<<

Route 9A Promenade Project PROJECT UPDATE World Financial Center

World Trade Center Site

Presentation to the WTC Committee of CB#1

December 13, 2010

NEW YORK STATE STATE OF DEPARTMENT OF TRANSPORTATION

David A. Paterson Stanley Gee Phillip Eng, P.E. Marie A. Corrado, Esq. Joseph T. Brown, P.E. Governor Acting Commissioner Regional Director Director, Major Projects Project Director, 9A

1 Presentation Outline

. Route 9A at the . NYSDOT Pending Work adjacent to the WTC & WFC Site - Cedar to Eastside Frontage - Memorial Access & Egress on Route 9A on 9/11/2011 - Pedestrian Bridges (West Thames & Vesey Street) - WTC Project Impact Zones - Traffic Shifts for WTC Projects . Current Route 9A and WTC Site Schedule . The Two Components of the Route 9A Promenade Project . World Financial Center Frontage . NYSDOT Completed Work South of Liberty Street - South Promenade - West Thames Park - Temporary Liberty Street Pedestrian Bridge Extension - Frontage . NYSDOT Completed Work North of Vesey Street . NYSDOT Pending Work North & South of WTC Site . Route 9A Promenade Project Status

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 2 12/13/2010 Route 9A at the World Trade Center Site Aerial Photo

1 WFC 2 WFC 3 WFC

GOLDMAN SACHS ROUTE 9A SB ROUTE 9A NB

VSC NATIONAL SEPTEMBER 11 MEMORIAL & MUSEUM VERIZON 1 WTC

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 3 12/13/2010 Route 9A at the World Trade Center Site Pending Route 9A Curblines with Permanent & Temporary Pavement

1 WFC 2 WFC 3 WFC

GOLDMAN ROUTE 9A SB SACHS

ROUTE 9A NB

90 WEST ST. VSC NATIONAL SEPTEMBER 11 MEMORIAL & MUSEUM VERIZON 1 WTC

Legend: = Pending 9A Curblines = Permanent 9A Pavement = Temporary 9A Pavement

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 4 12/13/2010 NYSDOT Route 9A Pending Work adjacent to WTC & WFC Sites

1 WFC 2 WFC 3 WFC Pavilion RWL Discharge BPC Pile Rehab 8 14 2 WFC Driveway 22

2 7 19 25 ROUTE 9A 15 20 21 25 12 17 25 18 9 4 3 South 16 North 5 11 11 10 Projection 11 Projection 24

CONCOURSE 13 Plant 23 Bridge Vesey 1 Chiller 13 6 VSC NATIONAL SEPTEMBER 11 1 WTC VERIZON MEMORIAL & MUSEUM

1) BPCA Liberty Bridge Extension 11) Temporary or Permanent Utilities for 17) Vesey Sewer, Utilities, POEs (on-going) 2) Temp. Pedestrian Bridge Removal 9/11 Memorial 10th Anniversary 18) Vesey North Crosswalk Opening 3) Liberty Bridge Pier Removal 12) Undercut, Lightweight Fill, Utilities, POE’s, 19) Vesey Bridge Removal 4) VSC Frontage / NB Roadway Raise Grade, Paving etc. at Memorial Frontage 20) North Chamber Slab Lowering 5) 90 West Street Frontage 13) Memorial Frontage (bollards, irrigation, 21) 9A – All Features 6) Memorial Access trench drains, trees, pavers) 22) 3 WFC Frontage 7) 9A Crosswalk at Liberty Street 14) 2 WFC Driveway Removal & 2 WFC Frontage 23) 1 WTC Frontage 8) 1 WFC Frontage (on-going) 15) 9A (All features) and Fulton Sewer at 24) Vesey Street Intersection Tie-In 9) Cedar St. Intersection Tie-In Concourse Crossing 25) 78” Interceptor Sewer Lining 10) Liberty St. Intersection Tie-In 16) Fulton Street Intersection Tie-In

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 12/13/2010 Cedar to Liberty Street Eastside Frontage 1 WFC 2 WFC 9A R.O.W.

