Environmental Monitoring Report

Semi-annual Report June 2013

VIE: Ha Noi Metro Rail System Project, - Nhon-Ha Noi Railway Station

Prepared by IDOM for the Ha Noi Metropolitan Urban Railway Management Board and the Asian Development Bank.

CURRENCY EQUIVALENTS (as of 1 July 2013)

Currency unit – dong (D) D1.00 = $0.00000472 $1.00 = D21,170

NOTE In this report, "$" refers to US dollars unless otherwise stated.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

INDEX OF CONTENTS

1. INTRODUCTION ...... 2 1.1. Objective of report ...... 2 1.2. Environment Monitoring Mechanism ...... 2 1.3. Environmental Management Plan (EMP) ...... 3 1.4. Site Environmental Compliance Inspection ...... 3 1.5. Project implementation progress...... 3 1.5.1. In-site on-going activities ...... 3 1.5.2. Previous activities ...... 4 1.5.3. Construction schedule for the subsequent months...... 5

2. COMPLIANCE WITH ADB LOAN AND APPLICABLE GOVERNMENT LAW REGULATIONS AND REQUIREMENTS ...... 5 2.1. Situation of compliance with ADB loan...... 5 2.2. Environmental compliance requirements situation of the Government...... 7

3. CHANGES IN PROJECT SCOPE ...... 8

4. INCORPORATION OF ENVIRONMENTAL REQUIREMENTS INTO THE PROJECT CONTRACTUAL ARRANGEMENTS ...... 8 4.1. Evaluation on function and responsibility of organization and implementation of environmental safety...... 8 4.2. Outstanding issues of combining environmental requirements into contract agreement with contractors ...... 11

5. SUMMARY OF IMPLEMENTATION OF ENVIRONMENTAL IMPACT MITIGATION AND COMPENSATION MEASURES ...... 12

6. SUMMARY OF ENVIRONMENTAL MONITORING ...... 14 6.1. Compliance inspections...... 14 6.1.1. Summary of inspection activities...... 14 6.1.2. Compliance with impact mitigation measures...... 15 6.2. Emission Monitoring Program (if related to or required in EMP) ...... 20 6.2.1. Summary of monitoring results at the Depot site...... 20 6.2.2. Results...... 20 6.2.3. Evaluation ...... 21 6.3. Summary of surrounding Environment Monitoring Program of the Depot site (air quality, noise, water quality, etc.) ...... 22 6.3.1. Summary of environment monitoring activities ...... 22

PAGE II

6.3.2. Results...... 22 6.3.3. Evaluation ...... 23 6.3.4. Overall evaluation of the environmental quality monitoring activities by CENMA...... 23 6.4. Monitoring Plan...... 26

7. OUTSTANDING ENVIRONMENTAL ISSUES AT THE METRO LINE 3...... 27 7.1. The existing big environment problems are determined ...... 27 7.2. The solutions and corrective action plan ...... 27 7.3. Necessary supplementary measures ...... 29 7.3.1. For CP01 (elevated section), CP03 (underground section and stations) and CP05 (Depot)...... 29 7.3.2. For CP02 (elevated stations) ...... 32

8. GRIEVANCES...... 34 8.1. Details on grievance/detailed regulations on grievance from local residents and relevant parties on environmental impacts...... 34 8.2. Solutions to deal with grievance letters settled or to be settled with information...... 34

9. CONCLUSIONS AND RECOMMENDATIONS ...... 35 9.1. Overall progress of implementation of environmental management measures...... 35 9.2. Identification of problems and solutions ...... 35 9.2.1. Conclusion ...... 35 9.2.2. Adjustment of monitoring (proposed based on monitoring experience/relevant trends)...... 36 9.2.3. Recommendations...... 36

ANNEX 1. SAMPLING DIAGRAM ...... 38

ANNEX 2. LOCATION OF MONITORING POINTS ...... 40

ANNEX 3. ENVIRONMENTAL MONTHLY SITE VISITS – MAY 2013 ...... 42

ANNEX 4. ENVIRONMENTAL MONTHLY SITE VISITS – JUNE 2013...... 47

PAGE III

INDEX OF TABLES

Table 1. Dates of actual site inspection/environmental monitoring activity conducted by Consultant...... 3

Table 2. Summary of project implementation progress...... 4

Table 3. Package CP04 and CP05 implementation progress – June 2013 ...... 5

Table 4: Mitigations Measures Required by EIA & EMP During the Construction Period at Depot Site ..20

Table 5. Features and environmental quality ranking of sampling points for monitoring emission for the Depot site...... 21

Table 6. Signs, features and environmental quality ranking of sampling points for monitoring surrounding environment of the Depot site...... 23

Table 7. Monitoring parameters at the Depot site ...... 25

Table 8. Examination of compliance and surrounding environment...... 26

Table 9. Solutions and corrective action plans ...... 29

PAGE IV

INDEX OF FIGURES

Figure 1. Organization for Environmental Management of CP04 ...... 14

Figure 2. Organization for Environmental Management of CP05 ...... 15

PAGE V

ACRONYMS AND ABBREVIATIONS ADB Asian Development Bank AFD Agence Française de Développement (French Development Agency) BHC Benzene Hexachloride Chemical compound BOD5 Biological Oxygen Demand five days BTNMT Ministry of Natural Resources and Environment CENMA Centre for Environmental & Natural Resources Monitoring and Analysis CO Carbon Monoxide COD Chemical Oxygen Demand CMC Construction monitoring consultant

DDT Dichlorodiphenyltrichloroethane DO Dissolved Oxygen

DGPTE Direction Generable du Tresor et de la Politique Economique EHS Environmental Health System EIA Environmental Impact Assessment EMP Environmental Management Plan EO Environmental Officer IEMC Independent environmental management consultants GPM Grievance Redress Mechanism GHG Green House Gas HANCOR Hanoi Construction Corporation HC Hydrocarbon HPC Hanoi People’s Committee L50 Noise level exceeded 50% of the time Leq Equivalent continuous sound pressure level [dB] Lmax Maximum Noise Level MRB Hanoi Metropolitan Railway Management Board NOx Nitrous Oxidies

O3 Ozone PIC Project Implementation Consultant

PM10 Particulate Matter with aerodynamic diameter < 10 microns PM2.5 Particulate Matter with aerodynamic diameter < 2.5 microns PPE Personal Protection Equipment QCVN Standard SO2 Sulphur Dioxide TSP Total Suspended Particulates VINACONEX Construction and Import-Export Corporation

PAGE 1

1. INTRODUCTION

1. Hanoi Pilot Urban Railway line No.3 (Nhon – Hanoi Raiway Station) Project includes 9 construction packages, of which just packages CP04 (depot civil works) and CP05 (depot architectural works) are currently being under construction by Vietnamese contractors. The Packages CP01 (viaduct section) and CP02 (elevated stations) are in the process of the Contract negotiations, whereas the pre-qualification stage is about to be completed for the Package CP03 (underground works, line and stations). The remaining packages CP06 to CP09 related with equipment and systems are at different stages of their Technical Design.

2. Asian Development Bank (ADB), Agency Françoise de Development (AFD) and Direction Generable du Tresor et de la Politique Economique (DGPTE) have assessed and agreed to provide a loan for Hanoi Pilot Urban Railway line No.3 (Nhon – Hanoi Raiway Station) Project.

3. Socially the project will be a benefit to the population in the project area. The population, located in the western area of Ha Noi will, by using the metro: avoid traffic congestion and reduce safety hazards (especially traffic accidents); reduce health problems (especially respiratory problems) due to air pollution and dust; and save time and benefit from a good transportation alternative to go to Ha Noi Center.

4. Beside the benefits of the project also have negative impacts on the local environment. Therefore the project has environmental management plan The Environmental Management Plan (EMP) which had been implemented by the Contractors during the construction works as specified in Environmental Impact Assessment (EIA).

5. Implementation result report of environmental management plan of the project (environmental monitoring/test results, environmental quality observation results) is to present compliance with environmental protection commitment as specified in EPM and EIA of ADB.

1.1. Objective of report

6. Environmental monitoring report for the first semi-annual of year (from April to June 2013) will aggregate the environmental performance of Hanoi Pilot Urban Railway line No.3 (Nhon – Hanoi Railway Station) Project in general and environmental control activities, the environmental mitigation measures are applied to the construction bidding package. This report reviews the compliance of environmental activities with approved EMP by MRB and proposed newly mitigation measures if necessary in the next time in order to control and minimize negative environmental impacts.

1.2. Environment Monitoring Mechanism

7. The National Environmental Expert of IDOM was mobilized for semi annual environment monitoring of the civil works for April 2013 during one month from May to June 2013. To reviewed the activities of the contractors in the project sites in order to ensure compliance with Environment Management Plan (EMP) of the Project and ADB’s Social Safeguard Policy Statement 2009. Environmental Expert was accompanied by The staffs MRB, Environmental specialist, PIC’s preventatives and Environmental and safety manager of Contractors.

8. The Environmental Specialist of IDOM has been mobilized to manage environmental issues since April 2013. The main tasks of Environmental Specialist is Undertake monthly monitoring of the work of the PIC in supervising the overall implementation of the various EMP provisions and the environmental performance of the contractors (in terms of implementation of mitigation measures for the construction phase as specified in the EMP / EIA and site specific environmental management action plans).

PAGE 2

1.3. Environmental Management Plan (EMP)

9. CP04’s and CP05’s EMP (Environmental Management Plan) were included in the bidding documents of civil works during the procurement stage. The contractors were required to consider the requirements of the EMP when submitting their bids as the conditions in the EMP become contractually binding on the contractors. The contractor must be supplied these details and it was noted that all contractors have now supplied a EMP. Copies of these were reviewed and found to be satisfactory.

1.4. Site Environmental Compliance Inspection

10. These EMP are monitored and enforced by the Environmental specialist of IDOM who use checklists included in the EMP. By using the checklists consistency is maintained between the packages. The checklists are compiled every month (From May to June, 2013). The checklists had been filled in correctly and reporting was thorough. No environmental issues were identified. No complaints from villagers were reported about impact of dust, noise, vibration and water quality from construction works at the time of the inspection. Dates of actual site inspection/environmental monitoring activity conducted by Environmental Expert and Environmental specialist for the period April to Jun 2013 Dates of actual site Dates of actual site inspection No Month inspection of Environmental specialist Environmental expert 1 April 20 20

2 May 11 11, 15, 23

3 June 20 6, 14, 20, 27

Table 1. Dates of actual site inspection/environmental monitoring activity conducted by Consultant

11. All contents, obtained results, analysis, evaluations and recommendations will be specifically presented in this report.

1.5. Project implementation progress

1.5.1. In-site on-going activities

The Project includes nine packages: - Construction Package CP01: Elevated line-section - Construction Package CP02: Elevated stations - Construction Package CP03: Tunnel and underground stations - Construction Package CP04: Depot infrastructure - Construction Package CP05: Depot architectural buildings - Construction Packages CP06, CP07, CP08, CP09: Equipment

Current situation of package Package name Tentative construction time implementation

CP01 (elevated line- Under contract negotiation process Tentative start of construction section) 9/2013

PAGE 3

Current situation of package Package name Tentative construction time implementation

CP02 (elevated stations) Contract awarded Tentative start of construction 8/2013

CP03 (tunnel and Prequalification is going to be finished underground stations)

CP04 (Depot infrastructure) Started on 9/2010, completed 90% of Expected to be completed in workload 8/2013

CP05 (Depot architectural Sub-items started in 4/2013 Period is extended 61 months buildings)

CP06 to CP09 (equipment To be implemented along and systems) 2014 - 2015 Table 2. Summary of project implementation progress

12. The project includes nine packages of which there are two packages CP04 (Depot infrastructure) and CP05 (Depot architectural buildings) currently being implemented.

13. Packages CP01 (viaduct part) and CP02 (elevated station) are under contract negotiation. Tentative start time for construction is 8/2013.

14. Package CP03 (underground work, line and station) is going to finish prequalification.

15. Package CP04 is Depot infrastructure constructed by Vinaconex and supervised by Systra - Project Implementation Consultant (PIC). At present, whole work of CP04 is finished 90% of total work amounts and tentatively completed in 8/2013.

