<<

Initial Environmental Examination

August 2012

MFF 0021-PAK: Power Distribution Enhancement Investment Program – Proposed Tranche 3

Prepared by the Electric Supply Company for the Asian Development Bank.

ISLAMABAD ELECTRIC SUPPLY COMPANY

INITIAL ENVIRONMENTAL EXAMINATION REPORT (IEE)

FOR

New 132 KV Sang Jani – Zero Point Double Circuit Transmission Line

POWER DISTRIBUTION ENHANCEMENT PROJECT (TRANCHE – III)

UNDER ASIAN DEVELOPMENT BANK MULTI TRANCHE FINANCING FACILITY (MFF)

AUGUST 2012 (DRAFT)

Prepared & Submitted By

ENVIRONMENTAL & SOCIAL SAFEGUARD UNIT OFFICE OF G.M (DEVELOPMENT) MANAGEMENT UNIT ISLAMABAD ELECTRIC SUPPLY COMPANY (IESCO) ISLAMABAD – .

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Table of Contents

1. INTRODUCTION 1 1.1 Overview 1 1.2 Scope of the IEE Study and Personnel 4 1.3 Structure of Report 5

2. POLICY AND STATUARY REQUIREMENTS IN PAKISTAN 6 2.1 Statutory Framework 6 2.1.1 Pakistan Environmental Protection Act, 1997 6 2.1.2 Pakistan Environmental Protection Agency Review of IEE and EIA Regulations, 2000 7 2.1.3 National Environmental Quality Standards 8 2.1.4 Other Relevant Laws 8

3. DESCRIPTION OF THE PROJECT 10 3.1 Type of the Project 10 3.2 Categorization of the Project 10 3.3 Need for the Project 10 3.4 Location and Scale of Project 11 3.5 Decommissioning and Disposal of Materials 13 3.6 Proposed Schedule for Implementation 14

4. DESCRIPTION OF THE ENVIRONMENT 16 4.1 Project Area 16 4.1.1 General Characteristics of Project Area 16 4.1.2 Affected Administrative Units 16 4.2 Physical Resources 16 4.2.1 Location, Topography, Geography, Geology, and Soils 16 4.2.2 Climate 17 4.2.3 Irrigation 18 4.2.4 Surface Water & Water Supply 18 4.2.5 Rivers and Tributaries 18 4.2.6 Air Quality 18 4.2.7 Noise 19 4.3 Biological Resources 20 4.3.1 Flora 20 4.3.2 Fauna 20

ii

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

4.3.3 Protected Areas / National Sanctuaries 20 4.4 Economic Development 20 4.4.1 & Livestock 20 4.4.2 Industries 21 4.4.3 Communication 21 4.4.4 Energy Sources 22 4.5 Social and Cultural Resources 22 4.5.1 Population Communities and Employment 22 4.5.2 Education and Literacy 23 4.5.3 Health Facilities 23 4.6 Cultural Heritage and Community Structure 24

5. SCREENING POTENTIAL ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 26 5.1 Project Location 26 5.1.1 Impact Assessment and Mitigation 26 5.2 General Approach to Mitigation 27 5.2.1 Cultural Heritage, Mosques, Religious Sites, and Social Infrastructure 28 5.3 Potential Environmental Impacts in Construction Phase 28 5.3.1 Encroachment, Landscape and Physical Disfiguration 28 5.3.2 Cut and fill and waste disposal 29 5.3.3 Trees, Ecology and Protected Areas 30 5.3.4 Hydrology, Sedimentation, Soil Erosion 30 5.3.5 Air Pollution from Earthworks and Transport 30 5.3.6 Noise, Vibration and Blasting 31 5.3.7 Sanitation, Solid Waste Disposal, Communicable Diseases 33 5.4 Potential Environmental Impacts in Operational Phase 33 5.4.1 Air Pollution and Noise from the Enhanced Operations 33 5.4.2 Pollution from Oily Run-off, Fuel Spills and Dangerous Goods 34 5.4.3 Enhancement 35

6. INSTITUTIONAL REQUIREMENTS & ENVIRONMENTAL MANAGEMENT PLAN 36

7. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE 52 7.1 Approach to Public Consultation 52 7.2 Public Consultation Process 52 7.3 Results of Public Consultation 53

iii

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

7.4 Grievance Redress Mechanism 53 7.5 Redress Committee, Focal Points, Complaints Reporting Recording and Monitoring 54

8. CONCLUSIONS 57 8.1 Findings and Recommendations 57 8.2 Summary and Conclusions 58

FIGURES AND MAPS

Figure 1.1: Pakistan EIA Process Figure 3.1: Jurisdiction Map of IESCO Figure 3.2: Location of Sang Jani – Zero Point Transmission Line Subproject Figure 3.3: Time Schedule for Tranche – III Project Figure 7.1: Grievance Redress Mechanism

APPENDICES

Appendix – I (A) Summary of Environmental Monitoring Plan (Matrix) Appendix – I (B) Monitoring Plan for Performance Indicators Appendix – I (C) Monitoring Plan Appendix – II Summary of Public Consultation Appendix –III Implementation Schedule for Tranche III –Distribution Enhancement Program Appendix – IV Summary of Lost Assets Appendix – V Photographs

iv

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

ABBREVIATIONS

ADB Asian Development Bank COI Corridor of Influence CSP Country Strategy Program DFO Divisional Forest Officer DIZ Direct Impact Zone DoF Department of Forests EA Environmental Assessment EARF Environment Assessment Review Framework EIA Environment Impact Assessment IEE Initial Environmental Examination EMP Environmental Management Plan E&SS Environment & Social Safeguard GDP ` Gross Domestic Product GIS Gas Insulated Switchgear GOP GS Grid Station GSS Grid Sub-Station LARP Land Acquisition and Resettlement Plan Leq Equivalent sound pressure level MPL Maximum permissible level NEQS National Environmental Quality Standards NGO Non Governmental Organization PC Public consultation PEPA Environmental Protection Agency PEPAct Pakistan Environment Protection Act 1997 (as regulated and amended) PPMS Project Performance Monitoring System REA Rapid Environmental Examination SIA Social Impact Assessment SP Subproject SR Sensitive Receiver TL Transmission line TOR Terms of Reference

Rupee, PKR Unit of Pakistan currency.

1 USD = 95 PKR

v

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

1. INTRODUCTION 1.1 Overview

1. This document is the Initial Environmental Examination (IEE) Report for the 132 KV Double Circuit Sang Jani - Zero Point Transmission Line, Tranche III sub-project, proposed by Islamabad Electricity Supply Company; (IESCO) under Asian Development Bank (ADB) financed Power Distribution and Enhancement Multi- tranche Finance Facility (PDEMFF).

2. Government of Pakistan (GoP) has requested ADB to provide the PDEMFF to facilitate investments in power distribution and development of networks of Independent Distribution Companies (DISCOs) that distribute power to end user consumers. The funding from ADB is expected to be released in stages (Tranches). The Power Distribution Enhancement Investment Program (PDEIP) is part of the GoP long term energy security strategy. The proposed ADB intervention will finance new investments in PDEIP and assist capacity building of sector related agencies. The investment program will cover necessary development activities in secondary transmission / distribution networks of DISCOs and Tranche-III loan is expected to be approved by ADB in 2012. The PDEMFF activities include extension (additional transformers) and augmentation (replacement of transformers with higher capacity) distribution line extensions, new and replacement distribution lines, additional substations, transformer protection and other non network activities. New distribution lines to and from various network facilities and some of the above activities will also be included in the later trenches. The proposed PDEMFF facility has been designed to address both investment and institutional aspects in the electrical power sector.

3. This Initial Environmental Examination Report presents the results and conclusions of Environmental Assessment Examination for the construction of 132 KV Double Circuit Sang Jani - Zero Point Transmission Line, Tranche III sub-project, proposed by IESCO. PEPCO has been nominated by Ministry of Water and Power (MOWP) to act as the Executing Agency (EA) with each DISCO (IESCO) being the Implementing Agency (IA) for work in its own area. PEPCO‘s role in the processing and implementation of the investment program is that of a coordinator of such activities as preparation of PC-1s and PFRs (Periodic Financing Request), monitoring implementation activities; that includes submission of Environmental Assessments for all subprojects in all trenches of the PDEMFF under ADB operating procedures. An IEE has been carried out to fulfill the requirements of ADB Safeguards Policy Statement, 2009.

Environmental & Social Safeguard Unit – IESCO Page 1 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

4. The Initial Environmental Examination requirements of the GoP for grid stations and power distribution subprojects are different to those of ADB. Under GoP regulations, the Pakistan Environmental Protection Agency Review of Initial Environmental Examination and Environmental Impact Assessment Regulations (2000) categorizes development subprojects into two schedules according to their potential environmental impact. The proponents of subprojects that have reasonably foreseeable impacts are required to submit an Initial Environmental Examination Report for their respective subprojects (Schedule I). The proponents of subprojects that have more adverse environmental impacts (Schedule II) are required to submit an environmental impact assessment (EIA). Distribution lines and substations are included under energy subprojects and Initial Environmental Examination Report is required for sub transmission / distribution lines of 11kV and less and large distribution subprojects (Schedule-I). EIA is required by GoP for all subprojects involving sub transmission / distribution lines of 11kV and above and for Grid Station (GS) substations (Schedule-II), Refer to Figure 1.1.

Environmental & Social Safeguard Unit – IESCO Page 2 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Figure 1.1: Pakistan EIA Process

Environmental & Social Safeguard Unit – IESCO Page 3 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

5. Initially subproject classification was carried out in 2012 and the Category is ‗B‘. Most of the construction impacts will take place with only local impacts and there are no potential significant environmental impacts associated with the Tranche-III sub-subproject construction. Initial environmental reconnaissance and REA carried out by IESCO under ADB guidelines in July 2012 indicated that all the Tranche-III sub-subprojects will be Category B.

6. Pakistan Environmental Protection Act, 1997 (PEPA 1997) requires the proponents of every development project in the country to submit either an Initial Environmental Examination (IEE) or "where the project is likely to cause an adverse environmental effect," an Environmental Impact Assessment (EIA) to the concerned environmental protection agency (EPA). The Pakistan Environmental Protection Agency (Review of IEE and EIA) Regulations, 2000 issued under the PEPA 1997 provide separate lists for the projects requiring IEE and EIA. Project types listed in Schedule-I are designated as potentially less damaging to the environment and those listed in Schedule-II as having more adverse effects. Schedule-I projects require an IEE to be conducted, provided they are not located in environmentally sensitive areas. For the schedule-II projects, conducting an EIA is necessary. The proposed project falls under the Schedule II of the Regulations; hence an EIA has to be conducted for it.

1.2 Scope of the IEE Study and Personnel

7. The Study Area included the identification of irrigation facilities, water supply, habitable structures, schools, health facilities, hospitals, religious places and sites of heritage or archaeological importance and critical areas (if any) within about 100m of the ROW of the TL. The works under the proposed subproject will involve construction of the new TL, construction of the bases, foundation pads and towers to support the distribution line along with erection of about 40 transmission line towers (28 km line length) The proposed project works will be carried out by IESCO‘s contractor and supervised by the IESCO management.

8. The field studies were undertaken by Assistant Manager (Environment) & Assistant Manager (Social Impact) of Environmental & Social Safeguard Unit IESCO along with the field surveys teams. The study team also benefited from technical support and other important information on the impacts of the proposed works briefed by the IESCO technical staff dealing with engineering, power transmission, socio- economic, re-settlement and institutional aspects.

9. A scoping and field reconnaissance was conducted on the subproject site, during which a Rapid Initial Environmental Examination was carried out to establish the

Environmental & Social Safeguard Unit – IESCO Page 4 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

potential impacts and categorization of subproject activities. The methodology of the IEE study was then elaborated in order to address all interests. Subsequently, secondary baseline environmental data was collected from possible sources, and the intensity and likely location of impacts were identified with relation to the sensitive receivers; based on the work expected to be carried out. The significance of impacts from stringing and construction of new TL were then assessed and, for those impacts requiring mitigation, measures were proposed to reduce impacts to within acceptable limits.

10. Public consultation (PC) was carried out in September 2012, in line with ADB guidelines. Under ADB requirements the Environmental Examination process must include meaningful public consultation during the completion of the draft IEE. In this IEE the PC process included verbal disclosure of the sub-subproject works as a vehicle for discussion. Consultations were conducted with local families and communities along the site of 132 KV Double Circuit Sang Jani - Zero Point Transmission Line tower sites and staff of the subproject management. The responses from correspondents have been included in Appendix II and summarized in Section 7 of this IEE.

1.3 Structure of Report

11. This IEE reviews information on existing environmental attributes of the Study Area. Geological, hydrological and ecological features, air quality, noise, water quality, soils, social and economic aspects and cultural resources are included. The report predicts the probable impacts on the environment due to the proposed subproject enhancement and expansion. This IEE also proposes various environmental management measures. Details of all background environmental quality, environmental impact / pollutant generating activities, pollution sources, predicted environmental quality and related aspects have been provided in this report. References are presented as footnotes throughout the text. Following this introduction the report follows ADB guidelines and includes: . Description of the Subproject . Description of Environmental and Social Conditions . Assessment of Environmental Impacts and Mitigation Measures . Mitigation Measures for Identified Impacts . Institutional Requirements and Environmental Management Plan . Environmental Monitoring Plan . Public Consultation . Recommendations and Conclusions

Environmental & Social Safeguard Unit – IESCO Page 5 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

2. POLICY AND STATUARY REQUIREMENTS IN PAKISTAN

12. Direct legislation on environmental protection is contained in several statutes, namely the Pakistan Environmental Protection Act (1997), the Forest Act (1927), the Punjab Wildlife Act (1974). In addition the Land Acquisition Act (1894) also provides powers in respect of land acquisition for public purposes. There are also several other items of legislation and regulations which have an indirect bearing on the subproject or general environmental measures. 2.1 Statutory Framework

13. The distributes legislative powers between the federal and the provincial governments through two ‗lists‘ attached to the Constitution as Schedules. The Federal List covers the subjects over which the federal government has exclusive legislative power, while the Concurrent List contains subjects regarding which both the federal and provincial governments can enact laws. ―Environmental pollution and ecology‖ is included in the concurrent list; hence both the federal and the provincial governments can enact laws on this subject. However, to date, only the federal government has enacted laws on environment, and the provincial environmental institutions derive their power from the federal law. The Punjab Environmental Protection Act 1996 is now superseded by the Pakistan Environmental Protection Act (1997). The key environmental laws affecting this subproject are discussed below. 2.1.1 Pakistan Environmental Protection Act, 1997

14. The Pakistan Environmental Protection Act, 1997 is the basic legislative tool empowering the government to frame regulations for the protection of the environment. The act is applicable to a wide range of issues and extends to air, water, soil, marine, and noise pollution, as well as to the handling of hazardous wastes. The key features of the law that have a direct bearing on the proposed subproject relate to the requirement for an initial environmental examination (IEE) and environmental impact assessment (EIA) for development subprojects. Section 12(1) requires that: ―No proponent of a subproject shall commence construction or operation unless he has filed with the Federal Agency an initial environmental examination [IEE] or, where the subproject is likely to cause an adverse environmental effect, an environmental impact assessment [EIA], and has obtained from the Federal Agency approval in respect thereof. The Pakistan Environmental Protection Agency has delegated the power of review and approval of IEE/EIA to the provincial environmental protection agencies, (refer to Figure 1.1).

Environmental & Social Safeguard Unit – IESCO Page 6 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

2.1.2 Pakistan Environmental Protection Agency Review of IEE and EIA Regulations, 2000

15. The Pakistan Environmental Protection Act, 1997 (PEP Act) provides for two types of Environmental Examinations: initial environmental examinations (IEE) and environment impact assessments (EIA). EIAs are carried out for subprojects that have a potentially ‗significant‘ environmental impact, whereas IEEs are conducted for relatively smaller subprojects with a relatively less significant impact. The Pakistan Environmental Protection Agency Review of IEE and EIA Regulations, 2001 (the ‗Regulations‘), prepared by the Pak-EPA under the powers conferred upon it by the PEP Act, categorizes subprojects for IEE and EIA. Schedules I and II, attached to the Regulations, list the subprojects that require IEE and EIA, respectively.

16. The Regulations also provide the necessary details on the preparation, submission, and review of IEEs and EIAs. The following is a brief step-wise description of the approval process (Refer to Figure 1.1):

(i) A subproject is categorized as requiring an IEE or EIA using the two schedules attached to the Regulations. (ii) An EIA or IEE is conducted as per the requirement and following the Pak-EPA guidelines. (iii) The EIA or IEE is submitted to the concerned provincial EPA if it is located in the provinces or the Pak-EPA if it is located in Islamabad and federally administrated areas. The Fee (depending on the cost of the subproject and the type of the report) is submitted along with the document. (iv) The IEE/EIA is also accompanied by an application in the format prescribed in Schedule IV of the Regulations. (v) The EPA conducts a preliminary scrutiny and replies within 10 days of the submittal of a report, a) confirming completeness, or b) asking for additional information, if needed, or c) returning the report requiring additional studies, if necessary. (vi) The EPA is required to make every effort to complete the IEE and EIA review process within 45 and 90 days, respectively, of the issue of confirmation of completeness. (vii) Then the EPA accords their approval subject to certain conditions: (viii) Before commencing construction of the subproject, the proponent is required to submit an undertaking accepting the conditions. (ix) Before commencing operation of the subproject, the proponent is required to obtain from the EPA a written confirmation of

1 The Pakistan Environmental Protection Agency Review of Initial Environmental Examination and Environmental Impact Assessment Regulations, 2000

Environmental & Social Safeguard Unit – IESCO Page 7 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

compliance with the approval conditions and requirements of the IEE. (x) An EMP is to be submitted with a request for obtaining confirmation of compliance. (xi) The EPAs are required to issue confirmation of compliance within 15 days of the receipt of request and complete documentation. (xii) The IEE/EIA approval is valid for three years from the date of accord. (xiii) A monitoring report is to be submitted to the EPA after completion of construction, followed by annual monitoring reports during operation.

