Resettlement Plan Resettlement Plan May 2012 PRC: Gansu Urban Infrastructure Development and Wetland Protection Project Dingxi Urban Infrastructure Development Component Prepared by Dingxi ADB Project Management Office for the Asian Development Bank. CURRENCY EQUIVALENTS (as of 30 April 2012) Currency unit – yuan (CNY) CNY1.00 = $0.1593 $1.00 = CNY6.2785 ABBREVIATIONS ADB – Asian Development Bank AV – administrative village AHs – affected households APs – affected persons HH – households CRO – client resettlement office DMG – Dingxi Municipal Government DPMO – Dingxi Project Management Office DUCIAM – Dingxi Urban Construction & Investment and Asset Management Ltd Co. LAR – land acquisition and resettlement PRO – project resettlement office ROs – resettlement offices RP – resettlement plan SES – social economic survey Twp township WEIGHTS AND MEASURES ha – hectare km – kilometer km2 – square kilometer m – meter m2 – square meter mu – Chinese unit of measurement for land area (1 mu = 666.67 m2 = 0.0667 ha) NOTE (i) In this report, "$" refers to US dollars. This resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. GANSU URBAN INFRASTRUCTURE DEVELOPMENT AND WETLAND PROTECTION PROJECT Dingxi Urban Infrastructure Development Component (ADB No:44020-PRC) RESETTLEMENT PLAN Dingxi ADB Project Management Office 30 April 2012 Dingxi Municipal People's Government A Letter of Guarantee on the Strict Implementation of Resettlement Plan of Dingxi’s Infrastructure Construction Project of the ADB Loan Gansu Urban Infrastructure Development and Wetland Protection Project Abbreviation ADB Asian Development Bank APs Affected Persons AV Administrative Village HH Household CRO Client Resettlement Office DPMO Dingxi Project Management Office DUCIAM Dingxi Urban Construction & Investment and Asset Management Ltd Co. mu 1mu = 0.006 ha PAH Project Affected Household PAP Project Affected Person PRO Project Resettlement Office RMB China yuan, the unit of Chinese currency RP Resettlement Plan SES Social Economic Survey Twp Township ¥ CNY Note: All abbreviations were explained in the text. TABLE OF CONTENTS A LETTER OF GUARANTEE ON THE STRICT IMPLEMENTATION OF RESETTLEMENT PLAN OF DINGXI’S INFRASTRUCTURE CONSTRUCTION PROJECT OF THE ADB LOAN GANSU URBAN INFRASTRUCTURE DEVELOPMENT AND WETLAND PROTECTION PROJECT EXECUTIVE SUMMARY ................................................................................................................... 1 E1. DESCRIPTION OF THE PROJECT AND LAND ACQUISITION AND RESETTLEMENT IMPACTS .......................................................................................................................... 1 E2. RESETTLEMENT PRINCIPLES AND ENTITLEMENTS .................................................. 1 E3. PUBLIC PARTICIPATION AND GRIEVANCE ............................................................... 1 E4. RESETTLEMENT AND LIVELIHOOD REHABILITATION ................................................ 2 E5. INSTITUTIONAL ARRANGEMENT ............................................................................. 2 E6. COST AND SCHEDULE .......................................................................................... 2 E7. MONITORING AND EVALUATION ............................................................................. 2 I. PROJECT OVERVIEW ..............................................................................................................3 1.1 INTRODUCTION OF DINGXI CITY .................................................................... 3 1.2 PROJECT CONTENTS ...................................................................................... 3 1.3 AFFECTED REGIONS ....................................................................................... 4 1.4 MEASURES TO MITIGATE IMPACTS ............................................................... 8 1.4.1 Measures Adopted at the Project Design Stage ................................................... 8 1.4.2 Measures to Be Adopted during LAR ................................................................... 8 1.4.3 Measures to Be Adopted during Construction...................................................... 9 1.5 PREPARATION AND PROGRESS OF THE PROJECT ..................................... 9 1.6 OWNERSHIP OF THE COMPONENT ............................................................. 10 II. PROJECT IMPACT ANALYSIS ............................................................................................. 11 2.1 DEFINITION OF PROJECT IMPACT ............................................................... 