1

Welcome William R. Clement Parkway Extension Functional & Preliminary Design Study PUBLIC INFORMATION DISPLAY SESSION

March 19, 2015 Public Information Display Session Format 1

Please use the sticky notes provided to post comments directly on the presentation boards.

Project staff are happy to answer your questions.

Please complete a comment sheet and submit it prior to leaving Purpose of the Study 2

The William R. Clement Parkway (WRCP) is:

» An important component of the City’s Strategic Road Network to accommodate the travel demand in west .

» Intended to provide an important north-south link in west Winnipeg.

» This project is an Engineering study, funding for construction is currently not in place.

Place Comments Here Recommended Extension 3

PORTAG R out E Route 62 85 ACADEMY

Route 95 OSBORNE The City of Winnipeg Transportation Master Plan Route 95 CORYDON Route Route CORYDON70 Route 96 Route 42 ROBLIN 90 241 Route GRANT Route GRANT Route 105 105 125 (TMP) Recommends WRCP Extension TAYLOR

KENASTON 100

M A N I TO B A Route WILKES 145 Route 80 MCGILLIVRAY » “The purpose of the TMP is to present a 427 Route IN 90 Route PEMBINA 155 BISHOP GRAND

WAVERLEY long-term strategy to guide the planning, Route 165 WRCP

WILLIAM R. CLEMENT PARKWAY

CHANCELLOR development, renewal and maintenance of a 3 MATHESON Route Extension 42 Route 100 80

multi-modal transportation system in a manner 100 that is consistent with project needs, and

ST. MARY

100

M 2 A N IT OB A 200

aligned with the City’s growth and the overall 3 PEMBIN

A

7 8

PERIMETER HIGHWAY 6 101 9 vision for a sustainable Winnipeg and region.” 101 204 Rou te 180

Route CHIEF PEGUIS TRAIL 90 59 PTH 6 EXTENSION

Rout 42 e Ro

ute Route BROOKSIDE BROOKSIDE 23 LEILA 17

Route INKSTER 25 INKSTER

FUTURE PR221 MCPHILLIPS 101 Route

OAK POINT 52 KEEWATIN Y KEEWATIN A

W

101 A WAY

D

A

N

A

C ARLINGTON

T Route SALTER Route Route MCGREGOR

R 47 SELKIRK HENDERSON HWY

O 20 90 MAIN Rou RALEIGH/GATECONCORDIA P te E 62 R T N CE

STURGEON LOGAN

Route PARKWAY » PARKWAY 57 NOTRE DAME

ST. JAMES ST. NAIRN

EDWARD SCHREYER SCHREYER EDWARD EDWARD SCHREYER SCHREYER EDWARD

Route The WRCP Extension Study is identified as part Route SASKATCHEWAN James Armstrong REGENT 37 37 425 Route PANDORA

Richardson Int’l KING EDWARD LAGIMODIERE ELLICE 57 PERIMETER HIGHWAY Airport Route 15 SILVER 115 DUGALD Route ARCHIBALD NESS 85 Route MARION A B M AN ITO 115 MORAY PORTAGE M A NI T O B A PORTAGE e Rout 101

Route 62 PLESSIS 85 PLESSIS ACADEMY

Route OSBORNE 95 ute Route Ro ute 20 95 CORYDON Ro Route Route CORYDON70 Route 96 Route 42 30 ROBLIN

M Route 90 A A 241 Route GRANT Route N I TO B GRANT Route FERMOR 135 105 MA 125 A 105 N I TO B ST. ANNE’S TAYLOR Route

M

52 A N ITO B A

PERIMETER HIGHWAY HIGHWAY PERIMETER PERIMETER

ST.ST.MARY MARY

KENASTON Route 100

M of the TMP’s future Strategic Road Network. A N I TO B A Route 165 WILKES 145 Route 80 MCGILLIVRAY 427 LAGIMODIERE

M Route DAKOTA Route A N IT O B A

90 MBINA 20 Route PE 100

M 155 A N I T O B A BISHOP GRANDIN BOULEVARD

WAVERLEY e ut Route Ro 0 165 15 Place Comments Here WARDE R

Route

WILLIAM R. CLEMENT PARKWAY

CHANCELLO 52 3 MATHESON Route 42 Route PERIMETER HIGHWAY 100 80

100

59

ST. MARY

100

M » 2 A N IT OB A 200

On April 25, 2012 Winnipeg City Council 3 PEMBINA

75 approved an amendment to the TMP to change City of Winnipeg Transportation Master Plan the WRCP Extension between Grant Ave. and Road Implementation Network Map Wilkes Ave. from a medium-term project to a short-term project. Project Study Area 4

William R. Roblin Blvd. Clement Pkwy Grant Ave.

