<<

Bi-annual Environmental Monitoring Report

Loans 2561 and 2729-ARM July - December 2017

Armenia: North-South Road Corridor Investment Program, Tranches 1 and 2

Prepared by the “Transport Project Implementation Organization” State Non-Commercial Organization based on the monthly Environmental Monitoring Reports of the Project Management Consultant

This bi-annual environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal of other status of any territory or area.

Table of Contents Part I Introduction ...... 6 1. Construction Activities and Project Progress During Reporting Period ...... 7 1.1 Tranche 1, -Ararat M2 road section (PK 9+312-PK 28+900) and Yerevan- M1 road section (PK 18+370-PK 29+773): ...... 7 1.2 Tranche 2 Ashtarak-Talin M1 road (PK 29+600-PK 71+500): ...... 8 2. Environmental Safeguards Staffing...... 8 2.1 Environmental Safeguards Staff of TPIO ...... 9 2.2 The Environmental Safeguards Staff of the PMC/Engineer ...... 9 2.3 The Contractor’s Environmental Unit ...... 10 Part II Environmental Management ...... 11 3. Environmental Safeguards Program ...... 11 3.1 Compliance with National Safeguards ...... 11 3.2 Compliance with ADB Safeguards ...... 11 3.3 Contractor’s Compliance with the EMP ...... 12 3.4 Approvals of the Site-specific environmental management plans for Quarries, Borrow Pits, Blasting works, Excavated Material Dumping, Topsoil Stockpiling, Concrete Batching Plants and Historical monuments ...... 12 3.5 ADB Mission ...... 12 3.6 A post-construction environmental audit for the Tranche 1 Road Sections ...... 13 3.7 Trainings and awareness raising orientation ...... 13 3.8 Archaeological Works Program ...... 13 3.9 Grievance redress mechanism and Consultations ...... 14 3.10 Communication ...... 16 Part III Environmental Monitoring ...... 17 4. Monitoring ...... 17 4.1 Monitoring of the Compliance with EMPs in Tranche 2 (Ashtarak-Talin road Section)...... 17 4.2 Instrumented Measurements and Monitoring of Environmental Parameters of Air Quality, Noise and Vibration, Water Quality...... 18 4.3 PPMS Indicators ...... 18 4.4 Non-compliance Notices ...... 19 Conclusions and Recommendations ...... 19

ANNEXES

ANNEX A: The Status of Topsoil Stockpiling and Excavated Unsuitable Material Dump Sites in Tranche 2

ANNEX B: Summary Table on Status of Archaeological Excavations

ANNEX C: Non-Conformances Detected During Monitoring Visits in Reporting Period

ANNEX D: Status of Measurements on Dust, Noise, Water Quality And Vibration in Jul-Dec 2016

ANNEX E: Status of environmental permits and licenses

ANNEX F: Location of Monitoring points on Dust, Noise, Water Quality and Vibration

ANNEX G: Post-construction Environmental Audit Checklist

List of Abbreviations

ADB Asian Development Bank

CEMP Contractor’s Environmental Management Plan

EMP Environmental Management Plan

EIA Environmental Impact Assessment

IEE Initial Environmental Examination

IES International Environmental Specialist

NES National Environmental Specialist

MNP Ministry of Nature Protection

MOTCIT Ministry of Transport, Communication and Information Technologies

MoC Ministry of Culture

SEMP Site Specific Environmental Management Plan

TMP Traffic Management Plan

TPIO Transport Project Implementation Organization” SNCO

EMR Environmental Monitoring Report Part I Introduction

This Bi-annual Environmental Monitoring Report covers the time period from July to December of 2017.

The Report was prepared with close cooperation with Project PMC/Engineer, which is the joint venture of French “Safege” and Spanish “Eptisa” companies for T1 and T2. 1. The RA has selected the Bavra-Yerevan-Agarak route as the North-South Road Corridor to be rehabilitated, reconstructed and expanded and has appointed the “North-South road Corridor Investment Program PIU” SNCO of the Ministry of Transport, Communication and Information Technologies (MOTCIT) to co-ordinate the work. The “North-South Road Corridor Investment Program Implementation Unit” SNCO and “Transport Projects Implementation Unit” State Institution were united and “Transport Project Implementation Organization” SNCO (TPIO) was established. The Program is funded by the Asian Development Bank (ADB) under a multi-tranche funding facility (MFF).

2. The MFF is designed to rehabilitate and upgrade national north-south roads to form a new, upgraded and expanded North-South highway. The main objective is to widen the existing 2-lane roads to become 4-lane divided roads along existing alignments wherever possible or to construct new alternate 2-lane roads where a single 4-lane road would not be feasible.

3. Tranche 1 Project is to improve two road sections of the North-South Corridor, namely, the M-1 section of road north from Yerevan to Ashtarak from km 18+370 to km 29+773 (Section 3 in the contract with Contractor) and the M-2 section of road south from Yerevan to Ararat from km 9+312 to km 47+400 (Section 2 in the contract with Contractor).

4. The Tranche 2 Project starts at km 29+600 in Ashtarak and end at km 71+500 close to Talin (Section 1 in the contract with Contractor). Two bypasses will be constructed in Agarak starting at km 29+934 to km 32+600, and in from km 36+600 to km 40+300. The Project will also have a new road alignment (8.95 kilometres) at Katnagbyur starting from km 59+950 to km 68+900 that will be located on the left side of the existing highway to join the existing alignment in Talin.

Figure 1. Tranche1 and Tranche2 of North-South Road Corridor

1. Construction Activities and Project Progress During Reporting Period

1.1 Tranche 1, Yerevan-Ararat M2 road section (PK 9+312-PK 28+900) and Yerevan-Ashtarak M1 road section (PK 18+370-PK 29+773): The Defects Liability Period has expired at the end of October, 2017.

During the Defects Liability Period the following construction works were implemented by “Corsan Corviam Construction” S.A. Armenian Branch: repairing of concrete pavement, repairing of cracks through injections, replacement of sealant on concrete pavement.

Safety/security measures: the construction works through this period include installation of traffic regulating signs/signals and maintenance of road. 1.2 Tranche 2 Ashtarak-Talin M1 road (PK 29+600-PK 71+500): Construction works were implemented by “Corsan Corviam Construction” S.A. Armenian Branch and its subcontractors AAB LLC, Aparag LLC, Betonica LLC, Dental Import LLC, Hydroenergetica LLC, Kamurjshin LLC, Feroinsa LLC, Miranda LLC, Bekor LLC and Mostovik LLC.

The following construction activities were implemented: clearing and grubbing, embankment, excavation, asphalt demolition, preparation of subgrade, sub base and base, reconstruction of Talin diversion, Installation of precast pieces, building of concrete wings, formwork placement wings, preparation of wings foundation, construction of drainage, concrete pavement and road maintenance works on Ashtarak-Talin M1 road section (PK 29+600-PK 71+500).

During the reporting period, no excavated material was removed to the dumping sites. All excavated materials were used for construction purposes. Removed asphalt was transported to Kaqavadzor-1 excavated dumping site area for temporarily stockpiling and further using for construction purposes. Removed topsoil materials were transported to the Aghdzk-2 and Kosh-4 topsoil stockpiling areas. Warning signs are installed near the dumping sites and top soil stockpiling places.

Safety/security measures: the construction works through this period include installation of concrete blocks and traffic regulating signs/signals and maintenance of road.

2. Environmental Safeguards Staffing

Transport Project Implementation Organization is implementing day-to-day management of project execution. The TPIO includes an Environmental Safeguards staff whose responsibilities include the management of all environmental aspects of the project.

The PMC/Engineer is providing Technical Assistance to the TPIO in the management and reporting of the project. Environmental Safeguards staff of the PMC/Engineer is responsible for supervising the construction works in relation to environmental and archaeological impact and, in particular, for supervising and reporting on the Contractor’s performance in the implementation of the EMP.

Contractor is implementing construction works. Contractor’s Environmental Unit is responsible for preparation and implementation CEMP and SEMPs, monitoring of the construction activities and reporting.

Monitoring Reporting

2.1 Environmental Safeguards Staff of TPIO 2.1.1 The Project Environmental Impact Management activities are undertaken by Head of Environmental Impact Management Service and Environmental Specialist:

Mr. Gevorg Afyan - Head of Environmental Impact Management Service is responsible for Environmental management of the project and compliance with the national environmental legislation of the RA and safeguard policies of financing Donors during the preparation and implementation of the Projects, including design, construction and supervision.

Mr. Mikael Tevosyan - Environmental and Archaeological Specialist is responsible for the compliance of the projects to safeguard policies of financing Donors and RA legislation.

2.2 The Environmental Safeguards Staff of the PMC/Engineer Presently the Environmental Safeguards Staff of the PMC/Engineer consists of:

Ms. Edita Vardgesyan, the National Environmental Specialist (NES), is responsible for the overall management of the environmental/ health & safety safeguards. She is employed on a contractual basis. NES was not involved in July and August due to vacation leave. During the reporting period her inputs were: 5 days in September, 4 days in October, 3 days in November and 3 days in December.

Mr. Boris Gasparyan, the National Archaeology Expert (NAE), is responsible for the consultancy on archaeological issues, supervision of archaeological excavations in Tranche 2, compliance of the construction activities to the related Armenian archaeological legislation and evaluation visits to the borrow pit, dumping and concrete plant sites with archaeological evaluation purposes. During the reporting period NAE inputs were 4 days in November.

