EB-2011-0140
IN THE MATTER OF sections 70 and 78 of the Ontario Energy Board Act 1998, S.O. 1998, c. 15 (Schedule B);
AND IN THE MATTER OF a Board-initiated proceeding to designate an electricity transmitter to undertake development work for a new electricity transmission line between Northeast and Northwest Ontario: the East-West Tie line.
INTERROGATORIES OF
RES CANADA TRANSMISSION LP
to
EWT L.P.
January 30, 2013
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 2 of 24
Interrogatory #1 Project Schedules
Reference:
a. AltaLink: Part B, Section 7
b. EWT: Part B, Exhibit 7
c. CNPI: Part B, Section 7
d. Iccon/TPT: Volume 1, Section 7
e. UCT: Section B, Section 7
f. RES: Exhibit N
Preamble:
Each applicant has prepared development and construction cost estimates that are dependent, inter alia, upon underpinning project schedule assumptions. Some applicants have assumed aggressive project schedules. For example, both UCT and EWT assume that the leave to construct process – from application to decision – can be completed in less than one year. The generalized phase-by-phase project schedule of each applicant is shown in the table below.
The questions below are intended to test the reasonableness of the scheduling assumption and the sensitivity of development and construction cost estimates to changes in the project schedule that underpins each such estimate.
Table 1: Project Schedules
Questions:
a. What evidence can EWT offer that a nine month leave-to-construct phase – from application to decision – is reasonable and achievable?
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 3 of 24
b. Provide an indication of the time required to obtain pre-construction environmental permits, following Ministry of Environment approval of EWT’s Environmental Assessment.
c. Indicate whether and, if so, where the time to apply for and obtain pre- construction permits is accounted for in EWT’s project schedule.
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 4 of 24
Interrogatory #2 Mining and Timber Rights
Reference:
a. AltaLink: no reference to mining or timber rights in its Land Plan (Part B, Section 9) or Costs (Part B, Section 8)
b. EWT: Part B, Exhibit 9
c. CNPI: Part B, Section 9, page 141 of 160
d. Iccon/TPT: no reference to mining or timber rights in its Land Plan (Volume 1, Section 9) or Costs (Volume 1, Section 8)
e. UCT: Section B, Section 9.2, Figure 29, page 134
f. RES: Exhibit B-1-1, page 12 of 35, lines 17-18, and page 13 of 35, lines 1-5; Exhibit B-3-2; Exhibit E-4-1, page 1 of 11, lines 5-8 and page 4 of 11, lines 15-17; Exhibit K-4-2, pages 12, 14, and 15, and Appendix A, D and E; Exhibit K-5-1, page 1 of 2, lines 17-24 and page 2 of 2, lines 25-47; Exhibit K-6-1; Exhibit L-1-1, page 4 of 4; Exhibit L-3-1, page 2.30 and Appendix C; Exhibit L- 4-1, pages 11-13; Exhibit N-2-3, page 2 of 3; Exhibit N-3-3, page 2 of 7; Exhibit P-5-1, page 11 of 12
Preamble:
Although most of the applications refer to mining claims and timber rights on Crown lands as routing issues that will need to be addressed, most are silent as to how such issues will be addressed and at what cost. The cost of obtaining required consents from parties with prior mining and timber rights on Crown lands that comprise part of a proposed transmission right-of-way can be material and significant. Obtaining such consents and/or otherwise dealing with such prior rights and entitlements can take a great deal of time.
Questions:
a. Indicate where, in its application, EWT provides a list of registered mining claims on Crown lands along EWT’s proposed transmission route(s).
b. Indicate where, in its application, EWT describes its plans to accommodate parties with registered mining claims and/or timber rights on Crown Lands that comprise part of its proposed transmission right-of-way(s).
c. Indicate where, in its application, EWT has estimated the cost of obtaining the consent and other permissions that would be required from parties who hold registered mining claims and/or timber rights on Crown Lands that comprise part of its proposed transmission right-of-way(s)?
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 5 of 24
d. Are the costs referred to in “c” above, included in:
(i) EWT’s development cost estimate; and/or
(ii) EWT’s construction cost estimate?
e. Indicate in which project phase – development, leave-to-construct or construction – EWT intends to negotiate consent agreements with parties who hold registered mining claims and/or timber rights on Crown lands that comprise part of its proposed transmission right-of-way(s).
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 6 of 24
Interrogatory #3 Land and Contingency Cost Exclusions
Reference(s):
a. Part B, Exhibit 6, Appendix 6A, Figure 1 and Figure 2
b. Part B, Exhibit 6, Appendix 6D, Figure 1 and Figure 2
c. Part B, Exhibit 8, page 4 of 31, lines 15-16
d. Part B, Exhibit 8, Table 8.1, pages 4-5 of 31
e. Part B, Exhibit 8, page 5 of 31, lines 14-15
f. Part B, Exhibit 8, page 15 of 31 risk tabulation
g. Part B, Exhibit 8, page 21 of 31, lines 5-6
h. Part B, Exhibit 8, Table 8.2, pages 22-23 of 31
i. Part B, Exhibit 8, page 23 of 31, line 5
Preamble:
EWT indicates that it has included $1.0 million in its development cost budget for “transaction costs for acquiring land rights for the Project excluding expropriation and the cost of land rights themselves”. An estimate of these excluded land costs is not included in its construction budget. In 2010, EWT’s affiliate, Hydro One, estimated “real estate” costs for the Project of $15,127,000, in its construction budget1.