11 2.2 PROJECT IMPACT SURVEY .......................................................................... 12 2.3 PROJECT IMPACTS ....................................................................................... 13 2.4 IMPACTS OF LAND ACQUISITION ................................................................. 13 2.4.1 Land Acquisition ................................................................................................. 13 2.4.2 Temporary Land Occupation.............................................................................. 20 2.5 AFFECTED BUILDINGS .................................................................................. 20 2.5.1 Affected Residential Buildings ............................................................................ 20 2.5.2 Affected Buildings of Enterprises and Institutions ............................................. 20 2.5.3 Affected Temporary Buildings .......................................................................... 24 2.5.4 Affected Attachments on the Buildings ............................................................... 24 2.6 AFFECTED VULNERABLE GROUPS....................................................................... 24 2.6.1 Identification of Affected Vulnerable Groups ..................................................... 24 2.6.2 Affected Families of Vulnerable Groups ............................................................ 25 III. SOCIO-ECONOMIC SURVEY ................................................................................................ 26 3.1 GENERAL INTRODUCTION OF SOCIO-ECONOMIC DEVELOPMENT OF THE REGIONS AFFECTED BY THE PROJECT ...................................................... 26 3.1.1 Population .......................................................................................................... 26 3.1.2 Socio-economic development of Anding District ................................................ 26 3.2 GENERAL SITUATION OF AFFECTED VILLAGES ......................................... 27 3.3 SAMPLE SURVEY ............................................................................................... 29 3.3.1 Sample Selection ................................................................................................. 29 3.3.2 Basic Charactaristics of Sampling Households ................................................. 29 3.3.3 Revenue Situation of Affected Households ......................................................... 34 3.3.5 Building Structure .................................................................................................. 3.3.6 Land Characteristics .......................................................................................... 36 3.3.7 Impacts after LAR ............................................................................................... 37 3.3.8 Affected People’s Basic Understands on LAR .................................................... 40 3.3.9 IMPACT ON ETHNIC MINORITIES AND GENDER ....................................... 43 3.4 ASSESSMENT OF SOCIAL IMPACT ............................................................... 44 IV. LEGAL AND POLICY FRAMEWORK .................................................................................. 45 4.1 GENERAL ....................................................................................................... 45 4.2 POLICY BASIS ................................................................................................ 45 4.2.1 Relevant Laws and Provisions Enacted by the Central Government ................. 45 4.2.2 Regulations and Policies Enacted by the People’s Government of Gansu Province .............................................................................................................. 45 4.2.3 Regulations and Policies Enacted by the DMG ................................................. 46 4.2.4 ADB’s Policies on Involuntary Resettlement ...................................................... 46 4.3 SUMMARY OF MAIN LAWS, REGULATIONS AND POLICIES ........................ 46 4.3.1 Summary of Relevant National and Provincial Laws and Regulations .............. 46 4.3.2 Abstracts of related regulations and rules of Gansu Province ........................... 50 4.3.3 ADB’s Relevant Policies on Involuntary Resettlement ....................................... 51 4.3.4 Comparison of ADB’s involuntary resettlement policies with the PRC’s LAR policies ................................................................................................................ 52 4.4 TARGET OF RESETTLEMENT ......................................................................
