The World Bank Implementation Status & Results Report Hubei Historic Town Conservation Project (P148523)

Hubei Jingzhou Historic Town Conservation Project (P148523)

EAST ASIA AND PACIFIC | | Urban, Resilience and Land Global Practice | IBRD/IDA | Investment Project Financing | FY 2016 | Seq No: 10 | ARCHIVED on 23-Nov-2020 | ISR44322 | Public Disclosure Authorized

Implementing Agencies: People's Republic of China, Hubei Jingzhou PMO

Key Dates

Key Project Dates

Bank Approval Date: 19-Jan-2016 Effectiveness Date: 25-Jul-2016 Planned Mid Term Review Date: 22-Oct-2018 Actual Mid-Term Review Date: 22-Oct-2018 Original Closing Date: 30-Jun-2021 Revised Closing Date: 31-Dec-2022 pdoTable

Project Development Objectives Public Disclosure Authorized Project Development Objective (from Project Appraisal Document) To conserve cultural heritage and improve water quality and tourism services in selected areas in Jingzhou Municipality.

Has the Project Development Objective been changed since Board Approval of the Project Objective? No

Components Table

Name

Public Disclosure Authorized Cultural Heritage Conservation and Tourism Services Improvement:(Cost $83.36 M) Water Environment Improvement:(Cost $31.92 M) Transport Improvement:(Cost $12.49 M) Assistance to Project Management and Capacity Building:(Cost $3.06 M)

Overall Ratings

Name Previous Rating Current Rating

Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Satisfactory Overall Risk Rating Moderate Moderate

Implementation Status and Key Decisions

Public Disclosure Authorized The project was restructured by the World Bank to make use of loan savings to further strengthen project outcomes, and extend its closing date by 18 months to December 31, 2022. The project is making steady progress toward achieving its objective of conserving critical cultural heritage sites and improving water quality and tourism services in Jingzhou Municipality. Conservation works in two cultural heritage sites have been completed and works on three additional sites are ongoing. The moat water quality meets the expected standards as a result of project-financed dredging of the moat and lakes as well as installation of wastewater interceptors. In addition, all 28 bus stops and 12 pedestrian crossings in the Historic Town

11/23/2020 Page 1 of 7 The World Bank Implementation Status & Results Report Hubei Jingzhou Historic Town Conservation Project (P148523)

have been upgraded as planned. The satisfaction rate of tourists from tourism services in project areas is around 80%. The project has benefited a total of 704,000 residents and tourists, 50% of whom are women, exceeding final target of 682,000 beneficiaries.

Risks

Systematic Operations Risk-rating Tool

Risk Category Rating at Approval Previous Rating Current Rating

Political and Governance Low Low Low Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Moderate Moderate Low Technical Design of Project or Program Substantial Moderate Low Institutional Capacity for Implementation and Substantial Moderate Moderate Sustainability Fiduciary Moderate Moderate Moderate Environment and Social Substantial Substantial Substantial Stakeholders Moderate Moderate Low Other -- Low Low Overall Substantial Moderate Moderate

Results

PDO Indicators by Objectives / Outcomes

Conserve cultural heritage

IN00918742 ►Direct project beneficiaries (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 682,000.00 704,000.00 682,000.00

Date 19-Nov-2015 23-Jul-2020 16-Nov-2020 31-Dec-2022

Exceed the year 2020 target of 682000 Comments:

IN00918745 Female beneficiaries (Percentage, Custom Supplement)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 50.00 50.00 50.00

11/23/2020 Page 2 of 7 The World Bank Implementation Status & Results Report Hubei Jingzhou Historic Town Conservation Project (P148523)

IN00918816 ►Cultural heritage sites conserved/rehabilitated under the project (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 2.00 2.00 5.00

Date 19-Nov-2015 23-Jul-2020 16-Nov-2020 31-Dec-2022 The result is presently below the 2020 target of 3. Conservation works of three remaining cultural heritage Comments: sites are ongoing and are expected to be completed by the end of 2020.

Improve water quality

IN00918743 ►Moat water meets Class IV for BOD (< 6 mg/l) for at least 10 of the 12 monthly samples per year (Text, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value NA Meet Class IV for BOD YES Yes

Date 19-Nov-2015 23-Jul-2020 16-Nov-2020 31-Dec-2022 Water sample monitoring showed that the moat water quality has reached Class IV for BOD with the completion of project-financed dredging and interceptors works, thereby achieving the 2020 and end-of Comments: project targets.