EWT has included an estimate of contingency costs of 20 percent in its OM&A budget and stated that “contingency is inherent in any development project”.
Questions:
a. The total amount budgeted for land costs in EWT’s development and construction cost estimates is $1.0 million:
(i) is $1.0M the total amount that EWT expects to expend for land rights for the project; and
1 Hydro One, Project Definition Report, Study Estimates for Options, East-West Tie Expansion, AR 18379, June 4, 2010, page 38 of 43.
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 7 of 24
(ii) if the response to (i) is “no,” what is the total amount EWT expects to expend on land rights for the project in each of the development and construction phases?
b. The Power Engineers’ study for the reference design (reference “a”) states that “the cost of ROW purchase and temporary land needs for construction are not included in this estimate”. Indicate where, in its application, EWT provides an estimate of the right of way costs for the reference design.
c. There is no estimate of right-of-way costs in the Power Engineers’ study for the proposed alternate CRS design. Indicate where, in its application, EWT provides estimates of the right-of-way costs for the alternate CRS design.
d. Although EWT has stated that “contingency is inherent in any development project,” it has not provided an estimate of contingency costs in either its development or its construction budget. Provide estimates of the contingency costs that would be added to EWT’s development budget and to its construction budget.
e. To what extent will existing land rights that are currently held by one of EWT’s parent companies (eg., Hydro One) be utilized or shared by EWT?
f. If land rights that are held by Hydro One are utilized or shared by EWT, will the existing agreements that govern Hydro One’s existing rights (for example, land use permits issued by the Crown), need to be renegotiated or changed?
g. If the response to “e” is “yes,” will EWT reimburse Hydro One in respect of any associated incremental costs? Is this cost included in EWT’s application and, if so, where?
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 8 of 24
Interrogatory #4 Costs of Alternate Routes
Reference(s):
a. Part B, Exhibit 9, pages 20-36 of 37
b. Part B, Exhibit 9, page 21 of 37, Figure 9.1
c. Part B, Exhibit 9, page 27 of 37, Figure 9.2
d. Part B, Exhibit 9, page 30 of 37, Figure 9.3
Preamble:
In its application, EWT considers the reference route and also identifies three alternative route options. The application specifies development and construction cost estimates for the reference route only.
Questions:
a. Indicate where, in EWT’s application, the length of the East-West Tie line under each of the three alternative route options is specified.
b. Confirm (with a “yes” or “no” response) if EWT’s project schedule, land acquisition plan, environmental assessment plan and permitting plan, as these are set out in its application, apply equally to the three alternative route options?
c. Confirm (with a “yes” or “no” response) if the estimates of development and construction costs, as set out in its application, apply equally to each of the three alternative route options.
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 9 of 24
Interrogatory #5 Pre-Designation Costs
Reference(s):
a. Part B, Exhibit 8, page 2 of 31, lines 1-6
b. Part B, Exhibit 8, pages 3 to 7 of 31
Preamble:
Pre-designation costs (from February 2, 2012) are included in the Board’s definition of development phase costs. EWT indicates that it incurred $1.545M prior to submitting its application and will incur additional costs, during the designation proceedings.
Questions:
a. Is the full $1.545M included in EWT’s development cost estimate of $22.1 million?
b. If the response is “no,” explain the basis of the response.
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 10 of 24
Interrogatory #6 Design Deviations, Variations, and Alternatives
Reference(s):
a. Application, page 4 of 6, lines 3-8
b. Summary, page 9 of 14, lines 10-28; page 10 of 14, lines 1-27; page 11 of 14, lines 1-5
c. Part B, Exhibit 6, Section 6.0, page 1 of 21, lines 18-19; page 2 of 21, lines 1- 7
d. Part B, Exhibit 6, Section 6.1, page 3 of 21, lines 1-8
e. Part B, Exhibit 6, Section 6.2, page 6 of 21, lines 10-11
f. Part B, Exhibit 6, Section 6.4, page 8 of 21, lines 1-26; page 9 of 21, lines 1- 37; page 10 of 21, lines 1-18; page 14 of 21, lines 7-25; page 15 of 21, lines 1-26; page 16 of 21, lines 1-4; page 18 of 21, lines 1-23; page 19 of 21, lines 1-13; page 17 of 21, Table 6.1
g. Part B, Exhibit 6, Appendix 6F
Preamble:
EWT has proposed design “deviations and variations” to the Reference Option as well as an alternate “single circuit design with CRS”. Moreover, EWT proposes not connecting at the Marathon TS as an option that may be considered in the future.
Section 6.4 of the Board’s Filing Requirements (Phase 1 Decision and Order dated July 12, 2012) states that: “[W]here the Plan is not based on the Reference Option the applicant must file …[a] Feasibility Study performed by the IESO”.
