MONTHLY OPERATIONAL SUMMARY

OF BANK AND IDA PROPOSED PROJECTS (As of May 31, 1983) SecM83-597 1 FROM: Vice President and Secretary June 17, 1983 CONTENTS

Section Page

I. - Eastern Africa 1 - 13 Public Disclosure Authorized II, - Western Africa 14 - 29 III. - East Asia and Pacific 30 - 40 IV, - South Asia 41 - 51 V. - Europe, Middle East and North Africa 52 - 66 VI. - Latin America and Caribbean 67 78 VII, - New Projects 79 82

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~1./ Lender];/ Procurement ii

I, EASTERN AFRICA

BOTSWANA Public Disclosure Authorized (WATER UTILITIES 22.0 (R) Water Supply III - Raising of Board presentation'scheduled for· CORPORATION) (Bank) Gaborone dam and expansion of July 5, (Co-financing with CDC treatment facilities to meet agreed for $10.8 million.) Gaborone's near-term water supply requirements; site Procurement: Main contract of investigations and preliminary about $30 million awarded for design for two future dams, raising dam. Total project cost estimated at $50 million,

Ministry of Health About Family Health - Improve Appraisal mission scheduled for 11.0 effectiveness of health June, Bank Project Preparation (Bank) services delivery by Facility advance of $480,000 strengthening critical approved to finance specialists components of health systems, and employ project manager to including maternal and child help Ministry of Health prepare health and family planning. project and carry out preliminary Total project cost to be study of health organization, determined.

Public Disclosure Authorized Botswana Development About DFC II - Line of credit to Appraisal report under Corporation and 12.0 Botswana Development preparation. National Development (Bank) Corporation and National Bank Development Bank for subprojects in various sectors; and technical assistance to strengthen NDB's capacity for promoting small and medium-sized enterprises, Total project cost to be determined.

!/ If the Government is the borrower, the name of the department, ministry or agency which is to implement the pr~ject is given. If the Government is to relend the proceeds to another entity, the name of that entity is given. If the Government is not the borrower, the borrower's name is given in capital letters in parentheses. 2/ The amount is in millions of U,S. dollars and is approximate and tentative, 11 The le.tter (N) before the project means that the project is a new listing in the Summary; the letter (R) means that the information about the project has been revised since the last issue of the Summary, Section VII of the Summary contains a recapitulation of the new projects listed in this issue, Public Disclosure Authorized Thie column contains available information, if any, about· action with respect to the procurement of goods and services expected to be financed by the Bank or IDA. Distribution:

Executive Directors and Alternates President Senior Vice Presidents Senior Management Council Vice Presidents, IFC Directors and Department Heads, Bank and IFC - 2 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and·Action on ~y Lender Y Procurement 4/

BURUNDI

Ministry of About Water Supply II - Feasibility study is underway, Rural 15.0 Rehabilitation of 48 rural IDA Project Preparation Facility Development (IDA) aqueducts. Total project cost advance of $470,000 approved to to be determined. complete preparation.

Ministry of 15.8 (R) Education III - Expansion of Approved by the Executive National (IDA) basic education and junior Directors on May 10. Credit Education secondary education. Total signed on June 9. project cost $19.3 million.

Ministry of About Technical Assistance - Appraisal'report under Planning 5.0 Improving efficiency of public preparation. (IDA) sector enterprises and project preparation and monitoring capabilities. Total project cost to be determined.

Ministry About Agriculture Muyinga - Pilot Project under preparation, of Agric_ulture 15.0 settlement scheme and (Priority of project to be (IDA) development of coffee and reassessed in context of sector foodcrop production in the review.) Muyinga province. Total project cost to be determined.

Ministry of About Agricultural Services. Total Project under preparation. Agriculture 10.0 project cost to be determined. (IDA)

COMOROS

Ministry of 2.3 (R) DFC I - Line of credit for Negotiations completed, Credit Finance and (IDA) financing of agroindustry and approved by the Executive Plan small-scale industry. Directors on June 2,

Ministry of About Rural Development - Land Project under preparation. Production 5.0 conservation and reafforesta­ (Co-financing with !FAD agreed,) and Industrial (IDA) tion and agricultural develop- Development .ment.

Ministry of About (R) Population - Health infrastruc­ Negotiations postponed to Public Health 2.7 ture and technical assistance mid-June at Government's request. (IDA) for population activities. Total project cost estimated at $3.0 million DJIBOUTI

·Ministry of About (R) Urban Sites and Services, .Preparation mission in the Public Works/ 8.0 Housing Develop~ent, urban field, An IDA Project District of (IDA) facilities, support for small­ Preparation Facility advance of Djibouti scale industry, artisans! $500,000 has been approved to enterprise and training, Total finance primarily consultants' project cost about $20.million. services.

Ministry of National About Human Resources - Possible Project under identification. Education, Youth and 6.0 components include secondary Sports (IDA) technical education, training, health services, etc. I ETHIOPIA

I Ministry of To be Livestock Development and Preparation report to be revised I Agriculture deter- Marketing - sector credit for on completion of Government's mined further livestock development, comprehensive review of livestock (IDA) sector.

See page 1 for footnotes. - 3 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~y Lender~/· Procurement 4/ ETHIOPIA (Cont'd)

Ministry of 20.0 (R) Urban Development I - Upgrading Approved by the Executive Public Works (IDA) of existing settlements in Directors on May 17. & Housing Addis Ababa with basic services and house improvement.loans and· development of new sites for self-help housing construc­ tion. Total project cost is $26.8 million net of taxes and duties, of which $7.5 million is foreign exchange.

(ETHIOPIAN To be Power III - Electric Preparation work underway. IDA ELECTRIC LIGHT deter­ transmission and possibly Project Preparation Facility AND POWER mined hydroelectric generation advance of $500,000 has been AUTHORITY (EELPA)) (IDA) facilities. approved to finance consulting services.

(ETHIOPIAN 70.0 (R) Roads VIII - Second phase of Negotiations substantially TRANSPORT (IDA) 1978/82 Road Sector Program. completed. CONSTRUCTION) To improve and expand the road network; strengthen road IDA Project Preparation Facility maintenance operations and road advance of $500,000 approved to sector institutions. finance consulting services to facilitate an early start-up of the project.

Ministry of 60.0 (R) Coffee Processing II and Documents under review. IDA Coffee and Tea (IDA) Marketing~ Second· phase of the Project Preparation Facility Development ongoing coffee processing advance of $700,000 approved to project. Total project cost is finance consultancy services, the $89.6 million net.of taxes and establishment of workshops and duties, of which $18.3 million other activities designed to is foreign exchange. facilitate an immediate start of the project.

Ministry To be Peasant Agriculture Development Preparation work underway. of deter­ I - Support for expansion and Agriculture mined intensification of integrated (IDA) agricultural services, including construction of rural roads, seed multiplication programs; provision of training facilities in selected areas.

Ministry of Mines 7.0 (R) Petroleum Exploration Promotion Negotiations substantially and Energy (MME) (IDA) - Geophysical surveys, completed. Board presentation on reprocessing of seismic data; June 14. IDA Project Preparation technical assistance to Facility advance of $1,000,000 Ministry of Mines and Energy. approved to finance exploration, Total project costs net of legal and accounting consultants taxes and duties estimated at to prepare the project. $9.4 million, of which $8.3 million is foreign exchange.

Ministry of To be (R) Agricultural Research - Appraisal mission scheduled for Agriculture deter- btrengthening of the research June/July. mined capacity of the Institute of (IDA) Agricultural Research of Ethiopia.

Telecommunications To be Telecommunications VI - To Appraisal report being prepared. Services of Ethiopia deter- improve and expand (Co-financing is being sought.) mined telecommunications services. (IDA)

Government of To be Education VI - Basic·education Project preparation underway. Ethiopia deter- and teacher training. mined IDA See page 1 for footnotes. - 4 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on .Y!!!.':I. J./ · Lender!/ Procurement !±./ KENYA

Ministry of Works 7.0 (R) Urban (Secondary Towns) - Negotiations completed. Board and Housing/Ministry (Bank) Extension ·of urban development presentation on June 16, of Local Government, 22.0 programs to smaller towns. and Local (IDA) Total project cost estimated at IDA Project Preparation Facility Authorities $37.4 million, advance of $1,0 million approved to finance consultant's fees for detailed design and engineering, technical assistance and training,

(INDUSTRIAL 20.0 (R) IDB V - Fifth line of credit to Project under preparation, DEVELOPMENT (IDA) IDB and Commercial Bank. BANK)

Ministry of 40.0 Cooperative Credit - Components Project preparation underway. Agriculture (IDA) to be identified,

(KENYA POWER 12.0 Power IV (Olkaria) - Third 15 Approved by the Executive COMPANY) (Bank) MW unit for the geothermal Directors on February 8. power station at Olkaria, with (Project being co-financed with associated auxiliaries and CDC $9,0 million equivalent and other necessary civil works. EIB $8,8 ·million equivalent.) Total project cost estimated at about $41.3 million.

(TANA AND ATHI About (R) Power V (Kiamb~re) - Civil Negotiations in progress. RIVERS DEVELOPMENT 116.0 works including powerhouse with (Substantial co-financing AUTHORITY) (Bank) two 70 MW units and associated required.) mechanical and electrical equipment, Total project cost Bank Project Preparation Facility estimated at $548,1 million. advance of $250,000 approved to finance consultants' fees to' update and revise project cost estimates and retain a panel of experts to provide independent technical advice until the project is approved and effective,

Ministry of 15.0 (R) .National Extension: Extension Negotiations completed. Board Agriculture (IDA) Services would be reorganized presentation on June 14, (!FAD in accordance with Training and expected to provide co­ Visit System, Total project financing.) cost estimated at $28,6 million. IDA Project Preparation Facility advance of $1,0 million approved to finance critical start-up activities and technical assistance.

(E.A. OIL About Energy - Engineering Studies: Project processing postponed at REFINERY) 6.1 Engineering and feasibility request of Government. (Bank) studies for refinery conversion, Total project cost estimated at $12.6 million,

(E.A. OIL - About Energy II (Refinery) - Refinery Project preparation awaiting REFINERY) 50.0 Conversion: Installation of outcome of engineering studies (Bank) secondary processing facility, mentioned above. (Co-financing and IFC participation being sought,)

Ministry of Energy About Energy Engineering (Geothermal). Preparation work underway. 10.0 - Exploration, development (Bank) drilling, and geothermal studies for several sites.

See page 1 for footnotes. - 5 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~y Lender]/ Procurement 4/ KENYA (Cont'd)

Ministry of 27.0 Highways Sector II: Road· Project under preparation. Transport and (Bank) maintenance, construction, Communications 63.0 training and pilot program to (IDA) develop private domestic construction capability and­ traffic enforcement.

Ministries of Works, About (R) Highways IV - Resurfacing and Appraisal mission tentatively and Transport and 17.0 rehabilitation of about 150 km scheduled for September. Communications (IDA) of paved roads not designed for (Co-financing with AfDB current levels of traffic. tentatively agreed for about $10 Continued technical assistance million.) for labor-intensive road construction and maintenance. IDA Project Preparation Facility Total project cost estimated at advance of $300,000 approved for $32 million. consultants to undertake engineering studies required to complete project 'preparation.

Lesotho National About DFC III - Third line of Credit Project to be defined. Development 10.0 to Lesotho National Development Corporation (IDA) Corporation. Total project cost to be determined.

Ministry of Health About (R) Population/Health/Nutrition - Appraisal mission tentatively and Social Welfare 3.0 Technical assistance to scheduled for September. (IDA) strengthen planning, financial management, and manpower development in the sector. Total project cost to be determined.

Ministry of About (R) Education IV - Provision of Project under preparation. Education 10.0 primary school classrooms (IDA) mainly in poorly-served areas; training in educational management; upgrading of vocational and technical teaching. Total project cost to be determined. MADAGASCAR

Ministry of About Rural Development Fund to Project under preparation by Agriculture l:Z.O finance village-level Government, with assistance from Production (IDA) infrastructure, such as RMEA. irrigation systems, feeder roads, collective storage facilities, and village water supply systems; training; and establishment of central project management unit.

Dire~torate General About (R) Urban I - Technical and Appraisal mission in the field. of Planning and 15.0 financial strengthening of Municipalities of (IDA) municipalities; demonstration IDA Project Preparation Facility Antananarivo and upgrading in Antananarivo ana advance of $150,000 approved to Toamasina. Toamasina; employment and assist in the further preparation income generation; traffic of the project. management. Total project cost estimated at about $18 million.

Ministry of 18.0 "(R) Lac Alaotra II - Intensifica­ Credit signed on May 10. Agriculture (IDA) tion of cultivation' in Lac (Co-financing agreed with FAC, Production Alaotra area (mainly rice). $4.4 million, and with CCCE, Includes seed production, $10.0 million.) marketing, irrigation Dllj.in­ tenance, extension, and IDA Project Preparation Facility assistance to SOMALAC. Total advance of $1.0 million approved. project cost estimated at $38.4 to finance construction and million. equipment.

See page 1 for footnotes. - 6 -

Member Country, and Borrower or Amount & Stage of-Process­ Implementing Probable ing and Action on ~y Lender Y Procurement 4/ MADAGASCAR (Cont'd)

Ministry of Public About (R) Highways VI - Resurface and Negotiations completed. Board Works 45.0 rehabilitate paved roads and presentation scheduled for June (IDA) strengthen the Ministry of 23. (Co-financing with AfDB for Works maintenance capability. $16.0 million, and !FAD for $1.4 Total project cost estimated at million probable.) $77 .87 million.

Ministry of About Irrigation Rehabilitation - Project under preparation. Agriculture 20.0 Strengthening of national Production (IDA) system for operation and maintenance of efficient network, and rehabilitation of networks.

(BANKIN' NY About (R) Industrial Sector - Credit Pre-appraisal mission in the INDOSTRIA (NATIONAL 15.0· through Bankin' NY Indostria field. INDUSTRIAL (IDA) (BNI). DEVELOPMENT BANK) (BNI))

Ministry of · About (R) Cotton - Sllll'llholder cotton Appraisal report being reviewed. Agriculture 15.7 development and ginnery (Co-financing with CCCE being Production (IDA) modernization. explored.)

Ministry of Health 6.8 (R)' Health - Improve.health Credit signed on May 20. (IDA) services, with particular attention to administrative, health planning, and drug distribution. Total project. cost estimated at $7.5 million.

Ministry of To be (R) Structural Adjustment Credit Appraisal mission in the field. Finance deter­ II. mined (IDA)

Ministry of 10.6 (R) National Rural Development Credit signed on May 20. Agriculture and (IDA) Program IV - Expansion of NRDP Natural Resources concept into new developing areas - Dedza Hille and Lilongwe North-East. Total project cost estimated at $12.5 million. Ministry of Works About (R) Highways V - Highway mainten­ Appraisal report under and Supplies 15.0 ance, road construction; third preparation. (Co-financing with (Bank) phase of District Roads ODA and AfDB being explored.) 26.9 Improvement and Maintenance (IDA) Program. Total· project cost IDA Project Preparation Facility estimated at· $88.2 million. advance of $360,000 approved to finance detailed engineering designs. Viphya l'ulp and 15.0 (R) Wood Industries Project - Appraisal mission scheduled for Paper Corporation (Bank) Construction of a sawmill and September/October. (Co~financing wood panel mill, including with KfW Germany, and ODA being associated infrastructure; explored.) technical assistance and train­ ing, and studies of alternative uses of the forestry resources. Total project cost estimated at $41.9 million.

Ministry of Finance About Urban I - To strengthen system Project preparation underway. 15.0 of housing finance and provide (IDA) low-cost urban housing. Total project cost to~ determined.

See page 1 for footnotes. - 7 -

Member Country, and Borrower or Amount & Stage of.Process­ Implementing Probable ing and Action on Agency l/ ~J:./ Procurement f!/ MALAWI (Cont'd)

(INDEBANK) About Second line of credit to Project identification underway. 15.0 INDEBANK for financing of (IDA) agricultural diversification projects. Total project cost to be determined. MAURITIUS

Ministry· of Public 15. 2 (R) Road Maintenance and Negotiations completed. Board Works (Bank) Rehabilitation - Total project presentation scheduled for July cost estimated at $19.l 19. Bank Project Preparatisn million. Facility advance of $246,000 has been approved to finance engineering and economic studies.

Ministry of About (R) Education III - Post-primary Identification mission Education and 15.0 technical .schools and tentatively scheduled for Cultural Affairs (Bank) vocational education. October.

(IRRIGATION About Northern Plains Irrigation - Project being prepared. AUTHORITY) 15.0 Irrigation infrastructure for (Financing of approximately $9.0 (Bank) about 2,500 ha; provision of million by AfDB already agricultural services and provided.) inputs for about 1,200 small farmers growing sugar cane and foodcrops.

Ministry.of Finance About (R) Second Structural Adjustment Negotiations completed. Board 40.0 Loan - Second program of presentation scheduled for July (Bank) support for economic reforma 12. (SAL II).

Ministry of Finance About (R) Technical Aasistance - To be Negotiations completed. Bogrd s.o processed concurrently with the presentation scheduled for July (Bank) SAL II to provide support 12. through studies and consultant assistance for structural adjustment.

Ministry of Public· 13.0 Water Supply~ Renovation and Approved by the Executive Works and Equipment (IDA) extension of water suppiy Directors on April 12. systems in five secondary centers. Total project cost estimat~d at $16.8 million •.

(BANQUE RWANDAISE DE . 1.0 BRD III - Third line ·of Credit Approved by the Executive DEVELOPPEMENT (BRD)) (IDA) to the Deve~opment Bank of Directors on April 5. Rwanda. to·finance industrial development.'

Ministry of About (R) First Agricultural Research - Project under preparation. Agriculture 10.0 Implementat'ion of an (IDA) agricultural research program, including institutional support, and technical assistance for agriculture policy analysis. Total project cost to be determined.

Ministry of Public About (R) Health/Population·. Total Identification mission in the Health 13.0 project cost to be determined. field. (IDA)

Ministry of Post and About (R) Communications Services - Appraisal mission tentatively Communications s.o Improvement and'expansion of scheduled for August. (IDA) telecommunications and postal services. Total project cost estimated at $32.l million.

See page l for footnotes. - 8 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on .!&!!!£I. 1/ . Lender J:./ Procurement f!/ SEYCHELLES Ministry of Planning About· Ports/Land Reclamation - Project under preparation. Bank 6.0 Reclamation of land, Project Preparation Facility (Bank) improvement of fishing and advance of $300,000 approved to commercial ports, and complete project preparation, development of industrial (Co-financing with AfDB, BADEA, site. Total project cost CCCE and Kuwait Fund being estimated at $25,0 million. explored,)

SOMALIA

(SOMALI DEVELOPMENT 10.0 DFC II - Assistance to the Project preparation underway. BANK) (IDA) Somali Development Bank.

Government of To be Fisheries - Support for small Appraisal'report being prepared. Somalia deter­ fisheries development, IDA Project Preparation Facility mined including·financing of advance of $550,000·approved.to· (IDA)- infrastructure and processing complete project preparation. facilities; financial and (Co-financing being explored,) technical assistance to artisanal fisheries.

Government of 10.0 (R) Afgoi Gas Delineation - Project preparation underway. Somalia· (IDA) Exploration of gas resources (Co-financing being explored,) in the Afgoi Region, and Project Preparation Facility further technical ass~stance to advance of $1,000,000 approved to Ministry of Mineral Resources. complete project preparation,

Government of 3.0 Technical Assistance - Second Project prepara~ion underway. Somalia (IDA) Credit for technical assistance to Ministry of Planning and Ministry .of Finance.

Government of To be N.W. Agriculture II - Project preparation underway. Somalia deter- Continuation of ongoing project mined which is assisting in the (IDA) development of the North-West Region through soil and water conservation, and other measures to increase agricul­ tural production,

Government of To be Education V - To be defined, Project identification underway. Somalia deter­ mined (IDA)

Ministry of eo.o (R) Gezira Rehabilitation - Trials, Board presentation on June 16. Irrigation and (IDA) studies and rehabilitation of (Co-financing has been arranged Gezira Board capital investments aimed at with the Arab Fund for Economic improving Gezira production. and Social Development for $50 Total project costs net of million-and with Italy for $7 taxes and duties estimated at million. Additional co-financing $226.0 million, with a foreign is expected from the Saudi Fund· exchange component of $150.0 and the United Kingdom.) · million, IDA Project Preparation Facility advance of $600,000 approved to complete project preparation.

Government of Sudan To be Sugar Rehabilitation - Credit Appraisal mission scheduled for deter­ would provide assistance for July/August. (Co-financing mined rehabilitation of sugar required,) (IDA) industry and would support policy changes in the subsector generally,

See page 1 for footnotes. - 9 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing end Action on ~ll. Lender 1/ Procurement f!/ SUDAN (Cont'd)

Government of Sudan 16.0 Highways III - Technical Negotiations substantially (IDA) assistance and training in' completed, (Co-financing of $8,3 maintenance for the Roads and million agreed with USAID,) Bridges Public Corporation (RBPC) and the Southern Region Ministry of Communications, · Transport and Roads (SRMCTR); and consulting services for planning.

Government of Sudan, To be (R) Petroleum - Petroleum Project processing has been deter- development and distribution. discontinued, mined (IDA)

Government of ·Sudan· 'To 'be Power IV - Expansion of power Appraisal mission scheduled for deter- generation and transmission July/August, (Co-financing mined facilities. · required.) (IDA) Government of Sudan To be Cotton Marketing - Rehabilita­ Project identification underway, deter- tion of Rinheries and mined strengthening of cotton produc­ (IDA) tion and marketing policy institutions.

Government of Sudan 20.0 (R) Education III -Engineering and Apprabal mission :Ip the field. (IDA) vocational training; textbook production; and institutional development.

Government of Sudan so.o (R) Agriculture Rehabilitation Board presentation on June 16, (IDA) Credit II - Support to the irrigation sub-sector through provision of foreign exchange for farm inputs and technical assistance. Total project cost estimated at $50.0 million.

Government of Sudan To be Agricultural extension/research Project preparation underway, deter- - To be defined. mined (IDA)

Government of Sudan To be (N) Petroleum Technical Assistance Project·preparation underway, deter- - To be defined. I mined (IDA)

Government of Sudan .To be (N) Agriculture Rehabilitation Project identification underway. deter- Credit III - Support to the mined irrigation sub-sector. (IDA).

TANZANIA·

Ministry of 40.0 (R) Harbours I - Improvements to Appraisal report being.prepared, Communications and (IDA)· Dar-es-Salaam Port. Total (Co-financing meeting held on May Transport project cost estimated at $86 30/31), million, with foreign exchange component of about $64.0 million.

Ministry of 20.0 Education VIII - Secondary Fur.ther preparation underway, Education (IDA) education. IDA Project Preparation Facility advance of $340,000 approved to finance detailed survey of schools considered for rehabilitation under the proposed project,

See page 1 for footnotes. - 10 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on Agency l/· Lender J:./ Procurement i/ TANZANIA (Cont'd)

Tanzania Electric 35.0 (R) Power IV - Construction of an Negotiations completed. Supply Co. Limited (IDA) 80 MW hydrostation and asso­ (Co-financing expected from (TANESCO) ciated works at Mtera, and France, KfW Germany, Italy, rehabilitation of the Ubundo Kuwait Fund, NORAD and SIDA.) diesel station in Dar-es-Salaam. Total project cost estimated at $218.1 million, with a foreign exchange component of $147.3 million.

Ministry of 50.0 Highways VI - Rehabilitation/ Project being prepared. Communication and (IDA) strengthening of the Tan Zam Transport Highway, and road maint~nance.

Ministry of Minerals 6.3 (R) Coal Engineering - Approved by the Executive (IDA) Engineering services for Directors on May 19. possible development of coal deposits in southern Tanzania, Total project cost estimated at $7.0 million.

Ministry of 20.0 Sugar Rehabilitation I - Project preparation underway, (IDA) Rehabilitation of sugar (Co-financing possibilities being I Agriculture production facilities, explored,) I incorporating both estate and ' smallholder operations. Total project cost estimated at $110.0 million, with a foreign exchange component of $100 million.

Ministry of Industry 18.0 (R) Mufindi Pulp and Paper II - Approved by the Executive National Development (IDA) Technical assistance for Directors on May 19. Corporation start-up of mill; and energy (Co-financing expected from SIDA conversion facilities. Total and the Federal Republic of project cost estimated at $45,0 Germany.) million, with a foreign exchange component of $35.0 million.

Ministry of Works 30.0 Roads III - Rehabilitation of Appraisal report being prepared. (IDA) trunk roads; re-equipping of maintenance unit, technical assistance; some upgrading, and construction of vital links under consideration.

Ministry of Power, 22.0 (R) Telecommunications - Approved by the Executive Posts and (IDA) Rehabilitation of postal Directors on May 17. Telecommunications services and telecommunica­ tions.

Ministry of Planning To be Technical Assistance II - Appraisal report being prepared. and Economic deter- Second line of credit to Development mined finance services for project (IDA) preparation, feasibility studies, training, institution building. ZAIRE

GECAMINES About Gecamines II - Rehabilitation, Awaiting outcome of technical 70.0 maintenance and expansion of assistance project. (IDA) existing mining facilities. Total project cost to be determined.

