<<

Involuntary Resettlement Assessment and Measures

Resettlement Plan Document Stage: Draft for Consultation Project Number: 39415 August 2010

SRI: Sustainable Power Sector Support II Project

Prepared by the Ministry of Power and Energy

The resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

Sustainable Power Sector Support II Project (RRP SRI 39415)

DRAFT RESETTLEMENT PLAN Sustainable Power Sector Support II Project SRI 39415

July 2010

Prepared by the Ministry of Power and Energy Government of

The Resettlement Plan is a document of the Borrower. The views expressed herein do not represent those of ADB’s Board of Directors, Management or Staff, and may be preliminary in nature due to the developmental stage of the Project.

Sustainable Power Sector Support II Project SRI 39415

TABLE OF CONTENTS

A. EXECUTIVE SUMMARY 1 B. PROJECT DESCRIPTION 1 1. Overview 1 2. Project Components 1 C. SCOPE OF LAND ACQUISITION AND RESETTLEMENT 4 1. Impact on Permanent Land Acquisition 4 2. Temporary Impact on Loss of Crop/Trees 4 D. SOCIOECONOMIC INFORMATION AND PROFILE 7 E. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION 8 1. Public Consultation 8 2. Information Disclosure 9 3. Continued Consultation and Participation 9 F. GRIEVANCE REDRESS MECHANISMS 10 G. LEGAL FRAMEWORK 10 H. ENTITLEMENTS, ASSISTANCE AND BENEFITS 11 1. Eligibility 11 2. Entitlements 11 I. INCOME RESTORATION AND REHABILITATION 13 J. RESETTLEMENT BUDGET AND FINANCING PLAN 13 1. Compensation 13 2. Assistance 13 3. RP Implementation and Support Cost 13 K. INSTITUTIONAL ARRANGEMENTS 14 L. IMPLEMENTATION SCHEDULE 15 M. MONITORING AND REPORTING 15

ANNEXURE-1: DETAILED DESCRIPTION ON PROJECT COMPONENTS ANNEXURE-2: CENSUS QUESTIONNAIRE ANNEXURE-3: BASELINE SOCIO-ECONOMIC QUESTIONNAIRE ANNEXURE-4: FINDINGS OF THE BASELINE SOCIO-ECONOMIC SURVEY ANNEXURE-5: SUMMARY DETAILS OF THE CONSULTATIONS ANNEXURE-6: BRIEF OVERVIEW OF VARIOUS RELEVANT POLICIES ANNEXURE-7: MONITORING INDICATORS AND SAMPLE FOR STATUS REPORT

Draft - August 2010 Page i Sustainable Power Sector Support II Project SRI 39415

LIST OF ABBREVIATIONS

ADB - Asian Development Bank AP - Affected Persons BoI - Board of Investment CEB - Ceylon Electricity Board CPS - Country Partnership Strategy EA - Executing Agency FGD - Focus Group Discussion GoSL - Government of Sri Lanka GRC - Grievance Redressal Committee GRM - Grievance Redress Mechanism HH - Households IA - Implementing Agency ID - Identity Cards IP - Indigenous People IR - Involuntary Resettlement LAA - Land Acquisition Act LKR - Sri Lankan Rupees MLLD - Ministry of Land and Land Development MoPE - Ministry of Power And Energy NIRP - The National Involuntary Resettlement Policy PEA - project executing agency PIU - Project Implementation Unit PUCSL - Public Utilities Commission of Sri Lanka Act RoW - Right of Way RP - resettlement plan SIA - Social Impact Assessment SLSEA - Sri Lanka Sustainable Energy Authority SPS - Safeguard Policy Statement -

Draft - August 2010 Page ii Sustainable Power Sector Support II Project SRI 39415

A. EXECUTIVE SUMMARY i. The Sustainable Power Sector Support II Project (The Project) is comprised of various components including the construction of new substations, upgrading of existing substations, construction of new transmission lines, strengthening of new circuits, installation of machinery and equipment, among other things, with the financial assistance of the Asian Development Bank (ADB). The Government of Sri Lanka’s (GoSL) Ministry of Power and Energy (MoPE) is the Executing Agency (EA), whilst the Ceylon Electricity Board (CEB) is the Implementing Agency (IA) for the transmission and distribution components. Additionally, Sri Lanka’s Sustainable Energy Authority (SLSEA) is the IA for the Energy Efficiency and Renewable Energy components. The proposed project will assist GoSL to develop economically viable and environmentally and socially sustainable project components: (i) transmission system strengthening to further improve energy efficiency and enable rural electrification; (ii) rural distribution system improvement in the Eastern and Uva Provinces to increase grid access and rural household connections to impoverished areas, many of which have been affected by conflict in recent years; and (iii) energy efficiency and renewable energy component. ii. The Resettlement Plan (RP) for the Sustainable Power Sector Support II Project has been prepared in accordance with the requirements of the ADB Safeguard Policy Statement (SPS), 2009, the GoSL’s National Involuntary Resettlement Policy (NIRP),2001 and the Land Acquisition Act (LAA) of 1950 (with amendments). The RP describes the level of impact caused by land acquisition due to the construction of the subproject components and identifies the compensation and rehabilitation measures for Affected Persons (AP). iii. Minimum land acquisition is required for the Project which is expected in one substation site. An assessment of land acquisition and resettlement has been carried out for the Project and its components. Physical displacement is not required for the transmission, distribution or energy efficiency components. The grid substations proposed for the project will mainly be built on existing government land. The substation at Vavunativu1 is the only facility that will require the acquisition of 2 Hectares (Ha) of private land, amounting to approximately 4% of the landowner’s land hold. The construction of transmission lines will not entail land acquisition or resettlement impacts. However, temporary impacts are foreseen on crops during the implementation and construction of the Project. A preliminary assessment has been carried out to calculate the approximate area of land to be considered for crop compensation due to the likely construction of the transmission lines. The assessment suggests that up to 302 Ha of private agricultural land could be temporarily affected due to damages caused to crops during the construction phase. This could potentially affect approximately 325 households, who own land along this stretch. iv. Consultations were held with relevant Government officials (CEB, MoPE, SLSEA, Land Department etc) during the Project planning and preparation phase. Consultations were also carried out with Project affected peoples and other interested stakeholders in the local community. Focus Group Discussions (FGD) were conducted with the local community at 46 locations with a total of 405 participants across different project locations. Timely information will be disseminated to Project affected stakeholders during the disclosure of resettlement planning documents. Resettlement information leaflets, containing information on compensation, entitlements and resettlement management provisions adopted by the Project, will be made available to affected stakeholders in the local language (Sinhalese). A summary of the RP and a copy of the entitlement matrix will be translated into the local language; and made available to affected stakeholders at CEB offices. The RP will also be disclosed on the EA/IA and ADB websites. Consultations with project affected stakeholders will be ongoing through out the entire project cycle as necessary. v. A grievance mechanism (GM) will be implemented to address any project-related concerns of APs. Grievances will first be first redressed as per the Public Utilities Commission of Sri Lanka (PUCSL) Act. Grievances not addressed as per the standard PUCSL Act will be brought to the Grievance Redress Committee (GRC). The GRC will consist of representatives from the APs, CEB, SLSEA, MoPE, Divisional Secretary, Land Officer under each Divisional Secretary, field level staff, and local community. The GRC will meet on a monthly basis (if grievances are brought to the Committee) to determine the merit of each grievance, and resolve grievances within a month of receiving the complaint. Unresolved grievances will be referred to a court of Law for redressal. vi. The policy framework and entitlements for the Project are based on the GoSL’s Land Acquisition Act (LAA), 1950, the National Involuntary Resettlement Policy (NIRP), 2001 (NRRP); and ADB’s Safeguards Policy Statement 2009. Based on the above policies, the following core involuntary resettlement principles

1 Advance action is being taken further by CEB where in CEB is currently in the process of getting a government land for Vavunativu substation following which there will be no requirement for private land acquisition and hence no resettlement impact will be occurred. Draft – August 2010 Page 1 Sustainable Power Sector Support II Project SRI 39415 have been adopted for the Project: (i) land acquisition and other involuntary resettlement impacts will be avoided or minimized by exploring all viable alternative project / component designs; (ii) time-bound resettlement plans (RPs) will be prepared and milestones and assistance will be provided to APs to ensure that they’re standard of living and livelihoods are maintained or improved as a result of the Project; (iii) ensure ongoing consultation with APs on compensation issues; timely disclosure of resettlement information; and inclusive participation of APs through out the planning and implementation phases of development; (iv) vulnerable and disadvantaged groups, including women headed households, will be provided with special assistance; (v) APs, including non-titled persons (e.g., informal dwellers/squatters, and encroachers), will be compensated for lost assets at replacement rates; (vi) compensation payments and resettlement assistance will be settled before the contractor acquires and takes possession of any land and prior to the commencement of construction activities; (vii) provision of income restoration and rehabilitation; and (viii) establishment of an appropriate grievance redress mechanism. All APs identified in the project-impacted areas within the specified cut-off date (30 June 2010) will be entitled to compensation for their affected assets, and rehabilitation measures. APs who settle in the affected areas after the cut-off date will not be eligible for compensation. The project will recognize both titleholders and non-titleholders.

Table 1: Entitlement Matrix Definition of Responsible Type of Nº Application Entitled Entitlement Agency Loss Person 1 Loss of Agricultural Legal  Compensation at replacement value or CEB/SLSEA private land land, titleholders/ on a land-for-land basis where feasible. through its homestead APs with  Provision of stamp duty, land respective land or customary registration and documentation fee (@ PIU vacant plot land right APs LKR 10,00 per title holder household) with Permit  Transitional allowance based on three from local months minimum wage rates @ LKR authority 12,000 per household  Notice to harvest standing seasonal crops. If notice cannot be given, compensation for crops will be provided.  Additional compensation for vulnerable households 2 Loss of Vacant plot, Appropriate  Transfer of land through inter MoPE/CEB/S government Agricultural government government department LSEA land land and departments  Payment of land value by CEB to the homestead concerned government and land departmental transfer of ownership. 3 Loss of trees Standing Legal  60 days advance notice to harvest CEB/SLSEA and crops trees and titleholder/ standing seasonal crops, if harvest is through its crops tenant/ not possible, cash compensation for respective leaseholder/ crops (or share of crops) equivalent to PIU sharecropper/ prevailing market price non-titled AP/  Cash compensation for perennial crops AP and fruit bearing trees based on annual net product market value multiplied by remaining productive years  Cash compensation equivalent to prevailing market price of timber for non-fruit trees  Additional compensation for vulnerable households 4 Temporary Land Legal  Provision of rent for period of CEB/SLSEA loss of land temporarily titleholders, occupation for legal titleholders. through its required for non-titled APs  Compensation for assets lost at respective sub-project replacement value, PIU construction  Restoration of land to previous or better conditions  Additionally, cash compensation will be paid for the temporary damage of crop

Draft – August 2010 Page 2 Sustainable Power Sector Support II Project SRI 39415

Definition of Responsible Type of Nº Application Entitled Entitlement Agency Loss Person under the RoW during the maintenance and repair after the construction. In case there is a need for repair or maintenance of the transmission lines in the future, the project authorities would properly inform the land owners for access to the land for maintenance and repairs, when necessary, and the land owners will maintain their right to continue to use the land for farming activities.  Additional assistance will be provided to vulnerable households 5 Any other - -  Unanticipated involuntary impacts will CEB/SLSEA loss not be documented and mitigated based on through its identified the principles of the Resettlement Plan. respective PIU 6 Impacts on All impacts Vulnerable  Land-for-land option will be a CEB/SLSEA vulnerable APs guaranteed option for vulnerable APs if through its APs available and if applicable in case of respective permanent land acquisition. If not PIU available, assistance will be provided for identifying new land and acquired at replacement value where required.  Additional allowance equivalent to LKR 10,000/- for loss of land or structure  Preference in project employment vii. The Project will not result in permanent displacement, physical or economic. The project will impact on only one household who will lose a small portion of land, otherwise most impacts are associated with the temporary loss of crops, for which relocation and income restoration of APs is deemed temporary in nature. The resettlement cost estimate for this subproject includes eligible compensation, resettlement assistance and support costs for the implementation of the RP. CEB and SLSEA will arrange in advance to allot the required budget to meet the costs associated with land acquisition and resettlement resulting from this Project. The total land acquisition and resettlement cost for the Project is estimated at LKR 9.54 million. viii. MoPE will be the Executing Agency (EA). CEB will be the Implementing Agency (IA) for the transmission strengthening and rural electrification components and two sub-components of energy efficiency and renewable energy (reactive power management and the Moragolla hydropower plant detailed design). SLSEA will implement the remaining energy efficiency and renewable energy sub-components. CEB has ongoing ADB-financed projects and will use the existing project management structure complemented by additional staff dedicated exclusively to implementing the proposed Project. Project Implementation Units (PIUs), including experienced staff headed by senior officers will be set up in CEB and SLSEA to undertake day-to-day project planning, implementation, and management activities. All land acquisition, resettlement, and compensation will be completed before the start of civil works. All land required for the Project will be provided free of encumbrances to the contractor prior to handing over the sub- project sites and the start of civil works. The RP implementation schedule is tentatively calculated as one year. Monitoring will be the responsibility of the EA (MoPE) and IAs (CEB and SLSEA) through it’s PIU. The PIU will prepare monthly monitoring reports and will submit regular updates to the ADB.

Draft – August 2010 Page 3 Sustainable Power Sector Support II Project SRI 39415

B. PROJECT DESCRIPTION

1. Overview 1. The Sustainable Power Sector Support Project II (The Project) includes various components including the construction of new substations, upgrading of existing substations, construction of new transmission line, strengthening of new circuits, installation of machinery and equipment, among other things, with the financial assistance of the Asian Development Bank (ADB). The project supports sector reforms, strengthening of transmission and distribution infrastructure and grid. The Government of Sri Lanka’s (GoSL) Ministry of Power and Energy (MoPE) is the Executing Agency (EA), whilst the Ceylon Electricity Board (CEB) is the Implementing Agency (IA) for the transmission and distribution components. Additionally, Sri Lanka’s Sustainable Energy Authority (SLSEA) is the IA for the Energy Efficiency and Renewable Energy components.

2. The proposed project is consistent with Sri Lanka's national and sector priorities. The Government's main goals are to improve the quantity, quality, and cost of service delivery, and to increase electricity connections in rural areas. The proposed project is also consistent with ADB's Sri Lanka Country Partnership Strategy (CPS). To help the Government achieve the above-mentioned goals, the CPS focuses, among other things, on (i) mitigating climate change through financing individual clean energy projects, including small and medium-scale hydro, (ii) funding transmission projects to remove grid constraints on absorbing additional capacity from renewable energy sources and achieving energy-efficiency improvements through strengthening of the transmission network, and (iii) improving connectivity for the poor.

3. This is a Resettlement Plan2 (RP) prepared for the Sustainable Power Sector Support II Project which is in accordance with the ADB Safeguard Policy Statement (SPS), 2009 GoSL’s National Involuntary Resettlement Policy (NIRP), 2001 and the Land Acquisition Act (LAA) of 1950 with amendments. The RP contains the extent of impact caused by land acquisition due to the construction of the subprojects and identifies and defines the compensation and rehabilitation requirements for Affected Persons (AP) which is, in this particular case, primarily economic displacement due to minimum land acquisition expected in one substation which will require the acquisition of less than 10% of land hold of one household. The RP is based on the engineering design and has been prepared in due consultation with project stakeholders. Attempts have been made by the engineering team during the design stage to minimize land acquisition and resettlement by adopting mitigation measures; i.e., selection of suitable sites.

2. Project Components 4. The proposed project will assist the GoSL to effectively implement the following project components: (i) transmission system strengthening to further improve energy efficiency and enable rural electrification; (ii) rural distribution system improvement in the Eastern Province and other outlying regions to expand rural household connections to the poor; and (iii) energy efficiency and renewable energy component. The transmission component will include strengthening of the system in the Southern, Eastern, and Northern parts of the country. It will enable the GoSL to address post-conflict areas electricity needs and bring cheaper hydropower to the population in the Northern and Eastern parts of the country from the North Central and Central Provinces through various transmission lines and substations. Details relating to the subproject components are provided below. The project area of influence is depicted in Figure 1. Detailed description of each project components is provided in Annexure-1. i. Transmission System Strengthening 5. The component will contribute to a reliable, adequate and affordable power supply that will contribute to sustainable economic growth and poverty reduction in the Eastern and Southern Provinces. The strengthened transmission system will alleviate existing sub-standard voltage conditions in the Ampara and provide increased load capacity in both the Eastern and Southern Provinces leading to improved efficiency and reliability in power supply. The component includes the following sub-projects:

 New Galle Power Transmission Development Project Construction of New Galle 3 x 31.5 MVA 132/33 kV Substation and Ambalangoda to New Galle 40 km double circuit 132 kV transmission line:  North East Power Transmission Development Project: Construction of to Vavunativu (via Ampara) 129 km double circuit 132 kV transmission line; to Madagama

2 The project is categorised as B as the impact on Involuntary Resettlement is insignificant. Resettlement is insignificant when less than 200 people experience major “impacts” defined as involving AP being physically displaced from housing and/or having 10% or more of their productive, income generating assets lost. Resettlement having insignificant IR impact is categorised as B which requires a - resettlement plan. Draft – August 2010 Page 1 Sustainable Power Sector Support II Project SRI 39415

16 km double circuit 132 kV transmission line; stringing of second circuit of existing Kotmale to Anuradhapura 163 km 220 kV transmission line; Monaragala 1 x 31.5 MVA 132/33 kV substation; Vavunativu 2 x 31.5 MVA 132/33 kV substation; Ampara 132/33 kV substation (existing) 2 x 132 kV feeder bays; and Pollonnaruwa 1 x 31.5 MVA 132/33 kV substation. ii. Expansion of Rural Electrification and Distribution System Improvement 6. The component will extend the low voltage (LV) system into remote villages and contribute to a more reliable and capacity enhanced distribution network in the , in the Eastern province and , and Koslanda Areas in the Uva Province. The component includes the following sub-projects:

 Ampara District Distribution Development Project (Eastern Province): Construction of medium- voltage (MV) and LV distribution lines comprising 486 rural electrification (RE) schemes, 12,190 households3; 165 km MV lines, 593 km LV lines and 67 MV/LV distribution substations  Ampara District Distribution Network Reliability Improvement Reliability Improvement of MV network comprising installation of 75 auto-reclosers and 100 load break switches  Eastern Province Distribution Capacity Development Purchase of tools and specialized vehicles for 30 line gangs in Ampara, Batticaloa and Trincomalee to enable implementation of rural electrification as well as future ongoing MV and LV line maintenance. iii. Energy Efficiency and Renewable Energy4  Tea Estate Micro-Hydro Rehabilitation and Repowering Pilot Project: comprising consulting support (a) to develop a detailed technical specification and funding eligibility criteria for micro-hydro rehabilitation and grid connection; (b) for provision of engineering assessment and monitoring of projects for the duration of the pilot project; and (c) funding for approximately 19 projects providing approximately 1.3 MW of grid connected capacity.  Reactive Power Management: comprising installation of 40 MVAr breaker switched capacitor banks at Aniyakanda (10 MVAr), Ambalangoda (10 MVAr) and Katunayake (20 MVAr) substations to facilitate transmission line loss reduction.  Moragolla5 Hydropower Station: preparation of a detailed engineering design of a 26.5 MW run-of- river hydropower station for possible financing under a subsequent ADB loan. This includes the review of the feasibility study, detailed engineering design and the preparation of bidding documents.

3 Poor households will be provided with credit support to be recovered in instalments over an extended period of time to enable them to finance initial connection charges. The credit will be available through a Rural Household Connection credit line under the ADB's Clean Energy and Access Improvement Project approved in 2009 and covering Ampara district among the three selected project districts. 4 Energy efficiency interventions to (i) implement appliance energy efficiency testing laboratories, (ii) conduct field trials of energy efficient lighting technology,( iii) develop an energy efficient lighting strategy roadmap, and (iv) provide training for energy auditors are proposed for separate funding under a grant from the Asian Clean Energy Fund under the Clean Energy Financing Partnership Facility. Full details of these sub-projects may be found in the associated TA proposal. 5 The feasibility study for Moragolla hydropower plant was prepared under financing from the Kuwait Fund for Arab Economic Development. Draft – August 2010 Page 2 Sustainable Power Sector Support II Project SRI 39415

Figure 1: Map of Project Area

220 kV Line 132 kV U/G Cable 132kV Tx Line 132 kV Tx Line (Future) 220/132 kV Substation 132 kV Substation Hydro Power Station Thermal Power Station

New 132/33 kV Polonnaruwa Grid Substation (1x31.5MVA)

New Double Circuit 132 kV Mahiyangane Vavunativu Tx Line via Ampara (117 km)

Ampara District Distribution Development and Network Reliability

New 132/33 kV Vavunativu Grid Substation (2x31.5MVA)

Second 220kV Circuit Anuradhapura - Kotmale Tx Line (163 km)

Estate Micro-Hydro Rehabilitation and Moragolla HPP PPTA Detailed Design

Ambalangoda - New Galle 132kV Double Strengthening of Circuit Tx Line Distribution System in (40 km) Uva Province

New 132/33 kV Monaragala Grid Substation (1x31.5MVA) 132/33 kV New Galle Grid Substation Monaragala 132 kV Line (3x31.5MVA) in Line Out Transmission Line (16 km)

Draft – August 2010 Page 3 Sustainable Power Sector Support II Project SRI 39415

C. SCOPE OF LAND ACQUISITION AND RESETTLEMENT

7. A census survey was carried out using the structured questionnaire (Annexure-2) for the permanent impact especially for the private land acquisition in the months of April - June 2010. All the project sites were visited and assessed for the IR impacts. The survey team was trained by the international resettlement specialist and the survey was closely monitored on a regular basis. The census survey included various aspects such as (i) assessment of land including quantity and typology (ii) Inventory of physical assets; (iii) potential income loss; (iv) impact on trees; (v) household characteristics, including social, economic and demographic profile and (vi) presence of informal settlers and non-titleholders.

1. Impact on Permanent Land Acquisition 8. Minimum land acquisition is required for the Project. An assessment of land acquisition and resettlement has been carried out for the Projects and each of its components. None will require physical displacement of affected peoples. This is common of projects that include transmission, distribution and energy efficiency components, as transmission lines require small areas of land, are generally located on existing government land, distribution lines are fixed along roads or existing easements and along roads given their isolated and small footprints. Construction of grid substations usually require small land parcel and land acquisition. The grid substations under the project will mostly be constructed on government land. The project will involve the construction of five new sub stations. Four out of five substations are proposed either on government or CEB land (Galle, Monaragala, Polonnaruwa, and Ampara). There is only one substation at Vavunativu6 which is proposed on private land for which 2 Hectares (Ha) of land will need to be acquired. This HH does not belong to an indigenous peoples group (IP) or to an ethnic minority. The impact is limited as the amount of land required for acquisition is very small compared to the total land holding of the HHs. According to the census survey, it is revealed that the percentage of loss is only 4% compared to the total land holding (Total land holding is 125 acres and the affected land is only 5 acres). However, the HH falls under the vulnerable category as it is a woman headed HH for which additional compensation provision has been made in the entitlement matrix. There are no structures and no trees found to be affected inside the land parcel. The land is privately owned agricultural land which does not have any share cropper or tenant. The total annual income of the HH is LKR 200,000 which shows that the HH does not fall below the poverty line. Therefore, this is considered to be an economically displaced HHs and the total numbers of economically displaced persons are two, one male and one female member.

2. Temporary Impact on Loss of Crop/Trees 9. The construction of transmission lines will not require land acquisition nor will it cause resettlement impacts. However, temporary impacts are foreseen on crop damage during the implementation and construction of the project activities. Efforts will be made to schedule the construction activities during the off season cultivation period. The compensation will be paid in cash before the construction activities begin except in cases where dispute of ownership arises which shall be settled before making the payment. A walkover survey was carried out on a sample basis. Additionally an assessment has been made to calculate the approximate area of land to be considered for crop compensation due to the likely construction of transmission lines. As per the assessment, approximately 302 HA of private agricultural land will be temporarily affected considering the loss of crop during the construction which will have approximately 325 HHs. The distribution and energy efficiency will neither have permanent and temporary impacts on land acquisition and resettlement. The summary details on the assessment of land acquisition and resettlement for each project components are described in Table 2

6 Advance action is being taken further by CEB where in CEB is currently in the process of getting a government land for Vavunativu substation following which there will be no requirement for private land acquisition and hence no resettlement impact will be occurred.

