1 Namami Gange - Component wise Allocation

“Namami Gange – Integrated Conservation Mission” approved by Cabinet on 13/05/2015 With an outlay of ₹ 20,000 Cr upto Dec 2020 Component A Ongoing projects having remaining central liabilities of Rs.7,272 crore

This includes 33 sewerage Projects (630 MLD STP) and 24 Ghats &Crematoria projects. Component B

New initiatives at an estimated cost of Rs.12,728 crore with 100% central assistance

This includes 102 sewerage Projects (3256 MLD STP) and 37 Ghats &Crematoria projects.

2 Salient Features

100% Centrally funded programme Hybrid O&M cost Annuity for 15 years based PPP included for model new adopted projects NAMAMI GANGE

5 year Comprehen dedicated sive Budget integrated allocation programme

Non- lapsable fund

3 Namami Gange Projects Overview

Sl Sanction Cost Projects Undertaken No. of Projects No (Rs in Cr) Pollution Abatement Projects Sewage Infrastructure (94 on Ganga, 8 on 1 102 16984 tributaries) 2 Bioremediation 8 26.94 3 Modular STPs –Decentralised Treatment 20 410 Upcoming Projects on Tributaries (7 states, 31 4 68 Under estimation tributaries, 68 towns) Sub total 198 17420.94 5 Rural Sanitation (4465 villages along Ganga) 1 1018 Total 199 18438.94

4 Namami Gange Projects Overview Sanction Cost Sl No Projects Undertaken No. of Projects (Rs in Cr) River Front, Ghats & Crematoria Projects 1 Ghats & Crematoria (Old) 24 204.39 2 Ghats & Crematoria (New) 37 721.94 3 Ghats Cleaning 1 15.00 4 River Surface Cleaning 1 55.24 5 River Front Development 2 270.55 Sub-total 65 1267.12 Other Projects 6 Institutional Development 6 340.41 Project Implementation Support / Research & 7 2 9.96 Study Projects 8 Biodiversity 4 31.91 9 Afforestation 11 113.28 10 Composite Ecological Task Force 1 167 Sub-total 24 662.56 Grand Total 288 20368.62 5 Status of Sewerage Projects

Status as on May 2014 Status as on May 2018 Under Tendering Process Tender S. Work- State STP Receive No. STP Under Tender Projec Comple in- Tender Complet Work-in- Capacit d & Under Projects Capacity Tenderin to be ts ted Progre to be ed progress y Finaliza Tendering (MLD) g floated ss floated (MLD) tion in process Ganga Main stem 1 10 24 1 9 - - 31 156 13 18 0 0 0 Uttar 2 12 334 - 7 3 2 27 743.5 8 8 1 10 0 Pradesh 3 4 55 - 4 19 529 - 10 3 0 6 4 1 12 - 0 1 0 2 16 - 2 0 - - 5 4 60 - 3 1 15 483.5 2 4 - 4 5 Sub Total 31 485 1 (18) 23 5 2 94 1928 23 42 4 14 11 Tributaries 6 Haryana 2 145 - 2 2 145 1 1 - - - 7 - - - 2 1044 - 1 - 1 - 8 U.P - - - 3 130.5 - 1 2 - - 9 Bihar - - - 1 9 - - 1 - - Sub Total 2 145 0 2 0 0 8 1328.5 1 3 3 1 -

Total 33 630 1 (18) 25 5 2 102 3256 24 45 7 15 611 Initiatives taken up by NMCG

. “One City One Operator” - STPs in 7 towns (Kanpur, , , Patna, , -Bally, Bhagalpur) are being integrated & tendered with Hybrid Annuity based projects – 4 already tendered during this period (Kanpur, Allahabad, Mathura & Kolkata) . Focus on 10 major towns contributing almost 64% of total sewage discharge. . Total STP capacity- 1109 MLD is being created at a cost of ₹ 9883 Cr in these towns . Performance evaluation of existing STPs completed in Uttarakhand, Uttar Pradesh and Bihar. . Project Engineers for and projects appointed by NMCG . Annual inspection of GPIs through technical institutions in a time bound manner. . Close monitoring of milestones. Field visits increased. . Regular Follow-up with State Agencies . Upcoming projects on tributaries- 68 towns in 7 states on 31 tributaries

