<<

Environmental Monitoring Report

Project Number 42459-014 Loan 3431 Semestral Report July to December 2020

April 2021

Sri Lanka: Local Government Enhancement Sector Project Additional Financing (LGESP-AF)

Prepared by LGESP (Pura Neguma) Project Management Unit for the State Ministry of Provincial Councils and Local Government Affairs, , and the Asian Development Bank.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgements as to the legal or other status of any territory or area.

Government of Sri Lanka State Ministry of Provincial Councils & Local Government Affairs

Semi Annual Environmental Safeguard Monitoring Report (HY2 - 2020 : 01 July 2020 to 31 December 2020)

January 2021

Local Government Enhancement Sector Project - Additional Financing ADB Loan Number 3431 - SRI

Project Management Unit Local Government Enhancement Sector Project 191 A, J R Jayewardene Centre, Dharmapala Mawatha, Colombo 07, Sri Lanka

2

ABBREVIATIONS

ADB - Asian Development Bank AF - Additional Financing CEA - Central Environmental Authority CKD - Chronic Kidney Disease

Management DSC - Design and Supervision Consultants EIA - Environmental Impact Assessment EMP - Environmental Management Plan GRC - Grievance Redress Committee GRM - Grievance Redress Mechanism IEE - Initial Environmental Examination LGESP - Local Government Enhancement Sector Project LGIIP - Local Government Infrastructure Improvement Project MPR - Monthly Progress Report MMDE - Ministry of Mahaweli Development & Environment SMPCLA - State Ministry Provincial Councils & Local Government NWSDB - National Water Supply and Drainage Board PS - Pradeshiya Shabha PMU - Project Management Unit CDTA - Capacity Development Technical Assistance ERD - External Resource Development PMC - Project Management Consultants RDA - Road Development Authority PRDA - Provincial Road Development Authority SPCU - Sub Project Coordination Unit SESMS - Site Specific Safeguard Monitoring System MCR - Mitigation compliance Report ROW - Right of Way PPE - Personel Protective Equipment SPS - Safeguard Policy Statement

3

Contents

Executive Summary ...... 6 1. INTRODUCTION ...... 8 1.1. Background ...... 8 1.2. Description of the components: ...... 8 1.3. Screening and categororiation of the sub-projects...... 9 1.4. Details of site personnel and/or consultants responsible for environmental monitoring...... 9 1.5. Locations of Sub-projects ...... 10 1.6. Construction activities during reporting period...... 10 1.6.1 Central Province...... 10 1.6.2 North Central Province ...... 13 1.6.3. North Western Province...... 16 1.6.4 UVA Province ...... 17 1.7. Description of Sub -projects Status of completion, approval and disclosure of safeguard documents (environment)...... 19 1.8 “B” category Sub-project progress and status...... 19 2. STATUS OF STATUTORY CLEARANCES ...... 23 3. COMPLIANCE STATUS WITH ENVIRONMENTAL LOAN COVENANTS ...... 26 4. COMPLIANCE STATUS WITH THE ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN 28 5. OVERALL COMPLIANCE WITH EMP ...... 28 6. APPROACH AND METHODOLOGY FOR ENVIRONMENTAL MONITORING OF THE PROJECT. 28 7. COMPLIANCE WITH ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN...... 29 7.1. Monitoring of Environmental Impacts on project surroundings...... 29 7.2 Public Compliants...... 31 7.3 Examples of good practices, non-compliance notices and corrective plans...... 31 8. MITIGATION MEASURES FOR PREVENTION OF COVID 19...... 35 9. SUMMARY OF KEY OUTSTANDING ISSUES...... 36 10. CONCLUSION...... 37

List of Figures Figure 1- Map indicating sub project locations...... 10 Figure 2- Pipe line being excavated ...... 11 Figure 3- Preparing to lay DI pipe over a water way by the of a small bridge ...... 11 Figure 4- Excavating a trench saving trees ...... 11 Figure 5- Trench has been excavated saving trees...... 12 Figure 6- Trench being excaveted ...... 12 Figure 7- Laying DI raw water main across the tank bund...... 13 Figure 8- Constructing interconnection from new one to with existing sump...... 13 Figure 9- DI pipe anchoring to the Brdge ...... 14 Figure 10 -Handing over to NWS&DB officials ...... 14 Figure 11- Pressure testing work of a pipeline section already completed...... 14 Figure 12- Internal road being reinstated after pipe laying completed...... 15 Figure 13- Filter house being constructed...... 15 Figure 14- Pipe line being laid in Row...... 15 Figure 15- Monitoring blasting process of a rock...... 16 Figure 16- Renovation of rainy type intake (bore hole) being done ...... 16

4

Figure 17- Excavation of a rock in a trench ...... 16 Figure 18- Water tower being constructed ...... 17 Figure 19-Clear water sump being constructed ...... 17 Figure 20- Valve chamber being constructed...... 17 Figure 21- A trench being backfilled...... 17 Figure 22- Pressure test being done...... 18 Figure 23- Trench excavation in progress...... 18 Figure 24- Storage tank under construction...... 18 Figure 25- Intake well being constructed ...... 18 Figure 26- Safety cones and tapes placed along road side...... 32 Figure 27- Safety signs placed on the road side while working...... 32 Figure 28-Wate tank with safety net in Karuwalagaswewa ...... 33 Figure 29- Pipe laying being done by slight deviation of alignment saving trees...... 33 Figure 30- Unsafe electrical connection...... 34 Figure 31- Log note giving instruction to rectify the unsafe electirical connection...... 34

List of Tables

Table 1-The status and overall physical progress of “B” category sub –projects as on 31st December 2020...... 19 Table 2-Statutory Clearances obtained...... 23 Table 3-Summery of status of loan covenant ...... 26 Table 4-Summarized compliance status of all Sub projects...... 28 Table 5: No of trees removed and replanted ...... 29 Table 6- Summary of Key Outstanding Issues...... 36

List of Appendices Appendix 1-Status of ADB’s approval of Initial Environmental Examination (IEE) Reports...... 38 Appendix 2 -Status of sub project under pre -construction phase as on 31.12.2020...... 54 Appendix 3 - Grievance redressal details status summary...... 55 Appendix 4 -A Completed Mitigation Compliance Report (MCR) used in SESM System- Water Supply Scheme - Nikaweratiya Ambanpola,December 2020.( NWP -AF-WS-CKD-14A)...... 54 Appendix 5- Computer Generated Mitigation Compliance Reports in SESMS in December 2020 / Category “B”...... 73 Appendix 6-Status Summery Report of Category “C” Sub-projects as on 31.12.2020 ...... 81 Appendix 7: Status report on COVID 19 mitigation as on 31st December 2020 ...... 85 Appendix 8: Guideline circulated by the PMU to resume office work and construction activities after lifting lockdown (curfew) imposed because of COVID-19...... 92

5

Executive Summary

The Local Government Enhancement Sector Project (LGESP) was approved by ADB on 29 September 2011 with an amount of $ 59 million equivalent from ADB’s Special Fund Resources. The loan became effective on 27 November 2011 and the loan closing date is 10 January 2018. State Ministry of Provincial Councils and Local Government (SMPCLG) (formerly Ministry of Provincial Council and Local Government (MPCLG)) is the executing agency which implemented the project through Project Management Unit (PMU), and subproject coordination units (SPCU) established in each provincial council (total seven) to supervise and coordinate and project implementation. LGESP has been supporting local infrastructure improvement and basic service delivery in less-developed areas in seven provinces (excluding the Northern and Eastern Provinces), based on a bottom-up, demand-driven approach. The project was performing well under the original loan, therefore ADB approved an additional financing loan in year 2016.

Impact of the project will be strengthening the financial and technical capacities of the local authorities of these seven provinces. The outcome will be improved local infrastructure and services delivered effectively by local authorities or NWSDB in less-developed areas of seven provinces in Sri Lanka. The additional financing loan has three outputs.

Output 1: Water supply systems in CKD-affected areas improved. Output 2: Local infrastructure and basic service delivery improved. Output 3: Local government policy reform advanced and capacity strengthened.

Institutional mechanism for Environmental Safeguards is adequate with officials of safeguard monitoring available at all tiers of project management like PMU, SPCU and supported by consultants.

IEEs of all subprojects submitted to ADB are approved and disclosed in ADB and Puraneguma websites. DDRs of all subprojects are also approved and disclosed in both web sites.

The required statutory clearances have been obtained for all sub-projects presently under construction as detailed in the main report.

Loan Covenants related to Environmental Safeguards are being complied regularly.

Environmental Management Plan is being monitored regularly through SESMS (a software developed by ADB) and regularly reported.

This semiannual report on Environment Safeguard discusses the overall physical progress with environmental compliance status of Category “B” sub projects for which IEEs have been prepared as per ADB SPS 2009 coming under Output 01. In addition, status of physical progress of Category “C” sub projects, coming under Output 02 has also been annexed. Physical progress of both Outputs is as on 31st December 2020.

Progress of sub-projects which are under construction are discussed in the report. There were no environmental issues in the sub projects which are completed. One sub project of output 01 is under pre-construction phase and its physical progress is not significant to report as it is still under bidding process. (Appendix 02).Overall summary of physical progress of category “B” sub projects is given in table 01. Appendix 01 gives the status of ADB approval of all IEE reports.

6

Appendix 04 and 05 give two examples of a selected sub project showing a completed Mitigation Compliance Report in the SESM system for the month of December 2020 and its related computer generated report where compliance status of mitigatory measures and further actions on improvement of mitigation measures have been given.

During this reporting period, it had been noticed that there has been reasonable compliance to Covid 19 guidelines and workers too seem to be adopted to new normal situation.

In conclusion, it can be mentioned that both environmental and health risks have been controlled in all subprojects, by taking the required mitigation measures, as and when required and as specified in the EMP.

The environmental safeguard compliance during the reporting period and cumulative basis can be said to be satisfactory.

7

Local Government Enhancement Sector Project - (Additional Financing) - (Loan No. 3431 - SRI)

Semi-Annual Environmental Safeguards Monitoring Report (For period H2 2020 01 July 2020 to 31 December 2020)

1. INTRODUCTION

1.1. Background

The Local Government Enhancement Sector Project (LGESP) was approved by ADB on 29 September 2011 with an amount of $59 million equivalent from ADB’s Special Fund Resources. This project was envisaged to improve the effective delivery of local infrastructure and services in selected LAs in less-developed areas of Sri Lanka. Under the project, 108 Local Authorities have been selected in seven provinces (excluding the Northern and Eastern provinces), whose reform plans are reviewed and confirmed by the government, will implement subprojects such as roads and bridges, water supply and sanitation, drainage, solid waste management, and other basic facilities, including buildings or enhancing health-care centers and public markets. The loan became effective on 27 November 2011. State Ministry of Provincial Councils and Local Government) (formerly known as Ministry of Provincial Council and Local Government (MPCLG)) is the executing agency and functioned through Project Management Unit (PMU) established in Colombo and subproject coordination unit (SPCU) established in each provincial council (total seven) to supervise and coordinate and project implementation. LGESP has been supporting local infrastructure improvement and basic service delivery in less-developed areas in seven provinces based on a bottom-up, demand-driven approach. The original loan was closed on 10 January 2018. Based on the performance of the original project, ADB agreed to provide an additional finance to the scale up the well performing project and to include; (i) improvement of water supply systems in areas affected by chronic kidney diseases (CKD); (ii) improvement of local infrastructure and basic services delivery; and (iii) advancing policy reform of PS and strengthening their capacity.

Impact and Outcome. Strengthened financial and technical capacity of the local authorities in less-developed areas within the selected seven provinces is the expected impact of the project. Improved local infrastructure and services delivered effectively by local authorities or National Water Supply and Drainage Board (NWSDB) in less-developed areas in these seven provinces will be the outcome of the project.

1.2. Description of the components:

The additional financing has three outputs as follows;1

Output 1: Water supply systems in CKD-affected areas improved. The additional financing will finance development and expansion of water supply systems in CKD-affected areas in the four provinces (Central, North Central, North Western, and Uva) to provide safe drinking water. The schemes include development of new water supply systems and expansion of existing systems, mostly run by NWSDB. Facilities such as raw water intakes, water treatment plants, overhead tanks, and transmission and distribution networks are eligible for financing. About 30 schemes will be developed or expanded, and will be implemented by respective provincial councils with technical inputs and supervision support from NWSDB. Considering the nature and

1 ADB (September 2016), Report and recommendation of the president to the board of directors, Proposed Loan for Additional Financing Democratic Socialist Republic of Sri Lanka: Local Government Enhancement Sector Project 8 complexity of the schemes, the piped-network will be operated by NWSDB, except in local authorities which have adequate operational capacity. If local authorities are identified to be the appropriate entity to implement the subprojects, such local authorities will first have to submit a reform plan, as practiced in the original project, prior to the subproject implementation. PMU, through design and supervision consultants (DSCs), will provide capacity augmentation for construction supervision, when the resources available from NWSDB are insufficient.

Output 2: Local infrastructure and basic service delivery improved. Social and economic infrastructure will be improved by newly participating local authorities. The approach will remain the same: 29 new Pradeshiya Sabhas from five provinces (Central, North Western, Southern, Uva, and Western) which have not been supported under the LGIIP and LGESP will first have to submit a reform plan approved through a council resolution, which will be reviewed and confirmed by the Ministerial Committee of MPCLG to ensure that the minimum reform requirements are met. Then they will be qualified for the provision of a capital grant for infrastructure improvement. Eligible subprojects include (i) environmental infrastructure, (ii) economic infrastructure, (iii) public health infrastructure, and (iv) other local authority facilities. PMU, through DSCs, will support preparation of design and ensure the quality of the work. For both outputs 1 and 2, only the subprojects that meet the subproject selection criteria will be implemented.

Output 3: Local government policy reform advanced and capacity strengthened. The additional financing will support establishment of IT solutions, which were developed under the original project and installed in the original 108 PradeshiyaSabhas, in 29 new PradeshiyaSabhas, and further advance business process reengineering in both original and new PradeshiyaSabhas. The activities will include (i) implementation support of the guidelines developed under the Capacity Development TA (CDTA), (ii) development and installation of additional software to simplify and increase efficiency of local administration, and (iii) capacity building programs to strengthen technical, financial, and administrative capacity of the original and new PradeshiyaSabhas, provincial councils, and SMPCLG.

1.3. Screening and categorization of the sub-projects.

The sector project is classified as environmental category B project where the impacts are manageable through implementation of a well-developed environment management and monitoring plan. The subproject does not fall within the “prescribed list” of projects that needs to undergo the environmental impact assessment process under the national environmental act and ADB’s SPS 2009.

1.4. Details of site personnel and/or consultants responsible for environmental monitoring.

The project has an “Environment and Social Safeguard Manager (PMU)” at central level i.e. the Project Management Unit and at the provincial level, each province Subproject Coordination Unit (SPCU), a Reform & Safeguard Manager (Social, Environmental and Gender) will look after the Environmental Safeguard issues. These officers in the project are supported by the “Environment Safeguard Expert” of the Project Management Consultants at National level and “Safeguard Expert (Environment)” of the Design and Supervision Consultants at Provincial Level who are hired during the design period.

9

1.5. Locations of Sub-projects The following map shows the locations of sub projects coming under category B and C. Table 01 and appendix 06 give list of Category B and C sub projects respectively.

Figure 1- Map indicating sub project locations.

1.6. Construction activities during reporting period. This section highlights the main construction activities undertaken during the reporting period.

1.6.1 Central Province.

Renovation of Existing Treatment Plant at Dambulla. (CP-AF-WS- CKD-11)

Construction completed. The facility was handed over to the NWS&DB in October, 2018 and is operational.

