JUSHI INDIA FIBERGLASS PVT.

LTD.

Plot No. E-5, Talegaon MIDC Area, Village-Badhalwadi, Taluka. Maval, District. Pune, -412208 PREFEASIBILITY REPORT

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

Contents 1. EXECUTIVE SUMMARY ...... 2 2. INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION ...... 4 3. PROJECT DESCRIPTION ...... 9 4. SITE ANALYSIS ...... 22 5. PLANNING BRIEF ...... 27 6. PROPOSED INFRASTRUCTURE ...... 29 i. Industrial Area ...... 29 ii. Residential Area ...... 29 iii. Green Belt ...... 29 iv. Social Infrastructure ...... 29 v. Connectivity ...... 29 vi. Drinking Water ...... 29 vii. Sewerage System ...... 30 viii. Industrial Waste Management ...... 30 ix. Solid Waste Management ...... 30 x. Power Requirement ...... 31 7. REHABILITATION AND RESETTLEMENT PLAN (R & R) ...... 31 8. PROJECT SCHEDULE & COST ESTIMATES ...... 31 9. ANALYSIS OF PROPOSAL ...... 32

1 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

1. EXECUTIVE SUMMARY Jushi India Fiberglass Pvt. Ltd. is a company originated from China Jushi Co. Ltd. Jushi China is the world’s largest Fiberglass producer. Company has proposed to install 220000 MT/Annum production capacity plant in Talegaon MIDC area at Plot No. E-5, Village Badhalwadi , Taluka. Maval, District. Pune -412208.

Fiberglass has a wide range of applications in automotive, sports and leisure, consumer goods and business equipment, building and construction, chemistry and chemical, wind energy, electrical and electronics, marine and Infrastructure sector. India is a fast developing country. Under the Indian government’s “Make in India” initiative, many development projects such as roads, area development, bridge construction, industrial area development are in pipeline, for which fiberglass will be a useful material due to its strength & durability. Proposed industrial development is expected to be helpful to Indian economy as it has a potential of reducing construction costs.

The company has procured 237023.00 sq. m. of land in Talegaon MIDC area. The total proposed BUA of the industry will be 2,84,282.99 Sq. M [FSI-276515.29 Sq.M.+ Non FSI- 7767.70 Sq.M.] Site is located in the MIDC area, hence, all required infrastructure such as roads, electricity and water will be supplied by the MIDC.

Fiberglass manufacturing activity does not come under the purview of the principal EIA Notification dated 14th September 2006 and amendment thereof, therefore the proposed industrial process does not require environmental clearance (EC) . However, total plot potential/proposed developing area of the project is greater than 1,50,000.00 sq. m. Thus, making EC under project activity 8(b) i.e. Townships and Area Development projects mandatory. The proposed project comes under the purview of Maharashtra State Environment Department, State Environmental Impact Assessment Authority (SEIAA) followed by the State Expert Appraisal Committee (SEAC-3).

Industry has proposed effluent treatment facility for trade effluent within the plant premises followed by the final treatment and disposal facility at Talegaon common CETP as per the agreement with MIDC. Bio-degradable food waste will be treated in OWC and prepared manure will be used for gardening purpose within plant premises.

2 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

Talegaon MIDC area is known as a foreign investor zone as there are many upcoming industries such as Peri India, Emerson Process Management, Emitech/ Continental, GE India, POSCO India Pune Processing Centre Pvt. Ltd., JCB India Ltd., Housco Hydraulics Pvt. Ltd. etc. In Talegaon MIDC area most of the industries are from chemical, steel and automotive sectors, which use fiberglass as a raw material. Local availability of raw materials is known to be of help in reducing costs of finished goods.

Proposed project is a green field project and Jushi India Fiberglass Pvt. Ltd. has clean environmental policy. Proposed plant is fully automized plant in order to avoid human error. The total estimated cost of the project is Rs. 3,500 Cr. Proposed industry is expected to generate around 200 to 250 employment opportunities for local people in construction phase while 550 to 600 direct employment opportunities in operation phase. Jushi India Fiberglass Pvt. Ltd. will export 66,000 tonnes of fiberglass annually in the international market, thus, generating additional revenue to the Indian government in the form of taxes.

3 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

2. INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION

i. Identification of the Project and Project Proponent : Jushi India Fiberglass Pvt. Ltd. is the proposed fiberglass manufacturing industry, which is to be established in Talegaon MIDC area at plot no. E-5, Village. Badhalwadi, Taluka. Maval, District. Pune, Maharashtra-412208. Industry has acquired 2,37,023.00 sq. m. of land in Talegaon MIDC area. Industry has proposed to produce 2,20,000 MT per annum of fiberglass.

Jushi India Fiberglass Pvt. Ltd. is the fully owned by China Jushi Co., Ltd. It is a public company listed in Shanghai Stock Exchange and specializes in the manufacture and sales of fiberglass and its fabrics as its main business. China Jushi has established 14 overseas production and trading subsidiaries in Egypt, USA, South Africa, France, Italy, Canada, Spain, India and Singapore, which form a rationally distributed global sales network.

ii. Brief description of nature of the project Jushi India Fiberglass Pvt. Ltd. is the first fiberglass manufacturing industry in India by China Jushi Co. Ltd. Manufactured fiberglass has a wide range of applications in major economic sectors viz. automotive; sports and leisure; consumer goods and business equipment; building and construction; chemistry and chemical; wind energy; electrical and electronics; marine; infrastructure etc.

Industry has proposed to manufacture 22,0000 MT per annum of fiberglass by using key raw materials – kaolin, limestone and silica sand, which will be imported or sometimes be purchased from the Indian market as per the availability. Manufactured product will both be exported (30% ) and sold in Indian market (70%).

Since the industry is proposed to be set up in the MIDC area, all required infrastructure such as land, road, water, electricity will be provided by MIDC. Proposed project is a green field project and it is fully atomization plant. Industry has prepared scientific disposal system for trade effluent and solid waste management.

4 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

iii. Need of the project and its importance to the country and or region As the fiberglass has numerous applications in building construction and infrastructure development due to its strength and durability, proposed industry will be an added advantage for construction sector.