Questions:
a. In reference “e”, EWT states that it “plans to evaluate whether [. . .] there is a need to interconnect the new line at Marathon..”:
(i) what is the basis for proposing this option; and
(ii) has the IESO considered the reliability and system performance of this option?
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 11 of 24
b. Has the IESO prepared feasibility studies for the design variations and deviations proposed by EWT in reference “c”, including EWT’s proposed “single circuit design with CRS”?
c. In reference “f”, EWT states as follows: “cost savings of approximately $116 million may be achievable by adopting a single circuit solution with CRS structures as used in ALT B compared to the Reference-Based Design, or approximately $70 million compared to the optimized double circuit design of Ref B.” In the absence of an IESO feasibility study confirming the reliability and performance of this design, where in its application does EWT present the factual underpinning of these estimates?
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 12 of 24
Interrogatory #7 Schedule Compression
Reference(s):
a. Application, page 4 of 6, lines 12-18
b. Summary, page 11 of 14, lines 7-21; page 12 of 14, lines 1-31
c. Part B, Exhibit 7, Section 7.2, page 5 of 49, lines 1-6; page 8 of 49, lines 13- 32; page 44 of 49, lines 16-22
d. Part B, Exhibit 7, Section 7.5.2.1, page 45 of 49, lines 8-12; page 46 of 49, lines 1-28; page 47 of 49, lines 1-27; page 48 of 49, lines 1-24; page 45 of 49, Figure 7.3
Preamble:
EWT has proposed a 36 month development schedule and indicates that it could be shortened to 23 months. It cautions however, that it “is inappropriate at this stage to assume a more aggressive environmental assessment timeline…”
Questions:
a. Provide a narrative that discusses the issues and concerns associated with an expedited development schedule, having regard, inter alia, to environmental assessment timelines.
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 13 of 24
Interrogatory #8 Bruce-Milton Project Experience
Reference(s):
a. Part A, Exhibit 2, Page 10 of 28, lines 17-19
b. Part B, Exhibit 8, Section 8.10.1, page 28 of 31, lines 4-11
Preamble:
EWT cites Hydro One’s experience on the Bruce to Milton project as an example of one of its partners completing a transmission project under budget and on time.
Hydro One’s 2007 leave to construct application estimated costs for the Bruce to Milton project at $635M and projected a December 2011 in-service date. Ultimately, the project went into service in June 2012 at a total cost of $709 M.
Questions:
a. Explain how EWT’s statement that the Bruce-Milton project came in under budget by $44M can be reconciled with the fact that the final cost of this project was at least $74M more than the original $635M estimate stipulated in Hydro One’s 2007 leave to construct application.1
b. Explain how EWT’s statement that the Bruce-Milton project was put into service “seven months ahead of schedule in 2012” (reference “a”) can be reconciled with the fact that the project did not go into service until June 2012, six months after the scheduled in-service date.2
1 EB-2007-0050, Exhibit B, Tab 4, Schedule 2, page 1 of 5, lines 1-8. 2 EB-2007-0050, Exhibit B, Tab 5, Schedule 2, page 1 of 1.
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 14 of 24
Interrogatory #9 Disparity in Affiliates’ Cost Estimates
Reference(s):
a. Part B, Exhibit 7
b. Part B, Exhibit 8
Preamble:
In 2010, Hydro One estimated the cost of the line portions of the East-West Tie line at $636 million (reference design) and another $43.7 million for development, for a total of $679.8 million1. It also projected a seven year schedule to achieve a December 2016 in-service date.
In its application, EWT is proposing to construct the East-West Tie line for approximately $427 million (within a range of $340 million to $510 million), at a development cost of $23.6 million (inclusive of $1.545 million in pre- designation costs) and for a total project cost of $450.6 million. EWT also proposes a 5.5 year development and construction schedule to achieve an in- service date of December 2018.
Given the relationship between EWT and Hydro One and the fact that EWT has relied on the credentials of Hydro One and its familiarity with the project to make the case that EWT has the requisite credentials to be the designated transmitter, the question of how these cost and schedule disparities can be reconciled is a reasonable one.
Questions:
a. Reconcile Hydro One’s 2010 estimate of project costs ($679.8 million) with EWT’s 2013 estimates of project costs ($450.6 million).
b. Reconcile Hydro One’s 2010 project schedule (7 years) with EWT’s project schedule for the East-West Tie line (5.5 years).