17. Distribution lines and grid substations of 11 kV and above are included under energy subprojects in Schedule II, under which rules EIA is required by GoP. Initial environment examination (IEE) is required for distribution lines less than 11 kV and large distribution subprojects (Schedule I). The proposed sub-project falls in schedule II, hence an EIA report has to be submitted to the relevant EPA, in this case the Pakistan Environment Protection Agency (Pak – EPA) as the proposed subproject will be located in jurisdiction of Capital and as well as Punjab Province.

2.1.3 National Environmental Quality Standards

18. The National Environmental Quality Standards (NEQS) were first promulgated in 1993 and have been amended in 1995, 2000 & 2010. The following standards that are specified in the NEQS may be relevant to the Tranche-3 subproject:

19. Maximum allowable concentration of pollutants (32 parameters) in municipal and liquid industrial effluents discharged to inland waters, sewage treatment facilities, and the sea (three separate sets of numbers)

20. Maximum allowable concentration of pollutants (2 parameters) in gaseous emissions from vehicle exhaust and noise emission from vehicles.

2.1.4 Other Relevant Laws

21. There are a number of other federal and provincial laws that are important in the context of environmental management. The main laws potentially affecting subprojects in this MFF are listed below:

I. The Punjab Wildlife Protection Ordinance, 1972 empowers the government to declare certain areas reserved for the protection of wildlife and control activities within in these areas. It also provides protection to

Environmental & Social Safeguard Unit – IESCO Page 8 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

endangered species of wildlife. As no activities are planned in these areas, no provision of this law is applicable to the proposed subproject.

II. The Forestry Act, 1927 empowers the government to declare certain areas reserved forest. As no reserved forest exists in the vicinity of the proposed subproject, this law will not affect to the proposed subproject.

III. The Antiquities Act of 1975 ensures the protection of Pakistan‘s cultural resources. The Act defines ‗antiquities‘ as ancient products of human activity, historical sites, or sites of anthropological or cultural interest, national monuments, etc. The Act is designed to protect these antiquities from destruction, theft, negligence, unlawful excavation, trade, and export. The law prohibits new construction in the proximity of a protected antiquity and empowers the Government of Pakistan to prohibit excavation in any area that may contain articles of archaeological significance. Under the Act, the subproject proponents are obligated to ensure that no activity is undertaken in the proximity of a protected antiquity, report to the Department of Archaeology, Government of Pakistan, any archaeological discovery made during the course of the subproject.

Environmental & Social Safeguard Unit – IESCO Page 9 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

3. DESCRIPTION OF THE PROJECT

3.1 Type of the Project

22. This Transmission Line Subproject comprises ―Construction of Sang Jani – Zero Point new transmission line of 40 new towers‖. The sub-project is located in the service area of IESCO presented in Figure 3.1. Sang Jani is a part of district of Punjab Province and located towards North of Islamabad district, the capital of Pakistan. Zero Point is the part of Islamabad. The Sang Jani has access from Islamabad through a tar coal road.

3.2 Categorization of the Project

23. Categorization is based on the most environmentally sensitive component of a sub project. The aspects of the subproject with potential of significant environmental impacts need to be assessed in detail and this initial environmental examination study has therefore focused on the significant impacts possible from the construction activities of the subproject.

24. The Sang Jani – Zero Point a new 132 kV Transmission Line subproject is categorized as a Category ‗B‘ sub-project under ADB requirements and as the subproject site does not have any environmentally sensitive receptor.

3.3 Need for the Project

25. The conditions of the power transmission system in Pakistan are inadequate to meet rapidly growing demand for electrical power. This situation limits national development and economic growth. To cope with the constraints, the existing power transmission infrastructure has to be improved, expanded and upgraded. The overall contribution of power infrastructure also requires institutional arrangements and capacity that support strategic management of the sector, and planning and management of investments. Overall the proposed PDEMFF facility has been designed to address both investment and institutional aspects in the electrical power sector.

26. The housing in all towns around Sang Jani and Zero Point are expanding. Therefore, the domestic, commercial and industrial power demands in increasing in all these areas. Refer to Figure 3.1 for large jurisdiction of IESCO.

Environmental & Social Safeguard Unit – IESCO Page 10 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Figure 3.1: Jurisdiction Map of IESCO

3.4 Location and Scale of Project

27. This IEE has included field reconnaissance of the proposed site of construction of new transmission line from Sang Jani to Zero Point. The works area is located within IESCO Jurisdiction. Figure 3.2 and Appendix V presents the location and photographs of subproject.

28. The proposed route of the stringing and construction of new transmission line appears to be environmentally feasible and technically appropriate.

Environmental & Social Safeguard Unit – IESCO Page 11 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Proposed Transmission Line

Figure 3.2: Location of Sang Jani – Zero Point Transmission Line Subproject

Environmental & Social Safeguard Unit – IESCO Page 12 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

29. This IEE has been conducted based on the assumptions available in July -August 2012, when the preliminary designs for the Sang Jani – Zero Point transmission line subproject was completed and the overall requirements for installation of the equipment had been identified. The detailed designs are currently being progressed by IESCO. At this stage, the construction activities under the SP are expected to include the usual localized civil works such as excavation and concreting of foundations for the new transmission line. Impacts from construction of the Sang Jani – Zero Point transmission line subproject are envisaged to be minor as land for TL, and no additional land needs to be acquired for construction of the TL. No additional land needs to be acquired for construction of the towers because the towers will mostly be erected in the existing route of 132 KV TL. The new towers would transverse very small area of cultivated land and mostly hilly barren area.

30. The designs for the Tranche-III subprojects will be developed under the subproject support component of the MFF. This IEE, however, is based on line route surveys (which includes alternative routes and the route which minimizes the social impacts is chosen). The line route is then submitted to the design formation which determines the line profiles and tower locations, these towers are then located on ground. The line design is based on the following parameters.

Table 3.1 Permissible Conductor Clearances Permissible Sr. No Description Clearance (Meters) 1. Cultivated land traversed by Vehicles 6.7 2. Roads/Streets 7.9 3. Communication/Power Lines 2.7 4. Highways 7.9 5. Rail Roads 7.9 6. Electrified Rail Road trolley wire 3.85 7. Rivers in high flood 9.1 8. Places accessible to pedestrian only 7.9 9. Building Roofs not accessible to peoples 5.2 10. Tops of trees 5.0 11. Canals 9.1

3.5 Decommissioning and Disposal of Materials

31. Decommissioning and disposal of discarded material from the subproject will be recycled and reused within the PEPCO system. No waste will be generated that can be classified as hazardous and requiring special disposal. In addition, in case any old transformers are to be replaced, they are not going to be disposed off or discarded and would be recycled and reused within the PEPCO system. As a policy, WAPDA has stopped using transformers that contain PCBs since 1969.

Environmental & Social Safeguard Unit – IESCO Page 13 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

3.6 Proposed Schedule for Implementation

32. Designs power transmission arrangements, access, review of environmental management and construction processes could take several months. When the detailed designs are completed, tendering and award of contract will take place over about three to six months. Then construction period will follow and best estimates indicate about eighteen to twenty four months. Appendix III presents the implementation schedule of the subproject, the implementation schedule of the Tranche-III is given in Figure 3.3.

Environmental & Social Safeguard Unit – IESCO Page 14 of 90 Power Distribution Enhancement Project – Tranche – III 132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Figure 3.3: Time Schedule for Tranche – III Project. (NOTE FOR SMEC: Please put the actual schedule)

Environmental & Social Safeguard Unit – IESCO Page 15 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

4. DESCRIPTION OF THE ENVIRONMENT

4.1 Project Area

4.1.1 General Characteristics of Project Area

33. The construction of new transmission line from Sang Jani to Zero Point is totally foothills area. The line is passing through an existing route excluding the houses or any other public infrastructure. However, very little cultivated land has been transverse and that is mostly near the sangjani area. The towers are proposed to transverse the hilly barren area. The TL is located in the rural areas of the foot hills.

4.1.2 Affected Administrative Units

34. The area to be indirectly affected by the construction of new transmission line of 132 kV from Sang Jani – Zero Point will require 30 meter wide strip for 28 km as working corridor during construction work, so an area of 30m x 28 = 840 sqm will be affected. The transmission line will pass through the following 07 villages only.

Table 4.1: Affected Administrative Units

Sections Villages to be Transverse Islamabad, Dohk Suleman, Jangi Syedian, Jamu Section – II Cooperative Housing Society, Itifaq colony, Jangi Syedian & Sangjani.

35. The transmission line will traverse only a few private farmlands which is 414m or 1.64 per cent of total area to be transverse by the TL. For most of its length it would transverse hilly barren area, which is 24.803 km (98.36 per cent of the total length), Refer to the Summary of Lost Assets Appendix IV.

36. Interviews were conducted with the public near the TL corridor (Appendix II) to obtain their views on the subproject, and any perceived impacts.

4.2 Physical Resources

4.2.1 Location, Topography, Geography, Geology, and Soils

37. Islamabad is located in the in the northeastern part of the country, within the Islamabad Capital Territory. The region has historically been a part of the crossroads of Punjab and with Margalla pass

Environmental & Social Safeguard Unit – IESCO Page 16 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

acting as the gateway between the two regions. The prevailing geologic conditions in the region are the results of extensive inundation, depositions, coastal movements, and erosions over a long period of time in the geological ages. Consequently, the region is one of folded mountains with sharp peaks, ridges, and a deeply incised youthful drainage system. The rock types are predominantly sedimentary.

38. The geology of the region is closely related to the formation process of Himalayan ranges resulting in intense deformation with complex folding, high angle strike-slip faults and crust thickening expressed in a series of thrust faults. The important tectonic changes which have had so much influence in the region are feebly visible, and it is only by considering the geology on a broader regional scale, as well as in site specific detail, that the effects can be appreciated. According to the 1998 census of Pakistan the district had a population of 805,235 of which 65.72% were urban.

39. Attock was declared as separate administrative districts since long. lies in the Punjab Province of Pakistan. It is bordered by the Haripur and districts of North-West Frontier Province to the north, to the east, district to the southeast, to the southwest, and North-West Frontier Province districts of and Nowshera to the west and northwest respectively. According to the 1998 census of Pakistan the district had a population of 1,274,935 of which 20.45% were urban.

40. Islamabad and its adjoining area features an atypical version of a humid subtropical climate, with hot summers accompanied by a monsoon season followed by mild and wet winters. The hottest months are from May to July, where average highs routinely exceed 38 °C (100.4 °F). The monsoon season is from July through September, with heavy rainfalls and evening thunderstorms. Winters are from October to March with temperatures variable by location. In the , temperatures stay mild, with sparse snowfall over the . The weather ranges from 15 °C (59.0 °F) in January to 37 °C (98.6 °F) in June. The highest temperature recorded was 48 °C (118.4 °F) in June, while the lowest temperature was -4 °C (24.8 °F) in January.

4.2.2 Climate

41. Climate of the district varies with altitude. The temperature generally remains between 2oC to 40oC. The Potohar Upland, commonly called the Potohar Plateau, spreading over 2.2 million-hectare of Punjab Province, lies to the south of northern mountains and is flanked in the west by River Indus and in the east by

Environmental & Social Safeguard Unit – IESCO Page 17 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

River . This 1,000-2,000 feet (305-610 m) upland is a typical arid landscape with denuded and broken terrain characterized by undulations and irregularities. These are a few outlying spurs of in the south, and those of Kheri Murat and in the north. Two seasonal streams - Rivers Haro and River Soan - flow from east to the west and after crossing the region in the north and in the middle respectively, fall in the Indus. River Kanshi traverses the eastern part of the plateau from north to south and drains into River Jhelum. These rivers and other hill torrents have cut deep valleys and are of little use for irrigation. Agriculture is thus almost entirely dependent on rainfall of 15-20 inches (380-500 mm)' and on the small dams built in the catchment areas of the streams.

4.2.3 Irrigation

42. On account of mountainous topography, a very small percentage of cultivable land is irrigated by means of small water channels which are made to bring water from rivers and nullahs. In most of the cases, spring water is diverted for irrigating paddy fields and vegetable fields by means of small channels.

43. The main vegetables grown in the district are brassica, turnip, radish, tomato, chili, garlic, onion, lady-finger, bringel, etc.

4.2.4 Surface Water & Water Supply

44. In the Islamabad district, 57.28 per cent of the housing units are using piped water, majority of which has that facility in their own houses. Rest of the population fetches water from springs and or Nullas. In the district Attock, 27 per cent of the housing units are using piped water, majority of which has that facility in their own houses. Rest of the population fetches water from springs and or Nullas.

4.2.5 Rivers and Tributaries

45. flows along the western boundary of the district in a north to south direction. However Sowan river, Korang river & Seasonal Nala in the area are the also water streams. However, other numerous rivulets flow in the district.

4.2.6 Air Quality

46. Air quality in most of the project area appears good based on observation during the study period. Emissions should be controlled at source under the EMP. There will be a few items of powered mechanical equipment to be used in the stringing and construction of TL works that will even may not give rise to complaints of

Environmental & Social Safeguard Unit – IESCO Page 18 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

dust and other emissions because due to hilly area and Nalas dust may not generate much. However if there is any, these should be minor and easily dissipated. Domestic sources of air pollution, such as emissions from wood and kerosene burning stoves as well as small diesel standby generators in some households, are minor.

47. There should be no source of atmospheric pollution from the project. In the operational phase the industrial facilities with fuel powered mechanical equipment will be the main polluters. All such emissions will be very well dissipated in the open terrain and there will be no cumulative effect from the project. The project area is distant from major sources of air pollution like industries or urban type traffic, domestic sources such as burning of wood and kerosene stoves, etc. or fugitive sources such as burning of solid wastes. Air quality in the project area appeared very good during the study period. Air quality measurements in major urban centers, carried out by Pak-EPA , revealed

that CO, SO2 and NO levels were in excess of the acceptable levels in some areas but the average levels were found below WHO standards. Air quality testing by 3 DISCOs (average values are : TSP 1.09 mg/m , CO 634 ppb , SO2 24.34 ppb, NO2 23.73 ppb ) through various consultants has revealed that most sub stations have

NO2, CO2 and CO values below international standards although TSP levels at some locations was higher than international standards.

48. The other major source of air pollution is dust arising from construction and other ground or soil disturbance, during dry weather, and from movement of vehicles on poorly surfaced or damaged access roads. It has been observed that dust levels from vehicles may even be high enough to obscure vision significantly temporarily.

4.2.7 Noise

49. Noise from vehicles and other powered mechanical equipment is intermittent. There are also the occasional calls to prayer from the PA systems at the local mosques but there are no significant disturbances to the quiet rural setting. However, the construction from the proposed power expansion will use powered mechanical equipment. Subjective observations were made of background noise and also of individual vehicle pass by events. Based on professional experience background daytime noise levels are probably well below 55dB (A) L90. DISCOs have carried out noise level measurements at various sub stations and transmission line locations within the system .These analyzed to calculate Leq values have resulted in Leq values much below the 85 dBA limit prescribed under the NEQs established by the EPA or the 75 dBA used by

Environmental & Social Safeguard Unit – IESCO Page 19 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

DISCOs/NTDC/PEPCO in the equipment specifications . Typical values were : average 46.21 dBA ; high 63.14 dBA ; and low 34.35 dBA.

4.3 Biological Resources

4.3.1 Flora

50. Pine, Kai, fir and other trees like poplar, shisham, kikar, willow, walnut, ban-akhore, and mannu are found plentiful in the district. Among flowers zianna, dahlia, merrygold, cosmos, daffodil aster and rose of different kinds are found in the district Mostly the population of the rural areas is very much keen and eagerly devoted in plantation of fruit plants and to suffice the purpose, agriculture nurseries are affording the demand of general masses.

4.3.2 Fauna

51. Wild life of the district is mostly confined to Margalla National Park. Various species of wildlife, include Rhesus monkeys, jackals, wild boars, porcupines, mongoose and the pangolin or scaly anteater. Leopard is less common. There are a number of species of poisonous snakes in the area, including cobras, Russell's Vipers, kraits—known in local parlance as the half-minute killer and indian phython. Birds in the park include Himalayan griffon vulture, laggar falcon, peregrine falcon, kestrel, Indian sparrow hawk, Egyptian vulture, white cheeked bulbul, yellow vented bulbul, paradise flycatcher, black partridge, cheer pheasant, Khalij pheasant, golden oriole, spotted dove, collared dove, larks, shrikes, wheatears and buntings.

4.3.3 Protected Areas / National Sanctuaries

52. In Pakistan there are several areas of land devoted to the preservation of biodiversity through the dedication of national parks and wildlife sanctuaries. There is no wetland except Indus River along the boundary of the district. Similarly there is no protected area or national Sanctuary near the area of works of the subproject.

4.4 Economic Development

4.4.1 Agriculture & Livestock

53. Except for a few places in district which are irrigated by means of water channels drawn from springs and hill torrents, other areas depend on the rainfall. The major crops of the district are maize and but at some places gram, bajra and jawar are also cultivated. Pulses of all kinds are also grown in different areas

Environmental & Social Safeguard Unit – IESCO Page 20 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

of the district. Beans of a good variety are cultivated in abundance. Similarly the soil of this district is ideal for grains. Sarsoon is also grown in different parts of the district. 54. The subsistence holding of the individual in the district is very small and they avail joint family system. Most of the people started horticulture instead of sowing other crops, with a view to gain livelihood in an easy way.

55. The district is deficit in food grains production. The local production hardly suffices for 2 to 3 months. The population of the district depends mainly on food grains/flour supplied by the Food Department, Punjab. Other commodities of daily use are brought from Rawalpindi and other neighboring markets of Pakistan.

4.4.2 Industries

56. Most of the industries in Islamabad are confined to Industrial Estate Islamabad (IEI), which houses more than 200 industries. IEI is spread over 625 acres of land on the border of of Rawalpindi and Islamabad. Types of industries and their approximate numbers are shown below:

Table 4.2: Types and Approximate Numbers of Industries in IEI.

