Service Changes Effective Sunday, November 20, 2016 Route Period Headway Veh Headway Veh Headway Veh Old New Old New Old New M-F Saturday Sunday

514 Cherry Early morning first car from termini 5:45 6:00 5:45 6:00 7:45 8:00 Reduced hours of service Late evening last car from termini 1:30 1:00 1:30 1:00 1:30 1:00

126 Christie All Construction completed at St. Clair West Station. Interline with 33 Forest Hill discontinued. Schedule reverts to May 2016 version.

108 Downsview Afternoon 7'30" 9'00" -1 Service reduction

121 Fort York - Esplanade AM Peak before 7:00 10' 12'30" -2 Service reduction and driving time changes AM Peak 10' 11' -1 Morning 15' 16' -1 15' 15' -1 Late evening last bus from termini 1:45 1:00 1:45 1:00 1:45 1:00

37 Islington AM Peak 5'30" 5'15" Service reliability improvement 37A to Woodbine Ctr & Humberwood 22' 21' 37B to Steeles 7'20" 7' M-F Midday 9' 9' 37A to Woodbine Ctr & Humberwood 18' 18' 37B to Steeles 18' 18' PM Peak 6'20" 6'20" 37A to Woodbine Ctr & Humberwood 19' 19' 37B to Steeles 9'30" 9'30" Early Evening 11'30" 10' 37A to Woodbine Ctr & Humberwood 23' 20' 37B to Steeles 23' 20' Late Evening 15' 13' 37A to Woodbine Ctr & Humberwood 30' 26' 37B to Steeles 30' 26'

35 Jane M-F Midday 6'15" 6'40" -1 Service reduction 35B to Pioneer Village 18'45" 20' 35C to Steeles 6'15" 6'40" Service Changes Effective Sunday, November 20, 2016 Route Period Headway Veh Headway Veh Headway Veh Old New Old New Old New M-F Saturday Sunday 43 Kennedy M-F Midday 5' 6' -2 Service reduction 43A to Steeles 10' 10' 43B to STC 10' 15' PM Peak 6' 6'40" -1 43A to Steeles 9' 10' 43B to STC 18' 20'

504 King Service reduction: Some trips into and out of service will be changed to originate/end at Broadview/Queen and Roncesvalles/King rather than operating north to the respective subway stations. Scheduled headways north of Queen will remain at 10' or better.

129 McCowan North AM Peak 4'30" 5' -2 Service reduction 129A to Major Mackenzie 13'30" 15' 129B to Steeles 4'30" 5'

57 Midland AM Peak 7'30" 8'20" -1 Service reduction

74 Mt. Pleasant Bus loop at St. Clair Station re-opens

133 Neilson AM Peak 9' 10' -1 Service reduction Service Changes Effective Sunday, November 20, 2016 Route Period Headway Veh Headway Veh Headway Veh Old New Old New Old New M-F Saturday Sunday / 301 Queen Night Streetcar service resumes to Neville Loop. The Spadina-King- Shaw diversion will operate until the end of November when city watermain work on Queen is supposed to be completed. A shuttle bus will be provided by unscheduled extras.

AM Peak / S-S Early AM 501 Humber to Neville 5' +4 7'30" +3 8' +2 501 Humber to Woodbine Loop 5' 7'30" 8' 501 Long Branch to Parliament 3 cars 3 cars From Long Branch at 7:19, 7:29 and 7:39 AM 501 Long Branch to Humber 9'30" 9'30" 10' 10' 10' 10' 501 Bus Coxwell to Neville Park 7' -6 10' -3 10' -3 M-F Midday / S-S Late AM 501 Humber to Neville 5'30" +4 6'30" +4 8' +2 501 Humber to Woodbine Loop 5'30" 6'30" 8' 501 Long Branch to Humber 10' 10' 10' 10' 10' 10' 501 Bus Coxwell to Neville Park 7' -6 8' -5 8' -5 PM Peak / S-S Afternoon 501 Humber to Neville 5'10" +4 5'30" +4 5'30" +4 501 Humber to Woodbine Loop 5'10" 5'30" 5'30" 501 Long Branch to Humber 9'30" 9'30" 10' 10' 10' 10' 501 Bus Coxwell to Neville Park 7' -6 8' -5 8' -5 Early Evening 501 Humber to Neville 5'30" +4 7' +3 9' +3 501 Humber to Woodbine Loop 5'30" 7' 9' 501 Long Branch to Humber 9'30" 9'30" 10' 10' 10' 10' 501 Bus Coxwell to Neville Park 8' -5 8' -5 9' -4 Late Evening 501 Humber to Neville 9' +2 10' +3 10' +3 501 Long Branch to Neville Loop 501 Humber to Woodbine Loop 9' 10' 10' 501 Long Branch to Humber 9' 9' 9' 10' 10' +5 501 Bus Coxwell to Neville Park 10' -3 10' -3 10' -3 Overnight 301 Long Branch to Neville Loop 30' 30' 30' 301 Long Branch to Bingham Loop 30' 30' 30'