Mr. Charles Adamson, the International Environmental Specialist (IES), is responsible for the provision of consultation on international best practices on environmental safeguards. During the reporting period his inputs were 15 days in October.

Mr. Karen Araqelyan, Road and H&S Specialist, is responsible for supervision and monitoring of the compliance of construction activities to health & safety requirements set in EIA and EMPs. He is a full time employee.

2.3 The Contractor’s Environmental Unit

The Contractor’s Environmental Unit is staffed by four people:

Mr. Gonzalo Gascon Ramos, the Quality and Environmental Manager, is responsible for the overall management of the Environmental Unit;

Mr. Viktor Bakhtamyan, the Environmental Consultant, to assist the Quality and Environmental Manager on the environmental management plan implementation;

Mr. Sos Amirkhanyan, the Social Relation Specialist, is responsible for the compliance of the Contractor’s activities to social part of the ADB Safeguard Policy Statement;

Mrs. Patricia Ortega Gonzalez, Health and Safety Manager, is responsible for the compliance of the Contractor’s activities to health and safety part of the ADB Safeguard Policy Statement.

Part II Environmental Management

3. Environmental Safeguards Program

3.1 Compliance with National Safeguards 3.1.1 In order to comply with national safeguard system and legislation, Contractor has obtained necessary permits and licenses for construction activities the list of which is presented in Annex E.

3.1.2 In the reporting period it was managed that construction complies with all national pertinent environmental laws and regulations.

3.1.3 As an environmentally active agent Contractor regularly provides the quarterly and annual environmental reports to MNP in accordance with Armenian legislation. The quarterly report for 2nd and 3rd quarters, 2017 are being submitted by Contractor during the reporting period.

3.1.4 Topsoil stockpiling operations are being implemented in accordance with applicable Armenian legislation and regulations, particularly RA Land Code (2001), RA Government Decision No.1396-N (2011) and RA Government Decision No.1404-N (2017).

3.1.5 The thresholds for monitoring of environmental parameters of dust, water, noise and vibration are set in accordance with standards and norms set by Armenian legislation as well as by EIA’s baseline data and IFC/WB standards where applicable.

3.1.6 Contractor ensures all necessary communication with local self-governmental bodies (communities) and regional administrative authorities (marzes) to comply with Armenian legislation during construction and obtains permits and approvals for any use of territory and roads for transportation, waste dumping, and material borrowing.

3.2 Compliance with ADB Safeguards 3.2.1 In order to ensure the environmental performance, it was supervised that the implementation of construction activities meets EMP requirements which is prepared in accordance with ADB Environmental Policy and RA legislation.

3.2.2 Prior to operating any site for topsoil stockpiling and excavated material disposal in Ashtarak- Talin M1 Road Tranche 2, the Site-specific Environmental Management Plan containing the identification of site-specific environmental impacts, risk assessment and mitigation measures is being prepared by Contractor guided with the Environmental Safeguards Information kit prepared by ADB Central & West Asia Department Safeguards Unit. The TPIO adopted and requests the PMC/Engineer and Contractor to pursue following procedures:: (i) Contractor selects the site for topsoil stockpiling or dumping of excavated material; (ii) PMC/Engineers’ NES and NAE visit the site and provide Contractor with site evaluation report with identified sensitive receptors and recommendations on the site use; (iii) Contractor secures the site and prepares SEMP based on the findings of evaluation report and submits for PMC/Engineer’s approval; (iv) The NES reviews the SEMP and issues an approval; (v) Then Contractor is permitted to start the site operation.

3.2.3 As category “A” project, ADB continues to conduct review missions at least every 6 months to check compliance of “North-South Road Corridor Investment Program” activities to ADB SPS (2009) requirements. ADB mission conducted loan reviews in North-South road corridor investment program, Tranche 2 during their sites visits in July, 2017. To monitor the ongoing situation joint visit was organized by the environmental specialists of the TPIO with the International Environmental specialist and National Environmental Consultant of ADB on 10 July 2017. Environmental compliance was reviewed during the visits.

3.3 Contractor’s Compliance with the EMP 3.3.1 Contractor is guided by the EIA and EMP for Tranche 2 as a part of the Bid and Contract documents, Site-specific Environmental Management plans, as well as by the Contractor’s Environmental Management Plan prepared by the contractor that detail on site environmental management requirements implementation and management, particularly construction impacts mitigation, monitoring and reporting requirements in order to ensure the environmental performance. Compliance with EMP is being regularly monitored and reported (see Part III Environmental Monitoring).

3.3.2 Pre-construction public hearings have been implemented by Contractor in communities impacted by the Project to meet the ADB SPS (2009) requirements on information disclosure and public participation.

3.4 Approvals of the Site-specific environmental management plans for Quarries, Borrow Pits, Blasting works, Excavated Material Dumping, Topsoil Stockpiling, Concrete Batching Plants and Historical monuments 3.4.1 The SEMPs for the following sites have been approved during the reporting period: Kosh-4 TSS (topsoil stockpiling site in Kosh community at km 40+800) and Aghtsk-2 TSS (for topsoil stockpiling in Aghtsk community at km 36+000). During the reporting period all generated topsoil was temporarily stockpiled at Talin-1, Talin-3, Kosh-4 and Aghtsk-2 topsoil sites.

3.4.2 There was no disposal of excavated materials during the reporting period. All the limited amount of excavated earth material has been re-used for construction purposes. Contractor is buying material form the existing quarries and didn’t open any new borrow pits.

3.4.3 The SEMPs for blasting works at km 48+140-49+600, 59+280-59+380, 64+350-64+480, 64+720-64+780 and 70+080-70+770 were approved by Engineer.

3.4.4 Detailed information on SEMPs for topsoil stockpiling and excavated material disposal is provided in monthly progress reports. No one site is declared by Contractor as closed. Status of topsoil stockpiling sites and excavated material dump sites, and the SEMPs for their operation as of 31 December 2017 are presented in Annex A.

3.5 ADB Mission 3.5.1 To check compliance of the Program activities to the ADB SPS (2009) requirements an ADB audit missions took place in July, October and November, 2017. Site visits were held to monitor on- going civil works in construction sites, Kaqavadzor concrete plant area, topsoil stockpiling sites and excavated material dumping sites. The environmental specialists of the TPIO, PMC/Engineer and Contractor with the National Environmental Consultant and International Environmental Specialist of ADB were participated and discussed the possible environmental, Health and Safety Issues. The International Environmental Specialist of ADB participated in visits in July and November. 3.6 A post-construction environmental audit for the Tranche 1 Road Sections 3.6.1 In addition to the previous post-construction environmental audits for the Tranche 1 Road Sections that took place in 2016, another post-construction environmental audit had been implemented in October, 2017. Environmental specialists of the Employer, PMC/Engineer and Contractor as well as IES of PMC/Engineer participated in the audit. The audit showed that construction works implemented during Defects Liability Period were appropriate and satisfactory in terms of all prescribed conditions in EMP to avoid or minimize environmental negative impacts in Yerevan-Ararat and Yerevan-Ashtarak road sections. Because the road maintenance was not anymore responsibility of the Contractor, the audit is considered the final one. The completed checklist is attached in Annex F.

3.7 Trainings and awareness raising orientation 3.7.1 On October 05, 2017 Environmental Staff of the Contractor with NES of the PMC/Engineer organized and implemented Environmental, Health and Safety training course for the workers of “AAB” LLC, “Aparag” LLC, “Betonica” LLC, “Dental Import” LLC, “Hydroenergetica” LLC, “Kamurjshin” LLC, “Feroinsa” LLC, “Mirada” LLC, “Bekor” LLC and “Mostovik” LLC subcontractors and “Corsan Corviam Construction” S.A. During the different courses, constructions workers were informed about possible negative environmental impacts and its mitigation and prevention measures as well as health and Safety requirements for the workers and machinery on site, preventive measures during the earth works, structural works, concrete and precast plant, general measures to keep on site and HS documentation. 51 participants attended the training.

3.7.2 Archaeological chance finds training for the Contractor’s and sub-contractor’s staffs was held on November, 2017. More detailed information is in Contractor’s monthly progress report of November, 2017.

3.8 Archaeological Works Program 3.8.1 All archaeological excavations planned according to Archaeological Work Plan were completed. During the implementation of construction works in the reporting period no archaeological chance finds or artefacts have been found.

3.8.2 In order to avoid large archaeological excavations and save the ancient settlements from destruction a new alignment is proposed to bypass archaeological structures discovered during archaeological excavation by the Contractor in Agarak Historical-Cultural Preserve. Although the new alignment will pass through the Agarak Historical-Cultural Preserve, the preliminary survey done by archaeologists of Institute of Archaeology and Ethnography SNCO NAS RA showed that its impact will be minor. The design work is planned to be done in 2018.

3.8.3 First stage of assessment of the vibration impact caused by operating vibration roller on the Caravanatun in (at Km 50+800) was implemented by the sub-contractor “Georisk” in August, 2017. The risk analysis and report identifies the sites beginning from which operation of vibration roller would not be allowable or would be dangerous in terms of the impact it may have on Caravanatun. Therefore, during construction works, the vibration roller will be used considering the critical points. The PMC will propose another compacted method to be used close to the critical points which shall be assessed by the Georisk. 3.8.4 Status of archaeological excavations as of 31 December 2017 is presented in the Annex B.

3.9 Grievance redress mechanism and Consultations 3.9.1 Grievance redress mechanism to address the complaints/suggestions of communities on excessive dust, noise, improper waste dumping and on other environmental issues is established which is described in Tranche 2 Environmental Impact Assessment. The grievance redress mechanism is additional to the existing channels of petitions in the form of letters and personal pleas established by local governments.

