SECTION 2-TRANSMISSION PLAN SUMMARY Nevada Power Is The

Total Page:16

File Type:pdf, Size:1020Kb

SECTION 2-TRANSMISSION PLAN SUMMARY Nevada Power Is The SECTION 2-TRANSMISSION PLAN SUMMARY Nevada Power is the electric utility for most of Southern Nevada. Its service area is approximately 4,500 square miles. Service is primarily to Las Vegas, Henderson, and several smaller towns in Clark County. Nevada Power is a wholly-owned subsidiary of Sierra Pacific Resources. Nevada Power operates 1,665 miles of Federal Energy Regulatory Commission ("FERC") jurisdictional transmission lines ranging from 500 kV to 69 kV. Transmission services are offered under the Sierra Pacific Resources Operating Companies' Open Access Transmission Tariff (OATT). Nevada Power's existing Rd-, transmission system is composed of am,-=- three sections as shown in Figure TP-1. The first part is the uncongested grid, where the vast majority of Nevada Powcr's customers reside. Geographically, the uncongested grid is located within thc Las Vegas Valley. Generally, the ability to deliver resources is not limited by the transmission facilities within this area. The second and third parts of the transmission system deal with congested portions of the transmission grid. These are shown on Figure TP-1 as heavy dashed lines. The second part is the Southern cut-plane, which allows s:"b, Nevada Power to bring in power % from market hubs - namely Mead, McCullough, and Eldorado Substations - located south of Las A Vegas in the Eldorado Valley. The Neda Power- Southern cut-plane consists of . fourteen 230 kV bulk transmission lines electrically situated in parallel with each other. These lines are connected to Mead, McCullough, Eldorado, and Hoover. They connect to several trading hubs south of Nevada Power's transmission system and proportionally bring in import or deliver out any export that is scheduled across this cut-plane. Annual studies are done to verify the capability of this cut-plane and to identify the southern cut plane transmission limitation. The third part is the Northern cut-plane, comprised of the Red Butte-Harry Allen 345 kV interconnection with PacifiCorp in Utah and the Crystal interconnection with the Navajo - McCullough 500 kV line. The lines south of Harry Allen 230 kV currently limit Nevada Power's ability to bring in generation resources and purchased power from north of Las Vegas, including resources from Reid Gardner, Crystal, and the Nevada- Utah border, as well as generation interconnected to Harry Allen 230 kV. With the addition of the Harry Allen - Mead ("HAM") 500 kV line in 2007, this constraint will be reduced so as not to be the limiting factor of the northern cut-plane. Annual studies are conducted to verify the capability of this cut-plane and to provide the northern cut-plane transmission limitation. SPECIFIC REQUESTS FOR COMMISSION APPROVAL In this 2006 Resource Plan, Nevada Power seeks Commission approval of the following (unless otherwise noted, all estimated costs are in year spent dollars). 1. To immediately begin securing and purchasing easements, rights of way (ROW), as well. as authorize necessary permitting and construction for the following Ely Energy Center ("EEC5)-related projects: - Ely Energy Center 500 kV Switching Station - Ely Energy Center-Robinson Summit 500 kV No. 1 Transmission Line - Robinson Summit 5001345 kV Switching Station - Falcon-Gonder 345 kV line fold into Robinson Summit 5001345 kV Substation - Harry Allen-Robinson Summit 500 kV No. 1 Transmission Line (EN-ti) - Harry Allen 500 kV Switching Station improvements for EEC (EN-ti) - Funding to initiate studies, permitting, and land acquisition for Nevada Power's Robinson Summit to Hany Allen 500 kV No. 2 Transmission Line. Total Estimated Cost: $570.6 million (Allocation - 80 percent to Nevada Power and 20 percent to Sierra). The timing of the expenditures may change due to Robinson Summit Substation being put into service in 2008 rather than 2010. 2. To immediately begin securing and purchasing easements, ROW, as well as authorize necessary permitting and construction for the following White Pine Energy Associates ("WPEA") and Great Basin Transmission Company ("GBT"), related projects: - Robinson Summit and Hany Allen Substation work necessary for GBT (LS Power) Transmission Interconnection of its Robinson Summit - Harry Allen 500 kV line - Harry Allen-Mead 500 kV line No. 2 and associated Substation work for the WPEA (LS Power) Point to Point Transmission Service Request - if executed or filed unexecuted 3. To immediately begin sccuring and purchasing easements, ROW, as well as authorize necessary permitting and construction for the following: Sunrise fold of Harry Allen to Mead 500 kV line and associated 230 kV, 138 kV and 69 kV modifications between Sunrise and Winterwood Substations Sunrise to Clark 230 kV transmission line Sunrise to Equestrian 230 kV transmission lines (two lines) Equestrian North 5001230 kV North Suhstation Equestrian North to Equcstrian 230 kV transmission