Nowadays, good quality fiberglass is imported in India as per requirements, however, import eventually results in increased costs of the development. Proposed site is located in Talegaon MIDC area and Chakan MIDC area is close to it. Presently Talegaon MIDC area is occupied by Veeprho Laboratories Pvt. Ltd., Dumax Trading Company, Badrivishal Chemicals & Pharmaceuticals, DN Fiber Glass Pultrusion Technology, Bericap India Private Limited, POSCO India Pune Processing Centre Pvt. Ltd. Ckdpack Packaging Pvt. Ltd. Pune, Peri India, Emerson Process Management, Continental among others. Talegaon MIDC is having majorly Automobile & its ancillary industries and in addition to that Chemical, Steel & Foundry industries are their; in which somehow they are consuming fibeglass. Hence proposed industry is having local and favourable market in Talegaon MIDC area itself as well as Chakan MIDC, Ranjangaon MIDC, Mumbai industrial area. Fiberglass product will be exported 66,000 MT/year in the international market which is expected to generate additional revenue of 66 millions USD/year for the Indian government in form of taxes. iv. Demand- Supply Gap The Fiber Glass Flooring Market was estimated at USD 421 Million in 2017 and expected to reach 987 USD Million by 2025.It is also expected to register a CAGR of 6.8% till 2025. Significant rise in the construction industry; the market for Fiber Glass Flooring is witnessing a surge in its valuation across the world. Growing application in industrial, residential and commercial buildings will boost the growth of the industry in coming years.

Increase in per capita income of the consumers combined with the properties of fiberglass such as ease of installation, aesthetic have triggered the market expansion. Also, the growth of construction sector acts as a key driver for this industry.

5 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

Indian fiberglass market was valued at $ 779 million in 2018 and is projected to grow at a CAGR of more than 8% to reach $ 1.2 billion by 2024. Anticipated growth in the market can be attributed to extensive use of fiberglass in construction industry. Fiberglass refers to a strong, lightweight material that consists of thin fibres of glass that can be transformed into a woven layer or used as reinforcement. Fiberglass is not as strong and stiff as carbon fibre-based composites, but it is less brittle and cheap in comparison with the latter. Increase in use of fiberglass for the manufacturing of automobile and aircraft body-parts, owing to its high strength and lightweight properties is anticipated to drive the market growth. Though the fiberglass market in India is witnessing a healthy growth landscape, health related issues and unstable prices of raw materials are likely to hinder the market growth.

In terms of types, India fiberglass market has been categorized into glass wool, direct & assembled roving, yarn, chopped strand and others. Of these categories, glass wool and chopped strand segments are expected to grow at a healthy rate during the forecast period, backed by growing automobile production in the country. Chopped strands are used to provide reinforcements in the automotive industry.

India fiberglass market is oligopolistic in nature with the presence of both global and local players. A large number of players have embraced new technologies for manufacturing the products as per client prerequisites. The players are investing heavily in the R&D to introduce innovative products in the market. Some of the leading players in India fiberglass market are Saint-Gobain India Private Limited, Goa Glass Fibre Limited, Jushi India Pvt. Ltd.,

6 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

U.P. Twiga Fiber Glass Ltd., Owens Corning, JR Fibreglass Industries Pvt. Ltd., Montex Glass Fibre Industries Private Limited, Ventura Fibre, Glassfibre & Allied Industries, etc.

v. Import Vs Indigenous Production of Fiberglass

India imports about 1,10,000 tonnes of fibreglass annually to meet the demand of 1,70,000- 1,80,000 tonnes. Glass fiber continues as the preferred Reinforcement Material for fabricators, due to low cost and compatibility with the production processes. In 2018, glass fibers constituted markets share of around 98.5% (Fig. 2) and close to 20% of the domestic demand for glass fiber was catered by import supply.

Carbon and Aramid Fibers, with low cost to performance ratio, are the import dependent markets destined to grow. Aramid fiber is mainly used in production of Bullet-Proof Jackets.

Formosa Plastics Corp., Taiwan, Kureha Corp., Japan, Toray Industries, Inc., Japan, Toho Tenax Co., Ltd., Japan, Osaka Gas Chemicals Co., Ltd., Japan and ZOLTEK™ Corporation, USA (acquired by Toray) are major exporters of Carbon Fibers to India. Carbon fibers are used mostly in Defense, Aerospace, Sporting goods and Automobiles sectors as a substitute for metals and ceramics. The demand of Aramid fibers is met by imports mostly through E. I. du Pont de Nemours and Company, USA and Koninklijke DSM N.V., Netherlands.

7 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

vi. Export Possibility

Jushi India Fiberglass Pvt. Ltd. will export 66000 tonnes per year of fiberglass.

vii. Domestic/ Export Market

Jushi India Fiberglass Pvt. Ltd. will sale product in Indian market mainly in Pune, Mumbai, Banglore, Kolkata, Jaipur, Nagpur and other metro cities wherever infrastructure development projects are running. In addition to that product will supply to depended industry Automobile sector, Sports and Leisure; Consumer Goods and Business Equipment; Building and Construction; Chemistry and Chemical; Wind Energy; Electrical and Electronics; Marine; Infrastructure etc.

Products will be exported to the Middle East, Europe and South East Asia as per international market requirement.

viii. Employment generation (Direct & Indirect) due to the project

Proposed project will generate 200-250 nos. of manpower during construction phase and 550-600 nos. of direct manpower during operation phase. In addition to that indirect employment to ancillary business such as hotel, canteen, grocery, fruit, vegetable etc.

8 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

3. PROJECT DESCRIPTION

i. Type of project including interlinked and interdependent projects, if any

Proposed project is green field project and it is newly setup in Talegaon MIDC area having total plot area 237023.00 Sq.M. and built up area is: 2,84,282.99 Sq. M [FSI-276515.29 Sq.M.+ Non FSI-7767.70 Sq.M.]

Fiberglass manufacturing industry doesn’t fall under the purview EIA Notification 14th September 2006 but plot potential of industry is more than 1,50,000.00 Sq.M. hence proposed industrial development would require environmental clearance under project activity 8(b) i.e. Townships and Area Development projects, from Maharashtra State Environment Department, State Impact Assessment Authority (SEIAA) followed by State Expert Appraisal Committee (SEAC-3).

ii. Location (Map showing general location, specific location and project boundary & project site layout) with coordinates

Proposed project site is located at plot no. E-5, of Talegaon MIDC Area. Site is located at Village Badhalwadi in Maval Taluka of . Site can be approached by Old Mumbai Pune Highway NH-4 by travelling distance of 11.5 km from and Mumbai- Pune junction.

