Inventory of Major Alberta Projects

Inventory of Major Projects

March 2011 Alberta Finance and Enterprise 4th Floor, Commerce Place , Alberta T5J 4L6 Inventory of Major Alberta Projects

Introduction

The Inventory of Major Alberta Projects is produced by Alberta Finance and Enterprise to assist firms in identifying potential supply opportunities.

The Inventory lists construction projects in Alberta valued at $5.0 million or greater that are planned, underway, or have recently been completed. This edition also identifies projects that have been put on hold or deferred due to the economic downturn. Project data is obtained from public and private information sources. Where possible, this data has been verified with the project proponent/developer. However, users of the Inventory may wish to confirm project data with the proponent/developer.

While efforts have been made to obtain the most recent information, it should be noted that projects are constantly being re-evaluated by industry. Although the Inventory attempts to be as comprehensive as possible, some information may not be available at the time of printing, or not published due to reasons of confidentiality.

The Inventory can be accessed on the Internet at www.albertacanada.com/about-alberta/inventory-of- major-projects.html. New projects and (where possible) updated information on current projects is added to the Internet database on a monthly basis. The print edition of the report is produced quarterly. Projects added to the Inventory between January 1 and March 31, 2011 are noted in upper case in the Project Description column. If you have questions or require additional information about the Inventory, contact Alberta Finance and Enterprise by phone at (780) 427-6787, or by fax at (780) 422-0061. Inventory of Major Alberta Projects Summary Value of All Projects Value of Projects on Project Sector # of Projects ($Millions) # on Hold Hold ($ Millions) Agriculture & Related 9 $262.7 0 Biofuels 12 $1,449.6 1 $210.0 Chemicals & Petrochemicals 4 $117.5 0 Commercial/Retail 53 $8,507.8 4 $186.0 Commercial/Retail and Residential 8 $2,663.8 4 $1,227.8 Forestry & Related 8 $298.5 0 Infrastructure 263 $17,834.6 6 $94.5 Institutional 136 $8,020.1 9 $360.5 Manufacturing 7 $674.2 2 $24.0 Mining 5 $4,945.0 1 $4,500.0 Oil & Gas 7 $1,440.0 0 Oil Sands 59 $106,495.6 9 $15,507.0 Other Industrial 6 $1,479.6 0 Pipelines 30 $7,526.7 1 $2,000.0 Power 40 $14,213.7 0 Residential 89 $4,850.7 18 $1,662.0 Telecommunications 2 $656.0 0 Tourism/Recreation 101 $3,820.3 4 $125.3 Total 839 $185,256.40 59 $25,897.1

1. This Inventory lists projects in Alberta, valued at $5 million or greater, that have recently been completed, are currently under construction, or are proposed to start construction within two years. Not all projects over this threshold are listed due to reasons of confidentiality and/or due to information not being available at the time of printing. 2. Project data is obtained from public information sources. Although, where possible, this data has been verified with the project proponent/developer, users of the Inventory may wish to confirm project data with the proponent/developer. 3. The Inventory does not breakdown project expenditures by any gi ven year. The cost of a project is the value of expenditures expected over all phases of project construction, which may span over two or more years. 4. The cost of projects listed in the Inventory are estimated values only.

Inventory of Major Alberta Projects

Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Agriculture & Related

Agropur Cheese Plant Expansion County of $23.0 2011 Under construction. Stuart Olson Dominion (near Construction. Diamond City)

Alberta Sustainable Grazing Reserve Maintenance and across Alberta $9.2 2010-2011 Under construction. Resource Development Infrastructure Upgrades

BioNeutra Substitute Sugar Plant and Starch Calmar $100.0 Proposed. Planned completion by 2012. Plant

Biosphere Technologies Biorefining Demonstration Facility Lacombe $35.0 Proposed Inc.

Cargill Inc. GRAIN ELEVATOR AND CROP MD of Smoky $13.0 2011- Announced. FWS Group (Phase 1). Phase 1 to be PROTECTION SEED SHED River (W of completed in 2011, phase 2 (grain terminal) to be MCLennan) added at later date.

Cargill Meat Solutions PLANT MODERNIZATION / High River $42.0 2011-2012 Announced EXPANSION

Hole's Greenhouses 'Enjoy Centre' Retail Complex St. Albert $25.0 2009-2011 Completed. Maclean Young Construction.

Ponoka Ag - Event Centre Ag - Event Centre Ponoka $8.5 2010-2011 Nearing completion. Stretch Construction. Facility Society (PAECS) will include the Canadian Professional Rodeo Hall of Fame.

Western Irrigation District Canal Upgrades Wheatland Cty $7.0 2010-2011 Nearing completion (btwn Lk and Strathmore) Biofuels

Alberta Ethanol and Integrated Biodiesel and Ethanol Red Deer County $190.0 Proposed. Planned construction start spring 2011. Biodiesel GP Refinery Phase 1 (near Innisfail)

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 1 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks All Peace Industries Ltd. Biodiesel Fuel Plant four locations $50.0 Proposed. Locations under consideration include under High Prairie, , Smoky Lake and consideration Waskatenau.

Bfuel Corp. Biodiesel Plant Lethbridge $35.0 2011-2012 Announced. County (near Chin)

BioStreet Canada Biodiesel Plant Minburn County $210.0 On hold. Trimark Engineering. (near Vegreville)

BioWaste to Energy for BECii CLEAN ENERGY CENTRE County of Two $11.6 Proposed Canada Integration AT GROW - GEN BIOGAS PLANT Hills () Initiative Corp. (BECii)

Blue Horizon Energy Inc. 'Blue Horizon' Biodiesel Facility MD of Smoky $160.0 Proposed. Feasibility study completed. Previously River (S of called Bluesky Biofuel Facility. McLennan)

City of Edmonton Biofuel Feedstock Plant Edmonton $38.0 Proposed for 2011

City of Edmonton / Biofuel Facility Producing Ethanol Edmonton $70.0 2010-2011 Under construction Alberta Energy Research from Municipal Solid Waste Institute / GreenField Ethanol / Enerkem Greenfield Alberta Biofuels

CR Fuels Inc. Alternative Energy (Ethanol, MD of Taber (E $325.0 Proposed for 2011 - 2013. Biodiesel and Biogas Digester) of Purple Springs) Complex

CR Fuels Inc. Biofuel Complex (Biofuel Village) Wheatland $235.0 2011-2012 Announced. Biodiesel, ethanol and electrical County (N of generation. Strathmore)

ECB Enviro North Biogas and Co-gen Plant (3.2MW) Lethbridge $25.0 Proposed for 2011. America Inc. County

Growing Power Hairy Hill Bio - Energy Facility (Integrated County of Two $100.0 2010-2012 Under construction (biogas facility). FWS / ATCO Midstream Biorefinery) Hills (near Hairy Construction. Biorefinery proposed for 2011 - 2012. Hill)

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 2 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Chemicals & Petrochemicals

Alberta Sulphur Terminals Sulphur Forming and Shipping Lamont County $35.0 2011 Announced. Planned construction start Q1 2011. (a division of Hazco Facility (E of Bruderheim) NRCB approved July 2009. Environmental Services)

Methanex Corp. Plant Infrastructure Upgrade / Re - $40.0 2010-2011 Completed Opening

NovaGreen Commercial Facility Killam $35.0 Proposed for late 2012 or early 2013.

NovaGreen Inc. Demonstration Facility Killam $7.5 2011 Announced

Commercial/Retail

Alberta Development 'Stampede Trail' Retail $150.0 Proposed for 2011 - 2013. Part of Stampede Park Partners Inc. Development, Calgary Stampede $400M expansion. Grounds

Alberta Infrastructure North Petroleum Plaza Tenant Edmonton $8.2 2010-2011 Nearing completion. Graham Construction. Improvements

Alliance Pipeline Office Alterations Calgary $5.5 Proposed

Aquatera Utilities Inc. Office Building $20.0 Proposed

Aspen Properties Ltd. 'Palliser Square' East and West Calgary $220.0 Proposed Towers

ATCO Electric Office / Warehouse $6.0 2010-2011 Under construction. Clark Builders.

Burnet Duckworth & INTERIOR ALTERATIONS Calgary $12.0 Proposed Palmer

Cadillac Fairview Corp. 'Calgary City Centre' Development Calgary $60.0 Proposed. Phase 2 onwards on hold. Phase 1 (Office Tower), Eau Claire District

Camgill Enterprises 'Century Crossing' Commercial $75.0 2010-2013 Under construction. Phased development. Development

Canadian Tire Real Canadian Tire / Marks Work Canmore $7.0 2011 Under construction Estate Ltd. Wearhouse Store, Gateway

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 3 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks CAPP Investments Ltd. 'Skyway Professional Centre' Red Deer $40.0 On hold. Timcon Construction. Originally proposed Medical Office Building for 2010 - 2011.

Church of Jesus Christ 'Lethbridge Welfare Complex' Office Lethbridge $5.2 Proposed LDS / Warehouse Building

City of Calgary Calgary Public Building Restoration, Calgary $25.0 2009-2011 Completed. Chandos Construction. Stephen Avenue Mall

Deloitte Office Alterations Calgary $6.0 2010-2011 Completed. Stuart Olson Dominion Construction.

Dialog Warehouse Calgary $16.0 Proposed

Federated Co - op Warehouse Expansion Calgary $6.1 Proposed

Genco Development Corp. '634 Genco Court' Office Building Calgary $21.0 On hold. Originally proposed for 2010 - 2011

Gregg Distributors Ltd. DISTRIBUTION CENTRE Edmonton $38.0 2011-2012 Announced. Dawson Wallace Construction.

GWL Realty Advisors Ltd. Warehouse Building 3, Prospect Edmonton $14.2 Proposed / Remington Development Business Park Corp.

Harvard Developments / 'Currents of Windermere' Retail Edmonton $500.0 2008-2011 Under construction. Willl include Cineplex theatre Cameron Development Development complex. Home Depot, Wal-Mart, Canadian Tire, Corp. London Drugs completed.

Hertz Rent A Car Car Rental Outlet Calgary $5.3 Proposed

Husky Energy NEW OFFICE BUILDING Lloydminster $24.4 2010-2011 Under construction. CANA Construction.

Imperial Equities Inc. Industrial Building RM of Wood $13.0 2010-2011 Completed Buffalo (Fort McMurray)

Inland Pipe PLANT PHASE 2 Calgary $8.3 Proposed

Lowe's Companies New Store, Sunridge Calgary $15.0 2010-2011 Under construction. Gioffre Companies Inc. Canada

Lowe's Companies Lowe's of South Edmonton Edmonton $17.0 2010-2011 Nearing completion. Wright Construction Western Canada Inc.

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 4 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Matco Investments Ltd. / 'Eighth Avenue Place' Office Calgary $600.0 2007-2011 Under construction. EllisDon Construction. Alberta Investment Building East Tower Management / SITQ

Matthews Southwest 'The Bow' Office Tower Calgary $1,500.0 2007-2012 Under construction. Ledcor Construction. Developments

McCall Electric Warehouse / Office Building Calgary $5.5 Proposed Wholesaler

MD of Foothills / Town of Charles Clark Medical Centre High River $5.2 2010-2011 Under construction. Chandos Construction. High River

Oxford Properties Oxford Airport Business Park Calgary $500.0 Proposed. Multi - phased project will take eight years to complete. Planned construction first building in 2011 - 2012.

PRISM Developments 'Prism Place' Office Building Calgary $36.7 2011-2012 Announced. Planned construction start May 2011.

ProCura Developments Associated Engineering Building Edmonton $10.0 Proposed. Planned start 2011. Renovations / Upgrades

Qualico Developments Conversion of Golden West Golf Edmonton $500.0 Proposed Course to Light Industrial / Business Park

Qualico Developments EPCOR Office Tower Edmonton $250.0 2008-2012 Under construction. Ledcor Construction.

Remington Development 'Quarry Park' Mixed-Use Calgary $1,000.0 2006-2015 Under construction. Phase 1 completed. Office Corp. Development phases 1 and 2 building A under construction.

Remington Developments Westwinds Business Park Phase 3 Calgary $13.0 Proposed for 2011 - 2012

RioCan RIET / Trinity 'Jacksonport' Retail Development Calgary $230.0 Proposed Development Group / Canada Pension Plan Investment Board

Royop Corporation 'Gates of Walden' Shopping Centre Calgary $10.5 2010-2011 Under construction. Dawson Wallace.

SmartCentres Power Centre Phase 2 Sylvan Lake $20.0 Proposed (Eight Buildings)

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 5 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks SmartCentres Sylvan Lake Power Centre (Ten Sylvan Lake $50.0 2007-2011 Under construction. Wal-Mart anchor tenant. Buildings) Dollarama nearing completion, Canadian Tire under construction

Southgate Chevrolet Car Dealership Calgary $6.5 2010-2011 Under construction. Barjac Construction Buick GMC Management.

Springwood Development Commercial Development Cochrane $75.0 On hold. Domtar site remediation will start by end of August 2010 and last up to two years.

Sun Life Financial INTERIOR ALTERATIONS Calgary $7.3 2011 Under construction. Stuart Olson Dominion Construction.

The Ironwood Group 'Ironwood Tower' Office Building Edmonton $50.0 On hold. Dominion Construction.

Totem Building Supplies New Store, Edmonton $6.0 2010-2011 Under construction. Dawson Wallace.

Town of St. Paul MEDICAL CENTRE St. Paul $6.0 Proposed

Trans America 'Millennium Ridge' Retail Strathcona $14.0 2010-2011 Under construction. Developments Development County ()

Wal - Mart Canada Interior Alterations Calgary $7.5 Proposed

Wal - Mart Canada South Side Store Expansion to Red Deer $5.0 2010-2011 Completed. Elan Construction. Supercentre

Wal - Mart Canada Corp. NEW STORE NORTHWEST (#1122) Edmonton $14.0 Proposed

WAM Development 'Stonegate Landing' Retail, Office Calgary $2,250.0 2010-2016 Announced. Land servicing underway. Possible Group / AIMCo and Industrial Development construction start industrial area in 2010.

Western Securities 'Hanson Square' Retail / Office Calgary $17.4 2010-2011 Under construction. Stuart Olson Dominion. Building Commercial/Retail and Residential

Anderson Builders Group Mixed Use Building Red Deer $8.0 2010-2011 Nearing completion (1989) Inc.

Baralot International 'Sky Plaza' Development (Office Calgary $66.0 On hold pending improved market conditions. Space and Condo Units) Originally proposed for 2010 - 2011.

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 6 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks FRAM Building Group / HIGHRISE AND MEDIUM RISE Calgary $300.0 Proposed. Possible construction start sometime in Slokker Canada Corp. / BUILDINGS, EAST VILLAGE 2012. Tricon Capital Group

Harvard Developments Eau Claire Market Redevelopment Calgary $750.0 On hold

Jade Developments 'Copperstone Village' Residential / Airdrie $11.8 On hold Commercial Building

River City Developments 'Elements at Rivers Edge' Mixed Red Deer $28.0 2010-2011 Under construction Use Building

Torode Commercial Ltd. 'Ramsay Exchange' Commercial, Calgary $1,100.0 Proposed. Phased development. Retail and Residential Development

WAM Development / 'Stampede Station' Retail / Office Calgary $400.0 2004-2011 On hold. Phase 2 (office towers). Opus Building Corp. Space, Hotel and Residential Buildings Forestry & Related

Alberta - Pacific Forest PLANT UPGRADES County of $62.9 Proposed for 2011 - 2012. Industries Ltd. (Al - Pac) Athabasca (Boyle)

Diashowa - Marubeni Construction / Installation of 25MW Peace River $40.0 2010-2011 Nearing completion Peace River Pulp Division Generator

Millar Western Forest Sawmill Fox Creek $45.8 2010-2011 Under construction Products Ltd.

Sundre Forest Products 2011 Capital Improvements Sundre $13.0 2011 Announced

West Fraser Mills Ltd. Recovery Boiler and Pulp Machine Hinton $37.8 Proposed Upgrades

West Fraser Mills Ltd. Sawmill Equipment Upgrades Hinton $39.0 2010-2012 Under construction.

West Fraser Mills Ltd. Facility Upgrades, Blue Ridge Woodlands $28.0 Proposed Lumber County (near )

Weyerhaeuser Electrical Turbine (48MW) County of $32.0 2010-2011 Completed Grande Prairie

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 7 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Infrastructure

Alberta Infrastructure Highway 201 Grade, Base and Calgary $41.6 2009-2011 Under construction. South Rock Ltd. Pave, Bridge (Stoney Tr / Crowchild Tr )

Alberta Infrastructure Federal Building Redevelopment Edmonton $165.0 2008-2011 Under construction. Clark Builders.