7 Focus on Large Cities of Ganga Main Stem

10 towns with a total sewage generation of 1897 Mld contribute almost 64% of total sewage (2953 Mld) discharge from the 97 towns to river Ganga

700 All figures are in Mld

600 26

500 30 15

400

615 300 72 589 150 310 457 456 200 310 320 270 234 100 82 200 150 160 102 45 40 63 65 45 35 60 41 0 Haridwar Kanpur Allahabad Varanasi Farrukhabad Patna Bhagalpur Kolkata Howrah Bally

8 Sewage Generation (2035) Existing Treatment Capacity (Mld) Ongoing Projects Under Tendering Approved Projects Status of Hybrid Annuity Sewerage Projects . Awarded projects: Project Signing of Agreement Start of work 82 MLD STP at Haridwar 11/10/2017 01/02/2018 50 MLD STP at Varanasi 11/10/2017 01/02/2018 Contract Signing

Progress of Works

9 Status of other Hybrid Annuity Sewerage Projects

S. Name of the Package Capacity Present Status Award Date No. in MLD (Tentative) (i) Mathura 30 Bids Received (14-03- 14/05/2018 2018); Evaluated (ii) Allahabad - Jhusi, Naini, 72 NIT published (16/03/2018) 19/06/2018 Phaphamau (iii) Unnao, Shuklaganj and Kanpur 49 NIT published (08/03/2018) 02/06/2018 (iv) Farrukhabad 35 NIT published (12/04/2018) 02/07/2018 (v) Mirzapur and Gazipur 38 NIT published (14/04/2018) 02/07/2018 (vi) Digha & Kankarbagh in Patna* 150 Likely NIT date-14/05/2018 11/07/2018 (vii) Bhagalpur* 65 Likely NIT date-30/05/2018 16/07/2018

(viii) Kolkata (Tolly’s Nalla) 26 NIT published (27/04/2018) 12/07/2018 (ix) Howrah &Bally; Kamarhati & 165 Likely NIT date-14/05/2018 12/07/2018 Baranagar *

*- Projects under World Bank funding

10

Sewerage Projects in Haridwar

Sewage Generation- 74 MLD Existing Capacity – 63 MLD Work in Progress – 82 MLD STP, I&D works, Arihant Vihar network All 20 drains being tapped

12 Uttarakhand– Completed Projects

S. No. Project STP at Cost - 3.66 Cr 1 STP capacity – 1.4 MLD

Sewerage Scheme in Devprayag 2 Cost – 4.50 Cr

I&D at 3 Cost – 9.61 Cr

I&D at Gopeshwar Triveni Ghat 4 Cost – 10.18 Cr

Sewerage Scheme at Triveni 5 Ghat, Cost – 7.23 Cr

13 Uttarakhand – Completed Projects

S. No. Project

Sewerage system & STP for Tapovan area, Rishikesh 6 Cost – 24.12 Cr STP capacity – 3.5 MLD

Sewerage Scheme at Ahbab Nagar 7 Jwalapur Zone E-2 at Haridwar Cost – 24.84 Cr Tapovan STP

STP at Sarai, Haridwar Cost – 24.91 Cr 8 STP capacity – 18 MLD

14 Uttarakhand– Completed Projects S. No. Project

Sewerage Scheme in 9 Cost – 0.45 Cr

Sewerage System and STP for Gangotri Dham 10 Cost – 10.48 Cr STP capacity – 1 MLD Gangotri

I&D at Devprayag 11 Cost – 7.27 Cr I&D at Badrinath 12 Cost – 7.26 Cr Sewerage Scheme in 13 Cost – 4.84 Cr Gangotri Total (13 projects) Cost – ₹ 139.35 Cr STP capacity – 23.9 MLD

15 Uttarakhand – Work in Progress

S.No. Project STP at Jagjeetpur & Sarai Cost – 273.37 Cr 1 STP capacity – 82 MLD Physical progress – 13.05 % Likely date of completion – Mar’19 Tertiary treatment of existing 27 MLD STP at Jagjeetpur & u/g of existing 18 MLD STP at Sarai 2 Cost – 32.65 Cr Physical progress – 10 % Likely date of completion – Nov’18 STP Sarai I&D at Sarai & Jagjeetpur Cost – 116.28 Cr 3 Physical progress – 48.86 % Likely date of completion – Dec’18

