E1699 v 2 World Bank Loan Project State Environmental Assessment Certificate

1106th, A-Grade Public Disclosure Authorized

Bengbu Integrated Environment Improvement

Project BIEIP Public Disclosure Authorized Report of Environment Management Plan

(Draft)

Public Disclosure Authorized

North Municipal Engineering

Design & Research Institute

August 2007 Public Disclosure Authorized Table of contents

1. GOAL OF ENVIRONMENT MANAGEMENT PLAN...... 3

1.1 PURPOSE OF ENVIRONMENT MANAGEMENT PLAN...... 3

1.2 ACTION GUIDELINES AND THE REQUIREMENTS...... 3

2. ESTABLISHMENT BASIS ...... 5

2.1 EVALUATION CRITERIA ...... 5

2.2 ESTABLISHMENTS BASIS ...... 9

3. PROJECT SURVEY...... 14

3.1 PROJECTS INTRODUCTION...... 14

3.2 PROJECT CONSTRUCTION CONTENT ...... 15

4. ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ...... 21

4.1 ENVIRONMENTAL IMPACTS ...... 21

4.2 MITIGATION MEASURES...... 35

5. IMPLEMENTATION ORGANIZATION ...... 41

5.1 ENVIRONMENT MANAGEMENT ORGANIZATIONS...... 41

5.2 ENVIRONMENTAL MONITORING ORGANIZATION ...... 44

5.3 CONTRACTOR’S DUTIES...... 44

5.4 TRAINING AND ABILITY CONSTRUCTION ...... 45

6. MONITORING PLANS ...... 47

6.1 ENVIRONMENT SUPERVISION OF CONSTRUCTION ACTIVITIES ...... 47

6.2 MONITORING PLANS...... 47

6.3 MANAGEMENT SYSTEM ...... 63

7. THE BUDGET AND THE FUND SOURCE OF THE ENVIRONMENT

MANAGEMENT PLAN...... 64

7.1 THE BUDGET OF ENVIRONMENT MANAGEMENT PLAN...... 64

7.2 FUND ORIGIN ...... 80 1. Goal of environment management plan

Purpose of environment management plan The construction implementation of this project will cause some environmental impacts on construction site. In the construction period, this project will have some adverse impacts on the atmospheric environment, the water environment, the sound environment and the ecological environment, while in the operation period, it will mainly benefit to the water environment and the ecological environment and improve the ability in prevention of flood and water logging. In order to explain in detail the contents of environmental impact elimination measures, environment management, environment supervision, environmental monitoring, and so on, the environment management plan has been formulated. It is a guideline document of the environment management in the project implementation process. Its function is as follows: (1) Make clear the goal of environmental protection and the measures of environment mitigation The project construction organization, the designing organization and the appraisal organization have investigated in detail on the panned land, confirmed the environmental protection goal, proposed the effective environment mitigation measures, and integrated them into the project design. (2) Be taken as the guidance document of environment management After the environmental monitoring plan is approved by the World Bank, it will be provided as the environmental protection text to the construction overseeing organizations, the environment surveillance organizations and other related organizations of this project construction period and the operation period. (3) To identify the responsibility and the functions of the related organizations The environment management plan has identified the responsibility and the function of the related functional departments and the management organizations and has proposed the channel and the way for communication exchange among each department’s. (4) Determine environmental monitoring plan during the construction period and the operation period The environmental monitoring plan in construction period and the operation period proposed in the environment management plan can guarantee the effective implementation of the environment mitigation measure and prompt processing of environment accident.

Action guidelines and the requirements Under the efforts of the World Bank officials, the international consultation experts, the environmental impact appraisal organization, the Environmental Protection Bureau and the project construction organization, the environment management goal of this project for construction period and the operation period has been determined as: maintains the coordinated development of social economy and environment in Bengbu City, improves the ecological environment in Bengbu City, reduces or mitigate the adverse effect on the project construction, minimizes environmental impacts. Specific actions: (1) To propose and implement the environment management and the environmental monitoring plan; (2) To propose and implement the pollutant control strategy to mitigate is adverse impact on the environment. Specific request: (1) To inspect the environmental monitoring standard determined in environmental monitoring plan during the construction period and the operation period; (2) To implement all the environment mitigation measures proposed in environmental impact assessment according to the stipulated procedure.

2. Establishment basis

2.1 Evaluation criteria 2.2.1 Environment quality standard (1) The atmospheric environment quality specification At present the ambient air quality appraisal carries out the corresponding standard according to Ambient air Quality Standard (GB3095-1996 + revision list in 2000). Table 2-1-1 Air pollutant density limiting value Unit: mg/m3 Standard Standard Standard Pollutant name Sample time density limiting density limiting density limiting value Level 1 value Level 2 value Level 3 Annual mean 0.02 0.06 0.10

Sulfur Dioxide, SO2 Daily average 0.05 0.15 0.25 1 hour average 0.15 0.50 0.70 Total suspended Annual mean 0.08 0.20 0.30 particles, TSP Daily average 0.12 0.30 0.50 Annual mean 0.04 0.08 0.08

Nitrogen dioxide, NO2 Daily average 0.08 0.12 0.12 1 hour average 0.12 0.24 0.24 Inspiration particles Annual mean 0.04 0.10 0.15

PM10 Daily average 0.05 0.15 0.25 (2) The surface water environment quality standard The surface water environment carries out Environmental Quality Standards for Surface Water (GB3838-2002) corresponding standard.

Table 2-1-2 Basic items standard limiting value of surface water environment quality standard Unit: mg/L (ph, excrement large intestine bacteria colony are the exceptions) Serial Item Standard value Type III Standard value Type No. 1 Ph (zero dimension) 69 6 9 2 The dissolved oxygen 5 3 3 Permanganate index 6 1 0 The five-day biochemical 4 4 6 oxygen demand 5 Ammonia nitrogen 1 1 . 5 Compounds of petroleum 6 0 . 0 5 0 . 5 class 7 Volatile phenols 0.005 0 . 0 1 8 Chemical oxygen demand 2 0 3 0 Excrement large intestine 9 10000 20000 bacteria colony (each/L) The total phosphorus 10 0 . 2 0 . 3 (calculated by P) The total nitrogen(lake, 11 1 1 . 5 reservoir) (calculated by N 0.0001 12 Mercury 0 . 0 0 1 13 Lead 0 . 0 5 0 . 0 5 14 Cadmium 0.005 0 . 0 0 5 (3)The sound environment quality standard The sound environment carries out Standards of Environmental Noise of Urban Area (GB3096-1993) corresponding standard. Table 2-1-3 Stand of environmental noise of urban area Unit: db(A) Category Day time Night time Type1 55 45 Type 2 60 50 Type 3 65 55 Type 4 70 55 (4) Soil environment quality standard The soil environment carries out Soil Environment quality Standard (GB15618- 1995) level three. Table 2-1-4 Soil environment quality standard Unit: mg/kg Item Arsenic Chromium Lead Mercury Paddy Arid Paddy field Arid land field land Soil ph 6.5 5 0 0 3 0 4 0 5 0 0 4 0 0 3 0 0 2.1.2 Pollutant emissions standard (1)Water pollution emissions standard The waste water during the construction period carries out Integrated Wastewater Discharge Standard (GB8978-1996) corresponding standard. Table 2-1-5 Pollutant highest permission emissions density Unit: mg/l Standard Standard Level 3 Serial No. Pollutant Standard Level 2 Level 1 1 Ph 6 9 6 9 6 9 2 Suspension SS 70 150 400 Biochemical oxygen 300 3 20 30 Demand BOD5 Chemical oxygen 500 4 100 150 Demand COD 5 Ammonia nitrogen 15 25 - 6 Petroleum class compounds 5 10 20 7 Animal and vegetable oil 10 15 100 The wastewater emissions from the sewage treatment plant carries out the state Discharge Standard of Pollutants for Municipal Wastewater Treatment Plant (GB18918-2002) Standard level A. Table 2-1-6 basic control project highest permission emissions density (date average value) Unit: mg/l (ph is the exception) Serial No. Basic control items Standard Level 1 A Standard Level 1 B 1 Ph 6 9 6 9 2 Chemical oxygen demand COD 50 60

3 Biochemical oxygen demand BOD5 10 20 4 Suspension SS 10 20 5 The total nitrogen(calculated by N) 15 20 6 Ammonia nitrogen calculated by N × 5 8 8 15 7 Total phosphorus calculated by P 0.5 1.0 × The values outside the parenthesis are the control targets when the water temperature >12, the values in the parenthesis are the control targets when the water temperature 1 2 .

The water supplied by the surface water works carries out Water Quality Standards for

Urban Water Supply CJ/T206-2005. Serial No. Item Standard level 1 A 1 Ph 6.5 8.5 2 The opacity INTU Oxygen consumption capacity 3 3mg/L codmn, calculated by O2 4 Total soluble total solid 1000mg/L Should not be inspected in each 5 Total large intestine bacteria colony 100ml water sample (2) Ambient air pollutant emissions standard The atmosphere carries out Integrated Emission Standard of Air Pollutants (GB16297-1996) air pollutant emissions limiting values of pollution source. Table 2-1-7 Integrated emission limiting value of air pollutants

Monitoring density limiting value for non-organized discharges Pollution source Pollutant Monitoring point Density mg/m3 New pollution source Particles Peak density at the boundary 1.0 The odor pollutants produced by the dump site and the scours silt carries out the State Emission Standards for Odor Pollutants (GB14554-93) (for new development, expansion or reconstruction projects) the Standard Level 2. Table 2-1-8 Odor pollutants standard value of factory border Level 2 (for new development, Serial No. Control item Unit expansion or reconstruction projects)

3 1 NH3 Mg/m 1.5

3 2 H2S Mg/m 0.06 The odor of the scours silt from the city sewage treatment plant carries out Discharge Standard of Pollutants for Municipal Wastewater Treatment Plant (GB18918-2002) as shown in Table 4. Table 2-1-9 Factory waste gas withdrawal highest permission density Unit: mg/m3

Serial No. Control item Standard level 2

1 Ammonia NH3 1.5

2 Hydrogen sulfide H2S 0.06 (3) Noise The noise at factory border carries out Method of Measuring Noise at Boundary of Industrial Enterprises (GB12348-90) standard according to the noise function regionalization. Table 2-1-10 Method of Measuring Noise at Boundary of Industrial Enterprises Unit: Leq db(A) Category Day time Night time Type 55 45 Type 60 50 Type 65 55 The construction site carries out corresponding standard according to Noise Limits for Construction Site (GB12523-1990).

Table 2-1-11 Noise Limits for Construction Site Noise limiting value db(A) Construction stage Main noise source Day time Night time Earth and stone stage Bulldozer, excavator, car loader, etc. 75 55 The stage of Cutting in All kinds of drop hammer, etc. 85 Prohibited line Structure construction Concrete mixers, inspire tamper, power 70 55 stage saw etc. Decoration stage Crane, elevator, etc 65 55