1 Hydro One Project Definition Report, AR 18379, Study Estimates for Options, East-West Tie Expansion, June 4, 2010, 43 pages
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 15 of 24
Interrogatory #10 Viability of Guyed Structures
Reference(s):
a. Summary, Page 10 of 14, lines 9-27; Page 11 of 14, lines 1-5; Page 13 of 14, lines 1-4
b. Part B, Exhibit 6, Page 2 of 21, lines 6-7; Page 14 of 21, lines 7-25; Page 15 of 21, lines 1-26; Page 16 of 21, lines 1-4; Page 17 of 21, lines 1-8; Page 18 of 21, lines 1-23; Page 19 of 21, lines 1-26; Page 20 of 21, lines 1-2; Page 17 of 21, Table 6.1;
c. Part B, Exhibit 6, Appendix 6D
d. Part B, Exhibit 6, Appendix 6E
e. Part B, Exhibit 6, Appendix 6F
f. Part B, Exhibit 7, Page 9 of 49, lines 10-16; Page 27 of 49, lines 26-27; Page 28 of 49, line 1; Page 49 of 49, lines 2-7
g. Part B, Exhibit 8, page 21 of 31, lines 15-18
h. Attachment 1: U.S. Bureau of Land Management Memorandum
i. Attachment 2: Wisconsin Department of Natural Resources, 2003-2004 Snowmobile Enforcement and Safety Report, page 14
j. Attachment 3: CBC article
k. Attachment 4: Meadow Lake Progress article
l. Attachment 5: NV Energy 2012 Integrated Resource Plan, Volume 16, filed with the Public Utilities Commission of Nevada on June 16, 2012, pages 10 to 11 and 90 to 94
Preamble:
EWT has proposed the use of a guyed cross-rope suspension (“CRS”) transmission structure to minimize construction costs, stating that “[e]very study conducted by POWER over the last 20 years that compares structure types for HV or EHV transmission line application points to significant capital cost savings when a guyed tower type is compared to a self-supported type.”
In North America, questions have been raised regarding the suitability of guyed structures, such as those proposed by EWT. There are numerous reasons why: concerns about the durability of structures in extreme climates;
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 16 of 24
difficulty managing vegetation around guyed structures; the need for wider rights-of-way; higher annual operation and maintenance costs; risk to bat and avian species; tower failure and in-line multiple tower cascades as a result of the loss of guy wires; accidental or intentional guy wire damage; and risk to recreational users of transmission right-of-way (e.g., snowmobilers).
EWT’s application offers little information regarding the suitability of guyed towers in northern Ontario, where extreme climate and corrosive soil conditions prevail. Nor does it address the other potential problems with guyed towers, listed above.
Questions:
a. Reference "h" (Attachment 1) comments on the use of guyed structures on public lands in the United States. The memorandum links guyed structures to increased avian mortality. Accordingly, with respect to transmission facilities located on United States public land "[t]he use of self-supported structures (i.e. structures that do not require guy wires for support and stability) are preferred wherever feasible".
(i) Indicate where, in its application, EWT addresses the risk to avian and bat species posed by guyed structures.
(ii) Confirm whether the cost of guyed towers included in EWT’s cost estimates is net the cost of mitigating the adverse effects of guyed structures on bat and avian species.
(iii) Confirm whether the cost of guyed towers included in EWT’s cost estimates is net of the cost of securing permits required under the Endangered Species Act, 2007, vis-à-vis the increased risk to certain avian and bat species.
b. There are many cases documenting injuries and fatalities that have resulted from high-speed collisions with transmission guy wires, particularly in the case of recreational snowmobilers (see Attachments 2, 3, and 4). It is not uncommon for designated recreational snowmobile trails, in northern Ontario, to follow transmission rights-of-way. In light of this, explain why EWT is proposing to use guyed structures.
c. The Executive Summary of the Power Engineers Report Assessment of the Use of CRS Structures on HV/EHV Transmission Lines (reference “c”) states that “[E]very study conducted over the last 20 years that compares structure types for HV or EHV transmission line application points to significant capital cost savings when a guyed tower type is compared to a self-supported type”. Confirm:
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 17 of 24
(i) how many studies reached this conclusion; and
(ii) how many such studies relate to projects that were actually constructed using guyed structures?
d. Notwithstanding the statement that Power Engineers has recommended the use of guyed structures in “multiple reports” over the last 20 years (reference “c”), only two North American installations of guyed CRS structures are identified. The most recent of these was installed in the 1980s. If guyed structures offer significant capital cost savings, compared to self-supporting structures, explain why guyed CRS installations are not more prevalent in North America.
e. There are documented cases, in North America, of guyed structures failing under extreme climatic conditions, for example, in high winds (see Attachment 5). Given the harsh climate in northern Ontario:
(i) indicate where, in its application, EWT describes the measures it intends to take in order to minimize the risk of tower failure; and
(ii) indicate whether EWT has included, in its construction cost and/or operations and maintenance estimates, a contingency for tower failure.
f. In respect of the CRS guy anchor foundations described in reference “c”, indicate where, in its application, EWT addresses the mitigation measures required to reduce the expected corrosion of guy anchors.
g. Indicate where, in its application, EWT addresses the inspection and maintenance procedures required to ensure the long-term performance of the guys supporting the towers described in references “c” and “d”?
h. Indicate where, in its application, EWT discusses the sufficiency of its annual operation and maintenance budget, in relation to the additional inspection and maintenance typically required for guyed structures.
i. Where in the proposal does EWT’s annual O&M budget address the additional operation and maintenance that would be required in respect of guyed structures?
