Roads Department of

Preparation of design Estimated time for bidding of Estimated time for work fulfilment documentation construction works N Name Approximate Length (km) Donor Status Comment

Start End Start End Start End

Ongoing Construction

1 Agara-Zemo Osiauri 12.00 September 2015 June 2017 WB Construction

2 New Bypass of - 15.20 July 2013 March 2017 JICA Construction

3 -Grigoleti (LOT I) 11.50 May 2014 May 2018 EIB Construction

4 Samtredia-Grigoleti (LOT II) 18.50 Mar-16 March 2019 EIB Construction

5 Samtredia-Grigoleti (LOT IV) 9.50 May 2015 May 2018 EIB Construction

6 Bypass(LOT II) 18.00 May 2013 December 2017 ADB Construction

Construction of --Bakurtsikhe (Bakurtsikhe-) 7 15.00 December 2016 June 2019 WB Construction Bypass Road (15km)

8 Reconstruction-Modernization of Nikea Str. In Kutaisi City 4.10 January 2016 May 2017 GOG Construction

9 -Zaridzeebi- 12.00 February 2016 July 2017 GOG Construction

10 Kutaisi-Samtredia Lightening 41.30 January 2017 June 2017 JICA Construction

Bidding of Ongoing and Planned Constructions

Construction 1 Bypass Road 14.30 October 2016 May 2017 June 2017 November 2020 ADB+AIIB bidding

Construction 2 Samtredia-Grigoleti (LOT III) 12.00 October 2016 March 2017 April 2017 November 2019 EIB bidding

Construction 3 Zemo Osiauri-Chumateleti (LOT I) 8.25 February 2016 March 2017 April 2017 April 2020 EIB bidding

Construction 4 Zemo Osiauri-Chumateleti (LOT II) 14.50 February 2016 March 2017 April 2017 April 2020 WB bidding 5 Grigoleti-Choloki 14.50 April 2016 May 2017 April 2017 October 2017 November 2017 November 2019 EIB Detailed design

6 Chumateleti- 50.00 February 2017 November 2017 June 2017 November 2017 December 2017 June 2020 ADB Detailed design

February-April July-September 7 -Goderdzi (LOT I) 29.70 August-October 2017 September 2019 KUWAIT Detailed design 2017 2017

8 Goderdzi-Zarzma (LOT II) 17.40 March 2017 September 2017 October 2017 August 2019 WB -??? Detailed design

Construction 9 Construction of Bridge over Debeda River 0.11 July 2016 EBRD bidding

10 Devdoraki Tunnel 1.20 January 2017 February 2017 January 2017 March 2017 Mar-17 December 2017 GOG Detailed design

11 Sno-Juta-Roshka-Shatili-Omalo-Khadori gorge-Akhmeta-Batsara 250.00 December 2016 February 2018 May 2017 June 2017 July 2017 September 2020 GOG+? Detailed design

12 - 60.00 January 2017 January 2018 April 2017 May 2017 June 2017 September 2020 GOG+? Detailed design

13 Zemo -Racha 50.00 January 2017 January 2018 April 2017 May 2017 June 2017 September 2020 GOG+? Detailed design

14 Sameba Church in 5.66 February 2017 March 2017 April 2017 November 2017 GOG Detailed design

Construction 15 Lightening works on Ruisi-Agara section 20.00 October 2016 January 2017 Mar-17 August 2017 WB bidding

Construction 16 Lightening works on Zestaponi-Kutaisi 15.17 January 2017 April 2017 May 2017 October 2017 JICA bidding

17 Lightening works of Kobuleti bypass (LOT I) 12.40 February 2017 June 2017 July 2017 December 2017 ADB Detailed design

Ongoing Design of Construction

1 Chumateleti-Khevi (F1) 11.10 February 2017 October 2017 September 2017 February 2018 Mar-18 March 2020 WB+??? Detailed design

2 Khevi-Ubisa (F2) 15.40 March 2017 December 2017 November 2017 April 2018 May 2018 September 2020 ADB+??? Detailed design

3 Ubisa- (F3) 10.50 March 2017 February 2018 January 2018 June 2018 July 2018 September 2020 EIB+??? Detailed design

4 Shorapani-Argveta (F4) 15.80 March 2017 April 2018 February 2018 July 2018 August 2018 September 2020 JICA Detailed design

5 Kvesheti-Kobi 26.00 May 2017 June 2018 November 2017 April 2018 May 2018 September 2020 Design

6 Natakhtari-Zhinvali 30.00 May 2017 August 2018 May 2018 October 2018 November 2018 September 2020 Detailed design 7 Batumi (Chorokhi)-Sarpi 11.00 June 2017 April 2018 January 2018 July 2018 August 2018 September 2020 Detailed design

8 -Red Bridge 35.00 February 2017 November 2017 November 2017 April 2018 May 2018 July 2020 Detailed design

9 Rustavi-Sadakhlo 40.00 February 2017 January 2018 November 2017 April 2018 May 2018 July 2020 Detailed design

10 - 30.00 May 2017 May 2018 January 2018 July 2018 August 2018 August 2020 Detailed design

11 Sagarejo-Bakurtsikhe 50.00 May 2017 May 2018 January 2018 July 2018 August 2018 August 2020 Detailed design

12 - (PFS and FS) 90.00 February 2017 January 2018 August 2018 January 2019 February 2019 October 2020 Design

13 Gurjaani(Chumlaki)-Telavi bypass 30.00 March 2017 December 2017 December 2017 May 2018 Sep-18 September 2020 Detailed design

14 Bakurtsikhe- 16.00 March 2018 December 2017 December 2017 May 2018 Sep-18 March 2020 Detailed design

15 River over Rioni river nearby 5.00 April 2016 September 2017 October 2017 April 2018 May 2018 August 2020 Detailed design

16 - 35.00 December 2016 October 2017 November 2017 April 2018 May 2018 September 2020 Detailed design

Total sum