Sr. No. Types of Industries Approximate # 1. Steel Melting Furnaces 8 2. Re-rolling Mills 11 3. Flour Mills 25 4. Oil and Ghee Mills 5 5. Marble Cutting and Polishing Units 31 6. Pharmaceuticals 10 7. Galvanizing 2 8. Metal Working and Engineering Units 23 9. Other un-categorised industrial units 130 Total 245 Survey Report – Environmental Survey of Industrial Estate Islamabad, 2006 (Pak-EPA)

4.4.3 Communication

57. Islamabad is connected with rest of Pakistan by roads viz: – Rawalpindi – Provincial Higways system (GT Road) & Motorway via National Highways. There is also railway line available in the district. Banazir Bhutto International Airport connected it with the other destinations. While Attock district is connected with Rawalpindi by two roads viz: Rawalpindi –

Environmental & Social Safeguard Unit – IESCO Page 21 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Attock Provincial Higways system & Motorway via National Highways. There is also railway line available in the district.

4.4.4 Energy Sources

58. About 76.2 percent housing units are using wood as cooking fuel in their houses while 56 percent are using gas for their purpose. 2.7 percent are using kerosene oil and other sources of cooking fuel in their houses.

4.5 Social and Cultural Resources

4.5.1 Population Communities and Employment

59. Total population of Islamabad district is 1.15 Million according to the estimates (2012) on the basis of last population census report 1998. According to the 1998 census of Pakistan the district had a population of 805,235 of which 65.72% were urban. The rural population of the district is about 34.28 percent of the total population, while Total population of Attock district is 1.8 Million according to estimated as in 2012 on the basis of last population census report 1998. According to the 1998 census of Pakistan the district had a population of 1,274,935 of which 20.45% were urban. The rural population of the district is about 79.55 percent of the total population.

60. Almost all the population of the district is Muslim. They constitute 98.3 per cent of the total population in rural as well as in urban areas. There are very few Christian, Hindu, Qadiani, schedule caste and other communities which are only 1.7 per cent of the total population.

61. Much like rest of the country, the male members of the family in the project area are the breadwinners (excluding the main city, Islamabad). Of the total male population, on average 47 % are economically active, while remaining 53 % are inactive. Among them 25 % are under the age of 10, remaining are students, domestic workers, landlords, property owners, retired persons, disabled and unemployed.

62. The bigger part of the rural population belongs to middle class or lower middle class, because of small landholdings and barani (rain-fed) area. The population of the is relatively better off, because many people from these areas are settled in European countries, and send remittances to their families in Pakistan/AJK.

Environmental & Social Safeguard Unit – IESCO Page 22 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

63. A new economic factor has been introduced by the establishment of a few factories in Rawalpindi and Islamabad and a large industrial area in the Jhelum, Chakwal and Oil field Region of Attock, in Chakwal and where a few large cement factories also installed.

4.5.2 Education and Literacy

64. Islamabad boasts the highest literacy rate in Pakistan at 87%, and has most advanced educational institutes in the country. A large number of public and private sector educational institutes are present here. The higher education institutes in the capital are either federally chartered or administered by private organizations and almost all of them are recognized by the Higher Education Commission of Pakistan. High schools and colleges are either affiliated with the Federal Board of Intermediate and Secondary Education or with the UK universities education boards, O/A Levels, or IGCSE. According to Academy of Educational Planning and Management's report, in 2009 there were a total of 913 recognized institutions in Islamabad (31 pre-primary, 2 religious, 367 primary, 162 middle, 250 high, 75 higher secondary and intermediate colleges, and 26 degree colleges). There are seven teacher training institutes in Islamabad along with there are 16 recognized universities in Islamabad.

65. The number of educational institutions available in the district is presented in table below.

Table 4.3: Section-II. Educational Institutions

Education status Numbers Enrollment District Universities Universities School Others School Others and Colleges and Colleges Attock 1,192 9 236 NA NA NA

4.5.3 Health Facilities

66. District Health Officer Supervises the health care activities at the district level. Islamabad has the lowest rate of infant mortality in the country at 38 deaths per thousand compared to the national average of 78 deaths per thousand. Islamabad has both public and private medical centers. The largest hospital in Islamabad is Pakistan Institute of Medical Sciences (PIMS) hospital. According to the Federal Bureau of Statistics of the Government of Pakistan, in 2008 there were 12 hospitals, 76 dispensaries, and 5 Maternity and Child Welfare Centers in the city.

Environmental & Social Safeguard Unit – IESCO Page 23 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

67. District Health Officer Supervises the health care activities at the district level. Following health units and hospitals have been established in the district.

Table 4.4: Section-II: Health Facilities

Sr. No. Number of Healthcare Facilities District Attock 1. Hospitals (150 beds and above) 3 2. Districts Headquarters Hospitals 1 3. Tehsil Headquarters Hospitals 4 4. Basic Health Units 57 5. Rural Health Centers 5 6. Maternity Community Health Centers 4 7. T.B Clinics 2 Others 8. (Sub Health Centers, Dispensaries and 32 Private Facilities)

4.6 Cultural Heritage and Community Structure

68. There exist a large number of sites of archeological, cultural, historical and religious significance in the project area. The major ones include the archeological and historical buildings and sites in Islamabad & Rawalpindi, in addition to these, a large numbers of shrines in almost all parts of the project area. A list of these places located in the project area is provided in Table 1 however no major historic or archaeological feature of noted within about 500m of the works.

69. Most of the population in Islamabad and Rawalpindi are ethnically of Aryan origin. The major casts/tribes/braderies of the area are Rawal, Junjua, Chohan, , Mughal, Qureshi, Syed, Bhatti, Satthi, Ghakkar, , Gujar, Jatt, Jalap, Minhas, Gondal, Shiekh, Kahut, Arain and Kashmiri.

Table 4.5: Places of Archeological, Historical or Religious Significance

Sr. No. Description Location About 22 km from Islamabad on Soan Bank, 1 Fort District Rawalpindi 2 Buddhist Stupa Bhallar, Rawalpindi 3 Buddhist Stupa Mankiyala, Rawalpindi 4 Rewat, District Rawalpindi

Environmental & Social Safeguard Unit – IESCO Page 24 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Sr. No. Description Location Areheoligal remains Texila District Rawalpindi at (, Hatial, 5 , Sir Sukh, Jaulian, Mohra Moradu and others) 6 Babar Khan Texila District Rawalpindi Nicholson Texila District Rawalpindi 7 Monument 8 Mughlai Gardens Wah, District Rawalpindi 9 Losar Baoli Wah, District Rawalpindi Areheoligal remains Texila District Rawalpindi at Taxila (Bhir Mound, Hatial, 10. Sirkap, Sir Sukh, Jaulian, Mohra Moradu and others) 11. Attock Khurd on Indus Bank, District Attock 12. Begum Saraj On GT Road near Khurd District Attock Shrine of Baba Wali District Attock 13. Qandhari Gurdwara Punja Hasanabdal, District Attock 14. Saheb 15. Lala Rukh Tomb Hasanabdal, District Attock 16. Hakim‘s Tomb Hasanabdal, District Attock 17. Saidan Baoli Hatti, District Attock 18. Chitti Baoli District Attock 19. Behram ki District Attock Source: District Census Reports, (1998); Guidelines for sensitive and critical areas; Pak-EPA

Environmental & Social Safeguard Unit – IESCO Page 25 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

5. SCREENING POTENTIAL ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 5.1 Project Location

5.1.1 Impact Assessment and Mitigation

70. This Tranche-III subproject will involve the construction of new 132kV Double Circuit Sang Jani – Zero Point transmission line subproject, 28 km in length. There are sensitive receivers (SR), structures of houses, schools, colleges, factories, which are more than 100m away from the TL ROW and there are no sensitive receivers or structures close to the TL ROW which could be possibly affected by certain activities of the SP works.

71. The location and scale of the works are very important in predicting the environmental impacts. Therefore, it is essential that a proper analysis is carried out during the subproject planning period. This process of impact prediction is the core of the IEE process and it is critical that the recommendations and mitigation measures are carried out according to, and with reference to the conditions on the ground in the affected areas in the spirit of the environmental examination process (Figures 3.2 shows the Site & route of the proposed subproject). In this section the potential environmental impacts are reviewed. Where impacts are significant enough to exceed accepted environmental standards, mitigation is proposed in order to reduce residual impact to acceptable levels. In this regard, the impact prediction plays a vital role as these predictions are used for developing mitigation measures and any alternative options, if appropriate. When the detailed designs are completed the impacts and mitigation measures will need to be further reviewed to take account of how the contracts are set up and in the light of any fine tuning of the subproject proposals.

72. The Environmental Management Plan (Section 5 and EMP Matrix Table 6.1) has been reviewed based on the assessment and shall be reviewed in due course at subproject inception and through construction in order to provide a feedback on any significant unpredicted impacts. It is based on the analysis of impacts, primarily to document key environmental issues likely to arise from subproject implementation, to prescribe mitigation measures to be integrated in the subproject design, to design monitoring and evaluation schedules to be implemented during subproject construction and operation, and to estimate costs required for implementing subproject mitigation measures. The EMP may be reviewed, if needed, at the subproject inception by the subproject management

Environmental & Social Safeguard Unit – IESCO Page 26 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

and approved before any construction activity is initiated, to take account of any subsequent changes and fine tuning of the proposals.

5.2 General Approach to Mitigation

73. Based on professional experience on some projects, contractors have put emphasis on the financial compensation for nuisances. This may be acceptable for some social impacts where evacuation is necessary or where houses have been accidentally damaged, however it is not best international practice to accept payment for environmental impacts. An approach whereby, the subproject contractor pays money for nuisances rather than `control impacts at source will not be acceptable. This practice should not be allowed, and financial compensation shall not be allowed as mitigation for environmental impacts or environmental nuisance.

74. During the preparation for the subproject construction phase the future contractors must be notified and prepared to co-operate with the executing and implementing agencies, subproject management, construction supervising consultants and local population in the mitigation of impacts. Furthermore the contractor must be primed through bidding stages and the contract documentation to implement the EMP in full, and be ready to engage or train staff in the management of environmental issues and to audit the effectiveness and review mitigation measures as the subproject proceeds.

75. The effective implementation of the EMP will be audited as part of the loan conditions and the executing agency (IESCO) must be prepared for this. In this regard the IESCO must fulfill the requirements of the law and guidance prepared by Pak EPA on the environmental aspects of power subprojects and the recommendations already made for the subproject in this IEE and under Pakistan‘s PEP Act.

76. The location of the residences, mosques, schools, hospitals and civic, cultural and other heritage sites has been reviewed in Section 5. There could be some potential impacts in the construction stage from disturbance and significant noise and dust. However, the alignment is through cultivated fields and or hilly barren area, and no receptors such as residences, mosques or schools close enough to the alignment to be significantly affected by the works.

77. Work on the tower sites could cause some generation of air borne dust, but any nuisance from this is likely to be very localized and temporary. Other project activities, e.g. movement of heavy vehicles on unpaved tracks during the works,

Environmental & Social Safeguard Unit – IESCO Page 27 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

could generate considerable dust. Water is available in the study area, although surplus water may not always be available to suppress dust at vulnerable locations in the dry season. Therefore as a general approach it is recommended that where works are within 15m of any residential sensitive receivers, the contractor should install segregation between the works and the edge of the sensitive receivers. The segregation should be easily erectable 2.5m high tarpaulin sheet and designed to retain dust and provide a temporary visual barrier to the works. Where dust is the major consideration the barrier can take the form of tarpaulins strung between two poles mounted on a concrete base. These can be moved along from tower base to tower base as the work proceeds.

78. Noise from the construction of the towers should not be a major consideration unless very close to schools or hospitals where construction should be avoided at sensitive times. In addition to the physical effect of mitigating dust and noise with barriers installation of such measures should be discussed with the local population and serve as a vehicle for further public consultation at the implementation stage to assist in public relations.

5.2.1 Cultural Heritage, Mosques, Religious Sites, and Social Infrastructure

79. The location of mosques and other cultural and other heritage SR sites has been reviewed in Section 5. There are no mosques or other religious sites close to the TL ROW (Refer to the Appendix IV).

80. The nearest clinic / hospital is more than 100m from the edge of the subproject or TL route. The TL may, however, cross katcha and or pacca roads. Apart from these features, there will be sufficient buffer distance between the works and any other SRs, so that no significant impacts should be expected. Public consultation should be undertaken at the implementation stage to ensure nuisances are not allowed to escalate for the SRs close to the TL route.

5.3 Potential Environmental Impacts in Construction Phase

5.3.1 Encroachment, Landscape and Physical Disfiguration

81. The extent of the proposed power expansion is moderate and should not extend beyond the power corridor (RoW) created by the subproject. No significant landscape impacts are expected from construction of the 132 KV D/C Sang Jani – Zero Point Transmission Line subprojects.

Environmental & Social Safeguard Unit – IESCO Page 28 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

5.3.2 Cut and fill and waste disposal

82. Disposal of surplus materials must also be negotiated through local authority approvals prior to the commencement of construction. The Subproject work should not involve any significant cutting and filling but minor excavations (down to 4m) and piling may be required to create the foundations for the towers. It is envisaged (depending on the mode of contract) that the surface under the towers will need to be scrabbled to remove unstable materials, or to stockpile topsoil.

83. Mitigation measures must focus on the minimization of impacts. In order to allow the proper functioning of the settlement sites (access to villages) during construction it is recommended that consideration be given to erect temporary hoardings immediately adjacent to the nearest houses and shops if they are within 15m of the power distribution line tower construction.

84. If surplus materials arise from the removal of the existing surfaces from specific areas, these should be used elsewhere on the subproject before additional soil, rock, gravel or sand is brought in. The use of immediately available material will generally minimize the need for additional rock based materials extraction from outside.

85. The subproject detailed designers have so far estimated that no substantial additional materials will be required subject to confirmation at the detailed design stage.

86. At this stage no areas require removal of woodland. However if specimen trees of religious plantations are affected the owners should be given the resources and opportunity to reinstate the woodland long term and a plantation compensation plan should be drawn up to replant the woodland/trees. In the event that the land is not suitable for plantation then other areas should be identified to replace the cut trees and sufficient areas should be identified to allow plantation of trees at a rate of say 3:1. The replacement ratio should allow for a high mortality rate among the newly planted trees in the dry environment or otherwise as based on advice from the forest authority.

87. Contractual clauses should be included to require each contractor to produce a materials management plan (one month before construction commences) to identify all sources of cement and aggregates and to balance cut and fill. The plan should clearly state the methods to be employed prior to and during the extraction of materials and all the mitigation measures to be employed to

Environmental & Social Safeguard Unit – IESCO Page 29 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

mitigate nuisances to local residents. Financial compensation shall not be allowed as mitigation for environmental impacts or environmental nuisance. Mitigation measures shall seek to control the impacts at source in the first place. The engineer shall be responsible to update the subproject cut and fill estimates and create Materials Master Plan to facilitate materials exchange between the different contract areas along the power line and sub-contractors on the power line and to provide an overall balance for materials and minimize impacts on local resources.

5.3.3 Trees, Ecology and Protected Areas

88. There are no Reserved or Protected Forests or trees near the TL alignment. The proposed 132 KV feeding transmission line for DGS will be required the construction of 40 towers which will be installed on the route disclosed by IESCO will not affect many trees. However, in case of removal of any tree on private or forest land during the works, written permission should be sought.

89. If for some unforeseen reason or change of alignment, any trees with religious significance or other trees need to be removed, written permission should be obtained from the forest authority and the owner after written justification by IESCO. Trees shall be planted to replace the lost trees with three trees planted to replace every cut tree (3:1) or more as agreed with the authority.

90. A requirement shall be inserted in the contracts that no trees are to be cut on the site of new 132kV Double Circuit Sang Jani – Zero Point transmission line subproject without the written permission from the supervising consultant who may permit the removal of trees if unavoidable on safety / technical / engineering grounds after written justification by IESCO and to the satisfaction of the forest authority and the owner.

5.3.4 Hydrology, Sedimentation, Soil Erosion

91. The drainage streams en-route of the subproject should not be impeded by the works. The scale of the works does not warrant hydrological monitoring.

5.3.5 Air Pollution from Earthworks and Transport

92. The material (cement, sand and aggregate) requirement of a typical 132 KV substation (about 150 cu m) and a 132 KV Transmission Tower (4.8 cu m, or 40 bags of cement per tower) are not large. In transmission line construction sand and aggregate are delivered directly to the tower location from the quarry / source, there is no intermediate or bulk storage of these materials .Similarly

Environmental & Social Safeguard Unit – IESCO Page 30 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

construction materials for the substation are stored within the substation site are scheduled as per the work progress (which is staggered as the buildings which require bulk of the construction materials are built in phases over 6 to 12 months period ), which means that at any given point in time the amount of construction material stored is not significant .The quantities of construction material required for a typical substation or transmission tower are not so large that they potentially represent a traffic hazard , these requirements are time dispersed in case of sub stations and time and space dispersed in case of transmission lines. Field observations indicate that ambient air quality is generally acceptable and that emissions from traffic and other powered mechanical equipment in the area are rapidly dispersed. There will be a few items of powered mechanical equipment to be used in the construction of the distribution line works that may give rise gaseous emissions. However these should be well dissipated. The major sources of complaint will likely be any necessary earthworks and local soil compaction.

93. Earthworks will contribute to increasing dust, and the foundation earthworks for the transformers and the line poles will generate dust and the following mitigation measures are needed:

Dust suppression facilities (water sprayers / hosepipe) shall be available where earth and cement works are required. Areas of construction (especially where the works are within 50m of the SRs) shall be maintained damp by watering the construction area. Construction materials (sand, gravel, and rocks) and spoil materials will be transported trucks covered with tarpaulins. Storage piles will be at least 30m downwind of the nearest human settlements All vehicles (e.g., trucks, equipment, and other vehicles that support construction works) shall be well maintained and not emit dark, smoky or other emissions in excess of the limits described in the NEQS. The need for large stockpiles should be minimized by careful planning of the supply of materials from controlled sources. Stockpiles should not be located within 50m of schools, hospitals or other public amenities such as wells and pumps and should be covered with tarpaulins when not in use and at the end of the working day to enclose dust.