The Grievance Procedure and Redress Mechanism steps are shown graphically in figure 2.

Figure 2. Grievance Procedure and Redress Mechanism

3.9.2 Contractor provided the Complaints Register book to every impacted community which is kept at the office of head of the community and is open accessed to community members. Also the posters posted in every community containing the contact information where to apply should any disturbances occur. Mr. Sos Amirkhanyan, the Contractor’s Social Relation Specialist, is responsible for collecting concerns about project activity. His telephone number, email address, and name are posted on the posters. No complains and/or suggestions on environmental issues are registered as of today.

3.9.3 During the reporting period the pre-construction public awareness raising meetings were organized in Ujan community on 6 September, 2017, in Aghtsk community on 8 September, 2017, and in Agarak community on 22 September 2017. The civil works and their environmental/ health & safety aspects, as well as the grievance redress mechanism were presented to the public. Complaints Register logs were handed to selected responsible persons of the communities and special information posters about construction with contact information posted in every community. It was emphasized that impact shall be temporary. Detailed data on the issues raised during the public meetings are presented in the Contractor’s Monthly Social Report for September, 2017. Proper functioning of the grievance redress mechanism in all communities is regularly checked by the Contractor and reported.

3.9.4 The Contractor has permanent communication with contact persons of 32 communities: Ashtarak, Nerkin Sasnashen, Verin Sasnashen, , Katnaghbyur, , Talin, , Kakavadzor, Shamiram, Aruch, Kosh, Ujan, Aghdzk, Agarak and communities ( marz), and communities ( marz). Various phone conversations and meetings were held with the contact persons and community members. The heads of communities have been informed prior the start of the blasting works in order to ensure safety of the public through member of council and advertisement.

3.9.5 No complaints or suggestions concerning environmental issues such as dust, noise, vibration, tree cutting and any other environmental issues were raised by any of the communities during the reporting period.

3.10 Communication Communication with PIU, PMC and Contractor’s environmental team during the reporting period took place via official correspondence and emails, phone calls and personal contacts. Particularly the following issues are being raised and processed:

- ADB’s mission visit; - necessity to update the CEMP; - necessity to update the outline of Contractor’s weekly and monthly reports; - data on stripped topsoil quantities; - trees that need to be removed from the RoW during the construction process; - scheduling of a visit of the PMC/Engineer’s IES, and determining the scope of tasks for the IES, - re-arrangement of the input time for NES for the next quarter. - update the Instrumental measurement plan on dust, noise, water and vibration - the progress in development of SEMPs; - the compliance of Contractor's activities in Tranche 2 to the SEMPs; - the instrumental measurements on dust, noise and vibration; - the findings of the monitoring visits and the progress of their correction; - other routine issues.

Part III Environmental Monitoring

4. Monitoring

During the reporting period monitoring activities were carried out according to the Monitoring program developed based on the ADB safeguards and EMP requirements. The TPIO/ PMC Monitoring program includes:

a. Regular monitoring site visits on monthly basis to check compliance of construction activities in the Tranche 2 to the EMP requirements, as well as monitoring of topsoil stockpiling and excavated material disposal; b. Unscheduled inspection visits when needed; c. Instrumented measurements and monitoring of environmental parameters of air quality, noise and vibration, water quality in road Tranche 2; d. Completion of the monitoring checklist and summary of compliances and non-compliances; e. Issue the non-compliance notices to the Contractor; f. Collection of monitoring data and providing to the PPMS g. Review of the Contractor’s weekly monitoring reports.

Two definitions are used to describe issues that have occurred and needs to be addressed: (i) Non-conformances are issues that are registered in checklists during monitoring visits and provided to the Contractor for corrective action. In this case issues are not relatively insignificant or corrective action shall be quickly completed. (ii) Non-compliances are major issues or repeated non-conformances that Engineer requests corrective action through official letter.

4.1 Monitoring of the Compliance with EMPs in Tranche 2 (Ashtarak-Talin road Section). Regular monitoring visits have been implemented. The regular monitoring were carried out by Contractor’s environmental specialist on a weekly basis and by the PMC/Engineer’s environmental specialist on a monthly basis.

To demonstrate deviations from accepted practices for protection of environment two terms are used in the report. Non-conformance is a detected issue that can be solved immediately or is not significant. Non-compliance is a detected issue that cannot be solved immediately, is significant or repeated periodically. In case of non-compliances, the non-compliance official letter is issued to the Contractor and works are stopped in an affected section until an issue is solved. In case of non- conformances, the non-conformances are reported to the contractor through monthly monitoring checklist with determined deadline when an issue should be solved.

4.1.1 The detected non-conformances are:

- the practice of unpermitted use of territories for parking of machinery in the non-permitted area outside the RoW, - trucks loaded with excavated material were non-covered while entering public roads, - the ERP posters were missing. - establishment of crushing machinery in area not approved by PMC/Engineer; - new hired workers not trained on environmental safeguards; - the dust and mud spreading preventative measures, like gravel layer at the accesses to the existing roads are not implemented; - Watering of construction sites during construction works were not implemented properly; - deviation from SEMPs while operating the Kosh-4 and Aghtsk-2 topsoil sites; - non- permitted discharge of concrete waste water.

4.2 Instrumented Measurements and Monitoring of Environmental Parameters of Air Quality, Noise and Vibration, Water Quality. 4.2.1 Instrumented measurements and monitoring of environmental parameters of air quality; noise and vibration have been implemented by the Contractor through the licensed subcontractor: ATMS Solutions LLC.

4.2.2 Baseline data collection. Contractor has completed the baseline data collection for dust, noise and vibration in 2014.

4.2.3 Routine instrumented measurements and monitoring are carried out on monthly basis unless construction works are not implemented in the areas where instrumental monitoring are envisaged and in case when cold weather condition effects on measurements.

4.2.4 Instrumented measurements and monitoring of environmental parameters (dust, noise, water and vibration) during the reporting period has been implemented at the following points: Vibration 1 (PK 50+700), Dust 5 (PK 38+500), Dust 9 (PK 50+800), Dust 10 (PK 63+200), Dust 12 (PK 69+800), Noise 4 (PK 38+370), Noise 8 (PK 50+900) and Noise 9 (PK 70+000). The measurement points are selected based on going construction works criteria.

4.2.5 According to the monitoring reports Noise Equivalent Level and Noise Maximum Level values were above the Threshold Limit Values (TLV) set by Sanitary norms but almost equal to the baseline level or below it. The main noise sources at all noise measurement points are operation of construction equipment and movement of cars and vehicles along the M1 highway. The dust actual concentrations in all measurement points in different daytime periods don’t exceed the daily average and maximum permissible concentrations. The vibration meter didn't register any vibration acceleration in the point Vibration 1 for three orthogonal axes (x,y,z) and the daily vibration exposure values are equal to 0.

4.2.6 Detailed information on the results of operational monitoring is presented in the Noise and Dust Assessment Reports available in “Corsan Corviam Construction” S.A. and PMC offices (see extract from reports in Annex D).

4.3 PPMS Indicators 4.3.1 During the reporting period the following environmental performance indicators were reported to be included into PPMS:

4.3.2 Quarterly numbers of environmental non-compliance notices from PMC/Engineer to Contractor were regularly measured based on standards for storm water, noise, dust and vibration and on any breaches of the EIA and EMP by PMC/Engineer or by Contractor under PMC’s control: 0 non-compliance notices. No unsolved notices are registered by the end of reporting period.

4.3.3 Quarterly numbers of environmental complaints from communities along the Ashtarak-Talin road section, from 2013 to 2017 based on Contractor’s records of complaints were verified by PMC/Engineer: 0 - no environmentally related complaints are received and registered during reporting period.

4.4 Non-compliance Notices 4.4.1 No non-compliance notices have been issued to the Contractor during the reporting period.

4.4.2 During reporting period no contamination on soil, water resources and disturbance of flora and fauna has been observed during the implementation of construction works.

4.4.3 Health support on the sites is continuously provided. No accidents were recorded within reporting period.

Conclusions and Recommendations

4.4.4 During the reporting period the program has ensured the compliance of Project activities to the national legislation such as Contractor’s regular environmental reports submitted to RA MNP in accordance with Armenian legislation: 2nd and 3rd quarters, 2017; all necessary communication with local (communities) and territorial administrative authorities (marzes) took place, as well as permits and approvals obtained for any use of territories and roads otside of RoW (3.1.1- 3.1.6).

4.4.5 Also the compliance with the requirements of ADB environmental safeguard was ensured such as Contractor’s environmental management plans, approval of Site-specific Environmental Management Plans containing the identification of site-specific environmental impacts, risk assessment and mitigation measures by the Project in pursuance of ADB SPS (2009) requirements on information disclosure and public participation, ADB conducted review missions to check compliance of the Program activities (3.2.1-3.3.2).

4.4.6 The SEMPs for the Kosh-4 TSS (topsoil stockpiling site in Kosh community at km 40+800) and Aghtsk-2 TSS (for topsoil stockpiling in Aghtsk community at km 36+000) have been approved during the reporting period. Аll generated topsoil was temporarily stockpiled at Talin-1, Talin-3, Kosh- 4 and Aghtsk-2 topsoil sites. There were no disposed excavated materials during the reporting period. The SEMPs for blasting works at km 48+140-49+600, 59+280-59+380, 64+350-64+480, 64+720- 64+780 and 70+080-70+770 were approved by Engineer. Contractor is buying material form the existing quarries and didn’t open any new borrow pit (3.4.1-3.4.8).