See page 1 for footnotes. - 11 -

Member Country, and ·Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~ll- Lender 1/ Procurement f!/

~ (Cont'd)

Department of To be Integrated Rural Development Identification underway. Agriculture deter­ Project in Kivu Region. Total mined project cost to be determined. (IDA)

Depa,;tment of About Railways II - Track Rehabilita~ Identification mission Transportation 68.0 tion, additional wagons, tele­ tentatively scheduled for (IDA) communications and technical September, assistance training. Total project cost to be determined.

GECAMINES 7.0 (R) Gecamines TAS. Provision of Credit signing tentatively (IDA) consultant assistance to schedule4 for July. strengthen company's manage­ ment. Total project cost estimated at $9.3 million.

Department of Energy · About (R) Petroleum Exploratio~ - Negotiations in June. 4.0 Technical Assistance. Total (IDA) project cost to b~ determined.

Departm!'nt of About Education Training/Technical Project preparation underway. Primary and 10.0 Assistance - Technical Secondary Education ,(IDA) assistance for training and improvement of planning; financial management and project implementation; studies relating to education policy and the Reform of Primary and Secondary Education. Total project cost to be.determined •.

Department of To be Research/Seeds - Support for Project preparation underway. Agriculture deter- development of priority mined agriculture research programs . (IDA) and 3eed production capabil- · ity. Total project cost to be determined.

Department of To be Maize II - Development of Maize Project preparation underway. Agriculture deter- production through improved mined input supply systems and infra­ (IDA) structure support. Total project_ cost to be determined.

SOCIETE FINANCIERE To be SOFIDE VII - Line of credit to Project being prepared. DE DEVELOPPEMENT deter- SOFIDE to meet capital invest­ (SOFIDE) mined ment requirements of sub­ (IDA) projects in the agriculture, transportation and industrial sectors.

Department of About (R) SNCZ Reil Technical Assistance Appraisal mission in the field. Transportation 20.0 - Assistance for management and (Co-financing with AfDB, cpcE.and (IDA) training, provision of FAC identified.) equipment for track renewal and spare parts. Total project cost estimated at $50.0 million.

Ministry of About (R) Rural Water Supply - Provision· Approved by the Executive Agriculture and 16.0 and extension of water supply Directors on May 12. Signing Water Development (IDA/IDA in six rural districts and tentatively scheduled for ·special institution building. Total end-June. Fund) project cost estimated at $20.0 million.

See page l for footnotes. - 12 -

Member Country, and ·Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on !8!!!£I. l/ Lender 1/ Procurement f!/ ZAMBIA (Cont'd)

(Zambia Forestry and About (R) Forestry III - Strengthening Negotiations tentatively Forestry Industries 22,4 management of IPD, and scheduled for July, (Co-financing (Bank) improving its logging and tentatively agreed with FINNIDA,) Corporation, Ltd,) I . (ZAFFICO) transport activities; and rehabilitation and expansion of Bank Project Preparation Facility aawmilling capacity, Total advance of. $450,000 approved to project cost estimated at finance preparation of detailed $43,1 million. engineering designs and bidd4'g documents for wood processing and handling faci;ities,

Ministry of About (R) Fisheries - Improvement of fish Appraisal, report being prepared. Agriculture and 7,0 production systems and market­ (Co-financing with FINNIDA being Water Development (IDA) ing channels, Total project explored,) cost estimated at $20,0 million,

Ministry of About Copper Mining - Rehabilitation Appraisal report being prepared. Kines 70,0 of copper mining facilities; (Co-financing with Italian Aid (Bank) exploration ~nd training Agency being explored,) programs, technical assistance, Total project coat to be determined,

Development Bank of About (R) DPC III - Third Line of Credit Preparation mission scheduled for Zambia · 20.0 to Development Bank of Z8lllbia •. September. (Bank) Total project cost to be 10.0 determined. (IDA)

Zambia Railways 20.0 (R) Railways IV - Training, Preparation mission scheduled for (IDA) technical assistance, track July, (Co-financing to be improvement, telecommunica­ explored.) tions, rolling stock, maintenance facilities. Total project cost to be determined,

Ministry of Kines 2.0 Petroleum Exploration Project to be defined. (IDA) Development - Financing exploration activities. Total project cost to be determined.

Ministry of Kines 4,3 (R) Kaamba Coal - Technical Credit signed on Kay 23, (IDA) assistance for a technical and economic study of feasibility of reorganizing and rehabili­ tating Kaamba Collieries Ltd, (MCL) mining complex, including examination of coal pricing and marketing and MCL's training needs; provision of critical spare parts and equipment; and training, Total project cost estimated at $6 .• 1 million,

Ministry of About (R) Agricultural Services - Project preparation underway, Agriculture and 15,0 Agricultural research and Water Development (IDA) extension service support for Ministry of. Agriculture. _Total project cost to be determined,

ZIMBABWE

Ministry of Roads 26,4 (R) Highways I - Construction of 85 Approved by the Executive and Road Traffic (Bank) km of Fort Victoria-Birch Directors on Kay 17, Loan Road; 400 km of gravel roads; signing scheduled for end-June, training and studies, Total (Co-financing with BADEA agreed project cost estimated at $77,4 for about $10 million,) million,

See page 1 for footnotes, - 13 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~ll Lender J,/ Procurement !±l ZIMBABWE .(Cont'd)

Ministry of About Agricultural Sector Planning Project preparation underway, Agriculture 16.0 Project Technical Assistance, (Bank) Total project coat to be determined,

Ministry of Industry About DFC I - Line of credit to a Project identification underway, and Energy 30,0 development bank which is to be (Bank) established, Total project cost to be determined,

Ministry of Local About Urban I - Urban infrastructure Appraisal mission scheduled 'for Government and 25,0 and housing development; and July, Physical Planning (Bank) technical assistance, Total project cost to be determined.

Ministry of Natural, About (R) Rural Afforestation - Support Approved by the Executive Resources 7.3 for rural afforestation. Total Directors on May 17, Credit (IDA) project cost estimated at $10,9 signing scheduled for end-June, million,

Ministry of About (R) Technical Assistance (Staffing Negotiations substantially Transport 40,0 and Training) - Technical completed, (Bank) Assistance ·and Training for the National Railways of·Zimbabwe. Bank Project Preparation Facility Total project cost estimated at advance of $0,2 million approved $58.2 million, for updating manpower study,

Ministry of 13.1 (R) National Extension and Research Board presentation tentatively Agr ic ult ure (Bank) Project, Total project cost scheduled for July 5, (!FAD estimated at about $177,2 co-financing of $18 million million, agreed,)

Ministry of About Agriculture Sector-· Project preparation underway·, Agriculture 20.0 Agriculture services and (Bank) marketing; input supply, with particular reference to communal areas.

REGIONAL

(SOCIETE 45.0 (R) Ruzizi II - Construction of a Board presentation tentatively INTERNATIONALE DES 27 MW hydroelectric power re-scheduled for August, PAYS DES GRANDS LACS station to serve Burundi, (Co-financing with FED, EIB end (SINELAC)) Rwanda sud Zaire, Total Italy is under discussion,) project cost estimated at $84,0 million, Three advances from the IDA Project Preparation Facility totalling $195,000 were approved to finance a review of the design criteria, tender preparation, verification of cost estimates, environmental studies, engineering studies and completion of legal documents pertaining to the creation of SINELAC,

(ELECTROGAZ, About (N) Power Distribution - Network Project preparation under way, Burundi; REGIE DE 25,0 rehabilitation and·expansion Advances from IDA Project DISTRIBUTION D'EAU (IDA) for Great Lakes Region, Total Preparation Facility for cost· and ET D'ELECTRICITE; project cost to be determined, engineering studies were approved Rwanda; SOCIETE as follows: Burundi $400,000; · NATIONALE Rwanda $440,000; and Zaire D'ELECTRICITE $440,000, (SNEL), Zaire)

See page l for footnotes, - 14 -

Member Country, and Borrower or Amount r. Stage of Process­ Implementing Probable ing and Action on ~ll Lender J:.I Procurement f!/

II. WESTERN AFRICA

Government of Benin 20.0 Second phase of Seme oilfield Project under preparation. (IDA) development. (Co-financing will be sought.)

Government of Benin 3.0 Technical assistance for Appraisal mission scheduled for (IDA) economic planning, financial June/July. management and project preparation~ ··

Goverm>1ent of Benin s.o (R) Forestry - Project to Appraisal report being prepared. (IDA) strengthen the fores'try (Co-financing with Federal services, management and Republic of Germany $5.0 extension of the teak million.) plantation for timber, poles and fuelwood. Total project cost about $12.8 million.

Governmemt of Benin u.o (R) Feeder Roads III - To finance Appraisal report being prepared. (IDA) rehabilitation and construction (Co-financing being sought.) of feeder roads in Benin, and, as an interim measure, provide for the maintenance of about 2,000 km of feeder roads; provide training for equipment operators snd mechanics. Total project cost about $18.8 million.

Government of Benin To be State Enterprises - Provide Appraisal mission scheduled for deter­ studies, line of credit, July. mined technical assistance and (IDA) training to certain key state enterprises.

CAMEROON

Ministere de 20.0 Urban Development I - Squatter Approved by the Executive l'Urbanisme et de (Bank) settlements upgrading in Directors on March 15. !'Habitat Douala; commun:fty facilities in (Co-financing with Switzerland of Yaounde; technical assistance about $5.5 million.) and training.

To be determined 32.0 Wood Processing Industries. Project preparation underway. (Bank) Total cost about $37.0 million plus $10.0 million for infrastructure.

Office National du 22.s Ports III - Extension of Approved by the Executive Port (Bank) general cargo facilities, _with Directors on March 31. provision for banana handling and floating craft, and Procurement: Bid evaluation· extension of data processing report for civil works has been system. Total project cost finalized. about $33.0 million.

Ministere de 45.0· Manpower Development - Preparation underway. !'Education (Bank) Expansion of teacher training Nationale for primary and technical education, and establishing a comprehensive system of vocational training and upgrading. Strengthening of key institutions responsible for educatio_n planning and administration.

See page 1 for footnoteY. - 15 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and.Action on ~l/' Lender 1./ Procurement!!/ CAMEROON (Cont'd)

Ministere de 22.Q (R) Western Province Rural Develop­ Negotiations tentatively !'Agriculture, and (Bank) ment Project Follow-up - scheduled for August/September. Union Centrale des Increasing rural incomes and (Co-financing tentatively agreed Cooperatives du Cafe living standards through with IFAD for $15,0 million.) Agricol de L'Ouest integrated development (UCCAO) emphasizing foodcrop produc­ tion, improved coffee process­ ing, and rural infra­ structure. Extension of development services initiated during the Western Highlands I Project (Cr. 784) with _particular emphasis on improved farmers' cooperative organiza­ tion and training as means of reaching major part of provin­ cial population. Total project cost estimated at $57,3 million.

Government of 30.0 (R) Second Special Rural Develop­ Appraisal mission in the field. Cameroon (Bank) ment Fund (FSAR II) -.To extend Government's efforts for accel­ erating rural construction and development. The proposals include: a village water supply component; a line of credit for small-scale high priority rural activities, studies, infrastructure, and specific production support. Total project cost about $50.0 million.

General Delegation 22.5 (R) Agricultural Research - Appraisal mission scheduled for for Scientific and (Bank) Improving scope and application September. Technical Research of national agricultural (DGRST) research through institution building involving DGRST and crop and livestock research institutes. Particular. emphasis on training, organization, evaluation and building pre-extension linkages to regional research and development. Total project cost about $45,0 million.

CAPE VERDE

Banco de Cabo Verde s.o Line of credit for assistance Preparation mission scheduled for (IDA) to small and medium-sized September. enterprises, and technical assistance. CENTRAL.AFRICAN REPUBLIC

Ministere de 10.4 (R) Cotton Areas Integrated Rural Approved by the Executive Directors !'Agriculture et de (IDA) Development ~-Five-year agri­ on May 31. Credit signing on June 13. l'Elevage cultural development program (Cofinancing confirmed with FAC aimed at rehabilitating and $3,9 million, FED $5.8 million, improving the production-of CCCE $8.5 million, and BADEA $3.1 cotton and food crops; million.) strengthening SOCADA, the proposed executing agency. IDA Project Preparation Facility Total program cost estimated at advance of $1.0 million approved $51,2 million (of which $23.6 for specialist services and million in foreign exchange), related logistical support; including recurrent expendi­ rehabilitation of buildings; tures. vehicles and equipment and operating costs to undertake training and establish evaluation capacity.

See page 1 for footnotes. - 16 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on .!!a!!& J../ Lender J:l Procurement!!/ CENTRAL APllICAN REPUBLIC (Cont'd)

Minietere de 11.0 (R) Education II - Reorganization Approved by the Executive l'Education (IDA) and strengthening of the School Directors on May 10 and signed on Rationale Construction and Repair and May 19. Maintenance Unit to enable it to build, repair and maintain school buildings. Rehabilita­ tion of about 300 primary schools in rural areas; provi­ sion of educational materials for the rehabilitated schools; strengthening of planning and evaluation capacities of the Ministry of Education; evalua­ tion of impact of improved facilities on student achieve­ ment. Total project coat estimated at $12.2 million.

Presidency 30.0 (R) Economic Rehabilitation Program Appraisal mission scheduled for (IDA) - Financing of imports to July. assist the Government in reconstruction of government buildings and reconstitution of administrative functions, and to strengthen public enterprises; establishing line of credit and associated technical assistance for small and medium scale enterprises.

CONGO, PEOPLE'S REPUBLIC OF THE

Miniatere dee Eaux 12.0 (R) Wood Processing Project - Approved by the Executive et l!'oreta (Bank) Establishment of logging, Directors on May 31. aawmilling and veneer produc­ (Co-financing arranged with Saudi tion complex in northern Congo, European Bank for $4.4 million, and technical assistance to suppliers' credits $7.78 million, improve forestry sector manage­ and local commercial banks $3.24 ment. Total project coat esti­ million.) mated at $40.0 million, of which $28.0 million in foreign Bank Project Preparation Facility exchange. advance of $500,000 approved to finance detailed engineering for sawmill and veneer plant.

Miniatere des 11.0 (R) Technical Assistance Project - Approved by the Executive Financea/Miniatere (Bank) Technical services to help Directors on May 19. de l'Interieur/ upgrade public-finance and Miniatere des external debt management; Travaux Publics assistance to properly plan and execute urban infrastructure investments. Total project coat estimated at $14.7 million.

Societe Nstionale de · 17 .O (R) Technical Assistance and Project under preparation. Bank. distribution d'eau (Bank) Rehabilitation Project - Project Preparation Facility (S_NDE) Rehabilitation of waterworks of advance of $300,000 approved to Brazzaville, Pointe Noire, finance preparatory studies. Loubomo, Nkayi and Kinkala; and· technical assistance to SNDE to upgrade organization, staff skills and management systems.

EQUATORIAL GUINEA

Miniaterio de 10.6 (R) Rehabilitation of cocoa and Appraisal mission in the field. Agricultura, (IDA) coffee. Project prepared with financing Ganaderia y from IDA Project Preparation Deaarrollo Rural Facility advance of $200,000.

See page 1 for footnotes. ._ 17 -

Member Country, and Borrower or Amount & Stage of Process­ Implement:1.ng Probable ing and Action on ~1.l ~J:l Procurement!!/ EQUATORIAL GUINEA (Cont'd)

Hinisterio de 6.0 (N) Technical Assistance - Resident Preparation/appraisal mission in Planificacion y (IDA) experts, probably including the field. Desarrollo Economico project coordinator, legal, forestry, agricultural, external debt, and mining experts; short-term consultants for studies and project preparation; houses, vehicles, and operating expenditures to support work of experts; training of national staff. Total project cost estimated at $7.0 million, of which $5.6 million in foreign exchange. THE GAMBIA

Ministry of e.o (R) Agricultural Development Appraisal report being prepared. Agriculture (l;DA) Project - Second phase of IDA Project Preparation Facility Rural Development Project advance of $670,000 to finance (Credit 644) would include services of a cooperative support for: traditional advisor and financial advisor; farmers, including extension, and detailed architectural and input supply snd msrketing engineering designs and services on a country-wide preparation of tender documents basis; the national seed for the buildings. (Possible multiplication scheme and co-financier: IFAD $5.0 million; research into irrigated and other co-financiers yet to be upland food crops·. Total identified.) project cost estimated at $40.3· million, of which about $34.3 million in foreign exchange,

Ministry of Economic 10.0 Urban Management and· Appraisal report being prepared. Planning and (IDA) Development: (i) preparation Industrial of 700 plots serviced with IDA Project Preparation Facility Development basic infrastructure and advance of $300,000 approved to facilities (roads, water, finance the costs ·of staffing and sanitation, electricity); (it) consultants services for upgrading of two existing feasibility studies, basic settlements near project equipment, technical assistance cities; (iii) support to and preliminary detailed municipal management. engineering work needed to facilitate project preparation.

Ministry of Works & 12.0 Urban development including Project preparation. completed. Housing, or a new (IDA) upgrading in Accra and support Government in process of agency to the Accra Municipality for re-examining project in order to rehabilitation and mainten­ determine its priority in the ance. Total cost estimated at lending program. $24.2 million at pre-appraisal, of which about $12.6 million was the foreign exchange component. Cost figures will be revised at appraisal.

To be determined 20.0 Cocoa III - Replanting and Decision on project preparation (IDA) rehabilitation of existing by FAO/CP to be deferred until cocoa. areas; technical Export Rehabilitation Credit is assistance for training and finalized. institution building.

Ghana Highway 40.0 (R) Fourth Highway - Rehabilitation Feasibility and engineering Authority (IDA) of bridges and msin roads, and studies now being completed under technical assistance. IDA Project Preparation Facility advance of $1.0 million. (Co-financing will be required._)

See page 1 for footnotes.

,"";,.. .:-~.::,.·;_ ).,.• '; •\ ... ,; .: - 18 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and·Action on Asm!.1/ Lender 1/ Procurement fi/

~ (Cont'd)

Ministry of Fuel and 11,0 (R) Petroleum Exploration Promotion Approved by the Executive Power (IDA) - Technical assistance, Directors on May 24, Project. strengthening petroleum preparation financed by IDA institutions, and energy Project Preparation Facility planning assistance, Total advances of $340,000 and coat est~mated at ·$12,0 million $375,000, of.which $11,0 million in foreign. exchange,

To be determined To be Public Administration Technical Further processing awaiting deter­ Assistance ·to assist 'the review of project scope, (The mined Government of Ghana 'in Commonwealth Fund and UNDP have (IDA) atrengthening·the·management of confirmed their interest in the civil service.and improving co-financing,) its strategy for·the state enterprises ·and increasing their efficiency, : Total ·cost about $11,5 million of which $7,9 million in.foreign exchange,

Ghana Oil Palm 20,0 (R) 011 Palm II - Consolidation of Project to be re-appraised in Corporation (GOPC) (IDA) activities undertaken under the October/November, completed Oil Pal~ ·1 project through· cont:inu,ed. p~ovision of t;ec;hnical assist.ance, manage-. ment·support and -training, Extension of exist·ing ·outgrower planting program and provision for: research activ.ities, ..Total coat about $42,3 million of which about. $13,0 m:Lliion in foreisn:exchange, .

Electric Corporation 20,0 (R) Fourth.Power Distribution - Re-appraisal mission in the of Ghana (ECG) (IDA) Rehabilitation of ECG's field, (Co-financing will be distribution network, .system needed), maintenance,-technical assistance and training.. Total project cost about $37,0 million, of which. $29,5 million in foreign exchange,

State Coal Mining To be (R) Export Rehabilitation Credit - Re-appraisal mission in the Corp; Cocoa deter- Spare parts and foreign input field, (Co-financing will be Marketing Board; mined requirements of cocoa, needed,) Ghana Port Authority (IDA) forestry, gold mining sectors, ports; and technical assistance,·

Bank of Ghana 40,0 (R) Reconstruction Import Credit - Negotiations substantially (IDA) Provision of quick-disbursing completed, Board presentation assistance to cover spare scheduled for June 28, parts, materials, equipment and (Co-financing will be needed,) other urgent· inputs in the agricultural and transport sectors.

GHAIP Oil Refinery 3,5 (R) Oil Refinery Technical . Appraisal report being prepared. c (IDA) Assistance - Studies to rehabilitate and rationalize the refinery, and to improve the product distribution,· systems.,·

Ministry of Mines 50,0 Nimba ir.on ore mining and Technical partner and manager and Geology (Bank) beneficiation with evacuation agreed, Feasibility studies are via existing facilities in being revised, Liberia,

See page l for footnotes, - 19 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~1/. Lender 1/ Procurement !!I .!1!!!!!A (Cont'd)

Ministry of 13.0 (R) Port of Conakry - Rehabilita­ Board presentation. on June 7, Transport (IDA) tion of port facilities, provi­ (Co-financing arranged with sion of cargo handling equip­ for $14,0 million, and with AfDB ment, technical assistance to Germany $6,0 million and GTZ improve port· administration and Germany $2.7 million.) operations. Total cost about $38.0 million. Procurement: All bid documents received and being evaluated.,

Ministry of Public · 1S.O (R) Highways III - Institution­ Appraisal report being prepared, Works ·(IDA) building by transformation of (Co-financing of about $42,0 existing force account brigades million.of foreign exchange is into a more autonomous project necessary,' in addition to construction unit with a· cofinancing of local costs by strengthened management struc­ USAID.) ture and stronger technical assistance; rehabilitation and maintenance of the priority network including re-gravelling. of gravel trunk roads, reha­ bilitation of·Conakry-Mamou Road and resealing of other .paved roads; training. Preparation of a transport plan. Technical assistance to Ministry of Public Works. Total cost about,$81.8 million, of which $S7.0 million in foreign exchange.

Ministry of Plann.ing 10.0 Technical Assistance.~ Planning Appraisal report being prepared, and Statistics, (IDA) and investment programming; IDA Project Preparation Facility Ministry of State project identification, advance of $200,000 financed Control, and the preparation and evaluation. project preparation. Central Bank Revision of accounting plans. External debt management,

Ministry of Mines 10.0 011 and Mineral Exploration -: A · Petroleum exploration component and Geology (IDA) geological field survey, a was appraised in March, seismic survey in the near Preparation of mineral component offshore, a mineral exploration underway, IDA Project program, and.technical Preparation Facility advance of assistance to the Ministry of $220,000 approved, Mines ·and Geology. and the National Oil Company for promotion of oil and mineral expioration,

Ministry of Housing, 10.0 (R) Conakry Urban Development.-. Appraisal report being prepared, Urban Development (IDA) Rehabil.itation of. existing, and and Domains construction·of new, drainage IDA Project Preparation Facility networks; refuse 'collection and advance.of $250,000 approved to training to improve municipal finance feasibility study, service management and.urban development planning,

GUINEA-BISSAU

Ministry of 16.0 (R) Rehabilitation and expansion of·. Board presentation scheduled for Transport (IDA) Bissau Port; ·reconstruction of· June 23,.• .(Co-financing arranged river ports and technical with BADEA $10 million, Kuwait assistance for port management · Fund $.10 million, Saudi Fund $8.5 and operations, Total .. cost million, and OPEC Fund $3 estimated at $47.5 million, million,

Ministry of Public 7.0 Rehabilitation of 500 k~ of Appraisal report being prepared. Works (IDA) paved and laterite roads; establishment·and equipment of three maintenance.districts; modernization.of ferry services, Est"-mated total., cost $13,5 million,

See page 1 for footnotes.

. ;,·::,.:. .' ; ,., .~ . - 20 -

Member Country, and Borrower or Amount & Stage of Proces~­ Implement'ing Probable ing end Action on ~ll Lender 1/ Procurement f!/ GUINEA-BISSAU (Cont'd)

Various Ministries To be Technical assistance for Appraisal mission scheduled for and Bank of deter­ macroeconomic management, September, Guinea-Bissau mined public administration and state (IDA) enterprises.

IVORY COAST .

Regie Abidjan-Niger 30.0 (R) Railways II - Realignment Appraisal processing will follow (RAN) (Bank) Petionara-Tafire; track renewal agreement on RAN's overall in Ivory Coast and Upper Volta; investment and financial locomotive maintenance rehabilitation programs, facilities; railway equipment, consulting services and training.

Energie Electrique 69.0 (R) Soubre Hydroelectric Project. Negotiations planned for de la Cote d'Ivoire (Bank) Construction of dam on June/July. (Co-financing will be Sassandra River; powerhouse, required and is being discussed civil works~ equipment, associ­ with official sources of finance ated transmission, consulting and export credit institutions.) and training services, and maintenance machine tools, Procurement: Retroactive resettlement and engineering. financing of $1.S million to be 328 MW capacity to meet growing recommended for consulting and demands in Ivory Coast. Total training services, and machine project cost in January 1982 tools. prices estimated at $519.4 million, of which $407 million in foreign exchange.

Government, SAPH 32.2 (R) Rubber Development IV - Board presentation scheduled for and SOGB (Bank) Supporting small-scale and June 23. (Co-financing arranged estate rubber production with CCCE $21,2 million and CDC activities, including main­ $14 million,) tenance of immature rubber, provision of processing facili­ ties and establishment of a further 3,900 ha,of small-scale outergrower rubber and 2,000 ha. of estates, and for research; 1,000 ha, of estate and 500 ha. of experimental planting. Total project cost estimated at $85.0 million, of which $39.3 million in foreign exchange.