Draft – August 2010 Page 4 Sustainable Power Sector Support II Project SRI 39415

Table 2: Impact on Land Acquisition and Resettlement Sl Nº Project Components Unit Quantity Impact on Temporary Impact on Remarks (Status on Land Ownership and Private land Crops7 Possession) Acquisition and Resettlement i. Transmission System Strengthening a. Grid Sub Stations a-1 New 3 x 31.5 MVA Number 1 Not Required Nil Existing CEB owned land, as the proposed 132/33 kV New Galle Grid (Area in Ha) (2 Ha) substation will be constructed adjacent to the Substation existing substation a-2 New 1 x 31.5 MVA Number 1 Not Required Nil Existing Government land is available, which 132/33 kV Monaragala (Area in Ha) (1 Ha) is free from encroachment and squatters Grid Substation a-3 T2b New 1 x 31.5 MVA Number 1 Not Required Nil Government land belonging to the Board of 132/33 kV Polonnaruwa (Area in Ha) (1 Ha) Investment (BOI) is available, free from Grid Substation encroachment and squatters a-4 New 2 x 31.5 MVA Number 1 Required Nil Private land acquisition required. The total 132/33 kV Vavunativu (Area in Ha) (2 Ha) land requirement is 5 Acres equivalent to 2 Grid Substation Ha. The land belongs to one land owner and is equivalent in size to 4% of the landowners total land hold. a-5 Existing Ampara 132/33 Number 1 Not Required Nil kV Grid Substation (Area in Ha) (0.5 Ha) b. Transmission Lines b-1 Ambalangoda to Galle km 40 Not Required (36 Ha of land for crop Impacts are temporary in nature and are 132 kV Transmission Line compensation) = 39 HH limited to minimal damage to crops during the construction phase b-2 Mahiyangana to km 117 Not Required (105 Ha of land for crop Impacts are temporary in nature and are Vavunativu 132 kV compensation) = 113 limited to minimal damage to crops during the Transmission Line via HHs construction phase Ampara b-3 Medagama to Monaragala km 16 Not Required (14 Ha of land for crop Impacts are temporary in nature and are 132 kV Transmission Line compensation) =15 limited to minimal damage to crops during the

7 The calculation to assess the area to be considered for crop loss under transmission lines is based on current assumptions. It should be noted that the detailed route survey will clearly demarcate the tower footings and right of way which is done prior to the commencement of civil works. The Right of Way has been considered as 30 metres and the total length of each transmission line has been multiplied by the proposed RoW width which gives the total area to be covered under the transmission lines. In Sri Lanka, 30% 0f the land is used for productive activities/cultivation (agriculture). The average land holding size per household in Sri Lanka is approximately 0.93 Ha (less than a Hectare). The total area of the calculated agricultural land is divided by the average land holding size which gives the approximate numbers of households to be temporarily affected due to the temporary loss of crop. Draft – August 2010 Page 5 Sustainable Power Sector Support II Project SRI 39415

Sl Nº Project Components Unit Quantity Impact on Temporary Impact on Remarks (Status on Land Ownership and Private land Crops7 Possession) Acquisition and Resettlement HHs construction phase b-4 Kotmale to Anuradhapura km 163 Not Required (147 Ha of land for crop Impacts will be temporary in nature and 220 kV Transmission Line compensation) = 158 involve minimal loss crop damage during Second Circuit Stringing HHs construction ii. Expansion of Rural Electrification and Distribution System Improvement8 1 Construction of medium- km 165 Not Required Nil The distribution lines are mostly done through voltage (MV) distribution poles and will not have any impact. Preference lines is always given to off season cultivation for construction activities. 2 Construction of low- km 593 Not Required Nil The distribution lines are mostly done through voltage (LV) distribution poles and will not have any impact. Preference lines is always given to off season cultivation for construction activities. 3 Construction of MV/LV Number 67 Not Required Nil The sub stations are pole based transformers distribution substations which will have no impact to landowners/crops III. Energy Efficiency and Renewable Energy9 1 Tea Estate Micro-Hydro Number 19 Not Required These are the exiting micro hydro plants inside Rehabilitation and the existing tea estates. Hence, no land Repowering Pilot Project acquisition is required Source: Census and Field Survey, April-June-2010

8 The other two subcomponents (i- Ampara District Distribution Network Reliability Improvement and ii- Eastern Province Distribution Capacity Development) under this component are non-physical items which will not entail land acquisition and resettlement. 9 The other two subcomponents (i- Reactive Power Management and ii- Moragolla Hydropower Station) under this component are non-physical items which will not entail land acquisition and resettlement. Draft – August 2010 Page 6 Sustainable Power Sector Support II Project SRI 39415

D. SOCIOECONOMIC INFORMATION AND PROFILE

10. In addition to the census survey, a social analysis has been carried out in both the project area and in the control group through a sample socio-economic baseline HHs survey of approximately 1,500 HHs in the project area and 301 HHs in control group during April to June 2010. The survey was carried out using a structured questionnaire (Annexure-3). The socio-economic survey covered about 93.67% HHs in the rural area and about 5.93% in the semi-urban area. Among the respondents, about 98% belong to simple HHs and 1.8% are shop owners. The ethnic composition is dominated by Sinhalese comprising 86% followed by Tamils (8.87%). The average family size is 4.14 and the sex ratio is 971 females per 1,000 males. In 11.8% the HH was headed by a woman in the project area. About 24.62 % of the population is illiterate. Ground water from wells in residence is the major source of water (41.82%) followed by public well access by 31.49% of the HHs. Tap water is accessed by 16.49% of the HHs in the project area. About 78.67 % of the HHs have their own flush toilet and 7.13 % have no toilet facility and depend on the neighbouring fields. Agriculture as main activity is as practiced by 44.13 % of the HHs followed by daily wage earners (27.2%). Similarly about 7 % of the HHs has agriculture as allied activities followed by working for other farmers and daily wage earners. White collar jobs like working in government sector is reported by 17.27 % of the HHs and 3.3 % work in private sectors. About 6.67% of the HHs have a small business.

11. The total average annual income per HH is LKR 171,983.82. About 9.27 % of the HHs report having loans. The average landholding size is of 0.93 hectares. About 81.7 % of the total land is cultivable. Rice cultivation is practiced by the majority (73.72 %) of HHs followed by vegetable cultivation 7.25%. The pattern of expenditure is reported to be more on food (52.21 %) to the total reported expenditure. About 15.27 % of HHs report having a health centre within the village. In 14.8 % of the HHs at least a family member was sick during the last one year preceding this survey. Migration is reported in 10.53 % of HHs. Among the migrated HHs about 95.57 % migrated individually and the rest with family. About 59.49 % of the HH members migrated to outside of the district, 19.62% to the capital city and 12.03% outside of the country. Mostly the migrated males and females are engaged in private and government jobs. About 77.8% of the women in the HHs are engaged in HH activities besides other activities. About 51.47 % of the women in the surveyed HHs are engaged in agriculture, and 19.87 % are engaged in allied activities like poultry, dairy, etc. Similarly 17.7 % are engaged in the collection and sale of forest product. Women’s participation in the HH decision making is positive. About 87.6 % of HHs report women participation in day-to-day activities of the HH in general. The women spent about 2 hours and 53 minutes in cooking and 4 hours and 10 minutes in average caring the young and the sick. On safety of women during day time, about 96.8 % of the HH reported feeling safe and during night time the safety perception decreases to 62.47 %. About 97.60 % of the surveyed structures are residential and 1.67 % are commercial. The average age of the structures is 10 years and 8 months. 45.07 % of the structure roofs are tiles, followed by asbestos sheet (23.13%) and corrugated iron sheet (22.13 %). Similarly 63.20 % have concrete floors and 29.67 % are made of earth/clay/ sand. About 65.67 % of the structure walls are made of bricks. 79.40 % of the structures are permanent, 11.67 % are temporary and 8.93 are semi-permanent. The average number of rooms per structure is 2.84 and only 1 room is lighted.

12. As per the survey, only 28.47 % HHs are electrified. About 63.23 % get power from solar energy and 36 % from the national grid. The majority (about 95.55 %) of electrified HHs use electricity for lighting and 72.37 % have TV and radio. Similarly 6.56 % of the HH also use electricity for pumping water. About 25.53 % have an electric meter at their HH. The average monthly electricity bill is LKR 90.75 among the electrified HHs. About 35.36 % of the HHs also extensively use non-electric energy such as kerosene and wood. Unelectrified HHs use kerosene and diesel for lighting purpose (95 %). The average expenditure on kerosene and diesel is LKR 581.29 per month by unelectrified HHs. About 87.87 % reported that they pay their electricity bill regularly. Details on the findings of the baseline survey are given in Annexure-4.

13. The census survey revealed that only one woman headed HH will be affected by the project. Women in the project area are largely involved in HH work, cultivation and other agricultural activities. Women will not be affected negatively due to the project. Any negative impacts of project on female-headed HH will be taken up on a case-to-case basis and assistance to these families will be treated on a priority basis. During disbursement of compensation and provision of assistance, priority will be given to female-headed HHs. Additionally, women headed HHs are considered as vulnerable and provision for additional assistance has been made in the entitlement. Provision for equal wage and health safety facilities during the construction will be ensured by the EA and IA. Therefore, the project activities will not have any negative impact on women. Additionally, a Gender Action Plan has been prepared for the entire project component which has been appended to the project document. The will be no impacts foreseen on Indigenous Peoples (IP), therefore, no action has been taken.

Draft – August 2010 Page 7 Sustainable Power Sector Support II Project SRI 39415

E. INFORMATION DISCLOSURE, CONSULTATION, AND PARTICIPATION

1. Public Consultation 14. Public consultation was carried out in the project areas with the objectives of minimizing probable adverse impacts of the project and to achieve speedy implementation of the project through bringing in awareness among the community on the benefits of the project. During Project preparation, consultations have been held with the concerned government officials (CEB, MoPE, SLSEA, land Department etc). Additionally, consultations were also carried out with the affected persons (APs) in the project area and with local community. Focus Group Discussions (FGD) were conducted with the local community at 46 locations with a total of 405 participants at different project locations. The issues covered during these consultations included the selection of project sites and the identification of potential impacts and other key issues, including addressing the current gaps in electric usage. These consultations provided inputs in identification of the felt needs of the communities, and the relevant stakeholders. The primary stakeholders are the APs, i.e., land owners who are going to lose small piece of land, the farmers who will be impacted temporarily due to loss of crop, local community and EA/IA. The methods used for the consultations are individual meetings, interviews, structured questionnaires, open ended questionnaire and Focused Group Discussion (FGD) with local community. A brief summary on public consultations is described in Table 3 and the detailed summary on various FGDs is given in Annexure 5.

Table 3: Summary of Consultations Incorporation into Date Participants and S.Nº Place Issues discussed RP and Project 2010 Numbers design A Colombo and other March to Government  Assessment of the  Capacity building project site offices in June (CEB engineers, environment and social program, for training Sri Lanka Environment safeguard capacities of on environmental and Officer in CEB, the CEB social/involuntary Engineers in  Understanding of the resettlement aspects SLSEA, Officer in externally funded to the CEB engineers Land ministry and projects implemented and environment field Level CEB to date, key issues divisions, as part of officials) pertaining to the project, environmental  Training on ADB’s Approximately 9 management, including new safeguard Policy officials were land acquisition and Statement-2009 consulted resettlement requirement B Sri Lanka (Various March to APs/APs and  Siting of the project  Site visits Project Locations) June Local Community components to avoid undertaken, and Kataboola (405 participants) impacts on land consultations with Tolabola, acquisition and owners of the land Udahentenna resettlement parcels where the Wellandura  Awareness about the substations are Strathodon project and social proposed to be Elteb impact established

Rassagala  Benefits of the  Assets on land, Glassough projects including structures, Nanu Oya trees evaluated, and Udaradella  Social and compensation Tillyrie Environmental provided for in the RP Hapugammana – problems in the region for the project. Parasas-ella  Presence of Ederapola environmental sensitive  Avoidance of Madacombra areas in the region socially and culturally Pitarathmale sensitive areas  Health and safety including the Moray issues environmentally sensitive areas Thalawakele

Maskeliya  Compensation payment mechanism  Compensation to Ragala initiatives for minimal be paid as per the fair

Draft – August 2010 Page 8 Sustainable Power Sector Support II Project SRI 39415

Incorporation into Date Participants and S.Nº Place Issues discussed RP and Project 2010 Numbers design Gonapitiya environmental/social market value impacts equivalent to Lathugala replacement value Bodagolla  Presence of Dewagramam Indigenous People  Potential likely Aligambe employment of the people in the project Bakinigasdoowa  Likely participation of activities. Sadunpura, the people for the Bambarawana future project implementation Kahatagasyaya Kalugolla Galoyapallama Tempana Hagamwala Dambana Indigenous village Panapitiya Galmaduwa Akkaraipattu Hijira Junction Dehigolla Meegasthenna Naranwana Naranwana Hillside watta 69th Junction Udayapura Mihindupura 49 Colony Thapalpola Welampale

2. Information Disclosure 15. To ensure transparency and the ongoing involvement and participation of APs and other stakeholders, project information will be disseminated through the disclosure of resettlement planning documents. Resettlement information leaflets containing information on compensation, entitlement and resettlement management adopted for the project will be made available in the local language (Sinhalese) and the same will be distributed to APs. The EA and IAs will keep the APs informed about the impacts, the compensation and assistances proposed for them and facilitate addressing any grievances. The information will also be made available at a convenient place, easily accessible to the APs. The summary of the RP and the entitlement matrix will be translated into the local language; disclosed to the APs; and made available at CEB’s offices. A copy of the RP will be disclosed on the EA/IA and ADB website.

3. Continued Consultation and Participation 16. For continued consultations, the following steps are envisaged in the project:

 The EA/IA will organise public meetings and will apprise the communities about the progress in the implementation of resettlement, social and environmental activities.  The EA/IA will organise public meetings to inform the community about the compensation and assistance to be paid. Regular update of the progress of the resettlement component of the project will be made by the IA.  All monitoring and evaluation reports of the resettlement components of the project will be disclosed in the same manner as that of the RP.  The EA/IA will conduct information dissemination sessions at major intersections and solicit the help of the local community leaders to encourage the participation of the APs in RP implementation.

Draft – August 2010 Page 9 Sustainable Power Sector Support II Project SRI 39415

 Key features of the entitlements will be displayed along the project corridor.  Attempts will be made to ensure that vulnerable groups understand the process and to take their specific needs into account

F. GRIEVANCE REDRESS MECHANISMS

17. Efficient Grievance redress mechanism will be developed to assist the APs resolve their queries and complaints. The Grievance Redress Mechanism (GRM) for the infrastructure development project provides an effective approach for complaints and resolution of issues made by the affected community in reliable way. This mechanism will remain active throughout the life cycle of the project. Thus Public Utilities Commission of Sri Lanka (PUCSL) Act creates an environment for all inhabitants of Sri Lanka and the contributors to its development, to have access to essential infrastructure and utility services in the most economical manner within the boundaries of the sustainable development agenda of the country. PUCSL’s mission is to regulate all the utilities within the purview of the PAAs, to ensure safe, reliable and reasonably priced infrastructure services for existing as well as future consumers in the most equitable and sustainable manner. All the members in PUCSL need to be informed by the PIU regarding procedures of GRM. The initial level of grievance will be addressed as per the PUCSL’s standard mechanism.

18. Grievances not settled as per the above PUCSL’s standard mechanism will be brought to the Grievance Redress Committee (GRC). The GRC will have representatives from APs, CEB, SLSEA, MoPE, Divisional Secretary, Land Officer under each divisional secretary, field level staff, and local community – where necessary. The main responsibilities of the GRC will be to: (i) provide support to APs/APs on problems arising from land/property acquisition; (ii) record AP/AP grievances, categorize, and prioritise grievances and resolve them; (iii) immediately inform the EA/IA of serious cases; and (iv) report to APs on developments regarding their grievances and the decisions of the GRC and the PIU. Other than disputes relating to ownership rights under the court of law, GRC will review grievances involving all resettlement benefits, compensation, relocation, replacement cost and other assistance. The GRC will meet every month (if grievances are brought to the Committee), to determine the merit of each grievance, and resolve grievances within a month of receiving the complaint-failing which the grievance will be referred to the appropriate court of Law for redressal. Records will be kept for all grievances received, including: contact details of the complainant, date the complaint was received, nature of grievance, agreed corrective actions and the date these were effected, as well as the final outcome. The GRCs will continue to function during the life of the Project loan including the defects liability period.

G. LEGAL FRAMEWORK

19. The policy framework and entitlements for the Project are based on GoSL’s Land Acquisition Act (LAA), 1950, the National Involuntary Resettlement Policy (NIRP), 2001; and ADB’s Safeguards Policy Statement 2009. A brief description on applicable laws and policies to the project are described in more detail below. The salient features of the Government’s and ADB polices, along with a gap analysis are summarised in Annexure-6.

20. The law governing acquisition of land for public purposes is the Land Acquisition Act, enacted in 1950 and which has been the subject of several amendments and revisions. LAA provides the legal basis to acquire land, if required for any project including in the electricity sector. The LAA sets out the procedures for acquiring land and for payment of compensation for acquired land. To ensure that people affected by development projects are treated in a fair and equitable manner, and that they are not impoverished in the process, GoSL has adopted the National Involuntary resettlement Policy (NIRP) in 2001. This policy established the framework for project planning and implementation.

21. The gap in Sri Lanka’s Land Acquisition Act of 1950 is that the Act provides only for compensation for land, structures and crops. It does not require project executing agencies (PEA) to address key resettlement issues such as (a) exploring alternative project options that avoid or minimize impacts on people; (b) compensating those who do not have title to land; (c) consulting affected people and hosts on resettlement options; (d) providing for successful social and economic integration of the affected people and their hosts, and (e) full social and economic rehabilitation of the affected people.

22. ADB has adopted Safeguard Policy Statement (SPS) in 2009 including safeguard requirements for environment, involuntary resettlement and indigenous people. The objectives of the policy are to avoid involuntary resettlement wherever possible; to minimize involuntary resettlement by exploring project and design alternatives; to enhance, or at least restore, the livelihoods of all displaced persons in real terms relative to pre-project levels; and to improve the standards of living of the displaced poor and other vulnerable groups. The involuntary resettlement safeguards covers physical displacement (relocation, loss of Draft – August 2010 Page 10 Sustainable Power Sector Support II Project SRI 39415 residential land, or loss of shelter) and economic displacement (loss of land, assets, access to assets, income sources, or means of livelihoods) as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas. It covers them whether such losses and involuntary restrictions are full or partial, permanent or temporary.

23. Based on the above polices, the core involuntary resettlement principles for the Project have been adopted which are: (i) land acquisition, and other involuntary resettlement impacts will be avoided or minimised exploring all viable alternative sub-project designs; (ii) where unavoidable, time-bound resettlement plans (RPs) will be prepared and APs will be assisted in improving or at least regaining their pre-program standard of living; (iii) consultation with APs on compensation, disclosure of resettlement information to APs, and participation of APs in planning and implementing sub-projects will be ensured; (iv) vulnerable groups will be provided special assistance10; (v) payment of compensation to APs including non- titled persons (e.g., informal dwellers/squatters, and encroachers) for acquired assets at replacement rates; (vi) payment of compensation and resettlement assistance prior to the contractor taking physical acquisition of the land and prior to the commencement of any construction activities; (vii) provision of income restoration and rehabilitation; and (viii) establishment of appropriate grievance redress mechanisms.

H. ENTITLEMENTS, ASSISTANCE AND BENEFITS

1. Eligibility 24. All APs who are identified in the project-impacted areas on the cut-off date11 will be entitled to compensation for their affected assets, and rehabilitation measures (as outlined in the entitlement matrix below) sufficient to assist them to improve or at least maintain their pre-project living standards, income- earning capacity and production levels. The project will recognize both titleholders and non-titleholders. APs who settle in the affected areas after the cut-off date will not be eligible for compensation. They, however will be given sufficient advance notice, requested to vacate premises and dismantle affected structures (if any) prior to project implementation.

2. Entitlements 25. Based on the above broad principles, a detailed description of each compensation measure and assistance for the project is provided in the entitlement matrix. APs will be entitled to a combination of compensation measures and resettlement assistance, depending on the nature of ownership rights of lost assets and scope of the impact, including social and economic vulnerability of the APs. The loss of crop, trees and agriculture during the construction of the transmission lines will be paid as instant cash compensation for the damaged period. People will use the land below the lines after the construction. In case there is a need for repair or maintenance of the transmission lines in the future, the project authorities would reach agreement with the land owners for access to the land for maintenance and repairs, when necessary, and that the land owners would continue to use the land for farming activities. The EA will provide cash compensation to the APs for the temporary loss of crop, if occurred, during the time of maintenance and repair. The entitlement matrix (Table 4) summarizes the main types of losses and the corresponding entitlements in accordance with GoSL and ADB policies.

Table 4: Entitlement Matrix Definition of Responsible Type of Nº Application Entitled Entitlement Agency Loss Person 1 Loss of Agricultural Legal  Compensation at replacement value or CEB/SLSEA private land land, titleholders/ land-for-land where feasible. through its homestead APs with  Provision of stamp duty, land respective land or customary registration and documentation fee (@ PIU vacant plot land right APs LKR 10,00 per title holder household) with Permit  Transitional allowance based on three from local months minimum wage rates @ LKR authority 12,000 per household  Notice to harvest standing seasonal

10 Vulnerable groups include poor households, households headed by women, the physically handicapped, and household headed by Indigenous People or ethnic minority. 11 The cut-off date for title holders is based according to the formal notification under LAA, and for non-titleholders the date of the census survey which is June 2010. Those who encroach into the subproject area after the cut-off date will not be entitled to compensation or any other assistance. Draft – August 2010 Page 11 Sustainable Power Sector Support II Project SRI 39415

Definition of Responsible Type of Nº Application Entitled Entitlement Agency Loss Person crops. If notice cannot be given, compensation for share of crops will be provided.  Additional compensation for vulnerable households 2 Loss of Vacant plot, Appropriate  Transfer of land through inter MoPE/CEB/S government Agricultural government government department LSEA land land and departments  Payment of land value by CEB to the homestead concerned government and land departmental transfer of ownership. 3 Loss of trees Standing Legal  60 days advance notice to harvest CEB/SLSEA standing seasonal crops, if harvest is and crops trees and titleholder/ not possible, cash compensation for through its crops tenant/ crops (or share of crops) equivalent to respective leaseholder/ prevailing market price PIU sharecropper/  Cash compensation for perennial crops and fruit bearing trees based on non-titled AP/ annual net product market value AP multiplied by remaining productive years  Cash compensation equivalent to prevailing market price of timber for non-fruit trees  Additional compensation for vulnerable households 4 Temporary Land Legal  Provision of rent for period of CEB/SLSEA loss of land temporarily titleholders, occupation for legal titleholders. through its required for non-titled APs  Compensation for assets lost at respective sub-project replacement value, PIU construction  Restoration of land to previous or better quality  Additionally, Cash Compensation will be paid for the temporary damage of crop under the RoW during the maintenance and repair after the construction. In case there is a need for repair or maintenance of the transmission lines in the future, the project authorities would properly inform the land owners for access to the land for maintenance and repairs, when necessary, and that the land owners would continue to use the land for farming activities.  Additional assistance to vulnerable households 5 Any other - -  Unanticipated involuntary impacts will CEB/SLSEA loss not be documented and mitigated based on through its identified the principles of the Resettlement Plan. respective PIU 6 Impacts on All impacts Vulnerable  Land-for-land option will be a CEB/SLSEA vulnerable APs guaranteed option for vulnerable APs if through its APs available and if applicable in case of respective permanent land acquisition. If not PIU available, assistance in finding new land.  Additional allowance equivalent to LKR 10,000/- for loss of land or structure  Preference in project employment

Draft – August 2010 Page 12 Sustainable Power Sector Support II Project SRI 39415

I. INCOME RESTORATION AND REHABILITATION

26. The project will not result in any permanent displacement may it be physical or economic. Temporary impacts on crops are foreseen for which adequate compensation has been provided in the entitlement matrix which will be as per the current market rate. Transitional allowances to the APs losing land has been provided in addition to the compensation based on a three months of minimum wage equivalent to LKR 12,000 per HHs. Also, vulnerable HHs will be paid an additional assistance on a lump sum basis equivalent to LKR 10,000 per HH. CEB/SLSEA will ensure that advance notice be issued to the APs prior to the start of the work and al the compensation will be paid prior to the start of the construction. The project will impact on only one HH who will lose a piece of land and most of the impacts are temporary loss on crop, therefore, the relocation and income restoration of the APs are very much temporary in nature. The APs will also be allowed to cultivate under the transmission line (under the RoW) after the completion of the work. In case of any maintenance work in the future, CEB will pay the APs for any loss of crop and trees less than 3 meters of height due to the work.

J. RESETTLEMENT BUDGET AND FINANCING PLAN

27. The resettlement cost estimate for the project includes eligible compensation, resettlement assistance and support cost for RP implementation. These are part of the overall project cost. The unit cost for land and crops in this budget has been derived through rapid field appraisal, consultation with affected families and relevant government authorities. Contingency provisions have also been made to take into account variations from this estimate. The components of the resettlement cost include various features such as, compensation for land at their replacement value; compensation for crops; assistance for transitional allowance and cost for implementation of RP. CEB and SLSEA will arrange in advance to allot the required budget in its budget to meet the requirement of land acquisition and resettlement cost.

1. Compensation 28. Private Agricultural Land: The unit rate for agricultural land has been assessed as LKR 800,000 per Hectare. This has been determined keeping in mind the replacement cost as revealed by the AP and as based on the market rate

29. Crop: The unit cost for the crop is LKR 20,000 per Hectare. This has been assessed as per the yielding of the land and as revealed by the APs during the consultation.

2. Assistance 30. Stamp Duty and Documentation Fees: The unit cost has been assessed on a lump sum basis which is LKR 10,000 per title holder HH

31. Transitional Assistance: This has been calculated based on three months of minimum daily wage rates. The usual wage rate per day is LKR. 200 and therefore the unit rate per HH is LKR 12,000.

32. Vulnerable HH Allowance: The unit cost has been assessed on a lump sum basis which is LKR 10,000 per vulnerable HH.

3. RP Implementation and Support Cost 33. Administrative cost: This has been calculated on a lump sum basis which is LKR 10, 00, 00 which will include, vehicle hire, documentation and grievance redress etc.