Recommended publications
  • World Bank Document
    Gansu Revitalization and Innovation Project: Procurement Plan Annex: Procurement Plan Procurement Plan of Gansu Revitalization and Innovation Project April 24, 2019 Public Disclosure Authorized Project information: Country: The People’s Republic of China Borrower: The People’s Republic of China Project Name: Gansu Revitalization and Innovation Project Loan/Credit No: Project ID: P158215 Project Implementation Agency (PIA): Gansu Financial Holding Group Co. Ltd (line of credit PPMO) will be responsible for microcredit management under Component 1. Gansu Provincial Culture and Tourism Department (culture and tourism PPMO) will be responsible for Component 2 and 3. The culture and Public Disclosure Authorized tourism PPMO will be centrally responsible for overseeing, coordinating, and training its cascaded PIUs at lower levels for subproject management. Both PPMOs will be responsible for liaison with the provincial PLG, municipal PLGs, and the World Bank on all aspects of project management, fiduciary, safeguards, and all other areas. The project will be implemented by eight project implementation units (PIUs) in the respective cities/districts/counties under the four prefecture municipalities. They are: Qin’an County Culture and Tourism Bureau, Maiji District Culture and Tourism Bureau, Wushan County Culture and Tourism Bureau, Lintao County Culture and Tourism Bureau, Tongwei County Culture and Tourism Bureau, Ganzhou District Culture and Tourism Bureau, Jiuquan City Culture and Tourism Bureau and Dunhuang City Culture and Tourism Bureau. Name of Components PIUs Gansu Financial Holding Group Co. Ltd (line of credit Public Disclosure Authorized PPMO). GFHG is designated as the wholesaler FI to handle Component 1. Under the direct oversight and Component 1: Increased Access to Financial management of the line of credit PPMO (GFHG), Bank Services for MSEs of Gansu is designated as the 1st participating financial institution (PFI) to handle micro- and small credit transactions.
    [Show full text]
  • World Bank Document
    World Bank-financed Project Public Disclosure Authorized World Bank-financed Gansu Revitalization and Innovation Project Resettlement Policy Framework (RPF) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Gansu Project Management Office (PMO) April 2019 Contents A Introduction ..................................................................................................... 1 B Objectives, Principles and Terms ................................................................... 1 C RAP Preparation and Approval ....................................................................... 2 D Institutional and Legal Framework .................................................................. 3 E Implementation Process ................................................................................. 1 F Financial Arrangements .................................................................................. 2 G Public Participation and Information Disclosure .............................................. 2 H Grievance Redress Mechanism ...................................................................... 3 I M&E ................................................................................................................ 4 Appendix 1: Components of the Project ................................................................. 6 Appendix 2: Location Map of Project Counties (Cities / Districts) ........................ 10 Appendix 3: Legal Framework for RAP Implementation......................................
    [Show full text]
  • Sediment Control and Fodder Yield Increase in Alfalfa (Medicago Sativa
    Field Crops Research 225 (2018) 55–63 Contents lists available at ScienceDirect Field Crops Research journal homepage: www.elsevier.com/locate/fcr Sediment control and fodder yield increase in alfalfa (Medicago sativa L) T production with tied-ridge-furrow rainwater harvesting on sloping land ⁎ Qi Wanga, , Fuchun Lib, Dengkui Zhanga, Qinglin Liuc, Guang Lid, Xiaoni Liua, Xiaoling Lie, Jin Chenf a College of Grassland Science, Gansu Agricultural University, Lanzhou, 730070, China b Tongwei County Agricultural Technology Extension Center, Dingxi, 743300, China c Agronomy College, Gansu Agricultural University, Lanzhou, 730070, China d College of Forestry, Gansu Agricultural University, Lanzhou, 730070, China e College of Water Conservancy and Hydropower Engineering, Gansu Agricultural University, Lanzhou, 730070, China f Dingxi Institute of Soil and Water Conservation, Dingxi 743000, China ARTICLE INFO ABSTRACT Keywords: Drought, water loss and soil erosion are the main factors restricting grain production and economic development Tied-ridging in the semiarid hill areas of Loess Plateau, China. A field experiment was conducted to determine the effects of Ridge-furrow rainwater harvesting different tillage systems (open-ridging and tied-ridging) on soil water moisture, runoff, sediment yield, fodder ff Runo yield and water use efficiency (WUE) on 2 slopes (5° and 10°), using traditional planting (without ridges and Sediment furrows) as a control, during 2 consecutive alfalfa growing years: 2015 and 2016. Results indicated that the Alfalfa fodder yield benefits of fodder yield and WUE increase from tillage system were more effective than the benefits from slope gradient on slight sloping land. Open-ridging and tied-ridging decreased runoff and sediment transport and increased soil moisture, fodder yield and WUE of alfalfa.