Ministry of 40.0 Rural Development III (CIDT) - Project under preparation, Agriculture (Bank) North and North-West Savannah and/or CIDT Rural Development project emphasizing cotton and foodcrops, increased farm participation in marketing, input supply and credit, Complementary activities include farm modernization, spread of animal traction, and project monitoring and evaluation. Negotiations completed, Board Government of Ivory Loan to support program of 250,7 (R) presentation scheduled for July 5. Coast (Bapk) structural adjustment, Government and 35.0 (R) Forestry II - Land clearing, Appraisal mission scheduled for SODEFOR (Bank) planting and maintenance of October. 20,000 ha; maintenance of 20,000 ha planted under the first forestry project; research and pilot developments·.

See page 1 for footnotes, - 21 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~ll Lender J:l Procurement i/ LIBERIA

Ministry of Public 7,0 (R) Highways V - Road maintenance; Appraisal report being prepared, Works (IDA) technical assistance and (Co-financing is required,) fellowships, and operating costs for Ministry of Public Technical assistance will be Works, Total cost estimated at started with an advance of $.20, 5 mi.llion of which $15', 7 $340,000 from the IDA Project million in foreign exchange, Preparation Facility,

Liberian Bank for 4,0 Credit for rehabilitation of Preparation underway, Development and (IDA) industrial and related Investment enterprises, Ministry of 10,7 Bong Agriculture Development II Appraisal 'report being P.repared, Agriculture (IDA) - Expansion of existing project (Co-financing being sought,) activities in Bong County,· Total cost estimated at $22,5 m:1.11:1.on.

Ministry of Planning 10,0 Program to (a) provide techni­ Project preparation underway, and Economic Affairs (IDA) cal assistance to monitor and IDA Project Preparation Facility evaluate the 1)Srformance of advance of $500,000 approved, public sector corporations; (b) rehabilitate and introduce maintenance programs in four public sector enterprises; and (c) help the Government privatize some corporat1ons now in the public sector,

Office du Niger 7,6 (R) Two broad components (a) ;Negotiations completed, Board (IDA) Gasohol Production of ethyl presentation tentatively alcohol from surplus molasses, scheduled for July 28, Studies · modification of existing on feasibility of introducing distillation facilities and gasohol, financed by IDA Project provision of infrastructure to Preparation Facility advances of handle and store ethyl alcohol $50,000, have been completed, for eventual blending with gasoline; and (b) financing for a Rehabilitation Task Force to prepare a program of technical, financial and administrative rehabilitation of entire agency, Total cost estimated at $8,3 million of which $7,2 million in foreign exchange,

Ministers d'Etat 8,5 (R) Rural Water Supply (in the Appraisal report being prepared, charge'de (IDA) Western Region) to be executed IDA Project Preparation Facility l'Industrie et de in parallel with.IDA Health advance of $440,000 approved; l'Equipement/Direc­ Project, Components include consultants appointed to assist tion Nationale (1) drilling boreholes; (11) in the preparation of tender d'Hydraulique et de preparing well-sites; (111) documents, (Co-financing will be l'Energie du Mali installing hand pumps·; and (iv) required,) (EdM) strengthening national water directorate, Total cost estimated at $13,1 million of which $11,1 million in foreign exchange.

Compagnie Malienne 25,9 (R) Mali Sud II - (1) extension of Negotiations in June, pour le (IDA) production of cotton, maize and (Co-financing with CCCE for $11,3 Developpement des rice; (11) development of million; FAC for $4,2 million; Textiles livestock and (iii) strengthen­ IFAD for $13.0 million; and the ing of public health services, Netherlands for $4,1 million Total cost estimated at $84,0 envisaged,) million of which $59.9 million in foreign exchange,

See page 1 for footnotes, - 22"'

Member Country, and·Borrower or Amount·& Stage of Process­ Implementing Probable ing and· Action on ~J./ Lender.]/ Procurement f!/

~ (Cont'd)

Ministere de la 16,7 Rural ~ealth, comprising (1) Appraisal report being prepared. Sante (IDA) training, (11) basic health IDA Project Preparation Facility prog'ram, (iii) drug supply and advance of $1,0 million has been (iv) applied research. Total· approved to help preparation of cost estimated at $17,6 million the project. of which $8.1 million in foreign exchange.

Ministere de 17.0 (R) Education III - (a) Institution Appraisal report being prepared. !'Education (IDA) building of the Ministty of (AfDB has expr~ssed interest i~ Rationale Education through strengthening co-financing with credit of of educational and manpower approxim4tely $8,9 million,) planning capabilities; and reorganizing technical educa­ IDA Project Preparation Facility tion directorate;(b) improve­ advance of $1,0 million to assist ment of basic education through in the preparation of the pro­ education reform, teacher posed project being considered. training and adult functional literacy; and (c) livestock and agricultural junior technicians training. Total cost.estimated at $18,7 million, of which $12,9 million in foreign exchange.

Ministere de 15.0 (R) Mopti Area Development and Appraisal report being prepared. !'Agriculture; and (IDA) Livestock - (i) Agricultural (Co-financing with CCCE, DIGIS, Ministere du credit; (ii) animal traction; FAC and AfDB envisaged.) Developpement Rural (iii) improved grazing and animal traction; (iv) seed IDA Project Preparation Facil1ty production; (v) applied advance of $152,000 approved to research; and (vi) crop assist in preparing the project. protection. Will also include livestock component to follow on from ongoing livestock project. Total project cost estimated at $40.0 million.

MAURITANIA

SONADER; Ministere 8.1 Technical Assistance to the Board presentation tentatively du Developpement (IDA)· Rural Sector.. Services of scheduled for September/October. Rural permanent and short-term (Co-financing with FAC for $1,5 consultants~ Office, million.) laboratory and workshop buildings for SONADER, Total IDA Project Preparation Facility project coat estimated at $10.5 advance of $750,000 to assist·in million of which $6;5 million · financing the continustion·of the in fore~gn exchange. activities of an ongoing Technical Assistance project to the Borrower, SONADER, until the credit for the proposed project becomes effective.

SONADER 9.0 (R) Small-Scale Irrigation·~· Appraisal report being prepared •. (IDA) Development of .1,500 ha·. ·of· small irrigated perime·ters •. Total cost estimated at $ll ;4 million, of which $6.1,milliorl in foreign exchange. ·

Ministere du 10.0 (N) Livestock Development - Project being prepared. Development rural (IDA) Establishment of pastoral Appraisal mission tentatively associations, strengthening of scheduled for September. IDA livestock services, vaccina­ Project Preparation Facility tion, distribution of drugs, Advance of $250,000 approved for abatoir in Nouakchott, applied preparation of project. research. Total cost about $18.0 million, of which $11,0 million in foreign exchange.

See page· 1 for footnotes. - 23 -

Member Country, and Borrower or Amount & Stage,of Process­ Iaq,lementing Probable ing and Action on !&!!!£I. l/ ~ll Procurement !/ fil!!!!! Ministere des 23.6 (R) Highways·Iv·-·strengthening·and iloard· presentation scheduled for Trsvaux Publics (IDA) resealing of bitumen roads-, June. 28.· road maintenance construction, training of ro\old milint_enance . personnel. · Total' cost esti- . mated at $24.8 million (net .(if' taxes), of which ·$17 .• 8 million in foreign exchange. . . . '

Minister~_du Plan 7.4 (R) Technical assistance ·to · Presiden°t'B Report being . (IDA). strengthen planning, monitor­ prepared. Financing to help_ ing, and evaluation capabili­ preparation was provided by an ties·of Ministry of Plan and advance of $705,000 from the IDA technical ministr:les,Totai Project'Preparation Facility. project cqst estlmated at $8.0 millio!l, of· .which $7.0 million in foreign_ exchange.

Ministere du 21.s (R) Irrigation Rehabilitation Appraisal mission tentatively Developpement Rural (IDA) Project· - To. ·rehabilitate scheduled for October. existing irrigation works; (Co-financing being sought.) procure equipment for: maintenance and operation of Financing to help preparation was irrigation works; ·supply provided for.by an advance of agricultural inputs; .train $900,000 from the IDA Project project staff, cooperative · Preparation Facility. managers and farmers. Ministere de 6.5 Water Supply - Technical Credit signing June 13, l'Hydraulique (IDA) Assistance and Rehabtlitation. (Co-financing with UNDP for Total cost estimated at $8.2 .. $1.05 million approved), million, of which $7.5 million in foreign exchange. · IDA Project Preparation Facility advance of $330,000 was approved to finance start-up activities necessary to insure rapid project implementation.

Ministere du 10.0 Small Rural Operations - Preparation underway. Financing Developpement Rural (IDA) Small-scale irrigation and to help preparation was provided bottomland development schemes; for by an advance of $430,000 cooperative and group support from the IDA Project Preparation activities; medium term loans Facility. to farmers.

Ministere des Mines 7.5 (R) Power Sector Planning:· Study President's Report being et de l'Industrie . (Il>A) of development of power· system, prepared. technical assistance and training. Total project coat about $7.9 million, .of which $7.5 million in foreign exchange.

NIGER~A·

Federal Ministry of 138.0 (R) Kaduna State Agricult·ural Negotiations scheduled for July. Agriculture (Bank) Development would include a statewide-package of basic agricultural services to farmers, and e feeder road end rural water program.· Total co.et es~imated _at: $2~0 .million•· Federal Ministry of 41.0 Small and med1U111"."BCa~e Following negotiations, the. Indus~ries (Bank) enterprise: pilot project.· Federal.Government, NBCI and the Total c·oiit · estimated at $72'. 7· · Bank agreed to introduce some million, of which $41.0 million changes in the project in foreign exchange. · · implementation proposals. These ·are now being worked out,

Federal Ministry of 100,0 Fertilizer Manufacturing· -' Project scope is currently under Industries (Bank) Nitrogen coaiplex_at.Onne. review. If findings are Total cost estimated at· $ln7;o positive, the project will be million, of which. $615.0 · · · ·: appraised in August. million in foreign exchange. (Co-financing of $336.5 million with US and Japan EXIMBANKS.)

See page 1 for footnotes. - 24 -

Member Country, and Borrower or Amount & Stage of Procesa­ Implementing Probable ing and Action on ~y ~ll Procurement i/ NIGERIA (Cont'd)

Federal Ministry of 37,0 (R) Second Urban Development - Imo Project deferred pending Rousing (Bank) State, Total cost estimated. at agreement with Government on $87,4 million, of which $37,0 arrangements for counterpart million in foreign exchange,. funding,

Procurement: Retroactive financing of $2 million proposed to cover project start-up coats from September 1, 1980,

Kano State Water 115,0 (R) Kano State Water Supply IV - Further processing of project Resources (Bank) Expansion of water supply awaiting State Government action Engineering and facilities in Greater Kano, on outstanding project matters, Construction Agency'

Federal Ministry of 44,0 (R) Benue Urban Development. Total Appraisal mission tentatively Rousing (Bank) cost estimated at $60 million scheduled for July, of which about half in foreign exchange.

Federal Ministry of -52,0 (R) Mambilla - Agricultural Project deferred pending Agriculture (Bank) Development - To develop Government's action on land seasonal and permanent crops, tenure and other project related livestock and forestry by issues, smallholders in a high­ potential highland area through farmer services, general infra­ structure and land reform, Total cost estimated at $114,5 million,

Federal Ministry of 82,0 (R) Southern Borno Agricultural Negotiations tentatively Agriculture (Bank) Development - To strengthen the scheduled for August, existing Ministry of Agricul­ ture and Natural Resources to provide technical advice and support to farmers, Total cost estimated at $138,0 million,

Borno State Water 80,0 (R) Borno State Water Supply - Appraisal mission in the field, Board (Bank) Improvement and expansion of water supply facilities in Maiduguri and other centers, Total cost estimated at $124,0 million,

Federal Ministry of 50,0 Irrigation I - To provide Project preparation report by Agriculture (Bank) supplementary irrigation infra­ FAO/CP under review, structure and other support services for smallholder irrigated agriculture along the Hadejia-Jamaare river system in Kano, Bauchi and Borno States,

Federal Ministry of 36,0 Sokoto Health - Construction, Appraisal report being .prepared, Health (Bank) and upgrading of about 180 rural health clinics in Sokoto State; technical assistance for staff development, child immunizations, and project management· and monitoring; technical assistance to strengthen the institutional capacity of the Sokoto State and the Federal Ministries of Health,

Federal Ministries 10,0 (R) Technical Assistance for Negotiations scheduled for of Finance and (Bank) monitoring external debt, August, Planning exchange control and plan implementation, and for strengthening the Federal Office of Statistics,

See page 1 for footnotes, - 25 -

Member Country, and Borrower or Amount· & Stage of Process­ Implementing Probable ing and Action on ~1.l Lender 1:.1 Procurement 4/ NIGERIA (Cont'd)

(NIGERIAN INDUSTRIAL 120.0 (R) NIDB IV - Line of Credit for Approved by the Executive DEVELOPMENT BANK (Bank) various sub-projects, mainly in Directors on June 2. LIMITED) the areas of the building (Co-financing of $70 million materials, agro and expected with EIB and commercial intermediate goods industries, banks.) and technical assistance for NIDB to undertake sector studies. Total cost estimated at $300 million of which $185 million in foreign exchange.

Lagoa State 100.0 (R) Lagoa Solid Waste Management Negotiations scheduled for July. Government Solid (Bank) and Drain Rehabilitation Waste Disposal Board Project - To upgrade and expand Procurement: Retroactive refuse collection/disposal and financing totalling about $2,5 improve the city wide storm million is proposed for storm water drainage system for cleaning, construction during the Metropolitan Lagos. The dry season. Also construction of project would also include some depots. maintenance technical assistance to facilities and· a transfer strengthen Local Government station. Council financial operations. Total coat estimated at $183.0 million.

Federal Ministry of 50.0 (R) Forestry II - The project will Pre-appraisal mission scheduled Agriculture (Bank) (l) support an afforee.tation for June. program; (2) .establish pulpwood and timber plantations; and support to forest management in three middle belt atatea.

Federal Government 250.0 (R) Fertilizer Import Loan - To Negotiations in end-June. of Nigeria (Bank) finance part of Nigeria's foreign exchange coats of fertilizer imports and to assist Federal Government in improving the management of the fertilizer sector, including organizational and operational aspects. Total cost estimated at $723 million, of which $377 million in foreign exchange.

Nigerian National 25.0 (R) Gas Engineering and Technical Negotiations scheduled for Petroleum (Bank) Assistance Project - Design mid-July. Corporation (NNPC) engineering for a proposed Eecravoa-Lagos gaa pipeline (ELP) project. Preparation of future natural gas and liquified petroleum gas projects. Technical assistance to NNPC. Total coat estimated at $31.5 million, of which $25.0 million in f~reign exchange.

Nigerian National 150.0 (N) Eacravos Beach-Lagos Gas Project preparation underway. Petroleum (Bank) Pipeline (ELP) Project - (Co-financing of $50 million with Corporation (NNPC) Transmission pipeline and gas EIB). gathering system from the Western Niger Delta area in Lagos. Total project cost estimated at $840 million, of which $620 million in foreign exchange.

Office dee Poetee 20.0 Telecommunications II - Preparation underway. et dea (Bank) Extension of Dakar telephone Telecommunications exchanges; extension of transmission network to the South and East of country; technical assistance.

See page l for footnotes. - 26 -

Member Country, and Borrower or · Amount & Stage of Process­ Implementing Probable ing and Action on ~1,· Lender J:/ Procurement i/ SENEGAL (Cont'd)

Societe 1s.o Irrigation IV - Rehabilitation Preparation underway. (Possible d'Amenagement et (IDA) of 5,870 ha of irrigation co-financing with CCCE, IFAD, d'Exploitation du perimeters in the Senegal River Kuwait Fund and Saudi Fund,) Delta (SAED) delta; electrification of pumping stations at Rong and Boundoum; construction of a power line. Estimated total cost $72.0 million, of which $46.o million in foreign · exchange.

Government of s.2 Regional Management School - Appraisal report being reviewed. Senegal (IDA) Construction and equipment of facilities and technical assistance to facilitate the transformation of the Senegalese Management School into a Regional Management Training School for CEAO member states. Total project cost estimated at $6.2 million. Government of 1a.o CR) Water Supply II - Extension and Appraisal report being prepared. Senegal (Bank) reinforcement of water supply Additional rehabilitation 6.6 in eleven secondary centers. component under discussion. (IDA) Studies for sewerage improve­ (Co-financing arranged with CCCE ment and technical assistance. for $7,8 million; other Estimated total cost: $32.5 co-financing required.) million.

Government of 12.0 (R) Dakar Port III - Container Appraisal report being prepared, Senegal (Bank) terminal facilities at Port of (Co-financing agreed with CCCE Dakar with ancillary services. for $9,9 million and Kuwait Fund Estimated total cost $38.0 for $8,0 million,) million. Negotiations completed, Board Govemment of 11.0 (R) Technical Assiatance to Senegal (IDA) Parapublic Sector II - presentation scheduled for July 5, Continuation of technical IDA Project Preparation Facility assistance activities financed advance of up to $500,000 under the first project, approv·ed to finance technical together with modifications in advisors to prepare comprehensive light of actual experience. enterprise plans and to initiate a cycle of audits and accounting assistance to companies to be assisted under the proposed project,

Societe de· 18.5 (R) Eastern Senegal Rural Negotiations substantially Developpement des (IDA) Development - Development of completed, (Co-financing Fibres Textiles cotton, food crops and arranged with FAC for $2,9 (SODEFITEX) livestock, Other components million, CCCE for $17.5 million are feeder roads, farmers' and Saudi Fund for $3.2 million,) organization, village water supply, functional literacy, An IDA Project Preparation maize processing program, Facility advance of $400,000 has primary health program, been approved to finance training and applied research, consulting services for preparing Total project cost estimated at feasibility study for· rural $49.1 million, of which $28.3 development in East Senegal'· million in foreign exchange. Region,and to complete a project preparation report,

Government of 14.0 (R) Highway V (Maintenance) - Appraisal documents being· Senegal (IDA) Support to the Road Fund to reviewed. ensure adequate maintenanc·e of the network, Estimated total cost: $54.0 million.

Government 'i,f 1.1 (R) Phosphate Industry Development ·Approved by the executive Senegal (IDA) Engineering - Tests on Directors on May 10, phosphate slime recovery and studies on long-term An IDA Project Preparation development of phosphate Facility advance of $800,000 sector. Estimated total cost approved to finance pilot tests $9.6 million. and studies.

See page 1 for footnotes. - 27 -

Member Country, and Borrower or · Amount & Stage of .Process­ Implementing ·Probable ing and Action on ~ll. ~1.1 Procurement !ii

~ (Cont'd)

Government of 3,0 (N) Engineering Credit for Urban Appraise~ 1D1asion scheduled for Senegal (IDA) Management - Technical July, assistance/equipment to define strategy for management of urban growth which stimulates and supports productive investments; support for institutional policy/financial reforms,

SIERRA LEONE

National Power 35,0 (R) Power (Hydro) V - Development Pre-appraisal report being Authority (IDA) of Bumbuna hydro plant on Seli­ consideted, Government river, Total project cost considering timing of project, estimated at $280,0 million, of (Co-financing will be required,) which $180,0 million in foreign exchange,

Ministry of 17,0 (R) Agriculture Sector - Support Appraisal mission in the field, Agriculture and (IDA) for policy and institutional Sector report being prepared, Forea~ry reforms; technical assistance (IFAD and ADF considering to reorganize and strengthen co-financing,) Ministry's ability to deliver services to farmers,

Ministry-of 20,0 (R) Education III - Primary school Approved by the Executive Education (IDA) construction, primary teacher Directors on May 3 and signed on training, textbook procurement May 20, (Co-financing expected and distribution; training of to be provided by British ODA,) administrative staff; strengthening of Ministry of Education planning unit and project evaluation, Total project cost estimated at $27,3 million of which $10.,0 million in foreign exchange,

Government of Togo 40,0 · (R) Credit to support program of Approved by the Executive (IDA) structural adjustment, Directors on May 17,

Regie Rationale des 12,0 (R) Lome Water Supply Project - Approved by the Executive Eaux du Togo (IDA) Support to expansion of ground­ Directors on.May 3. Credit signing water production installations on June 17, (Co-financing agreed and distribution system in with Caisse Centrale $4,1 million, Lome; includes studies and OPEC Fund $4.0 million, and technical assistance, Total BOAD $3.5 million,) project cost estimated.at $27,6 million of which $21,8 million IDA Project Preparation Facility in foreign exchange, advance of $441,000 approved to finance consultants' work for final design and preparation of tender documents for project waterworks,

Office Togolaia des To be Phosphoric acid plant, Pre-feasibility study awaited, Phosphates deter­ (Co-financing will be needed,) mined (Bank).

UPPER VOLTA ..

Regie Abidjan-Niger 8,0 (R) Railways II - IDA funds would Appraisal processing will follow (RAN) (IDA) help finance Upper Volta's agreement on RAN's overall share of RAN railway project, investment and financial Total project cost estimated at rehabilitation programs, $50,6 million. of which $39,6 including satisfactory resolution.· million in foreign exchange, ·of rail extension issue.

See page l for footnotes, - 28 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~1/ Lender 1/ Procurement i/ UPPER VOLTA (Cont'd)

Ministere des 20.0 (R) Kompienga Hydroelectric First stage appraisal mission has Travaux Publics (IDA) Project. Construction of 14 MW returned. Bid documents hydroelectric station on the received. Appraisal to be Kompienga River and 300 km of completed after evaluation of transmission line to bide and calculation of economic Ouagadougou. Total cost rate of return. (Co-financing estimated at $107.0 million agreed 1n principle with: CIDA with $89.0 million 1n foreign $16.0 million; FED $9.5 mill~on; exchange. FAC/CCCE $15.0 million, KfW Germany $17 million, Saudi Fund $12.0 million, AfDB $26 million, and poe~ibly Islamic Development Bank up to maximum of $25 million,)

Ministeres du Plan, 10.0 (R) Technical Assistance - Estab­ Preparation mission tentatively et de l'Economie et (IDA) lishment of Development Invest­ scheduled for June 1984, once des Finances ment Budget to strengthen agreement is reached with investment budgeting and moni­ Government regarding toring development expendi­ implementation.organization. tures. Total project cost estimated at $10.0 million.

Ministere du 21.0 (R) Food and Fertilizer Credit - Pre-appraisal mission in June, Developement Rural (IDA) Improve the supply and pricing (Co-financing with CCCE for $5 of cereal fertilizer; million, and Germany, GTZ, for $2 strengthen the Ministry of million is envisaged,) Rural Development and develop its ~bility to better assist and supervise the regional development organizations (ORDs). Studies to strengthen the ORDe, and to determine the possibility of reducing fertilizer cost by introducing cheaper formulations, including greater use of local rock phosphate, are also included.

Ministere de la 20.0 (R) Health I - Developing a primary Appraisal mission scheduled for S~nte Publique (IDA) health care network, and November. addressing long-term issues such as implementation of an effective rural health care delivery system, provision of drugs, cost recovery measures. It would extend immunization programs, provide training and rehabilitate rural health care facilities.

Minietere de 20.0 Education III - Provide support Pre-appraisal report being l'Education (IDA) for (a) the expansion and prepared. Appraisal mission Nationale quality improvement of primary scheduled for October. education, (b) the strengthening of educational planning and administration required to implement the sector strategy and (c) improve the quality of the agricultural. training centers of rural youth.

Minietere du 5.5 (R) Mining exploration and Appraisal report being prepared, Commerce, de (IDA) technical assistance project IDA Project Prepara~ion Facility l'Industrie, et des would provide Government with advance of $80,000 approved Mines an extensive evaluation and for preliminary geological delineation of the Perkoa evaluation study of ore deposits. massive sulfide deposit that could attract potential foreign investors; e·etablieh feasibility of small-scale gold mining at Dori-Yalogo, and provide technical assistance to strengthen project preparation activities.

See page 1 for footnotes. - 29 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~1/ ·~11 Procurement !/ UPPER VOLTA (Cont'd)

Ministere des 20.0 (R) Highways V - Paving of the Appraisal mission to be scheduled Travaux Publics et (IDA) Ouagadougou-Kaya road and once agreement is reached with de l 'Urbanisme improving the Kaya-Dori road to Government on rail extension all weather standards, Total issue, which is being discussed costs are estimated at $60,6 by the Government and IDA, million, (Co-financing with Germany (KfW) and poasibly Saudi Fund is envisaged,)

REGIONAL

To be determined 25.0 Air Traffic Safety Agency Project preparation work being (Bank) (ASECNA) - Aviation Regional carried out by ASECNA, Project• To finance a part of (Co-financing with other agencies ASECNA's 1982-86 investment envisaged,) plan of over $110.0 million, comprising air navigation improvements, radio aids, meteorological equipment, telecommunications equipment, field lighting approach, navigational aids, and technical assistance,

BOAD 6.1 BOAD II - Financing of regional Loan and credit signed on (Bank) and national development June 8. 14,0 projects. (IDA)

CIMAO 15.0 CIMAO II - To strengthen finan­ Approved by the Executive (IDA) cial structure of the regional Directors on February 24 •. cement clinker plant and to (Co-financing with EIB for ~7,0 provide technical assistance million and CCCE for $12,8 for plant operations, million),

Communaute 30.0 Nangbeto Bydropower Development Appraisal report being Electrique (IDA) - Construction of Mono River in prepared. (Substantial du Benin (CEB) Togo of dam, 63 ~ powerhouse co-financing required,) and associated transmission to meet new demand in Togo and Benin; resettlement; engineer­ ing and other consulting services, and training. Total project cost, including financial charges, estimated at $173.0 million.