Kassawan Upgradation of STP at Tapovan SPS (I&D Cost – 2.19 Cr 4 Sarai) Physical progress – 98 % Likely date of completion – May’18

16 Uttarakhand – Work in Progress

S.No. Project STP at Kirtinagar Cost – 4.23 Cr STP capacity – 0.06 MLD 5 Physical progress – 70 % Likely date of completion – May’18

I&D and STP at Cost – 13.14 Cr STP capacity – 0.525 MLD 6 Physical progress – 5 % Likely date of completion – Dec’18

I&D and STP at Kirtinagar STP Cost – 12.09 Cr STP capacity – 0.35 MLD 7 Physical progress – 12 % Likely date of completion – Dec’18

17 Uttarakhand – Work in Progress

S. No. Project

I&D with STP at Badrinath Cost – 18.23 Cr 8 STP capacity – 1.01 MLD Physical progress – 3 % Likely date of completion – Dec’18

I&D and STP at Badrinath Cost – 6.46 Cr 9 STP capacity – 0.15 MLD Physical progress – 14 % Likely date of completion – Dec’18

I&D and STP, at Chamoli Cost – 61.83 Cr 10 STP capacity – 4.38 MLD Physical progress – 11 % Likely date of completion – Dec’18 Nandprayag 18 Uttarakhand – Work in Progress

S. No. Project Upgradation of STP at Srinagar Cost – 15.40 Cr 11 Physical progress – 5 % Likely date of completion – Nov’18 I&D and STP at Srinagar Cost – 22.51 Cr 12 STP capacity – 1 MLD Physical progress – 8 % Srinagar STP Excavation Likely date of completion – Nov’18 I&D with STP at Joshimath Cost – 48.42 Cr Upgradation at Uttarkashi STP STP capacity – 3.78 MLD 13 Physical progress – 10 % Likely date of completion – Nov’18

Upgradation of STP (Gyansu) Cost – 10.03 Cr 14 Physical progress – 20 % Likely date of completion – Jun’18

19 Uttarakhand – Work in Progress

S. No. Project

Upgradation of STP at Swargashram,(Rishikesh) Cost – 5.20 Cr 15 Physical progress – 15 % Likely date of completion – Jun’18 Rising main and STP at Cost – 80.45 Cr 16 STP capacity – 12.5 MLD Physical progress – 12 % Likely date of completion – Mar’19 I&D at Arihant Vihar and New Garden, Haridwar 17 Cost – 4.68 Cr Physical progress – 11 % Likely date of completion – Oct’18 I&D with STP at Rishikesh Muni ki Reti SPS Cost – 158 Cr 18 STP capacity – 26 MLD Physical progress – 8 % Likely date of completion – Dec’19 Total (18 projects) Cost – ₹ 885.16 Cr STP capacity – 131.76 MLD 20 Cost: Rs. 6538.62 Cr Sewage Generation- 234 MLD Existing Capacity – 272MLD Under Tendering- 72 MLD All 20 drains being tapped Uttar Pradesh- Completed projects

S. No. Project

Sewerage & Non sewerage Schemes at District 'B' & 'E' of Allahabad 1 Cost – 199.26 Cr STP capacity – 85 MLD Kodra STP- 25 MLD

Sewerage work in District ‘E’ 2 Cost – 142 Cr

Sewerage & Non sewerage Schemes at District 'A' of 3 Alahabad Cost – 106.08 Cr STP capacity – 20 MLD Salori STP- 14 MLD STP at Salori Cost – 42.4 Cr 4 STP capacity – 14 MLD

23 Uttar Pradesh- Completed projects

S. No. Project

Sewerage System & STP works (Phase II) at Kannauj (Kali) Kannauj Cost – 43.66 Cr 5 STP- 13MLD STP capacity – 1 MLD

Sewerage Scheme at Narora, Narora STP- Bulandshahar 6 4MLD Cost – 34.87 Cr STP capacity – 4 MLD