    [Show full text]
  • China Human Rights Report 2017》
    臺灣民主基金會 Taiwan Foundation for Democracy 本出版品係由財團法人臺灣民主基金會負責出版。臺灣民主基金會是 一個獨立、非營利的機構,其宗旨在促進臺灣以及全球民主、人權的 研究與發展。臺灣民主基金會成立於二○○三年,是亞洲第一個國家 級民主基金會,未來基金會志在與其他民主國家合作,促進全球新一 波的民主化。 This is a publication of the Taiwan Foundation for Democracy (TFD). The TFD is an independent, non-profit foundation dedicated to the study and promotion of democracy and human rights in Taiwan and abroad. Founded in 2003, the TFD is the first democracy assistance foundation established in Asia. The Foundation is committed to the vision of working together with other democracies, to advance a new wave of democratization worldwide. 本報告由臺灣民主基金會負責出版,報告內容不代表本會意見。 版權所有,非經本會事先書面同意,不得翻印、轉載及翻譯。 This report has been published by the Taiwan Foundation for Democracy. Statements of fact or opinion appearing in this report do not imply endorsement by the publisher. All rights reserved. No portion of the contents may be reproduced in any form or by any means without prior written permission of the publisher. 臺灣民主基金會 Taiwan Foundation for Democracy 臺灣民主基金會 Taiwan Foundation for Democracy 《China Human Rights Report 2017》 Contents Foreword..................................................................................................... i Preface........................................................................................................ 1 Human Rights Dialogue and Confrontation between China and the West during 2017 ................................................................................. 29 Political Human Rights ...........................................................................
    [Show full text]
  • People's Republic of China: Gansu Urban Infrastructure Development
    Technical Assistance Consultant’s Report Project Number: 44020 March 2012 People’s Republic of China: Gansu Urban Infrastructure Development and Wetland Protection Project FINAL REPORT (Volume V of V) Prepared by HJI Group Corporation in association with Easen International Company Ltd For the Gansu Provincial Finance Bureau This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and ADB and the Government cannot be held liable for its contents. (For project preparatory technical assistance: All the views expressed herein may not be incorporated into the proposed project’s design. Gansu Urban Infrastructure Development and Supplementary Appendix 11 Wetland Protection Project (TA 7609-PRC) Final Report Supplementary Appendix 11 Dingxi Subproject Environmental Impact Assessment Report ADB Gansu Dingxi Urban Road Infrastructure Development Project Environmental Impact Assessment Report Gansu Provincial Environmental Science Research Institute, Lanzhou August 2011 Environmental Impact Assessment for ADB Urban Infrastructure Development Project Dingxi TABLE OF CONTENTS I. OVERVIEW .................................................................................................................................... 1 1.1 Evaluation Criterion ............................................................................................................ 1 1.1.1 Environmental Function Zoning .............................................................................. 1 1.1.2 Environment Quality Standards
    [Show full text]
  • TACR (4 of 5): People's Republic of China: Gansu Urban Infrastructure
    Technical Assistance Consultant’s Report Project Number: 44020 March 2012 People’s Republic of China: Gansu Urban Infrastructure Development and Wetland Protection Project FINAL REPORT (Volume IV of V) Prepared by HJI Group Corporation in association with Easen International Company Ltd For the Gansu Provincial Finance Bureau This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and ADB and the Government cannot be held liable for its contents. (For project preparatory technical assistance: All the views expressed herein may not be incorporated into the proposed project’s design. Gansu Urban Infrastructure Development and Supplementary Appendix 8 Wetland Protection Project (TA 7609-PRC) Final Report Supplementary Appendix 8 Dingxi Subproject