lines (two lines) Equestrian to Faulkner 230 kV line Equestrian North fold of Harry Allen to Mead 500 kV line Northwest 500/230 kV substation transformer bank No. 2 Thunderbird 2301138112 kV substation Thunderbird to Iron Mountain 230 kV line Thunderbird to Northwest Substation 230 kV line Five new 230112 kV substations along the Harry Allen to Northwest 230 kV line corridor Mobile 230 x 138/12 kV 25 MVA transformer for new 230/12 kV Substations Brooks 2301138 kV substation Southeast 1, Southeast 2, and West Henderson 230112 kV Substations Sinatra Project Iron Mountain Substation 2301138 kV transformer bank No. 2 Northwest Substation 2301138 kV transformer hank No. 2 Arden 230i138 kV transfomler bank No. 2 Valley Electric Interconnection at Northwest 230 kV substation Clark 2301138 kV bank No. 6 Transformer Change out Solargenix 230 kV Interconnection Total Estimated Cost: $848.9 million 4. To immediately begin securing and purchasing easements, ROW, as well as authorize necessary permitting and construction for the Clark Peaker Units project: Total Estimated Cost: $384.3 million 5. Westconnect membership costs for Nevada Power Company. The estimated WcstConnect membership cost is $52,000 in 2006, $54,000 in 2007, $55,000 in 2008, and $57,000 in 2009. 6. Spending up to $350,000 over a 12 month period for Nevada Powcr's participation in regional transmission expansion feasibility analysis. 7. Funding to initiate studies, permitting, and land acquisition for Sunrise to Highland, Highland to Sinatra, and Highland to Brooks 230 kV transmission lines (20071, Total Estimated Cost: $1,000,000 in 2007. TRANSMISSION PATH RATINGS Nevada Power owns three transmission paths, each consisting of one or more transmission lines, that are rated by the Western Electricity Coordinating Council ("WECC") and is a partial owner of one additional WECC-rated transmission path. Nevada Power and Sierra are in the process of rating the proposed Eastern Nevada Transmission Intertie ("EN-ti"). Descriptions of all the Nevada Power rated transmission paths are as Follows: Crvstal500 1 230 kV Path (WECC Path # 77) This path allows energy to be moved from the Navajo - McCullough 500 kV transmission line into the northeast comer of the Nevada Power system at Crystal. This path is rated for 950 MW of inbound flow measured at Crystal. Harry Allen - Red Butte 345 kV Path (WECC Path # 35) This path allows energy to be moved to and from Utah (PacifiCorp - East) to the northeast comer of the Nevada Power system at Hany Allen. This path is rated for 300 MW of bi-directional flow; however, actual schedules from Utah are significantly limited due to load growth in Southern Utah not by the Path rating. East of River (WECC Path #49) Nevada Power is a 25 percent owner in the Navajo - McCullough 500 kV transmission system. This line is one of several that comprise the WECC East of the River ("EOR) path #49. Nevada Power's contractual rights on the Navajo- McCullough 500 kV line are 371 MW in either direction along the entire length of this path. These rights can be used to deliver power to Nevada Power via Crystal or McCullough substations. A planned upgrade of the EOR path is expected to increase the Nevada Power rating - via a pro-rata share method of allocation of the total increase among the various EOR path owners. If Nevada Power participates in the funding of this upgrade project, it would be allocated approximately 75 MW of additional transmission capacity across this path. Nevada Power's rights would then be increased to 446 MW on the Navajo - McCullough 500 kV system. Centennial Proiect (WECC Path # 111-2) The Centennial Project has been granted a Phase I11 rating for delivery of 3,000 MW injected at the Hany Allen 500 kV substation. This rating has been evaluated for both the delivery of the full 3,000 MW rating to Mead substation, which is owned by the Westem Area Power Administration ("Western"), and for partial delivery of the rated power into the Nevada Power system with the balance going to Mead substation. Upon completion of the Centennial Project this Phase 111 rating will become a WECC Accepted Rating. Eastem Nevada Transmission Intertie ("EN-ti") The EN-ti is thc proposed Robinson Summit to Hany Allen 500 kV transmission line. Nevada Power has initiated the WECC Regional Review Process, the first stage of the WECC three-phase path rating process. The initial estimate for this rating is 2,000 MW north to south and 1,000 MW south to north. Great Basin Transmission, LLC (GBT) has also initiated the WECC path rating process for a second 500 kV transmission line that parallels the EN-ti 500 kV transmission line, between Robinson Summit and Hany Allen 500 kV substations. Both projects are being proposed to interconnect new coal generation projects in Northcrn Nevada, allow expanded access to renewable resources, and allow the combined utilization of Nevada Power and Sierra Pacific Power resources. Itizport Capability Import capability is the energy that can bc transferred into a control area.