2.2 Establishments basis Table 2-2-1 The detailed table of establishment basis Serial No. Establishment basis Policies, legal laws and regulations Environment Protection Law of the People’s Republic of China 1 president made 22nd (in December, 1989) Environmental Effect Appraisal Law of the People’s Republic of China 2 president to make 77th (in October, 2002) Water Pollution Prevention Law of the People’s Republic of China (in 3 May, 1996) Air Pollution Prevention Law of the People’s Republic of China (in 4 April, 2000) Ambient Noise Pollution Prevention Law of the People’s Republic of 5 China (in October, 1996) Water Law of the People’s Republic of China president to make 74th 6 (in October, 2002) Clean Production Promotion Law of the People’s Republic of China (in 7 June, 2002) Water and Soil Conservation Law of the People’s Republic of China (in 8 June, 1991) Serial No. Establishment basis June, 1991) Solid Waste Pollution Environment Prevention Law of the People’s 9 Republic of China state president makes 58th (in April, 2005) Water pollution Prevention Law Executive Regulation of the People’s 10 Republic of China the People’s Republic of China State Council 284th verbal command (in March, 2003) River Course Act of Administration of the People’s Republic of China 11 the State Council made 3rd (in June, 1988) The State Council about Realization Science Development View 12 Enhancement Environmental protection Decision the country to send the [2005] No 39 (in December, 2005) Items of basic construction Environmental protection Act of 13 administration the State Council 253rd verbal command (in November, 1998) Items of basic construction Environmental protection Classification 14 Management Name List Country Environmental protection Bureau to make 14th (on January 1, 2003) The State Council about To strengthen City Water supply Saving water 15 And Water pollution Preventing and controlling Work Notice the country sends the [2006]36 number(In November, 2000) In the river course management scope, the items of basic construction 16 management related stipulation (in April, 1992) Tap water source Protectorate Pollution Preventing and controlling 17 Management Stipulation National Environmental protection Bureau (in July, 1989) Organized Loan Items of basic construction Environmental effect 18 Appraisal Supervisory work about Enhancement International finance Notice the link to supervise the [1993]324 number Nation Ecological environment Protection Summary the State Council 19 country to send the [2000]38 number (in November, 2000) The National Environmental protection Bureau link however 20 [1994]184 number (in March, 1997) About Further Standard Environmental effect Appraisal Work Notice The Country Environmental Protection Bureau link to send the 21 [2002]88 number article About Enhancement Wetland Ecology Protection Work Notice (in 2002In July) The Environmental Effect Appraisal Public Participated in Tentative 22 method the link sending the [2006]28 number Province Cities Life Tap Water Source Environment Rule 23 Huaihe River Basin Water pollution Preventing and Controlling 24 Temporary Regulation the State Council 183rd verbal command (in August, 1995) Anhui Province People’s government Wan politics (1997)28 number 25 article Anhui Province People’s government To Implement the State Council about Practical Enhancement Environmental protection Decision Implementation Opinion on Anhui Province People’s government To 26 Implement Environmental protection Work Decision on the State Council Serial No. Establishment basis Implement Environmental protection Work Decision on the State Council about Science Development Opinion and Enhancement Environmental protection Decision Method of Anhui Province To implement the People’s Republic of 27 China River Course Act of Administration (in October, 1991) Anhui Province Agriculture Ecological Environment Protection Rule 28 (in August, 1999) Anhui Province Huaihe River Basin Water pollution Preventing and 29 controlling Rule (In September, 1993) Opinions on Further Improved Environmental effect Appraisal Quality 30 the Anhui Province environmental protection bureau link to supervise the (2002)46 number article (in April, 2002)

Ten items stipulate of The World Bank World Bank Service Handbook - - Environment Appraisal (Op 4.01) 1 World Bank Service Handbook - - National Minority (OD 4.02) 2 World Bank Service Handbook - - Natural Habitat (Op 4.04) 3 World Bank Service Handbook - - Plant Disease Management (OP 4 4.09) World Bank Service Handbook - - Cultural Relic (OP 4.11) 5 World Bank Service Handbook - - Non-Voluntary Immigration (Op 6 4.12) World Bank Service Handbook - - Forestry (Op 4.36) 7 World Bank Service Handbook - - Dam Security (Op 4.37) 8 World Bank Service Handbook - - International Canal Project (Op 9 7.50) The World Bank Service Handbook - - Has Disputed Area Project (OP 10 7.60) World Bank Procedure - - Information Public Policy (BP17.50) 11 The Technical Guidelines And Regulations Environmental Impact Assessment Technology Guidelines- General 1 Outline (Hj/T2.1-93) Environmental Impact Assessment Technology Guidelines- 2 Atmospheric Environment (HJ/T2.2-93) Environmental Impact Assessment Technology Guidelines - Ground 3 Water Environment (HJ/T2.3-93) Environmental Impact Assessment Technology Guidelines - Sound 4 Environment (Hj/T2.4-95) Environmental Impact Assessment Technology Guidelines - Non- 5 Pollution Ecology Influence (Hj/T19-1997) Serial No. Establishment basis Environmental Impact Assessment Technology Guidelines - Water 6 Conservation Water And Electricity Project (HJ/T88-2003) Items Of Basic Construction Environment Risk Assessment Technology 7 Guidelines (HJ/T169-2004) Development Items Of Basic Construction Conservation Of Water And 8 Soil Plan Technology Standard (SL204-98)

Project technology documents

Bengbu Loans The City Flood Prevention And The Ecological Environment Government

1 Project Environmental Effect Appraisal Warrant Using The World Bank, In November,

2006

2 Bengbu City Overall Plan (2005~2020)

Anhui Province Bengbu Urban Planning Area Ground Water Resources Development Uses 3 And Protects Plan

4 Bengbu Ecology City Construction Plan, Bengbu Municipal People’s Government

5 Bengbu Land Utilization Overall Plan (2005~2010)

6 Anhui Province Ecology Province Construction Overall Plan Summary (In January, 2004)

7 Bengbu Huaihe River Water Pollution Preventing And Controlling Plan

Reserch Repbengbu Environmental Protection Overall Plan (2005~2020) Memoir China 8 Environmental Science Research Institute

9 Bengbu City Flood Prevention Plan

10 Bengbu City Water Supply Water Source Plan Report

11 The Bengbu City Will Construct Plan In The Near Future (2006~2010 Years)

12 Bengbu City Draining Water Plan (2005~2020 Years)

13 Bengbu Environmental Protection “25” Plan

14 Bengbu Water Conservation Development “25” Plan Report (Draft)

15 Bengbu Provincial Level Cultural Relic Preservation Organ Name List

Long Zihu Ecological Environment Comprehensive Program Of Public Order Engineering 16 Project Letter Of Proposal

Bengbu New City Synthesis Development Zone Ecology Model District Construction 17 Overall Plan 18 Long Zihu Scenery Scenic Spot Area Overall Plan

19 Bengbu Urban District Ground Cultural Relic Distribution Data Sheet (In March, 2004)

Bengbu Mat Village Flood Prevention Management And Environment Improvement Project 20 Itemized Written Proposal

21 Bengbu Hebei Discrimination Area Plan (In 2002)

22 In Bengbu Huai Area Statistics Yearbook (In 2005) North Shore The Bengbu Huaihe River Prevents Floods Ecological Environment 23 Improvement Itemized Written Proposal In The Bengbu Huai Area Flood Prevention Eliminates Waterlogged And Urban 24 Environment Infrastructure Improvement Project Feasibility Study Report

Wuhe County Froth River Kouzhen (And Bengbu Fine Chemical Industry Garden) Overall 25 Plan (2005~2020 Years)

26 Statistics Yearbook (In 2006)

27 Guzhen County Seat Overall Plan (2003~2020)

28 Guzhen County City Flood Prevention Plan Report

29 Huaiyuan County City Flood Prevention Plan Report

30 The Huaiyuan City Will Construct Plan In The Near Future (2003~2005)

31 Huaiyuan County City Overall Plan (2003~2020) 3. Project Survey

3.1 Projects introduction 3.1.1 Project background Bengbu City is located northeast of Anhui Province and situated at the middle part of Huaihe River. It is a key city of processing industry, the business and center of the science and technology in Northern Anhui area in Anhui Province. Because it is located at the special position, at the cross of the Jin-Pu Railroad main line and Huaihe River, it is also the key position for aquatic and land transportation in Northern Anhui, and thus is regarded as the first port along Huaihe River. There are many inland rivers and lakes in Bengbu City, while the city is relatively lack of flood prevention facilities. So some part of the city is seriously submerges, big water logging when heavy rain, small water logging when light rain. Life and security of the citizens in the city cannot be effectively safeguarded. This has been affecting people’s ordinary life and the industry and agriculture production. Along with the development of urban economy and the increasing improvement of the people living level, the residents have paid more and more attention to the quality of life and the city ecological environment. But the present environment problems in Bengbu mainly are: the flood control standard is low, the flood disaster is frequent; the civil and the industrial sewage increase year by year, the necessary facility for the sewage collection, processing and so on is extremely insufficiency. This has not only restricted Bengbu’s sustainable development, but also had the extremely adverse consequences to ecological environment of Bengbu section region in the Huaihe River Valley. In order to realize the improvement and the comprehensive promotion of Bengbu inhabitant survival environment and the city overall ecological environment, it is the most important thing for the Bengbu social economy development to improve the city necessary infrastructure construction level and to enlarge to flood prevention and environment integrated improvement of Huaihe River and the city inland rivers and lakes when controlling strictly each kind of pollution at the same time. 3.1.2 Construction projects introduction The Bengbu Municipal Party Committee and City Government propose to improve further the construction facility of the city flood prevention and the ecological environment. They plan to use the World Bank loan to carry on the construction program of “Comprehensive Project of Bengbu floods prevention, the infrastructure and the ecological environment”. The entire project divides into 8 sub- project programs, involving four categories, the flood prevention and water logging governing project, the city ecological environment comprehensive programs such as silt clearing and improvement of the rivers and lakes, the vegetation restoring of the coast etc., the project of infrastructure integrated systems for city rain and wastewater network, and the project of water supply and the sewage treatment. The project construction scope covers the Bengbu urban district and three county regions including Huaiyuan, Guzhen, Wuhe with the total investment approximately 1,660,000,000 Yuan. The eight sub-projects of this project are: “The project of Tianhe River flood prevention and controlling”, “The project of Xijiagou flood prevention management and the environment improvement”, “the construction project of city drainage system and waterlogged draining pumping station”, “The project of flood prevention and waterlogged elimination and the environment improvement at Longzihu River”, “the project of flood prevention and waterlogged elimination and the urban environment infrastructure improvement in upper Huaihe zone”, “the project of flood prevention and the ecological environment treatment in Guzhen County”, “the project of flood prevention and the ecology environment treatment in Huaiyuan County” and “the project of flood prevention and the ecology environment treatment in Wuhe County”. 3.1.3 Project progressing plan Using the loans from the World Bank, Bengbu City plan to complete in 2012 the project of flood prevention, waterlogged elimination and the urban environment infrastructure improvement. The construction period is from 2008 to 2012, and 2006~2008 are in the project early preparing stage.

3.2 Project construction content

Table 3-2-1 Projects in

The investment Project content Construction scale (10000 Yuan) Beifei River Drainage Station Newly built, pulling discharge 12300 and the conveyance capacity is 80m3/s system Drainage Present pulling discharge capacity is Xiaobengbu 21.7m3/s, pulling discharge capacity Station 2496 Drainage Station 18.3m3/s after the extended construction Wangxiaogou Newly built, pulling discharge 3000 Drainage Station capacity is 40m3/s The Earth fill of the roadbed and the treatment of afforested belt, 800,000 m3, the channel earth for the scene built at the and afforests belt , 50,000 m3, to surroundings Earth and stone excavate earth for the scenery of 1786.75 for city engineering flushes filling area/ bulldoze flood area, 800,000 m3, the recipe prevention reorganization of afforested at North area(belt), 1,167,000 m3 Huaihe Concrete road Broad road in the riverside, 2636.67 River shore projects 11,909 m in length 3 bridges (Xiaobengbu Drainage Station, Beijing-Shanghai Road bridging 900 railroad, and the Wuxiaojie Drainage Station) The street light lighting system The facilities 10.533km flood prevention 439.96 projects communication system 10.533km Channel drainage system (the PVC tube) 10.533 km, irrigation Pipe network system of the afforests belt, 3049.8 drainage system 27.81km, the drain Laid with mortar 17,500 m3 Trees and the sod transplants planting 4668

Construction of 21 corresponding High speed way altogether 15.38 km 4300 roads , 213805m2 Construction of sewage pipe network in the west of North Daqing Road 6000

Total: 44437.18

Table 3-2-2 Wuhe county project The estimated Project content Construction scale investment (10000 Yuan) Sanpu Lake The design volume 50m3/s, total Pumping station waterlogged installed equipment capacity 8000 construction project draining pumping 6250KW station, the big The big ditch scours Sanpu big ditch, Mochongyinhe ditch scour and and the necessary River canal 12.02 km, scouring 850 the necessary building and the necessary buildings buildings Equipment and necessary civil Factory project projects for 30,000 tons daily 4300 water supply Surface water Necessary water works supply pipe network Water supply pipe network 40km 950 project Water supply pipe Water supply pipe 18km and the 1200 network auxiliary project Equipment for sewage treatment Factory district capacity 30,000 tons and its 5800 project Wastewater/ construction project sewage treatment Plant Necessary draining Storm sewer system 30km 2500 water pipe network project Sewage pipe network 40km 4000 West Yinhe Road 2000m ×9 m, Mohekou Town and Hongmiaoroad,4500m×7m, Road engineering the garden area path Jingyi Road, 2200m×9m, 3800 construction Zhongxin Road, 2100m×7m, Yimin Road 2600m×7m, South Yinhe Road 2000m×7m Total 31400