24 Uttar Pradesh- Completed projects

S. No. Project

Sewerage System & STP works at Garhmuhteshwar Cost – 46.51 Cr STP capacity – 9 MLD 7

Sewerage works in Anupshahar, Bulandshahar Cost – 75.79 Cr STP capacity – 2.5 MLD 8

Total (8 projects) Cost – ₹ 690.57 Cr STP capacity – 135.5 MLD 25 Uttar Pradesh- Work in progress projects S.No. Project Sewerage System in District 'C' & Allahapur, Allahabad Cost – 146.87 Cr Physical progress –84% 1 Chilla SPS Likely date of completion – May’18

Sewerage works in Sewerage District 'A' of Allahabad Cost – 288.94 Cr Physical progress – 65 % 2 Vivekanand Likely date of completion – Oct’18 Park SPS

Sewerage System with Sewer network in District 'B' of Allahabad Cost – 265.86 Cr Sewer Works in 3 Physical progress – 63 % Likely date of completion – Dec’18 Dist-B

26 Sewage Generation- 310 MLD Existing Capacity – 102 MLD Work in Progress – 310 MLD STP

All 37 drains being tapped Uttar Pradesh- Work in progress projects S.No. Project

Sewer network in District E of Allahabad - Part 2 Trenchless Cost – 52.78 Cr 4 Sewerline Physical progress –88% Likely date of completion – May’18

JICA assisted Ganga Action Plan Phase II project at Varanasi Dinapur STP 5 Cost – 641.19 Cr STP capacity – 140 MLD Physical progress –82% Likely date of completion – Jul’18

28 •District III Sewer network Sisamau Nala •District I network •Sisamau nala I&D works

Sewage Generation- 457 MLD Existing Capacity – 457MLD Work in Progress – 15 MLD Under Tendering- 30 MLD All 21 drains being tapped •District IV Sewer network Uttar Pradesh- Work in progress projects S.No. Project Sewerage System & STP works (Phase I) at Moradabad Cost – 279.91 Cr STP capacity – 58 MLD Physical progress – 87% Moradabad STP- 6 Likely date of completion – 58MLD Jun’18

I&D of Sisamau Nala of Kanpur city Cost – 63.8 Cr 7 Physical progress – 20 % Likely date of completion – Oct’18 Guptar Ghat SPS

Sewerage works in District I of Kanpur 8 Cost – 370.4 Cr Physical progress – 10 % Likely date of completion – Jul’20 30 Uttar Pradesh- Work in progress projects S.No. Project

STP for Assi-BHU District at Ramana Cost – 161.31 Cr 9 STP capacity – 50 MLD Likely date of completion – Dec’19

TOTAL (9 projects) Cost – ₹ 2271.06 Cr STP capacity – 248 MLD

31 Uttar Pradesh – Tender received and under finalization

Sanctioned STP Sewer Sl Date of Likely Date Name of the project Cost (₹ in Capacity Network No. Sanction of Award Cr.) (MLD) (Km) Interception, Diversion & Treatment 1 02.08.2017 27.98 2 1.16 May-18 works in Chunar, Dist. Mirzapur Rehabilitation of Sewage Infrastructure & 2 Augmentation/ up gradation of Existing 24.03.2017 33.82 5 - May-18 STP at

3 Mathura Sewerage Scheme (HAM) 17.10.2017 204.97 67.5 - May-18

Total 266.8 74.5 1.16

32 Uttar Pradesh – Under Tendering

Sanctioned STP Sewer Sl Likely Date Name of Project Cost (₹ in Capacity Network No. of Award Cr.) (MLD) (Km)

1 Sewerage Scheme & STP at Bithoor, Kanpur Nagar 13.4 2 - June-18

Interception, Diversion of drains & Sewage 2 71.26 10 0.44 July-18 Treatment works at Ramnagar Interception, Diversion of drains & Sewage 3 102.2 13 3.3 July-18 Treatment works at Unnao (HAM) Interception, Diversion of drains & Sewage 4 Treatment works at Shuklaganj, Dist. Unnao 65.18 6 0.15 July-18 (HAM) STP at Pankha, Kanpur and integration with July-18 5 967.23 30 16.5 existing STPs Interception, Diversion & Treatment works for 6 Naini (District G), Phaphamau (District F) & Jhusi 767.59 72 13.21 July-18 area District in Allahabad (HAM) Integrated project for development of STPs in 7 904.00 - - July-18 Allahabad alongwith existing Assets