See page l for footnotes. - 30 -

Member Country, and Borrower or Amount & Stage of Process­ Imple111enti'13 Probable ing and Action on Aa!!!!:I. 1/ ~11 Procurement f!/

III. BAST ASIA AND PACIFIC

Ministry of 35.3 (R) Heilongjiang Agriculture - Loan and credit signed on Msy 20, · - Agriculture, Animal (Bank) Development of 200,000 ha of Husbandry an!f 45.0 uncultivated land to grow Fishery (IDA) wheat, soybeans and corn.

Ministry of Water 150.4 CR> Lubuge Hydropower - Pre-negotiation mission scheduled Resources and (Bank) Construction of a rockfill dam, for early July. (Co-financing Electric Power tunnels, and a 600 MW sought.), underground powerhouse in Yunnan Province.

Ministry of Coal 240.0 (R) Luan/Jincheng Coal - Feasibility study underway. (Bank) Development of two (Co-financing being sought.) fully-mechanized longwall underground mines of up to 4 mtpa each iq Shanxi Province.

Ministry of 84.9 (R) Polytechnic/TV University Negotiations scheduled for July. Education (IDA) Project - Strengthening of post-secondary education by support of polytechnic and the Television University.

Ministry of 220.0 Railways I - Construction, Appraisal report being prepared. Railways (Bank) upgrading and electrification of track in Kenan, Shandong and Shanxi Provinces, primarily to transport coal for export, and assistance to electric locomotive factory for production of locomotives to be used on these lines.

Ministry of 100.0 (R) Rubber Development - Replanting Appraisal report being reviewed. Agriculture, Animal (IDA) and new planting of 35-40,000 Husbandry and ha. in Guangdong Province. Fishery

Agricultural Bank of 50.0 (R) .Rural Credit - Provision of Appraisal mission scheduled for China (ABC) (IDA) credit through ABC for July. agricultural and other rural activities in selected provinces and institutional development of ABC.

Ministry of Health 85.o Medical Education and Rural Pre-appraisal mission scheduled (IDA) Health - Strengthening of for July. teaching in medical colleges and of rural health services in selected provinces.

Ministry of 100.0 (R) University Development II - Further project preparation Education (IDA) Strengthening selected mission tentatively scheduled for technical universities to September. expand_' the quantity and improve the quality of science and technical graduates.

Ministry of, - 120.0 (R) Second Ports Project - Further project preparation Communications (Bank) lfodernizing and improving cargo mission tentatively scheduled for handling-facilities in selected September. ports.

Ministry of Finance 10.0 (R) Technical Cooperative Credit - Negotiations scheduled for July. (IDA) To provide technical assistance· for the preparation of projects proposed for-Bank financing, and for other related activities.

See page l for footnotes. - 31 -

Member Country, and.Borrower or Amount & Stage of Process­ Implement:1,ng Probable ing and Action on ~!/ Lender 2,/ Procurement.!!/ FIJI

Ministry of 15,0 (R) Tree Crops - To rehabilitate Appraisal report being prepared, Agriculture (Bank) the coconut industry,

INDONESIA

Ministry of Public 30,6 (R) First East Java Water Supply - Approved by the Executive Works (Bank) Assistance for urban and rural Directors on May 3, and sign

Ministry of 146,6 (R) Maritime Transport III -To Project preparation underway, Communications (Bank) develop selected ports, and (Co-fina~cing is envisaged,) related infrastructure,

Ministry of 55,0 Watershed Development I - Project Preparation Facility Agriculture (Bank) Integrated program of advance of $463,000 approved to reforestation, soil finance consultants and mapping conservation, and related services to advance the development in Java, preparation of this project,

Ministry of Industry . 100,0 Central Java Pulp and Paper·- A Project preparation under way, (Bank) pulp and paper complex in (Co-financing is envisaged,) Central Java, It will include a pulp and paper plant and mechanical wood industries,

Ministry of ,Public. 80,0 (R) Urban V - Urban services and Appraisal mission in end-June, Works (Bank) infrastructure improvement in East Java cities,

Ministry of 80,9 (R) Nucleus Estates·sugar·- To Negotiations in mid-June, Agriculture (Bank) establish 12,600.ha of nucleus estate and smallholders sugar Procurement: Bids for sugar cane plantations in South factory have been invited, Kalimantan, and construct processing facilities with capacity of about 4-5,000 tons of cane per day,

Ministry of PUblic 70,0 Swamp Reclamation II - Appraisal report being preparel, Works (Bank) Development of 30,000 ha of low-lying lands on the south Sumatra coast to settle about 11,000 families from Java/Bali, and related program support,

Bank Pembangunan 208, 9 (R) BAPINDO V - Provision of credit Approved by the Executive Indonesia (Bank) to and institutional Directors on May 10, and signed strengthening of BAPINDO - on May 31, State Develop~ent Bank,

Ministry of 45,0 Non formal. Education II: Appraisal report being prepared, Education and (Bank) Second phase - To strengthen Culture the government agency responsible for out-of-school education,

Ministry of Mining 279,0 (R) Power XIII - Construction o.f Approved by the Executive and Energy (Bank) 500 MW Cirata hydroelectric Directors on June 2 (Co-financing power facility, including approved by CDC for $20 million, ancillary construction; and an estimated $68 million will technical assistance, studies be ~inanced by export credits, and related equipment for Government's en~rgy sector program,

Ministry.of 107,4 (R) Polytechnic II - Second phase Approved by the Executive Education (Bank) of investments on polytechnic Directors on May 26, education,

See page l for footnotes,

·.. , ...... - 32 -

Member Country, and Borrower or Amount & Stage of Process­ Implement'f.ng Probable ing and Action on ~ll Lender 1/ Procurement !!I INDONESIA (Cont'd)

Ministry of 60,0 Nucleus Estates and Smallholder Project preparation underway, Agriculture (Bank) Cotton,

Ministry of 63,3 (R) Agricultural Training III - To Negotiations completed, Board Agriculture (Agency (Bank) upgrade provincial agricultural presentation scheduled for July for Agricultural development schools, and expand 26, Education, 'fraining, in-service training centers and Eztension) under management of AAETE,

Ministry of Manpower 63,5 (R) Transmigration IV (East Approved by the Executive and Transmigration (Bank) Kalimantan) - Development of Directors on May 24, and signed transmigration schemes in East on May ~l, Kalimantan,

Ministries of Public 150,0 Kedung Ombo Dam - Works Project preparation underway, Works and Mining and (Bank) (including coffer dam, Energy diversion tunnel and main dam construction) for Kedung Ombo dam,

Ministries of Public 80,0 (R) Second Provincial Irrigation - Appraisal report being prepared Works and Mining and (Bank) ( Development of capabilities of Energy selected provincial irrigation services to implement I' construction of small systems ii and accelerate rehabilitation ii works. II,, I; Ministry of Public 150,0 (R) Highway VI - To upgrade parts Appraisal mission in the field, Works (Bank) of arterial and collector road ii network, ,,11 Ministry of 120,0 Secondary Education I - Project preparation underway, Education and (Bank) Improvement of secondary Ii,, Culture education through in-service 11 upgrading of teachers, 'I improvement of examination I! systems and provision of 11 laboratory equipment, 1, Ministry of Public 40,0 W, Tarum Canal Enlargement - Project preparation under way, Works (Bank) Expan~ion of capacity of canal for raw water·supply to Jakarta and for irrigation.

Ministry of Health 40,0 (N) Community Health and Training - Project identification underway, (Bank) Expanded program of community health care including immunization, improvement of nursing and technical training, Government of 200,0 (N) Small Enterprise Development Project identification underway, Indonee.ia (Bank) III - To support the Government with Small Investment Credit (KIK)/Small Permanent Working capital Credit (KMKP) programs,

Ministry of 150,0 (N) Second University - Development Project preparation underway, Education and (Bank) of graduate and post-graduate Culture centers to upgrade university staff in key fields, including natural science and agriculture, engineering, and economics.

~ Ministry of To be Ports III - To provide Project under preparation by Transportation/Korea deter­ additional capacity, especially Government and consultants, Maritime and Port mined container handling capacity, (Co-financing is envisaged,) Au.thority (Bank)

See page 1 for footnotes, - 33 -

Member Country, and Borrower or Amount' Stage of Process­ Implementing Probable ing and Action on ~1.l Lender J:l Procurement.!/ KOREA (Cont'd)

Ministry of 65,0 (R) Jeonju Regional Development - Appraisal report being prepared, Construction (Bank) To help further develop economic growth, employment and urban infrastructure in the region's major urban areas of Jeonju, Gunsan and Iri,

Ministry of Finance 255,0 (R) Industrial Finance - Assistance Negotiations completed, Board (Bank) to the Government to reform the presentation on June 9, financial system; and provision of line of credit to the major development banks for term lending to industrial enterprises,

Economic Planning 200,0 (R) Highway Sector - To assist the Appraisal report being prepared, Board and other (Bank) Government in making policy and Ministries institutional adjustments in the highway sector and in implementing road investment plans.

Miniat-ry of 300,0 Second Structural Adjustment Project under preparation by Finance/Economic (Bank) Loan - To help the Government Government and consultants, Planning Board in further implementing its structural adjustment program which commenced under SAL I,

Ministry of 120,0 (R) Second Water Supply Loan - Appraisal report being prepared, Construction (Bank) Construction of a barrage for Busan source development, and assistance to the Government on planning and implementation of national water supply manage­ ment programs,

LAO PEOPLE'S DEMOCRATIC REPUBLIC

To be determined 6,2 (R) Agricultural Production Support Scheduled for Board presentation (IDA) - The project would finance 6 on June 28, (Co-financing is subprojecta, namely: small­ envisaged,) scale irrigation, agricultural production support, agricul­ tural road maintenance, live­ stock feed production, sugar processing, and warehousing and inventory management. Techni­ cal assistance for training and improving procurement pro­ cedures, Total cost estimated at $24,77 million with a foreign exchange component of $17,56 million.

To be Aetermined 30,0 Laos Electrification - Discussions with Government in (IDA) Generation, transmission, progress, and distribution of electricity in selected provinces,

To be determined To be Industrial Rehabilitation - Discussions with Government in deter­ Provision of equipment, progress. mined improved management practices, (IDA) and training to improve industrial efficiency and encourage export growth.

To be determined To be Agricultural Development - To Discussions with Government being deter­ assist in developing scheduled, mined agricultural support services (IDA) and the production of crops for export.

See page 1 for footnotes, - 34 -

Member Country, and Bor11ower or Amount & Stage of- Process­ Implementing Probable ing and Action on ~ll Lender-1/ Procurement,!/ MALAYSIA

Government 55,0 Small--Scale_Enterprise Project. being prepared by (Bank) (Industries I) - Assistance for Government, manufacturing and institutional deveiopm~nt, .

Economic Planning 86,22 (R) Transport Development Approved by the Executive Unit/Ministry of (Bank) Sabah-Sarawak Road - Directors on Kay 26, Works and Utilities Strengthening the planning and construction capability of the. road construction industry,· technical assistance and training, as well as financing for road construction and maintenance,

Ministry of 50,0 Western Johore II - Integrated Project being prepared by Agriculture (Bank) Development - Construction of Government·, farm roads and drainage facilities, and provision of agricultural support services,

Sabah Forestry 40,0 (R) Bengkoka Reforestation - The Appraisal mission in the field, Development (Bank) project will cover planting of Authority (SAFODA) 90,000 acres with fast growing hardwood, institutional strengthening of SAFODA, road construction, employment for tribal people, as well as housing and social infrastruc­ ture,

Ministry of 68,0 (R) Industrial Training - Improve­ Appraisal report being prepared, ·Education/Ministry (Bank) ment of manpower planning and of Labor and management by strengthening Manpower planning and management capability and by financing staff training, advisory services of public institu­ tions; constructing snd equipp­ ing two additional industrial training institutes snd three additional polytechnics_,

National Electricity 65,0 Rural Electrification II - Project being prepared by the Board (NEB) (Bank) Transmission· for grid Government, augmentation and.distribution in rural areas iri•the states of Kedah, Kelantan, _Pahang, Trengganu and Johore for the three-year period·l985-87,

PAPUA NEW GUINEA

Department of 14, l (R) Agricultural Support Services - Approved by Executive Directors Primary Industry (Bank) Improvement of agriculture on Kay 3, research and extension services,

Papua New Guinea 20,0 (R) Agricultural Credit III - The Appraisal report being prepared, Development Bank (Bank) project will provide funds to (PNGDB) the ·Development Bank for . term·. lending in tree crop development,: poul.try. and agro-processing, It will also provide training to strengthen the Development Bank and technical assistance on.the crop diversification program,

Jrepartment of 46,0 (R) Secondary. Educat~on -­ Appraisal report being prepared, Education (Bank) Improvement of the quality of (Co-financing is envisaged,) lower secondary- education . (grades 7.,-10), .

See page l for footnotes, - 35 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~l/. · Lender J:l Procurement.!/ PAPUA NEW GUINEA (Cont'd)

Department of 15,0 Nucleus Estate and Smallholder Project being prepared, Primary Industry (Bank) Tree Crop Project I - To (Commonwealth Development develop a combination of Corporation is expected to several derelict commercial co-finance,) estates and vacant areas of Government land in the Milne Bay Province into s viable oil palm· and cocoa nucleus estate, together with the peripheral development and support of small-scale· smallholder pian~inga of these crops~

PHILIPPINES

National Economic 67,0 Urban' IV (Regional Cities) - . Approved by the Executive and Development (Bank) Investments in-4-cities Directors on Karch 31, Authority including selected primary infrastructure,'tranaport, ~unicipal s_ervices and· facilities, aanitation·and shelter to support' regional urban economic·development, Total·project c~at estimated at· $109,5 million, with foreign exch~nge·cost of about $41,4 million,·

Ministry of Agrarian 46,0 (R) Rural·Development IV (Land Appraisal report being prepared. Reform (Bank) Settlement II)' -, Further assistance for·planning and execution·of:Government's land settlement program, The project would support a nation~wide geodetic network, aerial photography for survey­ ing and land filling, infra­ structure; agro-foreatry and technical aasiatance. Total project'coat·estimated at $76.4 million.

National 60,0 Rural Electrification II - To Project being prepared by Electrification (Bank) finance expansion of Government. (Co-financing is Administration Government's on-going rural envisaged.) electrification program,

Ministry of Public 135,0 (R) Highways V - Construction, Appraisal report being prepared, Works and Highways (Bank) maintenance and rehabilitation (KPWH) of national roads and bridges, and institutional strengthening of KPWH, Total project cost estimated at $335.S million,

Land Bank of the 40,0 (R) Small Farmer Development (Land Appraisal mission in the field, Philippines (LBP) (Bank) Bank II) - Further credit, aupport·aervicea and minor infrastructure assistance for land reform beneficiaries. Ministry of ~o.o Rainfed Agricultural Project being prepared by Agriculture (Ba~k) Development II (Mindanao) FAO/CP and Government, Support services and (Co-financing is envisaged,) infrastructure to promote diversified rainfed and upland crop/livestock systems in Mindanao region,

See·page 1 for footnotes, - 36 -

Member Country, and Borrower or ·Amount & Stage of Process­ Implementing Probable ing and Action on ~ll. Lender J:./ Procurement !!I PHILIPPINES (Cont'd)

National Economic 32,4 (R) Central Visayas Regional Appraisal report being prepared, and Development (Bank) Project - Integrated program of Bank Project Preparation Facility Authority (NEDA) watershed management, upland advance of $1,000,000 approved to agriculture, nearshore finance consultancy services, fisheries, social forestry, incremental costs in connection onfarm development, rural with recruitment of staff, and infrastructure and research in procurement of vehicles and Central Visayas, Total project equipment, cost estimated at $52,3 million,

Ministry of 125,0 (R) Telecommunications I - To Appraisal mission tentatively Transportation and (Bank) finance part of the 1984-90 schedule~ for October, Communications national investment program for (Co-financing is envisaged,) (MOTC) telecommunications, including reconstruction and expansion of Bank Project Preparation Facility network installations and advance of $500,000 approved to institutional support for finance the provision of MOTC, Total project cost consultancy services for studies estimated at $230 million, on the integration and regulatory strengthening of the sector and engineering studies,

Central Bank 100,0 (R) Agricultural Credit - To help Identification mission to be (Bank) finance part of the scheduled, Government's agricultural credit program,

National Housing 120,0 (R) Metro Manila Urban services Project being prepared by Authority (NRA) (Bank) Project - Support to the Government, (Co-financing will Government's zonal improvement be sought,) program involving mainly slum upgrading in Metro Manila and upgrading of basic services, Total project cost estimated at $200 million with foreign exchange cost of about $80 million,

Central Bank of the 200,0 Industrial Finance II - To Project being prepared by Philippines (Bank) finance industrial development Government, (Co-financing is through local development envisaged,) finance companies, Total foreign exchange requirement estimated at $350 million,

Ministry of Trade 100,0 Metalworking Industry - Project being prepared by the and Industry (Bank) Financial and institutional Government, (Co-financing may be support to the restructuring of sought,) the metalworking sector,

To be determined 130,0 Power VIII - Support for the Project being prepared by the (Bank) Government's program of hydro­ Government, (Co-financing may be electric power development, sought,)

To be ~etermined 100,0 Manila Water Supply III - Project being prepared by the (Bank) Proviaion of basic Government, (Co-financing from infrastructure in source various sources will be development for Metro Manila sought,) water supply, including headworks, treatment plant, distribution system and construction supervision, Total cost estimated at $900 million, of which about $400 million in foreign exchange,

Philippine National 40,0 Geothermal II - Support for the Project being prepared by the Oil Company (Bank) Government's program of Government, (Co-financing is geothermal power development, envisaged,)

To be determined 100,0 Balog-Balog Multipurpose - Project being prepared by (Bank) Expansion of Tarlac Irriga­ Government. tion System, Total cost estimated at $160 million,

See page l for footnotes, - 37 -

Member Country, and'Borrower or ·Amount & Stage of Process­ Implementfng Probable ing and Action on Agency 1/ Lender J:./ Procurement!!/ PHILIPPINES (Cont'd)

To be determined 50.0 Watershed Management II - Project being prepared by (Bank) Protection of Magat Watershed. Government. Total cost estimated at $100 million.

National Economic 50.0 (R) Central Visayas Regional Project being prepared by and Development (Bank) Project II: Emphasis on urban Government. Authority (NEDA) development supporting upgrading of municipal infrastructure, management of municipal enterprises, transportation, .traffic management, maintenance and training. Total project cost estimated at $100 million.

To be determined 50.0 (N) National Forestry - Support for Project being prepared by (Bank) the development of industrial Government and FAO/CP. tree plantations and strengthening of the Bureau of Forest Develo1111ent•a field capacity and services.

To be determined 50.0 (N) Secondary Cities Development - Project being prepared by (Bank) Expansion of basic municipal Government. services with emphasis on environmental sanitation, and strengthening of implementation capacity of local governments. Total project cost estimated,at $100 million.

To be de~ermined 75.0 (N) Rural Roads II - Further Project being prepared by (Bank) support for the Government's Government. program of rural road construction rehabilitation and maintenance.

SOLOMON ISLANDS

Government of 2.0 (R) Lungga Hydroelectric Power This project is no longer .in the Solomon Islands, (IDA) Project - Total project cost lending program and reporting Electricity estimated at $55 million. will be discontinued. Authority

Ministry of 3.0 (N) Agricultural Extension and Project being appraised by ADB Agriculture (IDA) Rural Development. for co-financing with IDA.

THAILAND

Ministry of 50.0 Irrigation XIII (Medium Scale Appraisal report being prepared. Agriculture and (Bank) Irrigation) - Strengthening of Cooperatives the Royal Irrigation Department and support for its irrigation development program.

Ministry of 40.0 Forestry I - Forest protection, Project preparation under way. Agriculture and (Bank) wood lot development, Cooperatives industrial plantations, forest villages and research, extension and training for Royal Forestry Department.

Ministry of 95.0 Rural Roads - Construction of Project preparation under way. Interior (Bank) rural roads country wide. (Co-financing being explored.)

(PETROLEUM AUTHORITY so.o Energy III (Sirikit 011 Field Project preparation under way. OF THAILAND (PTT)) (Bank) Development) - Possible investment related to onshore oil field development.

See page 1 for footnotes. Member Country, and Borrower or ., Amount·& Stage of·Process­ Implementing Probable ing and Action un ~1.l. Lender l:l Project 1/. Procurement f!/ THAILAND (Cont'd)

(ELECTRICITY 170.0 Nam Choan Hydroelectric - 187 m Scheduling of Board presentation GENERATING AUTHORITY (Bank) high rockfill dam with. four pending· Government decision on OF THAILAND (EGAT)) generating units· of 145 MW environmental issue. (Parallel each; switchyard, 230 Kv financing from bilateral, export transmission lines and credit and commercial sources engineering services, Total totalling $185 million, out of cost estimated at $540 million foreign financing requirement of of which $280 miilion. in about $355 million, being foreign exchange, considered,)

(STATE RAILWAY OF 107,0 (R) Railways VI -.To support· SRT's Board presentation scheduled for THAILAND (SRT)) (Bank) rail service expansion program September 20. (Parallel in the FYS3~86"period, Total financing with French/German project cost estimated at suppliers' credits of about $21 $330,l million with foreign million, $114 million of exchange component of $262,4 bilateral credits, and $59 million, · · million of local private· borrowings being considered,)

(PROVINCIAL 30,6 (R) Provincial Power Distribution Board presentation on June 9. ELECTRICITY (Bank) (Power XV) .- To support half of (OECF Japan will.finance the other AUTHORITY (PEA)) 2-3 year time slice of PEA's ' half of the program.) normal rural electrification program, Total cost about. $50,8 million of which $30,6 million in foreign exchange. (BANK FOR AGRICUL­ 70,0 (R) Agricultural Credit II - Board presentation on June 9. TURE AND AGRICUL­ (Bank) Provision of agricultural term (Co-financing of $20 million from TURAL COOPERATIVES) lending through the Bank for IFAD has been arranged,) Agriculture and Agricultural Cooperatives (BAAC), Total Procurement: Retroactive cost estimated at $188,5 financing of up to $7 million for million with a foreign exchange sub-loans, extended from April 1, component of $47,l million, 1983.

Ministry of Interior 30,0 (R) Land Titling - Acceleration of Appraisal report being prepared. (Bank) cadastral surveying and issuance of land titles in rural areas, and strengthening of land registration and administration system.

To be determined 90.0 Basic Education - Educational Project identification tmder way. (Bank) improvements at the primary level,

Ministry of Finance 50,0 Refinery - Possible rehabilita­ Project identification report (Bank) tion of Bangchak oil refinery, being reviewed.

Ministry of Finance so.o Regional Cities - Urban Appraisal mission in the field. (Bank) services and infrastructure improvement in.five regional cities.

Ministry of 60.0 Agricultural Support Services - Project preparation tmder way, Agriculture & (Bank) Strengthening the Ministry's Cooperatives overall capabilities, focusing particularly on.improving three of its departments (land development, fish and· livestock).

To be determined 135,0 Industrial Credit -.Delivery of Project preparation tmder way. (Bank) term finance arid ·technical (Co-financing from various sources assistance through·an apex to be sought.) mechanism.

See page l for footnotes. - 39 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~Ji. Lender J,/ Procurement i/ THAILAND (Cont'd)

Ministry of 100.0 (R) Provincial Roads II - Board presentation on June 9. Communications (Bank) Construction and improvement of about 1100 km of provincial roads; strengthening of about 1500 km of existing paved roads; and technical assistance. Total cost estimated at $166.6 million with a foreign exchange component of $72.75 million.

National Economic 50.0 (R) Rural Development I - Appraisal report being prepared. and Social (Bank) Assistance in funding the Development Board Government's national rural (NESDB) development program.

(ELECTRICITY 12.0 Mae Moh Lignite II - Expansion Appraisal report being prepared. GENERATING.AUTHORITY (Bank) of lignite mining capacity from OF THAILAND (EGAT)) 2.8 mtpy to 5.0 mtpy to supply Procurement for mining equipment No •. 6 and 7 generating units of to start mid-1983. 150 MW capacity each.

Electricity 55.0 (R) ERV.Transmission - Construction Pre-appraisal mission in the Generating Authority (Bank) of 500 'Kv transmission line field. of Thailand (EGAT) from the North to serve Bangkok. Total cost estimated Procurement: Prequalification at $120 million with a. foreign for contractor underway. exchange, component· of $55 million.