Assiniboine Forest

Oakdale Dr. Shaftesbury Blvd.

Buckingham Rd.

Elmhurst Rd.

Charleswood Rd. Ridgewood Ave. Sterling Lyon Pkwy Wilkes Ave.

CN Line

Study Area

Loudoun Rd.

Place Comments Here

Wyper Rd.

City of Winnipeg /

R.M. of Macdonald McGillivray Blvd. Boundary Project Scope 5

» Conduct a high-level functional design from Grant Ave. to McGillivray Blvd.

» Conduct a more detailed preliminary design from Grant Ave. to Wilkes Ave.

» Incorporate grade separation of WRCP Extension at the CN Main Line (North of Existing Wilkes Ave.).

» Develop alternatives for the WRCP Extension connection to Wilkes Ave.

» Twinning of Wilkes Ave. and develop realignment alternatives.

» Develop alternatives for the Harte Trail crossing of the WRCP Extension.

» Obtain Environmental Act Licencing for the WRCP Extension from Grant Ave. to Wilkes Ave. Place Comments Here » Undertake conceptual Environmental Assessment Study for the long-term Extension of the WRCP from Wilkes Ave. to McGillivray Blvd. WRCP Extension Phases 6

Phase I The WRCP Extension Includes two Phases: William R. Roblin Blvd. Clement Pkwy Grant Ave. » Phase I – Short-term Assiniboine Forest » Extension from Grant Ave. to

Oakdale Dr. Shaftesbury Blvd.

Buckingham Rd.

Elmhurst Rd.

Charleswood Rd. Ridgewood Ave. Sterling Lyon Pkwy Wilkes Ave. Wilkes Ave. CN Line » Phase II – Long-term* » Future extension of WRCP from

Study Phase II* Wilkes Ave. to McGillivray Blvd. Area

Loudoun Rd.

Place Comments Here

Wyper Rd.

City of Winnipeg /

R.M. of Macdonald McGillivray Blvd. Boundary

* As per the City of Winnipeg’s Transportation Master Plan Project Timeline 7

Winter 2015 Spring 2015 Summer 2015 Fall 2015 Winter 2016 Spring 2016

› Study › Develop & › Selection of › Initiate › Public Open › Study Commencement Evaluate a Preferred Preliminary House #2 Completion Alternatives Alternative Design Study › Initiate › Finalize the (Grant Ave. to Environmental › Public Open › Functional Preferred Wilkes Ave.) Reviews House #1 Design Alternative (Grant Ave. › Completion of (Grant Ave. to › Stakeholder to McGillivray Environmental Wilkes Ave.) & Meetings Blvd.) Reviews Prepare Final › Public Information Report Display Session (March 19, CMU)

We Are Place Comments Here Here City of Winnipeg Cycling Map 8

» Proposed Cycling Facilities from Pedestrian and Cycling Strategies Map (subject to Council approval)

Place Comments Here

Note: this document will supersede the pedestrian and cycling plan in the TMP, once approved by Council. Our Winnipeg - Urban Structure 9

RM OF » The WRCP Extension will pass WEST ST PAUL D RM OF B ROSSER-OLD KILD O N AN EAST ST PAUL

A AM BER TRAILS G URBAN STRUCTURE F

E RIVERBEND W EST KILD O N AN INDUSTRIAL through Recent Communities RM OF LEILA NORTH T C MANDALAY W EST RIVERGROVE A L AL ROSSER TEM PLETO N-SINCLAIR H VAL INKSTER GARDENS NORTH INKSTER INDUSTRIAL THE M APLES LEILA-McPHILLIPS TRIANGLE RIVER EAST

M ARGARET PARK

KILD O N AN PARK LEGEND

GARDEN CITY

SPRINGFIELD NORTH

INKSTER INDUSTRIAL PARK and New Communities known as H

TYNDALL PARK JEFFERSO N ROSSM ERE-A KIL-CONA PARK KILD O N AN DRIVE MYNARSKI

SEVEN OAKS

ROBERTSON McLEOD INDUSTRIAL BURROW S-KEEW ATIN OAK POINT HIGHW AY Downtown SPRINGFIELD SOUTH NORTH TRANSCONA YARDS

SHAUGHNESSY PARK INKSTER-FARADAY ROSSM ERE-B

BURROW S CENTRAL ST. JO H N 'S LU XTO N

OMAND'S CREEK INDUSTRIAL W ESTON SHOPS MUNROE W EST VALLEY GARDENS GRASSIE ST. JOHN'S PARK Precincts (Q, N and/or M). BROOKLANDS EAGLEMERE

