MINUTES OF THE MEETING CONDUCTED WITH DISTRICT ELECTRICITY COMMITTEE ON 06.09.15 AT 10 AM IN COLLECTORATE SRIKAKULAM UNDER THE CHAIR PERSON OF SRI FOR CIVIL AVIATION GOVT OF INDIA AND SENIOR MOST MP ON DEEN DAYAL UPADHAYAYA GRAMJYOTHI YOJANA ( DDUGJY) AND INTEGRATED POWER DEVELOPMENT SCHEME (IPDS).

The following Dignitaries have attended.

1. Sri P. Ashoka Gajapathi Raju, Hon’ble Minister of Civil Aviation, - Chairperson

2. Sri K. Rammohan Naidu, Hon’ble Member of Parliament - Co-Chairperson

3. Sri P. Laxmi Narasimham, Hon’ble District Collector, Srikakulam - Convener

4. Sri Vivek Yadav, Joint Collector, Srikakulam Dist.

5. Smt Ch. Dhanalaxmi, Hon’ble Chairperson, Zillaparishad, Srikakulam - Member

6. Sri Koona Ravi Kumar, Amadalavalasa, Hon’ble WHIP Govt of A.P - Member

7. Smt Gunda Lakshmi Devi, Srikakulam, Hon’ble MLA, Srikakulam - Member

8. Sri Ramana Murthy Baggu, Narasannapeta, Hon’ble MLA, Narsannapeta - Member

9. Sri G. Sarath Kumar, Superintending Engineer, APEPDCL, Srikakulam. - Member Secretary

10. Activities of the District Level Committee :

1) The committee should meet at least once in 3 months at the District Head Quarters.

2) The committee shall be consulted in the preparation of DPRs under DDUGJY and IPDS and would monitor the implementation of these schemes.

3) The committee would review the quality of power supply and consumer satisfaction and would promote energy efficiency and energy conservation.

4) Minutes of the meeting to be issued by the convener.

5) It is the responsibility of the Member Secretary to ensure that requisite meeting take place and a quarterly report is sent to the Nodal Agency i.e., REC (DDUGJY) and PFC (IPDS).

The Government of India has launched 2 Nos. new schemes "Deen Dayal Upadhayaya Gram Jyoti Yojana" (DDUGJY) for rural areas and Integrated Power Development Scheme (IPDS) for urban areas for 24X7 power supply in the state.

The objectives of scheme are:

DEEN DAYAL UPADHAYAYA GRAM JYOTI YOJANA (DDUGJY)

1) providing access to all house holds

2) Feeder Separation - Separation of agriculture and non-agriculture feeders facilitating judicious rostering of supply to agricultural & non- agricultural consumers in the rural areas.

3) System Strengthening - Strengthening and augmentation of sub-transmission & distribution (ST&D) infrastructure in rural areas.

4) Metering -Metering at distribution transformers, feeders and consumers end Under this scheme 60% of the amount will be given as grant, and the balance 40% as loan. The infrastructure is proposed for an amount of Rs. 136.71 Crores and submitted to M/s RURAL ELECTRIFICATION CORPORATION LIMITED (REC), NEW DELHI for sanction.

INTEGRATED POWER DEVELOPMENT SCHEME (IPDS)

(i) Strengthening of Sub-transmission and Distribution network in urban areas (ii) Metering of distribution transformers / feeders / consumers in urban areas (iii) Rooftop Solar Project, installation of solar panels and smart/net meters (iv) Continuing IT enablement of distribution sector and distribution network strengthening

Under this scheme 60% of the amount will be given as grant, and the balance 40% as loan. The infrastructure is proposed for an amount of Rs.40.86 Crores and submitted to M/s Power Finance Corporation, NEW DELHI for sanction.

The following points were raised by Hon’ble committee members:

 District Collector, convener has briefed on the 2nos Central Govt Schemes namely DDUGJY and IPDS  Sri Ashok Gajapathi Raju, Minister Chairperson has reviewed on the power supply position in the district and instructed to intimate the local surpanchs on the interruptions or breakdowns etc. And discussed on the proposed electrification of rural households under DUGVY and told to complete within the time frame after awarding of the work, as per the guidelines and to prepare time lines of monthly schedule for electrification of rural households and other works.  Sri Ram Mohan Naidu, MP Chairperson, discussed on the earlier submitted proposal for Rs.385 crores and present prosposal for Rs 136.7 crores. And told to submit the future requirements for lines and Sub-Stations other than House holds.  District Collector told to submit a report on the differences on the above proposals  Minister discussed on the solar pump sets works and told to speed up the works.

