Roads Department of

Estimated period for implementation of construction works

N Project name Estimated length (km) Donor Note

Commencement Completion

Ongoing construction

Remaining Works for the Construction of -Grigoleti Road 1 11.50 2018 2021 EIB ongoing Section of E-60 Highway Km 00+000 – Km 11+500 (Lot I)

Construction of Samtredia-Grigoleti Road Section Km 42+000 – Km 2 9.57 2015 2021 EIB ongoing 51+570 (Lot IV)

Construction of Grigoleti- Bypass Road Section km 0+000 to km 3 14.00 2019 2022 EIB ongoing 14+000 of E70 Highway

4 Construction of Bypass Road, Section km -1+000 – km13+325 12.33 2018 2021 ADB/AIIB ongoing

Construction works for the E-60 Highway Section from Zemo Osiauri to 5 6.36 2021 2023 WB ongoing Chumateleti Lot2 (Km 7+700-Km14+060)

Rehabilitation of Dzirula – – Moliti – Pona – Chumateleti 6 Secondary Road (50 km), Dzirula – Moliti Road Section from km 0+000 to 25.00 2018 2021 ADB ongoing km 24+620 (lot I)

Rehabilitation of Dzirula-Kharagauli-Moliti-Pona-Chumateleti Secondary 7 Road, Moliti – Chumateleti Road Section from km 24+620 to km 25.00 2019 2021 ADB ongoing 50+244(Lot 2)

8 Construction of Chumateleti-Khevi Section (F1) of E-60 Highway 11.60 2019 2022 WB/EIB ongoing

9 Construction of Khevi-Ubisa Road Section (F2) of E-60 Highway 12,2 2019 2022 ADB ongoing Estimated period for implementation of construction works

N Project name Estimated length (km) Donor Note

Commencement Completion

10 Construction of Ubisa- Road Section (F3) of E-60 Highway 13.00 2019 2022 EIB ongoing

11 Construction of Shorapani-Argveta Section (F4) of E-60 Highway 14,7 2019 2023 ADB ongoing

Upgrading of Bypass-Samtredia road into 4-lane highway, km 12 6.00 2019 2021 GOG ongoing 00+000-km6+000 (Lot 1)

Upgrading of Kutaisi Bypass-Samtredia road into 4-lane highway, 13 7.40 2019 2021 GOG ongoing km6+000-km13+400 (Lot 2)

Upgrading of Kutaisi bypass-Samtredia road into 4-lane highway, km 14 11.35 2019 2021 GOG ongoing 30+000 - km41+354 (Lot 4)

15 Construction of Kvesheti-Kobi Road (tunnel section) 10.00 2020 2024 ADB ongoing

16 Construction of Kvesheti-Kobi Road (road section) 12.70 2020 2023 ADB/EBRD ongoing

Rehabilitation-reconstruction of Batumi(Angisa)- (შ- 17 1)secondary road, -Goderdzi Pass Section (Lot 1 – from km5+195 to 24.54 2021 2023 KFAED ongoing km 29+732)

Rehabilitation-reconstruction of Batumi(Angisa)-Akhaltsikhe (შ- 18 1)secondary road, Goderdzi Pass –Zarzma Section (Lot 2 – from km0+000 42.00 2020 2022 KFAED ongoing to km 17+380) Estimated period for implementation of construction works

N Project name Estimated length (km) Donor Note

Commencement Completion

Akhmeta--Bakurtsikhe (construction of -Bakurtsikhe 19 15.50 2017 2021 WB ongoing bypass road)

Design and Build of Khidistavi-Ateni-Boshuri Road Section Rehabilitation 20 from km12,4 to km22,5 under Output-and Performance-Based 10.10 2017 2021 WB ongoing Contracting (OPBC) Methodology

Design and Build of --Ninigori Road Section 21 Rehabilitation from km1 to km30 under Output and Performance Based 30.00 2017 2021 WB ongoing Contracting (OPBC) Methodology

Rehabilitation Works for – Barisakho - Shatili Road Section from 22 9.52 2020 2021 WB ongoing km 16 – km 25.5 (Project Chainage 0+000 – 9+516)

Rehabilitation Works for Zhinvali – Barisakho - Shatili Road Section from 23 7.24 2020 2021 WB ongoing km25.5-km32 (project chainage 9+516 – 16+756)

Completed construction

Construction of Samtredia-Grigoleti Road Section km 11+500-to km 1 18.50 2016 2020 EIB Completed 30+000 (lot II)

Construction works for the E-60 Highway Section from Zemo Osiauri to 2 5.80 2017 2020 EIB Completed Chumateleti Lot1 (Km 0+000-Km5+800)

Construction works for the E-60 Highway Section from Zemo Osiauri to 3 1.90 2019 2020 WB Completed Chumateleti Lot2A (Km5+800 km7+700)

Upgrading of Kutaisi Bypass-Samtredia road into 4-lane highway, 4 17.50 2019 2020 GOG Completed km13+400 - km30+000 (Lot 2) Estimated period for implementation of construction works

N Project name Estimated length (km) Donor Note

Commencement Completion

Mountain roads

1 Sno-Juta-Roshka-Shatili-Omalo-Khadori Gorge-Batsara 134.7 2018 2022 GOG Rehabilitation works are underway

2 - 77.00 2018 2022 GOG Rehabilitation works are underway

3 Zemo -Racha 51.00 2018 2021 GOG Rehabilitation works are underway

Planned construction

1 Natakhtari-Zhinvali 27.00

2 Batumi (Chorokhi)-Sarpi 11.30

3 -Red Bridge 31.90

4 Algeti-Sadakhlo 29.30

5 - 35.00

6 Sagarejo-Bakurtsikhe 50.00

7 Gurjaani(Chumlaki)-Telavi Bypass 36.70

8 Bakurtsikhe- 16.70

9 Bridge over Rioni river near 2.50 Construction of Samtredia-Grigoleti Road Section Km 30+000 – Km 10 12 42+000 (Lot III)