10

Water Supply Extension to Dambulla and Kandalama. (CP -AF- WS-CKD-10A).

A total length of 83.347 km of pipe lines have been laid out of 132.631km⃰ and back filled by end December 2020.Presure testing of completed section was also carried out during the reporting period.

Figure 2- Pipe line being excavated

Water Supply Extension to Inamaluwa and Kithulhitiyawa. (CP -AF- WS-CKD-10B) A total length of 109.453km of pipe lines have been laid out of 110.547km⃰ and back filled by end December 2020. Construction work of valve chambers and laying of DI pipes over bridges were also carried out during this reporting period.

Figure 3- Preparing to lay DI pipe over a water Figure 4- Excavating a trench saving trees way by the of a small bridge

11

Water Supply Extension to and Habarana. (CP -AF- WS-CKD-10C)

A total length of 89.631 km of pipe lines have been laid out of 89.699 km⃰ and back filled by end December 2020.Below picture illustrate trench has been cut saving trees and back filling being done.

Figure 5- Trench has been excavated saving trees.

Water Supply Extension to Thithawelgolla and Galewela. (CP -AF- WS-CKD-10D) A total length of 116.85km of pipe lines have been laid out of 136.804km⃰ and backfilled by end December 2020. Pressure testing of completed section was also carried out during the reporting period. Construction of valve chambers was also carried out during the reporting period. Following figure shows a trench being excavated.

Figure 6- Trench being excaveted

⃰ Scope revised.

12

1.6.2 North Central Province

Water Supply Extension to Uttupitiya (from Kekirawa WaterSupply Scheme)/ (NCP-AF-WS- CKD-01)

Construction completed. A total of 11.86 km pipe line laid. Handed over to the NWS&DB in July 2018 and is operational.

Capacity Improvement to Minneriya Water Treatment Plant. (NCP-AF-WS-CKD-20A)

Initial contract terminated due to poor performance of the contractor. Another contractor appointed for minor balance works. Work in progress. No environmental issues.

Water Supply Extension to Bendiwewa. (NCP-AF-WS-CKD-21)

Laying of pipelines completed. Total length covered is 36.51km. Handed over to NWS&DB in September 2018 and is in operation.

Water Supply Extension to Mahailluppallama. (NCP-AF-WS-CKD-02)

Laying of pipelines completed. Total length covered is 57.16km. Handed over to NWS&DB in July 2019 and is operational.

Improvement to Existing Water Supply Schemes at Rajanganya and Galnewa. (NCP-AF- WS-AW-02)

Renovation of two ferro cent tanks, panel rooms and construction of two tube wells at Namalgomuwa and Kandegama areas completed during the reporting period and handed over to PS/Rajanganaya in September 2020 and now is operational.

Capacity Improvement of to Nuwarawewa Water Treatment Plant. (NCP-AF-WS-CKD-04)

Continue work on construction of water sump. sludge thickener, lagoon, filter house and replacing old raw water pipe line from intake to treatment plant were the main construction work were carried out during this reporting period. 1.16km raw water main DI pipe line has been completed. The photograph below illustrates, DI pipe laying across tank bund and construction of interconnection from existing water sump to newly constructed one.

Figure 8- Constructing interconnection from Figure 7- Laying DI raw water main across the new one to with existing sump. tank bund.

13

Water Supply Extension to Elagomuwa -Main and distribution lines. (NCP-AF-WS-CKD-03)

Laying of pipelines completed. Total length covered is 159.17 km.Handed over to NWS&DB on 5th September 2020. Fig 9 illustrates final construction i.e. anchoring DI pipe to Pubbogama Bridge.

Figure 9- DI pipe anchoring to the Brdge Figure 10 -Handing over to NWS&DB officials

Water Supply Extension to Sewagama Canal 3 area and Transmission line extension to Sewagama water tower. (NCP-AF-WS-CKD-07)

A total length of 60.86 km of pipe lines have been laid by end December 2020. The photograph below illustrates pressure testing being done.

Figure 11- Pressure testing work of a pipeline section already completed.

14

Extension of Water Supply Scheme to Thambala. (NCP-AF-WS-CKD-08)

Total length of 72.36 km of pipe lines have been laid out of 72.63km by end December 2020. Construction work of valve chambers continued during this reporting period. The photograph below shows DI pipe line laid in ROW and internal road being reinstated by paving cement blocks.

.

Figure 12- Internal road being reinstated after pipe laying completed.

Capacity Improvement of Kalawewa Water Treatment Plant, Ihalagama.(NCP-AF-WS-CKD- 06) Structural works of different components of the water treatment plant such as construction of water sump, filter house and pipe laying work continued during the reporting period. The photographs below illustrate the pipe laying and filter house being constructed. A total length of 2.6km has been laid out of 4.275km by end of December 2020.

Figure 13- Filter house being constructed. Figure 14- Pipe line being laid in Row.

15

Improvement to Existing Kebithigollawa Treatment Plant (NCP-AF-WS-CKD-09A)

A total length of 12.2 km of pipe lines have been laid out of 14.81km by end December 2020. Renovation of existing Intake (bore hole) at Manatiyawa too continued during this reporting period. The photographs below illustrate monitoring of rock blasting process by officials and exiting bore hole at Manatiyawa being rehabilitated.

Figure 16- Renovation of rainy type intake (bore Figure 15- Monitoring blasting process of a rock. hole) being done

1.6.3. North Western Province.

Work Supply Scheme for Ibbagomuwa Pradeshiya Sabah. (NWP-AF-WS-CKD-23/5A)

Construction completed. Handed over to NWSDB in August 2018. Now in operation

Water Supply Extension to Nikaweratiya Ambanpola. (NCP-AF-WS-CKD-14A)

A total length of 88.7 km of pipe lines have been laid and pipe laying completed by end December 2020.Photographs below illustrate excavating a rock for laying of pipeline.

Figure 17- Excavation of a rock in a trench

16

Karuwalagaswewa Water Supply Project. (NCP-AF-WS-CKD-15)

Construction of water storage tower and water treatment plant and pipe laying continued during the reporting period. A total of 12 km has been completed out of 72 km by end December 2020.The photographs below illustrate base of water sump and water storage tank being constructed.

Figure 18- Water tower being constructed Figure 19-Clear water sump being constructed

1.6.4 UVA Province

Water Supply Scheme, Rideemaliyadda (Kurawella and Ekiriyakumbura) / (UVA-AF-WS- CKD-16)

Construction completed. Handed over to Pradeshiya Sabah in December 2018. Now in operation.

Water Supply Extension from Rahathangama, Kumaragama and Kukurampola (from Buttala WSS)/ (UVA-AF-WS-CKD 18)

91.7 km of pipe laying completed out of 94.8km by end December 2020.Laying of pipes and pressure testing, placing valve chambers and fixing flow meters and backfilling continued during the reporting period. The photographs below show precast concrete valve chambers being constructed and placing them in the site.

Figure 21- A trench being backfilled. Figure 20- Valve chamber being constructed.

17

Laying of the Distribution Network in Bathalayaya and Blaganwewa areas. (UVA-AF-WS- CKD 19A) Laying of pipe line continued during the reporting period. 33.2 km of pipe laying completed out of 60.9 km by end December 2020 .The photographs below illustrate pressure testing being done of a completed section and backfilling of pipe laid section.

Figure 22- Pressure test being done. Figure 23- Trench excavation in progress.

Augmentation of Girandurukotte Treatment, Ulhitiya New Intake and Water Supply Extension. (UVA-AF-WS-CKD 19B)

Laying of pipe main continued during the reporting period. 0.62 km of pipe laying completed out of 5.6 km by end December 2020.Construction of storage tank, rapid sand filter, ground sump, sludge drying bed and chemical house continued during the reporting period. Construction of the intake well protected by a cofferdam in Ulhitiya Reservoir also continued during the reporting period. Pictures below illustrate storage tank and intake well protected by coffer dam being constructed

Figure 24- Storage tank under Figure 25- Intake well being constructed construction

18

1.7. Description of Sub-projects Status of completion, approval and disclosure of safeguard documents (environment).

 Status of Safeguard Documents (Environmental):

The status of completion, approval and disclosure of safeguard documents (environment) is given vide Appendix 1 (for Category B sub-projects) and Appendix 6 (for Category C sub- projects)

 Disclosure details:

. Project-based Document

As per the ADB’s Safeguards Policy Statement (SPS - 2009), Environmental Assessment and Review Framework (EARF) has been prepared and approved by ADB. The same is disclosed in ADB and Project’s website.

. Subproject-based Documents  As per ADB approved EARF, Initial Environmental Examination (IEE) reports for “Category B” and Due Diligence Reports – Environment (DDR – Env) for “Category C” subprojects are prepared as required for each of the sub projects. All approved IEEs and DDRs are disclosed in the ADB / Project websites.

1.8 “B” category Sub-project progress and status.

Table 1-The status and overall physical progress of “B” category sub –projects as on 31st December 2020. Status of the Sub Project Overall Physical No Name of Package Package Number Progress

Design Stage Pre- Constructi on Phase Constructi on Phase Operation al Phase Central Province- Output 1: Water supply in CKD affected areas The works included construction of water supply related buildings, installations of electrical and machineries and laying of pipelines CP-AF-WS- CKD- Renovation of existing 11 01 Treatment Plant at 100% ✓ Dambulla

Water Supply CP-AF-WS-CKD- 02 Schemes for Work in progress 12 ✓ Pahaladiggala Water Supply CP -AF- WS-CKD- Work in progress 03 Extension to Dambulla 10A ✓ 50 % (rural)and Kandalama. Water supply extension to CP -AF-WS- CKD Work in progress 04 Inamaluwa and - 10B ✓ Kithulhitiyawa ⃰75% Water supply CP -AF-WS- CKD Work in progress 05 extension to Sigriya - 10C ✓ 19

Status of the Sub Project Overall Physical No Name of Package Package Number Progress

Design Stage Pre- Constructi on Phase Constructi on Phase Operation al Phase and Habarana ⃰75% Work in progress

Water supply

extension to CP -AF-WS- CKD ✓ 06 69% Thithawelgolla and - 10D

Galewela

North Central Province- Output 1: Water supply in CKD affected areas The works included construction of water supply related buildings, installations of electrical and machineries and laying of pipelines Water Supply 100% Extension to NCP-AF-WS- 07 Uttupitiya (from CKD-01 ✓ Handed over to Kekirawa Water NWSDB Supply Scheme) Improvement of Minneriya tank was done under package NCP-AF-WS- No NCP-AFC-WS-

CKD-20 CKD20. Work of this contract stopped at Capacity improvement due to poor progress. 08 to Minneriya Water ✓ Treatment Plant Balance work of above awarded under new NCP-AF-WS- package

CKD-20A Work in progress. 84.4%

Water Supply Extensions to Completed. Handed 09 Bendiwewa (from NCP-AF-WS- ✓ over to NWSDB. Pollonnaruwa water CKD-21 100% supply scheme) Water Supply Completed. Handed Extensions to over to NWSDB. (i) Mahailluppallama NCP-AF-WS- 10 100% & (ii) Thirappane CKD-02 ✓

area (from Kekirawa

water supply scheme) Work in progress. Capacity improvements NCP-AF-WS- 92% 11 of Nuwarawewa CKD-04 ✓ WTP

Water supplyextension Work completed. Elagamuwa - Main

and distribution NCP-AF-WS- 12 100% Lines (from Dambulla CKD-03 ✓

Water Supply Scheme)

Improvements to Work in progress. NCP-AF- 13 Kalawewa Treatment 71% WS-CKD-06 ✓ Plant at Ihalagama (of

20

Status of the Sub Project Overall Physical No Name of Package Package Number Progress

Design Stage Pre- Constructi on Phase Constructi on Phase Operation al Phase Kekirawa Water Supply Scheme) Extension of pipe Work in progress. lines to Sewagama NCP-AF- 14 Canel- 3 area and WS-CKD-07 ✓ 84.2% Thambala Part 2 Water Supply Work in progress NCP-AF- 15 Extension to WS-CKD-08 ✓ Tambala ⃰91.9% Improvement to NCP-AF- Work in progress. 16 Kebithigollawa Water WS-CKD-09 ✓ 84% Supply Scheme.

Improvement to Water - Approval for NCP-AF- 17 Treatment Plant rebidding is pending WS-CKD-22. ✓ Tissawewa with ERD

North Central Province - Output 2: Water Supply Scheme – Additional Works

Improvements to

existing water supply

schemes at NCP-AF-WS-AW- 18 Work completed Rajanganaya and 02 ✓ Handed over to PS Namalgamuwa ,

Anuradhapura. North Western Province- Output 1: Water supply in CKD affected areas The works included construction of water supply related buildings, installations of electrical and machineries and laying of pipelines Water supply Scheme .Work completed and works of Ibbagomuwa- handed over to Supplying and laying of NWP-AF-WS- ✓ NWSDB. pipes for the CKD-05A 100% 19 Ibbagomuwa PS Areas Supply and Installation . Work completed and of pumps, treatment NWP-AF-WS- handed over to plant equipment and CKD-23. ✓ NWSDB. accessories for 100% Ibbagamuwa

Extension of water supply scheme of Work in progress. NWP -AF-WS - Nikaweratiya- 20 CKD- Ambanpola ✓ 90% 14A

Water Supply Work in progress. NWP-AF- 21 Scheme for 26% WS-CKD-15 ✓ Karuwalagawewa. UVA Province- Output 1: Water supply in CKD affected areas The works included construction of water supply related buildings, installations of electrical and machineries and laying of pipelines Water Supply extension from UVA-AF-WS- Work Completed . 22 ✓ Rahathangama, CKD-18 100 % % Kumaragama and 21

Status of the Sub Project Overall Physical No Name of Package Package Number Progress

Design Stage Pre- Constructi on Phase Constructi on Phase Operation al Phase Kukurampola (from Buttala WSS)

Kurawela Water Supply Work completed. 23 Scheme , ✓ Handed over to PS. Rideemaliyadda(Part I) UVA-AF- 100% WS-CKD-16 Ekiriyakumbura Water Work completed. Supply Scheme, Handed over to PS. 24 Rideemaliyadda( Part ✓ 100% II) This IEE includes Augmentation of three packages Giradurukotte namely UVA-AF-WS – Treatment , Ulhitiya UVA-AF- WS- 25 ✓ CKD 19A, 19B and 19 C New intake and WS CKD-19 ext. Belaganwewa, 19A – 43% 19 B - 28% Bathalayaya 19C – 1.5%.

⃰ Programe has been revised, scope of work has been increased.

22

2. STATUS OF STATUTORY CLEARANCES There are several clearances prescribed by certain legislations such as Municipal Councils Ordinance No. 29 of 1947, the Urban Councils Ordinance No. 61 of 1939 and the Act No. 15 of 1987 as amended Pradesiya Sabha, National Environment Act and related Regulations and Acts related to road reservations, archeological sites and felling of trees etc., where applicable need to be met before commencing activities of these sub projects. The status of statutory clearances as on 31st December 2020 is given in the table 02 below.

Table 2-Statutory Clearances obtained.

Central Province-- Output 1: Water supply in CKD affected areas

Sub-project Package S.No Name of Subproject Clearances Required Present Status Number

Renovation of existing Contraction done in the  N/A 01 CP-AF-WS-CKD-11 Treatment Plant at Dambulla NWDB premises itself.

