AMENDMENT IN THE ENVIRONMENTAL CLEARANCE FOR THE PROPOSED CONSTRUCTION OF RESIDENTIAL COMPLEX FORM I

FORMI

I. BASIC INFORMATION

S. No Item Details 1. Name of the project/s Amendment in the Environmental Clearance for the proposed construction of Residential development at Adayalambattu Villlage, Taluk, Thiruvallur District. 2. S.No. in the schedule The project is categorized under Schedule 8 (b) “Township & Area Development projects” of EIA Notification 2006 and its subsequent amendment 3. Proposed capacity / EC obtained Built-up area is 1,61964.85 area/length/tonnage to be Sq.m. handled/command area/lease Built up area for EC Amendment area/number of wells to be drilled requested is 1,60,922 sq.m 4. New/Expansion/Modernization New (Amendment in EC) 5. Existing Capacity/ Area etc. Existing Built up area is 1,61964.85 Sq.m. 6. Category of Project i.e. ‘A’ or ‘B’ Category B1 7. Dose it attract the general No condition? If yes, please specify. 8. Dose it attract the specific condition? Not Applicable If yes, please specify. 9. Location Plot/Survey/ Khasra. No 4, 5, 6, 7, 13, 14, 15, 73/1B and 73/1C Village Adayalambattu Taluk District Thiruvallur State Tamil Nadu 10. Nearest railway station/airport along Railway Station with distance in Km. Metro Station–3.74 km(E) Airport International Airport –9.25 km (S) 11. Nearest town, city, district Maduravoyal– 1.12 km (SE) headquarters along with distance in Km. 12. Village Panchayats, Zillaparished, Corporation of Chennai municipal corporation, local Address: 1131, EVR Periyar Salai, Park body(complete postal address with Town, , Chennai - 600 003 telephone nos. to be given) Telephone No: 044 25619555 13. Name of the applicant M/s.KG Foundation Private Limited 14. Registered address Marble Arch, Ground Floor, No.5, Bishop Wallers Avenue (East), ,Chennai- 600 004

a 2019 AMENDMENT IN THE ENVIRONMENTAL CLEARANCE FOR THE PROPOSED CONSTRUCTION OF RESIDENTIAL COMPLEX FORM I

15. Address for correspondence Name Mr. Haresh Kishor Designation (Owner/Partner/CEO) Director Address Marble Arch,Ground Floor, No.5, Bishop Wallers Avenue (East), Mylapore, Chennai- Pin Code 600 004 E-Mail [email protected] Telephone/ Mobile No 91 44 2499 9999 Fax No 91 44 2499 7577 16. Details of Alternative Sites No alternative sites examined Examined, if any, location of these sites should be shown on a topo sheet. 17. Interlinked Projects Not Applicable 18. Whether separate application of Not Applicable interlinked project has been submitted? 19. If yes, date of submission Not Applicable 20. If no, reason Not Applicable 21. Whether the proposal involves Not Applicable approval / Clearance under the following acts: if yes, details of the same and their status to be given. (a)The Forest (Conservation) Act, 1980? (b)The Wildlife (Protection) Act, 1972? (c)The C.R.Z Notification, 1991? 22. Whether there is any government No order/ Police relevant/ relating to the site? 23. Forest land involved (hectares) No 24. Whether there is any litigation pending No against the land/ or land in which the Project is proposed to be set up? (a) Name of the Court (b) Case No. (c) Order/ directions of the Court, if any And its relevance with the proposed Project

(I) ACTIVITY 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, and the like)

b 2019 AMENDMENT IN THE ENVIRONMENTAL CLEARANCE FOR THE PROPOSED CONSTRUCTION OF RESIDENTIAL COMPLEX FORM I

Details thereof (with Information/Checklist approximate quantities /rates, S.No. Yes/No confirmation wherever possible) with source of information data 1.1 Permanent or temporary No There will not be any change in the change in land use, land cover land use, land cover or topography or topography including as the site is categorized as Primary increase intensity of land use Residential use by Chennai (with respect to local land use Metropolitan Development Authority plan) (CMDA). 1.2 Clearance of existing land, No Not required vegetation and Buildings? 1.3 Creation of new land uses? No Not required 1.4 Pre-construction investigations Yes Geo technical investigation has been e.g. Bore Houses, Soil testing? done to find the suitability of soil for providing of adequate foundations for the proposed structure. The geotechnical investigation report is enclosed as Annexure X. 1.5 Construction works? Yes Construction of various buildings will be done systematically, with economy of materials and with due care on environmental protection. 1.6 Demolition works? No No demolition works will be carried out as the land is vacant. 1.7 Temporary sites used for Yes Inside the proposed site, a small construction works or housing area will be utilized temporarily for of construction workers? construction of sheds for the workers and materials. Water supply and sanitation facilities will be provided for them. Mostly workers will be deployed from local area only. 1.8 Above ground buildings, Yes Excavation works will be carried out structures or earthworks for foundation of the structures. including linear structures, cut Later on, the cut and fill process will and fill or excavations be required to the minimum extent for leveling. 1.9 Underground works mining or No No underground works will be tunneling? required as the proposed project is the construction of Residential buildings including commercial activities. 1.10 Reclamation works? No Only levelling of ground if required. 1.11 Dredging? No No need for dredging 1.12 Off shore structures? No Not required 1.13 Production and manufacturing No It’s a construction project. Hence processes? not applicable