Recommended publications
  • U.S. Department of the Interior Bureau of Land Management
    U.S. Department of the Interior Bureau of Land Management Final Environmental Assessment DOI-BLM-NV0S010-2009-1014-EA May 2016 Eastern Nevada Transmission Project APPLICANT Silver State Energy Association GENERAL LOCATION Clark County, Nevada BLM CASE FILE SERIAL NUMBER N-086357 PREPARING OFFICE U.S. Department of the Interior Bureau of Land Management Las Vegas Field Office 4701 N. Torrey Pines Drive Las Vegas, NV 89130 Phone: (702) 515-5172 Fax: (702) 515-5010 This page intentionally left blank. Table of Contents Chapter 1 - Purpose and Need ...................................................................................................1 1.1 Introduction ....................................................................................................................1 1.2 Project Background ........................................................................................................1 1.3 Purpose and Need for Action .........................................................................................2 1.4 Decisions to be Made .....................................................................................................7 1.5 BLM Policies, Plans, Authorizing Actions, and Permit Requirements .........................7 Chapter 2 - Proposed Action and Alternatives ........................................................................9 2.1 Introduction ....................................................................................................................9 2.1.1 Regulatory Framework for Alternatives
    [Show full text]
  • Transmission Plan
    2017-2018 TRANSMISSION PLAN March 14, 2018 REVISED DRAFT Foreword to Revised Draft 2017-2018 Transmission Plan This revised draft transmission plan reflects a number of changes from the draft plan released on February 1, 2018. To assist our stakeholders following the transmission plan cycle, we have summarized a number of those changes, with particular emphasis on a number of projects where the recommendations have progressed since the release on February 1 and the subsequent stakeholder meeting on February 8: • The model estimating the impact of the transmission plan on the ISO’s High Voltage TAC has been updated and the results added to the model. • The Oakland Clean Energy Initiative project is recommended for approval • The Phasor Measurement Unit project has been added and is recommended for approval • The Bridgerville-Garberville #2 115 kV line project is recommended to remain on hold. • The Kearney-Caruthers 70 kV Line Reonductor project is recommended to proceed with the original scope. • The recommended revised scope for the Kern 115 kV Area Reinfoement has been updated as presented at the February 8 stakeholder meeting. • Section 2.10 addressing the need for phasor measurement units to be installed on all ISO balancing authority area interties has been added. • Several projects approved in the 2016-2017 transmission planning cycle have been added to Table 7.1-1: Status of Previously-approved Projects Costing Less than $50M, that had been omitted from the table in the Draft 2017-2018 Transmission Plan. • The in-service date for a number of previously approved projects have been updated. A number of clarifications and edits have also been added throughout the plan to address other stakeholder comments.
    [Show full text]
  • U.S. Department of the Interior Bureau of Land Management
    U.S. Department of the Interior Bureau of Land Management Final Environmental Assessment DOI-BLM-NV-S010-2010-0091-EA November 2014 Southern Nevada Intertie Project APPLICANT Great Basin Transmission, LLC GENERAL LOCATION Clark County, Nevada BLM CASE FILE SERIAL NUMBER N-086359 PREPARING OFFICE U.S. Department of the Interior Bureau of Land Management Las Vegas Field Office 4701 N. Torrey Pines Drive Las Vegas, Nevada 89130 Phone: (702) 515-5172 Fax: (702) 515-5010 This page intentionally left blank. TABLE OF CONTENTS Chapter 1. Introduction .......................................................................................................... 1-1 1.1. Identifying Information ...................................................................................... 1-2 1.1.1. Title, EA Number, and Type of Project .............................................. 1-2 1.1.2. Location of Proposed Action ............................................................... 1-2 1.1.3. Name and Location of Preparing Office ............................................. 1-2 1.1.4. Identify the Case File Number ............................................................ 1-2 1.1.5. Applicant Name ................................................................................... 1-2 1.2. Purpose and Need for Action ............................................................................. 1-2 1.2.1. Background ......................................................................................... 1-2 1.2.2. BLM Purpose and Need .....................................................................