Table 3-2-3 Guzhen county project The estimated Project content Construction scale investment (10000 Yuan) Construction and reinforcement 504.38 River course and the of river bank 19.37 km in length dike project The river course (drain) scouring 452.04 44.54 km Construction project Construction project of road on of road on the crest for the crest for flood prevention 749 Flood flood prevention 15.12 km prevention and Construction of 10 new waterlogged Culvert and sluice (expanding, changing) culvert 518.78 draining project elimination and sluice, culvert Project Project of drain Construction of 6 new waterlogged pumping (expanding, changing) drain 1808 station waterlogged pumping station Bridge building 27 Newly built bridge 374 Slope protection Sod slope protection project 863.14 afforestation project 429300 m2 The project of New (change) construction the Project of drainage channel discharge pipe (cubic holes), 1955 sewage pipe (holes) 13050 m network in network in urban area and Project of wastewater wastewater Wastewater truncation pipeline in plumber pipes in truncation drinking water source area 5000 570 drinking water source pipeline in m area drinking water source area Total 7794.34

Table 3-2-4 Huaiyuan county project Project content Construction scale Investment estimated (10000 Yuan) Inpoundment silt clearing of Xushuishan Pond at the Chinese Medicine Hospital, 4393 m2, inpoundment silt clearing of Xushuishan Pond at the Luotuoling Hill, 10331 m2 Broadening and silt clearing of three mountain Flood Draining dig massif drains in the Langanqiao Bridge drainage 790 project system and one drain at the hill foot in Xinzhuangzi drainage system Constructs several low overflow batardeaux on four drains and bleeder holes at the bottom of batardeau Three drainage system draining pipe networks Draining water pipe consummation: Lizuizi, Langanqiao Bridge and 489 network project Xinzhuangzi, total length 6115m Build a new Lizuizi waterlogged draining Waterlogged pumping station 3.76m3/s; Expanding draining pumping 2500 Xinzhuangzi waterlogged draining pumping station station 13.57m3/s Build new roads(Jiankang Road, Changsheng Pipe network and Road, Fuqian Avenue) and their necessary storm the necessary path 3390 sewer system network with a total length of construction 8200m

Table 3-2-5 Xijiagou project The investment Construction content Construction scale estimate (10000 Yuan) Flood prevention Marsh land along both banks in the south of project marsh Tushan Road at the Baligou Eight mile land banking ditch river The waterlogged Section from Tushan Road at the course elimination 3098.3 project (slope Baligou to Qinjiashan Bridge government project Mat protection) village Qinjiashan Bridge, Xingzhonglu Bridge, river course Bridge building Xinghualu Bridge, Yuwanglu Bridge, government Yanshanlu Bridge Xiangpiba Dam project 30m to the south of Xingzhonglu Road project Afforestation and Both riversides in the south of the Tushanlu road Engineering Bridge Channel dredging Yanshan Road ~Sancha River Sancha River ~Moshao Youzhigou

Jinxu South Bridge, Tangjiahu Bridge, Lixiangzi Bridge, Changying Bridge, Xijiagou Bridge projects Changying South Bridge, Xiaoyujia Bridge, channel North Xiaoyujia Bridge, South Xiaoyujia 6450 dredging Bridge project Jinxu dike checks Jin Xuzi Dam South of three forks cross of main river channel waterlogged drain volume The river 3 46.3m /s south of three forks cross of retaining dam the right ditch waterlogged drain volume 27.2m3/s Table 3-2-6 Longzi Lake project The investment Construction content Construction scale estimate (10000 Yuan) Construction of pumping station for waterlogged Designed pulling discharge volume 40m3/s, 6760 draining at the Longzi equipment capacity 4000kw Lake Scouring of the south Scouring area 3,449,000m2, the scouring Longzi Lake folk recipe 1,150,000m3 Side slope conditionings Total length of the conditioning slope: 20km Mountain massif Caoshan Hill at the east bank of Longzi Lake 7450 vegetation restoration with the afforestation area South of the Longzi Lake 17.0~19.0m, land Coastal vegetation territory, the north entrance of the Huaihe restoration River region, artificial wetland area

Table 3-2-7 Flood prevention projects Tianhe in Bengbu City The investment Construction Construction scale estimate (ten content thousand Yuan) Tianhe pulling Designed volume 55m3/s, total installing capacity 6520 station 4000KW

Table 3-2-8 Urban wastewater and waterlogged draining project Investment Construction content estimated (10000 Yuan) Municipal Drainage Station Xinchuantang Nanshijia Zhihuai Construction Road Yinhu Road 7641 Committee Discharge pipe (including rain and sewage pipes) Economic Rain water project Development Sewerage 18601.5 Zone Road construction project High and New Rain project Technical Sewerage 9021 Development The sewage promoting pumping station Zone Rain project Longzi Lake Sewerage 3630 district Road construction project The sewage promoting pumping station

4. Environmental impacts and mitigation measures

4.1 Environmental impacts 4.1.1 Environmental impacts in construction period The construction period of this project is quite long and there are many residential area along the road, so the project construction may bring quite a lot influences on the environmental sensitive points. 1. Waste water The wastewater in the construction process includes production work wastewater and constructor’s sanitary sewage. The main origin of production wastewater includes: water seepage excavated from the hole in building foundation channel dredging project; the construction work wastewater during the concrete curing process, the main pollutant is the suspension; Under the natural rainfall and the surface washing effect, the pollution in the scouring sludge ,which is stored beside the bank, infiltrates or filtrates from the side with the stream runoff, resulting in second pollution to underground or the surface water body. Because of the construction machinery cleaning at the working site and the fuel oils leaking or dripping, a little construction wastewater containing the greasy dirt is produced. In the process of scouring sludge/silt storage, wastewater leaks from the draining silt with the suspension as the main pollutant. There is no toxic and hazardous substance in the production waste water. When discharging into the water environment, the major effect is suspension increase in the water. The sanitary sewage comes from the constructor daily lavation and cafeteria draining water. 2. Air In the construction process, the main atmospheric source of pollution produced is non-organized discharges of the raising dust, the waste gas of fuel oil and the odor from the dumping sludge place. The principal constituent of raising dust is TSP. The construction raising the dust mainly comes from the folk recipe excavating, floating and leakage in the material transportation process as well as in the processes of material loading, unloading and storing. The raising dust on the road comes from the construction machinery and the vehicles moving process. Raising dust emissions’ way is the intermittent indefinite quantity discharging. The influencing scope is the nearby the working site and along the transportation road.

The essential components of the waste gas of fuel oil are SO2, CO and NO2. They mainly come from the carrier vehicles and construction machinery using the fuel oil as the power. The influencing scope is the working site and along the transportation road. The odor from the dumping sludge place mainly includes the polluted sludge containing the spoiled organic matter breeds. When piles on the surface, may cause non-organized discharge of the odor material. It main materials causing the odor are the ammonia, the hydrogen sulfide, the volatile hydrogen, the volatility alcohols and aldehydes. 3. Noise The water pump, the excavator, the bulldozer and so on. will be used when river course dredging. In bridge construction, the drop hammer, the hoist, the bulldozer, the bulldozer and so on will be used. In the road engineering constructions, the road roller, the bulldozer and the concrete pushing machine and so on will be used. When in operation, noise of 1m annoyance to these mechanical devices curve acoustic source in 75~105db(A). The highest Annoyance value is from the drop hammer, its 1m annoyance value is approximately 95~105db(A). 4. Solid waste In construction period, solid waste produced includes construction residuals at working site, waste soil as well as constructor's life trash. 5. Ecological environment In the project construction process, before the scouring project water will be discharged completely from the construction section. The excavating and scouring of big ditches may cause influence to some benthoses. But it is temporary to the influence of the excavating and scouring of the river course on the aquatic biological speeches. When the scouring project ends, the water quality enhances, the aquatic biological survival environment will obtain restores with the improvement. In the construction process, it is a principle to take as far as possible little land, which reduces the destruction of the vegetations on both sides, and reduces soil erosion which the construction may bring.

Table 4-1-1 data sheet of pollution emission situation in the construction period in the project of water draining and waterlogged draining elimination

Pollution Source of The main pollutants and Note essential factor pollution influence the production quantity source Water Constructor sanitary Primarily COD BOD environment sewage Construction Primarily SS, petroleum

wastewater class Atmospheric The construction TSP, indefinite quantity Mainly in the environment raising dust emissions construction building materials dump site The transportation TSP, linear emissions Mainly along the way raising dust transported Rejected A small amount Rejected building solid Waste solids construction solids Construction waste A small amount Building materials waste material material primarily The constructor A small amount lives trash Sound Construction 75~105db(A) Space Influenced 100m environment machinery noise Carrier vehicle noise Discontinual influence Inside 50 meters on both sides of the path during day and night Ecological Surface excavating Soil erosion quantity Because of the construction environment at the working site, approximately 3000 tons dump storage and the space temporary pipeline excavating occupying for dumping

Table 4-1-2 Data sheet of pollution emission situation in the construction period in the project in Guzhen County Pollution Source of The main pollutants and the production essential factor pollution influence quantity source Water Living wastewater At most 50 m3/d,COD 14.8 kg/d environment Production wastewater A little ,mainly SS Atmospheric Raising dust TSP, emissions with uncertain amount

Environment Odor(waste soil) Non-organized emission of NH3 and H2S,odourless outside of 50 m Waste gas of fuel gas A little of SO2,CO and NO2 Solid waste Sludge in the pond 30,000 m3 Scouring work 273,400 m3 Life trash When the largest amount of construction work comes, it is 1.5 t/d Sound Construction machinery and Single sound source 85 110 db(A) environment Carrier vehicles

Table 4-1-3 Data sheet of pollution emission situation in the construction period in the project in Huaiyuan County Pollution Source of The main pollutants and Note essential pollution influence the production quantity factor source Water Constructor sanitary Primarily COD BOD environment sewage Including the seepaged water in excavating hole for Construction Primarily SS, petroleum building foundation, the wastewater class digged silt seep, the waste water in mechanical device cleaning Atmospheric The construction TSP, indefinite quantity Mainly in the dump site of environment raising dust emissions construction materials The transportation TSP, indefinite quantity Mainly at the both sides of raising dust emissions the transportation line Waste gas from A small amount of CO machinery fuel oil and NO2 Odor NH3 H2S From the sludge in clearing ditch and ponds Waste solids Rejected A small amount Sludge from the hole construction solids excavated for building foundation Construction waste A small amount Rejected building solid material The constructor lives A small amount trash Sound Construction 75~105db(A) Influenced space 100m environment machinery noise during day and night Carrier vehicle noise Discontinual influence Inside 50 meters on both sides of the path Ecological Construction site Destruction of Temporary occupying land environment vegetation and soil for dumping, surface erosion and lost excavating

Table 4-1-4 Data sheet of pollution emission situation in the construction period in the project in Huaishang Area Pollution Source of The main pollutants and Note essential factor pollution influ the production quantity ence source Atmospheric The TSP, indefinite quantity Mainly in the dump site of environment construction emissions construction materials and along raising dust the transportation lines Construction Waste gas of fuel oil machinery Water Constructor COD, BOD, etc. environment sanitary sewage Including the seepage water from excavated hole for building Construction foundation, the scouring silt SS, petroleum class, etc. wastewater seeping, the waste water produced in mechanical device cleaning Sound Construction Niose of 75~105db(A) Influenced space 100m during environment machinery noise day and night Carrier vehicle Noise discontinual Inside 50 meters on both sides of noise influence the path Waste solids Rejected Small amount Sludge from the hole excavated construction for building foundation ,rejected solids building solid The constructor Small amount lives trash Ecological Construction Soil erosion Construction dumping site and environment site excavation of holes for building foundation

Table 4-1-5 Data sheet of pollution emission situation in the construction period in the project in Longzi Lake Pollution Source of The main pollutants and the Note essential pollution influence production quantity factor source Water Residual water in 1,150,000m3 about environment the scouring project 2,400m3/d mainly is SS TN and TP Construction work Including construction Including the seepage wastewater at the wastewater containing water in hole excavating Longzihu suspension 300 m3/d, waste for building foundation, waterlogged water containing oil 8~10 digging silt seep, the waste draining pumping m3/d water in mechanical station device cleaning Constructor sanitary Altogether 25,200 tons, sewage when construction working is the busiest 38 m3/d Waste gas Raising dust Non-organized emission Influenced space 100m during and 50 meters on both sides of the path Waste gas of fuel oil Non-organized

emission CO and NO2 a small amount Odor Non-organized emission,

NH3,H2S Construction Noise source 75~105db(A) Influenced space 100m Noise machine noise during day and night Waste solids Silt scouring 1,320,000m3 Placed in the dumping field at the bank of Nanhu Lake The constructor Altogether 126 tons, 0.19t/d lives trash in the construction peak Construction waste Small amount Waste sands and stones material and the broken cement blocks in the unloading of Zhengjiadu floodgate and so on Ecology The habitant lives in The quantity of the habitant Short-term influence the bottom water in in the bottom water and its the sludge living environment Working area at Without any effort in soil Construction dumping site, construction site, erosion prevention soil hole excavating for space temporarily erosion approximately building foundation and occupying, sludge 600t/a the dumping site of the dumping site scoured silt