Alberta Infrastructure Federal Building Parkade and Edmonton $110.0 2009-2011 Under construction. Clark Builders. Centennial Plaza

Alberta Infrastructure Legislature Dome Renovations / Edmonton $6.1 2010-2012 Announced. Building Science Engineering. Repairs

Alberta Infrastructure Acheson Industrial Building and Edmonton/Parkla $20.1 Proposed for 2011 - 2012 Alberta Infrastructure Shop nd Cty Redevelopment

Alberta Infrastructure / MEDICAL EXAMINER BUILDING Edmonton $12.5 Proposed Alberta Health and ADDITION / RENOVATION Wellness

Alberta Transportation Highway Twinning Project (North across Alberta $1,900.0 1998-2012 Under construction. 500km across Alberta South Trade Corridor)

Alberta Transportation Southeast Section Calgary Ring Calgary $769.0 2010-2013 Under construction. Chinook Roads Partnership. Road () from 17 Ave SE to Highway 2A

Alberta Transportation Highway 22, Highway 11 and SH Clearwater and $20.0 2010-2011 Under construction. Riverside Contracting 766 Pave Lacombe (Montana). Highway 22 from Hwy 11 to Hwy 53; Counties Hwy 11 E of Condor to SH766; SH766 from N of Eckville to Hwy 12.

Alberta Transportation Twinning Highway 28 from 57 Ave to Cold Lake $26.4 2009-2011 Under construction 10 St

Alberta Transportation HIGHWAY 56 / SH 609 / SH 833 County of $8.0 Proposed. Hwy 56 from S of SH609 to Hwy 13; PAVE Camrose SH609 from Edberg to Hwy 56; SH833 from Camrose to SH617.

Alberta Transportation HIGHWAY 61 GRADE, BASE AND County of Forty $7.9 2011 Announced. South Rock. PAVE Mile

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 8 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Alberta Transportation Highway 16 and SH 831 Pave County of $14.4 2011 Announced. E Construction / Ruel Bros. Minburn (near Vegreville)

Alberta Transportation Highway 1 Pave County of Newell $15.4 2011 Announced. South Rock. (SH873 to W of SH884)

Alberta Transportation Highway 1 Pave County of Newell $16.1 2010-2011 Under construction. Border Paving. (W of Bassano to SH 550)

Alberta Transportation Highway 2 / Highway 2A / Highway County of $11.0 Proposed 13 / SH611 Pave

Alberta Transportation Bridge over N Saskatchewan River Drayton Valley $60.0 2010-2013 Announced. Phase 1 (eastern approach work) under construction.

Alberta Transportation Callingwood Rd and Lessard Rd Edmonton $45.0 2009-2011 Under construction. Alberco Construction. Interchanges,

Alberta Transportation Anthony Henday Dr / Stony Plain Rd Edmonton $168.6 2009-2011 Under construction. KMC / PCL A Joint Venture. Interchange

Alberta Transportation Anthony Henday Dr (Hwy 216) / Edmonton $14.0 2010-2011 Under construction. PCL Construction Management. Rabbit Hill Rd Interchange and Bridge

Alberta Transportation Anthony Henday / Cameron Heights Edmonton $25.0 2010-2011 Under construction. Graham Construction. Drive Interchange

Alberta Transportation Anthony Henday Drive NW Edmonton area $1,420.0 2008-2011 Under construction. NORTHWESTCONNECT General Partnership. Yellowhead Tr to Manning Freeway.

Alberta Transportation Highway 16 and SH 627 Grade, Edmonton area $15.1 2010-2011 Announced. E Construction / Ruel Brothers. Base and Pave and Intersection Improvements

Alberta Transportation Highway 13 / Highway 36 / SH 602 Flagstaff County $15.5 2010-2011 Under construction. Border Paving.

Alberta Transportation HIGHWAY 63 CLEARING AND Lac la Biche $0.0 2011-2012 Announced. Thompson Bros (Const) Ltd. $20.8 GRADING County million. Part of Highway 63 twinning project.

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 9 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Alberta Transportation Highway 12 Road Improvements Lacombe County $14.0 Proposed (Re - alignment) (Hwy 20 to SH 792)

Alberta Transportation SH 625 Grade, Base and Pave, Leduc County $14.5 2010-2011 Under construction. Border Paving. Bridge Culvert, Lighting ()

Alberta Transportation Roadwork plus Two Bridges Mackenzie $17.9 2010-2011 Under construction. Prairie North Construction. County

Alberta Transportation Highway 58 Grade, Base and Pave Mackenzie $26.7 2011-2012 Under construction. Knelsen Sand & Gravel. County (S of Negus Ck to High Level)

Alberta Transportation Highway 88 Base and Pave Mackenzie $18.2 2010-2011 Under construction. Ledcor Alberta. County (Tall Creek IR to Bear R)

Alberta Transportation Highway 33 Base, Grade and Pave MD of Big Lakes $11.7 2010-2011 Completed. E Construction. (Swan Hills area)

Alberta Transportation HIGHWAY 2 GRADE, BASE AND MD of Foothills $12.0 2011-2012 Announced. Mesken Contracting. PAVE PLUS BRIDGE REMOVAL (N of Nanton to S of Cayley)

Alberta Transportation Highway 43 Grade, Base and Pave MD of Greenview $25.7 2010-2011 Under construction. Richardson Bros (Olds) Ltd. From E of Crook Creek to W of Sturgeon Lk IR.

Alberta Transportation HIGHWAY 40 GRADE, BASE AND MD of Greenview $11.5 2011-2012 Announced. Wapiti Gravel Suppliers. PAVE (Berland R to S of Muskeg Cabins)

Alberta Transportation Twinning Highway 43 near Sturgeon MD of Greenview $26.0 2010-2012 Announced Lake Cree Nation (Crooked Ck to Valleyview)

Alberta Transportation Highway 88 Base and Pave MD of $11.7 2010-2011 Announced. Carmacks Enterprises. Opportunity (N of SH686 to Willow Creek)

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 10 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Alberta Transportation Highway 2A Grade, Base and Pave MD of Peace $7.2 2011 Announced. Ledcor Alberta. (Hwy 2 to Grimshaw)

Alberta Transportation Highway 1A Grade, Base and Pave MD of Rocky $9.5 2010-2011 Under construction. South Rock. View (E of Hwy 22 to W of SH 766)

Alberta Transportation Highway 9 Widen, Base and Pave MD of Rocky $20.4 2010-2011 Under construction. South Rock Ltd. View (N of Hwy 1 to N of SH566)

Alberta Transportation SH 791 EXTENSION FROM SH 590 Red Deer County $14.6 Proposed. Part of Alberta Transportations three- TO HIGHWAY 42 year construction program 2012-2014.

Alberta Transportation Interchange Reconfiguration jct Red Deer County $23.7 2010-2011 Under construction. Border Paving. Highways 2 / 11 (Grade, Base and (N of Red Deer) Pave)

Alberta Transportation Highway 21, Highway 56, SH 601 Red Deer, $12.6 2010-2011 Under construction. Border Paving. Hwy 21 from N and SH 590 Base and Pave Kneehill and of SH587 to S of Hwy 42; Hwy 56 from S of SH 589 Stettelr Counties to S of Hwy 12; SH601 from Hwy 12 to Hwy 21.

Alberta Transportation North - Bound Bridge across RM of Wood $127.0 2008-2011 Under construction. Flatiron Construction. Athabasca River Buffalo

Alberta Transportation Highway 63 Grading RM of Wood $17.6 2010-2011 Under construction. Prairie Roadbuilders. S of May Buffalo Tower to S of House River.

Alberta Transportation Highway 63 / Thickwood Blvd and RM of Wood $300.0 2009-2012 Under construction. South Rock. Highway 63 / Confederation Way Buffalo (Fort Interchanges McMurray)

Alberta Transportation Highway 63 Grade, Base and Pave RM of Wood $43.7 2010-2012 Under construction. Graham Bros. Construction Buffalo (Fort Group. N of Athabasca R to S of Thickwood Blvd. McMurray)

Alberta Transportation Twinning Highway 63 RM of Wood $940.0 2007-2015 Under construction.. Section N of Buffalo (Fort in 2010 - 2011 McMurray) to jct Hwy 55 (near Grassland)

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 11 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Alberta Transportation Highway 63 Pave RM of Wood $7.1 2010-2011 Under construction. Knelsen Sand and Gravel. Buffalo (S of SH881 to S of Hwy 69)

Alberta Transportation SH 727 PAVE Saddle Hills $6.7 2011 Announced. Knelsen Sand and Gravel. County (Hwy 49 to SH680)

Alberta Transportation SH 727 Grade and Bridges over Saddle Hills Cty $37.9 2009-2011 Under construction. Sureway Construction. Howard Creek and Kitsuan River (Hwy 49 to S of SH680)

Alberta Transportation Highway 28 Grade, Base and Pave $12.0 2010-2011 Under construction. E Construction / Ruel Brothers.

Alberta Transportation - Bow / Travers Reservoir Vulcan County $11.8 2010-2011 Under construction. Graham Infrastructure. Concrete Structures

Alberta Transportation Highway 24 Crack Repair and Pave Vulcan County $7.7 2010-2011 Under construction. Border Paving. Project includes (Hwy 23 to Bow SH817 sideslope repair from SH901 to S of R) Strathmore.

Alberta Transportation Highway 40 Grade, Base and Pave Yellowhead $6.0 Proposed. County (N of Hwy 16 to S of Pinto Ck)

Aquatera Utilities Inc. Wastewater Treatment Plant Grande Prairie $40.0 Proposed Upgrades

Barrhead Regional Water Water Treatment Plant Expansion Barrhead $13.0 Proposed Commission

Brazeau County Municipal Administration Building Drayton Valley $19.8 2009-2011 Nearing completion and Public Works Facility

Calgary Airport Authority North - South Parallel Runway Calgary $620.0 2011-2015 Announced. Planned construction start April 2011.

Calgary Airport Authority International Transborder Concourse Calgary $1,400.0 2011-2015 Announced. EllisDon Construction.

Calgary Airport Authority / Road Improvements to 36 St NE Calgary $10.5 2010-2011 Under construction City of Calgary between 48 Ave and Airport Rd

Calgary Convention Convention and Trade Show Facility Calgary $300.0 Proposed. Planned completion in late 2013. Centre Authority

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 12 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Calgary Municipal Land Infrastructure Upgrades, The Rivers Calgary $200.0 2007-2012 Under construction Corp. (CMLC) (including East Village)

Calgary Police Services Office Alterations Calgary $25.0 2009-2011 Under construction

Canadian National 'Calgary Logistics Park' Intermodal Rocky View $100.0 Proposed. Pending approvals. Railway (CN) Terminal County ()

Central Aviation / Springbank Airport Development Rocky View $6.0 Proposed. Scott Builders. Springbank Aero (Office and Hangar Expansion) plus County Properties Two New Hangars (Springbank)

City of Airdrie 'Chinook Winds' Regional Waste Airdrie $11.4 2010- Announced. Management Facility, Park and Operations Centre

City of Airdrie Emergency Services Facility, Airdrie $9.0 2010-2011 Under construction. Bird Construction. Chinook Winds

City of Airdrie West Side Emergency Services Airdrie $13.0 2010-2011 Under construction. Bird Construction. Station

City of Airdrie RCMP Detachment Airdrie $10.5 2010-2012 Under construction

City of Calgary St. Patrick's Island Bridge Calgary $15.0 Proposed

City of Calgary FIRE STATION, SOUTH CALGARY Calgary $10.0 Proposed. Graham Construction and Engineering.

City of Calgary 37 St / Glenmore Tr SW Interchange Calgary $40.0 Proposed. Detour bridge completed Sept 2010.

City of Calgary Interchange at 14 St and 90 Ave SW Calgary $12.9 On hold. Originally scheduled for 2008 - 2010.

City of Calgary WEST LRT 69 ST STATION Calgary $9.9 Proposed

City of Calgary Fire Station, Marda Loop Calgary $15.0 Proposed

City of Calgary Road Widening Peigan Tr from Calgary $9.0 On hold. Barlow Tr to 52 St SE

City of Calgary Westbrook LRT Station / Tower Calgary $37.1 Proposed

City of Calgary 52 St SE Widening Phase 3 Calgary $10.0 Proposed. Planned constructIon start October 2010. (Supporting Road Network)

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 13 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks City of Calgary 210 AVE TRUNK UTILITIES Calgary $6.0 Proposed CONTRACT 3B

City of Calgary Rehabilitation of Westbound Bow Calgary $8.0 Proposed Trail Bridge over CPR

City of Calgary Fire / Ambulance Station, Bridlewood Calgary $15.8 Proposed for 2012.

City of Calgary Interchange Trans Canada Highway Calgary $47.0 On hold. and Bowfort Rd NW

City of Calgary Fire Station, Royal Oak Calgary $15.0 Proposed for 2011 - 2012. Pending funding approval.

City of Calgary Widen 14 St W from 90 Ave S to Calgary $14.5 On hold. Anderson Rd

City of Calgary Fire Station, Seton Calgary $15.0 Proposed for 2011 - 2012.

City of Calgary Fire Station, Symons Valley Calgary $15.0 Proposed for 2011

City of Calgary Glenmore Water Treatment Plant Calgary $218.7 2004-2011 Nearing completion. PCL Construction. Upgrades / Expansion

City of Calgary Cranston Bow River Crossing Water Calgary $12.6 2008-2011 Under construction. Phased construction. Pipeline

City of Calgary 'Harvey Passage' Weir Calgary $16.6 2008-2011 Under construction. Degraaf Excavating Ltd. Reconstruction, Bow River

City of Calgary Emergency Operations Control Calgary $54.0 2009-2012 Under construction. Centre

City of Calgary LRT Extension Northeast, Calgary $124.0 2009-2012 Under construction. Standard General (grading, Westwinds to Saddle Ridge utilities, noise barrier, park and ride). Whitehorn Station PCL Construction.

City of Calgary LRT Extension NW to Rocky Ridge, Calgary $115.0 2009-2014 Under construction. LRT overpass over Stoney Tr. Tuscany Graham Construction Group. LRT track, station construction start 2012.

City of Calgary Lakeview Storm System Calgary $17.4 2010-2011 Nearing completion. Caliber Systems. Improvements

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 14 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks City of Calgary Metis Trail NE from 64 Ave to 96 Ave Calgary $18.6 2010-2011 Under construction (phase 2). Standard General. Phase 1 64 Ave LRT tunnel. Phase 2 link from 80 to 96 Ave.

City of Calgary 54 St SE Stormwater Wetland Pond Calgary $6.5 2010-2011 Announced. Caliber Systems.

City of Calgary Mahogany Storm Trunk Calgary $6.4 2010-2011 Nearing completion. Whissell Contractors.

City of Calgary 'Peace Bridge' Pedestrian Bridge Calgary $24.5 2010-2011 Nearing completion. Graham Infrastructure. over Bow R near Prince's Island

City of Calgary Sunalta West LRT Calgary $9.4 2010-2011 Under construction

City of Calgary Wastewater Sanitary Trunk / Lift Calgary $62.0 2010-2011 Under construction. Nose Creek trunk, Saddle Station Projects 2010 - 2011 Ridge relief trunk. Nose Creek Phase A contract 3 Whissell Contractors.

City of Calgary 7 Ave LRT Station Rehabilitation Calgary $20.0 2010-2011 Completed

City of Calgary West LRT Parkade Calgary $28.0 2010-2011 Under construction

City of Calgary Downtown Accommodation Plan Calgary $7.0 2010-2012 Announced (Three Buildings)

City of Calgary 96 Ave N Extension from Deerfoot Calgary $28.7 2010-2012 Under construction. Aecon Construction. Tr to Airport Trail and Deerfoot Tr / Airport Tr Interchange

City of Calgary West LRT Line from Downtown to Calgary $1,000.0 2010-2012 Under construction. SNC Lavelin Construction Westside Rec Centre (Pacific).