WILLIAM WHYTE DUFFERIN Major Redevelopment Sites W ESTON GRIFFIN GLENELM I TRANSCONA NORTH SASKATCHEW AN NORTH DUFFERIN INDUSTRIAL CHALMERS MUNROE EAST MEADOWS

PACIFIC INDUSTRIAL LO R D SELKIRK PARK LO G AN -C.P.R. G N I S S TALBO T-GREY O R C N A PEGUIS N O D L I RADISSON W EST ALEXANDER K KILD AR E-REDONDA CENTENNIAL EAST ELMW OOD

ST. JAM ES INDUSTRIAL SOUTH POINT DOUGLAS AIRPORT CHINA TO W N CANTERBURY PARK CIV New Communities IC SARGENT PARK CE TYNE-TEES KERN PARK NT VICTORIA WEST RE

DANIEL McINTYRE NORTH ST. BONIFACE REGENT MELROSE SPENCE PORTAGE & MAIN TISSOT MURRAY INDUSTRIAL PARK » E LLIC E-E TAG POR MISSION GARDENS TRANSCONA YARDS HERITAG E PARK Precincts require a “Precinct Plan” MISSION INDUSTRIAL COLONY SOUTH PORTAGE THE FO RKS DUGALD

CRESTVIEW ST. M ATTHEW S

MINTO Regional Mixed Use Centre CENTRAL ST. BONIFACE BUCHANAN R JA M E S W O O D BROADW AY-ASSINIBOINE HOLDEN KENSINGTON LEG ISLATURE DUFRESNE W EST BROADW AY KING EDW ARD STURGEON CREEK BOOTH POLO PARK ASSINIBOIA DOW NS DEER LO D G E W OLSELEY RIVER-OSBORNE TRANSCONA SOUTH

ROSLYN SILVER HEIGHTS STOCK YARDS ST. BONIFACE INDUSTRIAL PARK W EST W OLSELEY NORW OOD EAST A RM ST RO NG PO IN BRUCE PARK W ELLINGTON CRESCENT T NORW OOD WEST ARCHW OOD Regional Mixed Used Corridor GLENDALE McMILLAN MAGINOT

W OODHAVEN BIRCHW OOD to ensure organized development W ESTW OOD OLD TUXEDO CRESCENTW OOD SIR JOHN FRANKLIN KIRKFIELD VIALOUX NORTH RIVER HEIGHTS EARL GREY

EDGELAND SYM INGTON YARDS GLENW OOD RIVER W EST PARK RIVERVIEW RIDGEDALE WINDSOR PARK

NIAKW A PARK VARSITY VIEW ROCKW OOD MARLTON TUXEDO EBBY-WENTWORTH SOUTHBOINE LO R D ROBERTS J. B. MITCHELL CENTRAL RIVER HEIGHTS ASSINIBOINE PARK VARENNES Mature Communities

GRANT PARK ELM PARK ALPINE PLACE

W ESTDALE MATHERS KINGSTON CRESCENT THE MINT SOUTH RIVER HEIGHTS and transportation planning. BETSW ORTH SOUTH TUXEDO ROBLIN PARK ERIC COY ELMHURST NIAKW A PLACE SOUTHLAND PARK PARKER ST. GEORGE SOUTHDALE

WILDW OOD J POINT ROAD BROCKVILLE

BEAUM ONT LAVALEE RM OF RM NORBERRY Recent Communities RIDGEWOOD SOUTH Q VICTORIA CRESCENT WORTHINGTON BUFFALO HEADINGLEY CRESCENT PARK RM OF M AYBANK » LINDEN WOODS SPRINGFIELD New Communities are large land areas identified P MEADOW OOD SAGE CREEK TUXEDO INDUSTRIAL PULBERRY ISLAND LAKES ST. VITAL CENTRE Rural and Agricultural ROYALW OOD

M CHEVRIER WILKES SOUTH VISTA PEM BINA STRIP

LINDEN RIDGE O MINNETONKA W EST PERIMETER SOUTH N K for future urban development. These areas are not

AGASSIZ

DAKOTA CROSSING W EST FO RT GARRY INDUSTRIAL

MONTCALM Airport Area

W HYTE RIDGE W AVERLEY HEIGHTS RIVER PARK SOUTH currently served by a full range of municipal services. UNIVERSITY