33 UttarUttar Pradesh Pradesh State – Under Project Tendering Overview

Sanctioned STP Sewer Sl Likely Date Name of Project Cost (₹ in Capacity Network No. of Award Cr.) (MLD) (Km) Farrukhabad I&D and STP works (HAM) 8 213.62 35 - Jul-18

9 I&D works and STP, Mirzapur (HAM) 114.93 17 - Jul-18

10 I&D works and STP, Gazipur (HAM) 90.81 21 - Jul-18

Total 3310.22 206 33.6

34 Namami Gange Projects (20 Towns) in Bihar

Projects – 20 Cost: Rs. 4629.12 Cr Work in Progress – 10 Tender under evaluation-4 Under tendering- 6

35 Sewerage Projects in Patna

Sewage Generation- 286 MLD Existing Capacity – 109 MLD Work in Progress – 200 MLD Tender to be Floated- 150 MLD All 33 drains being tapped PM Laying Foundation Stone for Patna Sewerage Schemes (at Mokama)

37 Bihar– Ongoing projects S. No. Project Beur STP, Sewer Networks, SPS and STP at Buxar Patna Cost – 74.95 Cr 1 STP capacity – 16 MLD Physical progress – 39 % Likely date of completion – Feb’19

Sewage Treatment Plant - Beur for Patna, Bihar 2 Cost – 68.16 Cr STP capacity – 43 MLD Physical progress – 23 % Likely date of completion – Dec’19

Sewerage system with Sewer network, Patna Beur 3 Cost – 225.77Cr Physical progress – 22% Likely date of completion – Mar’20 Beur Network, Patna 38 BiharBihar State– Ongoing Project projects Overview S. No. Project Sewage Treatment Plant - Karmalichak for Patna, Bihar Saidpur STP, Cost – 77.04 Cr 4 Patna STP capacity – 37 MLD Physical progress – 24 % Likely date of completion – Dec ‘ 19 Saidpur STP and adjoining Network for Patna, Bihar Cost – 184.93 Cr 5 STP capacity – 60 MLD Physical progress – 22% Likely date of completion – Dec’19 Saidpur Sewer Network, Patna, Bihar Cost –Cr 6 STP capacity –6 MLD Physical progress –% Likely date of completion – Sewerage scheme at Pahari Zone V, Patna, Bihar Cost – 356.37Cr 7 (Agreement signed on 25-4-2018) Likely date of completion – Apr’21 39 BiharBihar State– Ongoing Project projects Overview

S.No. Project Sewerage scheme at Pahari (Zone IVA (S)), Patna, Bihar Cost – 184.86 Cr 8 (Recently Awarded) Karmalichak STP, Likely date of completion – Apr’21 Patna Sewerage Treatment Plant at Pahari - Patna, Bihar Cost – 191.62 Cr STP capacity – 60 MLD 9 (Agreement signed on 9-5-2018) Likely date of completion – April’21

Sewerage system with Sewer network ,Patna Karmalichak Cost – 277.42 Cr 10 (Recently Awarded) Likely date of completion – Aug’20

Total Cost (10 projects) – ₹1909.75 Cr STP capacity – 216 MLD 40 Abstract - Under Tendering Process projects Tender Under Projects Cost Tender to be floated Evaluation 10 2719.12 4 6

Bihar– Tender Received and Finalisation in Process:

Sanctioned Sewer Sl STP Capacity Likely Date of Name of Project Cost (₹ in Network No. (MLD) Award Cr.) (Km)