16. Package CP05 is Depot architectural building including building works (structure, architecture and finish) constructed by HANCORP. CP05 was constructed in 4/2013. At present, sub-items (temporary office for CP05) are being implemented and has being completed 80% of Temporary work office for CP05 at the Depot.

17. Package CP06 to CP09 relating to equipment and systems shall be constructed from 2013-2015 of the Project.

1.5.2. Previous activities

18. The Depot site is located at Minh Khai and Tay Tuu Communes in Tu Liem District, and covers an area of 150,500 m 2. An estimation of the progress of the activities of the on-going packages CP04 and CP05 are summarized in the table below presented.

ACTIVITIES DESCRIPTION COMPLETED

For Package CP04

Land grading About 15 ha 100%

Pile – slab 100%

Rainy drainage 100%

Fence 95%

Water supply system and fresh water tank 65%

PAGE 4

Sewage system 100%

Internal roads 65-70%

Cable trench 100%

External lightning 40%

For Package CP05

Temporary work office for CP05 at the Depot 80%

Table 3. Package CP04 and CP05 implementation progress – June 2013

19. It has to be noted that despite the construction activities of CP04 being expected to finalize by August 2013, there is a 750 m long stripe between the Road 70 and the construction site that now is still pending of land clearance.

1.5.3. Construction schedule for the subsequent months

20. Packages CP04 and CP05 continue under construction: MRB is actively implementing the remaining works. The contractual period for CP04 has been extended to 8/2013.

21. It is expected the signature of the contracts with the corresponding contractors of packages CP01 and CP02.

22. The package CP03 will see its prequalification stage finished.

2. COMPLIANCE WITH ADB LOAN AND APPLICABLE GOVERNMENT LAW REGULATIONS AND REQUIREMENTS

2.1. Situation of compliance with ADB loan

23. At present, additional Environmental Impact Assessment- ABD was developed completed by MRB. Basically, the updated Environmental Impact Assessment report – ADB has main content as given in EIA No.26194 August/2010 and just supplements, amends some legal documents on environmental protection stipulated by Vietnam, in which update of some newly- issued Vietnamese Code instead of old Vietnamese Codes and Vietnamese Standards without valid.

24. Three safety-monitoring levels are committed to be implemented in the Project: regular, periodical and public monitoring:

i. Regular monitoring is done by Construction Supervision Consultant (CSC). CSC shall bring monitoring results into project progress reports to be submitted to MRB and other relevant monitoring consultant/organizations. ii. Periodical monitoring (every month and every 6 months): is one part of the whole EMP supported by IEMC. The results shall be reported to MRB, ADB. iii. Public monitoring: the monitoring is implemented in accordance with regulations/procedure of Vietnam with technical and management assistance of MRB.

25. In accordance with regulations of ADB and Vietnam, contractors must implement EPM and SEP. Project progress for EPM and SEP is as follow:

PAGE 5

i. CP04, CP05 and CP01 include EMP into Bidding Document. EPM is developed by Systra. Environmental monitoring results show that content of EPM is not totally suitable with content of EMP given in EIA-2010, in particular, some detailed environmental management plans committed in EPM in EIA-ADB 2010 are not included into SPM at viaduct package (CP01) such as: public working safety plan and public health, chemical and oil leakage management plan, urgent response plan. ii. CP04 has completed 90% with application of the overall environmental monitoring system and direct monitoring in site of VINACONEX, CENMA. Regarding CP04, staffs in charge of environment are assigned as bridges for management and settlement of issues related to environmental sanitation and working safety between the CMC contractor and other relevant parties. Contractor of the package is Vinaconex. The Company has developed the EMP with supporting of SYSTRA (Project Implementation Consultant) and Hanoi Centre for Environmental and Natural Resources Monitoring and Analysis (CENMA) to implement environmental monitoring program. Detailed requirements in implementation of EMP were brought into bidding document and contract with Vinaconex. The contractor prepared and submitted EMP to MRB before construction time. During infrastructure (CP04) building, environmental monitoring activities are carried out by independent consultant. During construction of CP04, CENMA implements environmental quality monitoring activities. iii. Regarding CP05, HANCORP requested SYSTRA to develop EPM and SEP (ref. HPMLP/CP05). Environmental Management Plan was completed and submitted to MRB on 8/4/2013, but this time was late (4 weeks after construction). CP05 started since April, main items under CP05 have not been implemented by HANCORP. The Company signed the Contract with SYSTRA to implement the environmental management plan activities. iv. CP01, CP02 and CP03: are under bidding process.

26. Semi-annual report June/2013 based on the results of monthly environmental monitoring report at Depot site from May to June, 2013 (more detail the results of monthly reports at index 3 and index 4).

27. Grievance Redress Mechanism (GRM) i. In accordance with requirements in Protection Policy Statement of ADB (2009), MRB prepared one chapter of Grievance Redress Mechanism (chapter VIII in Environmental Impact Assessment Report of August 2010) in which the law, grievance redress, basis for the application of settlement of damages caused by activities, and monitoring of the Project was stated. GRM was presented clearly in accordance with Vietnamese regulations such as: - Meet requirements in accordance with regulations in item 8, article 20 of Environmental Protection Law passed on 29/11/2005 by the Socialist Republic of Vietnam - Meeting requirements of the Circular number 26/2011/TT-BTNMT dated 18/07/2011 of Ministry of Natural Resources and Environment stipulating in detail some articles of the Decree No. 29/2011/ND-CP

PAGE 6

dated 18/04/2011 of the Government which stipulates strategy environmental assessment, environmental impact assessment, environmental protection commitment; - Decision number 80/2005/QD-Tg of the Prime Minister on 18/4/2005 stipulating regulations for public monitoring - Decree no. 79/2003/NC-DP of the Government on democratic implementation regulations at public level; - Decision no. 34/2007/PL-UBTVQH11 dated 20/4/2007 of Parliamentary standing committee on implementation of democratic regulations at ward, commune level - Resolution no. 09/2008/NQLT-UBTWMTQVN of the Government- Vietnam Fatherland Front Committee dated 17/4/2008 on guidance of implementation of articles 11, 14, 16, 22 and 26 of democratic implementation at ward, commune and town level Besides, public consultation for environmental impact assessment of the project must satisfy requirements of safety, health and environment policy of ADB. ii. MRB and consultant have not developed GRM at project level The project commits to comply with Vietnamese law and issues relating to GRM; however, in accordance with ADB’s regulations, GRM at project level still needs to be implemented. At present, MRB is organizing GRM at project level with main contents as follows: When construction starts, contractors organize reception division to record claims. Claims (if any) of the public shall be reported to MRB by contractor within 24 hours. Contractor publicizes name and telephone number (including hot line) of reception staff. If claims are not settled at contractor level within 02 days since the date of claim letter, they shall be settled in accordance with compensation, claim mechanisms in legal system described in Environmental Impact Assessment report. iii. The fact shows that MRB has so far not received any claims (oral or written) on environmental issues of local residents and/or relevant parties as done package (CP04). iv. In coming months there shall possibly have claims of public on environmental issues in next packages. MRB shall follow Vietnamese law to review and settle them. Implementation measures shall comply with ADB’s policies.

2.2. Environmental compliance requirements situation of the Government

28. Project documents, letters relating to environment i. Environmental management plan was developed in three bidding documents (CP05, CP01, and CP02) of the project. Besides advantages of Environmental Management Plan, there are restrictions that should be overcome: Although environmental impact of packages is not similar, 3 environmental management plans have the same. In order to solve this problem, MRB submitted the final Environmental Management Plan guided by ADB to the Donors again on 20 June 2013. Due to the CP05 was signed between MRB and Contractor (HANCORP) it is under implementation. This modification was done as the Contract Appendix of CP05’s bidding document. The Contract of CP01 and CP02 has not yet signed between MRB and Contractors so all environmental compliance requirements of ADB cleared in EIA shall be included in EMP of each bidding contract. ii. CP-04 has completed 90% of the works, included list of environmental

PAGE 7

management plan contents.

29. For CP05’s EMP, after modification was done as the Contract Appendix of CP05’s bidding document which is approved by MRB.

30. The following are the environmental quality standards and regulations based on the Vietnam Standards promulgated by the Ministry of Science, Technology and Environment: i. QCVN 05:2009/BTNMT - National technical regulation on ambient air quality ii. QCVN 26:2010/BTNMT - National standard for Noise iii. QCVN 27:2010/BTNMT - National standard for Vibration iv. QCVN 08:2008/BTNMT - National standard for surface water quality v. QCVN 09:2008/BTNMT - National standard for underground water vi. QCVN 24:2009/BTNMT - National standard for waste water quality

31. Equipment certificates for compliance with National environmental specifications of CP05 has not checked yet because they stared to work on April and the construction work is Temporary work office of CP05 at the Depot site.

3. CHANGES IN PROJECT SCOPE

32. There are no changes in the scope as well as implementation items of the contract packages.

33. The project progress is generally as scheduled; however, the packages CP01 and CP02 were delayed for 1.5 to 2 months due to the Solar and Lunar New Years.

4. INCORPORATION OF ENVIRONMENTAL REQUIREMENTS INTO THE PROJECT CONTRACTUAL ARRANGEMENTS

34. Contract agreement, the manner in which EMP requirements are included in the contract agreements such as contract with contractors or other relevant parties.

4.1. Evaluation on function and responsibility of organization and implementation of environmental safety

35. MRB has considered and implemented environmental protection issues for project packages, including the construction and implementation of the general Environment Management Plan (EMP) and specific site environmental plan (SEP) as committed in the Environmental Impact Assessment report-ABD/2010. i. MRB’s main activities that are related to EMP activities include: - Establishing Environmental Committee which is responsible for ensuring timely implementation of EMP, including monitoring, reporting, and building capacity related to the safety - Assisting Construction Supervision Consultant (CSC) and concurrently responsible for monitoring the contractor’s implementation of environmental safety as part of the construction contract (this requirement will be included in the Terms of Reference (TOR of CSC); and - Employing competent local consultants as Independent

PAGE 8

Environmental Management Consultants (IEMC) to perform the task ii. MRB is responsible for ensuring that the related parts in the contract documents of the packages of the project items shall comply with the Environmental Management Plan (EMP) iii. MRB takes responsibility for contacting with agencies, local authorities and relevant units that are responsible for implementing and monitoring EMP, particularly with Department of Natural Resources and Environment and the wards and communes within the project area, for implementing EMP. iv. As for the monitoring of contractors’ activities, MRB shall be responsible for: - Checking the project implementation index related to environmental issues - Carrying out unscheduled examination to ensure the contractor is taking mitigation measures as specified in construction contract - Reviewing CSC’s periodical reports to ensure their compliance with mitigation measures v. MRB performed well in their role as a coordinator between the Environmental Supervision Consultant and Construction Supervision Consultant and the contractor in the environmental monitoring.

36. The contractors’ compliance with environmental protection regulations was assessed to be serious, which is detailed as follows: i. The construction contractor is responsible for all environmental activities specified in the contract between the contractor and the MRB. ii. The construction contractor is responsible for performing measures to mitigate environmental impacts and conforming to the EMP approved during the construction of the project’s packages. During the preparation of technical proposals, the contractor is allowed to study the EIA report and propose in their document an environmental management plan, including environmental protection and environmental impact mitigation measures in accordance with the Project’s approved environmental impact assessment report. However, since the EIA-ADB 2010 report must be revised and supplemented to be conformable to a number of Vietnam’s new environmental management regulations, the suitability of the EMP developed by the contractor (CP01, CP02, CP04 and CP05) is restricted. iii. The contractor prepared EMP. The contractor assigned their employee to manage environmental plan and labour safety. This employee directly carries out environmental mitigation and labour safety measures as specified in the approved environment plan. The environmental management plan of the Contractor was submitted to MRB and sent to CSC and IEMC for review. Changes (if any) shall be assessed in terms of feasibility and legally (laws, decrees, circulars and other regulations) before proper revisions are approved for specific cases at site. iv. As committed, the Contractor monthly submits progress reports enclosed with environmental sanitation and labour safety measures to the CMC and the Project Management Board. The results of observation of CP04 and CP05 at the Depot site likes that: - The contractor performs weekly inspection of the construction site to determine the compliance with environmental requirements - The contractor supervises once per month the implementation of EMP and the compliance with the environmental management plan.