Table 4-1-6 Data sheet of pollution emission situation in the construction period in the project of Mohe River Entrance Pollution Source of The main pollutants and Note essential factor pollution influence the production quantity source Atmospheric The construction TSP, indefinite quantity Mainly in the dump site of environment raising dust emissions construction materials and along the transportation line Sludge Scoured Odor (NH3 H2S) The place sludge cleared and the sludge dumping site Construction Waste gas of fuel oil machinery Water Constructor sanitary COD, BOD, etc. environment sewage Including the seepage water from excavated hole for Construction building foundation, the SS, petroleum class, etc. wastewater scouring silt seeping, the waste water produced in mechanical device cleaning Sound Construction Noise of 75~105db(A) Influenced space 100m environment machinery noise during day and night Carrier vehicle noise Discontinuous influence Inside 50 meters on both of noise sides of the path Waste solids Construction waste Small amount Sludge from excavated hole material for building foundation, waste construction material The constructor Small amount lives trash Sludge in scouring Placed and piled along the both sides of the ditch Ecological Working area on the Soil erosion Construction dumping field environment construction site , and hole excavating for temporary dumping building foundation site

Table 4-1-7 Data sheet of pollution emission situation in the construction period in the project of Tianhe River Pumping Station Pollution Source of The main pollutants and Note essential pollution influence the production quantity factor source Water Constructor sanitary Mainly COD, BOD, etc. environment sewage Including the seepage water from excavated hole for Construction Mainly SS, petroleum building foundation, the wastewater class, etc. scouring silt seeping, the waste water produced in mechanical device cleaning Atmospheric The construction TSP, indefinite quantity Mainly in the dump site of environment raising dust emissions construction materials The transportation TSP, indefinite quantity Mainly at the both sides of the raising dust emissions transportation line Solid waste Construction trash Small amount Sludge in hole excavating for building foundation Construction waste Small amount Mainly the waste construction material material The constructor Small amount lives trash Sound Construction Noise of 75~105db(A) Influenced space in 100m environment machinery noise during day and night Carrier vehicle noise Discontinuous influence Inside 50 meters on both sides of noise of the path Ecological Working area on the Soil erosion Construction dumping field environment construction site , approximately 1350 tons and hole excavating for temporary dumping building foundation site

Table 4-1-8 Data sheet of pollution emission situation in the construction period in the project of Xijiagou Pollution Source of The main pollutants and Note essential pollution influence the production quantity factor source Water Sewage 50 tons/d at most mainly environment COD The wastewater from Few mainly oils Mainly comes from scoured silt seeping, construction machinery The seepage water from Mainly SS excavated hole for building foundation Atmospheric Raising dust TSP emission with an Influenced space is around environment uncertain amount the construction field and along the transportation lines

Waste gas of fuel oil SO2 CO and NO2 small amount Odor NH3, H2S, Non-organized emission Solid waste Trashed soil 375,000 m3 Living trash At most 0.25 ton/d Sound Construction machinery At the 1m, Noise Influenced space is 100m environment and Carrier vehicle 75~105db(A) during daytime Ecological Soil erosion Soil erosion approximately environment 300-330 tons/a Underwater inhabitants Reduction in the amount Shot term of underwater inhabitants 4.1.2 Environmental impact in operation period 1. Water Treatment Plant The main sources of pollution in operation period are solid wastes (including sludge, life trash, etc.), pumping house noise, sanitary sewage in the factory district and so on. The main pollutants in the sanitary sewage of the water treatment plant are: SS,

BOD5, the ammonia nitrogen, COD and the animal and vegetable oils. The wastewater in the sludge removing in the sedimentation pond and the wastewater of the counter-flushing in the counter-flushing filtration pond disperses completely into the newly built sludge concentration basin in the factory district (moisture content 99%). Then concentrated sludge after the precipitation (moisture content 97%) is sent to the dehydration process and the filter cake is formed after filtration press dehydration (moisture content 80%). Then it is ready for shipment processing. While the filtered water from the sludge dehydration process returns to the water well and mixed with the raw water. There is no waste gas in normal operation process in the water treatment plant. But there is some with the leakage of the chlorine cylinder in the unusual situation. The noise of mechanical devices operation in the water works is produced in the blower room and the pumping room, respectively. The power of noise source of air blower and the water pump is 80~90db(A). The solid waste mainly includes the staff living trash, production sludge in the water works and the packing materials of the reagents added. 2. The wastewater treatment plant The main source of pollution in operation period are the solid wastes (including residual sludge, grid dregs, sinks granulated substance, etc.), the noise, the sanitary sewage and the production waste water in the factory, the odor and so on. The waste water includes discharging water emissions in sewage factory and the sanitary sewage in the factory. The sanitary sewage in the factory disperses into the sewage factory feed pump station directly. The odor discharging facility in the sewage treatment plant is mainly the grill and the feed pump room, the sand collector, the biological reaction pond, the sludge concentration basin and the sludge dehydration room and so on. The emissions way is non-organized discharging. The typical odor pollutant is H2S and NH3. The noise source in the sewage factory is the mechanical power noise such as the pumping equipments, the air blower, etc. Among the solid wastes, it is quite few of the thick grill dregs, the thin grill dregs and the sunk granulated substances and so on. While the main solid waste is the sludge cake which is the residual sludge removed from the second sinking pond and then is produced with the concentrated dehydration. 3. Road In the development zone, the main pollution produce in the operation period are the exhaust gas mainly from the automobile discharging; the noise produced when the vehicles move; the pollution from rain water runoff on the road. When the road completes the air pollutant will be mainly the exhaust gas which automobiles produce with its principal constituent of hydrocarbon, nox, CO. The exhaust pollutants will affect the whole atmospheric environment along the route because of the diffusion in the air. Except for the traffic volume, the affected scope is related to the diffusion conditions such as the local wind speed, wind direction, barometric pressure and atmospheric stability. The traffic noise influence assumes the linear pollution characteristic and has the continuity and gradualness. Its influenced scope is related to the traffic volume, the noise present situation as well as the sound environment standard and request during the daytime or at night. The density and the emission amount of the pollutant in the road rain water are concerned with many factors such as the traffic motor volume, vehicle type, precipitation intensity, rainfall cycle, path type and vehicle fuel performance, etc. It is usually difficult to estimate. Known from analogy, the pollutant density in the road rain water will have a changing process from large to small. The pollutant density will reach the highest in 0~15 minutes, reduce gradually afterwards, and tend to be steady after an hour of raining.

4. Drainage Station In this project, solid wastes are divides into two parts: the production waste and the staff living trash. In the operation of Drainage Station, there will be some waste residuals as there are the dirt grills and the dirt-clearing equipment at the station entrance. They are mainly the leaves, the branches, the water plants, the textile fibers, plastics and rubbers and other solid floating matter in the effluent. Table 4-1-9 Data sheet of pollution emission situation in the operation period in the project of City water and waterlogged draining Pollution Source of The main pollutants and Note essential pollution influence the production quantity factor source Water Staff’s living Mainly Wastewater amount 30m3/d environment sewage COD BOD ammonia nitrogen Noise Noise of pumping Source intensity 85-95 Affected space during daytime environment station db(A) is 100m Solid wastes Staff’s living 33000/a 9kg/d Stored together. The rubbish Environmental Sanitation Department cleans up and takes away The grill residue at 10000 tons/a Moisture content 60% he pumping station Table 4-1-10 Data sheet of pollution emission situation in the operation period in the project of Guzhen County Water Rain water on the road COD discharging volume 47.4 kg/d environment Sound Pimping room at the The noise at the factory border environment pumping station satisfies the standard.

Table 4-1-11 Data sheet of pollution emission situation in the operation period in the project of Huaiyuan County Pollution Source of The main pollutants Note essential pollution influence factor source Atmospheric Exhausted vehicle CO NOx environment gas on the road Water Rain water on the SS in main environment road Staff’s sewage at the COD BOD SS pumping station Noise Noise at the Source intensity 85-95 Affected space during the environment pumping station db(A) daytime is 100m Vehicle noise on the Affected discontinually road Solid wastes Staff’s living Small amount Stored together. The rubbish at the Environmental Sanitation pumping station Department cleans up and takes away The grill residuals at Small amount Moisture content 60% the pumping stations and pulling stations

Table 4-1-12 Data sheet of pollution emission situation in the operation period in the project of Huaishang

Pollution Source of The main pollutants and the Note essential pollution influence production quantity factor source Atmospheric Traffic vehicles The exhausted vehicle gas contains environment mainly hydrocarbons nox CO Water Staff’s living Mainly COD BOD environment sewage Rain water on the Mainly SS road Noise Drainage Station Noise intensity 85-95 db(A) environment Traffic on the road Traffic noise Solid waste Staff’s living Living rubbish 0.8t/a rubbish Grill residuals at the 6500 tons /a Moisture content station 60% Table 4-1-13 Data sheet of pollution emission situation in the operation period in

the project of Longzi Lake Pollution Source of pollution influence The main pollutants and the production essential source quantity factor Noise Operational noise of machinery Operational noise of the pump and air- equipment at the draining impressed power equipments approximately pumping station 100db(A) Wastewater Staff’s living sewage at the 3t/d totally 900t/a draining pumping station Solid wastes Staff’s living rubbish at the 15kg/d totally 4.5t/a draining pumping station Grill residuals at the draining 0.26 tons/a moisture content approximately pumping station 60%

Table 4-1-14 Data sheet of pollution emission situation in the operation period in

the project of Mohekou Pollution Source of The main pollutants and the Note essential pollution influence production quantity factor source

Atmospheric Exhausted gas of the Mainly hydrocarbons NOx CO environment traffic vehicles Water treatment plant Chlorine minor amount

Wastewater treatment H2S 0.0227kg/h NH30.12 kg/h plant Water Staff’s living sewage Mainly COD BOD environment Rain water on the road SS in main

Wastewater treatment BOD5 COD ammonia nitrogen, plant etc. Noise Drain pumping station, Operational noise of the equipments environment water treatment plant and wastewater treatment plant Traffic on the road Traffic noise Solid wastes Staff’s living rubbish Living rubbish Grid residual at the drain 3300 tons/a Moisture pumping station content 60% Sludge in the water 14.3m3/d Moisture treatment plant content 80% Sludge in the wastewater 9 t/a Moisture treatment plant content 80% Table 4-1-15 Data sheet of pollution emission situation in the operation period in

the project of Tianhe River drain pumping station Pollution Source of The main pollutants and the Note essential factor pollution influence production quantity source Water Staff’s living sewage Mainly Wastewater production environment COD BOD ammonia amount 7.65m3/d nitrogen Noise Noise at the pumping Source intensity 80-85db(A) Affected space 20~50m environment station Solid wastes Staff’s living rubbish 0.8 ton/a 2.25kg/d Stored together. The Environmental Sanitation Department cleans up and takes away Grid residuals at the 3600 tons/a Moisture content 60% drain pumping station

4.2 Mitigation measures

According to the environmental impact assessment documents and the project

characteristics, based on the analysis of the project’s pollution emission stages in the

construction period and in the operation period, the environmental impact mitigation measures

are proposed in view of the different type of pollutants, at the different time intervals and the

different places, respectively. See Table 4-2-1 for details.

Table 4-2-1 Abstract of the environmental impacts and the mitigation

measures Stage Environmental Mitigation Implementing Type Note factor measures agency Carries on the enough Before investigations and discussions to Based on the overall plan construction Land the project construction scale, Design Ecological and the flood prevention occupying reduce the amount of land organization plan occupying and relocations as few as possible Build temporary draining ditch around the construction site and the sedimentation pond in its low place. The construction wastewater and the site pond are discharged after meeting the standards after precipitation. The sludge wastewater on the construction site needs to be moved to the In special site using specific tunnels to be

dried which has, it is forbidden to discharge it to the agricultural field or the Construction water nearby. Sewage at the The constructors use the existed living construction facility near the construction site as far Water site , Construction Period as possible. For those temporary environment construction quarters sanitary sewages are sent to the organization working municipal sewage treatment plant for wastewater effective processing after septic tank processing, using special dirt collection vehicles. For those quarters in the city the sanitary sewage is connected to the municipal administration sewage pipe network for processing by the sewage treatment plant after septic tank processing. Enhance the management of raw material and construction site, reduces the temporary occupying of land.