Site surroundings: Site is located at Plot no. E-5 of Talegaon MIDC area. All the piece of land knows as Plot No. E-5 in the Talegaon Industrial Area Ph-II, within the village limits of Badhalwadi and outside the limits of Municipal Council, Taluka Maval, District Pune containing by admeasurements 237023 Sq. Mtrs of thereabouts and bounded as follows that is to say :

On or towards the north by - MIDC Road 75 Mtrs R/W and Open Space 21 On or towards the South by - Plot NO E-3/1 & MIDC Boundary On or towards the East by – Amenity No. 27 & Plot No. PAP D-231 On or towards the West by – MIDC Road 20 Mtr R/W

9 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

Site Location :

Jushi India Fiberglass Pvt. Ltd. Plot No. E-5, Village- Badhalwadi, Taluka.

Maval, District. Pune 412208

10 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

Site Specific Location

Jushi India Fiberglass Pvt. Ltd. Plot No. E-5, Village- Badhalwadi, Taluka. Maval, District. Pune-412208

11 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

Plot Boundary of Project Site

Site Coordinates

Point Latitude Longitude A 18047’36.55”N 73043’14.11”E B 18047’47.06”N 73043’23.86”E C 18047’42.53”N 73043’23.53”E D 18047’33.16”N 73043’34.22”E E 18047’36.55”N 73043’23.53”E F 18047’34.05”N 73043’26.23”E G 18047’33.55”N 73043’25.61”E H 18047’35.92”N 73043’11.40”E

12 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

Project Site Layout

Figure 1: Master Layout Plan of the Project Site (Attached as An Annexure-1)

Area Statement

Sr. No. Description Area (Sq.mt) 1 Area Of Plot 237023.00 2 REQUIRED OPEN SPACE 10% 23702.30 REQUIRED OPEN SPACE PROVIDED 23757.00 3 REQUIRED AMENITY 5% 11851.15 REQUIRED AMENITY PROVIDED 12109.20 4 NET PLOT AREA 213320.70 PERMISSIBLE FSI 1.50 5 Total permissible FSI -([4]*1 ) 213320.70 6 Proposed Buil tup area OF PHASE I, II & III 276515.29 7 Grand Total Built-up area (FSI Only) 276515.29 8 F.S.I. Consumed - [7] /[4] 1.30 9 Non FSI Area 7767.70 10 Total BUA (7+9) 284282.99 11 TOTAL Parking space required 10% of plot 23702.30

12 VISITOR PARKING 2370.23 13 TOTAL Parking space Provided 26216.66

13 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

Building Wise Area Statement

14 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC iii. Details of Alternative Sites Considered and the basis of selecting the proposed site, particularly the environmental considerations gone into should be highlighted

Before finalization of Talegaon sites three site were studied from Talegaon, Ranjangaon and Jhagadia region out of which Talegaon site was selected on the basis of their merits

Selection of site for the upcoming project for Jushi Fiberglass Pvt Ltd., was based on certain criteria which are listed below:

 Location of the plant (West/East/North/South)  Land price.  Market Place.  Geography and transportation of the plant location, the distance from major city and port.  Customer base.  Availability of the raw material.  Utilities (Energy/Water/Fuel/etc)  Labour (skills/cost/etc.)

Based on the above criteria following three sites were evaluated:

Sr.No. Description Talegaon Ranjangaon Jhagadia Remarks 1 Location of plant West west west Only western region was selected as mostly the western region is more industrialized. 2. Land Price & High price Moderate Price low Talegaon land price was Availability of land but MIDC price but but limited highest but had ample to launch limited land land choice for selection of Phase II available. availability. the land shape and size required for the process. 3. Market place Excellent Excellent Moderate Pune being an auto hub and the product is

15 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

mainly used in automobile spare parts, Pune Maharashtra preferred. 4. Geography and Connected Connected Connected Talagoan has two cities transportation of plant with two with Pune with connectivity, also the location (Distance major 50 KM and Ahmedabad port is quite close. from major city and cities Pune Mumbai city 250 KM ports and 200 KM Major Port Mumbai Mumbai Pipava port (within port 200 at a 120 KM KM distance of periphery) 300KM Mumbai port within 160 KM 5. Customer Bases 75% of the 75% of the 15 to 20% of Major customer base is customers customers the situated in are in and are in and customers Maharashtra. around around in and Mumbai Mumbai around and Pune and Pune. 6. Availability of raw Good Good Excellent Raw material material availability availability availability transportation in Talagaon is by way of road and rail 7 Utilities Excellent Good, gas Excellent Talagaon is having a (Energy/Water/Fuel) availability piped gas in MIDC is not phase II adequate

16 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

8 Labour Excellent Moderate Scarce Talegaon being near (Skill/Cost/availability) skill labour skilled skilled and around Pune and available labour labour Mumbai in huge available. availability. quantity though labour cost is higher

Conclusion:

After survey of the selected three location, we recommend Talegaon on the basis of the following merits:  Talegaon has better infrastructure than any other locations  Being a continuous process plant, which requires stable power source and adequate water, which is available in Maharashtra and specially in Talegaon having many large water bodies in and around Talegaon.  Skill labour for this process is a must as this process is not a run of the mill and requires a lot of skill and understanding to operate this process.

iv. Size or magnitude of operation

Jushi India Fiberglass Pvt. Ltd. is having total plot area 2,37,023.00 Sq.M. and total built up area will be 2,84,282.99 Sq.M. Industry is proposed to manufacture 220000 MT/Annum of Fiberglass. v. Project Description with process details

The production process of fiberglass mainly includes batching of mineral materials, glass melting, fiber forming, cake drying, roving, chopping, packaging etc

17 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

Schematic Diagram of Process Flow Chart

18 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

vi. Raw Material Requirement

Sr Amount Annual Consumption of Name of Raw No. (kg/1 ton finished Raw Material in Tonnes Material product) 1. Kaolin 488.2 107404 2. Silica sand 394 86680 3. Dolomite 45.1 9922 4. Limestone 449.6 98912 5. Gypsum 7.3 1606 6. Lithia mica 38 8360 7. TOTAL 1422.2 312884

vii. Water Requirement, its source and waste water management

Total water requirement will be 5023 m3/day . Required water will be supplied by MIDC. Waste water generation will be 1784 m3/day. Total effluent will be treated in ETP and connected to CETP for final treatment and disposal viii. Solid Waste Generation & Its Management

Non-Hazardous Waste

Sr.No. Type of Solid Waste Quantity Disposal 1 Wood/ Cardboards / 500 MT/M Sale to authorized vendor Paperboards / PP bag etc.