City of Calgary 13 Avenue Greenway Phase 1 (1 St Calgary $8.5 2011 Under construction. Volker Stein Contracting. SE to 4 St SW)

City of Calgary STORM WATER QUALITY Calgary $17.0 2011-2012 Announced. Planned construction of three ponds. RETROFITS

City of Calgary East Calgary Landfill Scalehouse Calgary $14.0 2011-2012 Announced and Entrance Replacement

City of Calgary East McKenzie Feedermain Calgary $20.0 2011-2012 Announced

City of Calgary Spyhill Landfill Scale House and Calgary $13.0 2011-2012 Announced Entrance Replacement

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 15 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks City of Calgary LAKEVIEW STORM SYSTEM Calgary $8.0 2011-2012 Announced UPGRADES PHASE 2

City of Calgary SPYHILL LANDFILL GAS Calgary $10.0 2011-2012 Announced COLLECTION SYSTEM AND TREATMENT

City of Calgary SHEPARD LANDFILL Calgary $8.0 2011-2012 Announced COLLECTION SERVICES DEPOT II

City of Calgary Feedermain phase 2 Calgary $7.0 2011-2012 Announced

City of Calgary SHEPARD LANDFILL Calgary $10.0 2011-2012 Announced STORMWATER COLLECTION AND TREATMENT EXPANSION

City of Calgary SADDLE RIDGE RELIEF TRUNK Calgary $5.0 2011-2012 Announced

City of Calgary NOSE CREEK SANITARY TRUNK Calgary $32.0 2011-2012 Announced PHASE B

City of Calgary CRESTMONT PUMP STATION Calgary $10.0 2011-2012 Announced

City of Calgary WEST PINE CREEK SANITARY Calgary $16.0 2011-2012 Announced. Caliber Systems. TRUNK PART 1 and MACLEOD TRAIL FEEDERMAIN PHASE 2

City of Calgary CURRIE PUMP STATION Calgary $15.0 2011-2012 Announced

City of Calgary Fire Station, Douglas Glen Calgary $7.0 2011-2012 Announced

City of Calgary EAST CALGARY LANDFILL Calgary $13.0 2011-2012 Announced COLLECTION SERVICES DEPOT

City of Calgary / Calgary Four Lane Underpass connecting Calgary $70.0 2010-2011 Under construction. Graham Construction. Municipal Land East Village and / Corporation Stampede Grounds (4 St SE)

City of Camrose Wastewater Treatment Facility Camrose $55.0 Proposed

City of Edmonton Kennedale Waste Management Edmonton $9.0 Proposed for 2011 - 2012. Facility Expansion

City of Edmonton FIRE STATION, HERITAGE VALLEY Edmonton $7.6 Proposed

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 16 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks City of Edmonton Heavy Repair and Equipment Edmonton $56.0 Proposed. Facility, Ellerslie

City of Edmonton LRT Parkade at Century Park Edmonton $15.0 Proposed

City of Edmonton Kennedale Traffic Operations Edmonton $7.0 Proposed Building

City of Edmonton Quesnell Bridge Widening and Edmonton $161.0 2009-2011 Under construction. Concreate USL Ltd. Rehabilitation

City of Edmonton Transit Park and Ride, Eaux Claires Edmonton $12.0 2010-2011 Completed

City of Edmonton Fire Station 27, Ellerslie Edmonton $10.1 2010-2011 Under construction. Stuart Olson Dominion Construction.

City of Edmonton Fulton Place and Capilano Edmonton $11.5 2010-2012 Under construction. Carmacks Enterprises. Neighbourhood Rehabilitation

City of Edmonton Police Station, Southwest Edmonton $20.8 2010-2012 Under construction. Clark Builders.

City of Edmonton LRT Extension from Downtown to Edmonton $725.0 2010-2014 Announced. EPCOR Tower tunnel nearing NAIT completion. Planned construction start spring 2011.

City of Edmonton Scona Road Improvements Edmonton $24.0 2011 Announced.

City of Edmonton 2011 SOUTH RESIDENTIAL AND Edmonton $8.8 2011 Announced. Lafarge Canada Ltd. Greenview INDUSTRIAL OVERLAY residential, McIntyre Industrial, Weir Industrial.

City of Edmonton 2011 Neighbourhood Renewal Edmonton $140.0 2011 Announced Projects

City of Edmonton GATEWAY BLVD / 23 AVE Edmonton $11.2 2011 Under construction. Park Paving. INTERCHANGE CONTRACT 2 (ROAD UPGRADING / REALIGNMENT)

City of Edmonton Engineering Services Office and Lab Edmonton $15.7 2011 Announced. Chandos Construction. Facility

City of Edmonton / 17 ST Edmonton $19.0 2011-2012 Announced. Graham Construction. INTERCHANGE

City of Edmonton REPLACEMENT FOR Edmonton $132.0 2013-2014 Announced WALTERDALE BRIDGE

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 17 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks City of Fort Saskatchewan Police Building Expansion Fort $5.6 Proposed for 2012. Saskatchewan

City of Fort Saskatchewan Civic Office Building (City Hall) / Fort $18.0 Proposed for 2011. To be built beside existing city Library Saskatchewan hall.

City of Fort Saskatchewan 100 Ave Downtown Improvements Fort $10.0 2010-2012 Under construction. Three - year project. Program Saskatchewan

City of Grande Prairie Wastewater Treatment Plant Grande Prairie $45.0 Proposed for 2011 - 2014. Tender call for general Upgrades Phase 2 contractor anticipated summer 2011.

City of Grande Prairie Fire Station #3, Centre West Grande Prairie $6.3 2010-2012 Under construction. Clark Builders. Industrial Park

City of Grande Prairie 116 ST UPGRADES BETWEEN 68 Grande Prairie $7.0 2011 Announced AVE AND 97 AVE

City of Leduc Public Services Buildings Leduc $10.7 2010-2011 Nearing completion. PCL Construction. Four buildings.

City of Lethbridge Transit Administration Centre Lethbridge $16.0 Proposed for 2011 - 2013. Expansion

City of Lethbridge Police Headquarters Expansion Lethbridge $26.7 Proposed for 2013 - 2015.

City of Lethbridge Upgrades to 28 St N Lethbridge $10.0 Proposed.

City of Lethbridge Fleet Services Building plus Other Lethbridge $17.3 2010-2011 Nearing completion. Western Construction and Work Combustion Services.

City of Lloydminster RCMP Detachment Building Lloydminster $10.2 Proposed

City of Lloydminster Sewage Treatment Plant Expansion Lloydminster $7.8 2010-2011 Announced

City of Medicine Hat Water Treatment Plant Discharge Medicine Hat $30.0 Proposed. Planned completion in 2014. Treatment Facility

City of Medicine Hat Alterations to Existing Building ( Medicine Hat $6.0 Proposed. Tender call expected late May / early future location of Environmental June. Utilities Dept)

City of Medicine Hat Fire Station, South Ridge Medicine Hat $7.5 Proposed. Planned completion by / in 2014.

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 18 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks City of Medicine Hat SOUTH RIDGE DRIVE UPGRADE Medicine Hat $11.7 Proposed TO FOUR LANES FROM HIGHWAY 1 (TCH) TO STRACHAN ROAD

City of Red Deer Gaetz Avenue Revitalization Project Red Deer $8.6 Proposed. Gaetz Avenue between 46 St. and 53 St.

City of Red Deer Intersection Upgrades 32 St Red Deer $8.0 Proposed for 2013. between Spruce Drive and 40 Avenue

City of Red Deer Intersection Improvements on Red Deer $8.5 Proposed for 2011 and / or 2012. Spruce Drive, Springfield Ave and 40 Ave

City of Red Deer Sanitary Sewer and Storm Water Red Deer $36.0 Proposed Sewer Improvements

City of Red Deer Wastewater Treatment Plant Red Deer $70.2 2007-2011 Under construction. Graham Industrial Services. Upgrade phases 1 to 3

City of Red Deer 2011 PAVING PROJECTS Red Deer $5.5 2011 Announced

City of Red Deer North Side Highway Connector Red Deer $15.5 2011-2012 Announced. Northside Construction Partnership Project phase 1A (grading Gaetz Ave to 78 St).

City of St. Albert Western Boundary Road Phase 3 St. Albert $47.0 Proposed. Giroux Rd to Villeneuve Rd. ()

City of St. Albert Arterial Road Connections to St. Albert $11.2 Proposed Anthony Henday Drive

City of St. Albert Landfill / Sewage Lagoon St. Albert $24.0 2008-2011 Nearing completion (phase 2). Remediation in Riel Park, phases 1 and 2

City of St. Albert Wastewater Capacity Expansion St. Albert $15.0 2010-2011 Announced

Clearwater County 2011 Local Roadwork Clearwater $5.7 2011 Announced. Sandstar Construction. County

County of Grande Prairie Inland Multi - Modal Logistics Park County of $28.0 Proposed (Integrated Rail / Truck Container Grande Prairie Depot) Phase 1

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 19 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks County of Grande Prairie 2011 Road Construction Projects County of $17.3 2011 Announced Grande Prairie

County of Newell County Office Building County of Newell $13.0 2010-2012 Under construction. Ledcor Construction.

County of St. Paul Krider Road Base and Pave County of St. Paul $5.0 Proposed

County of Vermilion River ACE REGIONAL WATER SYSTEM County of $14.3 2011 Announced. Nu Edge Construction. PHASE 1 WATERMAIN Vermilion River CONTRACTS 1 AND 2

County of Vermilion River ACE REGIONAL WATER SYSTEM Vegreville $6.0 Proposed PHASE 1 WATER TRANSFER STATION

Cypress County Eagle Butte Road Grade, Base and Cypress County $6.0 Proposed for 2011. Pave

Defence Construction Infrastructure Upgrades, CFB Cold Cold Lake $120.0 2006-2015 Under construction Canada Lake

Defence Construction Fire Station, CFB Suffield Cypress County $6.0 Proposed for 2011. Tender closes April 14. Canada (Ralston)

Defence Construction Training Accommodation Building, Edmonton $11.6 2011-2012 Under construction. Pentagon Structures. Canada CFB Edmonton

Defence Construction Community Centre, CFB Wainwright Wainwright $5.1 On hold. Originally proposed for 2011 - 2012. Canada

Edmonton Regional Edmonton International Airport Leduc County $1,800.0 2009-2012 Under construction. Central utilities plant 2010 - Airport Authority Expansion 2011 Stuart Olson. Apron expansion Dufferin Construction. Control tower and office building 2010 - 2012 EllisDon. Main terminal expansion 2009-2012 PCL Construction.

EPCOR North LRT Extension -- Distribution Edmonton $17.0 Proposed and Transmission Power Facilities

EPCOR 2011 WATER MAIN RENEWALS Edmonton $30.6 2011 Announced

Fort McMurray Regional Fort McMurray Airport Upgrade / RM of Wood $198.0 Proposed for 2011 - 2013. Terminal and expanded Airport Authority Expansion Buffalo (Fort parking. Tender for general contractor expected McMurray) June 2011.

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 20 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Hangar Development / Combined Hangar / Office Building, Leduc County $20.0 2010-2011 Under construction. Clarke Builders. Edmonton International Airport

Lac la Biche County Wastewater Treatment Facility, Lift Lac la Biche $22.0 Proposed for 2011 - 2012. Maple Reinders. Station and Forcemain County

Lac la Biche County Wastewater Biological Nutrient Lac la Biche $5.0 Proposed for 2011. Maple Reinders. Removal Facility County (Lac la Biche)

Lacombe County 2011 Road Construction and Paving Lacombe County $18.2 2011 Announced. Programs

MD of Bonnyville 54 Ave Reconstruction Bonnyville $5.6 Proposed

MD of Foothills / Town of SH 543 (Tongue Creek Rd) MD of Foothills / $17.4 2010-2011 Under construction. Graham Infrastructure. High River Extension High River

MD of Greenview Forestry Trunk Road Upgrading MD of Greenview $10.0 Proposed Project Phase 3

MD of Greenview 2011 LOCAL ROAD SURFACING MD of Greenview $5.8 2011 Announced. Wapiti Gravel Suppliers.

MD of Greenview Government Building Valleyview $5.2 2010-2011 Completed. Dawson Wallace.

MD of Lesser Slave River South Shore Wastewater Project MD of Lesser $10.0 2009-2011 Under construction. Phase 4 Urban Underground Slave River Solutions.

MD of Wainwright ROAD, TRUCK PIT MD of Wainwright $5.9 2011 Announced. Border Paving. ROAD BASE AND PAVE

Mountain View County Road Restoration Mountain View $12.0 2010- Proposed. Multi - year project. County

Municipality of Crowsnest Upgrades to Frank Sewer Plant Crowsnest Pass $30.0 Proposed for 2011 - 2019. To be completed in Pass stages over eight and a half years.

Northern Sunrise County / 'New Water' Regional Water Project Northern Sunrise $10.8 2010-2011 Announced. Good Brothers Construction (water Woodland Cree First Phase 2A County pipeline to Little Buffalo). Nation / Village of Nampa

Parks Canada Twinning Highway 1 Banff National $30.3 2009-2012 Under construction. Dawson Construction. Phase Park (Castle Jct 3B completed. to BC border)

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 21 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Parks Canada Twinning Trans - Canada Highway Banff National $46.7 2010-2011 Under construction. Aecon Group. and Associated Bridges Km 76 to 82 Park (near Lake Louise to BC)

Public Works and RCMP Detachment Building High Level $7.8 Proposed Government Services Canada

Red Deer Regional Airport Airport Alteration and Runway Red Deer County $6.0 On hold pending funding. Originally proposed for Extension 2010 - 2011.

Regional Municipality of REGIONAL LANDFILL CELLS 2, 3 RM of Wood $8.0 Proposed Wood Buffalo AND STOCKPILE PAD Buffalo

Regional Municipality of PARSONS CREEK WATER RM of Wood $12.0 Proposed Wood Buffalo RESERVOIR AND PUMP STATION Buffalo

Regional Municipality of REPLACEMENT BRIDGE FOR RM of Wood $10.0 Proposed Wood Buffalo FORT MACKAY RIVER BRIDGE Buffalo

Regional Municipality of GREGOIRE EAST SANITARY RM of Wood $14.0 Proposed Wood Buffalo OUTFALL CONTRACT 2 (HDD Buffalo SIPHON)

Regional Municipality of Highway 69 Improvements Contract RM of Wood $8.0 Proposed. Planned construction start March. Wood Buffalo 1 Buffalo

Regional Municipality of Saline Creek Outfall Sewer, Water RM of Wood $11.4 2010-2011 Under construction. Tri - City Contracting. Wood Buffalo Supply Buffalo

Regional Municipality of 2011 SOLID WASTE PROJECTS RM of Wood $23.0 2011 Announced Wood Buffalo Buffalo

Regional Municipality of 2011 WATER SERVICES RM of Wood $148.0 2011 Announced Wood Buffalo PROJECTS Buffalo

Regional Municipality of 2011 ROAD REHABILITATION AND RM of Wood $153.0 2011 Announced Wood Buffalo INFRASTRUCTURE PROJECTS Buffalo

Regional Municipality of 2011 TRANSPORTATION RM of Wood $144.0 2011 Announced Wood Buffalo PROJECTS Buffalo

Regional Municipality of Water Supply Line Upgrade RM of Wood $12.7 2010-2011 Under construction. Alpha Construction. Wood Buffalo Contract 1 Buffalo (Conklin)

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 22 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Regional Municipality of Franklin Ave / Highway 63 RM of Wood $10.0 Proposed Wood Buffalo Interchange Buffalo (Fort McMurray)

Regional Municipality of Parsons Creek Site Grading Stage 2 RM of Wood $16.9 2010-2011 Under construction. Sureway Construction. Wood Buffalo Buffalo (Fort McMurray)

Regional Municipality of Fire Station #5 (South Station) RM of Wood $19.4 2010-2011 Under construction. Marshall-Lee Construction. Wood Buffalo Buffalo (Fort McMurray)

Regional Municipality of Athabasca Water Treatment Plant RM of Wood $161.5 2010-2012 Under construction. Bird Construction. Wood Buffalo Upgrades Buffalo (Fort McMurray)

Regional Municipality of LOWER TOWNSITE RM of Wood $60.0 2011-2013 Announced Wood Buffalo REDEVELOPMENT (WATER Buffalo (Fort LINES, SEWER LINES, STORM McMurray) LINES, SURFACE WORK)

Regional Municipality of LOWER TOWNSITE RESERVOIR RM of Wood $13.0 Proposed Wood Buffalo AND PUMP STATION Buffalo (Ft McMurray)

Regional Municipality of Lower Townsite West Loop Road RM of Wood $6.0 Proposed for 2011. Wood Buffalo Contract 1 (Roadwork, Sanitary Buffalo (Ft Sewer, Watermain) McMurray)

Regional Municipality of Parsons Development Area Water RM of Wood $12.4 2010-2011 Under construction. Tri - City Contracting. Wood Buffalo Transmission Main Phase 1 Buffalo (Ft McMurray)

Regional Municipality of Holding Cell Facility RM of Wood $20.0 2011-2012 Announced. Planned construction start summer Wood Buffalo Buffalo (Ft 2011. McMurray)

Rocky View County Two Fire Stations, East Balzac and Rocky View $10.0 2010-2011 Under construction (Elbow). Balzac Devitt & Forand. Elbow Valley County

Rocky View County Wastewater Pipeline Rocky View $18.0 Proposed County ( to Langdon)

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 23 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Saddle Lake Cree Nation Water Treatment Plant Upgrades Saddle Lake $7.0 Proposed Contract 5 Cree Nation

Santas Anonymous / Jerry Forbes Centre for Community Edmonton $21.0 Proposed for 2011 - 2012. Synergy Projects. Christmas Bureau of Spirit Edmonton

South Red Deer Regional Regional Wastewater Pipeline Olds to Red Deer $96.0 2009-2014 Under construction. Three phases: Innisfail - Wastewater Commission Penhold; Penhold - Red Deer; Olds - Innisfail. Olds - Innisfail section to start construction late summer 2011. Penhold - Red Deer to be built after the other two phases.