Telephone 100.0 (R) Telecommunicatio.ns. V -. Project identification under . Organization of (Bank) Expansion.of. telep~one way. (Parallel co-financing from Thailand (TOT) facilities, 'particularly in . various sources to be rural and ·provincial .areas • . considered.) Total cost estimated at $1,630 million with a. foreign exchange component of $830 millioti•. ·

Ministry of Finance 190.0 Third Structural Adju~tment· Project preparation to begin in (Bank) Loan - To help the Government October/November. implement t_he next phase of its structural adjustment policies related to agriculture, industry, energy, fiscal policy and institutional reform,

VIET NAM

Ministry of To be Coal Expansion 1·- Development Project procesaing in abeyance. Electricity and Coal deter­ of a coal mine in Quang Ninh mined Province. Total project costs (IDA) tentatively estimated at $112 million.

Viet Nam Bank for To be Industrial Rehabilitatio~ Project processing in abeyance. Industry deter­ Project·- Rehabilitation·and mined expansion ·of textile, pulp and · (IDA) paper, and food processing industries. Total project cost tentatively estimated at $50 million.

Ministry of Water To be Nghe Tinh Agricultural Proj.ect processing in abeyance. Conservancy deter­ Rehabilitation and Development mined - Repair of flood damage on (IDA) irrigation and drainage works in northern part of Viet Nam heavily damaged by typhoons and floods in 1978, and construction of salinity and flood control works. Total project cost estimated at $128 million.

See page 1 for footnotes. - 40 -

Member Country, and Borrower or Amount & Stage of Process­ · Implementing Probable ing and Action on ~l/ Lender 1/ Procurement fi/ VIET NAM (Cont'd)

Ministry of To be Transport Rehabilitation - Project processing in abeyance, Transport deter­ Rehabilitation of port, roads mined and railways facilities and (IDA) inland waterways,

Ministry of Water To be Agricultural rehabilitation and Project processing in abeyan_ce; Conservancy deter­ development in provinces with mined high food production potential, (IDA)

See page l for footnotes, - 41 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Proli"alile · ing end Action on ~!/ Lender?:./ Procurement~

IV. SOUTH ASIA

BANGLADESH

Ministry of Porte, Up to Inland Water Transport III - ~o Project preparation underway. Shipping and Inland 40.0 assist Bangladesh Inland Water Water Transport/ (IDA) Transport Authority (BIWTA), BIWTC/BIWTA Bangladesh Inland Water Transport Corporation (BIWTC) and Ministr·y of Porta, Shipping and Inland Waterways (MPSI).

Ministry of Roads, About (R) Road Rehabilitation and Project preparation unden,ay. Highways and Road 40.0 Improvement - Strenthening of Transport (IDA) maintenance organization through training, provision of equipment and materials and technical assistance, possibly including selective rehabilitation of existing primary roa~s.

Bangladesh Sugar & 20.0 (R) Sugar - Mill rehabilitation, Board presentation scheduled for Food Corporation (IDA) improvement in mill farms, and July 5. (BSFIC) transportation in mill zones, strengthening of extension activities, technical assistance, and training.

Dhaka Water and About Dhaka WASA III - Extensions to Preparation report being Sewerage·Authority 40.0 water supply and sewerage prepared. (WASA) (IDA) systems.

Water Development About (R) WDB Sector Credit - Small Appraisal mission in the field. Board (WDB) 45.0 irrigation/drainage/flood (IDA) control projects.

Water Development About Bar1aal Patuakhali - Project preparation baa been Board (WDB) 25.0 Irrigation, drainage and flood delayed. (IDA) control works in Barisal and Patuakhali districts in southwest Bangladesh.

Water & Sewerage About District Town Water Supply - Preparation report being Authorities (to be 40.0 Water supply systems for Khulna prepared. estsblished) (IDA) and Rajshahi.

(PETROBANGLA) 23.0 (R) Petroleum Exploration Promotion Board presentation scheduled for (IDA) - Project components include: July 5. seismic surveys, technical assistance, data processing, hydrocarbon habitat study and promotional package.

Ministry of Local 100.0 (R) Rural Development II - Board presentation on June 14. Government, Rural (IDA) Extension of Integrated Rural (CIDA will cofinance $17.2 Development and Development Program (IRDP). million, ODA $10.5 million, and Cooperatives UNDP $1.6 million.)

Eatabiliahment 12.5 (R) Public Administration - Credit signed on May 16. Division of the (IDA) Improvement of the public Cabinet Secretariat administration training.

See page 1 for footnotes. - 42 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~l/ Lender ?:J Procurement !!J BANGLADESH (Cont'd)

National Committee 8,1 (R) Agricultural Training II - Board presentation rescheduled on Rural Training (IDA) Includes (a) facilities and for July 5, and Ministry of equipment for agriculture Agriculture extension training institutes and a regional academy of rural development; (b) experimental facilities to try new modes of extension in trial areas; (c) in-service training for present extension staff; and (d) technical assistance.

Fisheries Department About (R) Fisheries II - To be Appraisal mission tentatively 20.0 identified. scheduled for September. (IDA)

Bangladesh Chemical Up to Phosphate Gypsum - To Decision whether to proceed with Industries 25.0 manufacture cement clinker and the project will depend on Corporation (BCIC) (IDA) recover sulphur dioxide. results of consultant study, Gypsum washing facilities, calcination and storage equipment, cement kiln and ancillary facilities will be included,

Ministry of Local About Rural Roads & Marketing - Study by consultants underway. Government, Rural 30.0 Rehabilitation of rural roads, Development, end (IDA) rural markets and construction Cooperatives of small-scale storage.

Ministry of About Agricultural Research II - To Appraisal report being prepared, Agriculture 25.0 support and develop (IDA) agricultural research over a five-year period,

Ministry of About (R) Secondary Roads - To Preparation mission findings Transport and 30,0 rehabilitate and/or build about being reviewed. Communications (IDA) 200 miles of ·all-weather roads in foodgrain surplus areas,

Bangladesh Bank 65,0 (R) Agricultural Credit II - To Appraisal mission in the field, (IDA) support further reform of agricultural credit system, including provision of credit to farmers for on-farm investments,

Ministry of Energy 28,5 (R) Energy Efficiency and Refinery Approved by the Executive Resources (IDA) Rehabilitation - Including Directors on May 10, and signed quick-yielding refinery on May 16. debottlenecking and energy savings modifications, feasibility studies for additional future refinery modernization, energy audits for major oil and gas users, studies for future gas utilization,

Ministry of Finance 25,0 (R) Technical Assistance V - Board presentation tentatively (IDA) Technical assistance and scheduled for July 19, training subprojects, to be selected by mutual agreement, in the fields of policy, pre-investment planning, feasibility or engineering studies, or strengthening institutions responsible for project preparation and implementation,

See page 1 for footnotes, - 43 -

Member Country, and Borrower or Amount·& Stage of Process­ Implementing Probable ing and Action on ~l/ Lender!/ Procurement !!J BANGLADESH (Cont'd)

Ministry of Finance 150,0 (R) Imports Program XII - Provision Pre-appraisal mission findings and Planning (IDA) of foreign exchange for being reviewed, procurement of industrial raw materials and spare parts required to improve utilization of existing capacity, and for importation of agricultural inputs,

Bangladesh Textile 45,0 (R) Textile BMR II - Balancing, Appraisal mission scheduled for Mills Corporation (IDA) modernization and replacement late August, of machinery mainly for private sector textile mills,

To be determined 75,0 Industrial Sector Credit - Project preparation underway, (IDA) Provision of term finance to private sector industry through financial institutions to be selected.

Ministry of About Technica~ Education - Pre-appraisal mission findings Education and 26.0 Strengthening the technical being reviewed, Religious Affairs (IDA) education system,

Ministry of 30.0 (R) Ashuganj Fertilizer/Operations Negotiations tentatively Industries (IDA) and Maintenance - Continued scheduled for mid-August. plant operations assistance, staff training, spare parts and Procurement: Equipment damaged replacement of some equipment during the initial operation of damaged during commissioning, the plant needs to be replaced and initial operations of the expeditiously, (Retroactive newly constructed Ashuganj financing may be recommended for (Zia) Fertilizer Urea Factory, expenditure after February 1983,)

Government 3,0 (R) Technical Assistance - To help Negotiations in early June (IDA) prepare a pipeline of high in the field. priority projects sui,table for financing by the Government and external donors. Funds for technical assistance for pre-investment planning, feasibility and engineering studies, consulting and advisory services, setting up of planning and preparation units, and training of personnel.

BURMA

Ministry of 33,0 (R) Arakan Pulp and Paper - To Project preparation underway by Industry II (IDA) construct a pulp and paper mill Government, with assistance from with a capacity of 100 tons per consultants financed by an day of printing and writing advance of $150,000 from the IDA paper produced from a mixture Project Preparation Facility, of bamboo and indigenous hard­ woods, The project also includes associated infrastruc­ ture facilities,

Ministry of 14,0 (R) Groundwater (Tubewells) - To lloard presentation on June 7, Agriculture and (IDA) increase agriculture Forests productivity in the Central Dry Zone, through installation of tubewells and provision of agriculture support facilities,

Ministry of 27,0 (R) Wood Industries II - To further Appraisal report being prepared, Agriculture and (IDA) improve 'the supply of wood (Co-financing being explored,) Forests products to the domestic market,

See page 1 for footnotes. - 44 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and.Action on ~!I ~!/ Procurement'!} BURMA (Cont'd)

Ministry of 9.0 (R) Rubber Rehabilitation II - New Board presentation on June 14. Agriculture and (IDA) plantings and replanting& in Forests about 10,000 acres, expand reprocessing facilities, staff training and technical assi.stance.

Ministry of 22.0 Textiles - To implement a Appraisal report being prepared. Industry I· (IDA) finishing plant to serve the (Co-financing being explored.) Lower Burma area. The plant would complement the spinning and weaving facilities under implementation at Shwedaung. The project also includes a technical assistance component for rehabilitating and improving productivity in the sector.

Ministry of 20.0 Irrigation Rehabilitation - To Project preparation under way. Agriculture and (IDA) rehabilitate existing gravity Forests irrigatiCUl systems in the Central Dry Zone of Burma. Main component would comprise: major civil work including repairs to and remodelling of major structures, canal desilting and land development; provision of equipment and vehicles and agricultural support services.

Ministry of 50.0 (R) Ports III - Rehabilitation of Approved by the Executive Transport (IDA) Rangoon Port to enable the port Directors on May 24. to handle the anticipated increase in tonnage. Works would include the improvement of port lighting, service vessels and marine facilities. In addition, the project would provide new cargo handling equipment, spare parts, open and covered storage facilities, technical assistance and engineering services.

Ministry of 20.0 Transport/Distribution - Project identification underway. Transport (IDA) · Multimodal transport project to minimize bottlenecks in transporting timber and ~ther key export products: includes provision of storage; telecommunications; navigational and other facilities.

Ministry of 15.0 Seeds - Develop viable seed Project identification underway. Agriculture and (IDA) program covering Burma's major Forests crops including seed multipli­ cation and distribution for paddy, cotton, and other crops. Strengthen research, seed testing and quality control. Technical assistance and training.

Ministry of 15.0 (N) Paddy III - Follow-up to two Project preparation underway, Agriculture and (IDA) ongoing paddy development Forests projects to increase paddy production through the construction of flood protec­ tion and drainage faciliticR designed·to (i) exclude tidal and river flow surges; (ii) improve and extend natural internal drainage; and (iii) reclaim land that is currently deeply flooded or saline.

See page 1 for footnotes. - 45 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on Agency!./ Lender!/ Procurement !!J

BURMA (Cont'd)

Ministry of 21.0 (N) Grain Storage II - Follo.,..up of Feasibility report is currently Agriculture and (IDA) the first grain storage project being reviewed by the Government Forests to rehabilitate existing and IDA. storage and milling facilities; transportation; technical assistance and staff training.

To be determined 30.0 Rainfed Agriculture Project - Appraisal report being prepared. (IDA) Development of rainfed agricultural system in selected State(s).

Government of 46.2 (R) Himalayan Watershed Development Approved by the Executive (Bank) - To ameliorate the Directors on May 31. deterioration of the Himalayan ecosystem caused by deforestation, overgrazing, etc., and to carry out integrated area development schemes, including reforestation and fodder production, livestock and horticulture development, soil conservation and agricultural · extension.

Government of Uttar 120.0 (R) Upper Ganga Irrigation - Pre-appraisal mission in the Pradesh (IDA) Modernization of irrigation field. systems in Uttar Pradesh State.

Ministry of Shipping 285.0 Nhava Sheva Port - Construction Revision to project scope under and Transport/Nhava (IDA) of a new port facility to consideration. Sheva Port Trust relieve serious overcrowding and delays at Bombay Port.

To be determined 300.0 Petrochemicals - Production of Appraisal report under (Bank) petrochemicals based on Bombay preparation. High natural gas and/or production of basic aromatics and selected derivatives.

Government of Tamil 75.0 (R) Tamil Nadu Water Supply and Appraisal report being prepared. Nadu IDA) Sanitation Project - Water supply for three large towns, and about 60 middle-sized towns, and low-cost sanitation for 15 small towns.

Government of 50.0 Chambal (Rajasthan) Irrigation Awaiting confirmation from Rajasthan (IDA) II Project - Modernization of GOI/GOR on project scope to irrigation and drainage and complete preparation of appraisal command area development report. covering about 230,000 ha in the valley in Rajasthan.

Government of Orissa 156.4 (R) Upper Indravati Hydro-Electric Approved by the Executive (Bank) Project - Construction of a 600 Directors on May 10, and 170.0 MW hydro-electric generating signed on June 8. (IDA) station together with associated dams, channels and · tunnels· in Orissa State.

National Thermal 250.7 (R) Central Power Transmission Approved by the Executive Power Corporation (Bank) Project - Construction of a Directors on May 19, and (NTPC) network of 400 kv transmission signed on June 8. lines and associated sub-stations linking_ regional grids for three Regions.

See page 1 for footnotes.

·-; / - 46 -

Member Country, and Borrower- or Amount & Stage of-Process­ Implementing Probable ing and Action on ~!/ Lender Y Procurement!±./ INDIA_ (~ont'd)

Government of West 50.0 Haldia Water Supply and Project preparation underway, Bengal (IDA) Sewerage Project - Construction of 225 million liters/day treatment plant, 4 pumping stations and a 90 km long water transmission main to serve the Haldia Development Authority, 2 towns and rural communities en route.

Government of Bihar 50.0 Bihar Water Supply - Provision Project preparation underway. (IDA) of piped water supply to about 3 towns in the State of Bihar,

Government of Madhya 24.l (R) Madhya Pradesh Urban Board presentation scheduled for Pradesh (Bank) Development Project - Shelter June 28, and infrastructure investments in several medium-sized cities in the State of Madhya Pradesh,

Government of West 147.0 (R) Third.Calcutta Urban Approved by the Executive Bengal (IDA) Development Project - Expansion Directors on May 19, and and improvement of urban signed on June 8, service systems and institutional capabilities in the Calcutta Metropolitan District.

National Fertilizer 200.0 Madhya Pradesh Fertilizer - Appraisal report being prepared, Ltd. (Bank) Construction of one ammonia unit of 1,350 tons per day and two urea units of 1,100 tons per day each,

Government of 300.0 (R) Narmada Gujarat I - Appraisal report being prepared, Gujarat (IDA) Construction of Sardar Sarovar Dam, hydroelectric power stations of 1,400 MW, the Narmada main canal and a large network of canals and minor channels, to serve about 2 million ha,

Government of 100.0 Bombay Urban Development - Project preparation underway, Maharashtra (IDA) Program of slum upgrading and shelter renovation and construction for the Bombay Metropolitan Region,

Indian Railways (IR) 200.0 Railways Electrification - Post-appraisal issues under (Bank) Assistance to Indian Railways discussion, in its ongoing rail electrification program,

Government of Madhya 150,0 (R) Bodhghat Hydro-electric Project Preparation/pre-appraisal mission Pradesh (Bank) - Construction of a 600 MW in the field, hydro-electric generating station together with associated dams, channels and tunnels in Madhya Pradesh State,

To be determined 200,0 Thermal Power Plant Identification mission to be (Bank) Rehabilitation Project - scheduled following Government Selected investments to decision on project components increase capacity utilization and timing of proposal to Bank, in existing power plants,

011 & Natural Gas 170,0 (R) Cambay Basin Petroleum Project Appraisal mission tentatively Commission (OIIGC) (Bank) - Assistance to increase scheduled for August, onshore production rates in (Co-financing likely,) Gujarat.

Government of Orissa 105,0 (R) Second Orissa Medium Irrigation Negotiations completed, Board (IDA) Project - Continuation of presentation scheduled for July assistance to State in 5. upgrading irrigation network,

See page 1 for footnotes, - 47 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~!/ ~y Procurement !!J IIIDIA (Cont'd)

Tata Electric 190.0 (R) Trombay IV (Thermal Power) - Appraisal report being prepared, Company (Bank) Installation of 500 MW unit,

Government of 22.7 (R) Maharashtra Water Utilization - Board presentation on June 9. Maharashtra (Bank) Upgrading of minor distribution 32.0 and field channels covering (IDA) about 95,000 hectares.

National Thermal 165.0 .Farakka Thermal Power - Appraisal mission tentatively Power Corporation (IDA) Installation of three 500 MW scheduled for August/September, units, as the second stage of development of the Farakka plant in West Bengal,

Coal India, Ltd. 200.0 Coal - Assistance to GOI in Appraisal report being prepared, (IDA) expanding domestic production of stea~ and coking coal.

Ministry of 100.0 National Agricultural Extension Project preparation underway, Agriculture (IDA) Project - Assistance to the Directorate of Extension in strengthening extension systems in various.states through the introduction of the training and visit system,

Government of Madhya 200,0 Narmada (Madhya Pradesh) I - Project preparation underway, Pradesh (IDA) Construction of the Narmada Sagar Dam, hydro power stations and a large network of canals covering about 2,8 million ha,

Government of 30.0 Karnataka Social Forestry Appraisal report being prepared, Karnataka (IDA) Project - Afforestation of (Co-financing with the United wasteland and degraded forests, Kingdom is likely,) primarily to produce fuelwood and other forest products for use by local villages.

Ministry of Health 50.0 (R) Third Population Project - To Appraisal report being prepared, and Family Welfare (IDA) support implementation of an integrated family welfare program designed primarily to improve infant and maternal health and to lower birth rate,

To be determined 100.0 Cement Energy Savings - Assis­ Project preparation underway, (Bank) tance, through a financial intermediary, to several· cement plants to convert from wet to dry process.

Government of Tamil 42,0 (N) Periyar Vaigai II - Project preparation underway, Nsdu (IDA) Continuation of canal lining program begun under first project, and operation of completed system to improved standards.

Ministry of Water About (R) Marsyangdi Hydroelectric - Appraisal report under Resources 90.0 Hydroelectric power station in preparation, (Co-financing with (IDA) Central with 78 MW Federal Republic of Germany, installed capacity, Kuwait Fund, Saudi Fund, Japan transmission to'central grid, and ADB being considered, Need and consultancy.services. for additional co-financing,)

See page 1 for footnotes,

;_-,,.1 .•,.--·· - 48 -

Member Country, and Borrower or Amount & Stage of Process­ I'lllple11enting Probable ing and Action on !&!!!:I.!./ ~y Procurement !!f

~ (Cont'd)

Ministry of Works About (R) Tranaport III - Completion of Appraisal report being prepared. and Transport JJ.O the East/West Highway; road (Co-financing required; (IDA) maintenance; and technical diacuaaiona with Saudi Fund, assistance. Kuwait Fund, and U.K. ODA.)

Nepal About Telecommunications IV - Project components being Teleco11mUnicationa 22.0 Follow-up for expansion of identified. (Co-financing may Corporation (IDA) local and international be sought.) services.

Ministry of Forests 18.0 (R) Second Forestry Project - Negotiations substantially (IDA) Organization and management of· completed. reforestation programs, forestry research, monitoring and evaluation, and planning.

Ministry of Finance 6.0 (R) Second Technical Assistance Approved by the Executive (IDA) Project - Includes financing of Directors on June 2. engineering_and feasibility studies, consultancy services and training. Total coat estimated at $6.0 million, all in foreign ~xchange.

Ministry of Water 11.0 (R) Karnali Preparation - Phase I - Negotiations substantially Resources (IDA) Includes prepration of final completed. feasibility studies for the Chisapani multipurpose project; preliminary feasibility studies of a smaller upstream hydro-electric project; and consultancy services.

Miniatry of About (R) Babai Irrigation - Includes Appraisal report under Water 22.0 construction of weir and preparation. (Co-financing Resources (IDA) headworka on Babai River, required.) construction of irrigation and drainage facilities on about 13,000 ha of land, and strengthening of agricultural extension services in the area.

Miniatry of 5.0 (N) Primary F.clucation - To Project preparation underway. Education (IDA) strengthen the various institutions relating to primary education, and thereby assist with greater decentralization and program support as well aa,increasing administrative efficiency; teaching materials and staff training; technical assistance.

Ministry of Industry 5.0 (N) Industrial Development - To Project preparation underway. (IDA) provide long term funds through the Nepal Industrial Development Corporation (NIDC) to industrial enterprises in the private sector and aasist in the overall institutional development of NIDC; assist in the development of leather and leather goods, and provide assistance in developing the light engineering sector; address key problem areaa in industrial and export policies, procedures and administration through technical aeaistance.

See page 1 for footnotes. - 49 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~Jj Lender!/ Procurement~ PAKISTAN

Karachi Development 25.0 (R) Karachi Water Supply - Credit approved by the Executive Authority; Karachi (IDA) Expansion of Bulk Water Supply Directors on May 26. Water and Sewerage System and improvement·of Board sewerage system in Karachi.

Water and Power 65.0 (R) Fourth Drainage Project - Credit approved by the Executive Development (IDA) Improved drainage and Directors on May 31. Authority (WAPDA) reclamation of saline/alkaline (Co-financing expected with UK · 1and. $13.S million and Netherlands $3.5 million.)

Oil & Gas 30.0 (R) Second Toot Oil and Gas Negotiations substantially' Development (Bank) Development - Including further completed. (Co-financing being Corporation development of Toot field, sought.) technical assistance, and training. Procurement: Advance contracting for oil field servicea and retroactive financing of up to $3.0 million recommended.

Lahore Development 16.0 (R) Lahore Urban Development Credit signed on May 24. Authority (IDA) Project - Including upgrading of low-income areas, sites and services, and solid waste disposal.

Sui Northern Gas 43.0 (R) Pipelines SNGPL V - Expansion Board presentation scheduled for Pipelines Ltd. (Bank) of capacity of SNGPL's gas June 23. (Co-financing being (SNGPL) transmission system'and sought with commercial ba~s.) associated facilities. Procurement: Retroactive financing of up to $4.0 million and advance contracting for Stage I of pipeline recommended.

Government of 18.0 (R) Population - To assist the Credit signed on May 24. Pakistan (IDA) Government of Pakistan in (Co-financing with USAID $3.4 implementing its population million, and UK $2.7 million.) program. Priority will be given to intensifying services and information, education and communications.

Government of 7.0 (R) Coal Engineering - Exploration, Approved by the Executive Pakistan (IDA) feasibility studies and Directors on May 3 and signed on technology evaluation for May 24. coal-fired thermal power stations in Baluchistan. State Petroleum so.o Refinery Conversion - To Project preparation underway. Refining and (Bank) support the construction of a Petrochemical hydrocracker project in Corporation Limited Pakistan.

Water and Power 49.0 Power WAPDA IV - To support the Project preparation underway. Development (Bank) construction of a thermal power Authority (WAPDA) station.

Government of 30.0 Command Water Management - To GOP preparing project report. Pakistan (IDA) improve water management in subproject areas located in the four provinces.

See page 1 for footnotes. - 50 -

Member Country, and Borrower or Amount&· Stage of Process­ Implementing Probable ing and Action on ~!/ Lender!/ Procurement ~ PAKISTAN (Cont'd)

Government of 10,0 (R) Fifth Agricultural Development Board presentation on June 7, Pakistan (Bank) Bank of Pakistan Project - To (Co-financing expected with IFAD 47,8 assist ADBP's lending program $30 million, and with Italian (IDA) in the years 1984-86, with Government $20 million,) emphasis on on-farm development.

Government of 12,5. (R) Integrated Hill Farming - To Appraisal mission in the field, Pakistan (IDA) support crop and other development in hill areas,

Government of 50,0 (R) Industrial Credit - Assistance Appraisal report being prepared, Pakistan (IDA) to private investors through financial intermediaries.

Government of 140.0 SAL II - To support Initiating memorandum under Pakistan, Ministry (Bank/IDA) Government's Structural preparation, of Finance Adjustment Programs in the areas of Agriculture, Industry and Energy.