1) BPCA Liberty Bridge Extension 8 2) Temp. Pedestrian Bridge Removal 3) Liberty Bridge Pier Removal 4) VSC Frontage / NB Roadway 5) 90 West Street Frontage 9A Southbound 7 6) Memorial Access 2 7) 9A Crosswalk at Liberty Street 8) 1 WFC Frontage (on-going) 9) Cedar St. Intersection Tie-In 10) Liberty St. Intersection Tie-In 9A Northbound 3 4 9 10 5 1 9A R.O.W. 6

VSC 90 West Street National September () 11 Memorial & Museum

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 6 12/13/2010 Liberty to Fulton Street Eastside Frontage 2 WFC

9A R.O.W. 9A R.O.W. 14

15

12

11 16 11 11 9A R.O.W. 9A R.O.W. 13

11) Temporary or Permanent Utilities for 9/11 Memorial 10th Anniversary 12) Undercut, Lightweight Fill, Utilities, POE’s, Raise Grade, Paving etc. at Memorial Frontage 13) Memorial Frontage (bollards, irrigation, trench drains, trees, pavers) National September 14) 2 WFC Driveway Removal & 2 WFC Frontage 1 WTC 11 Memorial & 15) 9A (All features) and Fulton Sewer at Concourse Crossing Museum 16) Fulton Street Intersection Tie-In

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 7 12/13/2010 Fulton to Vesey Street Eastside Frontage 2 WFC 3 WFC GOLDMAN SACHS 9A R.O.W. 9A R.O.W.

22

19

9A Southbound 20 21

9A Northbound 17 18 25 25 25

Vesey Street Pedestrian Bridge Vesey 24 9A R.O.W.

17) Vesey Sewer, Utilities, POEs (on-going) 23 18) Vesey North Crosswalk Opening 19) Vesey Bridge Removal 9A R.O.W. 20) North Chamber Slab Lowering 21) 9A – All Features 22) 3 WFC Frontage National September 1 WTC 23) 1 WTC FrontageVERIZON 11 Memorial & 24) Vesey Street Intersection Tie-In Museum 25) 78” Interceptor Sewer Lining

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 8 12/13/2010 Memorial Access & Egress on Route 9A on September 11, 2011

MURRAY ST. MURRAY

ALBANY ST. ALBANY

NATIONAL SEPTEMBER 11 MEMORIAL & MUSEUM

MURRAY ST. MURRAY

GREENWICH ST.

NEW YORK STATE Access and Egress Zones in Route 9A to be determined DEPARTMENT OF TRANSPORTATION 9 12/13/2010 West Thames Pedestrian Bridge (BPCA/LMDC)

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 10 12/13/2010 Vesey Street Pedestrian Bridge View North from Liberty Street

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 11 12/13/2010 WTC Projects Impact Zones in Route 9A

1 WFC 2 WFC 3 WFC RWL Discharge BPCA Pile Cap Rehab

PAVILION GOLDMAN 2 WFC Driveway SACHS

78” Sewer ROUTE 9A Blast Protection BPCA Bridge South North Extension Projection

Projection Bridge Vesey Chiller Plant

CONCOURSE MEMORIAL PLAZA VSC WTC VERIZON STREETS 1 WTC NATIONAL SEPTEMBER 11 MEMORIAL & MUSEUM

WTC Site/BPCA Projects Working in Route 9A Legend: = Pending 9A Curblines = Concourse & = Memorial = WTC Streets = Other Projects Vesey Bridge = VSC = 1 WTC = Chiller Plant/RWL

Note: Pending Route 9A work requires continuous coordination with WTC Site Projects for staging and construction access.

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 12 12/13/2010 Traffic shifts for WTC Projects

Current NB & SB 9A Detour Locations 1 WFC 2 WFC 3 WFC

9A SB 9A NB

Vesey Bridge Vesey

VSC MEMORIAL 1 WTC VERIZON

Roadway Element Traffic/Access Estimated TOTALS Shifts since April Beyond 2010 2008 to end of 2010 Northbound Route 9A 9 16 25 Southbound Route 9A 7 15 22 Access 21 25 46 TOTAL 37 56 93

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 13 12/13/2010 Current Route 9A and WTC Site Schedule

Based on the PANYNJ Master Schedule 52 (June 2010) and other sources

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 14 12/13/2010 The Two Components of the Route 9A Promenade Project

WORLD FINANCIAL CENTER

Route 9A Southbound Route 9A Northbound

WTC MEMORIAL

Landscape / Urban Design Plan

WORLD FINANCIAL CENTER

WTC MEMORIAL

Utility Plan Busiest Utility Corridor in NYC

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 15 12/13/2010 World Financial Center Frontage Conceptual Plan & Aerial Photo

1 WFC 2 WFC 3 WFC

9A Southbound Conceptual Plan

Existing Aerial Photo

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 16 12/13/2010 World Financial Center Frontage 1 WFC Conceptual Plan