Improve tourism services

IN00918744 ►Satisfaction of tourists on tourism services in Jingzhou Historic Town (JHT) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 70.00 77.00 79.80 85.00

Date 19-Nov-2015 23-Jul-2020 16-Nov-2020 31-Dec-2022 The result is presently below the 2020 target of 85%. A tourists satisfaction survey for 2020 was conducted during the national holiday week in early October 2020. Survey data are being processed. Comments: Outcomes of the survey will be reported in the next semi-annual progress report (July-December 2020) and next ISR .

Intermediate Results Indicators by Components

Cultural Heritage Conservation and Tourism Services Improvement

IN00918817 ►City Wall restored under the project (Kilometers, Custom)

Baseline Actual (Previous) Actual (Current) End Target

11/23/2020 Page 3 of 7 The World Bank Implementation Status & Results Report Hubei Jingzhou Historic Town Conservation Project (P148523)

Value 0.00 9.50 9.50 11.28

Date 19-Nov-2015 23-Jul-2020 16-Nov-2020 31-Dec-2022

The 2020 target of 9.5km has achieved. Comments:

IN00918821 ►Heritage display space upgraded or created (Square Meter(m2), Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 6,800.00

Date 19-Nov-2015 23-Jul-2020 16-Nov-2020 31-Dec-2022 The result is as planned for 2020. This is a new indicator that measures the output of upgrading of Comments: Jingzhou Museum.

Transport Improvement

IN00918818 ►Roads rehabilitated, Non-rural (Kilometers, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 10.20 10.20 10.20

Date 19-Nov-2015 23-Jul-2020 16-Nov-2020 31-Dec-2022

2020 and end targets achieved in 2019. Comments:

IN00918822 ►Pedestrian crossing upgraded (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 12.00 12.00 12.00

Date 19-Nov-2015 23-Jul-2020 16-Nov-2020 31-Dec-2022

This sub-component had been completed. Comments:

IN00918825 ►Bus stops upgraded (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 28.00 28.00 28.00

Date 19-Nov-2015 23-Jul-2020 16-Nov-2020 31-Dec-2022

All the planned bus stops were satisfactorily upgraded by 2019, benefitting residents and tourists. Comments:

Water Environment Improvement

11/23/2020 Page 4 of 7 The World Bank Implementation Status & Results Report Hubei Jingzhou Historic Town Conservation Project (P148523)

IN00918819 ►Wastewater interceptors constructed inside and outside of the moat (Meter(m), Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 7,000.00 7,080.00 8,463.00

Date 19-Nov-2015 23-Jul-2020 16-Nov-2020 31-Dec-2022

The 7000 m target for 2020 has been exceeded. Comments:

IN00918823 ►Dredging of the moat and lakes with safe storage /disposal of the dredged materials (Cubic Meter(m3), Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 341,000.00 341,000.00 341,000.00

Date 19-Nov-2015 23-Jul-2020 16-Nov-2020 31-Dec-2022 2020 and end targets reached. The dredged materials have been disposed at a designated site, whose Comments: safety measures are expected to be improved.

Assistance to Project Management and Capacity Building

IN00918820 ►Participants rated the training/study tours good or excellent (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 80.00 80.00 80.00

Date 19-Nov-2015 23-Jul-2020 16-Nov-2020 31-Dec-2022

the 2020 and end targets have been reached according to the semi-annual progress report. Comments:

IN00918824 ►Participants in consultation activities during project implementation (number) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 2,606.00 2,800.00 3,000.00

Date 19-Nov-2015 23-Jul-2020 16-Nov-2020 31-Dec-2022

the 2020 target has been exceeded according to the semi-annual progress report. Comments:

IN00918826 Participants in consultation activities during project implementation - female (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 1,173.00 1,173.00 1,500.00

Date 19-Nov-2015 23-Jul-2020 23-Jul-2020 31-Dec-2022

11/23/2020 Page 5 of 7 The World Bank Implementation Status & Results Report Hubei Jingzhou Historic Town Conservation Project (P148523)

Performance-Based Conditions

Data on Financial Performance

Disbursements (by loan)

Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed

P148523 IBRD-85740 Effective USD 100.00 100.00 0.00 35.53 64.47 36%

Key Dates (by loan)

Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date

P148523 IBRD-85740 Effective 19-Jan-2016 26-Apr-2016 25-Jul-2016 30-Jun-2021 31-Dec-2022

Cumulative Disbursements

PBC Disbursement

Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC

11/23/2020 Page 6 of 7 The World Bank Implementation Status & Results Report Hubei Jingzhou Historic Town Conservation Project (P148523)

Restructuring History

Level 2 Approved on 19-Aug-2020

Related Project(s)

There are no related projects.

11/23/2020 Page 7 of 7