To avoid the influencing the ground water quality, spread the clay and so on as the infiltrates base layer at the bottom of putty sludge dump site. à Specifically spray water at least twice a day (coming and leaving) at the powdery material stack area and sweeps every day à Materials should lay under the Montoring is carried out roof as far as possible. Outdoor by the construction depositing should use covering matting. Construction Raising dust organization and the For powdery material, its transportation organization station of should be in tanks and its storage should environ00mentmonitoring be far away the residential area. à If there is a sector of environment sensitive in the scope of 100m from working location, a construction fence should be built around it Atmospheric à The bottom putty should sent environment using sealed tankers after preliminary drying. The dump site of bottom Construction Odor putty should built at the leewardly of organization environment sensitive such as schools, residential area s, etc. Be far away from the inhabited area with the distance >50m. Use the qualified fuel oils and enhance maintenance of mechanical Waste gas of device and the vehicles. Construction

fuel oil Arrange the reasonable organization route for carrier vehicles, guarantee the driving speed and reduce the idling time The polluted surface scouring silt is sent to the sanitary filling field for filling. The middle and lower scouring silt can be used as the filling Construction Construction soil in farmlands, the forest lands and organization Solid wastes trash, trashed the scenic areas. and project soil before using, the soil management environment and the soil texture of the organization putty should be monitored. Then it is classified and treated according to the monitor results.

The construction waste material should be sent out promptly. Clean the working location when the Solid wastes construction ends. Pile along the river or in the agricultural field or farmland is forbidden. Place moving restrooms at the construction battalion, wash and clean Civil and them regularly. environmental Living rubbish Place temporary trash stack spots at sanitary the construction site. The living trash department(s) should be stacked together and shipped promptly. Reduces the construction noise as far as possible, the first choice is to use low noise construction machines and the equipments. Doing noise check before equipments approach. Maintain equipments regularly. Place the working location reasonably.

Separate noisy and quiet sites. Avoid Environmental very noisy equipments work monitoring work will be Construction executed by the Sound simultaneously. Build construction Noise fence/encircle. organization construction organization environment Make scientific construction plan, and the environmental control the work time strictly. Stop monitoring station working from 22:00 to 6:00 if there is together. sector of environment sensitive within 100 m from working site. When commercial concrete is used in a centered region of environmental sensitive as well as in urban areas, use prefabricated concrete components before they are sent to the working site. Control working area. Destruction of Vegetation, vegetations outside the construction site Ecological Construction agricultural is prohibited. environment organization crops Afforestation or reclamation promptly when the construction finishes Avoid rainy season as far as possible and reduce the construction time in excavating of construction. Choose smooth location for temporary stack field and restore its vegetation as soon as possible after Construction Soil erosion using. Pile the soils excavated organization reasonably and set the drain and the bulkhead in the dump site, and be far away from water bodies ditch pond, river course , etc.

Strengthen necessary construction of draining water branch of dams area. Collect sanitary sewage along the project region as far as possible and enter the main current line. Supervise standard construction of pollution outlets in the enterprises. The enterprise separate Ordinary aquatic discharging to the surface water body is quality monitoring is Water Project Surface water forbidden in the draining project service executed by the environment organization area to keep good operation of the environmental sewage treatment plant. monitoring station. Rubbish dumping to both sides of the open and underground canals is prohibited. It is suggested that the path rain water should be collected and then precipitated in the buffer pool before discharge. Ã Establishment of health protection distance in the sewage factory, and enhance afforestation in the factory district, set up the afforested isolation belt. Ã Manage strictly to the sludge Atmospheric stack, the transportation and the Project Odor environment processing handling process in the organization sewage plant. Do sealed transportation to avoid sprinkling along the road and so on. Prevent risks and accidents and establish reacting system for the accident emergency.  Enhance the motor Vehicle Project vehicle management, exhausted gas organization and road maintenance

à Choose equipments with low noise and enhance their maintenance. Ordinary noise à Constructs afforestation Sound Project monitoring is executed by Noise isolation belt in the factory area, environment organization the environmental increase noise insulation effect, monitoring station. adopt the sound insulation sealing treatment for the main pump room and the equipment room.

à Carry on the track monitor to nearby sensitivity area in order to take the prompt preventing and controlling measure

Within 100 meters from both sides of the road, no permission for new building of environment sensitive such as school, hospital or residential area. Ã The environmental sanitation department is in charge of Project Living rubbish cleaning up and taking away organization every day. Ã The sludge shipment should use airtight special-purpose vehicles and the sludge Project Solid waste Sludge transportation time should organization control strictly, avoiding the transportation busy time as far as possible.

5. Implementation organization

5.1 Environment management organizations

5.1.1 Structure drawing of environment management organization The environment management organizations in construction period and the operation period are shown in Table 5-1-1. The frame of environment management structure in the construction period sees Figure 5-1-1. Table 5-1-1 The environment management organizations in charge in construction period and the operation period Rank Project management Construction Environment Track monitoring supervision management In the construction period Provincial Environmental level Protection Bureau in Anhui Province City level The office of world Environmental Environmental bank project Protection Bureau in Monitoring Station management in Bengbu City in Bengbu City Bengbu city Local The offices of each Environmental sub-project Protection Bureau in management the area of each sub- project In operation period Provincial Environmental level Protection Bureau in Anhui Province City level The office of world Environmental Environmental bank project Protection Bureau in Monitoring Station management in Bengbu City in Bengbu City Bengbu city Local The offices of each Environmental sub-project Protection Bureau in management the area of each sub- project

The Office of Bengbu Leading Group for The highest The Office of Environmental the Project of City Flood Prevention and environment Environmental Protection Bureau in the Ecological EnvironmentÀ Management management À ÀÀ of World Bank ÀÀ ÀÀ ÀÀ Anhui Province using World Bank Loans organization

The daily À À EnvironmentalÀ Protection The officeÀ Àof eachÀ sub- environment Bureau in Bengbu City project management management and

cognizant agency

Environment Environment À À EnvironmentÀ À EnvironmentÀ À Project Àdesign ÀÀ À ÀÀ À À ÀÀ À monitoring agency assessment agency supervision agency agency management implementing

agency in designing

Project contractor ImplementingÀ agencyÀ of À environmental protection Figure 5-1-1 Environment management organization schematic drawing in construction period

5.1.2 Responsibilities and functions The environment management of this project includes project management agency, the environment surveillance agency and the construction overseeing agency. i The project environment management agency The management organization in the operation period is shown in detail in Table 5-1-1.The main daily management organization in the construction section of this project is the office of world bank project management in Bengbu city. The management organization primary responsibilities are: Carry out every environmental protection laws and regulations and the general and specific policies from national government and the Department of water conservancy; Carry on the environment management to the project in the construction period and the operation time, report promptly to the Environmental Protection Bureau in Bengbu City when discovering environmental problems. Coordinates to pollution monitoring and routine environment monitoring work with the Bengbu environmental monitoring station. Request environmental monitoring organization or the related department to carry on environment supervision, the environmental monitoring and the environmental protection approval to the project.

Arrange regularly personnel training and the technical inspection and the formulation of environment control system. iThe environment cognizant agency The Environmental Protection Bureau in Bengbu City in under the supervision of the Environmental Protection Bureau in Anhui Province, surveillance construction agency to implement the environment management plan, execute related environment management laws and regulations and the standards, coordinates between various departments to complete the environmental protection work, and it is responsible for the surveillance and the inspection of construction, completion, the operation situation of environmental protection facility of the project in the administrative jurisdictional boundary. During the feasibility study stage and the designing stage, Environmental Protection Bureau in Anhui Province requested the Environmental Protection Bureau in Bengbu City to be responsible for implementation surveillance and the supervisory work of environmental protection of this project, to organize and the coordinate the related organizations to serve for the project environmental protection work, to examine and approve the project environmental impact assessment report (form).The Environmental Protection Bureau in Anhui Province instructed the Environmental Protection Bureau in Bengbu City to carry out each laws and regulations and to be responsible for the environmental protection facility completion approval. During the construction stage, under the work instruction of the Environmental Protection Bureau in Anhui Province, the Environmental Protection Bureau in Bengbu City executed related environment management laws, regulations and the standards, surveillance construction agency to implement the environment management plan, coordinated between various departments to complete the environmental protection work, has been responsible for the construction, completion approval, the operation inspection and the management by supervision of environmental protection facility of this project. In the operation stage, the Environmental Protection Bureau in Anhui Province instructed the Environmental Protection Bureau in Bengbu City and responsible department for the work to be in charge of the project. The project management departments in various sectors carried out the environmental protection laws, regulations and the standard, formulated environmental protection rules and regulations and inspected whole execution situation, investigated the project environment present situation, formulated environment quality control goal which is advantageous for the inspection, proposed the treatment measures, and reported to the Environmental Protection Bureau in Bengbu City, then organized environmental protection personnel inspection of certificates and the personnel trains work, was responsible for the environmental protection technological exchange. i Environment supervision organization in the construction period

Based on the national regulations on environment management of construction projects, this project executed environment supervision system. The entire project must have the environment supervision personnel, whose duty is mainly surveillance, inspection, and management control of the entire process in the construction period to all the environmental protection work, which has been done by the specialized implementation departments of environmental protection project and the project contractor. The environment supervision personnel will inspect and surveillance the realization situation of the environmental protection measure of construction agency according to overseeing plan content in the construction period. When the construction ends, he reports promptly to the overseeing organization and project trustee agency to carry on the environmental protection approval, and signs and issues the completion proof and the project turning report.

5.2 Environmental monitoring organization The Environmental Protection Bureau in Bengbu City and the offices of each sub-project management are in charge of the environment monitoring work of this project. The whole environmental monitoring work in the construction period and the operation period entrusts the Bengbu environmental monitoring station to undertake. Before the construction project starts, the construction agency should sign agreement of environmental monitoring in the construction period with the Bengbu Environmental Monitoring Station. Before the project’s final operation, they sign an agreement of environmental monitoring in the operation period with the monitoring station.

5.3 Contractor’s duties The contractor provides basic duty in the following area: (1) On site environmental protection management. The construction agency should complete preventing and controlling measure of the sewage, the waste gas, the noise, the solid waste and conservation of water and soil. He should provide simultaneously have the specialized environmental protection personnel voluntarily, who is responsible for environment management of the project in the construction period. He should provide the acoustic-meter, test at the point of environment sensitive around the project and guarantee sound environment of the environment sensitive point has been controlled under the sound environment quality standard. (2) Constructor’s residence and the professional hygienic management In the construction process there is mainly the earth and stone engineering with the working conditions in the natural environment. The working medium is non-toxic harmless material which do not have harm and influence to human body. But ventilates with the illumination residence should be provided for the constructor.

Disinfect the residence every month. Moreover, safe and sanitary level food should be provided for the constructor. (3) Safety control Establish and perfect formulation responsibility system of various kinds of work and rules for safe operation in various working procedures in the work position. The operator must have specialized training to avoid operation mistake in maintaining and to reduce the occurrence of the operation accident. (4) Social management Because this project involves many aspects such as the waterlogged drains pumping station, the pipeline network, the big ditch and pond scouring, sludge clearing in lakes, the Binhe Avenue, roads built in development zone, etc. The project office is responsible for the overall projects and coordinates the related management departments.

5.4 Training and ability construction

5.4.1 Training of environmental protection personnel In order to guarantee environment management work in a smooth and effective way, it is necessary to have the knowledge and skill training to the staffs of the construction and the administrative agency. Except for the introduction to all staff of this project the importance and the significance of implementation, there should be different trainings for different responsibilities and positions. 5.4.2 Monitoring abilities construction At the Environmental Monitoring Station in Bengbu City, there are six administrative offices: the General Administration Office, the Central Lab, the Physical Monitoring Lab, the Automatic Monitoring Lab, the Technical Office, the Comprehensive service Office. There are 128 set of instrument/equipment, among them the large-scale equipments are the atomic absorption Spectroscope, the atomic fluorescence Spectroscope, the gas chromatograph, the ion chromatograph and etc at the Environmental Monitoring Station in Bengbu City. At present the authenticated monitoring items are altogether 125 and are included into six kinds of items such as water, gas, sound, soil, etc. The ability construction fund application of World Bank Project will be used in the fundamental instruments and equipments at the Environmental Monitoring Station in Bengbu City. See the following table for the detail.