5.3.6 Noise, Vibration and Blasting

94. It is anticipated that powered mechanical equipment and some local labour with hand tool methods will be used to construct the subproject works. No blasting is anticipated. Powered mechanical equipment can generate significant noise and vibration. The cumulative effects from several machines can be significant. To

Environmental & Social Safeguard Unit – IESCO Page 31 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

minimize such impacts, the contractor for subproject should be requested by the construction supervision consultants (engineer) to provide evidence and certification that all equipment to be used for construction is fitted with the necessary air pollution and noise dampening devices to meet NEQS requirements.

Table 5.1 National Environmental Quality Standards for Noise

Category of S No. Effective from 1st July, 2010 Effective from 1st July, 2012 Area/Zone

Limit in dB(A) Leq*

Day time Night time Day time Night time

1. Residential are (A) 65 50 55 45 2. Commercial area (B) 70 60 65 55 3. Industrial area (C) 80 75 75 65 4. Silence zone (D) 55 45 50 45 Note: i. Day time hours: 6 .00 am to 10.00 pm ii. Night Time hours: 10.00 pm to 6.00 am iii. Silence zone: Zones which are declared as such by the competent authority. An area comprising not less than 100 meters around hospitals, educational institutions and courts and courts. iv. Mixed categories of areas may be declared as one of the four above-mentioned categories by the competent authority. v. dB(A) Leq: time weighted average of the level of sound in decibels on scale A which is relatable to human hearing.

95. Noise will be monitored at a distance of 100m from the boundary wall of any residential unit and should follow the NEQS 45db(A)Leq. It is recommended that no construction should be allowed during night time (10PM to 6PM). Any noise equipment should be located within DGS or as far from SRs as possible to prevent nuisance to dwellings and other structures from operation. However, if the noise still exceeds NEQS then noise barriers will be installed around the equipment to reduce the effects of the noise.

96. Vibration from construction of piles to support pads may be required for some tower construction and may be a significant impact but this should be short duration. Where vibration could become a major consideration (within say 100m of schools, religious premises, hospitals or residences) a building condition survey should take place prior to construction. The physical effect of piling

Environmental & Social Safeguard Unit – IESCO Page 32 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

should be assessed prior to construction and measures should be discussed with the local population as well as timing of the works to serve as a vehicle for further public consultation at the implementation stage and to assist in public relations. At nearby schools, the contractor shall discuss with the school principals the agreed time for operating these machines and completely avoid machine use near schools during examination times, if such a need arises.

5.3.7 Sanitation, Solid Waste Disposal, Communicable Diseases

97. The main issues of concern are uncontrolled or unmanaged disposal of solid and liquid wastes into natural drains, improper disposal of storm water and black water and open defecation by construction workers.

98. In order to maintain proper sanitation around construction sites, access to the nearby GS lavatories should be allowed, provision of temporary toilets should be made. Construction worker camps will not not be located in settlement areas or near sensitive water resources and portable lavatories or at least pit latrines should be provided.

99. Wherever water is allowed to accumulate, in temporary drainage facilities, due to improper storm water management, or improper disposal of wastewater generated from the site, it can offer a breeding site for mosquitoes and other insects. Vectors such as mosquitoes may be encountered if open water is allowed to accumulate at the subproject site. Temporary and permanent drainage facilities should therefore be designed to facilitate the rapid removal of surface water from all areas and prevent the accumulation of surface water ponds.

5.4 Potential Environmental Impacts in Operational Phase

5.4.1 Air Pollution and Noise from the Enhanced Operations

100. The subproject works will extend the power distribution lines but no houses, mosques or schools will be close to the new TL in the operational phase. However, it is recommended that an acoustical check be made on the detailed design to determine of any noise barriers are required. There should be no source of atmospheric pollution from the subproject. In the operational phase any nearby industrial facilities with fuel powered mechanical equipment will be the main polluters. All such emissions will be very well dissipated in the open terrain and there will be no cumulative effect from the subproject.

101. Noise impacts from the operation of the DGS equipment should be reviewed at the detailed design stage. The NEQS for noise close to residential areas will be complied with 45dB(A) Leq (exterior, boundary of DGS).

Environmental & Social Safeguard Unit – IESCO Page 33 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

5.4.2 Pollution from Oily Run-off, Fuel Spills and Dangerous Goods

102. No significant impacts from oily residues such as transformer oil and lubricants are expected to arise in this subproject. However control measures will be needed for oily residues such as transformer oil and lubricants in the case of accidental or unexpected release. Transformer oil is supplied in drums from an imported source and tap tanks are topped up as necessary on site. There are facilities in some GS maintenance yards for recycling (dehydrating) oil from breakers. However the areas upon which these recycling facilities are located have no dedicated drainage which can capture run-off. Oily residues and fuel and any contaminated soil residues should be captured at source and refueling and maintenance should take place in dedicated areas away from surface water resources. Contaminated residues and waste oily residues should be disposed at a site agreed with the local authority.

103. The DISCO/IESCO procedures for handling PCB need to be strengthened the maintenance of transformers need to be based on the manufactures instructions. There need to be performance evaluation procedure prescribed and followed for each power transformer. In working areas where PCBs are handled, it is necessary to monitor the levels of chlorinated solvents. In case of emergencies the first step is to attempt to control the spread of the liquid, this is especially relevant during transportation. In case of spills, emergency measures need to be taken by the persons specially trained and wearing protective clothes. Oil absorptive materials are a useful tool and needs to be spread over the spill. All equipment and surfaces exposed to the spill need to be washed with solvent. The best international procedures and guidelines need to be followed; one such guideline is the UNEP PCB transformers and capacitors – Form Management to Reclassification and disposal, May 2002. This however, is not relevant as this IEE is related to the development and construction if a new substation and PEPCO/DISCOs have already banned the use of any equipment that uses PCB.

104. IESCO already prohibits use of PCBs in new power transformers, there is however, need to prepare an inventory of any PCB carrying equipment in the system and all such equipment be replaced. The maintenance instructions prepared by the Technical Services Group needs to be reviewed and revised to add PCB based equipment maintenance and a procedure for handling any PCB spills. The Kot Lakhpat and Shalimar workshops already follow. Such procedures, however, these need to be reviewed and upgraded in the light of best international practice. This would include provision of special clothing availability of oil absorptive solvents, availability of steel containers. Training to staff on oil spills and special care during transportation of equipment using PCB‘s is required. TSG ensure that the maintenance schedule of each piece of

Environmental & Social Safeguard Unit – IESCO Page 34 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

hardware is adhered to DISCOs have also established a safety unit, which among other tasks, investigates all accidents .Frequency of accidents, on average is about 1 per DISCO per year (based on last 4 years record), about 60 % of these are non- fatal .Most accidents occur due to staff and supervision negligence .Detailed report of each accident is prepared.

5.4.3 Enhancement

105. Environmental enhancements are not a major consideration within the site of new 132kV Double Circuit Sang Jani – Zero Point transmission line subproject. However it is noted that it is common practice at many such sites to create some local hard and soft landscaping and successful planting of fruit trees and shrubs has been accomplished in many sites. This practice should be encouraged as far as practicable. Other opportunities for enhancements can be assessed prior to construction and proposed enhancements should be discussed with the local population to serve as a vehicle for further public consultation at the implementation stage and to assist in public relations. Trees removed for construction purposes should be replaced as compensation in line with best practice at ratio of three replaced for one removed however additional trees should be planted as enhancements where there is space along the TL.

Environmental & Social Safeguard Unit – IESCO Page 35 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

6. INSTITUTIONAL REQUIREMENTS & ENVIRONMENTAL MANAGEMENT PLAN

106. In this section, the mitigation measures that are required for the construction of 132 KV D/C Sang Jani – Zero Point Transmission Line subprojects under Tranche III subproject, to reduce residual impact to acceptable levels and achieve the expected outcomes of the project, are discussed. The Environmental Management Plan is based on the type, extent and duration of the identified environmental impacts for the under study tranche III sub-project. The EMP has been prepared following best practice and by reference to the ADB Environmental Guidelines 2011.

107. It is important that the recommendations and mitigation measures are carried out according to the spirit of the environmental examination process and in line with the guidelines. The EMP matrix is presented as Table 6.1. The impact prediction (Section 5) has played a vital role in reconfirming typical mitigation measures and in identifying any different approaches based on the feasibility and detailed design assumptions and any alternatives available at this stage.

108. Prior to implementation and construction of the sub-projects the EMP shall be reviewed by the IESCO and amended, if and as required, after detailed designs are complete. Such a review shall be based on reconfirmation and additional information on the assumptions made at the feasibility stage on positioning, alignment, location scale and expected operating conditions of the sub-projects. For example, in this case if there are any additional transmission lines or extension of the sub-station boundaries to be included, the designs may be amended and then the performance and evaluation schedules to be implemented during project construction and operation can be updated, and costs estimates can be revised. The EMP of IEE should than be revised on a sub-project by sub- project basis.

109. The EMP of IEE, must be reviewed by the project management and approved by the PEPA before any construction activity is initiated. This is also an ADB requirement in order to take account of any subsequent changes and fine tuning of the proposals. It is recommended that before the works contract is worked out in detail and before pre-qualification of contractors that the full extent of the environmental requirements for the subproject(s) and the IEE and EMP are included in the bidding documents. Past environmental performance of contractors and awareness of environmentally responsible procurement should also be used as indicators for prequalification of contractors.

Environmental & Social Safeguard Unit – IESCO Page 36 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

110. In order to facilitate the implementation of the EMP, during the preparation for the construction phase the IESCO must prepare the future contractors to co- operate with all stakeholders in the mitigation of impacts. Furthermore the contractor must be primed through the contract documentation and ready to implement all the mitigation measures. The effective implementation of the EMP will be audited as part of the midterm review of loan conditions and the executing agency must prepare for this at the inception stage.

111. The details of EMP given in the Table 6.1 are for the new 132kV Double Circuit Sang Jani – Zero Point transmission line subproject. The EMP matrix will have much in common for many other Tranche-III substation and line projects that have a similar scale of works and types of location but will be different for more complicated substation and line projects that involve impacts to land outside the existing substations and for lines traversing more sensitive land. In all cases separate dedicated IEEs must be prepared.

112. The impacts have been classified into those relevant to the design/preparation stage, construction stage and operation and maintenance stage. The matrix provides details of the mitigation measures recommended for each of the identified impacts, time span of the implementation of mitigation measures, an analysis of the associated costs and the responsibility of the institution. The institutional responsibility has been specified for the purpose of the implementation and the supervision. The matrix is supplemented with a monitoring plan (Appendix IB) for the performance indicators. An estimation of the associated costs for the monitoring is given with the plan. The EMP has been prepared following best practice and the ADB environmental examination guidelines 2011.

113. Prior to implementation of the subproject the IESCO needs to comply with several environmental requirements, such as submitting and EIA/IEE to PEPA and obtaining PEPA clearance (―No Objection Certificate‖ compiling acceptable EMP and Clearance Certificate) under PEPAct (guidelines and regulations 2000) and any other permissions required from other authorities. IESCO will also need to confirm that contractors and their suppliers have complied with all statutory requirements and have appropriate and valid licenses and permits for all powered mechanical equipment and to operate in line with local authority conditions.

114. The EMP (Table 6.1) is prepared taking into account the capacity of IESCO Environmental & Social Safeguard (E&SS) Unit. Presently, the E&SS Unit has one Environmental and one Social Impact expert under the supervision of a Deputy Manager Environmental and Social Safeguard (E&SS). The IESCO has shown

Environmental & Social Safeguard Unit – IESCO Page 37 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

much commitment to developing in-house environmental and social capability. It is envisaged that experience in this field should therefore develop in the near future. However it is also strongly recommended that for subprojects in future Tranches that the IESCO be prepared to engage more support where necessary to guide the subsequent formal assessment and submission process under the PEPAct and monitor compliance with the EMP.

115. The E&SS Unit has a good level of awareness and are responsible for addressing environmental concerns for subprojects. Whereas some of their work may in future be delegated to consultants they will need more training and resources if they are effectively provide quality control and oversight for the EMP implementation. They will require robust support from senior management staff members and the management consultant if they are to address all environmental concerns for the subprojects effectively. Specific areas for immediate attention are in EMP auditing, environmentally responsible procurement, air, water and noise pollution management and ecological impact mitigation.

116. It is also recommended that IESCO Board allow direct reporting to Board level from the in-house Environment and Social Safeguard section (E&SS). If the E&SS requires resources for larger subprojects then environmental specialist consultants could be appointed through the project implementation unit to address all environmental aspects in the detailed design. It is recommended that the project management unit (PMU) should liaise directly with the E&SS to address all environmental aspects in the detailed design and contracting stages. The graduate environmental manager will cover the implementation of environmental mitigation measures in the project packages.

117. Overall implementation of the EMP will become IESCO‘s responsibility (Appendix IC). IESCO and other parties to be involved in implementing the EMP are as follows:

 Contractors: responsible for carrying out the contractual obligations, implementing all EMP measures required to mitigate environmental impacts during construction;

 The IESCO Board of Directors will be responsible to ensure that sufficient timely resources are allocated to process the environmental examinations and to monitor implementation of all construction and operational mitigation measures required to mitigate environmental impacts, and

 Other government agencies such as the regional PEPA and state pollution authorities, Department of Forests, Department of Wildlife Services, who will be

Environmental & Social Safeguard Unit – IESCO Page 38 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

responsible for monitoring the implementation of environmental conditions and compliance with statutory requirements in their respective areas and local land use groups at the local levels.

118. Considering that other government agencies that need to be involved in implementing the EMP, training or harmonization workshops should be conducted for all Environment and Social Units (E&SSs) in all DISCOS to share the monitoring report on the implementation of the EMP in each DISCO and to share lessons learned in the implementation and to achieve a consistent approach decide on remedial actions, if unexpected environmental impacts occur.

119. The Monitoring Plan (Appendix IA) was designed based on the project cycle. During the preconstruction period, the monitoring activities will focus on (i) checking the contractor‘s bidding documents, particularly to ensure that all necessary environmental requirements have been included; and (ii) checking that the contract documents‘ references to environmental mitigation measures requirements have been incorporated as part of contractor‘s assignment and making sure that any advance works are carried out in good time. Where detailed design is required (e.g. for power distribution lines and avoidance of other resources) the inclusion and checking of designs must be carried out. During the construction period, the monitoring activities will focus on ensuring that environmental mitigation measures are implemented, and some performance indicators will be monitored to record the Subprojects environmental performance and to guide any remedial action to address unexpected impacts.

120. Monitoring activities during project operation will focus on recording environmental performance and proposing remedial actions to address unexpected impacts. The potential to use local community group‘s contacts for monitoring should be explored as part of the activities in setting up the Environmental and Social Safeguard section which should have regular meetings with the NGOs as a matter of good practice and to discuss matters of mutual concern.

121. At this stage, due to the modest scale of the new power distribution projects and by generally keeping to non-sensitive and non-critical areas the construction and operational impacts will be manageable. No insurmountable impacts are predicted providing that the EMP is implemented to its full extent and required in the contract documents. However experience suggests that some contractors may not be familiar with this approach or may be reluctant to carry out some measures. In order that the contractors are fully aware of the implications of the EMP and to ensure compliance, it is recommended that environmental measures

Environmental & Social Safeguard Unit – IESCO Page 39 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

be coasted separately in the tender documentation and that payment milestones are linked to environmental performance, vis a vis the carrying out of the EMP.

122. The effective implementation of the EMP will be audited as part of the loan conditions and the executing agency must be prepared for this. In this regard the IESCO (the IA) must be prepared to guide the design engineers and contractors on the environmental aspects.

Environmental & Social Safeguard Unit – IESCO Page 40 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Table 6.1: SUMMARY ENVIRONMENTAL MANAGEMENT PLAN (Matrix)

Environmental Timing to implement Locations to Resp Imp Resp mon Objectives Mitigation Measures recommended concern MM implement MM MM MM DESIGN STAGE Before the 1. Ensure that minimal flora is damaged commencement of To minimize damage Flora and Fauna 1. Flora and Fauna 2. Ensure that fauna especially bird nesting‘s are not construction ES SMEC ES IESCO to flora and fauna sensitive locations damaged activities/during design stage If lines or substation Before the ES IESCO To minimize 1. Hydrological flow in areas where it is sensitive, such as are relocated near commencement of with the ES 2. Hydrological hydrological and water courses or bridges and culverts. water courses, construction SMEC ES IESCO Impacts drainage impacts 2. Design of adequate major and minor culverts facilities culverts or bridges in activities/during (Design during constructions. will be completed the design stage design stage Consultant) reports 1. Conduct detailed acoustic assessment for all residential, 1. During detailed school, (other sensitive structures) within 50m of DGS and design stage. No later Ensure cumulative line. Noise sensitive ES IESCO than pre-qualification noise impacts are 2. If noise at sensitive receiver exceeds the permissible locations identified in with the ES ES IESCO or tender 3. Noise barriers acceptable in limit, the construction activities should be mitigated, the IEE/EIA/EMP or SMEC and ES negotiations. construction and monitored and controlled. as required / (Design SMEC 2. Include acoustic operational phase. 3. If noise at sensitive receiver exceeds the permissible approved by PEPA. Consultant) specification in the limit, the design to include acoustic mitigation (noise contract. barrier or relocation of noisy equipment) and monitoring. 1. Create waste management policy and plan to identify Ensure adequate sufficient locations for, storage and reuse of transformers disposal options for and recycling of breaker oils and disposal of transformer 1.Prior to detailed ES IESCO IESCO ESU. Locations all waste including oil, residually contaminated soils and scrap metal ―cradle design stage no later with the ES ES IESCO approved by EPA and 4. Waste disposal transformer oil, to grave‖. than pre-qualification SMEC with the IESCO and local waste residually 2. Include in contracts for unit rates for re-measurement or tender negotiations (Design ES SMEC disposal authorities. contaminated soils, for disposal. 2. Include in contract. Consultant) scrap metal. 3. Designate disposal sites in the contract and cost unit disposal rates accordingly. 5. Temporary Include mitigation in 1. Identify locations where drainage or irrigation crossing During designing Locations based on ES IESCO ES IESCO drainage and preliminary designs RoW may be affected by works. stage no later than drainage or irrigation with the ES with the

Environmental & Social Safeguard Unit – IESCO Page 41 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Environmental Timing to implement Locations to Resp Imp Resp mon Objectives Mitigation Measures recommended concern MM implement MM MM MM erosion control for erosion control 2. Include protection works in contract as a payment pre-qualification or crossing RoW near SMEC ES SMEC and temporary milestone(s). tender negotiations. DGS. drainage. Include EMP Matrix in tender documentation and make contractors responsible to implement mitigation measures Ensure requirements During tender by reference to EIA/IEE in contract. and preparation. Noise sensitive Include preparation of EMP review and method statement recommendations of No later than pre- locations identified in ES IESCO ES IESCO WM plan, TD and EC Plan in contract as a payment 6. Contract clauses environmental qualification or the IEE/EIA/EMP or with the ES with the milestone(s). assessment are tender negotiations as required / SMEC ES SMEC Require environmental accident checklist and a list of included in the In bidding documents approved by PEPA. controlled chemicals / substances to be included in the contracts. as evaluation criteria. contractor‘s work method statement and tender documentation. CONSTRUCTION STAGE Prepare a thorough drainage 1. Locations of each management plan to construction activity be approved by CSC to be listed by the CSC 1. Consideration of weather conditions when particular one month prior to a To ensure the proper engineer. construction activities are undertaken. commencement of implementation of 2. Special locations are 2. Limitations on excavation depths in use of recharge construction any requirements identified on the site areas for material exploitation or spoil disposal. ES SMEC Hydrology And mentioned in EPA by the contractor to ES 3. Use of landscaping as an integrated component of Proper timetable and Drainage Aspects conditions of minimize Contractor construction activity as an erosion control measure. prepared in ES IESCO approval letter in disturbances. 4. Minimizing the removal of vegetative cover as much as consideration with relation to Hydrology 3. A list of locations of possible and providing for it s restoration where the climatic of the project. irrigation channels / construction sites have been cleared of such areas. conditions of the area, drains to be compiled the different and included in the construction activities contract. mentioned here to be guided. 2. Orientation for To ensure that the 1. IESCO ESU environmental specialist to monitor and Induction course for All staff members in IESCO ES, ES IESCO Contractor, and CSC contractor and progress all environmental statutory and recommended all site agents and all categories. Monthly Contractor with the Workers workers understand obligations. above including all induction and six and ES ES SMEC .