161 Rogers Road Daytime 12' 15' -1 Service reduction

73 Royal York Daytime 73C to Clairport 13' 15' -1 Service reduction 73B to La Rose 30' 30' Service Changes Effective Sunday, November 20, 2016 Route Period Headway Veh Headway Veh Headway Veh Old New Old New Old New M-F Saturday Sunday 88 South Leaside Bus loop at St. Clair Station re-opens

512 St. Clair AM Peak / S-S Early AM Full service resumes to St. Clair Station 512 car from St. Clair Stn. to Keele 2'50" +6 9' +1 10'30" +1 512 car from St. Clair W to Keele 2'50" 8' 10' 512 bus from Oakwood to Yonge 2'30" -18 9'30" -4 9'30" -4 M-F Midday / S-S Late AM 512 car from St. Clair Stn. to Keele 4'30" +3 4'30" +4 5'30" +3 512 car from St. Clair W to Keele 4'15" 4'30" 5'15" 512 bus from Oakwood to Yonge 4'15" -11 4'30" -10 6'30" -7 PM Peak / S-S Afternoon 512 car from St. Clair Stn. to Keele 3'20" +6 4' +5 5'30" +3 512 car from St. Clair W to Keele 3'20" 4' 5'15" 512 bus from Oakwood to Yonge 3'20" -15 4' -12 5' -9 Early Evening 512 car from St. Clair Stn. to Keele 6'15" +2 5'30" +3 5'30" +3 512 car from St. Clair W to Keele 6' 5'30" 5'30" 512 bus from Oakwood to Yonge 5' -9 6'15" -7 7' -6 Late Evening 512 car from St. Clair Stn. to Keele 6' +3 8'15" +2 9'20" +2 512 car from St. Clair W to Keele 6' 8'15" 10' 512 bus from Oakwood to Yonge 7' -6 8' -1 10' -4

79 Scarlett Road Daytime 10' 12' -1 Service reduction

124 Sunnybrook PM Peak 6' 7'30" -1 Service reduction

168 Symington AM Peak 4'30" 5' -1 Service reduction Service Changes Effective Sunday, November 20, 2016 Route Period Headway Veh Headway Veh Headway Veh Old New Old New Old New M-F Saturday Sunday 68 Warden AM Peak 4'30" 5' -2 Running time adjustments; AM peak service reduction 68A to Steeles 4'30" 5' 68B to Major Mackenzie 22'30" 25' M-F Midday 9'45" 10' 68A to Steeles 9'45" 10' 68B to Major Mackenzie 39' 40' PM Peak 6'15" 6'15" 68A to Steeles 6'15" 6'15" 68B to Major Mackenzie 18'45" 25' Early Evening 10' 10' 68A to Steeles 10' 10' 68B to Major Mackenzie 40' 40' Late Evening 68A to Steeles 16' 15'

165 Weston Road North 165C to Canada's Wonderland Last day of service Sunday October 30.

Metrolinx Eglinton LRT Station M-F changes only in this update. Weekend changes to follow Projects in a future board period.

7 Bathurst AM Peak 9' 9'30" Forest Hill Stn construction M-F Midday 9' 9'30" PM Peak 8'10" 8'40" Early Evening 9'30" 10'30" Late Evening 10' 10'

