultural site.

57

July 13, 2018 1536607-2000-R01

7.8 Aguasabon River and Hays Lake

Table 7: Aguasabon River and Hays Lake O. Reg. 9/06 Evaluation Meets Criterion Criteria Rationale (Yes/No) Design Value or Physical Value Is a rare, unique, representative or early The Aguasabon River and Hays Lake is not a rare, unique, example of a style, type, No representative or early example of an impoundment lake. Impoundment expression, material or lakes are common throughout Ontario. construction method. Displays a high degree of The impoundment lake does not display a high degree of craftsmanship craftsmanship or artistic No or artistic merit. The lake was allowed to fill behind the dam in the 1940s merit. without additional human modification of the landscape. The impoundment lake is the result of a gravity dam, a common and Demonstrates a high degree well-known technology. There is no evidence that the creation of this lake of technical or scientific No involved anything more than an average level of skill and technical achievement. knowledge. Historical Value or Associative Value The creation of the Aguasabon River and Hays Lake as an impoundment Has direct associations with lake was directly associated with the expansion of pulp production along a theme, event, belief, the north shore of Lake Superior and with the development of power person, activity, organization, Yes generation locally and throughout Ontario. This river is linked to the or institution that is significant theme of Developing Economies and sub-theme of Extraction and to a community. Production in the Parks Canada System Plan. Yields, or has the potential to The impoundment lake filled the natural area behind the Hays Lake yield, information that control dam. There is no indication that the lake has the potential to yield contributes to an No information that contributes to an understanding of a community or understanding of a culture. The enlarged river and lake is essentially part of the surrounding community or culture. natural environment. Demonstrates or reflects the There is no evidence that the impoundment lake demonstrates or reflects work or ideas of an architect, the work or ideas of an architect, artist, builder, designer or theorist who artist, builder, designer or No is significant to a community. The lake is the result of the construction of theorist who is significant to a the control dam. community.

58

July 13, 2018 1536607-2000-R01

Table 7: Aguasabon River and Hays Lake O. Reg. 9/06 Evaluation Meets Criterion Criteria Rationale (Yes/No) Contextual Value The impoundment lake is not important in defining, maintaining or supporting the character of the area. The Aguasabon River and Hays Lake are larger as a result of the control dam but without the dam the Is important in defining, river and lake would still exist in its smaller, original size. maintaining or supporting the No character of an area. The river and lake, as a result of the dam, is not a significant indicator of the area’s character which is understood as part of the surrounding boreal forest dotted with small lakes and creeks. The character of the area is not unique. The impoundment lake is historically linked to its surroundings. One of the reasons the enlarged river and lake was created was to make it easier to extract timber from the northern forest in the area and support the local pulp industry. The impoundment lake is indirectly linked to the community of Terrace Bay. The creation of both the enlarged lake and Is physically, functionally, the community are historically linked to the Long Lake Diversion Project, visually or historically linked Yes the Hays Lake control dam and Aguasabon Generating Station. to its surroundings. The impoundment lake as an artificially formed feature is a result of the control dam. It is physically and visually linked to its surroundings. However, the impoundment lake is similar to nearby lakes in the boreal forest with the exception that it has been artificially enlarged. The character of the lake within the forest is not distinct. These links are not considered historically significant. The impoundment lake is not considered a landmark and not considered Is a landmark. No a significant historic place by the nearest community. The river and lake are valued as a recreational resource.

7.9 Evaluation Results The preceding evaluation has determined that:  The Gananoque Vein Gold Mine and Halonen Fluorite Mine could not be evaluated since the sites could not be found within the Project LSA. It is possible the sites are not in the LSA and/or the sites have been reclaimed by the forest.  The Molybdenite Lake Prospect and Bishop Lead Occurrence mine sites are not of CHVI since they do not meet any criteria of O. Reg. 9/06;  The Angler/Petrunka Quarry and Mackenzie Quarry sites are not of CHVI since they do not meet any criteria of O. Reg. 9/06;  The Angler Internment Camp is of CHVI since it meets six criteria of O. Reg. 9/06; and,  The Aguasabon River and Hays Lake is of CHVI since it meets two criteria of O. Reg. 9/06. Based on these results a draft Statement of CHVI has been prepared for the Angler Internment Camp and the Aguasabon River and Hays Lake (APPENDIX A).

59

July 13, 2018 1536607-2000-R01

8.0 IMPACT ASSESSMENT 8.1 Project Description NextBridge is proposing to construct and operate an approximately 450-km long, double-circuit 230 kV transmission line connecting the Lakehead Transformer Station in the Municipality of Shuniah, near the City of Thunder Bay, to the Wawa Transformer Station located east of the Municipality of Wawa, with a connection at the Marathon Transformer Station near the Town of Marathon (Figure 1).

Construction for the Project will include:  site preparation, including clearing of vegetation, grading, and stripping of topsoil;  construction of new access roads and improvements to existing roads;  construction of temporary workspaces (i.e., laydown yards, construction camps, storage yards, and construction easements);  transportation of construction equipment and materials along the ROW;  construction of the transmission line, including tower foundation excavation, structure assembly and erection, and conductor stringing and tensioning;  construction clean-up, decommissioning (i.e., the process of safely removing infrastructure from active use, whether it be temporary or permanent) of the temporary work spaces, and reclamation; and  operation and maintenance.

In planning the access roads, storage yards, laydown yards, construction camps, transmission line construction, and Project route, NextBridge has already taken measures to avoid cultural heritage resources. These are described below and depictions of the proposed footprint of the Project components are included in Figures 2 to 9. 8.1.1 Access Roads Temporary and permanent access roads will be required for the construction, operation and maintenance of the Project. The access requirements for construction and operation are different, as described in the sections below.

NextBridge has planned construction access according to the following selection hierarchy:

1) Use existing roads that connect to the Project ROW or individual structure sites, and which do not require upgrading or improvement.

2) Improve or widen existing roads or trails that connect to the Project ROW or individual structure sites.

3) Build new access roads that connect to the Project ROW where there are no existing roads or trails.

4) Build temporary roads to provide access to the individual structure sites where there are no existing roads. In some cases, these temporary roads will be graded between individual structure sites. These temporary roads will be for the purpose of construction, and will be reclaimed after construction.

According to the hierarchy above, NextBridge’s preference is to use existing roads or trails before improving or widening existing roads, or building new roads. Off-ROW access roads will be used where travel in the ROW with heavy equipment is not possible due to terrain or environmental sensitivities (i.e., ground conditions), or where access can be gained by using other off-ROW access, thereby reducing environmental impact (e.g., reduced water body crossings, avoidance of sensitive habitat or poor ground conditions).

60

July 13, 2018 1536607-2000-R01

Construction will require temporary access to the ROW and work spaces for clearing and site preparation, to each structure location with heavy equipment, and to the work spaces for clean-up and reclamation activities. Access to the transmission ROW will also be required for the transportation and distribution of personnel, equipment and materials along the ROW. Construction access will include use of existing roads that will not require upgrades or widening, existing roads that will require surface upgrades and widening to support construction activities, and construction of new access roads. Existing access roads will be widened or improved to be typically 8-m wide within a 20-m ROW. Access roads will be built as close as possible to the natural terrain contours to limit the amount of aggregate required. However, engineered aggregate will be required for the construction of new and upgraded access roads. Existing, improvement/widening, and new access roads will be all-weather and will be located within a cleared and grubbed ROW.