Environmental & Social Safeguard Unit – IESCO Page 42 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Environmental Timing to implement Locations to Resp Imp Resp mon Objectives Mitigation Measures recommended concern MM implement MM MM MM and have the capacity relevant IESCO staff month refresher SMEC to ensure the 2 Conduct special briefing for managers and / or on-site / new project staff course as necessary environmental training for the contractors and workers on the before until contractor requirements and environmental requirement of the project. Record commencement of complies. implementation of attendance and achievement test for contractors site work. mitigation measures. agents. At early stages of 3. Agreement on critical areas to be considered and construction for all necessary mitigation measures, among all parties who are construction involved in project activities. employees as far as reasonably 4. Continuous progress review and refresher sessions to practicable. be followed. Compile temporary drainage management plan one month before commencement of works. 1. Proper installation of temporary drainage and erosion control before works within 50m of water bodies. 2. Proper maintenance and management construction of

To prevent adverse TD and EC measures, including training of operators and 1.ES

water quality impacts other workers to avoid pollution of water bodies by the Contractor

due to negligence and considerate operation of construction machinery and

ensure unavoidable equipment. 2. Contractor

impacts are managed 3. Storage of lubricants, fuels and other hydrocarbons in has to check

3. Water quality effectively. Ensure self-contained dedicated enclosures >50m away from 1. 50m from water water

adverse impacts on water bodies. bodies 2. Relevant quality and ES SMEC water quality caused 4. Proper disposal of solid waste from construction 1 month prior to locations to be report to and ES by construction activities. construction. determined in the IESCO. IESCO activities are 5. Cover the construction material and spoil stockpiles detailed project review minimized. with a suitable material to reduce material loss and design. results sedimentation and avoid stockpiling near to water bodies. 6. Topsoil stripped material shall not be stored where natural drainage will be disrupted. 7. Borrow sites (if required) should not be close to sources of drinking water.

Environmental & Social Safeguard Unit – IESCO Page 43 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Environmental Timing to implement Locations to Resp Imp Resp mon Objectives Mitigation Measures recommended concern MM implement MM MM MM CONTROL ALL DUSTY MATERIALS AT SOURCE. 1. All heavy equipment and machinery shall be fitted in full compliance with the national and local regulations.(Relevant regulations are in the Motor vehicles fitness rules and Road Act). 1.Construction sites Contractor 2. Stockpiled soil and sand shall be slightly wetted before within 100m of should To minimize dust loading, particularly in windy conditions. sensitive receivers. maintain effectively and avoid 3. Fuel-efficient and well-maintained haulage trucks shall 2. A list of locations to acceptable IESCO ES complaints due to the be employed to minimize exhaust emissions. During all be included in 4. Air quality standard. / ES airborne particulate 4. Vehicles transporting soil, sand and other construction construction. contract and other SMEC matter released to the materials shall be covered. Limitations to speeds of such sensitive areas ES SMEC to atmosphere. vehicles necessary. Transport through densely populated identified by the CSC supervise area should be avoided. along the ROW during activities. 5. To plan to minimize the dust within the vicinity of works. orchards and fruit farms. 6. Spraying of bare areas with water. 7. Concrete plants. to be controlled in line with statutory requirements should not be close to sensitive receptors. 1.Construction sites Contractor 1. Review requirements for piling and use of powered within 100m of should mechanical equipment within 100m of SRs. sensitive receivers. maintain the 2. Review conditions of buildings and conduct public acceptable consultation with SRs to establish less sensitive time for To minimize ground 2. A list of locations to standards IESCO ES 5. Ground works involving piling and schedule works accordingly. 1 month prior to vibrations during be included in / SMEC Vibration 3. Non-percussive piling methods to be used wherever construction. construction. contract and other ES practicable. sensitive areas ES SMEC to 4. Percussive piling shall be conducted in daylight hours. identified by the CSC supervise 5. Hammer- type percussive pile driving operations shall along the ROW during relevant not be allowed at night time. works. activities. 1. Review requirements for use of powered mechanical 1.Construction sites Contractor To minimize noise equipment within 100m of SRs. within 100m of should 1 month prior to IESCO ES 6. Noise increases during 2. Conduct public consultation with SRs to establish less sensitive receivers. maintain the construction. / SMEC construction. sensitive time for works and schedule works accordingly. acceptable 3. All heavy equipment and machinery shall be fitted in 2. A list of locations to standards

Environmental & Social Safeguard Unit – IESCO Page 44 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Environmental Timing to implement Locations to Resp Imp Resp mon Objectives Mitigation Measures recommended concern MM implement MM MM MM full compliance with the national and local regulations be included in and with effective silencing apparatus to minimize noise. contract and other 4. Heavy equipment shall be operated only in daylight sensitive areas ES SMEC to hours. identified by the CSC supervise 5. Construction equipment, which generates excessive along the ROW during relevant noise, shall be enclosed or fitted with effective silencing works. activities. apparatus to minimize noise. 7. Well-maintained haulage trucks will be used with speed controls. 8. Contractor shall take adequate measures to minimize noise nuisance in the vicinity of construction sites by way of adopting available acoustic methods. SCHEDULE WORKS IN SENSITIVE AREAS (e.g. NEAR RIVERS) FOR DRY SEASON 1. Locations based on 1. In the short-term, temporary drainage and erosion history of flooding control plan to be presented with tender. Temporary problems indicated by Prevent adverse drainage and erosion control plan one month before local authorities. water quality impacts commencement of works to protect all areas susceptible to due to negligence and 1 month prior to erosion. (Permanent drainage works shall be in the final 2. A list of sensitive ensure unavoidable construction because design). areas during impacts are managed the area can be 2. Installation of TD and EC before works construction construction to be effectively. subject to unseasonal within 50m of water bodies. prepared by the detail ES heavy rain Plan IESCO ES 7. Soil Erosion / 3. Clearing of green surface cover to be minimized during design consultant in Contractor To minimize soil before and during / Surface Run-off site preparation. consideration with the and ES erosion due to the construction (cut and SMEC ES 5. Meaningful water quality monitoring up and cut and fill, land SMEC construction activities fill, land reclamation downstream at any tower site during construction within reclamation, borrow of towers, stringing of etc.) while a river or stream bed. Rapid reporting and feedback to areas etc. conductors and considering the CSC. creation of access climatic conditions. 5. Back-fill should be compacted properly in accordance 3. Locations of all tracks for project with IESCO design standards and graded to original rivers, streams, vehicles. contours where possible. culverts, irrigation 6. Cut areas should be treated against flow acceleration channels, roads and while filled areas should be carefully designed to avoid roads. improper drainage.

Environmental & Social Safeguard Unit – IESCO Page 45 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Environmental Timing to implement Locations to Resp Imp Resp mon Objectives Mitigation Measures recommended concern MM implement MM MM MM 7. Stockpiles should not be formed within such distances behind excavated or natural slopes that would reduce the stability of the slopes or cause slippage. 8. Measures shall be taken to prevent ponds of surface water and scouring of slopes. Newly eroded channels shall be backfilled and restored to natural contours. 9. Contractor should arrange to monitor and adjust working and adopt suitable measures to minimize soil erosion during the construction period. Contractor‘s TD and EC plan should be endorsed and monitored but CSC after consulting with concerned. authorities. 10. Replanting trees to be done before the site is vacated and handed back to IESCO with appropriate trees (other vegetation cover as appropriate) to ensure interception of rainwater and the deceleration of surface run-off. (consider also for future trances if civil works) 1. Use only EPA licensed sites for raw materials in order 1. List of borrow areas To minimize to minimize adverse environmental impacts. to be prepared with disruption and 2. Measures to be taken in line with any EPA license tender stage contamination of the conditions, recommendations and approval to be applied contractors method surroundings, to the subproject activities using the licensed source statement and minimize and or including: updated one month 8. Exploitation, avoid adverse Conditions that apply for selecting sites for material prior to construction. ES Handling, environ-mental exploitation. month prior to 2.List of routes of Contractor IESCO ES Transportation impacts arising out of Conditions that apply to timing and use of roads for starting of works. transport of and SMEC to / SMEC and Storage of construction material material transport. Update monthly. construction material agree format ES Construction exploitation, Conditions that apply for maintenance of vehicles used in is to be prepared for of reporting materials handling, material transport or construction. the contract and transportation and Conditions that apply for selection of sites for material agreed one month storage by using storage. prior to construction. sources that comply Conditions that apply for aggregate production. 3. Map of locations of with EPA license Conditions that apply for handling hazardous or storage is prepared by conditions dangerous materials such as oil, lubricants and toxic the contractor. chemicals.

Environmental & Social Safeguard Unit – IESCO Page 46 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Environmental Timing to implement Locations to Resp Imp Resp mon Objectives Mitigation Measures recommended concern MM implement MM MM MM 1. Waste management plan to be submitted to the CSC and approved by IESCO ESU one month prior to starting of works. WMP shall estimate the amounts and types of construction and decommissioning waste to be generated by the project. 2. Investigate ways and means of reusing/recycling decommissioned material from the project within PEPCO 1.Dumping: without any residual environmental impact. A list of temporary 3 Identifying potential safe disposal sites close to the stockpiling areas and 1.Contractor project, or those designated sites in the contract. One month prior to more permanent 2. SMEC ES 4 Investigating the environmental conditions of the starting of works. dumping areas to be and IESCO disposal sites and recommendation of most suitable and Update monthly prepared at the ESU should safest sites. contract stage for supervise 5. Piling up of loose material should be done in agreement and take segregated areas to arrest washing out of soil. Debris shall action to 9.Decommision Minimize the impacts not be left where it may be carried by water to ensure that IESCO/ and Waste from the disposal of downstream flood plains, dams, lagoons or other water contractor‘s ES SMEC Management construction waste. bodies. complete 6. Used oil and lubricants shall be recovered and reused relevant or removed from the site in full compliance with the A list of temporary activities national and local regulations. stockpiling areas and according to 7. Oily wastes must not be burned. Disposal location to be One month prior to more permanent EIA / IEE / agreed with local authorities/EPA. starting of works. dumping areas to be EMP 8. Waste breaker insulating oil to be recycled, Update monthly prepared at the requirement reconditioned, or reused at DISCO‘s facility. contract stage for & NEQS. 9. Machinery should be properly maintained to minimize agreement (in W M oil spill during the construction. Plan) 10. Machinery should be maintained in a dedicated area over drip trays to avoid soil contamination from residual oil spill during maintenance. 11 Solid waste should be disposed at an approved solid waste facility and not by open burning which is illegal and contrary to good environmental practice. 10. To ensure that the 1. Identify location of work camps in consultation with UPDATE Once a Location Map is Contractor IESCO Work Camp

Environmental & Social Safeguard Unit – IESCO Page 47 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Environmental Timing to implement Locations to Resp Imp Resp mon Objectives Mitigation Measures recommended concern MM implement MM MM MM Operation and operation of work local authorities. The location shall be subject to approval month prepared by the ESU / Location camps does not by the IESCO. If possible, camps shall not be located near Contractor. CSC (if required) adversely affect the settlements or near drinking water supply intakes. surrounding 2. Cutting of trees shall not b permitted and removal of environment and vegetation shall be minimized. residents in the area. 3. Water and sanitary facilities (at least pit latrines) shall be provided for employees. Worker camp and latrine sites to be backfilled and marked upon vacation of the sites. 4. Solid waste and sewage shall be managed according to the national and local regulations. As a rule, solid waste must not be dumped, buried or burned at or near the project site, but shall be disposed of to the nearest sanitary landfill or site having complied with the necessary permits of local authority permission. 5. The Contractor shall organize and maintain a waste separation, collection and transport system. 6. The Contractor shall document that all liquid and solid hazardous and non-hazardous waste are separated, collected and disposed of according to the given requirements and regulations. 7. At the conclusion of the project, all debris and waste shall be removed. All temporary structures, including office buildings, shelters and toilets shall be removed. 8 Exposed areas shall be planted with suitable vegetation. 9.IESCO and Construction Supervising Consultant shall inspect and report that the camp has been vacated and restored to pre-project conditions. To avoid negative Tree location and condition survey to be completed one Tree survey to be 11. Loss of Trees Route design and site impacts due to month before tender. completed one month and Vegetation identification (1 & 2) removing of The route for the distribution line should be selected so as before tender at SMEC ES IESCO ES Cover of the Areas during design stage landmark, sentinel to prevent the loss or damage to any orchard trees or relevant Locations and ES / SMEC for Towers and and other matters and specimen trees as other trees. Use of higher towers to be preferred to avoid with a Map to be Contractor ES Temporary Work- during construction well as green trees cutting. compiled prior to space of relevant activities vegetation and Clearing of green surface vegetation cover for tender by the design

Environmental & Social Safeguard Unit – IESCO Page 48 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Environmental Timing to implement Locations to Resp Imp Resp mon Objectives Mitigation Measures recommended concern MM implement MM MM MM surface cover. construction, borrow of soil for development, cutting trees consultant / IESCO and other important vegetation during construction ESU during detailed should be minimized by careful alignment. Written design and CSC to technical Justification for tree felling included in tree update as necessary. survey. At completion all debris and waste shall be removed and not burned. The contractor‘s staff and labour will be strictly directed not to damage any vegetation such as trees or bushes outside immediate work areas. Trees shall not be cut for fuel or works timber. Land holders will be paid compensation for their standing trees in accordance with prevailing market rates (LARP). The land holders will be allowed to salvage the wood of the affected trees. The contractor will plant three (3) suitable new trees outside the 30 meter corridor of the transmission line in lieu of one (1) tree removed. Landscaping and road verges to be re-installed on completion. Compensatory planting of trees/shrubs/ornamental plants (at a rate of 3:1) in line with best international practice. After work completion all temporary structures, including office buildings, shelters and toilets shall be removed. Providing induction safety training for all staff adequate warning signs in health and safety matters, and require 12. Safety Prior to Location to be ES To ensure safety of the workers to use the provided safety equipment. ES Precautions for the commencement and identified by the CSC IESCO/ workers Contractor Workers during construction with contractor. ES SMEC Providing workers with skull guard or hard hat and hard toe shoes. Minimize disturbance Submit temporary haul and access routes plan one month Prior to and The most important IESCO 13. ES of vehicular traffic prior to start of works. throughout the locations to be ESU / Traffic Condition Contractor and pedestrians Routes in vicinity of schools and hospitals to be avoided. construction. identified and listed. CSC

Environmental & Social Safeguard Unit – IESCO Page 49 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Environmental Timing to implement Locations to Resp Imp Resp mon Objectives Mitigation Measures recommended concern MM implement MM MM MM during haulage of Relevant plans of the construction Contractor on traffic materials and arrangements to be equipment. made available. Potential for spread of vector borne and communicable diseases from labour camps shall be avoided (worker To ensure minimum awareness orientation and appropriate sanitation should impacts from be maintained). Complaints of public ES All subprojects all 14.Social Impacts construction labour Complaints of the people on construction nuisance / to be solved as soon Contractor ES IESCO tranches force. on public damage close to ROW to be considered and responded to as possible ES IESCO health. promptly. Contractor should make alternative arrangements to avoid local community impacts. Awareness training Capacity building activities were taken by Environmental for all management To ensure that IESCO Initiate 15. Institutional Officer in Tranche 1. Environmental Management Unit and senior staff in officials are trained to preconstruction and IESCO & Strengthening and (EMU) was setup with in IESCO under Director IESCO at senior IESCO ESU understand and to continue beyond ADB Capacity Building Operations in Tranche 1. Development of strengthening engineer and above in appreciate EMP project completion. plan for the EMU should be taken up with resources. PMU and related units. OPERATIONAL STAGE Minimize air quality No significant Impacts Tranche 1.Monitor designs and all subprojects in ES IESCO IESCO 1. Air Quality Operational phase impacts plans for all future tranches. future tranches ESU Minimize noise No significant Impacts Tranche 1. Acoustic designs Operational phase all subprojects in ES IESCO IESCO 2.Noise impacts checking and plan for all future tranches. future tranches ESU Minimize improper Continue waste management arrangements in operational Operational phase all subprojects in ES IESCO IESCO 3. Waste disposal waste disposal phase of all subprojects and IESCO activities. future tranches ESU Employ landscaping contractor to monitor, water and Operational phase ES IESCO IESCO 3. Compensatory Maintain survival of all subprojects in feed replacement saplings and replace dead specimens as ESU tree planting trees planted future tranches necessary. Avoid landslips and Operational phase ES IESCO IESCO 4.Land slides and No significant Impacts in Tranche 1. Review designs all subprojects in loss of productive ESU soil erosion checking and plan for all future tranches. future tranches land 5. Water quality Minimize water No significant Impacts in Tranche 1. Review designs Operational phase all subprojects in ES IESCO IESCO

Environmental & Social Safeguard Unit – IESCO Page 50 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Environmental Timing to implement Locations to Resp Imp Resp mon Objectives Mitigation Measures recommended concern MM implement MM MM MM quality impacts checking and plan for all future tranches. future tranches ESU Monitor impacts from Operational phase ES IESCO IESCO 6 Crops and maintaining tree all subprojects in ESU Track growth of large trees under the conductors. vegetation clearance under future tranches transmission lines Ensure no Operational phase IESCO encroachments / Necessary signboards with limits of height clearances to ESU 7. Social safety construction under be placed all along the line. all subprojects in ES IESCO Impacts the transmission line. Identify and prevent any illegal encroachments under the future tranches No violation of DXLs.. clearance spaces.