c 2019 AMENDMENT IN THE ENVIRONMENTAL CLEARANCE FOR THE PROPOSED CONSTRUCTION OF RESIDENTIAL COMPLEX FORM I

1.14 Facilities for storage of goods No Temporary sheds will be or materials? constructed for the storage of cement, sand and other materials during construction phase. 1.15 Facilities for treatment or Yes Sewage generated shall be treated disposal of solid waste or liquid through STP of capacity 980 KLD effluents? and the treated sewage can be utilized for flushing and greenbelt development and excess will be disposed through STP. Biodegradable waste will be treated through Organic Waste Converter (OWC).Non-Biodegradable and inert waste will be collected and handed over to Authorized Recyclers. 1.16 Facilities for long term housing No There is no residential facility for of operational workers? operational workers as they will be deployed from local area. 1.17 New road, rail or sea traffic No The existing transportation during Construction or infrastructure will be made use operation? during construction and operational phase. 1.18 New road, rail, air, waterborne No The existing infrastructure would be or other transport adequate. infrastructure including new or altered routes and stations, ports, airports etc? 1.19 Closure or diversion of existing No As construction works will be within transport routes or a specified area, there is no need infrastructure leading to for closure or diversion of existing changes in Traffic movements? transport routes. The existing transport infrastructure will be made use of. 1.20 New or diverted transmission No Not envisaged lines or pipelines? 1.21 Impoundment, damming, No Not envisaged culverting, realignment or other changes to the hydrology of watercourses or aquifers? 1.22 Stream crossings? No No Stream crossings 1.23 Abstraction or transfers of No No Ground water shall be water form ground or surface abstracted. waters? 1.24 Changes in water bodies or No Rain water from within the proposed land surface affecting drainage development shall be properly or runoff? collected and routed to the rain water harvesting trenches along the boundary and the overflow will be

d 2019 AMENDMENT IN THE ENVIRONMENTAL CLEARANCE FOR THE PROPOSED CONSTRUCTION OF RESIDENTIAL COMPLEX FORM I

collected in the exclusive sumps to be provided for collection of rain water. Excess water will be discharged accordingly. 1.25 Transport of personnel or Yes Transport of personnel or materials for construction, construction materials during operation or decommissioning? construction phase will be through existing roads. 1.26 Long-term dismantling or No No long term works involved in the decommissioning or restoration proposed activity works? 1.27 Ongoing activity during No Only temporary thatched sheds will decommissioning which could be built for storing cement and have an impact on the other materials. So there will be no environment? decommissioning works. 1.28 Influx of people to an area Yes During construction period workers either temporarily or will be deployed locally permanently? 1.29 Introduction of alien species? No No such alien species are envisaged

1.30 Loss of native species or No No loss of native species will occur genetic diversity? as the site is plain 1.31 Any other actions? No Only eco-friendly activities like tree plantation will be undertaken

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply) Details thereof (with S. Information/Checklist approximate quantities /rates, Yes/No No. confirmation wherever possible) with source of information data 2.1 Land especially undeveloped or No There is no agricultural land. agricultural land (ha) 2.2 Water (expected source & Yes Total water Requirement 1020 KLD competing users) unit: KLD of which recycled water for flushing (345 KLD) and Green belt development (28 KLD) Excess Treated Sewage 497 KLD will be disposed to Nesapakkam STP. Fresh water requirement of 674 KLD shall be met through tanker lorries. 2.3 Minerals (MT) No Since the proposed project is the construction of Residential buildings there will be no usage of minerals 2.4 Construction material - stone, Yes Cement - 9,000bags aggregates, sand/soil Steel - 120 MT Sand - 7,000 cum

e 2019 AMENDMENT IN THE ENVIRONMENTAL CLEARANCE FOR THE PROPOSED CONSTRUCTION OF RESIDENTIAL COMPLEX FORM I

(expected source - MT) Brick - 1,00,000 Nos.