4.4.7 Environmental safeguard reviews were conducted within ADB audit missions. All recommendations were taken into account. Post-construction environmental final audit had been implemented in October, 2017 (3.5.1-3.6.1). 4.4.8 Environmental and Health and Safety training course had been held for the workers of “AAB” LLC, “Aparag” LLC, “Betonica” LLC, “Dental Import” LLC, “Hydroenergetica” LLC, “Kamurjshin” LLC, “Feroinsa” LLC, “Mirada” LLC, “Bekor” LLC and “Mostovik” LLC subcontractors and “Corsan Corviam Construction” S.A on October 05, 2017. Archaeological chance finds training for the Contractor’s and sub-contractor’s staffs was held on November, 2017 (3.7.1 – 3.7.2).

4.4.9 No construction works have been implemented in proximity to archaeologically sensitive areas. During the implementation of construction works in the reporting period no archaeological chance finds or artefacts have been found. A new alignment is proposed to bypass archaeological structures discovered during archaeological excavation by the Contractor in Agarak Historical- Cultural Preserve. The design work is planned to be done in 2018. First stage of assessment of the vibration impact caused by operating vibration roller on the Caravanatun in Aruch (at Km 50+800) was implemented by the sub-contractor “Georisk” in August, 2017. (3.8.1- 3.8.4).

4.4.10 Grievance redress mechanism has been established in all communities where construction works have been implemented. Preconstruction public consultation and other regular communication with impacted communities took place and the proper functioning of grievance redress mechanism in all communities regularly checked. No complaints and/or suggestions on environmental related issues such as excessive dust, noise, improper waste dumping, etc. are registered by the end of reporting period (3.9.1-3.9.5).

4.4.11 Project related issues were regularly communicated with the environmental specialists of TPIO and Engineer, as well as Contractor’s management and environmental team (3.10).

4.4.12 Monitoring activities implemented during the reporting period included monitoring site visits on monthly basis to check compliance of civil works to the Contractor’s EMPs in Tranche 2. In a monthly basis instrumented measurement of the dust, noise, water and vibration have been implemented in those measurement points close to which construction works were implemented. No non-compliance notices have been issued to the Contractor during the reporting period (4.1.1-4.4.2).

Action plan for the reporting period from January to June 2018: N Action Time frame Responsible 1. Consultancy provided to Contractor’s Every month during PMC environmental team on ADB Safeguard January-June 2018 Policy Statement 2. Consultancy provided to Contractor’s Every month during PMC environmental team on the Armenian January-June 2018 Environmental legislation requirements 3. Evaluation site visits and assistance to the Upon Contractor’s TPIO/PMC Contractor in the development of Site- request specific Environmental Management Plans for topsoil stockpiling and excavated material dump sites in Tranche 2 and other routine working documents. 4. Preparation and approval of Site-specific Upon the need TPIO/PMC/ Environmental Management Plans for topsoil Contractor stockpiling, excavated material dump sites and sections of blasting operations 5. Placement of signboards with project Upon new road PMC/ information and safety warning signs along section construction Contractor the road sections, all disposal sites and will be commenced, topsoil stockpiling areas. and new disposal site and topsoil stockpile will be established 6. Regular awareness orientation sessions for Upon the need PMC/ newly recruited staff Contractor 7. Redesign of the road realignment close to January-June 2018 TPIO Agarak archeological site 8. Update of the EIA January-June 2018 TPIO/ PMC 9. Review the outputs of the construction Every month during PMC monitoring program with regard to January-June 2018 measurement of dust, noise, water quality and vibration. 10. Monitor the Contractor’s construction works By the end of every TPIO/PMC to ensure the compliance with EMP, CEMP month and SEMP requirements 11. Collect and provide the relevant information By the end of March TPIO/PMC on environmental indicators to PPMS and end of June 2018 12. Preparation of the Tree Planting BY the end of Contractor Management plan and method statement for February 2018 maintenance 13. Implementation of chance find procedure in Upon the need TPIO/PMC/ case of discovery archaeological artifacts Contractor during construction 14. Review and addressing the GRM End of every month TPIO/PMC 15. Other routine issues like unscheduled site Upon the need TPIO/PMC visits, follow up of the detected defects, environmental assessment of re-designs, management of tree cutting, review and approval of Contractor’s documents, etc. 16. Reporting on environmental safeguards Monthly TPIO/PMC Bi-annual

ANNEX A. The Status of Topsoil Stockpiling and Excavated Unsuitable Material Dump Sites in Tranche 2

No Name of site SEMP approved (Y/N) Status of operation Topsoil temporary stockpiling sites 1. Katnaghbyur- 1 Yes Operated 2. Katnaghbyur-2 Yes Operated 3. Yeghnik 1 Yes Operated 4. Yeghnik 2 Yes Non operated 5. Talin-1 Yes Operated 6. Nerkin Bazmaberd-1 Yes Operated 7. Davtashen- 3 Yes Operated 8. Aruch- 1 Yes Operated 9. Kosh-3 Yes Non operated 10. Kosh-4 Yes Operated 11. Aghtsk-2 Yes Operated Excavated unsuitable material dump sites 12. Kosh- 1 Yes Non operated 13. Kosh-2 Yes Non operated 14. Talin-2 No Non operated 15. Talin-3 Yes Operated 16. Katnaghbyur-3 Yes Operated 17. Katnaghbyur-4 Yes Operated 18. Katnaghbyur-5 Yes Operated 19. Nerkin Bazmaberd-2 Yes Operated 20. Nerkin Bazmaberd 3 Yes Operated 21. Nerkin Bazmaberd 4 Yes Operated 22. Davtashen-1 Yes Operated 23. Davtashen- 2 Yes Operated 24. Aruch- 2 Yes Non operated 25. Verin Sasnashen-1 Yes Operated 26. Verin Sasnashen- 2 Yes Operated 27. Shamiram- 1 No Non operated 28. Shamiram- 2 Yes Operated 29. Kaqavadzor -1 Yes Operated 30. Parpi-1 No Non operated Concrete plants 31. Kaqavadzor concrete plant Yes Operated Blasting works 32. Km 48+140 - 49+600 Yes N/A

33. Km 54+300 – 54+400 Yes N/A

34. Km 56+050 –56+300 Yes N/A

35. Km 58+000 – 58+400 Yes N/A

36. Km 59+280 – 59+380 Yes N/A 37. Km 61+500 – 62+100 Yes N/A

38. Km 64+150 –66+350 Yes N/A

39. Km 68+300 – 68+500 Yes N/A 40. Km 70+080 - 70+770 Yes N/A Archaeological sites 41. Aruch Caravanatun Yes N/A Wetlands 42. Shahverd Yes N/A

ANNEX B Summary Table on Status of Archaeological Excavations Community Name of site Exacavating Contract Status of works entity signed 1 Parpi Nerkin Naver CHPC at MOC Yes Finished 2 Agarak Agarak Historical-Cultural IAE of NAS Yes Finished Preserve 3 Aghtsk Aghtsk-1 tomb field CHPC at MOC Yes Finished 4 Aruch Aruch archaeological - Yes Finished complex 5 Agarak (Talin) Hellenistic city remains - N/A There is no need of archaeological excavation due to road interchange redesign 6 Kakavadzor Kakavadzor tomb field CHPC at MOC Yes Finished 7 Nerkin N. Bazmaberd tomb field CHPC at MOC Yes Finished Bazmaberd 8 Verin & Nerkin Sasnashen archaeological CHPC at MOC Yes Finished Sasnashen complex As a result, a new archaeological site was discovered in Nerkin Sasnashen

The excavation was completed (see clause 9) 9 Nerkin N. Sasnashen CHPC at MOC Yes Finished Sasnashen archaeological complex (new discovered archaeological site) 9 Davtashen Davtashen archaeological IAE of NAS Yes Finished complex 10 Katnaghbyur Katnaghbyur archaeological IAE of NAS Yes Finished complex 11 Talin Talin tomb field IAE of NAS Yes Finished

ANNEX C Non-Conformances Detected During Monitoring Visits in Reporting Period Reference Requirement Action to Action date required/comment 1. The practice of unpermitted Machinery shall be Partially The Constructor shall use of territories for parking parked in the right improved follow the instruction of machinery in the non- of way or other otherwise non- permitted area outside the permitted areas compliance shall be RoW, issued

2. Trucks were overloaded Trucks loaded with Partially Exclude the operation and non-covered while earth entering the improved of trucks that don’t entering public roads public road shall be have covers covered 3. The ERP posters were The ERP posters Not The Constructor shall missing. should be posted improved follow the instruction otherwise non- compliance shall be issued

4. Establishment of crushing Before crushing Improved No further actions are machinery in area not machinery required approved by PMC/Engineer establishment the approval of the PMC/Engineer should be obtained 5. New hired workers not All new hired Improved No further actions are trained on environmental workers should be required safeguards trained before start of works

6. Dust and mud spread Ensure placement Partially The Constructor shall preventive measures like of gravel layer in improved follow the instruction gravel layer were poorly front of each otherwise non- implemented entrance to the compliance shall be public road issued 7. Watering of construction To prevent dust Partially The Constructor shall sites during construction spread the improved follow the instruction works were not construction sites otherwise non- implemented properly should be watered compliance shall be issued 8. Deviation from SEMPs Operate the sites Improved No further actions are while operating the Kosh-4 based on SEMPs required and Aghtsk-2 topsoil sites 9. Non- permitted discharge of Discharge the Improved No further actions are concrete waste water concrete waste required water only in permitted areas