Oil & Gas 51,5 (R) Petroleum Exploration - To Negotiations substantially Development (Bank) support the.Government's completed. (Co-financing being Corporation efforts t~ increase exploration sought with commercial banks,) of n!ltural. gas and enhance the chances of joint-venture exploration by foreign and domestic private oil companies. The project will consist of: (i) drilling of six exploratory welis on gas prospects; (ii) regional seismic surveys and basin studies; and (iii) promotion of potentially oil-prone areas to the private oil industry,

SRI LANKA

National Development 25,0 (R) Industrial Development - A Negotiations substantially Bank (NDB)/Develop- (IDA) credit line to NDB and DFCC for completed, ment Finance Corpo- onlending to private and public rations (DFCC) sector ·projects, and technical assistance to improve industrial efficiency, Ministry of Plan 23.0 Third.Rural Development Approved by the Executive Implementation (IDA). Project - Provision for inputs Directors on May 12, and services for dire~tly pro­ ductive sectors; rehabilitation and improve.aient· of economic infrastructure, including irrigation and transport; fisheries and livestock; social infrastructure improvement, including health and education,

Department of Up to Irrigation Rehabilitation Project preparation underway. Irrigation 35,0 Project - Rehabilitation and (IllA) modernization of a number of major irrigation tanks,

Department of Up to Second Road Maintenance Project Project preparation underway. Highways 20.0 - Rehabilitation of road (IDA) segments and bridges, and improved maintenance, for road network.

See page 1 for footnotes. - 51 -

Member Country, and Borrower or Amount Ii Stage of Process­ Implementing Probable ing and Action on ~!/ Lender Y Procurement !!_/ SRI LANKA (Cont'd)

Ministry of Mahaweli 49.0 Mahaweli. IV Project-· Project preparation 1D1derway. Development (Bank) Downstream development·work in Up to System B: Secondary and 30.0 tertiary canals; econ9D1iC and (IDA) social infrastructure for settlement.

Ministries of State Up to Third Tree Crops Rehabilitation Project preparation underway. Plantations, and 26.0 - Rehabilitation of tree crops Janatha Estate (IDA) --tea and rubber--plantations Development in the estate sector. ·

Ministry of Up to (N) Second Rubber Rehabilitation - Project preparation 1D1derway. Plantation 30.0 Replanting of over-aged, Industries (IDA) low-yielding smallholder rubber and improvement in rubber processing standards.

See page 1 for footnotes •. ·

;_,:. • •! ••-.•c.~~ - 52 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~ll ~?:.I Procurement!!/

V. EUROPE, MIDDLE EAST AND NORTH AFRICA

Ministry of Poets About (R) Telecommunications - Project Negotia_tions tentatively and 128.0 would consist of elements scheduled for mid-July, Telecommunications (Bank) included in a three year tranche of the telecommunica-­ Procurement: Advance tiona investment plan. contracting, under ICB, and according to Bank Guidelines for 5 contracts, totalling about $11,2 million equivalent. Possible retroactive financing of about $1,8 million equivalent,

Ministry of To be Water Supply in greater Further ~recessing dependent on Hydraulics deter­ Algiers - Expected to include resolution of remaining project mined works needed to help alleviate and sector issues. (Bank) the critical veter shortage in that area, and water supply/ Procurement: Project involves sewerage studies in small and advance contracting, with award intermediate cities, of a single contract for major civil works, and the possibility of retroactive financing of a small portion, SONELGAZ To be Power III - Project.would Preparation underway by deter­ include rural electrification, Government. mined (Bank)

Ministry of About (R) Southern Conveyor Water Appraisal report being prepared, Agriculture 12.0 Resources Development Project, (Co-financing will be required,) (Bank)

Ministry of Commerce 10.2 (R) Project for energy planning and Approved by the Executive and Industry; (Bank) conservation measures and Directors on May 19, Electricity renewable energy applications Authority of Cyprus on a pilot basis, Procurement: Retroactive financing of $300,000 to finance consultants contracted for project preparation and energy plan,

Ministry of 16.0 (R) Khrysokhou watershed Irrigation Approved by the Executive Agriculture (Bank) Development - Phase I to supply Directors on May 12 and signed on irrigation for 2,000 ha, May 20, Includes construction of Evretou dam, conveyance Procurement: Government has pipeline, storage ponds and iniciated, with Bank's consent, irrigation network, prequalification of contractors for construction of Evretou dam on which work is scheduled to EGYPT, ARAB REPUBLIC start January 1984, OF

Egyptian Public To be Fifth Drainage Project - Project to be prepared .by EPAD Authority for deter­ Continued support for Egypt's and Ministry of Health, Drainage Projects mined field drainage and bilharzia (EPAD) and Ministry (Bank) control program, of Health

See page 1 for footnotes. - 53 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~ll. ~11 Procurement!!/

EGYPT 1 ARAB REPUBLIC .Q! (Cont'd)

Arab Republic of 165.3 (R) El Dikheila Reinforcing Bar - Approved by the Executive Egypt (Bank) Direct Reduction/Electric Directors on May 12. Furnace Plant to produce rebars and light sections. Procurement: Bids on civil and building works received May 5. Technical proposals on bar mill submitted April 30. Invitation to bid on rod mill issued April 30. Prequalification for ' remaining packages well underway •

Arab Republic of . 41.5 . Irrigation Pumping Stations Loan signing on June 6 • Egypt (Bank) (R) Rehabilitation - Improve water control in existing major irrigation systems. Egyptian Electricity To be Fourth Power Project­ Project being prepared by EEA. Authority (EEA) deter­ Transmission. mined (Bank)

Arab Republic of 38.0 (R) Vocational Training I Loan signing on June 6. Egypt (Bank) Expansion and upgrading of vocational training in industrial and construction trades.

To be determined To be ·Gas Development V - Development Project to be prepared by deter­ and distribution of natural Egyptian General Petroleum mined gas. Corporation (EGPC). (Bank)

To be determined To be (R) Construction Industry Sector - Appraisal mission in the field. deter­ Assistance to Egypt's mined construction industry through (Bank) lines of credit and technical assistance.

Arab Republic of To be Vocational Training II - Project to be prepared by Egypt deter­ Continued support for Government. mined vocational training in Egypt. (Bank)

Egyptian Iron and To be (R) HADISOLB II - Stage two of Consultants are preparing a Steel Complex deter­ program to support HADISOLB to feasibility'report on which (HADISOLB) mined rehabilitate and balance its preliminary discussions are (Bank) present facilities. scheduled for late June.

Arab Republic of To be (R) Regional Water Supply/Sewerage Appraisal mission in the field. Egypt deter­ Engineering Loan - Provincial mined water supply and sanitary (Bank) engineering.

Arab Republic of 24.0 (R) Road Maintenance - Support for Board presentation scheduled for Egypt (Bank) Egypt's road maintenance June 28. program.

Arab Republic To be- (N) New Land Development II - Phase Project being prepared by the of Egypt deter­ II of the New Land Development Government and consultants. mined Project (West Nubariya). (Bank)

Arab Republic To be- (N) Agricultural Extension and Project being prepared by of Egypt deter­ Research - To assist Govenment Government/Bank and USAID. mined in developing national (Bank) agricultural extension and research.

See .page 1 for footnotes. - 54 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~1/ Lender J,./ Procurement 4/

EGYPT, ARAB REPUBLIC OF (Cont'd) Arab Republic To'be (N) Agricultural Credit for Project being prepared by the of Egypt deter- Mechanization - Line of credit Principal Bank for Development mined for farm mchanization in and Agricultural Credit (PBDAC) (Bank) several governoratea. in conjunction with Bank.

Arab Republic To be (N) Lake Manzala Development - Project being prepared by of Egypt deter- Reclamation and low coat Ministry of Land Reclamation and mined settlement of about 60,000 FAO/CP, (Bank) feddana of uncultivated land.

Arab Republic To be (N) DFC - Small and medium-industry Project being prepared by of Egypt deter- development. Credit channelled Government. mined through development finance (Bank) companies.

.!!Jlligfil (NATIONAL BANK OF 109.0 (R) Industry I - Energy Board presentation on June 14, HUNGARY) (Bank) conservation and interfuel (Co-financing to be sought.) substitution in selected induatriea,"and transfer of Procurement: Retroactive technology. financing of about $3.l million for project start-up activities.

(NATIONAL BANK OF 130.4 (R) Agriculture.- National grain Board presentation on June 14, HUNGARY) . (Bank) storage and agricultural · (Co-financing to be sought,) mechanization project.

(NATIONAL BANK OF To be (R) Industrial restructuring and Appraisal report being prepa~ed, HUNGARY) deter- export generation •. mined (Bank)

(NATIONAL BANK OF To be Petroleum I - Enhanced oil·· Project preparation underway, HUNGARY) deter- recovery/deep drilling for (Co-financing likely to be mined oil/gas. sought,) (Bank)

(NATIONAL BANK OF To be (R) Transport I - Railways, roads, Project under preparation, HUNGARY) deter- road transport, and possibly an (Co-financing likely to be mined inland waterway component. sought.) (Bank)

Jordan Valley To be Construction of a multi-purpose Further project processing Authority deter­ dam on the Yarmouk River at suspended at Government's mined Maqarin and improvement of request,_pending progress on (Bank) irrigation facilities in Jordan international riparian issues. Valley.

(ARAB POTASH About (R) Dead Sea Chemicals - Processing Feasibility study on potassium COMP~)° 2s.o by-products of the potash sulphate unde~ review, Appraisal (Bank) refinery, mission.tentatively scheduled for July, (Co-financing Ukely to be required.)

Ministry of About Education VI - Construction/ Appraisal report being prepared. Education 30.0 equipping of primary and (Co-financing likely to ~e (Bank) general secondary schools and required.) school laboratories, and technical assistance,

I See page l for footnotes, - 55 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing ·probable ing and Action on Agency 1/. Lender 1/ Project 1/ Procurement f!/ JORDAN (Cont'd)

Amman Water Supply To be Waste water evacuation and Preparation under way by Authority (AWSA) deter­ treatment in Amman Region. Government. (Co-financing likely mined to be required.) (Bank)

Amman Municipality About (R) Amman Transport and Municipal Board presentation on July 5. 30.0 Development - To include (Co-financing is being (Bank) upgrading and rehabilitation, arranged.) traffic engineering, road maintenance and signaling equipment, solid waste disposal, and technical assistance. Total cost estimated at $56 million of which foreign exchange $33 million.

Water Supply To be (R) Water supply rehabilitation and Preparation under way by· Corporation (WSC) deter- sewerage in seven cities. Government. ndned (Co-financing likely to be (Bank) required.)

To be determined About (R) Energy Development, including Appraisal report being prepared. 25.o power distribution, oil (Bank) exploration, renewable energy, and energy audits.

To be determined To be (N) Transport including railway, Preparation underway by deter- roads and port improvements. Government. mined (Bank)

To be determined To be Fisheries - Development of Preparatory studies under way. deter- fishing fleet and related port mined infrastructure, support (Bank) services to fishing industry, and marketing facilities.

To be determined To be Sewerage - Rehabilitation and Preparation underway by deter- extension of sewer network for Government and consultants. mined .Casablanca-Mohammedia region. (Bank)

Ministry of Public To be Family Health Program including Preparation underway by Health deter- basic health services, Government. mined training; health.education, (Bank) environmental sanitation, .and Bank Project Preparation Facility technical assistance-to advance of $75,000 approved to Ministry of Public Health. finance consultant services, logistical support, and additional surveys for the preparat.ion of the proposed health project, to test a new outreach system for the delivery of basic health services in Morocco.

See page 1 for footnotes. - 56 -

Menjber Country, and Borro~ei or Amount & Stage of Process­ Implementing Probable ing and Action on ~1/ 1!!!!!!!. ll Procurement!/ !!Q!Q££2. (Cont'd)

Fonds d'Equipement 16.0 (R) Municipal and Village Loan Loan signed on May 23. Communal (FEC) (Bank) Fund - Support for FEC's program to assist local authorities to identify, prepare, and finance communal infrastructure and production projects.

Ministry of 30.0 (R) Agricultural development on Loan signed on May 23. Agriculture (Bank) about 330,000 ha. in the Oulmes Rommani Regions, including: crop, forage and livestock development on rainfed lands; rehabilitation and extension of small-scale irrigation; and soil conservation measures.

Government of About Power IV - Construction of Appraisal report being prepared. Morocco 88.0 Debar el Oued multi-purpose dam (Co-financing will be required.) (Bank) and power plant. Procurement: ·Retroactive financing for an amount not exceeding $500,000 for project start-up activities is proposed.

Ministry of 85.0 Highway IV - Pavement Approved by the Executive Transport (Bank) strengthening and improvement, Directors on March 29. reconstruction of bridges, improvement of provincial roads, completion of Casablanca-Rabat Expressway, program of road maintenance, studies and technical assistance. Government of To be Telecommunication project - Preparation underway by Morocco deter­ Expansion of the existing Government. mined telecommunications systems. (Bank) Government of 25.0 Electro-mechanical Industries Government reactions awaited on Morocco (Bank) Project - Line of credit to key project issues and scope. Treasury, to be on-lent through Banque Nationale pour le Bank Project Preparation Facility Developpement Economique (BNDE) advance of $200,000 approved to and commercial banks to help set up an Industrial electrical, mechanical, and Planning and Policy Unit. metallurgical industries, as well as financing through Itr Office de Developpement Industrie (ODI) of participa­ II tions in such industries; Ii institutional strengthening, ii technical assistance. Government of 42.0 Development of small and medium Approved by the Executive Morocco (Bank) irrigation perimeters. Directors on March 29.

Office Cherifien des To be Establishment of about 10 Preparation underway by Phosphates (OCP) deter­ fertilizer blending and Government. mined distribution centers. (Bank)

O!IAREP 75.2 (R) Petroleum Exploration - Loan signed on May 23. (Bank) Follow-up to ongoing exploration project to support continuation of drilling in Essaouira and preparation of market and engineering studies.

See page l for footnotes. - 57 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing end Action on ~1.l ~11 Procurement ~/

~ (Cont'd)

Ministry of About Beni Amir Irrigation - Appraisal report being prepared. Agriculture 43.0 Rehabilitation of 13,000 ha and (Bank) construction of new system on 5,400 ha.

Caisse Nationale About CNCA V - Line of short- and Appraisal report being prepared. Credit Agricole 100.0 medium-term credit to CNCA over (Co-financing being sought•) (CNCA) (Bank) 1984-86.

Kingdom of Morocco To be Education VI - Strengthening of Preparation under way by deter­ vocational training. Government. mined (Benk) To be determined To be Casablanca Port - Preparation underway by deter­ Rehabilitation and extension of Government; pre-appraisal mined Casablanca Port; technical completed in March. (Bank) assistance to improve efficiency of port operations.

Office National Eau To be Fourth Water Supply - Identification/preparation under Potable (ONEP) ·deter­ Construction of regional water way by Bank and ONEP. mined supply systems in Settat - (Bank) Casablanca area and in rural centres of the Ouarzazate Province; house connection programs, and line of credit to ONEP.

PORTUGAL

To be determined About Textiles - Line of credit to Institutional arrangements for so.o finance modernization and project under discussion with (Bank) restructuring of textiles Government. (Co-financing likely enterprises. to be required.) To be determined To be (R) Fisheries development project. No project has been identified; deter- Components to be defined. therefore, further reporting on mined this item will be discontinued. (Bank)

Republic of Portugal To be (R) Agro-industry - Credit for Preparation underway. deter- expanded production and mined processing of fruits, (Bank) vegetables, wine, and dairy products.

Republic of Portugal 40.3 (R) Small and Medium-size Industry Loan signed on May 27. (Bank) (SKI) II - Second line of credit for small-and medium-size private enterprises. To be determined To be Mechanical Industries II - Preparation underway. deter-. Support to enterprises in (Co-financing likely to be mined mechanical and engineering required.) (Bank) industry for rehabilitation and modernization.

To be determined About Industrial Technology - Technical studies under review. so.o Upgrading of technological (Bank) support facilities for industry in light of needs for EEC entry.

Republic of Portugal About Housing - Possibly a general Preparation under way. so.o line of credit to provide (Bank) housing finance for low-income groups through a housing development bank.

See page 1 for footnotes. - 58 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~1.1 Lender 7=_/ Procurement!!/ PORTUGAL (Cont'd)

Republic of Portugal To be (R) · Coal Handling Port - Preparation under way. deter­ Construction of coal handling (Co-financing likely to be mined and general cargo facilities at required.) (Bank) Sines. Procurement: Firms prequalified for first phase of civil works and bide invited.

To be determined To be (N) Municipal Water Supply and Preparation underway. deter- Sewerage - provision of water mined supply and sewerage facilities (Bank) to municipalities, under overall sector program. ROMANIA

(INVESTMENT BANK) To be Industry XII (Galati Steel) - Appraisal mission postponed at deter- Construction at Galati steel the Government's request, pending mined enterprise of a cold reduction finalization of overall (Bank) mill and tinning line. development program. ·

(INVESTMENT BANK) To be Industry XI (Energy Saving Completion of techno-economic deter- Project and·Proceee Improvement studies delayed, pending mined in Steel Sub-sector and/or finalization of overall (Bank) coking coal plant) - Project development program. components to be determined. (Co-financing likely to be sought.)

(AGRICULTURAL BANK) About Agricultural Credit Negotiations postponed at the 66.0 (Transylvania) - Regional Government's request, pending (Bank) development project, including finalization of overall financing of agricultural and development program. agro-induetrial investment in (Co-financing likely to be Transylvania Region. sought.)

(AGRICULTURAL BANK) To be Agricultural Credit (Oltania) - Project preparation underway. deter­ A line of credit through BAFI (Co-financing likely to be mined for agricultural development in sought.) (Bank) the Oltania Region.

(AGRICULTURAL BANK) To be Irrigation IX - Drainage, land Appraisal mission delayed at deter­ reclamation and other related the Government's request, mined works on a sectorwide basis pending finalization of overall (Bank) within the context of the development program. Five-Year Plan. (Co-financing likely to be sought.)

(INVESTMENT BANK) To be Power V - Time slice investment Appraisal mission postponed at deter­ for second half of 1981-85 the Government's request, pending mined Plan. finalization of overall (Bank) development program.

(INVESTMENT BANK) To be South Constanta - Agigea Port - Appraisal mission postponed at deter­ Deep sea port and inner barge the Government's request, pending mined basin and other related finalization of overall (Bank) structures and equipment. development program. (Co-financing likely to be sought).

(AGRICULTURAL BANK) To be National Grain Storage - A line Appraisal mission postponed at deter­ of credit for expansion, the Government's request, pending mined rehabilitation and modernization finalization of overall (Bank) of national grain storage development program. facilities. (Co-financing likely to be sought).

(INVESTMENT BANK) To be Highways I - Construction of Completion of project studies deter­ 200 km of North-South 'delayed, pending finalization of mined Trane-European Highway overall development program. (Bank) (Bucharest-Constanta Section), and National Road Rehabilitation and Training,

See page 1 for footnotes. - 59 -

Member Country, and Borrower or Amount & Stage of· Process­ Implementing Probable ing and Action on ~ll Lender ]:.I Procurement.!/ ROMANIA (Cont'd)

(INVESTMENT BANK) To be Industry - Utilization of methane Completion of techno-economic deter- as chemical feedstock. studies delayed, pending mined finalization of overall (Bank) development program,

( INVESTMENT BANK) To be Petroleum II - Onshore deep Completion of techno-economic deter- exploration and field studies delayed, pending mined development. finalization of overall (Bank) development program.

(AGRICULTURAL BANK) To be Livestock V - Possible line of Completion of project studies deter- credit for production, delayed, pending finalizatiQn of mined processing and storage of major overall development program, (Bank) livestock products.

SYRIAN ARAB REPUBLIC·

To be determined To be Sewerage I - Sewerage Awaiting Government decision on deter- facilities for Rama and Homs, institutional arrangements. mined and institution-building in (Co-financing arranged with (Bank) sub-sector. Arab Fund,)

Syrian To be Telecommun_ications II - Awaiting Government decision on Telecommunications deter- Expansion of telecommunication . project scope and financing, Establishment (STE) mined services·in selected urban and (Bank~ rural areas. To be determined To be (R) Highways IV - Priority roads in Project being prepared by deter- NE Syria, maintenance operations Government. mined and training •. (Bank)

To be determined To be Sewerage II - Secondary treatment Awaiting Government decision on deter-· works, main interceptors and institutional arrangements,· mined secondary collection system for (Co-financing will be sought,) (Bank) Aleppo sewerage facilities,

To be determined To be (R) Education III - Extension of Preparatory studies underway, deter- vocational education and mined training. (Bank)"

Office National de 34.0 Urban Sewerage III - Rehabili­ Approved by the Executive l'Aeeainieeement (Bank) tation and expansion of sewerage Directors on March 29, (ONAS) systems in about 30 towns. Procurement: Project involves advance contracting, and retroactive financing of about $300,000 for final studies of the sewage system and preparation of bid documents,

Societe de Fonderie 16.8 (R) Industry IV - Rehabilitation and Approved ·by the Executive et de Mecanique (Bank) expansion of foundry to help meet Directors on June 2, (SOFO~CA.) the growing local demand for foundry products, and improve the Bank Project Preparat.ion ·Facility quality and cost effectiveness of advance of $600,000 approved to· castings thus creating also a complete preparation and finance sound ba·eis for exports, The the engineering for the project, project will consist of (i) modernization of SOFOMECA'e existing iron and steel foundry and reorganizing the productive facilities and installing new equipment; (ii) installation of a new fully-equipped. foundry for mechanical castings; and (iii) construction of a sand treatment plant to supply Tunisian foundries and other industrial users with high-quality sand,

See page 1 for footnotes, - 60 -

Member Country, and Borrower or Amount 6 Stage of Procees­ Implementing Probable ·ing and Action on ~ll ~l:.I Procurement i/

~ (Cont'd)

To be determined To be Irrigation Rehabilitation III - Project under preparation by deter- National Irrigation: Operation Government, mined and maintenance improvement (Bank) project,

To be determined About Energy Development - Possible · Identification mission scheduled 35,0 focus on onshore or off-shore for late 1983, (Bank) gas development,

To be determined To be Development of national Preparation by Government and deter- research and extension master FAO/CP underway, miried plans through integrated (Bank) cereal-livestock production project for Northern Tunisia,

To be determined To be Small Scale Industry II - Line Preparation by Government· deter- of credit to Government to be underway, mined used by colDIDercial banks for (Bank) lending to small-scale industries, .

To be determined To be Highways VI - Maintenance Project under preparation by deter- Project (follow up to Highways Government and consultants •. · mined IV), (Bank)

To be determined/ About (R) Nationwide Rural Water Supply Appraisal report being prepared, 44,5 Project, (Bank)

Gafsa Phosphate Co, About (R) Technical Assistance to Mining Appraisal report being prepared, and Ministry of 14,0 Sector to help improve and National Economy (Bank) expand operations of Gafsa Phosphate Company and investigate feasibility of establishing a potash industry,

Ministry of About (R) Sfax Flood Protection Project - Approved by the Executive Equipment 25,0 Consists of rehabilitation of Directors on May 24, (Bank) existing water courses and extension of dikes; Procurement: Retroactive construction of a belt canal in financing of about $600,000 for Sfax and minor flood protection detailed designs and bid works in neighboring villages; documents,· provision of maintenance equipment; staffing, equipping and operation of a unit to maintain and repair flood protection works; and provision of consulting services for related design and construction supervision.

To be determined To be Urban Transport II - Appraisal mission tentatively deter­ Investments in highway scheduled for September/October, mined infrastructure and traffic (Bank) management; strengthening of sector institutions,

Min~stry of Health To be Extension of integrated primary Pre-appraisal mission scheduled deter­ health care system (follow-up for June, mined to 1981 project), '(Bank)

See page l for footnotes, - 61 -

Member Country, and Borrower or Amount & Stage of Process­ Imp.Lemen ting Probable ing and Action on ~!/· Lender y Procurement i/ .I!!fil!!! (Cont'd)

Tunisian Electricity To be (R) Power IV - Continuation of Appraisal mission in mid-June. and Gas Company deter- ongoing program of rural (STEG) mined elec trif ica tion. (Bank)

To be determined To be Export Industries - Line of Preparation under way by local deter- credit for develnpment of development banks and Government. mined industries mainly oriented (Bank) towards export markets.

SOGITEX To be (N) Rehabilitation end expansion Preparatlon underway by SOGITEX deter- of textile mill; phase II of and consultants. mined ongoing project. (Bank)

Agricultural Bank of 150.4 (R) Agricultural Credit II - Board presentation on June 14. Turkey (TCZB) (Bank) Provision of agricultural credit through TCZB.

State Pulp end Paper To be (R) Paper Rehabilitation: Phase I Appraisal report being prepared. Enterprise (SEKA). deter­ - Rehabilitation of AKSU and mined Caycuma Mills; technical Bank Project Preparation Facility (Bank) assistance to improve (PPF) advance of $60,000 approved operations. to finance preparation work required for rebuilding the Dalaman board machine. This is a supplement to the PPF advance of $500,000 made in January 1981.

Republic of Turkey To be (R) Livestock Products Development Consultants selected by deter­ - Modernization of extraction Government; contract being mined and processing of livestock negotiated. (Bank) products from slaughtering stage onwards, for both export and domestic markets; and rationalization and expansion of milk and milk products industry.

Republic of Turkey 115. 3 (R) IAEE Irrigation: Completion of Board presentation on· June 14. (Bank) on-going irrigation and on-farm works; strengthening of Procurement: Retroactive extension services. financing up to $4 million for contracts signed after January 1, 1983.

Republic of Turkey; To be (R) Development of selected lignite Preparation mission tentatively TKI deter­ field(s) to expand production; scheduled for July. mined confirmation of lignite local (Bank) deposits and related technical Project Preparation Facility assistance. advance of $950,000 provided to help finance foreign exchange costs of preparation work.