Table 5-4-1 Table of Monitoring Ability Construction Project of the Environmental Monitoring Station in Bengbu City Serial Disposition The amount Equipment name Note No. quantity set (10000 Yuan) Blow-sweep ping 1 1 15 apparatus (P&T) 2 Spatial sample injector 1 8 High-pressured liquid 3 1 35 phase chromatograph Ultraviolet – visible light 4 1 1 spectroscopes 5 Nitrogen blow-meter 1 0.8 6 Vacuum gyro 1 0.8 Samples pre-treatment 7 1 3 equipment 8 Standard materials 8 A raid of analysis use 9 Reagent 5 A raid of analysis use Special sampling 10 0.2 equipments Gas chromatography 11 automatic sample 3 24 injector Solid extraction 12 1 3 membrane installment The solid extraction column plate Solid extraction column installment should 13 1 0.8 plate installment purchase with the solid extraction membrane installment. 14 Microwave resolution 1 25

extractor Solid extraction 15 50 0.5 A raid of analysis uses membrane diaphragm 16 Solid extraction column 50 0.15 A raid of analysis uses Total 130.05

6. Monitoring plans

6.1 Environment supervision of construction activities To make further clear about the environment supervision work in the construction period and the responsibility of related agencies. See Table 6-1-1for details.(in the table, PMU— project management unit; SE—supervision engineer; ESD—environment social management department, PMO—project management office)

6.2 Monitoring plans

6.2.1 Monitoring goal The environmental monitoring includes two stages in the construction period and the operation period. Its goal is to grasp comprehensively and promptly the pollution tendency of the planned project, to understand the project construction to the change degree and the influence scope of the local environment quality, and the environment quality tendency in the operation period, to report promptly to the department responsible for the work and feedback the information, to provide the scientific basis for the project environment management. 6.2.2 Monitoring implementation Based on the result of environmental effect forecast, test at the point where pollution may more significantly influenced sensitive and considerate one. According to pollution situation during the construction period and the operation period, the monitor content choose obviously affected sound environment, the ambient air, the bottom putty. The monitor factors are determined based on project

analysis of the pollution characteristic factor, the monitor analysis method will use the National Environmental protection Bureau promulgation Environmental monitoring Technology standard the corresponding project monitor analysis method, the evaluation criteria execution link comments the confirmation national standards. According to the project nature and its environmental characteristic, environmental monitoring contents in the construction period and in the operation time have been determined.

Table 6-2-1 Environmental supervision plan Responsible agency Schedule Behavior Comments Execution Surveillance Investment The construction period The plan should be submitted within 1st year The The Prepare for on site environment management plan PMU/SE 3 months after informing being (1~3 months) contractor contractor selected The Verify the scope of each construction working site which Request the contractor to provide the construction PMU PMO - the contractor suggested local map before the construction period Guarantee contractor’s behavior to conform to the SE goes to the working site every day The correlation standard’s requirements. Each week examine or each week. construction the working and facility condition, and the realization SE PMU - PMU goes to all the working site period situation of the anticipation requests and the mitigation every month. measures, which have been set in to the contractor. The Report the situation and serious degree (3 levels) which construction SE PMU - does not conformed to the correlation procedure period Immigratio n handling The & PMU& Guarantee the land taking schedule satisfy the construction coordinatio immigration - construction requirement period n office organizatio n The The PMU& Install the essential road safety symbol, guarantee The construction contractor traffic construction site surroundings security contractor period department PMU & the The The correspondi The The contractor submits renewed plan Posters in the affected area of temporary interruption of construction contractor ng contractor to ESD and the correlation service (water, gas, etc.) 3 days ahead of time. period organizatio department for approval. n

The Report the investigation of on site construction Weekly and monthly report SE PMU - situation weekly SRS report period monthly The Pay attention to the project construction Monthly report or the quarterly report PMU PMO - management requirements period Anhui The Province Pay attention to the project construction Monthly report or the quarterly report PMO Governmen management requirements period t & the World Bank The end of Restore the temporary occupying of land area, The The construction demolition and cleaning up construction trash, the PMU contractor contractor period material and the equipment The lowest requirement is to make up The The end of planting one tree when destroying If it is necessary, plant again the vegetations which have botanical construction Contractor Contractor one tree. The botanical garden been destructed in road construction. garden period department provides the department corresponding standard. The operation period Report to the PMO the discovered For one year since the project completes, the track situation which does not conformed investigation should be carried out on the restoring ESD PMO - to The regulations. Take it as the Conditions of temporary occupying land area. basis of the temporary suspension payment.

Table 6-2-2 Environmental monitoring plan of the project of City draining and waterlogged prevention in the construction period Regular Major Monitor Routine monitor supervising and effect Monitoring point and position Monitor target Executing standard frequency organization managing factor organization In City Construction area boundary Raises the construction Ambient Air Quality City monitoring Environmental (construction operation area) Tsp dust period Standard level 2 station Protection One point Twice Bureau Construction area boundary(construction Organization Leq , db( a ) In a City operation area) with Continuously construction Noise Limits for Environmental Noise One point certifications or equivalent a acoustic peak Construction Site Protection Construction temporary area boundary city monitoring level Twice Bureau One point station

Table 6-2-3 Environmental monitoring plan of the project of City draining and waterlogged prevention in the operation period

Major Monitoring point and position Monitor Monitor frequency Executing Routine monitor Regular supervising and target standard organization managing organization

target standard organization managing organization effect factor z West Shengli Rd., Tiandiren garden z East Shengli Rd,Suncheng Method of Village Measuring Noise z Zhongrong St.,Jianguo Rd. at Boundary of Community Total 7 points Industrial Request a z Hongqi 2 Rd., During operation Enterprises qualified City Environmental Sijiyangguang Garden Leqa Noise period, once for each organization with Protection Bureau z Dingmiao Village in point Type 1, certificates Longhu District Type 2, z Huangshan Village in Type 3, Gaoxin District Type 4. × z The drain prevention station at Yinghu Rd., Jianchaxincun Village ×Note 1 for the 4 draining pumping stations in the old city district noise at the factory boundary executes Method of Measuring Noise at Boundary of Industrial EnterprisesType 2, Type 4; 2 for the 2 wastewater pumping stations in the Gaoxin District noise at the factory boundary executes Method of Measuring Noise at Boundary of Industrial Enterprises type 3, Type 4; 3 for the 1draining pumping station in the Longzihu District noise at the factory boundary executes Method of Measuring Noise at Boundary of Industrial Enterprises type 3, Type 4. Table 6-2-4 Environmental monitoring plan of the Guzhen county project Sub Monitoring Environmental Monitoring point Monitoring item Monitoring frequency Monitoring Responsible Cognizant projects time main factor and position agency agency agency

City flood In the Environment z Left banking TSP 2 points in the Environment Water waterlogged construction air road of Huihe River construction period, once monitoring conservancy Environmental prevention period z Right banking for every point Station in bureau at Protection and road at Sanba River Bengbu City Guzhen Bureau in Damu Bridge to , county Bengbu City Sanbahan hole Environment Noise z At the right Leq Total 3 points monitoring banking road at In the operation period, Station at Sanba River (Damu monitor two cycles for Guzhen Bridge to Sanbahan each point, monitor once county hole during daytime and at One point night respectively for each z At the center of cycle Xiaolou Pumping Station z At the center of Guxi Pumping Station Bottom sludge Point and Position Arsenic, lead, Once, before the near Wangsiweizi at cadmium, construction starts, takes it Jiegou copper, zinc, as the environment mercury, background chromium, organic matter

In the Noise z Wujinli Village Leq 6 point in total, 1 cycle for operation z 1st Guzhen each point every year, period Middle School test once during day and z Wujin Primary night, respectively each School time z 2nd Guzhe Middle School z 2nd Guzhen Primary School z Guzhen People’s Hospital The City In Noise z The entrance of Leq 2 cycles in the The sewage construction the Party School at construction period, for Construction network period Dacheng Rd. each cycle, once during Bureau at and the z The entrance of day and night , Guzhen outlet dam the 2nd Guzhen respectively County tube in the Middle School at west of the Shengli Rd. Environmental city The entrance of the Protection People’s Hospital at Bureau at Guyang Rd. Guzhen Sludge Sludge removing of Arsenic, lead, Once basis monitoring County the ditches and the cadmium, before the construction ponds at Niushi copper, zinc, starts Alley mercury, chromium, organic matter

Table 6-2-5 Environmental monitoring plan of the Huaiyuan County

project in the construction period Regular Major Monitoring point and Monitor Monitor Executing Routine monitor supervising and effect position target frequency standard organization managing factor organization City Environmental Construction area In Ambient Air County Monitoring Raising boundary(construction Tsp construction Quality environmental Station and dust operation area) period Standard monitoring Environmental One point Once level 3 station Protection Bureau 1) Construction area City boundary(construction Environmental operation area) In a Noise Limits County Monitoring One point construction for environmental Noise Leqa Station and 2)Construction peak Construction monitoring Environmental temporary area Twice Site station Protection boundary Bureau One point Once, after Control City sludge Standards Environmental Sludge from the pond removing and County for Monitoring luotuoling hill and the Cd cr cu before environmental Sludge Pollutants in Station and pond at Chinese Hg pb as refilling, monitoring Sludges from Environmental Medicine Hospital takes it as the station Agricultural Protection environment Use Bureau background

Table 6-2-6 Environmental monitoring plan of the Huaiyuan County

project in the operation period Regular Major Monitoring Monitor Monitor Executing Routine monitor supervising and effect point and target frequency standard organization managing factor position organization Xinzhuang Method of City village where 1-2 times Measuring Environmental is the nearest When County Noise at Monitoring to the drains and Environmental Leq a Boundary of Station and Noise xinzhuangzi waterlogged Monitoring Industrial pumping in the flood Station Environmental Enterprises station season Protection Type 1 One point Bureau

Table 6-2-7 Environmental monitoring plan of the Huaishang County project in

the construction period Regular Major Monitoring point Monitor Monitor Executing Routine monitor supervising and effect and position target frequency standard organization managing factor organization Ambient Air Quality At the boundary Standard 4points City of construction level 2 Environmental Once environmental Air site ( binhe av., 3 Air Protection Tsp /year/point monitoring flood prevention pollutant Bureau station drain stations synthesis emissions standard Qualified At the boundary 4points agency with of construction Once /point Noise Limits certificate or Environmental site (3 flood in the for Noise Leq dba city Protection prevention drain construction Construction environmental Bureau stations, binhe period Site monitoring av. station Silt Soil scouring Beifei 3 points City environment Environmental River, Cd cr cu Once environmental Sludge quality Protection xiaobengbu, Hg pb as /year/point monitoring standar Bureau wangxiaogou station level 3 drain stations

Table 6-2-8 Environmental monitoring plan of the Huaishang County project

in the operation period Regular Major Monitoring Routine Monitor Monitor Executing supervising effect point and monitor target frequency standard and managing factor position organization organization One point at each Sound Two District City position of Environment points, Environmental Environmental Noise 24th middle Leq dba Quality Twice Protection Protection school, liu Standard /year Bureau Bureau village Type 3 ,respetively

Table 6-2-9 Environmental monitoring plan of the Longzi Lake project in the

construction period

Regular Monitoring Routine supervisin Major effect Monitoring Monitoring Monitoring Executing point and monitoring g and factor content target frequency standard position agency managing agency Water Water Ss tn tp Discharge Online Integrate Qualified City environment residual at outlet of the monitoring of ss, d agency with Environme dump site sedimentation tn and tp, Wastewat certificate or ntal at each dump Twice in the er city Protection site construction Discharg environmental Bureau period e monitoring Standard station Level 1 Atmospheric Raising Tsp Entrance to Once every year Ambient City City environment dust in the Xinfu at the Air Environmenta Environme construction village in the construction peak Quality l Monitoring ntal east side of time Standard Station Protection the draining level 2 Bureau pumping station of Longzi lake

Odor Nh3 h2s Dump site for Once, before the Emission sludge construction of Standards scouring project, for Odor take it as the Pollutant background slevel 2 value. Once in the operation period at the dump site of the scouring project Sound Noise of Leq Construction One point , Noise Qualified City environment construction operation Twice at the Limits for agency with Environme machinery area construction peak Construct certificate or ntal One point time ion Site city Protection environmental Bureau monitoring station Sludge Silt Cd cr c Choose two Two pints, after Control City City scouring u scouring area, sludge removing Standards environmental Environme Hg pb one and before for monitoring ntal as monitoring refilling, takes Pollutant station Protection point each them as the s in Bureau environment Sludges background from Agricultu ral Use