Annex D. Status of Measurements on Dust, Noise, Water Quality and Vibration in January-July 2017

Measurement Location PK Community Measurements parameter implemented during reporting period DUST Dust 1 Parpi CP Parpi, N/A Dust 2 32+600 Voskevas N/A Dust 3 33+700 Agarak N/A Dust 4 36+600 Aghtsk N/A Dust 5 38+500 Udjan monthly Dust 6 43+300 Kosh N/A Dust 7 44+850 Kosh N/A Dust 8 46+700 Shamiram N/A Dust 9 50+800 Aruch monthly Dust 10 63+200 Davtashen monthly Dust 11 69+000 Yeghnik N/A Dust 12 69+800 Talin monthly NOISE Noise 1 Parpi CP Parpi N/A Noise 2 32+500 Voskevas N/A Noise 3 36+400 Aghtsk N/A Noise 4 38+400 Udjan monthly Noise 5 43+800 Kosh N/A Noise 6 44+600 Kosh N/A Noise 7 46+400 Shamiram N/A Noise 8 50+900 Aruch monthly Noise 9 69+950 Talin monthly WATER Water 1 30+500 Parpi N/A Water 2 30+700 Parpi N/A Water 3 32+800 Voskevas N/A Water 4 32+900 Voskevas N/A VIBRATION Vibration 1 50+700 Aruch monthly N/A – The measurements were not taken at the measurements points because there were no on- going construction works near the points during the reporting period.

Noise, vibration and dust assessment report № 11 /July, 2017 /

Table 6. Results of noise measurements made at point "Noise 4" on 03.07.2017 (baseline noise measurements) Threshold limit Threshold limit Measurement Sound level Maximum sound value (equivalent value (maximum time (equivalent to sound level, LAmax, dBA to sound level), sound level), (from - till) level), LAeq, dBA dBA dBA Noise 4 1st measurement 68.4 86.4 2nd measurement 66.2 83.5 55 70 3rd measurement 67.2 84.8

Table 7. Results of noise measurements made at point "Noise 8" on 03.07.2017 compared with baseline noise measurements made on 02.11.2013

Sound level Maximum sound Threshold limit Threshold limit Measurement (equivalent to sound level, LAmax, dBA value (equivalent value (maximum time level), LAeq, dBA to sound level), sound level), (from - till) operational baseline operational baseline( dBA dBA (03.07.17) (02.11.13) (03.07.17) 02.11.13) Noise 8 1st measurement 62.2 60.0 88.5 71.6 2nd measurement 64.6 59.7 84.9 71.5 60 75 3rd measurement 66.5 59.4 86.8 71.6

Table 8. Results of dust (PM2.5 and PM10) measurements made at point "Dust 5" on 03.07.2017 (baseline dust measurements) Maximum permissible concentration (MPC) for dust, mg/m3 Measurement time Dust actual (from - till) concentration, mg/m3 Daily average Maximum value

Dust 5 PM2.5 0.004 0.035 0.16 1st measurement PM10 0.015 0.06 0.3 PM2.5 0.005 0.035 0.16 2nd measurement PM10 0.015 0.06 0.3 PM2.5 0.004 0.035 0.16 3rd measurement PM10 0.016 0.06 0.3 PM2.5 0.004 0.035 0.16 Average value PM10 0.015 0.06 0.3

Table 9. Results of dust (PM2.5 and PM10) measurements made at point "Dust 9" on 15.11.2016 compared with dust baseline measurements made on 02.11.2013 Maximum permissible concentration Measurement time Dust actual (MPC) for dust, mg/m3 (from - till) concentration, mg/m3 Daily average Maximum value operational baseline1 (03.07.17) (02.11.13) Dust 9 PM2.52 0.006 0.035 0.16 1st measurement 0.018 PM103 0.016 0.06 0.3 PM2.5 0.005 0.035 0.16 2nd measurement 0.017 PM10 0.006 0.06 0.3 PM2.5 0.017 0.035 0.16 3rd measurement 0.02 PM10 0.017 0.06 0.3 PM2.5 0.006 0.035 0.16 Average value 0.018 PM10 0.016 0.06 0.3

Table 10. Results of dust (PM2.5 and PM10) measurements made at point "Dust 10" on 03.07.2017 compared with dust baseline measurements made on 25-26.07.2013 Maximum permissible concentration Dust actual (MPC) for dust, mg/m3 Measurement time concentration, mg/m3 (from - till) operational baseline Daily average Maximum value (03.07.17) (25-26.07.13) Dust 10 PM2.55 0.007 0.035 0.16 1st measurement 0.017 PM106 0.014 0.06 0.3 PM2.5 0.009 0.035 0.16 2nd measurement 0.02 PM10 0.016 0.06 0.3 PM2.5 0.007 0.035 0.16 3rd measurement 0.02 PM10 0.015 0.06 0.3 PM2.5 0.008 0.035 0.16 Average value 0.019 PM10 0.015 0.06 0.3

Table 11. Results of vibration measurements made at point "Vibration 1" on 15.11.2016 (operational vibration measurements) compared with vibration baseline measurements made on 02.11.2016 Vibration actual exposure value, Vibration Vibration Measurement time m/s2 exposure action exposure limit (from - till) operational baseline value (EAV), m/s2 value (ELV), m/s2 (03.07.17) (02.11.13) Vibration 1 1st measurement 0 0 2nd measurement 0 0 0.5 1.15 3rd measurement 0 0 Average value 0 0

1Measurements for baseline study were conducted on 25-26.07.2013 and 02.11.2013 to determine dust concentration only. However, in accordance to the Government Decree № 1174-N dated 23.10.2013 PM2.5 and PM10 should be determined.

22.5um size particles

310um size particles Conclusions

1) As a TLV for evaluation of noise actual levels at measurement point "Noise 4" 55 dBA as equivalent and 70 dBA as maximum noise levels have to be applied, as this point is considered as located in residential area. 60 dBA as equivalent and 75 dBA as maximum noise levels (applied as TLVs for shops, trading halls, airports, railway stations, public service providers) are used for actual noise levels evaluation at point "Noise 8". 2) As a result of background noise level measurements, conducted at point "Noise 4" during the different daytime periods on 03.07.2017, the equivalent and maximum noise actual levels were above the TLVs set by Sanitary norms (55 dBA as equivalent and 70 dBA as maximum accordingly). 3) As a result of noise level measurements, conducted at point "Noise 8" during the different daytime periods on 03.07.2017, the equivalent and maximum noise actual levels were above the TLVs set by Sanitary norms (60 dBA as equivalent and 75 dBA as maximum accordingly). 4) One of the reasons of high noise level is the movement of cars/vehicles (for point Noise 4) as well as other construction equipment (for point Noise 8) along the M1 highway. 5) PM2.5 and PM10 (dust particles of 2.5um and 10um accordingly) actual concentrations at points "Dust 5", "Dust 9" and "Dust 10" in different daytime periods don’t exceed the daily average and maximum permissible concentrations (MPC) for residential areas set by the RoA Government Decree №160-N "Norms of maximum permissible concentrations of atmospheric air pollutants in residential areas". 6) According to the results of vibration instrumental measurements, no vibration exposures were detected near the measurement point "Vibration 1" (near Qaravanatun monument).

Noise, vibration and dust assessment report № 12 /August, 2017 /

Table 6. Results of noise measurements made at point "Noise 4"and “Noise 8” on 11.08.2017 compared with baseline noise measurements made on 03.07.2017

Sound level Maximum sound Threshold limit Threshold limit Measurement (equivalent to sound level, LAmax, dBA value (equivalent value (maximum time level), LAeq, dBA to sound level), sound level), (from - till) operational baseline operational baseline( dBA dBA (11.08.17) (03.07.17) (11.08.17) 03.07.17) Noise 4 1st measurement 61.5 68.4 84.6 86.4 2nd measurement 61.5 66.2 85.8 83.5 55 70 3rd measurement 59.5 67.2 85.0 84.8

Measurement Sound level Maximum sound Threshold limit Threshold limit time (equivalent to sound level, LAmax, dBA value (equivalent value (maximum (from - till) level), LAeq, dBA operational baseline operational Baseline to sound level), sound level), (11.08.17) (03.07.17) (11.08.17) (03.07.17) dBA dBA Noise 8 1st measurement 58.8 62.2 81.1 88.5 2nd measurement 57.1 64.6 84.7 84.9 60 75 3rd measurement 61.5 66.5 86.1 86.8