11 Bayview AM Peak 7'30" 8'30" Leaside Stn construction 11A to Steeles via Sunnybrook 15' 17' 11A Tripper 1 0 -1 11C to Sunnybrook 15' 17' M-F Midday 11A to Steeles via Sunnybrook 11' 12' PM Peak 7'30" 8'30" 11A to Steeles via Sunnybrook 15' 17' 11C to Sunnybrook 15' 17' Early Evening 12' 15' 11A to Steeles via Sunnybrook 24' 30' 11C to Sunnybrook 24' 30' Late Evening 15' 15' 11A to Steeles via Sunnybrook 30' 30' 11C to Sunnybrook 30' 30' Service Changes Effective Sunday, November 20, 2016 Route Period Headway Veh Headway Veh Headway Veh Old New Old New Old New M-F Saturday Sunday 29 Dufferin AM Peak 4' 4'30" Fairbank Stn construction 29C Wilson Stn to Princes' Gates 8' 9' 29H Tycos to Princes' Gates 8' 9' Midday 29A Wilson Stn to Dufferin Gate 4'20" 4'45" PM Peak 4'45" 5'15" 29C Wilson Stn to Princes' Gates 9'30" 10'30" 29H Tycos to Princes' Gates 9'30" 10'30" Early Evening 29A Wilson Stn to Dufferin Gate 5'30" 6' Late Evening 29A Wilson Stn to Dufferin Gate 8'30" 8'30"

33 Forest Hill AM Peak 16' 20' +1 30' 20' +1 Forest Hill and Chaplin Stns construction Midday 30' 20' +1 30' 20' +1 30' 20' +1 PM Peak 16' 20' +1 30' 20' +1 30' 20' +1 Early Evening 30' 20' +1 30' 20' +1 30' 20' +1 Late Evening 30' 20' +1 30' 20' +1 30' 20' +1

56 Leaside AM Peak 11'22" 12' Construction delays on Eglinton from Laird to Yonge 56A Donlands Stn to Eglinton Stn 22'45" 24' 56B Donlands Stn to Brentcliffe 22'45" 24' 56A Tripper 1 1 Midday 56A Donlands Stn to Eglinton Stn 17' 18' PM Peak 11'23" 12' 56A Donlands Stn to Eglinton Stn 22'45" 24' 56B Donlands Stn to Brentcliffe 22'45" 24' Early Evening 56A Donlands Stn to Eglinton Stn 30' 30'

90 Vaughan AM Peak 4' 4' -1 Construction delays on Eglinton from Oakwood to Allen

90A to Oakwood 8' 4' 90B to Eglinton W Stn 8' PM Peak 5'15" 5' -1 90A to Oakwood 10'30" 5' 90B to Eglinton W Stn 10'30" Service Changes Effective Sunday, November 20, 2016 Route Period Headway Veh Headway Veh Headway Veh Old New Old New Old New M-F Saturday Sunday Streetcar Shortage & Exhibition Loop

511 Bathurst Service will operate with buses to Exhibition. Streetcar service will resume in 2017 when track construction projects elsewhere plus additional Flexity deliveries provide a sufficient fleet. AM Peak / S-S Early AM 4' 3' 6' 6'30" M-F Midday / S-S Late AM 5' 4' 5' 5' 6' 5' PM Peak / S-S Afternoon 4'15" 3' 4' 4' 5' 4'15" Early Evening 5'30" 5' 6' 5' 8' 5' Late Evening 6' 5' 6' 5' 8' 5'

509 Harbourfront Service will operate to Fleet Loop until the December 18, 2016 board period due to track construction at Exhibition Loop. AM Peak / S-S Early AM 5'15" 6' 8' 9' 11' 9' +1 Running times adjusted to improve reliability. M-F Midday / S-S Late AM 5'45" 7' 5'30" 6'30" 5'30" 6'30" PM Peak / S-S Afternoon 5'15" 6' 5'15" 6' 5'15" 6' Early Evening 5'20" 6'20" 8' 9'30" 8' 9'30" Late Evening 8' 9' 8' 9'30" 8' 9'30" Schedule Arrangements for Christmas & New Year's Period

Fri Dec 16 Sat Dec 17 Sun Dec 18 Mon-Fri Sat Dec 24 Sun Dec 25 Mon-Tue Wed-Fri Dec 19-23 Dec 26-27 Dec 28-30

Schedule type Regular MF Regular Sat Regular Sun Regular MF Regular Sat Regular Sun Holiday Regular MF Service begins 6:00 6:00 8:00 6:00 6:00 8:00 6:00 6:00 Additional service * * * * Line 1 peak service Regular Regular Regular Line 2 peak service Regular Summer Summer Lines 3 & 4 peak service Regular Regular Regular