Republic of Turkey 300.8 (R) Structural Adjustment Loan IV - Board presentation scheduled for (Bank) To support structural June 23. adjustment in key areas.

To be determined To be Paper Rehabilitation - Phase Timing dependent upon progress of deter- II. Further rehabilitation of Phas·e I project. mined existing paper mills and (Bank) technical assistance to improve operations.

To be determined To be Export-Oriented Industries II - Timing dependent upon progres.s of deter- Balaucing or expansion of earlier loan for export-oriented mined carefully selected industries. (Bank) export-oriented private enterprises.

See page 1 for footnotes. - 62 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing end Action on ~ll ~11 Procurement!!./ TURKEY ceo.nt' d)

To be determined To be ·Small & Medium Industries - Identification mission scheduled deter­ Assistance to small and medium for July, mined scale industries through Halk (Bsnk) Bank and/or SYKB,

To be determined About (R) Thrace Gas Development - Appraisal mission planned for 100,0 Development of Thrace gas field end-September, (Bank) for either power-generation and/or fertilizer production.

To be determined To be (R) Agricultural Extension and Appraisal mission in early-Jupe, deter­ Applied Research - To mined strengthen and reorganize· (Bank) provincial agricultural extension and applied research services in a few selected provinces.

To be determined To be (R) Industrial Training - Develop­ Appraisal mission in the field, deter­ ment of in-service and mined pre-service industrial training (Bank) of supervisors, technicians and engineers.

·Turkish.Electricity 163,0 (R) TEK Power Transmission - To Board presentation scheduled for Authority (TEK) (Bank) support the construction of June 23, about 1500 km of 380-kv transmission lines to accommodate new generating capacity from plants being commissioned between 1983 and 1986; technical assistance,

Republic of Turkey To be Highways II - Rehabilitation of Preparation underway, deter­ selected roads; provision of mined equipment for roadworks and (Bank) highway safety; technical assistance and transport sector studies,

Turkish Petroleum About (R) Thrace Basin Gas Exploration - Board presentation scheduled for Corporation 55,2 Appraisal of recently dis­ June 28, (Bank) covered gas field and explora­ tory work to establish gas (~ reserve potential of Thrace B~in. I

Republic of Turkey About Technical Assistance to Appraisal report being prepared, 10.0 selected state economic (Bank) enterprises,

To be determined To be (N) Energy Saving - Energy Saving Studies/energy audits underway, deter­ investments in selected mined industries in public and (Bank) private sectors.

To be determined To be (N) Port Expansion - Expansion of Identification/preparation deter­ port capacity, modernization of mission scheduled for end-June, mined existing facilities, training (Bank) and studies,

See page 1 for footnotes, - 63 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on Agency 1/ 1!!!ill.1/ Procurement!!/ YEMEN ARAB REPUBLIC

Ministry of To be Wadi Jaw£ - Agriculture and Preparation underway. Agriculture deter­ rural development, including (Co-financing likely to be mined credit, feeder roads, extension required: Islamic Bank and (IDA) and livestock. Saudi Fund have expressed interest.)

Yemen r.ener!ll 19.0 (R) Power III - Regional Approved by the Executive Electricity (IDA) Electrification Phase II - To Directors on May 10 and sigaed on Corporation (YGEC) assist YGEC in extending its May 17. (Co-financing agreed with se?:Vice, at least cost, in the Islamic Bank for $9.0 million.) urban and rural areas, facilitate better utilization of its generation and transmission facilities, and strengthen its staffing, management, planning and finances.

Ministry of About (R) Central Highlands Agricultural Appraisal mission scheduled for Agriculture a.o Development - Agricultural July. (Co-financing under (IDA) development of Anis area in the discussion with various Central Highlands, including agencies.) minor irrigation, extension and credit.

Ministr,,.of 10.0 (R) Education V - Construction in Credit signed on May 17. Education (IDA) rural areas of primary teacher (Co-financing agreed with USAID training institutes and for $1.2 million.) district training centers, and provision of technical assistance.

Highway Authority About (R) Highways V - Construction of Negotiations substantially 13.0 about 32 km of high priority completed. (IDA) secondary roads and continuation of support for Procurement: Retroactive highway maintenance to Highway financing of up to $250,000 Authority. recommended.

Ministry of To be Rural Water Supply - Preparation underway. Electricity, Water deter- Engineering rehabilitation and (Co-financing likely to be and Sewerage mined maintenance of rural water required.) (IDA) supply systems.

Ministry of To be (R) Urban II - Slum upgrading, and Appraisal mission in the field. Municipalities and deter- sites and services components .(Co-financing may be required.) Housing mined in Hodeidah. (IDA)

Ministry of 11.0 (R) Supplemental Credit: Ibb and Appraisal mission scheduled for Electricity, Water (IDA) Dhamar Water Supply and September. (Co-financing will be and Sewerage Sewerage Project; and house required. Original cofinanciers: connections in project areas. Germany, The Netherlands and Arab Fund have expressed interest.)

Ministry of About Education VI - Construction in Appraisal report being prepared. Education 12.0 rural areas of primary teacher (IDA) training institutes and district training centers, and provision of technical assistance.

See page 1 for footnotes. - 64 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on .!e!ll. ll ~ll Project 11 Procurement 4/ YBMEH AIAB REPUBLIC (Cont'd)

Ministry of Economy To be (N) Industrial Bank of Yemen (IBY) Preparation underway, and Industry deter- II - Credit line to IBY to mined finance investment requirements (IDA) and provide further institutional support to IBY,

Yemen OU and To be (N) Minerals Exploration - Minerals Preparation underway, Minerals Resources deter- exploration, including Corporation mined feasibility studies, financing (YOMINCO) (IDA) of equipment, and technical assistance.

YEMEN. PEOPLE'S DEMOCRATIC REPUBLIC OF

Public Water 7,0 (R) Water Supply II - Water supply Negotiations substantially Corporation (IDA) for Greater Seiyun, and completed, (Co-financing of $6,8 assistance to Public Water million expected from Arab Fund,) Corp, (PWC) on sector investment priorities,

Mi.n:l.etry of 7,6 (R) Health Development I - Approved by the·Executive Health (IDA) Strengthening of primary health Directors on May 31, services, health manpower (Co-financing arranged with WHO development, and technical $0,6 million and UNICEF $0,4 assistance to Ministry of million,) Health,

Ministry of 6,0 (R) Education IV - Financing of Negotiations scheduled for early Education (IDA) vocational instructor training November, (Co-financing likely institute, rural extension to be required,) training center, educational materials production center, An IDA Project Preparation school maintenance program, and Facility advance of $220,000 technical assistance for each, approved to help establish a national coordinating tmit for vocational and technical training,

Ministry of To be Highways IV - Tentatively, Project preparation tmderway, Construction deter- procurement of road maintenance (Co-financing likely to be mined equipment; technical assistance required,) (IDA) and training for Highway Department,

Ministry of To be Agriculture Research and Project scope being identified, Agriculture and deter- Extension - To strengthen Agrarian Reform mined national agricultural research (IDA) and extension.

YUGOSLAVIA

Eight Yugoslav 120,0 (R) Power Transmission III - Negotiations substantially Electric Power (Bank) Financing of investments for completed, (Substantial Organiza'tiona national transmission network co-financing required for digital end control system, data processing equipment: hardware and software~)

Four Yugoslav About (R) Railway VI - To finance a Negotiations substantially Railway Transport 110,0 portion of the 1981-85 completed, Board presentation Organizations (Bank) Development Plana of the scheduled for July 12, Railway Transport (Co-financing likely to be Organizations: Belgrade required for rolling stock and (Serbia), Novi Sad (Vojvodina), other railway equipment,) Sarajevo (Bosnia-Herzegovina), and Skopje (Macedonia),

See page l for footnotes, - 65 -

Member Country, and Borrower or Amount & Stage of Process­ Impiementi!'8 Probable ing and Action on .Y!!!!.!:I. !/ . Lender 1/ Procurement!!/ YUGOSLAVIA (Cont'd)

Udruzena Beogradska 136.0 (R) Serbia Regional Development - Board presentation on June 9, . Benke (UBB) (Bank) Regional development primarily focussing on agriculture and (Efforts being made by Borrower agro-industries in less­ to secure about $50 million developed areas of Serbia. co-financing from commercial banks abroad,)

Procurement: Retroactive financ­ ing of up to $2,8 million for' preparing final designs and bidding documents for drainage; and for P;imary production.

To be determined To be (R) Montenegro Regional Appraisal mission in the field, deter­ Development - Regional mined development primarily focussing (Bank) on agriculture and agro-induetriee in less-developed areas of Montenegro.

Kosovska Banks About (R) Kosovo Regional Development - Board presentation on June 9. Pristine 79.0 Regional development primarily (Bank) focussing on agriculture and Procurement: Retroactive agro-induetriee in lees­ financing of up to $6,0 million developed areas of Kosovo, for preparation of rural roads.

To be determined About Highways XII - To assist Project preparation underway. 100.0 financing of construction of (Co-financing will be sought,) (Bank) priority roads including sections of the Trane-Yugoslav Highway.

Kosovoska Banks . About Industrial Credit VII - Line of Negotiations substantially Pristine; 10.0 credit primarily £.or labor completed, (Co-financing likely Investiciona Banka (Bank) intensive and export oriented to be required,) Titograd projects in Kosovo and Montenegro.

Privredna Banka About Bosnia Forestry - Development Awaiting Borrower's agreement on Sarajevo 70,0 of forest roads and project scope, (Suppliers' and (Bank) plantations, and provision of export credits may be utilized logging equipment, for road construction, logging and forestry equipment.)

To be determined About Lonjeko Polje Drainage Awaiting Government decision on 90,0 (Previously reported as part of institutional arrangements, (Bank) Sava Drainage II,) - Provision of drainage to about 49,000 ha in Croatia, Will include pumping stations, on-farm development, construction and farm equipment.

Udruzena About (R) Structural Adjustment Loan - To Negotiations completed. Board Beogradska 275.0 help Government address presentation scheduled for June Bsnka (Bank) medium-term adjustment issues, 28, especially in areas of investment, foreign trade, relative prices and energy, Funds to be disbursed through an export development fund to finance imports of raw materials, spare parts and capital goods for exporting industries,

See page 1 for footnotes, - 66 -

Member Country, and Borrower or Amount & · Stage of Process­ Implementing Probable ing and Action on ~!/ Lender J,l Procurement~/ YUGOSLAVIA (Cont'd)

Elektropnreda Boane 61.0 (R) Kiddle Neretva Hydropower - Negotiations substantially I Bercegouine­ (Bank) Supplementary Financing - completed. Sarajevo Construction of dam at Mostar and·power plant downstream, of recently completed 205 KW Salakoyac hydropower dam on Neretva River (under Loan 1561-YU).

Vojvodanska Banka, About (N) Fertiiizer Secto·r - Financing Appraisal completed. Novi Sad eo.o inputs, raw materials, tech­ Negotiations tentatively (Bank) nical and energy audits for scheduled for early-September. Yugoslav.. fertilizer industry,­ including incremental fertilizer requirements for. 1984-85.

See page l for footnotes. - 67 -.

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~1/ Lender J,l Procurement.!!/

VI. LATIN AMERICA AND CARIBBEAN

ARGENTINA

Ministry of Commerce 155.0 Ports I - Expansion and Economic reassessment of project and Maritime Affairs (Bank) modernization of Bahia Blanca and final design still pending, port facilities for grain exports. Total project cost estimated at $180 million of which about $130 million in foreign exchange.

Ministry of Public Up to Water Supply and Sewerage - Awaiting Government decision on Works, Sub-Ministry 195.0 Improvements and extensions to Central Coordinating Office, of Hydraulic (Bank) water supply and sewerage Resources, Direccion systems in the provinces of Provincial de Obras Mendoza and Santa Fe, including Sanitarias (DIPOS) technical assistance for and Obras Sanitaries institutional improvem~nt. de Mendoza (OSK)

Ministry of 100.0 (R) Highway.Sec~or - Improvements Approved by the Executive Public Works and (Bank) and construction of sections of Directors on May 31, Services the nationai h:1.ghway network ,in FYi983:86 and provincial· investment program. Tot~1- program cost estimated at $930.million of which. $350 million in fo~eign exchange,

(YACIMIENTOS 100.0 Oil and Ga~ Development· iI. Appraisal report being prepared, PETROLIFEROS (Bank) FISCALES (YPF))

BARBADOS

Ministry of Finance 12.0 Structural Adjustment Loan - To Proposal under consideration. (Bank) support Government economic program, ·

Ministry of Works 5.3 (R) Road Maintenance and Loan approved by the Executive (Bank) Rehabilitation·- Rehabilitation Directors on May 3 and signed on of priority roads, provision of May 13, - equipment and-strengthening of maintenance organization, Total project cost estimated at $7,1 million of which $5,3 million in foreign exchange,

Ministry of Energy To be (R) Power I - Rehabilitation and Reassessment of scope and and Communications deter­ expansion of transmission. and estimated cost of project are mined distribution facilities; energy pending, (Bank) studies, institutional strengthening,

See page 1 for footnotes. - 68 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~1/ Lender J,.I Procurement !ii .11.QhlilA

(EMPRESA NACIONAL DE 35.0 (R) Power V - Central Oriental Further processing depends on ELECTRICIDAD (ENDE)) (Bank) interconnection system, fourth reaching agreement with unit for Santa Isabel, and Government on actions needed to study of ENDE's and DINE's resolve current economic problems. organizational expansion, and a national tariff study. Total Government has also requested project cost estimated at $57.3 financing from Inter-American million of which $45 million in Development Bank for project. foreign exchange. Decision on participation is awaited.

Procurement: Advance contracting under !CB satisfactory to Bank for about $2.8 million; retroac­ tive financing of $0.2 million.

Ministry of ltural and 10.0 Santa Cruz Agricultural Further processing depends on Agricultural Affairs (Bank) Development - Credit, technical reaching agreement with assistance and social infra­ Government on actions needed to structure for settlement con­ resolve current economic solidation in Northern Santa problems. IDA Project Prepara­ Cruz. Total project cost tion Facility advance of $50,000 estimated at· $16.9 million of approved for technical studies. which $5.7 million in foreign exchange.

Ministry of Rural Up to Agricultural Credit II - Credit Further processing depends on and Agricultural 15.0 and technical assistance for reaching agreement with Affairs (Bank) crop and livestock development. Government on actions needed to resolve current economic problems.

(YACIMIENTOS 64.0 Oil and Gas Development - Further processing depends on PETROLIFEROS (Bank) Liquids condensate extraction reaching agreement with FISCALES BOLIVIANOS and gas recycling at Vuelta Government on actions needed to (YPFB)) Grande gas condensate field and resolve cur~ent economic secondary oil recovery at problems. Monteagudo oil fields. Total project cost estimated at $74 Procurement: (a) Project million of which $60 million in Preparation Facility advance of foreign exchange. $1 million approved for gas recycling simulation study, detailed design and preparation of bidding documents; (b) advance contracting under !CB satisfac­ tory to Bank for up to $24 million and retroactive financing of up t~ $6 million for drilling under consideration.

Ministry of Finance 30.0 BISA III - Assistance for small Further processing depends on (Bank) and medium mining operations reaching agreement with through local financial Government on actions needed to intermediaries, Banco implement project and resolve Industrial and Banco Minero. current economic problems.

(YACIMIENTOS 40.0 (R) Gas Pipeline Engineering - Further processing depends on PETROLIFEROS .(Bank) Engineering studies for reaching agreement with FISCALES BOLIVIANOS construction of natural gas Government on actions needed to (YPFB)) pipeline from Bolivia to resolve current economic Brazil. problems.

Instituto Nacional 75.0 Northwest Region Development Appraisal report being prepared. de Colonizacao e (Bank) Program III - New settlements. Reforms Agraria Total project cost estimated at (INCRA) $262 million of which $65 million in foreign exchange.

State of Sao Paulo Up to (R) Sao Paulo Health - Development Awaiting Government decisions on 40.0 of primary .health services in project issues and facility (Bank) State of Sao Paulo. Total designs. project cost estimated at $113.6 million of which $40 million in foreign exchange.

See page 1 for footnotes. - 69 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on !8!!:i!£l'.. 1/ Lender J,/ Procurement f!/ ~.(Cont'd) Secretaria de 67,8 (R) Bahia Rural Development II-· Loan signed on May 23, Planejamento da. (Bank) Integrated rural development in Presidencia, da northeast Bahia to assist small Republica farmers through provision of improved support services, land redistribution and infrastruc~ ture development,. Total project cost estimated at $173,6 million of which $25,6 million in foreign exchange,

Ministry of Up to Education V - Strengthening of Post-appraisal mission scheduled Education and 50,0 Brazil's secondary agricultural for June. Culture (Bank) school system through provision of training, equipment, furni­ ture, curriculum development and other technical assist­ ance, and assistance to second­ ary techn.ical schools.

Federative Republic 400,0 (R) Agro-Industries III - Credit Loan signed on May 25, of Brazil (Bank) for Agro-industries through the Central Bank of Brazil, Total project cost estimated st $1,140 million of which $400 million in foreign exchange,

Federative Republic 200,0 (R) Rural Electrification - Awaiting Government proposals on of Brazil (Bank) Connection to 140,000 rural electricity tariffs, consumers in the states of Minas Gersis and Parsna, Total project cost estimated st $639 million of which $233 million in foreign exchange,

Federative Republic 52,7 (R) Parsns Market Towns - Municipal Board presentation delayed to of Brazil (Bank) infrastructure and public await clarification of e·conomic services for minor urban situation, centers, Total project cost estimated at $150,2 million of which $52,7 million in foreign exchange,

Ministry of 40,0 (R) Education VI - Primary Appraisal continuation mission in Education and (Bank) Education in the North and the field, Culture Center-West areas.

Ministry of 100,0 (R) Education VII - Support for Appraisal continuation mission in Education and (Bank) science education and research the field, Culture development,

Petroleo Brssileiro 200,0 Gas Pipeline - Construction of Project preparation underway, S,A, (PETROBRAS) (Bank) natural gas pipeline from Santa Cruz, Bolivia to Sao Paulo,

Centrsis Eletricas Up to ELETROBRAS Distribution II - Appraisal report being prepared, Brasileirss S,A, 250,0 Power distribution in less (Bank) developed areas (Alagoas, Piaui, Mar·anhao, Amszonas, Rondonia) and for low-income consumers (Rio and Sao Paulo),

Federative Republic Up to (R) CODEVASF Irrigation - Follow-up Sector policy paper being of Brazil 50,0 irrigation development in the prepared by FAO/CP being reviewed (Bank) ~ortheast (probably in Sao with Government, Francisco river valley); studies; institutional strengthening,

Petrobras Up to (R) Fertilizer/Refinery - Energy Further processing and status of Fertilizsntes S,A, 100,0 Conservation - Energy_ ·project dependent on outcome of (PE;tROFERTIL) (Bank) conservation and plant energy sector review and strategy rationalization in the refinery definitions presently under way, and fertilizer sectors,

See page 1 for footnotes, - 70 "-

Member Country, and Borrower or Amount & Stage of Process­ Implement,ing Probable ing and Action on ~ll Lender J,/ Project 11. Procurement!!/

~ (Cont'd)

Federative Republic Up to Rural Development - Northeast Project preparation underway. of Brazil so.o Region I - Support of selected (Bank) regionwide rural development activities.

Federative Republic Up to (R) Alcohol and Biomass Energy Sub-aector review miasion in the of Brazii 150:0 Development II - Second phase field. (Bank) supp~rt for Brazil gasohol program.

Federative Republic 50.0 (R) Road Maintenance -·Improve Identification mission in the of Brazil (Bank) capabilities of rural state field. highway departments in the maintenance of roads.

Federative Republic 350.0 Industrial Sector - Industrial. Appraisal report being prepared. of Brazil (Bank) export development focusing·on improvement of import program _ for export production.

Federative Republic Up to Inland Waterways - Ports II - Awaiting information from of Brazil 100.0 Port development and waterways Ministry regarding investment (Bank) improvement. priori t:1.ee.

Federative Up to (R) Agricultural Sector - Loan Appraisal report being prepared. Republic of 300.0 would support changes in Brazil (Bank) Government agricultural credit policies.

Federative Up to Supplemental-Agriculture Appraisal report being prepared. Republic of 100.0 Project Financing - To provide Brazil (Bank) supplemental financing for agriculture projects.

Federative Republic Up to (R) Supplemental - Rural Roads - To Project discontinued. Other of Brazil 10.0 provide supplemental financing measures provided for under (Bank) for rural roads projects. Program of Special Assistance.

CARIBBEAN REGIONAL

Caribbean 1.0 (R) CDB III -.Credit for projects Loan approved by the Executive Development Bank (IDA) in Eastern Caribbean. Directors on May 17 and signed on (CDB) Mey 27.

CENTRAL AMERICA REGIONAL

Central American 50.0 Central American regional Project preparation underway. Bank for Economic (Bank) development. Integration

Ministry of Public 128.0 (R) Highways Reconstruction II - Loan approved by the Executive Works and Ministry (Bank) Reconstruction of sections of Directors on Mey 31. of Transport and the longitudinal highway and Telecommunications other main roads, major maintenance, planning and studies.

·Ministry of 75.0 (R) Agricultural Services and Appraisal mission in end-June. Agriculture (Bank) Credit~ Line of credit-to finance on-farm investments and incremental working capital, technical assistance and agricultural information services.

Min:l.stry of Housing 75.0 (R) Low-Income Housing. Appraisal report being prepared. and Urbanism (Bank)

See page l for footnotes. - 71 ·-

Member Country, and.Borrower or Amount & Stage of Process­ ImplementiJ18 Probable ing and Action on ~ll Lender J:./ Procurement.!/ COLOMBIA

Ferrocarriles Up to Railways VIII~ Rehabilitation Project preparation dependent on Nacionsles de 140.0 and modernization of railways progress of Railways VII. Colombia (CNR) (Bank) and technical aasistance; pos­ sibly construction of improved alignments. ·

CARBONES DE COLOMBIA 9.5 (R) Coal Exploration - Geological Negotiations in progress. (CARBOCOL) (Bank) and other studies on several coal basins: and technical assistance to CARBOCOL. Total project coat estimated at $17.8 million of which $8.5 million in foreign exchange.

(BANCO DE LA To be (R) Agriculture Credit - Credit for Project· preparation underway. REPUBLICA (BOR)) deter­ farm development and large- and mined medium-scale agro-industriea; (Bank) possible pilot credit/technical assistance component for small scale agro-industries; agro­ industrial research.

(EMPRESAS PUBLICAS 29.0 (R) Barranquilla Water - Extension Pre-appraisal mission planned for MUNICIPALES DE (Bank) of water· supply and sewerage September. BARRANQUILLA) facilities; improvement'of solid waste operation and technical assistance. (EMPRESAS PUERTOS DE To be Ports - Modernization of exist­ Rehabilitation project being COLOMBIA deter- ing ports through rehabilita­ defined by Government. Awaiting (COLPUERTOS)) mined tion and upgrading of existing information from Ministry of · (Bank) facilities. Public Works and COLPUERTOS.

(EMPRESA COLOMBIANA 60.0 Phosphate Fertilizer - Con­ Feasibility study expected to be DE MINAS (Bank) struction of facilities for completed in Auguat. (ECONOMINAS)) processing of local phosphate rock, including phosphoric acid, sulfuric acid, TSP and DSP.

Interconexion Up to Power - Bydropower. Project preparation underway. Electrica s.A. (ISA) 300.0 .. (Bank)

(EMPRESAS PUBLICAS Up to (R) Rio Grande Multipurpose - Preparation mission in June. DE MEDELLIN (EPM)) 120.0 Electricity Generation and (Bank) Water Supply. ·

(CORPORACION 100.0 CVC Calima III, Distribution/ Project Preparation underway. AUTONOMA DEL VALLE (Bank) Transmission/Generation, sub­ DEL RIO CAUCA (CVC)) stations.

(CORPORACION 300.0 Urra Hydroelectric. Project preparation underway. ELECTRICA DE LA (Bank) COSTA ATLANTICA (CORELCA)) ·

(EMPRESAS PUBLICAS 20.0 (R) Cucuta Water - Development of Preparation mission scheduled for MUNICIPALES DE (Bank) new water sources and July. CUCUTA (EMC)) rehabilitation of water system. Conatruction of sewage system and open drain canals.

See page 1 for footnotes. - 72 -

Member Country, and 'Borrower or Amount & Stage of Process­ Implementit1g Probable ing and Action on ~ll Lender J:./ Procurement i/ COLOMBIA· (Cont'd)

(BANCO DE LA To be Small-Scale Industry IV - Appraisa.l mission postponed REPUBLICA) (BR) deter­ Lending program by Corporacion pending discussions with BR.and mined Financiers Popular (CFP). CFP on possible inclusion of CFP. (Bank) in on-going industr!al credit project.

Instituto Colombiano 63.4 (R) Agricultural Research - Board presentation on June 7. Agropecuario (ICA) (Bank) Research to improve competi­ tiveness of Colombian agricul­ ture and to increase output.

To be determined 30.0 Agricultural Marketing - Project preparation underway. (Bank) Improve efficiency of distribu­ tion of agricultural products from farmgate to the consumer. inatituto de Fomento 150.0 (R) Ammonia Urea Fertilizer - Con­ Feasibility study expected to be Industrial (IFI) (Bank) struction of fertilizer plant completed in July. and ancillary facilities.