Resettlement Plan GANSU URBAN INFRASTRUCTURE DEVELOPMENT AND WETLAND PROTECTION PROJECT Dingxi Urban Infrastructure Development Component (ADB No: -PRC) RESETTLEMENT PLAN Dingxi ADB Project Management Office 30 March 2012 Gansu Urban Infrastructure Development and Wetland Protection Project Dingxi Component Abbreviation ADB Asian Development Bank APs Affected Persons AV Administrative Village HH Household CRO Client Resettlement Office DPMO Dingxi Project Management Office DUCIAM Dingxi Urban Construction & Investment and Asset Management Ltd Co. mu 1mu = 0.006 ha PAH Project Affected Household PAP Project Affected Person PRO Project Resettlement Office RMB China yuan, the unit of Chinese currency RP Resettlement Plan SES Social Economic Survey Twp Township
    [Show full text]
  • Resettlement Policy Framework
    RP1662 REV World Bank-financed Poverty Alleviation and Public Disclosure Authorized Agriculture Development Demonstration in Poor Areas Project Public Disclosure Authorized Resettlement Policy Framework Public Disclosure Authorized China State Council Leading Group for Poverty Alleviation and Development Foreign Capital Project Management Center Public Disclosure Authorized November 2014 Table of Contents Executive Summary .................................................................................................... 1 A. Project Overview, Principles and Rationale for a Resettlement Policy Framework.................................................................................................................... 4 B. Framework for Land Acquisition .......................................................................... 7 B1. Objectives and Relevant Terms of the Policy Framework ............................. 7 B2. Preparation and Approval of Resettlement Action Plans ............................... 8 B3. Institutional and Legal Framework .................................................................. 11 B4. Implementation Process.................................................................................... 13 B6. Budget Arrangements........................................................................................ 14 B6. Public Participation and Information Publication ........................................... 14 C. 4. Land Transfers and Use of Land as Shares ........................................... 15 D. Complaint
    [Show full text]
  • 150 Million Meals Donated China
    January-March 2009 Total Meals Donated as of March 31st: 150,563,400 150 Million Meals Donated Nourish the Children was founded in June 2002 by Nu Skin with a mission of saving malnourished children around the world. In just over 5 years NTC surpassed 100 million meals donated. Now having topped 150 million meals, we are well on our way to exceeding the next 100 million in just 3 years—by the end of 2010. Nourish the Children is an innovative partnership between a company and charities that was awarded Where Did Your Donations Go? the American Business Award for Best Corporate Social Destination Meals Responsibility Program in 2007. Africa 94 million Southeast Asia 25 million The food given through Nourish the Children is China & N. Asia 23 million VitaMeal® which was formulated specifically for Americas 5 million malnourished children with 25 vitamins and minerals. Middle East 1 million Other 2 million VitaMeal is produced in Malawi where the food plant Total 150 million can provide income for hundreds of workers and farmers and in China so that the food can reach Where they were needed most! children in China, Indonesia, Philippines, Thailand, etc. China Gansu Province Report “The reaction of kindergarten children to cooked VitaMeal was excellent. Some said the color of the food resembled chocolate. Some said that the food was like ‘Eight-Jewel Porridge.’ In no time, the children finished the food in their bowls. The VitaMeal donated by the Provincial Women’s Federation was very good for the growth of the ‘left – behind’ children, especially for the children who grew up in the rural mountainous areas where good nutrition is the exception.