1 WFC 2 WFC 3 WFC

ROUTE 9A SOUTHBOUND

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 17 12/13/2010 World Financial Center Frontage 1 WFC (Perspective View South at Liberty Street)

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 18 12/13/2010 World Financial Center Frontage 1 WFC (Perspective View North at Albany Street)

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 19 12/13/2010 World Financial Center Frontage 1 WFC

Current Conditions Proposed Rendering

3”

Retaining Wall with 3” Cap Elevation

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 20 12/13/2010 World Financial Center Frontage 2 WFC Conceptual Plan

1 WFC 2 WFC 3 WFC

ROUTE 9A SOUTHBOUND

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 21 12/13/2010 World Financial Center Frontage 2 WFC (Perspective View North at Liberty Street)

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 22 12/13/2010 World Financial Center Frontage 3 WFC Conceptual Plan

1 WFC 2 WFC 3 WFC

ROUTE 9A SOUTHBOUND

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 23 12/13/2010 World Financial Center Frontage Overall Perspective View North 3 WFC

2 WFC WTC Site

1 WFC

Albany Street

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 24 12/13/2010 South Promenade

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 25 12/13/2010 West Thames Park

Playground Basketball Community Half-Courts Garden Dog Run

ALBANY ST. ALBANY Lawn Walkway Walkway Bikeway Bikeway

9A SB

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 26 12/13/2010 Temporary Liberty Street Pedestrian Bridge Extension

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 27 12/13/2010 90 West Street Frontage

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 28 12/13/2010 Completed Route 9A North of Vesey Street 50 Year Roadway Pavement

Southbound Roadway (View South)

Northbound Roadway Southbound Roadway (View North) (View North) NEW YORK STATE DEPARTMENT OF TRANSPORTATION 29 12/13/2010 Completed Route 9A North of Vesey Street Planted Medians

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 30 12/13/2010 NYSDOT Route 9A Pending Work South and North of the WTC/WFC

BATTERY PARK CITY 2 WFC GOLDMAN 1 3 1 4 SACHS ST. MURRAY 1 ROUTE 9A 5 VSC MEMORIAL VERIZON 1 WTC WTC SITE

1. S. Promenade Granite Crosswalk Removal/Replacement 5. Final Tree Planting in Median Areas 2. Outfall Pipe Cleaning 3. BPU Walls Completion 4. Final Tree Plantings

4 2

1 5

3 NEW YORK STATE DEPARTMENT OF TRANSPORTATION 31 12/13/2010 Route 9A Promenade Project Status

PROMENADE SOUTH WEST STEET PROMENADE PROJECT PROJECT (Completed)

MURRAY ST. MURRAY GOLDMAN Dog 1 WFC 2 WFC 3 WFC W. Thames Park SACHS BPU Run WSU

VSC MEMORIAL 1 WTC VERIZON

9A South of Albany/ W. Thames Park 9A North of Vesey / Goldman Completed Completed

1 WFC 2 WFC 3 WFC

9A (SB)

9A (NB)

VSC MEMORIAL 1 WTC

9A at WTC Site / WFC Finish 9A in Stages 2014 +/- NEW YORK STATE DEPARTMENT OF TRANSPORTATION 32 12/13/2010 Questions and Answers

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 33 12/13/2010 How To Contact Us

Please send comments to or request further information from:

Mr. Joseph Brown, Project Director Ms. Lisa Weiss, Urban Design Director Mr. Thomas Mellett, Construction Manager Ms. Julie Nadel, Community Liaison

New York State Department of Transportation Route 9A Project Office 21 South End Avenue New York, NY 10280

9A Stakeholder Meetings are held throughout the duration of the project (3rd Friday of every month at LMCCC). The next meeting will be on December 17, 2010 at 10:30 AM.

Contact us at: 1-800-714-0454 • Email us at: [email protected] Please visit our web site at : www.route9a.info

NEW YORK STATE DEPARTMENT OF TRANSPORTATION 34 12/13/2010 Route 9A Promenade Project PROJECT UPDATE World Financial Center

World Trade Center Site

Presentation to the WTC Committee of CB#1

December 13, 2010

NEW YORK STATE STATE OF NEW YORK DEPARTMENT OF TRANSPORTATION

David A. Paterson Stanley Gee Phillip Eng, P.E. Marie A. Corrado, Esq. Joseph T. Brown, P.E. Governor Acting Commissioner Regional Director Director, Major Projects Project Director, 9A

35