Public Disclosure Copy The World Bank Implementation Status & Results Report Hubei Jingzhou Historic Town Conservation Project (P148523)
Hubei Jingzhou Historic Town Conservation Project (P148523)
EAST ASIA AND PACIFIC | China | Social, Urban, Rural and Resilience Global Practice Global Practice | IBRD/IDA | Investment Project Financing | FY 2016 | Seq No: 5 | ARCHIVED on 29-Apr-2018 | ISR31687 | Public Disclosure Authorized
Implementing Agencies: People's Republic of China, Hubei Jingzhou PMO
Key Dates
Key Project Dates
Bank Approval Date:19-Jan-2016 Effectiveness Date:25-Jul-2016 Planned Mid Term Review Date:28-Sep-2018 Actual Mid-Term Review Date:-- Original Closing Date:30-Jun-2021 Revised Closing Date:30-Jun-2021 Public Disclosure Authorized Project Development Objectives
Project Development Objective (from Project Appraisal Document)
To conserve cultural heritage and improve water quality and tourism services in selected areas in Jingzhou Municipality.
Has the Project Development Objective been changed since Board Approval of the Project Objective? No
PHRPDODEL
Components Public Disclosure Authorized
Name Cultural Heritage Conservation and Tourism Services Improvement:(Cost $83.27 M) Water Environment Improvement:(Cost $55.10 M) Transport Improvement:(Cost $21.35 M) Assistance to Project Management and Capacity Building:(Cost $5.15 M)
Overall Ratings
Name Previous Rating Current Rating
Progress towards achievement of PDO Satisfactory Satisfactory
Public Disclosure Authorized Overall Implementation Progress (IP) Moderately Satisfactory Satisfactory Overall Risk Rating Substantial Substantial
4/29/2018 Page 1 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Hubei Jingzhou Historic Town Conservation Project (P148523)
Implementation Status and Key Decisions
Under strong leadership of the municipal government, the project implementation has made substantial progress toward achieving the Project Development Objective (PDO: to conserve cultural heritage and improve water quality and tourism services in selected areas in Jingzhou Municipality). By April 15, 2018, the project had benefitted a total of 360,000 residents and tourists including 45% female. Tourist satisfaction has increased from the baseline 70% in 2016 to 74% in 2017. Conservation works of three cultural heritage (CH) sites are under implementation and are expected to be completed by the end of 2018. In terms of implementation progress, technical design documents of almost all the physical investments have been completed. Out of the total 27 Bank- financed contracts, 14 have been procured and the rest are on track to be procured. Another 22 contracts have been procured through counterpart funding as part of the project. Appropriate sites were selected for the temporary sediment stockpile and the tourism information center and thus relevant pending issues from previous missions were satisfactorily resolved. The PMO and PIUs, under strong leadership of the municipal government, are implementing the project at full speed with coordinated efforts. All the four components progressed significantly. Under Component A of Cultural Heritage (CH) Conservation, all the design documents have been completed, except for the design of tourist information center to be completed by July 2018. Required approvals from the State Administration of Cultural Heritage (SACH) were obtained for conserving all the CH sites under the component except one subproject awaiting SACH approval. Under Component B of Water Environment Improvement, among the three civil works contracts, a large contract on dredging of the moat was awarded and the works commenced. The contract on water body connection is under procurement. The bid of the largest contract on constructed wetland and embankment is expected to be published in May 2018. Under Component C of Transport Improvement, the successful installation of 28 bus stop kiosks and operation of the 30 clean-energy buses have doubled the ridership and improved satisfaction levels. Two large civil works contracts were awarded and commenced. Under Component D of Project Management and Capacity Building, all the five contracts were procured. The Project Management Company (PMC)has improved project management. Consultants have been hired for studies on historic city conservation and regeneration as well as and historic city traffic management. Three training sessions and one technical workshop were conducted in the past six months for capacity building.
Risks
Systematic Operations Risk-rating Tool
Risk Category Rating at Approval Previous Rating Current Rating
Political and Governance Low Low Low Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Substantial Substantial Substantial Institutional Capacity for Implementation and Substantial Substantial Substantial Sustainability Fiduciary Moderate Moderate Moderate Environment and Social Substantial Substantial Substantial Stakeholders Moderate Moderate Moderate Other -- Substantial Substantial Overall Substantial Substantial Substantial
Results
4/29/2018 Page 2 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Hubei Jingzhou Historic Town Conservation Project (P148523)
Project Development Objective Indicators
PHINDPDOTBL
Direct project beneficiaries (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 310,000.00 360,000.00 600,000.00
Date 19-Nov-2015 30-Jun-2017 16-Apr-2018 30-Jun-2021
PHINDPDOTBL
Female beneficiaries (Percentage, Custom Supplement)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 45.00 45.00 50.00
PHINDPDOTBL
Cultural heritage sites conserved/rehabilitated under the project (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 0.00 0.00 5.00
Date 19-Nov-2015 30-Jun-2017 16-Apr-2018 30-Jun-2021
Comments Conservation works of three cultural heritage (CH) sites are under implementation and are expected to be completed by the end of 2018.