    [Show full text]
  • World Bank Document
    Gansu Revitalization and Innovation Project: Procurement Plan Annex: Procurement Plan Procurement Plan of Gansu Revitalization and Innovation Project April 24, 2019 Public Disclosure Authorized Project information: Country: The People’s Republic of China Borrower: The People’s Republic of China Project Name: Gansu Revitalization and Innovation Project Loan/Credit No: Project ID: P158215 Project Implementation Agency (PIA): Gansu Financial Holding Group Co. Ltd (line of credit PPMO) will be responsible for microcredit management under Component 1. Gansu Provincial Culture and Tourism Department (culture and tourism PPMO) will be responsible for Component 2 and 3. The culture and Public Disclosure Authorized tourism PPMO will be centrally responsible for overseeing, coordinating, and training its cascaded PIUs at lower levels for subproject management. Both PPMOs will be responsible for liaison with the provincial PLG, municipal PLGs, and the World Bank on all aspects of project management, fiduciary, safeguards, and all other areas. The project will be implemented by eight project implementation units (PIUs) in the respective cities/districts/counties under the four prefecture municipalities. They are: Qin’an County Culture and Tourism Bureau, Maiji District Culture and Tourism Bureau, Wushan County Culture and Tourism Bureau, Lintao County Culture and Tourism Bureau, Tongwei County Culture and Tourism Bureau, Ganzhou District Culture and Tourism Bureau, Jiuquan City Culture and Tourism Bureau and Dunhuang City Culture and Tourism Bureau. Name of Components PIUs Gansu Financial Holding Group Co. Ltd (line of credit Public Disclosure Authorized PPMO). GFHG is designated as the wholesaler FI to handle Component 1. Under the direct oversight and Component 1: Increased Access to Financial management of the line of credit PPMO (GFHG), Bank Services for MSEs of Gansu is designated as the 1st participating financial institution (PFI) to handle micro- and small credit transactions.
    [Show full text]
  • Farmers' Rural-To-Urban Migration, Influencing Factors and Development Framework: a Case Study of Sihe Village of Gansu, China
    International Journal of Environmental Research and Public Health Article Farmers’ Rural-To-Urban Migration, Influencing Factors and Development Framework: A Case Study of Sihe Village of Gansu, China Libang Ma *, Meimei Chen, Xinglong Che and Fang Fang Department of City and Resources, College of Geography and Environmental Science, Northwest Normal University, Lanzhou 730000, China; [email protected] (M.C.); [email protected] (X.C.); [email protected] (F.F.) * Correspondence: [email protected]; Tel.: +86-931-797-1754 Received: 24 January 2019; Accepted: 6 March 2019; Published: 10 March 2019 Abstract: Farmers are the major participants in rural development process and their willingness to settle in urban areas directly affects the implementation of rural revitalization strategy. Based on Ostrom’s institutional analysis and development (IAD) framework, we analyzed farmers’ willingness to settle in urban areas and its influencing factors by binary Logistic regression and cluster analysis of survey data of 190 rural households in Sihe village of Gansu Province of China. The results show that: (1) In Sihe village, farmers’ willingness to settle in urban areas was low in general and influenced by their neighbors’ decisions or behaviors. Households willing and unwilling to migrate to urban areas both presented significant spatial agglomeration. (2) The factors influencing farmers’ willingness to settle in urban areas were analyzed from six aspects: individual characteristics, family characteristics, residence characteristics, cognitive characteristics, institutions, and constraints. The main influencing factors were found to be age, occupation, number of non-agricultural workers in the family, household cultivated land area, annual household income, house building materials, degree of satisfaction with social pension, homestead and contracted land subsidies, income constraints, and other constraints.