 Sri K.Ravi Kumar , WHIP Member asked Solar pump sets work not completed in Narasapuram (V) of Ponduru Mandal & told to complete the work at the earliest and told lines laid long back in house sites and over new houses constructing.  A New Sub Station was required at Sarubujji and also raised the point to require 24 Hrs supply to Industrial estate in Amadalavalasa and proposed with new 33/11 KV Sub Station.  Smt G. Laxmi Devi, MLA Srikakulam /Member, told that in Srikakulam constituency lines are passing over houses, lines getting rusted in sea coast areas, lineman handicapped to be transferred.  District Collector discussed on the 15 nos Sub Stations proposed in DDUGVY.  Sri K. Ravi Kumar, WHIP/Govt. of AP is told in Amadalavalasa Asst. Engineer post not filled. District Collector told to write a DO Letter to CMD, APEPDCL.  Smt Ch.Dhana Lakshmi, ZP Chairperson & Member DEC told iron poles laid long back got rusted including agriculture lines laid 50 years back and to replace lines passing over houses are to be shifted.  Sri B.Ramana Murthy, MLA Narasannapeta and Member DEC told to provide UG cable in Sea coast area, in Saravakota mandal the nunmber of households proposed to be electrified is low, the Timadam & Allada villages of Saravakota mandal are getting supply from Challavanipeta SS and requested to propose a new Sub station at Timadam(V).  The Hon’’ble Minister discussed on extension of continuous 7 hrs supply to Agricultural pump sets and the system improvement provision for regular works and also discussed on power supply status to Srikakulam Town. At present the Srikakulam town is getting supply from 132KV Substation Chilakapalem, which is at 10 KM distance from Srikakulam town. Recently a new 132KV Substation has been sanctioned for Srikakulam town. It is necessary to construct the new 132KV Sub station in Srikakulam town only.  District Collector finally concluded the meeting and told that time lines to be framed for the targeted quantities proposed in the scheme and the committee will meet once in 3 months.

COLLECTOR & DISTRICT MAGISTRATE SRIKAKULAM

To Sri P. Ashoka Gajapathi Raju, Hon’ble Minister of Civil Aviation, Vizianagaram, Sri K. Rammohan Naidu, Hon’ble Member of Parliament, Srikakulam Sri P. Laxmi Narasimham, Hon’ble District Collector, Srikakulam Smt Ch. Dhanalaxmi, Hon’ble Chairperson, Zillaparishad, Srikakulam Sri Koona Ravi Kumar, Amadalavalasa, Hon’ble WHIP Govt of A.P, Srikakulam, Smt Gunda Lakshmi Devi, Srikakulam, Hon’ble MLA, Srikakulam Sri Ramana Murthy Baggu, Narasannapeta, Hon’ble MLA, Narsannapeta Sri Vivek Yadav, Joint Collector, Srikakulam Dist.

" MiNUTESOF DISTRICTELECTRICITYCOMMITTEEMEETINGHELDON 16.07.2015 AT 14.00 Hours UNDERTHECHAIRPERSONOFSRIMUTTAMSETTISRINIVASARAO,HON'BlE MEMBER OF PARLIAMENTlOKSABHA, ANAKAPAlLl WITH CO-CHAIRPERSONSAND MEMBERSOF VISKAKHAPATNAMDISTRICT.THEFOllOWING DIGNITARIESAREATTENDED.