Table 6-2-10 Environmental monitoring plan of the Longzi Lake project in the

operation period Regular Monitorin Routine supervising Major effect Monitorin Monitorin g point Monitoring Executing monitorin and factor g content g target and frequency standard g agency managing position agency Sound Operation Leq One point 2 points in Noise Qualified City environment al noise of each total, Limits for agency Environmen the drain communit monitoring Construct with tal pumping y of Yuye once when ion Site certificate Protection station Xincun the drain Level 2 or city Bureau and pumping environm Jinyeyuan station in ental operation monitorin every g station year moni tor once during daytime and at night, respectively

Table 6-2-11 Environmental monitoring plan of the Mohekou Project in the operation period Main Monitoring Point and Monitoring Monitoring Executing Routine Regular affecting position index frequency standard monitoring supervising

factor agency and managing agency Construction site boundary ( drain pumping station, 4 points total, Ambient Air sewage once every Quality treatment TSP point in the Standard level plant, water construction City 2 treatment period environmental Atmosphere plant, one monitoring point in the station development zone 2 points, Emission Sludge scouring Once each in Standards County position Sanpudagou NH H S the for Odor environment Ditch, Mochong yinhe 3 2 construction Pollutants River supervision period level 2 brigade Construction site boundary ( drain Noise Limits 4points Once District pumping station, for each in the environmental Noise sewage treatment Leq,dba Construction construction monitoring plant, water treatment Site period station plant, one point in the development zone 2points Once each before the Soil Sludge scouring City construction Environment position Sanpudagou Cd Cr Cu environmental Sludge period, take it Quality Ditch, Mochong yinhe Hg Pb As monitoring as the Standard River station environment level 3 background

Table 6-2-12 Environmental monitoring plan of the Mohekou Project in the

operation period Regular

Main Routine supervising Monitoring Monitoring Executing affecting Monitoring index monitoring Point and frequency standard factor agency managing position Discharge 1 Sludge Standard of point once area in the Pollutants for At the period Atmosphere wastewater H S NH Municipal 2 3 of high treatment Wastewater temperature plant Treatment in summer Plant Level 2 Disperse into Water municipal quality of pipe network Inlet and if there is a outlet in 2 sewage Ph cod SS BOD ammonia Wastewater the cr points twice factory. Carry nitrogen wastewat /year /point out Integrated er Wastewater treatment Discharge plant Standard level 3 City County Water quality Environmental Environment at the inlet Monitoring Supervision Environmental Station Brigade Quality Water PH, turbidity, ammonia nitrogen, Standards for quality at total large intestine bacteria 2 Surface Water Water the inlet of colony, petroleum class, points twice level 3; For quality water permanganic index, total soluble /year /point water quality treatment solid of the outlet, plant Environmental Quality Standards for Surface Water One point at the Sound village environment near the 1 point Noise Leq dba Quality Sanpuhu Once /year Standard Lake Drain Type Pumping Station

Table 6-2-13 Environmental monitoring plan of the Tianhe Pumping Station Project in the construction period Regular Main Routine Monitoring Point and Monitoring Monitoring Executing supervising and affecting monitoring position index frequency standard managing factor agency agency Construction area Twice in Ambient Air City City Raising boundary(construction TSP the Quality environmental Environmental dust operation area) construction Standard monitoring Protection One point period level 2 station Bureau Construction area Qualified boundary(construction agency operation area) Twice in the Noise Limits with City One point for Leq construction certificate Environmental Noise Construction Construction Dba peak period or City Protection temporary area Site environmental Bureau boundary (south of monitoring the pumping station) station One point Control Standards Silt dug from the City City Once , after for pumping station hole Cd Cr Cu environmental Environmental Sludge dug and Pollutants in excavated for building Hg Pb As monitoring Protection before refill Sludges from foundation station Bureau Agricultural Use

Table 6-2-14 Environmental monitoring plan of the Xijiagou project in the

construction period Monitoring Regular Main Point and Routine supervisin Monitorin Monitori Monitoring Executing affecting position monitorin g and g content ng index frequency standard factor g agency managing agency Once each at 2 the points on City City Ambient construction ce each in Environm Environm Raising Air Quality TSP site at the ental ental dust Standard Xijiagou and constructio Monitorin Protection level 2 Atmosphe Baligou, n peak g Station Bureau ric respectively period environme One point each 2 nt sludge dumping points on site beside ce each in NH H Odor 3 2 Xijiagou and the S Baligou, constructio respectively n peak period Two points Level 1 of each for the Integrated Xiejiagou and Wastewater the Baligou, Discharge respectively Standard (different zones when and stage) discharging Qualified into the agency water body with City Constructi Inspect Sound to directly, certificate Environm on once – environme Leq while level requested ental machiner twice every nt 3 when by the Protection y noise year dispersing water Bureau into conservan municipal cy Bureau pipe network connected with the sewage factory Two points Control for the Standards 4 City City Xiejiagou and for Cd Cr points on Environm Environm the Baligou, Pollutants Sludge Silt dug Cu Hg e before the ental ental respectively in Sludges cleaning Monitorin Protection Pb As (different zones from the sludge g Station Bureau and stage) Agricultural Use

6.3 Management system (1) Environment quality report system Should establish the environment quality monthly report, the quarterly report, the annual report system as well as the implementation environment report system. (2) Working responsibility system There should be the special scope of responsibility and the working instruction to make it clear about the responsibility goal for each staff,. (3) Inspection and the rewards and punishment system Regular inspections should be carried out to operators and the rewards and punishment system should be put into practice.

7. The budget and the fund source of the

environment management plan

7.1 The budget of environment management plan

7.1.1 The budget table of the environment management plan in the construction period Table 7-1-1 The budget table of the environment management plan of the Project of City draining and waterlogged prevention in the construction period Project Annual budget RMB 36 months 3 Fund source years budget Four owners operate 4 persons 4 persons The wages: 2000×12 /4×4 = 24,000×3 = 72,000 Yuan Office expense: 24,000Yuan/a 30,000 Yuan Project Transportation 2,500×4=10,000Yuan 30,000 Yuan management Fee expense: 2,500×4=10,000Yuan 132,000 Yuan Total budget: PMO 44000Yuan Air quality monitor Laboratory analysis 1×3000 3000 Yuan 3000×3 9000Yuan Sample Project personnel management Fee Total wages for atmosphere analysis Noise monitor Laboratory analysis 2×1000 2000 Yuan 2000×3 6000 Yuan Sample Project personnel management Fee Total wages for noise monitor Budget for 4 persons 4 persons supervision 3000×12/4×4=36,000Yuan 36000×3= 108,000Yuan engineers 2500×4=10,000Yuan 10000×3=30,000Yuan Project The wages 2500×4=10,000Yuan 10000×3=30,000Yuan management Fee Office expense 56,000Yuan 168,000Yuan Transportation and monitoring expense expense Total budget for supervision agency Ability construction Technical supplied assistance expense Total budget of the 105,000Yuan 315,000Yuan environment management plan Note: Project management personnel monthly wages is calculated with 2000 Yuan, but the specified working time annually is different from each other according

to their sub-projects. Supervision engineers’ monthly wages is calculated with 3000 Yuan.

Expense for the atmosphere TSP monitoring is 3000 Yuan each time, for H2S,

NH3 monitoring, 5000 Yuan each time. Expense for Noise test at each point during one day and night is 1000 yuan each time. For the waste water regular monitoring of five items, the cost on monitoring is 3000 yuan each time. Expense of the water quality test in the water works examines is 5000 Yuan each time. SS, TP, and TN monitoring expense for the residual water in the dump site of Longzi Lake, 2000 Yuan, Sludge monitoring expense is 5000 Yuan each time each point.

Table 7-1-2 budget table of environment management plan of the Guzhen County project in the construction period Project Annual budget RMB 36 months 3 Fund source years budget PMU operation 2 persons 2 persons The wages: 2000×12/2×2 = 24,000 yuan 24000×3 = 72,0000 yuan Office expense: /a 60000 yuan Project Transportation expense: 10000×2=20000 yuan 60000 yuan managemen Total budget for l ESD 10000×2=20000 yuan 202000 yuan t Fee operation 62,000 yuan

Air quality and noise monitor 2×3 000=6000 yuan 6000×3=18,000 yuan Laboratory analysis Project Sample personnel manageme nt Fee Total budget for air and noise monitoring Soil monitor Laboratory analysis 3×2×1000×2=12,000 yuan 12000 yuan Project Sample personnel manageme Total budget for soil nt Fee analysis Budget for supervision 1person engineers 3000×12×1=36,000 yuan 36000×3=108,000 yuan (environmental monitor) 10000×1=10000 yuan 30000 yuan Project The wages 10000×1=10000 yuan 30000 yuan manageme Office expense 126,000 yuan 168,000 yuan nt Fee and Transportation monitorin expense g expense Total budget for supervision agency Total budget of the 216,000 yuan 410000 yuan environment management plan

Table 7-1-3 Budget table of environment management plan of the Huaiyuan County Project in the construction period Project Annual 2 years’ budget Fund source budget RMB County PMO operation 1person 1person The wages: 2000×12×1=24,000 2400×2 = 48,000 yuan Office expense: yuan 10000×2 = 20000 Project Transportation expense: 10000×1=10000 yuan yuan management Total budget: PMO 10000×1=10000 yuan 10000×2 = 20000 Fee 44,000 yuan yuan 88,000 yuan Soil monitor Laboratory analysis Project Sample personnel management Total budget for soil 1×5000 = 5,000 yuan 1×5000 = 5,000 yuan Fee nature analysis Air quality and noise monitor Laboratory Project analysis 3000×1=3,000 yuan 3000×2 = 6,000 yuan management Sample personnel Fee Total budget for air and noise monitoring Budget for supervision 1person 1person engineers 3000×12×1=36,000 36000×2=72,000 yuan (environmental yuan 10000×2=20000 yuan Project monitor) 10000×1=10000 yuan 10000×2=20000 yuan management The wages 10000×1=10000 yuan 112,000 yuan Fee and Office expense 56,000 yuan Transportation monitoring expense expense Total budget for supervision agency Ability construction Technical Provides assistance expense Total budget of the 108,000 yuan 211,000 yuan environment management plan

Table 7-1-4 budget table of the environment management plan of the Huaishang area Project in the construction period Project Annual 2 years’ Fund source budget RMB budget Development company in 1person 1person the new District, Water 2000×12×2=24,000 48,000 yuan Conservation Bureau yuan 20000 yuan owned 10000×1=10000 20000 yuan Project management The wages: yuan 88,000 yuan Fee Office expense: 10000×1=10000 Transportation expense: yuan Total budget: 44,000 yuan Air quality Laboratory analysis 4×3000 =12,000 Project management Sample personnel yuan Fee Total budget for 24,000 yuan atmospheric monitoring Noise monitor 4×1000 =4,000 8,000 yuan Project management yuan Fee Soil monitor Laboratory analysis Project management Sample personnel Fee Total budget for soil nature 3×5000 =15,000 15,000 yuan analysis yuan Budget for supervision 1person 1person engineers 3000×12×1=36,000 72,000 yuan (environmental yuan 20000 yuan monitor) 10000×1=10000 20000 yuan Project management The wages yuan 112,000 yuan Fee and monitoring Office expense 10000×1=10000 expense Transportation yuan expense 56,000 yuan Total budget for supervision agency Ability construction Technical assistance Provides expense Total budget 131,000 yuan 247,000 yuan

Table 7-1-5 budget table of the environment management plan of the Longzi Lake Project in the construction period Project Annual budget RMB Budget in the construction Fund source period Water Conservation Bureau, 1person 1person 30 Economic Development 2000×1×12=24,000 yuan 60000 yuan District operate 10000×1=10000 yuan 25,000 yuan Project The wages: 10000×1=10000 yuan 25,000 yuan management Office expense: 44,000 yuan 110,000 yuan Fee Transportation expense: PMO Soil monitor Laboratory analysis Project Sample personnel management Total budget for soil nature 5000×2=10000 yuan 10000 yuan Fee analysis Air quality and noise monitor Project Laboratory analysis management Sample personnel 1×3000 +2×5000 25000+5000×2+5000 Fee Total budget for =13,000 yuan =40000 yuan atmospheric monitoring Water quality monitor Total budget: wastewater 2000×2=4000 yuan 4,000 yuan monitor Budget for supervision 1person 1person engineers 3000×12=36,000 yuan 90000 yuan (environmental monitor) 10000×1=10000 yuan 25,000 yuan Project The wages 10000×1=10000 yuan 25,000 yuan management Office expense 56,000 yuan 140000 yuan Fee and Transportation monitoring expense expense Total budget for supervision agency Total budget of the 12.70000 yuan 30.40000 yuan environment monitoring plan