 Obtained from CEA  Obtained from PRDA Obtained from  PRDA  Agrarian  Galewela PS Water Supply Scheme for Development 02 CP-AF-WS-CKD-12 - Pahaladiggala. Office.  Obtained from Galewela PS

03 Water supply extension to CP-AF-WS-CKD-10A  Obtained from CEA Dambulla (rural),  Obtained from RDA Kandalama.  Obtained from PRDA  CEA  Obtained from  RDA Dambulla MC Water supply extension to CP-AF-WS-CKD-10B  PRDA  Obtained from 04 ma, Inamaluwa,  Dambulla MC Dambulla PS Kithulhitiyawa.  Dambulla PS  Obtained from  Galewela PS Galewela PS  Sri Lanka Mahaweli  Obtained from Sri Water supply extension to CP-AF-WS-CKD-10C Authority Lanka Mahaweli 05 Sigiriya, Habarana.  Agrarian Services Authority  Wildlife Dept.  Obtained from  Archeology Dept. Agrarian Services  Obtained from

Wildlife Dept. 06 Water supply extension to CP-AF-WS-CKD-10D  Obtained from Thithawegolla and Galewela. Archeology Dept., subject to AIA

North Central Province-- Output 1: Water supply in CKD affected areas

Sub-project Package S.No Name of Subproject Clearances Required Present Status Number  PS  Obtained from PS 07 Water Supply Extensions to  RDA  Obtained RDA Uttupitiya (from Kekirawa NCP-AF-WS-CKD-01  Wildlife Dept. water supply scheme)  Obtained Wildlife Dept.

23

 Construction will be -NA Balance work at Minneriya 08 Water Treatment Plant. NCP-AF-WS-CKD-20A done within NWS&DB premises itself.

 PS Water Supply Extensions to  Obtained from PS Bendiwewa (from  PRDA  Obtained from PRDA 09 water supply NCP-AF-WS-CKD-21  Irrigation Dept.  Obtained from scheme) Irrigation Dept  PS  Obtained from PS Water Supply Extensions to  Mahaweli Authority  Obtained from (i) Mahailluppallama & (ii)  RDA 10 Thirappane area from NCP-AF-WS-CKD-02 Mahweli Authority  PRDA Kekirawa water supply  Obtained from RDA scheme  Obtained from PRDA

 Construction will be

Capacity improvements of done within NWS&DB -NA 11 NCP-AF-WS-CKD-04 Nuwarawewa WTP premises itself.

 PS  Obtained from PS Water supply extension  RDA  Obtained from RDA Elagamuwa – Main and 12 NCP-AF-WS-CKD-03  PRDA  Obtained from PRDA distribution lines (from Dam  Mahaweli Authority bulla water Supply Scheme)  Obtained from Mahaweli Authority

Extension of pipe lines to  PS  Obtained from PS, Sewagama Canel-3 area and  PRDA  Obtained from 13 Transmission on main NCP-AF-WS-CKD-07  Irrigation Dept. PRDA, extension up to Sewagama  Obtained from Water Tower Irrigation Dept.  PS  Obtained from PS,  RDA  Obtained from RDA,

Water Supply Extension to  PRDA  Obtained from 14 NCP-AF-WS-CKD-08 Tambala Part 2 Irrigation Dept. PRDA,

 Obtained from Irrigation Dept.  RDA  Obtained from PS, NCP-AF-WS-CKD-06  PRDA  Obtained from RDA, Improvements to Kalawewa Treatment Plant at  Archaeology Dept.  Obtained from 15 Ihalagama (of Kekirawa PRDA, WSS)  Obtained from Archaeology Dept.

Work Improvements to Water NCP-AF-WS-CKD-09  PS  Obtained from PS Supply Schemes / 16 Kebithigollawa

17 Improvement to existing NCP-AF-WS-AW- 02  PS Rajanganya N/A water supply schemes at and Galnewa. Rajaganaya and Galnewa, .  Dept. of Archaeology  Obtained Irrigation NCP-AF-WS-AW- 22  Irrigation Depart Dept. 18 Improvement to Existing  Obtained from . Thisawewa Treatment Plant Archaeology Dept.

24

North Western Province-- Output 1: Water supply in CKD affected areas

S. No Name of Package Package Number Clearances Present Status Required

Water supply  RDA  Obtained from extensions to  PRDA RDA Ibbagamuwa NWP-AF-WS-CKD-05A  PS Ibbagamuwa  Obtained from PRDA  Obtained from 19 PS Ibbagamuwa

Supply and Installation of  PS Ibbagamuwa  Obtained from pumps, treatment plant PS Ibbagamuwa NWP-AF-WS-CKD-23 equipment and

accessories for Ibbagamuwa water supply scheme Extension of water  PRDA  Obtained from 20 supply scheme of NWP -AF-WS -CKD-  RDA PRDA Nikaweratiya-Ambanpola 14A  PS Maho  Obtained from RDA  Obtained from PS Maho

21 Water Supply Scheme NWP-AF-WS-CKD-15  PRDA  Obtained from for Karuwalagawewa  RDA PRDA

 Irrigation Dept  Pending from  PS RDA Karuwalagaswew  Obtained from a Irrigation Dept.  Obtained from Karuwalagaswe wa PS Uva Province-- Output 1: Water supply in CKD affected areas

Sub-project Package S.No Name of Subproject Clearances Required Present Status Number

22 Water Supply extension UVA-AF-WS-CKD-18  RDA  Obtained from from Rahathangama,  PRDA RDA Kumaragama and  Obtained from Kukurampola (from Buttala PRDA WSS)

23 Kurawela Water Supply  PRDA  Obtained from Supply Scheme / PRDA Rideemaliyadda (Part I) UVA-AF-WS-CKD-16( one package)

Ekiriyankumbura Water  Obtained from 24 Supply Scheme./  PRDA PRDA Rideemaliyadda (Part II)

25

25 Augmentation of UVA-AF-WS-CKD-19  RDA ­ Obtained from Giradurukotte Treatment  PRDA RDA Plant, Ulhitiya New intake  Sri Lanka Mahaweli ­ Obtained from and Water Supply extension Authority PRDA Belaganwewa, Bathalayaya ­ Obtained from Sri Lanka Mahaweli Authority.

3. COMPLIANCE STATUS WITH ENVIRONMENTAL LOAN COVENANTS The table 3 below summarizes the current status of compliance related to loan covenant.

Table 3-Summery of status of loan covenant No. (List Covenant Status of Action schedule) Compliance Required ( for pending activities) Schedule 5 - The Borrower shall ensure, - (Paragraph 8) and cause the Project Executing Agency to ensure, that the preparation, design, construction, implementation and operation of the project, including each eligible subproject, comply with (a) Being complied for applicable laws and all subprojects. regulations of the borrower relating Regular Monitoring to environment, is done. health and safety; (b) the

environmental safeguards; and (c) all measures and requirements set forth in the EARF, IEEs,DDRs,the EMP and Any corrective or preventative actions set forth in a Safeguards Monitoring Report.

The Borrower shall ensue, or cause to be ensured, that all bidding documents and contracts for works contain provisions that require contractors to:

a) comply with the measures relevant to the contractor set Bidding documents forth in any IEE, DDR EMP, have relevant (to the extent they concern clauses. impacts on affected people during construction) and any corrective or preventive actions set forth in the Safeguard Monitoring Report;

26

b) make available a budget for all environmental and social measures; c) provide the borrower with a written notice of any unanticipated environmental, risks or impacts that arise during construction, implementation or operation of project that were not considered in IEE, EMP and DDR;

d) adequately record the condition of the roads, agricultural lands and other infrastructure prior to starting to transport material and construction ;and

e) reinstate pathways, other local infrastructure and agricultural to at least their pre- project condition upon the completion of the construction. Schedule 5 The Borrower shall do or shall - (Paragraph 14) ensure that the following are done;

Safeguard a) Submit Semi Annual a)Being complied Monitoring safeguard monitoring report to and Reporting. ADB and disclose relevant information from such reports promptly upon submission. b) COVID 19 which an unanticipated b) If any unanticipated pandemic which is a environmental and /or social great social and risks arise during construction health risk that was or operation of the project that not considered in were not considered in any EMP or DDR IEE, EMP, DDR etc, promptly occurred during the inform ADB of the occurrence reporting period. of such risks or impacts with Covid 19 preventive detailed description of the guidelines in line event and proposes corrective with Health Ministry action plan ; and guidelines, were issued for all site as c) Report any actual or potential an update to regular breach of compliance with the Health and Safety measures and requirements Action plan and set forth in any EMP etc., after implemented in all becoming aware of the breach. sites.

c) No actual or potential breach of compliance with measures and requirements set forth in any EMP was observed during the reporting period

27

4. COMPLIANCE STATUS WITH THE ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN

All the contracts of output 02 which have commenced to date / completed are simple small value buildings (costs ranging from 0.1 to 0.4 Mn USD) with no adverse environmental impacts and water supply contracts as in output 01 which include mainly pipe laying have no significant adverse environmental impacts. However, Environmental Management Plans are prepared for each subproject and are monitored by the PMU and SPCU safeguard Managers with the support of consultants (PMC and DSCs) on a regular basis as explained in earlier sections. The completed mitigation compliance format for a particular site is given at Appendix 4 and its related computer generated report is given at Appendix 5.

5. OVERALL COMPLIANCE WITH EMP

Table 4-Summarized compliance status of all sub projects. No Sub Sub Project EMP being Status of Action proposed Project Contract implemented implementation and additional Name Documents(Y/N) (Y/N) (Excellent/ measures required Satisfactory/partially Satisfactory/Below Satisfactory) 1 All the All bidding/contract Yes Satisfactory Whenever a projects documents contain shortcoming is found in EMPs. respect of compliance to mitigation, the contractor has been advised to adopt suitable mitigation measures within a possible time period.

6. APPROACH AND METHODOLOGY FOR ENVIRONMENTAL MONITORING OF THE PROJECT.

Following is the Methodology adopted:

At design stage, all statutory clearances and procedures required for environmental safeguards are identified and obtained. At construction stage, a regular inspection is carried out by the PMU and SPCU safeguard Managers and project consultants to ensure that the environmental safeguard measures in general and the activities / measures mentioned in the EMP of the contracts in particular are implemented / complied. Corrective measures where necessary are being advised and remedial actions ensured regularly.

Environment Safeguard Managers of SPCU would monitor the progress of safeguard activities monthly using the computer-based Site-Specific Environmental Safeguards Monitoring System. (SESMS) introduced by ADB to monitor Category B sub projects. SESMS has been developed to assess the significance of sorted environmental issues screening through a risk matrix. SESMS will generate the Mitigation Compliance Report (MCR) for each month, when the current complied status of mitigation measures together with related scores are inserted. Monthly report so generated will give outstanding issues on priority basis to be attended.

28

Appendix 04 shows a sample Mitigation Compliance Report generated in the SESM System to record compliance status for a particular month by the Envt Safeguard Manager.

Environmental Safeguard Manager of PMU will oversee the monitoring process in all provinces under the advice and guidance of PMC’s safeguard expert. The Envt Safeguard Mangers of SPCUs were given necessary training on SESMS.

7. COMPLIANCE WITH ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN.

7.1. Monitoring of Environmental Impacts on project surroundings.

The sub projects classified under environment category B (as per ADB SPS 2009) are not large-scale projects. The environmental impact is therefore not spread over a wider extent around the project area. However, by taking mitigation and preventive measures, as specified in the EMP, causes for environmental risks are minimized.

Operations of excavators and earth moving machines which create noise were limited to being operated only during the daytime to minimize the disturbance to the neighboring community. Heavy machineries such as excavators used, were limited to maximum of two numbers at every project site and all machineries were found to have been undergone emission testing and therefore impact on the surrounding air quality was insignificant. Rocks encountered during excavation of trenches were blasted under extreme care with due permissions from relevant authorities and controlled blasting by undertaking every safety precaution to avoid any damage to nearby structures, workers and public.

In many project sites, pipeline alignment was changed to save big trees. In some project sites, where it was possible to shift the lines, a few trees have to be removed to cut trenches for pipe laying. In all such cases, planting of suitable tree species at 1:4 ratio were undertaken to compensate the plantation for the trees removed. In addition, contractors have also been encouraged to plant suitable trees even if no trees uprooted due to construction activities. Following table gives the summary of trees removed and replanted.

Table 5: No of trees removed and replanted

No of trees No of trees Total no of trees removed during Total no of trees replanted during removed from reporting period replanted from Package No reporting period. the start of the ( from the start of sub (from 01.07.2020 sub project to 01.07.2020 to project to date. to 31.12.2020) date. 31.12.2020) Water supply Mee -20 extension for - - Margosa- 10 Mailluppallama and Eboney -10 Teak -03 Thirappanae. (NCP-AF-WS-CKD- 02) Water Supply Teak -01 Mango – 05 extension to - - Albezia -02 Mee – 10 Elagomuwa –Main Margosa 03 Kumbuk – 10

29

No of trees No of trees Total no of trees removed during Total no of trees replanted during removed from reporting period replanted from Package No reporting period. the start of the ( from the start of sub (from 01.07.2020 sub project to 01.07.2020 to project to date. to 31.12.2020) date. 31.12.2020) and distribution lines. (NCP- AF-WS-CKD- 03) Extension of the pipe lines to Sewagama Mee -20 Teak -03 Canal 3 Area.( NCP- Kumbuk – 20 - - Margosa-01 AF-WS- CKD-07) Margosa - 20 Karaw-01

Improvement to Kalawewa Treatment Kumbuk -15 Plant at Ihalagama. - - Mango -03 Mee -05 (NCP-AF-WS-CKD- 06) Capacity improvement to Nuwarawewa Water Kumbuk – 15 Mango -03 Treatment plant. -. - Mango -05 Margosa -01 (NCP-AF-WS-CKD- 04) Water Supply Teak -02 Teak -06 Extension to Dambulla Jam -02 Jam -02 Mango -02 Guava-05 & Kandalama.(CP-AF- Pomerganate-03 Pomerganate-03 Guava-03 Mango -06 WS-CKD-10A) Guava-05 Guava-07 Mango-02 Mango -06 Water Supply Mango-07 Mango-25 Mango- 05 Extension to Inmaluwa Mango-02 Jam -02 Jam -10

& Kithulhitiyawa ((CP- Pomerganate-02 Pomerganate-05 Pomerganate-15 Pomerganate- 05 AF-WS-CKD-10B) Guava-06 Guava-20

WaterSupplyExtension Mango -05 Mango-08 to Sigiriya & Jack - 03 Pomerganate-04 Pomerganate-04 Teak- 03 Habarana.(CP-AF- Guava-05 Guava-06 Guava-11 Guava-02 WS-CKD-10C) Teak-03 Jack -03

Water Supply Albezia-02 Guava -05 Extension to Galewela Teak-04 Pomerganate-03 Mango-16 Mango-10 & Thithawelgolla.(CP- Mango -01 Guava-02 Guava-11 Jack-02 AF-WS-CKD-10D) Teak-04 Jack -02

Mango- 01 Water Supply Scheme for Rideemaliyadda( Kurawela and - - Mango -01 Mango -10 Ekiriyankumbura)- UVA-AF-WS-CKD-16

Outstanding issues related to environment safeguards were prioritized using SESMS monthly progress reports and more attention was given to resolve them. Prioritized issues were discussed thoroughly with the project manager or site supervisor and necessary advice was

30 given to them with a time target to correct immediately. Instructions related to safeguard issues were recorded in log books maintained in the site too, so that site supervisor could easily attend to the same.

As an example, December 2020 report of NWP-AF-WS-CKD-14A generated by SESM System is given in the Appendix 5. This report gives overall performance of mitigation measures against monitoring parameters, status of corrective action and further action to be taken with deadlines etc. Due to Covid 19 pandemic related lockdown countrywide, all construction sites were closed from around fourth week of March to fourth week May 2020 during which period, there was no physical progress at all project sites. After May 2020, work in all construction sites commenced with limited labour, keeping in compliance to the Covid 19 related advices / guidelines issued from Government from time to time. During this reporting period, it had been noticed that every site had been complied with Covid 19 guidelines and workers were too seemed to be adopted to new normal situation.