ADB = Asian Development Bank, AP = affected people, DDS = detailed design stage, EIA = Environmental Impact Assessment, EMP= environmental management action plan, EPA= Environmental Protection Agency, = Environmental and Social Implementation , GSS = Grid Substation, IOL = Inventory of Losses, LAC = Land Acquisition Collector, LARP = land acquisition and resettlement plan, MM = mitigating measure, NGO = nongovernment organization, PCB = Polychlorinated Biphenyls, PEPAct = Pakistan Environmental Protection Act 1997 (as regulated and amended), REA = Rapid Environmental Assessment, ROW = right of way, RRP = Report and Recommendation of the President, SF6 = sulfur hexafluoride, SR = sensitive receiver, TD = temporary drainage, VDC = Voluntary District Committee, WB = World Bank. Notes: Based on EIA/IEE reports to be revised at DDS, RAP, SIA and other engineering considerations may change.

Environmental & Social Safeguard Unit – IESCO Page 51 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

7. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

7.1 Approach to Public Consultation

123. The public consultation (PC) process with various stakeholders has been approached so as to involve public and other stakeholders from the earliest stages. Public consultation has taken place during the planning and design and viewpoints of the stakeholders have been taken into account and their concerns and suggestions for possible improvements have been included where appropriate. Much of the PC process to date has revolved around concerns for the mitigation of construction impacts and the possible side effects from the proximity of high voltage power lines and its equipment.

124. There is also a requirement for ongoing consultation for land acquisition and resettlement plan (LARP). In this case Resettlement Plan (RP) is documented separately. It is expected that this process will continue through all stages of the subproject in order to accommodate stakeholders' aspirations and to orient the stakeholders positively towards the project implementation and where possible to harness cooperation over access issues in order to facilitate timely completion.

7.2 Public Consultation Process

125. The public consultation process has commenced in the initial feasibility stages (prior to construction) in order to disclose the project information to the stakeholders and record feedback regarding the proposed project and preferences. The stakeholders involved in the process were the population likely to be impacted along the route of the proposed power lines; the village leaders and school teachers.

126. Prior to the implementation of the consultation, feedback, etc. has been carried out to support this IEE and recorded. The focus of attention has been the population near the proposed TL that may be affected by the Subproject implementation. The level of engagement varied from the stakeholder to stakeholder with some registering no major comment but it is noted that none registered any outright opposition to the subproject.

127. The disclosure of the enhancement project in advance and subsequent consultation with stake holders has advantages in the environmental examination and mitigation of impacts. Public consultation can also provide a conduit for the improvement of the project implementation to better serve the stakeholders.

Environmental & Social Safeguard Unit – IESCO Page 52 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

128. The environmental examination process under the Pakistan Environmental Protection Act only requires the disclosure to the public after the statutory IEE / EIA has been accepted by the relevant EPA to be in strict adherence to the rules. In this IEE the consultation process was performed to satisfy the ADB requirements. The locations of consultation and people consulted are listed in the full table of public consultation (male & female) presented in Appendix II.

7.3 Results of Public Consultation

129. The consultations identified some potential environmental and social impacts and perceptions of the affected communities. The male and female public consultation resulted in 18 responses in September 19 & 20, 2012 (Appendix II). The community generally supports the construction of the TL. The local poor people predominantly requested for unskilled and semi-skilled jobs on priority basis with the contractors during implementation of the project. No land acquisition and resettlement is involved in this subproject. However, compensation will be paid to the concerned parties / owners of land under the towers and where the loss of some trees and for damage to crops is expected.

130. On the basis of the consultations so far, it appears that the project will have no insurmountable environmental and social impacts but IESCO will have to make sure that compensation and assistance amounts are assessed justly and that skilled and unskilled employment should be preferentially given to the AP as far as is reasonably practicable.

7.4 Grievance Redress Mechanism

131. In order to receive and facilitate the resolution of affected peoples‘ concerns, complaints, and grievances about the project‘s environmental performance an Environmental Grievance Redress Mechanism (GRM) will be established the project. The mechanism will be used for addressing any complaints that arise during the implementation of projects. In addition, the GRM will include a proactive component whereby at the commencement of construction of each project (prior to mobilization) the community will be formally advised of project implementation details by Environment Specialist of DISCO, Environment Specialist of SMEC, the design and supervision consultant (DSC) and Environmental Specialist of the contractor (designs, scheduled activities, access constraints etc) so that all necessary project information is communicated effectively to the community and their immediate concerns can be addressed. This proactive approach with communities will be pursued throughout the implementation of each project.

Environmental & Social Safeguard Unit – IESCO Page 53 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

132. The GRM will address affected people's concerns and complaints proactively and promptly, using an understandable and transparent process that is gender responsive, culturally appropriate, and readily accessible to all segments of the affected people at no costs and without retribution. The mechanism will not impede access to the Country‘s judicial or administrative remedies.

7.5 Redress Committee, Focal Points, Complaints Reporting Recording and Monitoring 133. The Grievance Redress Mechanism, which will be established at each project level is described below:

134. EA will facilitate the establishment of a Grievance Redress Committee (GRC) and Grievance Focal Points (GFPs) at project location prior to the Contractor‘s mobilization to site. The functions of the GRC and GFPs are to address concerns and grievances of the local communities and affected parties as necessary.

135. The GRC will comprise representatives from local authorities, affected parties, and other well-reputed persons as mutually agreed with the local authorities and affected persons. It will also comprise the Contractor‘s Environmental Specialist, SMEC‘s Environmental Specialist and PIU Safeguards/Environmental specialist. The role of the GRC is to address the Project related grievances of the affected parties that are unable to be resolved satisfactorily through the initial stages of the Grievance Redress Mechanism (GRM).

136. EA will assist affected communities/villages identify local representatives to act as Grievance Focal Points (GFP) for each community/village.

137. GFPs are designated personnel from within the community who will be responsible for i) acting as community representatives in formal meetings between the project team (contractor, DSC, PIU) and the local community he/she represents and ii) communicating community members‘ grievances and concerns to the contractor during project implementation. The number of GFPs to be identified for each project will depend on the number and distribution of affected communities.

138. A pre-mobilization public consultation meeting will be convened by the EA Environment Specialist and attended by GFPs, contractor, DSC, PIU representative and other interested parties (eg. District level representatives, NGOs). The objectives of the meeting will be as follows:

(i) Introduction of key personnel of each stakeholder including roles and responsibilities,

Environmental & Social Safeguard Unit – IESCO Page 54 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

(ii) Presentation of project information of immediate concern to the communities by the contractor (timing and location of specific construction activities, design issues, access constraints etc.) This will include a brief summary of the EMP - its purpose and implementation arrangements; (iii) Establishment and clarification of the GRM to be implemented during project implementation including routine (proactive) public relations activities proposed by the project team (contractor, DSC, PIU) to ensure communities are continually advised of project progress and associated constraints throughout project implementation; (iv) Identification of members of the Grievance Redress Committee (GRC) (v) Elicit and address the immediate concerns of the community based on information provided above

139. Following the pre-mobilization public consultation meeting, environmental complaints associated with the construction activity will be routinely handled through the GRM as explained below and shown on Figure 7.1:

(i) Individuals will lodge their environmental complaint/grievance with their respective community‘s nominated GFP. (ii) The GFP will bring the individual‘s complaint to the attention of the Contractor. (iii) The Contractor will record the complaint in the onsite Environmental Complaints Register (ECR) in the presence of the GFP. (iv) The GFP will discuss the complaint with the Contractor and have it resolved; (v) If the Contractor does not resolve the complaint within one week, then the GFP will bring the complaint to the attention of the DSC‘s Environmental Specialist. The DSC‘s Environment Specialist will then be responsible for coordinating with the Contractor in solving the issue. (vi) If the Complaint is not resolved within 2 weeks the GFP will present the complaint to the Grievance Redress Committee (GRC). (vii) The GRC will have to resolve the complaint within a period of 2 weeks and the resolved complaint will have to be communicated back to the community. The Contractor will then record the complaint as resolved and closed in the Environmental Complaints Register. (viii) Should the complaint not be resolved through the GRC, the issue will be adjudicated through local legal processes. (ix) In parallel to the ECR placed with the Contractor, each GFP will maintain a record of the complaints received and will follow up on their rapid resolution. (x) EA will also keep track of the status of all complaints through the Monthly Environmental Monitoring Report submitted by the Contractor to the DSC and will ensure that they are resolved in a timely manner.

Environmental & Social Safeguard Unit – IESCO Page 55 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Affected Person through GFP

Contractor Redressed

Not Redressed

Committee Resolve with Implementation (DSC) Redressed Consultant

Not Redressed

Appeal to Grievance Redress Committee Redressed

Grievance Redress Redress Grievance Not Redressed

Resolve through Local Legal Process

Figure 7.1: Grievance Redress Mechanism

Environmental & Social Safeguard Unit – IESCO Page 56 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

8. CONCLUSIONS

8.1 Findings and Recommendations

140. This study was carried out at the planning stage of the project. Secondary data was used to assess the environmental impacts. The potential environmental impacts were assessed in a comprehensive manner. The report has provided a picture of all potential environmental impacts associated with the Project, and recommended suitable mitigation measures. This study recommends that some further follow up studies are undertaken during project processing in order to meet the ADB requirements.

141. There are some further considerations for the planning stages such as obtaining clearance for the project under the Pakistan Environmental Protection Act (1997) but environmental impacts from the power enhancements will mostly take place during the construction stage. There are also some noise impacts and waste management issues for the operational stage that must be addressed in the detailed design and through environmentally responsible procurement. At the detailed design stage the number of and exact locations for transmission tower enhancements may change subject to detailed surveys but the impacts are likely to be broadly similar at most locations and impacts have been reviewed in the environmental impact section of this IEE report.

142. There are a number of key actions required in the detailed design phase. Prior to construction the IESCO must receive clearance certification from the PEPA and IESCO must complete an EMP that will be accepted by the PEPA and agreed by the contractor prior to signing the contract. The information provided in this report can form the basis of any further submission to PEPA as required in future.

143. No land acquisition, compensation and resettlement are involved. However, some trees will be compensated to the concerned parties, if needed. However, provisions may be made in LARP, based on the proposed alignments these should not be difficult tasks and can be conducted as the detailed designs are worked out and to dovetail with the existing system and minimize adverse impacts and maximize benefits. A social impact assessment and resettlement action plan (LARP) has been completed in tandem with this IEE for the whole subproject. The study has:

Environmental & Social Safeguard Unit – IESCO Page 57 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

(i) Examined and assess the overall social and poverty profile of the project area on the basis of secondary data sources and preparation of a socio-economic profile of the project districts. (ii) Prepared a social and poverty analysis, taking into account socio-economic and poverty status of the project area of influence, including the nature, extent and determinants of poverty in the project area including assessment. In addition, estimation of the likely socioeconomic and poverty reduction impacts of the project should be included. (iii) Held consultations with relevant officials from the government and other relevant officials, including consultation with affected communities to assess responses to the project and ascertain the nature and scope of local participation in project planning and implementation. (iv) Identified, analyzed and, where appropriate, quantified the potential resettlement impacts (minimal) of the proposed Project on the area and the population.

144. Baseline monitoring activities should be carried out during project detailed design stage to establish the baseline of parameters for checking during the construction stage. The monitoring schedule (Appendix I) recommends monitoring on two occasions at the site location. The results should be integrated with the contract documentation to establish performance action thresholds, pollution limits and contingency plans for the contractor‘s performance.

145. During the commissioning phase noise monitoring should ensure that statutory requirements have been achieved. Monitoring activities during project operation will focus on periodic recording environmental performance and proposing remedial actions to address any unexpected impacts.

8.2 Summary and Conclusions

146. The construction of the new 132kV Double Circuit Sang Jani – Zero Point transmission line subproject is a feasible and sustainable option from the power transmission, engineering, environmental, and socioeconomic points of view. Implementation of the EMP is required and the environmental impacts associated with the subproject need to be properly mitigated, and the existing institutional arrangements are available. Additional human and financial resources will be required by IESCO to complete the designs and incorporate the recommendations effectively and efficiently in the contract documents, linked to payment milestones. The proposed mitigation and management plans are practicable but require additional resources.

147. This IEE, including the EMP, should be used as a basis for an environmental compliance program and be included as Appendices to the contract. The EMP shall be reviewed at the detailed design stage. In addition, any subsequent conditions issued by PEPA as part of the environmental clearance should also be

Environmental & Social Safeguard Unit – IESCO Page 58 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

included in the environmental compliance program. Therefore, continued monitoring of the implementation of mitigation measures, the implementation of the environmental conditions for work and environmental clearance, and monitoring of the environmental impact related to the operation of the subproject should be properly carried out and reported at least twice per year as part of the project performance report.

Environmental & Social Safeguard Unit – IESCO Page 59 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

APPENDICES

Environmental & Social Safeguard Unit – IESCO Page 60 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report APPENDIX – I (A)

SUMMARY ENVIRONMENTAL MONITORING PLAN (Matrix) No. Environmental Monitoring Tasks2 Implementation Responsibility Implementation Schedule DESIGN PHASE Audit project bidding documents to ensure IEE and 1.1 IESCO through project implementation unit. Prior to issue of bidding documents. EMP is included. Monitor final site selection process and final alignment IESCO with the assistance of an external Prior to IESCO approval of contractor‘s detailed 1.2 selection process and its environmental compliance with environmental consultant. alignment survey. EMP. Review the implementation of the Land Acquisition Plan and expropriation, including considerations IESCO with the assistance of an external Prior to IESCO approval of contractor‘s detailed 1.3 concerning vulnerable groups among land-owners, environmental consultant. alignment survey. farmers, and farm workers. Monitor contractor‘s detailed project design to ensure IESCO with assistance of project implementation Prior to IESCO approval of contractor‘s detailed 1.4 relevant environmental mitigation measures in EMP unit. alignment survey. have been included. Monitor the thorough implementation of detailed Environmental Guidelines for Construction Works, IESCO with the assistance of an external Prior to IESCO approval of contractor‘s detailed 1.5 including procurement, management, works, closing environmental consultant. designs. operations. Review the management plan for mineral construction IESCO with the assistance of an external Prior to IESCO approval of contractor‘s detailed 1.6 materials and waste management. environmental consultant. designs. Audit detailed designs of facilities and installations to IESCO with assistance of project implementation Prior to IESCO approval of contractor‘s detailed 1.7 ensure standard environmental safeguards/ mitigation unit. designs. measures (as identified in EMP) have been included. Review landscape design plan, including compensatory IESCO with the assistance of an external Prior to IESCO approval of contractor‘s detailed 1.8 planting. environmental consultant. designs. Monitor the performance of environmental training and IESCO with the assistance of an external 1.9 briefings and of the environmental awareness of project Continuous throughout the entire project period. environmental consultant. staff and IESCO.

2 Monitoring of issues related to compensation of landowners for land acquisition and loss of production, etc. are addressed in the Resettlement Action Plan.

Environmental & Social Safeguard Unit – IESCO Page 61 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report No. Environmental Monitoring Tasks2 Implementation Responsibility Implementation Schedule CONSTRUCTION PHASE Regular (monthly) monitoring and reporting (quarterly) IESCO with assistance of project implementation 2.1 of contractor‘s compliance with contractual Continuous throughout construction period. unit. environmental mitigation measures. Monitoring of the implementation of the Landscape IESCO with the assistance of an external 2.2 During the last phase of construction works. Design Plan. environmental consultant. Commissioning phase monitoring of as built equipment 2.3 IESCO. At commissioning. versus environmental performance criteria. OPERATION AND MAINTENANCE PHASE Observations during routine maintenance inspections of facilities and distribution lines rows. Inspections will include monitoring implementation of operational 3.1 IESCO. As per IESCO inspection schedules. mitigation measures versus environmental criteria specified in EMP, waste management and operational noise. Monitoring of the implementation of the Landscape IESCO with the assistance of an external 3.2 Twice per year for three years of operation. Design Plan. environmental consultant. Monitoring decommissioning of other plant required for 3.3 installation of MFF funded components and waste IESCO. During the life of the project. disposal.

LARP = Land Acquisition and Resettlement Plan. AP = Affected Persons. LAC = Local Authority Council. TD = Temporary Drainage. EC = Erosion Control. WM = Waste Management. GSC = Construction Supervision Consultant or Equivalent. TXL = Transmission Line. GSS = Grid substation. NEQS = National Environmental Quality Standards

Note: DDS=Detailed design stage. Based on EIA/IEE reports to be revised at DDS, RAP, SIA and other engineering considerations may change. EIA=environmental impact Assessment. EMP=, environmental management action plan = environmental management plan, EPA= Environmental protection Agency, TD = Temporary drainage. EC = Erosion control. NGO = non government organization ADB * = ADB checks that processes have been completed and signed off by DISCO before moving to construction stage.

