FFYs 2020-24 TIP Universe of Projects Region MPO 11/15/18 Table 1. TIP Projects to Consider for Programming REVISED 2/6/19

MassDOT Project PROJIS/TI MAPC Highway Evaluate in MPO Investment Municipality Proponent Project Name P ID Design Status Cost Estimate Subregion District 2018/2019 Program Notes Inner Core Reconstruction and Signal Improvements Newton Newton on Walnut Street, from Homer Street to 601704 25% design $ 4,648,360 ICC 6 Complete Streets Route 9 Added to the list of new projects to Boston Boston Neponset River Greenway (Phase 3) 608943 PRC-approved $ 4,972,500 ICC 6 X Bicycle and evaluate post 11/15/19 MPO meeting and Pedestrian initial TIP universe Pre-PRC; PRC- Reconstruction of Beacham Street from Everett Everett 609257 approval expected $ 9,180,000 ICC 4 X Complete Streets Broadway to the Chelsea City Line Dec. 2018 Pre-PRC; PRC- Traffic and Safety Improvements at Two Intersection Lynn Lynn 609254 approval expected $ 5,870,300 ICC 4 X Locations on Broadway Improvements Dec. 2018 Pre-PRC; PRC- Lynn Lynn Rehabilitation of Essex Street 609252 approval expected $ 16,925,000 ICC 4 X Complete Streets Dec. 2018 Staff was not able to evaluate this project Community Path, Belmont Component of Bicycle and this year. This is a section of a larger Belmont Belmont 609204 PRC approved $ 16,703,600 ICC 4 the MCRT (Phase 1) Pedestrian project that could be considered for the LRTP. Reconstruction of , from Boston Boston 601274 25% design $ 2,681,260 ICC 6 Complete Streets Court Street to Boston, Boston, Mountfort St. and Commonwealth Ave. PRC approved Intersection Staff was not able to evaluate this project 608956 $ 916,883 ICC 6 Brookline Brookline Connection (2017) Improvements this year. Reconstruction of Tremont Street, from PRC approved Boston Boston 601507 $ 4,400,000 ICC 6 Complete Streets Stuart Street to Marginal Road (1,830 ft.) (1996) Traffic Signal Improvements at Eight Intersection Boston Boston 606556 PRC approved $ 3,603,960 ICC 6 Locations Improvements Leverett Circle Pedestrian Bridge over Bicycle and Boston MassDOT 606703 PRC approved $ 11,040,000 ICC 6 Route 28, I-93 Ramps and Pedestrian Reconstruction on (Route 203) Gallivan Boston Boston Boulevard, from Neponset Circle to East of 606896 PRC approved $ 11,500,000 ICC 6 Complete Streets Morton Street Intersection Improvements on (Route 203) Morton Boston Boston Street, from West of Gallivan Boulevard to 606897 PRC approved $ 11,500,000 ICC 6 Complete Streets Shea Circle Innovation Boulevard Streetscape and Cambridge Cambridge Pedestrian Improvements, between Main 604993 25% design $ 992,163 ICC 6 Complete Streets Street and Binney Street (Phase I) Beacham and Williams Street Chelsea Chelsea 609083 PRC approved $ 8,281,525 ICC 6 Complete Streets Reconstruction Reconstruction of Beacham Street, from Chelsea Chelsea na Pre-PRC ICC 6 Complete Streets Spruce St. to the Everett City Line

1 FFYs 2020-24 TIP Universe of Projects Boston Region MPO 11/15/18 Table 1. TIP Projects to Consider for Programming REVISED 2/6/19