1 Sultanganj I&D and STP works 60.22 10 - May-18

2 Mokama I&D and STP works 53.81 8 - May-18

3 I&D and STP for Barh town 58 11 - May-18

4 I&D and STP works for Naugachia 60.79 9 - May-18

Total 232.82 38

41 Bihar– Tender to be floated

Sr. Project Name Approved STP capacity Sewer NIT Publication No Project Cost (MLD) Network Date (₹ in Cr.) (Km) Sewerage System and STP for Digha 1 824.00 100 288 May-18 zone, Patna (HAM) Sewerage System and STP for 2 578.89 50 150 May-18 Kankarbagh zone, Patna (HAM) I&D and STP works for Bhagalpur 3 254.13 65 - Jun-18 (HAM) Sewer Networks, SPS and STP, 4 294.02 30 174.75 May-18 Munger Sewer Network, SPS and STP, 5 230.07 17 114 May-18 Begusarai Sewer Networks, SPS and STP, 6 305.19 22 189.3 May-18 Hajipur Total 2486.3 284 916

42 Namami Gange Projects (2 Towns) in Jharkhand

Projects – 2 Work in Progress – 2 Cost: Rs. 149.59 Cr Sahibganj- 12 MLD STP, 55 km Sewer, ₹ 99.36 Cr,32% progress; likely completion- December 2018 Rajmahal- 3.5 MLD STP, 34 km Sewer, ₹ 50.23 Cr, recently awarded;

likely completion by June 2019 43 Sahibganj STP

44 Namami Gange Projects in West Bengal

Projects – 15 Completed –2 Work in Progress – 4 Under Tendering -4 Tender to be floated-5 Cost: Rs. 2606.58 Cr

45 WestWest Bengal Bengal State – Completed Project projectsOverview Sl No. Project

Sewerage Scheme & STP works at Gayeshpur Cost – 168.67 Cr STP capacity – 8.23 MLD 1

Sewerage Scheme & STP works at Kalyani Cost – 57.87 Cr 2 STP capacity – 4+17 MLD

Total Cost – 226.54 Cr STP capacity – 29.23 MLD 46 WestWest Bengal Bengal State –Ongoing ProjectProjects Overview

S.No. Project

Sewerage Scheme & STP works at Bhatpara Cost – 228.52 Cr 1 STP capacity – 31 MLD Physical progress – 91% Likely date of completion – Jun’18

Sewerage System & STP works at Halishahr Cost – 274.76 Cr 2 STP capacity – 16 MLD Physical progress – 28 % Likely date of completion – Dec’18

47 WestWest Bengal Bengal State – Ongoing ProjectProjects Overview S.No. Project Sewerage System & STP works at Budge-Budge Cost – 145.98 Cr 3 STP capacity – 9.3 MLD Physical progress –35 % Likely date of completion – Oct’19 Sewerage System with sewer network at Barrackpore Cost – 272.32 Cr 4 STP capacity – 24 MLD Physical progress – 24 % Likely date of completion – Dec’19 TOTAL (4 projects) - Cost ₹ 921.58 Cr STP capacity – 80.3 MLD

48 West Bengal – Under Tendering projects

Sanctioned STP Sewer Sl Likely Date Name of Project Cost (₹ in Capacity Network No. of Award Cr.) (MLD) (Km) Interception, Diversion & treatment works at 1 51.20 3.5 5.25 Jun-18 Behrampore Interception, Diversion & treatment works at 2 54.30 20 4 Jun-18 Interception, Diversion & treatment Works at 3 307.12 26.10 114 Jul-18 Tolly's Nullah (Adi Ganga) (HAM) Integration of STPs with rehabilitation and O&M of 4 165.16 - - Jul-18 existing Assets Total 577.78 49.6 123.25

49 WestWest Bengal Bengal State – Tender Project to be Overview floated

Tender to be floated:

Date of Sanctione STP Sewer NIT Sl Name of Project AA&ES d Cost (₹ Capacity Networ Publicatio No. in Cr.) (MLD) k (Km) n Interception, Diversion & treatment works at 1 02.08.2017 185.22 65 May-18 Howrah (HAM) Interception & Diversion with STP at Bally 2 10.10.2017 164.93 40 May-18 (HAM) Interception, Diversion & treatment works at 3 17.01.2018 172.10 60 9 May-18 Baranagar & Kamarahati (HAM) Interception & Diversion with STP at Hugli- 4 - 160 29.3 20 Jun-18 Chinsurah 5 Interception & Diversion with STP at Maheshtala - 198.43 28.1 Jun-18 TOTAL 880.68 222.4 29