1.Sri Muttamsetti Srinivasa Rao, Hon'ble MP, Loksabha,Anakapalli - Chairperson 2.Sri Kambhampati Haribabu, Hon'ble MP, Loksabha,Visakkhapatnam - Co-Chairperson 3.Sri N.Yuvaraju, .District Collector, - Convener 4.Sri Ganta Srlhivasa Rao, Hon'ble Minister, HRD,AP. Member 5.Sri V.GaneshKumar, Hon'ble MLA, South, Visakhapatnam Member 6.Sri PGVRNafdu, Hon'ble MLA, West, Visakhapatnam Member 7.Sri P.SrinivasaRao, Hon'ble MLA, Gajuwaka Member B.Sri P.GovindaSatyanarayana, Hon'ble MLA,Anakapalli Member 9.Sri B.SatyanarayanaMurthy, Hon'ble MLA, Pendurthy Member 10.Smt.L.Bhavani Bhaskar, Z.P. Chairperson Member 11.Sri P.S.RadhaKrishnan, Chief General Manager, NTPC,VSP Member 12.SriM.SatyanarayanaMurthy, SE/OI APEPDCL Member 13.Sri P.V. RamaRaju, District Manager I NEDCAPI VSP Member 14.Sri Ch. Pantulu, General Manager I Projects I APEPDCL

The District Collector, Visakhapatnam has informed that the District Electricity Committee Meeting will be conducted at least once in 3 months at the District Head Quarter. ACTIVITIYOF THE COMMITIEE The Committee shall be consulted in the preparation of DPRsunder DDUGJYand IPDSand would monitor the implementation of these schemes. The Committee would review the' quality -of power supply and consumer satisfaction and would Rromote energy efficiency and energy conservation. Minutes of the meeting~ be issuedby the convener It is the responsibility of the Member secretary to ensure that requisite meetings take place and a quarterly report is sent to the Nodal Agency i.e., REC(DDUGJY) and PFC(IPDS)

DEENDAYALUPADHAYAYAGRAMJYOTI YOJANA (DDUGJY)

The Government of India has launched a new scheme " Deen Dayal Upadhayaya Gram Jyoti Yojana" (DDUGJY) for rural areas against 24X7 power supply in the state. The objectives of scheme are:

>- 24X7Power for all by 2019. >- providing accessto all house holds. >- Feeder Separation - Separation of agriculture and non-agriculture feeders facilitating judicious rostering of supply to agricultural 8: non- agricultural consumersin the rural areas >- System strengthening - Strengthening and augmentation of sub-transmission 8: distribution (ST8:D)infrastructure in rural areas. >- Metering -Metering at distribution transformers, feeders and consumersend

~ ~~~~---'....:.__'I_AA~~~\~ _ , ~ Under this scheme 60% of the amount will be given as grant, and the balance 40% as loan. under scheme the infrastructure is proposed for an amount of Rs. Rs. 52112.18 lakhs and submitted to M/s RURAL ELECTRIFICATIONCORPORATIONLIMITED (REC), NEW DELHI for sanction.

INTEGRATED POWER DEVELOPMENT SCHEME (IPDS)

The Government of India has launched a new scheme "Integrated Power Development Scheme" (IPDS) for Urban/Semi-urban areas.

The objectives of scheme are:

>- Strengthening of Sub-transmissionand Distribution network in urban areas; >- Metering of distribution transformers / feeders / consumers in urban areas and, >- Rooftop Solar Project, installation of solar panels and smart! net meters as a mandatory component under IPDS >- Continuing IT enablement of distribution sector and distribution network strengthening as per the norms of the ongoing scheme of RAPDRPbysubsumingthe same in IPDS.

Under this scheme 60%of the amount will be given as grant, and the balance 40%as loan. under this scheme the following infrastructure is proposed for an amount of Rs. Rs. 11868.58lakhs and submitted to M/s Power Finance Corporation, NEWDELHIfor sanction.

The following points were raised by Honorable Member:

The Chairperson of the Committee Sri Muttamsetti Srinivasarao, Hon'ble MP, Loksabha, Anakapalli has instructed to maintain un-interrupted power supply and quality of power to all the consumers.

The Co-Chairperson of the Committee Sri Kambhampati Haribabu, Hon'ble Member of Parliament (Loksabha), Visakhapatnam and Members are instructed to conduct awareness programme on Rooftop Solar System and Agricultural Solar Pump sets through Pamphlets and Media.

The Co-Chairperson of the Committee Sri Kambhampati Haribabu, Hon'ble Member of Parliament (Loksabha), Visakhapatnam has instructed to obtain clarification to adopt Agricultural Solar Systemfor extsting Agricultural Services. The Committee Member of Sri Peela Govinda Satyanarayana, Hon'ble MLA, Anakapalli has informed that the Agricultural Solar System not adopted in RECs, Kasimkota as the Agricultural application registered nearly 600 Nos. in RECsarea. But single .service was not released on Agricultural Solar System. Accordingly the District Collector, Visakhapatnam informed that this issue will be taken to notice of Government of .