34. The resettlement budget requirements have been calculated based on the above parameters. The total land acquisition and resettlement cost for the Project is estimated to be LKR 9.54 million. Details are found below in Table 5. Table 5: Resettlement Cost Unit Rate Total Cost Item Unit Quantity (LKR) (LKR) A: Compensation for Acquisition of Private Land Agriculture Land (Private) for Hectare 8,00,000 2 16,00,000 A-1 Permanent Acquisitions Temporary Loss of agricultural Hectare 20,000 302 60,40,000 A-2 Land for crop compensation for Transmission Lines Draft – August 2010 Page 13 Sustainable Power Sector Support II Project SRI 39415

Subtotal A 76,40,000 B: Assistance B-1 Documentation Fees Lump Sum 10,000 1 10,000 B-2 Transitional Allowance Lump Sum 12,000 1 12,000 B-3 Vulnerable Allowances Lump Sum 10,000 1 10,000 Subtotal B 32,000 C: Support Implementation of RP C-1 Administrative cost Lump Sum 10,00,000 10,00,000 Subtotal C 10,00,000 TOTAL 86,72,000 Contingency (10% ) 8,67,200 Grand Total 95,39,200 Grand Total in LKR Million 9.54

K. INSTITUTIONAL ARRANGEMENTS

35. MoPE will be the Executing Agency (EA). CEB will be the Implementing Agency (IA) for transmission strengthening and rural electrification components and two sub-components of energy efficiency and renewable energy (reactive power management; and Moragolla hydropower plant detailed design). SLSEA will implement the remaining energy efficiency and renewable energy sub-components. A Steering Committee, established for the Project and chaired by the Secretary of the MoPE, will meet quarterly to provide overall guidance to the IAs and review the overall progress of the Project.

36. CEB has ongoing ADB-financed projects and will use the existing project management structure complemented by additional staff dedicated exclusively to implementation of the Project. Project Implementation Units (PIUs), including experienced staff and headed by senior officers will be set up in CEB and SLSEA to undertake day-to-day project implementation activities. Full-time project managers with qualified staff will be appointed to supervise sub-projects under each component. The PIUs will be responsible for overall project implementation, including procurement, accounting, quality assurance, social and environmental issues and coordination with concerned agencies. PIUs will also coordinate closely with the procurement committee, which will be appointed by the cabinet or MoPE depending on the size of contracts. SLSEA's PIU will be supported by project implementation consultants.

37. The PIU at CEB and SLSEA will be responsible for land acquisition and implementation of RP, and will take the overall responsibility with due coordination from the relevant govern ministry and department such as Ministry of Land and Land Development (MLLD) and Divisional Secretary. The CEB has an existing and well established Transmission Design and Environment Branch headed by Deputy General Manager (DGM) and the Environment Unit headed by Environment Officer with full capacity in safeguards planning and implementation and . The branch will be responsible for implementing safeguard issues associated with the Project through the PIU. However, SLSEA has to establish a PIU and will have to staff its adequate safeguards specialist or consultants in the PIU. Therefore, all the activities related to planning and implementation of safeguards components in this Project will be responsibility of CEB and SLSEA in their respective areas. However, MoPE will facilitate for higher level coordination with MLLD when required. Details on the institutional roles and responsibilities related to land acquisition and resettlement activities are described in Table 6.

Table 6: Institutional Roles and Responsibilities for Resettlement activities Activity Responsible Agency Project Initiation Stage Setting up of PIU and staff CEB/SLSEA/MoPE Finalisation of Project Sites CEB/SLSEA RP Preparation and Updating Stage Conducting Census of all APs CEB/SLSEA Conducting FGDs/meetings/ CEB/SLSEA Preparation of RP CEB/SLSEA Approval of RP ADB Disclosure of RP CEB/SLSEA/PIU RP Implementation Stage Fixing the compensation value PIU/CEB/SLSEA/MLLD/DIVISIONAL SECRETARY

Draft – August 2010 Page 14 Sustainable Power Sector Support II Project SRI 39415

Activity Responsible Agency Payment of compensation and Assistance PIU/CEB/SLSEA Taking possession of land CEB/SLSEA/MoPE Implementation of proposed rehabilitation measures CEB/SLSEA Grievances redressal CEB/SLSEA/PIU/GRC Internal monitoring CEB/SLSEA/MoPE ADB = Asian Development Bank, AP = Affected Persons, FGD = focus group discussion, GRC = Grievance Redress Committee, MLLD = Ministry of Land and land Development, PIU = project Implementation Unit, RP = Resettlement Plan, SLSEA = Sri Lanka Sustainable Energy Authority

L. IMPLEMENTATION SCHEDULE

38. All land acquisition, resettlement, and compensation will be completed before the start of civil works. All land required will be provided free of encumbrances to the contractor prior to handing over of sub-project sites and the start of civil works. However, public consultation, grievance redress and internal monitoring will be continued on an intermittent basis for the entire duration of the project. Implementation schedule for RP activities, including various sub tasks and a time line aligned to the civil work schedule is prepared and presented in Table 7.

Table 7: Implementation Schedule Activity Months 123456 7 8 9 1 1 1 0 1 2 1. Pre Implementation Stage Establishment of PIU at CEB and SLSEA  Appointment of designated staff at PIU  Census surveys including the ID cards   Consultations            RP preparation  RP review and approval (MoPE and ADB). The must be  submitted to ADB for clearance prior to award of contracts. Disclosure of the RP  Formation of GRC  Appointment of project management staff at SLSEA  2. RP Implementation Stage Issue notice to APs and  Disbursement of Compensation and resettlement     assistance Takeover possession of acquired property  Handover land to contractors Written confirmation to ADB from CEB/SLSEA through  MoPE when payment to APs has been completed. Permission to contractor to begin works once compensation to APs is confirmed. Start of the Civil Work  3. Intermittent Activity (Monitoring and GRM) Internal monitoring       Grievance Redress       ADB = Asian Development Bank, CEB = Ceylon Electricity Board, AP = AffectedPerson, GRM = Grievance Redress, ID = Identity Cards, MoPE = Ministry of Power and Energy, PIU = Project Implementation Unit, RP = Resettlement Plan, SLSEA = Sri Lanka Sustainable Energy Authority

M. MONITORING AND REPORTING

39. Monitoring will be the responsibility of the EA (MoPE) and IAs (CEB and SLSEA) through its PIU. The extent of monitoring activities, including their scope and periodicity, will be commensurate with the project’s risks and impacts. CEB and SLSEA is required to implement safeguard measures and relevant

Draft – August 2010 Page 15 Sustainable Power Sector Support II Project SRI 39415 safeguard plans, as provided in the legal agreements, and to submit monitoring reports (every 6 months) summarizing implementation performance. ADB will require MoPE, CEB and SLSEA to:

 establish and maintain roles, responsibilities, lines of communication and procedures for monitoring the implementation of the safeguard plans,  verify compliance with safeguard measures and their progress toward achieving the intended outcomes,  document and disclose monitoring results and identify necessary corrective and preventive actions in the periodic monitoring reports,  follow up on these actions to ensure progress toward the desired outcomes,(v) retain qualified and experienced external expert to verify monitoring information for projects with significant impacts and risks,  Submit periodic monitoring reports on safeguard measures as agreed with ADB.

40. The PIU established to work alongside CEB and SLSEA will be responsible for daily planning, implementation, feedback and trouble shooting, maintenance of individual AP files, managing and maintaining good community relationships and continuous dialogue, scheduling consultation dates, staying abreast of complaints or appeals placed and of submitting periodic progress reports. The PIU will prepare monthly monitoring reports and will compile the report which will be submitted to ADB on a semi-annual basis. Monitoring reports documenting progress on resettlement implementation and RP completion reports will be provided by the CEB and SLSEA to ADB for review. Additionally, ADB will monitor projects on an ongoing basis until a project completion report is issued.

41. The indicators for achieving the proposed objectives during the implementation of the RP of two types: (i) Process Indicators (Indicating project inputs, expenditure, staff deployment, etc.) and (ii) Output Indicators: Indicating results in terms of numbers of APs compensated, area of temporarily occupied lands restored, etc. A sample monitoring indicator is given in Annexure-7. Input and output indicators related to physical progress of the work will include items such as: (i) Training of EA/IA and other staff completed, (ii) Census, assets inventories, assessments and socio-economic studies completed, (iii) Grievance redress procedures in-place and functionality, (iv) Compensation payments disbursed, (v) Relocation of APs completed where applicable, (vi) Project employment provided to APs, (vii) Infrastructure rehabilitated or constructed, (ix) Income restoration activities initiated, (x) Number of HHs displaced and resettled, and (xi) Monitoring and evaluation reports submitted.

Draft – August 2010 Page 16 Sustainable Power Sector Support II Project SRI 39415

ANNEXURE-1

DETAILED DESCRIPTION OF PROJECT COMPONENTS

A. Transmission System Strengthening

1. This component will contribute to a reliable, adequate and affordable power supply for sustainable economic growth and poverty reduction in the Eastern and Southern provinces. The strengthened transmission system will alleviate existing sub-standard voltage conditions in Ampara District and provide increased load capacity in both the Eastern and Southern provinces leading to improved efficiency and reliability in power supply. The component includes the following sub-projects:

(i) New Galle Power Transmission Development Project: Construction of New Galle 3 x 31.5 MVA 132/33 kV Substation and Ambalangoda to New Galle 40 km double circuit 132 kV transmission line:

T1a: New 3 x 31.5 MVA 132/33 kV New Galle Grid Substation Construction of a new substation at Galle, comprising:

 132 kV double busbar switchyard with: o 4 feeder bays o 1 Static VAR Compensator bay +10 MVAr to - 20 MVAr for voltage support o 3 transformer bays o 1 bus-coupler bay o 3 x 31.5 MVA transformers  33 kV switchyard with o 3 transformer bays o 2 bus-section bays o 10 feeder bays o 2 generator bays o 6 capacitor bays with total of 30 MVA capacitors for loss reduction  Control Room and all associated communications, protection and control.

2. This substation is located adjacent to the existing Galle 132/33 kV substation, which is old and cannot be extended further. The existing double circuit 132 kV transmission line from Balangoda to Old Galle Substation will be diverted into the New Galle substation. The other two 132 kV feeder bays will accommodate the new Ambalangoda to Galle 132 kV double circuit transmission line (Item T1b).

T1b: Ambalangoda to Galle 132 kV Transmission Line 3. Construction of a new 132 kV transmission line Ambalangoda to Galle, comprising:

 40 km double circuit Zebra conductor with OPGW, connecting to: o 2 x 132 kV feeder bays at New Galle substation (Item T1a) o 2 x 132 kV feeder bays at Ambalangoda Substation (these two feeder bays, including all switchgear, control and relay panels and the like, are already installed under a previous CEB Project)

(ii) North East Power Transmission Development Project: Construction of Mahiyangana to Vavunativu (via Ampara) 129 km double circuit 132 kV transmission line; Monaragala to Madagama 16 km double circuit 132 kV transmission line; stringing of second circuit of existing Kotmale to Anuradhapura 163 km 220 kV transmission line; Monaragala 1 x 31.5 MVA 132/33 kV substation; Vavunativu 2 x 31.5 MVA 132/33 kV substation; Ampara 132/33 kV substation (existing) 2 x 132 kV feeder bays; and Pollonnaruwa 1 x 31.5 MVA 132/33 kV substation.

T2a1: New 1 x 31.5 MVA 132/33 kV Monaragala Grid Substation 4. Construction of a new substation at Monaragala comprising:

 132 kV single busbar switchyard with: o 2 feeder bays o 1 transformer bay o 1 x 31.5 MVA transformer

Draft – August 2010 Page 17 Sustainable Power Sector Support II Project SRI 39415

 33 kV switchyard with o 1 transformer bay o 4 feeder bays  Control Room and all associated communications, protection and control.

The two 132 kV feeder bays will accommodate the new Medagama to Monaragala 132 kV double circuit transmission line (Item T2a2), which in turn will connect to the existing to Inginiyana Hydro Station single circuit 132 kV transmission line.

T2b New 1 x 31.5 MVA 132/33 kV Polonnaruwa Grid Substation Construction of a new substation at Polonnaruwa, comprising:

 132 kV single busbar switchyard with: o 2 feeder bays o 1 transformer bay o 1 x 31.5 MVA transformer  33 kV switchyard with o 1 transformer bay o 4 feeder bays  Control Room and all associated communications, protection and control.

5. Polonnaruwa substation will be connected to one circuit, in a LILO (line-in, line-out) configuration, of the new Habarana to Valachchanai double circuit (with only one circuit to be strung initially) 132 kV transmission line which is scheduled for construction by CEB later this year (currently under bidding). The existing single circuit Habarana to Valachchanai 132 kV transmission line will not connect to Polonnaruwa substation.

T2c: New 2 x 31.5 MVA 132/33 kV Vavunativu Grid Substation Construction of a new substation at Vavunativu comprising:

 132 kV single busbar switchyard with: o 2 feeder bays o 2 transformer bays o 1 bus-section bay o 2 x 31.5 MVA transformer  33 kV switchyard with o 2 transformer bays o 8 feeder bays o 1 bus-section bay  Control Room and all associated communications, protection and control.

6. The two 132 kV feeder bays will accommodate the new Mahiyangana to Vavunativu 132 kV double circuit transmission line (Item T2e).

T2d Existing Ampara 132/33 kV Grid Substation 7. Augmentation of existing substation at Ampara comprising:

 Extension of 132 kV single busbar switchyard: o Additional 2 feeder bays.

8. The two new 132 kV feeder bays will accommodate one circuit of the new Mahiyangana to Vavunativu 132 kV double circuit transmission line (Item T2e) in a LILO configuration. Ampara substation is currently supplied by a single circuit 132 kV transmission line from Inginiyana Hydro Station, interconnected by the single circuit 132 kV transmission line to Badulla. The existing Inginiyana to Ampara transmission line does not meet modern standards and will need to be upgraded once Ampara is supplied by the new Mahiyangana to Vavunativu transmission line.

T2a2: Medagama to Monaragala 132 kV Transmission Line 9. Construction of a new 132 kV transmission line Medagama to Monaragala comprising:

Draft – August 2010 Page 18 Sustainable Power Sector Support II Project SRI 39415

 16 km double circuit Zebra conductor with GSW earth conductors, connecting to: o 2 x 132 kV feeder bays at Monaragala Substation (Item T2a1) o Existing Badulla to Inginiyana Hydro Station single circuit 132 kV transmission line

T2e Mahiyangana to Vavunativu 132 kV Transmission Line via Ampara 10. Construction of a new 132 kV transmission line Mahiyangana to Vavunativu comprising:

 87 km double circuit Zebra conductor with OPGW, connecting to: o 2 x 132 kV feeder bays at Vavunativu Substation (Item T2cd) o 2 x 132 kV feeder bays at Mahiyangana Substation (new bays by CEB)

11. Construction of a new 132 kV transmission line LILO from Mahiyangana to Vavunativu, to connect Ampara substation, comprising:

 30 km double circuit Zebra conductor with OPGW, connecting to: o Mahiyangana to Vavunativu 132 kV transmission line (Item T2e) o 2 x 132 kV feeder bays at Ampara Substation (Item T2d)

T2f: Kotmale - Anuradhapura 220 kV Transmission Line Second Circuit Stringing on existing 163 km 220 kV line Stringing of a second circuit on existing Kotmale to Anuradhapura 220 kV transmission line comprising:

 163 km second circuit Zebra conductor on existing double circuit towers, connecting to: o Existing 220 kV feeder bay at Kotmale Substation o Existing 220 kV feeder bay at Anuradhapura Substation

B. Expansion of Rural Electrification and Distribution System Improvement:

12. This component will extend the low voltage (LV) system into remote villages and contribute to a more reliable and capacity enhanced distribution network in Ampara district of the Eastern province and Haldummulla, Diyatalawa and Koslanda Areas in Uva Province. The component includes the following sub- projects:

(i) Ampara District Distribution Development Project (Eastern Province): Construction of medium- voltage (MV) and LV distribution lines comprising 486 rural electrification (RE) schemes, 12,190 households12; 165 km MV lines, 593 km LV lines and 67 MV/LV distribution substations

D1: Rural Electrification 13. The rural electrification component will electrify 12,190 rural households in Ampara District for the first time and will include:

 486 rural electrification schemes  63 distribution transformers, 3 phase, 100 kVA, 33/0.4 kV for a total of 6.3 MVA  4 distribution transformers, 3 phase, 160 kVA, 33/0.4 kV for a total of 0.64 MVA  165 km of 33 kV, 3 phase, overhead medium voltage distribution lines  593 km of 0.4 kV, 3 phase, low voltage overhead distribution lines  Electrification of 12,190 rural households

14. The rural electrification component will principally connect new customers by extending the existing LV network. New distribution transformers will be installed where the existing distribution transformer capacity is insufficient or where voltage constraints require additional distribution transformers.

(ii) Ampara District Distribution Network Reliability Improvement: Reliability Improvement of MV network comprising installation of 75 auto-reclosers and 100 load break switches

12 Poor households will be provided with a credit support to be recovered in instalments over an extended period of time to enable them to finance initial connection charges. The credit will be available through a Rural Household Connection credit line under the ADB's Clean Energy and Access Improvement Project approved in 2009 and covering Ampara district among the three selected project districts. Draft – August 2010 Page 19 Sustainable Power Sector Support II Project SRI 39415

D2: Distribution Reliability Improvement

15. The distribution reliability improvement component will improve the reliability and operational flexibility of the distribution network in Ampara district. This will be carried out by installing 33 kV auto- reclosers and 33 kV load break switches in the existing MV network. Modern auto-reclosers improve the protection and sectionalising capabilities of the network. This will ensure that the minimum number of customers is affected by fault and operational switching. In addition this type of switchgear can be operated remotely which reduces outage times as staff no longer have to travel to remote rural areas to operate the equipment manually. This component will include:

 75 x 33 kV Auto-reclosers  100 x 33 kV Load break switches

(iii) Eastern Province Distribution Capacity Development: Purchase of tools and specialised vehicles for 30 line gangs in Ampara, Batticaloa and Trincomalee Districts to enable implementation of rural electrification as well as future ongoing MV and LV line maintenance.

D3: Distribution Tools and Equipment

16. This component includes tools, equipment, heavy machinery and vehicles, including sundry spare materials for rehabilitation of the LV 0.4 kV network in Trincomallee, Batticaloa and Ampara Districts in the Eastern Province. The network in the Eastern Province is in poor shape with little maintenance having been carried out in recent times, the following new tools and equipment are therefore required to a) rehabilitate the existing MV and LV network and b) accelerate household rural electrification in the Province:

 30 tool sets for low voltage aerial bundled conductor (ABC)  30 hydraulic compression tools for conductor connections  45 portable single phase meter testing equipment to ensure accurate revenue metering  15 portable three phase meter testing equipment to ensure accurate revenue metering  20 earth resistance testers (1000 V) to ensure safe earthing  20 insulation testers (2500 V) to ensure adequate insulation  500,000 H connectors to remake poor conductor connections  50,000 compression sleeves to remake poor conductor connections  100 km of aerial bundled conductor and accessories to rehabilitate and reinforce the 0.4 kV low voltage network  200 fuse switch disconnectors, 4 pole, 160 A for isolating and protecting low voltage distribution mains  auger vehicles for digging pole foundations  cranes, 5 MT, for installation and removal of MV and LV poles  lorries, 10 ton, for carting miscellaneous materials, poles and conductor to site  3 bucket vehicles (elevated platform vehicles) for safe overhead line maintenance and construction work  3 all terrain vehicles, 4 wheel drive, for design, construction and maintenance work  3 crew cab utility vehicles for transport of staff and minor materials and equipment to site  2 fork lift vehicles, 5 ton, for loading/offloading heavy line materials and equipment.

D4: Strengthening of Distribution System in Uva Province

17. This component will strengthen the MV distribution system in Haldummulla, Diyatalawa, Ragala and Walapane areas in Uva province. Includes construction of 33 kV backbone line reinforcements to remove network constraints and improve voltage conditions to existing rural customers, comprising the following elements:

 33 km of Lynx conductor 13double circuit pole line  12 km of Lynx conductor single circuit pole line  Upgrade 9 km of existing pole line from racoon conductor to lynx conductor  Construct a two-section, single busbar gantry.

13 “Lynx” conductor is aluminium conductor steel reinforced (ACSR) with a nominal conductor cross-sectional area of 180 mm2. Draft – August 2010 Page 20 Sustainable Power Sector Support II Project SRI 39415

C. Energy Efficiency and Renewable Energy14:

(i) Tea Estate Micro-Hydro Rehabilitation and Repowering Pilot Project: comprising consulting support (a) to develop a detailed technical specification and funding eligibility criteria for micro-hydro rehabilitation and grid connection; (b) for provision of engineering assessment and monitoring of projects for the duration of the pilot project; and (c) funding for approximately 19 projects providing approximately 1.3 MW of grid connected capacity. (ii) Reactive Power Management: comprising installation of 40 MVAr breaker switched capacitor banks at Aniyakanda (10 MVAr), Ambalangoda (10 MVAr) and Katunayake (20 MVAr) substations to facilitate transmission line loss reduction. (iii) Moragolla15 Hydropower Station: preparation of a detailed engineering design of 26.5 MW run-of- river hydropower station for possible financing under a subsequent ADB loan. Includes review of feasibility study, detailed engineering design and preparation of bidding documents.

14 Energy efficiency interventions to (i) implement appliance energy efficiency testing laboratories, (ii) conduct field trials of energy efficient lighting technology,( iii) develop an energy efficient lighting strategy roadmap, and (iv) provide training for energy auditors are proposed for separate funding under a grant from the Asian Clean Energy Fund under the Clean Energy Financing Partnership Facility. Full details of these sub-projects may be found in the associated TA proposal. 15 The feasibility study for Moragolla hydropower plant was prepared under financing from the Kuwait Fund for Arab Economic Development. Draft – August 2010 Page 21 Sustainable Power Sector Support II Project SRI 39415

ANNEXURE-2

CENSUS QUESTIONNAIRE FOR SURVEY OF LAND LOSERS/ PROPERTY INVENTORY

1. Questionnaire Nº: ______Date: ......

2. Name of the Site: ______

3. Name of the Place (s)/Village /(s): ______

4. Plot Nº. ------

5. District: ______

6. Province: ______

7. Ownership of the Land 1. Private 2. Government 3. Religious 4. Community 5. Others

8. Type of Land 1. Irrigated 2. Non-Irrigated 3. Barren 4. Fallow

9. Use of Land 1. Cultivation 2. Orchard 3. Residential 4. Commercial 5. Forestation 6. Others 7. No Use

10. Total Area of the Land/ Plot (In case a portion of the land/ plot to be acquired/affected) (m2) ......

11. Area to be Acquired / Affected Land (m2) ......

12. Rate of the Land (Per Acre) 1. Market Rate (Rs.)...... ………. 2. Government Rate (Rs.)......

13. Name of the Land Holder ......

14. Father’s Name ......

15. Total Land you possess (Total possession: affected + unaffected) (in Hectare) 1. Irrigated...... 2. Non-irrigated ...... 3. Total......

16. Any of the following person associated with the Land

A. Agricultural Labour; 1. Yes; 2. No

B. Tenant; 1. Yes; 2. No

C. Share-Croppers; 1. Yes; 2. No

17. If yes, name of the agricultural Labour/Tenant/ Share-Croppers A...... B...... C...... D......

18. Any structure in the Affected Land 1. Yes; 2. No

19. Area of the affected structure (m2) …………………..

20. Type of Construction Structure

Draft – August 2010 Page 22 Sustainable Power Sector Support II Project SRI 39415

Sl Particulars Type of Construction Nº (1). Simple (thatch/sack/bamboo/slats, (2) Earth/clay/sand, (3) Wood, (4) Brick, (5), Concrete, (6) Corrugated iron sheet, (7) Tile, (8), Asbestos sheet and (9) Other, specify 1 Roof 2 Floor 3 Wall

21. Use of the Structure: 1. Residential; 2. Commercial; 3. Residential -cum-commercial; 4. Others …………

22. Age of the structure (Years)…………………….

23. Current Market Value of the Structure (in Rs..)......

24. Number of trees within the affected area 1. Total………………2. Fruit Bearing………3. Non-fruit Bearing…………4. Timber……………..

25. Social Category 1. Sinhalese; Sri Lankan Tamil; 3. Indian Tamil; 4. Muslim; 5. Other (Specify

26. Number of family members: Total…………Male………Female……….

27. Number of family members above 18 years 1. Son…………2. Unmarried daughter…………; 3. Divorcee/widowed daughter…………... 4. Others…………5. Total…………….