2.5 Forests and timber (source - No Usage of timber will be minimal MT) 2.6 Energy including electricity and Yes 12 MW Electricity will be availed fuels (source, competing users) from TANGEDCO. Unit: fuel (MT), energy (MW)

2.7 Any other natural resources No Not envisaged (use appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health Details thereof (with S. Information/Checklist approximate quantities /rates, Yes/No No. confirmation wherever possible) with source of information data 3.1 Use of substances or materials, No No such materials will be required which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies) 3.2 Changes in occurrence of No There will not be any occurrence of disease or affect disease diseases as our activities are vectors (e.g. insect or water confined to construction areas only borne diseases) 3.3 Affect the welfare of people No Employment will be given to local e.g. by changing living people thus the living standards of conditions? the people will get improved. 3.4 Vulnerable groups of people No There is no vulnerable group of who could be affected by the people who could be affected by the project e.g. hospital patients, project. children, the elderly etc., 3.5 Any other causes No Nil

4. Production of solid wastes during construction or operation or decommissioning (MT/month) Details thereof (with S. Information/Checklist approximate quantities /rates, Yes/No No. confirmation wherever possible) with source of information data 4.1 Spoil, overburden or mine No No Spoil, overburden or mine wastes wastes

f 2019 AMENDMENT IN THE ENVIRONMENTAL CLEARANCE FOR THE PROPOSED CONSTRUCTION OF RESIDENTIAL COMPLEX FORM I

4.2 Municipal waste (domestic and Yes The quantity of municipal solid or commercial wastes) waste generated from the proposed Residential Complex will be 3,885.58 kg/day 4.3 Hazardous wastes (as per No No hazardous wastes shall be Hazardous Waste Management generated Rules) 4.4 Other industrial process wastes No Not envisaged 4.5 Surplus product No Not envisaged 4.6 Sewage sludge or other sludge No STP sludge of 118 kg/day will be from effluent treatment used as manure for greenbelt development. 4.7 Construction or demolition Yes Construction waste will be used in wastes land filling and in road pavements in the surrounding low lying areas. 4.8 Redundant machinery or No Most of the equipments used during equipment construction phase will be hired 4.9 Contaminated soils or other No There is no source for contamination materials of soils or other materials 4.10 Agricultural wastes No Does not arise 4.11 Other solid wastes No No such waste

5. Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)

Details thereof (with S. Information/Checklist approximate quantities /rates, Yes/No No. confirmation wherever possible) with source of information data 5.1 Emissions from combustion of Yes The gaseous emissions are expected fossil fuels from stationary or from transport vehicles moving mobile sources inside the project site. The emissions are expected from Diesel Generator during operation phase. 5.2 Emissions from production No Does not arise since the proposed processes project is a Residential Development 5.3 Emissions from materials Yes Emissions like dust will arise during handling including storage or the transportation of materials and transport the dust will be controlled by slow movement of vehicles, covering the materials properly and by water spraying 5.4 Emissions from construction No Maximum construction works will be activities including plant and done with well-maintained equipment equipments. 5.5 Dust or odours from handling Yes Construction activities may lead to of materials including temporary increase in PM levels. construction materials, sewage Dust covers will be provided on and waste trucks that would be used for

g 2019 AMENDMENT IN THE ENVIRONMENTAL CLEARANCE FOR THE PROPOSED CONSTRUCTION OF RESIDENTIAL COMPLEX FORM I

transportation of materials prone to fugitive dust emission, Water sprinkling on road and new construction areas will be done at regular intervals to reduce spreading of dust particles. 5.6 Emissions from incineration of No There is no incineration activities waste 5.7 Emissions from burning of No No such activities will be permitted waste in open air (e.g. slash materials, construction debris) 5.8 Emissions from any other No No emissions from any other sources sources

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Details thereof (with S. Information/Checklist approximate quantities /rates, Yes/No No. confirmation wherever possible) with source of information data 6.1 From operation of equipment Yes Workers will be given ear plugs in e.g. engines, ventilation plant, noisy area. Acoustic enclosures will crushers be provided for the D.G. set 6.2 From industrial or similar No Not Applicable processes

6.3 From construction or Yes Noise levels in the range of 75-85 demolition dB (A) will be generated occasionally during the construction activities. Workers in the noisy areas will be provided with earmuffs and earplugs. 6.4 From blasting or piling No Not applicable 6.5 From construction or Yes During construction phase operational traffic construction materials will be transported by road, through well maintained vehicles to control noise, vibration and emissions. During operational phase traffic noise and emissions will be increased slightly that will be minimized by paving roads with asphalt/concrete, well maintained vehicles, slow movement of vehicles and by planting trees 6.6 From lighting or cooling No Not Applicable systems 6.7 From any other sources No Not Applicable

h 2019 AMENDMENT IN THE ENVIRONMENTAL CLEARANCE FOR THE PROPOSED CONSTRUCTION OF RESIDENTIAL COMPLEX FORM I

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: Details thereof (with S. Information/Checklist approximate quantities /rates, Yes/No No. confirmation wherever possible) with source of information data 7.1 From handling, storage, use or No There will be no handling of spillage of hazardous materials hazardous materials. 7.2 From discharge of sewage or No Sewage will be treated in STP of other effluents to water or the capacity 980KL. The treated sewage land (expected mode and place generated will be reused for flushing of discharge) and greenbelt development. Excess treated sewage will be discharged into the Nesapakkam STP. 7.3 By deposition of pollutants Yes Emissions from operation of DG emitted to air into the land or Sets will be within the prescribed into water limits and negligible. 7.4 From any other sources No Not envisaged 7.5 Is there a risk of long term No There will not be any long term buildup of pollutants in the buildup of pollutants in the environment from these environment from these sources sources?

