(DOE/EIS-0414-S1) SUPPLEMENTAL TO THE ENERGIA SIERRA JUAREZ U.S. TRANSMISSION LINE PROJECT FINAL ENVIRONMENTAL IMPACT STATEMENT September 2018 U.S. Department of Energy Office of Electricity Washington, DC 20585 COVER SHEET Responsible Federal Agency: U.S. Department of Energy (DOE), Office of Electricity (OE) Title: Supplemental Environmental Impact Statement (SEIS) for the Energia Sierra Juarez (ESJ) Transmission Line Project Final EIS (DOE/EIS-0414-S1) Location: San Diego County, California, Baja California, Mexico Contacts: For additional information on this Draft SEIS) contact: Brian Mills, Document Manager Office of Electricity, OE-20 U.S. Department of Energy Washington, DC 20585 Telephone: (202) 586-8267
[email protected] Abstract: A DOE Presidential permit (PP) is required before anyone can construct, operate, maintain, and connect an electric transmission line across the U.S. border. In December, 2007, Energia Sierra Juarez U.S. Transmission, LLC (ESJ) applied to DOE for a PP for an electric transmission line that would cross the international border between the U.S. and Mexico, near the town of Jacumba, California. In May 2012, DOE completed and released the ESJ Transmission Line Project Final EIS (DOE/EIS-0414) (Final EIS) that analyzed the potential environmental impacts associated with the PP requested by ESJ. DOE issued PP-334 to ESJ on August 31, 2012. The ESJ U.S. Transmission line, and an associated transmission line and wind farm in Mexico (constructed by an ESJ affiliate) were completed and operational by June 2015. DOE’s issuance of PP-334 was challenged in an action filed in the United States District Court for the Southern District of California (“the Court”) in December 2012.