South Red Deer Regional Wastewater Treatment Plant Red Deer $80.0 Proposed for 2011 - 2012. Wastewater Commission Upgrade Phase 4 (SRDRWC) / City of Red Deer

Strathcona County 17 St Water Reservoir / Pumphouse Strathcona $19.0 2009-2011 Under construction. Sure - Form Construction. Upgrades County

Strathcona County 2011 RURAL ROAD OVERLAY Strathcona $5.1 2011 Announced PROGRAM County

Strathcona County Ardrossan Wastewater Line Strathcona $30.0 Proposed. To be considered in 2011 budget. County (Ardrossan)

Strathcona County Rge Rd 220 Pave and Intersection Strathcona $12.6 2011-2012 Announced. Carmacks Enterprises. Upgrade (Rge Rd 220 / Hwy 15) County (N from Hwy 15)

Strathcona County Firefighter Training Centre / Fire Strathcona $17.5 Proposed Station 6 County (Sherwood Park)

Sturgeon County 195 Ave E and 82 St Grade, Base Sturgeon County $7.1 2010-2011 Under construction. Carmacks Enterprises. and Pave

Town of Beaumont St. Vital Park Reservoir and Beaumont $6.2 2009-2011 Nearing completion. Gabriel Construction. Pumphouse

Town of Beaumont / City 50 St Widening from SH625 to 41 Beaumont $40.0 Proposed of Edmonton Ave in Edmonton

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 24 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Town of Blackfalds RCMP Detachment Building and Blackfalds $5.3 2010-2011 Nearing completion. Shunda Consulting and Fire Station Construction Management.

Town of Bonnyville RCMP Detachment Building Bonnyville $5.5 2010-2011 Under construction. GenMec ACL Inc.

Town of / Water and Wastewater Treatment Rocky View $26.0 2010-2012 Under construction (phase 1 -- water treatment Rocky View County / Facility County / Bragg plant). Province of Alberta Creek

Town of Chestermere Sanitary Forcemain Chestermere $13.8 Proposed for 2012 or 2013.

Town of Chestermere Lift Station 13 (Sanitary Lift Station) Chestermere $9.0 Proposed for 2012 or 2013.

Town of Cochrane Centre Avenue Redevelopment Cochrane $9.0 Proposed for 2012

Town of Devon Water Treatment Plant Devon $5.6 2010-2011 Under construction. Nason Contracting Group.

Town of Didsbury North Industrial Area Roadwork and Didsbury $6.4 Proposed Stormwater Management

Town of Drayton Valley New Water Treatment Plant Drayton Valley $19.0 Proposed for 2011 - 2012.

Town of Drayton Valley WASTEWATER TREATMENT Drayton Valley $7.7 Proposed FACILITY EXPANSION

Town of High River / MD BRIDGE OVER HIGHWOOD RIVER High River $18.0 2011 Under construction of Foothills

Town of Lacombe HIGHWAY 2A GRADE, BASE AND Lacombe $17.1 2011-2012 Announced. Border Paving. PAVE

Town of Mundare Main Street Revitalization Mundare $6.3 2010-2011 Under construction

Town of Okotoks Southridge Emergency Services Okotoks $11.0 2011-2012 Announced. RCMP, municipal enforcement and Building fire station.

Town of Peace River Shaftesbury Water Treatment Plant Peace River $20.0 Proposed for 2011 - 2012. Regional system also Upgrades (part of regional water includes line to Dixonville, reservoir on West Hill. system with MD of Northern Lights)

Town of Slave Lake Water Treatment Plant Upgrades Slave Lake $9.8 2010-2011 Completed. Alpha Construction.

Town of Slave Lake Treated Water Reservoir and UV Slave Lake $8.1 2010-2011 Nearing completion. Alpha Construction. Disinfection

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 25 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Town of Sundre EAST SIDE SERVICING PROJECT Sundre $19.0 Proposed

Town of Sylvan Lake Town Administration Building Sylvan Lake $6.4 Proposed for 2011 - 2012. Tender for general contractor expected early 2011. Planned construction start mid 2011.

Town of Sylvan Lake Lakeshore Drive Redevelopment Sylvan Lake $6.0 Proposed for 2011. Phase 3

Town of Vauxhall / MD of Regional Water Treatment Plant and MD of Taber $19.3 2011-2012 Announced. Vauxhall to Enchant and Vauxhall to Taber Pipework Hays.

Town of Wetaskiwin 50 Ave (Main St) Makeover (Water / Wetaskiwin $11.0 2011-2012 Announced. Phase 1 (48 St to 50 St) in 2011, Sewer Lines and Streetscape) phase 2 (50 St to 53 St) in 2012. The remainder of phases 1 and 2 downtown (47 St to 48 St and 53 St to 56 St) to be completed at a later date.

Town of Whitecourt / Water and Sewer Lines at Whitecourt $7.0 2010-2011 Completed Whitecourt Airport

Village of Longview Water Treatment Plant Upgrades MD of Foothills $5.8 Proposed for 2011 and Wastewater Lagoon (Longview)

Village of Thorsby Water Treatment Plant Leduc County $6.3 2010-2011 Under construction. Nason Contracting Group. (Thorsby)

Vulcan County Water Treatment Plant Vulcan County $6.7 Proposed for 2011 - 2012. (near Vulcan) Institutional *Procurement activities under direction of associated School Board

Acadia Foundation New Seniors Lodge Hanna $15.0 2010-2011 Nearing completion. Kellar Construction.

Acadia Foundation / East Consort Lodge Renovations / Special Area 4 $9.2 2009-2011 Completed. Shunda Consulting and Construction Central Housing Society Expansion (Consort) Management.

AgeCare Health Services 'Walden' SUPPORTIVE LIVING Calgary $19.8 Proposed for 2011 - 2012 Ltd. FACILITY

AgeCare Health Services Seniors Supportive Housing Units, Strathmore $12.2 2009-2011 Under construction Ltd. Sagewood Lodge (Phase 1)

Alberta Health and Designated Assisted Living (DAL) Taber $13.0 2008-2011 On hold. FWS Construction. Wellness / Good Facility Samaritan Society

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 26 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Alberta Health and Edmonton Clinic South Building Edmonton $300.0 2008-2012 Under construction. PCL Construction. Wellness / University of (Ambulatory Learning Centre) Alberta

Alberta Health and Edmonton Clinic North Building Edmonton $250.0 2008-2012 Under construction. PCL Construction Management. Wellness /

Alberta Infrastructure Bow Island Health Centre Bow Island $5.0 2011-2012 Announced. Planned construction start August. Renovations

Alberta Infrastructure / Barrhead Healthcare Centre Barrhead $17.3 Proposed. Deferred pending results of Alberta Alberta Health and Redevelopment Health Services review. Wellness

Alberta Infrastructure / HOSPITAL RENOVATIONS Beaverlodge $5.3 Proposed Alberta Health and Wellness

Alberta Infrastructure / Calgary Cancer Infrastructure Plan Calgary $141.0 Proposed for 2012 - 2015 Alberta Health and Wellness

Alberta Infrastructure / Cross Cancer Institute Renovations Calgary $67.0 Proposed Alberta Health and Wellness

Alberta Infrastructure / Hospital for South Calgary (South Calgary $1,310.0 2007-2012 Under construction. EllisDon Construction. Kasian Alberta Health and Health Campus phase 1) Architecture / HDR Inc. Wellness

Alberta Infrastructure / Pediatric Intensive Care Unit Edmonton $8.1 Proposed for 2012 - 2013 Alberta Health and Expansion, Stollery Children's Wellness Hospital

Alberta Infrastructure / Edmonton Cancer Infrastructure Plan Edmonton $67.0 Proposed Alberta Health and Wellness

Alberta Infrastructure / Endoscopy Suite Expansion, U of Edmonton $14.5 Proposed for 2011 - 2012 Alberta Health and Alberta Hospital Wellness

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 27 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Alberta Infrastructure / Northern Alberta Urology Centre Edmonton $0.0 Proposed for 2012 - 2013. Part of the Edmonton Alberta Health and (Prostate Cancer Clinic) Clinic South project. Wellness

Alberta Infrastructure / Norwood - Glenrose Long Term Edmonton $68.0 On hold. Jen - Col Construction. Originally Alberta Health and Care Facility scheduled for 2008 - 2010. Wellness

Alberta Infrastructure / Emergency Dept Expansion, Stollery Edmonton $18.5 2010-2012 Under construction. PCL Construction. Alberta Health and Childrens Hospital / University of Wellness Alberta Hospital

Alberta Infrastructure / New Food Services Facility, Alberta Edmonton $9.5 2011-2012 Announced. Planned construction start May. Alberta Health and Hospital Wellness

Alberta Infrastructure / Edson Healthcare Centre Edson $108.0 2011-2014 Announced. Alberta Health and (previously described as New Wellness Hospital)

Alberta Infrastructure / Fort Saskatchewan Community Fort $87.0 2008-2012 Under construction. EllisDon Construction. Alberta Health and Hospital Saskatchewan Wellness

Alberta Infrastructure / QEII Hospital Emergency Room Grande Prairie $9.0 2010-2011 Under construction. Delnor Construction. Alberta Health and Renovations / Expansion Phase 2 Wellness

Alberta Infrastructure / High Prairie Health Complex High Prairie $90.0 2011-2013 Announced. Planned construction start late summer Alberta Health and (previously described as New 2011. Wellness Hospital)

Alberta Infrastructure / Continuing Care Centre Lacombe $10.0 On hold. Previously proposed for 2009 - 2010. Alberta Health and Renovations / Upgrades and Deferred pending results of Wellness Dementia Cottage review.

Alberta Infrastructure / CHINOOK REGIONAL HOSPITAL Lethbridge $10.0 Proposed. Alberta Health and FIRST FLOOR RENOVATIONS Wellness

Alberta Infrastructure / Chinook Regional Hospital Parkade Lethbridge $17.5 2010-2011 Under construction. Graham Construction. Alberta Health and Wellness

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 28 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Alberta Infrastructure / Chinook Regional Hospital Re- Lethbridge $112.7 2012-2015 Announced Alberta Health and development Phase 1 (Addition) Wellness

Alberta Infrastructure / Lloydminster Continuing Care Lloydminster $40.0 Proposed for 2011 - 2012. Alberta Health and Project (Replacement for Nursing Wellness Home Wing at Dr. Cooke Extended Care Centre)

Alberta Infrastructure / Medicine Hat Hospital Renovations Medicine Hat $200.0 2011-2015 Announced. Site work in 2011. Alberta Health and phase 1 Wellness

Alberta Infrastructure / Fort McMurray Continuing Care RM of Wood $35.0 Proposed for 2011 - 2012. Alberta Health and Centre (previously described as Buffalo (Fort Wellness Long Term Care Centre) McMurray)

Alberta Infrastructure / Strathcona Community County Strathcona $69.0 Proposed for 2013 - 2014 Alberta Health and Hospital Phase 2 County Wellness (Sherwood Park)

Alberta Infrastructure / Strathcona Community Hospital Strathcona $84.0 2010-2012 Under construction. EllisDon Construction. CASA Alberta Health and Phase 1 County House completed. Wellness (Sherwood Park)

Alberta Infrastructure / Cancer Centre Red Deer $59.5 2010-2013 Under construction. Stuart Olson Dominion Alberta Health and Radiation Therapy Clinic (Cancer Construction. Wellness / Alberta Clinic) Cancer Board

Alberta Infrastructure / Long Term Care Centre (Affordable Didsbury $26.5 Proposed for 2011 - 2012. Alberta Health and Supportive Living Spaces) Wellness / Bethany Care Society

Alberta Infrastructure / 'Community of Care' Personal Care Strathmore $35.0 On hold. Project scope under review by Alberta Alberta Health and Facility Health Services. Wellness / Carewest

Alberta Infrastructure / Good Samaritan Care Centre Stony Plain $31.0 2010-2011 Under construction. Chandos Construction. Alberta Health and Replacement Facility Wellness / Good Samaritan Society

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 29 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Alberta Infrastructure / Grande Prairie Regional Healthcare Grande Prairie $520.0 2011-2014 Announced. Planned construction start fall 2011. Alberta Health and Centre (Peace Country Health Includes cancer treatment centre. Wellness / Grande Prairie Centre) Regional College

Alberta Infrastructure* Four High Schools across Alberta $96.8 2010-2012 Under construction. Clark Builders. Edmonton (Mother Margaret Mary Grades 10-12), Calgary (Northwest Grades 10-12), Spruce Grove (St. Peter the Apostle Grades 9-12) and Sherwood Park (Archbishop Jordan Grades 9-12).

Alberta Infrastructure* Modernization Calgary $35.0 2009-2011 Under construction. Western Canada HS. Clark Builders.

Alberta Infrastructure* Replacement School for Ernest Calgary $33.6 2009-2011 Under construction. West Calgary High School. Manning HS Stuart Olson Constructors.

Alberta Infrastructure* CAREER AND TECHNOLOGY Calgary $6.2 2011 Under construction. Lord Shaughnessy HS. CENTRE MODERNIZATION Westcor Construction.

Alberta Infrastructure* New School (K to Grade 12) Drumheller $13.5 2008-2011 Under construction. St. Anthony's.

Alberta Infrastructure* Replacement Facility Edmonton $60.0 2008-2011 Under construction. Victoria School of Performing and Visual Arts. Aman Building Corp.

Alberta Infrastructure* Modernization (previously listed as Edmonton $6.0 2010-2011 Under construction. Prince Charles and Forest Renovations) Heights Schools. Synergy Projects.

Alberta Infrastructure* Renovations Edmonton $7.8 2010-2011 Under construction. Eastglen High School. Jen - Col Construction.

Alberta Infrastructure* Addition / Modernization Fort $13.2 2009-2011 Under construction. Fort Saskatchewan Elementary Saskatchewan School / Christian School. Chandos Construction.

Alberta Infrastructure* Replacement School (Grades 5 to 9) Millet $5.4 Proposed. Griffiths - Scott Middle School.

Alberta Infrastructure* Elementary School (K to Grade 6) Olds $8.0 2010-2011 Completed. Holy Trinity. Reed Atwood Builders.

Alberta Infrastructure* Modernization Picture Butte $13.4 2010-2011 Nearing completion. Picture Butte Jr / Sr High School. Western Construction and Combustion Services.

Alberta Infrastructure* Modernization (Phases 1 and 2) Ponoka $11.0 2010-2012 Under construction. Ponoka Composite HS. Graham Construction.

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 30 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Alberta Infrastructure* High School (Grades 7 to 12), RM of Wood $53.0 2009-2011 Nearing completion. Holy Trinity, including Timberlea Buffalo (Fort performing arts centre. Aman Building Corp. McMurray)

Alberta Infrastructure* New Junior High School (Grades 7 RM of Wood $40.8 2010-2011 Under construction. Ecole McTavish Jr HS. to 9) Buffalo (Fort Dowland Contracting. McMurray)

Alberta Infrastructure* High School (Grades 7 to 12) Slave Lake $13.7 2009-2011 Completed. St. Francis of Assisi. UFA Construction.

Alberta Infrastructure* Modernization / Addition Smoky Lake $10.2 2010-2011 Completed. Vilna School. Binder Construction. County (Vilna)

Alberta Infrastructure* Modernization Vauxhall $6.1 2010-2011 Under construction. Vauxhall Elementary. UFA Construction.

Alberta Infrastructure* Modernization Vauxhall $15.5 2010-2011 Under construction. Vauxhall HS. UFA Construction.

Alberta Infrastructure* / Ten Schools (P3 Project) across Alberta $253.0 2010-2012 Under construction. Edmonton (three K to Grade 9), B2L Partnership Calgary(four Grade 5 to 9, one K to Grade 9), Okotoks (K to Grade 9) and Langdon (Sarah Thompson School, K to Grade 4).

Alberta Solicitor General Provincial Police and Peace Officer Fort MacLeod $120.0 2012-2013 Announced. Planned construction start summer and Public Security Training Centre 2012.