Table 7. Results of dust (PM2.5 and PM10) measurements made at point "Dust 5", "Dust 9" and "Dust 10" on 11.08.2017 compared with dust baseline measurements made on 03.07.2017 Maximum permissible concentration Dust actual (MPC) for dust, mg/m3 3 Measurement time concentration, mg/m (from - till) operational baseline4 Daily average Maximum value (11.08.17) (03.07.17) Dust 5 PM2.5 0.003 0.004 0.035 0.16 1st measurement PM10 0.01 0.015 0.06 0.3 PM2.5 0.004 0.005 0.035 0.16 2nd measurement PM10 0.014 0.015 0.06 0.3 PM2.5 0.004 0.004 0.035 0.16 3rd measurement PM10 0.013 0.016 0.06 0.3 PM2.5 0.003 0.004 0.035 0.16 Average value PM10 0.012 0.015 0.06 0.3 Dust 9 PM2.5 0.006 0.006 0.035 0.16 1st measurement PM10 0.015 0.016 0.06 0.3 PM2.5 0.007 0.005 0.035 0.16 2nd measurement PM10 0.016 0.016 0.06 0.3 PM2.5 0.006 0.006 0.035 0.16 3rd measurement PM10 0.016 0.017 0.06 0.3 PM2.5 0.006 0.006 0.035 0.16 Average value PM10 0.015 0.016 0.06 0.3 Dust 10 PM2.5 0.008 0.007 0.035 0.16 1st measurement PM10 0.018 0.014 0.06 0.3 PM2.5 0.009 0.009 0.035 0.16 2nd measurement PM10 0.02 0.016 0.06 0.3 PM2.5 0.008 0.007 0.035 0.16 3rd measurement PM10 0.017 0.015 0.06 0.3 PM2.5 0.008 0.008 0.035 0.16 Average value PM10 0.018 0.015 0.06 0.3

Table 8. Results of vibration measurements made at point "Vibration 1" on 11.08.2017 (operational vibration measurements) compared with vibration baseline measurements made on 03.07.2017

4Measurements for baseline study were conducted on 25-26.07.2013 and 02.11.2013 to determine dust concentration only. However, in accordance to the Government Decree № 1174-N dated 23.10.2013 PM2.5 and PM10 should be determined. Vibration actual exposure value, 2 Vibration Vibration Measurement time m/s exposure action exposure limit (from - till) baseline operational value (EAV), m/s2 value (ELV), m/s2 (11.08.17) (03.07.17) Vibration 1 1st measurement 0 0 2nd measurement 0 0 0.5 1.15 3rd measurement 0 0 Average value 0 0

Conclusions

1) As a TLV for evaluation of noise actual levels at measurement point "Noise 4" 55 dBA as equivalent and 70 dBA as maximum noise levels have to be applied, as this point is considered as located in residential area. 60 dBA as equivalent and 75 dBA as maximum noise levels (applied as TLVs for shops, trading halls, airports, railway stations, public service providers) are used for actual noise levels evaluation at point "Noise 8". 2) As a result of noise level measurements, conducted at point "Noise 4" during the different daytime periods on 11.08.2017, the equivalent and maximum noise actual levels were above the TLVs set by Sanitary norms (55 dBA as equivalent and 70 dBA as maximum accordingly). 3) As a result of noise level measurements, conducted at point "Noise 8" during the different daytime periods on 11.08.2017, the equivalent noise actual levels measured at 10:55-11:05 and at 13:45- 13:55 were within the TLV set by Sanitary norms (60 dBA), while the equivalent noise actual level measured at 14:50-15:00 was above the TLV set by Sanitary norms (60 dBA). The maximum noise levels at point "Noise 8" were above the TLV set by Sanitary norms (75 dBA). 4) One of the reasons of high noise level is operation of construction equipment and movement of cars and vehicles along the M1 highway. 5) PM2.5 and PM10 (dust particles of 2.5um and 10um accordingly) actual concentrations at points "Dust 5", "Dust 9" and "Dust 10" in different daytime periods don’t exceed the daily average and maximum permissible concentrations (MPC) for residential areas set by the RoA Government Decree №160-N "Norms of maximum permissible concentrations of atmospheric air pollutants in residential areas". 6) According to the results of vibration instrumental measurements, no vibration exposures were detected near the measurement point "Vibration 1" (near Qaravanatun monument).

Noise, vibration and dust assessment report № 13 /September, 2017 /

Table 6. Results of noise measurements made at point "Noise 4"and “Noise 8” on 12.09.2017 compared with baseline noise measurements made on 03.07.2017

Sound level Maximum sound Threshold limit Threshold limit Measurement (equivalent to sound level, LAmax, dBA value (equivalent value (maximum time level), LAeq, dBA to sound level), sound level), (from - till) operational baseline operational baseline( dBA dBA (12.09.17) (03.07.17) (12.09.17) 03.07.17) Noise 4 1st measurement 66.4 68.4 86.9 86.4 2nd measurement 69.2 66.2 85.6 83.5 55 70 3rd measurement 67.6 67.2 86.8 84.8 Noise 8 1st measurement 61.6 62.2 85.9 88.5 2nd measurement 64.9 64.6 85.9 84.9 60 75 3rd measurement 65.4 66.5 86.4 86.8

Table 7. Results of dust (PM2.5 and PM10) measurements made at point "Dust 5", "Dust 9" and "Dust 10" on 12.09.2017 compared with dust baseline measurements made on 03.07.2017 Maximum permissible concentration Dust actual (MPC) for dust, mg/m3 3 Measurement time concentration, mg/m (from - till) operational baseline5 Daily average Maximum value (12.09.17) (03.07.17) Dust 5 PM2.5 0.01 0.004 0.035 0.16 1st measurement PM10 0.019 0.015 0.06 0.3 PM2.5 0.013 0.005 0.035 0.16 2nd measurement PM10 0.027 0.015 0.06 0.3 PM2.5 0.015 0.004 0.035 0.16 3rd measurement PM10 0.03 0.016 0.06 0.3 PM2.5 0.012 0.004 0.035 0.16 Average value PM10 0.025 0.015 0.06 0.3 Dust 9 PM2.5 0.013 0.006 0.035 0.16 1st measurement PM10 0.028 0.016 0.06 0.3 PM2.5 0.016 0.005 0.035 0.16 2nd measurement PM10 0.034 0.016 0.06 0.3 PM2.5 0.01 0.006 0.035 0.16 3rd measurement PM10 0.019 0.017 0.06 0.3 PM2.5 0.013 0.006 0.035 0.16 Average value PM10 0.027 0.016 0.06 0.3 Dust 10

5Measurements for baseline study were conducted on 25-26.07.2013 and 02.11.2013 to determine dust concentration only. However, in accordance to the Government Decree № 1174-N dated 23.10.2013 PM2.5 and PM10 should be determined. PM2.5 0.009 0.007 0.035 0.16 1st measurement PM10 0.019 0.014 0.06 0.3 PM2.5 0.008 0.009 0.035 0.16 2nd measurement PM10 0.018 0.016 0.06 0.3 PM2.5 0.008 0.007 0.035 0.16 3rd measurement PM10 0.017 0.015 0.06 0.3 PM2.5 0.008 0.008 0.035 0.16 Average value PM10 0.018 0.015 0.06 0.3

Table 8. Results of vibration measurements made at point "Vibration 1" on 11.08.2017 (operational vibration measurements) compared with vibration baseline measurements made on 03.07.2017

Vibration actual exposure value, 2 Vibration Vibration Measurement time m/s exposure action exposure limit (from - till) baseline operational value (EAV), m/s2 value (ELV), m/s2 (12.09.17) (03.07.17) Vibration 1 1st measurement 0 0 2nd measurement 0 0 0.5 1.15 3rd measurement 0 0 Average value 0 0

Conclusions

1) As a TLV for evaluation of noise actual levels at measurement point "Noise 4" 55 dBA as equivalent and 70 dBA as maximum noise levels have to be applied, as this point is considered as located in residential area. 60 dBA as equivalent and 75 dBA as maximum noise levels (applied as TLVs for shops, trading halls, airports, railway stations, public service providers) are used for actual noise levels evaluation at point "Noise 8". 2) As a result of noise level measurements, conducted at point "Noise 4" during the different daytime periods on 12.09.2017, the equivalent and maximum noise actual levels were above the TLVs set by Sanitary norms (55 dBA as equivalent and 70 dBA as maximum accordingly). 3) As a result of noise level measurements, conducted at point "Noise 8" during the different daytime periods on 12.09.2017, the equivalent and maximum noise actual levels were above the TLVs set by Sanitary norms (60 dBA as equivalent and 75 dBA as maximum accordingly). 4) The main reason of high noise level is operation of construction equipment and movement of cars and vehicles along the M1 highway. 5) PM2.5 and PM10 (dust particles of 2.5um and 10um accordingly) actual concentrations at points "Dust 5", "Dust 9" and "Dust 10" in different daytime periods don’t exceed the daily average and maximum permissible concentrations (MPC) for residential areas set by the RoA Government Decree №160-N "Norms of maximum permissible concentrations of atmospheric air pollutants in residential areas". 6) According to the results of vibration instrumental measurements, no vibration exposures were detected near the measurement point "Vibration 1" (near Qaravanatun monument).