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 18 of 24
Interrogatory #11 Future Expansion to 500kV
Reference(s):
a. Part B, Exhibit 6, Section 6.5.3
b. Part B, Exhibit 6, Appendix 6D
Preamble:
The Power Engineers CRS Report that is included in reference “b” states that the bundled 795 ACSR conductor, as proposed in EWT’s single circuit option, can set the stage for adding additional conductors for a future 4-bundle 500kV circuit. There is, however, minimal discussion as to what other components or modifications, beyond additional conductors, would be required to facilitate a future conversion to 500kV. These could include, for example, requirements for increased structure heights and widths, increased insulation and increased conductor phase spacing. EWT’s application does not indicate whether and when these additional components and modifications will be incorporated into its proposed design nor what the associated cost would be. In addition, it has not cited any plans or studies that indicate that 500 kV is being considered at any point in the future, for the area.
Questions:
a. Describe what other components and/or modifications to the proposed single circuit design, other than the bundled 795 ACSR conductor, (e.g. structure, insulator, and spacing modifications, etc.) would be required in order to accommodate a future 4-bundle 500kV circuit.
b. Indicate whether the components and/or modifications identified in response to question “a,” above, would be installed when the single-circuit design is first constructed or incorporated at a later date, when additional conductors are added to accommodate a 500kV circuit.
c. If required components and/or modifications would be installed at a later date, describe the expected construction timeline in respect of these modifications, having regard to the need to take the new single circuit line out of service. Comment on the length of the outage required to modify each transmission structure, install new conductors and upgrade station equipment.
d. Are the costs associated with the conversion of EWT’s single circuit design to a 500kV circuit included in the cost estimates set out in the application? If the response is “no”, explain why not.
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 19 of 24
e. Where, in its application, does EWT identify any definitive, announced plans for adding 500kV transmission in the project area, including the need and timing for such an addition.
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 20 of 24
Interrogatory #12 First Nations and Métis Participation
Reference(s):
a. Application, page 3 of 6, lines 7-13
b. Summary, page 2 of 14, lines 1-7; page 6 of 14, lines 8-30; page 7 of 14, lines 16-21; page 7 of 14, lines 1-26
c. Part A, Exhibit 3, Section 3.1, page 2 of 11, lines 1-12; page 3 of 11, lines 1- 24; page 4 of 11, lines 1-25; page 5 of 11, lines 1-34; page 6 of 11, lines 1-18; page 7 of 11, lines 1-21
Preamble:
EWT has made arrangements with some First Nations (through Bamkushwada LP) to participate as a partner in the East-West Tie line, in the event that EWT becomes the designated transmitter. These arrangements were announced by EWT on July 11, 2011.
It would appear that some First Nations and Métis communities have been excluded from participating in Bamkushwada LP. Moreover, the “Participating First Nations” have been granted preferential rights to provide goods and services to the project.
It would be helpful to understand more about the Bamkushwada arrangements, including whether they preclude another applicant from negotiating a comparable or better arrangement with a larger group of potentially affected First Nations and Métis communities (as identified by the Minister of Energy’s letter of May 31, 2011).
Questions:
a. How and why was it determined to include only six First Nations in the Bamkushwada group (defined by EWT as “Participating First Nations”)?
b. Were any of the 12 First Nations and Métis communities that are listed in the Minister of Energy’s May 31, 2011 letter to the OEB and who were not included as part of Bamkushwada LP (defined by EWT as “Non-Participating First Nations and Métis”) offered an opportunity to participate in the partnership and, if so, on what terms?
c. Under its arrangement with EWT, will Bamkushwada LP bear an equal share, relative to the other two EWT partners, of the costs of pre-designation, development and construction activities, in the event that EWT is designated?
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 21 of 24
d. Under its arrangement with EWT, will Bamkushwada LP bear an equal share of project risk during all phases of the project, relative to the other two EWT partners?
e. Does EWT’s participation arrangement with Bamkushwada LP constrain or preclude the Participating First Nations from considering alternate participation plans proposed by the designated transmitter, if that transmitter is not EWT?
f. What is the basis for the following statement in reference “b”, (page 6 of 14, lines 25-29): “For transmitters that have not made similar participation arrangements, there is a real risk they will not be able to do so, or that they will only be able to do so if they first take a similar amount of time to develop the necessary relationships, and then only if their visit on for the Project aligns with that of the Participating First Nations”?
g. Does EWT agree that comparable or better arrangements (from the perspective of First Nation and Métis communities, other affected stakeholders and/or Ontario ratepayers) could be entered into with a designated transmitter, other than EWT?
h. How will providing preferential rights to the Participating First Nations affect EWT’s ability to conduct successful consultation with Non-Participating First Nations and Métis communities?
i. Since EWT intends to give priority (with respect to employment, training, and commercial opportunities) to Participating First Nation community members and to businesses owned or controlled by a Participating First Nation or its members (see Summary, Page 7 of 14, lines 16-21), to what extent can Non- Participating First Nation and Métis communities, who are impacted by the project:
(i) provide goods and services to the Project; and
(ii) participate in the project?
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 22 of 24
Interrogatory #13 Proposed Rate Methodology
Reference(s):
a. Part B, Exhibit 8, Section 8.6, page 18 of 31
Preamble:
In Reference “a”, EWT states as follows:
“[EWT] believes that a traditional cost-of-service methodology is the most reasonable and transparent approach for a project at this ‘greenfield’ stage. Without project history, an incentive-based scheme may simply push project costs to be claimed at a later stage. Once the Project is operating, however, an incentive regime could be more fully considered. EWT also notes that the $6.87 billion of new transmission projects being built as part of Texas’ Competitive Renewable Energy Zone continue to be subject to conventional cost-of-service rate making by the Public Utility Commission of Texas even though the transmitters were selected through a highly innovative new process that shares many of the features of the Board’s own new designation process.”