MassDOT Project PROJIS/TI MAPC Highway Evaluate in MPO Investment Municipality Proponent Project Name P ID Design Status Cost Estimate Subregion District 2018/2019 Program Notes Reconstruction on Route 30 PRC approved Newton Newton (Commonwealth Avenue), from Weston 600932 $ 2,208,000 ICC 6 Complete Streets (1996) Town Line to Auburn Street Improvements of Route 128/I-95 and PRC approved Newton Newton 607940 $ 10,000,055 ICC 6 Complete Streets Grove Street (2014) Newton, Resurfacing and Related Work on Route 9, MassDOT 608821 PRC approved $ 7,337,000 ICC 6 Complete Streets Brookline from Dearborn Street to Natick Town Line Minuteman Advisory Group on Interlocal Coordination Littleton Littleton Reconstruction of Foster Street 609054 PRC approved $ 3,600,000 MAGIC 3 X Complete Streets MetroWest Regional Collaborative Pedestrian Hybrid Beacon Installation at Bicycle and Framingham MassDOT 608006 25% design $ 886,228 MWRC 3 Route 9 and Maynard Road Pedestrian

Intersection and Signal Improvements on Part of currently programmed 608566 (FFY Marlboroug Intersection MassDOT Route 20 (East Main Street/Boston Post 604231 25% design $ 1,706,600 MWRC 3 2023); District still prioritizing; funding h Improvements Road) at Concord Road years would need to be coordinated Rehabilitation and Rail Crossing Bicycle and Ashland Ashland 608436 PRC approved $ 990,000 MWRC 3 X Improvements on Cherry Street Pedestrian Traffic Signal Installation at Edgell Road at Intersection Framingham Framingham 608889 PRC approved $ 1,680,000 MWRC 3 X Central Street Improvements Resurfacing and Related Work on Route 9, Wellesley MassDOT 607340 PRC approved $ 16,462,400 MWRC 6 Complete Streets from Dearborn Street to Natick Town Line

Intersection Improvements - Boston Post Intersection Weston Weston 608940 PRC approved $ 1,219,250 MWRC 6 Road (Route 20) at Wellesley Street Improvements Weston MassDOT Reconstruction on Route 30 608954 PRC approved $ 8,117,562 MWRC 6 Complete Streets North Suburban Planning Council Reconstruction on Route 38 (Main Street), Wilmington Wilmington 608051 25% design $ 10,802,316 NSPC 4 X Complete Streets from Route 62 to the Woburn City Line Pre-PRC; PRC- Intersection Improvements at Lowell St. Intersection Wilmington Wilmington 609253 approval expected $ 3,400,000 NSPC 4 X and Woburn St. Improvements Dec. 2018 Middlesex Canal Park Improvements, from PRC approved Bicycle and Woburn Woburn Alfred Street to (Phase II - 606304 $ 799,820 NSPC 4 No current updates; no FDR on file (2010) Pedestrian Segment 5) Intersection Reconstruction at Route 3 PRC approved Intersection Woburn MassDOT (Cambridge Road) and Bedford Road and 608067 $ 1,440,000 NSPC 4 Design not being advanced currently (2014) Improvements South Bedford Street

2 FFYs 2020-24 TIP Universe of Projects Boston Region MPO 11/15/18 Table 1. TIP Projects to Consider for Programming REVISED 2/6/19