    [Show full text]
  • EB-2011-0140 in the MATTER of Sections 70
    EB-2011-0140 IN THE MATTER OF sections 70 and 78 of the Ontario Energy Board Act 1998, S.O. 1998, c. 15 (Schedule B); AND IN THE MATTER OF a Board-initiated proceeding to designate an electricity transmitter to undertake development work for a new electricity transmission line between Northeast and Northwest Ontario: the East-West Tie line. INTERROGATORIES OF RES CANADA TRANSMISSION LP to EWT L.P. January 30, 2013 12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 2 of 24 Interrogatory #1 Project Schedules Reference: a. AltaLink: Part B, Section 7 b. EWT: Part B, Exhibit 7 c. CNPI: Part B, Section 7 d. Iccon/TPT: Volume 1, Section 7 e. UCT: Section B, Section 7 f. RES: Exhibit N Preamble: Each applicant has prepared development and construction cost estimates that are dependent, inter alia, upon underpinning project schedule assumptions. Some applicants have assumed aggressive project schedules. For example, both UCT and EWT assume that the leave to construct process – from application to decision – can be completed in less than one year. The generalized phase-by-phase project schedule of each applicant is shown in the table below. The questions below are intended to test the reasonableness of the scheduling assumption and the sensitivity of development and construction cost estimates to changes in the project schedule that underpins each such estimate. Table 1: Project Schedules Questions: a. What evidence can EWT offer that a nine month leave-to-construct phase – from application to decision – is reasonable and achievable? 12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P.
    [Show full text]
  • Western Area Power Administration Desert Southwest Region's
    FINAL Western Area Power Administration Desert Southwest Region’s Facilities Historic Context Statement Edited by Lisa M. Meyer September 2014 FINAL Western Area Power Administration Desert Southwest Region’s Facilities Historic Context Edited by Lisa M. Meyer September 2014 DSW Region’s Facilities Historic Context Statement CONTENTS Contents Executive Summary ................................................................................................................... ES-1 1. Introduction ........................................................................................................................... 1-1 Purpose and Need .................................................................................................................. 1-1 Data Sources Consulted ......................................................................................................... 1-5 Current Document ................................................................................................................. 1-8 2. Statement of Context Part 1: DSW Region’s Transmission Power Systems………………………………………… ...................................................................................... 2-1 Temporal Context .................................................................................................................. 2-1 Geographic Context ............................................................................................................... 2-1 Historic Context ....................................................................................................................
    [Show full text]
  • Environmental Assessment DOI-BLM-NV-S010-2013-0052-EA DOE/EA-1960
    U.S. Department of the Interior Bureau of Land Management Environmental Assessment DOI-BLM-NV-S010-2013-0052-EA DOE/EA-1960 June 10, 2013 Townsite Solar Project Transmission Line PREPARING OFFICE U.S. Department of the Interior Bureau of Land Management Southern Nevada District Office Las Vegas Field Office 4701 N. Torrey Pines Drive Las Vegas, Nevada 702-515-5000 Office 702-515-5010 Fax Environmental Assessment for the Townsite Solar Project DOE/EA-1960 DOI-BLM-NV-S010-2013-0052 EA N-91290 Prepared For U.S. Department of the Interior Bureau of Land Management Southern Nevada District Office Las Vegas Field Office 4701 N. Torrey Pines Drive Las Vegas, NV Prepared by: 8250 West Charleston Boulevard, Suite 100 Las Vegas, NV 89117 June 10, 2013 Townsite Solar Project Environmental Assessment Contents Contents 1 Purpose and Need ................................................................................................................................. 1 1.1 Background ................................................................................................................................... 1 1.2 Relationship to Laws, Regulations, Policies, and Other Plans...................................................... 4 1.3 Supplemental Authorities .............................................................................................................. 4 1.4 Identifying Information ................................................................................................................. 6 2 Proposed Action and Alternatives
    [Show full text]
  • Mohave County Wind Farm Project
    BP Wind Energy North America Inc. Mohave County Wind Farm Project Plan of Development Submitted to BLM Kingman Field Office April 2013 Revision Mohave County Wind Farm Project Plan of Development Signature Page I certify that to the best of my knowledge, this document is accurate and fulfills the requirements for the Right of Way Grant process. This Plan of Development (POD) for the Mohave County Wind Farm Project site accompanies the Final EIS. Name Date ii Mohave County Wind Farm Project Plan of Development TABLE OF CONTENTS 1.0 PROJECT DESCRIPTION ....................................................................................................... 1-1 1.1 Introduction ...................................................................................................................... 1-1 1.1.1 Proposed Schedule ............................................................................................ 1-4 1.2 Proponent’s Purpose and Need for the Project ................................................................ 1-5 1.3 General Facility Description, Design, and Operation ...................................................... 1-5 1.3.1 Project Location, Land Ownership, and Jurisdiction ........................................ 1-5 1.3.2 Legal Land Description of Facility ................................................................... 1-5 1.3.3 Total Acreage .................................................................................................... 1-5 1.3.4 Number and Size of Wind Turbines .................................................................