Noise, vibration and dust assessment report № 14 /November, 2017 /

Table 5. Results of noise measurements conducted at point "Noise 4" and "Noise 8” on 14.11.2017 compared with baseline noise measurements made on 03.07.2017

Sound level Maximum sound Threshold limit Threshold limit Measurement (equivalent to sound level, LAmax, dBA value (equivalent value (maximum time level), LAeq, dBA to sound level), sound level), (from - till) operational baseline operational baseline dBA dBA (14.11.17) (03.07.17) (14.11.17) (03.07.17) Noise 4 1st measurement 64.1 68.4 83.7 86.4 2nd measurement 65.4 66.2 83.3 83.5 55 70 3rd measurement 67 67.2 85.1 84.8 Noise 8 1st measurement 64.2 62.2 83.7 88.5 2nd measurement 63.8 64.6 84.1 84.9 60 75 3rd measurement 61.3 66.5 82.8 86.8

Table 6. Results of noise measurements made at point "Noise 9" on 14.11.2017 (baseline noise measurements)

Threshold limit Threshold limit Measurement Sound level Maximum sound value (equivalent value (maximum time (equivalent to sound level, LAmax, dBA to sound level), sound level), (from - till) level), LAeq, dBA dBA dBA Noise 9 1st measurement 51.8 70.3 2nd measurement 50 68.2 55 70 3rd measurement 50.5 72.1

Table 7. Results of dust (PM2.5 and PM10) measurements conducted at point "Dust 5", "Dust 9" and "Dust 10" on 14.11.2017 compared with dust baseline measurements made on 03.07.2017

Maximum permissible concentration Dust actual (MPC) for dust, mg/m3 Measurement time concentration, mg/m3 (from - till) operational baseline Daily average Maximum value (14.11.17) (03.07.17) Dust 5 PM2.5 0.005 0.004 0.035 0.16 1st measurement PM10 0.033 0.015 0.06 0.3 PM2.5 0.008 0.005 0.035 0.16 2nd measurement PM10 0.017 0.015 0.06 0.3 PM2.5 0.009 0.004 0.035 0.16 3rd measurement PM10 0.019 0.016 0.06 0.3 PM2.5 0.007 0.004 0.035 0.16 Average value PM10 0.023 0.015 0.06 0.3 Dust 9 PM2.5 0.006 0.006 0.035 0.16 1st measurement PM10 0.015 0.016 0.06 0.3 PM2.5 0.008 0.005 0.035 0.16 2nd measurement PM10 0.017 0.016 0.06 0.3 PM2.5 0.008 0.006 0.035 0.16 3rd measurement PM10 0.019 0.017 0.06 0.3 PM2.5 0.007 0.006 0.035 0.16 Average value PM10 0.017 0.016 0.06 0.3 Dust 10 PM2.5 0.008 0.007 0.035 0.16 1st measurement PM10 0.016 0.014 0.06 0.3 PM2.5 0.006 0.009 0.035 0.16 2nd measurement PM10 0.016 0.016 0.06 0.3 PM2.5 0.01 0.007 0.035 0.16 3rd measurement PM10 0.023 0.015 0.06 0.3 PM2.5 0.008 0.008 0.035 0.16 Average value PM10 0.018 0.015 0.06 0.3

Table 8. Results of dust (PM2.5 and PM10) measurements made at point "Dust 12" on 14.11.2017 (baseline dust measurements)

Maximum permissible concentration Measurement time Dust actual (MPC) for dust, mg/m3 (from - till) concentration, mg/m3 Daily average Maximum value Dust 12 PM2.5 0.016 0.035 0.16 1st measurement PM10 0.034 0.06 0.3 PM2.5 0.011 0.035 0.16 2nd measurement PM10 0.024 0.06 0.3 PM2.5 0.013 0.035 0.16 3rd measurement PM10 0.026 0.06 0.3 PM2.5 0.013 0.035 0.16 Average value PM10 0.028 0.06 0.3

Conclusions

1) As a TLV for evaluation of noise actual levels at measurement points "Noise 4" and "Noise 9" 55 dBA as equivalent and 70 dBA as maximum noise levels have to be applied, as this point is considered as located in residential area. 60 dBA as equivalent and 75 dBA as maximum noise levels (applied as TLVs for shops, trading halls, airports, railway stations, public service providers) are used for actual noise levels evaluation at point "Noise 8" (see Table 3).

2) As a result of noise level measurements, conducted at point "Noise 4" during the different daytime periods on 14.11.2017, the equivalent and maximum noise actual levels were above the TLVs set by Sanitary norms (55 dBA as equivalent and 70 dBA as maximum accordingly). 3) As a result of noise level measurements, conducted at point "Noise 8" during the different daytime periods on 14.11.2017, the equivalent and maximum noise actual levels were above the TLVs set by Sanitary norms (60 dBA as equivalent and 75 dBA as maximum accordingly).

4) As a result of noise level measurements, conducted at point "Noise 9" during the different daytime periods on 14.11.2017, the equivalent noise actual levels were within the TLV set by Sanitary norms (55 dBA). Maximum noise actual levels measured between 11:05-11:15 and 15:45-15:55 were above the TLV set by Sanitary norms (70 dBA), while noise maximum level measured between 15:05-15:15 is within the TLV set by Sanitary norms (70 dBA).

5) The main noise sources at all noise measurement points are operation of construction equipment and movement of cars and vehicles along the M1 highway.

6) PM2.5 and PM10 (dust particles of 2.5um and 10um accordingly) actual concentrations at points "Dust 5", "Dust 9", "Dust 10" and "Dust 12" in different daytime periods don’t exceed the daily average and maximum permissible concentrations (MPC) for residential areas set by the RoA Government Decree №160-N "Norms of maximum permissible concentrations of atmospheric air pollutants in residential areas".

ANNEX E: Status of environmental permits and licenses

Environmental Permits In Name/Place Comment (Name of the authority, License and Licenses Place number, Date)

Environmental expertise Yes RA MNP Environmental Impact assessment and conclusion for Tranche Expertise Centre SNCO/ 22 July 2011/ 2 EE 62 Environmental expertise Yes RA MNP Environmental Impact assessment and conclusion for Expertise Centre SNCO/ 24 August 2013/ concrete batching plant EE 79 Environmental expertise Yes RA MNP Construction permit by Parpi community conclusion for Parpi No 175, March 2013 concrete batching plant Environmental Impact assessment and Expertise Centre SNCO/ 18 March 2013 / EE 16 Kaqavadzor concrete Yes Kaqavadzor Construction permit by Kaqavadzor batching plant community, No. 1, dated 18.11.2015, Ministry of Urban Development, Expertise positive conclusion No. 7/PF-423, dated 12.11.2015 Atmospheric air pollution permit from Ministry of Nature Protection, No. 5/19.3/55158, dated 25.12.2015 Quarry Yes Stone Land, Contractor buys material form the existing quarry (Ministry of Energy Infrastructures and Natural Resources of the RA, license No. 03A 075493, date:1/09/2012) Yes Nairi JSHSH, Nor Contractor buys material form the existing Geghi quarry (Ministry of Energy Infrastructures and Natural Resources of the RA, license No. 01A 000817, date:20/10/2012) Yes Shen Group Contractor buys material form the existing CJSC, quarry (Ministry of Energy Infrastructures Merdzavan and Natural Resources of the RA, license No. 03A 087918, date:17/07/2010) Yes AAB Project LTD, Contractor buys material form the existing Aramus quarry (Ministry of Energy Infrastructures and Natural Resources of the RA, license No. HA-L-14/668, date:25/07/2011) Yes Universal LTD, Contractor buys material form the existing Dashtavan quarry (Ministry of Energy Infrastructures and Natural Resources of the RA, license No. HA-L-14/600, date:20/11/2009) Yes Hamlet-Robert Contractor buys material form the existing LTD, Yerevan quarry (Ministry of Energy Infrastructures and Natural Resources of the RA, license No. Shat-29/543, date:18/07/2016) Topsoil stockpiling site Yes Katnaghbyur- 1, Permission on temporary stockpiling of Katnaghbyur-2/ topsoil issued by the head of Katnaghbyur community on 17.10.2013, No. 66 Katnaghbyur Approval of the municipality of Aragatsotn community, marz, No. 01/19/3236-13 dated Aragatsotn marz 18.10.2013 Yes Yeghnik 1, Permission on temporary stockpiling of Yeghnik 2/ topsoil issued by the head of Yeghnik community on 11.10.2013 Yeghnik Approval of the municipality of Aragatsotn Community, marz, No. 01/19/3180-13 dated Aragatsotn marz 14.10.2013

Yeghnik 2 has not operated Yes Talin-1/ Permission of the ministry of Transport and Communication, No. 01/16.1/7340- Talin City, 14, dated 27.06.2014 Aragatsotn marz Yes Nerkin Permission on temporary stockpiling of Bazmaberd-1, topsoil issued by the head of Nerkin Nerkin Bazmaberd community on 22.11.2013, Bazmaberd-2/ No. 054 Approval of the municipality of Aragatsotn Nerkin marz, No. 01/19/3608-13 dated Bazmaberd 22.11.2013 community, Aragatsotn marz Yes Davtashen- 3/ Permission on temporary stockpiling of topsoil issued by the head of Davtashen Davtashen community on 13.03.2014 community Approval of the municipality of Aragatsotn Aragatsotn marz marz, No. 01/19/740-14 dated 13.03.2014 Yes Aruch- 1/ Permission on temporary stockpiling of topsoil issued by the head of Aruch Aruch community, community on 17.07.2014 Aragatsotn marz Approval of the municipality of Aragatsotn marz, dated 17.07.2014 Yes Kosh-3/ Permission on temporary stockpiling of topsoil issued by the head of Kosh Kosh community, community on 07.10.2014 Aragatsotn marz Approval of the municipality of Aragatsotn marz, dated 06.10.2014 Yes Kosh -4/ Permission on temporary stockpiling of Kosh community, topsoil issued by the head of Kosh Aragatsotn marz community on 01.07.2017

Approval of the municipality of Aragatsotn marz, dated 16.06.2017 Yes Aghtsk 2 / Permission on temporary stockpiling of Aghtsk topsoil issued by the head of Aghtsk community, community on 01.06.2017 Aragatsotn marz Approval of the municipality of Aragatsotn marz, dated 16.06.2017 No Shamiram- 1/ The site has not been operated and the SEMP has not prepared yet. Approval Shamiram from marzpetaran has not taken. community, Aragatsotn marz Excavated unsuitable Yes Katnaghbyur-3, Permission of the municipality of material dumping site Katnaghbyur-4 , Katnaghbyur community on disposal Katnaghbyur-5 excavated subsoil No 076, dated 21.11.2013 Katnaghbyur community, Aragatsotn marz No Talin-2, Talin City, The site has not operated and the SEMP Aragatsotn marz has not prepared yet.