PAGE 9

v. During the construction, the construction contractors received the coordination and supervision of MRB, CSC, Independent Environmental Supervision Consultant (Idom), environmental management agencies, and local community on the compliance with EMP.

37. Evaluation results for environmental monitoring activities of CMC shows that CMC has taken seriously the weekly and monthly monitoring reports on environmental sanitation and labour safety issues at site. Besides, CMC has also performed well its roles and functions in environmental monitoring, namely:

i. CMC (Construction Monitoring Consultant) acts as a direct controller and supervisor based on a mitigation plan that was made by the contractor and approved with relevant parties. CSC is responsible for monitoring the implementation of safety policies of the contractor during the construction process and GPM, including keeping track of the self-monitoring process of the contractor. CSC supports IEMC to collect and provide the information on environmental indicators at site and project implementation information; ii. CMC supervises the implementation of mitigation measures of the contractor, timely propose and implement mitigation measures to meet the safety protection requirements on the environmental management of the project; action plans/ emergency plans to cope with environmental issues, emergencies and losses that may occur during the construction. Each package is assigned to each direct supervisor at site who weekly assesses the effectiveness of labour safety and environmental sanitation measures at each site. iii. CMC takes part in weekly examinations and monthly supervisions and regular meetings co-organized by the project-related parties to provide the project implementation information and necessary working programs to raise awareness of the environmental protection during the project construction. iv. Monthly, CMC submits the progress report enclosed with environmental sanitation and labour safety measures of the packages to the Project Management Board. In addition, as problems arise, CMC sends directly a dispatch to notice the Project Management Board and related parties to solve together. The environmental monitoring forms were done fully by CMC and environmental impact mitigation measures were incorporated in the construction progress reports.

38. Implementation of EMP of CP04 and CP05

i. The EMP was developed by the contractor VINACONEX and approved by MRB and ADB. ii. The consulting firms performed regular environment monitoring. iii. During the construction, the Contractor strictly complied with the requirements on environmental protection. iv. There is no complaint from local residents about the waste impact on the air environment, noise and vibration pollution. v. There have so far been no any accidents at the construction site CP04 and CP05. The health care for labourers was contracted by MRB with the medical centre of Tay Tuu Commune. vi. However, the EPM content of the package CP04 still excludes some issues, namely: some items have not mentioned yet or not expressed specifically as in the environmental impact assessment report-ADB 2010 such as: workers’ camp

PAGE 10

management plan, labour safety and public health plan, and emergency response plan.

vii. The mitigation measures required in the EMP are being partially implemented by the Contractor during April to June, 2013. The average ratio of the measures effectiveness is between 2 and 3 (in accordance to ADB rating system). The overall evaluation of the mitigation compliance given by the Consultant would thus be Fair (graded 3 in the rating system).

39. The Contractor in charge of package CP05 (HANCORP) submitted the EMP to MRB on April 2013. But the content of the required mitigation measures in the CP05’s EMP in the bidding document is not consistent with the EMP included in the EIA cleared by ADB. Due to the CP05 was signed between MRB and Contractor (HANCORP) and its under implementation thus MRB, Systra and HANCORP modified EMP as the contents and format of ADB guided. This modification has done as the Contract Appendix of CP05’s bid document by Systra. On the other hand, CP05 just started their work on April 2013 and implementation progress has just constructed the temporary work office at the Depot of the CP05, this construction work is not effect to environment during this time. Monitoring of environment quality inside project area and its surroundings (the Depot site) in accordance with ADB’s and Vietnam’s regulations )

i. The package CP04 was contracted by the contractor with Hanoi Centre for Environmental and Natural Resources Monitoring and Analysis (CENMA) to observe/monitor environmental quality of the construction site and surroundings (According to the tendering schedule in the letter No.3277/QB-UBND dated July 5, 2010 by Hanoi City People's Committee). ii. CENMA carries out the environment quality monitoring within the project area and its surroundings from May 2012 to August 2013. Details are as follows: Keeping track of environmental indicators related to air quality, noise and vibration, water environment (surface water, groundwater) and soil quality via field surveys; locating sampling points; analysing and compiling monthly environment monitoring reports at three project areas (depot, viaduct, and tunnel). iii. Presently CENMA sent monthly reports to the MRB and the contractor on environment quality monitoring results at the Depot site from April to June 2013.

4.2. Outstanding issues of combining environmental requirements into contract agreement with contractors

40. Monitoring results shows that some requirements and impact mitigation measures proposed in the EMP by SYSTRA in the bidding document are still inconsistent with the requirements and mitigation measures in the Environmental Impact Assessment report- ADB/2010.

i. The inconsistence between the EMP by SYSTRA in the bidding document and the environmental impact assessment report-ADB/2010 causes difficulties to the contractor during their implementation of the environmental protection plan as well as their assessment of the package’s compliance with this plan. For example: For the packages CP01 and CP02, some specific environmental management plans which were committed in the EPM of EIA-ADB/2010 were not showed in SEP of the package CP01 (viaduct) and do not show requirements on: workers’ camp management plan; labour safety and public health plan; oil leakage management plan; and emergency response plan. ii. Besides, some impact mitigation measures stated in the environmental impact assessment report - ADB (February 2010) are not included in the EMP in the

PAGE 11

bidding documents of CP01 and CP02, such as air pollution and noise control measures during the construction; sediment control measures at Thu le Lake during the construction; measures to minimize social conflicts during the construction, etc. iii. In fact, to meet practical conditions, the EMP developed in the bidding document may be somewhat different from the commitments in the EPM in EIA. However, these changes need to be carefully considered on the basis that higher environmental protection effectiveness must be obtained and consent of Hanoi People’s Committee and MRB must be reached.

41. Although the packages CP01, CP02, CP04, and CP05 are different in construction, natures and level of impact, EPM and SEP contents are considered and assessed by ADB’s environmental experts to be similarly developed. This is not consistent with the reality as well as with the contents stated in the EPM in the report EIA-ADB 2010.

42. International consulting firms and other related agencies implement the environmental monitoring. However, the project environment monitoring at site has not been furthered implemented by the independent environmental monitoring consultant since April 2012.

i. Coteba, international independent environmental consulting company, recently named as Artelia Ville & Transport, already performed the environmental monitoring at the construction site for six months, from November 2011 to April 2012. ii. The main activities Coteba performed during the environmental monitoring at the construction site include: - Reviewing monitoring obligations stipulated in the Environmental Impact Assessment report - Reviewing the general environmental management plans (for example, strategic planning, specific environmental management plan namely dust control, noise control plan, etc.) developed by the construction contractor; monitoring the implementation of commitments to minimize environmental impacts defined in the EMP - Preparing the monthly environmental monitoring reports for MRB and related donors AFD and ADB - In addition, Coteba also provided for HRB’s assessment the terms of reference for air, water and land monitoring activities and the final implementation of CENMA along the railway iii. Since April 2012, the implementation of environment monitoring activities at the construction site by the international independent environmental consulting company has not been continued. Currently, Idom is continued the deployment of this content

5. SUMMARY OF IMPLEMENTATION OF ENVIRONMENTAL IMPACT MITIGATION AND COMPENSATION MEASURES

43. During the construction of CP04, the contractor observes strictly the requirements on environmental protection and waste management during the construction.

i. Dust pollution control: During dry days, water twice or thrice at the surroundings of residential areas and entrance road to construction site

PAGE 12

ii. Noise and vibration control: Noise and vibration level are lower than the allowable level in Vietnamese standards iii. Flood control and prevention: The structure plan is designed at the ground level from 0.8 to 1.0 m higher than the regional ground level. However, it does not cause inundation to residential areas and neighbouring farming areas since storm water is collected into the drainage system and flows into the lakes in the project area iv. Wastewater control: Domestic wastewater by officials and workers at site is treated by septic tanks. The construction site is equipped with two double toilets. Sanitary waste is treated by underground septic tanks v. Sewage from the construction site CP04 and workers’ camps flows along the southern boundary, adjacent to the Road 70 vi. Solid waste control: Daily solid wastes and solid wastes from buildings are collected into containers every day. Then they will be transported for treatment along with the city wastes by local hygiene team (contracted with the package) vii. Toxic waste management (mainly oil): Toxic solid wastes at the package CP04 are mainly stamps in small quantities. The management of toxic wastes in the package CP04 was well performed as committed in the EIA. Toxic wastes arising after each work shift will be collected in barrels for treatment (employing relevant units to collect and process waste in accordance with the Vietnamese provisions stated in the Circular 12/2011 on toxic waste management) viii. The contractor provides enough safety equipment for workers (protective helmets, clothing, and shoes, etc.) and requests them to use this equipment. The Contractor conducts a safety training program every two months for workers ix. Fire and explosion control: Keep only about 200 litres of oil at the construction site. Fuel for machinery and trucks must not be stored at the construction site but taken from the town's petrol stations (close to the project area) instead x. So far, there have been no fire and explosion accidents or incidents at the package CP04.

44. Waste management at workers camps

i. Environmental sanitation at workers’ camps: The contractor built nine worker camps in the area close to Hanoi University of Industry. Each camp can accommodate 30 to 40 workers. In peak construction months, more than 200 workers live in camps. ii. Workers camps are located at low-lying area that was levelled with sand. This is an important factor contributing to improving the sanitary condition. iii. However, the surrounding area of the camps still has stagnant puddles of wastewater, and the drainage without covers are not concreted and covered by grass, which causes unpleasant odours and creates favourable environmental conditions for flies and mosquitoes. iv. At the camps, water tanks (about 10 m 3) were built to store freshwater for workers to bathe and wash. However, these water tanks have not been used and become a place to keep stagnant rainwater and even wastes, which causes pollution and affects badly to landscape. v. There are only few pumps to supply water to the camps, and they are located in

PAGE 13

low positions. At worker’s camps, there are two drilled wells (30 to 40 m deep) to supply domestic water for workers. They will become overloaded if there are too many workers (over 70 people). Besides, the faucets are placed too low (less than 1 m from the ground), which causes dirty water splash into buckets and basins during water obtainment. Therefore, the faucets should be raised (approximately 1 m) for convenience and hygiene when used. vi. The package CP04 is coming to an end and under the completion stage, thus, there are not many workers living in camps. Therefore, environmental sanitation problems in camps may not be settled as a matter of priority. However, it is necessary to improve this issue if the package CP05 uses this area as camps for their workers. vii. At the camps, there are two public toilets with many rooms. viii. At the camps, there are two kitchens but no canteens. Food safety is performed well without diseases or cases of food poisoning due to unsafe food.

45. Overall evaluation of waste management measures in CP04

i. In general, the contractor performed well the pollution control and environmental protection measures during the construction. ii. However, a number of mitigation measures have not been fully applied namely solid waste control and environmental sanitation control in the workers’ camps.

6. SUMMARY OF ENVIRONMENTAL MONITORING

6.1. Compliance inspections

6.1.1. Summary of inspection activities

46. In accordance with the requirements of the EIA (August 2010), the Contractor in charge of the package CP04 (Vinaconex) submitted the corresponding EMP, which included the organization chart of the Environmental Unit of the Contractor shown in the figure below.

Environmental and Safety Manager Mr Pham Dinh Khanh

Mr Nguyen Van Dinh Mr Nguyen Van Nghia Mr Nguyen Van Mr Nguyen Dac Linh Team Leader of Team Leader of MinhTeam Leader of Team Leader of Construction N o 1 Construction No 2 Construction No 3 Construction N o 4

Figure 1. Organization for Environmental Management of CP04

47. The Contractor in charge of package CP05 (HANCORP) submitted the EMP to MRB on April 2013 that included an Environmental Unit organization chart shown in figure below.