Questions:
a. In EWT’s view, does a traditional cost-of-service approach, that passes all cost overages deemed to be prudent to ratepayers, provide superior risk mitigation from the perspective of ratepayers, relative to an incentive-based methodology that allocates (i.e., shares) cost overages and underages between ratepayers and the utility? Explain the reasons that underpin your response.
b. Assuming that the East-West Tie line is placed into service on December 31 of the year preceding the year in which an initial cost-of-service application for the East-West Tie line is brought (the “Preceding Year”), calculate the incremental year 1 revenue requirement associated with a $50M capital cost overage (relative to EWT’s estimate of total project cost), under the traditional cost-of-service approach proposed by EWT.
c. Assuming that the project is placed into service on December 31 of the Preceding Year, calculate the incremental year 1 revenue requirement associated with a $50M cost overage (relative to EWT’s estimate of total project cost), under the traditional cost-of-service approach proposed by EWT but where the $50M cost overage earns a return on equity that is equal to the Board-prescribed (2013) rate for long-term debt.
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 23 of 24
Interrogatory #14 Partner Loans to EWT
Reference(s):
a. Part A, Exhibit 5, page 3 of 17
Preamble:
Reference “a” states that EWT “will finance the development of the Project through partner loans from Hydro One and GLPT-EWT (through Brookfield Infrastructure) to EWT. The partner loans are debt to the partnership and have no impact on the equity of the partnership which will remain equally shared by Hydro One, BLP, and GLPT-EWT during development. While third party funding may be arranged during the development stage, it is not expected to be required.”
Hydro One is a crown corporation whose sole shareholder is the Ontario Government.
Questions:
a. Confirm that if Hydro One grants a partner loan to EWT, the Ontario Government will, in effect, be subsidizing an equity investor’s participation in the project.
12115001_5|TORDOCS EB-2011-0140 Interrogatories of RES Canada Transmission LP to EWT L.P. Filed: January 30, 2013 Page 24 of 24
Interrogatory #15 Route Access and Water Crossings
Reference(s):
a. Exhibit 6, Appendix 6A, page 2; page 7; Figure 1; Figure 2
Preamble:
The East-West Tie line will be located in a relatively remote part of the province, characterized by limited existing road access and several hundred water crossings.
EWT does not quantify the cost of constructing the multiple water crossings that will be required. Moreover, in reference “a”, Appendix 6A at page 7, new access road construction is assumed to be required for “40% of the line length at a rate of $25,000/km”. However, in reference “a”, Appendix 6A, Figures 1 and 2, access road construction is assumed to be $9,000/km.
Questions:
a. Reconcile the two estimates of the cost of constructing new access roads: $25,000/km (Appendix 6A, p. 7) vs. $9,000/km (Appendix 6A, Figures 1 & 2).
b. Indicate where, in its application, EWT describes its plan for crossing watercourses and wetlands and explain how this plan is reflected in EWT’s cost estimates.
c. Indicate what level of costs for crossing wetlands and watercourses is included:
(i) in EWT’s development cost estimate; and
(ii) in EWT’s construction cost estimate.
d. Has EWT performed a quantitative access road inventory, including an assessment of the level of improvement effort per road type and the associated costs: “yes” or “no”.
e. Describe what consideration, if any, were given to helicopter construction and how these considerations were incorporated into EWT’s:
(i) development cost estimate; and
(ii) construction cost estimate.
having regard to the limitations to traditional ground access posed by the topography and extensive wetlands that characterize northern Ontario.
12115001_5|TORDOCS
ATTACHMENT 1
United States Department of the Interior BUREAU OF LAND MANAGEMENT California State Office 2800 Cottage Way, Suite W1623 Sacramento, CA 95825 www.blm.gov/ca
December 4, 2012
In Reply Refer To: 6840, 6510 (CA-930) P
EMS TRANSMISSION: 12/4/12 Instruction Memorandum No. CA-2013-004 Expires: 9/30/2014
To: All BLM CA District and Field Managers
From: State Director
Subject: Revision of Guy Wire and Lighting Requirements for Tall Structures
This Instruction Memorandum replaces IM CA-2011-003. This Instruction Memorandum provides requirements for all structures requiring guy wires and lights (e.g., meteorological towers, cell phone towers) on BLM administered lands for which the approval of said structures is done with a Categorical Exclusion. This Instruction Memorandum applies to all new structures. This Instruction Memorandum applies to existing structures only when they are modified, retrofitted, or reinstalled. In order to use a Categorical Exclusion (CX) under NEPA, a project must not adversely affect species of special concern (e.g., species protected under the Endangered Species Act or Bald and Golden Eagle Protection Act). Tall, thin structures, such as meteorological towers, pose a collision risk to wildlife species. These potential impacts are subject to analysis under the National Environmental Policy Act (NEPA) prior to our granting of a Right-of-Way. The implementation of these measures reduces the collision risk for avian species sufficiently that a CX may be used. If the guidelines below are not implemented, a full NEPA analysis (EA or EIS) must be conducted.