    [Show full text]
  • Integrated Resource Plan
    2019 Integrated Resource Plan Adopted by Burbank City Council at its December 11, 2018 Meeting Table of Contents Chapter 1 6 1.1 Introduction 7 1.2 Assumptions and Implications 7 1.3 Major Changes Since 2015 IRP 9 1.4 Proposed Policy Guidelines 9 1.5 Action Items 10 Chapter 2 11 2.1 Introduction 12 2.1.1 About the IRP 12 2.1.2 Key Policy Drivers 13 2.1.3 Major Challenges 13 2.1.4 IRP Overview 14 2.2 Starting with Customers 15 2.2.1 Public Input 15 2.2.2 Demand and Energy Forecast 16 2.3 Customer-Side Resources 17 2.3.1 Energy Efficiency 17 2.3.2 Demand Response 18 2.3.3 Electric Vehicles 20 2.3.4 Customer-Owned Generation 21 2.3.5 Results of Customer-Side Impacts 21 2.4 Supply-Side Resources: The SB350 Future 22 2.4.1 Retirement of IPP coal in 2025 23 2.4.2 IPP Coal Replacement Options 23 2.4.3 Results: Replacing IPP Coal 25 2.5 Supply-Side Resources: The SB100 Future 27 2.5.1 Retirement of IPP Coal in 2025 27 2.5.2 Same IPP Coal Replacement Options as in SB350 27 2.5.3 Results: Replacing IPP Coal 28 2.6 Over-Generation at High RPS Levels 30 2.7 STS Transmission Utilization 31 2.8 Greenhouse Gas Emissions 32 Burbank Water and Power - 2019 Integrated Resource Plan Page | 2 2.9 Transmission 33 2.10 Distribution 33 2.11 Customer Rate Impacts 33 2.12 EIM Participation 34 2.13 Proposed Policy Guidelines 34 2.14 Action Items 35 2.12 Conclusion 35 Chapter 3 36 3.1 About BWP 37 3.2 Load 38 3.2.1 BWP is a Fully-Resourced Utility 40 3.2.2 Load Patterns 41 3.2.3 Annual Energy Requirements 41 3.2.4 The Duck Curve 43 3.2.5 Over-Generation 47 3.3 Generation
    [Show full text]
  • Phase I Environmental Site Assessment
    LOCAL KNOWLEDGE | GLOBAL PERSPECTIVE 877 GRS CRE1 +1 213 908 2173 www.grs-global.com Los Angeles New York Due Diligence Chicago PHASE I San Francisco Project Management San Diego Financial Advisory ENVIRONMENTAL SITE ASSESSMENT Atlanta Strategic Asset Solutions PROPERTY REFERENCE: Dallas 6690 GRAND MONTECITO PARKWAY, LAS VEGAS, NV Frankfurt London Tokyo PHASE I ENVIRONMENTAL SITE ASSESSMENT Prepared for: FDIC as Receiver for Southwest USA Bank FIN 10267 40 Pacifica, Fifth Floor Irvine, CA Property Identification Asset# 10267F012 (Southwest USA Bank FIN 10267) 6690 Grand Montecito Parkway Las Vegas, NV Prepared by: Global Realty Services Group 325 Center Street, Laguna Beach, California 92651 877 GRS CRE1 | +1 213 908 2173 | www.grs-global.com Report Date: December 29, 2010 GRS Project #: 10-08517.3 RESTRICTED USE AND RELIANCE THE USE OF AND RELIANCE UPON THIS REPORT ARE STRICTLY LIMITED AS SET FORTH HEREIN TABLE OF CONTENTS Overview.............................................................................................................................................. 1 Data Gaps................................................................................................................................................................2 Limiting Conditions................................................................................................................................................. 2 Findings and Opinions.............................................................................................................................................3
    [Show full text]
  • 6. Cumulative Impacts