Environmental & Social Safeguard Unit – IESCO Page 62 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report APPENDIX – I (B)

MONITORING PLAN FOR PERFORMANCE INDICATORS Responsible Locations to Cost of Environmental Frequency to Timing to Check to Responsibility Cost of Performance Indicator (PI) Implement Implementat Concern Monitor PI Implement PI Supervision Supervision PI ion PI DESIGN and - PRECONSTRUCTION STAGE During detailed Initially design (later DISCO‘S Cell 1. Review of Environmental Management monthly by By completion of All project DISCO‘S, E&SS E&SS staff Contractor / later EMAP Action Plan (EMAP) is reviewed Contractor to cover detailed design. alignment / ADB* cost Contractor any unidentified cost impacts) Inventory of losses, Property 2. Social Completed prior to Before removal of APs acquisition, compensation and DISCO‘S Cell E&SS staff Impacts and commencement of houses and according to DISCO‘S Cell DISCO‘S /ADB* resettlement completed to RP staff cost cost Resettlement construction structures. RP & LAFC. requirements. During detailed design by Contractor to cover 3. Project Completion of All project Contractor DISCO‘S & E&SS staff Design changes notified any access roads Contractor disclosure detailed design. alignment. cost E&SS / ADB* cost and alignment changes, additional Villages. Contract follows ADB Guidelines on ERP. Performance bond. Method 4. Environmenta Statements Deposited Contractor lly Responsible Once, before Before Contract is include DISCO‘S DISCO‘S E&SS / DISCO‘S Cell Contractual clauses include cost Procurement. Contract is signed. signed. resources for Project Cell. ADB*. staff cost

(ERP) implementation of environmental mitigation mitigation measures tied to a measures. performance bond. Disposal options for all waste Monthly or as 1.Prior to Locations DISCO‘S cell transformer oil, residually required in waste detailed design approved by 5. Waste with the contaminated soils, scrap metal management plan stage no later local waste E&SS E&SS DISCO‘S disposal design agreed with DISCO‘S and local to identify than pre- disposal consultant. authority.. sufficient locations qualification or authorities.

Environmental & Social Safeguard Unit – IESCO Page 63 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report Responsible Locations to Cost of Environmental Frequency to Timing to Check to Responsibility Cost of Performance Indicator (PI) Implement Implementat Concern Monitor PI Implement PI Supervision Supervision PI ion PI for, storage and tender reuse of negotiations transformers and 2. Include in recycling of breaker contract. oils and disposal of transformer oil, residually contaminated soils and scrap metal ―cradle to grave‖. 2. Include in contracts for unit rates for re- measurement for disposal. 3. After agreement with local authority, designate disposal sites in the contract and cost unit disposal rates accordingly. 6. Noise and air As defined in Design changes included in EIA During detailed quality Completion of EIA DISCO‘S Cell Contractor DISCO‘S / DISCO‘S Cell (supplementary) & EMAP design by mitigation in detailed design. (supplementa / Contractor cost /ADB* staff cost approved by MOEST. Contractor. design. ry) & EMAP. Considered During detailed locations to design by One month be as DISCO‘S / and 7. Hydrological Temporary Drainage Contractor and before Contractor DISCO‘S Cell identified in Contractor DISCO‘S Project Impacts Management plan. monthly to cover commencement cost staff cost the Detailed Cell. any unidentified of construction Drainage impacts Report.

Environmental & Social Safeguard Unit – IESCO Page 64 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report Responsible Locations to Cost of Environmental Frequency to Timing to Check to Responsibility Cost of Performance Indicator (PI) Implement Implementat Concern Monitor PI Implement PI Supervision Supervision PI ion PI All stream During detailed and river design updated by One month 8. Temporary crossings and DISCO‘S / and Erosion Control and Temporary Contractor monthly before Contractor DISCO‘S Cell drainage and where slopes Contractor. DISCO‘S Project Drainage completed. to cover any construction cost staff cost erosion control indicate Cell. unidentified commences. erosion will impacts. be a problem. Locations agreed During detailed DISCO‘S cell design updated by One month 9. Planning in Contractor DISCO‘S / and Use of land agreed with Contractor monthly before Contractor DISCO‘S Cell construction consultation DISCO‘S Cell DISCO‘S Project surrounding residents & Villages. to cover any construction cost staff cost camps with facilitates. Cell. unidentified commences. community impacts. and the Contractor. Locations agreed with During detailed DISCO‘S cell design updated by One month in DISCO‘S / and 10.Traffic Temporary Pedestrian and Traffic Contractor monthly before Contractor DISCO‘S Cell consultation Contractor DISCO‘S Project Condition Management Plan agreed. to cover any construction cost staff cost with Cell. unidentified commences. community impacts. and the Contractor. 1. Strengthening plan agreed for DISCO‘S cell. 2. International environment 1. Once, 11. Institutional 1. As soon as /ADB cost of specialist (IES) 2. Once strengthening practicable Throughout DISCO‘S DISCO‘S Cell DISCO‘S / and IES & support and capacity 3. Increase staffing of DISCO‘S 3. Ongoing the project Project Cell. staff cost /ADB*. for 1 month building Cell. 4. Ongoing US$25,000 4. Train DISCO‘S Cell officials.

Environmental & Social Safeguard Unit – IESCO Page 65 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report Responsible Locations to Cost of Environmental Frequency to Timing to Check to Responsibility Cost of Performance Indicator (PI) Implement Implementat Concern Monitor PI Implement PI Supervision Supervision PI ion PI CONSTRUCTION STAGE All BOT staff 1. Before contract 1. Contractor agreed to provide members in is signed training to professional staff and all categories. Contractor 2. Before DISCO‘S and 1.Orientation for workers. 1. Once monthly with IES construction Contractor DISCO‘S to DISCO‘S Cell Contractor, and 2. Special briefing and training for 2. Ongoing induction assistance areas are opened cost observe and staff cost Workers Contractor completed. 3. Ongoing and six and record up record success 3. Periodic progress review month details. 3. Every six sessions. refresher months course 1. Drainage Management plan 2. Temp. Pedestrian & Traffic Management plan, 3. Erosion Control & Temp. Drainage plan Deliverable in final 4. Materials Management plan, form to DISCO‘S One month 2. Plans to control All of 5. Waste Management plan; cell one month before Contractor DISCO‘S Project DISCO‘S Cell environmental DISCO‘S Contractor 6. Noise and Dust Control plan, before construction construction cost Cell. staff cost impacts alignment. 7. Safety Plan commences for any commences. 8. Agreed schedule of costs for given stretch. environmental mitigation.{N.B. Forest Clearance and Compensatory Planting plan is prepared by DISCO’S cell} Locations to be provided During detailed with the Meaningful water quality Once (line item design by detailed monitoring up and downstream Independent when opening up Contractor and designs Contractor DISCO‘S / DISCO‘S Cell 5. Water quality during construction within 100m experienced construction near update to cover including all cost DISCO‘S Cell. staff cost of rivers. Rapid reporting and laboratory. water bodies). any unidentified bridges feedback by DISCO‘S. impacts. during construction within 100m

Environmental & Social Safeguard Unit – IESCO Page 66 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report Responsible Locations to Cost of Environmental Frequency to Timing to Check to Responsibility Cost of Performance Indicator (PI) Implement Implementat Concern Monitor PI Implement PI Supervision Supervision PI ion PI of rivers 1. Availability of water acceptable to community. No complaints. All local Prior to 4. Water 2. Guidelines established to 1. Monthly water supply Contractor DISCO‘S and DISCO‘S Cell submission of Contractor Resources minimize the water wastage 2. Monthly resources cost DISCO‘S Cell staff cost progress reports. during construction operations and rivers. and at worker camps. 1. Use of land agreed with 5. Spoil disposal surrounding residents & Villages. Monthly (line item Prior to All DISCO‘S Contractor DISCO‘S and DISCO‘S Cell and construction 2. Waste Management Plan when opening up construction. Contractor alignment. cost DISCO‘S Cell staff cost waste disposal implemented. construction). Update monthly. 3 No open burning Contractor DISCO‘S / Noise mitigation measures Maximum Monthly (line item should DISCO‘S Project implemented in line with allowable noise All DISCO‘S Contractor DISCO‘S Cell 6. Noise when opening up maintain the Cell will monitor guidelines for noise reduction levels are alignment. cost staff cost construction). accepted sample from ISO/TR11688-1:1995(E) 45dB(A)LEQ at SR standards activities. Monthly (line item Prior to Noise and dust control plan All DISCO‘S Contractor DISCO‘S and DISCO‘S Cell 7. Air quality when opening up construction. Contractor implemented. alignment. cost DISCO‘S Cell staff cost construction). Update monthly. Contractors workforce to Monthly (line item Prior to 8. Soil All DISCO‘S Contractor DISCO‘S and DISCO‘S Cell instructed and train handling of when opening up construction. Contractor Contamination alignment. cost DISCO‘S Cell staff cost chemicals construction). Update monthly. 1. Use of land agreed with 9. Work Camp surrounding residents & Villages. Monthly (line item Prior to All DISCO‘S Contractor DISCO‘S and DISCO‘S Cell Location and 2. Waste Management Plan when opening up construction. Contractor alignment. cost DISCO‘S Cell staff cost Operation implemented. construction). Update monthly. 3 No open burning One month DISCO’S / (E&SS 10. Safety Once (update before All DISCO‘S Contractor to actively DISCO‘S Cell Precautions for Safety Plan submitted monthly as Contractor. construction and alignment. cost supervise and staff cost Workers necessary) update quarterly. enforce. 11. Social 1. Local labour is used and Monthly (line item During All DISCO‘S Contractor DISCO‘S and DISCO‘S Cell Contractor Impacts workforce when opening up construction. alignment. cost DISCO‘S Cell staff cost

Environmental & Social Safeguard Unit – IESCO Page 67 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report Responsible Locations to Cost of Environmental Frequency to Timing to Check to Responsibility Cost of Performance Indicator (PI) Implement Implementat Concern Monitor PI Implement PI Supervision Supervision PI ion PI 2. Local educated people for construction). Update monthly. office work. 3. Complaints on construction nuisance damages close to ROW are responded to promptly by the Contractor. 4. Quarterly meetings with local VILLAGE for liaison purposes to monitor complaints. Contractor has included for some DISCO’S / One month enhancements in detailed designs Once (update (DISCO‘S Cell to 12. before All DISCO‘S Contractor DISCO‘S Cell Including planting of trees in monthly as Contractor. actively Enhancements construction and alignment. cost staff cost addition to bioengineering such necessary) supervise and update quarterly. as in median enforce. OPERATIONAL STAGE 1) Throughout project 1. Follow up on Tree Clearance 2) Each of three and Compensatory Planting Plan. years after initial 2. Records on survival of planted planting. 1) Quarterly trees. 3) Continuous for MOFSC and 1. crops and 2) Quarterly All DISCO‘S 3. The compensatory planting three years after Contractor E&SS DISCO‘S DISCO‘S Cell vegetation 3) Quarterly alignment. maintained project staff cost. 4) Quarterly 4. Audited report by E&SS for completion onsite and off-site compensatory 4) For four years planting. after initial clearance of the forest.

Note: LAFC = Land Acquisition Compensation Fixation Committee. DDS=Detailed design stage. Based on EIA/IEE reports to be revised at DDS, RAP, SIA and other engineering considerations may change, EIA=environmental impact Assessment. EMP=, environnemental management action plan = environnemental management plan, EPA= Environnemental Protection Agency,. TD = Temporary drainage. EC = Erosion control. NGO = non government organization. ADB * = ADB checks that processes have been completed and signed off by DISCO‘S before moving to construction stage.

Environmental & Social Safeguard Unit – IESCO Page 68 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

APPENDIX – I (C)

MONITORING PLAN

1. DISCO‘S have established the Environment and Social Safeguard Section (E&SS) manned by two professionals and support staff. The DISCO‘S instructional arrangement with respect to social and environmental monitoring and implementation is presented as follows:

INSTITUTIONAL ARRANGEMENTS

2. The institutional arrangements of planning and management of the Power Distribution Enhancement Program (or the ADB-funded Power Distribution Enhancement MFF Project) are described as follows (Refer to Figure C-1):

Pakistan Electric Power Company (PEPCO)

3. The Project Management Unit (PMU), PEPCO is the focal organization based in responsible for the Power Distribution Enhancement Program, for keeping liaison with the Government of Pakistan and Asian Development Bank (ADB) on behalf of all the DISCOs, and taking care of disbursement of funds (including ADB loan) and technical assistance through Consultants to, and coordination of the Program planning and management activities of the DISCOs. Distribution Companies (DISCOs)

4. The DISCOs included in the ADB-funded MFF Project (the Program) are:

(1) PESCO: Peshawar Electric Supply Company, Peshawar, Khyber Phukhton Khaw; (2) IESCO: Islamabad Electric Supply Company, Islamabad; (3) GEPCO: Electric Power Company, Gujranwala, Punjab; (4) LESCO: Lahore Electric Supply Company, Lahore, Punjab; (5) FESCO: Electric Supply Company, Faisalabad, Punjab; (6) MEPCO: Electric Power Company, Multan, Punjab; (7) QESCO: Electric Supply Company, Quetta, Baluchistan; and, (8) HESCO: Hyderabad Electric Supply Company, Hyderabad, .

Technical Assistance (Consultants)

5. PMU, PEPCO provides technical assistance to all the eight DISCOs through the following Consultants, based in Lahore:

. PPTA: Project Preparation Technical Assistance was hired by PEPCO in 2007 and since then it has so far assisted the DISCOs in preparing Tranche 1 & 2 Subprojects. The PPTA Resettlement Experts have thus far assisted the DISCOs in the preparation of LARPs and DDRs for the Subprojects included in Tranches 1 and 2.

Environmental & Social Safeguard Unit – IESCO Page 69 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

. PIC: Project Implementation Consultant is expected to be hired and mobilized by PEPCO by end-2009, to provide technical assistance to DISCOs in updating and implementation of the approved Subprojects. The PIC Resettlement Experts will assist the DISCOs in updation, revision and implementation of the LARPs and DDRs. . EMC: External Monitoring and Evaluation Consultant is expected to be hired and mobilized by PEPCO by end-2009, to independently monitor and evaluate the implementation of approved LARPs on the Tranche 1 and 2 Subprojects of all the DISCOs, and report directly to ADB with copy to the respective DISCOs.

Environmental & Social Safeguard Unit – IESCO Page 70 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

PEPCO Project Management Unit (PMU) (Project Coordination)

Chief Executive

IESCO

Project Implementation Consultant (PIC) Chief Engineer Development PPTA (IESCO Subprojects) Consultants External LARP Monitoring Consultant (EMC) Project Director (PD, GSC) (Grid System Construction)

Project

Implementation

Unit (PIU)

(Engineers & Patwaris)

Deputy Manager Province Board Environment and Social of Revenue Safeguard (E&SS).

Assistant DISCO LAC Assistant Manager District LAC Manager (Social Impact) (Environment)

Staff / Patwaris Field Patwaris

Figure C-1: Organization for LARP Planning, Implementation and Monitoring

Environmental & Social Safeguard Unit – IESCO Page 71 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Distribution Companies (DISCOs)

6. DISCO as the implementing agency (IA) bears the overall responsibility for the preparation, implementation and financing of all tasks set out in this LARP, as well as inter-agency coordination required for the implementation of the Subprojects. As such, it takes care of the preparation/updating and implementation of the LARPs and DDRs, and internal monitoring and evaluation activities (see also Chapter 10: Monitoring and Evaluation). Institutionally, DISCO typically has three functional divisions, namely, the Planning, Projects and Grid System Construction divisions (GSC).

Planning Division

7. The Planning Division is responsible for preparation of PC-1s, for preparation of load forecasts and feeder analysis. The division is responsible for preparation of the Energy Loss Reduction (ELR) work orders. Formerly subproject preparation and keeping liaison with the Government of Pakistan and Asian Development Bank (ADB), as the donor of this MFF Project had also been the responsibility of this division. But lately the activity has been shifted to the Office of Chief Engineer Development.

Chief Engineer Development

8. The former Projects Division has now been named as the Office of Chief Engineer Development (CED), is responsible for the overall planning, management and coordination of the approved Subprojects. The CED is currently being assisted by the PPTA Consultants (including the Resettlement Experts responsible for LARP/DDR preparation), in preparing the identified Subprojects in line with the ADB Policies, and obtaining approval from the donor ADB. Its major functions include keeping regular liaison with ADB and relevant departments of the federal, provincial and district governments, preparation, updating and implementation of the LARPs and the related monitoring and evaluation activities.

9. The CED contains a specially created cell to take care of the safeguards related activities, namely, the Environment and Social Safeguard Section (E&SS), headed by a Deputy Manager (E&SS), and assisted by two Assistant Managers, Environment and Social Impact, respectively. The Assistant Manager Social Impact is responsible for the preparation/updating, implementation and internal monitoring of the Subproject LARPs, with assistance from DISCO LAC and PIC Resettlement Expert.

10. The Scope of Work to be handled by the E&SS far exceeds the physical and professional ability and capabilities of the incumbents. To support the E&SS, to carry out its responsibilities, a Monitoring Consultant is being hired. In addition, a Project Implementation Consultant (IC) will also be hired who will also have social and environmental experts to assist IESCO in revising and updating the LARP as and when required, and then in implementation of the LARP. The Consultants will be provided full logistic support (including office space and field transport) by the DISCO.

Environmental & Social Safeguard Unit – IESCO Page 72 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Grid System Construction (GSC) Division

11. The Grid System Construction (GSC) Division is responsible for implementing the approved Subprojects, including construction/improvement of grid stations and transmission lines. This office is headed by the Project Director (GSC), and it will establish Project Implementation Units (PIUs), comprising Engineers and Patwaris, at the respective towns of each Subproject. The PD GSC has an in-house Land Acquisition Collector (LAC) to take care of the land acquisition and resettlement activities.