PAGE 14

Environmental and Safety Manager Mr Vu Ngoc Hong

Environmental Responsibility Manager Mr Pham The Giang

Noise and vibrations Site Waste manager Environmental Support Team Leader of monitoring staff Mr Pham The Giang staff Construction teams Mr Dang Vu Hung Mr Bui Nguyen Pho

Figure 2. Organization for Environmental Management of CP05

i. VINACONEX is the contractor who submitted the overall environmental management plan (EMP). The contractor assigned an environmental health and safety team including 01 manager (Mr. Pham Dinh Khanh) and four environmental officials (EO) in charge of each construction item.

ii. The EMP of CP05 has to be noted that according to the conclusion given by ADB on 12 June 2013, the content of the required mitigation measures in the CP05’s EMP in the bidding document is not consistent with the EMP included in the EIA cleared by ADB. In order to solve this problem, MRB submitted the final Environmental Management Plan guided by ADB to AFD and other donors again on 20 June 2013. Due to the CP05 was signed between MRB and Contractor (HANCORP) and its under implementation thus MRB, Systra and HANCORP modified EMP as the contents and format of ADB guided. This modification has done as the Contract Appendix of CP05’s bid document by Hancorp and Systra.

iii. Regarding the Environmental Awareness, both Contractors are aware of the mitigation requirements and they are willing to implement them as instructed in the EMP. The Contactor of CP04 has the corresponding copy of the said EMP, whereas the Contractor of CP05 is waiting for the approval EMP. Both contractors agree to accept the regulatory requirements and their updates from time to time.

6.1.2. Compliance with impact mitigation measures

48. The Environmental Management Plan of the Contractor proposed specific environmental impact mitigation measures The Contractor’s compliance level with mitigation measures during their construction is monitored by the Consultant.

49. According to the observations made during April to June and to the information received from Vinaconex and Hancorp the Package CP04, CP05 complies with the mitigation measures during the construction. On the other hand, CP05 just started their work on April 2013 and implementation progress has just constructed the Temporary work office at the Depot of the CP05

i. Building materials are neatly gathered at the temporary storage areas in the project area, not hindering the remaining under-construction items. ii. The surrounding area of the construction site is fairly clean and neat. iii. The contractor complies with labour safety regulations. Storm water and wastewater canals of the project are carefully covered after the construction.

PAGE 15

iv. The storage system of building materials is carefully organized. v. The coordination between the contractor and MRB is regularly maintained so that environmental and labour safety issues are timely settled. vi. The environmental monitoring samples were fully prepared by CENMA and environmental impact mitigation measures were also incorporated into construction progress reports; vii. Trucks for soil and sand transport are carefully covered before departing construction site.

50. Outstanding issues:

i. Workers' camps do not meet the environmental sanitary requirements. Daily domestic wastewater of workers is directly poured into canals and ponds at the camps, which exposes potential risks of diseases.

ii. As the entrance road to construction site is relatively narrow and is overcrowded with residents on both sides, the contractor needs to increase watering to avoid dust when material trucks pass through.

iii. It is necessary to promote the contract signing to hire the disposal area for dumping mud and land which are still stored in the project

iv. Improve the efficiency of communication channels between the ward and contractor in supporting the locality to dig drainage channels in the residential area (outside the Project).

51. The EMP is included in the EIA and provides a comprehensive list of mitigation measures to be implemented during construction of the Depot. This list is a backbone for the environmental measures to be observed by the Consultant, and gathers the main activities to be monitored.

52. Monitoring results of compliance with environmental impact mitigation measures at the Depot site are evaluated in the Table below.

YES LEVEL OF LEVEL OF MITIGATION MEASURES OF FIELDS MITIGATION MEASURES FROM EMP / COMPLIANCE COMPLIAN * OBSERVED NO * MAY/2013 JUNE/2013 Watering of the site with Strictly implement approved dust Air quality YES portable water tanks 2 2 control Plan loaded on the trucks Use electrically-powered equipment Using concrete-mixer rather than gas or diesel-powered YES 2 2 electricity equipment The sensitive receptors are located at reasonable Stationary emission sources as far YES distance from the 1 1 as possible from sensitive receptors potential stationery emission sources Only vehicles and equipment that Environmental & Safety are registered and have necessary YES managers of the 3 3 permits Contractors follow up this Could not observe at the Burning of wastes prohibited - - - site Construction equipment and All equipment and vehicles well-maintained and YES vehicles seem in good 2 2 compliant with national QCVN condition emission standards

Stockpiles moist and vehicles YES All equipment and 2 2

PAGE 16

YES LEVEL OF LEVEL OF MITIGATION MEASURES OF FIELDS MITIGATION MEASURES FROM EMP / COMPLIANCE COMPLIAN * OBSERVED NO * MAY/2013 JUNE/2013 covered by tarpaulin sheets vehicles seem in good condition Provide temporary covers (e.g., Materials to be used in tarpaulins, grass, etc.) on long term - long term are properly - - materials stockpiles stocked at the site Concrete mixing zone >100 m from Using precast concrete - - - nearest residential area from Tay Mo, My Dinh Wheels of the vehicles Clean road surfaces of debris/spills YES are cleaned before exiting 2 2 the site Watering of the site with Spray water on the exposed YES portable water tanks 2 2 surfaces to reduce dust emission loaded on the trucks All construction equipment and At this time all equipment machinery with emission control YES working at the site seem 2 2 equipment in compliance with the in good condition national and local regulations Fuel-efficient and well-maintained YES Same situation observed 1 1 trucks accepted only Speed limits in critical zones YES Same situation observed 2 2 Stockpiling material >100 m from the The Depot site is far from NA - - nearest residence residential area Immediate repairs of malfunctioning Could not observe at the - - - vehicles and equipment site Prior notification to the community NA - - on schedule of construction activities 24 hour community complaints YES Person in charge 2 2 hotline Strict implementation of Noise YES No noise impact 2 2 Control Plan All construction equipment and Only 05 Trucks, 05 vehicles with appropriate noise YES Excavator, 05 road roller 1 1 suppression equipment, compliant are working at the site with national regulations Use only vehicles and equipment Environmental & Safety that are registered and have YES managers of the 3 3 necessary permits Contractors follow up this All works are stopped at No noisy activities during night time YES 1 1 night Noise It must be used when No use of horns - - - urgent case Provide mitigation noise barriers? if YES 2 - noise levels too high Adapt work method for noisy YES Noise is well controlled 2 2 activities (sequential use) No noisy activities near schools Could not observe at the - - - during examination period. site Prior notification to the community NA - - on schedule of construction activities Risk still very low due to Strict implementation of Spill Hazmat YES limited amount of 2 2 Management Plan hazardous at site Fuel and Hazmat in dedicated Presenting storage at the YES 2 2 storage areas site YES Could not observe at the Availability of spill clean-up materials - - site Training of personnel for Hazmat YES Could not observe at the - - and spill control procedures site

PAGE 17

YES LEVEL OF LEVEL OF MITIGATION MEASURES OF FIELDS MITIGATION MEASURES FROM EMP / COMPLIANCE COMPLIAN * OBSERVED NO * MAY/2013 JUNE/2013 All storage containers are in good YES Could not observe at the - - condition with proper labelling site Regular check of containers for YES 2 2 leakage It is always right because Storage of hazardous materials the elevation of the Depot - - - above flood level site is 0.8-1.0 m higher than the local elevation. Equipment maintenance areas with Could not observe at the drainage to oil separator well - - - site maintained Management of Hazardous waste (storage, transport and off-site YES Oil 2 2 disposal) compliant with national and local regulations No contamination risk for back-up Back-up well is not - - - well necessary Drainage system adapted during construction with No impediment of natural drainage YES temporary drains 2 2 ditches discharging to the surface water Waste water is found in drainage channels inside the site and workers camp No waste discharge in drainage area. Grey water drained Drainage YES 4 4 channels to ditch of road which is opened sewer. Quality of impact should be checked. Provide where necessary alternative YES Drainage system 2 2 drainage for rainwater Regular inspection and maintenance By CENMA but should be YES 4 4 of drainage network checked more often Garbage bins is in Garbage bins and facilities within construction office but not project site for temporary storage of enough in worker camps. YES 3 3 construction waste and domestic Solid waste (plastic bag solid waste spread around kitchen and worker camp Manage solid waste according to type & store temporarily on site in Due to the low worker secure facilities (weather proof awareness solid waste YES 3 3 Solid flooring and roofing, security fencing spread around kitchen waste and access control, drainage and workers camp manage- collection system) mint. Contractor signed contract Ensure no waste is illegally dumped YES with URENCO Hanoi 3 3 within/outside project site /NO NO/At worker camps A large part of solid wastes at construction Regular collection and disposal of site which was collected wastes to approved sites by local YES - 3 by a local sanitation authorities. company to a local approved disposal site. Immediate repair any damage to community facilities (water supply & No damage of community Damage NA - - to sanitation, power supply, facilities occurred communit communication, etc.) y facilities No observed (continue Access roads damaged during - - - construction shall be rehabilitated checking)

PAGE 18

YES LEVEL OF LEVEL OF MITIGATION MEASURES OF FIELDS MITIGATION MEASURES FROM EMP / COMPLIANCE COMPLIAN * OBSERVED NO * MAY/2013 JUNE/2013 upon completion of works

Strictly implement approved Traffic NA Not applicable - - Management Plan No any traffic occurred Post traffic advisory signs in NA during the Depot - - coordination with local authorities construction Road traffic Schedule delivery of construction materials and equipment during non- NA Not applicable - - peak hours Monitoring of traffic conditions along access roads to ensure that project NA Not applicable - - vehicles are not causing congestion Implement approved Occupational and Community Health and Safety Health and Safety: YES YES 2 2 Plan, and approved Emergency /NO Community Health: NO Response Plan Appoint an EHS manager YES Only one manager of EHS 2 2 Conduct induction training for construction workers regarding EHS During the time of site measures, emergency response and NA visit don’t has any training - - prevention of HIV/AIDS and other for Contractors related diseases Provide first aid facilities that are Not all work camps, only YES - 3 readily accessible by workers some have Provide fire-fighting equipment at the Only watering truck for work areas and at construction YES dust considered. No 3 3 camps extinguishers available Provide adequate drainage in Drainage channels very workers camps to prevent stagnant NO bad, stagnant water 4 4 water and formation of breeding remaining sites for mosquitoes Provide adequate housing for all YES Poor 3 3 workers at the construction camps Public In the office and workers Reliable supply of potable water YES 2 2 and buy bottled water occupatio Only canteen at office Clean canteen/rest area YES 2 2 -nal area health Separate hygienic sanitation It is separated two areas and facilities/toilets and bathing areas (male and female). safety with sufficient YES 4 4 Bathing tank: cleaned and water supply for male and female filled workers Collection and disposal of solid Solid waste (Plastic bags) waste within the construction camp NO spread around kitchen 4 4 consistent with local regulations and worker camp Fencing of all areas with excavation All activities excavated YES - 1 >2 m deep lower than 2 m deep Appropriate personal protection equipment (PPE): safety boots, Helmet: ok; Other PPE: helmets, gloves, protective clothes, YES 2 2 ok breathing mask, goggles, and ear protection Reversing signals installed on all Few vehicle observed at YES 2 2 construction vehicles site Prevent fall of equipment/tool NA - - Implement fall prevention and protection whenever a worker is Not for CP04, exposed to the hazard of falling NA In case need: CP05 will - 2 more than 2 meters, of falling into be put the safety belts for operating machinery or through an all workers of CP05 opening: installation of guardrails

PAGE 19

YES LEVEL OF LEVEL OF MITIGATION MEASURES OF FIELDS MITIGATION MEASURES FROM EMP / COMPLIANCE COMPLIAN * OBSERVED NO * MAY/2013 JUNE/2013 with mid-rails and toe boards at the edge of any fall hazard area, proper use of ladders and scaffolds by trained employees, use of fall prevention devices, including safety belt and lanyard travel limiting devices to prevent access to fall hazard, fall protection devices Appropriate location of construction camps: far from communities and YES 1 1 avoid using communities resources Social (water supply, etc.) conflict This area is capital, so all Maximize number of workers from with NA peoples can have other - 1 local communities workers jobs with higher income Maximize goods and services Not applicable for this sourced from local commercial NA - 1 project enterprises Table 4: Mitigations Measures Required by EIA & EMP During the Construction Period at Depot Site

* Level of Compliance (Indicative examples) 1. Very Good (all required mitigations implemented) 2. Good ( the majority of required mitigations implemented) 3. Fair (some mitigations implemented) 4. Poor (few mitigations implemented) 5. Very Poor (very few mitigations implemented) NA Not Applicable - Not identified 53. The mitigation measures required in the EMP are being partially implemented by the Contractor. The average ratio of the measures effectiveness is between 2 and 3 (in accordance to ADB rating system). The overall evaluation of the mitigation compliance during May to June, 2013 (Consultant has just mobilized since April so the consultant activities during the April focused on reviewed documents and the at-a-glance assessment of the environment surrounding of the Project site) given by the Consultant would thus be Fair (graded 3 in the rating system.)