Operations will require permanent access to the ROW for lighter vehicles to conduct inspections, maintenance, emergency repairs, and vegetation management. A subset of the construction access roads has been identified for permanent access and will be maintained for operation and maintenance of the Project. Temporary access roads that are required for construction will be reclaimed following construction. 8.1.2 Temporary Construction Workspaces 8.1.2.1 Storage Yards Three storage yards to receive and distribute transmission line items (e.g., tower steel) are anticipated to be established near the City of Thunder Bay, Town of Marathon and Municipality of Wawa. The storage yards will be approximately 400 m by 400 m in size and will be located at least 30 m from water bodies. Where feasible, existing disturbed areas have been selected for the storage yards. The storage yard sites will be cleared of vegetation, grubbed and levelled where reasonable, and gravelled as needed for safety and stability. The storage yards may be equipped with perimeter lighting and fencing for safety and security. NextBridge has contacted the directly affected property owners or government agencies to acquire necessary permits and authorizations prior to establishment of the storage yards.

Materials from the storage yards will be transported by truck to laydown yards or to structure locations on the ROW as required. The contractor may choose to transport materials by helicopter to structure locations not accessible by ground vehicles. Existing sites with appropriate land use designations that can accommodate the Project requirements have been identified as priority locations for the storage yards. Storage yards will be reclaimed after their temporary use. 8.1.2.2 Laydown Yards Laydown yards will be established along the ROW to receive and temporarily store materials and equipment during construction. Where feasible, the contractor has identified existing disturbed areas as laydown yards. The laydown yards will be cleared of vegetation, grubbed and levelled where reasonable, and gravelled as required for safety and stability. The laydown yards may be equipped with perimeter lighting and fencing for safety and security. NextBridge has contacted the directly affected property owners or government agencies to acquire necessary permits and authorizations prior to establishment of laydown yards. Laydown yards will be located at least 30 m from water bodies and situated to avoid or limit potential environmental effects.

61

July 13, 2018 1536607-2000-R01

Materials stored at the laydown yards will typically include lattice structure components, poles, anchoring and guy wire material, structure materials, conductor and groundwire reels, insulators and conductor fittings, tools and equipment, and miscellaneous hardware. Some tangent structures may be assembled in laydown yards and equipment/components will be stored prior to delivery to the appropriate locations along the ROW. Specific assembly and erection methods for tangent structures will be determined during construction planning. Options include assembling the structures at laydown yards and moving them by helicopter to the ROW or assembling by crane at the structure location. The size of a laydown yards is approximately 300 m by 300 m; however, the size will ultimately depend on site characteristics, environmental constraints, and contractor requirements. Laydown yards will be reclaimed after their temporary use. 8.1.2.3 Construction Camps Lodging for the construction workforce will be required. Four construction camps will be established along the transmission line to provide temporary accommodation for the workforce. Construction camps are anticipated to be established in proximity to the Township of Nipigon, Township of Terrace Bay, Township of White River and Municipality of Wawa. Each construction camp will occupy an area of approximately 400 m by 400 m and will be located at least 30 m from water bodies. The size will ultimately depend on site characteristics, environmental constraints, and contractor requirements. Each construction camp will typically include a bunkhouse for approximately 200 to 250 workers; kitchen and dining hall; first aid station; communications system; waste water treatment system; water supply; solid waste (hazardous and non-hazardous) handling and storage facility; waste recycling area; electricity supply from diesel generators; and fuelling areas. Construction camps will be reclaimed after their temporary use. 8.1.2.4 Construction Easements Construction easements are anticipated to be required at large line angles to set up pulling equipment. Construction easements will provide space for equipment and materials and are planned to be used to enable conductor pulling/tensioning. 8.1.3 Transmission Line The transmission line will be designed to be an overhead 230 kV Alternating Current (AC) transmission line. The transmission line will consist of transmission structures, insulators, conductors, overhead shield wires (OHSW), optic fibre ground wire (OPGW), and grounding. The transmission line will require an approximately 450-km long ROW with a typical width of 64 m, which will be cleared of vegetation and will require permanent easement. The ROW width will vary at some points to accommodate topographic features and provide flexibility in final structure placement. The ROW width is narrower in some places to accommodate the crossing of sensitive features or constraints, and wider in other places to accommodate particularly challenging crossing locations. The width of the ROW varies based on the anticipated location of structures, the length of span, the terrain, soil conditions and anticipated line blowout, and is sufficient to contain the infrastructure within the boundaries of the easement.

Approximately 1,265 tower structures are expected to be used on the Project. The number of structures will depend on span distances between the structures, as determined by topographic, meteorological, and technical requirements and environmental and socio-economic constraints. The primary transmission structure will be steel, double-circuit Guyed-Y lattice tower structures, which are anticipated to be used for approximately 65% of the line length (Figure 37). Compared to typical self-supported lattice structures (Figure 38), the Guyed-Y structures generally weigh less and have smaller foundation systems, thus facilitating easier delivery, erection, and installation in challenging climate, soil conditions, and terrain.

62

July 13, 2018 1536607-2000-R01

The remainder of the tower structures will likely be constructed of self-supporting steel lattice and steel poles and will be used at turns in the line (turning structures) where the passable area of ROW may be too narrow for the Guyed-Y structure, at strategic locations to prevent cascade failures, or where additional strength is needed because of terrain or other obstacles. In some locations, such as provincial parks and conservation reserves, the structure type or location has also been selected based on consultation with interested parties to minimize impacts to sensitive features (e.g., wetlands and views).

In locations where the transmission line changes direction, the structures at the turning points will be designed to withstand higher forces. Dead-end structures (Figure 39) will be located near the TS and at the beginning and end of segments and are points at which Hydro One Networks Inc. will connect and tie-in the transmission line to the TS. Dead-end structures may also be used for any of the aforementioned reasons.

The Canadian Standards Association sets design criteria for overhead transmission lines that include minimum vertical clearances for transmission lines. Conductor clearance over ground (i.e., the distance between the ground and the closest point of the transmission line span) and other crossings will meet code required clearances. In addition to the minimum vertical clearance, NextBridge will add construction and survey tolerances so the line is constructed to meet the code-required minimums.

63

July 13, 2018 1536607-2000-R01

Figure 37: Typical Double Circuit Guyed Y Structure.

64

July 13, 2018 1536607-2000-R01

Figure 38: Typical Self-Supporting Tangent Structure.

65

July 13, 2018 1536607-2000-R01

Figure 39: Typical Self-Supporting Dead-end Structure.

66

July 13, 2018 1536607-2000-R01

8.1.4 Angler Re-Route After the Angler Internment Camp was identified in the draft EA Report, NextBridge modified the Project route to avoid and pass approximately 200 m east of the site. As depicted on Figure 40, a proposed access road weaves from the TransCanada Highway through the forest leading to Project footprint and then runs adjacent to the Angler Internment Camp site.