All Saints Parish New Catholic Church Lethbridge $15.0 Proposed for 2013 - 2015. Consolidation of St. Basil's, Assumption and St. Patrick's parishes.

All Seniors Care Living 'Laurel' Retirement Residence Edmonton $20.0 2010-2012 Under construction. Man - Shield Construction. Centres

Athabasca University Laboratory Addition / Renovations Athabasca $11.0 2010-2011 Completed

Bearspaw Christian Athletics Facility Calgary $5.6 2010-2011 Completed School

Bethany Care Society Affordable Housing Complex, Calgary $11.0 2011-2013 Announced. Planned construction start spring 2011. Riverview Village

Bethany Group 'Peace Hills Lodge' Seniors Facility Wetaskiwin $8.5 2009-2011 Nearing completion. Replacement for current Peace Hills Lodge.

Bow Valley College Campus Redevelopment and Calgary $170.0 2006-2012 Under construction. Stuart Olson Constructors. Expansion

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 31 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Brenda Stafford Affordable Assisted Living Facility Okotoks $15.3 2010-2012 Under construction. Medican Construction. Foundation

Calgary Academy / 'The Academies' Shared Campus (K Calgary $60.0 Proposed for 2010 - 2011. Tanbridge Academy to Grade 12 Educational Space and Recreation Centre)

Calgary Board of Education Centre Including Dr. Carl Calgary $80.5 2008-2011 Under construction. EllisDon Construction. Education Safran Centre

Carrington Communities Seniors Complex Rebuild after Fire Edmonton $10.0 Proposed. Planned completion by spring 2012.

Choices in Community 'Copper Sky Lodge' Assisted Living Spruce Grove $28.0 2010-2012 Under construction. Krawford Construction. Living Inc. Facility

Christenson Communities Royal Oak Village Seniors Housing Lacombe $16.8 2010-2012 Announced. Planned construction start Phase 3 fall Ltd. / Good Samaritans Phases 2 and 3 (Phase 2 Life 2010. Phase 2 (life lease) to follow phase 3. Society Lease, Phase 3 Designated Assisted Living)

City of Calgary Signal Hill Library Addition / Calgary $5.4 2010-2011 Completed. Devitt and Forand Contractors. Renovation

City of Edmonton Library Renovations / Expansion, Edmonton $9.5 Proposed Highlands

City of Edmonton NEW LIBRARY BRANCH MILL Edmonton $30.0 Proposed WOODS

City of Edmonton Jasper Place Library Renewal / Edmonton $14.0 2011-2012 Announced Expansion

City of Red Deer Civic Centre (City Hall) Renovations Red Deer $58.5 On hold. Project has been deferred to 2015 in 2010 / Expansion Phase 1 budget.

City of Red Deer Native Friendship Centre Red Deer $5.0 Proposed. Estimated cost range $5M to $8M.

Continuum Health Care / Supportive Living Complex High River $6.0 Proposed Eldercare Communities

Continuum Health Care Affordable Supportive Living Units, Camrose $11.0 2009-2011 Completed. Shunda Consulting and Construction Holdings Ltd. Sunrise Village Management.

Covenant Health New Designated Assisted Living Red Deer $25.0 Proposed for 2011 - 2012. In design stage. Facility

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 32 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Extendicare Seniors Facility, Eaux Claires Edmonton $25.2 2009-2011 Under construction

Fort McMurray Family New Women's Shelter RM of Wood $50.0 Proposed Crisis Society Buffalo (Ft McMurray)

Fresh Start Recovery Special Care Facility Calgary $6.8 2009-2011 Nearing completion Centre

Government of Alberta New Remand Facility Edmonton $620.0 2008-2012 Under construction. Stuart Olson Constructors.

Grande Prairie and School Expansion (Phases 1 to 3) Grande Prairie $9.0 2010- Under construction (phase 1). District Society for Christian Education

Grant MacEwan University University Service Centre Building Edmonton $20.0 2010-2011 Completed

Green Acres Foundation Sunny South Lodge Modernization / Coaldale $6.8 2009-2011 Completed. Sebring Construction. Renovations

High Prairie School Support Services Building High Prairie $10.0 Proposed. Pending funding approval. Division

Kopernik Polish Heritage Kopernik Seniors Complex and Edmonton $55.0 On hold Society / Good Samaritan Community Centre Society

Lac Ste. Anne Foundation Pleasant View Lodge Modernization Mayerthorpe $14.0 2010-2011 Completed. Krawford Construction. (New Building)

LDS Church LDS Calgary Temple Calgary $24.5 2010-2011 Announced

Mount Royal University 'The Bella Concert Hall' Calgary $73.0 Proposed. Planned completion in 2013. Conservatory of Music / Performance Hall

Mount Royal University Library Calgary $41.0 Proposed. Pending funding.

Mount Royal University Roderick Mah Centre for Continuous Calgary $35.5 2009-2011 Nearing completion. PCL Construction. Learning Expansion and Technology Wing Expansion

Mountain View Seniors Seniors Lodge and Life Lease Olds $21.6 2008-2011 Completed. Shunda Consulting and Construction Housing Building (Replacement Facility for Management. Mount View Seniors Lodge)

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 33 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Oi Kwan Foundation Oi Kwan Place Addition / Calgary $22.1 2010-2012 Under construction. Graham Construction. Renovations

Peace Country Health / Grande Prairie Campus of Care Grande Prairie $20.0 2010-2011 Under construction. Nahanni Construction. Chantelle Management Ltd.

Points West Living Cold Supportive Living Facility Cold Lake $17.0 Proposed Lake / Alberta Health Services

Points West Living Inc. Supportive Living Units, Westgate Grande Prairie $11.0 Proposed for 2011.

Points West Living Inc. Seniors Assisted Living Facility Grande Prairie $35.0 2009-2011 Nearing completion

Points West Living Ltd. Continuing Care Facility (Affordable Stettler $8.8 2011-2012 Announced Supportive Living Spaces)

Public Works and Bowden Institute Expansion Bowden $8.8 2011 Announced. UPA Construction Group. Government Services Canada

Public Works and Drumheller Institute Expansion Drumheller $25.0 Proposed Government Services Canada

Public Works and Edmonton Maximum Security Edmonton $22.7 Proposed Government Services Institution Expansion Canada

Public Works and Edmonton Institute for Women Edmonton $8.0 Proposed. Government Services Addition / Renovations Canada

Red Deer College Sports and Wellness Centre and Red Deer $100.0 On hold. Health Education Centre (Building Communities Through Learning Phase 2)

Rocky Senior Housing Westview Lodge Replacement Rocky Mountain $10.0 2010-2012 Under construction. Chandos Construction. Two Council Facility House phases.

Rocky View Foundation New Seniors Residence (Supportive Crossfield $9.2 2010-2012 Under construction. Keller Construction. Living Units)

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 34 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Santos Property Inc. 'The Gardens at Highway 2' Assisted Red Deer $23.0 Proposed for 2011 - 2012. Living Facility Phase 1

Shalem Society for Senior CARE CENTRE (SENIOR CITIZENS Calgary $5.8 Proposed Citizens Care HOME)

Slim Thorpe Recovery New Detox and Treatment Facility County of $16.2 2009-2011 Under construction Centre Vermilion River (W of Blackfoot)

Southern Alberta Institute Trades and Technology Complex Calgary $445.0 2010-2012 Under construction. PCL Construction. of Technology (SAIT)

Stoney Tribal Elementary School Stoney IR $12.0 2010-2011 Under construction. Trumbley and Hampton. Administration 142,143,144 (Morley)

Strathcona Shelter Society NEW WOMEN'S SHELTER Strathcona $6.8 Proposed (REPLACEMENT BUILDING FOR 'A County SAFE PLACE') (Sherwood Park)

The University of Calgary Experiential Learning Centre (ELC) Calgary $300.0 2008- Under construction (phase 1 Energy, Environmental, Experiential Learning Centre). EllisDon.

The University of Calgary Taylor Family Digital Library (TFDL) Calgary $163.0 2008-2011 Completed. Cana Construction.

The University of Calgary New Student Residence (Yamnuska Calgary $60.0 2009-2011 Completed. Intertech Construction Group. Hall)

The University of Calgary Schulich School of Engineering Calgary $23.4 2009-2011 Completed. EllisDon Construction. Renovation / Expansion Phase 1

The University of Calgary Interior Alterations, Clara Christie Calgary $6.0 2010-2011 Under construction. PCL Construction. Centre for Mouse Genomics

The University of Calgary SCIENCE BUILDING 'A' Calgary $8.0 2011-2013 Announced RENOVATIONS / REMEDIATION

The University of Calgary WASTEWATER TREATMENT Calgary $16.0 2011-2013 Announced. Graham Construction. PLANT

The University of Calgary Renovation of Former 8th and 8th Calgary $40.0 2009-2011 Completed. Graham Construction. / NorthWest Healthcare Health Centre for Urban Campus Properties

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 35 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Town of Beaverlodge / Seniors' Supportive Living Facility Beaverlodge $15.0 On hold Integrated Life Care Inc.

Town of High River Library Expansion and Theatre High River $16.7 Proposed. Complex

Town of Innisfail Innisfail Gathering Place (New Innisfail $9.0 2010-2011 Nearing completion. Pentagon Structures. Library, Seniors Centre and Meeting Rooms)

Trinity Place Foundation 'Glenway' Seniors Housing Facility Calgary $6.0 Proposed. Planned start July 2010.

University of Alberta STUDENT PHYSICAL ACTIVITY Edmonton $57.0 Proposed. Four - year project. AND WELLNESS CENTRE

University of Alberta Stem Cell Research Facility Edmonton $26.5 Proposed. Planned completion in 2 1/2 years (mid 2013).

University of Alberta CPOC Building Edmonton $35.0 2009-2011 Under construction. Chandos Construction.

University of Alberta Devonian Botanic Garden Ecological $30.0 Proposed Learning Centre

University of Alberta / City Performing Arts Centre, Augustana Camrose $11.5 Proposed. Fundraising underway. of Camrose / Camrose Campus County

University of Lethbridge APERTURE RESIDENTIAL PARK Lethbridge $15.0 Proposed for 2012. STUDENT RESIDENCES PHASE 3 (APARTMENTS)

Webber Academy Performing Arts Centre Calgary $9.9 2010-2011 Under construction. Stuart Olson Dominion.

Westlock Foundation Pembina Lodge Expansion Westlock $14.4 Proposed

Wimco Properties Ltd. 'Elk Island View - Bison Place' Lamont $6.0 On hold pending improved market conditions. Assisted Living Facility Manufacturing

Fiberex Glass Corp. Manufacturing Plant Leduc $30.0 Proposed. Pending funding.

Hi - Tech Canada Manufacturing Plant Phase 2 Ponoka $12.0 On hold. Fundraising underway. Developments Ltd.

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 36 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Hi Tech Canada Manufacturing Plant Phase 3 Ponoka $6.0 Proposed for 2011. Pre - built building to be Development Inc. assembled on site.

Hi Tech Canada Manufacturing Plant Phase 4 Ponoka $12.0 On hold. Dependent on market conditions. Development Ltd.

Lafarge Canada Plant Modernization (Upgrades and MD of Bighorn $600.0 Proposed Development) ()

Leading Manufacturing Oil Tank Manufacturing Facility Vermilion $5.0 2010-2011 Announced. Planned construction start fall 2010. Group Ltd.

Quantiam Technologies Furnace Coatings Manufacturing Edmonton $9.2 2010-2011 Completed. Scott Builders. Facility Mining

Alter NRG Corp. Fox Creek Coal Gasification Project MD of Greenview $4,500.0 On hold. Defining project scope. Looking for (near Fox Creek) strategic partner.

Coalspur Mines Ltd. 'Vista' Thermal Coal Mine Yellowhead $185.0 Proposed for 2013 - 2014. County (near Hinton)

Grande Cache Coal Development of #8 Surface Mine $180.0 2009-2012 Under construction. ERCB approval for #8 mine Corporation and #12 South B2 Underground Mine November 2009.

MAXIM Power Corp. Development of #14 Coal Mine Grande Cache $50.0 Proposed for 2010 - 2011. ERCB approval October 2009.

Parsons Creek Parsons Creek Aggregates RM of Wood $30.0 Proposed for 2011 - 2012, pending approvals. Aggregates Limestone Quarry Buffalo (N of Ft McMurray) Oil & Gas

AltaGas Income Trust Harmattan Co - Stream Project Mountain View $100.0 2011-2012 Announced. Cost range $100M to $120M. ERCB County approval December 2010. (Harmattan complex)

Free Energy International Geothermal Heat to Power Plant(s) MD of Big Lakes $7.0 Proposed Inc.

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 37 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Inclusive Energy Ltd. Liquids Storage Facility Yellowhead $40.0 Proposed. Planned completion spring 2011. County (near Edson)

Paramount Energy Trust Conversion of Depleted Gas Pool to near Vegreville $37.0 2010 Announced Natural Gas Storage Facility

Pembina Pipeline Corp. Midstream Capital Projects 2011- across Alberta $225.0 2011-2013 Announced 2013

Sunshine Oilsands 'Muskwa' Heavy Oil Project Phase 1 MD of Opportunity $31.0 Proposed. Five phases in total.

Swan Hills Synfuels LP Coal Gasification Plant MD of Big Lakes $1,000.0 Proposed for 2011 - 2014. PCL Industrial (Swan Hills area) Management (syngas processing facility). Oil Sands

Alberta Oilsands Inc. 'Clearwater West' SAGD Production RM of Wood $415.0 Proposed. Planned construction start in 2011, Buffalo (S of Fort pending approvals. Application filed January 2010. McMurray)

BP Canada / Value 'Terre de Grace' SAGD Oil Sands RM of Wood $3,500.0 On hold pending financing. Creation Inc. Project Buffalo

Canadian Natural 'Project Horizon' Mining and Drilling RM of Wood $1,080.0 Proposed. Approved Jan 2004. Resources Ltd. (CNRL) Project phase 2 / 3 Buffalo

Canadian Natural 'Kirby' In - Situ Oil Sands Project RM of Wood $1,250.0 2010-2013 Under construction. Application approved Q3 - 2010. Resources Ltd. (CNRL) Phase 1 Buffalo

Canadian Natural Bitumen Upgrader Phase 1 Sturgeon County $4,000.0 2012-2014 Announced. EPC SNC-Lavalin, PCL Industrial Resources Ltd. (CNRL) / (near Redwater) Management. Site preparation complete. North West Upgrading Inc.

Cenovus Energy 'Borealis' SAGD Project Phase 1 RM of Wood $1,000.0 On hold. Owner expects construction start 2014. Buffalo (N of Fort McMurray)

Cenovus Energy Inc. Christina Lake Thermal Expansion RM of Wood $3,000.0 Proposed for 2011 - 2016. Applications filed Project Phases 1E, 1F and 1G Buffalo (SE of October 2009. Estimated construction Phase 1E Conklin) 2011- 2014; Phase 1F 2012 - 2015; Phase 1G 2014 - 2016.

Cenovus Energy / 'Foster Creek' Oil Sands Project Lac la Biche $2,000.0 2011-2017 Announced. ERCB approval September 2010. Site ConocoPhillips Phases F, G and H County preparation underway.

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 38 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Cenovus Energy Inc. / 'Narrows Lake' In Situ Oil Sand RM of Wood $1,600.0 Proposed. Application filed early February. ConocoPhillips Project using Solvents Buffalo (Narrow Lake)

Connacher Oil & Gas Ltd. 'Great Divide' SAGD Expansion RM of Wood $600.0 Proposed for 2012 - 2013 Phase 1 Buffalo (S of Ft McMurray)

ConocoPhillips Canada / 'Surmont Phase 2' Oil Sands RM of Wood $2,000.0 2010-2014 Under construction Total Canada Development Buffalo

Devon Canada Corp. 'Jackfish' Oil Sands Project Phase 3 RM of Wood $1,000.0 Proposed for 2011 - 2015. Application filed Q3 - Buffalo (SE of 2010. Conklin)

Devon Canada Corp. 'Jackfish' SAGD Oil Sands Project RM of Wood $1,060.0 2008-2011 Completed Phase 2 (J2) Buffalo (SE of Conklin)

Dover Operating Corp. 'Dover' COMMERCIAL OILSANDS RM of Wood $2,500.0 Proposed for 2013 - 2015. Application filed (Dover OPCO) PROJECT PHASE 1 Buffalo February 2011. Five phases in total.

Enbridge Inc. Terminal Tankage (Storage Strathcona $260.0 Proposed for 2011 - 2012, pending regulatory Capacity) Expansion Phases 1 and 2 County approval.

E-T Energy Ltd. 'Poplar Creek' Bitumen Extraction RM of Wood $103.0 Proposed for 2011 - 2013. Planned construction Project Buffalo start late 2011, pending regulatory approvals.