MassDOT Project PROJIS/TI MAPC Highway Evaluate in MPO Investment Municipality Proponent Project Name P ID Design Status Cost Estimate Subregion District 2018/2019 Program Notes North Shore Task Force Reconstruction on Collins Street, from Danvers Danvers 602310 75% design $ 5,183,121 NSTF 4 Complete Streets Sylvan Street to Centre and Holten Streets Bicycle and Peabody MassDOT Independence Greenway Extension 609211 PRC approved $ 1,921,075 NSTF 4 X Pedestrian Beverly, Resurfacing and Related Work on Route Manchester- MassDOT 607707 PRC approved $ 2,300,000 NSTF 4 Complete Streets Possible scope change; no FDR on file 127 by-the-Sea Manchester- Manchester-by- Pine Street - Central Street (Route 127) to Pre-PRC; PNF na NSTF 4 Complete Streets No current updates; no FDR on file by-the-Sea the-Sea Rockwood Heights Road submitted 12/27/16 South Shore Coalition Improvements on Route 3A from Otis Street/Cole Road, including Summer PRC approved Hingham Hingham 605168 $ 7,500,001 SSC 5 Complete Streets Street and Rotary; Rockland Street to (2009) George Washington Boulevard Corridor Improvements and Related Work Holbrook Holbrook on South (Route 37) from 608543 PRC approved $ 4,000,200 SSC 5 Complete Streets No current updates; no FDR on file Snell Street to King Road Corridor Improvements along Nantasket Pre-PRC; PNF Hull Hull na SSC 5 Complete Streets No current updates; no FDR on file Avenue from Moutford Road to A Street submitted 6/30/16 Reconstruction on Route 3A, including Weymouth Weymouth Pedestrian and Traffic Signal 608231 PRC approved $ 10,780,100 SSC 6 Complete Streets Improvements Resurfacing and Related Work on Route Weymouth MassDOT 608483 PRC approved $ 2,400,000 SCC 6 Complete Streets 3A South West Advisory Planning Committee Rehabilitation on Route 16, from Route PRC approved Milford MassDOT 608045 $ 2,700,000 SWAP 3 Complete Streets 109 to Beaver Street (2014) South Main Street (Route 126) - Elm Street Pre-PRC; PNF No current updates; no FDR on file; Bellingham Bellingham na SWAP 3 Complete Streets to Douglas Drive Reconstruction submitted 3/13/17 proponent prioritizing 608887 Resurfacing and Intersection Design not being advanced currently; Franklin MassDOT Improvements on Route 140, from Beaver 607774 PRC approved $ 4,025,000 SWAP 3 Complete Streets minor improvements accomplished Street to I-495 Ramps recently

3 FFYs 2020-24 TIP Universe of Projects Boston Region MPO 11/15/18 Table 1. TIP Projects to Consider for Programming REVISED 2/6/19

MassDOT Project PROJIS/TI MAPC Highway Evaluate in MPO Investment Municipality Proponent Project Name P ID Design Status Cost Estimate Subregion District 2018/2019 Program Notes Three Rivers Interlocal Council Reconstruction of Canton Street and PRC approved Staff was not able to evaluate this project Westwood Westwood 608158 $ 2,880,000 TRIC 6 Complete Streets Everett Street (2015) this year. Intersection Westwood MassDOT Traffic Signal Improvements on Route 109 608947 PRC approved $ 453,600 TRIC 6 Improvements Multiple Subregions Multi-use Trail Connection, from Added to the list of new projects to Recreation Road to Upper Charles River ICC, Bicycle and Newton, Weston MassDOT 609066 PRC approved $ 2,661,498 6 X evaluate post 11/15/19 MPO meeting and Greenway including Reconstruction of MWRC Pedestrian initial TIP universe Pedestrian Bridge N-12-078=W-29-062 Intersection Improvements - Squantum PRC approved Intersection Milton Milton 608955 $ 979,763 ICC, TRIC 6 Street at Adams Street (2017) Improvements Reconstruction on Granite Avenue, from Milton MassDOT 608406 25% design $ 3,665,146 ICC, TRIC 6 Complete Streets Neponset River to Squantum Street

Already evaluated; reconsider for programming Evaluate for the first time this year Not evaluated; no data for evaluation

Subregions: ICC = Inner Core Committee. MAGIC = Minuteman Advisory Group on Interlocal Coordination. MWRC = MetroWest Regional Collaborative. NSTF = North Shore Task Force. NSPC = North Suburban Planning Council. SSC = South Shore Coalition. SWAP = South West Advisory Planning Committee. TRIC = Three Rivers Interlocal Council. Abbreviations: FDR = functional design report. LRTP = Long-Range Transportation Plan. MAPC = Metropolitan Area Planning Council. MassDOT = Massachusetts Department of Transportation. PNF = project need form. PRC = MassDOT Project Review Committee. TIP = Transportation Improvement Program.

4