Although the Project was re-routed to avoid the Angler Internment Camp the following Project components are planned:  A laydown area at the intersection of the highway and the access road;  The access road from the highway south to the proposed transmission ROW will be improved and turned into a permanent access road;  The current access road/trail south from the proposed transmission ROW around the Angler Internment Camp location is proposed as a temporary access road; and  A temporary access road is planned along an existing transmission ROW. Figure 40 (below) illustrates the proposed Project components relative to the Angler Internment Camp site and to the historic layout of the camp.

67

SATELLITE IMAGERY HISTORICAL MAP

C264 C264

C265 C265

C266 C266

")

(! !(

LAKE SUPERIOR SHORELINE

C C A A N N A A D D I I ANGLER CREEK A ANGLER CREEK A N N INTERNMENT CAMP P INTERNMENT CAMP P A A C C I I F F I I C C R R A A I I L L W W A A Y Y

LEGEND KEY MAP REFERENCE(S) Project Component Base Data Known Cultural Heritage Resource BASE DATA: MNRF LIO (2018), CANVEC (2017), DILLON (2014, 2015), MNDM (2017) (! PROJECT COMPONENTS: PROVIDED BY NEXTBRIDGE (2018) Proposed Tower Location Railway IMAGERY: PROVIDED BY NEXTBRIDGE (2014) "/ Angler Internment Camp Fence Line 0 100 200 300 ! Transmission Line ANGLER INTERNMENT CAMP: HQS 7236-96-101 - CONSTRUCTION AND MAINTENANCE OF Access Road Temporary for Construction ³ CAMPS. ANGLER, MICROFILM REEL C-5420, RG24, LIBRARY AND ARCHIVES CANADA. Angler Internment Camp Area Access Road - New Watercourse PRODUCED BY GOLDER ASSOCIATES LTD. UNDER LICENSE FROM ONTARIO MINISTRY OF 1:6,000 METRES Enhanced Management Area NATURAL RESOURCES, © QUEENS PRINTER 2018 Access Road - Improvement/Widening PROJECTION: TRANSVERSE MERCATOR DATUM: NAD 83 COORDINATE SYSTEM: UTM ZONE 16N Preferred Route ROW Water Body CLIENT PROJECT Local Study Area HERITAGE IMPACT ASSESSMENT, EAST-WEST TIE TRANSMISSION PROJECT THIS IF MEASUREMENT ISSHOWN, WHAT DOES SHEETTHE NOT SIZE MATCH HAS BEEN MODIFIEDANSI B FROM: 25mm

YYYY-MM-DD 2018-07-11 TITLE DESIGNED GOLDER JR PROPOSED PROJECT COMPONENTS RELATIVE TO THE WAWA J" PREPARED GOLDER JB ANGLER INTERNMENT CAMP SITE

REVIEWED GOLDER BH PROJECT NO. CONTROL REV. FIGURE APPROVED GOLDER HJD 1536607 1

PATH: S:\Clients\NextBridge\East_West_Tie\99_PROJ\1536607_EA\40_PROD\0040_HIA_Report\1536607-0040-HC-0010.mxd PATH: 2:36:31 PM PRINTED AT: 2018-07-11 ON: 40 0 July 13, 2018 1536607-2000-R01

8.1.5 Discovery of Cultural Heritage Resources Contingency Plan NextBridge will be implementing a contingency plan for unexpected discoveries. The following activities will be implemented in the event previously unidentified cultural heritage resources are suspected or encountered. The ‘Discovery of Heritage or Archaeological Resources Contingency Plan’ in Section 6.4 of the Construction Environmental Protection Plan (Appendix 4-II of the EA Report) outlines steps NextBridge and its Contractors must take in the event previously unidentified heritage or archaeological resources are suspected or encountered. A summary of contingency steps specific to cultural heritage resources is provided below.

Incidental discovery measures for NextBridge include:

1) In the event that a previously unidentified cultural heritage resources are suspected or encountered unexpectedly during construction, NextBridge will bring in a cultural heritage specialist and contact the relevant communities or stakeholders for guidance (e.g., MTCS, Lakehead Region Conservation Authority, local First Nation(s), or the municipality), as required.

2) For heritage discovery, suspend activity at that location until the cultural heritage specialist has assessed the potential cultural heritage resource and determined a suitable course of action in consultation with NextBridge and, if necessary, the appropriate regulatory agencies and local communities.

3) The cultural heritage specialist develop an appropriate mitigation plan in consultation with NextBridge and, if necessary, the appropriate regulatory agencies and local communities. The cultural heritage specialist may deem it necessary to visit the site to evaluate the potential cultural heritage resource and develop an appropriate mitigation plan.

4) If assessment of the cultural heritage resource is deemed necessary, the site will be assessed based on the following criteria:

. the significance of the site;

. the location of the site with respect to the Project footprint;

. the feasibility of alternate routing or siting to avoid the resource; and

. guidance from MTCS.

5) Based on site assessment, recommendations will be made in consultation with MTCS (e.g., documenting, removing and salvaging).

6) Protecting potential cultural heritage sites identified adjacent to the ROW, if deemed appropriate based on the assessment.

Incidental discovery measures for the Contractor include:

1) In the event that cultural heritage resources not previously identified are suspected or encountered during construction: IMMEDIATELY HALT WORK IN THAT LOCATION and notify NextBridge. Potential cultural heritage resources should be suspected when the following are discovered:

. cabins and other old-looking structures;

. old industrial structures;

69

July 13, 2018 1536607-2000-R01

. culturally modified tress such as mature trees with well-defined bark scars; or

. groups of artifacts or significant modifications to the landscape that appear to be from historic logging and mining activity.

2) Suspend work immediately near newly discovered feature. Work at that location may not resume until permission is received from the Owner.

3) Temporarily flag off the 5 m around the resource to protect the feature.

4) Follow mitigation measures provided by the NextBridge. 8.2 Project Phases 8.2.1 Construction Phase Project construction is expected to occur over an approximately 26-month timeframe. Construction activities will continue year-round, with some construction activities being staged as practical to avoid or minimize potential effects on environmentally sensitive features and life cycle periods.

Steps in the Construction Phase include:  Surveying and Flagging: From this survey, the exact location of the preferred route ROW, structures, access roads, and laydown yards will be determined. Sensitive environmental features will be avoided to the extent practicable.  Clearing and Grubbing: Vegetation will be cleared and grubbed along access roads, around tower structures, construction camps, laydown yards, storage yards, and temporary construction easement sites. Most vegetation in the ROW will be cleared and grubbed unless identified as a sensitive feature.  Topsoil Stripping and Grading: Topsoil stripping and grading will be completed along the ROW and other access and construction areas, as required. It is anticipated that topsoil stripping and grading will take place on access roads, storage yards, laydown yards, and construction camps. Gravel or other surface improvements (e.g., corduroy) will be used where required on access roads.  Construction of Infrastructure: Construction of the construction camps, access roads, and laydown yards will be conducted prior to or at the same time as transmission line construction.  Staking of Structure and Guy Anchor Locations: Following ROW clearing and construction of infrastructure, field survey crews will mark (i.e., stake) the specific locations of the structures, foundations, and guy anchors. Staked locations will be field verified and shifted if necessary to avoid sensitive features or other obstacles.  Construction of Transmission Line: The transmission line will be designed to be an overhead 230 kV Alternating Current (AC) transmission line. The transmission line will consist of transmission structures, insulators, conductors, overhead shield wires (OHSW), optic fibre ground wire (OPGW), and grounding. The typical Guyed-Y lattice tower foundation will likely be a drilled pier or capped micropile foundation, requiring a single approximately 1 m diameter pier and typically four approximately 6-inch diameter anchors for the guy wires. The self-supporting tower structures will require four approximately 1 m diameter piers.  Decommissioning, Clean-Up and Reclamation: Construction infrastructure that is not required for Project operation (e.g., temporary access roads and laydown yards) will be decommissioned and reclaimed following completion of construction.