28. Is it a woman headed household? 1. Yes 2. No

29. Is it a household owned by physically handicapped? 1. Yes 2. No

30. Main Occupation of the Head of the Household (Main Source of Income) 1. Agriculture; 2. Commercial /business; 3. Service Holder; 4. Others (Specify)…………

31. Total Annual income of the family (Rs.)………….

32. How much you earn (Total Annual Income) from the affected Land / land to be acquired (Rs.) ………………………..

33. Willing to shift 1. Voluntarily; 2. Need Resettlement

34. Compensation Options: 1. Land for land loss; 2. Cash for Land loss; 3. House/Shop for House/ Shop loss; 4. Cash for House/ Shop loss

35. Desire Assistance and other help: 1. Shifting Allowance; 2. Employment Opportunities in Construction work; 3. Assistance/ Loan from other ongoing development scheme; 4. Training for Vocational activities 5. Others (specify ...... )

Details of the APs

Age Sex Occupation Marital Status Education Years 1. Male 1. Service 1. Married 1. Illiterate 2. 2. Business 2. Unmarried 2. Literate Sl. Name of the Family Female 3. Agriculture 3. Widow 3. Up to Nº Member 4. Study 4. Widower middle 5. Housewife 5. Others 4. Middle 6. Labour 5. Graduate 7. Unemployed 6. Above 8. Professional Graduate

Draft – August 2010 Page 23 Sustainable Power Sector Support II Project SRI 39415

1

2

3

4

5

6

7

8

9

10

11

12

13

Draft – August 2010 Page 24 Sustainable Power Sector Support II Project SRI 39415

ANNEXURE-3 BASELINE SOCIO-ECONOMIC SURVEY QUESTIONNAIRE (HOUSEHOLDS)

Identification Sheet

I. Schedule Nº 1.1 Name of the Project Site ______1.2 Address a. Village / Town b. Grama Niladari Division c. Divisional Secretary Division d. District e. Province 1.3 Type of settlement 01 Rural; 02 Semi- Urban; 03 Urban 1.4 Distance from the district centre (in Kms) 1.5 Distance from the province centre (in Kms) 1.6 Type of Respondent 01- Household, 02- Shops, 03. Small scale industry 1.7 Ethnicity of the Household 01. Sinhalese 02 Tamils 03 Muslims

A. Spot Check

B. Back Check

C. Result of the interview 01. Completed 02. Partially completed 03. Refused 04. Not

available

Name of Interviewer ______Name of Supervisor ______

Signature ______Signature ______

Date ______Date ______

Draft – August 2010 Page 25 Sustainable Power Sector Support II Project SRI 39415

2. HOUSEHOLD INFORMATION & ACCESS TO BASIC AMENITIES

Nº Question Coding categories codes Skip Coding boxes 201 What is the name of the head of the household? ______202 Ethnicity of the Sinhalese 01 Household Sri Lankan Tamil 02 Indian Tamil 03 Muslim. 04 Other (Specify) 05 06 203 Whether the household Yes 01 headed by a woman No 02 206 204 Name of the woman. ______

205 Current marital status of Widow 01 the woman War widow 02 Husband migrated 03 Divorced 04 Separated 05 Others ______06 Household composition

206 Children below 10 years 206.1 Male ______Males 206.2 Female 206.1 206.3 Total ______Females

______Females 206.2

206.3

207 Adult (10 to 60 years) 207.1 Male ______Males 207.2 Female 207.1 207.3 Total ______Females

______Females 207.2

207.3

208 Aged above 60 years 209.1 Male ______Males 209.2 Female 209.1 209.3 Total ______Females

______Females 209.2

209.3

209 What is the main source Piped water of drinking water for Piped into residence / yard / members of your plot 01 household? Public tap 02 Ground water (First 2 Responses) Hand pump in residence /

yard plot 03 Public hand pump 04 Well in residence / yard / plot 05 Public well 06 Draft – August 2010 Page 26 Sustainable Power Sector Support II Project SRI 39415

Nº Question Coding categories codes Skip Coding boxes Surface water Spring 07 River / stream 08 Pond / lake 09 Dam 10 Others specify ______77 210 Do you have electricity in Yes 01 the house? No 02 211 What kind of toilet facility Flush Toilet does your household Own flush toilet 01 have? Shared flush toilet 02 Public flush toilet 03 Pit toilet / Latrine Own pit toilet / latrine 04 Shared pit toilet / latrine 05 Public pit toilet / latrine 06 No facility / bush / field 07 Others ______77

3. HOUSEHOLD ECONOMY Nº Question Coding categories codes Skip Coding boxes Economic activities of the Household. 301 Agriculture is practiced at Yes 01 the household as No 02 301.1

301.1 Main activity 301.2 Allied activity 301.2 302 Working for other Yes 01 farmers is practiced at No 02 the household as 302.1

302.1 Main activity 302.2 302.2 Allied activity 303 Household having Small Yes 01 enterprise as No 02 303.1

303.1 Main activity 303.2 Allied activity 303.2 304 Government Job is Yes 01 practiced in the No 02 Household as 304.1

304.1 Main activity 304.2 304.2 Allied activity 305 Private Job is practiced in Yes 01 the Household as No 02 305.1

305.1 Main activity 305.2 Allied activity 305.2 306 Business / Trading is Yes 01 practiced in the No 02 Household as 306.1

306.1 Main activity 306.2 306.2 Allied activity 307 Daily Wage is practiced in Yes 01 the Household as No 02 307.1

307.1 Main activity 307.2 Allied activity 307.2 Draft – August 2010 Page 27 Sustainable Power Sector Support II Project SRI 39415

Nº Question Coding categories codes Skip Coding boxes 308 Others (specify) Yes 01 ______is No 02 practiced in the 308.1 Household as

308.1 Main activity 308.2 308.2 Allied activity 309 Do your household Yes 01 possess agricultural land? No 02 333 310 What is the total possession of the land ______(Hectares) by the household? 311 What is the total Cultivable land ______(Hectares) possessed by the household? 312 What is the total Non- Cultivable land ______(Hectares) possessed by the household? Cropping Patterns 313 Does your household Yes 01 cultivate rice? No 02 318 314 How many seasons rice One 01 is cultivated in a year? Two 02 Three 03 315 What is the total yield of rice your household gets? ______(Quintals) 316 What is the total yield of rice per hectare? ______(Quintals) 317 What is the average price per quintal of rice Rupees ______318 Does your household Yes 01 cultivate Potato/Cassava? No 02 323 319 How many seasons One 01 Potato/Cassava is Two 02 cultivated in a year? Three 03 320 What is the total yield of Potato/Cassava your ______(Quintals) household gets? 321 What is the total yield of Potato/Cassava per ______(Quintals) hectare? 322 What is the average price per quintal of Rupees ______Potato/Cassava 323 Does your household Yes 01 cultivate Vegetables? No 02 328 324 How many seasons One 01 Vegetables is cultivated in Two 02 a year? Three 03 325 What is the total yield of Vegetables your ______(Quintals) household gets?

Draft – August 2010 Page 28 Sustainable Power Sector Support II Project SRI 39415

Nº Question Coding categories codes Skip Coding boxes 326 What is the total yield of Vegetables per hectare? ______(Quintals) 327 What is the average price per quintal of Vegetables Rupees ______328 Does your household Yes 01 cultivate Fruits? No 02 328 329 How many seasons Fruits One 01 is cultivated in a year? Two 02 Three 03 330 What is the total yield of Fruits your household ______(Quintals) gets? 331 What is the total yield of Fruits per hectare? ______(Quintals) 332 What is the average price per quintal of Fruits Rupees ______328 What other item does Yes 01 your household cultivate No 02 please specify______? 329 How many seasons this One 01 item is cultivated in a Two 02 year? Three 03 330 What is the total yield of this item your household ______(Quintals) gets? 331 What is the total yield of this item per hectare? ______(Quintals) 332 What is the average price per quintal of this item Rupees ______Annual Income 333. Types of sources 334. whether any earning from the 335. Annual income in sources Rupees 01. Yes 02. No a Agriculture b Service c Business d Labour e Professional F Any other ______g Total from all Sources CONSUMPTION PATTERN Kindly indicate the consumption/expenditure on different items in last one year. Particulars / Source Annual Expenditure (Rs.) 336.1 Food 336.2 Transportation 336.3 Clothing 336.4 Health 336.5 Education Draft – August 2010 Page 29 Sustainable Power Sector Support II Project SRI 39415

Nº Question Coding categories codes Skip Coding boxes 336.6 Communication 336.7 Social functions 336.8 Agriculture (such as seeds, hiring of farm implements etc.) 336.9 Consumption of fuel for household 336.10 Electric Bill 336.11 Others (Specify)______Does your household own any of the following (Ask about each item separately)

337 Radio Yes 01 No 02 338 Bicycle Yes 01 No 02 339 Television Yes 01 No 02 340 L.P.G Connection/ Gas Yes 01 Cylinder No 02 341 Computer Yes 01 No 02 342 Refrigerator Yes 01 No 02 343 Washing Machine Yes 01 No 02 344 Motor cycle/Scooter Yes 01 No 02 345 Car Yes 01 No 02 346 Air Conditioner Yes 01 No 02 Indebtedness

347 Do you have any Yes 01 outstanding loan or debt? No 02 354 348 Please indicate your borrowings during last Rs______one year (in Rs) 349 What was the money Meeting the medical used for? expenses 01 To repay debts 02 (First 3 Responses) On food 03 On education 04 To start/upgrade business 05 Helping relatives 06 Improvement in house 07 Social obligation (Marriage / rituals / funerals) 08 Religious visit 09 Durable goods 10 To meet the daily Expenses 11 Others

Draft – August 2010 Page 30 Sustainable Power Sector Support II Project SRI 39415

Nº Question Coding categories codes Skip Coding boxes specify______77

350 To whom do you owe the Banks 01 money? Local /private money lender 02 Shopkeeper/traders 03 (First 2 Responses) NGO /Self Help Group (SHG) 04 Relative/friends 05

Chit Fund/Committee 06 Government Scheme 07 Others specify______77 351 Please specify the interest rate you usually pay on a loan to the different sources per year

351. Banks

1 351. Local / Pvt money lender

2 351. NGO /Self Help Group

3 (SHG 351. Relative/friends

4 351. Chit fund / committee

5 351. Government scheme

6 351. Others ______

7 352 Do you manage to make Yes, always 01 F354 your repayments on time? Some times 02 No 03 353 How have you handled Take another loan 01 this situation? Pay more interests 02 Sell Jewellery 03 (First 2 Responses) Borrow from relatives 04

Sell other HH assets 05 Others specify______77 COVERAGE UNDER GOVERNMENT DEVELOPMENT SCHEMES 354 Have you availed any Yes 01 benefit from different No 02 schemes? 355 From which source you Government 01 have received the Ngo 02 benefit? Funding Agency 03 Others ______04 (First 2 Responses) 356 What type of help you Loan 01 have received? Training 02 Employment 03 (First 2 Responses) Grant 04

357 If received loan, (01 in 356) then kindly indicate Rs______the amount you have NA 99 received? 358 If received training, (02 in 356) then kindly indicate ______the type of training you NA 99 have received?

Draft – August 2010 Page 31 Sustainable Power Sector Support II Project SRI 39415

Nº Question Coding categories codes Skip Coding boxes 359 After availing this scheme Yes 01 did your annual income No 02 increase? 360 If Yes, by what percentage it has 360.1______% 360.1 increased and amount? 360.2 Rs______360.2 361 If No (02 in 359) then what is the reason? ______

4. HEALTH STATUS No. Question Coding categories codes Skip Coding boxes General Health 401 If Someone falls sick in Private Doctor/Clinic 01 your family where does Government Doctors/Health he/she go for consultation Centres 02 or treatment? (Usually) NGO run health centre 03 Village Quacks 04 Pharmacist / Medicine Store 05 Others______77 402 Why do you prefer these Doctor is known to us 01 places? Doctor is nearby/facility is nearby 02 Doctor is good/staff is good 03 Medicine is effective 04 Treatment is free or less costly 05 Others ______77

402 What is the health facility Sub centre 01 nearest to your village? Dispensary 02 PHC / CHC 03 Govt. hospital 04 Facility by NGO 05 Private Health Facility 06 Village Quack 07 Other (specify)______77 403 Where is it located? Within the Village 01 406 Outside the Village 02 404 How far is the facility from your village? ______Kms

405 What are the modes of Public transport 01 transport available to Vehicle from health facility 02

reach the facility? Pvt. transport 03 Bullock cart 04 (Multiple Response) Others ______77

406 Was any member of your Yes 01 family affected by any No 02 410 major illness during the last one year? 406 How many members in your family were ill? ______Nos.

408 What type of illness they Respiratory Problems 01

Draft – August 2010 Page 32 Sustainable Power Sector Support II Project SRI 39415

No. Question Coding categories codes Skip Coding boxes suffered from? General Fever 02 408.1 Malaria 03

408.1 Member 1 Typhoid 04 408.2 408.2 Member 2 Gastro Intestinal Problems 05 408.3 Member 3 Non-communicable diseases 06 408.3 Diarrhoea 07 Jaundice 08 Diabetes 09 Tuberculosis 10 Others ______11 Not Applicable 12 409 What type of treatment Allopathic 01 they have taken? Homeopathic 02 Herbal 03 Traditional 04 No Treatment 05 410 Did any woman in your Yes 01 household deliver a baby No 02 414 in the last 3 years? 411 Where was the baby At home 01 delivered? At govt. health facility 02 (Probe for the youngest At Pvt. Health facility 03 baby at home who is less At Charitable Health centre 04 than 3 years) Others ______05 412 Doctor 01 Who assisted the delivery ANM / LHV 02 at home? Mid wife 03

Elderly women / family 04 (Ask to those HH where members 05 the baby is delivered at Local quacks 06 home) Others ______07 413 Health Facility is far 01 Better care at home 02 Can’t afford health facility What was the reason that expenses 03 the baby was delivered at Inadequate time to go to home? facility 04

Poor quality health service 05 (First 2 Responses) Customary 06 Others ______07

414 Where did you get most At home 01 of the antenatal check up At govt. health facility 02 done? At Pvt. Health facility 03 (ask about the woman At Charitable Health centre 04

who have delivered Others ______05 during the last 3 years) (First 2 Response) 415 During the last pregnancy how many times the ______times pregnant woman visited a health facility for antenatal check up? 416 Are you satisfied with the Very satisfied quality of service you Satisfied received during the Not so satisfied antenatal check ups? Very dissatisfied

Draft – August 2010 Page 33 Sustainable Power Sector Support II Project SRI 39415

5. Migration Nº Question Coding categories codes Skip Coding boxes General Health 501 Do you or family Yes 01 members migrate for No 02 work? 502 If yes, No. of members 502. 1 ______Males 502.1 502. 1 Males 502.2 ______Females 502.2 Females 502.2 503 Whether migrated Individually 01 individually or with the With Family 02 family? 504 What is the Place of Within the district 01 Migration? Other districts 02

Capital city 03 (take responses Outside of the country 04 according to the number of members migrated) 505 What kind of job do they Agricultural Labour 01

take (Males)? Non- Agricultural Labour 02 505.1 Trade & Business 03 505.1 Member 1 Others ______04 505.2 505.2 Member 2 505.3 Member 3 505.3 506 What kind of job do they Agricultural Labour 01

take (Males)? Non- Agricultural Labour 02 506.1 Trade & Business 03 506.1 Member 1 Others ______04 506.2 506.2 Member 2 506.3 Member 3 506.3 507 What are the total earnings of the members those who have migrated Rs______for work in a month?

508 At what time of the year Summer 01 do you / they migrate? Winter 02 Rainy season 03

6. STATUS OF WOMEN (Please fill this section by interviewing the women of the household preferably the spouse or an adult) Nº Question Coding categories codes Skip Coding boxes Economic Activities 501 Kindly indicate what kind of economic/ non-economic activities female members of your family are engaged in? 501. Cultivation Yes 01 1 No 02 502. Allied Activities (Dairy, Yes 01 1 Poultry, Sheep rearing, No 02 etc) 503. Collection and Sale of Yes 01 1 forest products No 02 504. Yes 01 Trade & Business 1 No 02 505. Yes 01 Agricultural Labour 1 No 02

Draft – August 2010 Page 34 Sustainable Power Sector Support II Project SRI 39415

Nº Question Coding categories codes Skip Coding boxes 506. Yes 01 Non-Agricultural Labour 1 No 02 507. Yes 01 HH Industries 1 No 02 508. Yes 01 Service 1 No 02 509. Yes 01 Households Work 1 No 02 501. Others (Specify): Yes 01 10 …………….. No 02 502 If, engaged in economic activities how much they contribute to total family Rs______income of the year 503 Does your female member have any say, in decision making of household matters on the following issues? 503. Financial matters 1 503. Education of child 2 503. Yes 01 Health care of child 3 No 02 503. Yes 01 Purchase of assets 4 No 02 503. Yes 01 Day to day activities 5 No 02 503. On social functions and Yes 01 6 marriages No 02 503. Yes 01 Others……… 7 No 02 504 Please tell me what is the time spent on different activities of the household in a normal day (24 hours) 504. Cooking 1 ______Hrs 504. Cleaning (House, clothes, 2 utensils, etc) ______Hrs 504. Fuel wood collection 3 ______Hrs 504. Water collection 4 ______Hrs 504. Daily marketing 5 ______Hrs 504. Caring for the young and 6 sick ______Hrs 504. Watching TV (other 7 leisure activities) ______Hrs 504. Any others ______8 ______Hrs 505 How safe do you regard Yes (feel safe) 01 the neighbourhood / To some extent 02 village for women and No 03 children during the day Don’t know / can’t say 04 time? 506 How safe do you regard Yes (feel safe) 01 the neighbourhood / To some extent 02 village for women and Not at all safe 03 children during the night Don’t know / can’t say 04 time? 507 Do the women of your Can move freely 01 household can freely go Only during the day time 02

Draft – August 2010 Page 35 Sustainable Power Sector Support II Project SRI 39415

Nº Question Coding categories codes Skip Coding boxes outside to work, for No cannot move freely 03 marketing, or accessing Cant say / don’t know 04 hospitals, educational institutes, etc? 508 How often women of your Never 01 510 household go outside the Every day 02 house to fetch water in a 1 to 2 days 03 week? 3 to 4 days 04 5 to 6 days 05 509 Does the woman have Yes 01 easy access to get water No 02 from out side? 510 Do you have a toilet at Yes 01 512 your household? No 02 511 Can a woman access Yes 01 public toilets and bathing No 02 facilities in the evening easily? 512 Do you have adequate Yes adequate 01 street lighting during the Yes, but only sometimes 02 night? No street light 03 513 Do you think the provision Yes 01 of adequate street lights No 02 will result in the increase of the women’s mobility during the evening?

6. EDUCATION Nº Question Coding categories codes Skip Coding boxes 601 Kindly provide information on the household members those who are 6 years and above.

602 What is the total number of children attending pre – 602.1 ______Male nursery classes? 602.2 ______Female 602.1 602.3 ______Total 602.1 Male 602.2 602.2 Female

602.3 Total 602.3

603 What is the total number of children attending / 603.1 ______Male

attended primary level of 603.2 ______Female 603.1 education? 603.3 ______Total

603.1 Male 603.2 603.2 Female 603.3 Total 603.3

604 What is the total number of members attending / 604.1 ______Male

attended secondary level 604.2 ______Female 604.1 of education? 604.3 ______Total

604.1 Male 604.2 604.2 Female 604.3 Total 604.3

605 What is the total number

of members attending / 605.1 ______Male 605.1 attended Graduation level 605.2 ______Female

Draft – August 2010 Page 36 Sustainable Power Sector Support II Project SRI 39415

Nº Question Coding categories codes Skip Coding boxes of education? 605.3 ______Total 605.2

605.1 Male 605.3 605.2 Female 605.3 Total

606 What is the total number of members illiterate in 606.1 ______Male the household? 606.2 ______Female 606.1 606.3 ______Total 606.1 Male 606.2 606.2 Female

606.3 Total 606.3

7. STRUCTURE/ BUILDING INFORMATION Nº Question Coding categories codes Skip Coding boxes 701 What is the use of the Residential 01 structure? Commercial 02 Residential cum commercial 03 Others 04 702 What is the age of the structure in years? ______years 703 Please specify the type of Simple (thatch / sack / construction on the bamboo / slats) 01 following items of the Earth/clay/sand 02 household? Wood 03 703.1 Brick 04 703.1 Roof Concrete 05 703.2 703.2 Floor Corrugated iron sheet 06

703.3 Wall Tile 07 703.3 Asbestos sheet 08 Others ______09 704 What is the distance of the structure from the ______Kms project site (km) 705 What is the type of the Temporary 01 structure? Semi permanent 02 Permanent 03 706 What is the total number of rooms available in this ______Nos. structure? 707 How many rooms are lighted in your house? ______Nos. 708 How many rooms are cooled in your house? ______Nos.

8. ENERGY USAGE Nº Question Coding categories codes Skip Coding boxes 801 Is your house electrified? Yes 01 No 02 834 802 Where do you get the Government 01 power supply from? Community Based 02 Own Arrangement 03 Govt. & Community 04 Govt. & Own Arrangement 05 Community & own 06 arrangement 07 All of above 08 Draft – August 2010 Page 37 Sustainable Power Sector Support II Project SRI 39415

Nº Question Coding categories codes Skip Coding boxes 803 What is the main source Govt. grid 01 of electricity? Micro-hydro power 02 Generator 03 Solar 04 Bio-gas 05 Others ______06 804 Since when your house / structure have been ______years electrified? (in years) 805 How many hours per day

electricity is usually 805.1 ____ Hrs in Summer 805.1 available during 805.2 ____ Hrs in Winter 805.1 Summer 805.3 ____ Hrs in Monsoon 805.2 Winter 805.2 805.3 Monsoon 805.3 806 Do you use electricity for Yes 01 lighting? No 02 808

807 What is the duration of consumption for lighting? ______hrs 808 Do you use electricity for Yes 01 cooking? No 02 810

809 What is the duration of consumption for cooking? ______hrs 810 Do you use electricity for Yes 01 heating and cooling? No 02 812

811 What is the duration of consumption for heating ______hrs and cooling? 812 Do you use electricity for Yes 01 pumping water? No 02 814

813 What is the duration of consumption for pumping ______hrs water? 814 Do you use electricity for Yes 01 running TV and tape No 02 816 recorder?

815 What is the duration of consumption for TV and ______hrs tape recorder? 816 Do you use electricity for Yes 01 computer? No 02 818 817 What is the duration of consumption for ______hrs computer? 818 Do you use electricity for Yes 01 running business? No 02 820 819 What is the duration of consumption for running ______hrs business? 820 Please specify the number of following electrical appliances you have at your household?

820. Lamps 1 ______Nos. 820. Heater 2 ______Nos. Draft – August 2010 Page 38 Sustainable Power Sector Support II Project SRI 39415

Nº Question Coding categories codes Skip Coding boxes 820. Fans 3 ______Nos. 820. TVs 4 ______Nos. 820. Washing Machines 5 ______Nos. 820. Water Pumps 6 ______Nos. 820. Air conditioners 7 ______Nos. 820. Refrigerators 8 ______Nos. 820. Others______9 ______Nos. 821 Is there any meter Yes 01 system? No 02 823 822 If yes what is the unit rate of your electric bill. Rs. ______823 ______If No how it is managed? ______

824 How much is the usual monthly consumption of ______units electricity (watt/kilowatt/units)? (please check the last month bill) 825 Where do you pay the bill? ______826 What is the frequency of Monthly 01 payment of your bill? Bi-monthly 02 Quarterly 03 yearly 04 827 Is there electric theft Yes 01 cases? No 02 828 Who is responsible for the maintenance? ______829 Do you use other non- Yes 01 electric energy source No 02 even if your house is electrified?

If yes please give the details. 831 Hrs of 832 Quantity of 830 Source of Usage 833 Expenditure (Rs) Consumption Consumption 1 Kerosene/ Diesel

2 Battery

3 Wood

4 Gas

5 Solar

6 Other

To be asked those who do not have electricity. Usage Pattern (Put 01 for Yes and 02 for No)

Draft – August 2010 Page 39 Sustainable Power Sector Support II Project SRI 39415

Nº Question Coding categories codes Skip Coding boxes Source 834 Lighting 835 Cooking 836 Heating

1 Kerosene/ Diesel

2 Battery

3 Wood

4 Gas

5 Solar

6 Other ______837 Please specify the number of assets used for lighting, heating and cooking (non-electric)

837. Kerosene/Diesel Lamps 1 _____ Nos 837. Battery Lamps 2 _____ Nos 837. Gas Cylinders 3 _____ Nos 837. Solar Panel 4 _____ Nos 837. Other Specify 5 _____ Nos 838 What is the monthly expenditure and hours of 838.1 Rs. ______838.1 consumption of using kerosene / diesel lamp for 838.2 ______Hrs lighting? 838.2 839 What is the monthly 839.1 Rs. ______expenditure and hours of 839.1

consumption of using 839.2 ______Hrs battery lamps for lighting? 839.2 840 What is the monthly 840.1 Rs. ______expenditure and hours of 840.1

consumption of using gas 840.2 ______Hrs cylinders for lighting? 840.2 841 What is the monthly 841.1 Rs. ______expenditure and hours of 841.1

consumption of using 842.2 ______Hrs solar panels for lighting? 841.2 842 What is the monthly expenditure and hours of 843.1 Rs. ______842.1 consumption of other sources like ______for 844.2 ______Hrs lighting? 842.2 843 What would you prefer to pay if you get electricity at Rs______your place? 844 Ask this question to the Will use for lighting 01 woman of the Will use for cooking 02 household For heating and cooling 03 Will use TV and radio 04 What are the types of For pumping water 05 usages you would prefer Others ______06 if you get electricity connection at your home?

(Multiple response Draft – August 2010 Page 40 Sustainable Power Sector Support II Project SRI 39415

Nº Question Coding categories codes Skip Coding boxes possible)

9. Opinion about the Current Status of Energy Usage Nº Question Coding categories codes Skip Coding boxes 901 Are you satisfied with the Yes 01 current electric flow to No 02 your house? 902 Are you satisfied with the Yes 01 non-electric energy in No 02 your house? 903 Do you think Diesel Yes 01 Generator create inner No 02 pollution in the house? 904 Do you think use of Yes 01 diesel/kerosene fuel is No 02 expensive? 905 Do you think there is a Yes 01 requirement of electric No 02 power supply to your area? 906 Will you be willing to pay Yes 01 the bill regularly if you are No 02 provided with the electricity? 907 How much increase ((%) can you afford to pay compared to your current amount of electric billing ( ______% To be asked to Electrified Households) 909 How much can you afford Yes 01 to pay per month for the No 02 electricity bill if your house is connected with electricity (To be asked to Non-Electrified Households 910 What will be your usage Yes 01 pattern if you are given a No 02 regular electric power 911 Will you cooperate to Yes 01 minimise the theft (if No 02 occurs) and responsible for maintenance of the power supply? 912 How much extra power do you need for your ______% household usage (%)? 913 Do you think the Yes 01 proposed project will help No 02 in increasing the living standard and help in minimising poverty?