7.2 Public Complaints. / Grievance Redressal An effective ADB approved project-specific three tier Grievance Redress Mechanism (GRM) is in place for timely hearings and facilitate solutions. The Grievance Redress Mechanism of the project is also disclosed on project website www.puraneguma.lk. The list of grievances recorded and attended is provided regularly in the quarterly progress reports. The Grievances Redressal Status Summary Report for the reporting period is attached to this report as Appendix 03.

Complaints received or anomalies noticed were attended without long delays and corrective measures were taken. No grievance was recorded from sub projects of component 01 and only one grievance of package no WP-AF-HOM-06 (Construction of public market and car park with a toilet block at Homagama town for Homagama PS) of component 02 in western province was recorded during this reporting period. The issue was the blocking of entrance to the market. This issue was resolved with the complainers to their satisfaction. No Grievances reported during the reporting period in the other provinces.

7.3 Examples of good practices, non-compliance notices and corrective plans.

Mitigation measures listed in EMP are implemented by the contractor. There were a few noncompliance issues that needed special attention and issuing of notices to the contractor. This section illustrates some of the good practices and major noncompliance issues that occurred during the reporting period. Examples of corrective plans/ instructions given by Envt. Safeguard Manger and measures taken by contractor are also discussed in this section. The issues are presented subproject wise with samples from log notes, and photographs etc.

31

Output 01 – Category B sub projects a) Supplying and Laying of distribution network in Bathalayaya and Belaganwewa areas. (UVA -AF-WS-CKD-19A) Following picture shows safety measures taken while working in ROW.

Figure 26- Safety cones and tapes placed along road side.

b) Water Supply Extension to Dambulla and Kandalama/Central Province. (CP-AF- WS-CKD-10A).

Following picture shows safety measures taken to avoid accidents to road users.

Figure 27- Safety signs placed on the road side while working.

32 c) Water Supply for Karuwalagaswewa Pradeshiya Sabah / North Western Province (NWP-AF-WS-CKD-15). The picture below illustrates water storage tank being constructed with safety nets fixed around it.

Figure 28-Wate tank with safety net in Karuwalagaswewa . d) Improvement to Kalawewa Treatment Plant at Ihalagama / North Central Province / (NCP -AF-WS -CKD-06)

Figure 29- Pipe laying being done by slight deviation of alignment saving trees.

33 f) Augmentation of Giradurukotte Treatment plant and Intake civil works/UVA Province (UVA-AF-WS-CKD-19B).

Below is an example of unsafe electrical connection with no safety at all and the log note issued by Safeguard Manager / UVA Province giving instruction to correct it immediately and also some other instructions on safety precautions to be taken at the site.

Figure 30- Unsafe electrical connection. Figure 31- Log note giving instruction to rectify the unsafe electirical connection.

34

8. MITIGATION MEASURES FOR PREVENTION OF COVID 19. With the outbreak of COVID 19 Pandemic (second wave) construction activities of the LGESP (AF) were considerably reduced during the reporting period with compliance to guidelines and precautionary measures applied by the Ministry of Health and the same guidelines circulated by the PMU. Appendix 07 and 08 give status report on mitigation measures against COVID 19 and guidelines circulated by the PMU to resume office work and construction activities after lifting lockdown (curfew) imposed because of COVID-19 respectively. The following actions have been advised at the construction sites of LGESP (AF) that resumed constructions.  Reduce access to the site (Only essential visitors (workers, supervisors, and managers) were allowed on site))  Plan the work and activities to reduce close contact  Increase the overall level of hygiene of the site (hand washing) - all staff will sanitize themselves at the entrance, frequently during work and while going.  Prioritize health and safety of staff, workers, and their surrounding communities  Increase awareness of the workforce on COVID 19 guidelines.  Regular check of temperature. Unfortunately, a death case was reported on 9th December 2020 at around 5.30 pm at the subproject site of Haburugala Sub Office, Ayurvedha, Library, and Conference Hall for Bentota Pradeshiya Sabah (SP-AF-BEN 10) in Southern Province. The worker had fallen on the ground while taking the remaining steel bars to the storeroom. According to the eyewitnesses (co-workers of the subproject site), the incident was not an accident. The worker had been taken immediately taken to Balapitiya hospital for required medical treatment. It was reported that the person was brought dead to the hospital. As per the prevailing COVID 19 regulation, a PCR test had been performed on the body and found it was COVID 19 positive. Finally, the government cremated the dead body as per the prevailing COVID 19 regulation without handing it over to the relatives. Immediately the health inspectors of the area issued instructions to lock-down the subproject site and quarantined the other five workers who worked with the Corona victim. Apart from this incident, there had been no other COVID 19 cases reported.

35

9. SUMMARY OF KEY OUTSTANDING ISSUES.

Outstanding issues in the 1st half of the current year mainly consisted of issues related to occupational safety such as inadequate use of PPEs and inadequate and improper use of safety barriers specially at excavating trenches in ROWs. When these issues were revealed by the safeguard managers, prompt actions were taken to correct those and ensured safety of workers and public.

Outstanding issues of the reporting period in respect of each sub project that are under construction were recorded as given in Appendix 5. Outstanding issues are shown with an average score (from 0 to 5) indicating overall performance over last six months. Appendix 5 is only an example of a particular sub project generated in the SESMS. Key outstanding issues are summarized in the following table.

Table 6- Summary of Key Outstanding Issues. Sub Project Package No Key Outstanding Issues

Capacity Improvements NCP-AF-WS-CKD-04 Access road near to the construction site need to Nuwarawewa Water to be reinstated. Use of PPEs not adequate. Treatment Plant

Extension to Sewagama NCP-AF-WS-CKD-07 Inadequate safety measures and safety signs to Canel-3 from pedestrian crossing. Polonnaruwa WSS.

Pipeline Extension upto NCP-AF-WS-CKD-08 Inadequate safety measures at the excavated Thambala and trenches. Adequate number of safety signs Development of existing should be placed at the road side. Use of PPEs WSS not adequate...

Extension of Water NWP -AF-WS -CKD- Access road near to the construction site need Supply Scheme of 14A to be reinstated .Inadequate number of safety Nikaweratiya-Ambanpola signs at the road side.Dispoasl site to be

reinstated. All workers noticed not wearing PPE adequately.

Water Supply Extension CP-AF-WS-CKD - Unused soil stock piles need to be removed.. to Dambulla & 10A Kandalama.

Water Supply Extension CP-AF-WS-CKD - Unused soil stock piles need to be removed. to Inamaluwa and 10B Access roads to be reinstated. Stagnated water Kithulawala . in the site to be removed. Replanted trees to be maintained.

Water Supply Extension CP-AF-WS-CKD - Unused soil stock piles need to be removed to Sigiriya Habarana. 10C Soils bunds to be established where required

36

Use of PPEs not up to standard. Replanted trees to be maintained.

Water Supply Extension CP-AF-WS-CKD - Access roads to be reinstated. Unused soil to Thithawelgolla- 10D piles to be removed. Galawela.

Supplying and Laying of UVA-AF-WS-CKD Use of PPEs not up to standard. Regular tool the Distribution Network 19A box meetings to be held. in Bathalayaya and Belaganwewa

Augmentation of UVA - WS - CKD - Found unprotected plug points and advise d Girandurukotte Treatment 19B contractor to fix them with safely. Unused soil Plant and Intake Civil stokes to be removed. Adequate soil Work. conservation bunds to be provided to where it

required. Use of PPEs not up to standard.

Whenever outstanding issues are observed in the site, safeguard managers give necessary advice to the contractor to rectify them. Issues noticed and advice given are also recorded in the log book maintained in the site office. The outstanding issues will be followed up continuously for rectification.

10. CONCLUSION Compliance status of proposed mitigation measures in the EMP were monitored during every site visit and corrective actions were taken to remedy outstanding issues. Monitoring status and actions taken against each sub project are summarized in the monitoring tables annexed to the report.

Compliance status of taking preventive measures recommended in the EMPs such as ensuring employees to be equipped with PPEs during construction works and placing safety signs boards and providing barricades in vulnerable locations to establish safety of workers and the community and mitigations for disposal of wastes generated were below the expected level in some contracting sites. Environment Safeguard Managers have coordinated corrective measures by providing necessary guidance and advices to the Project Managers and Site Supervisors to ensure the environmental safeguard including occupational and public safety. For every outstanding issue, time target was given to resolve the issue which was later closely monitored to ensure the issues was properly attended or not. It has been noticed that contractors have taken measures to resolve them.

Environment Safeguard Managers also discussed outstanding issues at every monthly progress review meeting by highlighting importance of taking migratory measures and preventive measures through the action plan adopted by the contractors.

37

Appendix 1-Status of ADB’s approval of Initial Environmental Examination (IEE) Reports.

A. Output 1 - (Water Supply Systems in CKD affected areas improved) Category “B”

Central Province No Sub Project Package No ADB Approval 1 Renovation of existing treatment CP AF WS CKD11 Approved. Vide e – plant at Dambulla. mail on 17.10.2016

2 Water Supply Extension to Dambulla CP AF WS CKD10A Updated IEER approved. Vide e – and Kandalama Rural Areas. mail on 28.03.2020. 3 Water Supply Extension to CP AF WS CKD10B Updated IEER approved. Vide e – Inamaluwa and Kithulhitiyawa Rural mail on 08.04.2020 Areas 4 Water Supply Extension to Sigiriya CP AF WS CKD10C Updated IEER approved. Vide e – and Habarana mail on 28.03.2020 5 Water Supply Extension to CP AF WS CKD10D Updated IEER approved. Vide e – Thithawelgolla and Galewela Rural mail on 10.04.2020 Areas. 6 Water Supply Extension to CP AF WS CKD12 Updated IEER approved. Vide e – Pahaladiggala mail on 22.04.2020. North Central Province 7 Water Supply Extension to NCP AF WS CKD 01 Updated IEER Uththupitiya (from Kekirawa WSS) approved. Vide e – mail on 19.06.2019. 8 Water Supply Extension to i) NCP AF WS CKD 02 Updated IEER Mahailluppallama and ii) Thirappane area ( from Kekirawa Water Supply approved. Vide e – Scheme) mail on 19.06.2019. 9 Water Supply extension to NCP AF WS CKD 03 Updated IEER Elagamuwa – Main and Distribution approved. Vide e – Lines( from Dambulla Water Supply mail on 19.06.2019. Scheme) 10 Capacity Improvement to NCP AF WS CKD 04 Updated IEER Nuwarawewa Water Treatment Plant approved. Vide e – mail on 19.06.2019. 11 Improvements to Ihalagama ( NCP AF WS CKD 06 Updated IEER Kalawewa) Treatment Plant. approved. Vide e – mail on 14.05.2020. 12 Water Supply Extension to Sewagama NCP AF WS CKD 07 Updated IEER Canal 3 approved. Vide e – mail on 13 .11.2019 13 Improvement of Existing Water supply NCP AF WS CKD 08 Updated IEER Scheme (Thambala Part 2) approved. Vide e – mail on 13 .11.2019

38

14 Capacity Improvements to Minneriya NCP AF WS CKD 20 Updated IEER Water Treatment Plant approved. Vide e – mail on 19 .06.2019 15 Water Supply Extension to NCP AF WS CKD 21 Updated IEER Bendiwewa Water Supply Scheme. approved. Vide e – mail on 19 .06.2019 16 Improvement to Kebithigollawa NCP AF WS CKD Updated IEER 09A Water Supply Project approved. Vide e – mail on 19 .04.2019 17 Improvement of Thisawewa NCP -AF-WS - CKD - Updated IEER 22 Treatment Plant approved. Vide e – mail on 19 .06.2020 18 Improvement to existing Water NCP-AF-WS-AW-02 Updated IEER supply Schemes at Rajanganaya and approved. Vide e – Galnewa mail on 30.01.2019 North Western Province 19 Extension of Water Supply NWP-AF-WS-CKD - Updated IEER 14A Scheme of Nikaweratiya / approved. Vide e – Ambanpola. mail on 17.04.2020 20 Karuwalagaswewa Water Supply NWP AF WS CKD 15 Updated IEER Scheme. approved. Vide e – mail on 11.12.2018 21 Water Supply Scheme at NWP-AF-WS-CKD- Updated IEER 05 Ibbagamuwa approved. Vide e – mail on 19.06.2019 22 Supply & Installation of Pumps, NWP-AF-WS-CKD- Updated IEER 23 treatment plant equipment and approved. Vide e – Accessories for Ibbagomuwa Water mail on 19.06.2019 Supply Scheme. UVA Province 23 Water Supply extension from UVA-AF-WS-CKD-18 Updated IEER Rahathangama, Kumaragama and approved. Vide e – Kukurampola. (from Buttala Water mail on 26.05.2020 Supply Scheme)

24 Water Supply extension for UVA-AF-WS-CKD-16 Updated IEER Rideemaliyadda /Kurawela (Part I) approved. Vide e – mail on 02.10.2019 25 Water Supply extension for UVA-AF-WS-CKD-16 Updated IEER Rideemaliyadda /Ekiriyankumbura approved. Vide e – (Part II) mail on 02.10.2019 26 Augmentation of Girandurukotte UVA-AF-WS-CKD-19 Updated IEER Treatment plant and Ulhitiya Intake Civil Works and Water Supply approved. Vide e – Extension to Belaganwewa, mail on 02.10.2019 Batalayaya. Note -All approved reports are published in Project Website - www.puraneguma.lk/Additional Financing

39

Appendix 2 -Status of sub project under pre -construction phase as on 31.12.2020.

Output 01 – Category B

This table gives the compliance status of sub project that is under pre- construction phase where no significant physical progress to be reported.

Province Sub project Package No Remarks Improvement to Water Pending approval for North Central Province Treatment Plant Rebidding by ERD Thissawewa NCP-AF- WS-CKD- 22

54

Appendix 3 - Grievance redressal details status summary.

Western Province

Output 02 - Category C

No Name of Summar Detail of Date Regi: Process of redressal LA’s & y of complaina of Numb Date GRC or Outco Redress Remar Subproje Grievanc nt Recei er of other me or ed ks / ct es pt meetin stakeholder Solutio Yes / No further g s/ n details Participate d 01 Construct Road Business 2020. 1 2020. Chairman of The PS Yes ion of block disturbanc 08, 20 09., 08 PS, PS has Public entering e due to Members, taken Market the road block Secretary, action and Car Market Superintend to Park with of works, SE, remove a Toilet Construction the road Block at Manager, block Homaga and R&SM ma town for Homaga ma PS

North Central Province No Grievances reported during the reporting period

North Western Province No Grievances reported during the reporting period

Central Province No Grievances reported during the reporting period

Southern Province No Grievances reported during the reporting period

Uva Province No Grievances reported during the reporting period

55

Appendix 4 -A Completed Mitigation Compliance Report (MCR) used in SESM System- Water Supply Scheme - Nikaweratiya Ambanpola,December 2020.( NWP -AF-WS-CKD-14A).