A wide variety of bird species have been documented to collide with guy wires and power lines. It is generally believed that birds collide with lines because the lines are invisible to the birds or because the lines are not seen until it is too late for birds to avoid it. Large, less maneuverable birds are especially vulnerable to collisions with guy wires, which are relatively thin and difficult to see from a distance. Poor weather conditions, such as fog, rain or snow, as well as darkness, make the lines even more difficult to see. The following measures increase the visibility of such structures.
1. The use of self-supported structures (i.e., structures that do not require guy wires for support and stability) are preferred whenever feasible. The structure should be painted so that it stands out from the surrounding environment to provide optimum visibility for birds. However, if the use of self-supported structures is not feasible, non-self-support structures with guy wires may be used provided that the wires are marked using the following protocols.
2. Each and every guy wire (not just external wires) should be clearly marked for the length of the wire. Starting at the top of the guy wire, the first marker must be placed within the first 15 feet of length. The last marker can be no more than 15 feet from the ground at the end of the guy wire. Markers should be of a color that does not blend with the wire. Choice of marker and spacing of the markers along the guy wire must use one of the following options.
a. Spiral flight diverters (i.e., open-ended BIRD FLIGHT™ diverter or closed SWAN FLIGHT™ diverter or equivalent technology) spaced at intervals no greater than 15 feet apart.
b. "FireFly™” ‘flapper’ secured with a dropped forged galvanized cable (u-bolt) clamp or equivalent technology, spaced at intervals no greater than 30 feet apart.
c. In an alternating pattern, FireFly™ (or equivalent technology), and spiral flight diverters (e.g., open-ended BIRD FLIGHT™ diverter or closed SWAN FLIGHT™ diverter or equivalent technology) at spacing intervals of 15 feet apart.
Applicants must comply with manufacturer recommendations when using the methods outlined above. If an applicant proposes an alternative method of marking guy wires, that method must be approved by the BLM, and the applicant must conduct regular monitoring for bird fatalities (including scavenger and detectability correction factor studies) for all structures with guy wires.
3. Avoid placing lines within wetlands, over canyons, or within important avian movement corridors (i.e., between foraging and nesting sites).
4. Lights are sometimes used to mark guy wires and power lines. Because lights can both attract and confuse migrating birds, use lights only if lighting is needed for aviation safety. Unless otherwise requested by the Federal Aviation Administration, use only the minimum number of strobed, strobe-like, or blinking incandescent lights with a minimum intensity, maximum “off-phased” duel strobe lights. No steady burning lights (e.g., L-810) should be used. All lights should illuminate simultaneously.
5. If fatalities are observed, they must be reported immediately to the managing Field Office and the State Wildlife Specialist.
Questions on implementing measures for guy wires and lighting to reduce avian collisions may be directed to Amy Fesnock at (916) 978-4646.
Signed by: Authenticated by: Karen L. Barnette Richard A. Erickson Acting State Director Records Management
ATTACHMENT 2
Wisconsin Department of Natural Resources 2003-2004 Snowmobile Enforcement & Safety Report
Produced by the Bureau of Law Enforcement, Recreation Enforcement and Education Section PUB-LE-203 2004
The Wisconsin Department of Natural Resources provides equal opportunity in its employment, programs, services, and functions under an Affirmative Action Plan. If you have any questions, please write to Equal Opportunity Office, Department of Interior, Washington, D.C. 20240.
This publication can be made available in alternative formats (large print, Braille, audio-tape, etc.) upon request. Please call (608-261-0765) for more information. Table of Contents
Summary ...... 3
History of Snowmobile Fatalities by Fiscal Year...... 5
Snowmobile Fatality Rate to Number of Snowmobiles Registered ...... 5
History of Instructors & Students Certified...... 6
Snowmobile Fatality Rate to Warden Enforcement Hours ...... 7
Snowmobile Citation Rate to Warden Enforcement Hours...... 7
Alcohol Involvement in Snowmobile Fatalities ...... 8
Age of Fatality victims...... 8
Number of Fatal Accidents by Time and Day ...... 9
Helmet Use...... 10
Engine Size of Snowmobiles Involved in Crashes ...... 10
Engine Displacement Compared to Victim Machine ...... 11
Studded Track Information...... 12
Victim Operator Snowmobile Safety Training...... 12
Citations Issued Summary ...... 13
Snowmobile Fatality Summary...... 14 - 19
Scott Hassett Randal Stark - Director Secretary Bureau of Law Enforcement Department of Natural Resources Department of Natural Resources
Karl Brooks Julie Fitzgerald ATV/Snowmobile Administrator ATV, Boat, Snow Program Assistant Bureau of Law Enforcement Bureau of Law Enforcement Department of Natural Resources Department of Natural Resources
2 State of Wisconsin Department of Natural Resources Bureau of Law Enforcement
2003-2004 Snowmobile Program Report Summary
The 2003-2004 Snowmobile Program Report was compiled from the 25 fatal investigations and other data collected during the fiscal year 2003-2004 (a fiscal year runs from July 1 – June 30).