50 Status of Existing Sewerage Infrastructure & Interventions  97 towns on Ganga Main Stem  Sewage Generation : 2953 MLD (Yr. 2016), 3603 MLD (Yr 2035)  Available Treatment Capacity (01/11/2017) : 84 STPs – 1584 MLD in 46 Towns 39 STPs- Working satisfactorily 12 STPs (91 MLD)- Up-gradation & O&M Sanctioned 8 STPs (530 MLD)- Integrated under One City One Operator 23 STPs – Tender for upgradation 2 STPs discarded; Status of Existing 84 STPs Defunct (270 Recently mld) - 31 STPs commissioned, working fine alongwith long 37% 46% term O&M (733 MLD) - 39 STPs

Operational and non 17% compliant & under utilized (581 mld) - 14 STPs 51 Present Status of Existing STPs State Working fine – Up-gradation & Integrated under Up- Discarded Total Necessary O&M One City One gradation Nos. (MLD) Nos. (MLD) Interventions Sanctioned Operator through taken Nos. (MLD) Nos. (MLD) Atkins Nos. (MLD) Nos. (MLD) Uttarakhand 9 (91.9) 2 (9.5) 11(101.4) Lakkar Ghat Srinagar Uttar 17 (437.31) 4 (343) 1 (27) 2 (7.5) 24(814.81) Pradesh Jajmau 130 Jajmau Kalindipuram Bingawan 210 CETP Jajmau 5 Shantipuram Trivenipuram Bihar 3 (84) 3 (38) 1 (2) 7(124) Pahari, Buxar Chhapra Bhagalpur (BP) West Bengal 10 (119.42) 7 (43.25) 4 (187) 21 (194.27) 42(543.94) Bhatpara– 4nos. Anupara (BP) Budge-Budge Gardenreach Barrackpore Keorapukur Maheshtala (BP) Kamarhati (BP) Total 39 (732.63) 12 (90.75) 8 (530) 23 (223.27) 2 (7.5) 84 (1584.15)

Implementati Operating Execution- 10 Bidding- 6 (445) Bid prep- Execution- 10 (75.27) on Status (75.27) Bid prep- 2 (85) 23(223.27) Bidding – 6 (445)52 Bid prep – 2 (15) Bid prep – 27 (323.27) Upcoming Projects on Tributaries

Sr. No. of No. of State No. Tributaries Towns 1 Uttarakhand 1 1 2 Uttar Pradesh 10 33 3 Bihar 7 15 4 Jharkhand 2 2 5 West Bengal 1 3 6 Rajasthan 3 4 7 Madhya Pradesh 7 10 TOTAL 31 68 Decentralised Treatment of 20 drains in 15 cities through Modular Treatment System

• 20 drains which are not covered in sewerage projects have been identified • Pollution flowing in 20 drains in 15 cities (about 60 MLD) to be contained & treated using modular STPs, • First of its kind offered on services contract model and include removal of trash, solid waste and pollution load. • Bhudana, Muzaffar nagar, Gajraula, Moradabad, Hapur, Gulaothi, Kasganj, Unnao, Bhadohi, Kunda in UP and Titagarh, Jangipur, Champdani, Chandannagar and Belur in West Bengal. • Tenders on services model are under process • Award of work by May’2018 end. • Modular STPs are ready to install tailored systems and will be operational in six months time. • After successful response to the tenders, the model will be replicated in other untapped drains. Rural Sanitation

Ministry of Drinking Water and Sanitation has taken up construction of IHHLs, liquid waste management for all 1662 Gram Panchayats.

Villages (Near Ganga) S. No. State Completed IHHL Declared as ODF

1 Bihar 321324 468

2 Jharkhand 24977 66

3 U.P 388340 1604

4 Uttarakhand 9540 222

5 W.B 339507 2105

Total 1083688 4465

Total Cost – Rs. 841.3 Crores 55 Ghats and Crematoria No. Of Status No. of Cost Ghats Crematoria Total Completed Under Progress Under Tendering Projects (₹ in Cr) (G) (C) (T) G C G C G C 37 151 54 205 721.94 32 6 104 22 15 26