Fort Hills Energy Corp. 'Fort Hills' Oil Sands Mine RM of Wood $9,600.0 Proposed. Corporate approval for construction (Suncor Energy Inc. / Buffalo expected by end of 2012. Planned to come Total SA / Teck Cominco) onstream in 2016.

Grizzly Oil Sands ULC 'Algar Lake' SAGD Oil Sands Project RM of Wood $500.0 Proposed for 2011 - 2012. SNC - Lavelin. Buffalo (SW of Fort McMurray)

Horizon North Logistics Oil Sands Work Camp northern Alberta $25.0 Proposed Inc.

Horizon North Logistics OIL SANDS ACCOMMODATION RM of Wood $20.0 2011 Announced Ltd. CAMP Buffalo (near Ft McMurray)

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 39 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Husky Energy Inc. / BP 'Sunrise Thermal Project' SAGD Oil RM of Wood $2,500.0 2012-2013 Announced. SaipamSpA. Application approved. PLC Sands Project Phase 1 Buffalo (N of Fort Corporate approval Nov 2010. WorleyParsons McMurray) Canada EPC field facilities.

Husky Energy Inc. / BP 'Sunrise Thermal Project' Phase 2 RM of Wood $1,900.0 On hold pending review of costs and project Plc. Buffalo optimization

Imperial Oil Ltd. 'Nabiye' Oil Sands Project MD of Bonnyville $1,300.0 Proposed. Planned on - stream by 2015. (Cold Lake area)

Imperial Oil Resources / 'Kearl Lake' Oil Sands Mine Phase 1 RM of Wood $8,000.0 2009-2012 Under construction. Three production trains / ExxonMobil Canada Buffalo phases in total. Application approved (all phases). AMEC (EPC). Fluor Corp infrastructure and facilities.

Ivanhoe Energy 'Tamarack' Bitumen Project Phase 1 RM of Wood $1,250.0 Proposed for 2012 - 2013. Application filed Buffalo (near Fort November 2010. McMurray)

Japan Canada Oil Sands Hangingstone SAGD Commercial RM of Wood $1,200.0 Proposed for 2011 - 2014. Application filed. Limited (JACOS) / Nexen Production Project Buffalo (S of Fort Approval expected Q3 2011 Inc. McMurray)

Korea National Oil 'BlackGold' In Situ Oil Sands Project RM of Wood $300.0 2011-2012 Announced. GS Engineering and Construction Corp. Company (KNOC) Phase 1 Buffalo (SE of Conklin)

Korea National Oil 'BlackGold' Oil Sands Project Phase RM of Wood $540.0 Proposed for 2013 - 2015, pending approvals. Corporation (KNOC) 2 Buffalo (SE of Conklin)

Laricina Energy Ltd. 'Germain' Commercial MD of Opportunity $250.0 Proposed for 2011 - 2012, pending approvals. Demonstration Project (Solvent - Smaller scale pilot plant approved by ERCB Cyclic SAGD) completed.

MEG Energy Corp. In Situ Oil Sands Project Phase 2B RM of Wood $1,400.0 2011-2012 Announced. Planned construction start early 2011. Buffalo (Christina Corporate approval December 2010. Lake)

N-Solv Corp. Pilot Plant RM of Wood $50.0 Proposed Buffalo

OPTI Canada / Nexen Inc. 'Long Lake South' SAGD Project RM of Wood $2,790.0 On hold due to uncertain financial markets and Phase 2 (Kinosis) Buffalo escalating capital cost. Cost estimates are preliminary. Corporate approval deferred til late 2011.

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 40 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks OPTI Canada Inc / Nexen Ash Processing Pit (part of Long RM of Wood $175.0 2008-2011 Under construction. Inc. Lake project) Buffalo

Osum Oil Sands Corp. 'Taiga' Oil Sands Project MD of Bonnyville $1,570.0 Proposed for 2011 - 2018. Application filed (N of Cold Lake) January 2010.

Pengrowth Energy Trust SAGD Pilot Project, Lindbergh RM of Wood $50.0 2011 Announced Buffalo

Penn West Energy Trust / Development of Seal Lake MD of Big Lakes $150.0 2010-2011 Announced China Investment Corp. Operations (N of High Prairie)

Petrobank Energy and 'May River' Commercial Bitumen RM of Wood $250.0 Proposed for 2010 - 2012. Application filed Resources Project Phase 1 Buffalo December 2008. FEED underway.

PTI Group Wapasu Creek Lodge Expansion RM of Wood $460.0 2009-2011 Nearing completion Buffalo (N of Fort McMurray)

Royal Dutch Shell 'Orion' Heavy Oil SAGD Facility MD of Bonnyville $340.0 2005-2010 On hold. Phase 1 completed, phase 2 on hold (Phases 1 and 2) (Hilda Lake) pending review. Approved Oct 2004. Phased development, building to 20,000 bpd.

Shell Canada ATHABASCA OIL SANDS RM of Wood $2,000.0 Proposed. Muskeg River Mine, Jackpine Mine and PROJECT DEBOTTLENECK Buffalo / Scotford. Corporate decision in 2011. PHASE 1 Strathcona County

Shell Canada / Chevron / 'Quest' CARBON CAPTURE AND near Ft $900.0 Proposed for 2012 - 2015. Pending corporate Marathon Oil STORAGE PROJECT Saskatchewan to approval. Application filed November 2010. Thorhild Cty

Shell Canada Ltd. 'Carmon Creek' Bitumen Project Northern Sunrise $3,450.0 Proposed for 2011 - 2016. Two central processing County (NE of facilities and three co-generation units. Peace River)

SilverBirch Energy 'Frontier' Oil Sands Mine Phase 1 RM of Wood $6,000.0 Proposed. Application to be filed early 2011. Buffalo Approval expected in 2014.

SilverBirch Energy 'Equinox' Oil Sands Mine (Lease 14) RM of Wood $2,500.0 Proposed. Application to be filed with Frontier in Buffalo early 2011.

Southern Pacific 'McKay' SAGD Oil Sands Project RM of Wood $450.0 2011-2012 Under construction. Application filed May 2009. Resource Corp. Phase 1 Buffalo (N of Fort Approval October 2010. McMurray)

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 41 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Suncor Energy Inc. North Steepbank Mine Extension RM of Wood $400.0 On hold. Application approved November 2006. Buffalo

Suncor Energy Inc. 'Voyageur South' Oil Sands Mining RM of Wood $4,400.0 On hold pending market conditions. Application Operation Buffalo filed July 2007. Corporate approval January 2008.

Suncor Energy Inc. 'Firebag' Oil Sands Project Phase 4 RM of Wood $2,000.0 Proposed for 2011 - 2013. ERCB approval March Buffalo 2010.

Suncor Energy Inc. 'Firebag' Oil Sands Project Stage 3 RM of Wood $900.0 2010-2011 Nearing completion. Cord WorleyParsons. Buffalo

Suncor Energy Inc. MacKay River SAGD Expansion RM of Wood $1,000.0 On hold pending review of project costs. Application Buffalo (NW of filed Dec 2005. Fort McMurray)

Suncor Energy Inc. / Total 'Voyageur' Oil Sands Third Upgrader RM of Wood $11,600.0 2011-2016 Announced. Project does not include bitumen feed SA (U3) Buffalo to upgrader.

Suncor Energy Services 'Firebag' Administration Complex RM of Wood $177.0 On hold. Bird Construction. and Village Camp Core Buffalo (N of Fort McMurray)

Sunshine Oilsands 'West Ells' Oil Sands Project MD of Opportunity $385.0 Proposed for 2011 - 2012.

Syncrude Canada Ltd. South West Sand Storage RM of Wood $34.6 Proposed. Application filed. Conversion Buffalo

Syncrude Canada Ltd. Phase 4: Upgrader Expansion RM of Wood $2,300.0 Proposed. Pre-engineering study underway Phase 2 / Aurora South Mine Trains Buffalo (Fort (AMEC). Expansion SNC-Lavalin, Fluor Daniel. 1 and 2 McMurray) Train 3 AMEC.

Syncrude Canada Ltd. Sulphur Emission Reduction RM of Wood $1,600.0 2005-2011 Under construction Program (SERP) Buffalo (Mildred Lake)

Total E&P Canada Ltd. / Joslyn North Mine RM of Wood $6,000.0 Proposed. Application filed early 2006. ERCB Suncor Energy Inc. Buffalo conditional approval January 2011. Corporate approval to proceed expected by end of 2012.

TriStar SAGD Pilot Project RM of Wood $100.0 Proposed Buffalo (S of Ft McMurray)

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 42 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Williams Canada OFF- GAS EXTRACTION PLANT RM of Wood $311.0 2011-2013 Announced MODIFICATIONS AND Buffalo and CONSTRUCTION OF DE - Redwater ETHANIZER Other Industrial

Defence Construction Range Control Facility, CFB Suffield Cypress County $5.1 2011-2012 Under construction. Wahl Construction. Canada

Defence Construction Land Force Western Area Edmonton $17.0 Proposed for 2011. Canada Headquarters, CFB Edmonton

Defence Construction Kitting Facility, Canadian Manoeuvre Wainwright $19.5 Proposed for 2011. Cost estimate includes Canada Training Centre, CFB Wainwright demolition of existing facility. Pending approval.

Defence Construction Maintenance Facility, CFB Wainwright $30.0 Proposed for 2011 - 2013. Tender call anticipated Canada Wainwright spring 2011.

Public Works and Lethbridge Research Centre Lethbridge $8.0 Proposed. Tenders close April 19. Government Services Building 102 Exterior Envelope Canada Replacement

TransAlta Corp. / 'Project Pioneer' Carbon Capture Parkland County $1,400.0 Proposed for 2012 - 2014. FEED underway. TransCanada Pipelines and Storage (CCS) Project at Ltd. Pipelines

Athabasca County Athabasca Regional Water Pipeline County of $28.0 Proposed for 2011 - 2012. From Boyle to Grassland Athabasca / Wandering River.

Enbridge Inc. 'Athabasca' Pipeline Capacity between Cold $200.0 Proposed. To be completed by early 2014. Expansion 2 Lake and Hardisty

Enbridge Inc. 'Waupisoo' Pipeline Expansion Edmonton to Fort $400.0 2011-2013 Announced. Planned construction start June 2011. McMuyrray

Enbridge Inc. 'Norealis' Bitumen Pipeline, Husky RM of Wood $475.0 Proposed for 2012 - 2013. Sunrise to Cheecham Terminal Buffalo

Enbridge Inc. 'Wood Buffalo' Crude Oil Pipeline RM of Wood $370.0 Proposed Buffalo

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 43 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Enbridge Inc. Pipelines and Terminal Facilities, RM of Wood $250.0 Proposed Christina Lake Heavy Oil Project Buffalo

Enbridge Inc. 'Athabasca' Oil Pipeline Expansion 1 RM of Wood $185.0 Proposed for 2012 - 2013. Application to be filed Buffalo to early 2011. Hardisty

Enbridge Inc. 'Fort Hills' Bitumen / Diluent RM of Wood $2,000.0 On hold til markets improve. Originally proposed for Pipelines and Terminal Facilities Buffalo to near 2010 - 2012. Pending approvals. Edmonton

Enbridge Pipelines 'Woodland' BITUMEN PIPELINE RM of Wood $100.0 Proposed for 2011 - 2012 Buffalo (Kearl to Cheecham Terminal)

Enbridge Pipelines Inc. 'Northern Gateway' Bitumen and RM of Wood $1,500.0 Proposed for 2014 - 2015. Application filed May Condensate Pipelines (Alberta Buffalo to Alberta 2010. Construction cost entire pipeline (Alberta portion) / BC border and BC) $5.5 billion.

Enhance Energy Inc. CO2 Pipeline (Alberta Carbon Trunk near Edmonton $600.0 2012-2014 Announced. Revised application submitted to Line) to Camrose and ERCB November 2010. Lacombe Counties

Highway 3 Water Regional Water System Bow Island / Cty of Forty Mile / $8.5 Proposed Committee Grassy Lake / Burdett MD of Taber

Inter Pipeline Fund PIPELINE SYSTEM CONNECTION Cold Lake area $14.0 2011 Announced UPGRADES AND EXPANSIONS

Inter Pipeline Fund COLD LAKE MAIN LINE Cold Lake area $11.0 2011 Announced EXPANSION

Inter Pipeline Fund 'Polaris Pipeline' Expansion / Edmonton area $135.0 Proposed for 2010 - 2012. Planned construction Extension of Existing Diluent Pipeline to Kearl Lake start mid - 2010 pending approvals. oilsands project

Keyera Corp. Pipeline and Storage Facilities central Alberta $11.0 2010 Completed

Keyera Corp. 'Carlos' NATURAL GAS PIPELINE central Alberta $30.0 2010-2011 Nearing completion

Keyera Corp. Pipeline and Connections Edmonton / Fort $58.0 Proposed Saskatchewan

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 44 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Keyera Corp. Two 4KM Pipelines Connecting new Edmonton / $18.0 2011 Under construction. One pipeline has been ADT Facility to Fort Saskatchewan Strathcona completed, the other is nearing completion. Pipeline System County

Mountain View Regional Water Line Twinning Innisfail to Olds $34.0 2010- Under construction (Phase 1 nearing completion). Water Services Commission

Pembina Pipeline Corp. Willesden Green Pipeline across Alberta $40.0 2011-2012 Announced Expansion, Trunk Line Improvements and Debottlenecking

Pembina Pipeline Corp. Drayton Valley Trunk Line Extension central Alberta $6.0 Proposed

Pembina Pipeline Corp. Pipeline Debottleneck and central Alberta $11.0 Proposed Construction of Truck Terminals

Pembina Pipeline Corp. Oil Pipeline Capacity Expansion central Alberta $23.0 2010-2011 Announced. Pipeline runs from Willseden Green to Buck Creek.

Pembina Pipeline Corp. PIPELINE REACTIVATION / Yellowhead $15.0 2011 Announced RECERTIFICATION County (Edson area)

Pembina Pipelines 'Nipisi' Heavy Oil and 'Mitsue' Slave Lake and $440.0 2010-2011 Under construction Income Fund Condensate Pipelines Whitecourt areas to Edmonton

Plains Midstream Canada 'Rainbow Pipeline II' Butane and Northern Sunrise $200.0 Proposed for 2011 - 2012. (Plains) Condensate Pipeline County to Strathcona County

Swan Hills Synfuels Synthetic Gas Pipeline Swan Hills to $50.0 Proposed Whitecourt

Vermilion River Regional Regional Water System Phase 1 Counties of $31.2 Proposed Water System (VRRWS) Vermilion River, Minburn and Two Hills

Williams Energy 'Boreal' Natural Gas Liquids (NGL) Fort McMurray to $283.0 2010-2011 Announced. $US. Pipeline Redwater

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 45 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Power

Alberta Electric System Rebuild of Electricity Infrastructure Drayton Valley, $30.0 2010-2013 Under construction. Hinton nearing completion. Operator (AESO) Wabamun, Edson, Hinton

Alberta Electric System Transmission Reinforcement, Hanna east central $1,000.0 Proposed. Stage 1 to be in service by 2012, stage 2 Operator (AESO) Region Alberta in service by 2017.

Alberta Electric System TRANSMISSION LINE REBUILD Wetaskiwin to $60.0 Proposed. Project includes new substation near Operator (AESO) (138kV) Didsbury Didsbury and upgrades to Ponoka substation

Alberta Electric Systems TRANSMISSION SYSTEM central Alberta $206.0 Proposed. New substations near Didsbury, Ponoka Operator (AESO) UPGRADE and Innisfail, substation upgrades and west Lacombe.

Alberta Electric Systems Transmission Line, Poplar Hills to County of $20.0 Proposed over five to seven years (completion Operator (AESO) Grande Prairie Grande Prairie between 2015 and 2017).

Alberta Electric Systems Transmission Line MD of Greenview $150.0 Proposed over five to seven years (completion Operator (AESO) / Cty of Grande between 2015 and 2017). Line from of Little Prairie Smoky to Grande Prairie.

Alberta Wind Energy 'Oldman River' Wind Farm (50MW) MD of Pincher $47.0 Proposed. Pending completion of transmission line Corp. Creek (NE of Pincher Creek to Lethbridge. Pincher Creek)

Alberta Wind Energy Two Wind Generation Projects $840.0 Proposed. Windy Point (62MW, planned Corp. / Mainstream (350MW total) construction start 2012) and Waterton Colony. Renewable Power

Alberta Wind Energy 'Oldman 2' Wind Farm (46MW) MD of Pincher $120.0 2012 Announced. Planned construction start spring 2012. Corporation / Mainstream Creek (NE of Canada Pincher Creek)

AltaLink Western Alberta Transmission Line Edmonton to $1,100.0 Proposed for 2012 - 2014.. Application filed March (500kV) Calgary 2011.