Environmental Issues Mitigation measures Monitoring Mitigation Mitigation Status Further Corrective Actions Moni Photo Actio to consider Parameter Implement effectiveness of Required/Timely t Locati n ed Correcti Para on ve m Id Current Overa Action Nature of Further Agreed Month ll Corrective Actions deadline Perfo r

Activity: 1 Site clearing before starting construction

Environment (i)To avoid un- (i)Trees exactly to be Not Select 0.00 Not Site clearing has 1 Edit

degradation caused necessary tree removed are Required Require been completed by cutting large trees cutting by demarcated d (Removal of greenery) demarcating trees exactly to be removed

(ii)To avoid un- (i) Project ROW is Not Select 0.00 Not Site clearing has 2 Edit

necessary tree demarcated by Required Require been completed cutting by means of stand poles d demarcating project or barricading tapes ROW by means of visible to operational stand poles or staff barricading tapes visible to operational staff

(iii)To implement (i)Suitable land is Not Select 0.00 Not No replanting 3 Edit

tree re-planting selected Required Require program is required program to d due to non-removal of trees

54

Environmental Issues Mitigation measures Monitoring Mitigation Mitigation Status Further Corrective Actions Moni Photo Actio to consider Parameter Implement effectiveness of Required/Timely t Locati n ed Correcti Para on ve m Id Current Overa Action Nature of Further Agreed Month ll Corrective Actions deadline Perfo r

compensate lost (ii)Suitable plants are Not Select 0.00 Not No replanting 4 Edit

greenery selected and Required Require program is required maintained at a d due to non-removal nursery of trees

(iii)Tree planting Not Select 0.00 Not No replanting 5 Edit

implemented (1: 3 Required Require program is required rate) d due to non-removal of trees

(iv)Plants are Not Select 0.00 Not No replanting 6 Edit

maintained until self- Required Require program is required survival d due to non-removal of trees

Environment pollution (i)To provide soil (i)Adequate soil Not Select 0.00 Not No any site clearing 7 Edit

caused by eroded soil conservation bunds conservation bunds Required Require activities in this during rains after site and maintain are provided and d period clearing maintained regularly

Activity: 2 Land preparation by cutting embankments and filling slopes

Pollution of (i) To provide turfing, (i)Turfing, soil Not Select 0.00 Not No such places were 8 Edit

surrounding soil conservation conservation bunds, Required Require found during this environment caused bunds, or any other or any other d period because land by eroded soil arrangements to arrangements to

55

Environmental Issues Mitigation measures Monitoring Mitigation Mitigation Status Further Corrective Actions Moni Photo Actio to consider Parameter Implement effectiveness of Required/Timely t Locati n ed Correcti Para on ve m Id Current Overa Action Nature of Further Agreed Month ll Corrective Actions deadline Perfo r draining from protect soil erosion protect soil erosion clearing activities unprotected from earth work from earth work are almost completed earthwork during provided rains

Activity: 3 Construction of structures including earth work (intakes, bridges, water towers, treatment plants, buildings)

Safety of workers at (i) To provide (i) Embankment Not Select 0.00 Not embankment 9 Edit

deep embankment protection by Required Require collapses are not foundation/trenches/t protection by shoring, sheet piling d found due to hard rial pits is endangered shoring, sheet piling or any other soil. by embankment or any other arrangements is collapse arrangements as provided as directed directed by the by the Engineer Engineer

Safety of workers and (i)To provide (i)Adequate buffer Partly 3.Avera 4.06 Un- Buffer margin has 10 Edit

pedestrians is adequate buffer margins provided ge resolved been provided endangered by margin along along pedestrian adequately but excavated material pedestrian paths paths where barricade, sign stockpiles which block where stockpiles are stockpiles are placed board and other pedestrian paths. placed safety precautions have not been provided. Advised to PM to provide proper safety precautions.

56

Environmental Issues Mitigation measures Monitoring Mitigation Mitigation Status Further Corrective Actions Moni Photo Actio to consider Parameter Implement effectiveness of Required/Timely t Locati n ed Correcti Para on ve m Id Current Overa Action Nature of Further Agreed Month ll Corrective Actions deadline Perfo r

Safety of workers (i)To place material (i)Material stockpiles Not Select 3.89 Not No such deep 11 Edit

working inside deep stockpiles away from are kept away from Required Require excavation activities foundations/trenches the edge of the the edge of the d were found during /trial pits is embankments or embankments or this period endangered by take any other other suitable material pieces falling precaution precautions are from stockpiles taken dumped close to edge of the embankment.

Environment pollution (i) To protect Material stockpiles Not Select 0.83 Not No such considering 12 Edit

caused by material material stockpiles, wash away during Required Require level stockpiles in wash away from wash away during rains are protected d the site. stockpiles during rains rains by covering/ by providing covering/providing conservation bunds conservation bunds or any other or any other arrangement arrangements

Environment pollution (i)To remove unused Unused stockpiles Not Select 0.00 Not trench excavation, 13 Edit

caused by unremoved stockpiles before are removed before Required Require pipe laying, back stockpiles wash away construction construction d filling and during rains (even completion completion compaction done after construction) simultaneous.(Regar ding to excavation soil) No other material stockpiles in the site

57

Environmental Issues Mitigation measures Monitoring Mitigation Mitigation Status Further Corrective Actions Moni Photo Actio to consider Parameter Implement effectiveness of Required/Timely t Locati n ed Correcti Para on ve m Id Current Overa Action Nature of Further Agreed Month ll Corrective Actions deadline Perfo r

Hazardous mosquito (i)To remove (i)Stagnant water is Select Select 0.11 Select 14 Edit

breading caused by stagnant water regularly removed stagnant water inside regularly to ensure the excavated pits, mosquito breading is trenches and not taken place (ii)Tested water Select Select 0.00 Select 15 Edit foundations samples ensured that mosquito breading is not taken place

Environment pollution (i)To divert removed (i) Removed waste Select Select 0.06 Select 16 Edit

at wastewater to a water is diverted to a surrounding/downstr drainage path with drainage path with eam area caused by silt traps by silt traps ensuring wastewater removed protecting surrounding/downstr from pits, trenches surrounding/downstr eam environment is and foundations eam environment not polluted

Activity: 4 Rock drilling and crushing

Health hazards of (i)To control rock (i) Dust control Not Select 1.17 Not No rock drilling 17 Edit

drillers and others in dust generation by arrangements are Required Require activities during this the vicinity by means of covering provided by covering d period breathing rock dust drill holes with drill holes with mixed air during rock wetted gunny bags or wetted gunny bags or drilling and crushing dripping water and or dripping water and spreading/dripping spreading/dripping

58

Environmental Issues Mitigation measures Monitoring Mitigation Mitigation Status Further Corrective Actions Moni Photo Actio to consider Parameter Implement effectiveness of Required/Timely t Locati n ed Correcti Para on ve m Id Current Overa Action Nature of Further Agreed Month ll Corrective Actions deadline Perfo r

water at rock water at rock crushing crushing

(ii)To provide dusk (i)Dusk masks are Not Select 1.33 Not No rock drilling 18 Edit

masks for rock provided for rock Required Require activities during this drillers and others in drillers and others d period the vicinity during working in the rock drilling and vicinity during rock crushing drilling and crushing

Activity: 5 Rock blasting

Community and (i)To arrange (i) Standard rock Not Select 2.50 Not No rock blasting 19 Edit

occupational safety is standard rock blasting safety Required Require activities during this endangered by blasting safety arrangements are d period insufficient protective arrangements provided including measures during rock including prior prior warning blasting warning

Activity: 6 Burrowing, transporting, placing aggregate material (earth, gravel, sand, metal, quarry dust etc.)

Hazardous mosquito (i) To reinstate (i) GSMB approval is Not Select 1.94 Not Such material has 20 Edit

breading caused by burrow pits as per obtained for burrow Required Require not used used in this stagnant water inside GSMB guidelines pits and burrowing d period material

59

Environmental Issues Mitigation measures Monitoring Mitigation Mitigation Status Further Corrective Actions Moni Photo Actio to consider Parameter Implement effectiveness of Required/Timely t Locati n ed Correcti Para on ve m Id Current Overa Action Nature of Further Agreed Month ll Corrective Actions deadline Perfo r

burrow pits after (ii) Burrow pits are Not Select 1.94 Not Such material has 21 Edit

mining reinstated as per Required Require not used used in this GSMB guidelines d period (even though the material supply is outsourced)

Health hazard due to (i)To make sure that (i) Dusty material is Not Select 1.94 Not Such material has 22 Edit

windblown dust while dusty material is transported only by Required Require not used used in this transporting dusty transported only by covered trucks d period material by uncovered covered trucks. trucks at dry weather

Health hazard due to (i)To make sure that (i) Dusty material Not Select 1.39 Not Such material has 23 Edit

windblown dust from dusty material stockpiles are Required Require not used used in this dumped dusty stockpiles are covered at dry d period material stockpiles at covered at dry weather dry weather weather.

Public safety is (i)To make sure that (i)Trucks are not Not Select 3.33 Not Such material has 24 Edit

endangered by trucks are not overloaded while Required Require not used used in this material pieces overloaded while transporting material d period thrown out from transporting material overloaded trucks while moving.

60

Environmental Issues Mitigation measures Monitoring Mitigation Mitigation Status Further Corrective Actions Moni Photo Actio to consider Parameter Implement effectiveness of Required/Timely t Locati n ed Correcti Para on ve m Id Current Overa Action Nature of Further Agreed Month ll Corrective Actions deadline Perfo r

Public safety is (i) To reinstate access (i)Access roads are Partly 1.Not 2.78 Un- Temporary 20/01/20 25 Edit

endangered by use of roads regularly reinstated regularly Complie resolved reinstated. Advised 21 access roads damaged d to PM to reinstate by heavy vehicle properly.. movements

Pollution of (i)To protect fine (i)Fine aggregate Not Select 0.28 Not Such material has 26 Edit

surrounding aggregate material material stockpiles Required Require not used used in this environment by fine stockpiles wash away are protected from d period aggregates washed from site during rains wash away by away from material by covering and/or covering and/or stockpiles during rains providing providing conservation bunds conservation bunds

Activity: 7 Pipe-laying, installation of valves and hydrants, pressure testing, providing service connection and reinstatement of trenches

Occupational and To provide sufficient Sufficient protective Select Select 2.33 Select 27 Edit

public safety is protective measures measures are taken endangered by around pipe-laying, around pipe-laying, insufficient protective installation of valves installation of valves measures around and hydrants, and hydrants, pipe-laying, pressure testing, pressure testing, installation of valves providing service providing service and hydrants, connections and connections and pressure testing, reinstatement of reinstatement of providing service trenches. trenches. connections and

61

Environmental Issues Mitigation measures Monitoring Mitigation Mitigation Status Further Corrective Actions Moni Photo Actio to consider Parameter Implement effectiveness of Required/Timely t Locati n ed Correcti Para on ve m Id Current Overa Action Nature of Further Agreed Month ll Corrective Actions deadline Perfo r reinstatement of trenches.

Domestic and public (i) To carry out a (i) Survey is carried Not Select 0.00 Not No any vibro- 28 Edit

safety is endangered survey to identify out to identify Required Require compaction by wall crack existing wall cracks existing wall cracks d activities in this propagation due to and vulnerable and vulnerable period. vibro-compaction at structures before structures before trench reinstatement commencing commencing construction. construction.

(i) To implement (i) Engineer approved Not Select 0.00 Not No any vibro- 29 Edit

engineer approved action plan is Required Require compaction action plan while prepared and d activities in this carrying out vibro- implemented while period. compaction at carrying out vibro- vulnerable locations compaction at vulnerable locations (e.g. reducing vibration rate and increasing number of passes or decreasing layer thickness)

Activity: 8 Storing Asphalt/ Bitumen at site and use for road reinstatement

62

Environmental Issues Mitigation measures Monitoring Mitigation Mitigation Status Further Corrective Actions Moni Photo Actio to consider Parameter Implement effectiveness of Required/Timely t Locati n ed Correcti Para on ve m Id Current Overa Action Nature of Further Agreed Month ll Corrective Actions deadline Perfo r

Environment pollution (i)To pay special (i)Oily bitumen Not Select 0.56 Not No such material 30 Edit

caused by oily attention by covering material is covered Required Require were used during bitumen wash away oily bitumen material before rains d period during rains before rains

Activity: 9 Managing storage material

Environment pollution (i)To avoid draining (i)Draining oil spills to Yes 5.Fully 3.89 Resolve 31 Edit

caused by oil spills oil spills to surrounding Complie d draining to surrounding environment is d surrounding areas environment by protected by sealing sealing leaked places leaked places or any or any other means other means with with regular and regular and close close observation observation

Polluting surrounding (i)To protect (i)Washable material Not Select 0.83 Not No such considering 32 Edit

environment by washable material stockpiles (at open Required Require level stockpiles in material stockpiles (at stockpiles (at open storage) are d the site. open storage) wash storage) by covering protected by away during rains them during rainy covering them during season and /or rainy season and /or providing providing conservation bunds conservation bunds

Activity: 10 Deploying heavy machinery/heavy equipment/ tractors/ trucks/ vehicles at construction work

63

Environmental Issues Mitigation measures Monitoring Mitigation Mitigation Status Further Corrective Actions Moni Photo Actio to consider Parameter Implement effectiveness of Required/Timely t Locati n ed Correcti Para on ve m Id Current Overa Action Nature of Further Agreed Month ll Corrective Actions deadline Perfo r

Public nuisance (i)To provide (i)Adequate Yes 5.Fully 3.89 Resolve 33 Edit

caused by noise adequate noise measures have been Complie d generation during barriers when and taken to control d construction where necessary noise by providing noise barriers when and where necessary

Occupational and (i)To deploy fitness (i)Fitness certificated Yes 5.Fully 4.17 Resolve 34 Edit

public safety is certificated heavy heavy machinery/ Complie d endangered by machinery/ tractors/trucks/ d deploying heavy tractors/trucks/ vehicles are deployed machinery/heavy vehicles equipment/ tractors/trucks/ vehicles with (ii)To check running (ii)Running Yes 5.Fully 4.17 Resolve 35 Edit substandard running requirements such as requirements such as Complie d conditions and workability of horns, workability of horns, d running requirements. lights, signals lights, lights, signals lights, warning alarms, warning alarms, locks, etc. and locks, etc. and running condition of running condition of tyres, brakes, free tyres, brakes, free from oil leaks and from oil leaks and exhausting CO exhausting CO beyond limits etc. beyond limits etc. have been periodically checked and ensured.

64

Environmental Issues Mitigation measures Monitoring Mitigation Mitigation Status Further Corrective Actions Moni Photo Actio to consider Parameter Implement effectiveness of Required/Timely t Locati n ed Correcti Para on ve m Id Current Overa Action Nature of Further Agreed Month ll Corrective Actions deadline Perfo r

Occupational and (i)To employ (i)Experienced drivers Yes 5.Fully 4.17 Resolve 36 Edit

public safety is experienced drivers and operators have Complie d endangered by and operators for been employed for d deploying heavy heavy heavy machinery/heavy machinery/heavy machinery/heavy equipment/ tractors/ equipment/ tractors/ equipment/ tractors/ trucks/ vehicles with trucks/ vehicles trucks/ vehicles less experienced deployed for deployed for operators/drivers construction work. construction work.

Activity: 11 Deploying heavy machinery/equipment/ and loading/unloading trucks at construction work

Occupational and (i)To deploy heavy (i)Heavy Yes 5.Fully 3.61 Resolve 37 Edit

public safety is machinery/equipmen machinery/equipmen Complie d endangered by t/ and t/ and d deploying heavy loading/unloading loading/unloading machinery/equipment trucks only with trucks are deployed / and trained helping with trained helping loading/unloading assistants equipped assistants equipped trucks without trained with PPEs and with PPEs and helping assistants signaling devices signaling devices equipped with PPEs and signaling devices.