Table 7-1-6 Budget table of the environment management plan of the Mohekou project in the construction period Project Annual 2 years’ budget Fund source budget RMB Construction and financial 1person 1person company, Water 2000×12×1=24,000 48,000 yuan Conservation Bureau yuan 20000 yuan Project owned 10000×1=10000 yuan 20000 yuan management The wages: 10000×1=10000 yuan 88,000 yuan Fee Office expense: 44,000 yuan Transportation expense: Total budget: Air quality Laboratory analysis Project Sample personnel management Total budget for 4×3000 +2×5000 22,000 yuan Fee atmospheric monitoring =22,000 yuan Noise monitor 4×1000=4,000 yuan 8,000 yuan Project management Fee Soil monitor Laboratory analysis Project Sample personnel management Total budget for soil nature 2×0.5=10000 yuan 10000 yuan Fee analysis Budget for supervision 1person 1person engineers 3000×12=36,000 yuan 72,000 yuan (environmental monitor) 10000×1=10000 yuan 20000 yuan Project The wages 10000×1=10000 yuan 20000 yuan management Office expense 56,000 yuan 112,000 yuan Fee and Transportation monitoring expense expense Total budget for supervision agency Total budget 136,000 yuan 240,000 yuan

Table 7-1-7 Budget of environment management plan of the Tianhe River Pumping Station project in construction period Project Annual budget RMB 30 months’ budget Fund source Water Conservation Bureau 1person 1person owned 2000×12/2×2=12,000 30,000 yuan The wages: yuan 12,500 yuan Project Office expense: 10000×1/2=5,000 yuan 12,500 yuan management Fee Transportation expense: 10000×1/2=5,000 yuan 55,000 yuan Total budget: PMO 22,000 yuan Soil monitor Laboratory analysis Project Sample personnel management Fee Total budget for soil nature 1×5000=5,000 yuan 5,000 yuan analysis Air quality Laboratory analysis Sample personnel Total budget for 3000×2=6000 yuan 6000 yuan atmospheric monitoring Noise monitor Laboratory analysis Project Sample personnel management Fee Total budget for noise 2×2×1000=4,000 yuan 4,000 yuan monitoring Budget for supervision 1person 1person engineers 3000×12/2=18,000 yuan 45,000 yuan (environmental 10000×1/2=5,000 yuan 12,500 yuan monitor) 10000×1/2=5,000 yuan 12,500 yuan Project The wages 28,000 yuan 70,000 yuan management Fee Office expense and monitoring Transportation expense expense Total budget for supervision agency Total budget of the 65,000 yuan 140,000 yuan environment monitoring plan

Table 7-1-8 Budget of environment management plan of the Xijiagou Project in construction period Project Annual 30 months’ budget Fund source budget RMB Water Conservation 1person 1person Bureau operated 0.2×12=24,000 yuan 72,000 yuan The wages: 10000×1=10000 yuan 30000 yuan Project management Office expense: 10000×1=10000 yuan 30000 yuan Fee Transportation expense: 44,000 yuan 132,000 yuan Total budget: PMO Soil monitor Laboratory analysis Project management Sample personnel Fee Total budget for soil 4×5000=20,000 yuan 20,000 yuan nature analysis Air quality Laboratory analysis Project management Sample personnel Fee Total budget for 2×3000+2×5000= 16,000 16,000 yuan atmospheric monitoring yuan Noise monitor Laboratory analysis Project management Sample personnel Fee Total budget for noise 2×2×1000=4,000 yuan 12,000 yuan monitoring Budget for supervision 1person 1person engineers 3000×12=36,000 yuan 108,000 yuan (environmental 10000×1=10,000 yuan 25,000 yuan monitor) 10000×1=10,000 yuan 25,000 yuan Project management The wages 56,000 yuan 158,000 yuan Office expense Fee and monitoring Transportation expense expense Total budget for supervision agency Total budget of the 140000 yuan 33.80000 yuan environment monitoring plan

7.1.2 Budget of environmental management plan in operation period

Table 7-1-9 Budget of environment management plan of the urban drainage project in the operation period Project Annual budget RMB 3 years’ budget Fund source Four owners operate 1person 1person The wages: 2000×12×1=2.40000 72,000 yuan Project Office expense: yuan/a 30,000 yuan management Transportation expense: 10000×1=10000 yuan 30,000 yuan Fee Total budget: PMO 10000×1=10000 yuan 132,000 yuan 44,000 yuan Air quality monitor Laboratory Project analysis Sample management personnel fee Total budget for atmosphere analysis Noise monitor Laboratory analysis Project Sample 0.1×7=0.70000 yuan 2.10000 yuan management personnel fee Total budget for noise monitor Budget for supervision engineers Project The wages management Office expense Fee and Transportation monitoring expense expense Total budget for SE Total budget of the 51,000 yuan 153,000 yuan

environment management plan

Table 7-1-10 Budget of environment management plan of the Guzhen County Project in the operation period Project Annual 3 years’ budget Fund source budget RMB PMU operate 1person 1person The wages: 1×0.2×12 = 24,000 72,000 yuan Office expense: yuan 30,000 yuan Transportation expense: 10000×1= 10,000 30,000 yuan Project Total budget: ESD operates yuan 132,000 yuan management Fee 10000×1= 10,000 yuan 44,000 yuan Water quality monitor Laboratory analysis Sample personnel Project Total budget for water management Fee quality analysis Air quality and noise monitor Laboratory analysis Project Sample personnel 6×1000=6000 yuan 18,000 yuan management Fee Total budget for atmosphere and noise analysis Soil monitor Laboratory analysis Sample personnel Project Total budget for soil analysis management Fee

Budget for supervision Project engineers management Fee The wages and monitoring Office expense expense Transportation expense Total budget for SE Total budget of the 50,000 yuan 150,000 yuan environment management plan

Table 7-1-11 Budget of environment management plan of the Huaiyuan County

project in the operation period Project Annual budget RMB 3 years’ budget Fund source Water conservation 1person 1person Bureau(Shantang, flood drainage ditch, pipe 2000×12×1=24,000 yuan 72,000 yuan network, drain pumping 10000×1=10,000 yuan 30,000 yuan station) operate 10000×1=10,000 yuan 30,000 yuan Project The wages: 44,000 yuan 132,000 yuan management Fee Office expense: Transportation expense: Total budget: PMO operates Water quality monitor Laboratory Project analysis Sample personnel management Fee Total budget for water quality analysis Air quality and noise monitor Laboratory analysis 1000×1=2,000 yuan 6,000 yuan Project Sample personnel management Fee Total budget for atmosphere and noise analysis Budget for supervision engineers The wages Project Office expense management Fee Transportation and monitoring expense expense Total budget for SE Ability construction Technical Provides assistance fee Total budget of the 46,000 yuan 138,000 yuan environment management plan

Table 7-1-12 Budget of environment management plan of the Huaishang District project in the operation period Project Annual 3 years’ budget Fund source budget RMB Development company of 1person 1person new district, and water 2000×12×1= 24,000 72,000 yuan conservation bureau operate yuan 30,000 yuan The wages: 10000×1=10,000 30,000 yuan Project management Office expense: yuan 132,000 yuan Fee Transportation expense: 10000×1=10,000 Total budget: Project yuan Coordinates Office operates 44,0000 yuan Air quality monitor Laboratory analysis Sample personnel Project management Fee Total budget for atmosphere analysis Water quality monitor Laboratory analysis Sample personnel Project management Fee Total budget for water quality analysis Noise monitor Laboratory analysis Project management Sample personnel Fee Total budget for noise 2×2×1000=4,000 12,000 yuan monitor yuan Budget for supervision engineers The wages Project management Office expense Fee and monitoring Transportation expense expense Total budget for SE Ability construction Technical assistance Provides fee Total budget of the 48,000 yuan 144,000 yuan environment management plan

Table 7-1-13 Budget of environment management plan of the Longzi Lake project in the operation period Project Annual 3 years’ budget Fund source budget RMB Water Conservation 1 person 1 person Bureau operate 2000×12=24,000 24000×3=72,000 yuan The wages: yuan 40,000 yuan Office expense: 10000×1=10,000 30,000 yuan Project management Transportation expense: yuan 132,000 yuan Fee PMO 10000×1=10,000 yuan 44,000 yuan Water quality monitor Laboratory analysis Project management Sample personnel Fee Total budget for water quality analysis Air quality and noise monitor Laboratory Project management analysis 1000×2=2,000 6,000 yuan Fee Sample personnel yuan Total budget for atmospheric monitoring Budget for supervision engineers (environmental monitor) Project management The wages Fee and monitoring Office expense expense Transportation expense Total budget for SE Ability construction Technical assistance Provides fee Total budget of the 46,000 yuan 138,000 yuan environment monitoring plan

Table 7-1-14 Budget of environment management plan of the Mohekou project in the operation period Project Annual budget RMB 3 years’ budget Fund source Construction and financial 1person 1person company, Water 2000×12=2.40000 yuan 24000×3= Conservation Bureau 10000×1=10000 yuan 72,000 yuan owned 10000×1=10000 yuan 30000 yuan Project management The wages: 44,000 yuan 30000 yuan Fee Office expense: 132,000 yuan Transportation expense: Total budget: PMO operates Air quality Laboratory analysis Project management Sample personnel 1×5000=5,000 yuan 15,000 yuan Fee Total budget for atmospheric monitoring Water quality monitor Laboratory analysis Project management Sample personnel Fee Total budget for water 2×2×10000 (0.3+0.5) 96,000 yuan quality analysis =32,000 yuan Noise monitor Laboratory analysis Project management Sample personnel 1000×1=1,000 yuan 3,000 yuan Fee Total budget for noise monitoring Budget for supervision engineers The wages Project management Office expense Fee and monitoring Transportation expense expense Total budget for SE Ability construction Technical assistance Provides fee Total budget of the 82,000 yuan 246,000 yuan environment monitoring plan

Table 7-1-15 Budget of environment management plan of the Tianhe Pumping Station project in the operation period Project Annual 3 years’ budget Fund source budget RMB Water Conservation 1person 1person Bureau owned 2000×2×1=4,000 yuan 12,000 yuan The wages: 1×20000/12=2,000 yuan 6,000 yuan Project Office expense: 1×2/12=2,000 yuan 6,000 yuan management Fee Transportation expense: 8,000 yuan 24,000 yuan Total budget: PMO operates Water quality monitor Laboratory analysis Sample personnel Project management Fee Total budget for water quality analysis Air quality and noise monitor Laboratory analysis Project Sample personnel management Fee Total budget for atmospheric and noise monitoring Budget for supervision engineers The wages Project Office expense management Fee Transportation and monitoring expense expense Total budget for SE Ability construction Technical Provides assistance fee Total budget of the 8,000 yuan 24,000 yuan environment monitoring plan

Bengbu City Environment Management Plan for Flood Prevention and Ecological Environment Improvement Project

7.2 Fund origin Table 7-2-1 Table of expense and Fund origin of the environment management plan Total expenses of Expense of Overall environment environment expenses of Content of sub- management plan in management plan in environment Fund origin projet the construction the 3 years’ of management period operation period plan Project City drainage 315,000 yuan 153,000 yuan 468,000 yuan management prevention Project Fee Project of Flood prevention and Project biological 410,000 yuan 150,000 yuan 560,000 yuan management environment Fee treatment in the Guzhen County Project of Flood 211,000 yuan 138,000 yuan 349,000 yuan Project prevention and management environment Fee treatment in the Huaiyuan County Project of Flood 247,000 yuan 144,000 yuan 391,000 yuan prevention and Project biological management environment Fee treatment in the Huaishang District Longzi Lake 304,000 yuan 138,000 yuan 442,000 yuan Project Project management Fee Mohekou Project 240,000 yuan 246,000 yuan 486,000 yuan Project management Fee Tianhe pumping 140,000 yuan 24,000 yuan 164,000 yuan Project station management Fee Xijiagou Project 338,000 yuan Project management Fee Total 2205,000 yuan 993,000 yuan 3198,000 yuan

Bengbu City Environment Management Plan for Flood Prevention and Ecological Environment Improvement Project