    1 6. Cumulative Impacts 6.1 Introduction This chapter addresses potential cumulative impacts to the environment that could be associated with implementation of the build alternatives for the Boulder City/U.S. 93 Corridor Study in concert with one or more other past, present, or reasonably foreseeable future actions or projects. Specifically, this chapter is prepared in accordance with the requirements of NEPA and guidance from the federal CEQ, Considering Cumulative Effects under the National Environmental Policy Act. The CEQ regulations define a “cumulative impact” for purposes of NEPA as follows: Cumulative impact is the impact on the environment that results from the incremental impact of the action when added to other past, present, and reasonably foreseeable future actions regardless of what agency (federal or nonfederal) or person undertakes such other actions. Cumulative impacts can result from individually minor, but collectively significant, actions taking place over a period of time (40 CFR §1508.7). This cumulative impacts chapter gives emphasis to the actions or projects that are likely to cause adverse cumulative impacts (i.e., projects that would occur relatively close to the project site). For other transportation projects in the region, this analysis focuses primarily on the potential impacts of reasonably foreseeable future actions. The impacts of past and present actions are also discussed but in less detail and in a more qualitative manner. 6.2 Cumulative Impacts Analysis 6.2.1 Other Actions/Projects Included in the
    [Show full text]
  • 14-0191 So CA Pub Power Authority OS.Xps
    . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Maturity Schedules $151,880,000 Apex Power Project, Revenue Bonds, 2014 Series A (Tax-Exempt) Due Principal Interest July 1 Amount Rate Yield CUSIP 2030 $10,015,000 5.000% 3.510%(1) 84247PHF1 2031 14,855,000 5.000 3.630(1) 84247PHG9 2032 15,600,000 5.000 3.720(1) 84247PHH7 2033 16,380,000 5.000 3.790(1) 84247PHJ3 2034 17,200,000 5.000 3.850(1) 84247PHK0 2035 18,055,000 5.000 3.890(1) 84247PHL8 2036 18,960,000 5.000 3.920(1) 84247PHM6 2037 19,910,000 5.000 3.940(1) 84247PHN4 2038 20,905,000 5.000
    [Show full text]
  • DOE/EA-1470: Environmental Assessment Harry Allen-Mead 500
    U.S. Department of the Interior Bureau of Land Management Las Vegas Field Office Las Vegas, Nevada March 2004 Interstate Intertie Centennial Plan Environmental Assessment Harry Allen-Mead 500kV Transmission Line Project Harry Allen - Mead 500kV Transmission Line DOE/EA-1470 Chapter 1 Purpose and Need 1.1 Introduction The construction of new transmission and distribution facilities is required throughout the western United States to meet the increasing demand for power as more people move to many of the fastest growing communities. According to Executive Order 13212 dated May 18, 2001, “The increased production and transmission of energy in a safe and environmentally sound manner is essential to the well-being of the American people…agencies shall take appropriate actions, to the extent consistent with applicable law, to expedite projects that will increase the production, transmission, or conservation of energy.” Las Vegas is one of the fastest growing communities in the United States, and the demand for additional power transmission and use continues to increase as more and more people move into the Las Vegas Valley. The population is expected to increase to more than 2 million people in the next 10 years or less, which will put a demand on the existing power transmission system that cannot be met without system upgrades and improvements. Nevada Power Company (Nevada Power) is proposing to use Federally-administered lands and interconnection requests to the Federal power system. Therefore, the lead agency, Bureau of Land Management (BLM) along with cooperating agencies, Bureau of Reclamation (USBR) and Western Area Power Administration (Western), have prepared this Environmental Assessment (EA) as part of their decision-making process.
    [Show full text]