2 Metal Scrap 35 MT/M Sale to vendor

3 Waste/Scrap Glass 2700 MT/M Sale to third party

4 Plastic Drums 100 Nos./M Sale to authorized vendor

5 Refractory bricks 1 MT/M Sale to vendor

6 Other Solid Waste 125 MT/M Sale to third party

7 E-Waste 10 MT/M Sale to MPCB approved vendor

19 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

Hazardous Waste Sr. Name Waste Category as Quantity Disposal No. per HW&M Rules 2016 1 Used/spent oil spent 5.1 50 MT/A Sale to authorized vendor/ CHWTSDF 2 Wastes/residue containing 5.2 52 MT/A Sale to authorized oil vendor/ CHWTSDF 3 Discarded 33.3 5000 Sale to authorized containers/barrels/liners Nos./A vendor/ CHWTSDF 4 Used Lead Acid batteries 20 Nos./A Sale to authorized MPCB battery processor vendor 5 Refractory bricks/ 2 MT/A Sale to vendor/ Used Chrome blocks CHWTSDF 6 Chemical waste(Bad 35.3 180 MT/A Sale to vendor/ batch) CHWTSDF 7 ETP Sludge 35.3 243MT/M Send to CHWTSDF

20 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC ix. Schematic Representations of the feasibility drawing which give information of EIA purpose

21 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

4. SITE ANALYSIS

i. Connectivity

Selected project site is located in Talegaon MIDC area, hence MIDC is already developed 75 meter wide road for approach to the site. Site can be access through NH-4 Old Mumbai Pune highway which is 11 km away. Nashik Pune Highway NH-50 is 15.5 km away from site. East side of project site Chakan Industrial area is developed in which all tar roads are 60 meter wide. South side of project site Taleagon MIDC area, Talegaon Dhabade and Vadgaon is situated in which all tar roads are 45-60 meter wide. Lohgaon Pune airport is 32 km (aerial) away from site. Capital of Maharashtra i.e. Mumbai is 95 km (aerial) away. Jawaharlal Nehru Port at Panvel is 82 km away from site.

ii. Land Form, Land Use & Land ownership

Presently site is undeveloped. It is expansion of Talegaon MIDC area. Though site is located in MIDC area land use of site is industrial use. Jushi India Fiberglass Pvt. Ltd. has taken site on lease basis from MIDC.

iii. Topography (Along with the Map)

Presently land is undeveloped. Land is partly flat and mostly undulating. Land is having maximum elevation at 664 meter (MSL) in North direction and lowest elevation 647 meter (MSL) in south direction. Land is having slope North to South. (Annexure 2- Contour Plan of the Site)

iv. Existing Land use pattern

Land use of the site is declared as industrial use. Other industrial development activities are going on in surrounding areas. There will be no ecological sensitive area within 10 km from project site boundary. (Annexure 3- Topographical Survey of India Map)

22 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

v. Existing Infrastructure

Site is undeveloped. Required infrastructure such as roads, light & electricity will be provided by MIDC.

vi. Soil Classification

Soil texture at the project site and around observed as silty clay. pH of the soil is recorded 7.33 while sodium absorption ratio (SAR) is 4.40.The soil in the area is deficient in nitrogen content and potash & phosphorus content are found within the range of Ministry of Agricultural guidelines 2011.

Site is located in Seismic Zone- IV.

vii. Climatic Data from Secondary Sources

The regional surface meteorological data viz., temperature, relative humidity, wind speed and direction, station level pressure, rainfall etc. has been compiled from IMD Pune for Pune station (25 KM away from project site) for the period 1995-2004.

Analysis of the Data Recorded at IMD – Pune The Meteorological data of IMD Pune for the period of 1995 to 2004 is discussed below:

a) Temperature The winter season starts from December and continues till the end of February. During this season, monthly mean maximum temperature is found to be 32.30C occurring in the month of February whereas, monthly mean minimum temperature occurs in the month of December & January as 11.1oC. Both the day and night temperatures increase rapidly during the onset of Pre monsoon season from March to May.

23 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

During Pre monsoon the monthly mean maximum temperature found to be 37.8C in the month of April and monthly mean minimum temperature as 15.6C in the month of March. An appreciable drop in mean maximum temperature is recorded with the onset of monsoon. The monthly mean maximum temperature in monsoon season was observed to be 31.7C in the month of June, while monthly mean minimum temperature was observed to be as 20.9C in the month of September. By end of September with the onset of post monsoon season (October & November), day temperature rises slightly with the monthly mean maximum temperature was observed to be as 31.5C in October and the minimum temperature is observed as 14.5oC in November.

b) Relative Humidity During Pre-monsoon period, the monthly mean relative humidity was observed to be in the range of 48%-61% at 0830 hrs and at 1730 hrs it is observed in the range of 21%-39%. During the monsoon season, relative humidity ranges between 77%-86% at 0830 hrs and 66%-78% at 1730 hrs. In the post-monsoon season the range was observed to be between 78%-81% at 0830 hrs and at 1730 hrs the range of relative humidity occurred between 46%-56%.

During winter season the range of humidity was observed between 75%-87% at 0830 hrs and 27%-39% at 1730 hrs. It is observed from the data that the air is dry in pre monsoon and winter seasons while it is humid during monsoon and post monsoon seasons due to heavy rains in the region.

c) Station Level Pressure In winter season, the mean pressure observed at 0830 hrs was in the range of 951.5 to 953.4 hpa and at 1730 hrs, it is observed in the range of 947.7 to 949.7 hpa with the maximum in December. In monsoon season, the station level pressure was observed to be in the range of 942.9 to 947.3 hpa at 830 hrs and at 1730 hrs it is ranged between 941.6 to 944.5 hpa.

24 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

It can be seen from the data that not much variation is observed in the average atmospheric pressure levels. The pressure levels are found to be fairly constant over the region.

d) Rainfall The average annual rainfall observed based on the 10 years IMD data is 689.7 mm. About 80% of the rainfall is received during the southwest monsoon. Pre monsoon rains are also observed in the region. Our project area falls under medium rainfall zone, receiving average annual precipitation of 500 mm. The rainfall map of Pune district is shown in map below.

Figure 2: Climate Conditions of Pune District

a) Wind Speed/Direction

Generally light to moderate winds prevails throughout the year with slightly stronger winds in the early monsoon period. Winds are light and variable in the post-monsoon and winter seasons particularly during the morning hours, while during the afternoon hours the winds are slightly stronger. The wind pattern for the period of 1990-2003 is presented as windroses Figure 3.

25 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

It is observed from the data that the predominant wind direction in the region is west followed by northwest for most part of the year. The average wind speed in the region is observed to be in the range of 1.9 to 8.5 kmph.