To be determined 68.0 Agriculture Diversification - Second preparation mission (Bank) Investments to diversify agri­ scheduled for June. culture production from coffee zones, promote agro-industry and strengthen marketing systems.

Financiers Electrics .100.0 Power co-financing assistance. B-loan of $150 million Nacional (FEN) (Bank) Financing of electricity envisaged. Appraisal report investment projects through being prepared. sector financial entity (FEN).

(INSTITUTO To be Irrigation Rehabilitation II - Project preparation underway. COLOMBIANO DE deter­ Rehabilitation of ·irrigation HIDROLOGIA, mined and drainage districts. METEROLOGIA (Bank) Y ADECUACION DE TIERRAS (HIKAT)) COSTA RICA

Inatituto de Tierraa ·Up to Development of Coto Sur area. Further processing postponed y Colonizacion 26.5 Total project cost estimated at pending agreement with the (ITCO) . (Bank) $49 million of which $26.5 Government on the Bank's future million in foreign exchange. lending program.

Inatituto Up to Power VII - Hydroelectric power Further processing postponed Coatarricenae de 45.0 plant (Palomo or Sandillal), pending agreement with the Electricidad (ICE) (Bank) and transmission distribution Government on the Bank's future expansion program. lending program.

Government 25.2 (R) Credit to promote exports. Loan approved by the Executive (Bank) Directors on Kay 3, and signed on Kay 21. Government eo.o CR> Structural Adjustment. Lellding. Preparation underway. (Ballk) DOMINICAN REPUBLIC

Ministry of 12.0 (R) Education III - Support and Negotiations scheduled for.late Education (Bank) expansion of rural primary June. education facilities. Total project cost estimated at $20 million of which $9 million in foreign exchange.

Corporacion 20.0 (R) Thermal plant rehabilitation Appraisal mission tentatively Dominicans de (Bank) and transmission - Technical scheduled for July. Electricidad (CDE) assistance for reduction of distribution losses, studies and training.

See page l for footnotes. - 73 -

Member Country, and ·Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~)J Lender!/ Procurement.!/ DOMINICAN REPUBLIC (Cont'd)

Corporacion 36,0 (R) Coal Pier - Construction of Completion of appraisal mission Dominicana de (Bank) berth for unloading coal now confirmed for June based on Electricidad (CDE) vessels, and studies for medium engineering, economic and and long-term coal import needs environmental studies being and required facilities, reviewed,

AYUNTAMIENTO DE 7,1 (R) Santo Domingo Municipality: Approved by the Executive SANTO DOMINGO (Bank) Technical Assistance Project, Directors on May 26, Loan Municipal development for the signing qn June 10, city of Santo Domingo, Total project cost estimated at $17,5 million of which $9,2 million in foreign exchange,

Republic of Santo Up to (N) Highway Maintenance III - Project preparation underway, Domingo 35,0 Financing for.road (Bank) reconstruction/rehabilitation works,

Corporacion 3,5 (N) Power Engineering - Technical Project preparation underway, Dominicana de (Bank) assistance for detailed Electricidad (CDE) engineering for the proposed Haina Coal Port,

Corporacion Estatal Up to Petroleum I - Project Project preparation underway, Petrolera 50,0 components could include water Ecuatoriana '(CEPE) '(Bank) injection in oil fields,

Ministry of 30,0 Agricultural Credit II, Project preparation in progress, Agriculture and (Bank) Banco Nacional de Fomento

Instituto 70,0 Power Transmission II, Further processing depends on Ecuatoriano de (Bank) adoption by Government of Electrificacion satisfactory measures to improve (INECEL) sector finances,

Republic of Ecuador 8,0 (R) Education IV - Improvement of Further processing depends on · (Bank) rural primary education, firm indication from Government that it wishes to proceed with project,

Instituto 15,0 (R) Technical assistance to IEOS Preparation mission scheduled for Ecuatoriano (Bank) and BEDE; and works in some July, de Obras · secondary cities, Sanitarias (IEOS) and Banco de Desarrollo del Ecuad<>T (BEDE)·

Autoridad 15,0 Ports III - Improvement of port Mission has discussed arrange­ Portuaria (Bank) channel, ments for hydraulic study de Guayaquil necessary for project prepara­ tion,

EL SALVADOR

Banco Central Up to Export sector - Provision of El9ctions planned for December 40,0 long-term industrial credit for 1983 will delay negotiations to (Bank) export oriented enterprises, March 1984, to allow new Administration to become involved,

Comision Ejecutiva Up to (R) Power VIII - Electrification ·Project consideration postponed de Desarrollo 40,0 for agriculture and rural at Government's request, Further Hidroelectrico del (Bank) industry; rehabilitation of processing will depend on Rio Lempa (CEL) distribution for San Salvador; indication from Government that upgrading of Ahuachapan · it wishes to proceed, geothermal field; geothermal feasibility studies, Total project cost $68 million of which $47 million in foreign exchange.

See page l for footnotes,

,··.'"-',!;-•:.·· ! - 74 - I

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~ll ~?,../ Procurement i/ GUATEMALA

I Banco Nacional de ls To be Urban Development, Further preparation depends on I• Vivienda deter­ progress in developing sector I mined strategy policies, (Bank)

Empresa Guatemaltecs 30,0 Communications III - Further Awaiting completion of financial de Comunicsciones (Bank) expansion of telephone network plan, (GUATEL) including cable network, dis­ tribution and long distance Procurement: International facilities, Total project cost tenders, including credit offers estimated st $208,0 million of for the financing of part of the which $146,0 million in foreign equipment', were advertised in exchange. March,

Empress Electrics de 25,0 (R) Power V - Distribution Appraisal report being pre.pared, Guatemala (EEG) and (Bank) expansion program of EEGSA Instituto Nscionsl (Distribution company of Procurement: International de Electrificscion Guatemala City) and tenders are expected to be (INDE) pre-investment and training advertised by October, studies for 1NDE,

Ministry of 18,5 (R) Education III - Expansion and Negotiations completed, Board Education (Bank) improvement of primary presentation scheduled for June education in poor urban areas. 28,

Central Bank 35,0 (R) Industrial Credit - To finance Negotiations completed, Board (Bank) investments in small and presentation scheduled for July medium-scale enterprises, and 19, for establishment of export fund to finance imported inputs needed for export diversifica­ tion; technical assistance to public and private sectors,

Guyana Electricity 15,0 Power II - Rehabilitation of Appraisal report being prepared, Corporation (GEC) (Bank) generation and distribution plant, Management, technical, and training assistance,

Organisme de Up to (R) Integrated Rural Development of Negotiations in progress. Developpement du 19,l Northern Plain - Second stage. Nord (ODN) (IDA) Total project cost estimated st $29,2 million of which $14,7 million in foreign exchange,

Electricite d' 22,0 Power IV - Project description Project preparation underway, Haiti (EDH) (IDA) under review, In order to compensate for limited availability of the Peligre ·Hydro Plant due to s severe drought, an emergency thermal generating project is being considered.

HONDURAS

San Pedro Sula 15,0 (R) Water supply, sewerage and Appraisal mission in the field, Municipal Corp, (Bank) drainage - for San Pedro Sula (Co-financing of $19 million WATER DIVISION and technical assistance to being sought from Commonweal·~h (DIMA) DIMA, Total project cost Development Corporation and estimated ·St $44 million of Government of Norway,) which $31,3 million in foreign exchange,

See page l for footnotes. - 75 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~ll Lender J,l Procurement i/ HONDURAS (Cont'd)

Central Bank 45.0 (R) Agricultural Credit - Primarily Loan approved by the Executive (Bank) long and mediµm.-term Directors _on May 19. development credits to large and small farmers. Total project cost estimated.at $72.5 million of which $45 million in foreign exchange.

JAMAICA To be determined 15.0 (R) Urban Transport - Improvement Appraisal report being prepared. (Bank) in infrastructure, traffic management and rolling stock.

To be determined 15.1 (R) Industrial Credit - Long-term . Loan approved by the Executive (Bank) development credits to export Directors on May 26. industries, including small-scale industries. Ministry of f5.1 (R) Export Crops - Credit and Negotiations in June. Agriculture (Bank) technical support for expansion of export crop production.

Export Credit 30.1 (R) Third Export Development Fund Board presentation on June 16. Insurance· (Bank) Project - To provide foreign Corporation exchange and credit to Procurement: Retroactive. exporters of nontraditional financing of $200,000 for manufactured and agricultural technical assistance. products and to qualified domestic enterprises producing inputs for .the export producers. The project would support the trade liberalization and export incentive measures adopted by the Government as part of its structural adjustment program.

Ministry of 15.0 (R) Highway Maintenance - Asphaltic Loan approved by the Executive Construction (Bank) overlay and resurfacing of Directors on May 26. portion of main road network; maintenance equipment and technical assistance for institutional strengthening and training. Total project cost estimated at $47 million of which $23.5 million in foreign exchange.

Ministry of 60.2 (R) Second Structural Adjustment Board presentation on June 14. Finance (Bank) Loan - To finance imports of r·aw materials, intermediate '- goods, non-luxury consumer goods, capital equipment and spare parts.

~ Banco Pesquero y Up to Fisheries. Appraisal report being prepared. Portuario (BANPESCA) 50.0 Priority of project to be (Bank) reviewed with new Government.

Secretaria de Up to Pujal Coy - Irrigation and Project preparation underway. Agricultura y 100.0 agricultural 'development in the Priority of project to be Recursos Hidraulicoa (Bank) Panuco Basin. reviewed with new Government. (SARR)

NACIONAL 115.0 Agricultural Marketing - Loan approved by the Executive FINANCiERA (Bank) Improvement.of·infrastructure Directors on April 19. (NAFINSA) and services for storage, transport, and.sale of · perishable agricultural products.

Secretaria de Up to Rural development. Project identification awaiting Programacion y 200.0 impact evaluation of the PIDER Presupuesto (SPP) (Bank) projects.

See page 1 for footnotes. - 76 -

Member Country, and· Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~ll Lender J:l Procurement ii

~ (Cont'd).

Banco National de 100.3 (R) Water Supply and Sewerage - Loan approved by the Executive Obras y Servicios (Bank) Construction of water supply Directors on May 17, Publicos (BANOBRAS) and sewerage system in a number of medium size cities, and Procurement: International provision of technical tenders are expected to be assistance to the beneficiary advertised in late 1983, water companies and to the Sinaloa State Water Company.

Banco Nacional 350,0 (R) Export Sector - Support to Board presentation on June 23, de Comercio (Bank) export-oriented industries, Exterior including assistance to them to import raw materials and components.

Banco Pesquero y Up to Industrial Ports - Civil works, Project preparation being carried Portuario (BANPESCA) 100,0 equipment and technical out under port development (Bank) assistance for new industrial preparation project financed by ports, the Bank,

Banco Nacional de 25,0 (R) Water Pollution Control - Pilot Mission currently in the field. Obras y Servicios (Bank) program aimed at abating and Will discuss with Government Publicos (BANOBRAS) controlling of water pollution tentative timetable and priority in the Middle Lerma River ass:1.gnment. basin, Total cost estimated at about $60 million of which $25 million in foreign exchange,

Nacional Financiers 175,0 (R) Medium and Small Industry - Negotiations completed, Board (NAFINSA) (Bank) Credit for small and medium presentation on June 23. industrial development,

Nacional Financiers Up to Agricultural Credit - Priority Project preparation underway, (NAFINSA) 400,0 long and medium-term (Bank) development credits to farmers, Two agencies likely to be included - FIRA and FICART,

To be determined Up to Chiapas Highway - Rural roads Project preparation underway, 70,0 construction, improvement and (Bank) maintenance to support an integrated regional development program for the State of Chiapas,

Secretaria de Up to Highway Sector - Continuation Project preparation underway, Comunicaciones 100,0 of modernization initiated y Tranapo~tes (SCT) (Bank) under the first sector loan (1671-ME).

NICARAGUA

Instituto 30,0 Expansion of Managua's water Further processing depends on Nicaraguense de Agua (Bank) supply system, agreement being reached with y Alcantarillados Government on a Bank lending (INAA) program,

Fondo Especial de Up to Line of credit for agricul­ Further processing depends on Desarrollo (FED) 15,0 ture - Total project cost agreement being reached with (Bank) estimated at $30,0 million of Government on a Bank lending which about $8,0 million in pr'ogram; foreign exchange,

Instituto Up to Electric Power - Engineering Further processing depends on Nicaraguense de 10,0 studies for hydroelectric and agreement being reached with Energia (INE) (Bank) geothermal projects; study of Government on a Bank lending Managua distribution network; program, financing of training and technical assistance leading to institutional improvements,

See page 1 for footnotes, - 77 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~ll Lender ]:.I Procurement ii PANAMA

Banco Nacional de ll.O (R) Livestock III - Livestock Appraisal report being reviewed, Panama (BNP) (Bank) Development. For meat and milk production through provision of credit. Total project cost estimated at $25.5 million of which $6,9 million in foreign exchange.

Instituto de Up to (R) Power VI - Distribution Negotiations completed, Board Recurses Hidraulicos 32.1 project, To provide power to presentation on June 9. y Electrificacion (Bank) industry and greater number of (IRHE) households, technical assistance for institution building, improving distribution and reducing system losses. Total project cost estimated at $59,4 'million of which $32,0 million in foreign exchange,

Government 60.0 (N) Structural Adjustment Lending. Appraisal mission in the field. (Bank)

PARAGUAY

Ministry of 40.0 Agricultural development Alto Preparation by Government Agriculture (Bank) Parana - Agricultural exten­ underway. Selection of sion, credit, research, health consultants financed under facilities, and rural roads in pre-investment fund for basic Southeastern Paraguay, studies still in process,

Fondo Ganadero 25.0 (R) Livestock VII - Credit and Appraisal report being prepared, (Bank) technical assistance to large, medium and small-sized specialized livestock producers.

Ministry of 14.0 Education V - Basic education Government has requested Education (Bank) for development and frontier postponement of project zones, including improvements processing, in the management of the education system.

Banco Nacional de 40,0 (R) Agricultural Credit - Board presentation on June 7, Fomento (BNF) (Bank) Investments and incremental operation credit for medium and small farmers,

Ministry of 6.2 (R) Vocational Education II - Appraisal report being prepared, Education (Bank) Expansion of basic skills; training services for rural population,

Banco Agrario del 130,0 (R) Agricultural Credit VI - Board presentation on June 7, Peru (Bank) Medium- and long-term credit for agricultural development.

. Ministry of 24,0 (R) Education II - Primary Post-appraisal mission in June. Education (Bank) education in urban areas.

See page 1 for footnotes, - 78 -

Member Country, and Borrower or Amount & Stage of Process­ Implementing Probable ing and Action on ~11· Lender:!,./ Procurement.!!/ PERU (Cont'd)

To be determined Up to Mining II - Unidentified. Project identification so.o discussions underway. (Bank)

Ministry of Housing Up to Urban Development II - Project preparation suspended and Banco de la 30.0 Construction of sites and pending receipt of Government Vivienda (BANVIP) (Bank) services, upgrading, housing proposal on sector mortgage settlement, and supervised interest rates. credit.

YUNCAN S.A. 140.0 Power VII - 126 MW Yuncan Appraisal report being prepared. (Bank) hydroelectric plant. (Co-financing being sought.)

Servicio Nacional de 50.0 (R) Water supply and sewerage in Preparation underway. Abaetecimiento de (Bank) several secondary-sized cities Agua Potable y and towns. Provision of Alcantarillado technical assistance for (SENAPA) institution building.

Ministry of Up to Irrigation Rehabilitation III - Project preparation underway. Agriculture so.o Rehabilitation of drainage and Bank Project Preparation Facility (Bank) irrigation systems in up to advance of $500,000 approved to eight coastal valleys. finance aerial mapping for a pre-feasibility study.

To be determined To be Sugar Rehabilitation - Bank Project Preparation Facility deter- Rehabilitation and improvement advance of $500,000 to finance mined of management for sugar feasibility study. (Bank) cooperatives.

Central Government 60.0. (R) Metropolitan Development - Appraisal report being prepared. (Bank) Improvement of Lima's urban Second Bank Project Preparation transport system; markets, and Facility advance of $500,000 made solid waste management, and for feasibility and engineering related institutional studies.for project design. development,

To be determined Up to Structural Adjustment Loan - To Preparation underway, 200.0 finance priority imports in (Bank) conjunction with a program of economic adjustment.

Prime Minister's 40.0 (R) Selva Central Rural Development Appraisal·mission in the field. Office (Bank) - Agricultural credit, feeder roads, land titling, extension services, social infrastruc­ ture.

Administracion ss.o Power VI (Thermal) - Construc­ Further processing dependent on Nacional·de Ueinae y (Bank) tion of a combined cycle Government policy decision. Tranemisiones thermal plant, step-up substa­ (Suppliers' credits probable.) Electricae (UTE) tion and transmission line, Procurement: Retroactive financing amounting to $700,000 for consultant services to be recommended.

To be determined 5.0 (R) Public and Business Administra­ Project postponed indefinitely. (Bank) tion - Provision of facilities Reporting to be discontinued. and technical assistance for training public and private managers.

See page 1 for footnotes.· - 79 -

VII, NEW PROJECTS

ADDED IN THIS ISSUE

Amount & Member Probable Country Lender Project Stage of Processing

EASTERN AFRICA

To be Petroleum Technical Assistance - Project preparation under deter­ To be defined, way. mined (IDA)

To be A~riculture Rehabilitation Project identification under. deter­ Credit III - Support to the way, ' mined irrigation sub-sector. (IDA)

REGIONAL About Power Distribution - Network Project preparation under way. 25.0 rehabilitation and expansion for Advances from IDA Project Prepara­ (IDA) Great Lakes.Region, Total project tion Facility for cost and engin­ cost to be determined, eering studies were approved as follows: Burundi $400,000; Rwanda $440,000; and Zaire $440,000.

WESTERN AFRICA

EQUATORIAL 6.0 Technical Assistance - Resident Preparation/appraisal mission GUINEA (IDA) experts, probably including project in the field. coordinator, legal, forestry, agri­ cultural, external debt, and mining experts; short-term consultants for studies and project preparation; houses, vehicles, and operating ex­ penditures to support work of experts; training of national staff. Total cost estimated at $7.0 million, of which $5.6 million in foreign exchange.

MAURITANIA 10.0 Livestock Development - Establishment Project being prepared, Appraisal (IDA) of pastoral associations, strengthen­ mission tentatively scheduled for ing of livestock services, vaccination, September. IDA Project Prepara­ distribution of drugs, abatoir in tion Facility advance of $250,000 Nouakchott, applied research. Total approved for preparation of cost about $18.0 million, of which project. $11.0 million in foreign exchange.

150.0 Escravos Beach-Lagos Gas Pipeline Project preparation under way. (Bank) (ELP) Project - Transmission pipeline (Co-financing of $50 million with and gas gathering system from EIB,) the Western Niger Delta area in Lagos, Total project cost estimated at $840 million, of which $620 mil­ lion in foreign exchange.

3.0 Engineering Credit for Urban Appraisal mission scheduled (IDA) Management - Technical assistance/ for July. equipment to define strategy for management of urban growth which stimulates and supports productive investments; support for institu-. tional policy/financial reforms,

EAST ASIA AND PACIFIC

INDONESIA 40.0 Community Health and Training - Project identification under (Bank) Expanded program of community way. health care i.ncluding immunization, improvement of nursing and technical training. - 80 -

Amount & Member Probable Country Lender Project Stage of Processing

EAST ASIA AND PACIFIC (cont'd)

INDONESIA 200.0 Small Enterprise Developme~t III - Project Identification under (Bank) To support the Government with Small way. Investment Credit (KIK)/Small Perma­ nent Working Capital Credit (KMKP) pro_grams.

150.0 Second University - Development Project preparation under way, (Bank) Centers - graduate and postgraduate to upgrade university staff in key fields, including natural science and agriculture, engineering, and economics.

PHILIPPINES 50.0 National Forestry - Support for Project being prepared by (Bank)· the development of industrial tree Government and FAO/CP, plantations and strengthening of the Bureau o1 Forest Development's field capacity and services.

50.0 Secondary Cities Development - Project being prepared by (Bank) Expansion of basic municipal services Government, with emphasis on environmental sani­ tation, and strengthening of imple­ mentation capacity of local govern­ ments, Total project cost estimated at $100 million,

75,0 Rural Roads II - Further support for Project being prepared by (Bank) the Government's program of rural Government, road construction rehabilitation and maintenance.

SOLOMON ISLANDS 3,0 Agricultural Extension and ~ural Project being appraised by (IDA) Development, ADB for co-financing with IDA.

SOUTH ASIA

15,0 Paddy III - Follow-up to two ongoing Project preparation under way. paddy development projects to increase paddy production through the construc­ tion of flood protection and drainage facilities designed to (i) exclude tidal and river flow surges; (ii) improve and extend natural internal drainage; and (iii) reclaim land that is currently deeply flooded or ·saline,

21.0 Grain Storage II - Follow-up of the Feasibility report is currently (IDA) first grain storage project to re­ being reviewed by the Govern­ habilitate existing storage and ment and IDA, milling facilities; transportation; technical assistance and staff training.

42.0 Periyar Vaigai II - Continuation of Project preparation under way, (IDA) canal lining program begun under first project, and operation of completed system to improved stan­ dards. - 81 -

Amount & Member Probable Country Lender Project Stage of Processing

SOUTH ASIA (cont'd)

5.0 Primary Education - To strengthen Project preparation under way. (IDA) the various institutions relating to primary education, and thereby assist with greater decentraliza­ tion and program support as well as increasin'g administrative efficiency; teaching materials and staff training; technical assistance.

5.0 Industriai Development - To provide Project preparation under way. (IDA) long term funds.through the Nepal Industrial Development Corporation (NIDC) to industrial enterprises in the private sector and assist in the overall institutional development of NIDC; assist in the development.of leather and leather goods, and provide assistance in developing the light engineering sector; address key prob­ lem areas in industrial and export policies, procedures and administra­ tion through technical assistance.

SRI LANKA Up to Second Rubber Rehabilitation - Replant­ Project preparation under way. . 30.0 ing of over~aged low-yielding small­ (IDA) holder rubber and improvement in rubber processing standards.

EUROPE, MIDDLE EAST AND NORTH AFR)CA

EGYPT, ARAB To be New Land Development II - Project being prepared by the llEPUBLIC OF deter­ Phase II of the New Land Develop­ Government and consultants. mined ment Project (West Nubariya), (Bank)

To be Agricultural Extension and Research - Project being prepared by deter­ To assist Government in developing Government/Bank and USAID, mined national agricultural exten~ion and (Bank) research.

To be Agricultural Credit for Mechaniza­ Project being prepared by the deter­ tion - Line of credit for farm Principal Bank for Development mined mechanization in several governor­ and Agricultural Credit (PBDAC) (Bank) ates. in conjunction with Bank.

To be Lake Manzala Development - Reclamation Project being prepared by deter­ and low cost settlement of about Ministry of Land Reclamation and mined 60,000 feddans of uncultivated FAO/CP, (Bank) land,

To be DFC - Small- and medium-industry Project being prepared by deter­ development. Credit channelled Government. mined through development finance com­ (Bank) panies.

To be Transport including railway, roads Preparation under way by deter­ and port improvements. Government. mined (Bank)

PORTUGAL To be Municipal Water Supply and Sewerage - Preparation under way. deter­ Provision of water supply and sewerage mined facilities to municipalities, under (Bank) overall sector program.

To be Rehabilitation and expansion of Preparation under way by SOGITEX deter­ textile mill; phase II of ongoing and consultants. mined project. (Bank) - 82 -

Amount & Member Probable Country Lender Project Stage of Processing

EUROPE, MIDDLE EAST AND NORTH AFRICA (cont'd)

To be Energy Saving - Energy Saving invest­ Studies/energy audits under deter­ ments in selected industries in public way, mined and private sectors, (Bank)

To be Port Expansion - Expansion of port Identification/preparation deter­ capacity, modernization of existing mission scheduled end-Juqe. mined facilities, training and studies. (!lank)

YEMEN ARAB To be Industrial Bank of Yemen (IBY) II - Preparation under way, REPUBLIC deter­ Credit line to IBY to finance in­ mined vestment requirements and provide (IDA) further institutional support to IBY.

To be Minerals Exploration - Minerals Preparation under way, deter­ exploration, including feasibility mined studies, financing of equipment, (IDA) and technical assistance.

YUGOSLAVIA About Fertilizer Sector - Financing Appraisal completed, Negotia-. 80.0 inputs, raw materials, technical and tions tentatively scheduled (Bank) energy audits for. Yugoslav fertilizer for early September. industry, including incremental fertilizer requirements for 1984-85.

LATIN AMERICA AND CARIBBEAN

DOMINICAN Up to Highway Maintenance III~ Financing Project preparation under way. REPUBLIC 35,0 for road reconstruction/rehabilita­ (Bank) tion works,

3.5 Power Engineering - Technical assis­ Project preparation under way, (Bank) tance for detailed engineering for the proposed Haina Coal Port.

60.0 Structural Adjustment Lending. Appraisal mission in the (Bank) ,field.