Activity: 12 Occupational and public health and safety during construction

65

Environmental Issues Mitigation measures Monitoring Mitigation Mitigation Status Further Corrective Actions Moni Photo Actio to consider Parameter Implement effectiveness of Required/Timely t Locati n ed Correcti Para on ve m Id Current Overa Action Nature of Further Agreed Month ll Corrective Actions deadline Perfo r

Occupational and (i)To prepare a SMP (i)SMP is prepared Yes 5.Fully 4.17 Resolve 38 Edit

public safety is and to obtain and obtained Complie d endangered by engineer's approval engineer's approval d starting project to implement before for implementation activities without starting the project before starting the implementing activities project activities engineer approved safety management plan (SMP)

Occupational and (i)To provide (i) Adequate water Not Select 0.11 Not Rainy period 39 Edit

public health is adequate water spreading system Required Require endangered by spreading system or/and sprinkler d breathing windblown or/and to deploy attached water dust during sprinkler attached bowsers are regularly construction at dry water bowsers provided weather regularly

(ii) Water spreading Not Select 0.11 Not Rainy period 40 Edit

system or/and Required Require sprinkler attached d water bowsers are regularly deployed.

Occupational and (i)To provide (i)Standard PPEs Select Select 2.22 Select 41 Edit

public (visitors) safety standard PPEs to all (quality, size) are is endangered by employees and provided to all engaging visitors and to ensure employees and

66

Environmental Issues Mitigation measures Monitoring Mitigation Mitigation Status Further Corrective Actions Moni Photo Actio to consider Parameter Implement effectiveness of Required/Timely t Locati n ed Correcti Para on ve m Id Current Overa Action Nature of Further Agreed Month ll Corrective Actions deadline Perfo r work/visiting site they are fully visitors who engage without wearing equipped with PPEs project works standard PPEs while engaging project works (i)All employees and Select Select 2.22 Select 42 Edit

visitors are fully equipped with standard PPEs while engaging project works

Occupational health is (i) To provide (i)Sanitary facilities Yes 5.Fully 4.17 Resolve 43 Edit

endangered by adequate sanitary are provided for Complie d insufficient sanitary facilities to office/camps and d facilities provided at office/camps and maintained the office/camps regularly monitor the quality and adequacy quality and adequacy regularly

Occupational and (i)To provide safety (i)Safety measures at Yes 5.Fully 4.17 Resolve 44 Edit

public safety is measures at storage storage area of Complie d endangered by lack of area of flammable/hazardou d safety measures at flammable/hazardou s material as per storage area of s material as per engineer approved flammable/hazardous engineer approved SMP have been material SMP and maintain provided and the adequacy and maintained the quality by taking adequacy and quality timely actions

67

Environmental Issues Mitigation measures Monitoring Mitigation Mitigation Status Further Corrective Actions Moni Photo Actio to consider Parameter Implement effectiveness of Required/Timely t Locati n ed Correcti Para on ve m Id Current Overa Action Nature of Further Agreed Month ll Corrective Actions deadline Perfo r

by taking timely actions

Occupational and (i)To provide safety (i)Safety measures on Yes 5.Fully 4.17 Resolve 45 Edit

public safety is measures on electrical works Complie d endangered by unsafe electrical works (damaged wiring d electrical works (damaged wiring harnesses, broken (damaged wiring harnesses, broken power outlets and harnesses, broken power outlets and plug tops, unsafe power outlets and plug tops, unsafe fittings, unsafe power plug tops, unsafe fittings, unsafe power cables etc.) as per fittings, unsafe power cables etc.) as per engineer approved cables etc.) engineer approved SMP have been taken SMP and maintained and maintained the the adequacy and adequacy and quality quality by regular by regular checking checking

Occupational and (i)To provide (i)Safety precautions Select Select 2.61 Select 46 Edit

public safety is adequate safety (sign boards, fire endangered by lack of precautions (sign extinguishers, first safety precautions boards, fire aide, emergency (sign boards, fire extinguishers, first exists, safe extinguishers, first aide, emergency assembling points, aide, emergency exists, safe etc.) as per engineer exists, safe assembling points, approved SMP have assembling points, etc.) as per engineer been provided and etc.) approved SMP and ensured the

68

Environmental Issues Mitigation measures Monitoring Mitigation Mitigation Status Further Corrective Actions Moni Photo Actio to consider Parameter Implement effectiveness of Required/Timely t Locati n ed Correcti Para on ve m Id Current Overa Action Nature of Further Agreed Month ll Corrective Actions deadline Perfo r

ensure the adequacy adequacy and quality and quality by regular by regular checking. checking.

Occupational and (i)To conduct safety (i)Safety awareness Select Select 2.89 Select 47 Edit

public safety is awareness programs programs for endangered by lack of for employees and employees and awareness and community at project community at project careless handling of affected areas affected areas PPEs, tools, including school including school equipment, children as per children have been accessories, heavy engineer approved conducted as per items, lengthy items, SMP. engineer approved explosives, chemicals, SMP. and wastage etc.

(ii)To conduct regular (i)Regular toolbox Partly 3.Avera 2.78 Not Advised to PM to get 48 Edit

tool box meetings for meetings for ge Require immediate action for employees as per employees have been d this engineer approved conducted as per SMP. engineer approved SMP.

Activity: 13 Office, camp and construction waste disposal

69

Environmental Issues Mitigation measures Monitoring Mitigation Mitigation Status Further Corrective Actions Moni Photo Actio to consider Parameter Implement effectiveness of Required/Timely t Locati n ed Correcti Para on ve m Id Current Overa Action Nature of Further Agreed Month ll Corrective Actions deadline Perfo r

Environment is (i)To provide facilities (i)Waste/garbage Yes 5.Fully 3.61 Resolve 49 Edit

polluted by haphazard to segregate and segregation is Complie d disposal of collect construction implemented (e.g. d construction waste waste and reusable and and office/camp office/camp garbage disposable garbage without at recommended construction waste, segregation (within locations within biodegradable waste, project premises) project premises composting waste, and hazardous waste etc.) and adequate facilities are provided to collect at recommended locations/bins within project premises

(ii)Ensured Yes 5.Fully 3.61 Resolve 50 Edit

construction waste Complie d and office/camp d garbage are not scattered all over the premises and garbage is not spilling from the bins

Environment is (i)To provide (i)Adequate Yes 5.Fully 4.06 Resolve 51 Edit

polluted by disposal of waste/garbage waste/garbage Complie d pre-collected disposal disposal yards have d

70

Environmental Issues Mitigation measures Monitoring Mitigation Mitigation Status Further Corrective Actions Moni Photo Actio to consider Parameter Implement effectiveness of Required/Timely t Locati n ed Correcti Para on ve m Id Current Overa Action Nature of Further Agreed Month ll Corrective Actions deadline Perfo r construction waste arrangements to been selected and and office/camp dump at permitted local authority garbage to yards and to permission is unauthorized reinstate disposal obtained locations (outside yards regularly. project premises) (ii)Adequate and Yes 5.Fully 3.67 Resolve 52 Edit

regular Complie d waste/garbage d disposal arrangements have been provided

(iii)Ensured Yes 5.Fully 4.06 Resolve 53 Edit

biodegradable and Complie d hazardous waste is d not disposed to the disposal yards

(iv)Ensured disposal Select Select 2.72 Select 54 Edit

yards are reinstated regularly

(v)Ensured Yes 5.Fully 3.50 Resolve 55 Edit

waste/garbage is not Complie d disposed to d unauthorized

71

Environmental Issues Mitigation measures Monitoring Mitigation Mitigation Status Further Corrective Actions Moni Photo Actio to consider Parameter Implement effectiveness of Required/Timely t Locati n ed Correcti Para on ve m Id Current Overa Action Nature of Further Agreed Month ll Corrective Actions deadline Perfo r

locations (outside project premises).

This sample Compliance Monitoring Report (CMR) is a computer generated one from the SESM System and it shows how the effectiveness of mitigation and other related information are reported in the System monthly

72

Appendix 5- Computer Generated Mitigation Compliance Reports in SESMS in December 2020 / Category “B”.

Computer-generated monthly mitigation compliance reports of the following sub projects that are under construction at present have been used to summarize the overall progress of the safeguard status of sub projects during the reporting period. These reports would give a boarder picture of the cumulative status of environmental compliance over the period from 1st July to 31st December 2020.

i) North Western Province- NWP-AF- WS -CKD 14A, NWP-AF- WS -CKD 15 ii) North Central Province - NCP -AF –WS- CKD 04, NCP- AF- WS- CKD 07, NCP –AF- WS- CKD 06, NCP- AF WS -CKD 08, NCP- AF- WS- CKD 09 iii) UVA Province – AF- WS- CKD 18, UVA – AF- WS –CKD- 19A, UVA – AF- WS- CKD 19B

iv) Central Province - CP-AF-WS-CKD 10A, CP-AF-WS-CKD 10B, CP-AF-WS-CKD 10C, CP-AF-WS- CKD 10D

As an example, computer generated mitigation compliance report of sub project (NWP-AF-WS-CKD-14A) for the month of December 2020 is given below. Its computer based data sheet (MCR) is given in appendix 4 above.

73

APPENDIX 5(cont.…)

Sub Project: Extension of Water Supply Scheme of Nikaweratiya-Ambanpola

Project Code: NWP -AF-WS -CKD-14A/ North Western Province

Outstanding Environmental Issues Report: December 2020

Environmental Mitigation Measure Monitoring Parameter Overall Statu Natur e Agree Issue Performa s Of Of Furth d nce Corre er Corre deadli ctive ctive ne Actio Actio n n

Environment pollution (i)To divert removed (i) Removed waste 0.06 at wastewater to a water is diverted to a surrounding/downstr drainage path with silt drainage path with silt eam area caused by traps by protecting traps ensuring wastewater removed surrounding/downstream surrounding/downstream from pits, trenches environment environment is not and foundations polluted Hazardous mosquito (i)To remove (i)Stagnant water is 0.11 breading caused by stagnant water regularly removed stagnant water inside regularly to ensure the excavated pits, mosquito breading is trenches and not taken place foundations Occupational and (i)To provide adequate (i) Adequate water 0.11 Not Rainy public health is water spreading system spreading system or/and Requir period endangered by or/and to deploy sprinkler sprinkler attached water ed breathing windblown attached water bowsers bowsers are regularly dust during regularly provided construction at dry weather Occupational and (i)To provide adequate (ii) Water spreading system 0.11 Not Rainy public health is water spreading system or/and sprinkler attached Requir period endangered by or/and to deploy sprinkler water bowsers are regularly ed breathing windblown attached water bowsers deployed. dust during regularly construction at dry weather Pollution of (i)To protect fine (i)Fine aggregate 0.28 Not Such materi surrounding aggregate material material stockpiles are Requir al has not environment by fine stockpiles wash away protected from wash ed used used aggregates washed from site during rains by away by covering in this away from material covering and/or providing and/or providing period stockpiles during conservation bunds conservation bunds rains

Environment (i)To pay special (i)Oily bitumen material is 0.56 Not No such pollution caused by attention by covering covered before rains Requir materi al oily bitumen wash oily bitumen material ed were used away during rains before rains during period

74

Environment (i) To protect material Material stockpiles wash 0.83 Not No such pollution caused by stockpiles, wash away away during rains are Requir consid material wash away during rains by covering/ protected by ed ering level from stockpiles providing conservation covering/providing stockpi les during rains bunds or any other conservation bunds or any in the site. arrangement other arrangements

Polluting surrounding (i)To protect washable (i)Washable material 0.83 Not No such environment by material stockpiles (at stockpiles (at open storage) Requir consid material stockpiles (at open storage) by covering are protected by covering ed ering level open storage) wash them during rainy season them during rainy season stockpi les away during rains and /or providing and /or providing in the site. conservation bunds conservation bunds

Health hazards of (i)To control rock dust (i) Dust control 1.17 Not No rock drillers and others in generation by means of arrangements are Requir drilling the vicinity by covering drill holes with provided by covering drill ed activiti es breathing rock dust wetted gunny bags or holes with wetted gunny during this mixed air during rock dripping water and bags or or dripping water period drilling and crushing spreading/dripping water and spreading/dripping at rock crushing water at rock crushing

Health hazards of (ii)To provide dusk masks (i)Dusk masks are 1.33 Not No rock drillers and others in for rock drillers and others provided for rock drillers Requir drilling the vicinity by in the vicinity during rock and others working in the ed activiti es breathing rock dust drilling and crushing vicinity during rock drilling during this mixed air during rock and crushing period drilling and crushing

Health hazard due to (i)To make sure that dusty (i) Dusty material 1.39 Not Such materi windblown dust from material stockpiles are stockpiles are covered Requir al has not dumped dusty covered at dry weather. at dry weather ed used used material stockpiles at in this dry weather period

Hazardous mosquito (i) To reinstate burrow (i) GSMB approval is 1.94 Not Such materi breading caused by pits as per GSMB obtained for burrow pits Requir al has not stagnant water inside guidelines and burrowing material ed used used burrow pits after in this mining period

Hazardous mosquito (i) To reinstate burrow (ii) Burrow pits are 1.94 Not Such materi breading caused by pits as per GSMB reinstated as per GSMB Requir al has not stagnant water inside guidelines guidelines (even though ed used used burrow pits after the material supply is in this mining outsourced) period

Health hazard due to (i)To make sure that (i) Dusty material is 1.94 Not Such materi windblown dust while dusty material is transported only by Requir al has not transporting dusty transported only by covered trucks ed used used material by uncovered covered trucks. in this trucks at dry weather period

75

Occupational and (i)To provide standard (i)Standard PPEs (quality, 2.22 public (visitors) safety PPEs to all employees size) are provided to all is endangered by and visitors and to ensure employees and visitors engaging work/visiting they are fully equipped who engage project works site without wearing with PPEs while engaging standard PPEs project works

Occupational and (i)To provide standard (i)All employees and 2.22 public (visitors) safety PPEs to all employees visitors are fully equipped is endangered by and visitors and to ensure with standard PPEs while engaging work/visiting they are fully equipped engaging project works site without wearing with PPEs while engaging standard PPEs project works

Occupational and To provide sufficient Sufficient protective 2.33 public safety is protective measures measures are taken around endangered by around pipe-laying, pipe-laying, installation of insufficient protective installation of valves and valves and hydrants, measures around hydrants, pressure testing, pressure testing, providing pipe-laying, providing service service connections and installation of valves connections and reinstatement of trenches. and hydrants, reinstatement of trenches. pressure testing, providing service connections and reinstatement of trenches. Community and (i)To arrange (i) Standard rock blasting 2.5 Not No rock occupational safety is standard rock safety arrangements are Requir blastin g endangered by blasting safety provided including prior ed activiti es insufficient protective arrangements warning during this measures during rock including prior period blasting warning

Occupational and (i)To provide adequate (i)Safety precautions (sign 2.61 public safety is safety precautions (sign boards, fire extinguishers, endangered by lack of boards, fire first aide, emergency safety precautions extinguishers, first aide, exists, safe assembling (sign boards, fire emergency exists, safe points, etc.) as per extinguishers, first assembling points, etc.) engineer approved SMP aide, emergency as per engineer have been provided and exists, safe approved SMP and ensured the adequacy and assembling points, ensure the adequacy quality by regular checking. etc.) and quality by regular checking. Environment is (i)To provide (iv)Ensured disposal 2.72 polluted by disposal waste/garbage disposal yards are reinstated of pre-collected arrangements to dump at regularly construction waste permitted yards and to and office/camp reinstate disposal yards garbage to regularly. unauthorized locations (outside project premises) Public safety is (i) To reinstate (i)Access roads are 2.78 Outsta Tempo rary 20/01/ endangered by use access roads reinstated regularly nding reinsta ted. 2021 of access roads regularly Advise d to damaged by heavy PM to vehicle movements reinsta te properl y..