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment Details thereof (with S. Information/Checklist approximate quantities /rates, Yes/No No. confirmation wherever possible) with source of information data 8.1 From explosions, spillages, No Not envisaged fires etc from storage, handling, use or production of hazardous substances 8.2 From any other causes No Not envisaged 8.3 Could the project be affected No The area under study falls in Zone- by natural disasters causing III (Moderate) according to the environmental damage (e.g., Indian Standard Seismic Zoning floods, earthquakes, landslides, Map. The structure was designed to cloudburst etc)? be earthquake resistant. There will not be any long term buildup of pollutants in the environment from these sources

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality

i 2019 AMENDMENT IN THE ENVIRONMENTAL CLEARANCE FOR THE PROPOSED CONSTRUCTION OF RESIDENTIAL COMPLEX FORM I

Details thereof (with S. Information/Checklist approximate quantities /rates, Yes/No No. confirmation wherever possible) with source of information data 9.1 Lead to development of Yes Supporting and ancillary supporting. Utilities, ancillary development will take place which in development or development turn will improve environment. stimulated by the project which (e.g.,) Plantation of trees, rainwater could have impact on the harvesting, and Storm water drains environment e.g. Supporting etc., Basic infrastructure will be infrastructure (roads, power developed in the proposed area. supply, waste or waste water treatment, etc.) Housing development Residential Apartment will be constructed Extractive industry No Extraction Supply industry No Industrial activity 9.2 Lead to after-use of the site, No Not Applicable which could have an impact on the environment 9.3 Set a precedent for later Yes Towards an organized urban developments developmental activity 9.4 Have cumulative effects due to No Not envisaged proximity to other existing or planned projects with similar effects

(II) Environmental Sensitivity

Aerial distance S. Name/ (within 15 km.) Areas No. Identity Proposed project location boundary 1. Areas protected under NIL - international conventions, national or local legislation for their ecological, landscape, cultural or other related value 2. Areas which are important or National Park 9.75 km (SE) sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests

3. Areas used by protected, No No significant important or sensitive species of species flora or fauna for breeding, nesting, foraging, resting, over

j 2019 AMENDMENT IN THE ENVIRONMENTAL CLEARANCE FOR THE PROPOSED CONSTRUCTION OF RESIDENTIAL COMPLEX FORM I

wintering, migration 4. Inland, coastal, marine or 0.85km (S) underground waters Thiruverkkadu Lake 2.78 km (SSW) Ambattur Eri 3.45 km (NNE) Lake 4.22 km (NNW) Eri 5.46 km (NNE) 6.05 km(SE) 5. State, National boundaries No Not Applicable 6. Routes or facilities used by the No Not Applicable public for access to recreation or other tourist, pilgrim areas 7. Defense installations No NIL within 10 km radius 8. Densely populated or built-up The site is located area within the Chennai --- Metropolitan City 9. Areas occupied by sensitive man-  Ravina Hospital 1.05 km (SE) made land uses (hospitals,  Urban Health Training 0.7 km (S) schools, places of worship, Centre community  Kavin Hospital 1.36 km (SW)

10. Areas containing important, high NIL --- quality or scarce resources (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11. Areas already subjected to Not applicable --- pollution or environmental damage. (those where existing legal environmental standards are exceeded) 12. Areas susceptible to natural The area under study --- hazard which could cause the falls in Zone-III, project to present environmental according to the Indian problems (earthquakes, Standard Seismic Zoning subsidence, landslides, erosion, Map. flooding or extreme or adverse climatic conditions)

k 2019 AMENDMENT IN THE ENVIRONMENTAL CLEARANCE FOR THE PROPOSED CONSTRUCTION OF RESIDENTIAL COMPLEX FORM I

“I hereby given undertaking that data and information given in the application and enclosures are true to the best of the knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.”

DATE: 00.00.2019 PLACE: CHENNAI

SIGNATURE OF THE APPLICANT WITH SEAL

NAME : MR. HARESH KISHOR DESIGNATION : DIRECTOR ADDRESS : KG Foundation Private Limited Marble Arch, Ground Floor, No.5, Bishop Wallers Avenue (East), Mylapore, Chennai-600 004.

l 2019