Yes Talin-3, Talin-3, Permission of the municipality of Talin Talin City, community on disposal of excavated Aragatsotn marz subsoil, No 056 dated 15.06.2016

Yes Nerkin Permission of the municipality of Nerkin Bazmaberd 3, Bazmaberd community on disposal of Nerkin excavated subsoil No 053, dated Bazmaberd 4, 21.11.2013

Nerkin Bazmaberd community, Aragatsotn marz Yes Davtashen-1, Permission of the municipality of Davtashen-2, Davtashen community on disposal of excavated subsoil dated 02.12.2013 Davtashen community, Aragatsotn marz Yes Aruch- 2/ Permission of the municipality of Aruch community on disposal of excavated Aruch community, subsoil No 94, dated 17.07.2014 Aragatsotn marz Yes Verin Sasnashen- Permission of the municipality of Verin 1, Sasnashen community on disposal of Verin Sasnashen- excavated subsoil dated 24.02.2014 2/

Verin Sasnashen community, Aragatsotn marz Yes Kosh- 1, Permission of the municipality of Kosh Kosh- 2/ community on disposal of excavated subsoil dated 25.08.2014 Kosh community, Aragatsotn marz Yes Shamiram- 2/ Permission of the municipality of Shamiram community on disposal of Shamiram excavated subsoil, dated 07.03.2014 community, Aragatsotn marz Yes Kaqavadzor -1/ Permission of the municipality of Shamiram community on disposal of Kaqavadzor excavated subsoil No. 50, dated community, 07.04.2014 Aragatsotn marz No Parpi-1/ The site has not operated and the SEMP has not prepared yet. Parpi community, Aragatsotn marz

ANNEX F: Location of Monitoring points on Dust, Noise, Water Quality and Vibration

Noise 1, Dust 1 Points "Dust 1" and "Noise 1" are located within the boundary of concrete plant which is constructed to supply ready mix concrete for the Project needs. There are no residential houses in the vicinities. Noise 2, Dust 2 Points "Dust 2" and "Noise 2" are located on M1 Yerevan- highway near Agarak community. In the close vicinity of the measuring point charging station and number of shops are located. Dust 3 Point "Dust 3" is located on M1 Yerevan-Gyumri highway 0.99 km to the west of Agarak community. There is number of industrial facilities in the vicinity of the measurement point. Noise 4, Dust 5 Points "Noise 4" and "Dust 5" are located on M1 Yerevan-Gyumri highway, in the south part of Ujan community. Distance between the points "Noise 4" and "Dust 5" and the nearest residential house is 30-40 m. Noise 5, Dust 6 Points "Noise 5" and "Dust 6" are located near Kosh community. The distance between the point "Noise 5" and the nearest residential house is 0.04 km, while the distance between the point "Dust 6" and the nearest residential house is 0.05 km Noise 6, Dust 7 Points "Noise 6" and "Dust 7" are located near Kosh community. The distance between the point "Noise 6" and the nearest residential house is 0.05 km, while the distance between the point "Dust 7" and the nearest residential house is 0.09 km Noise 7, Dust 8 Points "Noise 7" and "Dust 8" are located near Shamiram and Aruch communities. The point "Noise 7" is situated near to residential houses, while the distance between the point "Dust 8" and the nearest residential house is 0.08 km. Vibration 1, Noise 8, Dust 9 Points “Vibration 1”, “Noise 8” and “Dust 9” are located on M1 Yerevan-Gyumri highway. The distance between the measurement points and the nearest community (Aruch village) is about app. 1.5 km to the south. Point “Vibration 1” is situated in front of Qaravanatun monument, while points “Noise 8” and “Dust 9” are located near the Narek restaurant. Dust 10 Point "Dust 10" is located on the earth road connecting M1 Yerevan-Gyumri highway with the Davtashen community. The distance between the M1 road and the measurement point is approx. 150 m, while the distance between the measurement point and the nearest residential house (Davtashen community) is approx. 200 m. Noise 9 The measurement point Noise 9 is located near M1 and M9 road junction, where the construction works are currently conducted. The point is placed within the area of Tallin residential community. The distance between the measurement point and nearby residential house is approx. 50 m. Dust 11 Point is located on M1 Yerevan-Gyumri highway, in the north-east of Talin community, app. 0.93 km to the north to the point "Dust 11". Near the point restaurant "Mush", a charging station and few other buildings are located. Dust 12 The measurement point Dust 12 is located to the south-west of M1 and M9 road junction, where the construction works are currently conducted. The point is placed within the area of Tallin residential community.

Figure 1 Section of Parpi, Voskevas and Agarak communities

Figure 2 Section of Aghdzk community

Figure 3 Section of Ujan community

Figure 4 Section of Kosh community

Figure 5 Section of Shamiram and Aruch communities

Figure 6 Section of Aruch Kakavadzor communities

Figure 7 Section of Nerkin Bazmaberd communities

Figure 8 Section of Verin Sasnashen and Nerkin Sasnashen communities

Figure 9 Section of Davtashen and Katnaghbyur communities

Figure 10 Section of Yeghnik and Talin communities

Figure 11 Section of Talin community

ANNEX G: Post-construction environmental audit checklist for Tranche 1, Date: 04.10.17

No Measure/s suggested as Chec Activity Impacts Measures Implemented . per k

1 Project site vegetation Change of land cover, Plantation and vegetation N / A There is no affections rehabilitation erosion resulting from the measures (trees, grass (re-vegetation) construction activities etc.) Proper landscaping with N / A Issues will arise where long paved drainage channels release storm runoff into unprotected areas such as steep gorge sides. This is evident in at least one location where a collector channel directs runoff to the left embankment (heading to Talin) of the Kasakh River bridge at Ashtarak. Due to lack of armouring at the release point the already high velocity of the runoff is now eroding the side of the gorge adjacent to the bridge. This may have longer term consequences for the integrity of the bridge.

The issue is currently under Engineer’s investigation and possible solution to this shall be proposed.

. 2 Erosion of soil Storing and managing N / A There are no effects Top soil management removed topsoil for re- use for landscaping activities 3 Oil management Equipment and machinery Avoid oil spill to open soil. Yes There are no oil spillages repairing Repair works to be taken on concrete cover area. 4 Waste management Waste accumulation, air Collect and disposal all Yes Construction wastes are removed to and soil pollution wastes including approved dump sites construction debris at designated location; The rubber waste generated as a result of works is temporarily stored at Parpi CP area, The Parpi CP will be operated for Tranche 2

Dumping sites restored Yes Ashtarak-2 DS used during DLP is and submitted officially to closed and handed over to Ashtarak local communities community. Masis DS is closed and handed over to Masis community 5 Noise and vibration, air Excessive noise and Noise shall be monitored N / A No complaints were lodged by APs management vibration due on a periodic basis in during the DLP to new road response to any complaints.

6 Air management Air quality deterioration Air quality has been N / A No complaints were lodged by APs due monitored associated during the DLP to new road with vehicle emissions on a periodic basis and in response to any complaints Traffic management Hazards and Public access and Yes All the accesses are provided. There 7 safety issues access to the housing, are no complaints from APs logged related to traffic shops, business and during DPL. public activities Appropriate signage is Yes The marking signage is approved by installed road police and the installation is in process 8 Road reinstatement Road damages causing Streets with installed Yes All the existing network was replaced pollution, traffic network reinstated to pre- and new network installed according disturbance and accidents construction or better to the design. conditions, Trees replanted as needed N / A There is no affections Access road reinstated to Yes Access roads are provided to all pre-construction or better houses and business located around conditions the road. There were no complains logged during the DLP 9 Borrow sites and quarries Land slide, soil erosion, Borrow sites and quarries Yes The both borrow sites used for Tranche change in riverbed and restored 1: and site, were landscape, accidents closed on respectively 4 and 13th June 2014, properly restored and handed over to local communities. There were no borrow pits used during DLP. Contractor purchased the material from existing quarries on contractual basis. 10 Existing Infrastructure Damage or disturbance to Reinstatement to pre- Yes Existing infrastructure is reinstated up facilities existing services (supply of construction conditions or to the pre construction condition electricity, water, gas, proper relocation, to be and/or properly relocated. There are no telecom etc.) certified by the service complaints received‐ during DPL. companies 11 Camp site facilities Residual pollution and All temporary/field plants No Masis concrete plant is closed and disturbance to the localities (asphalt, concrete, handed over to the owner. Parpi crushing, etc.) have been concrete plant will be operating for dismantled and removed. Tranche 2. Permanently operating N/A Contract with asphalt milling plants (asphalt, concrete, plant was completed. The plant was crushing, etc.) have been not used during DLP properly handled and closed/surrendered. All temporary facilities N/A Contractor didn't established camps or removed and cleaned up any other temporary facilities for Thanche 1 during DLP 12 Archaeological/historical Destroying influence on All required excavation N / A There were no archaeological issues in sites cultural and archaeological works have been finished Tranche 1. monuments and artefacts and approved by MOC No post construction influence on cultural monuments 13 GRM Unresolved complaints All grievances have been Yes There were no grievances logged from Affected People solved and AP's satisfied during the DLP