70

July 13, 2018 1536607-2000-R01

8.2.2 Operation Phase Upon commissioning, the Project will operate on a continuous basis. Operational activities will include inspection, maintenance, vegetation management of the transmission line, infrastructure and ROW, and emergency response.

Typical maintenance activities include: a) Detailed structure climbing and helicopter inspections; b) line hardware and insulator thermography; c) comprehensive vegetation management; d) ROW inspections; and e) visual patrol.

Access roads required during the operation of the Project will be maintained by NextBridge and used to access the Project area for maintenance purposes, to complete inspections, and for emergency purposes. Maintenance associated with these roads will include regular inspections (annually), vegetation maintenance.

During the operation phase, vegetation management measures will be implemented with a goal to ensure vegetation does not interfere with the safe and reliable operation and maintenance of the transmission line, or prohibit access to the transmission line structures, with a compatible vegetation height of approximately 2 m or less. Maintenance activities associated with vegetation will generally include mechanical, manual, and chemical (herbicide) methods for ensuring that vegetation remains at an appropriate height to protect the facility and improve public and worker safety.

Visual ground and aerial patrols will be completed to identify areas that require vegetation clearing, and the schedule will be based on growth cycles, system security, public health/safety, protecting the environment, and maintenance associated with the existing Hydro One transmission line.

71

July 13, 2018 1536607-2000-R01

9.0 IMPACT ASSESSMENT AND CONSERVATION RECOMMENDATIONS When determining the effects that a development or site alteration may have on known or identified built heritage resources or cultural heritage landscapes, the MTCS Heritage Resources in the Land Use Planning Process advises that the following direct and indirect adverse impacts be considered:  Direct impacts . Destruction of any, or part of any, significant heritage attributes, or features;

. Alteration that is not sympathetic or is incompatible, with the historic fabric and appearance;  Indirect Impacts . Shadows created that alter the appearance of a heritage attribute or change the viability of a natural feature or plantings, such as a garden;

. Isolation of a heritage attribute from its surrounding environment, context or a significant relationship;

. Direct or indirect obstruction of significant views or vistas within, from, or of built and natural features; or

. A change in land use such as rezoning a battlefield from open space to residential use, allowing new development or site alteration to fill in the formerly open spaces.

Impacts from both phases of the Project have been evaluated including the residual effects of the undertaking post construction, as outlined in the MTCS Guideline for Preparing the Cultural Heritage Resource Component of Environmental Assessments (1992) and Information Bulletin 3: Heritage Impact Assessments for Provincial Heritage Properties (2017). These are:  magnitude (amount of physical alteration or destruction);  severity (irreversibility or reversibility of impact);  duration (length of time an impact persists);  frequency (number of times an impact can be expected); and  range (spatial distribution: widespread or site-specific) An assessment of potential risks resulting from the proposed Project on the identified cultural heritage resources in the LSA — the Angler Internment Camp — is presented in Table 8 and – the Aguasabon River and Hays Lake— is presented in Table 9. Where an impact has been identified, conservation measures are recommended.

72

July 13, 2018 1536607-2000-R01

Table 8: Angler Internment Camp - Assessment of Direct and Indirect Adverse Impacts Resulting from the Project Risk of Adverse Recommended Conservation/ Significance of Project Phase and Activities Rationale Residual Effects Impact Mitigation Measures Residual Effects  Avoid the Angler Internment Camp; . Prohibit use of the ATV trail west of the existing Hydro One transmission corridor as a temporary access road  If this section of trail must be used as an access road, the following actions should be Construction Phase: prohibited; Surveying and Flagging Project activities will be north and east  of the site, though any temporary . Improvements beyond Clearing and Grubbing  improvements to the existing ATV trail basic re-surfacing; Topsoil Stripping and  Medium to high through the Angler Internment Camp . Excavation; and Grading risk of direct (see Figure 41) such as clearing and No predicted Construction of adverse impacts to grubbing, construction of access road . Removing existing access Very low if  residual effects if Infrastructure heritage attributes infrastructure and/or topsoil stripping or road infrastructure. mitigation all mitigation that are grading, followed by the removal of any If cultural material such as measures are Staking of Structure and  measures are  irreversible, short- improvements as part of the cleanup artifacts are found while implemented Guy Anchor Locations implemented. term, infrequent, and reclamation phase of the Project making improvements to the Construction of  and site-specific. will have a direct adverse impact to the trail or during use of the Transmission Line site through disturbance to the temporary access route,  Clean-up and trenches, mounds, or archaeological implement the Project Reclamation features adjacent to the access road. Discovery of Heritage or Archaeological Resources Contingency Plan.  Site plan control and communication; The Angler Internment Camp site should be clearly marked on project mapping and communicated to all project personnel for avoidance during construction phases of the Project.

73

July 13, 2018 1536607-2000-R01

Table 8: Angler Internment Camp - Assessment of Direct and Indirect Adverse Impacts Resulting from the Project Risk of Adverse Recommended Conservation/ Significance of Project Phase and Activities Rationale Residual Effects Impact Mitigation Measures Residual Effects Although there is no predicted risk of adverse direct or indirect impact, the following preventative measures are recommended: Since the Project will be located over  Site plan control and Operation Phase: 200 m to the east of the site, and there communication;  Detailed structure are two existing transmission corridors . The Angler Internment climbing and helicopter between the site and the Project, there Camp site should be inspections is no risk of indirect impact from clearly marked on project shadows, isolation, direct or indirect No predicted Line hardware and No risk of direct or mapping and Very low if  obstruction of significant views or residual effects if insulator thermography indirect adverse communicated to all mitigation vistas, nor a change in land use that all mitigation Comprehensive impacts to heritage project personnel for measures are  will adversely affect the site. Views of measures are vegetation management attributes. avoidance during implemented the existing transmission line and the operation phases of the implemented. ROW inspections  Project from the site are completely Project. Visual patrol  obstructed by thick vegetation.  If cultural material such as  Access road use and Additionally, no new roads construction artifacts are found while maintenance is planned as part of the operation making improvements to the phase. trail or during use of the temporary access route, enact the Project Discovery of Heritage or Archaeological Resources Contingency Plan.