ANY OTHER ISSUES (COMMENTS/ SUGGESTIONS)

Draft – August 2010 Page 41 Sustainable Power Sector Support II Project SRI 39415

ANNEXURE - 4 FINDINGS ON THE BASELINE SOCIO-ECONOMIC SURVEY

1.1 General 1 Socio-economic details of the project area were collected based on a sample survey. In addition to the demographic and social data collected during census survey, socio-economic information was collected from project area through a structured socio-economic baseline questionnaire. This socio-economic questionnaire was administered in the project area. A total of 1,500 sample households were surveyed as part of the socio-economic survey in the project area and 301 households in the non-project area.

1.2 Socio-economic Details 2. The following section deals with various socio-economic indicators of the households.

1.3 Type of Settlement 3. The sub project areas on a larger scale belong to the rural area which shows that out of the 1,500 households, 1,405 (93.67%) households reside in rural areas. Various types of settlements in the project area covered during the survey are given in Table 1 shown as beneficiary. Similarly in the non-project area which is shown as control group in Table 1, 270 (89.7 %) belong to rural area.

Table 1: Type of Settlement Sl Nº Beneficiary Control Group Type of Settlement Nº %Age Nº %Age 1 Rural 1,405 93.67 270 89.70 2 Semi-Urban 89 5.93 31 10.30 3 Urban 6 0.40 0 0.00 Total 1,500 100.00 301 100.00

1.4 Type of Settlement 4. In the sub project area about 98 % and about 99.34 % are households. Details on the type of respondents in the sub-project and non-project area are shown in Table 2.

Table 2: Type of Respondents Sl Nº Type of Beneficiary Control Group Respondents Nº %Age Nº %Age 1 Households 1,471 98.07 299 99.34 2 Shops 27 1.80 2 0.66 3 Small scale industry 2 0.13 0 0.00 Total 1,500 100.00 301 100.00

1.5 Ethnicity 5. In the sub-project area majority about 85.93 % belongs to Sinhalese ethnic group and about 8.87 % are Tamils. Similarly in non-project area 82 % are Tamils and Sinhalese comprise about 17.94 %. Details are given in Table 3.

Table 3: Ethnicity of Households Sl Nº Beneficiary Control Group Ethnicity Nº %Age Nº %Age 1 Sinhalese 1,289 85.93 54 17.94 2 Tamils 133 8.87 247 82.06 3 Muslims 19 1.27 0 0.00 4 Thelingu 59 3.93 0 0.00 Total 1,500 100.00 301 100.00

1.6 Women Headed Households 6 In the project area about 11.8 % of the households are headed by women and similarly in non- project area about 23.59 % are headed by a woman. Details are given in Table 4. Draft – August 2010 Page 42 Sustainable Power Sector Support II Project SRI 39415

Table 4: Women Headed Household Sl Nº Beneficiary Control Group Women headed Nº %Age Nº %Age 1 Yes 177 11.80 71 23.59 2 No 1,323 88.20 230 76.41 Total 1,500 100.00 301 100.00

1.7 Demographic Features of APs 7 The total households covered during the socio-economic sample survey are 1500 in sub project area and 301 in non-project area. The average family size is 4.18 and the sex ratio of the project affected population is 971 females: 1000 males.

8 Similarly in the non-project area the average family size is 3.36 and the sex ratio of the project affected population is 1,040 females per 1,000 males. Details are given in Table 5.

Table 5: Demographic Feature Sl Nº Particulars Beneficiary Control Group Number/% Age Number/% Age 1 Total Household 1,500 301 2 Sex Ratio 971 1,040 3 Average Household Size 4.18 3.36

1.8 Literacy 9 The total literacy is reported to be 62.22 % in the subproject area. The literacy indicator shows that 34.87 % of the males and amongst females about 31.77 % have attended secondary level. Only about 1 % have attended graduation or above level. Details are given in Table 6.

Table 6: Education of Households (Beneficiary) S.Nº Category Male Female Total Nº % Nº % Nº % 1 Pre-School 118 5.68 83 4.13 201 4.92 2 Primary 472 22.74 467 23.26 939 22.99 3 Secondary 724 34.87 638 31.77 1,362 33.35 4 Graduation 20 0.96 19 0.95 39 0.95 5 Illiterate 742 35.74 801 39.89 1,543 37.78 Total 2,076 100.00 2,008 100.00 4,084 100.00

10 Similarly in the non-project area the total literacy is reported to be 67.44 % in the subproject area. The literacy indicator shows that 37.64 % of the males and amongst females about 29.13 % have attended secondary level. Details are given in Table 7.

Table 7: Education of Households (Control Group) S.Nº Category Male Female Total Nº % Nº % Nº % 1 Pre-School 20 5.62 20 5.25 40 5.43 2 Primary 97 27.25 114 29.92 211 28.63 3 Secondary 134 37.64 111 29.13 245 33.24 4 Graduation 0 0.00 1 0.26 1 0.14 5 Illiterate 105 29.49 135 35.43 240 32.56 Total 356 100.00 381 100.00 737 100.00

1.9 Source of Drinking Water 11 In the project area well is the major source of water for the households. About 74.53 % are depended on well and 12.30 % are depended on pipe water. Similarly in the non-project area 46.78 % are depended on well and about 42.71 % are depends on public hand pump. Details are given in Table 8.

Draft – August 2010 Page 43 Sustainable Power Sector Support II Project SRI 39415

Table 8: Source of Drinking Water Sl Nº Beneficiary Control Group Source of Drinking water Nº %Age Nº %Age 1 Piped into residence / yard / plot 184 12.30 20 6.78 2 Public tap 63 4.19 10 3.39 3 Hand pump in residence / yard plot 15 1.01 0 0.00 4 Public hand pump 34 2.30 129 42.71 5 Well in residence / yard / plot 627 41.82 18 6.10 6 Public well 472 31.49 122 40.68 7 Spring 7 0.47 0 0.00 8 River / Stream 60 3.99 0 0.00 9 Pond / lake 3 0.20 0 0.00 10 Pvt Shared well 10 0.68 0 0.00 11 Neighbour's Well 8 0.54 0 0.00 12 Others 15 1.01 1 0.34 Total 1500 100.00 301 100.00

1.10 Types of Toilet 12 About 78.67 % of the households in the project area have own flush toilets at their households. About 7.13 % have no facilities and use bush, open space for defecating. On the other hand in the non- project area majority about 82 % have no toilet facility at their household. Details are given in Table 9.

Table 9: Types of Toilet Sl Nº Beneficiary Control Group Toilet Nº %Age Nº %Age 1 Own flush toilet 1,180 78.67 39 12.96 2 Shared flush toilet 95 6.33 3 1.00 3 Public flush toilet 1 0.07 0 0.00 4 Own pit toilet / latrine 94 6.27 10 3.32 5 Shared pit toilet / latrine 7 0.47 0 0.00 6 No facility / bush / field 107 7.13 247 82.06 7 Others 16 1.07 2 0.66 Total 1,500 100.00 301 100.00

1.11 Major Economic Activities 13 In the project area agriculture is practiced as the main activity by 44.13 % of the households followed by daily wage earners 27.20 %. Similarly about 17.27 % have government jobs and 3.33 % are in private jobs. Details are given in Table 10.

14 Similarly in the non-project area daily wage earner as the main activity is done by 44.13 % of the households. About 39.43 % are practicing agriculture. Similarly about 4.32 % have government jobs and 1 % are in private jobs. Details are given in Table 10.

Table 10: Types of Occupation Sl Beneficiary Control Group Nº Occupation Main Activity Allied Activity Main Activity Allied Activity Nº %age Nº %age Nº %age Nº %age 1 Agriculture 662 44.13 106 7.07 119 39.53 18 5.98 2 Working for other farmers 130 8.67 89 5.93 28 9.30 14 4.65 3 Small enterprise 34 2.27 8 0.53 2 0.66 0 0.00 4 Government Job 259 17.27 34 2.27 13 4.32 6 1.99 5 Private Job 50 3.33 15 1.00 3 1.00 0 0.00 6 Business / Trading 63 4.20 12 0.80 5 1.66 2 0.66 7 Daily Wage 408 27.20 89 5.93 136 45.18 15 4.98 8 Others 90 6.00 7 0.47 31 10.30 8 2.66 Total 1,500 100.00 1,500 100.00 301 100.00 301 100.00 Draft – August 2010 Page 44 Sustainable Power Sector Support II Project SRI 39415

1.12 Agricultural Land 15 In the sub project area about 56.13 % of the households have agricultural land where as in the non- project area about 51.16 % of the households possess agricultural land. Details are given in Table 11.

Table 11: Possession of Agricultural Land Sl Nº Beneficiary Control Group Possess Land Nº %Age Nº %Age 1 Yes 842 56.13 154 51.16 2 No 658 43.87 147 48.84 Total 1,500 100.00 301 100.00

1.13 Type of Land 16 In the project area a total of 778.20 hectares land is possessed by 841 households with an average possession of 0.93 hectares. About 81.7 % (635.83 hectares) of the total land is cultivable. Similarly in the non-project area a total of 145.21 hectares land is possessed by 154 households with an average possession of 0.94 hectares. About 88.86 % (129.04 hectares) of the total land is cultivable. Details are given in Table 12.

Table 12: Possession of Types of Land (Hectares) Sl Nº Land type Beneficiary Control Group Total Average Total Average Nº of Land in Possession Nº of Land in Possession HH Hectares in Hectares HH Hectares in Hectares 1 Cultivable Land 793 635.83 0.80 138 129.04 0.94 2 Non-Cultivable 404 142.37 0.35 44 16.17 0.37 Total 841 778.20 0.93 154 145.21 0.94

1.14 Cropping Pattern 17 In the project area rice is cultivated by 73.72% of the households those have agricultural land followed by vegetable (7.25 %). Similarly in the non-project area rice is cultivated by 92.86 % of the households those have agricultural. Details are given in Table 13.1.

Table 13.1: Cropping Pattern Sl Nº Beneficiary Control Group Types of Crop Nº %Age Nº %Age 1 Rice 620 73.72 143 92.86 2 Potato/Cassava 14 1.66 2 1.30 3 Vegetables 61 7.25 1 0.65 4 Fruits 15 1.78 1 0.65 5 Others 131 15.58 7 4.55 Total 841 100.00 154 100.00

18 Moreover in the project area rice is cultivated once a year by 45 % of the households and the rest 55 % cultivates for two seasons in a year. Similarly out of the 61 households those cultivate vegetables about 54 % cultivate for a one season in a year and 39.34 % cultivate twice in a year. Details are given in Table 13.2

Table 13.2: Number of Seasons Sl Nº Beneficiary & Nº of Seasons Agricultural One Two Three Total products Nº %age Nº %age Nº %age Nº %age 1 Rice 279 45 341 55.00 0 0 620 100.00 2 Potato/Cassava 8 57 6 42.86 0 0 14 100.00 3 Vegetables 33 54 24 39.34 4 6.56 61 100.00 4 Fruits 8 53 4 26.67 3 20.00 15 100.00 5 Others 106 81 20 15.27 5 3.82 131 100.00 Draft – August 2010 Page 45 Sustainable Power Sector Support II Project SRI 39415

19 Similarly in the non-project area rice is cultivated once a year by 49 % of the households and the rest 51 % cultivates for two seasons in a year. Details are given in Table 13.3

Table 13.3: Number of Seasons Sl Nº Control Group & Nº of Seasons Agricultural One Two Three Total products Nº %age Nº %age Nº %age Nº %age 1 Rice 66 49 68 51 - - 134 100 2 Potato/Cassava 2 - 0 - - - 2 - 3 Vegetables 1 - - - - - 1 - 4 Fruits 1 - - - - - 1 - 5 Others 7 - - - - - 7 -

1.15 Average Yield 20 In the project area the average yield of rice are 37 quintals, potato 9.88 quintals, fruits 9.30 quintals and vegetables 7 quintals. Similarly in the non-project area the average yield of rice is 33.9 quintals. Details are given in Table 14.

Table 14: Average Yield in Quintals Sl Nº Beneficiary Control Group Types of Crop Average Average Nº Yield Nº Yield 1 Rice 620 36.99 134 33.90 2 Potato/Cassava 14 9.88 2 1.25 3 Vegetables 61 7.08 1 0.5 4 Fruits 15 9.30 1 1.50 5 Others 130 21.42 7 6.82 Total 620 36.99 134 33.90

1.16 Source of Earnings 21 Agriculture is the major source of earnings for 48.33 % of the households in the Project area followed by income from labour (39.27 %). The next income is from service and profession. On the other hand in the non-project area majority of the households reported earnings from labour (58.14%) followed by agriculture (39.20 %). Details are given in Table 15.

Table 15: Source of Earnings Sl Nº Beneficiary Control Group Source Nº %Age Nº %Age 1 Agriculture 725 48.33 118 39.20 2 Service 188 12.53 7 2.33 3 Business 109 7.27 9 2.99 4 Labour 589 39.27 175 58.14 5 Professional 150 10.00 16 5.32 6 Fishing 21 1.40 5 1.66 7 Petty Trade/ Pvt Job 14 0.93 4 1.33 8 Others 202 13.47 51 16.94 Total 841 100.00 301 100.00

1.17 Annual Income 22 The total average income from all sources in the project area is Rupees 171,983.82. The average annual earnings of the professionals are maximum amongst all the sources of income. The professionals earn about Rupees 222,124.80 per year. The average annual income from the services is the next highest income. The average annual income from the service is rupees 206,206.81. As already discussed, agriculture is practiced by majority of the households and the average annual income from agriculture is rupees 102,352.96. Details are given in Table 16.

Draft – August 2010 Page 46 Sustainable Power Sector Support II Project SRI 39415

23 Similarly the total average income from all sources in the non-project area is Rupees 106,056.42. The average annual earnings of the service holders are maximum amongst all the sources of income. The service doing households earn about Rupees 247,171.43 per year. The average annual income from the professional is the next highest income. The average annual income of the professionals is rupees 183,412.50. As already discussed, agriculture is practiced by majority of the households and the average annual income from agriculture is rupees 71639.41. Details are given in Table 16.

Table 16: Average Annual Earnings from different Sources in LKR Sl Nº Sources Beneficiary Control Group 1 Agriculture 102,352.96 71,639.41 2 Service 206,206.81 247,171.43 3 Business 164,344.95 60,222.22 4 Labour 104,938.98 77,309.71 5 Professional 222,124.80 183,412.50 6 Fishing 929,33.33 63,200.00 7 Petty Trade/ Pvt Job 84,892.86 102,500.00 8 Others 98,407.50 51,545.10 Total (Average Earnings) 171,983.82 106,056.42

1.18 Expenditure Pattern 24 The total annual average expenditure per household is rupees 106,898/- in the project area. Major expenditure about 52.21 % is incurred on food followed by expenditure on transport (10.92%) and clothing (7.41 %). The expenditure on education is 7.30 %, agriculture 7.13 % and on health is 5.07 % in the project area.

25 Similarly the total annual average expenditure per household is rupees 68,506/- in the non-project area. Major expenditure about 59.18 % is incurred on food followed by expenditure on agriculture in 8.94 %, transport (8.32%) and clothing (6.52 %). The expenditure on education is 4.76 % and on health is 3.68 % in the non-project area. Details about the expenditure are described in Table 17.

Table 17: Expenditure pattern of the Household Beneficiary Control Group Sl Reported Annual %age to total Reported Annual %age to Total Nº Items HH Average Expenditure HH Average Expenditure 1 Food 1,496 55,811.80 52.21 299 40,538.8 59.18 2 Transport 1,496 11,672.57 10.92 299 5,702.84 8.32 3 Clothing 1,496 7,916.04 7.41 299 4,463.98 6.52 4 Health 1,496 5,421.39 5.07 299 2,519.56 3.68 5 Education 1,496 7,805.58 7.30 299 3,263.21 4.76 6 Communication 1,496 3,797.36 3.55 299 1,318.06 1.92 7 Social functions 1,496 1,609.73 1.51 299 612.70 0.89 8 Agriculture 1,496 7,623.86 7.13 299 6,124.83 8.94 9 Fuel 1,496 3,947.83 3.69 299 3,685.63 5.38 10 Electric Bill 1,496 699.74 0.65 299 276.39 0.40 11 Others 1,496 592.38 0.55 299 0.00 0.00 Total Expenditure 1,496 106,898.29 100.00 299 68,506.00 100.00

1.19 Possession of Assets 26 Possession of durable goods differs from each household depending on the nature of the durable goods. In the project area common durable goods are bicycles (65.27 %), radio (56.53 %), and television (36.33 %). Two wheelers are possessed by only 20 % of the households. The expensive items are possessed by vey less percentage of the households in the project area.

27 Similarly in the non-project area common durable goods are bicycles (47.18 %), radio (23.92 %), and television (9.30 %). Two wheelers are possessed by only 6.31 % of the households. The expensive items are possessed by vey less percentage of the households in the non-project area. Details are given in Table 18.

Draft – August 2010 Page 47 Sustainable Power Sector Support II Project SRI 39415

Table 18: Possession of Household Assets Sl Nº Beneficiary Control Group Assets Nº %Age Nº %Age 1 Radio 848 56.53 72 23.92 2 Bicycle 979 65.27 142 47.18 3 Television 545 36.33 28 9.30 4 L.P.G Connection/ Gas Cylinder 29 1.93 0 0.00 5 Computer 15 1.00 1 0.33 6 Refrigerator 53 3.53 9 2.99 7 Washing Machine 14 0.93 0 0.00 8 Motor cycle/Scooter 301 20.07 19 6.31 9 Car 27 1.80 3 1.00 10 Air Conditioner 13 0.87 0 0.00 Total 1,500 100.00 301 100.00

1.20 Indebtedness 28 In the project area about 9.27 % of the households have taken loan and in the non-project area about 3.32 % have loans. Details are given in Table 19.

Table 19: Indebtedness Sl Nº Beneficiary Control Group Any Loan Nº %Age Nº %Age 1 Yes 139 9.27 10 3.32 2 No 1361 90.73 291 96.68 Total 1500 100.00 301 100.00

1.21 Average Loan Amount 29 In the project area the average loan amount is rupees 85,884 and in the non-project area the average loan amount is 34,870. Details are given in Table 20.

Table 20: Amount Taken as Loan Sl Nº Amount in Sri Lankan Beneficiary Control Group Rupees Nº %Age Nº %Age 1 Up to 10,000 21 15.11 2 20.00 2 Rs. 10,001 to 20,000 19 13.67 2 20.00 3 Rs. 20,001 to 50,000 27 19.42 5 50.00 4 Rs. 50,001 to 100,000 46 33.09 1 10.00 5 Rs 100,001 to 200,000 18 12.95 0 0.00 6 More Than 2 Lakh 8 5.76 0 0.00 Total 139 100.00 10 100.00 Average Loan 85,884.89 34,870

1.22 Use of the Loan 30 In the project area about 40.29 % of the households out of 139 households those taken loan used the loan amount in the improvement of the house. The next major use is on the up gradation and investment in business. Similarly in the non-project area about 4 households have taken loan for improvement of the houses. Details are given in Table 21.

Table 21: Usage of the Loan Amount Sl Nº Beneficiary Control Group Usage Nº %Age Nº %Age 1 Medical Expenses 5 3.60 0 0.00 2 To repay debts 4 2.88 0 0.00 3 On food 2 1.44 0 0.00 4 To start/upgrade business 20 14.39 0 0.00

Draft – August 2010 Page 48 Sustainable Power Sector Support II Project SRI 39415

Sl Nº Beneficiary Control Group Usage Nº %Age Nº %Age 5 Helping relatives 1 0.72 1 10.00 6 Improvement in house 56 40.29 4 40.00 7 Durable goods 1 0.72 0 0.00 8 In Farming / Agriculture 7 5.04 0 0.00 9 Buy Vehicle 5 3.60 0 0.00 10 Building Home 1 0.72 0 0.00 11 Buying Land 1 0.72 0 0.00 12 Others 36 25.90 5 50.00 Total 139 100.00 10 100.00

1.23 Source of the Loan 31 In the project area about 56.12 % of the households took loans from the bank. In the project area, about 14.39 % took loans from the government schemes and 10.79 % from the private money lenders. In the non-project area, about 60 % of the households took loans from the banks. Details are given in Table 22.

Table 22: Source of the Loan Sl Nº Beneficiary Control Group Source Nº %Age Nº %Age 1 Bank 78 56.12 6 60.00 2 Local /private money lender 15 10.79 1 10.00 3 Shopkeeper/traders 1 0.72 1 10.00 4 NGO /Self Help Group 5 3.60 0 0.00 5 Relative/friends 3 2.16 0 0.00 6 Chit Fund/Committee 6 4.32 0 0.00 7 Government Scheme 20 14.39 1 10.00 8 Others 11 7.91 1 10.00 Total 139 100.00 10 100.00

1.24 Repayment 32 In the project area about 90.65 % of the households are able to pay the loan amount on time. Similarly in the non-project area about 80 % of the households are able to pay the loan amount on time. Details are given in Table 23.

Table 23: Managing Repayment Sl Nº Beneficiary Control Group Manage Nº %Age Nº %Age 1 Yes, Always 126 90.65 8 80.00 2 Some times 12 8.63 2 20.00 3 No 1 0.72 0 0.00 Total 139 100.00 10 100.00

1.25 Managing Crisis 33 In the project area out of 12 households who faced problems in repaying the loan amount, about 50% reported paying more interest to manage the crisis. Details are given in Table 24.

Table 24: Managing the crisis during payment Sl Nº Beneficiary Control Group Management of Crisis Nº %Age Nº %Age 1 Take another loan 3 25.00 1 50.00 2 Pay more interests 6 50.00 1 50.00 3 Borrow from relatives 1 8.33 0 0.00 4 Sell other HH assets 1 8.33 0 0.00 5 Others 1 8.33 0 0.00

Draft – August 2010 Page 49 Sustainable Power Sector Support II Project SRI 39415

Sl Nº Beneficiary Control Group Management of Crisis Nº %Age Nº %Age Total 12 100.00 2 100.00

1.26 Benefits from Schemes 34 In the project area about 23.73 % of the households received benefits from different schemes. Similarly in the non-project area about 49.17 % of the households received benefits from different schemes. Details are given in Table 25.

Table 25: Availing benefits from Schemes Sl Nº Any benefits from Beneficiary Control Group schemes Nº %Age Nº %Age 1 Yes 356 23.73 148 49.17 2 No 1,144 76.27 153 50.83 Total 1,500 100.00 301 100.00

1.27 Sources of Benefits 35 In the project out of 356 households those received benefits from the schemes about 96.91 % received it from the government and the rest received it from different NGOs. Similarly in the non-project area out of 148 households those received benefits from different schemes about 90.54 % received it from the government. Details are given in Table 26.

Table 26: Source of Benefits Sl Nº Beneficiary Control Group Source Nº %Age Nº %Age 1 Govt 345 96.91 134 90.54 2 NGO 21 5.90 49 33.11 3 Others 4 1.12 4 2.70 Total 356 100.00 148 100.00

1.28 Type of Help 36 In the project area out of 356 households those received benefits from the schemes about 96.63 % received grants and 2.53 % received loans. Similarly in the non-project area out of 148 households those received benefits from different schemes about 98.65 % received grants. Details are given in Table 27.

Table 27: Types of Help Sl Nº Beneficiary Control Group Types of help Nº %Age Nº %Age 1 Loan 9 2.53 1 0.68 2 Training 2 0.56 0 0.00 3 Employment 1 0.28 1 0.68 4 Grant 344 96.63 146 98.65 Total 356 100.00 148 100.00

37 The average amount received by the households in the project area is rupees 5938 and in the non- project area is rupees 348.60.

1.29 Type of Help 38 About 51.12 % admitted of increase in their annual income after receiving the benefits from scheme in the project area. Similarly in the non-project about 68.24 % admitted that their annual income has increased after receiving benefits from schemes. Details are given in Table 28.

Draft – August 2010 Page 50 Sustainable Power Sector Support II Project SRI 39415

Table 28: Reported Increase in Annual Income Sl Nº Beneficiary Control Group Increase in Income Nº %Age Nº %Age 1 Yes 182 51.12 101 68.24 2 No 174 48.88 47 31.76 Total 356 100.00 148 100.00

39 In the project area the annual income increased by 3.8 % and in the non-project area the increase is 5.34 %.

1.30 Treatment Seeking Places 40 In the project area about 81.07 % of the households reported visiting a government facility when someone falls sick at home. About 18.8 % visit a private facility. Similarly in the non-project about 96.68 % of the households reported visiting a government facility when someone falls sick at home. Details are given in Table 29.

Table 29: Treatment Seeking Places Sl Nº Beneficiary Control Group Health Facilities Nº %Age Nº %Age 1 Private Doctor/Clinic 282 18.80 10 3.32 2 Government Doctors/Health Centre 1,216 81.07 291 96.68 3 NGO run health centre 1 0.07 0 0.00 4 Village Quacks 1 0.07 0 0.00 Total 1,500 100.00 301 100.00

1.31 Reasons for Preferring Treatment Places 41 In the project area about 70.40 % of the households preferred a health facility as treatment is free or less costly. Similarly in the non-project about 85.05 % of the households preferred a health facility as treatment is free or less costly. Details are given in Table 30.