6.2. Emission Monitoring Program (if related to or required in EMP)

6.2.1. Summary of monitoring results at the Depot site

54. Environmental Monitoring Program is proposed in the Environmental Impact Assessment and Environmental Management Plan. The contractor shall be responsible for complying with relevant regulations, and one of the monitoring tasks is to ensure the compliance with environmental regulations.

55. Emission Monitoring Program is implemented by CENMA at 4 monitoring points including 1 point of air environment quality, 1 point of noise level, 1 point of vibration; 1 point of wastewater.

6.2.2. Results

56. Summary of environmental quality monitoring results during the period from April to June 2013

i. Air Pollution The monitoring point KXQ1 (Located in the North-eastern corner of Depot) has good ambient air quality, the parameters for ambient air monitoring are lower than the allowable limits in the National Regulation (QCVN 05:2009 -

PAGE 20

Vietnamese Code on Ambient Air Quality). ii. Noise and vibration Noise monitoring results are also made at the monitoring site of KXQ1 as for the air environment. Equivalent sound level measured from 6 am to 9 pm ranges between 51.6 and 61.7dBA, higher than the allowable limits at some of the measurement periods. 31/48 measurement times (64.6% of the total measurement times) on January, 20/48 measurement times on February (42% of the total), 30/48 times (62.5% of the total) on March, 25/48 times (52% of the total) on April, 23/48 times (48% of the total) on May and 27/48 time (56% of the total) on June 2013. iii. Vibration at Depot Vibration acceleration measured from January to June 2013 varies from 33.7 to 47.6 dB, lower than the allowable limit in the National Regulations of Vietnam (75 dB). iv. Wastewater Coliform parameter is 2.4 times higher than the National Regulations of Vietnam 14: 2008. Other parameters are all below the allowable limit of the Regulation.

6.2.3. Evaluation

57. The pollution level should be compared with the relevant emission standards and/or the performance indicators noted in the EMP. All excessive pollution needs to be considered and monitored. In addition, the emission level can be compared with basic conditions (if the database is available) and described about the quality or evaluated on the base of ranking system as follows: 1. Very good. 2. Good. 3. Average. 4. Not good. 5. Bad.

Sampling Sign of Coordinates Environmental No Location features point sample Longitude Latitude quality ranking

1 Ambient air KXQ1 0576581 2328785 The first air sampling 1 point is located at the upwind direction of Depot (station), in the Northeast, bordered with the field of flowers, far from the reservoir of Depot about 120 m

2 Noise KXQ1 0576581 2328785 As above 3

3 Vibration KXQ1 0576581 2328785 As above 1

4 Wastewater NT1 0576582 2328784 The wastewater 4 sampling point at irrigation canals is available and located in the Depot area, near the position of KXQ1

Table 5. Features and environmental quality ranking of sampling points for monitoring emission for the Depot site

PAGE 21

6.3. Summary of surrounding Environment Monitoring Program of the Depot site (air quality, noise, water quality, etc.)

6.3.1. Summary of environment monitoring activities

58. Surrounding environment Monitoring Program is implemented by CENMA at 5 monitoring points including 1 point of air environment quality, 1 point of noise level, 1 point of vibration; 1 point of surface water, 1 point of underground water. Specific information about the monitoring points is shown in the table.

6.3.2. Results

59. Summary of environmental quality monitoring results from January to June 2013

i. Air pollution The monitoring point of KXQ2 (West of Depot, at the main entrance and about 10 m away from Road 70) has signs of pollution. The total suspended particulates (TSP) in some measurement periods exceed the allowable limits in the Vietnamese standard: 1.04 to 1.11 times higher than the allowable limits. Benzene concentration parameters during some measurement also exceeded the allowable limits in the Vietnamese Standard, 1.01 to 1.08 times higher. Dust concentrations PM10 and PM2.5, lead dust cannot show the pollution level specifically because Vietnam does not currently have standards for the comparison (within 1 hour). In summary, the ambient air quality during six months including January to June 2013 showed the monitoring point of KXQ2 had signs of dust pollution (TSP), benzene. CENMA explains that the reason is due to direct impacts from the transport activities on the construction site and the Road 70. ii. Noise Equivalent sound level measured from 6 am to 9 pm ranges between 51.6 and 61.7 dBA, higher than the allowable limits at some of the measurement periods. 31/48 measurement times (64.6% of the total) on January, 20/48 measurement times on February (42% of the total), 30/48 times (62.5% of the total) on March, 21/48 measurement times (43.5%) on April, 23/48 measurement times (48%) on May and 22/48 measurement times (46%) on June 2013. iii. Vibration Vibration acceleration measured during three months from January to June 2013 is from 33.7 to 47.6 dB, and lower than the allowable limit in the National Standard of Vietnam (75 dB). iv. Surface water The monitoring results of lake water in Depot on January 2013 show that the lake is contaminated in comparison with the required standards. The oil content (Jan/2013) is 5 to 6.1 times higher than stated in 08:20081 BTNMT. Nitorit content is 2.9 to 3.1 times higher than stated in 08:20081 BTNMT. Finally, COD content is 1.03 to 1.7 times higher than stated in 08:2008 BTNMT. According to CENMA, the reason is that the lake water has remained stagnant for a long time. In February, March and April 2013, Hanoi Centre for environmental and natural

PAGE 22

resources monitoring and analysis did not take samples because the lake water in the Depot was being suck dry for the dredge. v. Groundwater The monitoring results of groundwater during three months including January, February and March 2013 showed that the groundwater was contaminated with Ammonium, specifically 1.9 to 2.2 times higher on January 2013; 5.7 to 5.2 times higher in February 2013, 1.6 to 1.8 times in March 2013, and 2.4 to 2.5 times in April 2013. On February 2013 alone, the observation results also showed that the groundwater was polluted with Manganese (1.59 to 1.62 times higher than the allowable limits).

6.3.3. Evaluation

60. The pollution level should be compared with the relevant emission standards and/or the performance indicators noted in the EMP. All excessive pollution needs to be considered and monitored. In addition, the emission level can be compared with basic conditions (if the database is available) and described about the quality or evaluated on the base of ranking system as follows: 1. Very good. 2. Good. 3. Average. 4. Not good. 5. Bad.

Geographic No Sampling Sign of Environmental coordinates Location point sample quality ranking Longitude Latitude

1 Ambient air KXQ2 0576067 232858 In the West of Depot, at the 3 9 main entrance to Depot and 10 m away from the Road 70

2 Noise KXQ 0576581 232878 As above 3 5

3 Vibration KXQ2 0576581 232878 As above 1 5

4 Surface NM1 0576005 232878 The surface water sampling 4 water 3 point at the reservoir (circle) is located in Depot.

5 Groundwater NN1 0576481 232849 The groundwater sampling 3 9 point at workers’ camps in the construction site of Depot is located behind the dormitory of Hanoi University of Industry.

Table 6. Signs, features and environmental quality ranking of sampling points for monitoring surrounding environment of the Depot site

6.3.4. Overall evaluation of the environmental quality monitoring activities by CENMA

61. Environmental Monitoring Program is proposed in the Environmental Impact Assessment and Environmental Management Plan. The contractor shall be responsible for complying with relevant regulations, and one of the monitoring tasks is to ensure the compliance with environmental regulations.

PAGE 23

i. The Promoter selected CENMA to perform the environmental monitoring of air, noise, vibration and water environment, including such items Depot, viaduct and tunnel construction site. ii. CENMA is a unit directly under the Hanoi Department of Natural Resources and Environment. The environmental monitoring results were performed through monthly reports by CENMA including the following contents: Providing monitoring results of the month, assessing the monitoring results and proposing measures on environmental impact mitigation caused by construction activities of the project (if any), planning the implementation of monitoring for the next month to propose MRB and related parties for the approval. iii. CENMA laboratory is equipped with modern and suitable equipment for sampling and analysis activities of environmental quality. Laboratory officials are qualified and experienced in the field of environmental monitoring and supervision. iv. Environmental Monitoring Program is proposed in the Environmental Impact Assessment and Environmental Management Plan. The contractor shall be responsible for complying with relevant regulations, and one of the monitoring tasks is to ensure the compliance with environmental regulations. v. CENMA provides environmental monitoring data, which was measured, analysed and reported monthly during the period from May 2012 and expected to August 2013. vi. The compliance with requirements on the measurement points as well as monitoring parameters in Depot is defined in the Environmental Impact Assessment and Environmental Management Plan (Chart of monitoring points in Depot is shown in Appendix).

62. CENMA provides environmental monitoring data, which was measured, analysed and reported every month during the period from May 2012 and (expected) to August 2013. Currently, only two packages (CP04 and CP05) are being implemented, so this report only uses the measurement data in Depot.

63. The compliance with requirements on the measurement points as well as monitoring parameters in Depot is defined in the Environmental Impact Assessment and Environmental Management Plan (the chart of monitoring points in Depot is shown as Index 1 and Index 2)).

64. CENMA supplemented more and more specific monitoring components than EIA- ADB/EPM

i. According to EIA-ADB, the environmental components that are not monitored include surface water, environment and wastewater. ii. These two environmental components were monitored and supplemented by CENMA. This supplementary wastewater monitoring activity is appropriate. iii. The lake (with area of 15.7 ha) within the construction site is selected as a surface water monitoring point. Due to being under the excavation and embankment construction, the water source here is unstable. Thus, there are no monitoring data for some months when the lake has no or very little water, no surface water in natural conditions.

65. Observation parameters

i. CENMA selected more parameters to monitor than the requested by EIA-ADB. Parameters for the atmosphere: O3, total dust, dust Pb, Benzen. For surface

PAGE 24

water: pH, DO, SS, COD, Bods (20°C), Ammonium, Nitr ite, Nitrate, Phosphate, oil, Chloride, Fluoride, Cyanide, Arsenic, Cadmium, Pb, Cr III, Cr VI, Cu, Zn, Nickel, Fe, Hg, Aldrin, Dieldrin, Endrin, BHC, DDT, Endosunfat (thiodan), Lindan, chlordane, Heptachlor, Paration, Malation, etc. ii. These parameters were selected to monitor the package because they are appropriate to the environmental standards issued in Vietnam. iii. For groundwater environment: pH, hardness, total solids, COD (KMnO4), Cl -, F -, - - 2- - NO 2 , NO 3 , SO 4 , S , Phenol, α total radioactivity and E. coli (Table below).

Environmental According to EIA-ADB Implemented by CENMA components

Air environment HC, CO, SO 2, NO x, dust and CO, SO 2, NO x, O 3, Total dust, Dust micro-climate parameters PM 10 & PM 2,5 , dust Pb, Benzen, HC

Noise Leq , Lmax , L 50 Vibration Velocity, acceleration and vibration frequency Surface water pH, SS, turbidity, BOD, pH, Dissolved oxygen (DO), Total suspended COD, DO, Oil, Coliform, solids, COD, BOD5 (20ºC), Amoni, Nitrit, heavy metals Nitrat, Phosphat, surfactant, Total oil, Clorua, Florua, Xianua , Asen , Cadimi , Chi , Crom III , Crom VI , D6ng , Kern , Niken , Mercury , chlorinated organic plant protection chemicals (Aldrin +Di eldrin , Endr in, BHC , DDT ,E ndo sunfat (Thiodan ) Lin dan. Chlordan e, Hept ac hlor ); P hosphorus organic plant protection chemicals (Par ation.Mal at ion) ; O rganic chemicals (2 ,4D,2,4,5T ,para quat) ; E.coli ,Coliform Groundwater pH, electrical conductivity, pH, Hardness, Total solids, COD (KMnO 4), hardness, oil, Fe, Coliform Heavy Metals (As, Cr, Cd, Cu, Pb, Zn, Ni, Hg, Fe, Mn, Se), SVOC, VOC, TPH and coliforms, Cl-, F-, NO2-, NO3-, SO42-, CN-), Phenol, As , Cd, Pb, Cr6+ Cr6+, Cu, Zn, Mn, Hg¸ Se), total radioactivity α Mn, E. Coli ,Coliform, Total petroleum organic (THP), semi-volatile organic compounds (SVOC) Wastewater Report EIA-ADB-2011 not pH, TSS, TDS, S2) BOD5, NH4+, Nitrat NO3- proposed , Oil, surfactant, PO43-, total Coliform Table 7. Monitoring parameters at the Depot site

66. The selection of the parameters of chlorinated organic plant protection chemicals to monitor the surface water of the package CP04 and CP05 is not necessary.