76

Occupational and (ii)To conduct regular (i)Regular toolbox 2.78 Not Advise d to public safety is tool box meetings for meetings for employees Requir PM to get endangered by lack employees as per have been conducted as ed immedi ate of awareness and engineer approved per engineer approved action for careless handling of SMP. SMP. this PPEs, tools, equipment, accessories, heavy items, lengthy items, explosives, chemicals, and wastage etc. Occupational and (i)To conduct safety (i)Safety awareness 2.89 public safety is awareness programs for programs for employees endangered by lack employees and and community at project of awareness and community at project affected areas including careless handling of affected areas including school children have been PPEs, tools, school children as per conducted as per equipment, engineer approved SMP. engineer approved SMP. accessories, heavy items, lengthy items, explosives, chemicals, and wastage etc. Public safety is (i)To make sure that trucks (i)Trucks are not 3.33 Not Such materi endangered by are not overloaded while overloaded while Requir al has not material pieces transporting material transporting material ed used used thrown out from in this overloaded trucks period while moving.

Environment is (i)To provide (v)Ensured 3.5 Resolv polluted by disposal waste/garbage disposal waste/garbage is not ed of pre-collected arrangements to dump at disposed to unauthorized construction waste permitted yards and to locations (outside project and office/camp reinstate disposal yards premises). garbage to regularly. unauthorized locations (outside project premises) Occupational and (i)To deploy heavy (i)Heavy 3.61 Resolv public safety is machinery/equipment/ and machinery/equipment/ ed endangered by loading/unloading trucks and loading/unloading deploying heavy only with trained helping trucks are deployed with machinery/equipmen t/ assistants equipped with trained helping assistants and loading/unloading PPEs and signaling equipped with PPEs and trucks without trained devices signaling devices helping assistants equipped with PPEs and signaling devices.

Environment is (i)To provide facilities to (i)Waste/garbage 3.61 Resolv polluted by haphazard segregate and collect segregation is ed disposal of construction waste and implemented (e.g. construction waste office/camp garbage at reusable and disposable and office/camp recommended locations construction waste, garbage without within project premises biodegradable waste, segregation (within composting waste, and project premises) hazardous waste etc.) and adequate facilities are provided to collect at recommended locations/bins within project premises

77

Environment is (i)To provide facilities to (ii)Ensured construction 3.61 Resolv polluted by haphazard segregate and collect waste and office/camp ed disposal of construction waste and garbage are not scattered construction waste office/camp garbage at all over the premises and and office/camp recommended locations garbage is not spilling garbage without within project premises from the bins segregation (within project premises) Environment is (i)To provide (ii)Adequate and regular 3.67 Resolv polluted by disposal waste/garbage disposal waste/garbage disposal ed of pre-collected arrangements to dump at arrangements have been construction waste permitted yards and to provided and office/camp reinstate disposal yards garbage to regularly. unauthorized locations (outside project premises) Safety of workers (i)To place material (i)Material stockpiles 3.89 Not working inside deep stockpiles away from are kept away from the Requir No such foundations/trenches the edge of the edge of the ed deep /trial pits is embankments or take embankments or other excava tion endangered by any other precaution suitable precautions are activiti es material pieces taken were found falling from during this stockpiles dumped period close to edge of the embankment.

Environment (i)To avoid draining oil (i)Draining oil spills to 3.89 Resolv pollution caused by spills to surrounding surrounding environment is ed oil spills draining to environment by sealing protected by sealing leaked surrounding areas leaked places or any other places or any other means means with regular and with regular and close close observation observation Public nuisance (i)To provide (i)Adequate measures 3.89 Resolv caused by noise adequate noise have been taken to control ed generation during barriers when and noise by providing noise construction where necessary barriers when and where necessary

78

Safety of workers (i)To provide adequate (i)Adequate buffer 4.06 Outsta Buffer and pedestrians is buffer margin along margins provided along nding margin has endangered by pedestrian paths pedestrian paths where been provid excavated material where stockpiles are stockpiles are placed ed adequ stockpiles which placed ately but block pedestrian barrica de, paths. sign board and other safety precau tions have not been provid ed. Advise d to PM to provid e proper safety precau tions.

Environment is (i)To provide (i)Adequate 4.06 Resolv polluted by disposal waste/garbage disposal waste/garbage ed of pre-collected arrangements to dump at disposal yards have construction waste permitted yards and to been selected and and office/camp reinstate disposal yards local authority garbage to regularly. permission is unauthorized obtained locations (outside project premises) Environment is (i)To provide (iii)Ensured 4.06 Resolv polluted by disposal waste/garbage disposal biodegradable and ed of pre-collected arrangements to dump at hazardous waste is not construction waste permitted yards and to disposed to the disposal and office/camp reinstate disposal yards yards garbage to regularly. unauthorized locations (outside project premises) Occupational and (i)To deploy fitness (i)Fitness certificated 4.17 Resolv public safety is certificated heavy heavy machinery/ ed endangered by machinery/ tractors/trucks/ deploying heavy tractors/trucks/ vehicles vehicles are machinery/heavy deployed equipment/ tractors/trucks/ vehicles with substandard running conditions and running requirements.

79

Occupational and (ii)To check running (ii)Running requirements 4.17 Resolv public safety is requirements such as such as workability of ed endangered by workability of horns, horns, lights, signals lights, deploying heavy lights, signals lights, warning alarms, locks, etc. machinery/heavy warning alarms, locks, and running condition of equipment/ etc. and running condition tyres, brakes, free from oil tractors/trucks/ of tyres, brakes, free from leaks and exhausting CO vehicles with oil leaks and exhausting beyond limits etc. have substandard running CO beyond limits etc. been periodically checked conditions and and ensured. running requirements.

Occupational and (i)To employ experienced (i)Experienced drivers and 4.17 Resolv public safety is drivers and operators for operators have been ed endangered by heavy machinery/heavy employed for heavy deploying heavy equipment/ tractors/ machinery/heavy machinery/heavy trucks/ vehicles deployed equipment/ tractors/ trucks/ equipment/ tractors/ for construction work. vehicles deployed for trucks/ vehicles with construction work. less experienced operators/drivers Occupational and (i)To prepare a SMP and (i)SMP is prepared and 4.17 Resolv public safety is to obtain engineer's obtained engineer's ed endangered by approval to implement approval for starting project before starting the project implementation before activities without activities starting the project implementing activities engineer approved safety management plan (SMP) Occupational health (i) To provide adequate (i)Sanitary facilities are 4.17 Resolv is endangered by sanitary facilities to provided for office/camps ed insufficient sanitary office/camps and and maintained the quality facilities provided at regularly monitor the and adequacy regularly office/camps quality and adequacy Occupational and (i)To provide safety (i)Safety measures at 4.17 Resolv public safety is measures at storage area storage area of ed endangered by lack of flammable/hazardous flammable/hazardous of safety measures at material as per engineer material as per engineer storage area of approved SMP and approved SMP have been flammable/hazardou maintain the adequacy provided and maintained s material and quality by taking the adequacy and quality timely actions by taking timely actions Occupational and (i)To provide safety (i)Safety measures on 4.17 Resolv public safety is measures on electrical electrical works ed endangered by works (damaged wiring (damaged wiring unsafe electrical harnesses, broken power harnesses, broken power works (damaged outlets and plug tops, outlets and plug tops, wiring harnesses, unsafe fittings, unsafe unsafe fittings, unsafe broken power outlets power cables etc.) as per power cables etc.) as per and plug tops, unsafe engineer approved SMP engineer approved SMP fittings, unsafe power and maintained the have been taken and cables etc.) adequacy and quality by maintained the adequacy regular checking and quality by regular checking

80

Appendix 6-Status Summery Report of Category “C” Sub-projects as on 31.12.2020

Local Government Enhancement Sector Project: Additional Financing (LGESP - AF)

Output 2: Service Delivery Improvement.

Central Province

No Project area Package No Status Construction of Maternity & Health Care Center 01 & Community Physical works completed. for Malate PS CP-AF-MAT-03 DDR Environment Report approved by ADB.

Construction of PS Sub Office, Library & 02 Community Hall at CP-AF-NUW-05 . Physical works completed Nanuoya for Nuwara-Eliya PS DDR Environment Report approved by ADB

Construction of Maternity Care center at 03 Kurukuttala for Udunuwara CP-AF-UDU-06 Physical works completed DDR Environment Report approved by ADB

Construction of Maternity Clinic, Library and 04 Community Hall CP-AF-KUN-02A with 200 chairs each in Mahawatta and Polgolla

for . Physical works completed. Kundasale PS. DDR Environment Report approved by ADB.

05 Construction of PS sub Office. Library and Health Centre in CP-AF-KUN-02B . Physical works are in progress

Pollgolla for Kundasale PS. DDR Environment Report approved by ADB.

06 Physical works completed. Construction of Vehicle Park and Daily Market at Gelioya for CP-AF-UDU-01 DDR Environment Report approved by ADB. Udunuwara PS.

Physical works completed. 07 Construction of Multipurpose Building and development of CP-AF-PAL-04 DDR Environment Report approved by ADB. roads in town area

Balance work of a water supply project 08 (Udapalatha, Physical works are in progress Ududubbara and Wilgamuwa, Hettipola). DDR Environment Report approved by ADB.

CP-AF-WS-AW- 01

North Western Province

81

No Project area Package No Status

. Physical works are in progress

09 Construction of PS Building and Library at NWP-AF-NAR-02 DDR Environment Report approved by ADB.

Narammala for Narammala PS.

Physical works are in progress Construction of new two story public market 10 complex at NWP-AF-POL-01 DDR Environment Report approved by ADB. Polgahawela for Polgahawela PS.

. Physical works completed Construction of new library building at 11 Dunkannawa for NWP-AF-NAT-03 DDR Environment Report approved by ADB Naththandiya PS.

12 Panangoda, Mahilawa, Kruswatte drinking water NWP-AF-NAT-06

Supply projects for Naththandiya PS. DDR Environment Report approved by ADB . Physical works are in progress

Construction of Multipurpose Building at 13 Madurankuliya. NWP-AF-PUT-04 DDR Environment Report approved by ADB

Physical works completed.

Construction of New Library Building at 14 Madurankuliya for NWP-AF-PUT-07 DDR Environment Report approved by ADB Madurankuliya PS. Physical works completed. DDR Environment Report has been approved by 15 Construction of Multipurpose building including ADB PS office at NWP-AF-KUR-05 Thiththawela for Kurunegala PS. Works completed

Southern Province

Improvement of existing PS premises with Work completed. 16 Auditorium & SP-AF-AMB-06 Vehicle Park at Batapola for Ambalangoda PS, DDR Environment report approved by ADB

Construction of PS building with Ayurvedic 17 center & SP-AF-BAD-07 DDR Environment report approved conference hall at Baddegama for Baddegama PS. Work completed.

Construction of Multipurpose Building at 18 Balapitiya Towm for Balapitiya PS SP-AF-BAL-08 Construction completed.

DDR Environment report approved by ADB.

19 Construction of Weekly fair at Goonagala for SP-AF-BEN-05

Bentota PS Construction completed.

82

No Project area Package No Status

DDR Environment report approved. 20 Construction of PS Sub office at Haburugala for SP-AF-BEN-10 Construction completed Bentota PS

Construction of PS Building with Library & 21 Center SP-AF-HAB-04 DDR Environment report approved by ADB. & PS Chamber ( 3 storied building) for Habaraduwa PS Construction work completed.

22 Construction of PS Building & Weekly Fair at ‘ SP-AF-RAT-09 DDR Environment report approved by ADB.

Nayagoda for Rathgama PS. Construction work completed.

Construction of Crematorium and Access road to the Crematorium at Warakapitiya for Weligama 23 PS. SP-AF-WEL-03 DDR Environment report approved by ADB.

. Work in progresss

24 Construction of PS building for Tangalle PS and SF-AF-TAN-01 DDR Environment report approved by ADB. Multipurpose Bldg. (Bus stand, weekly fair, Post office & Construction completed. Toilet block) at Netolpitiya for Tangalle PS.

Improvement of Kekanadura sub town for DDR Environment report has been approved by 25 Matara PS (a) Bus SP-AF-MAT-02 ADB. stand, Three-wheeler Park with Drainage sys. (b). Construction of existing building above 1st floor with roof for Construction work in progress. Library, PS Sub office and Auditorium.

Western Province

WP-AF-KEL-01 DDR Environment report approved by ADB. Multipurpose building including public library, Ayurveda, Construction work in progress. preschool and children park at Nahena for Kelaniya PS and comfort centre at Kiribathgoda town for Kelaniya 26 PS.

WP-AF-MAH-02 Multipurpose bldg. including PS office, medical 27 centre, DDR Environment report pproved by ADB. Ayurveda, public library and pre-school at Construction work completed.

pahala Karagahamuna for Mahara PS.

Construction of a Auditorium/ community Hall at Kadirana. WP-AF-KAT-03 DDR Environment report approved by ADB.

83

No Project area Package No Status 28 Construction work in progress.

DDR Environment report approved by ADB. Multipurpose bldg. including Public market, main 29 PS WP-AF-WAT-04 Construction work in progress. office, sub office and Ayurveda at Mahabage for Wattala PS.

WP-AF-JAL-05 DDR Environment report approved by ADB. Construction of PS office building including 30 public Construction work completed. library and auditorium at Kandana for Ja-Ela PS.

DDR Environment report approved by ADB. Construction of Public Market and Car Park with a Toilet Block at Homagama town for 31 Homagama PS WP-AF-HOM-06 Construction work in progress

32 Construction of public market at Wadduwa for DDR Environment report approved by ADB. WP-AF-PAD-07 Panadura PS, Construction work in progress

Construction of office complex including sub

office, DDR Environment report approved by ADB. WP-AF-BER-08 33 library at Aluthgama for Beruwala PS. Construction Completed

Construction office building including main

office, sub DDR Environment report approved by ADB.

34 office auditorium, library and record room for Kalutara PS WP-AF-KAL-09 Construction work completed. UVA Province

Construction of Water Supply Project for UVA – AF- PAS- DDR Environment report approved by ADB. 35 PS. 01 Construction work in progress. Output 1

Relaying and Extension of Distribution to UVA-AF-WS- Rahathangama Area CKD-17 DDR Environment Report approved by ADB on 31.12.2020. 36

84

Appendix 7: Status report on COVID 19 mitigation as on 31st December 2020

North Western Province Subproject 1) .Extension of Water supply scheme Nikawaratiya, Ambanpola  Letter of Guideline to resume office work and construction activities after lifting curfew imposed for COVID19 issued by PD has been circulated. Precautionary  Health and Safety Guidelines for Sri Lankan construction Sites to be adopted during measures COVID 19 outbreak issued by Construction Industry Development Authority has been taken by distributed. SPCU  Awareness programs have been conducted

View of the practical application

Hand washing Body temperature Keeping Social Inspection of PHI recording distance

Subproject 2). Construction of PS building at Thitthawella, Kurunegala  Letter of Guideline to resume office work and construction activities after lifting curfew imposed on COVID19 issued by PD has been circulated. Precautionary  Health and Safety Guidelines for Sri Lankan Construction Sites to be adopted during measures taken by COVID 19 outbreak issued by Construction Industry Development Authority has been SPCU distributed.  Awareness programs have been conducted. Hand washing facilities have been provided.

View of the practical application

Inspection of PHI Awareness session

Subproject 3). Construction of PS Building at Narammala  Letter of Guide line to resume office work and construction activities after lifting curfew Precautionary imposed on COVID19 issued by PD has been circulated. measures  Health and Safety Guidelines for Sri Lankan Construction Sites to be adopted during taken by COVID 19 outbreak issued by Construction Industry Development Authority has been SPCU distributed.  Awareness programs have been conducted.