Table 30: Reasons for preferring the Treatment Places Sl Nº Beneficiary Control Group Reasons Nº %Age Nº %Age 1 Doctor is known to us 178 11.87 2 0.66 2 Doctor is nearby/facility is nearby 170 11.33 33 10.96 3 Doctor is good/staff is good 44 2.93 8 2.66 4 Medicine is effective 52 3.47 2 0.66 5 Treatment is free or less costly 1,056 70.40 256 85.05 Total 1,500 100.00 301 100.00

1.32 Nearest Place of Treatment Places 42 In the project area for 77.33 % of the households a government hospital is the nearest place of treatment. Similarly in the non-project a government hospital is the nearest place of treatment for 98.67 % of the households. Details are given in Table 31.

Table 31: Nearest Place of Treatment Sl Nº Beneficiary Control Group Nearest Place Nº %Age Nº %Age 1 Subcentre 38 2.53 0 0.00 2 Dispensary 240 16.00 1 0.33 3 PHC / CHC 3 0.20 0 0.00 4 Govt. hospital 1,160 77.33 297 98.67 5 Facility by NGO 5 0.33 2 0.66 6 Private Health Facility 54 3.60 1 0.33 Total 1,500 100.00 301 100.00

Draft – August 2010 Page 51 Sustainable Power Sector Support II Project SRI 39415

1.33 Location of the Health Facility 43 In the project area about 84.73 % of the households reported of location of the health facility outside of the village. Similarly in the non-project about 78.41 % reported of location of the health facility outside of the village. Details are given in Table 32.

Table 32: Location of the Place of Treatment Sl Nº Beneficiary Control Group Location Nº %Age Nº %Age 1 Within the Village 229 15.27 65 21.59 2 Outside the village 1,271 84.73 236 78.41 Total 1,500 100.00 301 100.00

39 The average distance of a health facility is 7.18 km in the project area and 8 km in the non-project area.

1.34 Modes of Transportation 44 In the project area about 58.40 % of the households depend on a public transport system to reach a health centre. And about 33.33 % depend on private transport system. Similarly in the non-project area about 95.68 % of the households depend on a public transport system to reach a health centre. Details are given in Table 33.

Table 33: Mode of Transportation Sl Nº Beneficiary Control Group Transport Nº %Age Nº %Age 1 Public Transport 876 58.40 288 95.68 2 Vehicle from health facility 30 2.00 4 1.33 3 Pvt. Transport 500 33.33 7 2.33 4 Bullock cart 23 1.53 2 0.66 5 Others 71 4.73 0 0.00 Total 1,500 100.00 301 100.00

1.35 Incidence of Illness 45 In the project area about 14.80 % of the households reported of a family member falling sick during the last one year. In the non-project area, about 14.80 % of the households reported of a family member falling sick during the last one year. Details are given in Table 34.

Table 34: Reported Incidence of Illness of family members at the Household Sl Nº Beneficiary Control Group Illness Nº %Age Nº %Age 1 Yes 222 14.80 42 13.95 2 No 1,278 85.20 259 86.05 Total 1,500 100.00 301 100.00

1.36 Incidence of Illness 46 In the project area out of 222 households those reported of a family member falling sick, in 91 % of the households only one member fell sick. And in the rest 9 % households two family members fell sick. Similarly in the non-project area out of 42 households those reported of a family member falling sick, in 97.62 % of the households only one member fell sick and in the rest 2.38 % households two family members fell sick. Details are given in Table 35.

Table 35: Number of family members fallen ill Sl Nº Beneficiary Control Group Number of members Nº %Age Nº %Age 1 One Member 202 90.99 41 97.62 2 Two Members 20 9.01 1 2.38 Total 222 100.00 42 100.00

Draft – August 2010 Page 52 Sustainable Power Sector Support II Project SRI 39415

1.37 Types of Diseases 47 In the project area the reported diseases are respiratory problems (27.69 %), general fever (12.81 %), diabetes (8.68 %) and heart problems (4.55 %). Similarly in the non-project area the reported diseases are general fever (32.56 %), diabetes (23.26 %) and respiratory problems (11.63 %). Details are given in Table 36.

Table 36: Types of Diseases Sl Nº Beneficiary Control Group Diseases Nº %Age Nº %Age 1 Respiratory Problems 67 27.69 5 11.63 2 General Fever 31 12.81 14 32.56 3 Typhoid 1 0.41 1 2.33 4 Gastro Intestinal Problems 3 1.24 1 2.33 5 Diabetes 21 8.68 10 23.26 6 Heart Problem 11 4.55 1 2.33 7 Injury / Accident 5 2.07 0 0.00 8 Hyper Tension 9 3.72 0 0.00 9 Malaria 2 0.83 0 0.00 10 Unclassified / Others 116 47.93 24 55.81 Total Members 242 100.00 43 100.00

1.38 Types of Treatment 48 About 90.91 % in the project area and 93 % in the non-project area preferred allopathic treatment for the ailments of the family members. In the project area the reported diseases are respiratory problems (27.69 %), general fever (12.81 %), diabetes (8.68 %) and heart problems (4.55 %). Similarly in the non- project area the reported diseases are general fever (32.56 %), diabetes (23.26 %) and respiratory problems (11.63 %). Details are given in Table 37.

Table 37: Types of Treatment Sl Nº Beneficiary Control Group Treatments Nº %Age Nº %Age 1 Allopathic 220 90.91 40 93.02 2 Homeopathic 6 2.48 0 0.00 3 Herbal 4 1.65 0 0.00 4 Traditional 6 2.48 1 2.33 5 No Treatment 6 2.48 2 4.65 Total Members 242 100.00 43 100.00

1.39 Deliver at the Household 49 In the project area about 9 % of the households reported of delivery of a child in the family. Similarly in the non-project area about 17.61 % of the households reported of baby being delivered. Details are given in Table 38.

Table 38: Number of Households Reported Delivery during Last One Year Sl Nº Beneficiary Control Group Delivery happened Nº %Age Nº %Age 1 Yes 135 9.00 53 17.61 2 No 1,365 91.00 248 82.39 Total 1,500 100.00 301 100.00

1.40 Place of Delivery 50 In the project area out of 135 households those reported of a delivery in the family about 91.85 % of the deliveries are institutional and 8.15 % of the deliveries happened at home. Similarly in the project area out of 53 households those reported of a delivery in the family about 77.36 % of the deliveries are institutional and 22.64 % of the deliveries happened at home. Details are given in Table 39. Draft – August 2010 Page 53 Sustainable Power Sector Support II Project SRI 39415

Table 39: Place of Delivery Sl Nº Beneficiary Control Group Place Nº %Age Nº %Age 1 At home 11 8.15 12 22.64 2 At govt. health facility 124 91.85 40 75.47 3 At Charitable Health centre 0 0.00 1 1.89 Total 135 100.00 53 100.00

1.41 Delivery Assistant 51 In the project area 85.93 % of the deliveries are assisted by doctors and in the non-project area 75.47 % of the deliveries are assisted by doctors. Details are given in Table 40.

Table 40: Delivery Assisted By Sl Nº Beneficiary Control Group Person Assisted Nº %Age Nº %Age 1 Doctor 116 85.93 40 75.47 2 ANM / LHV 15 11.11 0 0.00 3 Mid wife 4 2.96 2 3.77 4 Elderly women / family 0 0.00 10 18.87 5 Elderly women / family 0 0.00 1 1.89 Total 135 100.00 53 100.00

1.42 Reasons for Home Deliveries 52 In the project area out of 11 home deliveries 63.64 % happened due to distance of the health facility. About 36.36 % home deliveries happened as households think better care at home. In the non-project area out of 12 home deliveries 58.33 % happened due to distance of the health facility. About 25 % of the households reported of inadequate time to reach the health facility. Details are given in Table 41.

Table 41: Reasons for Home Deliveries Sl Nº Reasons Beneficiary Control Group (2 responses) Nº %Age Nº %Age 1 Health Facility is far 7 63.64 7 58.33 2 Better care at home 4 36.36 2 16.67 3 Inadequate time to go to facility 0 0.00 3 25.00 4 Can’t afford health facility expenses 3 27.27 0 0.00 Total 11 100.00 12 100.00

1.43 Place of Antenatal Checkups 53 In the project area about 93.33 % of the women had antenatal checkups in government health facility and in the non-project area about 66 % had antenatal checkups in similar facility. Details are given in Table 42.

Table 42: Place of Antenatal Check Ups Sl Nº Beneficiary Control Group Places Nº %Age Nº %Age 1 At home 6 4.44 4 7.55 2 At govt. health facility 126 93.33 35 66.04 3 At Pvt. Health facility 3 2.22 8 15.09 4 At Charitable Health centre 0 0.00 2 3.77 5 Others 0 0.00 4 7.55 Total 135 100.00 53 100.00

54 The average number of antenatal checkups conducted is 12 and in the non-project area it is 9.75 times.

Draft – August 2010 Page 54 Sustainable Power Sector Support II Project SRI 39415

1.44 Perceived Satisfaction 55 In the project area about 32.59 % of the women reported of being very satisfied on the maternal services and in the non-project area about 28.30 % reported of being very satisfied. Details are given in Table 43.

Table 43: Perceived Satisfaction Sl Nº Beneficiary Control Group Perceptions Nº %Age Nº %Age 1 Very Satisfied 44 32.59 15 28.30 2 Satisfied 86 63.70 36 67.92 3 Not So Satisfied 5 3.70 2 3.77 Total 135 100.00 53 100.00

1.45 Migration 56 In the project area about 10.53 % of the households reported of migration of a household member during the last one year and it is 8.97 % in the non-project area. Details are given in Table 44.

Table 44: Percentage of Households Reported Migration Sl Nº Beneficiary Control Group Any Migration Nº %Age Nº %Age 1 Yes 158 10.53 27 8.97 2 No 1,342 89.47 274 91.03 Total 1,500 100.00 301 100.00

57 In the project area a total of 193 (male 151 and female 42) persons migrated and in the non-project area 36 (male 28 and female 8) persons migrated.

1.46 Types of Migration 58 Out of 158 households those reported migration in the project area about 95.57 % migrated individually and 4.43 % migrated with the family. Similarly in the non-project area out of 27 households those reported migration about 92.59 % migrated individually and 7.41 % migrated with the family. Details are given in Table 45.

Table 45: Types of Migration Sl Nº Beneficiary Control Group Types Nº %Age Nº %Age 1 Individually 151 95.57 25 92.59 2 With family 7 4.43 2 7.41 Total 158 100.00 27 100.00

1.47 Place of Migration 59 Majority about 59.49 % migrated outside of the district in the project area and 19.62 % migrated to the capital city. Similarly in the non-project area about 51.85 % migrated outside of the district in the project area and 22.22 % migrated outside of the country. Details are given in Table 46.

Table 46: Place of Migration Sl Nº Beneficiary Control Group Place Nº %Age Nº %Age 1 Within the district 14 8.86 5 18.52 2 Other districts 94 59.49 14 51.85 3 Capital city 31 19.62 2 7.41 4 Outside of the country 19 12.03 6 22.22 Total 158 100.00 27 100.00

Draft – August 2010 Page 55 Sustainable Power Sector Support II Project SRI 39415

1.48 Types of Job 60 Among the males in the project area about 56.29 % are in government and private jobs and 21.19 % are in army / police. Similarly among the males in the non-project area about 50 % are in government and private jobs and 39.29 % are working as non-agricultural labour. Details are given in Table 47.1.

Table 47.1: Types of Jobs Performed by the Migrated Members (Male) Sl Nº Beneficiary Control Group Types of Jobs Nº %Age Nº %Age 1 Agricultural Labour 3 1.99 3 10.71 2 Non-agricultural Labour 15 9.93 11 39.29 3 Trade & Business 16 10.60 0 0.00 4 Others (Service, Pvt and Govt,) 85 56.29 14 50.00 5 Army / Police 32 21.19 0 0.00 Total 151 100.00 28 100.00

61 Among the females in the project area about 57.14 % are in government and private jobs and 23.81 % are in doing business. Similarly among the females in the non-project area about 75 % are in government and private jobs and 25 % are working as non-agricultural labour. Details are given in Table 47.2.

Table 47.2: Types of Jobs Performed by the Migrated Members (Female) Sl Nº Beneficiary Control Group Types of Jobs Nº %Age Nº %Age 1 Agricultural Labour 2 4.76 0 0.00 2 Non-agricultural Labour 4 9.52 2 25.00 3 Trade & Business 10 23.81 0 0.00 4 Others (Service, Pvt and Govt,) 24 57.14 6 75.00 5 Army / Police 2 4.76 0 0.00 Total 42 100.00 8 100.00

62 The average monthly income of the migrated members in the project area is rupees 18,675 and rupees 18,111 in the non-project area.

Women Empowerment 1.49 Activities performed by Women 63 In the project area about 77.80 % of the women as usual are engaged in household works. In the economic activities 51.47 % of the women are engaged in agriculture, 19.87 % in allied activities, 17.73 % in collection and sale of forest products and 11.33 % are engaged as agricultural labours.

64 In the non-project area about 87.71 % of the women as usual are engaged in household works. In the economic activities 32.23 % of the women are engaged in agriculture, 11.96 % each in allied activities and collection and sale of forest products and 10.63 % are engaged as agricultural labours. Details are given in Table 48.

Table 48: Types of Economic and Non-Economic Activities performed by Women of the Households Sl Nº Beneficiary Control Group Types of Activities Nº %Age Nº %Age 1 Cultivation 772 51.47 97 32.23 2 Allied Activities (Dairy, Poultry, Sheep rearing, etc) 298 19.87 36 11.96 3 Collection and Sale of forest products 266 17.73 36 11.96 4 Trade & Business 113 7.53 11 3.65 5 Agricultural Labour 170 11.33 32 10.63 6 Non-Agricultural Labour 90 6.00 15 4.98 7 HH Industries 50 3.33 28 9.30 8 Service 169 11.27 30 9.97 9 Households Work 1,167 77.80 264 87.71 Draft – August 2010 Page 56 Sustainable Power Sector Support II Project SRI 39415

Sl Nº Beneficiary Control Group Types of Activities Nº %Age Nº %Age 10 Others 27 1.80 7 2.33 Total 1,500 100.00 301 100.00

1.50 Women’s Participation in Decision Making 65 In the project area about 87.60 % of the women participate in the decision making in the household on day to day activities. On other issues in 77.80 % of the households woman participate in financial matters and 66.60 % in the education of the child.

66 In the non-project area about 93.36 % of the women participate in the decision making in the household on day to day activities. On other issues in 88.70 % of the households woman participate in financial matters and 58.80 % in the education of the child. Details are given in Table 49.

Table 49: Women’s Participation in Household’s Decision Making Sl Nº Beneficiary Control Group Types of Participations Nº %Age Nº %Age 1 Financial matters 1,167 77.80 267 88.70 2 Education of child 999 66.60 177 58.80 3 Health care of child 1,146 76.40 101 33.55 4 Purchase of assets 1,125 75.00 243 80.73 5 Day to day activities 1,314 87.60 281 93.36 6 On social functions and marriages 1,147 76.47 234 77.74 7 Others 343 22.87 40 13.29 Total 1,500 100.00 301 100.00

1.51 Time spent by women in different activities 67 In the project area on an average a woman spend about 2 hours 53 minutes on cooking, 1 hour 18 minutes in cleaning and 4 hours 10 minutes on caring for the young and sick. The woman spends about 2 hours and 55 minutes in leisure activities.

68 Similarly in the non-project area on an average a woman spend about 2 hours 25 minutes on cooking, 1 hour 26 minutes in cleaning and 4 hours 28 minutes on caring for the young and sick. Details are given in Table 50.

Table 50: Average time spent by Women’s in performing different activities in a day Sl Nº Types of Activities Beneficiary Control Group 1 Cooking 2 hrs 53 minutes 2 hrs 25 minutes 2 Cleaning (House, clothes, utensils, etc) 1 hr 18 minutes 1 hr 26 minutes 3 Fuel wood collection 1 hr 0 minutes 51 minutes 4 Water collection 47 Minutes 38 minutes 5 Daily marketing 43 31 6 Caring for the young and sick 4 hrs 10 minutes 4 hrs 28 minutes 7 Watching TV (other leisure activities) 2 hrs 55 minutes 2 hrs 43 minutes

1.52 Women’s Perception on safety during day time 69 In the project area 96.80 % of the women feel safe during the day time and in the non-project area 93.35 % feel safe. Details are given in Table 51.

Table 51: Women’s Perception on the safety during day time Sl Nº Beneficiary Control Group Perception Nº %Age Nº %Age 1 Yes 1,452 96.80 287 95.35 2 To some extent 39 2.60 13 4.32 3 No 5 0.33 1 0.33 4 Don’t know / can’t say 4 0.27 0 0.00

Draft – August 2010 Page 57 Sustainable Power Sector Support II Project SRI 39415

Sl Nº Beneficiary Control Group Perception Nº %Age Nº %Age Total 1,500 100.00 301 100.00

1.53 Women’s Perception on safety during day time 70 In the project area 62.47 % of the women feel safe during the night time and in the non-project area 43.19 % feel safe and another 42.52 % feel safe to some extent. Details are given in Table 52.

Table 52: Women’s Perception on the safety during night time Sl Nº Beneficiary Control Group Perception Nº %Age Nº %Age 1 Yes 937 62.47 130 43.19 2 To some extent 367 24.47 128 42.52 3 No 179 11.93 43 14.29 4 Don’t know / can’t say 17 1.13 0 0.00 Total 1,500 100.00 301 100.00

1.54 Women’s Perception on their Mobility 71 In the project area about 78.67 % of the women feel that they can move freely and in the non-project area 47.18% feel that they can move freely. However in the non-project area about 52.82 % of the women feel that they can move freely during the day time. Details are given in Table 53.

Table 53: Women’s Perception on their Mobility Sl Nº Beneficiary Control Group Perception Nº %Age Nº %Age 1 Can move freely 1,180 78.67 142 47.18 2 Only during the day time 272 18.13 159 52.82 3 No cannot move freely 14 0.93 0 0.00 4 Cant say / don’t know 34 2.27 0 0.00 Total 1,500 100.00 301 100.00

1.55 Incidence of Women Going Outside to Fetch Water 72 In the project area about 61.52 % of the households reported that women do not go outside to fetch water. Among the rest, in 37.27 %of the household, women go outside to fetch water every day. Similarly in the non-project area about in 88.37 % households women go outside to fetch water every day. Details are given in Table 54.

Table 54: Incidence of women going outside to fetch water Sl Nº Beneficiary Control Group Occasion Nº %Age Nº %Age 1 Never 923 61.53 35 11.63 2 Everyday 559 37.27 266 88.37 3 1 to 2 days 17 1.13 0 0.00 4 5 to 6 days 1 0.07 0 0.00 Total 1,500 100.00 301 100.00

1.56 Access to Water 73 Out of the 577 households in the project area where women go outside to fetch water, about 53.21 % of the women have easy access to water from outside. Similarly in the non-project out of the 266 households where women go outside to fetch water, only about 36.47 % of the women have easy access to water from outside. Details are given in Table 55.

Table 55: Percentage of women reported easy access to water Sl Nº Beneficiary Control Group Easy Access to water Nº %Age Nº %Age 1 Yes 307 53.21 97 36.47 Draft – August 2010 Page 58 Sustainable Power Sector Support II Project SRI 39415

Sl Nº Beneficiary Control Group Easy Access to water Nº %Age Nº %Age 2 No 270 46.79 169 63.53 Total 577 100.00 266 100.00

1.57 Toilet at the Household 74 In the project area about 87.47 % of the households have toilets at their respective places. Similarly in the non-project only about 13.62 % of the households have toilets. Details are given in Table 56.

Table 56: Percentage of Households having Toilet Sl Nº Beneficiary Control Group Toilet Nº %Age Nº %Age 1 Yes 1,312 87.47 41 13.62 2 No 188 12.53 260 86.38 Total 1,500 100.00 301 100.00

1.58 Easy Access to Toilets 75 In the project area out of the 188 households those don’t have a toilet at home; about 35.11 % of the women of their households have easy access to toilets. Similarly in the non-project area only about 11.92 % of the households have easy access to toilets out of 260 households those don’t have toilets at their home. Details are given in Table 57.

Table 57: Percentage of women having access public toilets and bathing facilities in the evening easily Sl Nº Easy Access to Beneficiary Control Group Public Toilets Nº %Age Nº %Age 1 Yes 66 35.11 31 11.92 2 No 122 64.89 229 88.08 Total 188 100.00 260 100.00

1.59 Street Lights 76 In the project area about 93.67 % of the households admitted that that there is no adequate provision of street lighting during the night. Similarly in the non-project area about 89.70 % of the households admitted that that there is no adequate provision of street lighting during the night. Details are given in Table 58.

Table 58: Adequate street lighting during the night Sl Nº Beneficiary Control Group Street Light Nº %Age Nº %Age 1 Yes Adequate 61 4.07 25 8.31 2 Yes, but only sometimes 34 2.27 6 1.99 3 No street lighting 1,405 93.67 270 89.70 Total 1,500 100.00 301 100.00

77 In the project area about 98.60 % of the women in the households admitted that that the provision of adequate street lights will result in the increase of the women’s mobility during the evening. In the non- project area almost all the households admitted about this. Details are given in Table 59.

Table 59: Percentage of women admitted provision of adequate street lights will result in the increase of the women’s mobility during the evening Sl Nº Beneficiary Control Group Street Light Nº %Age Nº %Age 1 Yes 1,479 98.60 299 99.34 2 No 21 1.40 2 0.66 Total 1,500 100.00 301 100.00

Draft – August 2010 Page 59 Sustainable Power Sector Support II Project SRI 39415

Structures 1.60 Use of Structures 78 In the project area majority about 97.60 % of the structures are residential and only 1.67 % of the structures are commercial. Similarly in the non-project area about 98.34 % of the structures are residential. Details are given in Table 60.

Table 60: Use of the Structure Sl Nº Beneficiary Control Group Use Nº %Age Nº %Age 1 Residential 1,464 97.60 296 98.34 2 Commercial 25 1.67 5 1.66 3 Residential cum commercial 8 0.53 0 0.00 4 Others 3 0.20 0 0.00 Total 1,00 100.00 301 100.00

1.61 Age of the Structures 79 In the project area the average age of the structures is 10 years and 8 months. Similarly in the non- project area the average age of the structures is 3 years and 3 months. Details are given in Table 61.

Table 61: Age of the Structure Sl Nº Beneficiary Control Group Age Nº %Age Nº %Age 1 Less than 1 year 29 1.93 2 0.68 2 1 year to less than 5 years 376 25.03 270 89.76 3 5 years to less than 10 years 452 30.14 8 2.73 4 10 years to less than 20 years 402 26.83 8 2.73 5 20 years to less than 50 years 224 14.97 12 4.10 6 50 years and above 17 1.10 0 0.00 Total 1,500 100.00 301 100.00 Average Age 10 yrs 8 months 3 years 3 months

1.62 Types of Roof 80 In the project area majority about 45.07 % of the structures have a tile roof followed by asbestos (23.13 %) and Corrugated iron sheet (22.13 %). Similarly in the non-project area in the majority of structures the roof is of corrugated iron sheet (79.60 %). Details are given in Table 62.

Table 62: Type of Roofs Sl Beneficiary Control Group Roof Type Nº Nº %Age Nº %Age 1 Simple (thatch/ sack/ bamboo/ slats) 115 7.67 8 2.68 2 Earth/clay/sand 7 0.47 1 0.33 3 Wood 3 0.20 0 0.00 4 Brick 1 0.07 0 0.00 5 Concrete 6 0.40 0 0.00 6 Corrugated iron sheet 332 22.13 240 79.60 7 Tile 676 45.07 8 2.68 8 Asbestos sheet 347 23.13 43 14.38 9 Coconut Branches 13 0.87 1 0.33 Total 1,500 100.00 301 100.00

1.63 Type of Floors 81 In the project area majority about 63.20 % of the structures have concrete floors, and about 29.67 % have earth / clay and sand floors. Whereas in the non-project area majority about 78.41 % of the structures have earth, clay and sand floors and 12.62 % have concrete floors. Details are given in Table 63.

Draft – August 2010 Page 60 Sustainable Power Sector Support II Project SRI 39415

Table 63: Type of Floors Sl Beneficiary Control Group Floor Type Nº Nº %Age Nº %Age 1 Simple (thatch/ sack/ bamboo/ slats) 60 4.00 24 7.97 2 Earth/clay/sand 445 29.67 236 78.41 3 Wood 4 0.27 0 0.00 4 Brick 13 0.87 1 0.33 5 Concrete 948 63.20 38 12.62 6 Corrugated iron sheet 5 0.33 2 0.66 7 Tile 16 1.07 0 0.00 8 Asbestos sheet 3 0.20 0 0.00 9 Coconut Branches 6 0.40 0 0.00 Total 1,500 100.00 301 100.00

1.64 Type of Walls 82 In the project area majority about 65.67 % of the structures have brick walls and 22.53 households have earth, clay and sand walls. Whereas in the non-project area majority about 62.79 % of the structures have simple thatch, sack, bamboo walls and 15.95 % have earth, clay and sand walls. Brick walls are there with only 8.97 % of the structures. Details are given in Table 64.