AltaLink South Foothills Transmission Project Fort Macleod to $345.0 Proposed to start construction summer 2012, (240kV) High River pending approvals.

AltaLink TRANSMISSION LINE (240kV) AND MD of Pincher $300.0 Proposed. Application to be filed in 2012. 'Chapel Rock' SUBSTATION Creek (Pincher Creek to )

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 46 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks AltaLink TRANSMISSION LINE (240kV) southern Alberta $400.0 Proposed FROM CASSILS TO BOWMANTON

AltaLink Management Ltd. TRANSMISSION LINE 666L County of Newell $8.0 Proposed. AUC approval January 2011. (W of Brooks)

AltaLink Management Ltd. RUSSELL 632S SUBSTATION MD of Pincher $17.2 Proposed. AUC approval January 2011. Creek

ATCO Electric Transmission Line High Level to Mackenzie $77.5 2009-2011 Completed Sulphur Point County (High Level to near Rainbow Lake)

ATCO Power Eastern Alberta Transmission Line Edmonton to $1,650.0 Proposed for 2012 - 2014. (500kV) Calgary

Chickadee Creek Energy Biomass Energy Project (24MW) Whitecourt $100.0 Proposed for 2010 -2012. Inc. / Millar Western

City of Medicine Hat Concentrating Solar Thermal Energy Medicine Hat $9.0 Proposed for 2010 - 2012 Demonstration Project

ENMAX Corp. 'Shepard Energy Centre' Natural Calgary $1,400.0 Proposed for 2011 - 2015. AUC conditional Gas Fired Generating Plant (800MW) approval October 2010.

ENMAX Energy Corp. 'Bonnybrook Energy Centre' Power Calgary $200.0 Proposed. Pending approvals. Planned in - service Plant (165MW) early 2013.

EPCOR Distribution and 'Heartland' Transmission Line Wabamun to Ind $387.0 Proposed. Public hearing begins April 11, 2011. Transmission / AltaLink (500kV) Heartland NE of Application filed with Alberta Utilities Commission Management Fort (AUC) September 2010. Saskatchewan

Greengate Power Corp. 'Radar Hill' Wind Farm (100MW) Red Deer County $200.0 Proposed (between Red Deer and Pine Lake)

Greengate Power Corp. 'Blackspring Ridge' Wind Power Vulcan County $700.0 Proposed for 2012 - 2013 (phase 1). Project (300MW) (near Carmangay)

Greengate Power Corp. 'Stirling' Wind Farm (100MW) Warner County $250.0 Proposed for 2011. Pending AUC approval. (Stirling)

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 47 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Greengate Power Corp. / 'Halkirk' Wind Farm phases 1 and 2 Paintearth $350.0 2011-2013 Announced Capital Power Corp. (150MW each) County (near Halkirk)

MAXIM Power Corp. Gas Fired Electric Plant (190MW) Lamont County $140.0 Proposed. To be built next to existing Deerland (NE of substation. Pending financing. Bruderheim)

MAXIM Power Corp. 'Milner Expansion' Coal - Fired MD of Greenview $1,400.0 Proposed Generating Plant (500MW) (near Grande Cache)

Montana Alberta Tie Ltd. Electrical Substation near Lethbridge $6.0 2010 Under construction. SNC-Lavelin. (MATL)

Naturener Energy Canada 'Prairie Home' Wind Farm Phase 2 County of Warner $100.0 Proposed for 2011 - 2012 (89 MW)

Naturener Energy Canada East Palliser Transmission Line Cypress County $100.0 Proposed

Naturener Energy Canada 'Wild Rose' Wind Farm (200MW) Cypress County $400.0 Proposed. AUC approval October 2010. Dependent Phase 1 (S of Irvine) on approval of East Palliser Transmission Line.

Naturener Energy Canada 'Wild Rose' Wind Farm Phase 2 Cypress County $410.0 Proposed. Planned to be in - service in 2012. (162MW) (S of Medicine Hat)

Nexen / Joss Power 'Hand Hills' Wind Farm (80MW) Starland County $200.0 Proposed for 2010 - 2011 (E of Delia)

Otoka Energy Corp. Waste to Energy Gasification Plant Brazeau County $100.0 Proposed construction start phase 1 in 2011. Three (25MW) (near Drayton phases. Pending approvals. Valley)

Plasco Energy Group / Plasma Gasification Plant (waste - Red Deer County $93.0 Proposed for 2011 - 2012. Pending federal funding. Central Waste to - energy conversion) (Horn Hill Waste Management Commission Transfer Site)

Suncor Energy / Teck 'Wintering Hills' Wind Farm (88MW) Wheatland $350.0 2010-2011 Under construction. AUC approval June 2010. Resources Ltd. County (near Drumheller)

Swan Hills Synfuels Power Generation Plant (300MW) Whitecourt $500.0 Proposed. Planned construction start 2012.

The University of Calgary Cogeneration Plant (12MW) Calgary $48.0 2010-2011 Completed

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 48 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Trans Canada Corp. 'Saddlebrook' Natural Gas Fired MD of Foothills $400.0 Proposed. Pending approvals. Power Plant (350MW) (near High River) Residential

Alberta Ronald Ronald McDonald House Red Deer $12.0 2010-2011 Under construction. Timcon Construction. Macdonald House

Alpha - Anderson Joint Affordable Housing Project Edson $6.5 2010-2011 Announced Venture

Amacon 'St. Albert Village' Condo Towers St. Albert $450.0 On hold. Approved by city council May 2008. and Urban Village on Grandin Park Plaza Site

Anthem Riverfront Land 'Waterfront' Condominiums (Three Calgary $750.0 On hold (sites 2 and 3). EllisDon Construction. Holdings Towers and Five Podiums) plus Building 1 nearing completion. Townhouses

Apex Lifestyle 'Union Square' Condominium Calgary $25.0 On hold. EllisDon Construction. Communities Apartment Building Phase 2

Arcus Developments 'Astoria on 10th' Condominium Tower Calgary $60.0 On hold. Ledcor Construction. Original schedule 2007 - 2010

Asset Builders Corp. Row Housing Complex Sylvan Lake $6.2 Proposed

Assured Developments 'Akoya at the Bridges' Apartment Calgary $40.1 On hold. Building Phase 2

Avalon Central Alberta 'Verde in Clearview Ridge' Red Deer $35.0 2011-2013 Under construction Townhouse Development

BCM Developments 'The Maxx' Condominiums Edmonton $15.8 2009-2011 Completed

Bethany Group 'Brookside' Seniors Condominiums Camrose $18.0 2010-2011 Under construction. WCMI Construction Services.

Bond Street Properties 'The Bond Centre' Condominium RM of Wood $160.0 Proposed. Pending financing. Towers 1 and 2 Buffalo (Fort McMurray)

Bosa Development / Residential / Retail Complex (Three Calgary $300.0 Proposed. Construction over five to seven years. Embassy Development Towers), East Village

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 49 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Brenda Strafford Affordable Housing Project Calgary $29.0 2008-2011 Completed. Golden Triangle Construction Foundation Ltd. (Apartment Building) Management.

CAIRN Corporation 'Cairn on the Boulevard' Affordable Grande Prairie $14.0 2011-2013 Announced Housing Project

Calgary Homeless HOME CONSTRUCTION PROJECT Calgary $24.0 Proposed Foundation

Cardel Homes 'Lighthouse Landing' Townhouses Calgary $9.2 2010-2011 Under construction Building A5

Cardel Lifestyles 'Village at Prestwick' Building B Calgary $6.6 Proposed (Apartment Building)

Cardel Lifestyles Prestwick Place' Apartment Buildings Calgary $20.0 2010-2011 Under construction

Carma Developers / 'Aurora' Phase 1: Mira Condominium Edmonton $325.0 2007-2011 Under construction Urban Landmarks Master Tower plus Townhouses Builder

Carrington Properties 'L'Attitude' Condominium Apartment Edmonton $15.9 2010-2011 Completed Building

Century Group Lands 'Liberty Junction' Apartments and Red Deer County $41.5 On hold until spring 2011 (Phase 1). Corp. Town House Complex

Christenson 'Centre in the Park' Housing / Retail Strathcona $230.0 2006-2011 Under construction. Can-Der Construction. Developments / Western / Commercial Development County Asset Management (Sherwood Park) Group (WAM)

City of Calgary The Bridges Phase 2 Site 15 Calgary $18.5 Proposed Affordable Housing Project (Mcpherson Place)

City of Camrose / Wild Rose Arena Site Affordable Camrose $9.0 2010-2011 Under construction. WCMI Construction Services. Bethany Group Housing Project

Cold Lake Affordable Apartment Complex Cold Lake $5.5 On hold. Housing Society (CLAHS)

Concept Homes Row Housing Development Edmonton $11.0 Proposed

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 50 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Concord Pacific Inc. Condominium Apartment Building Calgary $30.0 On hold pending a shift in the economy. and Townhouses, Eau Claire

Cove Properties 'Monarch at Mackenzie' BUILDING 1 Calgary $7.4 Proposed for 2011 - 2012 PHASE 2

Cove Properties 'Nuera 2' Apartment Building Calgary $31.0 Proposed for 2011 - 2012

Cove Properties Ltd. 'Monarch at Mackenzie Towne' Calgary $25.0 Proposed Condominium Apartment Building

Devonian Properties 'Longboat Landing' Townhouses and RM of Wood $560.0 Proposed (phase 2 and phase 4 onwards). Apartments Buffalo (Fort Earthworks and deep services anticipated to be McMurray) completed by early 2013.

Devonian Properties 'Longboat Landing' Earthworks and RM of Wood $90.0 2010-2012 Under construction Deep Services Buffalo (Ft McMurray)

Diamond Trust 'Sky Tower' Apartment Building Calgary $47.8 On hold. ITC Construction Group. Development

Edmonton YMCA Boyle Renaissance Phase 1 -- Edmonton $42.2 2010-2012 Under construction. Clark Builders. 'Welcome Village' Affordable Housing and Community Centre

Evolution by Greenboro 'Origins at Cranston' APARTMENT Calgary $5.6 Proposed CONDOMINIUM BUILDING

Evolution by Greenboro 'Valour Park' TOWNHOUSE Calgary $5.0 Proposed COMPLEX

Greater Edmonton Rosslyn Place Apartment Building Edmonton $10.0 2010-2011 Nearing completion. Delnor Construction. Foundation Addition (New Building)

Grosvenor Canada Ltd. 'Drake' Apartment Building Calgary $12.0 Proposed

Habitat for Humanity / TOWNHOUSES Calgary $13.5 Proposed Trico Homes

Hawthorne Homes 'Mosaic Cranston' Townhouses Calgary $20.0 2010-2012 Under construction

Homburg - Centron Kai Mortenson Towers (Two Calgary $130.0 2010-2012 Under construction (tower 1 Oslo parkade). Centron Teamworks Residential Towers) Construction. Construction of tower expected to start spring 2011.

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 51 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Homes by Avi Townhouses Calgary $7.0 Proposed

Horizon Housing Society AFFORDABLE HOUSING Calgary $9.0 Proposed

IMC Construction Condominium Building Sylvan Lake $5.2 2010-2011 Announced. Planned construction start spring 2010.

Intergulf Cidex 'Treo Beacon Heights' Apartment Calgary $7.2 Proposed Building 1

Intergulf Cidex 'Treo Beacon Heights' Apartment Calgary $6.3 Proposed Building 4

Intergulf Cidex 'Treo Beacon Heights' Apartment Calgary $6.4 Proposed Buildings 2 and 3

Jarvis Bay Developments 'The Savanna' Condominium Sylvan Lake $20.0 Proposed. Scope of work revised. Complex

Kanas Corporation Apartment Building Calgary $11.1 Proposed

Kanas Corporation Lumino Building C Condo Apartment Calgary $9.0 Proposed for 2011 - 2012. Building

Kanas Corporation 'Lumino West' Affordable Housing Calgary $11.1 2010-2011 Nearing completion (Apartment Building)

Kanas Corporation Lumino Building B Apartment Calgary $14.8 2011-2012 Under construction Building

Lake Placid Developments 'Centuria on the Park' Condo Calgary $27.0 Proposed to bring building to grade by March 2011. Apartments

Leaside Development 'Cornerstone Village' Residential Olds $50.0 2008-2011 Under construction (phase 2). Four phases. Corp. Development (Apartment Building Phases 3 and 4 apartment condominiums. and Villa Bungalows)

Libbie Young Centre SUPPORTIVE LIVING UNITS AND Lloydminster $5.0 2011-2012 Announced. Tender closes April 14. COMMUNITY CENTRE

Luxe Developments Condominium Apartment Building Calgary $32.0 On hold

Luxe Developments 'Vida' CONDOMINIUM APARTMENT Calgary $6.3 2010-2011 Under construction BUILDING

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 52 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Medican Developments 'Canvas at Millrise' Condo Building Calgary $12.0 2010-2011 Completed Postfire Renovations

Medican Developments 'Sierras of Michener Hill' Red Deer $8.5 2009-2011 Nearing completion Condominium Complex Phase 1

Monarch Group (took 'Axxess' and 'Reflections' Condo Sylvan Lake $8.1 2008-2011 Under construction. Title to Axxess project over from Medican Complexes, Beacon Hill transferred to Monarch Land Development. Developments)

Mustard Seed Ministry Affordable Housing Tower Calgary $60.0 2011-2012 Announced. Clark Builders. Planned construction (Apartment Building) start July.

North Peace Housing Affordable Housing Project Peace River $7.0 Proposed for 2010 - 2011. Foundation

Park Place Communities Row Housing Complex, Schonsee Edmonton $7.5 Proposed

Perera Shawnee Ltd. 'Highbury Tower Residences' Calgary $40.5 On hold. Perera Development Group. Condominiums Phase 2

Perera Shawnee Ltd. 'Highbury Tower Residences' Calgary $32.0 On hold. Originally proposed for 2011 - 2013 Condominiums Phase 3

Pointe of View 'Rocky View Pointe' Condo Cochrane $25.0 Proposed Development Apartment Building

ProCura Real Estate 'Mayfair Village' Highrise Apartment Edmonton $56.5 2010-2011 Under construction. Clark Builders. Complex phase 1 (South Tower)

ProCura Real Estate 'Azure' Condo Complex Phase 1 Edmonton $6.5 Proposed. Services

ProCura Real Estate 'Mayfair Village' North (Second) Edmonton $100.0 Proposed. Clark Builders. Services Tower

Qualex - Landmark Group 'Luna' Condominium Apartment Calgary $50.0 2010-2011 Under construction. Intertech Construction Group. Building

Schizophrenia Society of 'Iris Court' Affordable Supportive Edmonton $5.1 On hold. Alberta Living Facility

Source Development 'Manchester Station' Condo Calgary $25.0 On hold. Corp. Apartments

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 53 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Statesman Group of 'Riverside Quays' Condominium Calgary $28.0 Proposed for 2012 - 2013. Companies Apartments Phase 5

Statesman Group of 'Riverside Quays' Condo Apartments Calgary $18.0 Proposed for 2012 - 2013. Planned start within a Companies and Townhouses Phase 4 year after completion Phase 3.

Statesman Group of 'Landings at Cougar Ridge' Calgary $30.0 2010-2012 Announced. Planned construction start spring 2011. Companies Townhouse Development

Streetside Development Townhouses and Condo Apartments Calgary $28.0 2011-2013 Under construction

Streetside Development 'Pefect Fit' CONDOMINIUM Calgary $12.5 Proposed. In redesign Corp. APARTMENT BUILDING

Streetside Developments 'Ginger Park' Townhouse Complex Calgary $6.8 Proposed (Buildings S,T,V,X,Y)

Swerve Living 'Swerve Living' Condominium Red Deer $9.5 Proposed. Pending funding. Building

Unity Builders Group 'Wilderness Ridge' Buildings A, B, Canmore $15.0 2010-2011 Completed C, D Rebuild after 2009 Fire

Urban Landmarks 'The Britnell' Apartments (Two Edmonton $20.5 On hold. Urban Landmarks. Buildings)

Valour Place Society 'Valour Place' APARTMENT Edmonton $10.0 Proposed HOUSING FOR MILITARY DURING REHABILITATION / TREATMENT

Westcorp Inc. 'London at Heritage Station' Calgary $200.0 2006- Under construction. Towers 1 and 2 completed. To Condominium Towers be built in five stages.

Wimco Properties Ltd. 'Elk Island View - Heron Place' Lamont $6.0 On hold. Wimco Construction Ltd. Project expected Condominium Apartment Building to start after Motel 6, pending improved market conditions.