NORMAND PARK BRIDGW ATER FOREST

BRIDGW ATER LAKES FAIRFIELD PARK Precincts Many of these lands were previously designated as B R I D G W A W AVERLEY W EST B T E R FO RT RICHMOND C E N T R M APLE GROVE PARK E RM OF

BRIDGW ATER TRAILS Rural Policy Area in Plan Winnipeg 2020. MACDONALD RICHMOND WEST

ST. VITAL PERIMETER SOUTH

SOUTH POINTE CLOUTIER DRIVE

W AVERLEY W EST D

RICHMOND LAKES

ST. NORBERT PARC LA SALLE » Recent Communities are areas of the city that were L planned between the 1950s and the late 1990s. They

TURNBULL DRIVE TRAPPISTES RM OF PERRAULT RITCHOT LA BARRIERE are primarily low and medium density residential PLANNING, PROPERTY & DEVELOPMENT DEPARTMENT with some retail. The road network is a blend of

012345 Kilometers November 2013 modified grid and curvilinear, often without sidewalks City of Winnipeg Complete Communities Directions Strategy or back lanes. These are typically stable residential communities with limited redevelopment potential over the next 30 years. Ridgewood South Precinct Q Plan 10

» Precinct Q Plan approved as a Transportation PolicyRoblin Boulevard Map by-law, now called Ridgewood, Betsworth Avenue Betsworth Avenue

Oakdale Drive Oakdale Eldridge Avenue

will be a new residential Road Dieppe Eldridge Avenue

Civic Street Civic

Harstone Road Harstone

Perimeter Highway Perimeter Municipal Road Municipal 11

Rannock Avenue 88.3ac(gross) Charleswood Road Charleswood Rannock Avenue 10 William R Clement Parkway

neighbourhood. Street Haney 33.9ac(gross)

PROPOSED Road Elmhurst Pepperloaf Cr Pepperloaf

9 PEDESTRIAN Laxdal Road Laxdal 8 OVERPASS

28.4ac(gross) 64.4ac(gross)

Fairmont Road Fairmont Coventry Road Coventry

Buckingham Road Buckingham Ridgewood Avenue North Collector (East)

Collector West Transportation Corridor 3 North 24.4ac » 136.0ac(gross) 7 6 66.4ac(gross) Development is commencing 4 Wilkes Avenue (Two Mile Road)

133.2ac(gross) 34.3ac Fairmont Road Fairmont

Perimeter Highway Perimeter 2

1 Road Harstone 5 Community Row Community 189.0ac(gross) 32.8ac(gross) Road Municipal 116.2ac(gross)

Charleswood Road Charleswood INTERSECTION Collector IMPROVEMENTS South Wilkes Avenue SUBJECT TO in Ridgewood and there will DETAILED TRAFFIC

Collector ANALYSIS Liberty Street Liberty South Road Loudoun

CNR Rivers Mainline INTERSECTION Recreational Pathways IMPROVEMENTS Wilkes Avenue Drive Oakdale be associated intersection SUBJECT TO Expressway and Connectors DETAILED TRAFFIC ( Future) INTERSECTION ANALYSIS IMPROVEMENTS Collector SUBJECT TO DETAILED TRAFFIC

ANALYSIS Local Access Roads

Community Row Community Charleston Road Charleston improvements at Wilkes Ave. Road Charleswood Cycling Facilities Pedestrian Facilities PM

Road Closing 4:28:47

Howe AvenueRoundabout 100 and Charleswood Rd. this year. 10/27/2010 Ridgewood South Precinct Plan » Transportation plans in this by- law depict the WRCP Extension Place Comments Here as the main access in and out of the neighbourhood. » Grade separation is planned for the WRCP and Harte Trail. ’s Capital Region TMP 11

Legend 010205 KM ± » The long-term WRCP Extension (Phase II) will be Future Interchange RM of ARMSTRONG Proposed New Routes RM of GIMLI LAKE of Proposed Additional Lanes WELL WINNIPEG UV11 partially outside of the City’s boundary and will UV59 UV17 Grand Beach

Grand TOWN of require coordination with the Rural Municipality WINNIPEG Marais BEACH

VILLAGE of DUNNOTTAR of Macdonald and Manitoba Infrastructure and RM of ST. LAURENT TOWN of TEULON UV12 Transportation (MIT). UV6 RM of ST. CLEMENTS RM of 8 9 ROCKWOOD UV UV RM of ST. 7 Clandeboye UV ANDREWS