67. CENMA combined two types of monitoring including environmental compliance monitoring and surrounding environmental monitoring. These two types are implemented for different targets (see Table below).

Examination of Monitoring surrounding Type of monitoring compliance environment

Responsibility The contractor Government organizations on environmental protection and management Targets To ensure liquid To ensure construction works no to wastewater and exhaust have bad impacts to the

PAGE 25

fume arising from the surroundings (wastewater receiving construction works to be sources, air quality) solved in accordance with mission standards Standards Exhaust fume and Air and water quality meet standards wastewater meet or usage objective emission standards Sampling points Checking/ measuring For wastewater: Outside the wastewater at discharge construction site, it is expected to be gates of exhaust gas and wastewater receiving sources (rivers, noise in adjacent areas lakes, groundwater) between the site and the For ambient air and noise: the external environment. surroundings of the site Monitoring/examination, Weekly or Monthly Monthly or quarterly (or half year) supervision frequency Monitoring/examination, Selection of Many parameters including all supervision parameter representative representative parameters were parameters selected to monitor/ check the compliance Table 8. Examination of compliance and surrounding environment

68. Comparison Standards

i. Environmental monitoring activities are performed by CENMA in compliance with the current standards and regulations of Vietnam (regulations on receiving, preservation, transportation, sample analysis). ii. Comparison Standards on are based on the current Vietnamese Code. iii. Several monitoring parameters is not currently prescribed in the Vietnamese Code, therefore; the monitoring results are only informative, namely: Dust parameter PM10 and PM 2.5, Pb dust. iv. Besides, it should be noted that QCVN 24:2009/BTNMT – Vietnamese Code on wastewater quality is now amended into QCVN 40:2011/BTNMT. CENMA needs to consider this appropriately.

6.4. Monitoring Plan

69. Activities proposed to be implemented in the next 6 months:

i. Periodic monitoring at works site ii. Monitoring of the tasks of the PIC in the general implementation of the regulations, according to the EMP and to the environmental protection activities of the contractors of CP02, CP04 and CP05 by Consultants. iii. Ensuring regulations in the EMP (mitigation, monitoring, reporting etc.) to be conducted comprehensively and timely and in accordance with the approved budget in the EMP iv. Coordinating with CENMA to assess the quality of the surrounding environment, including the monitoring plan of the package CP02 (elevated station) - pre- construction period v. Monitoring plan of the package CP02 (elevated station) - pre-construction period vi. As scheduled, eight (8) environmental monitoring points will be performed at eight (8) locations, including five (5) air monitoring locations, two (2) surface

PAGE 26

water monitoring locations and one (1) groundwater. vii. As proposed by CENMA, the position NM2 is replaced to suit practical conditions. According to the ToR, the position NM2 is located at the interchange between the viaduct line, national railway and beltway for the priority 3. However, during the survey, CENMA did not find a suitable position. Therefore, CENMA proposed to choose a monitoring point of surface water for the replacement. About 100 meters far from Cau Giay Street in the Northeast, at the lake of the Party Committee of Cau Giay because this monitoring point is located near the viaduct construction line. viii. CENMA selected more parameters to monitor than those required in the EIA- ADB. The parameter for the atmosphere: O3, total dust, dust Pb, Benzen; For surface water: pH, DO, SS, COD, Bods (20°C), Ammoni um, Nitrite, Nitrate, Phosphate, oil, Chloride, Fluoride, Cyanide, Arsenic, Cadmium, Pb, Cr III, Cr VI, Cu, Zn, Nickel, Fe, Hg, Aldrin, Dieldrin, Endrin, BHC, DDT, Endosunfat (thiodan), Lindan, chlordane, Heptachlor, Paration, Malation, etc. ix. These parameters are selected to monitor the construction package performance because they are appropriate to the environmental standards issued in Vietnam. x. The selection of the parameters of chlorinated organic plant protection chemicals to monitor the surface water for the package CP04 is not necessary, may be cancelled.

7. OUTSTANDING ENVIRONMENTAL ISSUES AT THE METRO LINE 3

7.1. The existing big environment problems are determined

70. For example, non-compliance with loan covenants, EMP and / or environmental requirements of the government, inappropriate environmental pollution mitigation measures or incidents, accidents etc.

i. Surface water is monitored to have a total Coliform content higher than the allowable limit. ii. Wastewater is monitored to have a total Coliform content higher than the allowable limit. iii. Currently there are some stagnant puddles of water at worker’scamps. They may become a hazard to the health of workers there. iv. A part of wastes at camps that was thrown into the surroundings may become a hazard for the health of workers here. v. Cooking activities at workers’ camps may cause fire and explosion.

7.2. The solutions and corrective action plan

71. Showing clearly corrective action plan is implemented to address non-compliance issues and identified problems. The Action Plan includes specific actions to solve problems, people who are responsible for the implementation of measures and duration/ targets to execute and complete necessary measures. The Action Plan can be expressed in the form of table/ matrix (below). The timeframe and responsibility to report the progress of Corrective Action Plan to ADB should also be mentioned in this part.

No Issue Cause Required Responsibil Duration Description of

PAGE 27

actions -ity (targets) Solution

Outstanding issues in previous reports

1 Air pollution Transport Increase PRB, During the Increase at point impacts of the spraying Contract construction spraying KXQ2 (gate Road 70 close water for dust or CMC phase water for dust close to the to the project reduction (package reduction Road 70) CP04)

2 Sanitation Public Raising PRB, During the Providing conditions in sanitation sanitation Contract construction public camps of awareness of awareness orCMC phase hygiene at CP04 is not workers is for workers (package camps, but good poor. CP04) by not often September, No hygiene 2013 rules at camps

3 Surface Little lake Digging the PRB, During the Completing water at the water (due to lake quickly Contract construction the surroundings under the orCMC phase excavation of of CP04 has excavation), (package the lake a total stagnant water CP04) by Coliform September, content 2013 higher than the allowable limit.

4 Domestic Mud is No pouring PRB, During the Improving the wastewater stagnant in the wastewater Contract construction sanitation has a total drainage directly into orCMC phase conditions at Coliform system; the drainage (package camp content rainwater system, no CP04) by higher than flows and dredging September, the allowable brings mud, 2013 limit. surrounding into the drainage system.

New issues in this report

1 Drainage Mud is Dredging PRB, Implementin Dredging system at stagnant in the mud and raw Contractor g mud and raw camps of drainage wastes from CMC immediately wastes from CP04 is system the drainage and the drainage currently system/ monitoring system/ stagnant implementing regularly implementing immediately activities of immediately and regularly the workers and regularly in the in camps in the construction (package construction phase CP05) up to phase December, 2013

2 A part of Public Raising PRB, Implementin Cleaning wastes at sanitation sanitation Contractor g camps from camps CP04 awareness of awareness CMC immediately top to bottom/ that was workers is for workers and Implementing

PAGE 28

thrown into poor. making monitoring immediately the hygiene rules regularly No hygiene surroundings at camps activities of rules at may become (package the workers camps. a hazard for CP05) in camps the health of (package workers CP05) up to here. December, 2013

3 Cooking Public Raising PRB, Implementin Making right at sanitation sanitation Contract, g hygiene rules workers’ awareness of awareness CMC immediately at workers’ camps may workers is for workers and camps cause fire poor. monitoring Making and regularly No hygiene hygiene rules explosion. activities of rules at camps at workers’ the workers camps in camps (package (package CP05) CP05) up to December, 2013

4 Residential Local Local Local During the The project areas authorities authorities authorities construction coordinates outside the have not strengthen PRB phase with the package agreed with the (package locality to CP04 are at some of coordination CP05) up to support the the risk of households on with related December, digging of inundation land area for households 2013 drainage as raining digging the channels in due to low drainage the residential foundation channel area (outside the project) Table 9. Solutions and corrective action plans

7.3. Necessary supplementary measures

7.3.1. For CP01 (elevated section), CP03 (underground section and stations) and CP05 (Depot)

72. Supplementary pollution reduction measures to limit bad impacts on the environment caused by air pollution:

i. Establishing and developing an excavation and transportation plan, choosing kinds of vehicles in compliance with standards. The vehicle floor is lined tightly and has a hood to avoid the spillage on the road. ii. Signing a transportation contract and solving in accordance with the provisions of law with the local urban environmental company. iii. Shielding arising areas and using water trucks to water roads of material transportation iv. Building a temporary car washing station v. Using nets or soft barriers canvas or mesh fabric together with protective screen to cover the entire outside of the project in the construction period to prevent the

PAGE 29

spread of dust, building materials in the surroundings and ensure labour safety. vi. Shielding levelled areas and construction sites with one layer of corrugated metal fence of 2.5 to 3 m because the construction site is near communication route. vii. Dust arising during the construction will be minimized to the lowest level through the following solutions such as watering the surfaces of disordered areas during the construction and the transportation routes nearby the project. viii. Finishing the construction of each phase and each item, and performing the construction management and supervision well on the site. The ground bases are compacted right after the excavation to prevent dust and ensured about the hardness according to the design. ix. Making appropriate timetables and routes for transportation of the material to avoid dust and environmental pollution around the project site. The timetable ensures the construction progress and complies with circulation regulations of the city. x. Arranging routines for transportation properly. Transportation on holidays is arranged in accordance with provisions of the Hanoi People's Committee. xi. Implementing seriously Decision 02/2005 on transportation of bulk materials on streets.

73. Supplementary noise mitigation measures to reduce bad impacts on the environment caused by noise:

i. The speed limit for vehicles and machinery during the operation in the project on the roads through densely populated areas, public areas, schools is not over 10 km/h. ii. The machinery that makes noise and vibration during the construction such as road rollers, excavators, will only be allowed to work during the day, excluding lunch breaks. iii. Restricting big noises: concrete drilling and cutting, mixing and pouring concrete, digging, shovelling at night (from 10 pm to 6 am). iv. Not using old construction machinery with broken sound reduction systems because they may cause noise pollution. Regularly maintaining sound reduction components of the construction machinery and equipment. v. Preventing noise from sensitive subjects: In the case of the required distance cannot be ensured, the construction contractor will take measures to minimize noises in sensitive areas. One of these measures is to build anti-noise walls around the major sources of noise, etc. vi. Construction workers will be equipped with anti-noise devices such as protective helmets, hearing protectors.

74. Pollution mitigation measures for the overflow of rainwater and sewage to the surrounding environment:

i. It is strictly banned to wash dedicated machines and equipment at sources of water or any areas directly flowing into the regional drainage system. ii. Types of materials are put away from the drainage system to prevent the loss and leakage into the drainage system of the city.

PAGE 30

iii. Ensuring rainwater from the construction works not to be stagnant in the drainage system by checking, dredging, clearing regularly; preventing construction wastes from the sewer system to avoid the blockage and stagnancy. iv. All wastewater arising from the works including construction wastewater, equipment-washing water will be collected in catch basins and reused partly and periodically for construction activities. The remaining wastewater is treated preliminarily on the project site to ensure the maximum reduction of water environment pollutants and discharged through a temporary drainage system, which is designed properly. v. During construction, oil and oil waste from construction vehicles and machinery will be stored and discarded in accordance with regulations to avoid the water pollution. All equipment are monthly checked to prevent the leakage of oil and the lubrication shall be conducted only in machinery maintenance and repair areas. vi. The construction organization signed the lease agreement on portable toilets of the Urban Environment Company, which is capable of providing services during the construction period. vii. Defining waste collection areas,... avoiding discarding household rubbish disorderly for the environmental pollution viii. After finishing the construction phase, toilets will be dismantled and packed up, removed by the competent leasing company

75. Measures to reduce soil pollution:

i. The construction contractor will strictly cool to avoid the infiltration of wastewater with oil and toxic chemicals into the soil. ii. Collecting wastewater and solid wastes for the treatment iii. Making basements in accordance with technical requirements

76. Impact mitigation measures for toxic substances:

i. Providing containers of sludge oil, toxic daily wastes and signing a contract with the urban environmental company to treat in accordance with regulations of the Circular 12/2011/TTBTNMT.