    [Show full text]
  • Download 363.93 KB
    Forestry and Ecological Restoration Project in Three Northwest Provinces (RRP PRC 40684) Project Administration Manual Project Number: 40684 Loan and/or Grant Number(s): L2744/G0250 March 2016 People's Republic of China: Forestry and Ecological Restoration Project in Three Northwest Provinces Contents I. PROJECT DESCRIPTION 1 A. Rationale 1 B. Impact and Outcome 3 C. Outputs 3 D. Special Features 5 II. IMPLEMENTATION PLANS 6 A. Project Readiness Activities 6 B. Overall Project Implementation Plan 7 III. PROJECT MANAGEMENT ARRANGEMENTS 9 A. Project Implementation Organizations – Roles and Responsibilities 10 B. Key Persons Involved in Implementation 11 C. Project Organization Structure 12 IV. COSTS AND FINANCING 13 A. Cost Estimates by Expenditure Category, Component and Financier 20 B. Allocation and Withdrawal of (Loan and/or Grant) Proceeds 17 C. Contract and Disbursement S-curve 18 D. Fund Flow Diagram 19 V. FINANCIAL MANAGEMENT 20 A. Financial Management Assessment 20 B. Disbursement 20 C. Accounting 22 D. Auditing 23 VI. PROCUREMENT AND CONSULTING SERVICES 23 A. Advance Contracting and Retroactive Financing 23 B. Procurement of Goods, Works and Consulting Services 24 C. Procurement Plan 25 D. Consultant's Terms of Reference 30 VII. SAFEGUARDS 32 VIII. GENDER AND SOCIAL DIMENSIONS 37 IX. PERFORMANCE MONITORING, EVALUATION, REPORTING AND COMMUNICATION 33 A. Project Design and Monitoring Framework 33 B. Monitoring 36 C. Evaluation 37 D. Reporting 37 E. Stakeholder Communication Strategy 37 X. ANTICORRUPTION POLICY 37 XI. ACCOUNTABILITY MECHANISM 38 XII. RECORD OF PAM CHANGES 38 Project Administration Manual Purpose and Process The project administration manual (PAM) describes the essential administrative and management requirements to implement the project on time, within budget, and in accordance with government and Asian Development Bank (ADB) policies and procedures.
    [Show full text]
  • Gansu WLAN Hotspots 1/11
    Gansu WLAN hotspots NO. SSID Location_Name Location_Type Location_Address City Province 1 ChinaNet Jinlun Hotel Hotel Political way No.3 LanZhou Gansu 2 ChinaNet Nanjing lying Zhuang Hotel Hotel TianShui Road No.20 LanZhou Gansu 3 ChinaNet LanZhou Oriental Hotel Hotel TianShui Road No. 523 LanZhou Gansu 4 ChinaNet Haitian Hotel LanZhou Hotel Xijin Road No. 678 LanZhou Gansu 5 ChinaNet Yinxin Building Hotel PingLiang Road, No. 396 LanZhou Gansu 6 ChinaNet Cui Ying Building Hotel TianShui Road No. 226 LanZhou Gansu 7 ChinaNet Palace Hotel Hotel AnNing WestRoad, No. 515 LanZhou Gansu 8 ChinaNet Flying Hotel Hotel TianShui Road No. 529 LanZhou Gansu 9 ChinaNet Sunshine Building Hotel QingYang Road, No. 428 LanZhou Gansu 10 ChinaNet Jinjiang sunshine Hotel Donggang West Road No. 481 LanZhou Gansu 11 ChinaNet lanDa Technology Square Emporium TianShui Road, No. 248 LanZhou Gansu 12 ChinaNet TeDa Business Hotel Hotel BaiYing Road, No. 383 LanZhou Gansu 13 ChinaNet Computer LanZhou City Emporium Weiyuan Road Nankou LanZhou Gansu 14 ChinaNet LanZhou Friendship Hotel Hotel Xijin West No.16 LanZhou Gansu 15 ChinaNet Togane Hotel Hotel GanNan Road, No.349 LanZhou Gansu 16 ChinaNet LanZhou University School TianShui Road,No. 222 LanZhou Gansu 17 ChinaNet Provincial Organization Department hostels Hotel DongGang West Road, No. 543 LanZhou Gansu 18 ChinaNet TianQing Shennong Ecological Park Entertainment 51 New villege No.19-1 DiaoYing Gou LanZhou Gansu 19 ChinaNet The past is still Cafe Entertainment Plaza West Side LanZhou Gansu 20 ChinaNet Silver Peak Hotel Hotel North Binhe Road No.8 LanZhou Gansu 21 ChinaNet Health School School Dong Gang WestRoad,No.4 LanZhou Gansu 22 ChinaNet Trade and Industry Building Business Building ZhangYe Road, No.
    [Show full text]