Table 64: Type of Walls Sl Beneficiary Control Group Wall Type Nº Nº %Age Nº %Age 1 Simple (thatch/ sack/ bamboo/ slats) 121 8.07 189 62.79 2 Earth/clay/sand 338 22.53 48 15.95 3 Wood 30 2.00 0 0.00 4 Brick 985 65.67 27 8.97 5 Concrete 8 0.53 0 0.00 6 Corrugated iron sheet 11 0.73 37 12.29 7 Tile 1 0.07 0 0.00 8 Asbestos sheet 1 0.07 0 0.00 9 Coconut Branches 5 0.33 0 0.00 Total 1,500 100.00 301 100.00

1.65 Type of Walls 83 In the project area majority about 65.67 % of the structures have brick walls and 22.53 households have earth, clay and sand walls. Whereas in the non-project area majority about 62.79 % of the structures have simple thatch, sack, bamboo walls and 15.95 % have earth, clay and sand walls. Brick walls are there with only 8.97 % of the structures. Details are given in Table 65.

Table 65: Type of Structure Sl Nº Beneficiary Control Group Structure Type Nº %Age Nº %Age 1 Temporary 175 11.67 179 59.47 2 Semi permanent 134 8.93 75 24.92 3 Permanent 1,191 79.40 47 15.61 Total 1,500 100.00 301 100.00

1.66 Number of rooms: 84 In the project area the average number of rooms is 2.84 and the average number of lighted rooms is 1.01. in the project area only 15 rooms are cooled rooms. Similarly in the non-project area the average number of rooms is 1.44 and the average number of lighted rooms is 0.43. Details are given in Table 66.

Draft – August 2010 Page 61 Sustainable Power Sector Support II Project SRI 39415

Table 66: Number of rooms Sl Nº Rooms Beneficiary Control Group 1 Average Nº of Rooms 2.84 1.44 2 Average Nº of Lighted Rooms 1.01 0.43

Electricity 1.67 Availability of Electricity 85 In the project area the average year of electrification is 6.44 years and in the non-project area it is about 8.59 years. In the project area about 28.47 % of the households are electrified and in the non-project area only 7.31 % of the households are electrified. Details are given in Table 67.

Table 67: Percentage of Households Electrified Sl Nº Beneficiary Control Group Whether electrified Nº %Age Nº %Age 1 Yes 427 28.47 22 7.31 2 No 1,073 71.53 279 92.69 Total 1,500 100.00 301 100.00

1.68 Source of Power Supply: 86 In the project area about 48.71 % get electricity by their own arrangement and 34.66 % get electricity from the government. In the non-project area all the households receive electricity from the government. Details are given in Table 68.

Table 68: Source of Power Supply Sl Nº Beneficiary Control Group Supply Source Nº %Age Nº %Age 1 Government 148 34.66 22 100.00 2 Community Based 12 2.81 0 0.00 3 Own Arrangement 208 48.71 0 0.00 4 Govt. & Community 5 1.17 0 0.00 5 Govt. & Own Arrangement 1 0.23 0 0.00 6 Community & own 2 0.47 0 0.00 7 Community & own arrangement 51 11.94 0 0.00 Total 427 100.00 22 100.00

1.69 Source of Power 87 In the project area about 63.23 % gets electricity from solar energy, and 36.07 % gets electricity from the government power grid. In the non-project area all the households receive electricity from the government. Details are given in Table 69.

Table 69: Source of Electricity Sl Nº Beneficiary Control Group Source Nº %Age Nº %Age 1 Govt. grid 154 36.07 22 100.00 2 Micro-hydro power 1 0.23 0 0.00 3 Generator 2 0.47 0 0.00 4 Solar 270 63.23 0 0.00 Total 427 100.00 22 100.00

1.70 Seasonal Availability of Electricity: 88 In the project area the average hours of availability if electricity is 21.37 hours in the summer and monsoon, 21.57 hours during winter. Similarly in the the non-project area all the households receive electricity on an average 23.6 hours throughout the year. Details are given in Table 70.

Draft – August 2010 Page 62 Sustainable Power Sector Support II Project SRI 39415

Table 70: Seasonal availability of electricity Sl Nº Beneficiary Control Group 1 Average Availability of electricity during Summer 21.37 23.6 2 Average Availability of electricity during Winter 21.57 23.6 3 Average Availability of electricity during Monsoon 21.37 23.6

1.71 Usage of Electricity 89 In the project area 95.55 % of the households use electricity for lighting, 72.37 % for using television and tape recorder and 6.56 % for pumping water. Similarly in the non-project area all the households use electricity for lighting, 90.91 % for using television and tape recorder and 22.73 % for heating and cooling purpose. Details are given in Table 71.

Table 71: Types of Usage of Electricity Sl Beneficiary Control Group Usage Type Nº Nº %Age Nº %Age 1 Electricity for Lighting 408 95.55 22 100.00 2 Electricity for cooking 10 2.34 1 4.55 3 Electricity for heating and cooling 17 3.98 5 22.73 4 Electricity for pumping water 28 6.56 0 0.00 5 Electricity for running TV & tape recorder 309 72.37 20 90.91 6 Electricity for computer 12 2.81 0 0.00 7 Electricity for running business 8 1.87 0 0.00 Total 427 100.00 22 100.00

1.72 Average Hours of Consumption of Electricity 90 In the project area on average electricity is used for 5.64 hours for lighting, 5.63 hours for pumping water, 3.95 hours for pumping water and 3.44 hours for running television and tape recorder. Similarly in the non-project area for lighting electricity is used for 5.31 hours and 5 households use electricity for heating and cooling for 11.1 hours. Details are given in Table 72.

Table 72: Average duration of use of electricity Sl Nº Beneficiary Control Group Purpose In hours In hours 1 Electricity for Lighting 5.64 5.31 2 Electricity for cooking 1.55 2 3 Electricity for heating and cooling 3.95 11.1 4 Electricity for pumping water 5.63 - 5 Electricity for running TV and tape recorder 3.44 3.65 6 Electricity for computer 1.79 - 7 Electricity for running business 3 -

1.73 Possession of Electrical Appliances 91 In the project area those have electricity at their home 94.38 % have lamps and the average possession is 5.39. About 73.30 households have television and the average possession is one each. Electric Fans is possessed by 16.39 % with an average possession of 1.51. About 11.24 % possess refrigerator and 6.79 % possess water pumps the average possession of these items is one.

92 In the non-project area those have electricity at their home almost all of them have lamps and the average possession is 8.59. About 90.91 % households have television and the average possession is one each. Electric Fans is possessed by 45.45 % with an average possession of 1.6. About 36.36 % possess refrigerator and 22.73 % possess water pumps the average possession of these items is one. Details are given in Table 73.

Draft – August 2010 Page 63 Sustainable Power Sector Support II Project SRI 39415

Table 73: Possession of Types Electrical Appliances Sl Nº Beneficiary Control Group Appliances Nº of Average Nº of Average HH % Age Nº HH % Age Nº 1 Lamps 403 94.38 5.39 22 100.00 8.59 2 Heater 22 5.15 1 5 22.73 1 3 Fans 70 16.39 1.51 10 45.45 1.6 4 TVs 313 73.30 1 20 90.91 1 5 Washing Machines 9 2.11 1 1 4.55 1 6 Water Pumps 29 6.79 1 5 22.73 1 7 Air conditioners 2 0.47 1 0 0.00 0 8 Refrigerators 48 11.24 1 8 36.36 1 9 Lap top 1 0.23 1 0 0.00 0 Total 427 100.00 22 100.00

1.74 Electric Meter

93 In the project area those have electricity at their home 25.53 % have an electricity meter. Similarly in the non-project area 77.27 % of the electrified households have an electricity meter. Details are given in Table 74.

Table 74: Possession of electricity meter Sl Nº Possess Electric Beneficiary Control Group Meter Nº %Age Nº %Age 1 Yes 109 25.53 17 77.27 2 No 318 74.47 5 22.73 Total 427 100.00 22 100.00

1.75 Place of Payment 94 In the project area those have electricity at their home 62.12 % pay their electricity bills in either banks or post office and the rest in CEB. Similarly in the non-project area all the households pay their electricity bills in the banks and post offices. Details are given in Table 75.

Table 75: Place of payment of electricity bill Sl Nº Beneficiary Control Group Place Nº %Age Nº %Age 1 Bank / Post Office 82 62.12 22 100.00 2 CEB 50 37.88 0 0.00 Total 132 100.00 22 100.00

1.76 Period of Electricity Bill 95 In the project area 87.41 % pay their electricity bills in a monthly cycle. Similarly in the non-project area 95.45 % pay their electricity bills in a monthly cycle. Details are given in Table 76.

Table 76: Period of payment of electricity bill Sl Nº Beneficiary Control Group Period Nº %Age Nº %Age 1 Monthly 118 87.41 21 95.45 2 Bi-monthly 9 6.67 1 4.55 3 Quarterly 8 5.93 0 0.00 Total 135 100.00 22 100.00

1.77 Electricity Theft 96 In the project area 91.50 % admitted of no case of electricity theft. Similarly in the non-project area 80 % admitted of no case of electricity theft case. Details are given in Table 77.

Draft – August 2010 Page 64 Sustainable Power Sector Support II Project SRI 39415

Table 77: Electricity theft case Sl Nº Beneficiary Control Group Theft Case Nº %Age Nº %Age 1 Yes 13 8.50 4 20.00 2 No 140 91.50 16 80.00 Total 153 100.00 20 100.00

97 The responsibility of maintenance lies with CEB admitted by both project and non-project area.

1.78 Use of Non-Electrical Source 98 In the project area 35.36 % of the electrified households also use alternate energy. Similarly in the non-project area 31.82 % use alternate energy sources other than electricity. Details are given in Table 78.

Table 78: Use of non-electrical sources by electrified households Sl Nº Use non-electrical Beneficiary Control Group source Nº %Age Nº %Age 1 Yes 151 35.36 7 31.82 2 No 276 64.64 15 68.18 Total 427 100.00 22 100.00

1.79 Average consumption of Non-Electrical Energy 99 In the project area 18.74 % of the electrified households use kerosene and diesel as alternate energy. The average hours of consumption is 7.64 hours and the monthly average expenditure is rupees 749.25. Similarly 8.9 % use wood and average hours of consumption is 1 hour and 29 minutes. No cost is incurred on fire woods. Details are given in Table 79.1.

Table 79.1: Consumption hours of alternate sources by electrified households (Beneficiary) Sl Nº Average Hrs Average of Quantity of Expenditure Alternate Source Nº of HH %age HH consumption consumption in rupees 1 Kerosene/ Diesel 80 18.74 7.64 5.11 749.25 2 Battery 1 0.23 - 150 3 Wood 38 8.90 1.29 17 Nil 4 Gas - - - - - 5 Solar 96 22.48 5.77 - 51,196 Total 427 100.00 - - -

100 In the non-project area 22.73 % of the electrified households use kerosene and diesel as alternate energy. The average hours of consumption of kerosene and diesel is 11.66 hours and the monthly average expenditure is rupees 155. Details are given in Table 79.2.

Table 79.2: Consumption hours of alternate sources by electrified households (Control Group) Sl Nº Average Hrs Average of Quantity of Expenditure Alternate Source Nº of HH %age HH consumption consumption in rupees 1 Kerosene/ Diesel 5 22.73 11.66 1.3 155 2 Battery - - - - 3 Wood 3 13.64 3 23.33 Nil 4 Gas - - - - - 5 Solar - - - - - Total 22 100.00 - - -

1.80 Alternate Energy Usage in non-Electrified Households 101 In the project area 95 % of the households those don’t have electricity use Kerosene and Diesel for lighting purposes and 9.23 % for cooking purpose. Similarly battery is used by 8.76 % for lighting and 94.41 % of the households use wood for cooking and 6.34 % of the households use solar energy for lighting. Details are given in Table 80.1. Draft – August 2010 Page 65 Sustainable Power Sector Support II Project SRI 39415

Table 80.1: Alternate Energy resources and their use by non-electrified households (Beneficiary) Sl Nº Lighting Cooking Heating Energy Sources Nº %age Nº %age Nº %age 1 Kerosene/ Diesel 1,020 95.06 99 9.23 3 0.28 2 Battery 94 8.76 2 0.19 0 0.00 3 Wood 11 1.03 1,013 94.41 87 8.11 4 Gas 3 0.28 4 0.37 2 0.19 5 Solar 68 6.34 1 0.09 0 0.00 Total 1,073 100.00 1,073 100.00 1073 100.00

102 In the non-project area 97.85 % of the households those don’t have electricity use Kerosene and Diesel for lighting purposes. Similarly battery is used by 13.62 % for lighting and wood is used by 7.53 % for lighting. About 95.34 % of the households use wood for cooking. Details are given in Table 80.2.

Table 80.2: Alternate Energy resources and their use by non-electrified households (Control Group) Sl Nº Lighting Cooking Heating Energy Sources Nº %age Nº %age Nº %age 1 Kerosene/ Diesel 273 97.85 0 0.00 0 0.00 2 Battery 38 13.62 0 0.00 0 0.00 3 Wood 21 7.53 266 95.34 23 8.24 4 Gas 0 0.00 0 0.00 0 0.00 5 Solar 0 0.00 0 0.00 0 0.00 Total 279 100.00 279 100.00 279 100.00

1.81 Use of Non-Electrical Appliances in non-Electrified Households 103 In the project area 94.5 % of the households those don’t have electricity possess Kerosene and Diesel lamps and the average number is 2.72. Similarly 14.26 % of the households possess battery lamps and the average possession is 1.26. Solar panels are possessed by 5.96 % of the non-electrified households and each possesses at least one.

104 Similarly in the non-project area about 94.5 % of the households possess kerosene and diesel lamps and the average number of possession is 2.23. Similarly 16.13 % of the households possess battery lamps and the average possession is 1.07. Details are given in Table 81.

Table 81: Use of non-electrical appliances in non-electrified households Sl Nº Beneficiary Control Group Appliances Nº of Averag Nº of Averag HH % Age e Nº HH % Age e Nº 1 Kerosene/Diesel Lamps 1,014 94.50 2.72 267 95.70 2.23 2 Battery Lamps 153 14.26 1.26 45 16.13 1.07 3 Gas Cylinders 2 0.19 1 - - - 4 Solar Panel 64 5.96 1 - - - Total 1,073 100.00 100.00 279 100.00 2.23

105 The average monthly expenditure on kerosene and diesel is rupees 581.29 in the project area, followed by rupees 210 on battery lamps. Similarly in the non-project area the average monthly expenditure on kerosene and diesel is rupees 350.47 in the project area, followed by rupees 150 on battery lamps.

1.82 Payment Preference 106 In the project area the households preferred to pay rupees 353.73 on an average for the monthly electricity bill. In non-project area the households prefer to pay rupees 267.48 per month as electricity bill. Details are given in Table 82.

Table 82: Payment Preference Sl Nº Beneficiary Control Group 1 Preference to pay monthly electricity bill in rupees 353.73 267.48

Draft – August 2010 Page 66 Sustainable Power Sector Support II Project SRI 39415

1.83 Preference of use of electricity by women headed households 107 In the project area among the women headed households all of them will use electricity for lighting, 64.79 % will use for watching television and using radio. In the non-project area all the women headed households will use electricity for lighting. Details are given in Table 83.

Table 83: Type of use of electricity as preferred by women headed households Sl Nº Beneficiary Control Group Preferred type of Usages Nº %Age Nº %Age 1 Will use for lighting 142 100.00 60 100.00 2 Will use for cooking 5 3.52 1 1.67 3 For heating and cooling 3 2.11 0 0.00 4 Will use TV and radio 92 64.79 10 16.67 5 For pumping water 2 1.41 2 3.33 6 Others 1 0.70 1 1.67 Total 142 100.00 60 100.00

1.84 Satisfaction on the Current Flow 108 In the project area about 93.67 % of the households are not satisfied on electricity current flow. On the other hand in the non-project area 99.34 % are not satisfied. Details are given in Table 84.

Table 84: Percentage of households satisfied on the current electricity flow Sl Nº Beneficiary Control Group Whether satisfied Nº %Age Nº %Age 1 Yes 95 6.33 2 0.66 2 No 1,405 93.67 299 99.34 Total 1,500 100.00 301 100.00

1.85 Satisfaction on the non-electric energy 109 In the project area about 97.40 % of the households are not satisfied on non-electric energy. Similarly in the non-project area 99.00 % are not satisfied. Details are given in Table 85.

Table 85: Percentage of households satisfied on non-electric energy Sl Nº Beneficiary Control Group Whether satisfied Nº %Age Nº %Age 1 Yes 39 2.60 3 1.00 2 No 1,461 97.40 298 99.00 Total 1,500 100.00 301 100.00

1.86 Diesel Generator as a Polluting Agent 110 In the project area about 53.07 % of the households admitted that diesel generator creates pollution. Similarly in the non-project area 68.44 % stated that diesel generator creates pollution. Details are given in Table 86.

Table 86: Percentage of households admitted diesel generator creating pollution Sl Nº Diesel create Beneficiary Control Group pollution Nº %Age Nº %Age 1 Yes 796 53.07 206 68.44 2 No 704 46.93 95 31.56 Total 1,500 100.00 301 100.00

1.87 Diesel Generator as a Polluting Agent 111 In the project area about 89.93 % of the households admitted that diesel and kerosene as expensive. Similarly in the non-project area 95.35 % of the households admitted that diesel and kerosene as expensive. Details are given in Table 87.

Draft – August 2010 Page 67 Sustainable Power Sector Support II Project SRI 39415

Table 87: Percentage of households admitted diesel / kerosene as expensive Sl Nº Diesel / kerosene as Beneficiary Control Group expensive Nº %Age Nº %Age 1 Yes 1,349 89.93 287 95.35 2 No 151 10.07 14 4.65 Total 1,500 100.00 301 100.00

1.88 Requirement of Electric Power 112 In the project area about 90.07 % of the households admitted requirement of electric power. Similarly in the non-project area about 96.01 % of the households admitted requirement of electric power. Details are given in Table 88.

Table 88: Percentage of households feels the requirement of electric power Sl Nº Electric power Beneficiary Control Group required Nº %Age Nº %Age 1 Yes 1,351 90.07 289 96.01 2 No 149 9.93 12 3.99 Total 1,500 100.00 301 100.00

1.89 Regular Payment of Bill 113 In the project area about 87.87 % of the households admitted of paying regular electric bill. Similarly in the non-project area about 92.03 % of the households admitted will pay electricity pay regularly. Details are given in Table 89.

Table 89: Percentage of households admitted of paying electricity bill regularly Sl Nº Beneficiary Control Group Will pay electric bill Nº %Age Nº %Age 1 Yes 1,318 87.87 277 92.03 2 No 182 12.13 24 7.97 Total 1,500 100.00 301 100.00

1.90 Electricity Theft 114 In the project area about 72.60 % of the households showed willingness to cooperate to minimise electricity theft. Similarly in the non-project area about 75.08 % of the households showed willingness to cooperate to minimise electricity theft. Details are given in Table 90.

Table 90: Percentage of households those will cooperate to minimise electricity theft Sl Nº Beneficiary Control Group Will cooperate Nº %Age Nº %Age 1 Yes 1,089 72.60 226 75.08 2 No 411 27.40 75 24.92 Total 1,500 100.00 301 100.00

1.91 Benefits of the Project 115 In the project area about 94.40 % of the households admitted that the project will help the people. Similarly in the non-project area about 92.03 % admitted that the project will help the people. Details are given in Table 91.

Table 91: Percentage of households feels the project will help Sl Nº Beneficiary Control Group Will cooperate Nº %Age Nº %Age 1 Yes 1,416 94.40 277 92.03 2 No 84 5.60 24 7.97 Total 1,500 100.00 301 100.00

Draft – August 2010 Page 68 Sustainable Power Sector Support II Project SRI 39415

ANNEXURE-5 SUMMARY DETAILS OF THE CONSULTATIONS Date, Location and Number of Issue Raised Summary of Discussion Participants in Consultation Name of the Component /Site: Kahawatta PLC - . General perception about . Most of the people are Kataboola State the project and the aware of the project, but Number of Participants: 14 awareness about the they did not know about the Name of the Village: Kataboola proposed project. details. Some of the people Name of the Gramaseva Division: Katabola, . Any critical issue or concern are not aware of the Kadiyanlena proposed project. Name of the District: , Nuwara Eliya by the local people Name of the Province: Central regarding the project. . All villagers welcomed the Date: 15.06.2010 . Any criteria to be projects and were apprehensive of increased Name of the Component /Site: Kahawatta PLC- considered during project electricity supply. Craighead State design, construction and Number of Participants: 14 operation stage. . Most of the villages in the Name of the Village: Tolabola, Udahentenna . Employment Potential in the Tea Estate component had Name of the Gramaseva Division: Pathakada project which is of benefit to electricity from the Name of the District: Kandy, village. Government Grid. In the other component some of Name of the Province: Central . Ethnic Minorities Date: 15.06.2010 the villages did not have /Indigenous peoples electricity supply. Name of the Component /Site: Kahawatta PCL- composition Rassagala . Perceived benefits by the . General socio-economic villagers from the Number of Participants: 08 standing of the village Name of the Village: Wellandura subproject are electricity . Current rates for the Name of the Gramaseva Division: Yawinna generation, better electricity agricultural land Name of the District: Ratnapura supply to the houses, Name of the Province: Sabaragamuwa . Source of Power Supply employment opportunities during the construction . Sources and Usage of Date: 15. 06.2010 phase and in general Electricity Name of the Component /Site: : Strathodon development of the village. estate- Watawala Plantation . Source of drinking water Number of Participants: 8 . There will be no losses from . Loss of the Tea Estate Project. In Name of the Village: Strathodon residential/commercial Name of the Gramaseva Division: Parasas-ella the other component, the structures, if any due to the perceived negative impacts Division project Name of the District: Kegalle are temporary loss of crop Name of the Province: Sabaragamuwa (Replace . Loss of community life like . In general people do not by Agrakanda) any Market Places or foresee any major problem Date: 12.06.2010 community activities to be with resettlement affected Name of the Component /Site: Madulsima PCL- . However, people believe Elteb Estate . Shortage of water for that any loss of Number of Participants: 14 human consumption, structure/land needs proper Name of the Village: Elteb irrigation, and other relocation within the same Name of the Gramaseva Division: Eltab downstream uses. area or village to avoid any Name of the District: Badulla . Negative impact on food loss of community life and Name of the Province: Uva grain availability/land use (if conflict with others Date: 14. 06.2010 any) to PAFs . People wanted the project

. Project impacts on authority and competent Name of the Component /Site: Balangoda PCL- landslides or soil erosion in authority for land acquisition Rassagala the locality to deal fairly with land Number of Participants: 14 acquisition and payment of Name of the Village: Rassagala . Health and Safety Issues compensation Name of the Gramaseva Division: Rassagala, . Resettlement and Land Polwatugoda Acquisition . Most of the people wanted cash as means of Name of the District: Ratnapura . Protected Areas Name of the Province: Sabaragamuwa compensation. Date: 07. 06.2010 . Environmentally sensitive . Many villagers suggested Name of the Component /Site: Kelani PLC- Areas that the authority should Glassough Estate . Health status, Availability of have camp in the village Number of Participants: 14 Hospitals and over all and finalise the land Name of the Village: Glassough environmental condition acquisition process and Name of the Gramaseva Division: Glassough . Type of compensation settle all issues in Name of the District: Nuwara Eliya expected (Cash or Kind) consultation with the people Name of the Province: Central . Perceived benefits from the . The villagers desired that Date: 19. 06.2010 project the project authority should pay the compensation for . Perceived losses from the land and structure at market DraftName – ofAugust the Component 2010 /Site: Kelani PLC- Page 69 Edinburgh Sustainable Power Sector Support II Project SRI 39415

Date, Location and Number of Issue Raised Summary of Discussion Participants in Consultation Number of Participants: 14 project rate Name of the Village: Nanu Oya . Organisations of a social . The villagers demanded Name of the Gramaseva Division: Nanu Oya nature (NGOs/CBOs/ Civil that the during project Name of the District: Nuwara Eliya Society) active in the area. implementation, the Name of the Province: Central . Organisation of the village authority should employ Date: 08. 06.2010 and its structure labourers from the villages for construction activities. Name of the Component /Site: Kelani PLC- . Decision makers on Udaradella Estate community related issues . Many participants argued Number of Participants: 14 that they will be happy to . Likely involvement of local participate in project Name of the Village: Udaradella people in the Name of the Gramaseva Division: Bangala Hatha implementation by providing implementation of the labour and cooperating with Name of the District: Nuwara Eliya project the project implementing Name of the Province: Central authorities Date: 11. 06.2010 . People want the project Name of the Component /Site: Kelani Valley PLC authority to consult Tillyrie State continuously during the Number of Participants: 14 project implementation to Name of the Village: Tillyrie solve local problems Name of the Gramaseva Division: Tillyrie Name of the District: Nuwara Eliya . Most of the people were Name of the Province: Central happy with the consultation Date: 09.06.2010 process. Name of the Component /Site: Kelaniweli Plantation, Kelani Estate: Number of Participants: 11 Name of the Village: Hapugammana –Parasas- ella Name of the Gramaseva Division: Parasas-ella Division Name of the District: Kegalle (AGA Division- Yatiyanthota) Name of the Province: Sabaragamuwa Date: 12/ 06/2010 Name of the Component /Site: Kelani Valley Plantation- Edarapola Number of Participants: 10 Name of the Village: Ederapola Name of the Gramaseva Division: Poona-Ela Name of the District: Kegalle Name of the Province: Sabaragamuwa Distance from the District Head Quarter: 40 km Date: 20/ 06/2010 Name of the Component /Site: Elpitiya PLC- Madacombra Estate Number of Participants: 14 Name of the Village: Madacombra Name of the Gramaseva Division: Madacombra Name of the District: Nuwara Eliya Name of the Province: Central Date: 17. 06.2010 Name of the Component /Site: Agarapathana PLC- Pitarathmale Number of Participants: 08 Name of the Village: Pitarathmale Name of the Gramaseva Division: Pitarathmale Name of the District: Badulla Name of the Province: Uva Date: 12. 06.2010 Name of the Component /Site: Hapugastenna PCL- Demodara Estate Number of Participants: 10 Name of the Village: Demodara Name of the Gramaseva Division: Demodara Draft – August 2010 Page 70 Sustainable Power Sector Support II Project SRI 39415