77. Measures to reduce regional traffic congestion:

i. During the construction phase, it is necessary to have reasonable solutions for material transport, mostly at night, and specific transportation to avoid causing traffic congestion in the project area; strictly comply with the Decision 26/2003/QD-UB of the Hanoi People’s Committee on transportation in the city of Hanoi ii. Avoid stopping, parking and travelling near the project during peak hours iii. Coordinating with local traffic police to cool the traffic flow on the road iv. The signalling system is designed in accordance with Regulations on road signs TCN237-01. Road signs are made from corrugated iron and painted with reflective paint v. Arranging signs fully in surrounding areas of the project and from a distance

PAGE 31

78. Labour safety and hygiene measures, prevention of environmental problems:

i. Building solid fences to separate dangerous areas such as transformer stations, combustible materials, communication routes and making fences to separate construction areas with surrounding areas ii. Electric grid and throw –over switches which may cause electric spark need to be arranged safely iii. Compliance with regulations on labour safety when making construction plans such as construction methods, equipment arrangement, accident prevention measures, lightning prevention, arrangement of warehouses, materials, temporary camps, logistics service of construction etc. iv. Designing lighting system for night jobs and project protection

79. Improving the environmental sanitation at workers’ camps:

i. Cleaning the whole area, sweeping and collecting garbage ii. Buying more dustbins and dredging drainage channels iii. Cleaning cisterns

7.3.2. For CP02 (elevated stations)

80. Supplementary pollution reduction measures to limit bad impacts on the environment caused by air pollution:

i. Shielding arising areas and using water trucks to water roads of material transportation ii. Using nets or soft barriers canvas or mesh fabric together with protective screen to cover the entire outside of the project in the construction period to prevent the spread of dust, building materials in the surroundings and ensure labour safety iii. Dust arising during the construction will be minimized to the lowest level through the following solutions such as: watering for the surfaces of disordered areas during the construction and transportation routes nearby the project iv. Finishing the construction of each phase, each items; performing the construction management and supervision well on the site v. Making transport timetables and routes for material transportation appropriately and scientifically to avoid dust for the environmental pollution around the project site. The timetable ensures the construction progress and complies with circulation regulations of the city. vi. Arranging routines for transportation properly. Transportation on holidays is arranged in accordance with provisions of the Hanoi People's Committee. vii. Implementing seriously Decision 02/2005 on transportation of bulk materials on streets

81. Supplementary noise mitigation measures to reduce bad impacts on the environment caused by noise:

i. The speed limit for vehicles and machinery during the operation in the project on the roads through densely populated areas, public areas, schools is not over 10 km/h. ii. The machinery which makes big noise and vibration during the construction

PAGE 32

such as road rollers, excavators will only be allowed to work during the day, excluding lunch breaks. iii. Restricting big noises: concrete drilling and cutting, mixing and pouring concrete, digging, shovelling at night (from 10 pm to 6 am). iv. Not using old construction machinery with broken sound reduction system because they may cause noise pollution. Regularly maintaining sound reduction components of the construction machinery and equipment. v. Preventing noise from sensitive subjects: In the case of the required distance cannot be ensured, the construction contractor will take measures to minimize noises in sensitive areas. One of these measures is to build anti-noise walls around the major sources of noise, etc. vi. Construction workers will be equipped with anti-noise devices such as protective helmets, hearing protectors.

82. Pollution mitigation measures for the overflow of rainwater and sewage to the surrounding environment:

i. It is strictly banned to wash dedicated machines and equipment at sources of water or any areas directly flowing into the regional drainage system. ii. Types of materials are put away from the drainage system to prevent the loss and leakage into the drainage system of the city. iii. Ensuring rainwater from the construction works not to be stagnant in the drainage system by checking, dredging, clearing regularly; preventing construction wastes from the sewer system to avoid the blockage and stagnancy. iv. During construction, oil and oil waste from construction vehicles and machinery will be stored and discarded in accordance with regulations to avoid the water pollution. All equipment are monthly checked to prevent the leakage of oil and the lubrication shall be conducted only in machinery maintenance and repair areas. v. The construction organization signed the lease agreement on portable toilets of the Urban Environment Company, which is capable of providing services during the construction period. vi. Defining waste collection areas avoiding discarding household rubbish disorderly for the environmental pollution vii. After finishing the construction phase, toilets will be dismantled and packed up, removed by the competent leasing company.

83. Measures to reduce soil pollution:

i. The construction contractor will strictly cool to avoid the infiltration of wastewater with oil and toxic chemicals into the soil. ii. Collecting wastewater and solid wastes for the treatment iii. Making basements in accordance with technical requirements

84. Impact mitigation measures for toxic substances:

i. Providing containers of sludge oil, toxic daily wastes and signing a contract with the urban environmental company to treat in accordance with regulations of the Circular 12/2011/TTBTNMT.

PAGE 33

85. Measures to reduce regional traffic congestion:

i. During the construction phase, it is necessary to have reasonable solutions for material transport, mostly at night, and specific transportation to avoid causing traffic congestion in the project area; strictly comply with the Decision 26/2003/QD-UB of the Hanoi People’s Committee on transportation in the city of Hanoi. ii. Avoid stopping, parking and travelling near the project during peak hours iii. Coordinating with local traffic police to cool the traffic flow on the road iv. The signalling system is designed in accordance with Regulations on road signs TCN237-01. Road signs are made from corrugated iron and painted with reflective paint. v. Arranging signs fully in surrounding areas of the project and from a distance

86. Labour safety and hygiene measures, prevention of environmental problems:

i. Building solid fences to separate dangerous areas such as transformer stations, combustible materials, communication routes and making fences to separate construction areas with surrounding areas ii. Electric grid and throw-over switches which may cause electric spark need to be arranged safely. iii. Compliance with regulations on labour safety when making construction plans such as construction methods, equipment arrangement, accident prevention measures, lightning prevention, arrangement of warehouses, materials, temporary camps, logistics service of construction etc. iv. Designing lighting system for night jobs and project protection

8. GRIEVANCES

8.1. Details on grievance/detailed regulations on grievance from local residents and relevant parties on environmental impacts

87. Grievance, nature of grievance letter, submitted daily grievance letter, grievance letter received by the office, etc.

88. MRB has so far not received any grievance (oral or written) from local residents and/or relevant parties on environmental issues of the implemented packages CP04 and CP05.

8.2. Solutions to deal with grievance letters settled or to be settled with information

89. Name and assign specific staffs or officials in grievance redress departments, agencies, project management board, local authority, contractor/supervisor who are involved in implementing, documenting and settling grievance.

90. Specific measure to settle grievance and implementation duration

91. Currently MRB is carrying out GRM at project level with main contents as follows: When construction starts, contractors organize reception division to record claims. Claims (if any) of the public shall be reported to MRB by contractor within 24 hours. Contractor publicizes name and telephone number (including hot line) of reception staff. If claims are not settled at contractor level within 2 days since the date of claim letter, they shall be settled in accordance

PAGE 34

with compensation, claim mechanisms in legal system described in Environmental Impact Assessment Report.

9. CONCLUSIONS AND RECOMMENDATIONS

9.1. Overall progress of implementation of environmental management measures

92. The packages CP04, CP05, CP01 and CP02 have included EMP into the bidding document. The EPM is prepared by Contractors and supported by Systra.

93. The CP04 has been so far completed 90% of the works with the application of the general and direct environmental monitoring systems in the construction site of VINACONEX, independent consultant and CENMA.

94. Regarding CP05, HANCORP Contractor has already requested SYSTRA, to prepare EPM and SEP (construction package ref.: HPLMLP/CP05). The environmental management plan was completed and submitted to MRB on April 8, 2013. However, its preparation and submission to MRB was late (four weeks after the commencement of the construction). However, the content of the required mitigation measures in the CP05’s EMP in the bidding document is not consistent with the EMP included in the EIA cleared by ADB. In order to solve this problem, MRB submitted the final Environmental Management Plan guided by ADB to the donors again on 20 June 2013. Due to the CP05 was signed between MRB and Contractor (HANCORP) and its under implementation thus MRB, Systra and HANCORP modified EMP as the contents and format of ADB guided. This modification has done as the Contract Appendix of CP05’s bid document..

95. The compliance with environmental requirements of CP04 and CP05 is satisfying level. It may be considered that conditions on the depot site are most probably much easier to handle in terms of environment and safety than what is anticipated on the construction sites along the metro Line 3. So, for the environmental and safety management of CP01 and CP02 the difficulties to be faced later on (which will definitely be a higher) must be thoroughly estimated

96. The monitoring activities of the Project’s GRM was shown in the Environmental Impact Assessment (EIA) by ADB 2010. Currently MRB and the Consultant are preparing GRM for the Project. MRB has so far received no complaints (in either oral or written forms) on environmental issues.

97. Hanoi Centre for Environmental and Natural Resources Monitoring and Analysis (CENMA) performed the monitoring/supervision of environmental quality at the construction site and the surrounding environment of the Depot site (including CP04 and CP05). CENMA sent MRB and the Contractor monthly reports on the quality monitoring results of the environment from May 2012 to June 2013.

98. There have been no environmental incidents or environmental complaints during April to June at the Depot construction site.

9.2. Identification of problems and solutions

9.2.1. Conclusion

99. Air pollution at KXQ2 (the gate of the Project area – near Road No.70). Solution: Increasing water spraying to reduce dust. 100. The environmental sanitary conditions at camps are not good. Solution proposed: Organizing public cleaning at camps. However, this activity has not been frequently held.

PAGE 35

101. The total value of coliform in the surface water of the neighbouring area and in the domestic wastewater under the CP04 is higher than the allowable standard. Solution proposed: Completing the lake digging and improving environmental sanitary conditions at workers’ camps. 102. The drainage system at the worker camps under CP04 is presently stagnant. Solution proposed: Dredging and picking up coarse waste from the drainage system to be immediately and frequently implemented during the construction. 103. Waste at the workers camp under the CP04 is partially dumped into the surrounding environment, which can threaten the workers’ health. Solution proposed: Cleaning the camps/to be immediately implemented. Cooking at the workers camp under the CP04 can cause fires and explosions. Solution proposed: Increasing the workers awareness and preparing regulations for workers. 104. The residential area outside the CP04 may be flooded in heavy rains due to its low elevation. Solution proposed: The Project should work with the locality to assist them to dig drainage canal for this area (outside the Project area). 9.2.2. Adjustment of monitoring (proposed based on monitoring experience/relevant trends) 105. Environmental specialist (Idom) inspection continuing the levels of compliance of the applicable mitigation measures at the construction site for the whole Metro line 3 project until June 2014. 106. Some impact mitigation measures stated in the environmental impact assessment report - ADB (February 2010) are not included in the EMP in the bidding documents of CP01 and CP02, such as air pollution and noise control measures during the construction; sediment control measures at Thu le Lake during the construction; measures to minimize social conflicts during the construction, etc. MRB has been solved and completed EMPs. 9.2.3. Recommendations 107. The compliance with EMP should be weekly or monthly monitored by environmental specialist. MRB should continue to request the Contractor to take effective measures in order to carry out the environmental monitoring plan as supported by the PIC (SYSTRA). 108. For new construction packages, MRB should request that feasible mitigation measures mentioned in the EIA report-ADB (February 2010), which are included in the bid price and contract documents, must be applied. 109. MRB should consider EMPs in the EIA Report by ADB, which are incorporated in the bid invitation for all civil structures under Hanoi Urban Railway Line 3. MRB should consider and request the contractors to follow EMP regulations to minimize adverse impacts on the environment. 110. Workers of the construction contractors have to be better trained on their roles in environmental safety and on the compliance with environmental impact mitigation measures during the construction. It is them who are primarily responsible for the compliance with the EMP regulations of the construction contractor. 111. For CP05, MRB should consider on worker camps because worker camp area is a lower lying than the Depot site about 1 m, this area is permanently submerged with stagnant water during rainy season. 112. The contractor needs to pay more attention to the worker camps and their sanitation to avoid insanitation and diseases when the hot season comes. The sewerage canal behind the workers’ camps should be dredged to improve the landscape and eliminate unpleasant odour. Nylon waste at stagnant pools around the workers’ camps should be picked up, and these pools should be levelled with sand. The waste management in the workers’ camps needs to be improved. Each camp should assign a worker to involve in cleaning around their camps once

PAGE 36

or twice a week. Cooking in camps should be forbidden, and joint cooking area for each worker team should be specified. Since the camps use underground water, the Contractor and CMC should pay attention to measures to fill up the wells after the construction so as to avoid polluting underground water; 113. It is necessary to enhance the capability of MRB staff and relevant individuals and organizations who are involved in the survey, to study on monitoring environmental safety in foreign countries with similar projects.