Figure 3: Wind Rose for 0830 & 1730 Hrs: IMD – Pune (1990-2003)

26 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC viii. Social Infrastructure Available

Details of social infrastructure available from project site is presented below; Sr.no. Name of Social Infrastructure Distance from Site (aerial km) 1. Talegaon MIDC Police Station 5.5 2. Talegaon MIDC Fire Station 6.5 3. National Training Centre in Umbare 3.5 Navalakh 4. Indryani College 7.5 5. Siddhant College of Engineering, 5.5 Sadumbre 6. Sai Clinic, Mangarul 3.5 7. Indrayni Clinic 5.5 8. Harneshwar Hospital 8 9. Shivaji Theatre in Talegaon 11

5. PLANNING BRIEF

i. Planning Concept

After getting environmental clearance from state environment department construction will start on site. Proposed plant construction will be completed within 12-15 months of period. Project will be commissioned in April 2021.

ii. Population projection

During construction of the project approximately 200-250 nos. of workers will be required. For construction phase local contractor will appoint and they will manage labour force as per construction activity.

27 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

During operation of the project approximately 550-600 manpower would require. Manpower will recruit as per their educational qualifications. Mostly for workshop floor local technical diploma, B.COM, technical degree holder will prefer. High skilled manpower will be recruited as per their experience and knowledge. All manpower will commute to project site from nearby urban areas and Pune city. Hence there is no major population growth due to proposed project.

iii. Land use Planning

Sr. Description Area (Sq.mt) No. 1 Area Of Plot 237023.00

REQUIRED OPEN SPACE 2 23702.30 10% REQUIRED OPEN SPACE 23757.00 PROVIDED 3 REQUIRED AMENITY 5% 11851.15 REQUIRED AMENITY 12109.20 PROVIDED 4 NET PLOT AREA 213320.70 PERMISSIBLE FSI 1.50 5 Total permissible FSI -([4]*1 ) 213320.70 Proposed Buil tup area OF 6 276515.29 PHASE I, II & III Grand Total Built-up area 7 276515.29 (FSI Only)

8 F.S.I. Consumed - [7] /[4] 1.30 9 Non FSI Area 7767.70 10 Total BUA (7+9) 284282.99 TOTAL Parking space required 11 23702.30 10% of plot 12 VISITOR PARKING 2370.23 13 TOTAL Parking space Provided 26216.66 iv. Assessment of Infrastructure Demand Proposed site is located in MIDC area hence all required infrastructure such as roads, water & electricity will be provided by MIDC only.

28 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

v. Amenities/Facilities

Industry will develop amenities for their working manpower such as dormitory, canteen, garden and lounge area etc.

6. PROPOSED INFRASTRUCTURE

i. Industrial Area In the proposed project industrial will built up 2,84,282.99 Sq.M. [FSI-276515.29 Sq.M.+ Non FSI-7767.70 Sq.M.] of area.

ii. Residential Area Only dormitory will be provided for emergency staff, which critical for running continuous plant ( 10564.30 Sq.M.).

iii. Green Belt Industry will develop green area within plant premises.

iv. Social Infrastructure No any additional infrastructure proposed as project is located in Talegaon MIDC area.

v. Connectivity Site is well connected through Mumbai-Pune highway, Nashik-Pune highway and Chakan MIDC area hence there is no additional connectivity is required. Jawaharlal Nehru Port at Panvel is just 82 km away. Pune Railway Station is 38 km (aerial distance) from project site

vi. Drinking Water In operation phase domestic water demand is estimated 86 CMD and it will be supplied by MIDC.

29 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC vii. Sewerage System Industry will design separate sewerage & effluent network within plant premises. Generated sewage will collected in septic tank and septic tank overflow will mixed with industrial effluent which will be treated in ETP and send it to the CETP for final treatment and disposal. viii. Industrial Waste Management Total water requirement will be 5023 m3/day and waste water generation will be 1784 m3/day. Effluent treatment will be given within plant later on waste water connected to CETP for final treatment and disposal. Hazardous waste will be sent to the CHWTSDF, MEPL Ranjangaon and non-hazardous waste will be disposed-off through authorized vendor/ recycler/reprocessor.

ix. Solid Waste Management Non-Hazardous Waste

Sr. No. Type of Solid Waste Quantity Disposal 1 Wood/ Cardboards / 500 MT/M Sale to authorized vendor Paperboards / PP bag etc. 2 Metal Scrap 35 MT/M Sale to vendor 3 Waste/Scrap Glass 2700 MT/M Sale to third party 4 Plastic Drums 100 Nos./M Sale to authorized vendor 5 Refractory bricks 1 MT/M Sale to vendor 6 Other Solid Waste 125 MT/M Sale to third party 7 E-Waste 10 MT/M Sale to MPCB approved vendor

Hazardous Waste

Sr. Name Waste Category as per Quantity Disposal No. HW&M Rules 2016 1 Used/spent oil spent 5.1 50 MT/A Sale to authorized vendor/ CHWTSDF

30 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

2 Wastes/residue containing 5.2 52 MT/A Sale to authorized vendor/ oil CHWTSDF 3 Discarded 33.3 5000 Sale to authorized vendor/ containers/barrels/liners Nos./A CHWTSDF 4 Used Lead Acid batteries 20 Nos./A Sale to authorized MPCB battery processor vendor 5 Refractory bricks/ 2 MT/A Sale to vendor/ CHWTSDF Used Chrome blocks 6 Chemical waste(Bad 35.3 180 MT/A Sale to vendor/ CHWTSDF batch) 7 ETP Sludge 35.3 243MT/M Send to CHWTSDF

x. Power Requirement The total power requirement for proposed project would be 40 MVA and it will be supplied by MSEDCL. As back up power industry has proposed to installed 5 nos. of DG sets of 500 kW and alternative source of power as a Solar energy of 3000 kVA.

7. REHABILITATION AND RESETTLEMENT PLAN (R & R) As the site is located in declared Talegaon MIDC area hence there is no requirement of R&R plan.

8. PROJECT SCHEDULE & COST ESTIMATES

Construction of the project will complete within 12-15 months after getting environmental clearance from Maharashtra State Environment Department. As per planning construction of the project will start from April 2020 and commission of project will start from April 2021.

31 | P a g e

Prefeasibility Report for proposed Industrial Construction by Jushi India Fiberglass Pvt. Ltd, Talegaon MIDC

The total estimated cost of the project is Rs. 3,500.00 Cr which may increase or decrease during actual construction and commissioning of the project on the basis of book of accounts.