Sat Dec 31 Sun Jan 1 Mon Jan 2 Tue-Fri Sat Jan 7 Sun Jan 8 Mon Jan 9 Jan 3-6 Schedule type Special Sunday Holiday Summer MF Saturday Sunday Regular MF Service begins 6:00 9:00 6:00 6:00 6:00 8:00 6:00 Additional service Line 1 peak service Regular Regular Line 2 peak service Summer Regular Lines 3 & 4 peak service Summer Regular Evening standby trains Line 1 10 Line 2 8 Last Trains Union to Finch 3:30 AM Union to Downsview 3:34 AM Yonge to Kipling & Kennedy 3:37 AM Kennedy to McCowan 4:05 AM Sheppard-Yonge to Don Mills 3:58 AM

* Additional standby and service relief streetcars and buses will be provided. Construction Projects and Diversions November 20, 2016

June 18-July 29 18-July June

Nov 20-Dec 17 20-Dec Nov 16 26-Dec Nov

May 7-June 17 7-June May

July 30-Sept 2 30-Sept July

Feb 12-Mar 25 12-Mar Feb

Oct 15-Nov 25 15-Nov Oct

Sept 3-Oct 14 3-Oct Sept

Mar 26-May 6 26-May Mar

Dec 18-Jan 7 18-Jan Dec 6 17-Jan Dec

Jan 8-Feb 11 8-Feb Jan

2018 2019

Route Activity

Ending November 19

511 Bathurst Exhibition Loop Construction Route cut back to Fleet Loop

512 St. Clair (East end) St. Clair Stn construction Route partly replaced by buses 74 Mt. Pleasant Diversion bypassing station 88 South Leaside 33/126 Forest Hill/Christie St. Clair W. Stn. Construction Interlined

501 Queen Neville Loop Construction Replaced by shuttle bus E of Coxwell 301 Queen Diverted to Bingham Loop 143 Downtown/Beach Express E end loop changed

Ending November 30 (est)

301/501 Queen Queen W water main Diversion via King from Spadina to Shaw

Ending December 17

509 Harbourfront Exhibition Loop Construction Routes cut back to Fleet Loop

Planned to end January 7

141 Downtown Mt Pleasant Richmond Street construction Diversion via Queen 142 Downtown Avenue Road 143 Downtown Beach 144 Downtown Don Valley 145 Downtown Humber Bay

22 Coxwell / 70 O'Connor Construction at Coxwell Station Routes combined to bypass loop Construction Projects and Diversions November 20, 2016

June 18-July 29 18-July June

Nov 20-Dec 17 20-Dec Nov 16 26-Dec Nov

May 7-June 17 7-June May

July 30-Sept 2 30-Sept July

Feb 12-Mar 25 12-Mar Feb

Oct 15-Nov 25 15-Nov Oct

Sept 3-Oct 14 3-Oct Sept

Mar 26-May 6 26-May Mar

Dec 18-Jan 7 18-Jan Dec 6 17-Jan Dec

Jan 8-Feb 11 8-Feb Jan

2018 2019

Route Activity Planned to end February 11

1 Yonge Construction at Davisville Chse 3 trains temporarily operated from Wilson

Planned to end Early 2017

41 Keele Subway construction Additional running time and buses 107 Keele North

Ongoing

32 Eglinton West Renforth Gateway construction Route Change 112 West Mall

45 Kipling Six Points Reconstruction Diversion and extra running time 46 Martin Grove

32 Eglinton West Eglinton LRT constuction Additional running time and buses 5 Avenue Road 61 Avenue Road North 7 Bathurst 29 Dufferin 33 Forest Hill 90 Vaughan 54 Lawrence East 34 Eglinton East 11 Bayview 100 Flemingdon Park 56 Leaside 51 Leslie 74 Mt. Pleasant Routes interlined 103 Mt. Pleasant North Construction Projects and Diversions November 20, 2016

June 18-July 29 18-July June

Nov 20-Dec 17 20-Dec Nov 16 26-Dec Nov

May 7-June 17 7-June May

July 30-Sept 2 30-Sept July

Feb 12-Mar 25 12-Mar Feb

Oct 15-Nov 25 15-Nov Oct

Sept 3-Oct 14 3-Oct Sept

Mar 26-May 6 26-May Mar

Dec 18-Jan 7 18-Jan Dec 6 17-Jan Dec

Jan 8-Feb 11 8-Feb Jan

2018 2019

Route Activity

97 Yonge Yonge/Sheppard construction Route split

3 SRT & 131 Nugget SRT fleet overhaul Reduced SRT, increased Nugget service