85

 New register of workers with basic information and daily updated page with their health condition. Hand washing facilities have been provided.

View of the practical application

Awareness session Keeping Social distance

North Central Province Subproject 4). Capacity Improvement to Nuwarawewa Water Treatment Plant (WTP)  Letter of Guideline to resume office work and construction activities after lifting curfew imposed on COVID19 issued by PD has been circulated. Health and Safety Guidelines for Sri Lankan Construction Sites to be adopted during COVID 19 outbreak issued by Precautionary Construction Industry Development Authority has been distributed. measures taken by  Awareness programs have been conducted. SPCU  New register of workers with basic information and daily updated page with their health condition.  Hand washing facilities have been provided.

View of the practical application

Awareness session Body temperature recording

Subproject 5). Improvement of Kalawewa Treatment Plant/ Ihalagama  Every contractor was were made aware trough letter regarding initiate construction base on guidelines issued by CIDA and April 2020.  Organized a Special meeting for Project managers and key staff follow up restriction rule imposed by SL Government. Precautionary  Introduced format to maintain record of daily body temperatures of all workers and measures officers. taken by  Provide soft copy of COVID - 19 prevention poster (created by Health ministry) to display SPCU site premises.  Hand washing facilities, gloves, and facemask have been provided.  Awareness programme have been conducted on instruction given by the PHI ( PHI did not participate to some meeting due to busy work schedule )

86

View of the practical application

Awareness session Hand washing facilities

UVA Province Subproject 6). Augmentation of Giradurukotte Treatment Plant and Intake Civil Works  Disinfection of site offices, Camps, Toilets, Stores, Rest room etc.  Develop a reporting system .  Display all the relevant posters, leaflets, signboards on COVID 19  Establishment of hand washing station. Precautionary  Holding site meetings with social distance other health precautions. measures  Washing hands with soap at least 20 seconds before entering & leaving the work place. taken by SPCU  Use of standard face mask, gloves  Using of sanitizers as far as possible  Checking body temperature of all workers daily.  Keeping the sites clean

View of the practical application

Keepinf social distance at site Sanitizing the office premises

Western Province Subproject 7). Construction of Office Complex at Aluthgama for Beruwala Pradeshiya Sabha- Stage I A meeting was held on 14th May 2020 with PHI, LA, Contractor, Consultant & SPCU officers and instructions given to follow the safety issues regarding COVID 19.Disinfection of site offices, Camps, Toilets, Stores, Rest room etc.

Submission of Contractor’s New Health & safety action plan in complying with the health Precautionary guidelines issued by the government related to COVID-19 epidemic (if any): To be submitted measures taken by  Report on any incident of COVID 19 Patient in the site Area: Not reported SPCU  Brief description of the health safeguard precautions already Taken at the site: o Arranged washing facility with soap. o Workers instructed to keep social distancing requirement of 1 o Wearing masks and gloves, not sharing foods and drinks.  Method of health and precautionary measures adopted for checking Workers / Supervisors 87

before daily work commencement: - Tool box meeting to remind requirements.  Staff Member / worker / his or her family member / anybody in the locality affected by the virus attack? -Not reported  If workers are living in a camp: Method of health and precautionary measures adopted to prevent COVID 19 virus attack: Distance criterion / Meals arrangement / Personal hygiene/Daily temperature checking etc. - No resident workers Distance criterion / Meals arrangement / Personal hygiene / Any checking arrangement by DSC or SPCU: Disinfection of the site

View of the Awareness session practical application

8). Construction of Public Market and Car Park including a Toilet Block at Homagama Town for Subproject Homagama Prdeshiya Sabha.  A meeting was held on 14th May 2020 with PHI, LA, Contractor, Consultant & SPCU officers and instructions given to follow the safety issues regarding COVID 19  Disinfection of site offices, Camps, Toilets, Stores, Rest room etc.  Submission of Contractor’s New Health & safety action plan in complying with the health guidelines issued by the government related to COVID-19 epidemic (if any): To be submitted  Report on any incident of COVID 19 Patient in the site Area: Not reported  Brief description of the health safeguard precautions already Taken at the site:  Arranged washing facility with soap. Precautionary  Workers instructed to keep social distancing requirement of 1 measures  Wearing masks and gloves, not sharing foods and drinks. taken by Method of health and precautionary measures adopted for checking Workers / SPCU  Supervisors before daily work commencement: - Tool box meeting to remind requirements.  Staff Member / worker / his or her family member / anybody in the locality affected by the virus attack? -Not reported  If workers are living in a camp: Method of health and precautionary measures adopted to prevent COVID 19 virus attack: Distance criterion / Meals arrangement / Personal hygiene/Daily temperature checking etc. - No resident workers  Distance criterion / Meals arrangement / Personal hygiene / Any checking arrangement by DSC or SPCU:

88

View of the practical application

Awareness session Hand washing facilities

9). Construction of Multipurpose Building including PS office and Public Library at Kandanafor Subproject Ja-Ela Pradeshiya. Precautionary measures Same as above in subproject 8 taken by SPCU

View of the practical application

Awareness session

Subproject 10). Construction of Auditorium/Community Hall at Kadirana for Katana Pradeshiya Sabha Precautionary measures Same as above in subproject 8 taken by SPCU

View of the practical application

Awareness session

11). Construction of Multipurpose Building including Maternity Clinic, Pre-school , Youth Centre, Subproject Library & Multipurpose Hall at Nahena for Kelaniya Pradeshiya Sabha Precautionary measures Same as above in subproject 8 taken by SPCU

89

View of the practical application

Body temperature recording Inspection of PHI

Subproject 12). Construction of Public Market at Wadduwa for Panadura PradeshiyaSabha (Stage I) Precautionary measures Same as above in subproject 8 taken by SPCU

View of the practical application

Disinfection of the site Inspection of PHI

13). Construction of Multipurpose Building including Public Market and PS Office at Mahabage Subproject for Wattala PS Precautionary measures Same as above in subproject 8 taken by SPCU

View of the practical application

Awareness given by PHI

Southern Province 14). Construction of Crematorium and Funeral Parlor at Warakapitiya for Weligama Pradeshiya Subproject Sabha Precautionary measures Letter of Guide line to resume office work and construction activities after lifting curfew taken by imposed on COVID-19 issued by PD has been circulated SPCU 90

Health and Safety Guidelines for Sri Lankan Construction Sites to be adopted during COVID 19 outbreak issued by Construction Industry Development Authority has been distributed. Health and Safety Guidelines for Construction Sites under LGESP to be adopted during COVID 19 outbreak has been send by Provincial Project Director, Southern Province. New register of workers with basic information and daily updated page with their health condition with body temperature. Awareness programs have been conducted. 15). Improvement of Kekanadura Sub Town (a) Bus Stand, Three Wheeler Park with Drainage Subproject system (b) Construction of Existing Building (Above 1st Floor) with roof for Library, PS Sub Office and Auditorium at Kekanadura for Matara Pradeshiya Sabha Precautionary measures Same as above in subproject 14 taken by SPCU 16). Construction of Haburugala Sub Office, Ayurvedha, Library and Conference Hall for Bentota Subproject Pradeshiya Sabha Precautionary measures Same as above in subproject 14 taken by SPCU

91

Appendix 8: Guideline circulated by the PMU to resume office work and construction activities after lifting lockdown (curfew) imposed because of COVID-19.

To resume office work and construction activities in all sites, after COVID 19 outbreak normalize, your attention is focused on adhering following:

While all guidelines of Government are to be followed, some of the key points are as follows:

A. General Measures to be taken by Employer / Site In-charge:

1) The head of the office / site in-charge should collect the details of all the staff – (i) Travel details in past one month before joining back office / site work; (ii) details of any fever, cough, cold / running nose, (and all Covid-19 symptoms) in the last month; (iii) Details of coming into contact with any Covid-19 patient in the last one month ( A suggested format is given vide Attachment 1);

2) The head office / site in-charge should arrange the awareness session on Covid- 19 disease which include, details of the disease, its mode of spreading, precautions to be taken and reporting requirements. This should be organized to each and every staff / worker and acknowledgement taken from the respective staff;

3) The employer should provide necessary personnel protective equipment (PPE) like masks, gloves sanitizers, etc. as required to personnel and office and train the staff on use and disposal of these equipment in the awareness programs mentioned above. Adequate washing facilities to be made available in the project site / office;

4) If any worker or his / her neighbor or community reports symptoms, it is the duty of the employer or site / officer in-charge to report to concerned health authorities immediately without fail.

5) The employer / site in-charge to organize regular health checks (Periodically) once in 3 / 4 days (twice a week) to assess the condition of the staff and document them properly. If a staff shows any symptoms of Covid -19 he / she should be sent for quarantine and the staff and his associates to offered for testing by reporting to appropriate authorities

6) The Employer’s should refrain from / be cautious and doubly sure on health conditions on employing persons from high-risk areas.

7) A brief report / check list should be prepared fortnightly on each project site before 5 days after completion of the fortnight for first two months and monthly reports thereafter by 5th of next month and submitted to the PMU. (Sample of Covid -19 briefing report is attached vide Attachment 2).

8) The officials in-charge of the site should be in close contact with provincial / national health officials for the required support.

9) Key guidelines on prevention of Covid -19 should be displayed in office / project office as appropriate at all prominent places.

92

10) Partial Staffing on rotation with others working at home / staffing on shift basis to be explored and decided upon by the head of office / site in-charge.

B. Key Measures to be taken in the office / Project Site:

Sl. Particulars Measures to be taken in office / project No. Site 1 Entrance and Exit to work places and other The staff / worker should wash his / her times. hand and shoes before entering and exit from the office / project site (required Alcohol based solution / sanitizer, washing facility with soap solution to be provided in the site). After touching any doubtful surface, the staff should wash the hand thoroughly. 2 Marking Attendance Before thumb print or signing in a register the staff should wash his hand thoroughly in office or site. 3 Waste disposal All waste generated in office or sites dispose hygienically parallelly with the master plan provided by Local authority in the area. Masks and other related material should also be disposed off after proper disinfection and as per procedures. Open burning should not be practiced for disposal in the site. 4 Imported Material Disinfection Any imported material from other countries to be disinfected before bringing the same to the site or office as necessary 5 Disinfect Common Areas When and where necessary common areas to be disinfected as required in collaboration with the MOH office or Local Authority of the area. Special attention should be paid when the sites are opened for the first time. Cleaning/ disinfecting the sites should be done before they are opened for civil work activities (especially stores, yards and labor camps) 6 Personal Protective Equipment Use all required and appropriate Personal Protective equipment like mask, gloves and boots continuously during work. 7 Social Distancing in worksite Staff should keep a standard distance of more than 1 mt between each other while interacting / working in office and project site and should always keep their face covered with mask. There should be no physical contacts like shaking hands and sitting together etc. Do not enter the site / work place without a mask. 8 Group activities of workers Workers / Staff should refrain from close meetings and meet only on absolutely necessary issues with proper social distance maintained. Mobiles and applications to be used to max for

93

Contacts and correspondence. 9 Night stay in camps All safety facilities to be provided and the social distancing requirements should be maintained. 10 Use of drugs and Alcohol Totally prohibited 11 Precaution while leaving home The staff / worker should wash hands and shoes properly before leaving home. 12 Precautions on reaching home. The staff should wash all clothes / and have a wash before touching any person or item in the house to ensure safety of oneself and family persons. All items like car keys, specs etc. should be disinfected / washed as the first thing before reaching home. 13. Sharing of food / Articles etc. Sharing of food / items with each other should be avoided for next few months until normalcy is back or if done, should be done with full care and required disinfection. 14 Maintenance of toilets and common facilities All toilets and common facilities to be disinfected periodically to control the incidence / spread. 15 Reporting responsibility of staff Staff should report immediately without fail for any symptoms for self and associates on Covid-19 for appropriate informed decision 16 Provisioning of a dedicated team for cleaning A dedicated team shall be assigned for activities and safety of cleaning staff cleaning work at sites. These staff should be provided with all appropriate P P E a n d t h e y should b e wearing the PPE while on duty. Instructions should be given to wash or sanitize their hands thoroughly after each encounter (e.g. after cleaning each room, wash room, front desk, etc.) 17 Arrangements for transportation of staff to and Following special precautions are to be from sites taken if staff is to be transported: Clean and disinfect all vehicles used for transportation. No front loaders or other construction machinery shall be used for transportation of staff. Vehicles used for transportation of staff should have adequate capacity to provide appropriate physical distancing. A designated officer must be present to open and close doors of the vehicle for passengers and no passenger shall be allowed to handle the door. All passengers shall wear face masks during travel. 18 Emergency response plan in case a worker at An isolation room should be maintained at site is found or suspected to infected with site. COVID 19 The suspected worker should continue to wear a mask and kept in isolation and all relevant precautions should be taken to

94

limit t h e s p r e a d o f t h e d i s e a s e , until transfer to hospital. Assistance should be taken from hotline 1390 and follow the instructions given or alternatively transfer the worker to the nearest government hospital, by ambulance. Or through “Suwasariya” ambulance service through 1990

Note: The above is indicative to cover key areas. The guidelines / annexures released by Government from time to time as required shall be followed in total. Important Note: All contractors shall develop a health and safety (HS) management plan or update the existing HS plan based on the guidelines presented in section B and submit to respective SPCU for approval before commencement of site ac

95

Attachment 1 Details of staff resuming work after the Lockdown in the country due to Covid 19 (to be filled by the supervisor of the site or office secretary or any assigned person after getting details from the worker / staff and data to be compiled) Name of the Project / Site/ Office: 1 Name of Staff / Worker 2 Designation 3 NID number

Yes No 1 Do you have / had following symptoms in past one month: (Please tick appropriately) (a) Fever (b) Cough (c) Running nose (d) Breathlessness (e) Vomiting (f) Headache (g) Fatigue /Muscle pain / Joint pain (h) Any other symptoms (specify) 2 Did you travel abroad and return during last one month If yes, mention the country’s name If yes, please mention whether you got sick during the travel 3 Did you come in contact with any Covid - 19 Patient during last one month If yes, give details of the person – Name, ID number, Locality

Undertaking 1: • I will inform the employer / office if I get any symptoms of Covid- 19 during the period of work. • I will inform the employer / office, If I get my co-worker / neighbor / community person gets the symptoms of Covid -19. • I will follow all the instructions on Covid -19 without fail.

Name and Signature of the staff

Undertaking 2: • I have been provided the necessary awareness session Covid -19 on .

Name and Signature of the staff Please Note: This information will be kept confidential and thanks for the cooperation.

96

Attachment 2 Monthly Briefing Report on measures to Prevent Covid -19 in work places.

1. Monthly report : From to

2. Details of Work Place: (insert location and details of office)

3. No. of staff worked during this month:

4. Have all the staff worked this month provided an awareness session: Yes / No

If not, what is the reason.

5. Are there cases of Covid-19 reported among your staff during the reporting period: Yes / No.

If yes, give details of case and actions taken to report to authorities.

6. Are the facilities provided in the site in accordance to social distancing rules?

7. Are all records on Covid -19 measures required in office / site maintained – Yes / No

8. Details of Personal Protective Equipment Provided.

9. Names of officers in-charge to supervise Covid -19 safeguard measures and details of site inspections done to verify the measures.

10. Details of Awareness programs on Covid -19 provided to all staff / workers.

11. Any other information the officer / employer would like to share to bring to the notice of Government.

Note1: Attach Photographs showing compliance to Covid -19 guidelines. Note2: Reports to be given initially for next 6 months and then continue after instructions.

Awareness given by PHI