9. ANALYSIS OF PROPOSAL

India is developing country and under government programme Make In India it is the huge investment of foreign client in India. Market research analysis revels that there is short of Fiber Glass against demand. Fiber Glass is having good strength and durability hence it is being used in Automotive; Sports and Leisure; Consumer Goods and Business Equipment; Building and Construction; Chemistry and Chemical; Wind Energy; Electrical and Electronics; Marine; Infrastructure sector etc. Presently in India many development activities in the form of road construction, area development, bridge construction etc. are proposed and going on. Hence proposed Fiber Glass industry would be helpful in reduction in construction cost due to availability of material in local market. In addition to that proposed industry is planning to export Indian manufactured material in international market which earn revenue to Indian government in the form of taxes and duties. Proposed industry will generate 200-250 nos. of Jobs in construction phase and 550-600 nos. of direct employment in operation phase. Many other ancillary business such as grocery market, fruit & vegetable market, hotel, house rent, restaurant etc. will run on overall Talegaon MIDC development. The overall impact of the proposed project would be positive on Indian economy as well as regional development.

32 | P a g e

N STRUCTURES/ Building NOS & NAME STAMP OF APPROVAL 400 kV Transmission Line PH- 1 1/1 B1- 100,000 TONS/YEAR FIBERGLASS PRODUCTION WORKSHOP (PHASE- I) B2- QUARRY STORAGE YARD B3- BATCHING WORKSHOP 1 B4- BATCHING WORKSHOP 2 B5- PACKAGING MATERIALS WORKSHOP B6- TRANSFORMER SUBSTATION B7- ENTRANCE GUARD M I D C 75 M WIDE ROAD B8- GAS STATION 658.8 M I D C 75 M WIDE ROAD B9- OXYGEN STATION B10- EFFLUENT TREATMENT PLANT Nala inlet 1 GATE NO-1 B11- WATER SUPPLY STATION 2 NO.600MM DIA R.C.C. PIPE 1 NO.75MM DIA R.C.C. PIPE PIPE LINE 7.50 12.00 WATER LINE B12 - DORMITORY (PHASE 1) 297.1 3.00 F.F.L. 4.00 659.20 B13 - WASTE REPOSITORY Entrance guard 7.00 B7 ( PHASE I) B B14 - Exhaust Gas Treatment ( PH-I) P-04 12.00 PH-2 Area 254.07 ST-1 P-05 Area 692 400 kV Transmission Line B16 - DORMITORY (PHASE II)

12.0 12 M WIDE ROAD WITH 1:25:54 SLOPE 12 M WIDE ROAD WITH 1:25:54 SLOPE 12.0 Nala inlet 2 358.2 . B15- 100,000 TONS/YEAR FIBERGLASS

M G:\NSAA- ACER\1-NSAA- INDUSTRIAL\59-INGRAIN- ABHAY- JUSHI INDIA\01-APPROVAL DRAWINGS\SUB- WORKING- 1-07.11.19\1-Sub Dwg\LOCATION PLAN.JPG . PRODUCTION WORKSHOP (PHASE- II)

Q RWH P-03 Area 1592.50 RWH S 57.2 P-27 - 1192 SQM. B17- CHOPPED STRAND MAT WORKSHOP INDEX- PHASE I,PH-II & PH-III 9 12 M W I D E R O A D Nala inlet 3 1 7 12.0 0 M 12.0 2 5 P-16 3 . Sr. -

2

1 12 M W I D E R O A D B18- FIBERGLASS FABRIC PRODUCTION P

a Discription Area (Sq.mt)

Area 286 5.0 Area 110 e No. r ST-4 P-17 WORKSHOP

A RWH 8 12.0 P-21 B19 - Exhaust Gas Treatment ( PH-II) 1 1 Area Of Plot 237023.00 1 1

2 area 84 2 2 2 4 2

15.3 15.0 20.0 4 M 44.90M 9 PH-3

M . M 9 2 REQUIRED OPEN SPACE 10% 23702.30 30.24M a 2 1

M

e 3

1 W OXYGEN STATION W r

2

A W

RWH AM-02 REQUIRED OPEN SPACE PROVIDED 23757.00 B6 B20- 20,000 TONS/ YEAR High performance a W B8 RWH A

RWH a

e

e F.F.L. B9 ( PHASE I) I ( PHASE I) I r

r

Fiber glass Production Line work shop I a

3 REQUIRED AMENITY 5% 11851.15

654.48 a B11 ( PHASE I) D D

I 4.00

4 8 0

D P

GAS STATION

N

Waste repository 1 3 1 9 A D LOCATION PLAN

- 0

T

- B1 ( PHASE I) r 5

7 REQUIRED AMENITY PROVIDED 12109.20 E E ( PHASE I) 2 .

P

H

2 e

E P

0 0

W F.F.L. 1.00 - n Area 129 B13 18.00

E P-25

a m 1 3 R

A o R

r R P i

654.48 e 1 Y

2750 4 NET PLOT AREA 213320.70 t

100,000 TONS/YEAR FIBERGLASS PRODUCTION WORKSHOP(PHASE -I)

o r HWAY 8 PAT R

3 y f

a a l O

4.00 O t STORM WATER 4 STORM WATER O s

e

A INLET

. 45.00 OUTLET p a s F.F.L.

r Area 876

P-24 n

O

0 PERMISSIBLE FSI 1.50 p

e b

A

a A A r 2 0

654.48 u A u

6 r .

1 1 s 3

OP-5 A 16.5 A

5

T RWH 3 S

5

3

RWH n r RWH RWH

1 RWH 2

3 5 Total permissible FSI -([4]*1 ) 213320.70

15.0 .

D

D 0 4 1 o D e

2 i

Area 1390.16 a 1 - t

- a t D

e

2 22.0 a P a - e 2 1 P - r .

t 6 Proposed Builtup area OF PHASE I, II & III 276515.29 T

100.5 0

r 5 S W s A 5 a 3

.

0 M 1 Exhaust Gas 7 Grand Total Built-up area 276515.29 - 9.00M GATE PILLAR. 3

P W Treatment 2 BRUSHED STEEL 20.8 - 8 F.S.I. Consumed - [7] /[4] 1.30

PERFORATED SHEETS P Water Tower 50.0 SECTION A-A

RBW DEPTH 15.0M COMPANY I B14 RWH

5.0 RWH

P-19 1

TOTAL Parking space requirted 10% of plot 23702.30 D

Area 104.22 2 ST3 ( PHASE I)

AM-03

ARTIFICIAL GROUND WAT ER RECHARGE M

STRUCTURE MIDC SERVICE GREEN BELT VISITOR PARKING 2370.23

E 15 M W I D E R O A D

15.0

12 M W I D E R O A D

4.50 W 12 M W I D E R O A D 12.00 R TOTAL Parking space Provided 26216.66

50.3

O N

( PHASE II) I A

18.4 12.0 19.4

L

. D EQ. EQ.