RM of » RM of BROKENHEAD The TMP calls for highway network WOODLANDS Winnipeg - Selkirk CITY of SELKIRK UV4 Corridor East TOWN of STONEWALL Selkirk UV67 Stony improvements adjacent to the study area that Mountain UV44 TOWN of BEAUSEJOUR RM of ST. FRANÇOIS UV27 Birds Hill XAVIER RM of RM of WEST Provincial Headingley Bypass ROSSER will have to be considered. These include: ST. PAUL RM of EAST Park St. Rosser ST. PAUL Eustache Oakbank Corridor St. 101 UV26 UV Oakbank François RM of » Xavier SPRINGFIELD Future interchanges on PTH 101 (Perimeter Highway). Anola Dugald 15 1 UV ³² CITY of WINNIPEG RM of RM of CARTIER HEA DIN GLEY » Future twinning of McGillivray Blvd. UV100 RM of TA CH E Lorette Ile des UV2 1 Chênes ³² Sanford TOWN of Place Comments Here RM of RM of STE. ANNE MACDONALD UV3 St. Norbert St. RITCHOT Adolphe UV59 RM of STE. Bypass TOWN of ANNE Ste. NIVERVILLE UV206 Agathe

UV52 CITY of UV75 STEINBACH

RM of HA NOV ER

VILLAGE of ST-PIERRE-JOLYS RM of LA RM of 12 RM of DE UV BROQUERIE MOR RIS SALABERRY

RM of 23 TOWN of UV MOR RIS ROLAND Figure 5.2: Future Highway Improvements Manitoba’s Capital Region Transportation Master Plan Study Area Considerations 12

Limited Right-of-way Property Ownership

Temporary Harte Trail Dog Park Crossing Burr Oak Stand Burr Oak Future Grade Forest/ Separation Roblin Blvd. Wildlife William R. Clement Pkwy Grant Ave.

ASSINIBOINE Varsity View FOREST

Oakdale Dr. Shaftesbury Blvd. High Pressure

Buckingham Rd. Sportsplex Ridgewood Ave. Elmhurst Rd. Charleswood Rd. Sterling Lyon Pkwy Gas Line Wilkes Ave. Hydro CN Line High Voltage Substation FORT WHYTE Hydro Towers CN Main Line Grade Separation Future Road Feedermain CITY OF WINNIPEG R.M. OF HEADINGLEY Connections to WRCP Wilkes Ave. Alignment Place Comments Here Options R.M. OF MACDONALD Study Area

Perimeter Hwy.

Future Extension of Bishop Grandin Blvd. R.M. of Macdonald McGillivray Blvd. Land Use/Services Future

Interchanges Perimeter Hwy. Grant Ave. to Wilkes Ave. - Existing Conditions 13

Temporary Dog Park (Unofficially Known as Charleswood Dog Park) Commercial Development William R. William Pkwy Clement

Charleswood School/ Grant Ave. Curling Club/Eric Coy Arena

ELMHURST ERIC COY NEIGHBOURHOOD NEIGHBOURHOOD Coy Ave. Community Community Access Access Eldridge Ave.

Charleswood Mennonite Church

Fairmont Rd. Fairmont Residential & City Haney St. Owned Property

McDowell Dr. Burr Oak Tree Stands Place Comments Here

Ridgewood Ave.

Wilkes Ave. CN Rail Line Study Harte Trail Varsity View Area Sportsplex/ Marj Edey Park Next Steps 14

Spring 2015 Summer 2015 Fall 2015 Winter 2016 Spring 2016

› Develop & › Selection of › Initiate › Public Open › Study Evaluate a Preferred Preliminary House #2 Completion Alternatives Alternative Design Study › Finalize the (Grant Ave. to › Public Open › Functional Preferred Wilkes Ave.) House #1 Design Alternative (Grant Ave. › Completion of (Grant Ave. to to McGillivray Environmental Wilkes Ave.) & Blvd.) Reviews Prepare Final Report

Next Step Place Comments Here

If you would like to be notified personally of future events, please [ [ leave your name and email or mail address on your comment sheet. Thank You 15

On behalf of the Project Team, thank you for your

attendance and participation. Please fill out a feedback

form before you leave.

For more information, contact:

Chris Baker, MMM Group | [email protected] | 204.943.3178

Public Consultation Lead: David Jopling, MMM Group | [email protected] | 204.943.3178

Project website:

http://winnipeg.ca/WRCP-Extension