GHATS

Rudraprayag Alaknanda Original site Present Proposed River Bathing Ghat - 1

CREMATORIA

Original site Present Proposed 56 Srinagar Nathaini Cremation ghat Ghats and Crematoria - Uttarakhand

No. Of Status No. of Cost Ghats Crematoria Total Completed Under Progress Under Tendering Projects (₹ in Cr) (G) (C) (T) G C G C G C 9 22 22 44 175.08 8 6 13 16 1 0

RAMKUND GHAT DEVPRAYAG

RHS RUDRAPRAYAG

57 Chandi Ghat RFD Development of Chandi Ghat (Adjacent to Chandi Ghat Bridge, Haridwar)

PRE - PROJECT SCENARIO PRESENT SCENARIO

Main Component of Chandi Ghat Project- Project cost- 50.36 Cr •Bathing Ghat- 630 m long Physical progress- 55% •Cremation Ghat- 140 m long Expenditure- 26.17 Cr •STP- 25 KLD Likely Date of Completion- Dec-18 •Water & Sewer Network- 1.5 km •Overhead Water Tank- 70 KLD 58 Ghats and Crematoria – Uttar Pradesh

No. Of Status No. of Cost Ghats Crematoria Total Completed Under Progress Under Tendering Projects (₹ in Cr) (G) (C) (T) G C G C G C 11 87 25 112 397.70 23 0 61 1 3 24

Sarsaiya ghat, Kanpur

Ravani katiri Ghat, Balawali Bhairav, Kaushalya, Bharat & to Anupshahr Pandav Ghats Bithoor

59 Ghats and Crematoria - Bihar

No. Of Status Cost (₹ in No. of Projects Crematoria Completed Under Progress Ghats (G) Total (T) Cr) (C) G C G C 5 14 1 15 40.86 0 0 14 1

Gola ghat, Buxar

Pul Ghat, Sonepur Konhara Crematoria, Hajipur60 Patna RFD

Cost: ₹ 243.27 Crore Expenditure: ₹ 167 Crore No. of Ghats: 20 Complete: 16 Promenade: 6.6 km Complete: 4.7 km Crematoria : 1 Civil Work complete overall 85% complete

Patna RFD 61 Ghats and Crematoria - Jharkhand

No. Of Status No. of Cost Ghats Crematoria Total Completed Under Progress Under Tendering Projects (₹ in Cr) (G) (C) (T) G C G C G C 4 12 2 14 62.07 1 0 7 1 4 1

Maskaliaya Crematorium

Sarkanda Ghat Sahibganj to Rajmahal 62 Ghats and Crematoria – West Bengal

No. Of Status No. of Cost Ghats Crematoria Total Completed Under Progress Under Tendering Projects (₹ in Cr) (G) (C) (T) G C G C G C 7 15 4 19 44.24 0 0 9 3 6 1

Girish ghat, Garulia

Babughat, Garulia

63 Bhatpara Crematorium River and Ghat Cleaning

Trash Skimmers • Trash skimmers are deployed in 11 cities. • Delhi, Haridwar, Garhmukteshwar, Kanpur, Allahabad, Varanasi, Patna, Sahibganj, Howrah, Mathura- Vrindavan, and Nabadwip.

Ghat Cleaning IL&FS Environmental Infrastructure and Service Ltd. (IEISL) to clean 84 Ghats in Varanasi for 3 years at the cost of Rs.5.0 Crores per year under tripartite agreement between NMCG, Varanasi Nagar Nigam & IEISL. • Similar Ghat Cleaning activities are being taken up for other major towns such as Haridwar, Kanpur- Bithoor, Allahabad ,Mathura-Vrindavan

Man Mandir Ghat

64 Afforestation

FRI, has prepared afforestation plan of 1,34,106 hectare areas at an estimated cost of INR 2294 crores. 2016-2018 STATE Area in ha. Rs crore Uttarakhand 5369 35.497 Uttar Pradesh 831 18.652 Bihar 600.5 24.924 Jharkhand 396 13.428 West Bengal 3588 19.64 Total 10785 112.141

65 Biodiversity

• Biodiversity conservation to study restoration & rehabilitation of the aquatic environment of River Ganga • Assessment of Fish & fisheries in Ganga river system for developing sustainable conservation & restoration plan

66 Thank You

67