A A RWH Exhaust Gas

A

0

D MIDC

12.00M 0 M

P 5.00 r

0

I

. STORM WATER

STORM WATER

5 e

Treatment

1 V

INLET 7 OUTLET E 1 0

D a 2 - R

Q B2 2

7

N 1 1 1

S 1

S

6 A A

A -

I M

a 2

R O 6

B L 136.0 B19 e RWH P 8

F.F.L. N A r

2750 2 B3 Raw material Storage Yard

6

D A O T

0 654.48 ( PHASE I) W

H I 4 48.8

-

V

(Quarry Storage Yard) R

8 R

Batching Workshop 1 A P

O S

P-10Area 566

U TYPICAL

I

I DETAILS FOR RBW DEPTH 15.0M O a

RWH F.F.L. G

N e

H

B15 D

D TYPICAL SECTION OF RAIN WATER HARVESTING PIT r M

654.48

T

2

R

H

8 M W I D E R O A D

A 0.75 M HIGH

Q

. .

C

R 75.7

2

86.0 ( PHASE I) E 4

.

S O C TYPICAL MS WELD MESH

9 0

U 100,000 TONS/YEAR FIBERGLASS PRODUCTION WORKSHOP ( PHASE II)

-

4 1 0.75

4 B

G 120.5 90.0

1 O .

3 H 10.0 R

X

2 3

8 F.F.L. 60.0

B4

R

C 0.23 M THICK

3 . O

M 12.00M

C U

654.48

. L R.C.C. COMPOUND WALL C

1.5 Batching Workshop 2 V a

E

A - W 24.0

e B

RWH R

r C O F.F.L.

T 35.0 GROUND LVL.

4.5 X ( PHASE I)

A D

654.48 N

C RAIN WATER HARVESTING

I

A U

L L 3

D

V A 50.0

- B20

E

D

P

R I

T V 260.0 E 9 M W I D E R O A D 48

O R 0 RWH E L E V A T I O N O F E N T R A N C E G A T E.

S R

0 I

. O

96.0 RWH

0 N

O A N D S E C T I O N O F C O M P O U N D W A L L.

2 18.0 20,000 TONS/YEAR T P-09

H 8

A

High-Performance R 21.0

Area 4889 82.0 O

97.0 TYPICAL

fiberglass production line U a

21 M W I D E R O A D 12.0

D G

Workshop (PHASE III) e r H

B17

R

B18 A

. C

F.F.L. . C RWH RWH RWH RWH RWH RWH RWH RWH

ST-SEPTIC TANK 8 Chopped Strand Mat Workshop(PHASE II) 654.48 - D Fiberglass Fabric B

0 O -

Production Workshop(PHASE II) X

F.F.L. 47.0 C P 654.48 F.F.L. U 12.0 L 52.0 V OWNER /PROJECT NAME

654.48 E

15.0 R

62.0 T RWH RWH RWH RWH

2 OP-1 -

O RWH Area 16141.00 SQ.M. M/S. JUSHI INDIA FIBERGLASS PVT.LTD

N RWH RWH 2.0 1 E 12.0

2 12 M W I D E R O A D 12 M W I D E R O A D RWH RWH RWH RWH RWH RWH RWH RWH 3 T 2 STAMP/SIGN. M

A ST-6 94.0 M RWH

G F.F.L. 2.0 B12 RWH 654.78 P

F.F.L.

W - W 6 164.0 13.2 ( PHASE I) 6 P 2

654.48 B10 1 M Dormitory (PHASE 1) 2

- . RWH

6 Defluorination 246.2 pool 2

M

0 0

W Effluent Treatment Plant

Nala Exit 2 7 I Q I

A

I

S

A Area 4548.34

D

D r D OP-4 7 -

e r 7

T B5 Aerobic pool 2 Anoxic pool 2 E TYPICAL 1 e a S Defluorination

2 pool 1 0

Area 1485 SQM Primary sink 2

a

R E 9

E

54.0 69.0 Nala Exit 3 2 O 1 66.7 Aerobic pool 1 Anoxic pool Up a 1 - Packaging Materials Workshop 9

6 e

A SEPTIC TANK PLAN P 7 r R 2 R

8 8

O A

RWH D F.F.L.

6.00

Regulation Accident 1 Primary O pool 654.48 O pool Sludge sink 1 tank MR. RAMACHANDRAN SAMBASIVAN 8 - AM-01

F.F.L. T

Up S

B16 A RWH 654.78 ( PHASE I) A DIRECTOR

SIGN & STAMP

Dormitory 3.0

( PHASE II) D D J U S H I RWH P-06 Area 1085 MASTER PLAN 7 . 01 12 M W I D E R O A D 0 9.7 9.2 12 M W I D E R O A D 4 PROJECT ADDRES 12.0 12.0