74

C260 C261 LAKE SUPERIOR C262 SHORELINE

!. 03263 AY TRA IGHW NSCANADA H C263

C264

"

" C265

"

" LAKE

" SUPERIOR " " SHORELINE

" LAKE " SUPERIOR C266 SHORELINE " "

"

"

LAKE SUPERIOR

"

"

"

(LAC SUPÉRIEUR) "

"

"

"

"

"

" " " " "

" "

"

"

" "

" !( " C267

C A ANGLER CREEK N A INTERNMENT CAMP D I A N P A C I F I C R A I LW

A C268 Y

LEGEND KEY MAP REFERENCE(S) Project Component Base Data AMIS Site BASE DATA: MNRF LIO (2017), CANVEC (2017), DILLON (2014, 2015), MNDM (2017) !. PROJECT COMPONENTS: PROVIDED BY NEXTBRIDGE (NOVEMBER 2017) Proposed Tower Location Highway ANGLER INTERNMENT CAMP: HQS 7236-96-101 - CONSTRUCTION AND MAINTENANCE OF "/ !( Known Cultural Heritage Resource 0 0.25 0.5 0.75 Railway CAMPS. ANGLER, MICROFILM REEL C-5420, RG24, LIBRARY AND ARCHIVES CANADA. Access Road Temporary for Construction "" Recommendation: Do Not Use ³ IMAGERY: PROVIDED BY NEXTBRIDGE (2014) Access Road - New ! Transmission Line PRODUCED BY GOLDER ASSOCIATES LTD. UNDER LICENSE FROM ONTARIO MINISTRY OF Angler Internment Camp Fence Line 1:10,000 KILOMETRES Watercourse NATURAL RESOURCES, © QUEENS PRINTER 2017 Access Road - Improvement/Widening Angler Internment Camp Area PROJECTION: TRANSVERSE MERCATOR DATUM: NAD 83 COORDINATE SYSTEM: UTM ZONE 16N Enhanced Management Area Access Road - Existing CLIENT PROJECT Preferred Route ROW Water Body HERITAGE IMPACT ASSESSMENT, EAST-WEST TIE Laydown Yard TRANSMISSION PROJECT THIS IF MEASUREMENT ISSHOWN, WHAT DOES SHEETTHE NOT SIZE MATCH HAS BEEN MODIFIEDANSI B FROM: Temporary Construction Easement 25mm Local Study Area YYYY-MM-DD 2018-07-11 TITLE DESIGNED GOLDER JR ANGLER INTERNMENT CAMP CONSERVATION WAWA J" PREPARED GOLDER JB RECOMMENDATIONS

REVIEWED GOLDER BH PROJECT NO. CONTROL REV. FIGURE APPROVED GOLDER HJD 1536607 1

PATH: S:\Clients\NextBridge\East_West_Tie\99_PROJ\1536607_EA\40_PROD\0040_HIA_Report\1536607-0040-HC-0011.mxd PATH: 2:35:13PM PRINTED AT: ON: 2018-07-11 41 0 July 13, 2018 1536607-2000-R01

Table 9: Aguasabon River and Hays Lake - Assessment of Direct and Indirect Adverse Impacts Resulting from the Project Risk of Adverse Recommended Conservation/ Significance of Project Phase and Activities Rationale Residual Effects Impact Mitigation Measures Residual Effects The Project crosses the river and lake Construction Phase: at a location where an existing  Surveying and Flagging transmission line also crosses. The  Clearing and Grubbing river and lake at this location is a  Topsoil Stripping and naturalized part of the landscape. With Grading the exception of its enlarged size, there No risk of direct or are no tangible heritage attributes of No predicted  Construction of indirect adverse this cultural heritage resource where No conservation/ mitigation  residual effects Not applicable. Infrastructure impacts to heritage the Project footprint crosses. measures are required. are anticipated.  Staking of Structure and attributes. Construction of the project will not Guy Anchor Locations adversely impact the control dam and  Construction of generating station that hold back this Transmission Line impoundment lake, nor will the Project  Clean-up and have an impact on the historic nature of Reclamation the site as a source of power generation or logging river. The Project crosses the river and lake Operation Phase: at a location where an existing transmission line also crosses. The Detailed structure  river and lake at this location is a climbing and helicopter naturalized part of the landscape. With inspections the exception of its enlarged size, there Line hardware and No risk of direct or are no tangible heritage attributes of  No predicted insulator thermography indirect adverse this cultural heritage resource where No conservation/ mitigation  residual effects Not applicable. Comprehensive impacts to heritage the Project footprint crosses. Operation measures are required.  are anticipated. vegetation management attributes. of the project will not adversely impact ROW inspections the control dam and generating station  that hold back this impoundment lake, Visual patrol  nor will the Project have an impact on  Access road use and the historic nature of the site as a maintenance source of power generation or logging river.

76

July 13, 2018 1536607-2000-R01

10.0 SUMMARY STATEMENT In December 2015, NextBridge Infrastructure LP retained Golder Associates Ltd. (Golder) to provide a number of services for an Environmental Assessment (EA) of the East-West Tie Transmission Project, a proposed 450-km long double-circuit 230 kV transmission line in northwestern Ontario between the Lakehead Transformer Station in the Municipality of Shuniah, near the City of Thunder Bay, to the Wawa Transformer Station located east of the Municipality of Wawa. To address potential impacts to cultural heritage resources Golder provided a preliminary screening and assessment of the effects for the Environmental Assessment Report for the East-West Tie Transmission Project (Section 16: Cultural Heritage Resources), then conducted a Heritage Impact Assessment (HIA) for cultural heritage resources identified during the preliminary screening.

During the preliminary screening, seven potential cultural heritage sites were identified to be at risk of direct impact. These included six mines and quarries, and an internment camp for Japanese-Canadians and German Prisoners of War established during the Second World War known as the ‘Angler Internment Camp’. During preparation of this HIA an eighth cultural heritage resource was identified —the Aguasabon River and Hays Lake near the community of Terrace Bay.

Evaluation of these sites using the criteria prescribed in Ontario Regulation 9/06 determined that:  The Gananoque Vein Gold Mine and Halonen Fluorite Mine could not be evaluated since the sites could not be found within the Project LSA. It is possible the sites are not in the LSA and/or the sites have been reclaimed by the forest.  The Molybdenite Lake Prospect and Bishop Lead Occurrence mine sites are not of CHVI since they do not meet any criteria of O. Reg. 9/06;  The Angler/Petrunka Quarry and Mackenzie Quarry sites are not of CHVI since they do not meet any criteria of O. Reg. 9/06;  The Angler Internment Camp is of CHVI since it meets six criteria of O. Reg. 9/06; and  The Aguasabon River and Hays Lake is of CHVI since it meets two criteria of O. Reg. 9/06. Golder determined that the Project will not have an adverse direct or indirect impact on the cultural heritage value of the Aguasabon River/Hays Lake. However, this HIA also determined that without mitigation measures the Angler Internment Camp is at risk of direct adverse impact from the Project. Golder therefore recommends the following actions prior to, and during construction.  Avoidance: Project operations should avoid the Angler Internment Camp;  Site plan control and communication: The Angler Internment Camp should be clearly marked on project mapping and communicated to all project personnel for avoidance during construction; and  Monitoring and contingency planning: Periodic monitoring should be conducted during construction to ensure that the Angler Internment Camp is being avoided, and the ‘Discovery of Heritage or Archaeological Resources Contingency Plan’ in Section 6.4 of the Construction Environmental Protection Plan (Appendix 4- II of the EA Report) should be followed during construction in the area adjacent to the Angler Internment Camp.