PAGE 37

ANNEX 1. SAMPLING DIAGRAM

PAGE 38

Coordinate Sampling Sign of No Longitud Location features point sample Latitude e

1 Ambient air KXQ1 0576581 2328785 The first air sampling point is located at the upwind direction of Depot (station), in the Northeast, bordered with the field of flowers, far from the reservoir of Depot about 120 m.

2 KXQ2 0576067 2328589 Located to the west of the Depot, at the main gate, and about 10 m from Road No. 70

3 Surface NM1 0576005 2328783 Surface water sample is obtained at the Water lake (round) inside Depot.

4 Groundwater NN1 0576481 2328499 Groundwater sample is obtained at the workers’ camps of the depot, which are behind the dormitory of Hanoi University of Industry.

5 Wastewater NT1 0576582 2328784 The first wastewater sampling point is at the existing irrigation ditch, inside the depot, near KXQ1.

6 NT2 0575989 2328848 The second wastewater sampling point is at the irrigation ditch of the residential area, outside Depot. It is located on the junction and opposite to the gate of Nhon cemetery.

PAGE 39

ANNEX 2. LOCATION OF MONITORING POINTS

PAGE 40

PAGE 41

ANNEX 3. ENVIRONMENTAL MONTHLY SITE VISITS – MAY 2013

PAGE 42

1. Introduction

Project HANOI PILOT URBAN RAILWAY LINE NO. 3 (N HON – HANOI RAILWAY STATION )

Date 11 and 23 May 2013

Time 09:00 am

Location The Depot site

2. Construction activities at the Depot site  Filling of internal roads

 Digging cable trench

 External lightning

3. Existing equipment at the Depot site  2 Trucks

 1 Excavators

 1 concrete-mixer

4. Number works at site

80 workers at site at the time of inspection but none of them is local resident.

5. Summary of the recommendations

Conclusions on site visit & Comments and Current No Current Status recommendations Conclusion levels  Should clean-up  Cooking in Camp workers camp  Rubbish in Camp 1 Cleanness of the Site  Cooking activities 3  Bath area is not in workers camp clean should be banned

Waste bins should be 2 Solid waste & sanitation Plastic bags in Camps maintained in the 3 workers camp

 Awful smell Monthly spray anti- 3 Health and safety  Mosquito in camp mosquito chemical in 3 workers camp area

There are water Drainage and water quality Filing water stagnant 4 stagnant puddles in 4 control areas by sand camps area.

The contractor need 5 Conclusion of visiting to: -  Improve cleanness

PAGE 43

Conclusions on site visit & Comments and Current No Current Status recommendations Conclusion levels in workers camp area  Monthly spray anti- mosquito chemical in workers camp area  Stop cooking in sleeping area  Filing water stagnant areas by sand

* Mitigation Effectiveness Rating Criteria (Indicative examples) 1. Very Good (all required mitigations implemented) 2. Good (the majority of required mitigations implemented) 3. Fair (some mitigations implemented) 4. Poor (few mitigations implemented) 5. Very Poor (very few mitigations implemented) NA Not Applicable 5. Pictures of works site

Filling of internal roads Digging cable trench

Construction area Construction area

PAGE 44

Waste disposal at construction site Waste area at construction site

Drainage of construction site Water supply of workers camp

PAGE 45

Water supply for washing at workers camp Stagnant puddles in camp area

Cooking activities in workers camp Store of construction site

Workers camp Outside of Workers camp

PAGE 46

ANNEX 4. ENVIRONMENTAL MONTHLY SITE VISITS – JUNE 2013

PAGE 47

1. Introduction

Project HANOI PILOT URBAN RAILWAY LINE NO. 3 (N HON – HANOI RAILWAY STATION )

Date 06 June 2013

Time 09:00 am

Location The Depot site

2. Construction activities at the Depot site  Fresh water tank

 Filling of internal roads

 Digging cable trench

 Fencing

 The work building at the Depot of the CP05

3. Existing equipment at the Depot site  5 Trucks

 5 Excavators

 5 Filling of internal roads

 1 Concrete-mixer

4. Number works at site

180 workers at site at the time site visit, CP04 is urgently finished all construction activities on- time so more worker are mobilized at this month.

5. Summary of the recommendations

Conclusions on site visit & Comments and Current No Current Status recommandations Conclusion levels  Cooking activities in worker camp  Cooking in Camps should be banned 1 Cleanness of the Camp  Rubbish in Camps 3  Should clean-up worker camp  Waste bins should  Plastic bags in be maintained in Camps the workers camp  Toilets are very  Regularly clean up 2 Solid waste & sanitation unsanitary 3 toilets  Bath area is not  Regularly clean up clean baths

PAGE 48

Conclusions on site visit & Comments and Current No Current Status recommandations Conclusion levels

 Awful smell Monthly spray anti- 3 Health and safety  Mosquito in camp mosquito chemical in 3 worker camp area

There are water Drainage and water quality Filing water stagnant 4 stagnant puddles in 3 control areas by sand camps area.

The contractor need to:  Improve cleanness in worker camp area  Monthly spray anti- mosquito chemical in worker camp area 5 Conclusion of visiting -  Stop cooking in sleeping area  Filing water stagnant areas by sand  Regularly clean up toilets  Regularly clean up baths

* Mitigation Effectiveness Rating Criteria (Indicative examples) 1. Very Good (all required mitigations implemented) 2. Good (the majority of required mitigations implemented) 3. Fair (some mitigations implemented) 4. Poor (few mitigations implemented) 5. Very Poor (very few mitigations implemented) NA Not Applicable 6. Pictures of works site

PAGE 49

Fresh water tank The work building at the Depot of the CP05

Digging cable trench Filling of internal roads

Cleansing Pile – slab Fence construction and cable trench

PAGE 50

Water filling to reduce dust and useful for rolling The collective kitchen (canteen) of Vinaconex’s internal roads staffs

The collective kitchen of VC2’s workers of CP04 Cooking in worker camp of team- VC5

Water tank in front of worker camp Stagnant puddles in work camp area

PAGE 51

1. Introduction

Project HANOI PILOT URBAN RAILWAY LINE NO. 3 (N HON – HANOI RAILWAY STATION )

Date 14 June 2013

Time 09:00 am

Location The Depot site

2. Construction activities at the Depot site  Rainy drain ditch

 Fresh water tank

 Filling of internal roads

 Digging cable trench

 Fencing

 The work building at the Depot of the CP05

3. Existing equipment at the Depot site  4 Trucks

 5 Excavators

 5 Filling of internal roads

 1 Concrete-mixer

4. Number works at site

160 workers at site at the time site visit. Since a small number of workers living in camp so the cleanliness in camp area is quite good.

5. Summary of the recommendations

Conclusions on site visit Comments and Current No Current Status and recommendations Conclusion levels  Clean up water  Water tank in front tank of work camp is in  Cooking activities very poor condition 1 Cleanness of the Camp in workers camp 3  Cooking in Camp should be banned  Rubbish in Camp  Should clean-up workers camp  Plastic bags in  Waste bins should Camps be maintained in 2 Solid waste & sanitation  Toilets are very the workers camp 4 unsanitary  Regularly clean up  Bath area is not toilets

PAGE 52

Conclusions on site visit Comments and Current No Current Status and recommendations Conclusion levels

clean  Regularly clean up baths  Monthly spray anti-  Awful smell mosquito chemical  Mosquito in camp in workers camp 3 Health and safety  Some work camp area 2 do not have fist aid  Should provide fist box aid box to all work camp There are water Drainage and water quality Filing water stagnant 4 stagnant puddles in 4 control areas by sand camps area.

The contractor need to:  Clean up water tank  Improve cleanness in workers camp area  Monthly spray anti- mosquito chemical in workers camp 5 Conclusion of visiting area -  Stop cooking in sleeping area  Filing water stagnant areas by sand  Regularly clean up toilets  Regularly clean up baths

* Mitigation Effectiveness Rating Criteria (Indicative examples) 1. Very Good (all required mitigations implemented) 2. Good (the majority of required mitigations implemented) 3. Fair (some mitigations implemented) 4. Poor (few mitigations implemented) 5. Very Poor (very few mitigations implemented) NA Not Applicable

PAGE 53

6. Pictures of works site

Rainy drainage trench Fresh water tank

The work building at the Depot of the CP05 Filling of internal roads

Fence construction and cable trench Fence, internal road and cable trench

PAGE 54

Cleansing Pile – slab The collective kitchen of VC2’s workers of CP04

Cooking activities in workers camp Waste bin of each work camp

Stagnant puddles in work camp area Stagnant puddles in work camp area

PAGE 55

Stagnant puddles in front of work camps Waste around work camp

PAGE 56

1. Introduction

Project HANOI PILOT URBAN RAILWAY LINE NO. 3 (N HON – HANOI RAILWAY STATION )

Date 27 June 2013

Time 09:00 am

Location The Depot site

2. Construction activities at the Depot site  Fresh water tank

 Filling of internal roads

 Digging cable trench

 Fencing

 Rainy drain ditch

 The work building at the Depot of the CP05

3. Existing equipment at the Depot site  5 Trucks

 6 Excavators

 6 Filling of internal roads

 1 Concrete-mixer

4. Number works at site

190 workers at site at the time site visit. Since a big number of workers (both CP04’s workers and CP05) living in camp areas so the cleanliness in camp are too poor.

5. Summary of the recommendations

Conclusions on site visit Comments and Current No Current Status and recommendations Conclusion levels  Cooking activities in workers camp  Cooking in Camp should be banned 1 Cleanness of the Camp  Rubbish in Camp 3  Should clean-up workers camp  Water tank in front  Clean up water tank of worker camp is  Waste bins should very poor condition be maintained in 2 Solid waste & sanitation  Plastic bags in the workers camp 4 Camps  Regularly clean up  Toilets are very toilets

PAGE 57

Conclusions on site visit Comments and Current No Current Status and recommendations Conclusion levels unsanitary  Regularly clean up  Bath area is not baths clean  Additional fist aid box should be  Additional fist aid provided to all box has not worker camp provided yet. 3 Health and safety  Monthly spray anti- 3  Awful smell mosquito chemical  Mosquito in camp in workers camp area

There are water Drainage and water quality Filing water stagnant 4 stagnant puddles in 4 control areas by sand camps area.

The contractor need to:  Clean up water tank  Maintain cleanliness in camp area.  Monthly spray anti- mosquito chemical in workers camp 5 Conclusion of visiting area -  Stop cooking in sleeping area  Filing water stagnant areas by sand  Regulary clean up toilets  Regular clean up baths

* Mitigation Effectiveness Rating Criteria (Indicative examples) 1. Very Good (all required mitigations implemented) 2. Good (the majority of required mitigations implemented) 3. Fair (some mitigations implemented) 4. Poor (few mitigations implemented) 5. Very Poor (very few mitigations implemented) NA Not Applicable

PAGE 58

6. Pictures of works site

Fresh water tank The work building at the Depot of the CP05

Filling of internal roads Filling of internal roads

Filling water to reduce dust and useful for rolling Fence, cable trench, internal road to be finished internal roads

PAGE 59

Drainage behind work camp Drainage behind work camp

Stagnant puddles in work camp area Stagnant puddles in work camp area

Cooking activities in the sleeping camp Waste bin of each work camp

PAGE 60

Waste behind bathroom of staff (The work building Stagnant puddles in front of camp of CP04)

PAGE 61