The Hon'ble Minister for HRDSri Ganta Srinivasa Raohas instructed to commence all schemeswhich were aided / granted by either union Govt. or State Govt. with prior intimation to Public Representatives only. , The Hon'ble MLA Pendurthy Sri B. SatyanarayanaMurthy has asked for possibility of Solar panels at a distance place from bore and connecting the bore with cable. As some part of agriculture and is being used for solar panels. And also asked for availability of higher capacity motors ie., more than 5 HP. All the members informed that in the next meeting there will be a detailed review on scheme power supply posttion and consumer problems. Insisted for presence of RECMDand other higher authorities of APEPDCLto attend the next ReviewMeeting.

SUPER~NGINEER, OPERATION:VISAKHAPATNAM. To:

Sri Muttamsetti Srinivasa Rao, Hon'ble MP, Loksabha, Anakapalli Sri Kambhampati Haribabu, Hon'ble MP, Loksabha, Visakkhapatnam Sri N.Yuvaraju, District Collector, Visakhapatnam Sri Ganta Srinivasa Rao, Hon'ble Minister, HRD,Andhra Pradesh Sri V.Ganesh Kumar, Hon'ble MLA, South, Visakhapatnam Sri PGVRNaidu, Hon'ble MLA, West, Visakhapatnam Sri P.Srinivasa Rao, Hon'ble MLA, Gajuwaka Sri P.Govinda Satyanarayana, Hon'ble MLA, Anakapalli Sri B.Satyanarayana Murthy, Hon'ble MLA, Pendurthy Smt.L.Bhavani Bhaskar, Z.P. Chairperson Sri P.S.RadhaKrishnan, Chief General Manager, NTPC,VSP Sri P.V. Rama Raju, District Manager I NEDCAPI VSP

Copy submitted to the Chief General Manager/Projects/APEPDCLNisakhapatnam. Copy to the Assistant Divisional Engineer I Technical to CMD Peshi APEPDCL/ Visakhapatnam.

Endt.No.SE/ONSP/DEITIAEIT1/F. Minutes IDNa. 3615/15. Dt: 23 .07.2015. Minutes of the ))istrict Electricity Committee meeting held on 28-08-2015 at 4.00 PM Court Hall, Collectorate, Kakinada under the Chairperson of Sri. Thota Narsimham, Hon'ble MP, Kakinada with Co-Chairpersons and Members of East Godavari ))istrict. The fallowing ))ignitaries are attended.

1. Sri Thota Narasimham, Hon'ble M.P. Kakinada Chairperson. 2. Sri H.Arun Kumar, District Collector, E.G.Dist. Convener 3. Sri Namana Rambabu, Z.P. Chairman, E.G.Dist. Member 4. 'Sri D.Ramalingeswara Rao, M.L.A. Tuni Member 5. Sri Varupula Subbarao, M.L.A. Prathipadu Member 6. Smt. Pilli Ananta Lakshmi, M.L.A. Kakinada Rural Member 7. Sri Vanamadi Venkateswara Rao, M.L.A. Kakinada City- Member 8. Sri Jyothula Venkata Apparao (Nehru), M.L.A. Jaggampeta - Member 9. Smt. Vanthala Rajeswari M.L.A. R.Ch.Varam Member 10. Sri Y.S.N. Prasad, Superintending Engineer, Operation, APEPDCL - Member Secretary.

The Honorable Chairperson, East Godavari has informed that the District Electricity Committee meeting will be conducted at least once in three months at District head quarters.

Activities of the committee ~ The committee shall be consulted in the preparation of DPRs under DDUGJY and IPDS and would monitor the implementation of these schemes. ~ The committee would review the quality of power supply and consumer satisfaction and would promote energy efficiency and energy conservation. ~ Minutes of the meeting to be issued by the convener. ~ It is the responsibility of the Member secretary to ensure that requisite meetings take place and a quarterly report is sent to the Nodal Agency i.e., REC (DDUGJY) and PFC (IPDS).