77

July 13, 2018 1536607-2000-R01

CLOSURE We trust that this report meets your current needs. If you have any questions, or if we may be of further assistance, please contact the undersigned.

Golder Associates Ltd.

Benjamin Holthof, M.M.A., M.Pl., CAHP Hugh Daechsel, M.A. Cultural Heritage Specialist Principal, Senior Archaeologist

BH/HJD/mvrd

Golder, Golder Associates and the GA globe design are trademarks of Golder Associates Corporation.

https://golderassociates.sharepoint.com/sites/10435g/2000_reg applications/2018_cultural heritage/ewt_heritage-impact-assessment_2018_july 13.docx

78 July 13, 2018 1536607-2000-R01

11.0 REFERENCES

Arthurs, David 1984 Red Rock House H.B.C. Post. Nipigon Gazette August 15.

Bagnato S, Shragge J, editors. 1984 From Footpaths to Freeways. Ontario Ministry of Transportation and Communications, Historical Committee.

Baldwin D. 1976 The Fur Trade in the Moose-Missinaibi River Valley 1770-1917. Research Report 8, Ministry of Culture and Recreation, Toronto ON. Barry, Paul 1984 A Step into History – “Black Siding”. Terrace Bay-Schreiber News. Wednesday April 25, 1984. Pg 12. Bogue M. 2007. Around the Shores of Lake Superior: A Guide to Historic Sites. University of Wisconsin Press, Madison WI.

Bostock HS. 2014. Physiographic regions of Canada. Geological Survey of Canada, “A” Series Map no. 1254A, ed. 2. Boyd, David. G. 1899 Michipicoton Mining Division. In the Eighth Report of the Ontario Bureau of Mines 1899. Warwick Bro’s & Rutter, Printers Toronto.

Bray M. 1984 The Place and the People. In Bray, M, Epp E, editors. A Vast and Magnificent Land, pp.3-26. Bradbury Tamblyn and Boorne Ltd., Thunder Bay.

Brozowski R, Topps K, Ross D. 1984 Agriculture and Settlement. In Bray, M, Epp E, editors. A Vast and Magnificent Land, pp.109-126. Bradbury Tamblyn and Boorne Ltd., Thunder Bay. Canada’s Historic Places 2010 Standards and Guidelines for the Conservation of Historic Places in Canada. Second Edition. Accessed at http://www.historicplaces.ca/en/pages/standards-normes.aspx

Chisholm B. Gutsche A, Floren R. 1998 Superior: Under the Shadow of Gods. Lynx Images Inc.

City of Thunder Bay 2017 Thunder Bay History. Online Resource: http://www.thunderbay.ca/Living/culture_and_heritage/tbay_history.htm

Crins WJ, Gray PA, Uhlig PWC, Wester MC. 2009 The ecosystems of Ontario, Part 1: Ecozones and Ecoregions. Ministry of Natural Resources Peterborough Ontario, Inventory, Monitoring and Assessment, SIB TER IMA TR 01, 71pp.

79

July 13, 2018 1536607-2000-R01

Freeman, E.B. 1993 Southern Ontario Mining History. Wat on Earth, news May 1993. University of Waterloo. [online] accessed at: https://uwaterloo.ca/wat-on-earth/news/southern-ontario-mining-history Geology Ontario 1988 Feasibility Study on the Marathon Area. Report 2.13588 to the Mining Lands Section. [online pdf] accessed at: http://www.geologyontario.mndm.gov.on.ca/mndmfiles/afri/data/imaging/42D16SW0138/42D16SW0138.P df

Gilbert A. 1984 Mining. In Bray, M, Epp E, editors. A Vast and Magnificent Land, pp.89-108. Bradbury Tamblyn and Boorne Ltd., Thunder Bay. Guillet, G.R. 1964 Fluorspar in Ontario. Industrial Mineral Report No. 12. Ontario Department of Mines. [pdf]. Hawley, J.E. 1929 Geology of the Sapawe Lake Area with Notes on Some Iron and Gold Deposits of Rainy River District. In the Thirty-eighth Annual Report of the Department of Mines, [online pdf] accessed at: http://www.geologyontario.mndmf.gov.on.ca/mndmfiles/pub/data/imaging/ARV38/ARV38.pdf International Molybdenum Association (IMOA). n.d. Molydbenum Properties. [online] accessed at: http://www.imoa.info/molybdenum/molybdenum- properties.php n.d. Molybdenum History. [online] accessed at: https://www.imoa.info/molybdenum/molybdenum-history.php

Johnston F.J. 1968 Molybdenum Deposits of Ontario. Ontario Department of Mines, Mineral Resources Circular No. 7. [pdf]. Kemp, David 2017 Thunder Bay. Online Resource: http://www.thecanadianencyclopedia.ca/en/article/thunder-bay/

Klimko O. 1994 The Archaeology of Land Based Fur Trade Posts in Western Canada. Thesis submitted in partial fulfillment of the requirements for the Degree of Doctor of Philosophy in Department of Archaeology, Simon Fraser University. Leavitt, Thad W.H. 1879 History of Leeds and Grenville Ontario, From 1749 to 1879 with Illustrations and Biographical Sketches of some of its Prominent Men and Pioneers. Recorder Press, Brockville. [online pdf] Accessed at: https://ia800205.us.archive.org/26/items/leedsgrenville00leavuoft/leedsgrenville00leavuoft.pdf Library and Archives Canada. n.d. Internment Camps: Second World War. Online Resource: http://www.collectionscanada.gc.ca/obj/005/f2/005-1142.27.004.pdf n.d. HQS 7236-96-101 - Construction and maintenance of camps. Angler, Microfilm Reel C-5420, RG24.

Lovell, John 1895 Lovell’s Gazetteer of British North America. John Lovell & Son, Montreal.

80

July 13, 2018 1536607-2000-R01

Marathon & District Historical Society and Museum (MDHSM) n.d. The Marathon Peninsula. Online Resource: http://marathondistrictmuseum.weebly.com/the-marathon- peninsula.html

Melady, John. 1981 Escape from Canada! The Untold Story of German POWs in Canada 1939-1945. Macmillan of Canada, Toronto.

Miquelon D. 2001 Envisioning the French Empire: Utrecht, 1711-1713. French Historical Studies 21(4):653-677.

Morse E. 1979 Fur Trade Routes of Canada. NorthWord Press, Minoqua WI Municipality of Wawa 2017 History. Online Resource: http://www.wawa.cc/living-in-wawa/about-wawa/history/

Natural Resources Canada 2002 A History of Mining and Mineral Exploration in Canada and Outlook for the Future. [online pdf] accessesd at: http://publications.gc.ca/site/eng/home.html

New World Encyclopedia 2017 Fluorite. [online] accessed at: http://www.newworldencyclopedia.org/entry/Fluorite

Newell, Dianne 2011 Technology on the Frontier: Mining in Old Ontario. UBC Press, Vancouver.