PHINDPDOTBL
Moat water meets Class IV for BOD (< 6 mg/l) for at least 10 of the 12 monthly samples per year (Text, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Investments to meet Investments to meet Value NA Class IV for BOD have Class IV for BOD were Yes not yet been procured. procured recently.
Date 19-Nov-2015 30-Jun-2017 16-Apr-2018 30-Jun-2021
4/29/2018 Page 3 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Hubei Jingzhou Historic Town Conservation Project (P148523)
PHINDPDOTBL
Increased satisfaction of tourists on tourism services in Jingzhou Historic Town (JHT) (Percentage, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 77.00 70.00 74.00 85.00
Date 19-Nov-2015 30-Jun-2017 16-Apr-2018 30-Jun-2021
Overall Comments By April 16, 2018, the project had benefitted a total of 360,000 residents and tourists including 45% female. Tourist satisfaction has increased from the baseline 70% in 2016 to 74% in 2017. Conservation works of three cultural heritage (CH) sites are under implementation and are expected to be completed by the end of 2018.
Intermediate Results Indicators
PHINDIRITBL
City Wall restored under the project (Percentage, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 0.00 0.00 100.00
Date 19-Nov-2015 30-Jun-2017 16-Apr-2018 31-Dec-2021
Comments Contracts of city-wall conservation were just procured and are expected to be completed by the end of 2018.
PHINDIRITBL
Wastewater interceptors constructed inside and outside of the moat (Meter(m), Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 0.00 1,300.00 7,080.00
Date 19-Nov-2015 30-Jun-2017 16-Apr-2018 30-Jun-2021
4/29/2018 Page 4 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Hubei Jingzhou Historic Town Conservation Project (P148523)
PHINDIRITBL
Dredging of the moat and lakes with safe storage /disposal of the dredged materials (Cubic Meter(m3), Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 0.00 15,000.00 250,000.00
Date 19-Nov-2015 30-Jun-2017 16-Apr-2018 30-Jun-2021
PHINDIRITBL
Roads rehabilitated, Non-rural (Kilometers, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 0.00 0.00 10.20
Date 19-Nov-2015 30-Jun-2017 16-Apr-2018 30-Jun-2021
PHINDIRITBL
Pedestrian crossing upgraded (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 0.00 0.00 12.00
Date 19-Nov-2015 30-Jun-2017 16-Apr-2018 30-Jun-2021
PHINDIRITBL
Bus stops upgraded (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 0.00 28.00 28.00
Date 19-Nov-2015 30-Jun-2017 16-Apr-2018 30-Jun-2021
Comments All the bus stops under the project were satisfactorily upgraded and benefitting residents and tourists.
4/29/2018 Page 5 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Hubei Jingzhou Historic Town Conservation Project (P148523)
PHINDIRITBL
Participants rated the training/study tours good or excellent (Percentage, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 80.00 80.00 75.00
Date 19-Nov-2015 30-Jun-2017 16-Apr-2018 30-Jun-2021
PHINDIRITBL
Participants in consultation activities during project implementation (number) (Number, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 1,390.00 1,390.00 2,000.00
Date 19-Nov-2015 30-Jun-2017 16-Apr-2018 30-Jun-2021
PHINDIRITBL
Participants in consultation activities during project implementation - female (Number, Custom Breakdown)
Baseline Actual (Previous) Actual (Current) End Target
Value 0.00 600.00 600.00 1,000.00
Date 19-Nov-2015 30-Jun-2017 16-Apr-2018 30-Jun-2021
Overall Comments The project is implemented at full speed and the IOI annual targets are expected to be met by the end of 2018.
Data on Financial Performance
Disbursements (by loan)
Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed
P148523 IBRD-85740 Effective USD 100.00 100.00 0.00 14.46 85.54 14%
Key Dates (by loan)
4/29/2018 Page 6 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Hubei Jingzhou Historic Town Conservation Project (P148523)
Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date
P148523 IBRD-85740 Effective 19-Jan-2016 26-Apr-2016 25-Jul-2016 30-Jun-2021 30-Jun-2021
Cumulative Disbursements
Restructuring History
There has been no restructuring to date.
Related Project(s)
There are no related projects.