The Superintending Engineer / Operation / Rajahmundry, Member Secretary explained about the two schemes launched by Government of India. ~ DDUGJY (Deeo Dayal Upadhyaya Gram Jyothi Yojana Scheme)

The main objectives of the scheme are

24X7 Power for all households. Providing access to all households. To separate agricultural and non-agriculture feeders in rural areas. Strengthening and Augmentation of Sub Transmission & Distribution infrastructure in rural areas. The DDUGJY scheme is prepared for Rs.363.78 crores. In this scheme 60%of the amount will be given as grant and the balance 40% as loan from MIs. Rural Electrification Corporation Limited (REC), New Delhi.

~ Integrated Power Development Scheme (IPDS)

The main objectives of the scheme are

Strengthening and Augmentation of Sub Transmission & Distribution infrastructure and metering urban / semi urban areas. 9Nos. towns in (Rajahmundry, Kakinada, Pithapuram, Samalkota, Peddapuram, Ramachandrapuram, Mandapeta, Tuni, Amalapuram) The scheme is prepared first priority for Rs.89.l1 crores. In this scheme 60% of the amount will be given as grant, and the balance 40% as loan from MIs Power Finance Corporation (PFC), New Delhi. The fallowing points were raised and suggested by the Honorable Members of the committee. Sri. Varupula Subbarao, Honorable MLA, Prathipadu requested to fulfill the schemes and extend supply to remote hilly areas. The Honorable MLA also requested to shift all the electrical lines passing over households and also requested for new 132/33 KV Substation at Annavaram and 33/11 KV SS at Lingamparthy. Sri. D.Ramalingeswara rao, Honorable MLA, Tuni pointed out that there is no supply to housing colony in Uppragudem, Ward No:23 of Tuni and also requested for rectification of low voltage in Tuni-Rural area. Sri. Jyothula Venkata Apparao, (Nehru) Honorable MLA, Jaggampeta requested for replacement of old conductor and poles in villages under this scheme. The Honorable MLA requested not to erect new EHT lines in the present corridor and requested for change of corridor for future line and also requested to enhance compensation to farmers who loose the lands due to tower lines. The Honorable MLA also requested for construction of new 220 KV SS at Kirlampudi, 132 KV SS at Jaggampeta, 2 Nos. 33/11 KV Substations at Irripaka and Nayakampalli villages. Sri. Vanthala Rajeswari, Honorable MLA, Rampachodavaram requested to extend supply in Rajavomrnangi village for the consumers who paid Rs. 125/- & Requested to rectify low voltage problem. The Honorable MLA also requested to convert the existing 6.3 KV line with over head cable to reduce interruptions & accidents and requested to

rectify loose spans and asked for new DTRs in her constituency. Smt. Pilli Anantha Lakshmi, Honorable MLA, Kakinada-Rural requested for 3 Nos. Substations at Indrapalem, Gaigolupadu and Ramanayyapeta. The Honorable MLA also requested for 108 Nos. DTRs in her constituency and requested to extend supply to un-

electrified colonies in Kakinada and Karapa. Sri. Vanamadi Venkateswara Rao, Honorable MLA, Kakinada-City requested for 5 Nos. Substations in Kakinada Town, and requested to carry out GGH Substation work on top priority irrespective of schemes in view of emergency. The Honorable MLA also requested for 120 Nos. Distribution Transformers in his constituency, and for

replacement of damaged lines and poles. The Honorable M.P. and chairperson of the committee conveyed all the points covered in the schemes and requested the honorable collector to provide vacant lands for construction of new substation at Kirlampudi, Annavaram and Jaggampeta. The Honorable M.P. and chairperson also requested all the members and APEPDCL members to make the schemes grand success.

East Goshavari District. To Sri Thota Narasimham, Hon'ble M.P. Kakinada, Sri H.Arun Kumar, District Collector, E.G.Dist, Sri Namana Rambabu, Z.P. Chairman, E.G.Dist. Sri D.Ramalingeswara Rao, M.L.A. Tuni Sri Varupula Subbarao, M.L.A. Prathipadu Smt. Pilli Ananta Lakshmi, M.L.A. Kakinada Rural Sri Vanamadi Venkateswara Rao, M ... L A Kak· ma d a C· ity Sri Jyothula Venkata Apparao (Nehru), M ... LA J aggampeta Smt. Vanthala Rajeswari M.L.A. R.Ch.Varam

Sri Y.S.N. Prasad, Superi in ten di mg E ngmeer, . Operation, APEPDCL.