Wimco Properties Ltd. 'Elk Island View - Swan Place' Lamont $6.0 On hold pending improved market conditions. Condominium Apartment Building

Wood Buffalo Housing 'Hawthorne Heights at Eagle Ridge' RM of Wood $45.0 2009-2011 Completed and Development Townhouses and Apartment Condos Buffalo (Fort Corporation McMurray)

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 54 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Wood Buffalo Housing 'Stony Mountain Plaza' Affordable RM of Wood $32.0 Proposed and Development Housing Project Buffalo (Fort Corporation (WBHDC) McMurray)

Woodfine Developments 'Fusion Plaza' Apartments Phase 1 Grande Prairie $45.0 On hold indefinitely.

Telecommunications

City of Grande Prairie Outdoor Wireless Network Initiative Grande Prairie $6.0 Proposed

TELUS 2011 NETWORK EXPANSION / across Alberta $650.0 2011 Announced. Fibreoptic lines and cellphone towers. ENHANCEMENT Tourism/Recreation

Alberta Infrastructure Renewal / Edmonton $147.0 Proposed. Bird Construction. Project re-design Expansion Phase 1 underway.

Alberta Tourism, Parks Parks Infrastructure Projects 2009- across Alberta $5.4 2009-2011 Completed and Recreation 2011

Argyll Velodrome Indoor Velodrome and Multi-Use Edmonton $32.0 Proposed for location by Peter Hemingway Pool Association Sports Facility

BCP Construction Hotel Blackfalds $7.5 Proposed

Bear Development Corp. Hotel Sylvan Lake $7.0 2010-2011 Completed

Bearspaw - Glendale SPORTS FACILITY Rocky View $6.0 Proposed for 2011 - 2012. Phased development. Community Association County (Bearspaw)

Calgary Exhibition and 'Western Event Centre' Agriculture Calgary $65.0 Proposed for 2012 - 2014. Part of Stampede Park Stampede Arena and Exhibit Hall $400M expansion.

Calgary Science Centre New 'Telus World of Science Calgary $69.8 2009-2011 Under construction. Cana Construction. Location Calgary' Science Centre near .

Calgary Winter Club PHASE 1 - ADDITION Calgary $14.0 2011-2012 Under construction. Chandos Construction.

Calgary Zoo 'Antarctic Landing' Penguin Exhibit Calgary $24.5 2010-2011 Nearing completion. Ledcor Construction.

Cantos Music Foundation King Edward Hotel Redevelopment Calgary $125.0 Proposed. Museum, recording studio and music and Cantos at the King Eddy centre. National Music Centre

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 55 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Carlson Hotels Radisson Calgary Airport East Hotel Calgary $19.0 2011-2012 Announced. Anticpated construction start spring and Conference Centre, near 2011. Calgary Airport

Chateau Inn Ltd. Best Western Hotel Sylvan Lake $10.0 2010-2011 Nearing completion

Chinatown and Little Italy MUSEUM AND CULTURAL Edmonton $6.0 Proposed Business Association HERITAGE CENTRE

City of Airdrie Genesis Place Phase 3 (Twin Ice Airdrie $18.0 Proposed Arena, Meeting and Multi-Use Space)

City of Calgary Devonian Gardens Renovation Calgary $14.5 Proposed. Project will be completed as a Phase 2 continuation of Phase 1.

City of Calgary Brighton Athletic Park (four soccer Calgary $8.0 Proposed. Part of city's ten - year infrastructure plan fields) (2008 - 2017)

City of Calgary Development of Lynnview Ridge as Calgary $22.0 Proposed Parkland, Golf Course

City of Calgary Centennial Arena Expansion Calgary $17.0 2010-2011 Completed. Cana Construction.

City of Calgary / Calgary 'Fields for Life' Artificial Turf Soccer Calgary $13.0 Proposed. Fundraising underway. Soccer Federation Fields

City of Calgary / Seton Recreation Centre, Seton Calgary $70.0 Proposed Sport Recreation Culture and Wellness Society

City of Calgary / South South Fish Creek Recreation Centre Calgary $21.0 2010-2011 Under construction. Chandos Construction. Fish Creek Recreation Expansion (Two Ice Surfaces) Association

City of Calgary / YMCA / Genesis Centre of Community Calgary $66.0 2009-2011 Under construction. Stuart Olson Constructors. Martindale Community Wellness Association / United Way / Genesis Land Development Corp.

City of Cold Lake Community Event Centre Phase 1 at Cold Lake $15.3 2010-2012 Under construction. Scott Builders. Stage 1 is the the Energy Centre hockey rink. Stages 2 / 3 second hockey rink and additional facilities. Estimated cost phases 1 and 2 range $20M to $25M.

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 56 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks City of Cold Lake COLD LAKE ENERGY CENTRE Cold Lake $20.0 2010-2012 Under construction. Scott Builders. PHASE 2 (COMMUNITY EVENT CENTRE)

City of Edmonton Recreation Centre / Library, Edmonton $80.0 Proposed for 2011-2013. Meadows

City of Edmonton Multi - Purpose Facility, Clareview Edmonton $90.0 Proposed. Renovation / expansion of Clareview Twin Arenas, plus new library, Catholic high school.

City of Edmonton Outdoor Pool, Kinsmen Park Edmonton $5.5 2009-2011 Nearing completion. Jen - Col Construction. (Replacement for )

City of Edmonton North Centre Community Recreation Edmonton $95.0 2009-2012 Under construction. Clark Builders. Field house Centre, completed.

City of Edmonton 'Polar Extremes Arctic Shores' Sea Edmonton $15.0 2010-2011 Under construction. PCL Construction. Mammals (Pinniped) Exhibit, Valley Zoo

City of Entrance and Wander Edmonton $35.0 2011-2012 Announced. Planned construction start August Path Project 2011.

City of Fort Saskatchewan JUBILEE RECREATION CENTRE Fort $7.0 Proposed. To be undertaken after Sportsplex RENOVATIONS Saskatchewan renovations.

City of Grande Prairie Dave Barr Arena Expansion Grande Prairie $14.0 on hold

City of Grande Prairie Aquatics and Wellness Multiplex Grande Prairie $98.2 2009-2011 Under construction. Wright Construction Western Inc. Part of the Community Knowledge Campus.

City of Grande Prairie Prairie Art Gallery Restoration Grande Prairie $10.0 2010-2011 Under construction. Chandos Construction.

City of Lethbridge Two Sheet Ice Arena, West Lethbridge $19.0 Proposed for 2011 - 2012. Tender call general Lethbridge contractor possible spring 2011.

City of Lethbridge North Lethbridge Regional Park Lethbridge $15.0 Proposed for completion by 2017. Estimated cost range $15M to $20M.

City of Lethbridge Community Arts Centre Lethbridge $12.6 Proposed for 2012. Tenders close April 7.

City of Lethbridge ENMAX Centre Renovations / Lethbridge $33.7 2009-2012 Under construction. Ward Bros Construction. Expansion

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 57 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks City of Medicine Hat Regional Event Centre, Box Springs Medicine Hat $89.8 On hold. Business Park

City of Red Deer Rotary Recreation Park Phase 2 Red Deer $23.0 Proposed for 2011 - 2012. Conversion of current museum to accommodate the Golden Circle Seniors Centre.

City of St. Albert Redevelopment Red Willow Park St. Albert $11.0 On hold West

City of St. Albert Riel Park Reclamation Phase 2 St. Albert $8.5 2010-2011 Nearing completion

City of Wetaskiwin / Aquatic Facility Wetaskiwin $18.6 Proposed County of Wetaskiwin

Clearwater County Multi - Use Trail Clearwater $6.8 Proposed County (Rocky Mtn House to )

County of Grande Prairie Regional Sportsplex (Twin Ice Arena County of $26.0 2011-2012 Announced. Kaldon Construction. and Soccer Pitch) Grande Prairie (Clairmont)

Dolemo Developments 'Edworthy Club' Health Club Calgary $1,000.0 Proposed. Spa, squash courts, hockey rinks, movie theatre and condo hotel.

Dub Architects Ltd. Redevelopment of Alberta Hotel Edmonton $15.0 2009-2011 Nearing completion

Edmonton Korean Multicultural Centre, Ellerslie Edmonton $8.4 Proposed Community Centre Foundation

Edmonton Minor Soccer Soccer Facility (27 to 29 Playing Parkland County $6.0 Proposed to start construction 2012. Phased Association Fields) project over several years.

Edmonton Volleyball GO Community Centre Court Sports Edmonton $36.0 2010-2011 Under construction. Clark Builders. Centre / Edmonton Grads Complex Basketball Centre / Ortona Gymnastics Club

Fort Edmonton 'Spirit of the ' Aboriginal Edmonton $15.0 Proposed. Foundation Village, Park

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 58 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Fort Edmonton Historical Renovations / Edmonton $13.9 2010-2011 Under construction. PCL Construction. Foundation Revitalization (Capitol Theatre)

Hilton Hotels Homewood Suites Extended Stay Calgary $36.3 2010-2012 Under construction. Chamberlain Construction Hotel Services.

Innoka Point Resort Corp. Innoka Resort Canmore $15.0 2010-2012 Under construction. Phased development (five buildings).

Louis Bull Tribe Casino Wetaskiwin $12.0 Proposed. Pending approvals. County

Marmot Basin New High Speed Ski Lift (Paradise Jasper National $7.0 2011 Announced Express) and Relocation of Paradise Park Triple Chair

Marriott Hotels Marriott Calgary Airport Calgary $21.8 2010-2011 Completed. Graham Construction.

Marriott Hotels and Marriott Hotel RM of Wood $20.0 Proposed Resorts Buffalo (Fort McMurray)

Mayfield Hospitality Hotel and Convention Centre Medicine Hat $25.0 Proposed. Contingent on Regional Event Centre.

MD of Foothills / Dunbow Indoor Arena next to Heritage MD of Foothills $5.8 Proposed Recreation Board Heights School

Parks Canada Infrastructure Upgrades Banff National $9.7 Proposed. Projects include Cave and Basin parking Park lot, roadwork in Banff, washrooms at C&B and Johnston Canyon, improvements to Banff Museum exterior, Sulphur Mtn boardwalk repairs.

Parks Canada Cave and Basin National Historic Banff National $13.8 2010-2012 Announced. Site Renovations Park (Banff)

Parks Canada Waterton Lakes National Park Waterton Lakes $9.4 2009-2011 Under construction Upgrades and Repairs National Park

Parks Foundation Calgary Perimeter Pathway System (Beltway) Calgary $50.0 2010- Under construction. Multi-year project.

Pipestone Creek 'River of Death and Discovery' Wembley $26.4 2011-2012 Announced. Expected RFP for general contractor Dinosaur Bed Project Dinosaur Centre early spring 2011. Committee

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 59 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Platinum Investments Inc. Marriott Courtyard Hotel, Edmonton Edmonton $7.5 2010-2011 Completed West

Pomeroy Inn & Suites / Hotel at Olds College (Part of Olds $12.0 Proposed for 2011 - 2012. Olds College Canadian Institute for Rural Entrepreneurship)

Pumphouse Theatre Theatre Expansion Phase 1 Calgary $10.5 On hold

Red Deer Curling Club Building Renovation Red Deer $5.6 2011 Under construction

Regional Municipality of 2011 PARKS PROJECTS RM of Wood $22.0 2011 Announced Wood Buffalo Buffalo

Regional Municipality of Anzac Leisure Facility RM of Wood $24.0 Proposed. Possible construction start spring 2011. Wood Buffalo Buffalo (Anzac)

Regional Municipality of Performing Arts Centre, MacDonald RM of Wood $10.0 Proposed. Feasibility study to be done. Wood Buffalo Island Park Buffalo (Fort McMurray)

Regional Municipality of Athletic Field, Timberlea High RM of Wood $15.0 2011-2012 Under construction. Wilco Contractors NW. Wood Buffalo School Site Buffalo (Ft McMurray)

River Valley Alliance Valley Devon to Fort $110.0 Proposed Trail Phase 1 Saskatchewan

Royal Canadian Legion, New Legion Building Edmonton $8.7 2010-2011 Nearing completion. PCL Construction. Branch #175

Strathcona County Recreation Complex Addition / Strathcona $17.1 2010-2011 Completed. Delnor Construction. Renovation County (Ardrossan)

Strathcona County Broadmoor Golf Club Addition / Strathcona $5.1 2010-2011 Under construction. Atkinson Construction. Modernization County (Sherwood Park)

Strathcona County Millennium Place Expansion Strathcona $8.4 2010-2011 Under construction. Delnor Construction. County (Sherwood Park)

Temple REIT Refurbishment of Capri Centre as Red Deer $8.0 2011 Announced Sheraton Hotel

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 60 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks The Friends of Medalta Medalta Site Restoration, Historic Medicine Hat $7.5 2009-2011 Under construction Society Clay District

The Titan Entertainment 'The Titan Project' Entertainment Rocky View $40.0 Proposed for completion in late 2011 or early 2012. Group Inc. Venue County (Balzac)

Town of Banff Recreation Centre Redevelopment Banff $31.0 2009-2011 Completed. Stuart Olson Dominion Construction. Phases 1 and 2

Town of Beaumont Centre Communautaire Beaumont Beaumont $6.2 Proposed. Project has been placed in the Town's Community Centre (CCBCC) 10-year capital plan.

Town of Beaverlodge New Indoor Pool / Community Centre Beaverlodge $11.6 2010-2012 Under construction.

Town of Blackfalds Fieldhouse (Recreation Facility) Blackfalds $8.0 Proposed. Pending funding.

Town of Canmore Multiplex Canmore $31.4 2011-2012 Announced. Graham Construction and Engineering. Will include library, daycare, aquatics facility, climbing wall, retail space, administration space and community space.

Town of Cochrane New Aquatic Facility Cochrane $26.0 Proposed. Feasibility study completed.

Town of Drumheller Badlands Community (Multi - Use) Drumheller $14.0 2010-2011 Under construction. Dawson Wallace Construction. Facility Phase 1

Town of Grande Cache Recreation Centre Expansion / Grande Cache $19.8 2009-2011 Completed. Chandos Construction. Revitalization

Town of Grimshaw Community Multiplex Grimshaw $16.0 2010-2011 Nearing completion. Cormode & Dickson Construction. Arena, fitness centre, walking track and field house.

Town of High River New Recreation Facility High River $20.0 Proposed. No construction expected in 2011.

Town of Mayerthorpe Hockey Arena (Exhibition Centre) Mayerthorpe $5.2 2010-2011 Nearing completion. Chandos Construction.

Town of Morinville Community Cultural Centre Morinville $11.0 2010-2011 Nearing completion. PCL Construction.

Town of Slave Lake Arctic Ice Centre Upgrades and Slave Lake $11.9 2010-2011 Under construction. Jen-Col Construction. Fieldhouse

Town of Westlock / Westlock 'Spirit Centre' Sports Westlock $12.6 2010-2011 Under construction. Brenex Construction. Westlock County Complex

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 61 Project Sector/ Project Project Cost in Construction Company Name Description Location $ Millions Schedule Remarks Trestle Creek Golf Resort RV Resort, Recreation Centre, Parkland County $30.0 Proposed for 2010 - 2014. Construction schedule is Equine Centre, Sports Park and 27 for golf course. First nine hole to be completed for Hole Golf Course play in summer 2011.

United Horsemen of Horse Racing Complex Phase 1 Rocky View $35.0 Proposed for 2011 - 2012. Alberta County (near Balzac)

Village of Standard / New Community Hall Wheatland $6.0 Proposed construction start spring 2011. Standard Community Hall County Fundraising underway. Association (Standard)

Winsport Canada Canada Olympic Park Facility Calgary $322.0 2007-2011 Under construction. Cana Construction. Freestyle Expansion and Upgrade ski area completed. Athletic and ice complex.

Winsport Canada Olympic Oval Roof Restoration Calgary $8.0 2011 Announced

April 01, 2011 Alberta Finance and Enterprise New projects are shown in upper case in the Project Description column 62

Alberta Finance and Enterprise You can access the Inventory of Major Alberta Projects and the following related 4th Floor Commerce Place department publications on the Internet at: 10155-102 Street http://albertacanada.com/about-alberta/statistics-and-publications.html : Edmonton, AB T5J 4L6 Canada ♦ Alberta Oil Sands Industry Quarterly Update ♦ Monthly Economic Review Telephone: 780.427.6787 ♦ Highlights of the Alberta Economy Fax: 780.422.0061 ♦ Facts on Alberta ♦ Place-to-Place Price Comparison Survey Website:www.albertacanada.com

© 2011 Government of Alberta

ISSN: 1702-2851 ISSN: 1718-1399 (pdf)

Printed in Canada