NextBridge Infrastructure LP 2018 Environmental Assessment Report for the East-West Tie Transmission Project (amended, February).

Old Time Trains 2009 History of the Township of Terrace Bay. [online] accessed at: http://www.trainweb.org/oldtimetrains/industrial/history/Terrace_Bay.htm

Ontario Division of Mines 1975 Dorion – Wolf Lake Area (Eastern Part) District of Thunder Bay. Preliminary Map P.995. margin notes.

Ontario Geological Survey. 1981 Preliminary Map P.2406 Geological Series Precambrian Geology of the Molybdenite Lake Area Covering Parts of Andre and Bailloquet Townships Algoma District. 1;15,840. Notes. [online] Accessed at: http://www.geologyontario.mndm.gov.on.ca/mndmfiles/pub/data/imaging/P2406//p2406.pdf

1991 Bedrock Geology of Ontario, southern sheet; Ontario Geological Survey, Map 2544, scale 1: 1 000 000.

Ontario Power Generation 2018 Aguasabon Generating Station. [online] accessed at: https://www.opg.com/generating- power/hydro/northwest-ontario/Pages/aguasabon-station.aspx

Payne, Michael and Deborah Welch 2017 Marathon. Online Resource: http://www.thecanadianencyclopedia.ca/en/article/marathon/

81

July 13, 2018 1536607-2000-R01

Peet, S.E., and J.C. Day 1980 The Long Lake Diversion: An Environmental Evaluation. Canadian Water Resources Journal. Vol.5 No.3. [online pdf] Accessed at: https://www.tandfonline.com/doi/pdf/10.4296/cwrj0503034

Rowe, Johanna 2012 There’s gold in them hills: eastern shoreline of Lake Superior has brilliant past. Sault Star. Sunday February 5, 2012. [online] Accessed at: http://www.saultstar.com/2012/02/05/theres-gold-in-them-hills- eastern-shoreline-of-lake-superior-has-brilliant-past

Smith VC. 1984 Lumbering, Pulp and Paper, and Forestry. In Bray, M, Epp E, editors. A Vast and Magnificent Land, pp.71-88. Bradbury Tamblyn and Boorne Ltd., Thunder Bay ON. Statistics Canada 2011 Census Profile, Wawa. Online Resource: http://www12.statcan.ca/census-recensement/2011/dp- pd/prof/details/page.cfm?Lang=E&Geo1=POPC&Code1=0394&Geo2=PR&Code2=01&Data=Count&Sea rchText=wawa&SearchType=Begins&SearchPR=01&B1=All&Custom=&TABID=1

2016 Census Profile, Marathon. Online Resource: http://www12.statcan.gc.ca/census-recensement/2016/dp- pd/prof/details/page.cfm?Lang=E&Geo1=CSD&Code1=3558059&Geo2=CD&Code2=3558&Data=Count &SearchText=marathon&SearchType=Begins&SearchPR=01&B1=All&TABID=1

2016 Census Profile, Nipigon, Township. Online Resource: http://www12.statcan.gc.ca/census- recensement/2016/dp- pd/prof/details/page.cfm?Lang=E&Geo1=CSD&Code1=3558044&Geo2=CD&Code2=3558&Data=Count &SearchText=nipigon&SearchType=Begins&SearchPR=01&B1=All&TABID=1 2016 Census Profile, Thunder Bay, City. Online Resource: http://www12.statcan.gc.ca/census- recensement/2016/dp- pd/prof/details/page.cfm?Lang=E&Geo1=CSD&Code1=3558004&Geo2=CD&Code2=3558&Data=Count &SearchText=thunder%20bay&SearchType=Begins&SearchPR=01&B1=All&TABID=1

Steckley J, Cummins B. 2008 Full Circle, Canada’s First Nations. Toronto: Pearson Prentice Hall, 2008. 122.

Stuart IT. 2003 The Organization of the French Fur Trade, 1650-1760. Lake Superior to Rainy Lake, In Morrison, J., editor. Three Centuries of Fur Trade History, pp.15-22. Thunder Bay Historical Museum Society, Thunder Bay.

Sutcliffe RH. 1991 Proterozoic Geology of the Lake Superior Area. Pages 627 661 in: P.C. Thurston, H.R. Williams, R.H. Sutcliffe, and G.M. Stott, editors. Geology of Ontario. Special Volume 4, Part 1, Ontario Geological Survey, Queen’s Printer for Ontario, Toronto, Ontario. Terrace Bay Public Library n.d. Aguasabon Generating Plant – Tunnel Construction. Description attached to a photograph in the library collection posted online. [online] Accessed at: http://images.ourontario.ca/TerraceBay/56522/data

Thurston PC.

82

July 13, 2018 1536607-2000-R01

1991 Geology of Ontario: introduction. In: P.C. Thurston, H.R. Williams, R.H. Sutcliffe, and G.M. Scott, editors. Geology of Ontario. Special Volume No. 4. Toronto, Ontario: Ontario Geological Survey. 3-26.

Township of Nipigon 2017 Historical Walking Tour. Online Resource: https://nipigon.net/visitors/attractions/historical-walking-tour/ Union Publishing Company 1910 Province of Ontario Gazetteer and Directory 1910-1911. Union Publishing Company, Ingersoll.

Voorhis E. 1930 Historic forts and trading posts of the French regime and of the English fur trading companies. Ottawa, Department of the Interior. World Nuclear Association 2018 Brief History of Uranium Mining in Canada. Uranium in Canada Appendix 1. [online] Accessed at: http://www.world-nuclear.org/information-library/country-profiles/countries-a-f/appendices/uranium-in- canada-appendix-1-brief-history-of-uran.aspx Wylie, William N.T. 1986 Exploring Mining History: A Preliminary Study. Historic Sites and Monuments Board of Canada. Manuscript. [pdf]. Zimmerman, Ernest Robert. 2015 The Little Third Reich on Lake Superior: A History of Canadian Internment Camp R. The University of Alberta Press, Edmonton, Alberta.

Legislation, Policy and Heritage Guidance Documents Government of Ontario 1990 Environmental Assessment Act, R.S.O. 1990, c. E.18. [online] Accessed at: https://www.ontario.ca/laws/statute/90e18

1990 Ontario Heritage Act, R.S.O. 1990, Chapter O.18. [online] Accessed at: http://www.e-laws.gov.on.ca/html/statutes/english/elaws_statutes_90o18_e.htm 1990 Planning Act, R.S.O. 1990, c. P.13. [online] Accessed at: https://www.ontario.ca/laws/statute/90p13

2006 Ontario Regulation 9/06, Criteria for Determining Cultural Heritage Value or Interest. [online] Accessed at: https://www.canlii.org/en/on/laws/regu/o-reg-9-06/latest/o-reg-9-06.html

2006 Ontario Regulation 10/06, Criteria for Determining Cultural Heritage Value or Interest of Provincial Significance. [online] Accessed at: https://www.ontario.ca/laws/regulation/060010

2015 Ontario Regulation 116/01, Electricity Projects. [online] Accesses at: https://www.ontario.ca/laws/regulation/010116Ministry of Culture and Recreation