Date, Location and Number of Issue Raised Summary of Discussion Participants in Consultation Name of the District: Badulla Name of the Province: Uva Date: 14. 06.2010 Name of the Component /Site: Maskeliya Plantation PLC, Moray Estate Number of Participants: 6 Name of the Village: Moray Name of the Gramaseva Division: Moray Division Name of the District: Nuwara -Eliya Name of the Province: Central Province Date: 19/ 06/ 2010 Name of the Component /Site: Muskeliya PLC- Thalawakele Estate Number of Participants: 14 Name of the Village: Thalawakele Name of the Gramaseva Division: Thalawakele Name of the District: Nuwara Eliya Name of the Province: Central Date: 16. 06.2010 Name of the Component /Site: Maskeliya -Glentilt Number of Participants: 9 Name of the Village: Maskeliya Name of the Gramaseva Division: Maskeliya Name of the District: Nuwara -Eliya Name of the Province: Central Date: 13/06/2010 Name of the Component /Site: Maturata PLC- Ragala Estate Number of Participants: 14 Name of the Village: Ragala Name of the Gramaseva Division: Ragala Name of the District: Nuwara Eliya Name of the Province: Central Date: 18. 06.2010 Name of the Component /Site: Maturata PLC- Gonapitiya Estate Number of Participants: 14 Name of the Village: Gonapitiya Name of the Gramaseva Division: Gonapitiya Name of the District: Nuwara Eliya Name of the Province: Central Date: 18. 06.2010 Name of the Component /Site: Maturata PLC- Mahauwa Estate Number of Participants: 14 Name of the Village: Walapane Name of the Gramaseva Division: Walapane Name of the District: Nuwara Eliya Name of the Province: Central Date: 17. 06.2010 Name of the Component /Site: Ampara Distribution- Lathugala Number of Participants: 10 Name of the Village: Lathugala Name of the Gramaseva Division: Lathugala Name of the District: Ampara Name of the Province: Eastern Date: 04/05/2010 Name of the Component /Site: Ampara Distribution- Bodagolla Number of Participants: 08 Name of the Village: Bodagolla Name of the Gramaseva Division: Bodagolla Name of the District: Ampara Name of the Province: Eastern Draft – August 2010 Page 71 Sustainable Power Sector Support II Project SRI 39415

Date, Location and Number of Issue Raised Summary of Discussion Participants in Consultation Date: 30/04/2010 Name of the Component /Site: Ampara Distribution- Aligambe Number of Participants: 06 Name of the Village: Dewagramam Aligambe Name of the Gramaseva Division: Dewagramam A/22 Name of the District: Ampara Name of the Province: Eastern Date: 03/05/2010 Name of the Component /Site: Ampara Distribution – Bakinigasdoowa Number of Participants: 9 Name of the Village: Bakinigasdoowa Name of the Gramaseva Division: Galodai Name of the District: Ampara Name of the Province: Eastern Date: 07.05.2010 Name of the Component /Site: Ampara Distribution- Bambarawana Number of Participants: 08 Name of the Village: Sadunpura, Bambarawana Name of the Gramaseva Division: Sadunpura 142/E Name of the District: Ampara Name of the Province: Eastern Date: 08/05/2010 Name of the Component /Site: Ampara Distribution- Kahatagasyaya Number of Participants: 12 Name of the Village: Kahatagasyaya Name of the Gramaseva Division: Kahatagasyaya W/100A Name of the District: Ampara Name of the Province: Eastern Date: 01/05/2010 Name of the Component /Site: Ampara Distribution- Galoyapallama Number of Participants: 12 Name of the Village: Kalugolla Galoyapallama Name of the Gramaseva Division: Kalugolla W/28E Name of the District: Ampara Name of the Province: Eastern Date: 30/04/2010 Name of the Component /Site: Ampara Distribution-Tempana Number of Participants: 06 Name of the Village: Tempana Name of the Gramaseva Division: Kudaharasgala 136 Name of the District: Amapara Name of the Province: Eastern Date: 06/05/2010 Name of the Component /Site: Amapara Distribution- Hagamwala Number of Participants: 05 Name of the Village: Hagamwala Name of the Gramaseva Division: Hagamwala Name of the District: Ampara Name of the Province: Eastern Date: 07/05/2010 Name of the Component /Site: Mahiyangana to Nawagirinagar Tx line- Dambana Indegenous Village Number of Participants: 06 Name of the Village: Dambana Indigenous village Name of the Gramaseva Division:Dambana Draft – August 2010 Page 72 Sustainable Power Sector Support II Project SRI 39415

Date, Location and Number of Issue Raised Summary of Discussion Participants in Consultation Name of the District: Badulla Name of the Province: Uva Date: 19/05/2010 Name of the Component /Site: Galle Grid Substation Number of Participants: 05 Name of the Village: Panapitiya Name of the Gramaseva Division: 91/A Randenigama ,Karandeniya Name of the District: Galle Name of the Province: Southern Date: 22/04/2010 Name of the Component /Site: Low Voltage (Galmadu Junction) Number of Participants: 04 Name of the Village: Galmaduwa Name of the Gramaseva Division: Damana Name of the District: Ampara Name of the Province: Eastern Date: 16/05/2010 Name of the Component /Site: Akkaraipattu Distribution substation -Low Voltage improvement Number of Participants: 1 Name of the Village: Akkaraipattu Name of the Gramaseva Division: Alayadivembu Name of the District: Ampara Name of the Province: Eastern Date: 16/05/2010 Name of the Component /Site: Galmadu- Akkaraipattu (hijira Junction)- Low voltage improvement Number of Participants: 05 Name of the Village: Hijira Junction Name of the District: Ampara Name of the Province: Eastern Date: 16/05/2010 Name of the Component /Site: Proposed Mahiyangana Sub Station Number of Participants: 06 Name of the Village: Dehigolla Name of the Gramaseva Division: Dehigolla 3/B Name of the District: Badulla Name of the Province: UVA Date: 19/05/2010 Name of the Component /Site: Moneragala TX line – Bakinigahawela Tapping point Number of Participants: 05 Name of the Village: Meegasthenna Name of the Gramaseva Division: Pubbawela Name of the District: Moneragala Name of the Province: Uva Date: 14.05.2010 Name of the Component /Site: Moneragala Medagama TX line – Buthsaranapitiya Junction Number of Participants: 4 Name of the Village: Naranwana Name of the Gramaseva Division: Naranwana Name of the District: Moneragala Name of the Province: Uva Date: 15.05.2010 Name of the Component /Site: Moneragala Medagama TX line – Buthsaranapitiya Junction Number of Participants: 4 Name of the Village: Naranwana Name of the Gramaseva Division: Naranwana Name of the District: Moneragala Draft – August 2010 Page 73 Sustainable Power Sector Support II Project SRI 39415

Date, Location and Number of Issue Raised Summary of Discussion Participants in Consultation Name of the Province: Uva Date: 15.05.2010 Name of the Component /Site: New Galle 132 KV Line Number of Participants: 06 Name of the Village: Hillside watta Name of the Gramaseva Division: Haliwala 130/B Name of the District: Galle Name of the Province: South Date: 24/04/2010 Name of the Component /Site: Nawagirinagar- Ampara TX Line (69th Junction) Number of Participants: 04 Name of the Village: 69th Junction Name of the District: Ampara Name of the Province: Eastern Date: 17/05/2010 Name of the Component /Site: TX Line Nawagirinagar-Ampara ( Udayapura) Number of Participants: 04 Name of the Village: Udayapura Name of the Gramaseva Division: Udayapura W/93/A Name of the District: Ampara Name of the Province: Eastern Date: 16/05/2010 Name of the Component /Site: TX Line, Proposed Ampara Sub Number of Participants: 04 Name of the Village: Mihindupura Name of the Gramaseva Division: Mihindupura Name of the District: Ampara Name of the Province: Eastern Date: 16/05/2010 Name of the Component /Site: TX Line Nawagirinagar Junction Number of Participants: 07 Name of the Village: Selvapuram-49 Colony Name of the Gramaseva Division: Selvapuram Name of the District: Batticalo Name of the Province: Eastern Date: 18/05/2010 Name of the Component /Site: Mahiyangana- Nawagirinagar TX Line ( Thapalpola) Number of Participants: 06 Name of the Village: Thapalpola Name of the Gramaseva Division: Thapalpola 144/D Name of the District: Ampara Name of the Province: Eastern Date: 18/05/2010 Name of the Component /Site: Mahiyangana- Nawagirinagar TX Line (Welampale) Number of Participants:06 Name of the Village: Welampale Name of the Gramaseva Division: Welampale 2E Name of the District: Badulla Name of the Province: UVA Date: 19/05/2010

Draft – August 2010 Page 74 Sustainable Power Sector Support II Project SRI 39415

ANNEXURE- 6 BRIEF OVERVIEW ON VARIOUS RELEVANT POLICIES

1. LAND ACQUISITION ACT 1950 ALONG WITH AMENDMENTS BY 2009 1. The law governing acquisition of land for public purposes is the Land Acquisition Act (LAA), enacted in 1950 and which has been the subject of several amendments and revisions. LAA provides the legal basis to acquire land, if required for any project including in the electricity sector. The LAA sets out the procedures for acquiring land and for payment of compensation for acquired land.

2. A notice is issued specifying that land is potentially required for a public purpose, and this permits authorised personnel to undertake investigations (surveys, boreholes, and setting out of boundaries etc) to determine suitability. If the land is deemed suitable for the public purpose a written declaration to that effect is made, and notices are issued describing the land, the intention to acquire the land, and requiring that persons with an interest in the land notify (in writing) the acquiring officer of their claim (including the expected amount of compensation)16.

3. The acquiring officer then holds an inquiry into the market value of the land, the claims for compensation, and the respective interests of the claimants, as well as any other related matters. At the conclusion of the inquiry the acquiring officer either makes a decision on the claims or refers the claims to the District Court or Primary Court.

4. Following the decision (either by the acquiring officer or the courts), the acquiring officer makes an award determining the persons who are entitled to compensation, the total amount of compensation deemed to be allowed for the acquisition, and the apportionment of the compensation between the persons with interest in the land. In the event of a dispute over the determination, it may be appealed to either the Compensation Review Board or Court of Appeal (on questions of law following a decision by the Compensation Review Board), provided that the appeal is lodged within 21 days of receipt of notification of the award.

5. Provided that there are no appeals, the compensation is paid (the LAA allows for an initial payment and the remainder to be paid in instalments). If the person with an interest in the land has agreed to a land exchange in lieu of cash, the transfer is put into effect at this time. After the awards are made the Minister publishes or gazettes a “vesting order” for the possession of the land, after which time occupants of any buildings located on the land to be vested are given notice to vacate.

2. NATIONAL INVOLUNTARY RESETTLEMENT POLICY 2001 (NIRP) 6. To ensure that people affected by development projects are treated in a fair and equitable manner, and that they are not impoverished in the process, GoSL has adopted National Involuntary resettlement Policy (NIRP) in 2001. This policy would establish the framework for project planning and implementation. Subsequently, it will be necessary to prepare guidelines on resettlement planning and implementation to be used by the PEA. In the past, project related resettlement of Sri Lanka has been guided by Land Acquisition Act of 1950, as amended from ti e to time. However, as it did not have adequate provisions for full social and economic rehabilitation of the people to be resettled, Sri Lanka has adopted NIRP. The policy assigns the overall responsibility of its implementation to the Ministry of Land Development, with the project approving agencies and the Central Environmental Authority too being assigned responsibilities of evaluation and implementation. In addition to the NIRP, a cabinet decision has been adopted in 2006, (as amended in 2007) specifically for the payment of compensation for families affected by land acquisition for power sector development projects and works connected with electrical undertakings. As stated earlier, no involuntary resettlement is foreseen in this project. However in case any involuntary resettlement becomes unavoidable, compensation would be paid in accordance with the NIRP and the Cabinet Decision of 2006 (amended in 2007)

7. The policy will apply to all development-induced land acquisition or recovery of possession by the State. A comprehensive Resettlement Action Plan will be required where 20 or more families are affected and if less than 20 families are affected the policy still applies but a plan can be prepared to a lesser level of detail. The policy will apply to all projects regardless of source of funding and. The policy will apply to all projects in the planning phase on the date this policy comes into effect, and all future projects. Some of the

16 The acquiring officer can also request any person with an interest in the land to deliver a statement setting out the names and addresses of every other person with any form of interest (whole or partial) in the land.

Draft – August 2010 Page 75 Sustainable Power Sector Support II Project SRI 39415 basic objectives of the NIRP are to (i) avoid, minimise and mitigate negative impacts of involuntary resettlement by facilitating the reestablishment of the affected people on a productive and self-sustaining basis. The policy should also facilitate the development of the project-affected people and the project; (ii) to ensure that people adversely affected by development projects are fully and promptly compensated and successfully resettled and the livelihoods of the displaced persons should be re-established and the standard of living improved; (iii) ensure that no impoverishment of people shall result as a consequence of compulsory land acquisition for development purposes by the State, (iv) to assist adversely affected people in dealing with the psychological, cultural, social and other stresses caused by compulsory land acquisition; (v) to make all affected people aware of processes available for the redress of grievances that are easily accessible and immediately responsive, (vi) to have in place a consultative, transparent and accountable involuntary resettlement process with a time frame agreed to by the PEA and the affected people.

8. The Broad principles of the NIRP are as follows:

 Involuntary resettlement should be avoided or reduced as much as possible by reviewing alternatives to the project as well as alternatives within the project.  Where involuntary resettlement is unavoidable, affected people should be assisted to re-establish themselves and improve their quality of life.  Gender equality and equity should be ensured and adhered to throughout the policy.  Affected persons should be fully involved in the selection of relocation sites livelihood compensation and development options at the earliest opportunity  Replacement land should be an option for compensation in the case of loss of land; in the absence of replacement land cash compensation should be an option for all affected persons  Compensation for loss of land, structures, other assets and income should be based on full replacement cost and should be paid promptly. This should include transaction costs.  Resettlement should be planned and implemented with full participation of the provincial and local authorities.  To assist those affected to be economically and socially integrated into the host communities, participatory measures should be designed and implemented.  Common property resources and community and public services should be provided to affected people.  Resettlement should be planned as a development activity for the affected people.  Affected persons who do not have documented title to land should receive fair and just treatment.  Vulnerable groups should be identified and given appropriate assistance to substantially improve their living standards.  Project Executing Agencies should bear the full costs of compensation and resettlement.

3. ADB’S SAFEGUARD POLICY STATEMENT, 2009 (SPS) 9. ADB has adopted Safeguard Policy Statement (SPS) in 2009 including safeguard requirements for environment, involuntary resettlement and indigenous people. The objectives of the Involuntary Resettlement Safeguard policy is to avoid involuntary resettlement wherever possible; to minimise involuntary resettlement by exploring project and design alternatives; to enhance, or at least restore, the livelihoods of all displaced persons in real terms relative to pre-project levels; and to improve the standards of living of the displaced poor and other vulnerable groups.

10. The involuntary resettlement safeguards covers physical displacement (relocation, loss of residential land, or loss of shelter) and economic displacement (loss of land, assets, access to assets, income sources, or means of livelihoods) as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas. It covers them whether such losses and involuntary restrictions are full or partial, permanent or temporary. The main policy principles of the Involuntary Resettlement Safeguard are:

(i) Screen the project early on to identify past, present, and future involuntary resettlement impacts and risks. Determine the scope of resettlement planning through a survey and/or census of displaced persons, including a gender analysis, specifically related to resettlement impacts and risks. (ii) Carry out meaningful consultations with affected persons, host communities, and concerned non-government organisations. Inform all displaced persons of their entitlements and resettlement options. Ensure their participation in planning, implementation, and monitoring and evaluation of resettlement programs. Pay particular attention to the needs of vulnerable groups, especially those below the poverty line, the landless, the elderly, women and Draft – August 2010 Page 76 Sustainable Power Sector Support II Project SRI 39415

children, and Indigenous Peoples, and those without legal title to land, and ensure their participation in consultations. Establish a grievance redress mechanism to receive and facilitate resolution of the affected persons’ concerns. Support the social and cultural institutions of displaced persons and their host population. Where involuntary resettlement impacts and risks are highly complex and sensitive, compensation and resettlement decisions should be preceded by a social preparation phase. (iii) Improve, or at least restore, the livelihoods of all displaced persons through (i) land-based resettlement strategies when affected livelihoods are land based where possible or cash compensation at replacement value for land when the loss of land does not undermine livelihoods, (ii) prompt replacement of assets with access to assets of equal or higher value, (iii) prompt compensation at full replacement cost for assets that cannot be restored, and (iv) additional revenues and services through benefit sharing schemes where possible. (iv) Provide physically and economically displaced persons with needed assistance, including the following: (i) if there is relocation, secured tenure to relocation land, better housing at resettlement sites with comparable access to employment and production opportunities, integration of resettled persons economically and socially into their host communities, and extension of project benefits to host communities; (ii) transitional support and development assistance, such as land development, credit facilities, training, or employment opportunities; and (iii) civic infrastructure and community services, as required. (v) Improve the standards of living of the displaced poor and other vulnerable groups, including women, to at least national minimum standards. In rural areas provide them with legal and affordable access to land and resources, and in urban areas provide them with appropriate income sources and legal and affordable access to adequate housing. (vi) Develop procedures in a transparent, consistent, and equitable manner if land acquisition is through negotiated settlement to ensure that those people who enter into negotiated settlements will maintain the same or better income and livelihood status. (vii) Ensure that displaced persons without titles to land or any recognisable legal rights to land are eligible for resettlement assistance and compensation for loss of non-land assets. (viii) Prepare a resettlement plan elaborating on displaced persons’ entitlements, the income and livelihood restoration strategy, institutional arrangements, monitoring and reporting framework, budget, and time-bound implementation schedule. (ix) Disclose a draft resettlement plan, including documentation of the consultation process in a timely manner, before project appraisal, in an accessible place and a form and language(s) understandable to affected persons and other stakeholders. Disclose the final resettlement plan and its updates to affected persons and other stakeholders. (x) Conceive and execute involuntary resettlement as part of a development project or program. Include the full costs of resettlement in the presentation of project’s costs and benefits. For a project with significant involuntary resettlement impacts, consider implementing the involuntary resettlement component of the project as a stand-alone operation. (xi) Pay compensation and provide other resettlement entitlements before physical or economic displacement. Implement the resettlement plan under close supervision throughout project implementation. (xii) Monitor and assess resettlement outcomes, their impacts on the standards of living of displaced persons, and whether the objectives of the resettlement plan have been achieved by taking into account the baseline conditions and the results of resettlement monitoring. Disclose monitoring reports.

4. GAPS BETWEEN VARIOUS POLICIES

11. In Sri Lanka the Land Acquisition Act of 1950 as amended from time to time only provides for compensation for land, structures and crops. It does not require the PEAs to address key resettlement issues such as (a) exploring alternative project options that avoid or minimise impacts on people; (b) compensating those who do not have title to land; (c) consulting affected people and hosts on resettlement options; (d) providing for successful social and economic integration of the affected people and their hosts, and (e) full social and economic rehabilitation of the affected people. A gap analysis of various policies has been given in Table 1

Draft – August 2010 Page 77 Sustainable Power Sector Support II Project SRI 39415

Table 1: Comparison of ADB’s policy with National Policies and Laws Land Acquisition ADB’s Involuntary National Involuntary Sl. Act 1950 along with Resettlement Policy Resettlement Policy 2001 Remarks Nº Amendments by Principles (2009) (NIRP) 2009 1 Involuntary resettlement This principle is equally No such objective is NIRP 2001 meets should be avoided emphasised under NIRP outlined ADB IR Policy wherever possible 2001 requirements 2 Minimise involuntary NIRP 2001 aims to No such objective is NIRP 2001 meets resettlement by minimise displacement and outlined ADB IR Policy exploring to promote, as far as requirements project and design possible, non-displacing or alternatives least-displacing alternatives 3 Conducting census of Preparation of inventory of No provision or NIRP 2001 meets displaced persons and loses including people and procedure specified. ADB IR Policy resettlement planning their properties and requirements preparation of re-settlement implementation plan were out lined under NIRP 2001 4 Carry out meaningful NIRP 2001 ensure No provision made NRIRP 2001 consultation with adequate rehabilitation meets ADB IR displaced persons and package and expeditious Policy ensure their participation implementation of the requirements in planning, rehabilitation process with implementation and the consultation and active monitoring of participation of the affected resettlement program families 5 Establish grievance Project involving involuntary No provision made NIRP 2001 meets redress mechanism resettlement needs to have ADB IR Policy Grievance redress requirements mechanisms for affected people 6 Support the social and Restoration and No provision made NIRP 2001 meets cultural institutions of rehabilitation of social and ADB IR Policy displaced persons and cultural institutions should requirements their host population. be provided and same facilities should be given to host families under NIRP 2001 7 Improve or at least NIRP 2001 emphasises the No provision made NIRP 2001 meets restore the livelihoods of same ADB IR Policy. all displaced persons 8 Land based Loss of asset to be No provision made NIRP 2001 meets resettlement strategy compensated to the extent ADB IR Policy. of actual loss 9 All compensation should The compensation award Market value for land NIRP 2001 meets be based on the shall take into account the and replacement ADB IR Policy principle of replacement market value of the value for structures requirements. cost property being acquired should be paid This requirement according to the also meets under regulation no.1596/12 regulation Dated 07/04/2009 of no.1596/12 land acquisition act 07/04/2009 of land acquisition act 10 Provide relocation NRRP 2007 emphasises In case of loss of land NIRP 2001 meets assistance to displaced the same and structures only ADB IR Policy. persons compensation should Part of this be paid requirement provided under Draft – August 2010 Page 78 Sustainable Power Sector Support II Project SRI 39415

Land Acquisition ADB’s Involuntary National Involuntary Sl. Act 1950 along with Resettlement Policy Resettlement Policy 2001 Remarks Nº Amendments by Principles (2009) (NIRP) 2009 regulation no.1596/12 of 07/04/2009 11 Ensure that displaced NIRP 2001 also recognises No provision made NIRP 2001 meets persons without titles to the non-titleholders to ADB IR Policy land or any recognisable provide same benefits as requirements. legal rights to land are others eligible for resettlement assistance and compensation for loss of non-land assets. 12 Disclose the NIRP 2001 ensure this No provision made NIRP 2001 meets resettlement plan, principle ADB IR Policy including documentation requirements of the consultation in an accessible place and a form and language(s) understandable to affected persons and other stakeholders. 13 Conceive and execute NIRP 2001 emphasises to No provision made NIRP 2001 meets involuntary resettlement integrate rehabilitation ADB IR Policy as part of a concerns into the requirements development project or development planning and program. Include the full implementation process costs of resettlement in the presentation of project’s costs and benefits. 14 Pay compensation and Full payment of No provision made. NIRP 2001 meets provide other compensation as well as There is a provision ADB IR Policy resettlement adequate progress in under LAA under requirements entitlements before resettlement shall be emergency situations physical or economic ensured in advance of the land and property can displacement. actual displacement of the be taken over for affected families. development projects without paying compensation before displaced the people under 38A of the act The compensation pays in later stage for such cases 15 Monitor and assess The policy equally No provision made NIRP 2001 meets resettlement outcomes, emphasises the ADB IR Policy their impacts on the requirement for monitoring requirements standards of living of displaced persons.

Draft – August 2010 Page 79 Sustainable Power Sector Support II Project SRI 39415

ANNEXURE-7 MONITORING INDICATORS AND SAMPLE FOR STATUS REPORT S. Nº R&R Activities Progress Remarks Pre Construction Activities and R&R Activities 1 Assessment of Resettlement impacts due to changes in project design (If required) 2 Preparation/ updating of Resettlement Plan based on changes in project design 3 Approval of updated Resettlement Plan from ADB 4 Disclosure of updated Resettlement Plan 5 Establishment of Grievance Redressal Committee 6 Capacity building of ESC Verification of APs Census list; assessment on compensation and assistance, and readjustment 7 Land Acquisition Resettlement Plan Implementation 1 Payment of Compensation as per replacement value of land & assets to APs 2 Disbursement of assistance to title holders 3 Disbursement of assistance to non-title holders 4 Disbursement of special assistance to Vulnerable groups 5 Replacement/ shifting of community property resources 6 Reinstallation of public utilities 7 Records of Grievance Redressal 8 Temporary Relocation of Hawkers and Vendors 9 Income Restoration Measures through training Social Measures during Construction as per Contract Provisions 1 Prohibition of employment or use of children as labour 2 Prohibition of Forced or Compulsory Labour 3 Ensure equal pay for equal work to both men and women 4 Implementation of all statutory provisions on labour like health, safety, welfare, sanitation, and working conditions 5 Maintenance of employment records of workers

Draft – August 2010 Page 80