3.4 M/S. JUSHI INDIA FIBERGLASS PVT.LTD 415.5 Nala Exit 1

GROSS BUILT UP AREA STATEMENT E-5 TALEGAO MIDC, BADHLEWASTI, PH- 1 A B A+B Ground Second GROSS Building Ground Floor First Floor. Third Floor Fourth Floor fifth Floor Sixth Floor Total Area NON FSI AREA TALUKA- MAVAL, DIST- PUNE-412208, coverage Floor BUILT UP B1- 100,000 TONS/YEAR FIBERGLASS PRODUCTION 23552.88 33731.47 1845.18 29765.15 7903.68 4285.42 607.82 575.51 78714.23 1171.22 79885.45 MAHARASHTRA, INDIA WORKSHOP (PHASE- I) B2- QUARRY STORAGE YARD 15619.97 23429.95 ------23429.95 0.00 23429.95 B3- BATCHING WORKSHOP 1 1937.72 2791.88 814.90 448.10 254.08 - - 4308.96 235.12 4544.08 OPEN SPACE PROVIDED AMENITY SPACE PROVIDED PARKING SPACE PROVIDED B4- BATCHING WORKSHOP 2 1777.06 2574.53 646.85 - - - - - 3221.37 100.99 3322.36 LIASONING ARCHITECT B5- PACKAGING MATERIALS WORKSHOP 11409.36 20445.24 ------20445.24 0.00 20445.24 OPEN SPACE AMENITY SPACE PARKING SPACE B6- TRANSFORMER SUBSTATION 746.97 746.97 677.27 535.06 - - - - 1959.30 0.00 1959.30 NO SQ.M. NO SQ.M. NO SQ.M. B7- ENTRANCE GUARD 84.46 84.46 ------84.46 0.00 84.46 OP-1 16141 AM-1 6660 P-1 279 B8- GAS STATION 66.00 66.00 66.00 0.00 66.00 ------OP-2 907 AM-2 3120 P-2 8468 AR.NILESH SURYAWANSHI B9- OXYGEN STATION 4000.00 4000.00 4000.00 0.00 4000.00 ------OP-3 3834 AM-3 2329 P-3 1592 7236.29 150.41 7386.70 B10- EFFLUENT TREATMENT PLANT 2101.80 3021.03 4215.26 - - - - - OP-4 1485 P-4 254 2272.11 1129.14 3401.25 Reg. Architect B11- WATER SUPPLY STATION 2899.52 1770.38 501.73 - - - - - OP-5 1390 P-5 692 5288.62 778.29 6066.91 B12 - DORMITORY (PHASE 1) 2296.27 2077.61 769.36 807.27 796.01 796.01 42.36 - P-6 1085 B13 - WASTE REPOSITORY 787.84 1181.76 ------1181.76 0.00 1181.76 P-7 977 B14 - Exhaust Gas Treatment ( PH-I) 80 80 - - - - - 80.00 0.00 80.00 P-8 820 P-9 4889 PRINCIPAL ARCHITECT GRAND TOTAL 67359.846 96001.273 9470.54 31555.59 8953.77 5081.43 650.18 575.51 152288.29 3565.17 155853.46 P-10 566 P-11 170 PH-2 P-12 166 AR.ABHAY BHONSALE B16 - DORMITORY (PHASE II) 888.97 888.97 888.97 888.97 888.97 888.97 52.54 - 4497.39 0.00 4497.39 P-13 790 Reg.no: CA/2000/26678 B15- 100,000 TONS/YEAR FIBERGLASS P-14 228 23552.88 PRODUCTION WORKSHOP (PHASE- II) P-15 133 B17- CHOPPED STRAND MAT WORKSHOP 7408.65 53145.36 3868.76 30209.74 7934.87 3000.57 607.82 575.51 99342.62 1244.27 100586.89 P-16 286 P-17 110 B18- FIBERGLASS FABRIC PRODUCTION WORKSHOP 5862.39 P-18 232.44 B19 - Exhaust Gas Treatment ( PH-II) 80 80 - - - - - 80.00 0.00 80.00 P-19 104.22 P-20 119 5th Floor,ITTS House,Kala Ghoda,Fort ,Mumbai -400001. P-21 84 Website :www.ingrainarchitects.com , Board Line: +9122 66355760 GRAND TOTAL 54114.33 4757.73 31098.71 8823.84 3889.54 660.36 575.51 103920.01 1244.27 105164.28 P-22 302 P-23 45 PH-3 STAMP/SIGN. P-24 876 DWG. NO. 101 SR.NO. B-20 High performance Fiber glass Production Line 5760.00 7163.97 826.75 7275.90 4264.28 776.10 20306.99 2958.26 23265.25 P-25 129 Cad Ref. work shop P-26 1628 P-27 1192 GRAND TOTAL 7163.97 826.75 7275.90 4264.28 776.10 0.00 0.00 20306.99 2958.26 23265.25 TOTAL 23757 TOTAL 12109.2 TOTAL 26216.66 DATE 20.11.19 TOTAL AREA OF PHASE I, PHASE II, & PHASE 157279.57 15055.02 69930.19 22041.88 9747.07 1310.54 1151.02 276515.29 7767.70 284282.99 III REQUIRED 23702.2 REQUIRED 11851.1 REQUIRED 23702.2 AR.ABHAY BHONSALE ANNEXURE- II

N

M I D C 75 M W I D E R O A D

M I D C 75 M W I D E R O A D

D

A

O GPS-1

R

E

D I

W

M

G-1 0

2

C

G-12 D

I

M OWNER /PROJECT NAME M/S. JUSHI INDIA FIBERGLASS PVT.LTD G-13 G-11 STAMP/SIGN.

G-14

MR. RAMACHANDRAN SAMBASIVAN DIRECTOR J U S H I SIGN & STAMP PROJECT ADDRES M/S. JUSHI INDIA FIBERGLASS PVT.LTD

E-5 TALEGAO MIDC, BADHLEWASTI, G-15 TALUKA- MAVAL, DIST- PUNE-412208, MAHARASHTRA, INDIA

LIASONING ARCHITECT

AR.NILESH SURYAWANSHI Reg. Architect

ARCHITECT AR.ABHAY BHONSLE Reg.no: CA/2000/26678

5th Floor,ITTS House,Kala Ghoda,Fort ,Mumbai -400001. Website :www.ingrainarchitects.com , Board Line: +9122 66355760

DWG. NO. 101 SR.NO. STAMP/SIGN.

Cad Ref.

DATE 20.11.19 CONTOUR SITE LAYOUT PLAN 73°45'0"E Nandurbar

Amravati Nagpur Gondiya Dhule Jalgaon Bhandara Akola Wardha Buldana Nashik Washim Chandrapur Aurangabad Yavatmal Gadchiroli Jalna Hingoli ± Thane Parbhani 18°50'0"N 18°50'0"N Project Mumbai Ahmadnagar Nanded Location Bid Raigarh Pune Latur Osmanabad Satara Solapur Ratnagiri Sangli

Kolhapur Sindhudurg

Peth Wada !Manchar ! ! Kurvandi ! Ausari Bhivpuri Ambhu Ambegaon ! ! Tahasil ! Karjat (Raigarh) Chas Tahasil ! Malegaon !

Nethersole Dam Rajgurunagar (Khed) ! Khed ! Rajmachi Tahasil ! Takwa Karle ! Project Mawal ! !( Location Tahasil Shirur Lonavala Wadgaon Tahasil !Khandala! Bedsa ! Chakan ! Talegaon Dabhade ! Bhaja ! !( ! Haveli Sudhagad Tahasil Alandi Plot Boundary Tahasil ! Chinchwad Shirur ! Pimpri ! Tahasil Kolwan Mulshi ! Khadki ! Bhamburda! Tahasil ! Pune City Tahasil !

Toposheet No.

1. 47 F /09 2. 47 F /13

PROJECT Jushi Fiber Glass India Pvt Ltd

CLIENT TITLE Toposheet Map

05 Km. Radius from building environment Project Boundary 0 0.475 0.95 1.9 Km. Shalini Apartment, Flat No. 10, 2nd Floor, Plot No. 16, Aundh, Pune - 411007

18°45'0"N 73°45'0"E 18°45'0"N