Conservation Wardens investigate all fatal snowmobile incidents and as such, Wisconsin law requires that a conservation warden or law enforcement officer be notified immediately of any snowmobile incident that results in an injury requiring medical treatment by a physician. In addition, the operator(s) involved in these reportable incidents must file a written report with the Department of Natural Resources within 10 days, in so far as they are capable of doing so.
FATAL INCIDENT CAUSES
The primary type of crash causing the victim's death continues to be striking a fixed object such as trees or ice/rock. The secondary type of crash leading to the victim's death this reporting period was collision with another snowmobile. The leading contributing factors were alcohol and excessive speed.
There were 12 (9 the previous year) fatal crashes that investigators directly identified speed as a contributing factor to the death of the operator/passenger. Of the 12 speed related fatals, 9 of those that died had consumed alcohol or 75% (77% the previous year) of the speed related victims.
Alcohol was identified as another major contributing factor. The 2003-04 laws expressly stated a person is under the influence of alcohol once their blood alcohol level reaches 0.08; however, for the purposes of this report, any alcohol level identified in the coroner's report (by percent) is considered to be a contributing factor.
Seventy-two percent (18 of the victims) of the known toxicology reports performed show alcohol was consumed by the victim. Toxicology examinations were not performed on six victims; one victim had no alcohol present. A review of the alcohol involved fatals show that no victims had less than 0.03 alcohol levels. Twenty percent of the victims that consumed alcohol showed levels less than .08%. Twenty percent of the victims that consumed alcohol had levels from 0.10 to 0.199%. The other thirty-six percent of the alcohol related victims were reported at 0.20 or above, with one victim result at 0.284.
WHO WAS INVOLVED
Twenty-four of the 25 victims were male. Victim ages ranged from 15-60 years, with the average age 35.2 years old; last season's average age was 35.3 years. The largest percentage of victims was age 30-39 years. The second largest age group was age 40-49 years at 24%. Three children under 16 were killed this reporting period. Of the 25 fatal incidents, 19 of the victims were Wisconsin residents while 4 were from Illinois and 2 from Minnesota. The majority of the victims (22) had not received Wisconsin Snowmobile Safety Training. Of the 25 victims, 18 were known to have been wearing a helmet, 3 were not wearing a helmet. 3 WHEN DO THE FATAL INCIDENTS OCCUR
A correlation was observed by reviewing fatality statistics for the past ten years. Inferences can be drawn as to the time of day and the day of the week that fatal incidents are most likely to occur. Statistics show the majority of the snowmobilers were fatally injured on Friday, Saturday or Sunday. Saturdays show a higher number of victims over any other day. The time of day/night that snowmobilers are most likely to be involved in a deadly incident is between the hours of 7:00 pm - 3:00 am.
FACTORS TO BE CONSIDERED
The statewide 2003-2004 snowmobile season never really acquired traditional snowfall depths, it began late and was essentially the same as the previous year. Open water remained a hazard throughout the season. Open water was a contributing factor for six of the fatal incidents. Many trails in the southern portion of the state did not open the entire season and trails in the north were plagued with poor snow depths resulting in less than prime conditions.
Wisconsin has been tracking alcohol involved fatals for many years with traditional results showing alcohol as a main contributing factor.
Percent of Victims Killed Showing Alcohol as a Contributing Factor
100% 80% 60%
40% 46% 47% 72% 61% 66% 84% 20%
Percent of total Victims 0% 1998-99 1999-00 2000-01 2001-02 2002-03 2003-04 Snowmobile Season
4 History of Snowmobile Fatalities
45 The 10-year 40 fatal average is * 25 deaths per 35 39 year. 30 30 34 26 25 22 25 The amount of 26 20 snowfall and 20 21 number of 15 Trend hours ridden, 15 are not reflected 10 and can affect * Past reports show 38 fatals were recorded during the snow season of 1999-00. However, an the number of 5 additional victim died 7-1-01, from injuries sustained during the winter of 1999-00 fatals that Number of Fatalities 0 occur.
5 6 7 8 9 0 1 2 3 4 -9 -9 -9 -9 -9 -0 -0 -0 -0 -0 94 95 96 97 98 99 00 01 02 03 Beginning the 1999-2000 Snowmobile Fatality Rate season, the nonresident to Number of Snowmobiles Registered trail pass became required for all 350,000 snowmobiles not registered in WI and as a 300,000 59,623 38,222 42,977 result the 43,537 Department was 250,000 21,779 able to identify the number of 200,000 nonresident 193,184 208,200 214,331 226,886 220,652 snowmobiles operated in WI. 150,000 182,124 202,216 214,611 232,320 206,416
100,000 18.91 16.47 16.81 12.5 11.3 Fatals per 11.39 10.09 9.32 15.1211.2 100,000 6.6 50,000 9.32 Registrations. 10.7 8.91 8.91 15.12 0 Registered Snowmobiles
-95 -96 -00 -01 -02 -03 -04 2 94 95 96-97 97-98 98-99 99 00 01 0 03
Resident fatals/100,000 ----- Resident and Nonresident fatals/100,000