12. The DISCO LAC, along with field Patwaris, in addition to implementation of the LARP activities, will provide in-field assistance to the Resettlement Experts of E&SS and PIC in updating, revision and internal monitoring of the LARPs. He normally works as an independent entity, but in case of local needs like price updating, grievance redress, etc., may involve the local Union Councils and other leaders at the local levels, and/or the District LACs and Province Board of Revenue for addressing broader level matters and resolving permanent Land Acquisition issues (not applicable to this Subproject). He will be provided technical assistance by the Resettlement Experts included in both E&SS and PIC teams.

District Government

13. The district government have jurisdiction for land administration, valuation and acquisition. At the provincial level these functions rest on the Province Board of Revenue while at the district level they rest on the District Land Acquisition Collector (District LAC). Within LAC office the Patwari (land records clerk), carry out specific roles such as titles identification and verification required by the IESCO LAC.

Responsibility for Internal and External Monitoring

14. Land acquisition and resettlement tasks under the Program will be subjected to both internal and external monitoring. Internal monitoring will be conducted by E&SS, assisted by DISCO LAC and PIC Resettlement Expert. The external monitoring responsibilities will be assigned to an External Monitoring Consultant (EMC) to be engaged by PMU, PEPCO according to the Terms of Reference (TOR) that have been approved by ADB. Terms of Reference of the monitoring consultants (MC) as follows:

Environmental Monitoring

An environment evaluation expert(s) for a period of four (4) person-month (on as and when required basis) who will undertake monitoring of IEEs and also other environmental issues related to design, construction and commissioning of the sub- projects according to the relevant reports already prepared and approved by DISCO‘S/ADB. The expected completion time of these projects is one years.

Environmental & Social Safeguard Unit – IESCO Page 73 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

(A) Design Phase

. Monitor final site selection process and final alignment selection process and its environmental compliance with EMP. . Review the implementation of the land acquisition plan and expropriation, including considerations concerning vulnerable groups among land-owners, farmers, and farm workers. . Monitor contractor‘s detailed project design to ensure relevant environmental mitigation measures in EMP have been included. . Monitor the detailed environmental guidelines for construction works, including procurement, management, works, closing operations etc in the light of IEE and EMP. . Review the management plan for mineral construction materials and waste management. . Audit detailed designs of facilities and installations to ensure standard environmental safeguards/ mitigation measures (as identified in EMP) have been included. . Review landscape design plan, including compensatory planting. . Monitor the performance of environmental training and briefings for the creation of environmental awareness of project staff and DISCO‘S.

(B) Construction Phase

. Regular monitoring and reporting of contractor‘s compliance with contractual environmental mitigation measures in light of IEE and EMP. . Monitoring of the implementation of the landscape design plan.

(C) Operation and Maintenance Phase

. Monitoring of routine maintenance of facilities and transmission line in light of mitigation measures specified in EMP. . Monitoring of the implementation of the landscape design plan. . The MC will mainly assist the E&SS cell in the monitoring functions. DISCO‘S is also in the process of hiring management consultants, who will assist the Project Management Unit (PMU) of DISCO‘S in amongst other matters relating to the implementation of the IEE/LARP including updating of LARP s (price updating) and updating of IEE and EMPs when ever major changes are made to the approved sub projects. . Terms of reference for Project Implementation (Management) Consultants . Terms of Reference (related to social and environmental aspects) of the Project Implementation (Management) Consultants are specifically, the PMC shall ensure that: i. All environmental examinations, frameworks, and plans for all the subprojects should be conducted and implemented in accordance with ADB‘S environment policy and environmental examination guidelines, and Pakistan Environmental Examination regulations and guidelines.

Environmental & Social Safeguard Unit – IESCO Page 74 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

ii. All land acquisition, and resettlement framework and plan are implemented promptly and efficiently according to its terms in accordance with the applicable Pakistan laws, and ADB‘S policy on involuntary resettlement. iii. PMU will guarantee that all subprojects affecting ethnic minorities are constructed and operated in accordance with the requirements of ADB‘S policy on indigenous peoples and applicable Pakistan rules and regulations. iv. PMU will follow the principles of the ADB‘S policy on gender and development and use appropriate Pakistan laws during each subproject implementation. v. Ensure that subproject specific environmental and social mitigation measures are incorporated into contract documents. vi. Supervise and evaluate the implementation of environmental mitigation ad monitoring measures as specified in the environment management plans (EMP). vii. Update the EMP as necessary, including carrying out supplemental Environmental Examinations for additional subprojects appraised after loan approval. viii. Supervise social safeguard‘s related reporting requirements and ensure its timely submission. The reporting documents include LARP‘S updating, progress and completion reports. ix. Monitor and supervise resettlement and other social impact mitigation activities, as defined in the approved and final LARP‘S. x. Ensure no civil works to be done unless the applicable provisions of the LARP are, including in particular the timely delivery of compensation to affected families have been complied with. xi. Establish a grievance mechanism procedure for the subprojects. xii. Conduct and develop internal monitoring and evaluating reporting system of the LARPS and EMPS implementations. The report will also include any change in the implementation schedule, problems or difficulties encountered and work to be carried out in the next period in accordance with procedures and details acceptable to ADB. The monitoring reports will be included in the quarterly progress report to be submitted to ADB.

Environmental & Social Safeguard Unit – IESCO Page 75 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Project Monitoring Activities during the Project Cycle:

The Activities at various stages of the project cycle have been summarized in the terms of reference for consultants as presented in Table AX3.1.

Table AX3.1 Monitoring Program for Tranche 3 Monitoring Monitoring Parameter Timing Responsibility Locations DESIGN PHASE DISCO‘S through Audit project bidding documents to Prior to issue of 1. - project implementation ensure IEE and EMP is included biding documents unit. Monitor that the selection process Prior to DISCO‘S DISCO‘S with the and final alignment selection approval of assistance of and 2. - process and its environmental contractor‘s detail external environmental compliance with EMP alignment survey consultants Monitor contractor‘s detail project Prior to DISCO‘S DISCO‘S with the design to ensure relevant approval of 3. - assistance of project environmental mitigation measures contractor‘s detail implementation unit in EMP have been included alignment survey Monitor through implementation of Prior to DISCO‘S DISCO‘S with the detail environmental guidelines for approval of assistance of and 4. construction works including - contractor‘s detail external environmental procurement management, works design consultants and closing operation Prior to DISCO‘S DISCO‘S with the Review the mineral, construction approval of assistance of and 5. - materials and waste management contractor‘s detail external environmental design consultants Prior to DISCO‘S DISCO‘S with the Audit detail design of facilities and approval of 6. - assistance of project installation to ensure standard contractor‘s detail implementation unit design Table AX3.1 Monitoring Program for Tranche 3 (continued) CONSTRUCTION PHASE Monitoring Parameter Monitoring Locations Timing Responsibility Construction sites, During routine 1 Observation of soil erosion PMU campsites monitoring At wells and surface water bodies near grid Before mobilization Contractor/PMU station and construction campsites 2 Water quality Selected local wells Monthly Contractor/PMU Selected locations at nearby surface water Monthly Contractor/PMU bodies

Environmental & Social Safeguard Unit – IESCO Page 76 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Construction sites, 3 Water consumption Daily Contractor/PMU campsite Checks for any damage to During routine 4 water course, groundwater Construction sites PMU monitoring wells Construction sites, Before mobilization Contractor/PMU campsites 5 Ambient air quality Construction sites, Once every two Contractor/PMU campsites months Construction sites, During routine campsites Contractor/PMU monitoring Checks for exhaust emissions 6 Checks for dust emissions Construction sites, During routine campsites, project Contractor/PMU monitoring roads Fortnightly or during the construction 7 Noise At nearby communities Contractor/PMU activities causing noise. Throughout the field 8 Public concerns At nearby communities PMU activities.

Table AX3.1 Monitoring Program for Tranche 3 (continued) OPERATIONAL PHASE Monitoring Parameter Monitoring Locations Timing Responsibility Selected sites for After construction 1 Compensatory tree planting DISCO‘S plantation of trees phase Land under the During routine 2 Crops and vegetation DISCO‘S transmission line maintenance Population along During routine 3 Social safety Impacts DISCO‘S transmission line maintenance Complete record of sampling and analysis should be maintained and documented. PMU = Project Monitoring Unit, DISCO‘S = Distribution Companies

Summary of Estimated Costs for EMP

Table AX3.2 Summary of EMP Cost for Implementation Tranche III Sub-projects Estimated Cost Activities Description Pak. Rs. US $ Staffing, audit and 1 person for 3 years 2137500 22,500 monitoring Monitoring activities As detailed under EMP 8312500 87,500 As prescribed under EMP and Mitigation measures 2850000 30,000 IEE Transport 1 dedicated vehicle 3 years 1784100 18,780 Contingency contingency 723235 7,613 Total 15,807,335 1,66,393 I US$ = 95 Pak. Rupees

Environmental & Social Safeguard Unit – IESCO Page 77 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report APPENDIX – II

SUMMARY OF PUBLIC CONSULTATION

(INTERVIEWER RESPONDENTS)

8.1 No. Participants Name Participants Profession Address Date 8.2 8.3 01. Mr. Zafar Yousaf Local Resident Dohk Suleman 20-09-2012 8.4 8.5 02. Mr. Malik Banaras Local Resident Dohk Suleman 20-09-2012 8.6 8.7 03. Mr. Iftikhar Ahmed Local Resident Jangi Syedian 20-09-2012 8.8 8.9 04. Mr. Azhar Bukhari State Officer Jamu Kashmir Cooperative Housing Society 20-09-2012 8.10 8.11 05. Mr. Ayub Khan Local Resident Itifaq colony 20-09-2012 8.12 8.13 06. Mr. Ibrar Ahmed Local Resident Sangjani 20-09-2012 8.14 8.15 07. Mr. Syed Mateen Shah Local Resident Sangjani 20-09-2012 8.16 8.17 08. Mr. Rizwan Ali Local Resident Sangjani 20-09-2012 8.18 8.19 09. Mr. Ali Zafar Local Resident Sangjani 20-09-2012 8.20 8.21 10. Mr. Salman Khan Local Resident Sangjani 20-09-2012 8.22 8.23 11. Mr. Muhammad Rafique Local Resident Sangjani 20-09-2012 8.24 8.25 12. Mr. Syeda Umza Local Resident Jangi Syedian 20-09-2012 8.26 8.27 13. Mr. Rashida Bano Local Resident Dohk Suleman 20-09-2012 8.28 8.29 14. Mr. Sehnila Atique Local Resident Dohk Suleman 20-09-2012

Environmental & Social Safeguard Unit – IESCO Page 78 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report Issues Raised / Concerns expressed / Suggestions & No. Proposed Measure Action Taken / Proposed Requests. IESCO should pay compensation of crops Compensation should be paid adequately and 01. Crop and tree compensation should be fair and timely. and trees fairly and timely at least 15 days timely. before civil works. IESCO should pay compensation of crops Compensation should be paid adequately and 02. Crop and tree compensation should be fair and timely. and trees fairly and timely at least 15 days timely. before civil works. Local skilled and unskilled labor should be used Skilled and unskilled labor should be preferred IESCO should employ Skilled and unskilled 03. wherever possible. from the area. labor from the area. Design of the line should not be changed, but if 04. necessary at any stage houses and structures should be Construction work should be completed in time. IESCO should complete all work timely. avoided. Design of the line should not be changed, but if necessary at any stage houses and structures should be 05. Construction work should be completed in time. IESCO should complete all work timely. avoided.

Load shedding is more in villages and affects all spheres 06. - - of life including schools. Design of the line should not be changed, but if 07. necessary at any stage houses and structures should be Construction work should be completed in time. IESCO should complete all work timely. avoided. IESCO should avoid distribution lines to 08. Line should not pass over the houses Line should be avoided to pass over the houses. pass over the houses. IESCO should avoid distribution lines to 09. Line should not pass over the houses. Line should be avoided to pass over the houses. pass over the houses. Load shedding is more in villages and affects all spheres 10. - - of life including schools. Local skilled and unskilled labor should be used Skilled and unskilled labor should be preferred IESCO should employ Skilled and unskilled 11. wherever possible. from the area. labor from the area. IESCO should avoid distribution lines to 12. Local norms should be honored. Line should not pass over the houses of the colony. pass over the houses. IESCO should avoid distribution lines to 13. Local norms should be honored. Line should not pass over the houses of the colony. pass over the houses.

Environmental & Social Safeguard Unit – IESCO Page 79 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report Issues Raised / Concerns expressed / Suggestions & No. Proposed Measure Action Taken / Proposed Requests. IESCO should pay compensation of crops Compensation should be paid adequately and 14. Crop and tree compensation should be fair and timely. and trees fairly and timely at least 15 days timely. before civil works. Crop and tree compensation should be fair and timely. IESCO should pay compensation of crops Compensation should be paid adequately and 15. and trees fairly and timely at least 15 days timely. before civil works.

Design of the line should not be changed, but if 16. necessary at any stage houses and structures should be Construction work should be completed in time. IESCO should complete all work timely. avoided. Design of the line should not be changed, but if 17. necessary at any stage houses and structures should be Construction work should be completed in time. IESCO should complete all work timely. avoided. Design of the line should not be changed, but if 18. necessary at any stage houses and structures should be Construction work should be completed in time. IESCO should complete all work timely. avoided. Design of the line should not be changed, but if 19. necessary at any stage houses and structures should be Construction work should be completed in time. IESCO should complete all work timely. avoided.

Environmental & Social Safeguard Unit – IESCO Page 80 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report APPENDIX – III

IMPLEMENTATION SCHEDULE FOR TRANCHE III –DISTRIBUTION ENHANCEMENT PROGRAM Responsibility Year 2012 Year 2013 Year 2014 Year 2015 Year 2016 LARP Activity / Task Primary Secondary I II III IV I II III IV I II III IV I II III IV I II III IV Initial Resettlement Survey LARP preparation DISCO Consultants Review of TL Alignment; Diversions to Avoid Resettlement Impacts; and DISCO Consultants

Revision of LARP Design finalized by DISCO; approved by ADB. LARP disclosure - Brochure in DISCO-PMU CE DEV.

Preparation Requests to Relevant Govt. Deptts. for NOCs DISCO-PMU CE DEV. Tender Preparation and Tendering of Works. DISCO-PMU CE DEV. IEE/LARP Revision - Updation of Prices and Resettlement Costs (if necessary) DISCO-PMU CE DEV. Mobilize project supervision consultant Government DISCO Information dissemination regarding compensation payment & evacuation DISCO-PMU CE DEV.

dates

Adjust compensation rates & rehabilitation costs for inflation (if necessary) DISCO-PMU CE DEV. Submit revised IEE/LARP to EPA/ADB. LARP Approval prior to Award of Govt/ADB DISCO-PMU Contract for civil works .Ensure contracts reflect EMP Delivery of compensation. Payments to be made prior to the start of Civil DISCO-PMU CE DEV.

Implementation Works Grievance Redress Process DISCO-PMU CE DEV. IEE/LARP monitoring (internal, and mobilization of EMA & up-dation of DISCO-PMU EMA baseline survey)

Possession of land for starting works DISCO-PMU Contractor

Site Demarcation of Affected Lands Contractor mobilized, civil works commenced Contractor Consultant

Final payment of crop compensation PMU CE DEV. Construction LARP monitoring; post-evaluation report EMA DISCO/ADB

Environmental & Social Safeguard Unit – IESCO Page 81 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report APPENDIX – IV

SUMMARY OF LOST ASSETS

SUMMARY OF TREES AND OTHER PRODUCTIVE INFRASTRUCTURES ALONG ROW; 100M (Not define yet at this stage)

Back Span Productive Infrastructure Others

No.

No.

- -

Neem

Others

-

-

Shurbs /

(Type)

Bushes

Popular ological

the Area.

Tower Tower Type

Ailanthus

site/Game

Brick Brick Kiln

To Tower To

Wood treeWood treeWood

Reserve etc.)

Forest (Type)

From From Tower

Fruit Orchard

Topography of

Distance (m) in

Others/

Wood treeWood

Wood treeWood

(Graveyard/Arche Poultry/Fish Farm 132 KV D/C Feeding Transmission Line for New Sang Jani IIGrid Station

Not 0 1 ------Yes - define 1 2 Not define yet ------Yes - yet at at this stage. this 2 3 ------Yes - stage. AreaHilly

TOTAL (Subproject):

Environmental & Social Safeguard Unit – IESCO Page 82 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

SUMMARY OF CROPPING AND OTHER INFRASTRUCTURES ALONG ROW; 100M (Not define yet at this stage)

Back Span Housing Infrastructure

No.

No.

well (Nos)

Nos.

-

Canal/

Mosque

Tower Tower Type

To Tower To

Road Type

Land Status

From From Tower

BHU/ School/

Railway track

Houses/ Shops

Distance (m) in Power Line KV

Tube

Compact Village Drain/Minor/WC 132 KV D/C Feeding Transmission Line for New Sang Jani IIGrid Station Not 0 1 Hilly Area ------define 1 2 Not define yet Hilly Area ------yet at at this stage. this 2 3 Hilly Area ------stage. TOTAL (Sub-project): ------

SUMMARY OF CROPPING WOOD TREES AFFECTED BY THE CONSTRUCTION OF 132KV TL SUBPROJECT (Not define yet at this stage)

L Reach Affected Wood Trees (No.) (Tower Nos.) Paplar / Alianthus / Chirpine Neem Others Total Trees From To Euclyptus Rubinea 132 KV D/C Feeding Transmission Line for New Sang Jani IIGrid Station 0 1 1 2 2 3 Total Subproject: ------Percentage: ------

Environmental & Social Safeguard Unit – IESCO Page 83 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report APPENDIX – V

PHOTOGRAPHS

Proposed Site of Sang Jani – Zero Point TL.

Existing Sang Jani – Zero Point TL.

Environmental & Social Safeguard Unit – IESCO Page 84 of 90

132 KV Sang Jani – Zero Point D/C Transmission Line Subproject (IESCO) Initial Environmental Examination (IEE) Report

Public Consultation at proposed TL Site.

Public Consultation project affectes.

Environmental & Social Safeguard Unit – IESCO Page 85 of 90