83

July 13, 2018 1536607-2000-R01

International Council on Monuments and Sites (ICOMOS) 1964 International Charter for the Conservation and Restoration of Monuments and Sites (The Venice Charter). [online pdf] Accessed at: http://www.icomos.org/en/charters-and-texts 1983 Appleton Charter for the Protection and Enhancement of the Built Heritage (The Appleton Charter). [online pdf] Accessed at: http://www.icomos.org/en/charters-and-texts 1999 The Australia ICOMOS Charter for Places of Cultural Significance (The Burra Charter). [online pdf] Accessed at: http://www.icomos.org/en/charters-and-texts Nobel Bruce J., and Robert Spude 1997 Guidelines for Identifying, Evaluating and Registering Historic Mining Sites. National Register Bulletin No. 42. U.S Department of the Interior, National Park Service. [online pdf] Accessed at: https://www.nps.gov/nr/publications/bulletins/nrb42/

Ontario Ministry of Municipal Affairs, Ministry of Housing 2014 Provincial Policy Statement. [online] Accessed at: http://www.mah.gov.on.ca/Page10679.aspx

Ontario Ministry of Tourism, Culture & Sport (MTCS) 1972 A Topical Organization of Ontario History. Historical Sites Branch, Division of Parks.

1992 Guidelines on Preparing the Cultural Heritage Resource Component of Environmental Assessments. [pdf].

2006 Ontario Heritage Tool Kit. [online] Accessed at: http://www.mtc.gov.on.ca/en/heritage/heritage_toolkit.shtml

2010 Standards & Guidelines for Conservation of Provincial Heritage Properties [pdf].

2014 Standards & Guidelines for Conservation of Provincial Heritage Properties. Heritage Identification & Evaluation Process [pdf].

2016 Criteria for Evaluating Potential for Built Heritage Resources and Cultural Heritage Landscapes a Checklist for the Non-Specialist. [pdf].

2017 Standards & Guidelines for Conservation of Provincial Heritage Properties: Information Bulletin 3 - Heritage Impact Assessments for Provincial Heritage Properties [pdf]. Parks Canada Agency 2000 National Historic Sites of Canada System Plan [pdf].

84

July 13, 2018 1536607-2000-R01

APPENDIX A Statements of CHVI for the Angler Internment Camp, and the Aguasabon River and Hays Lake

Appendix A, East-West Tie Transmission Project – HIA 1536607-2000-R01

STATEMENTS OF CULTURAL HERITAGE VALUE OR INTEREST ANGLER INTERNMENT CAMP AND THE AGUASABON RIVER/ HAYS LAKE. Statement of Cultural Heritage Value or Interest –Angler Internment Camp Description of Site – Angler Internment Camp, Town of Marathon The Angler Internment Camp is located approximately 5 kilometres north of the Town of Marathon, in McCoy Township, Thunder Bay District. The site covers approximately 20 hectares on the west side of Angler Creek, and includes widely dispersed surface and archaeological remains of camp buildings, linear features, and artifacts. Statement of Cultural Heritage Value or Interest The Angler Internment Camp is one of few Second World War internment camp sites in Ontario. It was constructed at the site of the Ontario Highway Construction Camp No. 12 in 1940 after the Dominion of Canada agreed to intern enemy combatant Prisoners of War (POWs) captured by British forces. The first POWs arrived at Angler Internment Camp on January 10, 1941, and by May 1942 the camp housed 689 men. On June 14, 1942, the POWs were transferred to another facility and replaced by Japanese Canadians, with 190 arriving from the Vancouver Immigration Building on June 19, 1942. These internees remained until the camp was closed on July 29, 1946.

Angler Internment Camp is known for one of the largest and most notorious escape attempts to occur at a Canadian POW camp during World War II. On April 18, 1941, 28 German POWs emerged from a one-metre wide and 50- metre long tunnel they had excavated beneath the southernmost barracks to just beyond the wire perimeter fence. Twenty-four (24) of the escapees were quickly recaptured, but two were killed, and two made it as far as Medicine Hat, Alberta before being arrested and returned to Angler Internment Camp.

The Angler Internment Camp is of cultural heritage value or interest as a rare and representative example of a large, purpose-built Second World War internment camp for POWs and civilian internees in Canada, and one with direct association with the policies of ethnic segregation and suspension of civil liberties enacted on the Japanese Canadian community under the War Measures Act. As a well-preserved archaeological site, the camp has the potential to contribute to our understanding of internment camp design and architecture, and the life of German POWs, Japanese internees, and members of the Veterans Home Guard during its short but momentous period of occupation. Heritage Attributes The heritage attributes that reflect the Angler Internment Camp’s physical or design value include its:  Remote location adjacent to the CPR rail line;  Shape and spatial arrangement of features;  Surface remains including concrete foundations of the northern internee quarters, well holes, trenches, earthworks, and fence posts; and,  Artifacts surviving on the surface including a stove or chimney pipe, metal flashing, metal cans, pots, and plumbing pipe.

1 Appendix A, East-West Tie Transmission Project – HIA 1536607-2000-R01

Statement of Cultural Heritage Value or Interest –Aguasabon River and Hays Lake Description of Site – Aguasabon River and Hays Lake The Aguasabon River is a 70 km long river that flows south from Long Lake to Lake Superior. It includes Hays Lake, an impoundment lake behind the Hays Lake dam in the Township of Terrace Bay Ontario. The impoundment lake is northwest of the community of Terrace Bay. Statement of Cultural Heritage Value or Interest The Aguasabon River was enlarged as part of the Hydro Electric Power Commission of Ontario’s (HEPCO) Long Lake Diversion Project in the 1930s. Water from the Kenogami River was redirected through Long Lake, into the Black River —renamed the Aguasabon River— and into Lake Superior between 1935 and 1938 in order to increase water flow for power generation throughout the Great Lakes and improve the accessibility of the area for timber extraction. In the 1940s HEPCO built the Hays Lake control dam and Aguasabon Generating Station to generate power locally and support the establishment of a pulp mill and company town for the Longlac Pulp & Paper company.The Aguasabon River and Hays Lake impoundment lake is the result of these large scale interventions in the landscape of northern Ontario.

The impoundment lake has cultural heritage value or interest as part of a human modified landscape with historical and contextual value. The impoundment lake is directly historically linked to the history of power generation in Ontario as part of the Long Lake Diversion project and as the headwater lake for the Aguasabon generating station. It is historically associated with the extraction of timber resources in Ontario as part of the Long Lake Diversion project and as the log booming ground of the pulp mill in Terrace Bay. The Aguasabon River and Hays Lake has contextual value for its historical links to the surrounding forest landscape and the community of Terrace Bay as part of a larger human modified landscape. The enlarged river and lake provided an avenue for people to access the surrounding landscape for resource extraction and use. The community of Terrace Bay was built as a result of the enhanced ability to use local resources. The Aguasabon River is one part of a relationship between people and the landscape. Heritage Attributes The heritage attributes that reflect the Aguasabon River and Hays Lake include its:  Size due to the Hays Lake Control Dam; and,  Artificially controlled water level.

2

golder.com